20111129 Gen Column Shortening Presentation

download 20111129 Gen Column Shortening Presentation

of 31

Transcript of 20111129 Gen Column Shortening Presentation

  • midas Gen

    midas Gen Advanced Webinar Column Shortening for High-rise Building

  • 2

    Column Shortening for High-rise Building

    Introduction in Column Shortening

    Project Applications

    Procedure for Construction Stage Analysis

    Useful features for Construction Stage Analysis

    Demonstration

    03

    11

    14

    19

    24

  • 3

    Introduction in Column Shortening

    Project Applications

    Procedure for Construction Stage Analysis

    Useful features for Construction Stage Analysis

    Demonstration

    03

    11

    14

    19

    24

    Introduction in Column Shortening

  • One Stop Solution for Building and General Structures

    4

    Introduction

    Why construction stage analysis?

    Column Shortening

    Wind Live

    Earthquake

    Completed structure

    Live, Wind and Seismic Loads Sequential Loading: Dead Loads

    Construction Sequence

    Dead

    (1) Dead load is sequential load.

  • One Stop Solution for Building and General Structures

    5

    Introduction

    Why construction stage analysis?

    Column Shortening

    End Moment of Girder by Stories (Wall Connection)

    Comparison between with and without considering sequential loading

  • One Stop Solution for Building and General Structures

    6

    Column Shortening Elastic stresses due to gravity loads Creep caused by gravity load Drying shrinkage Temperature variations of exposed columns

    Steel Concrete

    Elastic Creep

    Shrinkage

    19.6 - -

    6.1 4.6 6.1

    Total 19.6 16.8

    Shortenings of an 80-story column (cm)

    Introduction Column Shortening

    Why construction stage analysis?

    (2) Compensation for the differential column shortening in high-rise building

  • One Stop Solution for Building and General Structures

    7

    Effects of column shortening

    Deforms in pipes, elevator rails, cladding Cracks in partitions

    Introduction Column Shortening

    Nonstructural Effect

    Structural Effect

    Distorted slabs or beams due to differential movements

    Gravity load redistribution

  • One Stop Solution for Building and General Structures

    8

    Shortening related to construction sequence

    Introduction Column Shortening

    Pre-slab installation shortenings Shortenings of supports that take place up to the time of slab installation

    Post-slab installation shortenings

    Shortenings of supports that take place after the time of slab installation

    :Compensation

    : Design Level

    : Pre-slab Installation shortening

    : Post-slab Installation shortening

  • One Stop Solution for Building and General Structures

    9

    Compensation for differential column shortening

    Introduction Column Shortening

    Reinforced Concrete Structure Pre-slab installation shortenings has no importance Compensation by leveling the forms Post-slab installation shortenings due to subsequent loads and

    creep/shrinkage

    Steel Structure Columns are fabricated to exact length. Attachments to support the slabs Pre-slab installation shortenings need to be known. Compensation for the summation of Pre-installation and Post-installation

    shortenings

  • One Stop Solution for Building and General Structures

    10

    Application procedure for column shortening

    Application in field

    Material & Section property Loads, Construction sequence

    Pre-analysis for column shortening

    Considering load redistribution due to differential shortening

    Analysis

    Updating material properties by experiments Construction sequence considering the field condition

    Column Shortening analysis

    Compressive strength Modulus of elasticity Creep & Shrinkage

    Material Experiment

    Using Strain gauge

    Measuring shortening

    Predicting shortening for further stages Providing an amount of compensation

    Column Shortening re-analysis

    Introduction Column Shortening

  • 11

    Project Applications

    Introduction in Column Shortening

    Project Applications

    Procedure for Construction Stage Analysis

    Useful features for Construction Stage Analysis

    Demonstration

    03

    11

    14

    19

    24

  • One Stop Solution for Building and General Structures

    12

    Project Applications

    Burj Khalifa (Dubai, UAE)

    Column Shortening

    Height 705 m No. of floors 160 Location Dubai, United Arab Emirates Function / Usage Office Building & Residential Building Designer Adrian D. Smith Architect Skidmore, Owings & Merrill General Contractor Samsung Development

    over

    view

  • One Stop Solution for Building and General Structures

    13

    Project Applications

    SK S-Trenue (Seoul, Korea)

    Column Shortening

    Area 39,600m2 No. of floors 36 Location Seoul, Korea Function / Usage Office Building Structure Type Composite Structure Foundation Type Mat Foundation Lateral load resisting system RC Core + Steel + RC Composite Frame

    over

    view

  • 14

    Procedure for Construction Stage Analysis

    Introduction in Column Shortening

    Project Applications

    Procedure for Construction Stage Analysis

    Useful features for Construction Stage Analysis

    Demonstration

    03

    11

    14

    19

    24

  • One Stop Solution for Building and General Structures

    15

    How to use the construction stage analysis in midas Gen

    Define materials, sections

    Assign elements, boundaries, & loads to the groups

    Define time dependent materials

    Enter the construction stage analysis data

    Perform an analysis

    Check results for each construction stage

    Check column shortening

    Creep & Shrinkage Compressive strength

    Specify the duration of CS Activate/Deactivate element groups / boundary groups/ load groups

    Procedure for Construction Stage Analysis Column Shortening

  • One Stop Solution for Building and General Structures

    16

    Time Dependent Material Properties

    Column Shortening

    1. Creep effects of concrete members having different maturities

    2. Shrinkage effects of concrete members having different maturities

    3. Time dependent compressive strength gain for concrete members

    Procedure for Construction Stage Analysis

    Creep/Shrinkage - Eurocode, ACI, CEB-FIP, PCA, India Comp. Strength

    - Eurocode, ACI, CEB-FIP, Ohzagi , India

    Time dependent material properties

    Construction Stage

  • One Stop Solution for Building and General Structures

    17

    Construction Stage Analysis Data

    Column Shortening Procedure for Construction Stage Analysis

    0 day 10 day 20 day 30 day 40 day

    Construction Stage Duration Construction Stage Duration

    Activation or Deactivation of

    element, boundary, and load

    Activation or Deactivation of load with time span from

    the stage start

    Activation or Deactivation of

    element, boundary, and load

  • One Stop Solution for Building and General Structures

    18

    Check results for each construction stage

    Column Shortening Procedure for Construction Stage Analysis

    Analysis results can be checked for each construction stage.

    Absolute minimum or maximum results of envelope can be also checked among entire construction stages.

    Results for creep and shrinkage effect are provided.

    [Beam Forces for each construction stage] [Displacement due to Creep & Shrinkage]

    CS1

    CS3

    CS6

    CS10

    CS12

    Min/Max

  • 19

    Useful Features for Construction Stage Analysis

    Introduction in Column Shortening

    Project Applications

    Procedure for Construction Stage Analysis

    Useful features for Construction Stage Analysis

    Demonstration

    03

    11

    14

    19

    24

  • One Stop Solution for Building and General Structures

    20

    Building Model Generation Wizard

    Column Shortening Useful Features for Construction Stage Analysis

    The wizard readily allows us to define the timing of elements created and loadings applied in the

    construction stages during the erection of a building.

    You may find it more convenient to first click the [Automatic Generation] button to define the basic

    construction stages and modify them as necessary.

  • One Stop Solution for Building and General Structures

    21

    Construction Stage Analysis for Composite Members

    Column Shortening Useful Features for Construction Stage Analysis

    Define an analytical model for each construction stage by assigning activated or inactivated sections

    corresponding to each construction stage of a composite section.

    By using Composite Section for Construction Stage, we can consider the construction sequence with

    creep and shrinkage effect.

  • One Stop Solution for Building and General Structures

    22

    Auto Climbing Formwork System

    Column Shortening Useful Features for Construction Stage Analysis

    Construction stage for auto climbing formwork system (ACS) can be generated in midas Gen.

  • One Stop Solution for Building and General Structures

    23

    Tendon Loss

    Column Shortening Useful Features for Construction Stage Analysis

    Pre-stress load can be considered in construction stage analysis.

    Tendon primary / secondary forces are provided with pre-stress loss graph.

  • 24

    Demonstration

    Introduction in Column Shortening

    Project Applications

    Procedure for Construction Stage Analysis

    Useful features for Construction Stage Analysis

    Demonstration

    03

    11

    14

    19

    24

  • 25

    One Stop Solution for Building and General Structures Design Procedure Demonstration

    Example model

    Structural plan & section

    9@4=

    36m

    2@

    4.5=

    9m

    5m

    50m

  • 26

    One Stop Solution for Building and General Structures Design Procedure

    Section name Section size

    G1 G2 G3 G4

    WG1 WG2

    400x700 400x700 600x800 500x800 400x700 600x800

    Story C1 C1A C2 C3 C4

    10~12 8~9 6~7 4~5 2~3

    1

    600x600 800x800

    800x1000 1000x1000 1000x1200 1000x1300

    500x600 500x600 500x600 600x600 700x700 700x700

    600x600 600x800 600x800 800x800

    900x1000 1000x1000

    600x700 600x800 600x800 800x800 800x800

    1000x1000

    600x700 600x800 600x800 800x800 900x900 900x900

    Section Size and Material Properties

    Girder

    Column

    Wall Thk = 200

    fck = 240 kg/cm2

    fck = 280 kg/cm2

    fck = 280 kg/cm2

    Demonstration

  • 27

    One Stop Solution for Building and General Structures Design Procedure

    Construction Schedule

    3rd day

    1F Formwork Installation

    1F Concrete Casting

    2F Formwork Installation

    2F Concrete Casting

    1st day 8th day 10th day

    3 levels of shoring Construction cycle time=7 days Time of removal of lowest level of shores from concreting of top floor=5 days

    Age

    Age

    0 5

    0

    7

    Demonstration

  • 28

    One Stop Solution for Building and General Structures Design Procedure

    Construction Schedule

    3F Formwork Installation

    12

    5

    15th day

    3F Concrete Casting

    7

    17th day

    0

    1F Formwork Removal 4F Formwork Installation

    22th day

    4F Concrete Casting

    24th day 29th day

    2F Formwork Removal 5F Formwork Installation

    Age

    Age

    14

    5

    12

    19

    14

    21

    7

    0 5

    12

    19

    26

    Demonstration

  • 29

    One Stop Solution for Building and General Structures Design Procedure

    Date Work Formwork Removal Formwork Installation

    Conc. Casting

    Stage Definition

    Program Date

    Stage Duration

    1 1F Formwork Installation 1F

    3 1F Concrete Casting 1F

    8 2F Formwork Installation 2F

    10 2F Concrete Casting 2F

    15 3F Formwork Installation 3F

    17 3F Concrete Casting 3F

    22 1F Formwork Removal, 4F Formwork Installation 1F 4F stage 1

    1 7

    24 4F Concrete Casting 4F 3

    29 2F Formwork Removal, 5F Formwork Installation 2F 5F stage 2

    8 7

    31 5F Concrete Casting 5F 10

    36 3F Formwork Removal, 6F Formwork Installation 3F 6F stage 3

    15 7

    38 6F Concrete Casting 6F 17

    43 4F Formwork Removal, 7F Formwork Installation 4F 7F stage 4

    22 7

    45 7F Concrete Casting 7F 24

    Construction Schedule

    Demonstration

  • 30

    One Stop Solution for Building and General Structures Design Procedure

    Date Work Formwork Removal Formwork Installation

    Conc. Casting

    Stage Definition

    Program Date

    Stage Duration

    50 5F Formwork Removal, 8F Formwork Installation 5F 8F stage 5

    29 7

    52 8F Concrete Casting 8F 31

    57 6F Formwork Removal, 9F Formwork Installation 6F 9F stage 6

    36 7

    59 9F Concrete Casting 9F 38

    64 7F Formwork Removal, 10F Formwork Installation 7F 10F stage 7

    43 7

    66 10F Concrete Casting 10F 45

    71 8F Formwork Removal, 11F Formwork Installation 8F 11F stage 8

    50 7

    73 11F Concrete Casting 11F 52

    78 9F Formwork Removal, 12F Formwork Installation 9F 12F stage 9

    57 7

    80 12F Concrete Casting 12F 59

    85 10F Formwork Removal 10F stage 10 64 7

    92 11F Formwork Removal, 1~3F SDL 11F

    stage 11

    71

    7 95 4~6F SDL 74

    98 7~9F SDL 77

    99 12F Formwork Removal 12F stage 12

    78 7

    101 10~12F SDL 80

    133 Live Load dummy 112 28

    Construction Schedule

    Demonstration

  • Thank You! Thank You!

    One Stop Solution for Building and General Structures

    [email protected] http://en.midasuser.com/

    1Column Shortening for High-rise Building 3IntroductionIntroductionIntroductionIntroductionIntroductionIntroductionIntroduction 11Project ApplicationsProject Applications 14Procedure for Construction Stage Analysis 16 17 18 19Useful Features for Construction Stage AnalysisUseful Features for Construction Stage AnalysisUseful Features for Construction Stage AnalysisUseful Features for Construction Stage Analysis 24DemonstrationDemonstrationDemonstrationDemonstrationDemonstrationDemonstration 31