2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To...
Transcript of 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To...
![Page 1: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/1.jpg)
ARIZONA PUBLIC SERVICE COMPANY 2010-2019
TEN-YEAR PLAN
Prepared for the Arizona Corporation Commission
January 2010
![Page 2: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/2.jpg)
ARIZONA PUBLIC SERVICE COMPANY 2010 - 2019
TEN-YEAR PLAN
TABLE OF CONTENTS
GENERAL INFORMA nON .......................................................................................................... 1
Changes From 2009-2018 Ten-Year Plan .................................................................................. 6
New Projects In The 2010-2019 Ten-Year Plan ......................................................................... 6
Conceptual Projects In The Feasibility Planning Phase ............................................................. 6
PLANNED TRANSMISSION MAPS ............................................................................................ 8
Arizona EHV And Outer Divisions ............................................................................................ 9
Phoenix Metropolitan Area ....................................................................................................... 10
Yuma Area ........................................................................................................ ........................ 11
PLANNED TRANSMISSION DESCRIPTION ........................................................................... 12
Morgan - Pinnacle Peak SOOkV Line (2010) .. ................................................................................ 12
Morgan Raceway-Avery - TS6 - Pinnacle Peak 230kV Line (2011) .... .............................................. 13
TS12 loop-in of Saguaro - Milligan 230kV Line (2012) .................................................................. 14
Delany- Palo Verde SOOkV Line (2012)* ..................................................................................... IS
34S/69kV Interconnection at Western's Flagstaff 34SkV bus (2012) ................................................. 16
Mazatzal loop-in ofCholla-Pinnacie Peak 34SkV Line (2013) ............................................. 17
Bagdad 11SkV Relocation Project (2014) ................................................................................ 18
Desert Basin-Pinal Central 230kV Line (2014) .............................................................................. 19
Pinal Central- Sundance 230kV Line (2014) ................................................................................. 20
Delany- Sun Valley SOOkV Line (2014) ....................................................................................... 21
Sun Valley - Trilby Wash 230kV Line (2014) ......................................................................... 22
Palo Verde Hub - North Gila SOOkV #2 Line (2014)* ............................................................. 23
-i-
![Page 3: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/3.jpg)
North Gila - TS8 230kV Line (2014) ....................................................................................... 24
Palm Valley- TS2- Trilby Wash 230kVLine(201Sj .................................................................... 25
Morgan-Sun Valley500kV Line (2016) ...................................................................................... 26
Mural- San Rafael 230kV (To Be Determined) ...................................................................... 27
Jojoba loop-in of TS4-Panda 230kV Line (To Be Determined) ............................................... 28
TS8 - Yucca 230kV Line (To Be Determined) ........................................................................ 29
Sun Valley - TSlO -TSll 230kV Line (To Be Determined) ............................................ ...... 30
Buckeye - TSll - Sun Valley 230kV Line (To Be Determined) ............................................. 31
Morgan - Sun Valley 230kV Line (To Be Determined) ............................................ ............... 32
Raceway - Westwing 230kV Line (To Be Determined) .......................................................... 33
El Sol- Westwing 230kV Line (To Be Determined) ............................................................... 34
Palo Verde - Saguaro 500kV Line (To Be Determined) .......................................................... 35
* Projects are included in APS's response to Commission Decision No. 70635, Docket No. E-00000D-07-0376 regarding transmission for renewable energy projects. See additional information in the Ten-Year Plan related to development plans and in-service dates.
-ll-
![Page 4: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/4.jpg)
ARIZONA PUBLIC SERVICE COMPANY 2010-2019
TEN· YEAR PLAN
GENERAL INFORMATION
Pursuant to A.R.S. §40-360.02, Arizona Public Service Company ("APS") submits its
2010-2019 Ten-Year Plan. Additionally, pursuant to Arizona Corporation Commission
("Commission") Decision No. 63876 (July 25,2001) concerning the first Biennial Transmission
Assessment, APS is including with this filing its Transmission Planning Process and Guidelines
and maps showing system ratings on APS's transmission system. The Transmission Planning
Process and Guidelines outline generally APS's internal planning for its high voltage and extra-
high voltage transmission system, including a discussion of APS's planning methodology,
planning assumptions, and its guidelines for system performance. The system ratings maps show
continuous and emergency system ratings on APS's extra-high voltage system, and on its Metro,
Northern, and Southern 230kV systems. The Ten-Year Plan is conducted and filed annually with
the Commission.
This 2010-2019 Ten-Year Plan describes planned transmission lines of 115kV or higher
voltage that APS may construct or participate in over the next ten-year period. Pursuant to
A.R.S. §40-360(1O), underground facilities are not included. There are approximately 181 miles
of 500kV transmission lines, 83 miles of 230kV transmission lines, 6 miles of 115kV
transmission lines, and 12 bulk transfonners contained in the projects in this Ten-Year Plan
filing. The total investment for the APS projects and the anticipated APS portion of the
participation projects as they are modeled in this filing is estimated to be approximately $520
million and the projects will add an expected 2,000 MW of additional extra high voltage
("EHV") scheduling capability. Also, over the next ten years the import capability into the
Phoenix area will increase by 3,658 MW, while the import capability into the Yuma area will
-1-
![Page 5: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/5.jpg)
increase by 220 MW. 1.2 The following table shows a breakdown of the projects contained in this
Ten-Year Plan.
Descril!tion Projects in Ten-Year Plan
500k V transmission lines 181 miles 230kV transmission lines 83 miles 115k V transmission lines 6 miles Bulk Transformers 12 Total Investment $520 million Extra High Voltage Scheduling Capability +2,000 MW (+28 %). Total Phoenix Area Import +3,658 MW (+26 %)a Yuma Area Import +220 MW (+39 %)' • Based on 2009 values.
Some of the facilities reported in past Ten-Year plan filings that have been completed,
canceled, or deferred beyond the upcoming ten-year period are not included in this report. The
projects at the end of this Ten-Year Plan that have "to be determined" in-service dates are
projects that have been identified but that are either still outside of the ten-year planning window
or have in-service dates that have not yet been established. They have been included in this
filing for informational purposes. A summary of changes from last year's plan is provided
below, along with a list of projects that have l;>een added to this year's Ten-Year Plan. Also, a
section is included that briefly describes projects still in the feasibility planning phase.
For convenience of the reader, APS has included system maps showing the electrical
connections and in-service dates for all overhead transmission projects planned by APS for
Arizona, the Phoenix Metropolitan Area, and the Yuma area. Written descriptions of each
proposed transmission project are provided on subsequent pages in the currently expected
I Import capability increase is predicated on the Palo Verde to North Gila 500kV and North Gila to TS8 230kV projects. The Palo Verde to North Gila project was identified as one of APS's primary renewable transmission projects in response to Decision 70635 and will require approval for construction in the timeframe indicated.
Import capability and scheduling capability are different numbers because "import" capability is an electrical ability to serve customers in a load pocket where "scheduling" capability is a contractual right to use the transmission line. Both are needed to reliably serve load.
-2-
![Page 6: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/6.jpg)
chronological order of each project. The line routings shown on the system maps and the
descriptions of each transmission line are intended to be general, showing electrical connections
and not specific routings, and are subject to revision. Specific routing is recommended by the
Arizona Power Plant and Transmission Line Siting Committee and ultimately approved by the
Commission when issuing a Certificate of Environmental Compatibility and through subsequent
right-of-way acquisition. Pursuant to A.R.S. §40-360.02(7), this filing also includes technical
study results for the projects identified. The technical study results show project needs that are
generall y based on either security ( contingency performance), adequacy (generator
interconnection or increasing transfer capability), or both.
APS participates in numerous regional planning organizations and in the WestConnect
organization. Through membership and participation in these organizations, the needs of
multiple entities, and the region as a whole, can be identified and studied. This allows for
potentially maximizing the effectiveness and use of new projects. Regional organizations of
which APS is a member include the Western Electricity Coordinating Council ("WECC"), the
Southwest Area Transmission Planning ("SWAT"), and WestConnect (which established a
formal sub-regional transmission planning process during 2007). The plans included in this
filing are the result of these coordinated planning efforts. APS provides an opportunity for other
entities to participate in future planned projects. As a participant in the SWAT-Southeastern
Arizona Transmission Study ("SATS") subcommittee, APS worked with other stakeholders in
Cochise County to develop a transmission plan that will address the recommendations in the
Fifth Biennial Transmission Assessment ("BTA") regarding providing continuity of service
(Decision No. 70635 dated December 11,2008).3
J Southwest Transmission Coop, Inc. ("SWTC"), on behalf of other participating utilities, will be submitting the Summary Report and Reference Filing of the Cochise County Technical Study Report as part of its Ten· Year Plan submittal.
-3-
![Page 7: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/7.jpg)
As part of its planning process, APS is also evaluating the potential for renewable
resource and associated transmission development. In response to the Fourth BT A order
(Decision No, 69389 dated March 22, 2007), on August 6, 2008, the Joint Biennial Transmission
Assessment Report on Renewables and Available Transmission Capability was submitted to the
Commission on behalf of APS, Salt River Project, Tucson Electric Power, and Southwest
Transmission Cooperative. That report described the collaborative efforts and analysis that was
completed with the Southwest Area Transmission Sub-Regional Planning Group to address
transmission for renewable resources, including an assessment of Available Transfer Capacity, a
description of locations, and the transmission needed to bring renewable resources to load.
In addition, in response to the Fifth BT A order, and in collaboration with SWAT and its
subgroups, other utilities, and stakeholders, APS developed plans to identify future renewable
transmission projects and proposed funding mechanisms to construct the "top three" renewable
transmission projects. APS submitted a report containing its prioritized renewable transmission
projects to the Commission on October 30, 2009.4 The projects selected are:
1. Delany - Palo Verde 500kV;
2. North Gila - Palo Verde 500kV #2;
3A. Palo Verde to Liberty;
3B. Gila Bend to Liberty; and
4. Delany - Blythe (Arizona Portion of Devers II).
4 Additionally, in APS's recent rate settlement (approved in Decision No. 71448 dated December 30, 2009) the Company agreed to "commence permitting, design, engineering, right of way acquisition. regulatory authorization ... and line siting for one or more new transmission lines or upgrades" and "to construct such transmission liners) or upgrade(s)"' once APS obtains all required permitting and authorizations (see Exhibit A, § 15.4 of Decision No. 71448). APS intends to pursue the Delany to Palo Verde 500 kV line to begin complying with this commitment, as described in the Company's 1129/10 filing requesting approval of RTPs and their associated action plans.
-4-
![Page 8: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/8.jpg)
Additionally, the specific development plans associated with the APS filing on October 30, 2009
will require Commission approval because they propose in-service dates and actions that may be
beyond what is necessary for the reliable service of APS customers under a traditional analysis.s
Absent Commission approval, in-service timeframes may differ from that indicated throughout
this document.
APS believes that the projects identified in this 2010-2019 Ten-Year Plan, with their
associated in-service dates, will ensure that APS's transmission system meets all applicable
reliability criteria. Changes in regulatory requirements, regulatory approvals, or under! ying
assumptions such as load forecasts, generation or transmission expansions, economic issues, and
other utilities' plans, may substantially impact this Ten-Year Plan and could result in changes to
anticipated in-service dates or project scopes. Additionally, future federal and regional mandates
may impact this Ten-Year Plan specifically and the transmission planning process in general.
This Ten-Year Plan is tentative only and, pursuant to A.R.S. § 40-360.02(F), is subject to change
without notice at the discretion of APS.
5 See APS filing dated 1129110 requesting approval of RTPs and their associated action plans.
-5-
![Page 9: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/9.jpg)
CHANGES FROM 2009-2018 TEN-YEAR PLAN
The following is a list of projects that were changed or removed from APS's January
2009 Ten-Year Plan, along with a brief description of why the change was made.
Morgan-Pinnacle Peak 500kV Line.
In the 2010-2019 Ten-Year Plan, the TS9 substation has been renamed and referred to as
the Morgan substation.
In-Service Date Changes.
Project Name Previous In-Service Date New In-Service Date
Desert Basin - Pinal Central 230kV 2013 2014
Pinal Central - Sundance 230k V line 2013 2014
The tn-serVice dates shown 10 thIS table are based on load projects, not potentIal mterconnectIons. New generatIOn interconnection may accelerate the in-service date.
NEW PROJECTS IN THE 2010-2019 TEN-YEAR PLAN
Mural- San Rafael 230kV.
This project is in response to the Fifth BTA order, which required the establishment of a
long range system plan for Cochise County. This project is needed to serve the electrical energy
need in the Cochise County area and is anticipated to be ajoint participation 230kV circuit.
CONCEPTUAL PROJECTS IN THE FEASIBILITY PLANNING PHASE
Palo Verde/Gila Bend Area To Valley Transmission Capacity.
Additional transmission capacity will be studied from the Palo Verde/Gila Bend areas to
the Phoenix load center. This transmission capacity is a robust component of the overall APS
transmission and resource need. The areas around and west of Palo Verde as well as the Gila
Bend area contain some of the best solar resources in the country. APS expects that at least a
-6-
![Page 10: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/10.jpg)
portion of the future solar resources specified in the APS resource plan will be developed in
relatively close proximity to these areas and will be supported by this transmission capacity.
These areas also provide access to existing gas resources and, in the case of Palo Verde, potential
new gas resources and market purchases. APS expects to need additional Palo Verde/Gila Bend
transmission capacity, beyond what is shown in this plan, to deliver these resources to load and
current! y expects to require this additional capacity in the 2018-2019 timeframe absent a desire
for advanced renewable resource development.
-7-
![Page 11: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/11.jpg)
PLANNED TRANSMISSION MAPS
• Arizona EHV and Outer Divisions (see page 9) • Phoenix Metropolitan Area (see page 10) • Yuma Area (see page 11)
-8
![Page 12: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/12.jpg)
APS EHV & OUTER DIVISION 1151230 KV TRANSMISSION PLANS 2010 - 2019
TO ELDORADO
TO IMPERIAL VALLEY
TO CRYSTAL
SELIGMAN
HARQUAHALA ___ _
2014
GILARIVERI PANDA
NAVAJO
MOENKOPI
MAZATZAL 2013
COOLIDGE
.-. VALLEY FARMS
PINAL CENTRAL 2014
A GRANDE
FOUR CORNERS
~~4:"-;.~>-:e
LEGENp
..L POWER PLANT
EXISTING 500 KV LINES EXISTING 345 KV LINES
EXISTING 230 KV LINES
EXISTING 115 KV LINES
PLANNED 500KV LINES PLANNED 230KV LINES
~ NUCLEAR POWER PLANT
• 115KV & ABOVE SUBSTATION (EXISTING)
o 230KV & ABOVE SUBSTATION (FUTURE)
Substa tion locations and line rouUngs depict an electrical connection only and do n2I. relleet any assumed physical locations or routing.
-9-
SAGUARO ORACLE SAN MANUEL JUNCTION
ADAMS
MU~ 12124109
Transmission Planning Tony\St. te_010
![Page 13: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/13.jpg)
PHOENIX METROPOLITAN AREA TRANSMISSION PLANS 2010·2019
2016~~-------------- ~~:~!!:.~ ,..- - - -"-r'1.'-~-'
R:AC:E1'N'~Y.""'!:: - __ .'-- ./ ~-,. / TBD -----,
201 ~VE.Ji, \ . / TS10 ,. /
o-:- TBD,. /
I~ " / SUN VALLEY dI . ~/2014 TRILBY """I~::::: WASH
I ~. I .. IQ I " /f TO
TO I PALO VERDE II
DELA"lY ~II \ I ~II ' '0 BELL
TS11 I TBD
RD. II
II
II II
I I I TS2 J.-l.
TBD I1 .. . ; 1 Nil
PALM II VALLEY
ELSOL
WHITE TANKS
,~----
TBD \ .. ' \ <3.' \ 0,
DEER VALLEY
AGUA
To Prescott '-:;
2010 -~--------------=
TS6 2012
101
LONE PEAK
REACH
TO GLEN
CANYON
ci II: C ::Ii 0::
BELL RD.
TO
PHOENIX 1-10FWY.
VERDE BASELINE RD.
.. OINn Y OWNED EXISTING 500KV LINES :=== APS EXISTING 345KV LINES APS EXISTING 230KV LINES
Panda
APS PLANNED LINES 230KV 500KV
230KV SUBSTATION (EXISTING.
230KV SUBSTATION (FUTUREO
GENERATING SITE & 230KV SUBSTATION 1M
230kV LINES OWNED BY SRP ORWAPA
345kV LINES OWNED BY WAPA
-10-
.... - ..... ~-.. TO BROWNING 1/20f10
Transmission Planning
![Page 14: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/14.jpg)
To Pilot Knob
H.O.
Laguna
San Luis
Yuma Area Transmission Plans 2010- 2019
yeA Power Plant
Double Circuit
2014
To ~------~ #2 Imperial ValleY "_I~ To
TS8 230169kV 2014
EXISTING SOOKV LINES EXISTING 161KV LINES
EXISTING 69KV LINES
APS PLANNED LINES
North Hassayampa Gila
Mittry
Clrcult·2014 2- Circuit. TBD
• • • • • • '-.
SOOKV SUBSTATION
NON-APS SUBSTATION
500kV ------
69KV SUBSTATION (EXISTING)
69KV SUBSTATION (FUTURE)
230KV SUBSTATION (FUTURE)
GENERATING SITE &. 69KV SUBSTATION
230kV ------Street. H~hway
• o • o o
1M Substation locations and line routings depict an electrical connection only and
do.D2l reflect any assumed physical locations or routing. 1120/10
Transmission Planning
-11-
![Page 15: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/15.jpg)
Line Designation
Project Sponsor
Other Participants
Size
Arizona Public Service Company 2010-2019
Ten-Year Plan Planned Transmission Description
Morgan - Pinnacle Peak 500kV Line (2010)
Arizona Public Service
SRP
(a) Voltage Class 500kV AC
(b) Facility Rating To be detennined
(c) Point of Origin Morgan substation to be in-service by 2010; Sec. 33, T6N, RIE
(d) Intermediate Points of Interconnection
(e) Point of Tennination
(1) Length
Routing
Purpose
Date
(a) Construction Start
(b) Estimated In Service
Perntitting / Siting Status
Pinnacle Peak substation; Sec. 4, T5N, RIE
Approximately 1.2 miles
South from Morgan substation approximately 2 miles, generally paralleling the Navajo-Westwing 500kV lines, then turning east at approximately Dove Valley road to west side of Interstate 17, the line will continue 5 miles south to approximately the Happy Valley Road alignment where it turns east to the Pinnacle Peak substation, parallel to an existing 230kV transmission line corridor.
This project is a result of joint planning through the SWAT forum. The project is needed to increase the import capability to the Phoenix Metropolitan area and the export/scheduling capability from the Palo Verde area to provide access to both solar and gas resources. The project also strengthens the transmission system on the east side of the Phoenix Metropolitan valley. The project is a joint participation project with APS as the project manager. The loop-in of the Navajo-Westwing 500kV line into the Morgan substation is the first phase of the project. Also, the line will be constructed as 500J230kV double-circuit capable, with the Morgan-Raceway-Avery-TS6-Pinnacle Peak 230kV line as the 230kV circuit.
2008
2010
Certificate of Environmental Compatibility issued on 2113107 (Case No. 131, Decision No. 69343, TS9-Pinnacle Peak 500!230kV Project).
-12-
![Page 16: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/16.jpg)
Line Designation
Project Sponsor
Other Participants Size
(a) Voltage Class (b) Facility Rating (c) Point of Origin
(d) Intennediate Points of Interconnection
(e) Point of Tennination
(f) Length
Routing
Purpose
Date (a) Construction Start (b) Estimated In Service
Pennitting / Siting Status
Arizona Public Service Company 2010-2019
Ten-Year Plan Planned Transmission Description
Morgan Raceway-Avery - TS6 - Pinnacle Peak 230kV Line (2011)
Arizona Public Service
None
230kVAC 3000 A Morgan substation to be in-service in 2010; Sec. 33. T6N, RlE
Raceway substation; Sec 4, T5N, RIE. Avery substation in-service TBD; Sec. 15, T5N, R2ETS6 substation to be in-service by 2014; Sec. 8, T4N, R3E Pinnacle Peak substation; Sec. 10, T4N, R4E
Approximately 27 miles
The Morgan 5001230kV substation will be constructed adjacent to the Dugas - Westwing 500kV line corridor. The Morgan-Raceway 230kV circuit will be constructed south num the Morgan substation to the existing Raceway substation. The circuit continues south num Raceway Substatioll approximately 1 mile, parallel to existing Navajo-Westwing transmission lines, then east approximately 9 miles along the Dove Valley Road alignment to the location of the future Avery substation. From Avery Substation the line will continue east along Dove Valley Road to Interstate 17. At Interstate 17, the route will head south 5 miles to the to the Happy Valley Road alignment. The line will tum east, generally parallel to an existing 230kV transmission line corridor, for approximately 10 miles to the existing Pinnacle Peak substation. This project is needed to provide electric energy in the northern portions of the Phoenix Metropolitan area, as well as adjacent areas to the north. The in-service date for the TS6 substation is currently scheduled for 2012. The in-service date for the Avery substation is currently outside the ten year planning horizon. The in-service dates for the substations and the 2nd 5001230k V transfonner at Morgan will be continuously evaluated in future planning studies.
2008 2010
Certificate of Environmental Compatibility issued on 2/13/07 (Case No. 131, Decision No. 69343, TS9-Pinnacle Peak5001230kV Project).
-13-
![Page 17: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/17.jpg)
Line Designation
Project Sponsor
Other Participants
Size
(a) Voltage Class
(b) Facility Rating
(c) Point of Origin
(d) Intermediate Points of Interconnection
Arizona Public Service Company 2010 - 2019
Ten-Year Plan Planned Transmission Description
TS 12 loop-in of Saguaro - Milligan 230k V Line (2012)
Arizona Public Service
None
230kVAC
188 MVA
Saguaro-Milligan 230kV line; approximately Sec. 17, nos, RIOE
(e) Point of Termination TS12 substation to be in-service by 2012; Sec. 17, nos, RIOE
(f) Length Less than 1 mile
Routing The TS12 230/69kV substation will be constructed adjacent to the Saguaro-Casa Grande 230k V line, approximately 2 miles west of the Saguaro Generating Facility.
Purpose This project is needed to provide electric energy in southern Pinal County as well as increase the reliability and continuity of service for these areas.
Date
(a) Construction Start 2011
(b) Estimated In Service 2012
Permitting / Siting Status It is not anticipated that a Certificate of Environmental Compatibility will be needed for this project.
-14-
![Page 18: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/18.jpg)
Arizona Public Service Company 2010-2019
Ten-Year Plan Planned Transmission Description
Line Designation Delany Palo Verde 500kV Line (2012)
Project Sponsor Arizona Public Service
Other Participants SRP,CAWCD
Size
(a) Voltage Class 500kVAC
(b) Facility Rating To be determined
(c) Point of Origin Palo Verde Switchyard
(d) Intermediate Points of Interconnection
(e) Point of Termination Future Delany switching station; approximately Sec. 25, T2N, R8W
(1) Length Approximately 15 miles
Routing Generally leaving the Palo Verde Hub vicinity following the Palo Verde-Devers #1 and the Hassayampa-Harquahala 500kV lines to the Delany Switchyard site in Sec. 25, T2N, R8W.
Purpose This project will increase the export! scheduling capability from the Palo Verde area to provide access to both solar and gas resources. This is anticipated to be a joint participation project. APS will serve as the project manager. The initial plan of service for the project will be a 500kV line between the Palo Verde Switchyard and the Delany Switchyard.
Date
(a) Construction Start 2011
(b) Estimated In Service 2012
Permitting / Siting Status Certificate ofEnvironmental Compatibility issued 8/17/05 (Case No. 128, Decision No. 68063, Palo Verde Hub to TS5500kV Transmission project). AP8, as project manager, holds the CEC.
6 The in-service date of2012 results from the Commission's directive in Decision No. 70635 and assumes Commission approval ofthe APS Renewable Transmission Action Plan ("RTAP") filed 1129/10. Absent approval, the in-service date of this project would be in 2014, coincident with the Delany to Sun Valley 500kV project.
-15
![Page 19: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/19.jpg)
Line Designation
Project Sponsor
Other Participants
Size
(a) Voltage Class
(b) Facility Rating
( c) Point of Origin
(d) Intermediate Points of Interconnection
Arizona Public Service Company 2010-2019
Ten-Year Plan Planned Transmission Description
345/69kV Interconnection at Western's Flagstaff 345kV bus (2012)
Arizona Public Service
None
345kVAC
100MVA
Western's Flagstaff 345kV substation; Sec. 24, T21N, R9E
(e) Point of Termination A new Flagstaff 69kV substation to be in-service by 2012; Sec. 24, T21N, R9E
(f) Length
Routing
Purpose
Date
Less than 1 mile
A 345/69kV transformer will interconnect into Western's Flagstaff substation.
This project is needed to provide the electrical source and support to the sub-transmission system in APS's northern service area. The project will provide increased reliability and continuity of service for the communities in northern Arizona.
(a) Construction Start 2011
(b) Estimated In Service 2012
Permitting I Siting Status It is not anticipated that a Certificate of Environmental Compatibility will be neededfor this project.
-16-
![Page 20: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/20.jpg)
Line Designation
Project Sponsor
Other Participants
Size
(a) Voltage Class
(b) Facility Rating
( c) Point of Origin
(d) Intermediate Points of Interconnection
Arizona Public Service Company 2010-2019
Ten-Year Plan Planned Transmission Description
Mazatzal loop-in of Cholla - Pinnacle Peak 345kV Line (2013)
Arizona Public Service
None
345kVAC
100MVA
Cholla-Pinnacle Peak or Preacher Canyon-Pinnacle Peak 345kV line; near Sec. 3, T8N, RIOE
(e) Point of Termination Mazatzal substation to be in-service by 2013; Sec. 3, T8N, RI0E
(f) Length Less than 1 mile
Routing The Mazatzal 345/69kV substation will be constructed adjacent to the Cholla-Pinnacle Peak 345kV line corridor.
Purpose This project is needed to provide the electric source and support to the sub-transmission system in the area of Payson and the surrounding communities. Additionally, improved reliability and continuity of service will result for the communities in the Payson area.
Date
(a) Construction Start 2012
(b) Estimated In Service 2013
Permitting I Siting Status It is anticipated that an application for a Certificate of Environmental Compatibility will be filed in 2010.
-17-
![Page 21: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/21.jpg)
Line Designation
Project Sponsor
Other Participants
Size
(a) Voltage Class
(b) Facility Rating
(c) Point of Origin
(d) Intermediate Points of Interconnection
Arizona Public Service Company 2010-2019
Ten-Year Plan Planned Transmission Descriptiou
Bagdad 115kV Relocation Project (2014)
Arizona Public Service
None
115kV AC
430 A
Bagdad Capacitor switchyard; Sec. 10. Tl4N, R9W
(e) Point of Termination Bagdad Mine substation; Sec. 31, Tl5N, R9W
(f) Length Approximately 5.5 miles
Routing Beginning at the existing APS capacitor switchyard and extending in a southwesterly direction for approximately 1.5 miles, then turning in a northwesterly direction approximately 4 miles to the existing Bagdad Mine substation. The project primarily crosses federal BLM lands, private lands (owned by the mine) and a short segment on Arizona State Trust Lands.
Purpose Freeport McMoRan mc. (HFMI") has future plans to expand the mine in the location of the existing 115k V transmission line. They have requested that APS move the line in a southerly direction beyond the limits of the planned expansion.
Date
(a) Construction Start 2013
(b) Estimated m Service 2014
Permitting / Siting Status Certificate of Environmental Compatibility issued on 7/16/09. (Case No. 143, Decision No. 71217, Bagdad 115kV Relocation Project).
-18-
![Page 22: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/22.jpg)
Line Designation
Project Sponsor
Other Participants
Size
(a) Voltage Class
(b) Facility Rating
(c) Point of Origin
(d) Intennediate Points of Interconnection
(e) Point ofTennination
(t) Length
Routing
Purpose
Date
(a) Construction Start
(b) Estimated In SelVice
Pennitting / Siting Status
Arizona Public Service Company 2010 - 2019
Ten-Year Plan Planned Transmission Description
Desert Basin - Pinal Central 230kV Line (2014)
Salt River Project
Arizona Public SCIVice
230kVAC
To be detennined
Desert Basin Power Plant Switchyard; Sec. 13, T6S, RSE
Pinal Central substation to be in-service by 2013; Sec. 30, T6S, R8E
Approximately 21 miles
From the Desert Basin Generation Station, in Casa Grande near Bums and Kortsen Roads, approximately 6 miles generally south and east to a point on the certificated SEV 500kV line near Cornman and Thornton Roads (vicinity of the proposed CA TSHV03 Substation). Then the 230kV line will be attached to the SOOkV structures for approximately 15 miles to the proposed Pinal Central Substation south of Coolidge, J\Z.
The project will improve the reliability of the 230k V system in the region by reducing the loading on existing lines in the area; increase local area system capacity and create one of the 230k V components of the CATSHV proposed transmission system for the central Arizona area APS participation in the project, along with the Sundance-Pinal Central 230kV line, will allow APS to increase the reliability and capability of delivering the output of the Sundance Generation Facility.
2012
2014
Authority for the portion of the 230kV line to be attached to the 500kV structures is providedfor in the CEC granted in Case No. 126, awarded in 2005 (Commission Decision No. 68093 and No. 68291), and subsequently corifirmed in Decision No. 69183, which approved SRP's compliance filingfor Condition 23 of the CEe. SRP was granted a CEC for Case No. 132 in 2007 (Commission Decision No. 69647) for the approximately six mile portion of the project not previously permitted from Desert Basin Generating Station to the vicinity ofComman and Thornton Roads south of Cas a Grande.
-19-
![Page 23: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/23.jpg)
Line Designation
Project Soonsor
Other Participants
Size
(a) Voltage Class
(b) Facility Rating
( c) Point of Origin
(d) Intermediate Points of Interconnection
(e) Point ofTerrnination
(f) Length
Routing
Purpose
Date
(a) Construction Start
(b) Estimated In Service
Permitting / Siting Status
Arizona Public Service Company 2010 - 2019
Ten-Year Plan Planned Transmission Description
Pinal Central- Sundance 230kV Line (2014)
Arizona Public Service
ED-2
230kVAC
3000 A
Sundance substation; Sec. 2, T6S, R7E
Pinal Central substation to be in-service by 2013; Sec. 30, T6S, R8E
Approximately 6 miles
The project will originate at a new substation on the Sundance property, proceeding west and then south along Curry Road to the half-section between State Route 287 and Earley Road. The fInal west to east aligmnent connecting into the Pinal Central Substation will be located within an ACC-approved corridor and is subject to further design and right-of-way acquisition analysis.
This project will serve increasing loads in Pinal County, and throughout the APS system, and will improve reliability and continuity of service for the communities in the area. Also, the project will increase the reliability of Sundance by providing a transmission line in a separate corridor than the existing lines that exit the plant. This project, in conjunction with the Desert Basin-Pinal Central 230k V project, will allow APS to reliably and economically deliver energy from Sundance over APS's transmission system. The project will be constructed as a 230kV double-circuit capable line, but initially operated as a single-circuit. The in-service date for the second circuit will be evaluated in future planning studies.
2013
2014
Certificate of Environmental Compatibility issued 4/29/08 (Case No. 136, Decision No. 70325, Sundance to Pinal South 230kV Transmission Line project). Note - the Pinal South substation is now referred to as Pinal Central.
-20-
![Page 24: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/24.jpg)
Line Designation
Project Sponsor
Other Participants
Size
(a) Voltage Class
(b) Facility Rating
( c) Point of Origin
(d) Intennediate Points of Interconnection
Arizona Public Service Company 2010-2019
Ten-Year Plan Planned Transmission Description
Delany - Sun Valley 500kV Line (2014)
Arizona Public Service
SRP,CAWCD
500kVAC
To be determined
Delany Substation
(e) Point of Tennination Sun Valley substation to be in-service by 2014; Sec. 29, T4N, R4W
(f) Length Approximately 28 miles
Routing Generally follows the Palo Verde-Devers #1 lines until crossing the CAP canal. Then easterly, generally following the north side of the CAP canal to the new Sun Valley substation.
Purpose This project will serve projected need for electric energy in the area immediately north and west of the Phoenix Metropolitan area. It will increase the import capability to the Phoenix Metropolitan area as well as increase the export! scheduling capability from the Palo Verde area to provide access to both solar and gas resources. The project will also increase the system reliability by providing a new transmission source to help serve the areas in the western portions of the Phoenix Metropolitan area. This is a joint participation project with APS as the project manager.
Date
(a) Construction Start 2012
(b) Estimated In Service 2014
Permitting / Siting Status Certificate of Environmental Compatibility issued 8/17/05 (Case No. 128, Decision No. 68063, Palo Verde Hub to TS5 500kV Transmission project). APS, as project manager, holds the CEC.
-21-
![Page 25: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/25.jpg)
Line Designation
Project Sponsor
Other Participants
Size
(a) Voltage Class
(b) Facility Rating
(c) Point of Origin
(d) Intermediate Points of Interconnection
Arizona Public Service Company 2010-2019
Ten-Year Plan Planned Transmission Description
Sun Valley - Trilby Wash 230kV Line (2014)
Arizona Public Service
None
230kV AC
3000 A
Sun Valley substation to be in-service by 2014; Sec. 29, T4N, R4W
(e) Point of Tennination Trilby Wash substation to be in-service by 2014; Sec. 20, T4N, R2W
(f) Length
Routing
Purpose
Date
Approximatel y 15 miles
East from the Sun Valley substation along the CAP canal to approximately 243rd Ave., south to the existing 500kV transmission line corridor, and then east along the corridor to the Trilby Wash substation.
This project is required to serve the need for electric energy in the western Phoenix Metropolitan area. Also, the project will provide more capability to import power into the Phoenix Metropolitan area along with improved reliability and continuity of service for communities in the area including El Mirage, Surprise, Youngtown, Buckeye, and unincorporated Maricopa county. The first circuit is scheduled to be in-service for the summer of 2014 and the in-service date for the second circuit will be evaluated in future planning studies.
(a) Construction Start 2013
(b) Estimated In Service 2014
Pennitting / Siting Status Certificate of Environmental Compatibility issued 5/5/05 (Case No. 127, Decision No. 67828, West Valley North 230kV Transmission Line project).
-22-
![Page 26: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/26.jpg)
Line Designation
Project Sponsor
Other Participants
Size
(a) Voltage Class
(b) Facility Rating
(c) Point of Origin
(d) Intermediate Points of Interconnection
Arizona Public Service Company 2010-2019
Ten-Year Plan Planned Transmission Description
20147
Palo Verde Hub - North Gila 500kV #2 Line (2014)
Arizona Public Service
SRP, lID, WMIDD
500kV AC
To be determined
Hassayampa switch yard
(e) Point of Termination North Gila substation; Sec. 11, T8S, R22W
(I) Length Approximately 110 miles
Routing This line will generally follow the route of the existing Hassayampa - North Gila 500kV #1 line.
Purpose This project will increase the import capability for the Yuma area and export/scheduling capability from the Palo Verde area to provide access to both solar and gas resources. This is a joint participation project with APS as the project manager. This project will also allow the system to accommodate generation interconnection requests.
Date
(a) Construction Start 2011
(b) Estimated In Service 2014
Permitting / Siting Status Certificate of Environmental Compatibility issued 1/23/08 (Case No. 135, Decision No. 70127, Palo Verde Hub to North Gila 500kV Transmission Line project).
7 The in·service date of 2014 assumes Commission approval of the APS RTAP, filed 1129/10.
-23-
![Page 27: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/27.jpg)
Line Designation
Project Sponsor
Other Participants
Size
(a) Voltage Class
(b) Facility Rating
(c) Point of Origin
(d) Intermediate Points of Interconnection
Arizona Public Service Company 2010 - 2019
Ten-Year Plan Planned Transmission Description
North Gila - TS8 230kV Line (2014)
Arizona Public Service
None
230kV AC
3000 A
North Gila substation; Sec. II, T8S, R22W
(e) Point of Termination TS8 230kV substation to be in-service by 2014;TBD
(f) Length To be determined
Routing The routing for this line has not yet been determined.
Purpose This project serves the need for electric energy, improved reliability, and continuity of service for the greater Yuma area. This project is expected to be double circuit capable with one circuit in service in 2014 and the second circuit in service at a date to be determined.
Date
(a) Construction Start 2012
(b) Estimated In Service 2014
Permitting / Siting Status It is anticipated that an application for a Certificate of Environmental Compatibility will be filed in 2010.
8 This project is linked with the Palo Verde to North Gila SOOkV project and will likely have the same in-service date.
-24-
![Page 28: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/28.jpg)
Line Designation
Project Sponsor
Other Participants
Size (a) Voltage Class (b) Facility Rating (c) Point of Origin
(d) Intermediate Points of Interconnection
(e) PointofTerrnination
(t) Length
Routing
Purpose
Date (a) Construction Start (b) Estimated In Service
Permitting / Siting Status
Arizona Public Service Company 2010- 2019
Ten-Year Plan Planned Transmission Description
Palm Valley - TS2 - Trilby Wash 230kV Line (2015)
Arizona Public Service
None
230kVAC 3000 A Palm Valley substation; Sec. 24, T2N, R2W
TS2 substation to be in-service by TBD; Sec. 25, TIN, R2W
Trilby Wash substation to be in-service by 2014; Sec. 20, T4N, R2W
Approximately 12 miles
North from the Palm Valley substation, generally following the Loop 303 to Cactus Road, west on Cactus Road to approximately 191st Avenue, and then north on 191st Avenue to the Trilby Wash substation.
This project will serve the need for electric energy in the western Phoenix Metropolitan area and additional import capability into the greater Phoenix Metropolitan area. The proposed second 230kV source for Trilby Wash provides improved system reliability and continuity of service for communities in the area; such as El Mirage, Surprise, Youngtown, Goodyear, and Buckeye. The first circuit is scheduled to be in-service for the summer of 2015; the in-service date for the second circuit will be evaluated in future planning studies. The in-service date for the TS2 substation is currently outside of the ten year planning horizon and will be continuously evaluated in future planning studies.
2014 2015 The Palm Valley- IS2 230kV line portion was sited as part of the West Valley South 230kV Transmission line project and a Certificate of Environmental Compatibility was issued 12124/03 (Case No. 122, Decision No. 66646). The Trilby Wash-IS2 230kV line portion was sited as part of the West Valley North 230kV Transmission line project and a Certificate of Environmental Compatibility was issued 5/5/05 (Case No. 127, Decision No. 67828).
-25-
![Page 29: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/29.jpg)
Line Designation
Project Sponsor
Other Participants
Size (a) Voltage Class
(b) Facility Rating
( c) Point of Origin
(d) Intermediate Points of Interconnection
(e) Point of Termination
(f) Length
Routing
Pumose
Date
Arizona Public Service Company 2010-2019
Ten-Year Plan Planned Transmission Description
Morgan - Sun Valley SOOkV Line (2016)
Arizona Public Service
SRP,CAWCD
SOOkV AC
To be determined
Sun Valley substation to be in-service in 2014; Sec. 29, T4N, R4W
Morgan substation to be in-service in 2010; Sec. 33, T6N, RlE
Approximately 40 miles
Generally the line will head north-northeast out of the Sun Valley substation and then east to the Morgan substation.
This project is needed to serve the need for electric energy in the Phoenix Metropolitan area. It will increase the import capability to the Phoenix Metropolitan area, as well as increase the export/scheduling capability from the Palo Verde area, which includes both solar and gas resources. The project will also increase the reliability of the EHV system by completing a SOOkV loop that connects the Palo Verde Transmission system, the Southern Navajo Transmission system, and the Southern Four Comers system. Additionally, the project will increase reliability by providing a second SOOkV source for the Sun Valley substation and providing support for multiple Category C and D transmission contingencies. This project is anticipated to be S00J230kV double-circuit capable.
(a) Construction Start 2013
(b) Estimated In Service 2016
Permitting I Siting Status Certificate oj Environmental Compatibility issued on 311712009 (Case No. 138, Decision No. 70850, TS5-TS9 5001230kV Project) An application Jor right-oj-way on the BLM portion oj the project has been submitted and will require NEPA compliance prior to land acquisition and Jinal engineering.
-26-
![Page 30: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/30.jpg)
Line Designation
Project Sponsor
Other Participants
Size
(a) Voltage Class
(b) Facility Rating
(c) Point of Origin
(d) Intermediate Points of Interconnection
Arizona Public Service Company 2010 -2019
Ten-Year Plan Planned Transmission Description
To Be Determined
Mural - San Rafael 230kV (To Be Determined)
Arizona Public Service
To be determined
230kV AC
To be determined
Mural substation
(e) Point of Termination San Rafael substation
(f) Length To Be Determined
Routing The route for this project has not yet been determined. Generally the line will head west-northwest out of the Mural substation and then west to the San Rafael substation.
Purpose
Date
This project was identified in the 2008 Biennial Transmission Assessment and is needed to serve the need for electric energy in the Cochise County area. It will increase the import capability to the Cochise County area, as well as increase the reliability of the local EHV system.
(a) Construction Start To be determined
(b) Estimated In Service To be determined
Permitting / Siting Status An application for a Certificate of Environmental Compatibility has not yet been filed.
-27-
![Page 31: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/31.jpg)
Line Designation
Project Sponsor
Other Participants
Size
(a) Voltage Class
(b) Facility Rating
(c) Point of Origin
(d) Intermediate Points of Interconnection
Arizona Public Service Company 2010-2019
Ten-Year Plan Planned Transmission Description
To Be Determined
Jojoba loop-in of TS4-Panda 230kV Line (To Be Determined)
Arizona Public Service
None
230kV AC
188MVA
TS4-Panda 230kV line; Sec. 25, T2S, R4W
(e) Point of Termination Jojoba 230/69 substation with an in-service TBD; Sec. 25, T2S, R4W
(f) Length Less than 1 mile
Routing The Jojoba 230/69kV substation will be constructed adjacent to the TS4-Panda 230k V line.
Purpose This project is needed to provide the electrical source and support to the sub-transmission system to serve the need for electric energy for the communities including Buckeye, Goodyear, and Gila Bend. The project will also increase the reliability and continuity of service for those areas.
Date
(a) Construction Start To be determined
(b) Estimated In Service To be determined
Permitting 1 Siting Status Certificate of Environmental Compatibility issued 10116100 (Case No. 102, Decision No. 62960, Gila River Transmission Project) for the Gila River Transmission Project included the interconnection of the 230kV substation.
-28-
![Page 32: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/32.jpg)
Line Designation
Project Sponsor
Other Participants
Size
(a) Voltage Class
(b) Facility Rating
(c) Point of Origin
(d) Intermediate Points of Interconnection
Arizona Public Service Company 2010-2019
Ten-Year Plan Planned Transmission Description
To Be Determined
TS8 - Yucca 230kV Line (To Be Determined)
Arizona Public Service
None
230kV AC
To be determined
Yucca substation; Sec. 36, T7S, R24W
(e) Point of Termination TS8 substation will be in-service in 2014; to be determined
(f) Length To be determined
Routing The routing for this line has not yet been determined.
Purpose This double circuit 230k V project is needed to serve the need for electric energy, improved reliability, and continuity of service for the greater Yuma area. This will project will also provide a second electrical source to the future TS8 substation. The ability to transmit electric energy generated by renewable resources in the region may be an additional benefit subject to study by APS in regional planning forums.
Date
(a) Construction Start To be determined
(b) Estimated In Service To be determined
Permitting / Siting Status An application for a Certificate of Environmental Compatibility has not yet been filed.
-29-
![Page 33: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/33.jpg)
Line Designation
Project Sponsor
Other Participants
Size
(a) Voltage Class
(b) Facility Rating
( c) Point of Origin
(d) Intermediate Points of Interconnection
Arizona Public Service Company 2010 - 2019
Ten-Year Plan Planned Transmission Description
To Be Determined
Sun Valley - TSlO -TSII 230kV Line (To Be Determined)
Arizona Public Service
None
230kV AC
To be determined
Sun Valley substation to be in-service by 2014; Sec. 29, T4N, R4W
A future TS 10 substation; location to be determined
(e) Point of Termination A future TSII substation; location to be determined
(f) Length To be determined
Routing The routing for this line has not yet been determined.
Purpose This project will be needed to provide a transmission source to serve future load that emerges in the current! y undeveloped areas northwest of the White Tank Mountains. This line is anticipated to be a 230k V line originating from the Sun Valley substation, with the future TS 10 230/69k V substation to be interconnected into the 230k V line.
Date
(a) Construction Start To be determined
(b) Estimated In Service To be determined
Permitting / Siting Status An application for a Certificate of Environmental Compatibility has not yet been filed.
-30-
![Page 34: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/34.jpg)
Line Designation
Project Sponsor
Other Participants
Size
(a) Voltage Class
(b) Facility Rating
(c) Point of Origin
(d) Intermediate Points of Interconnection
Arizona Public Service Company 2010 - 2019
Ten-Year Plan Planned Transmission Description
To Be Determined
Buckeye - TSll- Sun Valley 230kV Line (To Be Determined)
Arizona Public Service
None
230kV AC
To be determined
Sun Valley substation to be in-service by 2014; Sec. 29, T4N, R4W
A future TS 11 substation; location to be determined
(e) Point of Termination Buckeye substation; Sec. 7, TIN, R3W
(f) Length To be determined
Routing The routing for this line has not yet been determined.
Purpose This project is needed to serve the need for electric energy in the largely undeveloped areas west of the White Tank Mountains. This project will provide the first portion of the transmission infrastructure in this largely undeveloped area and provides a transmission connection between the northern and southern transmission sources that will serve the area. Improved reliability and continuity of service will result for this portion of Maricopa County. It is anticipated that this project will be constructed with double-circuit capability, but initially operated as a single circuit. The in-service date and location of the TS 11 230/69kV substation will be determined in future planning studies based upon the development of the area.
Date
(a) Construction Start To be determined
(b) Estimated In Service To be determined
Permitting I Siting Status An application for a Certificate of Environmental Compatibility has not yet been filed.
-31-
![Page 35: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/35.jpg)
Line Designation
Project Sponsor
Other Participants
Size
(a) Voltage Class
(b) Facility Rating
(c) Point of Origin
(d) Intermediate Points of Interconnection
Arizona Public Service Company 2010-2019
Ten-Year Plan Planned Transmission Description
To Be Determined
Morgan - Sun Valley 230kV Line (To Be Determined)
Arizona Public Service
None
230kV AC
To be determined
Sun Valley substation to be in-service by 2014; Sec. 29, T4N, R4W
To be determined
(e) Point of Termination Morgan substation to be in-service in 2010; Sec. 33, T6N, RIE
(f) Length Approximately 40 miles
Routing This line is expected to be co-located with the Sun Valley to Morgan 500kV line, which generally heads north-northeast out of the Sun Valley substation and then east to the Morgan substation.
Purpose This project will be needed to provide a transmission source to serve future load that emerges in the currently undeveloped areas south and west of Lake Pleasant. This line is anticipated to be the 230kV circuit on the Sun Valley-Morgan 5001230kV doublecircuit line.
Date
(a) Construction Start To be determined
(b) Estimated In Service To be determined
Permitting / Siting Status Certificate of Environmental Compatibility issued on 311712009 (Case No. 138, Decision No. 70850, TS5-TS9 5001230kV Project).
-32-
![Page 36: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/36.jpg)
Line Designation
Project Sponsor
Other Participants
Size
(a) Voltage Class
(b) Facility Rating
(c) Point of Origin
(d) Intennediate Points of Interconnection
Arizona Public Service Company 2010 - 2019
Ten-Year Plan Planned Transmission Description
To Be Determined
Raceway - Westwing 230kV Line (To Be Detennined)
Arizona Public Service
None
230kV AC
To be detennined
Westwing substation; Sec. 12, T4N, RIW
(e) Point of Tennination Raceway substation; Sec. 4, T5N, RIE
(f) Length Approximately 7 miles
Routing Northeast from Westwing substation paralleling existing transmission lines to the Raceway 230kV substation.
Purpose This project will serve the need for electric energy in the far north and northwest parts of the Phoenix Metropolitan area and provide contingency support for multiple Westwing 5001230k V transfonner outages. The in-service date will continue to be evaluated in future planning studies.
Date
(a) Construction Start To be detennined
(b) Estimated In Service To be detennined
Pennitting / Siting Status Certificate of Environmental Compatibility issued 6118103 (Case No. 120, Decision No. 64473, North Valley 230kV Transmission Line Project).
-33-
![Page 37: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/37.jpg)
Line Designation
Project Sponsor
Other Participants
Size
(a) Voltage Class
(b) Facility Rating
(c) Point of Origin
(d) Intermediate Points of Interconnection
Arizona Public Service Company 2010-2019
Ten-Year Plan Planned Transmission Description
To Be Determined
El Sol- Westwing 230kV Line (To Be Detennined)
Arizona Public Service
None
230kV AC
To be determined
Westwing substation; Sec. 12, T4N, RIW
(e) Point of Termination El Sol substation; Sec. 30, T3N, RIE
(f) Length Approximately II miles
Routing Per certificate. Generally following the existing WestwingSurprise-El Sol 230kV corridor.
Purpose This project will increase system capacity to serve the Phoenix Metropolitan area, while maintaining system reliability and integrity for delivery of bulk power from Westwing south into the APS Phoenix Metropolitan area 230kV transmission system.
Date
(a) Construction Start To be determined
(b) Estimated In Service To be determined
Permitting / Siting Status Certificate of Environmental Compatibility issued 7126173 (Case No.9, Docket No. U-1345 J. Note that this Certificate authorizes two double-circuit lines. Construction of the first double-circuit line was completed in March 1975. Construction of the second line, planned to be built with double-circuit capability, but initially operated with a single circuit, is described above.
-34-
![Page 38: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/38.jpg)
Line Designation
Project Sponsor
Other Participants
Size
(a) Voltage Class
(b) Facility Rating
(c) Point of Origin
(d) Intennediate Points of Interconnection
Arizona Pnblic Service Company 2010 - 2019
Ten-Year Plan Planned Transmission Description
To Be Determined
Palo Verde - Saguaro 500kV Line (To Be Determined)
CATS Sub-Regional Planning Group Participants
To be detennined
500kV AC
To be detennined
Palo Verde switchyard; Sec. 34, TIN, R6W
(e) Point of Tennination Saguaro substation; Sec. 14, nos, RlOE
(f) Length Approximately 130 miles
Routing Generally south and east from the Palo Verde area to a point near Gillespie Dam, then generally easterly until the point at which the Palo Verde-Kyrene 500kV line diverges to the north and east. The corridor then continues generally south and east again, adjacent to a gas line corridor, until converging with the Tucson Electric Power Company's Westwing-South 345kV line. The corridor follows the 345k V line until a point due west of the Saguaro Generating Station. The corridor then follows a lower voltage line into the 500kV yard just south and east of the Saguaro Generating Station.
Purpose This line is the result of the joint participation CATS study. The line will be needed to increase the adequacy of the existing EHV transmission system and permit increased power delivery throughout the state.
Date
(a) Construction Start To be determined
(b) Estimated In Service To be detennined
Pennitting / Siting Status Certificate of Environmental Compatibility issued 112311976 (Case No. 24, Decision No. 46802).
-35-
![Page 39: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/39.jpg)
A subsidiary of Pinnacle West Capital Corporafion
TRANSMISSION PLANNING
PROCESS AND GUIDELINES
APS Transmission Planning
January 2010
![Page 40: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/40.jpg)
TRANSMISSION PLANNING PROCESS AND GUIDELINES
I. INTRODUCTION and PURPOSE ................................................................ 1
II. PLANNING METHODOLOGY
A. General ........................................................................................................... 1
B. Transmission Planning Process ...................................................................... 2
1. EHV Transmission Planning Process ...................................................... 2
2. 230kV Transmission Planning Process .................................................... 3
3. Transmission Facilities Required for GenerationiResource Additions ... 3
C. Ten Year Transmission System Plans ........................................................... .4
D. Regional Coordination Planning ................................................................... .4
1. Western Electricity Coordinating Council... ........................................... .4
2. Sub-Regional Planning Groups ............................................................... .4
3. West Connect ........................................................................................... 5
4. Joint Studies ............................................................................................. 5
E. Generation Schedules ..................................................................................... 5
F. Load Projections ............................................................................................ 6
G. Alternative Evaluations .................................................................................. 6
1. General ..................................................................................................... 6
2. Power Flow Analyses .............................................................................. 6
3. Transient Stability Studies ....................................................................... 7
4. Short Circuit Studies ................................................................................ 7
5. Reactive Power Margin Analyses ............................................................ 7
6. Losses Analyses ....................................................................................... 7
7. Transfer Capability Studies ...................................................................... 7
8. Subsynchronous Resonance (SSR) .......................................................... 7
9. FACTS ..................................................................................................... 8
10. Economic Evaluation ............................................................................... 8
![Page 41: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/41.jpg)
III. PLANNING ASSUMPTIONS
A. General
1. Loads ........................................................................................................ 8
2. Generation and Other Resources ............................................................. 8
3. Nominal Voltage Levels .......................................................................... 8
4. Sources of Databases ............................................................................... 9
5. Voltage Control Devices .......................................................................... 9
6. Phase Shifters ........................................................................................... 9
7. Conductor Sizes ....................................................................................... 9
8. 69kV System Modeling ........................................................................... 9
9. Substation Transformers .......................................................................... 10
a. 500k V & 345k V Substations ............................................................. 10
b. 230kV Substations ............................................................................. 10
10. Switchyard Arrangements ........................................................................ 10
a. 500k V & 345k V Substations ............................................................. 10
b. 230kV Substations ............................................................................. 11
11. Series Capacitor Application ................................................................... 11
12. Shunt and Tertiary Reactor Application .................................................. 12
B. Power Flow Studies
1. System Stressing ...................................................................................... 12
2. Displacement ............................................................................................ 12
C. Transient Stability Studies
1. Fault Simulation ....................................................................................... 12
2. Margin ...................................................................................................... 12
3. Unit Tripping ........................................................................................... 13
4. Machine Reactance Representation ......................................................... 13
5. Fault Damping ......................................................................................... 13
6. Series Capacitor Switching ...................................................................... 13
D. Short Circuit Studies
1. Generation Representation ....................................................................... 13
2. Machine Reactance Representation ......................................................... 13
ii
![Page 42: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/42.jpg)
3. Line Representation ................................................................................. 13
4. Transformer Representation ..................................................................... 13
E. Reactive Power Margin Studies ..................................................................... 14
IV. SYSTEM PERFORMANCE
A. Power Flow Studies
1. Normal (Base Case Conditions)
a. Voltage Levels
1) General ............................................... """""'''''''' ........................ 14
2) Specific Buses .................................... """'"'''''''' ......................... 14
b. Facilities Loading Limits
1) Transmission Lines ................................................... " ................. 15
2) Underground Cable ...................................................................... 15
3) Transformers ................................................................................ 15
4) Series Capacitors .......................................................................... 15
c. Interchange of V ARs ......................................................................... 15
d. Distribution of Flow ................................. """'"'''''''' ......................... 15
2. Single Contingency Outages
a. Voltage Levels ................................................................................... 15
b. Facilities Loading Limits
1) Transmission Lines ...................................................................... 15
2) Underground Cable ...................................................................... 16
3) Transformers ................................................................................ 16
4) Series Capacitors .......................................................................... 16
c. Generator Units ................ """"""""""""'"'''''''''''''' ......................... 16
d. Impact on Interconnected Systems .................................................... 16
B. Transient Stability Studies ............................................................................. 16
1. Fault Simulation .............................................. "" .. " .. "." .......................... 16
2. Series Capacitor Switching ...................................................................... 1 7
3. System Stability ....................................................................................... 17
4. Re-closing ................................................................................................ 17
iii
![Page 43: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/43.jpg)
C. Short Circuit Studies ...................................................................................... 17
D. Reactive Power Margin Studies ..................................................................... 17
IV
![Page 44: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/44.jpg)
I. INTRODUCTION AND PURPOSE
The Transmission Planning Process and Guidelines (Guidelines) are used
by Arizona Public Service Company (APS) to assist in planning its Extra High
Voltage (EHV) transmission system (34SkV and SOOkV) and High Voltage
transmission system (230kV and IISkV). In addition to these Guidelines, APS
fo llows the Western Electricity Coordinating Council's (WECC) regional
planning reliability criteria for system disturbance and performance levels. These
WECC Reliability Criteria are (I) WECC/NERC Reliability Criteria for
Transmission System Planning and (2) Minimum Operating Reliability Criteria,
which can be found in their entirety on the WECC website;
(http://www.wecc.bizldocumentsll i brary/procedures/CriteriaMaster. pd D. These
Guidel ines are for internal use by APS and may be changed or modified. Thus,
others should not use these Guidelines without consultation with APS.
II. PLANNING METHODOLOGY
A. General
APS uses a deterministic approach for transmission system planning.
Under this approach, system performance should meet certain specific criteria
under normal conditions (all lines in-service) and for any single contingency
condition (anyone element out-of-service). In general, an adequately planned
transmission system will:
• Provide an acceptable level of service that is cost-effective for normal and
single contingency operating conditions.
• Maintain service to all firm loads for any single contingency outage;
except for radial loads.
• Not result in overloaded equipment or unacceptable voltage conditions for
single contingency outages.
• Not result in cascading for single or double contingency outages.
• Provide for the proper balance between the transmission impOlt capability
and local generation requirements for an import limited load area.
![Page 45: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/45.jpg)
Although APS uses a deterministic approach for transmission system
planning, the WECC reliability planning criteria provides for exceptions based
upon a probabilistic approach. APS uses these probabilistic criteria when/where
appropriate in the transmission planning process. Historical system reliability
performance is analyzed on a periodic basis and the results are used in the design
of planned facilities.
These planning methodologies, assumptions, and guidelines are used as
the basis for the development of future transmission facilities. Additionally,
consideration of potential alternatives to transmission facilities (such as
distributed generation or new technologies) is evaluated on a case-specific basis.
As new planning tools and/or information become available revisions or
additions to these guidelines will be made as appropriate.
B. Transmission Planning Process
APS' transmission planning process consists of an assessment of the
following needs:
• Provide adequate transmission to access designated network resources
in-order to reliably and economically serve all network loads.
• Support APS' and other network customers' local transmission and
sub-transmission systems.
• Provide for interconnection for new resources.
• Accommodate requests for long-term transmission access.
During this process, consideration is given to load growth patterns, other
system changes affected by right-of-way, facilities siting constraints, routing of
future transportation corridors, and joint planning with neighboring utilities,
governmental entities, and other interested stakeholders (see APS OA TT
Attachment (E).
1. EHV Transmission Planning Process
APS' EHV transmission system, which consists of 500kV and 345kV, has
primarily been developed to provide transmission to bring the output of large
base-loaded generators to load centers, such as Phoenix. Need for new EHV
2
![Page 46: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/46.jpg)
facilities may result from any of the bullet items described above. APS'
annual planning process includes an assessment of APS' transmission
capability to ensure that designated network resources can be accessed to
reliably and economically serve all network loads. In addition, biennial RMR
studies are performed to ensure that proper balance between the transmission
import capability and local generation requirements for an import limited load
area are maintained.
2. 230k V Transmission Planning Process
APS' 230kV transmission system has primarily been developed to provide
transmission to distribute power from the EHV bulk power substations and
local generators to the distribution system and loads throughout the load areas.
Planning for the 230k V system assesses the need for new 230/69k V
substations to support local sub-transmission and distribution system growth
and the reliability performance of the existing 230k V system. This process
takes into account the future land use plans that were developed by
government agencies, Landis aerial photo maps, master plans that were
provided by private developers, and APS' long-range forecasted load densities
per square mile for residential, commercial, and industrial loads.
3. Transmission Facilities Required for GenerationlResource Additions
New transmission facilities may also be required in conjunction with
generation resources due to (I) a "merchant" request by an Independent
Power Producer (IPP) for generator interconnection to the APS system, (2) a
"merchant" request for point-to-point transmission service from the generator
(receipt point) to the designated delivery point, or (3) designation of new
resources or re-designation of existing units to serve APS network load
(including removal of an older units' native load designation). These
studies/processes are performed pursuant to the APS Open Access
Transmission Tariff (OA TT).
3
![Page 47: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/47.jpg)
C. Ten Year Transmission System Plans
Each year APS uses the planning process described in section B to update
the Ten-Year Transmission System Plan. The APS Ten Year Transmission
System Plan identifies all new transmission facilities, 115kV and above, and all
facility replacements/upgrades required over the next ten years to reliably and
economically serve the load.
D. Regional Coordinated Planning
1. Western Electricity Coordinating Council (WECC)
APS is a member of the Western Electricity Coordinating Council. The
focus of the WECC is on promoting the reliability of the interconnected bulk
electric system. The WECC provides the means for:
• Developing regional planning and operating criteria.
• Coordinating future plans.
• Compiling regional data banks for use by the member systems and the
WECC in conducting technical studies.
• Assessing and coordinating operating procedures and solutions to regional
problems.
• Establishing an open forum with interested non-project participants to
review the plan of service for a project.
• Through the WECC Transmission Expansion Policy Committee,
performing economic transmission congestion analysis.
APS works with WECC to adhere to these planning practices.
2. Sub-Regional Planning Groups
Southwest Area Transmission Planning (SWAT) and other sub-regional
planning groups provide a forum for entities within a region, and any other
interested parties, to determine and study the needs of the region as a whole.
It also provides a forum for specific projects to be exposed to potential
partners and allows for joint studies and participation from interested parties.
4
![Page 48: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/48.jpg)
3. WestConnect
APS and the other WestConnect members executed the WestConnect Project
Agreement for Subregional Transmission Planning in May of 2007. This
agreement promotes coordination of regional transmission planning for the
WestConnect planning area by formalizing a relationship among the
WestConnect members and the WestConnect area sub-regional planning
groups including SWAT. The agreement provides for resources and funding
for the development of a ten year integrated regional transmission plan for the
WestConnect planning area. The agreement also ensures that the
WestConnect transmission planning process will be coordinated and
integrated with other planning processes within the Western Interconnection
and with the WECC planning process.
4. Joint Studies
In many instances, transmission projects can serve the needs of several
utilities and/or IPPs. To this end, joint study efforts may be undertaken. Such
joint study efforts endeavor to develop a plan that will meet the needs and
desires of all individual companies involved.
E. Generation Schedules
For planning purposes, economic dispatches of network resources are
determined for APS' system peak load in the following manner:
a. Determine base generation available and schedule these units at maximum
output.
b. Determine resources purchased from other utilities, IPPs, or power
marketing agencies.
c. Determine APS' spinning reserve requirements.
d. Schedule intermediate generation (oil/gas steam units) such that the
spinning reserve requirements, in section ( c) above, are met.
e. Determine the amount of peaking generation (combustion turbine units)
required to supply the remaining system peak load.
5
![Page 49: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/49.jpg)
Phoenix area network resources are dispatched based on economics and
any existing import limitations. When possible, spinning reserve will be carried
on higher cost Phoenix area network generating units.
Generation output schedules for interconnected utilities and IPPs are based
upon consultation with the neighboring utilities and IPPs or as modeled in the
latest data in WECC coordinated study cases.
F. Load Projections
APS substation load projections are based on the APS Corporate Load
Forecast. Substation load projections for neighboring interconnected utilities or
power agencies operating in the WECC area are based on the latest data in WECC
coordinated study cases. Heavy summer loads are used for the Ten-Year
Transmission System Plans.
G. Alternative Evaluations
l. General
In evaluating several alternative plans, comparisons of power flows,
transient stability tests, and fault levels are made first. After the alternatives
are found that meet the system performance criteria in each of these three
areas comparisons may be made of the losses, transfer capability, impact on
system operations, and reliability of each of the plans. Finally, the costs of
facility additions (capital cost items), costs of losses, and relative costs of
transfer capabilities are determined. A brief discussion of each of these
considerations follows.
2. Power Flow Analyses
Power flows of base case (all lines in-service) and single contingency
conditions are tested and should conform to the system performance criteria
set forth in Section IV of these Guidelines. Double or multiple contingencies
are examined, but in general, no facilities are planned for such conditions.
Normal system voltages, voltage deviations, and voltage extreme limitations
are based upon operating experience resulting in acceptable voltage levels to
6
![Page 50: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/50.jpg)
the consumer. Power flow limits are based upon the thermal ratings andlor
sag limitations of conductors or equipment, as applicable.
3. Transient Stability Studies
Stability guidelines are established to maintain system stability for single
contingency, three-phase fault conditions. Double or multiple contingencies
are examined, but in general, no facilities are planned for such conditions.
4. Short Circuit Studies
Three-phase and single-phase-to-ground fault studies are performed to
ensure the adequacy of system protection equipment to clear and isolate faults.
5. Reactive Power Margin Analyses
Reactive Power Margin analyses are performed when steady-state
analyses indicate possible insufficient voltage stability margins. V-Q curve
analyses are used to determine post-transient voltage stability.
6. Losses Anal yses
A comparison of individual element and overall transmission system
losses are made for each alternative plan being studied. The losses computed
in the power flow program consist of the eR losses of lines and transformers
and the core losses in transfonners, where represented.
7. Transfer Capability Studies
In evaluating the relative merits of one or more EHV transmission plans,
both simultaneous and non-simultaneous transfer capability studies are
performed to determine the magnitude of transfer capabilities between areas
or load centers.
8. Sub synchronous Resonance (SSR)
SSR phenomenon result from the use of series capacitors in the network
where the tuned electrical network exchanges energy with a turbine generator
at one or more of the natural frequencies of the mechanical system. SSR
countenneasures are applied to prevent damage to machines as a result of
transient current or sustained oscillations following a system disturbance.
SSR studies are not used directly in the planning process. SSR
countenneasures are determined after the transmission plans are finalized.
7
![Page 51: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/51.jpg)
9. FACTS (Flexible AC Transmission System)
FACTS devices are a recent application of Power Electronics to the
transmission system. These devices make it possible to use circuit reactance,
voltage magnitude and phase angle as control parameters to redistribute power
flows and regulate bus voltages, thereby improving power system operation.
FACTS devices can provide series or shunt compensation. These devices can
be used as a controllable voltage source in series or as a controllable current
source in shunt mode to improve the power transmission system operations.
FACTS will be evaluated as a means of power flow control and/or to provide
damping to dynamic oscillations where a need is identified and it is
economicall y justified.
10. Economic Evaluation
In general, an economic evaluation of alternative plans consists of a
cumulative present worth or equivalent annual cost comparison of capital
costs.
III. PLANNING ASSUMPTIONS
A. General
1. Loads
Loads used for the APS system originate from the latest APS Corporate
Load Forecast. In most cases, the corrected power factor of APS loads is
99.5% at 69kV substations.
2. Generation and Other Resources
Generation dispatch is based on firm power and/or transmission wheeling
contracts including network resources designations.
3. Normal Voltage Levels
a. Nominal EHV design voltages are 500kV, 345kV, 230kV, and 115kV.
b. Nominal EHV operating voltages are 535kV, 348kV, 239kV, and 119kV.
8
![Page 52: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/52.jpg)
4. Sources of Databases
WECC Heavy Summer base cases are the sources of the databases. Loop
flow (unscheduled flow), of a reasonable amount and direction, will be
allowed for use in planning studies.
S. Voltage Control Devices
Devices which can control voltages are shunt capacitors, shunt reactors,
tap-changing-under-Ioad (TCUL) and fixed-tap transformers, static V AR
compensators, and machine V AR capabilities. If future voltage control
devices are necessary, these devices will be evaluated based upon economics
and the equipment's ability to obtain an adequate voltage profile on the EHV
and HV systems.
6. Phase Shifters
In general, where phase shifters are used, schedules are held across the
phase shifter in base case power flows and the phase shifter tap remains fixed
in the outage cases.
7. Conductor Sizes
Existing transmission voltages utilized by APS are 230kV, 34SkV, and
SOOkV. It is presently planned that the 34SkV transmission system will not be
expanded, thus all future APS EHV lines will be SOOkV or 230kV. Planned
SOOkV lines will initially be modeled using tri-bundled 1780 kCM ACSR
conductor (Chukar). Preferred construction for 230kV lines consists of 21S6
kCM ACSS conductor on steel poles.
8. 69kV System Modeling
230kV facility outages may result in problems to the underlying 69kV
system due to the interconnection of those systems. For this reason, power
flow cases include a detailed 69kV system representation. Solutions to any
problems encountered on the 69kV system are coordinated with the
subtransmission planning engineers.
9
![Page 53: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/53.jpg)
9. Substation Transformers
a. 500kV and 345kV Substations
Bulk substation transformer banks may be made up of one three-phase
or three single-phase transformers, depending upon bank size and
economics. For larger banks where single-phase transformers are used, a
fourth (spare) single-phase transformer will be used in a jack-bus
arrangement to improve reliability and facilitate connection of the spare in
the event of an outage of one of the single-phase transformers. TCUL will
be considered in the high voltage windings, generally with a range of plus
or minus 10%. High voltage ratings will be 500kV or 345kV class and
low voltage windings will be 230k V, 115k V, or 69k V class.
b. 230kV Substations
For high-density load areas, both 230/69kV and 69/12.5kV
transformers can be utilized. 230/69k V transformers will be rated at
1131150/188 MVA with a 65°C temperature rise, unless otherwise
specified. 69/12.5kV transformers will be rated at 25/33/41 MVA with a
65°C temperature rise, unless otherwise specified.
With all elements in service, a transformer may be loaded up to its top
Forced Oil Air (FaA) rating without sustaining any loss of service life.
For a single contingency outage (loss of one transformer) the remaining
transformer or transformers may be loaded up to 20% above their top FaA
rating, unless heat test data indicate a different overload capability. The
loss of service life sustained will depend on the transformer pre-loading
and the outage duration. Tap setting adjustment capabilities on 230/69kV
transformers will be ±5% from the nominal voltage setting (230/69kV) at
2Y2% increments.
10. Switch yard Arrangements
a. 500kV and 345kV Substations
Existing 345kV switchyard arrangements use breaker-and-one-half,
main-and-transfer, or modified paired-element circuit breaker switching
10
![Page 54: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/54.jpg)
schemes. Because of the large amounts of power transferred via SOOk V
switchyards and the necessity of having adequate reliability, all SOOkV
circuit breaker arrangements are planned for an ultimate breaker-and-one
half scheme. If only three or four elements are initially required, the
circuit breakers are connected in a ring bus arrangement, but physically
positioned for a breaker-and-one-half scheme. The maximum desired
number of elements to be connected in the ring bus arrangement is four.
System elements such as generators, transformers, and lines will be
arranged in breaker-and-one-half schemes such that a failure of a center
breaker will not result in the loss of two lines routed in the same general
direction and will minimize the impact of losing two elements.
b. 230kV Substations
Future 230/69kV substations should be capable of serving up to 4S2
MVA of load. 400 MVA has historically been the most common
substation load level in the Phoenix Metropolitan area. Future, typical
230/69kV substations should accommodate up to four 230kV line
terminations and up to three 230/69kV transformer bays. Based upon
costs, as well as reliability and operating flexibility considerations, a
breaker-and-one-half layout should be utilized for all future 230/69kV
Metropolitan Phoenix Area substations, with provision for initial
development to be a ring bus. Any two 230/69kV transformers are to be
separated by two breakers, whenever feasible, so that a stuck breaker will
not result in an outage of both transformers.
11. Series Capacitor Application
Series capacitors may be used on EHV lines to increase system stability,
for increased transfer capability, and/or for control of power flow. The series
capacitors may be lumped at one end of a line because of lower cost; however,
the capacitors are generally divided into two banks, one at either end of a line,
for improved voltage profile.
11
![Page 55: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/55.jpg)
12. Shunt and Tertiary Reactor Application
Shunt and/or tertiary reactors may be installed to prevent open end line
voltages from being excessive, in addition to voltage control. The open end
line voltage must not be more than 0.05 per unit voltage greater than the
sending end voltage. Tertiary reactors may also be used for voltage and V AR
control as discussed above.
B. Power Flow Studies
1. System Stressing
Realistic generation capabilities and schedules should be used to stress the
transmission system in order to maximize the transfer of resources during the
maximum load condition.
2. Displacement
In cases where displacements (due to power flow opposite normal
generation schedules) may have an appreciable effect on transmission line
loading, a reasonable amount of displacement (Generation Units) may be
removed in-order to stress a given transmission path.
C. Transient Stability Studies
1. Fault Simulation
When studying system disturbances caused by faults, two conditions will
be simulated:
a. Three-phase-to-ground faults, and
b. Single-line-to-ground faults with a stuck circuit breaker in one phase with
back-up delayed clearing.
2. Margin
a. Generation margin may be applied for the contingencies primarily affected
by generation, or
b. Power flow margin may be applied for the contingencies primarily
affected by power flow.
12
![Page 56: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/56.jpg)
3. Unit Tripping
Generator unit tripping may be allowed in-order to increase system
stability performance.
4. Machine Reactance Representation
For transient stability studies, the unsaturated transient reactance of
machines with full representation will be used.
5. Fault Damping
Fault damping will be applied to the generating units adjacent to faults.
Fault damping will be determined from studies that account for the effect of
generator amortisseur windings and the SSR filters.
6. Series Capacitor Switching
Series capacitors, locations to be determined from short circuit studies,
will be flashed and reinserted as appropriate.
D. Short Circuit Studies
Three-phase and single-phase-to-ground faults will be evaluated.
1. Generation Representation
All generation will be represented.
2. Machine Reactance Representation
The saturated subtransient reactance (X"d) values will be used.
3. Line Representation
The transmission line zero sequence impedance (Xo) is assumed to be
equal to three times the positive sequence impedance (XI).
4. Transformer Representation
The transformer zero sequence impedance (Xo) is assumed to be equal to
the positive sequence impedance (XI). Bulk substation transformers are
modeled as auto-transformers. The two-winding model is that of a grounded
wye transformer. The three-winding model is that of a wye-delta-wye with a
solid ground.
13
![Page 57: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/57.jpg)
E. Reactive Power Margin Studies
Using Q-V curve analyses, APS assesses the interconnected transmission
system to ensure there are sufficient reactive resources located throughout the
electric system to maintain post-transient voltage stability for system normal
conditions and certain contingencies.
IV. SYSTEM PERFORMANCE
A. Power Flow Studies
1. Normal (Base Case Conditions)
a. Voltage Levels
I) General
(a) 500kV bus voltages will be maintained between 1.05 and 1.08 p.u.
on a 500kV base.
(b) 345kV bus voltages will range between .99 and 1.04 p.u. on the
345kV system.
(c) 500kV and 345kV system voltages are used to maintain proper
230kV bus voltages.
(d) Voltage on the 230kV and 115kV system should be between 1.01
p.u. and 1.05 p.u.
(e) Tap settings for 230/69kV and 345/69kV transformers should be
used to maintain low side (69kV) voltages of 1.03 to 1.04 p.u.
Seasonal tap changes may be required.
2) Specific Buses
(a) APS Pinnacle Peak 230kV bus voltage should be between 1.025
p.u. and 1.035 p.u.
(b) APS Westwing 230kV bus voltage should be between 1.04 p.u.
and 1.05 p.u.
(c) Saguaro 115kV bus voltage will be approximately 1.035 p.u.
(d) Voltage at the Prescott (DOE) 230kV bus should be approximately
1.02 p.u.
14
![Page 58: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/58.jpg)
b. Facility Loading Limits
1) Transmission Lines
Transmission line loading cannot exceed 100% of the continuous
rating, which is based upon established conductor temperature limit or
sag limitation.
2) Underground Cable
Underground cable loading should not exceed 100% of the
continuous rating with all elements in service. This rating is based on
a cable temperature of 85°C with no loss of cable life.
3) Transformers
Transformers cannot exceed 100% of top FaA, 65°C rise,
nameplate ratings.
4) Series Capacitors
Series Capacitors cannot exceed 100% of continuous rating.
c. Interchange of V ARs
Interchange of V ARs between companies at interconnections will be
reduced to a minimum and maintained near zero.
d. Distribution of Flow
Schedules on a new project will be compared to simulated power
flows to ensure a reasonable level of flowability.
2. Single Contingency Outages
a. Voltage Levels
Maximum voltage deviation on APS' major buses cannot exceed 5%.
This deviation level yields a close approximation to the post-transient
V AR margin requirements of WECC.
b. Facilities Loading Limits
1) Transmission Lines
Transmission line loading cannot exceed 100% of the lesser of the
sag limit or the emergency rating (30-minute rating) which is based
upon established conductor temperature limits.
15
![Page 59: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/59.jpg)
2) Underground Cable
Underground cable loading should not exceed the emergency
rating during a single-contingency outage. This rating is based on a
cable temperature of 105°C for two hours of emergency operation with
no loss of cable life.
3) Transformers
Transformers cannot exceed 120% of top FOA, 65°C nse,
nameplate ratings.
4) Series Capacitors
Series Capacitors cannot exceed 100% of emergency rating.
c. Generator Units
Generator units used for controlling remote voltages will be modified
to hold their base case terminal voltages.
d. Impact on Interconnected System
Single contingency outages will not cause overloads upon any
neighboring transmission system.
B. Transient Stability Studies
Transient stability studies are primarily performed on the 500k V and
345kV systems.
1. Fault Simulation
Three-phase-to-ground faults and single-line-to-ground faults, simulating
a stuck circuit breaker in one phase with back-up delayed clearing will be
simulated. Fault clearing times of four cycles after fault inception (5 cycles
for a 230kV fault) and a back-up clearing time of twelve cycles after fault
inception is utilized. System elements are switched out at the appropriate
clearing times, as applicable. Fault damping will be applied when applicable
at fault inception.
16
![Page 60: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/60.jpg)
2. Series Capacitor Switching
Series capacitors, at locations determined from short -circuit studies, will
be flashed at fault inception and will be reinserted depending on their
reinsertion types.
3. System Stability
The system will be considered stable if the following conditions are met:
a. All machines in the system remain synchronized as demonstrated by the
relative rotor angles.
b. Positive system damping exists as demonstrated by the damping of
relative rotor angles and the damping of voltage magnitude swings. For
N-l disturbances, voltages for the first swing after fault clearing should
not drop below 75% of pre-fault value with maximum time duration of 20
cycles for voltage dip exceeding 20%.
4. Re-closing
Automatic re-closing of circuit breakers controlling EHV facilities is not
utilized.
C. Short Circuit Studies
Fault current shall not exceed 100% of the applicable breaker fault current
interruption capability for three-phase or single-line-to-ground faults.
D. Reactive Power Margin Studies
For system normal conditions or single contingency conditions, post
transient voltage stability is required with a path or load area modeled at a
minimum of 105% of the path rating or maximum planned load limit for the area
under study, whichever is applicable. For multiple contingencies, post-transient
voltage stability is required with a path or load area modeled at a minimum of
102.5% of the path rating or maximum planned load limit for the area under
study, whichever is applicable.
17
![Page 61: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/61.jpg)
2009 SYSTEM RATING MAPS
PREPARED BY
TRANSMISSION OPERATIONS Aug 2009
![Page 62: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/62.jpg)
TABLE OF CONTENTS .
LEGEND ---------------------- 1
EHV------------------------- 2
METRO 230KV --------------------. 6
NORTHERN 230KV ------------------- 8
SOUTHERN 230KV ------------------- 10
METRO EAST --------------------- 12
METRO CENTRAL ------------------- 14
WESTERN ---------------------- 16
NORTHEAST - -- ------------------ 19
NORTHWEST --------------------- 21
SOUTHEAST --------------------- 23
SOUTHWEST --------------------- 24
![Page 63: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/63.jpg)
I
SYMBOL
### - ###
###
M
V
H
LEGEND
SYSTEM RATING MAPS
DESCRIPTION
-
CURRENT LIMIT IN AMPS LIMITING ELEMENT CONDUCTOR LIMIT IN AMPS
TRANSFORMER LIMITS ARE IN MVA
OVERHEAD TRANSMISSION LINE
UNDERGROUND CABLE
MOTOR OPERATED SWITCH
VACCUM SWITCH
HYDRAULIC SWITCH
BREAKER NUMBER
1
![Page 64: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/64.jpg)
CRYSTAL CYX
.--.-, NAVAJO NV I, EHV-1 ~
Capacitors 1137
f--------Capacitor at ww ! 2200
2 3696 2330
....L..._.L..*"L.. 500KV
#lAA ~ __ _, 840 MVA. 345KV
1800 + TO
3 1900
•
Capacitors 2330
8 9 500KV
ELDORADO EOX
(SCE)
500KV
1880 Capacitors -------I
1810 I----'l'---Capacitors-----...J
2480
ca~I~iYors MOENKOPI 2330 MK
2480
#3 r---3 336 MVA
230KV
FOUR CORNERS FC
FC-230 ~----'
SAN JUAN
PANDA PND- §
500 MVAuk 230KV 1750
Capacitors 2330 GILA RIVER -,----,-,
GLX
3000
r----------m~-_-r---_, -r -,-7~7_5r°c;.0;.;;KV.__7_r WESTWING WW
MEAD MEX
~ 2200 ~CAPS...J.....L...~ 3000
3000 r------PCB---~_;
3733
r :-t-------'j'--'T'--- 3000 -~:-:---::::L #lA 16 635 MVA
rr-r~ 230 kV -'--'---7''----'--;3f-L--;3>-'#lB 635 MVA 230kV
7 DEX 230kV
#4
#1 1500 MVA 230KV
1493 MVA 230KV m DEVERS t-'-~~5~MVA
8 2700-------------~r_~r-~~-r=~~~~~~~~~;=~~~~ 2786 2700 2700
2978
JOJOBA I > REDTi~WK JJX
4017 ~ 3000 2257
IMPERIAL VALLEY
IVX
i--220,~-=r -'-r-'-
Rev. 06130/09
#1 240 MVA 69KV
2200 Capacitors
2700
#4 240 MVA 69KV
PALO VERDE PLX
4017
HASSAYAMPA HAAX KYRENE
KYX
![Page 65: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/65.jpg)
CRYSTAL CYX
t ug ~2750
8 9 500KV
EL DORADO EOX
(SCE)
MEAD MEX a 2970 ---L...J.......
NAVAJO NV
SOOKV
2538
2362
EMERGENCY RATING (AMPS)
2362
MOENKOPI MK
2443
#1 395 MVA
230KV
#3 395 MVA 230KV
~-------- 3000 ----,
.-------- 3000 ---'P--;
2362
~~----------~--~------ 3000 ------;
#3A r-....;;:;:.:.;~ 717 MVA
230kV
#1AA 1225 MVA
34SKV
FC-230
500KV
EHV-1 EMERGENCY RATINGS
1800~ TO SAN JUAN
GILA RIVER .---.-, GLX
#1 1875 MVA 230KV
m DEVERS
7 DEX ---------------------1I~r_~~1F~~~~~~~~~~~-3645 8
IMPERIAL VALLEY
#1 240 MVA 69KV
T'f 2970
Rev. 06130/09
cr--297G---3: ::E--
#4 240 MVA 69KV
PALO VERDE PLX
HASSAYAMPA HAAX
TO PINAL WEST
KYRENE KYX
![Page 66: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/66.jpg)
CHOLLA r----------C> CH
1026 Capacitors - C15
2330 SUGARLOAF
22 SFL
TO CORONADO
#4 r---T'--"-----,---j 725 MVA
115KV
... #7
725 MVA 115KV
1143
1t 3 ~ TORTOLITA
TOX
I EHV-2 I
MOEN:OPI HII--r-018 FOURCORNERS ~~------"
FC
M 500KV I ' 1810 '----- Capacitors - C7'--~
2480
1---------1150-------,
#8 143 MVA
69KV
f-----;}-1150'------'
1086
#4 625 MVA
230KV
1086
PREACHER CANYON PR #6
h-3~100MVA ~ 69KV
1---''---3 ~ 50 f,lVA ~ 69KV
#14 625 MVA
230KV
#7 L--+-~~~700MVA
230KV 345KV
PINNACLE PEAK PP
EMISSION ABATEMENT~--...J
#1
-r---.--.--'T--.-345KV
TO 1800~ SAN
JUAN
#8 625 MVA
230KV
EMISSION ~--~ABATEMENT
#2 #2 780 L:;A
L FC-69
TO PILLAR
Rev. 0719109
II
![Page 67: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/67.jpg)
1539
#6 750 MVA
TO CORONADO
#4 r-----~~_.----~ 835MVA
115KV
#7 835 MVA 115KV
EHV-2 EMERGENCY RATINGS
EMERGENCY RATING (AMPS)
FOUR CORNERS r=:::..:..:---~ MOENKOPI H:II---r-01 FC
MK 500KV L L---------- 2«3 ----~
i 5 11------15201--------,
#8 160 MVA
69KV
11 1 ______ ~_15201-------...J
1310 PREACHER CANYON
PR h~.::t~100#~VA
f7"" 69KV
I--L-.::t f "'- 50 tiVA f7"" 69KV
#14· 625 MVA
230KV
#7 L----+-+--"!. 700 MVA
230KV 345KV
PINNACLE PEAK PP
EMISSION ABATEMENTr....,.;,-----
#1
-,----,-----.---..:M- 345KV
TO 1800~ SAN
JUAN
#8 625 MVA
230KV
EMISSION L-----~ABATEMENT
1009 T 50;VA #2
L FC-69
TO PILLAR
Rev. 07/9IG9
![Page 68: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/68.jpg)
'"
.,. 188 MVA
69KV
WADDELL WAX
GILA BEND GB
M9
#8 #12 100 MVA 100 MVA
69KV 69KV
188~VA -"""",-----.3 69KV ~
502 GB XFMRs
1099
.3 188 MVA
69KV
PANDA 3 PND
T 879
.i 1099 LIBERTY I LBX
"-==--1 .
1740
PALM VALLEY
PV
TO LIBERTY
Rev. 07/9/09
1740 -----.L.., 099----e!H
TO RUDD SOOKV
1850
.,2 188 MVA
69KV
AGUAFRIA AFX
#5 11l--T""--;J~'188 MVA
69KV
#8 '-----3~ 188 MVA
69KV
#16 188 MVA
69KV
#10 188 MVA
69KV
METRO 230KV I i 2200~ AFX
#4
PINNACLE PEAK (SRP) PXX
#3 188 MVA
69KV
PINNACLE PEAK PP
1-....----1818 "F'--- 720'---
REACH
1493 MVA 1818 #1. 188 MVA
69KV MR; H 3 :::;V: #7
700 MVA 345KV
#6 188 MVA
69KV SOOKV "--",- TO
180~ LIBERTY t TO
ALEXANDER AXR
1850 5
1105
2164
LONEPEAK ~8MVA LP 69KV
#7 188 MVA 69KV #1
188 MVA 69KV r'----,---- 1156 "F'----110S
#1 188 MVA
69KV '17 188 MVA
69KV
L. _ MEADOWBROOK
_ 900 _~ME 1156
t GLENDALE GL
912-- -1279"''''- - ,
""l='----21 001--3::
#10 188 MVA
69KV
1 #9
1 3 1287*
i
#6 187 MVA
69KV
187 MVA 69KV #10
167 MVA 69KV
#1. 188 MVA
69KV
COUNTRY CLUB 1----1 . CC
1150""" 1404-,
TO
., 188MVA"'::-H
69KV
BRANDON SRP
8 - - - 900- - --------1 LINCOLN STREET
LS
• DynamiC Rating
#1. 625 MVA 345KV
937
937
#6 167 MVA
69KV
937
TO 900""";'" KYRENE
OCOTILLO OC
•• No forced cooling on GT ..ce, Cooling both ends LS·CC . .. Forced cooling on GT ..ce, Cooling one end LS.c;C
![Page 69: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/69.jpg)
GILA BEND GB
#8 100 MVA
69KV
502
#3 188 MVA
69KV
#1 2 100 MVA
69KV
PANDA PND
#14 #11 188 MVA 188 MVA
69KV 69KV 2410~ AFX
WADDELL WAX
er 919
#4 1875 MVA
SOOKY
#12 188 MVA
69KV
1800--"-- TO ~LlBERTY
#4 TO 188 MVA ' ---l-~ #4
GILA RIVER 69KV I'" 188 MVA SOOKV ~_---'::r 69KV
1375
#1 188 MVA
69KV
METRO 230KV EMERGENCY RATINGS
PINNACLE PEAK (SRP) PXX
PINNACLE PEAK PP
DEER VALLEY ~'88~VA OV 69KV
7 2000 45 #10 720---
188 MVA 42 69KV REACH
2000
t TO
ALEXANDER AXR
#14 188 MVA
69KV
,-'----,- 1200
MR; H 3 ::::VA.
2000 5
LONEPEAK r.. MVA LP .9KV
#1 188 MVA
.9KV
8 #7 188 MVA 69KV
1322
#4 625 MVA 34SKV
1600~ TO PPWAPA
#7 700 MVA
345KV #.
188 MVA 69KV
TO PINNACLE PEAK
720~ (SRP) PXX
#14 625 MVA 345KV
~ ~
'233 LIBERTY LBX
1740 1367 ----e!H AGUAFRIA AFX
MEADOWBROOK
_1.75~- ME
#17 188 MVA
69KV
1034
~.c::...--I 4
PALM VALLEY
PV
1740
TO SRP· .... '--"'==WTX
Rev. 07/15109
r B TO RUOD SOOKV
2000
#5 1-.... .....::~ 1 88 MVA
69KV
'----'l~ 1 88~VA 69KV
#10 188 MVA
69KV
2164
1 #9
I 3 2000 , ..
187 MVA 69KV
205 MVA 69KV
COUNTRY CLUB 1--- 4 CC
#10 167 MVA
.9KV
1740 #1
188 MVA """,'---I--69KV
-.:: __ 2400'-- -:r
#10 , •• MVA' """,'---"
69KV
TO BRANDON
SRP
- - - 950- - ------j
LINCOLN STREET LS
#13 167MVA ... '-~
69KV
1034
#6 167 MVA
69KV
1034
TO 967~ KYRENE
OCOTILLO OC
![Page 70: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/70.jpg)
TO PEACOC K FORT ROCK
FT JUNIPER MTN
JM
NORTHERN 230KV NELSON SUB
300 ~ 300 300 40 --j SELIGM 1-__ 81+---RV CT~RV CT"----...L--RV CT-------'--XFMR AN COMPRESSOR 650 650 650 650 SCE
800 ROUND VALLEY RV
PRESCOTT PRX
#1. 188 MVA
69KV
r (.::D.:::O=.E)!,-__ 673 ___ _ L.--{
841 #6
188 MVA ~---l 69KV
,-----'----'-----. .-------1 7 770
673
#1 83MVA
#2 83MVA
GAVlLAN PEAK
GV #11
188 MVA, --E:--'---1 69KV
430
WILLOW LAKE WL
TO WAPA
PPK
1255f
WL B~ijOCOND~TO BAG DAD
WILLOW LAKE 115KV
VERDE VE
LEUPP h LW
#3 100MVA --E-~
69KV f----53.---~
M
705- M~M-705
#1 336 MVA
500KV
#11 100 MVA
69KV
800
8
#1. 100MVA
69KV
#3 f---:;~ 336 MVA
500KV
YAVAPAI YP
#4 167 MVA
69KV
COCONINO CQ
#7 203 MVA
345KV
#2 1--~100MVA
CHOLLA CH
69KV
Rev. 07/15/2009
![Page 71: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/71.jpg)
TO PEAC OC K
NELSON SUB
FORT ROCK FT
JUNIPER MTN JM
NORTHERN 230KV EMERGENCY RATINGS
1---1 8 1-+---3001300 ____ ...L __ 300 -----L--40 I SELIGMAN COMPRESSOR ----, SCE
800 ROUND VALLEY RV
PRESCOTT PRJ(
". 188 MVA 69KV
VERDE VE
LEUPP h LW
r(~D..:.O::!E).---__ 673----L---I .3
100 MVA "'--1-1 .9KV
1---530-----1
M
725- M..lM- 725
930 #6
188 MVA. -oE:-----69KV
,--___ L-_---l ____ , I r----- 7 890 .,.
100MVA .9KV
673
" 83MVA
.2 83MVA
GAVILAN PEAK
GV
'" 188 MVA -oE;-L-69KV
570~TO BAGDAD
WILLOW LAKE 115KV
WILLOW LAKE WL
TO WA P A
PP K
2 1381 t
., 395 MVA
soaKV 939
i--"~ 395~VA soaKv
L-.._-----,_ 8
YAVAPAI YP
.11 100 MVA
69KV
#4 167 MVA
.9KV
COCONINO CQ
'12 167 MVA
69KV
.7 243 MVA
34SKV
Rev.07{1612Q09
'2 i--+ 100 MVA .9KV
CHOLLA CH
., 50MVA
69KV
![Page 72: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/72.jpg)
SRP KYRENE
38
900
SRP KNOX ~~~~-----r----, 69KV
f--- 2986
KYRENE KYX
~ OCOTILLO
OC
LAKESHORE 11-------, LSX l
L-____ 900---'
MILLIGAN ~658~658 MGT r--~
TOLTEC TLT
_~-'4 __ __+M- TAT MOMOLI ~ TL
'2 100 MVA 69KV
L--_720 ____ --L-j
SAGUARO SG
900
DESERT BASIN DBN
- +----l I-_---+_ CASA GRANDE 3 CG
i 1099
.3 50 MVA
1 12KV
5
12KV
Rey. 07/16109
![Page 73: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/73.jpg)
KNOX SRP KNX
KNOX -E~-=~-----r~~-69KV SANTA ROSA
SR
SOUTHERN 230KV EMERGENCY RATINGS
1------- 2986 -----I TO
f----3Io .. WAPA TEST TRACK
SRP KYRENE
38
967
~ OCOTILLO
OC
f---- 2986
KYRENE KYX
LAKESHORE 1--___ ---. LSX l
720
69KV 37l--------:~----l 1----------------2000----,
SR EO-3
SR ~--- 900 ---- EO-3
f-- --'---- 2000 ------~ 69KV
VISTA VS
L----- 900--..J
MILLIGAN ~658~658 MGT r---~
TOLTEC TLT
900
DESERT BASIN DBN
__ ~_'_4 __ -jM_ TAT MOMOLI ! TL
#2 100 MVA
69KV T
_+----1 1--_-+_CASA GRANDE 3 CG
L---720----...L-{ 4 1-...L.--~:----i
SAGUARO SG
115KV
M
1 .3
50MVA 12KV
Rev. 07/17/09
![Page 74: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/74.jpg)
r-225 ------EJ-1 CHILDS V CZ
I N.O. ,---- - 1600
225
ROCK SPRINGS RS
TABLE MESA TM
1600
'" 188 MVA 230kV
I . WILD BURRO H WBR .,. 188 MVA
230kV 225
7
900
.,0 188 MVA
230kV
, ~ : ~CA~'" 7 2 ..
#6 187 MVA
230kV
90LA-0 HUMBUG , •• MVA HG 230kV
7 3 1600--~
I METRO EAST - 1 I
,----------- ------1600'---------------. PINNACLE PEAK
PP
DOVE VALLEY DVY
YORKSHIRE YK
DEER VALLEY DV
1000
UNION HILLS .-----=Ux,H,.:. --,
N.O. " 188 MVA
230kV
900 -""'- PARADISE """?,l"" JOMAX ---;JII""" Page ME·2 Y
LONEPEAK LP
f--'---- 900----l 7
1000~ BUFFALO ~1600 3 JX
, ... ~::ge ME·' I :
900
230kV
900-----, 1600 CAVE r01 CREEK
3 AQUEDUCT 1000~ 900~ AQ
LOOL~OUT 3 SUNNYSLOPE Page Me -1
MOON VALLEY ML
NORTH VALLEY NY
658 CA
STAGECOACH STG
I I I I I I I MONTE CRISTO
MCR
1LOMAVISTA Page Me-1
900- ' n
900 900 1000
1200 3 f---SUB DISC 7 f----'
1600
~+til-----900---~
\---- 900
1000 -",,-- SKUNK -----;7"""'" CREEK
ROSE GARDEN RSG
TURF TU
10001-----
1600~TO ~ESTWING CALDERWOOD
CLW
900
1600
~TOUT SIT
7
900 1
PYRAM lD
9 900~'
900
PINN PK EAST PPE
1f----9001---1
EAST END ......L. Page ME-2 ~900 ~',...L,~....I
1640
1000 f-------900----------l ~ PageW·2
900 3 A
f---900 7 THOMPSON PEAK ..... gOO PageME-2 ~ t DEADMAN
WASH OM
PIONEER PNR
BISCUIT FLATS BCT RAWHIDE~
Page ME-2 ~ 1600
Rev. 07128109
PINN PK Page ME-2
![Page 75: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/75.jpg)
PARADISE PD
BOULEVARD BV
#4 r-----------------~188MVA
230kV
#2 f-------C) .. 188 MVA 230kV
5 PP Page ME·2 1000
900~ PINNACLE PK
7 1000
DESERT RIDGE DG 90
DIXILETA Page ME·1
f----900 --- /f'----j
#3 188 MVA
230kV
LONE PEAK
UNION HILLS page ME·1
LP BUFFALO BF
AQUEDUCT page ME·1
EASTERN OFFICE
EO
~:6::----~ ~900
DESERT SPRINGS
PINN PK EAST
Page ME·1
-"0... TO REACH J 1600~ Page ME.2
JOMAX JX
I METRO EAST - 2 I
1600 f31 I DOVE VALLEY SHEA ~ DVY SHA
RAWHIDE RH
THOMPSON PK ALTADENA n TK AT 5
900~900 3 1600
__ .. __ 0 900
900
DOWNING 21-----' DD #6
f-----3~ 167 MVA --:.J...::- 230kV
#1. f-----3~167 MVA
230kV
P~fS~~1600 #14
f-----3~·188 MVA 230kV
Page ME-1
f-----l000-----, 1600
ROADRUNNER RR
DS ,-----900------1 1600
CENTURY CE
f-----900-----' L--------9005 ~ L---900-------------I.----900---'
f0--1000 7 POLK DOUBLETREE CHAPARRAL
CPL
SUNN~~LOPE TOTW vN
.o
. 5 900~PL5K DT OCOTILLO
OC 3 7 900----..,
40TH PLACE FP
HOHOKAM ~ __ --lEl4:f71---_---1.-rT'-----1600 HKM 7 ·----850-
~900 5 3 850 ----------.., -------:::c I L.:J BUTTE TEMPE BU
TP
CAMELBACK CB ." ·'lJ
MCCORMICK 658 MC
7 OR 1- ORANGEWOOD
658---J101,J MUMMY MTN. L:.J I
MM Rev. 07128109
![Page 76: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/76.jpg)
BELL lr,;,------1ooo------' BLL F
SKUNK CREEK SKC
GREENWAY GW
'----900---""1
r----1000------0tEJ----900
MONTE CRISTO 13 1200 MCR
15 MCRDISC~ 1530 DEER VALLEY 3
DV
HONEYWELL HW
900
.-----900'-------j
r-------900'-----~
r--,----900-----j 5
LOMA VISTA LV
#1
I METRO CENTRAL - 1 I
900------G"U AGUA FRIA ----...:...J] AF
ARROYO AY
SUNNYSLOPE SS
MOON VALLEY ML
188 MVA <IiE:----j 230kV
~900~~~K~~~
1000 ROADRUNNER RR
r-----1000-------~-j7 .----900-----'
#0 188 MVA
230kV 900 r----1600 ---,
1-_____ 900'-----rsllr;1r-----900'----~_"13 ~ SHAW CHERYL SH
CRL
900 I
#3 167 MVA
230kV
ORANGEWOOD OR
18rMVA~1Of------------1200--------------j 230kV
8 MUMMY MTN MM
MEADOM~BROOK ~ > ~AMELBAC:- ' 658-
page ME·2
900
GRISWOLD GRW
Re ... . 07129109
![Page 77: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/77.jpg)
I METRO CENTRAL - 2
ENCANTO EN
ORANGEWOOD ~-1200 PageMC1 ~
I .. 187 MVA
230kV
~-~-'900 f---'- - - - 900 - ------f
1600 J
N.O. MCDOWELL
MD
.----- 900 1 1 1 1
INDIANOLA IN
METRO MET
COUNTRY CLUB CC
900
MEADOWBROOK ME
f------'900-----l 1 1 1 1 1 1
1 1 1
f--- 900 ---1 #6
187 MVA 230kV
900--~
9
1- _ - - - - 900- ----I ..
167 MVA 230kV
L----- 900------~
900
~---1600~ L 825T 825
LIBERTY IRON LIT
1600-----,
900
,.---- 900 900----i --=-' 2 '3
FILLMORE FL
L--- 900--~
1 3 5
GARFIELD GF
EVANS CHURCHILL
EC
~--------1600 ---__.,
LINCOLN ST. LN
1600
18:~VA ELWOOD~ 230kV EW
WEST PHOENIX 5 4 1
WP DURANGO
900-----l
3
LINCOLN ST. WEST LL
1-----1600
f-~~18:~VA 230kV
1200 23rd Switch
1600 DU HARBOR
HR
YALE YL
900
23RD ST. TW
POLK PLK
fi 900 900 OCOTILLO OC
850 I
1
1
1
., 187 MVA
230kV
TEMPE TP
900 - --1
900
JACKSON ST. JS
Rev. 08111109
![Page 78: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/78.jpg)
HARQUAHALA HQ
TONOPAH
Tf; DESERT SKY TARTESSO #2
BUCKEYE BK
I !
#6 167 MVA
230KV
WESTERN - 1
I DSK TRT 'ggo~"A
f---.L--532 - M----'----- 532--M, M-'---'------r--~~-----l M 532
WATSON
~ .. ~ TUTHILL
SADDLE MTN. SW
M N.O.
L~ M
I M
BUNYAN BY .. J
2 CT 388
1-__ -1 PALOMA PLM
69KV
HORN HN
AZTEC AZ.
I HYDER HY
WINTERS BURG WG
I 532
1600
FIELD CENTER~
'--- 532 ----i .f N.O. I
69KV
6~ I
1----- 590---------"X N.O.
VAL~~CIA 9 100
BASELINE BZ PALM 1--" ROBBINS BUTTE
ROB
1--" RAINBOW VALLEY RB
LOWER RIVER LR
532 !.--__ -j JOJOBA ! JJ
ARLINGTON AL
PATTERSON PTS
658
L----- M~MI----- 532 ------~
6~
6~ 658
VALLEY WT-3
WT·' SARIVAL
BUTTER
J COTTON
BT CCR I f---,---6~---.L----~~---------6~---------~
N.O . .f t V
AIC #8
100 MVA\-4------1 230kV
N.O. GILLESPIE GP
#" 100 MVA
230kV
AJOIMPROVEMENTCO'
h 300------t&-300 f--.L-- CT 5 CT---'-----r-------.-----r--187'----'----.-----~ 326 326 I ~Y I
GILA BEND GB
THAYER THY CRATER AJO
CF AJ COFFEEPOT
CFP
Rev. 07/31/09
L1j PERRYVILLE
PY
![Page 79: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/79.jpg)
HEDGEPETH I WESTERN - 2 h CALDERWOOD
CLW HAT~~ELD H~~S ~·II::::::::::::::::::::::::~~ ~1600~900~ 900 __ ~:>~BISC~t+LATS
en z w Cl
~ ~ -900-
STARDUST SQ f '" 188 MVA
230kV
1600 ~ ·'9' ME· l
1000------01 PEAK
3 - 900-----cD1 PYR TO SKUNK CREEK
Page MC·1 1600 (!)Q.
en ~ 1 -I ~ I ~ I
N.C. V
".
ARROWHEAD WESTBROOK GREENBRIER AW WK GN
TO GREENWAY Page Me-1
PLEASANT PT
1000 PEORIA PA
Page MC-1 .........;:-
LOMA VISTA LV
I ----I 188 MVA 1000
DEL RIO DR
TO GREENWAY~900~3
9
900
ARROYO 1 AY SURPRISE SC
I I I
230kV WESTWING WW
f---900----1f----900--...J
MARINETIE MR
900
f---900--~
900
1 McMICKEN
MCM
FESTIVAL RANCH
FRT
900 JAVELINA 1600
9001------,
HEARN MOU DYSART 3 HE N1
AJ.,N VIEW
1600~ TO WESTWING
DY
900~ TO MORRISTOWN
ELSOL ES 1000 65, '600-Bj WAWo
ELL
- 658-----1 #4
900---------1 2!r~~--~ 188MVA
~ L. 230kV
900 7 3 '12
VARNEY 658 167MVA
M 9001---,r-!
o 7 N.O.
1200
VR Q-'O' 230kV
• LUKEFIELD
L--------900------'
LF
900
1600
cb COLTER -W CLT
1600
t TO
WHITE TANKS
Page W-3
Rev. 01131/09
900
![Page 80: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/80.jpg)
TUTHILL TTH
fl2J-'~'~'~' 900
BUCKEYE page MW-1
N.O.
#3 188 MVA
230kV PIMA PM
CREEK LITCHFIELD PCK LH
WESTERN - 3
WHITE TANKS WT
#5 t-"""?'~ 188 MVA
230kV ~ PEBBLE
f---- 9oo 900--0-f-0------900------E:J-t-0--1600
PALM VALLEY
PV
f---1600---,
COLTER CLT
#8 188 MVA ......:::-...,
230kV
AGUA FRIA ~1600 3 7 1600 TO ---0t&-PAGE W-2
WTX
At S -ffi1.0SRP
P R 3
S P
900
f------L-V-1 93~900 WILD FLOWER SARIVAL SAR WZ
1-----900------0fEJI----900'---~I----1600 ----' PERRYVILLE
PY
~343
7 XFMR 900
ESTRELLITA ET
COLDWATER CW
1------------1600--------------------~
Rev. 07131/09
![Page 81: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/81.jpg)
r---I GRAND CANYON GC TONALEA HAMBLIN GAP
f-T_Q----L ____ H_L...!----,_: S
NAVAJO COPPER
'5 I NORTHEAST-1
I
LECHE
'5 POWELL
PWX
, N.O. 532 - M---'-----121 TUBA CITY
TC APS : PAGE GLEN CANYON
f---I RED BUTTE RD
WILAHA WX
SAGE VALLEY
MILLER SGV
WASH MLW
VALLE VA
CATARACT CREEK
CK NADASY
ND
f---I RAM~ ASO
'----I HOWARD MESA r HM
'----I RED LAKE r RL
252 420 """'"-- CQ Line #1
---;;7"""" page NW-1
BEAR SPRINGS
BS
SHADOW SD
CAMERON CM
FOUR CORNERS NTUA
M
GCX
GRAY MOUNTAIN WAUNETA SPIDER WEB
~f ------f1l1-t1 __ G_~____'_ _____ wl_A...I...._ ___ ' l_B ..1.. M-.----I HANKS
~~ HK BLACK MESA
BM WUPATKI WU
OSBORNE TANK OT
SANDVIG SV
NAVAJO DEPOT~ NAD
FISH SAWMILL 300 FS
1-.l----CT----,-1 532
.-------.----532W · "I IW°w.:r' WILLIAMS PARKS
(EPNG) PK COCONINO CQ
~90:·0.+
900-----Br WIX
532-----1 #12
167 MVA~----1 230kV
'----i DAVENPORT r DA KACHINA 1-,-----532------1
KA
NEWMAN SEDSOENAl..rsL-400 - MT M-..l----l PARK PU WM lo..::..f NP pag'- Nw.,~490 7
#4
ELDEN ELN
532 ___ WINSLOW --::-- page NE-2
f----1200
532
:::.:.,;f-------r-- 532-'-----i GA GARLAND PRARIE M~ '~~.re~A~--i SWITZER CANYON
SZ
WILLIAMS WM
MUNDS PARK MP
Rev. 0814/09
![Page 82: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/82.jpg)
N o
I NORTHEAST- 2 I
JEDITTO WHITE INDIAN NTUA TESIHAN CONE WELLS JDX TX WCX IWX
1-1 -h~326-.l...---~-~----~ KEAMS CANYON 532--M LEROUX
KC LX
~_~ LEUPP JCT. LJ
HASHKNIFE HKF DRYLAKE
OK
PINK CLIFFS L-__ -I ___ ~ PCF I
CHOLLA CH
300 BCT----532
f----.- 50 ~VA 230kV
N.O. M WOODRUFF
WR
WINSLOW WS
#2 100 MVA""""';------1
230kV 1-__ 532 ____ ___ -L-____ L~...j BACON
BC '--___ 300 .- CT· --------I
532-
78 XFMR
532
-.-L BLUE RIDGE
BR
1--__ DIABLO DB
I--_~ SUNSHINE SK
1---_ PADRE PE
I--__ ~ WINONA WN
400 CTr-------L----~-------532
ZENIFF 2 ZF
#1
#8 ! t-------3~143 MVA
345kV
270 MVA,ooOOI!'-----500kV
ABITIBI ACX
1-----16001-----.:::r
L---------16001--------532
1-1 HEBER
532 LINDEN I LNX L. ___ :T---1 ______ 532'-~
PIGLET PX
ST. JOHNS NEC
WAGON .----.--1 WHEEL SHUMWAY
WGX SHM
CORONADO CNX
SAFFEL CANYON
NEC STEVEN s, L---_--1
NEC r
PINETOP LAKES
PTX
;f-----I DRUM BEAT NEC
" '5 1~--~~ ALCHESAY I '" 15 NEe.
'---- 532---r,oU COCONINO L.:::ll CQ
SPRINGERVILLE NEC
Re~ . 0814109
![Page 83: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/83.jpg)
I I
NORTHWEST - 1 WHITE HORSE LE BARRON
WH LB WILLIAMS WM
r------- .M----~ I f-----r-~~:____I": MI ___________ T...J.... ____________ T...J.... ______ ,-- 490 ---------Gl-l COCONINO
532 I N.O. I L.:...J I CQ x N.O. 490 ROGERS LAKE
TOCK~252
PINE OLD HOME RG CEMENT
CMX SPRINGS
PS MANOR YAVAPAI
OHM YP
M
' _______ 4_9_0=-3· 9 1---D-E-W-EY----·6001-----ri
1_ ~ pa9t W-2
#11 h---"'~ 100 MVA
230kV ~ I-_ WELCH
WC
M CHINO WELLS
PF X N.O. i
ASHFORK AS
GREY f0--- .66 BEARS 7 XFMR:-+--
GBS 900
M
M...L++-CROOKTON JCT.
CJT CHINO ~~~ VALLEY 532
CV • 500
MI-------.r-- .• M CT L--j 532
EIGHT POLLOCK --'-_ L-...L--'--- PAULDEN MILE PQ PU
STURM RUGER
SRG ANTELOPE
AN
#6 188 MVA
230kV
WILLOW LAKE WL
532
LONESOME --,--L...., VALLEY
LY
CHILDS pa9tw .2
900 I- N.O.
X N.O.
532
TAPCO TA I MINGUS 1
L-___ 900----.l M i 278 532 ...L----l-
532'--L....i GLASSFORD HILL GHT
N.O.
L---------------900'------j
CREEK EMC OBERLIN PATTON WICKENBURG POPLAR WASH
~T PTN WB STANTON YARNELL POP 326 r- 900----l 240 ----Bi SN YA KIRKLAND JCT. L---0i
VERDE VE
~900--Vi 900--V I ~i:t~~jy C M ___ L---___ -'---'-____ K_J~---M_-.87________0i 1 9?0 I l 326 AGUILA BUCKEYE WILHOIT WHITESPAR
MCMICKEN 900 .m...m.. 90~0 7 FLYING E c AG EAGLE EYE ~ WQ WSP MC~ NO L FE 400 400 EE M N.O. LIBERTY
MORRISTOWN . . , CT CT l+-~~'---,---L-------l 4 5 MQ 532 532 LBX (DOE)
SALOME2 N.O.,.. N.O. 7 230kV SURPRISE N.O. SA PARKER
SC 'M---V '84 f+-~=------'------------< 9 I- N.O. VICKSBURG PAX (DOE)
1----'--240~ HAVASU VB 69kV HU Rev. 815109
![Page 84: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/84.jpg)
.3 100 MVA
230kV
.,. 100 MVA
230kV
CEMENT CMX
VERDE VE
k:D-T--532
900 l ~ 900,----:;~7--,p;T------" COTTONWOOD N.O. X X N.O. MH CT
OAK 8:~EEK 532 532'--,-+----' M
I
N.O. X 900
H:D---J YAVAPAI
CAPITAL 3 BUTTE
CP 532
HAYFIELD J YP
QUAIL SPRINGS
QS
I NORTHWEST - 2 I
CORNVILLE CN
900--1.1....------j1 MCGUIREVILLE
MG
~ WILLOW MINGUS
MS HD I I
'" '"
LAKE WL
cp 532
LONESOME VALLEY
LY
~Mo--. -~ 532
900
532
400 I-M-CT:-~
532 MUNDS PARK SEDONA
MP SE
BALD MOUNTAIN BMT ~ I r:I SDG
r---532~532~age NW-1
GLASSFORD HILL GHT
- -'-:::r::-'- DEWEY DW
M
COPPER t STRAWBERRY CANYON STR
CU CHILDS IRy~NG T ro~~326----'r-__ -'-_-MI M- 326
r---G1 '-' ,---326
400 ----L-CT GODDARD MAZATZAL 532 GD MZT
PREACHER CANYON
PR
TONTO TT
CORDES SYCAMORE SY
~800
1 BCT--~ 900
900 CDS
~---1I--------,-C---532---.-f31..- 532--+---~ --.l.'::::-' Y I ROCK SPRINGS POLAND ORMES -. RS
JUNCTION OM PJ
Rev. 08110/09
![Page 85: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/85.jpg)
WINGFIELD FARRELL WF CA~gOD FR HIDDEN VALLEY
''",0' f--- f:J e-, "'
SOUTHEAST-1
326-----1 PAPAGO PG
SX 278 ~:: ___ ---':'~--.l_-.lIN_~N~XD~:=~=====~6:60:~=-~f-J~~==-M'WG~I L .. •• MGO ,~ ", I ", .., ~__________ 900
TOLTEC 658 ---0i M TL T ----J:D-tB- ARICOPA (DOE)
900
SADDLE BROOKE RANCH
~900 EA~TG~ TE 900 MAX
CASA GRANDE #2 EG VISTA CG M 100 MVA VS ---'1'J3I--- 900
SAGUARO ~ ASARCO PIT
1600~TTX
1600~ FR
1600~ TALX
1600~ SDNX
1600~ PNX
SBK
730
SAN MANUEL SM
MINE
800 BCT-----.J 1010
#4 725 MVA __ - --'
SOOkV
SG 1092 I AX ~TO DESERT BASIN
#7 167 MVA
---ff'-- CASA GRANDE (DOE)CGX
300- MT M-----@j ---L-ED-4
TUCSON (~~~) ~600-- c=
o 600
JU~~~lcfN VA~~ FARMS ~~l #7 725 MVA
500kV 2
PINAL APS PZ
#1 75MVA
115KV
5
PINAL SRP PZX
M~~L DON LUIS SAN
~ DL PEDRO 200
x}il 5 T ~ , SPD M_~~J---E:H MCNEAL 53l 400 184----'--i2..H PALOMINAS N.D. MN
#3 4 3 B5CT ______ ....:...P~A.:L _____ L ___.JFAIRVIEW
50 MVA 69kV 32 FA
OJX 445~445~"5kV9 5
2 TUCSON 723:-----1
(~~~) 8 502 COOLIDGE __ ___.J
TO ADAMS CLX ED ~~ A ~ SNAKE J:M 39 rj BO~WILL
14>-J-. M~O M 1 ~~l 69kV DEL BAC DBX 12 11 115kV M @H
NOGALES APACHE NOX APX
12.47kV
Re .... 08110/09
![Page 86: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/86.jpg)
HAVASU CAP
BUCKSKIN BN
PLANET PN
BILL WILLIAMS WELLFIELD
BWX WFX
I SOUTHWEST - 1 I
WILLOW LAKE PARKER WL
~~ 1-_--.--'-_240----'--A-PS------'--A-PS---'-----''------'----1N
.Cf-. T""T ___ ---1,8B f-B~A'-~_lAX_lD~BDI__----cc__----.-_430-i,
PARKER PKR 161kV
COLORADO CR
HEADGATE ROCK HGX
532
I N.C. -/-
(ODE) I MEeD l APS
BAGDAD TOWNSITE ,
12kV 115kV
161kV
001 APS - -#3 BLACK PEAK
35 MVA BP 161kV
BAGDAD TOWN BGD
- X--.... -----'.-240-,-----240---._l N.C. ~ 184~V :TV---'--'84s.oJ N.C.
HAVASU HU
QUARTZSITE QZ COPPERSTONE
WELLS CSW
COPPERSTONE MINE CSM
UTTING UT VICKSBURG
VB SALOME
SA
Rev. 6,110109
EAGLE EYE EE
![Page 87: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/87.jpg)
RIVERSIDE RVS
YUCCA YU
1200 7 SUB EQUIP
1600
1200 CT
1600
YCAX
,t 900
900
1600
1600
KINDER MORGAN
KM
SOUTHWEST - 2
MITTRY MT
1---- 900-------0f0---900 9001--1.1---1000
NORTH GILA NG
#4 f--~ 240MVA
500kV
900
10TH ST. TE
900--+-...,
QUECHAN QU YUMA PALMS
REDONDO RE
YMT
#1 1---,.. 240 MVA 500kV
67 MVA 67 MVA 161kV ~ 161kV
IVALON IV
900-+-+-1 . _----'~-800 ,- CT 1600
FOOTHILLS FH
SENATOR WASH SWX
1200
'" UI
8~ N.O. + PILOT KNOB
PKX
N.O.+
LI ------658-----,-900 M--900-----1
32ND ST. 1600 TH
~ BAJA
LAGUNA BJ LG rfi I MARINE AIR BASE ARABY
~ ~ MA AA CT CT 900--01-EJ--900---Bt0--900
ISA~NLLUIS ~ 20 MVA¢ SONORA ~_ SU
CFE f-t- 900 400-----MtIM-----EJ-1H-&---348 WAPA _ 25MVA
900---l APS 34.5kV
YCWU MEXICO LOAD l4.5kV
Rev. 8110/09
GILA GIX
![Page 88: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/88.jpg)
ARIZONA PUBLIC SERVICE COMPANY
TEN-YEAR PLAN
2010 -2019
TECHNICAL STUDY REPORT
FOR
THE ARIZONA CORPORATION COMMISSION
JANUARY 2010
![Page 89: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/89.jpg)
Executive Summary
Pursuant to NERC Standard TPL-OOI "System Performance Under Normal (No Contingency) Conditions (Category A)", Arizona Public Service (APS) performs annually a Category A analysis. The Category A analysis is performed for system conditions listed in Table I of the NERCIWECC Planning standards.
Results of the study indicate that, with the projects identified in APS's Ten-Year Transmission Plan, APS is fully compliant with NERC Standard TPL-OO I.
Pursuant to NERC Standard TPL-002 "System Performance Following Loss of a Single Bulk Electric System Element (Category B)", APS performs annually a Category B contingency analysis. In Table I of the NERCIWECC planning standards, there are a total of four different Category B events that are to be studied each year to meet NERC Standard TPL-002.
A comprehensive list of contingencies was developed for the Category B contingency analysis and performed for the system conditions listed in Table I of the NERCIWECC Planning standards based on engineering judgment. APS believes that the selection of contingencies for inclusion in these studies, which is based on Category B of Table 1 of the NERCIWECC Planning standards, is acceptable to WECC. If requested by WECC, APS will implement measures to correct any deficiencies that have been identified by WECC.
Results of the study indicate that, with the projects identified in APS's Ten-Year Transmission Plan, APS is fully compliant with NERC Standard TPL-002.
![Page 90: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/90.jpg)
Table of Contents Page
I. Introduction ............................................................................................... 1
II. Base Case Development ............................................................................ l
III. Power Flow Analyses ................................................................................ 3
IV. Stability Analysis ....................................................................................... 6
V. Category A & B Contingency Study Results .......................................... 6
Appendices
A. Representative Contingency List ................................................. AI-AI2
B. Power Flow Maps .......................................................................... BI-B8
C. 2013 Stability Plots ........................................................................ 1-426
D. 2019 Stability Plots ........................................................................ 1-451
![Page 91: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/91.jpg)
ARIZONA PUBLIC SERVICE COMPANY 2009-2018
I. Introduction
TEN-YEAR PLAN TECHNICAL STUDY REPORT
This technical study report is perfonned and filed annually with the Arizona Corporation Commission ("Commission") pursuant to ARS §40-360.02 and Commission Decision No. 63876 (July 25,2001). This report summarizes the results of power flow analyses and stability analyses for the APS system.
Power flow analyses were conducted for every year within the ten year planning window (2010-2019) and performed for two scenarios: (i) assumption that all transmission system elements are in service and within continuous ratings (Category A); and (ii) assumption of an outage on a single element, with all remaining system elements remaining within emergency ratings (Category B). Voltage deviations for these scenarios must also be within established guidelines. These voltage deviation guidelines closely approximate post-transient VAR margin requirements of the Western Electricity Coordinating Council (WECC). More detail is provided in APS's Transmission Planning Process and Guidelines, which is also included in the annual APS Ten-Year Plan filing.
The stability analyses were performed to simulate electrical disturbances on the transmission system and evaluate the system response. The desired result is that all generators will remain on line, no additional lines will open, and the system oscillations will damp out.
Results of the power flow and stability analyses aid in determining when and where new electrical facilities are needed because of reliability or security reasons. Additionally, some facilities are planned to address adequacy concerns. These include the interconnection of generation to the transmission system or efforts to increase import capability and/or export/scheduling capability to load-constrained or other areas.
II. Base Case Development Power flow cases were created for each year of the 2010-2019 study time frame.
These cases were developed from the latest available WECC heavy summer power flow cases.
The 2009 Valley Operating case was chosen as the first seed case. This case was developed from a 2008 WECC Heavy Summer base case. The WECC case was then updated in a coordinated effort between APS and SRP to include the sub-transmission and distribution models and was the basis for the valley operating studies perfonned by APS and SRP for the 2009 summer operating season. This case was used as the seed case in the creation of the 2010, 2011, and 2012 power flow cases used for the power flow analyses performed for the 2010-2019 Ten-Year plan. Each intennediate case developed was updated with the forecasted loads and any system additions/upgrades that are planned in the respective year.
![Page 92: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/92.jpg)
The second seed case chosen was the 2013 Heavy Summer power flow case that was developed through the CATS-EHV sub-committee of SWAT. A recent WECC 2012 heavy summer power flow case was used as the initial case to develop the WestConnect 2013 heavy summer power flow case. In a collaborative effort, the Arizona utilities used the jointly developed 2013 WestConnect case to develop a 2013 summer case that included the sub-transmission and distribution systems of the Arizona utilities. This seed case was used to develop the 2014, 2015, and 2016 power flow cases. Each intermediate case developed was updated with the forecasted loads and any system additions/upgrades that are planned in the respective year.
The final seed case chosen was the CATS 2019 heavy summer power flow case. The latest WECC 2018 heavy summer power flow case was used as the initial case to develop the CATS 2018 heavy summer power flow case. In a collaborative effort, the Arizona utilities used the jointly developed 2019 CATS case to develop a 2019 summer case that included the sub-transmission and distribution systems of the Arizona utilities. This seed case was used to develop the 2017 and 2018 power flow cases. The 2017 case was updated with the forecasted load for 2017 and removed any system additions/upgrades that were planned for 2018 and 2019. The 2018 case was updated with the forecasted load for 2018 and removed any system additions/upgrades that were planned for 2019.
These cases represent the latest transmission and sub-transmission plans, load projections, and resource plans of utilities and independent power producers. By utilizing WECC base cases, all loads, resources, firm power transfers, and planned projects within the WECC system are represented. By using jointly developed seed cases the most accurate Arizona system is represented.
2
![Page 93: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/93.jpg)
III. Power Flow Analyses Base case and single contingency conditions are evaluated to determine system
needs and timing. Various iterations of possible solutions lead to the final plans for transmission additions. The contingency analysis involves simulations for every nonradial 115kV or above line that APS owns, partially owns, or operates. Transformer outages are also evaluated.
The APS system includes several reactive power resources that are used to maintain bus voltages within the limited defined by The Transmission Planning Process & Guidelines. These reactive power resources include shunt devices, series compensation, and tap changing transformers. The reactive power resources are adequate and meet the system performance.
APS does not have any existing or planned control devices. These devices exist outside the APS control area; however, they are not utilized or their operation is not necessary as a result of the contingencies in this study.
No planned outage of bulk electric equipment at APS occurs during the heavy summer peak time. Therefore it is not necessary to study planned outages since this TenYear Plan study focuses on the heavy summer peak time.
Results of the power flow studies are tabulated in a Security Needs Table and an Adequacy Needs Table, below. These tables identify eleven transmission projects that are included in this Ten-Year Plan filing. Some of the projects were classified as Adequacy Needs because of the uncertainty of generation location, project size, and transmission availability in the later years. As projects near the five-year planning time frame, they may be redefined as Security Needs projects. For the projects included in the Security Needs Table, selected maps of the power flow simulations are contained in Appendix B showing the pre-project scenario (outage and resulting violation) and the post-project scenario (outage and no criteria violations).
3
![Page 94: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/94.jpg)
a e , ecunty ee s a e , T bl 1 S 't N d T bl Transmission In
Project Service Critical Outage Limiting Element Map
Year Youngs Canyon 2012 230/69kV Voltage deviations on the sub- Bl-(Flagstaff) transformers at transmission system in the area B2 345/69kV Coconino resulting in load shedding interconnection TS6230kV 2012 Adobe-Deer Valley Overloads Deer Valley-Rose Garden B3-substation 69kV line 69kV line B4
Adobe-Stout 69kV Overloads Deer Valley-Rose Garden B5-line 69kV line B6
Mazatzal 345kV 2013 Owens-Preacher Voltage deviations on the sub- B7-substation Canyon 69kV line transmission system in the area B8
resulting in load shedding
4
![Page 95: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/95.jpg)
a e . equacy ee s a e • T hi 2 Ad N d T hi Transmission In
Project Service System Benefits Year
Loop-in of Navajo- 2010 Increases import capability for the Phoenix Metropolitan area and Westwing SOOkV into export/scheduling capability from the PV area to provide access Morgan SOOkV to both solar and gas resources. Increases transmission system substation (2010) and reliability and ability to deliver power from these resources. Morgan-Pinnacle Peak Provides additional voltage support to the Phoenix Metropolitan SOOkV line (2010)
230kV and sub-transmission system. Loop-in of Saguaro- 2012 Provides a transmission source to serve the new load developing Casa Grande 230kV in the local area that does not have any electrical facilities existing line into TS 12 230k V in the area. substation Desert Basin-Pinal 2014 Increases the reliability of the Sundance generating facility and South 230kV line provides an APS transmission path for delivery of the full output and Pinal South- of the Sundance generating facility. Provides another Sundance 230kV line transmission path in the regional system, thereby increasing the
system reliability and capacity in order to continue to serve the growing electrical demand in an economical and reliable manner.
Palo Verde vicinity 2014 Increases import capability for the Yuma area and to North Gila 500kV. export/scheduling capability from the PV area to provide access
to both solar and gas resources. Increases transmission system reliability and ability to deliver power from these resources. Increases transmission system reliability.
North Gila-TS8 2014 Increase transmission system reliability and ability to distribute 230kV line. and deliver power within the Yuma area. Delany-Sun Valley 2014 Increases the import capability for the Phoenix Metropolitan area 500kV line & Sun and export/scheduling capability from the PV area to provide V alley-Trilby Wash access to both solar and gas resources. Increases the system 230kV line reliability by providing a new transmission source to help serve
the growing areas in the western portions of the Phoenix Metropolitan area.
Palm Valley-TS2- 2015 Provides a second 230kV source for Trilby Wash so that it is not Trilby Wash 230kV served as a radial substation, thereby increasing the local system line reliability. Also, connecting the Sun Valley-Trilby Wash 230kV
line to Palm Valley also increases the reliability of the high voltage transmission system on the western side of the Phoenix Metropolitan area.
Sun Valley-Morgan 2016 Increases import capability for the Phoenix Metropolitan area and 500kV line. export/scheduling capability from the PV area which includes
both solar and gas resources. Increases transmission system reliability and ability to deliver power from these resources. Provides a second 500k V source for the Sun Valley substation. Provides support for multiple Category C and D transmission contingencies.
5
![Page 96: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/96.jpg)
I
I
2
3 4
IV. Stability Analyses A stability simulation for simulated three-phase faults was performed for 2013
and 2019 for every non-radialllSkV, 230kY, 34SkY or SOOkY line that APS owns (totally or partially) or operates. It has been APS's experience that stability concerns do not manifest on the sub-transmission system, which is primarily designed to deliver power to load. Therefore, no simulations were performed at voltage levels less than llSkY, except at generator substation. Additionally, every new proposed generation plant will be required to perform stability evaluations prior to receiving permission to interconnect to the transmission system.
Existing and planned protection systems are utilized in the study, including any backup or redundant system, and represent fault clearing times, the operation of the protection system, and the resulting removal of the faci lity that would occur as a result of the simulated even. Each simulation modeled a 3-phase bus fault, appropriate series capacitor flashing and reinsertion, fault removal, and transmission line removal. System performance was evaluated by monitoring representative generator rotor angles, bus voltages and system frequency. Plots of these system parameters are included in Appendices C and D. The stability simulations performed to date indicate that no stability problems limit the transmission system.
V. Category A & B Contingency Study Results
A high level overview of the results for the Category A and Category B contingences is shown in Table 3. From this table, it is shown that each of the Category A and Category B contingencies meets the NERCIWECC Planning Standards.
a e : T bl 3 0 vervlew 0 fC ategory A&BS d dR tan ar esu ts 1-5 year Time Frame 6-10 year Time Frame
Standards Case Years Standards NERC Planning Standards Category A Case Years Studied Met? Studied Met?
All Facilities in Service 20 to through 2014 Yes 20 15 through 20 19 Yes 1-5 year Time Frame 6- 10 year Time Frame
Standards Case Years Standards NERC Planning Standards Category B Case Years Studied Met? Studied Met? 3-Phase Fault with Normal Clearing -Generator 20 I 0 through 2014 Yes 2015 through 2019 Yes 3-Phase Fault with Normal Clearing -Transmission Circuit 20 I 0 through 20 14 Yes 2015 through 2019 Yes 3-Phase Pault with Normal Clearing -Transformer 20 to through 20 14 Yes 20 15 through 2019 Yes Loss of an Element without a Fault 20 I 0 through 2014 Yes 2015 through 2019 Yes
Table 3 is a high level summary that shows, with the projects listed in Tables 1 & 2, the APS system meets the criteria listed in NERC Standards TPL-OO land TPL-002. The transient stability plots are detailed in Appendices C & D. Due to the size of the power flow thermal and voltage steady state analysis the detailed results are not included. However, they are avai lable upon request by WECC or any other authorized stakeholder.
6
![Page 97: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/97.jpg)
APPENDIX A
Representative Contingency List (2016 used as an example year)
![Page 98: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/98.jpg)
2016 Single Contingenc~ List (Categoa Bl Outage Number Type Contingency Circuit # line_I Line CHOLLA 500.0 to SAGUARO 500.0 Circuit I line_2 Line FOURCORN 500.0 to MOENKOPI 500.0 Circuit 1 line_3 Line NAVAJO 500.0 to MOENKOPI 500.0 Circuit I line_4 Line CHOLLA 345.0 to PNPKAPS 345.0 Circuit I line_5 Line CHOLLA 345.0 to PRECHCYN 345.0 Circuit 1 line_6 Line FOURCORN 345.0 to CHOLLA 345.0 Circuit I line_7 Line FOURCORN 345.0 to CHOLLA 345.0 Circuit 2 line_8 Line BUCKEYE 230.0 to LIBERTY 230.0 Circuit 1 line_9 Line CACTUS 230.0 to OCOTILLO 230.0 Circuit I line_IO Line CACTUS 230.0 to PPAPS N 230.0 Circuit I line_II Line CTRYCLUB 230.0 to LINCSTRT 230.0 Circuit I line_12 Line CTRYCLUB 230.0 to GRNDTRML 230.0 Circuit I line_13 Line DEERV AL Y 230.0 to ALEXANDR 230.0 Circuit I line_14 Line DEERV AL Y 230.0 to PINPKSRP 230.0 Circuit I line_15 Line ELSOL 230.0 to AGUAFRIA 230.0 Circuit I line_16 Line GLENDALE 230.0 to GRNDTRML 230.0 Circuit I line_17 Line GLENDALE 230.0 to AGUAFRIA 230.0 Circuit I line_I 8 Line LEUPP 230.0 to COCONINO 230.0 Circuit I line_19 Line LINCSTRT 230.0 to OCOTILLO 230.0 Circuit I line_20 Line LINCSTRT 230.0 to WPHXAPSN 230.0 Circuit I line_21 Line LONEPEAK 230.0 to PPAPS E 230.0 Circuit I line_22 Line LONEPEAK 230.0 to SUNYSLOP 230.0 Circuit I line_23 Line MEADOWBK 230.0 to CTRYCLUB 230.0 Circuit I line_24 Line MEADOWBK 230.0 to SUNYSLOP 230.0 Circuit I line_25 Line REACH 230.0 to LONEPEAK 230.0 Circuit I line_26 Line REACH 230.0 to PPAPS C 230.0 Circuit I line_27 Line PPAPS N 230.0 to OCOTILLO 230.0 Circuit I line_28 Line PPAPS N 230.0 to PINPKSRP 230.0 Circuit I line_29 Line PPAPS N 230.0 to PINPKSRP 230.0 Circuit 2 line_30 Line PPAPS W 230.0 to PINPK 230.0 Circuit I line_31 Line SAGUARO 230.0 to TATMOMLI 230.0 Circuit I line_32 Line SNTAROSA 230.0 to TATMOMLI 230.0 Circuit I line_33 Line SNTAROSA 230.0 to TESTTRAK 230.0 Circuit I line_34 Line SURPRISE 230.0 to EL SOL 230.0 Circuit I line_35 Line SURPRISE 230.0 to WESTWNGW 230.0 Circuit I line_36 Line WESTWNGW 230.0 to PINPK 230.0 Circuit I line_37 Line WHTNKAPS 230.0 to EL SOL 230.0 Circuit I line_38 Line WHTNKAPS 230.0 to RUDD 230.0 Circuit I line_39 Line WPHXAPSS 230.0 to WPHXAPSN 230.0 Circuit I line_ 40 Line PPAPS W 230.0 to PPAPS C 230.0 Circuit I line_41 Line PP APS C 230.0 to PP APS E 230.0 Circuit I line_42 Line PP APS N 230.0 to PP APS E 230.0 Circuit 1 line_ 43 Line WPHXAPSS 230.0 to RUDD 230.0 Circuit I line_44 Line YAVAPAI 230.0 to VERDEN 230.0 Circuit 1 line_45 Line Y A V AP AI 230.0 to WILOWLKE 230.0 Circuit I line_46 Line KYR·NEW 230.0 to OCOTILLO 230.0 Circuit I line_ 47 Line KYR·NEW 230.0 to KNOX 230.0 Circuit I line_48 Line GILARIVR 230.0 to GILABEND 230.0 Circuit I
AI
![Page 99: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/99.jpg)
line_49 Line WPHXAPSN 230.0 to WlITNKAPS 230.0 Circuit 1 line_50 Line FORTROCK 230.0 to ROUNDVLY 230.0 Circuit 1 line_51 Line FORTROCK 230.0 to JUNIPRMT 230.0 Circuit I line_52 Line WILOWLKW 230.0 to PRESCOTT 230.0 Circuit I line_53 Line WILOWLKW 230.0 to WILOWLKE 230.0 Circuit I line_54 Line JUNIPRMT 230.0 to SELIGMAN 230.0 Circuit I
line_55 Line CORONADO 500.0 to SIL VERKG 500.0 Circuit 1 line_56 Line PALOVRDE 500.0 to WESTWING 500.0 Circuit 1 line_57 Line PALOVRDE 500.0 to WESTWING 500.0 Circuit 2 line_58 Line PALOVRDE 500.0 to RUDD 500.0 Circuit I line_59 Line PERK PS2 500.0 to PERKINPS 500.0 Circuit 1 line_60 Line HASSY AMP 500.0 to REDHA WK 500.0 Circuit I line_61 Line HASSY AMP 500.0 to REDHA WK 500.0 Circuit 2 line_62 Line HASSYAMP 500.0 to PALOVRDE 500.0 Circuit 1 line_63 Line HASSY AMP 500.0 to PALOVRDE 500.0 Circuit 2 line_64 Line HASSY AMP 500.0 to PALOVRDE 500.0 Circuit 3 line_65 Line HASSY AMP 500.0 to PINAL_ W 500.0 Circuit I
line_66 Line HASSY AMP 500.0 to ARLINTON 500.0 Circuit I line_67 Line HASSY AMP 500.0 to MESQUITE 500.0 Circuit 1 line_68 Line AGUAFRIA 230.0 to WESTWNGW 230.0 Circuit 1 line_69 Line AGUAFRIA 230.0 to ALEXANDR 230.0 Circuit 1 line_70 Line AGUAFRIA 230.0 to WHITETNK 230.0 Circuit I line_71 Line BRANDOW 230.0 to KYRENE 230.0 Circuit 1 line_72 Line BRANDOW 230.0 to PAPAGOBT 230.0 Circuit I line_73 Line BRANDOW 230.0 to WARD 230.0 Circuit 1 line_74 Line BRANDOW 230.0 to WARD 230.0 Circuit 2 line_75 Line CORBELL 230.0 to KYRENE 230.0 Circuit 1 line_76 Line KYRENE 230.0 to KYR-NEW 230.0 Circuit 1 line_77 Line KYRENE 230.0 to SCHRADER 230.0 Circuit I line_78 Line ORME 230.0 to RUDD 230.0 Circuit I line_79 Line PAPAGOBT 230.0 to PINPKSRP 230.0 Circuit 1 line_80 Line ROGERS 230.0 to THUNDRST 230.0 Circuit I line_81 Line ROGERS 230.0 to ROGSW AP A 230.0 Circuit 1 line_82 Line ROGERS 230.0 to ROGSWAPA 230.0 Circuit 2 line_83 Line SANTAN 230.0 to CORBELL 230.0 Circuit 1 line_84 Line SANTAN 230.0 to THUNDRST 230.0 Circuit I line_85 Line SCHRADER 230.0 to SANTAN 230.0 Circuit I line_86 Line THUNDRST 230.0 to GOLDFELD 230.0 Circuit I line_87 Line THUNDRST 230.0 to GOLDFELD 230.0 Circuit 2 line_88 Line KNOX 230.0 to SNT AROSA 230.0 Circuit I line_89 Line BROWNING 230.0 to SANTAN 230.0 Circuit 1 line_90 Line RUDD 230.0 to WHITETNK 230.0 Circuit 1 line_91 Line RUDD 230.0 to LIBERTY 230.0 Circuit I line_92 Line COPPERVR 230.0 to FRISCO 230.0 Circuit 1 line_93 Line APACHE 230.0 to BUTERFLD 230.0 Circuit I line_94 Line APACHE 230.0 to RED TAIL 230.0 Circuit I line_95 Line APACHE 230.0 to WINCHSTR 230.0 Circuit I line_96 Line BUTERFLD 230.0 to SAN RAP 230.0 Circuit 1 line_97 Line MORENCI 230.0 to GREEN-AE 230.0 Circuit I
line_98 Line RED TAIL 230.0 to DOSCONDO 230.0 Circuit 1
A2
![Page 100: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/100.jpg)
line_99 Line SAHUARIT 230.0 to BICKNELL 230.0 Circuit 1 line_IOO Line MEADN 230.0 to HVRA3A4 230.0 Circuit I
line_101 Line MEADS 230.0 to MEAD N 230.0 Circuit I
line_I02 Line DAVIS 230.0 to RIVIERA 230.0 Circuit 1 line_1 03 Line DAVIS 230.0 to MEAD N 230.0 Circuit I
line_104 Line DAVIS 230.0 to TOPOCK 230.0 Circuit 2 line_105 Line HOVRA5A6 230.0 to MEAD S 230.0 Circuit I
line_I06 Line HOVRA7-9 230.0 to MEAD S 230.0 Circuit I
line_I07 Line MEAD 500.0 to PERKINS 500.0 Circuit I line_1 08 Line PARKER 230.0 to EAGLEYE 230.0 Circuit I
line_1 09 Line PARKER 230.0 to BLK MESA 230.0 Circuit 1 line_1 10 Line PARKER 230.0 to HAVASU 230.0 Circuit I line_III Line PARKER 230.0 to HARCUVAR 230.0 Circuit I line_1 12 Line COOLIDGE 230.0 to SUN ARIZ 230.0 Circuit I
line_1I3 Line COOLIDGE 230.0 to SUN ARIZ 230.0 Circuit 2
line_1 14 Line LIBERTY 230.0 to WESTWNGW 230.0 Circuit I
line_1 15 Line LIBERTY 230.0 to LONE BUT 230.0 Circuit I line_1 16 Line LIBERTY 230.0 to PHXW AP A 230.0 Circuit I
line_1 17 Line LIBERTY 345.0 to PEACOCK 345.0 Circuit I
line_1 18 Line LONE BUT 230.0 to TESTTRAK 230.0 Circuit I line_1 19 Line LONE BUT 230.0 to SUN ARIZ 230.0 Circuit I
line_120 Line MCCONICO 230.0 to DAVIS 230.0 Circuit I line_121 Line MCCONICO 230.0 to GRIFFITH 230.0 Circuit 1 line_1 22 Line MCCONICO 230.0 to HARRIS 230.0 Circuit I
line_123 Line PHXW AP A 230.0 to LONE BUT 230.0 Circuit I
line_124 Line PINPK 230.0 to PINPKSRP 230.0 Circuit I
line_1 25 Line PINPK 230.0 to PINPKSRP 230.0 Circuit 2
line_1 26 Line TESTTRAK 230.0 to CASAGRND 230.0 Circuit I
line_127 Line HILLTOP 230.0 to MCCONICO 230.0 Circuit I
line_1 28 Line N.HA VASU 230.0 to PARKER 230.0 Circuit I
line_1 29 Line N.HAVASU230.0 to TOPOCK 230.0 Circuit I
line_l30 Line HOVRN7N8 230.0 to MEAD S 230.0 Circuit I
line_131 Line HOVRN5N6 230.0 to MEAD S 230.0 Circuit I
line_1 32 Line HOVRN3N4 230.0 to MEAD S 230.0 Circuit I
line_1 33 Line HOVRNIN2 230.0 to MEAD S 230.0 Circuit 1 line_1 34 Line HOVRAIA2 230.0 to MEAD S 230.0 Circuit I
line_1 35 Line HARCUV AR 230.0 to HARCU AZ 230.0 Circuit I line_136 Line HARCUVAR 230.0 to HASSYTAP 230.0 Circuit I
line_l37 Line SPKHILTP 230.0 to COOLIDGE 230.0 Circuit I
line_l38 Line GRIFFITH 230.0 to PEACOCK 230.0 Circuit I
line_1 39 Line PEACOCK 230.0 to HILLTOP 230.0 Circuit 1 line_140 Line PEACOCK 345.0 to MEAD 345.0 Circuit I
line_141 Line TOPOCK 230.0 to BLK MESA 230.0 Circuit I
line_142 Line TOPOCK 230.0 to SOPOINT 230.0 Circuit I line_1 43 Line TOPOCK 230.0 to SOPOINT 230.0 Circuit 2
line_144 Line HASSYT AP 230.0 to HASSY AZ 230.0 Circuit I
line_1 45 Line HASSYTAP 230.0 to LIBERTY 230.0 Circuit I
line_146 Line RNDVL YTP 230.0 to ROUNDVL Y 230.0 Circuit I
line_1 47 Line RNDVL YTP 230.0 to PEACOCK 230.0 Circuit I
line_148 Line ROGSW AP A 230.0 to PINPK 230.0 Circuit I
A3
![Page 101: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/101.jpg)
line_1 49 Line ROGSW APA 230.0 to PINPK 230.0 Circuit 2 line_ISO Line ROGSW AP A 230.0 to SPKHIL TP 230.0 Circuit I line_lSI Line FLAGSTAF 345.0 to GLENCANY 345.0 Circuit I line_152 Line FLAGSTAF 345.0 to GLENCANY 345.0 Circuit 2 line_153 Line FLAGSTAF 345.0 to PINPKBRB 345.0 Circuit I line_154 Line FLAGSTAF 345.0 to PINPKBRB 345.0 Circuit 2 line_155 Line GLEN PS 230.0 to NAV AJO 230.0 Circuit 1 line_156 Line KAYENTA 230.0 to SHIPROCK 230.0 Circuit I line_157 Line KAYENTA 230.0 to LNGHOUSE 230.0 Circuit I line_158 Line SHIPROCK 345.0 to FOURCORN 345.0 Circuit I line_159 Line NAVAJO 230.0 to LNGHOUSE 230.0 Circuit I line_160 Line TS4 230.0 to PLMVL Y 230.0 Circuit 1 line_161 Line RUDD 230.0 to PLMVL Y 230.0 Circuit I line_162 Line LIBERTY 230.0 to TS4 230.0 Circuit I line_163 Line BUTERFLD 230.0 to SLOAN 0.0 Circuit I line_1 64 Line DOSCONDO 230.0 to HACKBERY 230.0 Circuit I line_165 Line HACKBERY 230.0 to MORENCI 230.0 Circuit I line_166 Line ORME 230.0 to RUDD 230.0 Circuit 2 line_1 67 Line ABEL 500.0 to BROWNING 500.0 Circuit I line_1 68 Line DAVIS 230.0 to ZORB 230.0 Circuit I line_1 69 Line ZORB 230.0 to TOPOCK 230.0 Circuit I line_l70 Line FOURCORN 500.0 to FCW 500.0 Circuit I line_171 Line MOENKOPI 500.0 to RME 500.0 Circuit I line_In Line NAVAJO 500.0 to RME 500.0 Circuit I line_173 Line DRPP 500.0 to FCW 500.0 Circuit I line_174 Line DRPP 500.0 to FCW 500.0 Circuit 2 line_l75 Line RME 500.0 to FCW 500.0 Circuit I line_1 76 Line NAVAJO 500.0 to DUGAS 500.0 Circuit I line_l77 Line MORGAN 500.0 to WESTWING 500.0 Circuit I line_l78 Line MORGAN 500.0 to PNPKAPS 500.0 Circuit 1 line_179 Line SGRLF 500.0 to CHOLLA 500.0 Circuit I line_1 80 Line DUGAS 500.0 to MORGAN 500.0 Circuit 1 line_181 Line AVERY 230.0 to RACEWAY 230.0 Circuit I line_182 Line AVERY 230.0 to TS6 230.0 Circuit I line_183 Line TS6 230.0 to PP APS W 230.0 Circuit I line_184 Line SNVLY 230.0 to TRLBY 230.0 Circuit I line_1 85 Line SNVLY 230.0 to TRLBY 230.0 Circuit 2 line_1 86 Line CORONADO 500.0 to SGRLF 500.0 Circuit I line_187 Line PD-MORNC 230.0 to FRISCO 230.0 Circuit I line_188 Line CHOLLA 230.0 to LEUPP 230.0 Circuit I line_1 89 Line SNVLY 230.0 to HASSY AZ 230.0 Circuit I line_1 90 Line MEADS 230.0 to EQUEST 230.0 Circuit I line_1 91 Line MEADN 230.0 to EQUEST 230.0 Circuit 2 line_192 Line MEADN 230.0 to NEWPORT 230.0 Circuit I line_1 93 Line MEADN 230.0 to EASTSIDE 230.0 Circuit I line_194 Line MOENKOPI 500.0 to MARKETPL 500.0 Circuit I line_195 Line NAVAJO 500.0 to CRYSTAL 500.0 Circuit I line_1 96 Line FOURCORN 345.0 to RIOPUERC 345.0 Circuit I line_197 Line FOURCORN 345.0 to SAN_JUAN 345.0 Circuit I line_198 Line FOURCORN 345.0 to WESTMESA 345.0 Circuit I
A4
![Page 102: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/102.jpg)
line_199 line_200 line_201 line_202 line_203 line_204 line_205 line_206 line_207 line_208 line_209 line_2ID line_211 line_212 line_213 line_214 line_215 line_216 line_217 line_218 line_219
line_220 line_22I line_222 line_223 line_224 line_225 line_226 line_227 line_228 line_229 line_230 line_23I line_232 line_233 line_234 line_235 line_236 line_237 line_238 line_239 line_240 line_24I line_242 line_243 line_244 line_245 line_246 line_247 line_248
Line FOURCORN 230.0 to PILLAR 230.0 Line HENDRSON 230.0 to MEAD N 230.0 Line HALLEN 500.0 to MEAD 500.0 Line BC TAP 230.0 to MEAD N 230.0 Line DAVIS 230.0 to MCCULLGH 230.0 Line MEAD N 230.0 to DECATUR 230.0 Line MEAD S 230.0 to PAHRUMP 230.0 Line MEAD S 230.0 to GREENWAY 230.0 Line MEAD S 230.0 to MCCULLGH 230.0 Line MEAD S 230.0 to MCCULLGH 230.0 Line MEAD 500.0 to MARKETPL 500.0 Line PINTO PS 345.0 to FOURCORN 345.0 Line SIGURDPS 230.0 to GLENCANY 230.0 Line SHIPROCK 345.0 to SAN_JUAN 345.0 Line HASSYAMP 500.0 to N.GILA 500.0 Line MOENKOPI 500.0 to ELDORDO 500.0 Line PALOVRDE 500.0 to DEVERS 500.0 Line MEAD S 230.0 to ELDORDO 230.0 Line MEAD S 230.0 to ELDORDO 230.0 Line PARKER 230.0 to GENE 230.0 Line CAMINO 230.0 to MEAD S 230.0
Line CAMINO 230.0 to MEAD S 230.0 Line MEAD N 230.0 to ARDEN 230.0 Line MEAD S 230.0 to DIAMOND 230.0 Line MEAD S 230.0 to DIAMOND 230.0 Line HARQUAHA 500.0 to DEVERS 500.0 Line MEAD N 230.0 to SINATRA 230.0 Line EQUEST N 500.0 to MEAD 500.0 Line SNVLY 500.0 to MORGAN 500.0 Line DELANY 500.0 to SNVLY 500.0 Line PRECHCYN 345.0 to MAZATZAL 345.0 Line MAZATZAL 345.0 to PNPKAPS 345.0 Line JOJOBA 230.0 to GILARIVR 230.0 Line JOJOBA 230.0 to TS4 230.0 Line TRLBY 230.0 to TS2 230.0 Line TS2 230.0 to PLMVL Y 230.0 Line MORENCI 230.0 to PD-MORNC 230.0 Line PANTANO 230.0 to NEWTUCSN 230.0 Line NEWTUCSN 230.0 to SAHUARIT 230.0 Line BOWIE 500.0 to PINAL_C 500.0 Line BOWIE 500.0 to ARROYO 500.0 Line MOENKOPI 500.0 to YAVAPAI 500.0 Line Y A V AP AI 500.0 to WESTWING 500.0 Line DELANY 500.0 to HARQUAHA 500.0 Line DEERV AL Y 230.0 to WESTWNGE 230.0 Line WESTWNGW 230.0 to WESTWNGE 230.0 Line RACEWAY 230.0 to WESTWNGE 230.0 Line WESTWNGE 230.0 to EL SOL 230.0 Line HASSY AMP 500.0 to DELANY 500.0 Line PERKINS 500.0 to PERKINPS 500.0
A5
Circuit I Circuit I Circuit I Circuit I Circuit I Circuit I Circuit I Circuit I Circuit I Circuit 2 Circuit I Circuit I Circuit I Circuit I Circuit I Circuit I Circuit 1 Circuit I Circuit 2 Circuit I Circuit E Circuit W Circuit I Circuit I Circuit 2 Circuit I Circuit I Circuit I Circuit I Circuit I Circuit I Circuit I Circuit I Circuit I Circuit I Circuit I Circuit I Circuit I Circuit I Circuit I Circuit I Circuit I Circuit I Circuit I Circuit I Circuit I Circuit I Circuit I Circuit I Circuit I
![Page 103: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/103.jpg)
line_249 line_250 line_25I line_252 line_253 line_254 line_255 line_256 line_257 line_258 line_259 line_260 line_26I line_262 line_263 line_264 line_265 line_266 line_267 line_268 line_269 line_270 line_27I line_272 line_273 line_274 line_275 line_276 line_277 line_278 line_279 line_280 line_28I line_282 line_283 line_284 line_285 line_286 line_287 line_288 line_289 line_290 line_29I line_292 line_293 line_294 line_295 line_296 line_297 line_298
Line Line Line Line Line Line Line Line Line Line Line Line Line Line Line Line Line Line Line Line Line Line Line Line Line Line Line Line Line Line Line Line Line Line Line Line Line Line Line Line Line Line Line Line Line Line Line Line Line Line
PAPAGOBT 230.0 to KYR-NEW 230.0 PINAL_C 500.0 to TORTOLIT 500.0 SAGUARO 500.0 to TORTOLIT 500.0 SAGUARO 500.0 to TORTOLIT 500.0 BICKNELL 345.0 to VAIL 345.0 GREEN-AE 345.0 to GREENLEE 345.0 GREENLEE 345.0 to COPPERVR 345.0 GREENLEE 345.0 to WILLOW 345.0 GREENLEE 345.0 to WINCHSTR 345.0 HIDALGO 345.0 to GREENLEE 345.0 MCKINLEY 345.0 to SPRINGR 345.0 MCKINLEY 345.0 to SPRINGR 345.0 PINALWES 345.0 to SOUTH 345.0 SAN_JUAN 345.0 to MCKINLEY 345.0 SAN_JUAN 345.0 to MCKINLEY 345.0 SOUTH 345.0 to GATEWAY 345.0 SOUTH 345.0 to GATEWAY 345.0 SPRINGR 345.0 to CORONADO 345.0 SPRINGR 345.0 to GREENLEE 345.0 SPRINGR 345.0 to LUNA 345.0 SPRINGR 345.0 to V AIL2 345.0 TORTOLIT 345.0 to NLOOP345 345.0 V AIL 345.0 to SOUTH 345.0 WESTWING 345.0 to PINALWES 345.0 WESTWING 345.0 to SOUTH 345.0 WHTHILLS 345.0 to MEAD 345.0 WHTHILLS 345.0 to PEACOCK 345.0 WILLOW 345.0 to BOWIE 345.0 WILLOW 345.0 to BOWIE 345.0 WINCHSTR 345.0 to V AIL 345.0 WINCHSTR 345.0 to WILLOW 345.0 FRANCONI 230.0 to GRIFFITH 230.0 FRANCONI 230.0 to N.RA V ASU 230.0 MCCONICO 230.0 to MERC230 230.0 WHTHILLS 230.0 to MERC230 230.0 RACEWAY 230.0 to RACEWYW A 230.0 PRSCOTW A 230.0 to PRESCOTT 230.0 PRSCOTW A 230.0 to RNDVLYTP 230.0 GA VLINW A 230.0 to GA VILNPK 230.0 GA VLINW A 230.0 to PINPK 230.0 GA VLINW A 230.0 to PRSCOTW A 230.0 N.w ADDEL 230.0 to RACEWYW A 230.0 RASSYAMP 500.0 to N.GILA 500.0 ANDERSON 230.0 to KYR-NEW 230.0 SIL VERKG 230.0 to GOLDFELD 230.0 ABEL 230.0 to DINOSAUR 230.0 RACEWYW A 230.0 to WESTWNGE 230.0 CASGRAPS 230.0 to MILLIGAN 230.0 TSI2 230.0 to SAGUARO 230.0 MILLIGAN 230.0 to TSI2 230.0
A6
Circuit I Circuit I Circuit 1 Circuit 2 Circuit I Circuit 1 Circuit I Circuit I Circuit I Circuit I Circuit I Circuit 2 Circuit I
Circuit I Circuit 2 Circuit I Circuit 2 Circuit I Circuit I Circuit I Circuit I Circuit I Circuit I Circuit I
Circuit I Circuit I Circuit I Circuit I Circuit 2 Circuit I Circuit I Circuit I Circuit I Circuit 1 Circuit I Circuit I Circuit I
Circuit I Circuit I Circuit I Circuit I Circuit I Circuit 2 Circuit 1 Circuit I Circuit I Circuit 1 Circuit I Circuit I Circuit I
![Page 104: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/104.jpg)
line_299 Line VERDE S 230.0 to VERDE N 230.0 Circuit I line_300 Line VERDE S 230.0 to COCONINO 230.0 Circuit I line_301 Line GILA 230.0 to NGL-E 230.0 Circuit I line_302 Line GILA 230.0 to NGL-W 230.0 Circuit I line_303 Line SLRC 230.0 to GILA 230.0 Circuit 2 line_304 Line SLRC 230.0 to GILA 230.0 Circuit I line_305 Line GLENDALE 230.0 to GLENDALW 230.0 Circuit I line_306 Line GLENDALW 230.0 to AGUAFRIA 230.0 Circuit I line_307 Line BUCKEYE2 230.0 to LIBERTY 230.0 Circuit I line_308 Line EAGLEYE 230.0 to BUCKEYE2 230.0 Circuit I line_309 Line BUCKEYE 230.0 to BUCKEYE2 230.0 Circuit I line_310 Line CORONADO 500.0 to CHOLLA 500.0 Circuit I line_311 Line PERKINPS 500.0 to WESTWING 500.0 Circuit I line_312 Line BUCK230 230.0 to lHINDS 230.0 Circuit I line_3l3 Line PALOVRDE 500.0 to DELANY 500.0 Circuit I line_314 Line HASSY AMP 500.0 to HARQUAHA 500.0 Circuit I line_315 Line SNT AROSA 230.0 to DBG 230.0 Circuit I line_316 Line DBG 230.0 to CASGRAPS 230.0 Circuit I line_317 Line KYRENE 500.0 to BROWNING 500.0 Circuit I line_318 Line PERKINPS 500.0 to PERK PS I 500.0 Circuit I line_319 Line BROWNING 500.0 to SIL VERKG 500.0 Circuit I line_320 Line PINAL_C 500.0 to ABEL 500.0 Circuit I line_32I Line PINAL_C 500.0 to SNTAROSA 500.0 Circuit I line_322 Line PINAL_ W 500.0 to SNT AROSA 500.0 Circuit I line_323 Line JOJOBA 500.0 to GILARJVR 500.0 Circuit I line_324 Line JOJOBA 500.0 to GILARJVR 500.0 Circuit 2 line_325 Line JOJOBA 500.0 to KYRENE 500.0 Circuit I line_326 Line HASSY AMP 500.0 to JOJOBA 500.0 Circuit I line_327 Line ORME 230.0 to ANDERSON 230.0 Circuit I line_328 Line ORME 230.0 to ANDERSON 230.0 Circuit 2 line_329 Line PINPKSRP 230.0 to BRANDOW 230.0 Circuit I line_330 Line PINPKSRP 230.0 to BRANDOW 230.0 Circuit 2 line_33I Line SANTAN 230.0 to RS-24 230.0 Circuit I line_332 Line SCHRADER 230.0 to RS-24 230.0 Circuit I line_333 Line ABEL 230.0 to RS-24 230.0 Circuit I line_334 Line ABEL 230.0 to RS-24 230.0 Circuit 2 line_335 Line ABEL 230.0 to SANT AN 230.0 Circuit I line_336 Line BROWNING 230.0 to DINOSAUR 230.0 Circuit I line_337 Line BROWNING 230.0 to RANDOLPH 230.0 Circuit I line_338 Line ABEL 230.0 to RANDOLPH 230.0 Circuit I line_339 Line PINAL_C 230.0 to DBG 230.0 Circuit I line_340 Line PINAL_C 230.0 to RANDOLPH 230.0 Circuit I line_341 Line SUN ARJZ 230.0 to PINAL_C 230.0 Circuit I line_342 Line N.GILA 230.0 to TS8 230.0 Circuit I tran_343 Tran CHOLLA 500.00 to CHOLLA 345.0 Circuit I tran_344 Tran CHOLLA 500.00 to CHOLLA 345.0 Circuit 2 tran_345 Tran FOURCORN 500.00 to FOURCORN 345.0 Circuit I tran_346 Tran WESTWING 500.00 to WESTWNGW 230.0 Circuit I tran_347 Tran WESTWING 500.00 to WESTWNGW 230.0 Circuit 2 tran_348 Tran GILARJVR 500.00 to GILARIVR 230.0 Circuit 1
A7
![Page 105: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/105.jpg)
tran_349 Tran FOURCORN 345.00 to FOURCORN 230.0 Circuit 1 tran_350 Tran FOURCORN 345.00 to FOURCORN 230.0 Circuit 2 tran_351 Tran PNPKAPS 345.00 to PPAPS C 230.0 Circuit J tran_352 Tran PNPKAPS 345.00 to PPAPS N 230.0 Circuit 2 tran_353 Tran PNPKAPS 345.00 to PPAPS E 230.0 Circuit 3 tran_354 Tran KYRENE 500.00 to KYRENE 230.0 Circuit 7 tran_355 Tran PERKINS 500.00 to PERK PS 1 500.0 Circuit 1 tran_356 Tran PERKINS 500.00 to PERK PS2 500.0 Circuit 1 tran_357 Tran SIL VERKG 500.00 to SIL VERKG 230.0 Circuit 1 tran_358 Tran BROWNING 500.00 to BROWNING 230.0 Circuit 1 tran_359 Tran BROWNING 500.00 to BROWNING 230.0 Circuit 2 tran_360 Tran RUDD 500.00 to RUDD 230.0 Circuit J tran_361 Tran RUDD 500.00 to RUDD 230.0 Circuit 2 tran_362 Tran RUDD 500.00 to RUDD 230.0 Circuit 3 tran_363 Tran MESQUITE 500.00 to MESQUITE 230.0 Circuit J tran_364 Tran COPPERVR 345.00 to COPPERVR 230.0 Circuit I tran_365 Tran BICKNELL 345.00 to BICKNELL 230.0 Circuit J tran_366 Tran GREEN-AE 345.00 to GREEN-AE 230.0 Circuit J tran_367 Tran MEAD 345.00 to MEAD N 230.0 Circuit I tran_368 Tran MEAD 500.00 to MEAD N 230.0 Circuit J tran_369 Tran LIBERTY 345.00 to LIBTYPHS 230.0 Circuit J tran_370 Tran LIBTYPHS 230.00 to LIBERTY 230.0 Circuit J tran_37 J Tran PEACOCK 345.00 to PEACOCK 230.0 Circuit 1 tran_372 Tran GLEN PS 230.00 to GLENCANY 230.0 Circuit J tran_373 Tran GLENCANY 345.00 to GLENCANY 230.0 Circuit 1 tran_374 Tran GLENCANY 345.00 to GLENCANY 230.0 Circuit 2 tran_375 Tran PINPKBRB 345.00 to PINPK 230.0 Circuit 1 tran_376 Tran PINPKBRB 345.00 to PINPK 230.0 Circuit 2 tran_377 Tran PINPKBRB 345.00 to PINPK 230.0 Circuit 3 tran_378 Tran SHIPROCK 345.00 to SHIPROCK 230.0 Circuit 1 tran_379 Tran RUDD 500.00 to RUDD 230.0 Circuit 4 tran_380 Tran SNVLY 500.00 to SNVL Y 230.0 Circuit 1 tran_381 Tran SNVLY 500.00 to SNVL Y 230.0 Circuit 2 tran_382 Tran MORGAN 500.00 to RACEWAY 230.0 Circuit 1 tran_383 Tran MORGAN 500.00 to RACEWAY 230.0 Circuit 2 tran_384 Tran PNPKAPS 500.00 to PPAPS N 230.0 Circuit J tran_385 Tran PNPKAPS 500.00 to PPAPS E 230.0 Circuit 1 tran_386 Tran MEAD 500.00 to MEAD N 230.0 Circuit 2 tran_387 Tran CHOLLA 345.00 to CHOLLA 230.0 Circuit J tran_388 Tran CHOLLA 345.00 to CHOLLA 230.0 Circuit 2 tran_389 Tran MEADS 230.00 to MEAD 287.0 Circuit 1 tran_390 Tran SHIP PS 230.00 to SHIPROCK 230.0 Circuit 1 tran_39 J Tran ARROYO 500.00 to ARROYO 345.0 Circuit J tran_392 Tran ARROYO 500.00 to ARROYO 345.0 Circuit 2 tran_393 Tran WESTWING 500.00 to WESTWNGE 230.0 Circuit J tran_394 Tran YA V AP AI 500.00 to Y A V APAI 230.0 Circuit 1 tran_395 Tran Y A V AP AI 500.00 to Y A V AP AI 230.0 Circuit 2 tran_396 Tran CORONADO 500.00 to CORONADO 345.0 Circuit 1 tran_397 Tran CORONADO 500.00 to CORONADO 345.0 Circuit 2 tran_398 Tran PINAL_ W 500.00 to PINALWES 345.0 Circuit 1
A8
![Page 106: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/106.jpg)
tran_399 Tran TORTOLIT 500.00 to TORTOLIT 345.0 Circuit I tran_ 400 Tran WESTWING 500.00 to WESTWING 345.0 Circuit 1 tran_ 401 Tran WHTHILLS 345.00 to WHTHILLS 230.0 Circuit 1 tran_ 402 Tran WINCHSTR 345.00 to WINCHSTR 230.0 Circuit I tran_ 403 Tran BOWIE 500.00 to BOWIE 345.0 Circuit 1 tran_ 404 Tran BOWIE 500.00 to BOWIE 345.0 Circuit 2 tran_ 405 Tran GREEN-AE 345.00 to GREEN-AE 230.0 Circuit 2 tran_ 406 Tran NGL-E 230.00 to N.GILA 500.0 Circuit 1 tran_ 407 Tran NGL-W 230.00 to N.GILA 500.0 Circuit 1 tran_ 40B Tran ABEL 500.00 to ABEL 230.0 Circuit 1 tran_ 409 Tran COPPERVR 345.00 to COPPERVR 230.0 Circuit 2 tran_ 410 Tran KYRENE 500.00 to KYR-NEW 230.0 Circuit 6 tran_ 411 Tran KYRENE 500.00 to KYRENE 230.0 Circuit B tran_ 412 Tran ABEL 500.00 to ABEL 230.0 Circuit 2 tran_ 413 Tran PINAL_C 500.00 to PINAL_C 230.0 Circuit 1 tran_ 414 Tran PINAL_C 500.00 to PINAL_C 230.0 Circuit 2 tran_ 415 Tran SNT AROSA 500.00 to SNT AROSA 230.0 Circuit 1 tran_ 416 Tran N.GILA 500.00 to N.GILA 230.0 Circuit 1 tran_417 Tran PNPKAPS 500.00 to PPAPS W 230.0 Circuit I gen_ 41B Gen CORONADI 22.0 Unit 1 gen_ 419 Gen CORONAD2 22.0 Unit 1 gen_420 Gen NA V AlO 1 26.0 Unit 1 gen_ 421 Gen NAVAJO 2 26.0 Unit 1 gen_422 Gen NAVAJO 3 26.0 Unit 1 gen_423 Gen SANTAN 1 13.B Unit 1 gen_424 Gen ARL-CTl IB.O Unit 1 gen_425 Gen ARL-CT2 IB.O Unit 1 gen_426 Gen ARL-STl IB.O Unit 1 gen_427 Gen HGC-CTl 16.0 Unit 1 gen_42B Gen HGC-STl 13.B Unit 1 gen_ 429 Gen HGC-CT2 16.0 Unit 1 gen_430 Gen HGC-ST2 13.B Unit 1 gen_ 431 Gen HGC-CT3 16.0 Unit 1 gen_432 Gen HGC-ST3 13.B Unit 1 gen_ 433 Gen MES-CTl IB.O Unit 1 gen_434 Gen MES-CT2 IB.O Unit 1 gen_435 Gen MES-STl IB.O Unit 1 gen_436 Gen MES-CT3 IB.O Unit 1 gen_ 437 Gen MES-CT4 IB.O Unit 1
gen_ 43B Gen MES-ST2 IB.O Unit 1 gen_439 Gen CHOLLA 13.B Unit 1 gen_440 Gen CHOLLA2 22.0 Unit 1 gen_441 Gen CHOLLA3 22.0 Unit 1
gen_442 Gen CHOLLA4 22.0 Unit 1 gen_443 Gen FCNGEN 1 20.0 Unit 1 gen_444 Gen FCNGEN 2 20.0 Unit 1 gen_445 Gen FCNGEN 3 20.0 Unit 1 gen_446 Gen FCNGN4CC 22.0 Unit 4 gen_447 Gen FCNGN5CC 22.0 UnitS gen_44B Gen OCOTGT2 13.B Unit 1
A9
![Page 107: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/107.jpg)
gen_449 Gen PALOVRDI 24.0 Unit I gen_450 Gen PALOVRD2 24.0 Unit I gen_ 451 Gen PALOVRD3 24.0 Unit 1 gen_452 Gen SAGUARO I 15.S Unit I gen_453 Gen SAGUAR02 15.5 Unit 1 gen_454 Gen WPHXCCI 13.S Unit 1 gen_455 Gen WPHXCC2 13.S Unit I gen_456 Gen WPHXCC3 13.S Unit I gen_457 Gen WPCC5CTl 15.0 Unit 1 gen_4SS Gen WPCCSCT2 15.0 Unit I gen_459 Gen WPCC5STl 16.5 Unit I gen_460 Gen WPCC4CTl 13.S Unit I gen_46I Gen RED-CTI IS.O Unit I gen_462 Gen RED-CT2 IS.O Unit 1 gen_463 Gen GJL-CTl IS.O Unit 1 gen_464 Gen GJL-CT2 IS.O Unit I gen_465 Gen GJL-STl IS.O Unit I gen_466 Gen GJL-CT3 IS.O Unit I gen_467 Gen GJL-CT4 IS.O Unit 1 gen_46S Gen GJL-ST2 IS.O Unit 1 gen_469 Gen GJL-CTS IS.O Unit 1 gen_470 Gen GJL-CT6 IS.O Unit 1 gen_471 Gen GJL-ST3 IS.O Unit I gen_ 472 Gen GJL-CT7 IS.O Unit I gen_ 473 Gen GJL-CTS IS.O Unit 1 gen_474 Gen GJL-ST4 IS.O Unit I gen_475 Gen APACHST2 20.0 Unit I gen_476 Gen APACHST3 20.0 Unit I gen_477 Gen RED-CT3 IS.O Unit I gen_47S Gen RED-CT4 IS.O Unit I gen_ 479 Gen RED-STl IS.O Unit I gen_4S0 Gen RED-ST2 IS.O Unit I gen_ 4S1 Gen SANTN 5S IS.O Unit 1 gen_4S2 Gen SANTN 5A IS.O Unit 1 gen_4S3 Gen SANTN 6A IS.O Unit I
gen_4S4 Gen SANTN 6S 13.S Unit 1 gen_ 4S5 Gen HOOVERA3 16.5 Unit 1 gen_4S6 Gen HOOVERA4 16.5 Unit 1 gen_4S7 Gen HOOVERAS 16.5 Unit 1
gen_4SS Gen HOOVERA6 16.5 Unit 1 gen_4S9 Gen HOOVERA7 16.5 Unit I gen_490 Gen HOVRAIA2 16.5 UnitAl gen_ 491 Gen HOVRAIA2 16.5 Unit A2 gen_492 Gen HOVRNIN2 16.5 UnitNI gen_493 Gen HOVRNIN2 16.5 UnitN2 gen_494 Gen HOVRN3N4 16.5 Unit N3 gen_495 Gen HOVRN3N4 16.5 UnitN4 gen_496 Gen HOVRN5N6 16.5 Unit N5 gen_497 Gen HOVRN5N6 16.5 Unit N6 gen_49S Gen HOVRN7NS 16.5 Unit N7
AIO
![Page 108: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/108.jpg)
gen_499 Gen HOVRN7NS 16.5 UnitNS gen_SOO Gen GLENCI-2 13.S Unit I gen_SOI Gen GLENCI-2 13.S Unit 2 gen_S02 Gen GLENC3-4 13.S Unit 3 gen_S03 Gen GLENC3-4 13.S Unit 4 gen_S04 Gen GLENCS-6 13.S Unit S gen_SOS Gen GLENCS-6 13.S Unit6 gen_S06 Gen GLENC7-S 13.S Unit 7 gen_S07 Gen GLENC7-S 13.S Unit S gen_SOS Gen SOPOINTI 16.0 Unit I gen_S09 Gen SOPOINT2 16.0 Unit 2 gen_SIO Gen SOPOINT3 16.0 Unit 3 gen_SII Gen GRIFFfHI IS.O Unit I gen_Sl2 Gen GRIFFfH2 IS.O Unit 2 gen_Sl3 Gen GRIFFfH3 IS.O Unit 3 gen_Sl4 Gen BLYENGI 16.0 Unit I gen_SIS Gen BLYENG2 16.0 Unit I gen_Sl6 Gen BLYENG3 16.0 Unit I gen_Sl7 Gen HAVASUl2 13.2 Unit I gen_SIS Gen HAVASUl2 13.2 Unit 2 gen_Sl9 Gen DBG-CTl IS.O Unit I gen_S20 Gen DBG-CT2 IS.O Unit I gen_S21 Gen DBG-STl IS.O Unit I gen_S22 Gen DRPPGI 24.0 Unit I gen_S23 Gen DRPPG2 24.0 Unit I gen_S24 Gen BOWIE_GI IS.O Unit I gen_S2S Gen BOWIE_G2 IS.O Unit I gen_S26 Gen BOWIE_G3 IS.O Unit I gen_S27 Gen BOWIE_G4 IS.O Unit I gen_S2S Gen BOWIE_SI IS.O Unit I gen_S29 Gen BOWIE_S2 IS.O Unit I gen_S30 Gen DMPCCT#I 13.S Unit 1 gen_S31 Gen SPRGENI 19.0 Unit I gen_S32 Gen SPR GEN2 19.0 Unit I gen_S33 Gen SPR GEN3 21.0 Unit I gen_S34 Gen SPR GEN4 21.0 Unit I gen_S3S Gen SUNDTGEI 13.S Unit I gen_S36 Gen SUNDTGE2 13.S Unit I gen_S37 Gen SUNDTGE3 13.S Unit 1
gen_S3S Gen SUNDTGE4 IS.O Unit I gen_S39 Gen OCOTGTI 13.S Unit 1 gen_S40 Gen WPHXGTI 13.S Unit I gen_S41 Gen WPHX ST4 12.S Unit 1 gen_S42 Gen OCOTST2 13.S Unit I gen_S43 Gen OCOTSTI 13.S Unit 1 gen_S44 Gen WPHXGT2 13.S Unit I gen_S4S Gen WPHX ST6 12.5 Unit I gen_S46 Gen FAIRVWII 12.5 Unit I gen_S47 Gen CHILDS 2.3 Unit I gen_S4S Gen IRVING 2.3 Unit I
All
![Page 109: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/109.jpg)
gen_549 Gen ABITIBI 13.8 Unit 1 gen_550 Gen YUCCAGEN 13.8 Unit 1 gen_551 Gen YUCCACTI 13.2 Unit 1 gen_552 Gen YUCCACT2 13.2 Unit 1 gen_553 Gen YUCCACT3 13.8 Unit 1 gen_554 Gen YUCCACT4 13.8 Unit 1 gen_555 Gen RVERSIDE 69.0 Unit 1 gen_556 Gen YUCCACT5 13.8 Unit 1 gen_557 Gen YUCCACT6 13.8 Unit 1 gen_558 Gen SLRC-STI 21.0 Unit 1 gen_559 Gen SLRC-CT2 18.0 Unit 1 gen_560 Gen SLRC-CTI 18.0 Unit 1 gen_561 Gen SANTAN 2 13.8 Unit 1 gen_562 Gen SANTN 5B 18.0 Unit 1 gen_563 Gen SANTAN 4 13.8 Unit 1 gen_564 Gen CROSSHYD 69.0 Unit 1 gen_565 Gen AGUAFR3 18.0 Unit 1 gen_566 Gen AGUAFR 1 13.8 Unit 1 gen_567 Gen AGUAFR2 13.8 Unit 2 gen_568 Gen ABELGI 13.8 Unit 1 gen_569 Gen ABELG2 13.8 Unit 1 gen_570 Gen ABELG3 13.8 Unit 1 gen_571 Gen ABELG4 13.8 Unit 1 gen_572 Gen ABELGS 13.8 Unit 1 gen_573 Gen ABELG6 13.8 Unit 1 gen_574 Gen ABELG7 13.8 Unit 1 gen_575 Gen ABELG8 13.8 Unit 1 gen_576 Gen ABELG9 13.8 Unit 1 gen_577 Gen KYREN 7S 13.8 Unit 1 gen_578 Gen KYREN 7A 18.0 Unit 1 gen_579 Gen SANTAN 3 13.8 Unit 1
AI2
![Page 110: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/110.jpg)
APPENDIXB
Power Flow Maps
![Page 111: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/111.jpg)
Coconino 230/69kV Substation Outage without Youngs Canyon (Flagstaff) 345/69kV Substation (2012)
1..2
JlP 4.4 -0.3 _
1. 018
31 . 1 4 .'
- 15 . 0 2 . 3
11. 0 _ 1.2_
11. 0 __
1. 006
/
-- ~r-::,~O~:~~----~f-7~~~~:~·~~--~ --2~:: 1. 018 Shed 16 MW @
t\"\..."'ODY Coconino 15 _______ t;ol
Shed9.7MW@ Woody Mountain
»::'J1I1'k!~
1.3
Shed 13.9 MW Coconino 21
~V = 4.5%
r ~ g __ 119.2
_____ _ _ ~:--- 12 . 2
:J 28.4 '-------\--~24. 21 1 1'.4- 4 . 1 -- 11 . 2 1 . 3_
. 3 Close eN.O.) Coconino -•• Williams tap 69kV tie
L002
1. 021
- 0.0 1!, b1 -22.0
- 0.0 1" b2 - 14."J
BI
ro :'.I!Jf-P
----- 1 I I ,
44 . 4 11 . 1
1.100 'v"VV
.-33' . 2 ,.. 2 1 . 1 _330 .] - 32. 0
-333. 6 -- 28.' _331 . 8 -- 30.5
1. 0 20
44 . 4
ro C::'Lli Ck.'t)' ON
TO
P!lUlkC::...r. ~£.1,.}:
** Shed 39.6 MW Total
![Page 112: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/112.jpg)
Coconino 230/69kV Substation Outage with Youngs Canyon (Flagstaff) 34S/69kV Substation (2012)
4 . 1 __
4 . 1 '"
'~ 1lP 4.4 -
•. 3 .,
• . 995
'W-f.1 ",'.0,. 1~~n 0 . 5 0 . 5 U
• . •• 4
-. --_.---------
.-- ---
1
- '.9 16 . • - 11 . • _
2 . 1--11---~i8~. j3~1~i3~· i2~ II 13 . 1 11 . • _ 2 . 2_
• . 994
",' IlIO!lk 19 . • _ 1-46 . 4
:L4--2. l
_13 . ' "
1.1 _
1. 014
I
-83.1
PkDR£.
.-21 . 5 -1 • . 4
TO
.s'JlIS HUI£
40 . • _ 1=12 . '
I 2 . 2 ,I- 21. 5_ ~ •• ,~D
1.4 . 81 • . 4 .• ~
•• 1. .16 1..11
~~ tlV = 2.2% __ 341-1
-- 4 . 1 tlV = 2.3 % -- n . 1
__ 336 . 1 ~34 _ 6
-286 . 8
----------
' ~.g f--1l7 . D
24 . 8
_285.2 - 26 . 5
1 . 026
:J "1 3 . 2-4 .1-~
2.4-- --------~:--- 11-3 1-------------------------...;4"."'58_ 1 1. 023
1.3_
I..
PAR}: ••• .5 ClIIm .. u.
\ ' 1 :':.:.cl:
~ 0 .• 'I b1 ___ 21.5 1'1'
= 0.0 II, b2 14.4
B2
![Page 113: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/113.jpg)
Adobe - Deer Valley 69kV Outage without TS6 230/69kV Substation (2012)
Shed 34.8 MW
To Adobe
DEER VALLEY 1. . 028 1!l4019
g .,
JS .' 0 .0 0 .0
!!4 .0 -..0 .0 ' .5 --50 .1
14 .0 lte .::! LI ' .0
21 .0 ' .0
21 .1 1440 .6 ' .1 - ' .0
34 .0 --- ---- -------- -- , ., 19 .6
1 .2 1 . 02e 111020
0 0 0 .;
0 0 0
...
To Stout
1 .02'"
1 .0 2 .> •
TURr
2t . l. ' .5
20 .6 ' .0
1 . 021
33 .e 2 .'
>D .> 1 .0
etOSI1
B3
~?!~H vIt4~~1 20 .1
' .0
21.1 ' .2
~ . DlD
To TSf
•• Shed 34.8 MW Total
. -- ------- -. ---- ------
I .' 0 .5
5 .3 31. .9 :3 .5 5 .6
1 .021 114:205
UllI OD HI!.L!:! 1 .023 ell.DO
4:4: . 4: 2 .'
25.1 61 .6 3 .4 US ,O
32 .9 ' .0
1. 023
,., 5 .'
>D .g .. , 84:099
LOm: PEAI< 1 .032 el255
' .2 '15 .' >.0 > .•
2 .' 26 .2
24 . 2 __ J24 .9
' .2 .,. 26 .0
:31 .11 , .> 5 .2 ::1.1 . l.
1. 032 1!14256
LO OKOUT 1 .019 214:051
Deer Valley - Rose Garden 69kV line loaded @ 99.6%
0 0 0 .;
< 0 0 0 .;
![Page 114: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/114.jpg)
Adobe - Deer Valley 69kV Outage with TS6 230/69kV Substation (2012)
___ _________ __ ___ _____ To Adobe
DEER VALLI:Y ~ . C30 8"0l.9
5 .' .. , ,., 1 .0
go.o ..;.- 0 .0 I"h ' . 5 -50 . 9
101 . 0 0 0 , .. 0
....
21 ,0 0 0 ". 0
....
27 . '1 136 . ~ 0 0 , .. - ' .0 0 ..;
35 .5 ----------------- , .. 113 .9 ' .2
1 .030 154:020
To Stout
R OSE (PARDEII' ~ . 019 "",,0155
11 .9 2 . 1
21 . 1 2 , '
1 .019
""'O!l.0
0 ,0 ,2
YOP.K5HIP.I:
1. 0 63 .3 :3 . 6 .9
1 .030
,., ,., •
Tup. r
24:.1 ' .5
20 .6 , .. 1 .022
3S .3 ,.,
.. . 2
M091
B4
IlORTH VALLEY 1 .0lB 15",0'6
20 .1 ' .5
21 .1 ,,' 1. .OlD
AQUEDUCT 1 .021 Bi20t
5 .' ' ,5
1.021
>2 . '
•••
UllI on HILLS 1.024: BUDO
49 .1 ,,' 25 .1 64:.9
3 . '5: U ,S
5 ,1 5 . ' , .. .,' e40g!;l
LOm: PEAK 1 .032 84:255
5 ,0 " ,2
2 .' ' .0
1 .' 2 15 .9
24 .2 _llSI . 9 ' .2 .... 215 .8
" .5 5 .2 ' .5 " .5
1.032 84256
L OOKOUT 1 .020 15"051
31.2 __ 2 . 15 __
Deer Valley - Rose Garden 69kV line loaded @ 61.20/0
To TSti
0 0 0 ..;
0 0 0
...
![Page 115: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/115.jpg)
Adobe - Stout 69kV Outage without TS6 230/69kV Substation (2012)
Shed 27.8MW
r--------------- ToAd~t
DEER VALLEY 1 .026 ISt01.9
1 .2 2i .4
' .3 5 .<
18 .4 ..... 0 .0 3 .0 -50 .6
11 .0 154 .15 , .< 3 .'
21 .0 3 .'
21 .1 151 .15 3 .< - 2 .1
4:3 .5 30 .1 • . < 3 .3
1i .l. 3 . '
1.026 01020
I'· ' 0 0 0 ...
0 0 0 ...
0 0 "! ...
T o StO'l.1t.
RO SE GAP.DEl1' ~ . OOg !StOe5
2 .5 ' . 2
51 .3 5 .<
31.3 2 .< ,.<
TURr
2'1 .1 30 .6 3 .5 2 .'
20 .6 14: .2
B5
n ORTH VALLE"l 1 . 004 e4016
20 .1 < .•
21. .1 3 .2
1 .004:
To T 3·£
** Shed 27.8 MW Total
AQUEDUCT .. _ .... ---.. _. ------ -1 .021 tlt2Di
3 .0 0 .<
5.3 30 .3 3 . 5 5 .•
1 .021 "'!205
mu oD' HILLS 1 .022 eHJJO
31.2 2 .0
2 5 .1 15 .1 3 . t 1.6 .2
Lam; PEiIK 1 .031 84:255
>'3 'l5 . •
. .< 0 .<
< .3 26 .3
2'1 . 2 _l26 .1 3 .2 ~ 26 .1
30 .2 ~6 . 0
5 .' :1..1 . 15 1.03l. IU256
L OOKOUT 1 .018 154051
Deer Valley - Rose Garden 69kV line loaded @ 99.6%
0 0 0 ...
0 0 0
...
![Page 116: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/116.jpg)
Adobe - Stout 69kV Outage with TS6 230/69kV Substation (2012)
To Stout
To Adobe R OSe GARDEn 1 .019 84:01!lS
,.-.., .. ),1 .9 0 . '
2 .1 .. DEER VALLEY 21 .1 3 .0 1.. 0251 8"'019 2 . ' .,
3 .' 1 .019 11'1086
•• _ .2 1 . '
86 .1 .... 0 . 0 I,·h 3 .5 -50 . 9
14 .0 H3 .2 0 0
L. 3 ." 0
" 14 .0 3 .0
21 .0 0 0
3 .8 0 1 . 029 ..;
0 21 .1 ltD.9 0
3 .' - 3 .3 0
" 50 .9 32 .9 6 .0 .. , T1,TRl'
eo.'I ' .3 201 . l 32 .1
1..029 15'10 20 3 .5 3 .5
20 .6 12 .0 3 ._ 3 ._
1 . 022 ISt091
n ORTH v ALLEY ~ . O~1 8""016
20 .1 .. "
n .? 3.'
J. .011
5 .3 3 .5
1 . 026
Uln OD' HILLS 1 .02'" en.co
: U .O 3 .1
25 .1 ' U .3 3 . ' >3 .5
B6
LOm: PEAK 1..032 8"255
5 . ' >5 .2
L6 ' .0 .. 21 .0
24 .2 3 .2
15 . '
1~O3~
L OOKOUT 1.. 01.9 "iDS1
Deer V alley - Rose Garden 69kV line loaded @ 42.5%
To TS ti
0 0 0 ..;
0 0
" "
![Page 117: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/117.jpg)
Owens - Preacher Canyon 69kV outage without Mazatzal 34S/69kV Substation (2013)
1.026
T O CHOLLA 382 . 5 55 . 7
T O KAZAT ZAL 374 .1 54.6 ~
3TRAloIBEP.RY 3 4 Sk V
Loaded to 99.5% 1.00 R
4.8 ~ Ton o C ULD9 / :vm. 0 . 0 - 1.018
1.008 ~ 1.4
'" - ---..35 . 9 __ 30.4 -+-11.3
V -15 . 5 -16.5
~ _31.0 V J ~
7.9 --14.0 KA2AT2AL 0 . 2 _
~ 11. 020 ....
~ - - - ~ .... ...... j -9.6
~ -0.2 ! 1. 014
- o . l -(>AP ~ -0.0
~ ~ 1.000 ,
r-"--------G) ,
345 :KV _10.3 t t t l h.018 1.8
1.020 '" ... "' ... """ '" '" ... "' .... "' "' TO "'TO
PJU: ACHCt PIltIfACI.I:
CAD'YOD' PUK
B7
PP.I:ACltEP.
CAlTYOD'
Il. 2 . 3 _ 0.2 __
•• 5 . 9 _
1.025
....... 8 . 2 --0.9
0 . 7 -f- - - -- , I
,
Shed 8.5 MW @ PI
/ - - - - - - 1.4 ..f>l AP
-0.0 ......
I - 0.0 I ..,... 11.3
1.022
" ~ < ~AP CI"I -2 . 3
c:i ? -0 . 0 Ir, hI 1 . 051 - 2 . 7
'il :; < - 10 . 2 , ** Shed 8.5 MW AP
.. > - 3.1 "
- 0.0 'I" b2 - 2.7 ,.
Total
1.068
![Page 118: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/118.jpg)
CHILD S
v
.... c
~~ - 0.1 -f'>AP -0.0 v
1.025
Owens - Preacher Canyon 69kV outage with Mazatzal 345/69kV Substation (2013)
j • c .. ....
1. 026
T O CHOLLA 397 ._3 _ 53.2 -
PRE ACHER
CAl1YOll'
I > 2 . 3 _ 0.2 ~
:5 " '6
1.025
--...8 . 2 ....... 0 . 9
T O MAZATZAL ____ ~38~9~.~0~~I-~' 1_< ~5~·i9~-~1 52.1 _ ...< > 0 . 6 - - - - - - ,
STRAlmERP.Y ~ 4SkV
1. 02
t t .... '" .... '" co '" '"' T O
PREACKtP.
CAlfYOll'
@ I - 9.9
4.8 - T OIlT O - - - - - -If--,--;~-I
-->- 0 . 0 0 . 0 - 1.042
I
KAZ ATZAL
41.3 _ 3.6 _
33 . 1 -"" j 5 .5_
1.046
~4S :hV ,. Ih.018
'"' '" "' ... ... '" "'TO
purnACLE
"UK
"'-0 . 1
" I~~~~~~>-~ = ~:~ C:AP 1~9 . 6 <. -0 . 0 => -0 . 0 lu b1
1.083 - 2.8
I n
~ " -- 10 . 2 ...... 10 . 3 v~ <, If_7''''''2-'-. ~1-"' .. "'. -7-->-1 - 3 . 1
- 0 . 0 III b2 -2 . 9
1.095
B8
1.041
AP
![Page 119: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/119.jpg)
APPENDIXC
2013 Stability Plots
![Page 120: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/120.jpg)
Table of Contents Simulatiou Page
Transmission Element Outages From Bus (Fault Location} To Bus kV
ABEL BROWNING 500 1 ABEL DINOSAUR 230 2 ABEL PINALC 500 3 ABEL RANDOLPH 230 4 ABEL RS-24 230 5 ABEL SANTAN 230 6
AGUAFRIA ALEXANDR 230 7 AGUAFRIA ELSOL 230 8 AGUAFRIA GLENDALE 230 9 AGUAFRIA GLENDALW 230 10 AGUAFRIA WESTWNGW 230 11 AGUAFRIA WHITETNK 230 12 ALEXANDR AGUAFRIA 230 13 ALEXANDR DEERVALY 230 14 ANDERSON KYR-NEW 230 15 ANDERSON ORME 230 16 ARLINTON HASSYAMP 500 17
AVERY RACEWAY 230 18 AVERY TS6 230 19
BRANDOW KYRENE 230 20 BRANDOW PAPAGOBT 230 21 BRANDOW PINPKSRP 230 22 BRANDOW PINPKSRP 230 23 BRANDOW WARD 230 24 BRANDOW WARD 230 25 BROWNING ABEL 500 26 BROWNING DINOSAUR 230 27 BROWNING KYRENE 500 28 BROWNING RANDOLPH 230 29 BROWNING SANTAN 230 30 BROWNING SILVERKG 500 31 BUCKEYE2 BUCKEYE 230 32 BUCKEYE2 EAGLEYE 230 33 BUCKEYE2 LIBERTY 230 34 BUCKEYE BUCKEYE2 230 35 BUCKEYE LIBERTY 230 36 CACTUS OCOTILLO 230 37 CACTUS PPAPSN 230 38
CASAGRND TESTTRAK 230 39 CASGRAPS DBG 230 40 CASGRAPS MILLIGAN 230 41 CHOLLA CORONADO 500 42 CHOLLA FOUR CORN 345 43 CHOLLA FOUR CORN 345 44 CHOLLA LEUPP 230 45
![Page 121: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/121.jpg)
Simulation Page
From Bus {Fault Locationl To Bus kV CROLLA PNPKAPS 345 46 CROLLA PRECHCYN 345 47 CROLLA SAGUARO 500 48 CROLLA SGRLF 500 49
COCONINO LEUPP 230 50 COCONINO VERDES 230 51 COOLIDGE SPKIDLTP 230 52 COOLIDGE SUN ARIZ 230 53 COOLIDGE SUN ARIZ 230 54 CORBELL KYRENE 230 55 CORBELL SANTAN 230 56
CORONADO CROLLA 500 57 CORONADO SGRLF 500 58 CORONADO SILVERKG 500 59 CORONADO SPRINGR 345 60
CRYSTAL NAVAJO 500 61 CTRYCLUB GRNDTRML 230 62 CTRYCLUB LlNCSTRT 230 63 CTRYCLUB MEADOWBK 230 64
DBG CASGRAPS 230 65 DBG PINALC 203 66 DBG SNTAROSA 230 67
DEERVALY ALEXANDR 230 68 DEERVALY PINPKSRP 230 69 DEERVALY WESTWNGE 230 70
DEVERS HARQUARA 500 71 DEVERS PALOVRDE 500 72
DINOSAUR ABEL 230 73 DINOSAUR BROWNING 230 74
DUGAS MORGAN 500 75 DUGAS NAVAJO 500 76
EAGLEYE BUCKEYE2 230 77 EAGLEYE PARKER 230 78
ELSOL AGUAFRIA 230 79 ELSOL SURPRISE 230 80 ELSOL WESTWNGE 230 81 ELSOL WRTNKAPS 230 82
FLAGSTAF GLENCANY 345 83 FLAGSTAF GLENCANY 345 84 FLAGSTAF PINPKBRB 345 85 FLAGSTAF PINPKBRB 345 86 FOUR CORN CROLLA 345 87 FOUR CORN CROLLA 345 88 FOURCORN FCW 500 89 FOUR CORN MOENKOPI 500 90
![Page 122: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/122.jpg)
Simulation Page
From Bus (Fault Location) To Bus kV GAVILNPK GAVLINWA 230 91 GAVLINWA GAVILNPK 230 92 GAVLINWA PINPK 230 93 GAVLINWA PRSCOTWA 230 94 GILARIVR JOJOBA 230 95 GILARIVR JOJOBA 500 96 GILARIVR JOJOBA 500 97
GILA NGL-E 230 98 GILA NGL-W 230 99 GILA SLRC 230 100 GILA TS8 230 101
GLENCANY FLAGSTAF 345 102 GLENCANY FLAGSTAF 345 103 GLENDALE AGUAFRIA 230 104 GLENDALE GLENDALW 230 105 GLENDALE GRNDTRML 230 106 GLENDALW AGUAFRIA 230 107 GLENDALW GLENDALE 230 108 GOLDFELD SILVERKG 230 109 GOLDFELD THUNDRST 230 110 GOLDFELD THUNDRST 230 111 GRNDTRML CTRYCLUB 230 112 GRNDTRML GLENDALE 230 113 HARQUAHA DELANY 500 114 HARQUAHA DEVERS 500 115 HARQUAHA HASSYAMP 500 116 HASSYAMP ARLINTON 500 117 HASSYAMP DELANY 500 118 HASSYAMP HARQUAHA 500 119 HASSYAMP JOJOBA 500 120 HASSYAMP MESQUITE 500 121 HASSYAMP N.GILA 500 122 HASSYAMP N.GILA 500 123 HASSYAMP PALOVRDE 500 124 HASSYAMP PALOVRDE 500 125 HASSYAMP PALOVRDE 500 126 HASSYAMP PINALW 500 127 HASSYAMP REDHAWK 500 128 HASSYAMP REDHAWK 500 129 HASSYTAP LIBERTY 230 130 HASSY AZ SNVLY 230 131 JOJOBA GILARIVR 230 132 JOJOBA GILARIVR 500 133 JOJOBA GILARIVR 500 134 JOJOBA HASSYAMP 500 135
![Page 123: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/123.jpg)
Simulation Page
From Bus (Fault Locationl To Bus kV JOJOBA KYRENE 500 136 JOJOBA TS4 230 137 KNOX KYR-NEW 230 138 KNOX SNTAROSA 230 139
KYR-NEW ANDERSON 230 140 KYR-NEW KNOX 230 141 KYR-NEW KYRENE 230 142 KYR-NEW OCOTILLO 230 143 KYR-NEW PAPAGOBT 230 144 KYRENE BRANDOW 230 145 KYRENE BROWNING 500 146 KYRENE CORBELL 230 147 KYRENE JOJOBA 500 148 KYRENE KYR-NEW 230 149 KYRENE SCHRADER 230 150 LEUPP CHOLLA 230 151 LEUPP COCONINO 230 152
LIBERTY BUCKEYE2 230 153 LIBERTY BUCKEYE 230 154 LIBERTY HASSYTAP 230 155 LIBERTY LONE BUT 230 156 LIBERTY PEACOCK 345 157 LIBERTY PHXWAPA 230 158 LIBERTY RVDD 230 159 LIBERTY TS4 230 160 LIBERTY WESTWNGW 230 161
LINCSTRT CTRYCLUB 230 162 LINCSTRT OCOTILLO 230 163 LINCSTRT WPHXAPSN 230 164 LONEPEAK PPAPSE 230 165 LONEPEAK REACH 230 166 LONEPEAK SUNYSLOP 230 167 LONE BUT LIBERTY 230 168 LONE BUT PHXWAPA 230 169 LONE BUT SUN ARIZ 230 170 LONE BUT TESTTRAK 230 171
MARKETPL MOENKOPI 500 172 MAZATZAL PNPKAPS 345 173 MAZATZAL PRECHCYN 345 174 MEADOWBK CTRYCLUB 230 175 MEADOWBK SUNYSLOP 230 176 MESQUITE HASSYAMP 500 177 MILLIGAN CASGRAPS 230 178 MILLIGAN TS12 230 179 MOENKOPI ELDORDO 500 180 MOENKOPI FOUR CORN 500 181
![Page 124: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/124.jpg)
Simulation Page
From Bus !Fault Location) To Bus kV MOENKOPI MARKETPL 500 182 MOENKOPI NAVAJO 500 183 MOENKOPI RME 500 184 MOENKOPI YAVAPAI 500 185
MORGAN DUGAS 500 186 MORGAN PNPKAPS 500 187 MORGAN SNVLY 500 188 MORGAN WEST WING 500 189
N.GILA HASSYAMP 500 190 N.GILA HASSYAMP 500 191
N.WADDEL RACEWYWA 230 192 NAVAJO CRYSTAL 500 193 NAVAJO DUGAS 500 194 NAVAJO MOENKOPI 500 195 NAVAJO RME 500 196
OCOTILLO CACTUS 230 197 OCOTILLO KYR-NEW 230 198 OCOTILLO LINCSTRT 230 199 OCOTILLO PPAPSN 230 200
ORME ANDERSON 230 201 ORME ANDERSON 230 202 ORME RUDD 230 203 ORME RUDD 230 204
PALOVRDE DEVERS 500 205 PALOVRDE HASSYAMP 500 206 PALOVRDE HASSYAMP 500 207 PALOVRDE HASSYAMP 500 208 PALOVRDE RUDD 500 209 PALOVRDE WESTWING 500 210 PALOVRDE WESTWING 500 211 PAPAGOBT BRANDOW 230 212 PAPAGOBT KYR-NEW 230 213 PAPAGOBT PINPKSRP 230 214 PERKINPS WESTWING 500 215 PERKINS MEAD 500 216
PHXWAPA LIBERTY 230 217 PHXWAPA LONE BUT 230 218 PINALWES SOUTH 345 219 PINALWES WESTWING 345 220
PINALC ABEL 500 221 PINALC BOWIE 500 222 PINALC DBG 230 223 PINALC RANDOLPH 230 224 PINALC SNTAROSA 500 225 PINALC SUN ARIZ 230 226 PINALC TORTOLIT 500 227
![Page 125: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/125.jpg)
Simulation Page
From Bus {Fault Locationl To Bus kV PINALW HASSYAMP 500 228 PINALW SNTAROSA 500 229
PINPKBRB FLAGSTAF 345 230 PINPKBRB FLAGSTAF 345 231 PINPKSRP BRANDOW 230 232 PINPKSRP BRANDOW 230 233 PINPKSRP DEERVALY 230 234 PINPKSRP PAPAGOBT 230 235 PINPKSRP PINPK 230 236 PINPKSRP PINPK 230 237 PINPKSRP PPAPSN 230 238 PINPKSRP PPAPSN 230 239
PINPK GAVLINWA 230 240 PINPK PINPKSRP 230 241 PINPK PINPKSRP 230 242 PINPK PPAPSW 230 243 PINPK ROGSWAPA 230 244 PINPK ROGSWAPA 230 245 PINPK WESTWNGW 230 246
PLMVLY RUDD 230 247 PLMVLY TS2 230 248 PLMVLY TS4 230 249 PNPKAPS CHOLLA 345 250 PNPKAPS MAZATZAL 345 251 PNPKAPS MORGAN 500 252 PPAPSC PPAPSE 230 253 PPAPS C PPAPSW 230 254 PPAPS C REACH 230 255 PPAPSE LONEPEAK 230 256 PPAPSE PPAPSC 230 257 PPAPSE PPAPSN 230 258 PPAPSN CACTUS 230 259 PPAPSN OCOTILLO 230 260 PPAPSN PINPKSRP 230 261 PPAPSN PINPKSRP 230 262 PPAPSN PPAPSE 230 263 PPAPSW PINPK 230 264 PPAPSW PPAPS C 230 265 PPAPSW TS6 230 266
PRECHCYN CHOLLA 345 267 PRECHCYN MAZATZAL 345 268 PRESCOTT PRSCOTWA 230 269 PRESCOTT WILOWLKW 230 270 PRSCOTWA GAVLINWA 230 271 PRSCOTWA PRESCOTT 230 272 PRSCOTWA RNDVLYTP 230 273
![Page 126: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/126.jpg)
Simulation Page
From Bus {Fault Location) To Bus kV RACEWAY AVERY 230 274 RACEWAY RACEWYWA 230 275 RACEWAY WESTWNGE 230 276
RACEWYWA N.WADDEL 230 277 RACEWYWA RACEWAY 230 278 RACEWYWA WESTWNGE 230 279 RANDOLPH ABEL 230 280 RANDOLPH BROWNING 230 281 RANDOLPH PINALC 230 282
REACH LONEPEAK 230 283 REACH PPAPS C 230 284
REDHAWK HASSYAMP 500 285 REDHAWK HASSYAMP 500 286
RME MOENKOPI 500 287 RME NAVAJO 500 288
RNDVLYTP PEACOCK 230 289 RNDVLYTP PRSCOTWA 230 290 RNDVLYTP ROUNDVLY 230 291
ROGERS ROGSWAPA 230 292 ROGERS ROGSWAPA 230 293 ROGERS THUNDRST 230 294
ROGSWAPA PINPK 230 295 ROGSWAPA PINPK 230 296 ROGSWAPA ROGERS 230 297 ROGSWAPA ROGERS 230 298 ROGSWAPA SPKHILTP 230 299
RS-24 ABEL 230 300 RS·24 ABEL 230 301 RS·24 SANTAN 230 302 RS·24 SCHRADER 230 303 RUDD LIBERTY 230 304 RUDD ORME 230 305 RUDD ORME 230 306 RUDD PALOVRDE 500 307 RUDD PLMVLY 230 308 RUDD WHITETNK 230 309 RUDD WHTNKAPS 230 310 RUDD WPHXAPSS 230 311
SAGUARO CHOLLA 500 312 SAGUARO TATMOMLI 230 313 SAGUARO TORTOLIT 500 314 SAGUARO TORTOLIT 500 315 SAGUARO TS12 230 316 SANTAN ABEL 230 317 SANTAN BROWNING 230 318 SANTAN CORBELL 230 319
![Page 127: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/127.jpg)
Simulatiou Page
From Bus (Fault Location) To Bus kV SANTAN RS-24 230 320 SANTAN SCHRADER 230 321 SANTAN THUNDRST 230 322
SCHRADER KYRENE 230 323 SCHRADER RS-24 230 324 SCHRADER SANTAN 230 325
SGRLF CHOLLA 500 326 SGRLF CORONADO 500 327
SILVERKG BROWNING 500 328 SILVERKG CORONADO 500 329 SILVERKG GOLDFELD 230 330
SLRC GILA 230 331 SLRC TS8 230 332
SNTAROSA DBG 230 333 SNTAROSA KNOX 230 334 SNTAROSA PINALC 500 335 SNTAROSA PINALW 500 336 SNTAROSA TATMOMLI 230 337 SNTAROSA TESTTRAK 230 338
SOUTH WESTWING 345 339 SPKIDLTP COOLIDGE 230 340 SPKIDLTP ROGSWAPA 230 341 SUNYSLOP LONEPEAK 230 342 SUNYSLOP MEADOWBK 230 343 SUN ARIZ COOLIDGE 230 344 SUN ARIZ COOLIDGE 230 345 SUN ARIZ LONE BUT 230 346 SUN ARIZ PINALC 230 347 SURPRISE ELSOL 230 348 SURPRISE WESTWNGW 230 349
TATMOMLI SAGUARO 230 350 TATMOMLI SNTAROSA 230 351 TESTTRAK CASAGRND 230 352 TESTTRAK LONE BUT 230 353 TESTTRAK SNTAROSA 230 354 THUNDRST GOLDFELD 230 355 THUNDRST GOLDFELD 230 356 THUNDRST ROGERS 230 357 THUNDRST SANTAN 230 358
TS12 MILLIGAN 230 359 TS12 SAGUARO 230 360 TS4 JOJOBA 230 361 TS4 LIBERTY 230 362 TS4 PLMVLY 230 363 TS6 AVERY 230 364 TS6 PPAPSW 230 365
![Page 128: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/128.jpg)
Simulation Page
From Bus (Fault Location) To Bus kV TS8 GILA 230 366 TS8 SLRC 230 367
VERDEN VERDES 230 368 VERDEN YAVAPAI 230 369 VERDES COCONINO 230 370 VERDES VERDEN 230 371
WARD BRANDOW 230 372 WARD BRANDOW 230 373
WESTWING MORGAN 500 374 WESTWING PALOVRDE 500 375 WESTWING PALOVRDE 500 376 WESTWING PERKINPS 500 377 WESTWING PINALWES 345 378 WESTWING SOUTH 345 379 WESTWING YAVAPAI 500 380 WESTWNGE DEERVALY 230 381 WESTWNGE ELSOL 230 382 WESTWNGE RACEWAY 230 383 WESTWNGE RACEWYWA 230 384 WESTWNGE WESTWNGW 230 385 WESTWNGW AGUAFRIA 230 386 WESTWNGW LIBERTY 230 387 WESTWNGW PINPK 230 388 WESTWNGW SURPRISE 230 389 WESTWNGW WESTWNGE 230 390 WHITETNK AGUAFRIA 230 391 WHITETNK RUDD 230 392 WHTNKAPS ELSOL 230 393 WHTNKAPS RUDD 230 394 WHTNKAPS WPHXAPSN 230 395 WILOWLKE WILOWLKW 230 396 WILOWLKE YAVAPAI 230 397 WILOWLKW PRESCOTT 230 398 WILOWLKW WILOWLKE 230 399 WPHXAPSN LINCSTRT 230 400 WPHXAPSN WHTNKAPS 230 401 WPHXAPSN WPHXAPSS 230 402 WPHXAPSS RUDD 230 403 WPHXAPSS WPHXAPSN 230 404 YAVAPAI MOENKOPI 500 405 YAVAPAI VERDEN 230 406 YAVAPAI WESTWING 500 407 YAVAPAI WILOWLKE 230 408
![Page 129: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/129.jpg)
Simulation Page
Transformer Outages {Fault on High Sidel High Side Low Side Transformer
Substation Voltage Voltage # BROWNING 500 230 1 409 BROWNING 500 230 2 410
CHOLLA 345 230 1 411 CHOLLA 345 230 2 412 CHOLLA 500 345 1 413 CHOLLA 500 345 2 414
CORONADO 500 345 1 415 CORONADO 500 345 2 416 FOUR CORN 345 230 1 417 FOUR CORN 500 345 1 418 GILARIVR 500 230 1 419
GLENCANY 345 230 1 420 KYRENE 500 230 6 421 KYRENE 500 230 7 422 KYRENE 500 230 8 423 LIBERTY 345 230 1 424
LIBTYPHS 230 230 1 425 MORGAN 500 230 1 426 PINALC 500 230 1 427 PINALC 500 230 2 428 PINALW 500 345 1 429
PINPKBRB 345 230 1 430 PINPKBRB 345 230 1 431 PINPKBRB 345 230 3 432 PNPKAPS 345 230 1 433 PNPKAPS 345 230 2 434 PNPKAPS 345 230 3 435 PNPKAPS 500 230 E 436 PNPKAPS 500 230 N 437 PNPKAPS 500 230 W 438
RUDD 500 230 1 439 RUDD 500 230 2 440 RUDD 500 230 3 441 RUDD 500 230 4 442
SILVERKG 500 230 1 443 WESTWING 500 230 1 444 WESTWING 500 230 2 445 WESTWING 500 345 1 446
YAVAPAI 500 230 2 447
![Page 130: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/130.jpg)
Simulation
Generator Outages (Fault at Generator Terminals) Cholla 4 Four Corners 5CC Gila River STl Navajo 2 Ocotillo ST2 Palo Verde I Redhawk CT2 & STl Saguaro CT3 Sundance G3 & G4 West Phoenix North 5CT2 West Phoenix South CCI Yucca 1
448 449 450 451 452 453 454 455 456 457 458 459
![Page 131: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/131.jpg)
Plots provided upon request
![Page 132: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/132.jpg)
APPENDIXD
2019 Stability Plots
![Page 133: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/133.jpg)
Table of Contents Simulation Page
Transmission Element Outages From Bus (Fault Locationl To Bus kV
ABEL SNTAROSA 500 1 ADAMS BOOTIDLL 115 2
AGUAFRIA ALEXANDR 230 3 AGUAFRIA ELSOL 230 4 AGUAFRIA GLENDALW 230 5 AGUAFRIA WESTWNGW 230 6 AGUAFRIA WESTWNGW 230 7 AGUAFRIA WHITETNK 230 8 ALEXANDR AGUAFRIA 230 9 ALEXANDR ALEXNDR 230 10 ALEXANDR DEERVALY 230 11 ALEXNDR ALEXANDR 230 12
ANDERSON KYR-NEW 230 13 ANDERSON ORME 230 14 ANDERSON ORME 230 15
APACHE SNMANUEL 115 16 ARLINTON HASSYAMP 500 17
AVERY PNPKAPS 230 18 AVERY RACEWAY 230 19 AVERY TS6 230 20
BRANDOW KYRENE 230 21 BRANDOW PAPAGOBT 230 22 BRANDOW PINPKSRP 230 23 BRANDOW PINPKSRP 230 24 BRANDOW WARD 230 25 BRANDOW WARD 230 26 BROWNING ABEL 500 27 BROWNING DINOSAUR 230 28 BROWNING KYRENE 500 29 BROWNING SANTAN 230 30 BROWNING SILVERKG 500 31 BROWNING SNTAROSA 500 32 BUCKEYE LIBERTY 230 33 BUTERFLD APACHE 230 34
CACTUS OCOTILLO 230 35 CACTUS PNPKAPS 230 36
CASAGRND TESTTRAK 230 37 CASGRAPS DBG 230 38 CASGRAPS MILLIGAN 230 39 CASGRAPS SAGUARO 230 40
CHOLLA CORONADO 500 41 CHOLLA FOUR CORN 345 42 CHOLLA FOURCORN 345 43 CHOLLA LEUPP 230 44 CHOLLA PNPKAPS 345 45
![Page 134: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/134.jpg)
Simulation Page
From Bus (Fault Location) To Bus kV CHOLLA PRECHCYN 345 46 CHOLLA SAGUARO 500 47 CHOLLA SGRLF 500 48 CHOLLA SILVERKG 500 49
COCONINO LEUPP 230 50 COCONINO VERDES 230 51 COOLIDGE SPKHILTP 230 52 COOLIDGE SUN ARIZ 230 53 CORBELL KYRENE 230 54 CORBELL SANTAN 230 55
CORONADO CHOLLA 500 56 CORONADO SGRLF 500 57 CORONADO SILVERKG 500 58 CORONADO SPRINGR 345 59
CRYSTAL NAVAJO 500 60 CTRYCLUB GRNDTRML 230 61 CTRYCLUB LINCSTRT 230 62 CTRYCLUB MEADOWBK 230 63
DBG CASGRAPS 230 64 DBG SNTAROSA 230 65
DEERVALY ALEXANDR 230 66 DEERVALY PINPKSRP 230 67 DEERVALY WESTWNGE 230 68
DELANY SNVLY 500 69 DEVERS HARQUAHA 500 70 DEVERS PALOVRDE 500 71
DINOSAUR BROWNING 230 72 DUGAS NAVAJO 500 73 DUGAS RACEWAY 500 74
EAGLEYE LIBERTY 230 75 EAGLEYE PARKER 230 76 ELDORDO MOENKOPI 500 77
ELSOL AGUAFRIA 230 78 ELSOL SURPRISE 230 79 ELSOL WESTWNGW 230 80 ELSOL WHTNKAPS 230 81
FLAGSTAF GLENCANY 345 82 FLAGSTAF GLENCANY 345 83 FLAGSTAF PINPKBRB 345 84 FLAGSTAF PINPKBRB 345 85
FOUR CORN CHOLLA 345 86 FOUR CORN CHOLLA 345 87 FOUR CORN MOENKOPI 500 88 GAVILNPK GAVLINWA 230 89 GAVLINWA GAVILNPK 230 90
![Page 135: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/135.jpg)
Simulation Page
From Bus (Fault Locationl To Bus kV GAVLINWA PINPK 230 91 GAVLINWA PRSCOTWA 230 92 GILABEND GILARIVR 230 93 GILARIVR GILABEND 230 94 GILARIVR JOJOBA 230 95 GILARIVR JOJOBA 500 96 GILARIVR JOJOBA 500 97
GLENCANY FLAGSTAF 345 98 GLENCANY FLAGSTAF 345 99 GLENDALE GLENDALW 230 100 GLENDALE GRNDTRML 230 101 GLENDALW AGUAFRIA 230 102 GLENDALW GLENDALE 230 103 GOLDFELD SILVERKG 230 104 GOLDFELD THUNDRST 230 105 GOLDFELD THUNDRST 230 106 GRNDTRML CTRYCLUB 230 107 GRNDTRML GLENDALE 230 108 HARQUAHA DEVERS 500 109 HARQUAHA HASSYAMP 500 110 HASSYAMP ARLINTON 500 111 HASSYAMP HARQUAHA 500 112 HASSYAMP JOJOBA 500 113 HASSYAMP KYRENE 500 114 HASSYAMP MESQUITE 500 115 HASSYAMP N.GILA 500 116 HASSYAMP N.GILA 500 117 HASSYAMP PALOVRDE 500 118 HASSYAMP PALOVRDE 500 119 HASSYAMP PALOVRDE 500 120 HASSYAMP PINALW 500 121 HASSYAMP REDHAWK 500 122
JOJOBA GILARIVR 230 123 JOJOBA GILARIVR 500 124 JOJOBA GILARIVR 500 125 JOJOBA HASSYAMP 500 126 JOJOBA KYRENE 500 127 JOJOBA TS4 230 128 KNOX KYR-NEW 230 129 KNOX SNTAROSA 230 130
KYRENE BRANDOW 230 131 KYRENE BROWNING 500 132 KYRENE CORBELL 230 133 KYRENE HASSYAMP 500 134 KYRENE JOJOBA 500 135
![Page 136: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/136.jpg)
Simulation Page
From Bus (Fault Locatioul To Bus kV KYRENE KYR-NEW 230 136 KYRENE SCHRADER 230 137
KYR-NEW ANDERSON 230 138 KYR-NEW KNOX 230 139 KYR-NEW KYRENE 230 140 KYR-NEW OCOTILLO 230 141 KYR-NEW PAPAGOBT 230 142
LEUPP CHOLLA 230 143 LEUPP COCONINO 230 144
LIBERTY BUCKEYE 230 145 LIBERTY EAGLEYE 230 146 LIBERTY HASSYTAP 230 147 LIBERTY LONE BUT 230 148 LIBERTY ORME 230 149 LIBERTY PEACOCK 345 150 LIBERTY PHXWAPA 230 151 LIBERTY RUDD 230 152 LIBERTY RUDD 230 153 LIBERTY TS4 230 154 LIBERTY WESTWNGW 230 155
LINCSTRT CTRYCLUB 230 156 LINCSTRT OCOTILLO 230 157 LINCSTRT WPHXAPSN 230 158
LONEPEAK PNPKAPS 230 159 LONEPEAK REACH 230 160 LONEPEAK SUNYSLOP 230 161 LONE BUT LIBERTY 230 162 LONE BUT PHXWAPA 230 163 LONE BUT SUN ARIZ 230 164 LONE BUT TESTTRAK 230 165
MAZATZAL PNPKAPS 345 166 MAZATZAL PRECHCYN 345 167
MEADOWBK CTRYCLUB 230 168 MEADOWBK SUNY SLOP 230 169
MEAD PEACOCK 345 170 MESQUITE HASSYAMP 500 171 MILLIGAN CASGRAPS 230 172 MILLIGAN SAGUARO 230 173 MOENKOPI ELDORDO 500 174 MOENKOPI FOUR CORN 500 175 MOENKOPI MARKETPL 500 176 MOENKOPI NAVAJO 500 177 MOENKOPI RME 500 178 MOENKOPI YAVAPAI 500 179
N.GILA HASSYAMP 500 180
![Page 137: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/137.jpg)
Simulation Page
From Bus (Fault Locationl To Bus kV N.GILA HASSYAMP 500 181
N.HAVASU PARKER 230 182 N.HAVASU TOPOCK 230 183 N.WADDEL RACEWYWA 230 184
NAVAJO CRYSTAL 500 185 NAVAJO DUGAS 500 186 NAVAJO MOENKOPI 500 187 NAVAJO RACEWAY 500 188 NAVAJO RME 500 189
OCOTILLO CACTUS 230 190 OCOTILLO KYR-NEW 230 191 OCOTILLO LINCSTRT 230 192 OCOTILLO PNPKAPS 230 193
ORME ANDERSON 230 194 ORME ANDERSON 230 195 ORME LIBERTY 230 196 ORME RUDD 230 197 ORME RUDD 230 198
PALOVRDE DELANY 500 199 PALOVRDE DEVERS 500 200 PALOVRDE HASSYAMP 500 201 PALOVRDE HASSYAMP 500 202 PALOVRDE HASSYAMP 500 203 PALOVRDE RUDD 500 204 PALOVRDE SNVLY 500 205 PALOVRDE WESTWING 500 206 PALOVRDE WESTWING 500 207 PAPAGOBT BRANDOW 230 208 PAPAGOBT KYR-NEW 230 209 PAPAGOBT PINPKSRP 230 210 PEACOCK LIBERTY 345 211 PEACOCK MEAD 345 212 PHXWAPA LIBERTY 230 213 PINALWES SOUTH 345 214 PINALWES WESTWING 345 215
PINALS ABEL 500 216 PINALS SNTAROSA 500 217 PINALS TORTOLIT 500 218 PINALW HASSYAMP 500 219 PINALW SNTAROSA 500 220
PINPK GAVLINWA 230 221 PINPK PINPKSRP 230 222 PINPK PINPKSRP 230 223 PINPK PNPKAPS 230 224 PINPK ROGSWAPA 230 225
![Page 138: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/138.jpg)
Simulation Page
From Bus (Fault Location) To Bus kV PINPK ROGSWAPA 230 226 PINPK WESTWNGW 230 227
PINPKBRB FLAGSTAF 345 228 PINPKBRB FLAGSTAF 345 229 PINPKSRP BRANDOW 230 230 PINPKSRP BRANDOW 230 231 PINPKSRP DEERVALY 230 232 PINPKSRP PAPAGOBT 230 233 PINPKSRP PINPK 230 234 PINPKSRP PINPK 230 235 PINPKSRP PNPKAPS 230 236 PLMVLY RUDD 230 237 PLMVLY TS2 230 238 PLMVLY TS4 230 239 PNPKAPS AVERY 230 240 PNPKAPS CACTUS 230 241 PNPKAPS CHOLLA 345 242 PNPKAPS LONEPEAK 230 243 PNPKAPS MAZATZAL 345 244 PNPKAPS OCOTILLO 230 245 PNPKAPS PINPKSRP 230 246 PNPKAPS PINPKSRP 230 247 PNPKAPS PINPK 230 248 PNPKAPS PRECHCYN 345 249 PNPKAPS RACEWAY 500 250 PNPKAPS REACH 230 251 PNPKAPS TS6 230 252
PRECHCYN CHOLLA 345 253 PRECHCYN MAZATZAL 345 254 PRECHCYN PNPKAPS 345 255 PRESCOTT PRSCOTWA 230 256 PRESCOTT WILOWLKW 230 257 PRSCOTWA GAVLINWA 230 258 PRSCOTWA PRESCOTT 230 259 PRSCOTWA RNDVLYTP 230 260 RACEWAY AVERY 230 261 RACEWAY DUGAS 500 262 RACEWAY NAVAJO 500 263 RACEWAY PNPKAPS 500 264 RACEWAY RACEWYWA 230 265 RACEWAY SNVLY 500 266 RACEWAY WESTWING 500 267
RACEWYWA N.WADDEL 230 268 RACEWYWA RACEWAY 230 269 RACEWYWA WESTWNGE 230 270
![Page 139: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/139.jpg)
Simulation Page
From Bus {Fault Location) To Bus kV REACH LONEPEAK 230 271 REACH PNPKAPS 230 272
REDHAWK HASSYAMP 500 273 REDHAWK HASSYAMP 500 274
RME MOENKOPI 500 275 RME NAVAJO 500 276
ROGERS ROGSWAPA 230 277 ROGERS ROGSWAPA 230 278 ROGERS THUNDRST 230 279
ROGSWAPA PINPK 230 280 ROGSWAPA PINPK 230 281 ROGSWAPA ROGERS 230 282 ROGSWAPA ROGERS 230 283 ROGSWAPA SPKHlLTP 230 284
RUDD LIBERTY 230 285 RUDD LIBERTY 230 286 RUDD ORME 230 287 RUDD ORME 230 288 RUDD PALOVRDE 500 289 RUDD PLMVLY 230 290 RUDD WHITETNK 230 291 RUDD WHTNKAPS 230 292 RUDD WPHXAPSS 230 293
SAGUARO CASGRAPS 230 294 SAGUARO CHOLLA 500 295 SAGUARO MILLIGAN 230 296 SAGUARO SILVERKG 500 297 SAGUARO TATMOMLI 230 298 SAGUARO TORTLIT2 500 299 SAGUARO TORTOLIT 500 300 SAGUARO TORTOLIT 500 301 SANTAN BROWNING 230 302 SANTAN CORBELL 230 303 SANTAN SCHRADER 230 304 SANTAN THUNDRST 230 305 SANRAF BUTERFLD 230 306
SCHRADER KYRENE 230 307 SCHRADER SANTAN 230 308
SGRLF CHOLLA 500 309 SGRLF CORONADO 500 310
SILVERKG BROWNING 500 311 SILVERKG CORONADO 500 312 SILVERKG GOLDFELD 230 313 SILVERKG SAGUARO 500 314 SNTAROSA ABEL 500 315
![Page 140: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/140.jpg)
Simulation Page
From Bus (Fault Locationl To Bus kV SNTAROSA BROWNING 500 316 SNTAROSA DBG 230 317 SNTAROSA KNOX 230 318 SNTAROSA PINALS 500 319 SNTAROSA PINALW 500 320 SNTAROSA TATMOMLI 230 321 SNTAROSA TESTTRAK 230 322
SNVLY DELANY 500 323 SNVLY PALOVRDE 500 324 SNVLY RACEWAY 500 325 SNVLY TRLBY 230 326
SUNYSLOP LONEPEAK 230 327 SUNYSLOP MEADOWBK 230 328 SUN ARIZ COOLIDGE 230 329 SUN ARIZ COOLIDGE 230 330 SUN ARIZ LONE BUT 230 331 SURPRISE ELSOL 230 332 SURPRISE WESTWNGW 230 333
TATMOMLI SAGUARO 230 334 TATMOMLI SNTAROSA 230 335 TESTTRAK CASAGRND 230 336 TESTTRAK LONE BUT 230 337 TESTTRAK SNTAROSA 230 338 THUNDRST GOLDFELD 230 339 THUNDRST GOLDFELD 230 340 THUNDRST ROGERS 230 341 THUNDRST SANTAN 230 342 TORTLIT2 SAGUARO 500 343 TORTOLIT PINALS 500 344 TORTOLIT SAGUARO 500 345 TORTOLIT SAGUARO 500 346
TRLBY SNVLY 230 347 TRLBY TS2 230 348
TS2 PLMVLY 230 349 TS2 TRLBY 230 350 TS4 JOJOBA 230 351 TS4 LIBERTY 230 352 TS4 PLMVLY 230 353 TS6 AVERY 230 354 TS6 PNPKAPS 230 355
WARD BRANDOW 230 356 WARD BRANDOW 230 357
WESTMESA FOUR CORN 345 358 WESTWING MEAD 500 359 WESTWING PALOVRDE 500 360
![Page 141: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/141.jpg)
Simulation Page
From Bus (Fault Location) To Bus kV WESTWING PALOVRDE 500 361 WESTWING PINALWES 345 362 WESTWING RACEWAY 500 363 WESTWING SOUTH 345 364 WESTWING YAVAPAI 500 365 WESTWNGE DEERVALY 230 366 WESTWNGE RACEWYWA 230 367 WESTWNGE WESTWNGW 230 368 WESTWNGW AGUAFRIA 230 369 WESTWNGW AGUAFRIA 230 370 WESTWNGW ELSOL 230 371 WESTWNGW LIBERTY 230 372 WESTWNGW PINPK 230 373 WESTWNGW SURPRISE 230 374 WESTWNGW WESTWNGE 230 375 WHITETNK AGUAFRIA 230 376 WHITETNK RUDD 230 377 WHTNKAPS ELSOL 230 378 WHTNKAPS RUDD 230 379 WHTNKAPS WPHXAPSN 230 380 WILOWLKE WILOWLKW 230 381 WILOWLKE YAVAPAI 230 382 WILOWLKW PRESCOTT 230 383 WILOWLKW WILOWLKE 230 384 WPHXAPSN LINCSTRT 230 385 WPHXAPSN WHTNKAPS 230 386 WPHXAPSN WPHXAPSS 230 387 WPHXAPSS RUDD 230 388 WPHXAPSS WPHXAPSN 230 389
YAVAPAI MOENKOPI 500 390 YAVAPAI WESTWING 500 391 YAVAPAI WILOWLKE 230 392
![Page 142: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/142.jpg)
Simulation Page
Transformer Outages (Fault on High Sidel High Side Low Side Transformer
Substation Voltage Voltage # BROWNING 500 230 1 393
CHOLLA 345 230 1 394 CHOLLA 345 230 2 395 CHOLLA 500 345 1 396 CHOLLA 500 345 2 397
CORONADO 500 345 I 398 CORONADO 500 345 2 399 FOUR CORN 345 230 1 400 FOUR CORN 345 230 2 401 FOURCORN 500 345 1 402 GILARIVR 500 230 1 403 GOLDFELD 230 1I5 1 404
KYRENE 500 230 6 405 KYRENE 500 230 7 406 KYRENE 500 230 8 407 LIBERTY 345 230 1 408
LIBTYPHS 230 230 I 409 PINALW 500 345 1 410
PINPKBRB 345 230 1 411 PINPKBRB 345 230 2 412 PINPKBRB 345 230 3 413 PNPKAPS 345 230 1 414 PNPKAPS 345 230 2 415 PNPKAPS 345 230 3 416 PNPKAPS 500 230 1 417 PNPKAPS 500 230 2 418 PNPKAPS 500 230 3 419
PRESCOTT 230 1I5 1 420 PRESCOTT 230 1I5 2 421 RACEWAY 500 230 1 422 RACEWAY 500 230 2 423
RUDD 500 230 I 424 RUDD 500 230 2 425 RUDD 500 230 3 426 RUDD 500 230 4 427
SAGUARO 230 1I5 1 428
![Page 143: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/143.jpg)
Simulation Page
Transformer Outages (Fault on High Sidel High Side Low Side Transformer
Substation Voltage Voltage # SAGUARO 500 115 1 429 SILVERKG 230 115 1 430 SILVERKG 500 230 1 431 SNTAROSA 500 230 1 432
SNVLY 500 230 1 433 WESTWING 500 230 1 434 WESTWING 500 230 2 435 WESTWING 500 230 3 436 WESTWING 500 345 1 437
YAVAPAI 500 230 1 438 YAVAPAI 500 230 2 439
![Page 144: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/144.jpg)
Simulation
Generator Outages (Fault at Generator Terminals) Cholla 4 Four Corners 5CC Gila River STI Navajo 2 Ocotillo ST2 Palo Verde 1 Redhawk CT2 & STl Saguaro CT3 Sundance G3 & G4 West Phoenix North 5CT2 West Phoenix South CC 1 Yucca 1
440 441 442 443 444 445 446 447 448 449 450 451
![Page 145: 2010-2019El Sol-Westwing 230kV Line (To Be Determined) ..... 34 Palo Verde - Saguaro 500kV Line (To Be Determined) ..... 35 * Projects are included in APS's response to Commission](https://reader035.fdocuments.us/reader035/viewer/2022071020/5fd3d2e300977462de51b8a5/html5/thumbnails/145.jpg)
Plots provided upon request