2-27-13 The Drive Toward Data Driven Estimating Update …€¦ · The Drive Toward “data...
Transcript of 2-27-13 The Drive Toward Data Driven Estimating Update …€¦ · The Drive Toward “data...
1
The Drive Toward
“data driven” Estimating
Boeing/Lockheed Martin/Northrop GrummanOriginal March 2011
Updated February 2013
BOE Training Material
2
Background/Objectives
Background: There is a significant industry effort to increase the quality of contractor estimating processes. The industry has applied the term “data driven” estimating to this new method of developing and documenting our basis of estimates(BOEs). “data driven” Estimating methods have certain characteristics that are starting to emerge as standards within our industry.
Objectives:— What is driving our industry toward the use of “data driven” estimating
methods and why is this a business imperative
— Review the current primary estimating methods
— Be able to identify the characteristics of good “data driven” estimating processes and how they are represented in our BOEs
— What are objective-scope-measures and how are they used in a ”data driven” estimate
— Provide examples of “data driven” versus non-data driven BOEs
3
“data driven” Estimating - Contents
BOE - Description
“data driven” Estimating - Definition
The Future – Fundamentals of data driven Estimating
Developing Relationships from History – The Cost Estimating Relationship (CER) Process
“data driven” Estimate Examples – We are the Customer
Summary
Backup Charts/Supplemental Resources
4
Purpose of a BOE
Documents and substantiates effort required to perform tasks — Documents basis and assumptions— Details understanding of requirements— Conveys credibility by clearly defining tasks and assumptions— Demonstrates that estimates are credible, defendable and realistic
(historical data)
Provides evidence that estimate is consistent with other proposal volumes
Time-phased resources consistent with IMP/IMS Allocates skill mix appropriate for task Aligns with Work Breakdown Structure (WBS), SOW, and other
product structures Meet customer funding, timing, and/or scheduling constraints
5
BOEs – The Components A BOE consists of the following main elements:
1. Work Element ID – WBS, SOW, Location, CLIN, NRE/Rec…2. Description of the products or services delivered and the tasks
to be performed3. Estimating method, rationale, assumptions, and computations
used to develop the estimate— Method of quoting
4. Relevant historical data and comparability of the historical data to the current program— Explanation of any adjustments made to historical cost or
programmatic data (i.e., use of modifiers)
5. Estimated labor resources to perform the defined tasks6. Expenditure profile (time-phasing) of labor resources7. Other elements as required by the cost proposal instructions
6
BOE Estimating Methods Labor estimates are developed using one or these typical
estimating methods— Judgment – based on subject matter expert (SME) experience with similar
efforts. — Level-of-Effort/Support - uses resource-based estimates that are often
based on a predetermined level of support for a given period of time — Analogy/Comparison Method – estimate based on historical frame of
reference from a similar effort with adjustments for programmatic or technical differences
— Standard Time Estimating - Labor Standards and Realization/ Performance Factors - time necessary to complete a defined element of work following a prescribed (recognized) technique or method.
— Unit Method – generally a simple ratio (not always statistically validated)— Follow-on Based On Actuals – extrapolation of actuals (CEAC, production)— Parametric Cost Models – use of calibrated, internally developed, or
commercially available cost models — Cost Estimating Relationships (CERs) - equations developed based on
historical, statistically correlated relationships
— Note: Material or Other Direct Costs may be estimated by data such as quotes or catalogs . See FAR for specific cost element and degree of competition requirements
7
Customer Expectations
Customers/DCAA/DCMA expect contractors to begin adopting improved estimating methods to support TINA-compliant proposals and other estimating products
Least Preferred
Judgment
Most Preferred
“Fact Based”Estimating Methods
Move To Fact Based ASAP
8
BOE Methodologies – Credibility Scale
Historical resource based estimates are easier to support than judgmental type estimates.
Customer Credibility LaborHigh Follow-on Projections
based on ActualsAnalogy/Comparison
CER’sParametric Estimates /
Cost ModelsStandards
Unit MethodsLevel Of Effort
Low Judgment
9
Customer Consequences – Poor Estimating
Failure to be responsive to customer estimating processes could be grounds for— Non-compliance with RFP or government regulations— Rejection of proposal and possibly defective pricing— Estimating System Inadequacy
Penalties for bad BOEs include:— Questioned costs— DCAA/Government Deficiency Report— Negotiation losses— Negative factor in competitive evaluations— Defective pricing and fraud prosecution— Suspension of bidding and debarment— Holdbacks
10
“data driven” BOEs – Basic Definition Fact Based Estimating: Estimating processes/BOEs that
provide the supporting information and rationale necessary for accurate, credible and traceable estimates
Information includes:— Use of defined estimating methods
— Historical data from past programs
— Use of objective scope measures and complexity factors where appropriate
Rationale addresses:— Complete description of the estimating approach
— Explanation of the applicability of the historical information
Estimating process must be documented, consistent and repeatable
11
Fact Based BOEs – The Fundamentals
1. Estimate develop using a defined and documentedestimating processes
2. Methods rely on scope measures (attributes) and complexity factors (parametrics) – when applicable
3. Complete estimate development process is explained and documented in the BOE — Professional judgments, modifiers/adjustment factors, and historical
context is adequately explained— Process is consistent and repeatable
4. Estimate relies on relevant historical data and context that is accessible and verifiable — Shows use of latest and most current relevant data— Supports all resource estimates with verifiable data
5. Estimating processes are monitored for learning and improvement as required to support future estimates
12
Objective Work-Scope Measures (OSM)
Scope Measures: estimating predictive measures – technical measures relating to the size of the effort (attributes)— Generally physical and technical measures— Sized at different product levels - system, subsystem, box, etc. — Example:
— Work Products: # drawings by type, sheet counts, # documents & sheet count, SLOC by category, # requirements, # reviews, # test & type, weight, quantities, etc.
Traits/Complexity Factors: characteristics that can improve the accuracy of relationships developed for the OSMs — Example:
— Scope Measures = Drawings— Traits: (numeric and descriptive): # Drawings, Type of Drawing; Drawing
Heritage; Item Next Higher Assembly/Element; Number of Sheets; # of Revisions
— Example: — Scope Measures = Source Lines of Code (SLOC)— Traits: Software Language; New SLOC; Modified SLOC; Reuse SLOC; Actual
Total Delivered SLOC, Deleted SLOC, Auto Generated Code, etc
13
Why Use Scope Measures and Traits in BOEs?
Scope Measures - help to scope the size of the effort to be estimated — Objective quantitative measures of scope to be performed — Directly correlate to (predictors) resource estimates for work products and
tasks — Understanding the size (scope) of the proposed effort is critical to
developing an accurate estimate (BOE) — The BOE author should explain the derivation, source, and application of
the scope measures in the BOE
Traits/Complexity Modifiers – address unique characteristics of the scope measures that can affect required effort to produce— Capture the effects of technical and programmatic differences between
historical programs and the current proposed effort.— The “produceability” can vary widely for any scope measure - traits can
be used to explain the differences— Sometimes requires judgment
14
Objective Scope Measures - Examples
Source Lines of Code (SLOC)
Function points
Computer Software Configuration Item (CSCI)
Number of drawings
Power requirements
Number/type of subsystems, subassemblies, components
Volume (Dimensions)
Weight
Number/type of reviews
Number of end items
Number/type of tools
Number of Contract Data Requirements Lists (CDRLs)
Number of Subcontract Data Requirements Lists (SDRLs)
Number of system requirements
Number of Interface Control Drawings ( ICDs)
Number of payloads
Number of program segments
Number of internal interfaces
Number of external interfaces
Number of risks
Number of architectural trades
Candidate Estimating Attributes
Software
Hardw
are
System
s Engine
ering
15
Traits/Complexity Factors - ExamplesDesign reuse
Performance factors
Complexity
Reuse and pedigree
New technology
Components/functional complexity
Schedule
Requirements maturity
Technology Readiness Level (TRL) requirements/maturity path
Multi‐functional analyses
Testing (qualification; prototype‐protoqualification; delta qualification; static; modal)
Assembly, Integration and Test (AI&T))
Training requirements
Mission profile and environments
Mission design (data rates, pointing stabilities, Technical Performance Measurements (TPMs))
Oversight and analyses of subcontracted elements
Risk
Program maturity/life cycle
Complexity
Schedule
Heritage
Required documentation
Estimating Modifier
Software
Hardw
are
System
s Engine
ering
16
Explaining Adjustment to a BOE
Provided below are some examples of adjustments that may be required to improve the accuracy of the estimate. The list is not meant to be totally inclusive of adjustments an estimator has available in their tool box.— Technical Complexity ~ Labor Estimate
— Improvement Curves ~ Labor Estimate
— Schedule adjustments ~ Labor Estimate
— Quote Decrement ~ Material Estimate
— Quantity Adjustment ~ Material Estimate
— Escalation ~ Material Estimate
— Exchange Rate ~ Material Estimate
In order to use an objective or subjective adjustment, an estimator must explain it thoroughly in the BOE.
17
Using Historical Data in a BOE
Use of Historical Data Must Address:— Source of data – generally from the organization’s certified
historical data repositories— Complete identification of the nature, source and details of
relevant historical data
Ensure compliance with A.C.T.T.R. by documenting the following: — Actual historical hours— Charge numbers included— Technical data used— Time frame of historical data— Repository or source of historical data
18
Developing a Relationship from Historical Data
The statistical analysis process used in the development of a cost estimating relationship (CER) is documented in numerous industry and statistical sources
The objective of the analysis is to validate that a significant statistical relationship exists for the CERs and to demonstrate that the CERs accurately predict effort or costs
CER Strengths
— Past performance reflective of future costs
— Lean and credible estimating method in preparing BOEs
— More scientific and objective than judgement
19
Processs Step:1. Identify Need2. Establish Estimate Structure3. Identification of Effort/Cost Drivers4. Selection of Equation Form5. Selection of Population6. Data Collection7. Data Normalization8. Generate the Cost Estimating Relationship (CER)9. Validate the Results10. Document
Developing a “data driven” Relationship (CER)
numeratordenominator
item to estimateknown item
poolbase
dependent variableindependent variable
20
Developing a “data driven” Relationship (CER)
Regression Analysis: Develop mathematical relationship to make inferences about a future probabilistic event based on a sample of historical data.
If relationship exist between two or more variables, such as weight and hours of effort/cost required, regression analysis is a powerful tool for the cost estimator/analyst.
Regression analysis consists of curve fitting and the analysis of the descriptive and inferential statistics that result from the fit of the data.
21
Developing a “data driven” Relationship (CER)
Y
X
Y
XPositive Linear Relationship Positive Increasing
Curve-linear Relationship
Y
X
Y
XNegative Linear Relationship
Y
XPositive Decreasing Curve-linear Relationship
Negative Increasing Curve-linear Relationship
xbby 10
xbby 10
baxy )1b(
baxy )1b0(
baxy )1b(
22
Preparation of the Historical Data (CER) Step 1: Select the dependent variable to be estimated (e.g. results =
hours, cost)
Step 2: Determine the auditable source of historical data (both cost and technical measures)
Step 3: Define the population(s), subpopulations, and sample(s) of data considering methods of collection (sites, programs, stratifications)
Step 4: Select logical and measurable independent variables and determine their auditable sources of data (SLOCs, Drawings, Pages, Hours)
Step 5: Extract the data and verify its accuracy and completeness using “tests of reasonableness”
Step 6: Prepare the data for use in EXCEL or a statistical tool to perform the regression analysis
Step 7: Test the resulting relationship for accuracy
23
Interpretation Decision Criteria of Statistical Results
Statistical Measure Purpose of Measure Target Value for Good Fit
Correlation Coefficient Measures the fit of the CER model. Gives a quick look at the percentage of the total variation that has been explained by the regression line.
R2 ≥ .80
.50 < R2 < .80
.50 ≤ R2
Coefficient of Variation Measures the target goal for predictability within one standard error (68% of the data). The C.V. is calculated at the mean of Y, allowing the comparison of one CER to another. Calculated from the Standard error which measures the dispersion of the data.
C.V. ≤ 50%
50% < C.V. < 100%
C.V. ≥ 100%
Usability Criterion Judges reliability or usefulness of the CER measured on data points in analysis determining confidence of the results based on F-test when R2 should be .80.
Population ≥ 10
6 ≤ Pop < 10
Pop < 6
Meets guidelines
Below guidelines, acceptable with proper understanding
Below guidelines
24
Data Driven Estimating - Examples
We are all confronted in our daily lives with estimates for products and services— E.g. Home remodel, auto repair
We evaluate the credibility of these estimates based upon the content of the estimate
We need to apply this customer mentality when we review our own proposal cost volumes and BOEs
Example: Everyone has dealt with an automobile repair estimate that we struggle to feel comfortable with. Evaluate
the following BOEs for automobile repair service – how do we as consumers know that we are getting a fair price for these
services
25
D&G Auto – Poor, Fair or Good BOECriteria
• Description of the products or services delivered and the tasks to be performed
• Estimated labor resources to perform the defined tasks
• Time-phasing of labor resources
• The estimating method, rationale, assumptions, and computations used to develop the estimate
• Identification of the relevant historical data and comparability of the historical program to the current program
• Explanation of any adjustments made to the historical data or estimate (i.e., use of modifiers)
26
D&G Auto – Poor, Fair or Good BOECriteria
• Description of the products or services delivered and the tasks to be performed
• Estimated labor resources to perform the defined tasks
• Time-phasing of labor resources
• The estimating method, rationale, assumptions, and computations used to develop the estimate
• Identification of the relevant historical data and comparability of the historical program to the current program
• Explanation of any adjustments made to the historical data or estimate (i.e., use of modifiers)
27
D&G Auto – Poor, Fair or Good BOECriteria
• Description of the products or services delivered and the tasks to be performed
• Estimated labor resources to perform the defined tasks
• Time-phasing of labor resources
• The estimating method, rationale, assumptions, and computations used to develop the estimate
• Identification of the relevant historical data and comparability of the historical program to the current program
• Explanation of any adjustments made to the historical data or estimate (i.e., use of modifiers)
28
“data driven” Estimating – The Challenges Ahead
Focus – Improve estimating products across all estimating stake-holders (e.g. BOEs, Earned Value, Cost Analysis and Program Execution (CAPE), Independent Cost Evaluation (ICE), Business Case Analysis)
The debate as we evolve to our future –— At what level will we be generating estimates (e.g. subsystem, assembly)— What scope measures (OSM) will we be using — How will we document our estimating processes— Same or different approaches for firm business, ROMs/NTE, EAC/ETC?— What measures/approaches will be cost credible with our customers
Historical databases, processes and strategies need to be flexible as we evolve toward the future “improved” estimating products— Estimating, Cost Modeling and Engineering teams working together— As the desired characteristics of these high quality estimating methods
evolve – our methods must evolve also.
Immediate needs:— Documented estimating process — Good historical data — Libraries of BOEs demonstrating data driven estimating approaches
29
Backup Charts/Supplemental Resources
30
Judgment: Least preferred, least credible estimating method –very subject to bias— Generally not based upon historical data, scope measures or other sound
estimating approaches
Relies on Subject Matter Expert (SME) estimate’s of small work packages aggregated to complete hardware, software, etc tasks— State author’s experience from which to make an estimate
— Programs worked; Years in industry— Decompose effort into well defined tasks and subtasks
Disclose if historical methods were investigated and not used, and why they were not used
Estimating Method - Judgment
Rarely are we asked to quote something that does not have some similar historical likeness !
31
Estimating Method - LOE Level of Effort (LOE) - Use when customer specifies effort to
be provide over a stated period of time on work that can be stated only in general terms— Requirement for specific skills/talents that tend to be headcount driven— Used when product cannot be well defined
Contract is for delivery of hours not product. Payment based on effort expended not results achieved.— Restricted LOE Contracts — Statement of Work (SOW) that specifically calls out LOE by customer
What is NOT LOE— Level loading of labor not specifically directed by customer— Staffing a position (i.e. Program Manager) as 160 hrs/month during
period of performance on a completion type contract
32
Estimated Cost (New Design) = Historical Cost (Similar Design) + Complexity or Scaling Factor
Estimating Method – Analogy/Comparison
Analogy/Comparison: This method is based on historical context or frame of reference from a similar effort. Compares items being estimated to items of similar configuration and known cost to produce estimate— Includes use of historical data— Addresses differences between historical data and proposed solution
being estimated— May use relevant estimating attributes and complexity or adjustment
factors (modifiers) to reflect programmatic, technology, requirements or technical differences
— Clearly document in BOE why and how factors are used and validated
33
Estimating Method – Standard Time
Labor standard - time necessary to complete a defined element of work following a prescribed method, for an average (qualified) worker working at a 100% efficiency with no hindrances, breaks, delays or fatigue over extended periods of time— Realization/Performance factors recognize actual experience measured
against the standards
— This method is most often used in manufacturing or production related estimates.
— Examples:
— Manufacturing operation: Time required to complete a drilling operation on a product adapter
— Car servicing: Factory maintenance manual sets a standard number of minutes for each type of repair
34
Estimating Method – Unit Method
Unit Method: Relies on an accumulation of past experience divided by cost driver to produce cost per unit
— Example: Labor cost of developing and fielding entire ground station and costing using number of ground stations to be fabricated
— Example: ABC widget has 11 square feet of surface area. Actual design hours for XYZ widget (10 square feet of surface area) were 80 hours. 80 hours/10 square feet = 8 hours per square foot. Therefore ABC widget will take 88 (8 X 11) hours to design
A Simple Ratio (not statistically validated) of X to Y Is A Unit Method
35
Estimating Method – Follow-on Effort (Actuals)
Follow-on based upon program actuals— Commonly used when developing an estimate of labor or
material for continuing efforts (usually)— Production hardware— Spare parts, Repairs, or Retrofit— Sustaining Engineering— Estimate At Complete (EAC)
Definition: An estimate that uses historical data (hours, material dollars, weights, etc.) to project continuing future efforts of the same product line, process or part.
36
Estimating Method – Parametric Model Parametric Model: Utilizes mathematical calibrated models
that derive project cost or effort from attributes / metrics of project— Source lines of code (SLOC), function points (FPs), COTS
product characteristics, Weight, Size— The measurement is based on the technical, physical, or other
end item characteristics Facilitates alignment of program baselines
(e.g. IMS and Staffing plans) Customer RFP often dictates use Utilized by customer to evaluate BOEs and bid overall Used by ICE to evaluate bid position & performance risk Performed by an experienced cost modeler Commercial parametric models include: PRICE, SEER
37
Estimating Method – Parametric Model, Cont…
Parametric Model: is a group of cost estimating relationships used together to estimate entire cost proposals or significant portions thereof.— These models are often computerized and may include many inter-
related CER’s both cost-to-cost and cost-to-non-cost estimating techniques estimating relationships to predict complex
— Some models use a very limited number of independent estimated values and a series of Parametric inter-related cost-to-noncost estimating techniques relationships to predict complex proposal cost structures
38
Estimating Method - CER Cost Estimating Relationships: Statistical estimating
methods that produce mathematically fitted functions — Developed by mathematically relating effort or time estimates to
OSM, traits or other feature of product or manufacturing environment
Relationship may be based on single or multiple measures (independent variables) representing estimating attributes, complexity measures, or other measures of effort. — The results from application of the CERs (dependent variable) is
frequently a labor estimate expressed in hours/staff-months or an estimate of time in days/weeks/months.
Example: Based on actuals of four projects (design hrs/ sq ft) using linear regression, this estimating
relationship is created:Design Hours = 9.32 * sq ft - 14.3
39
Hardware Cost Modeling
Estimate system acquisition costs based upon:— Quantitative parameters such as complexity, quantity,
weight, and size; and
— Quantitative parameters such as environmental specification, type of packaging, and level of integration; and schedule parameters such as months to first prototype, manufacturing rate, and amount of new design
— Electronic hardware items are characterized by the electronic application and type of componentry
— Mechanical and structural elements can be described in terms of their construction, type of material, functionality, machinability and manufacturing process
40
“data driven” Estimating
Why Basis of Estimate (BOE) Focus?
BOE - Description
“data driven” Estimating - Definition
Fundamentals of “data driven” Estimating
“data driven” Estimate Examples – We are the Customer
Non-Proprietary BOE Training Material Available to All
41
Background/Objectives
Background: There is a significant industry effort to increase the quality of contractor estimating processes. The industry has applied the term “data driven” estimating to this new method of developing and documenting our estimates/BOEs. “data driven” Estimating methods have certain characteristics that are starting to emerge as standards within our industry.
Objectives:— What is driving our industry toward the use of data driven estimating
methods and why is this a business imperative
— Be able to identify the characteristics of good data driven estimating processes and how they are represented in our BOEs
— Provide examples of “data driven” versus non-data driven BOEs
— Raise the bar by providing access to non-proprietary BOE training
42
Responsibilities
4
Mapping of DFARS 252.215.7002 Cost Estimating System Requirements to Major Estimating System Components
Roles
Training
Estimate Data Sources
Estimate Preparation
Estimate Review
Estimate Approval
Internal Controls
Well Supported Data Driven Estimating in Key to Estimating System Health
1. Establish clear responsibility for preparation, review, and approval of cost estimates and budgets.
2. Provide a written description of the organization and duties of the personnel responsible for preparing, reviewing, and approving cost estimates and budgets.
3. Ensure that relevant personnel have sufficient training, experience, and guidance to perform estimating and budgeting tasks in accordance with the established procedures.
4. Identify and document the sources of data and the estimating methods and rationale used in developing cost estimates and budgets.
9. Provide for the use of historical experience, including historical vendor pricing information, where appropriate.
11. Integrate information available from other management systems.
15. Provide procedures that ensure subcontract prices are reasonable based on a documented review and analysis provided with the prime proposal, when practicable.
5. Provide for adequate supervision throughout the estimating and budgeting process.
6. Provide for consistent application of estimating and budgeting techniques.
7. Provide for detection and timely correction of errors.
8. Protect against cost duplication and omissions.
10. Require use of appropriate analytical methods.
14. Provide procedures to update cost estimates and notify the Contracting Officer in a timely manner throughout the negotiation process.
12. Require management review, including verification of the estimating and budgeting policies, procedures, and practices .
13. Provide for internal review of, and accountability for, the acceptability of the estimating system, including the budgetary data supporting indirect cost estimates and comparisons of projected results to actual results, and an analysis of any differences.
16. Provide estimating and budgeting practices that consistently generate sound proposals that are compliant with the provisions of the solicitation and are adequate to serve as basis to reach a fair and reasonable price.
17. Have an adequate system description, including policies, procedures, and estimating and budgeting practices, that comply with the Federal Acquisition Regulation and Defense Federal Acquisition Regulation Supplement.
43
DFARS 252.215.7002 Cost Estimating System Requirements4. Identify and document the sources of data and the estimating methods
and rationale used in developing cost estimates and budgets.
9. Provide for the use of historical experience, including historical vendor pricing information, where appropriate.
11. Integrate information available from other management systems.
6. Provide for consistent application of estimating and budgeting techniques.
10. Require use of appropriate analytical methods.
15. Provide procedures that ensure subcontract prices are reasonable based on a documented review and analysis provided with the prime proposal, when practicable. Provide for adequate supervision throughout the estimating and budgeting process.
Estimate Review
Estimate Data Sources
Estimate Preparation
44
Purpose of a BOE
Documents and substantiates effort required to perform tasks — Documents basis and assumptions— Details understanding of requirements— Conveys credibility by clearly defining tasks and assumptions— Demonstrates that estimates are credible, defendable and realistic
(historical data)
Provides evidence that estimate is consistent with other proposal volumes
Time-phased resources consistent with IMP/IMS Allocates resources such as skill mix appropriate for task Aligns with Work Breakdown Structure (WBS), SOW, and other
product structures Meet customer funding, timing, and/or scheduling constraints
45
BOEs – The Components A BOE consists of the following main elements:
1. Work Element ID – WBS, SOW, Location, CLIN, NRE/Rec…2. Description of the products or services delivered and the tasks
to be performed3. Estimating method, rationale, assumptions, and computations
used to develop the estimate— Method of quoting
4. Relevant historical data and comparability of the historical data to the current program— Explanation of any adjustments made to historical cost or
programmatic data (i.e., use of modifiers)
5. Estimated labor and ODC resources to perform the defined tasks
6. Expenditure profile (time-phasing) of resources7. Other elements as required by the cost proposal instructions
46
BOE Estimating Methods Estimates are developed using one or more of these typical
estimating methods— Judgment – based on subject matter expert (SME) experience with similar
efforts. — Level-of-Effort/Support - uses resource-based estimates that are often
based on a predetermined level of support for a given period of time — Analogy/Comparison Method – estimate based on historical frame of
reference from a similar effort with adjustments for programmatic or technical differences
— Standard Time Estimating - Labor Standards and Realization/ Performance Factors - time necessary to complete a defined element of work following a prescribed (recognized) technique or method.
— Unit Method – generally a simple ratio (not always statistically validated)— Follow-on Based On Actuals – extrapolation of actuals (CEAC, production)— Parametric Cost Models – use of calibrated, internally developed, or
commercially available cost models — Cost Estimating Relationships (CERs) - equations developed based on
historical, statistically correlated relationships(See full training package for more details)
47
Customer Expectations
Customers/DCAA/DCMA expect contractors to begin adopting improved estimating methods to support TINA-compliant proposals and other estimating products
Least Preferred
Judgment
Most Preferred
“Fact Based”Estimating Methods
Move To Fact Based ASAP
48
BOE Methodologies – Credibility Scale
Historical resource based estimates are easier to support than judgmental type estimates.
Customer Credibility LaborHigh Follow-on Projections
based on ActualsAnalogy/Comparison
CER’sParametric Estimates /
Cost ModelsStandards
Unit MethodsLevel Of Effort
Low Judgment
49
Customer Consequences – Poor Estimating
Failure to be responsive to customer estimating processes could be grounds for— Non-compliance with RFP or government regulations— Rejection of proposal and possibly defective pricing— Holdbacks
Penalties for bad BOEs include:— Questioned costs— DCAA/Government Flash Report— Negotiation losses— Negative factor in competitive evaluations— Defective pricing and fraud prosecution— Suspension of bidding and debarment
50
“data driven” BOEs – Basic Definition Fact Based Estimating: Estimating processes/BOEs that
provide the supporting information and rationale necessary for accurate, credible and traceable estimates
Information includes:— Use of defined estimating methods
— Historical data from past programs
— Use of objective scope measures and complexity factors where appropriate
Rationale addresses:— Complete description of the estimating approach
— Explanation of the applicability of the historical information
Estimating process must be documented, consistent and repeatable
51
Fact Based BOEs – The Fundamentals
1. Estimate developed using a defined and documentedestimating processes
2. Methods rely on scope measures (attributes) and complexity factors (parametrics) – when applicable
3. Complete estimate development process is explained and documented in the BOE — Professional judgments, modifiers/adjustment factors, and historical
context is adequately explained— Process is consistent and repeatable
4. Estimate relies on relevant historical data and context that is accessible and verifiable — Shows use of latest and most current relevant data— Supports all resource estimates with verifiable data
5. Estimating processes are monitored for learning and improvement as required to support future estimates
52
Objective Work-Scope Measures (OSM)
Scope Measures = estimating predictive measures – technical measures relating to the size of the effort (attributes)— Generally physical and technical measures— Sized at different product levels - system, subsystem, box, etc. — Example:
— Work Products: # drawings by type, sheet counts, # documents & sheet count, SLOC by category, # requirements, # reviews, # test & type, weight, quantities, etc.
Traits/Complexity Factors: characteristics that can improve the accuracy of relationships developed for the OSMs — Example:
— Scope Measures = Drawings— Traits: (numeric and descriptive): # Drawings, Type of Drawing; Drawing
Heritage; Item Next Higher Assembly/Element; Number of Sheets; # of Revisions
— Example: — Scope Measures = Source Lines of Code (SLOC)— Traits: Software Language; New SLOC; Modified SLOC; Reuse SLOC; Actual
Total Delivered SLOC, Deleted SLOC, Auto Generated Code, etc
53
Why Use Scope Measures and Traits in BOEs?
Scope Measures - help to scope the size of the effort to be estimated — Objective quantitative measures of scope to be performed — Directly correlate to (predictors) resource estimates for work products and
tasks — Understanding the size (scope) of the proposed effort is critical to
developing an accurate estimate (BOE) — The BOE author should explain the derivation, source, and application of
the scope measures in the BOE
Traits/Complexity Modifiers – address unique characteristics of the scope measures that can affect required effort to produce— Capture the effects of technical and programmatic differences between
historical programs and the current proposed effort.— The “produceability” can vary widely for any scope measure - traits can
be used to explain the differences— Sometimes requires judgment
54
Explaining Adjustment to a BOE
Provided below are some examples of adjustments that may be required to improve the accuracy of the estimate. The list is not meant to be totally inclusive of adjustments an estimator has available in their tool box.— Technical Complexity ~ Labor Estimate
— Improvement Curves ~ Labor Estimate
— Schedule adjustments ~ Labor Estimate
— Quote Decrement ~ Material Estimate
— Quantity Adjustment ~ Material Estimate
— Escalation ~ Material Estimate
— Exchange Rate ~ Material Estimate
In order to use an objective or subjective adjustment, an estimator must explain it thoroughly.
55
Using Historical Data in a BOE
Use of Historical Data Must Address:— Source of data – generally from the organization’s certified
historical data repositories— Complete identification of the nature, source and details of
relevant historical data
Ensure compliance with A.C.T.T.R. by documenting the following: — Actual historical hours— Charge numbers included— Technical data used— Time frame of historical data— Repository or source of historical data
56
“data driven” Estimating - Examples
We are all confronted in our daily lives with estimates for products and services— E.g. Home remodel, auto repair
We evaluate the credibility of these estimates based upon the content of the estimate
We need to apply this customer mentality when we review our own proposal cost volumes and BOEs
Example: Everyone has dealt with an automobile repair estimate that we struggle to feel comfortable with. Evaluate
the following BOEs for automobile repair service – how do we as consumers know that we are getting a fair price for these
services
57
D&G Auto – Poor, Fair or Good BOECriteria
• Description of the products or services delivered and the tasks to be performed
• Estimated labor resources to perform the defined tasks
• Time-phasing of labor resources
• The estimating method, rationale, assumptions, and computations used to develop the estimate
• Identification of the relevant historical data and comparability of the historical program to the current program
• Explanation of any adjustments made to the historical data or estimate (i.e., use of modifiers)
58
D&G Auto – Poor, Fair or Good BOECriteria
• Description of the products or services delivered and the tasks to be performed
• Estimated labor resources to perform the defined tasks
• Time-phasing of labor resources
• The estimating method, rationale, assumptions, and computations used to develop the estimate
• Identification of the relevant historical data and comparability of the historical program to the current program
• Explanation of any adjustments made to the historical data or estimate (i.e., use of modifiers)
59
D&G Auto – Poor, Fair or Good BOECriteria
• Description of the products or services delivered and the tasks to be performed
• Estimated labor resources to perform the defined tasks
• Time-phasing of labor resources
• The estimating method, rationale, assumptions, and computations used to develop the estimate
• Identification of the relevant historical data and comparability of the historical program to the current program
• Explanation of any adjustments made to the historical data or estimate (i.e., use of modifiers)
60
“data driven” Estimating – The Challenges Ahead
Focus – Improve estimating products across all estimating stake-holders (e.g. BOEs, EV, CAPE, ICE, Business Case Analysis)
The debate as we evolve to our future –— At what level will we be generating estimates (e.g. subsystem,
assembly)— How will we document our estimating processes
Historical databases, processes and strategies need to be flexible as we evolve toward the future “improved” estimating products— Estimating, Cost Modeling and Engineering teams working
together— As the desired characteristics of these high quality estimating
methods evolve – our methods must evolve also.
Immediate needs: — Documented estimating process — Good historical data — Libraries of BOEs demonstrating data driven estimating
approaches
61
Back Up
62
Estimated Cost (New Design) = Historical Cost (Similar Design) + Complexity or Scaling Factor
Estimating Method – Analogy/Comparison
Analogy/Comparison: This method is based on historical context or frame of reference from a similar effort. Compares items being estimated to items of similar configuration and known cost to produce estimate— Includes use of historical data— Addresses differences between historical data and proposed solution
being estimated— May use relevant estimating attributes and complexity or adjustment
factors (modifiers) to reflect programmatic, technology, requirements or technical differences
— Clearly document in BOE why and how factors are used and validated
63
Judgment: Least preferred, least credible estimating method –very subject to bias— Generally not based upon historical data, scope measures or other sound
estimating approaches
Relies on SME estimate’s of small work packages aggregated to complete hardware, software, etc tasks— State author’s experience from which to make an estimate
— Programs worked; Years in industry
— Decompose effort into well defined tasks and subtasks
Disclose if historical methods were investigated and not used, and why they were not used
Estimating Method - Judgment
Rarely are we asked to quote something that does not have some similar historical likeness !
64
Estimating Method - LOE Level of Effort - Use when customer specifies effort to be
provide over a stated period of time on work that can be stated only in general terms— Requirement for specific skills/talents that tend to be headcount driven— Used when product cannot be well defined
Contract is for delivery of hours not product. Payment based on effort expended not results achieved.— Restricted LOE Contracts — SOW that specifically calls out LOE by customer
What is NOT LOE— Level loading of labor not specifically directed by customer— Staffing a position (i.e. Program Manager) as 155 hrs/month during
period of performance on a completion type contract