199'5 ftTIt A LABORATORY STUDY OF SEDIMENT DISTRIBUTION …
Transcript of 199'5 ftTIt A LABORATORY STUDY OF SEDIMENT DISTRIBUTION …
K£F5"01'3199'5"ftTIt
A LABORATORY STUDY OF SEDIMENTDISTRIBUTION AT CHANNEL BIFURCATION
'.' ."
ATAULHANNAN
/1/111111!f~~~!""UiIIII- ; .I.
DEPARTMENT OF WATER RESOURCES ENGINEERINGBANGLADESH UNIVERSITY OF ENGINEERING & TECHNOLOGY,
DHAKA
NOVEMBER 1995
A LABORATORY STUDY OF SEDIMENTDISTRIBUTION AT CHANNEL BIFURCATION
ATAUL HANNAN
IN PARTIAL FULFILLMENT OF THE REQUIREMENTSFOR
DEGREE OF MASTER OF SCIENCE IN ENGINEERING(WATER RESOURCES)
DEPARTMENT OF WATER RESOURCES ENGINEERINGBANGLADESH UNIVERSITY OF ENGINEERING & TECHNOLOGY,
DHAKA
NOVEMBER 1995
This is to certify that the thesis on A LABORATORY STUDY OF SEDIMENT
DISTRIBUTION AT CHANNEL BIFURCATION has been done by me. Neither of
this thesis nor the part thereof has been submitted elsewhere for the award of any
degree or diploma.
•
ATAUL HANNANCountersigned by the Candidate
CERTIFICATE
t .
•
\(k,-Dr. M. R. KABIRCountersigned by the Supervisor
Prof. M. Monowar Hossain
Mr. A. K. M. Shamsul Hoque
=e~~.Dr. M. A. Matin
Dr. M. R. Kabir
Prof. Ainun Nishat
NOVEMBER 1995
ATAUL HANNAN
We hereby recommend that the thesis presented by
BANGLADESH UNIVERSITY OF ENGINEERING AND TECHNOLOGYDEPARTMENT OF WATER RESOURCES ENGINEERING
Member(Head of the Department )
Member(External)
Member
Member
Chairman of the Committee( Supervisor)
entitled " A LABORATORY STUDY OF SEDIMENT DISTRIBUTIONAT CHANNEL BIFURCATION" be accepted as fulfilling this part ofthe the requirements for the degree of Master of Science in Engineering(WATER RESOURCES).
ABSTRACT
Morphological behavior of bifurcatibns and confluences which are typical features ofrivers and
estuaries are still not properly understood phenomena. Recently a few researchers have done
some work on bifurcation with the help of I-D model which are not developed particularly for
this purpose. In these l-D models the bifurcation phenomena has been represented by'the help
of nodal point relations. The distribution of sediment at bifurcation is a three dimensional
phenomena. It is very difficult to '~et a clear idea of three dimensional problem with the helpf 1 D d I S I . . h' .,.. d . bo - mo e s. 0, to get some mSlg t mto lliC pnenomcn& an process, la oratory
experiment was initiated at the laboratory of Department of Water Resources Engineering,
BUET. As the bifurcation phenomena is a very complicated one, assumptions were made to
make the problem as simple as possible.
After constructing the experimental set-up all the facilities were tested whether they were
working according to simplification. All instruments were calibrated and the model produced
results as .expected. After being satisfied that the experimental set-up was functioning properly,
main experiments were carried out.
Experiments were carried out with two noses representing two different bifurcation conditions.
The first nose gave results which fits well with the theory S2 = k(tJ2J "']. The only differencesS3 q3
was that with the increase of discharges the value of m (nose geometry) did not remain
constant rather it increased. In case of the second nose the value of m increased with discharge
but at a lower rate. Here the calculated normal depths were far a way from the actual normal
depths of the two downstream branches. This is because the shape of the nose created an
additional influence in the model. So, the results of the two noses can not be compared since
the conditions are not the same. But it can be interred trom the resuits that no gen~ral relation
in the case of sediment distribution over the two downstream branches can be expected since it
depends not only on the geometry of the nose but also on the condition of the downstream
branches as compared to nose configuration. Further studies will help in better under standing
the problem since this may be the beginning of such kind of study.
I
'AdKNOWLEDGMENT
The author acknowledges his sincere gratitude and thanks to Dr. M. R. Kabir, Assistant Professor,
Department of Water Resources Engineering, BUET who introduced the author to the interesting
field of sediment' Tr,ansport Technology. The author is really grateful to his s!lpervisor for his
constant encouragement and wise guidance throughout the experimental investigation and during .
the preparation of this thesis.
The author's sincere thanks are also to the numbers of the examination committee, Dr. Ainun
Nishat, I'rofessor of the Water Resources Engineering Department, Dr. M. M. Hossain,'
Professor and Head of the Water Resources Engineering Department, Dr. ,M. A. Matin,
Associate 'Professor of the Water resources Engineering Department, BUET, Dhaka and Mr. A.
K: M. Shamsul Hoque, Chief Engineer, Planning BWDB, Dhaka for their special interest,
valuable suggestions and help on many occasions.
The author also wishes to thank Prof. M de Vries, Dr. Wang, Mr. van Mierlo, P. den Dekker and
lM vanVoorthuizen. Without their help the model would never have been built. The
experiments were carried out together with two M.Sc students of TU Delft R. Roosjen and C.
Zwanenburg. The author wishes to give special thanks to them for their good co-o~eration.
Also thanks to Mr. van der Wal, who spent some his of spare time in helping to start up the
model, and time to time practical advice given by him was very useful.
The author 'also wishes to thank Md. Salim Kaiser, Assistant Foreman Instructor of
Machines~op, BUET for his help'in constructing allthe steel structures in the model. Thanks are
'also due to Mr. Nazimuddin and Mr. Mostofa. for their kind and constant assistance in
performing the laboratory fests.
ATAUL HANNAN
ii
TAJLE OF CONTENTSi
Abstract
Acknowledgment
Table of Contents
Listof Tables
List of Figures
List of Main Symbols
CHAPTER-l INTRODUCTION
1.1 SCOPE OF THE STUDY"
1,2 OBJECTIVES OF'THE RESEARCH
CHAPTER-2 REVIEW OF LITERATlJ1lli
2, I PREVIOUS RESEARCHES
2,1.1 SOME REMARKS
2,2 INCIPIENT MOTION OF SEDIMENT PARTICLES
2.2, I SHIELDS DIAGRAM
2,3 SEDIMENT MOVEMENT IN RIVERS
CHAPTER-3 THEORETICAL CONSIDERATION
3.1 GENERAL CONSIDERATIONS
3,2 THEORETICAL ANALYSIS
, 3.2,1 SINGULAR POINTS,
3,2,2 THE STABILITY OF THE SINGULAR POINTS
CHAPTER-4 EXPERIMENTAL SET-UP
4, I EXPERIMENTAL SET-UP
4,1.1 THE TEMPORARY PART
iii
I
ii
iii
vii
vii '
x
I
2
3
7
7
8
9
II
12
14
15
18
18
"
4,1.1.1 INFLOW ZONE
4.1.1.2 THE CHARACTERISTICS OF THE MAIN BRANCH
4.1.1.3 THE CHARACTERISTICS OF BRANCH 2 AND 3
4.1.1.4 CONFIGURATION OF THE BIFURCATION
,4.1.1.5 SANDTRAPS
4.1.1.6 OUTFLOW SECTION,
4.1.2 THE PERMANENT PA~TI
4.1.2.1 DOWNSTREAM RESERVOIR
4.1.2.2 PUMP
4.1.2.3 PIPE LINEi
4.1.2.4 UPSTREAM RESERVOIR,,i '
4.1.2.5 THE REGULJ).TING AND MEASURING SYSTEM
4.1.2.5.1 THt TAIL GATES
4.1.2.5.2 THE STILLING BASIN AND TRANSITION FLUMES
4.1.2.5.3 THE GUIDING VANES AND TUBES
4.1.2.5.4 THE ApPROACH CHANNEL AND THE REHBOCK
WEIRS
4.1.2.5.5 THE STILLING BASINS CONNECTED WITH
REHBOCK' WEIRS
4.2 THE WATER CIRCUIT
4.3 SEDIMENT CIRCUIT,
4.4 SAND FEEDER
4.5 SEDIMENTS
,4.6 THE MEASURING TECHNIQUES
4.6.1 DISCHARGE MEASUREMENTS
4.6.2 SEDIMENT TRANSPORT MEASUREMENTS
4.6.3 WATER LEVEL MEASUREMENTS
4.6.4 BED LEVEL MEASUREMENTS
4.7 TEST RUNS .
iv
19
19
2020202223
23
23
.23
24
25,
25
2626
26
27
27
28
2828292930
31
32
33
CHAPTER-5 EXPERIMEN~AL PROCEDURE
5.1 BEFORE STARTING THE MODEL FOR EXPERIMENT THE FOLLOWING THINGS
59
6061
- 64
4747
4748
4950
51
52
53
53
54
55
5656
58
WERE DONE 34
5.2 DURING THE EXPERIMENT THE FOLLOWING THINGS WERE DONE 36
5.3 PROBLEMS FACED DURING MODEL CONSTRUCTION, OBSERVATION AND DATA
COLLECTION 42
CHAPTER-7 CONCLUSION AND RECOMMENDATION
v
7.1- CONCLUSION
7.2 RECOMMENDATION FOR FURTHER STUDY
REFERENCES
TABLES
. CHAPtER-6 DATA ANALYSIS, RESULTS AND DISCUSSION
, .
.;l:c FIGURES 71
PLATES 151
APPENDIX-A DETAIL OF THE REHBOCK WEIRS A-I
APPENDIX-B ACCURACY OF THE REHBOCK WEIRS B-1
?,. APPENDIX-C CALIBRATION CHART OF THE BUCKETS C-l
APPENDIX-D PROGRAM TO CALCULATE THE NORMAL DEPTHS 0-1
vi
LIST OF TABLES
TABLE 2.1: ' HYDRAULIC AND SEDIMENT PARAMETERS OF THE NILE RIVER AT
BENI - MAZZAR 64TABLE 6.1 :' RESULTS OF THE FIRST ,NOSE (30 Lis) 65TABLE 6.2: RESULTS OF THE FIRST NOSE (40 Lis) . 66TABLE 6.3: RESULTS OF THE FIRST NOSE (20 Lis) 61TABLE 6.4: . RESULTS OF THE SECOND NOSE (30 Lis) 68'TABLE 6.5: RESULTS OF THE SECOND .NOSE (40 Lis) 69 .. . ,TABLE 6.6': RESULTS OF THE SECOND NOSE (20 Lis) 70
LIST OF FIGURES
FIGURE 1.1 THE CONFLUENCE Al-m BIFURCATION OF RIVER SYSTEM 71
FIGURE 2.1 MODE~ OF THE BENI-LAZZAR REACH OF THE NILE RIVER 724 !
FIGURE 2.2 ALIGNMENT OF THE THREE DREDGED CHANNELS 73
FIGURE 2.3 SCHEMATIZED MAIN AND SECONDARY CHANNELS SYSTEM 14
FIGURE 2.4 SHIELDS DIAGRAM FOR INCIPIENT MOTION .74
FIGURE 3.1 PHASE DIAGRAM IS CASE OF m«5i3) 15
FIGURE 3.2 PHASE DIAGRAM IS CASE OF m >(5/3) 75
FIGURE 4.1, GENERAL LAYOUT OF THE SET-UP 76
vii
FIGURE 4.19B CALIBRATION CURVE FOR SAND FEEDER NO.2 91
FIGURE 4.20 THE GRAIN SIZE DISTRIBUTION OF WASHED AND'UNWASHED SAND 92
FIGURE 4.21 DETAIL OF THE STILLING BASINS 93
FIGURE 4.22 DETAIL OF THE SPECIAL PIN 93
r FIGURE 4.23 DETAIL OF THE BED LEVEL MEASUREMENT POINTS 94
FIGURE 4.24 RESULTS OF THE TEST RUNS 95
FIGURE 5.1 LAYOUT OF THE 'PIPE LINE '(FIRST) 96
FIGURE 6.1-6:41 BED LEVEL EVOLUTION 97-137
fFIGURE 6:42-6:47 VARIATIONOF DISCHARGE WITH RUN TIME 138-144
J
FIGURE 6:48-6.53 RELATION BETWEEN SEDIMENT TRANSPORT RATIO AND DISCHARGE
RATIO.
ix
145-150
CHAPTER-l
INTRODUCTION
Bifurcations and Confluences are typical features of rivers and estuaries. In most cases,
confluences occur in the upstream and bifurcations occur in the downstream of a river in the
delta area, although it is not applicable in all rivers. Braided rivers, in particular, are
.characterized by a repetition of confluence. and bifurcations. In cha.tlllel networks in,
estUaries, confluences turn into a bifurcation at the turn of the tide. Fig. 1.1 shows the
definition sketch of bifurcation and confluence of river.
At a confluence one may know the discharge and the sedim~nt transport in each of the
upstream channels. The discharge and sediment transport in the downstream channel is
simply the sum of those in the upstream channels. At a bifurcation, however, it has to be' ,
determined how the discharge and sediment are distributed over the downstream channel.
The distribution of ,the discharge can easily be determined by the geometry and the,hydraulic resistance of the idownstream channels. Now the problem is to determine the
distributiOll of sediment ov~r the branches as the sediment distribution is influenced by the
local three-dimensional phenomena (Bulle, 1926 ; de Vries, 1992).
The morphological behaviour of bifurcation in rivers is still a poorly understood problem.
This is exemplified by the fact that very little literature can be found dealing with this
subject. This scarcity in available literature must, however, not be seen as an indication of
the less importance of the subject, but rather it shows the difficulty of the problem with
which many river engineers are confronted.
1.1 SCOPE OF THE STUDY
Bangladesh 'is situated jn the floodplain of the three great rivers, the Brahmaputra, the
Ganges and the Megl;ma. The Brahmaputra river originates from the northern slope of the
Himalayas in Tibet, China and flows eastward, then turns to south and then to west through
India to th~ border of Bangladesh. Within Bangladesh the stream is known as the Jamuna
river. This Jamuna river (braided) and some other braided rivers that are so-called
anabianched channel system are characterized by a repetition of bifurcations and
confluences. Bank protection and river training works have been taken up and are also. ~ . . .
going on in many reaches of the Jamuna river in connection with flood control and bank. ,
erosion problems' and also for Jamuna multipurpose bridge. For better design and
mai\ltenance of such river Engineering works it is essential that proper study relating to
river bifurcation phenomena shoul? be carried out to have good insight into the problem of
river bifurcation whi.ch plays a vital role in bank erosion and river shifting phenomena in a
braided river. Realizing the importance of bifurcation effect on river morphology and
necessity of having better knowledge about bifurcation, the present study has been initiated.
1.2 OBJECTIVES OF THE RESEARCH
So far only few researchers ha~e done some theoretical study relating to some limited
aspects of river bifurcation. Consequently extensive study covering both theoretical and
experimental aspects of bifurc,ation problems are essential. In the present study, attemptsI • .
have been taken 'to the following aspects in particular.,
(a) to understand the physics of the phenomena of sediment transport at bifurcation
(b) to estimate the transport rat~s and yields, and. ,(c) to develop an empirical relation to calculate sediment transport rate In the tWo
downstream charinel at bifurcation using the observed data.
2
'(
CHAPTER - 2
REVIEW OF LITERATURE
Through an extensive literature surv~yvery little information was found with respect to
the sediment distribution over the downstream branches at a bifurcation. The number of
existing one dim'ensional sediment transport models are small in number. Moreover very
few of, these one -dimensional' mathematical models have bifurcation options. Both
,bifurcations and confluences are treated as the same phenomena in the models which
contains bifurcation options but there is a significant difference between the modelling'
of a bifurcation and the modelling of a confluence. Attention is also drawn to the fact
that very few of the models '1ifhich contain both bifurcation and confluence have nodal '
point relations by whi~h the three-dimensional phenomena can be parameterized in the
most convenient way.
2.1 PREVIOUS RESEARfHES
Boreli and Bruck (1956, aftet Wang,1993) attempted to analyse the conditions of
stability of a river branch for fhe sake of off-take design. They considered the river, ' ,
branch a natural off-take, whose properties could be used in diversion design. Their
works were mainly concerned on the stability of river branches for the design of
diversions.
Vermeer and others (1990) developed a di,<tc,rteds,~"!F,r'-")vRb!e-bedmodd r"'p!'e~ent;llg
a 6-km reach of the Nile River at the Hydrauii<.:sand Sediment Research Institute' at
Beni-Mazar (HSRl). Itwas constructed to study alternative solutions of maintaining the
navigation channel. The three dimensional river model was constructed in an area of 38
by 12 m (Fig 2.1). The bed, banks and islands were shaped according to the field survey
carried out by the Institute and the model scaling ratios were determined in the
recirculating flume. Although bank erosion was observed along the Nile River Reach,
the selection of fixed banks in the model was justified because erosion of the banks is a
much slower process than morphological changes in the bed. The average hydraulic and
)
sediment properties of the Beni-Mazar reach of the Nile River (Table 2.1) were obtained
from field studies just prior to building of the model.
In the model bed levels were measured at 25 cross sections (Fig. 2. I) and the water
surface level at 8 points in the main and side channels. A mixture of recirculating water
and sediment were fed into the model through the manifold. Adjustable vertical slots
.and vanes were used to adjust the lateral variation of veJoc.ity and s~diment load. The
purpose of these tests were planned to help improve the navigation through the reach by
dredging channels of 80 m width (with side slopes 7H:IV) each and bed level of25.25.
This bed level was designed in such a way as to provide a flow depth of 3.5 m during
the winter closure period. The profile of the dredged channels was modelled according
to the prototype data, as well as the vertical and horizontal scales of the model. Each of
the three dredged channels, included in these tests are shown in Fig. 2.2 and was
separately reproduced in the model. The dredging process was carried out in such a way
as not to disturb the calibrated bed configuration in the surrounding areas of the model.
Here the study was mainly concerned for'the navigation depths of the channels and not
with the sediment distribution r~tio.
In an one-dimensional network model the behaviour of the morphological
development according to the model simulation is strongly influenced by the nodal
point relation at bifurcations, For a simple case of one river bifurcation into two
branches both flowing into a lake, it is shown by Wange!. al (1993) that the;
behaviour of the long-term morphological development is totally determined by the
used nodal poi~t relation. For certain relations the bifurcation is stable and otherwise it
is unstable. The nodal point relations are given below.
The first nodal 'point relation is
(2. I)
This is probably the relation that is used inmost operational models. In the DELFT
HYDRAULICS one-dimensional model WENDY developed by D. Wang and others
4
5
(2..2)
(2.3)8, Q,-=a(-)+ ~83 Q3
this relation is one of the two default options. The second default option in WENDY is
the following relation.
Klaassen et al (1993) approached the problem of the stability of braided rivers from a
complete different angle. They are concerned with the prediction of changes in braided
rivers from a statistical point of view,. where the probability of occurrence .of different
p'otential developments play an important role.
. where Bj is the width of branch i.
With the above options a physically realistic stable situation can never be reached. The
combination of this relation with ID model (WENDY), in which the width of branches
are constant, leads to a constant ratio S2 / S3, which is physically unrealistic. So, this
will not give good result. There is another option of WENDY which is given below.
.In this option the constant a and ~ have to be given by the user. This option was used
in WENDY specially for the use of Beni,Mazar model 'which was done by Vermeer in
1990.
Some geologist like Best, Bristow and Ferguson (1993); carried out some some work
to understand the braiding processes in gravel,bed and sand-bed rivers, but not with the
sediment distribution phenomena over the two downstream branches at a bifurcation.
Their study includes the mechanisms of braid bar initiation, the influence of flow stage
and aggradational regime upon the depositional architecture over a range of channel
scales, variation and interaction of channel geometry, water flow,' 3D variation of bed
geometry, bed texture, bed load transport in braided ?ravel bed rivers and long term
trends in channel and floodplain geometry.,
o
,'"
.A,
)
Schropp (1994) carried out a case study on the morphological development of the
secondary channel system planned at Bernmelerwaard. Theoretical analysis as well as
numerical computations using an one-dimensional model was carried out in this study.
With the theoretical approach the morphological equilibrium situation of a main and
secondary channel system was determined. The schematised network model is shown"
in Fig. 2.3. The length of the river section parallel to' which the secondary channel is
located is 2400 m and secondary channel is 2940 m of length. The secondary channel
will also influence the upstream river and downstream river. Therefore a river section of
50 km at both ends is included in the network model. The river Waal( the main channel)
as well as the secondary channel are assumed to be prismatic, i.e. the cross-section is the
same over the entire length and rectangular in shape. For the main channel this
assumption agrees quite well with the reality but the cross-section of the secondary,
channel does vary iIi the length direction and it is triangular rather than rectangular in
shape~ The width of the main channel.' is' 260 m and that of the secondary channel. is
taken such that the discharge through the secondary channel will be about 5% of the
total discharge at the initial state. The' bottom of the secondary channel is about 3 m
higher than that of the main channel. In the modd the sediment transport in the
undisturbed situation is assumed to be in equilibrium and it is assumed that the 'transport
formula of Meyer-Peter-Muller applies for the Waal. This model is known as SOBEK
and the options are the same as that of WENDY. The purpose of the study is to
investigate influences of various morphological parameters rather than to make
prediction for a partiCular case. It appeared that the sediment distribution to the main and
the secondary channel at the ~ifurcation is very important for the system. However,. ,knowledge on this subject is' very limited. A literature survey on the sediment,
i
distribution at bifurcation poiIits in natural rivers and artificial channels have been
carried out by Akkerman (1993). The scarceavailab!e data have also been well
documented by Akkerman.
den Dekher and van Voorthuizen (1994) applied the options of WENDY for,
bifurcation. After realizing that the def'1ult options would not givC'rp.~!isticr"s\l!ts Dr.
Wang et al (1994) looked for a more gener~!ised options at1.dafter that they proposed
the noaa! point options that is mentiomia in Chapter-3. Dekker and Voorthuizen ran the
, 6
WENDY program With that option for different values' of m. They concluded that if the .
value of m is greater than 5/3 then both the downstream branches remain open and if
the value ofm is less than 5/3 then one of the branches closes.
Richardson and Thome (1995), of the University of, Nottingham carried out ajoint
research' work with River Survey Project (FAP-24) to study the secondary currents in
a bifurcated channel. Secondary currents are defined as currents which. occur in the
plane normal to the axis of the primary flow. For the study a suitable site was selected,
which contain a single bifurcation-bat-confluces morphological unit, in the left bank
anabranch of the Brahmaputra (Jamuna) River about 10 km south of Bahadurabad.
The study indicated' that the pattern of secondaiy currents in a bifurcation chaimel is
more complex than the existing hypotheses. The main purpose of this joint study was
,to improve the understanding of the factors which' are important in determining the'. ,
sediment transport distribution at bifurcation and to pr~dict the overall morphological
trends.
I
2.1.1 SOME REMARKS
The discussion so far made is nJainly concerned with the works on research works done
in case of a bifurcation. It can be seen that no comprehensive field measurements are,available with which ,one can understand the physics of the phenomena of ~ediment
transport at bifurcation. It is also not possible to understand the problem clearly with the,help of a I D mod~1 becau~e the sediment distribution at bifurcation is a three
dimensional phenomena. So, it was thought that a laboratory experimental study on
bifurcation would give more insight knowledge to the problem and would be immensely,beneficial.
2.2 INCIPIENT MOTION OF SEDIMENT PARTICLES
Considering a steady and uniform flow in an open channel with a given slope and
, movable bed made up of uniform noncohesive material it will be found that the material, .
comprising the bed will be stationary for small discharges. However, if the discharge is
increased by a certain value, it will be found that there is random motion of the
7
motion of sediment particles comprising t.~eb~d.These are described below:
(2.4)
8
(, ,/ P /'/2) d'J = 0v ,
Three different approaches have 'been ti'sed to establish the c~n.dition for .incipient
individual particles on the bed. In other words, the flow condition is such that sediment
particles of given characteristics just start moving. This condition is known as the
condition of critical motion or the condition of incipient motion of the sedimentary
particles.
• I , •
1. Competency: Here the size of the bed material is related to either bed velocity or
mean velocity of flow, which just causes the particle to move.
2. Lift concept : In this case it is assumed that when the upward force due to flow is
just greater than the submerged weight of the particle, the condition of incipient
motion is established.
3. Critical tractive force approach: This approach is based on the idea, that the tractive
force exerted by the flowing water on the channel bed in the direction of flow is,
mainly responsible for thel motion of the sediment ary particles.
Among the three approaches to the problem of defining the hydraulic conditions at
incipient motion viz. competency, lift concept, and critical tractive force, it is the critical, ,
2.2.1 SHIELDS DIAGRAM
tractive force approach seems to be more rational and sound than others and is now used
more often than the other two approaches. There are numerous formulae based on this
but the most widely used is the Shields non-dimensional relationship.
that is,
Major variables that affect the incipient motion or' uniform sediment on a level bed
include 'c' d , Ys - y, p and v. From dimensional analysis, they maybe grouped into the
following dimensionless parameters
•
Or
I.
).
(2.6)
(2.5)
dl f ) JI/2)
-;{ O,ll ~ '-1 gd: '
which appears as a family of karalle! lines in the diagram. From the value of the third,,parameter, the value of the critical Shields stress is obtained at an intersection with the
Shields curve 'from which 'c can be calculated. The Shields diagram has gained wide
acceptance, However, it is not without criticism.
:1
is the dimensionless critical shear stress and is often referred to as the, critical Shields
stress, "c' The right-hand side is called the critical boundary Reynolds number and is
9
Where V'c = ('dP)I/2 is the critical friction velocity. The left hand side of the equation, ,
in Eq. 2..5 , they' become the Shields stress and boundary Reynolds number and are
designated as ,. and R., respectively. Figure 2.4 shows the functional relationship of
Eq. 2.5 'established based on experimental data, obtained by Shields (1936) and other
investigators, oli flumes with flat bed. It is generally referred to as the Shields diagram.
Each data point corresponds to the cqndition of incipient sediment motion. The Shields
diagram ,contains the, critical shear stress 'c as an implicit variable that cannot be
obtained directly,' To overcome this difficulty, the ASCE Sedimentation Manual (1975)
utilizes a third dimensionless parameter
denoted by R.c. When any bed shear stres, '0' 0::ici' tria., 'c, is used in the two quantities
2.3 SEDIMENT MOVEMENT IN RIVERS
An important aspect of fluvial processes is the movement of sediment in rivers, to which
river morphology and river channel changes are closely related. The term load, as used
in sediment transport, may refer to the sediment that is in motion in a stream. It is also. ,used to denote the rate at which sediment is moved, for example, cubic feet per second
or tons per day. The lattt;r usage is preferred in river morphology.
There are two copunon classifications of the load in a stream. The first divides the load
into bed load and suspended load; the second separates the load into wash load and bed-
material load.
Bed load - It is defined as that part of the load moving on, or near, the bed by rolling, .
saltation, or sliding.
Suspended load -It is defined as that part of the load that moves in suspension.
Wash load - It refers to the finest portion of sediment, generalIy silt and clay, that is
washed through the channel, with an insignificant amount of it being found in the bed.
Bed-material load - It consists 'of particles that are generalIy found in the bed material.
"
.,
,10
Only bed-load transport is considered.
Equations
The bed from were not considered.I
The water level at the downstrealn boundary was kept constimt. 'I , " ,
5) The charmel banks are fixecl.
6) The morphological changes in the upstream river due to disturbances in the downstream, ,
• .. j
The morphological' behaviour of bifurcations is a complex and poorly understood problem.
Considering the complexity and scope of the problem, several asswnptions and restrictions
were made in order to make the problem simple. These asswnptions and the basic equationsI
are given below:
equilibriwn states. The analysis in this chapter gives answer to the question which one of the
equilibriwn states is stable and which one is not.
branches will be <.:ansidered. The morphological equilibriwn condition has already been
analysed by Prof. M. de Vries (1992). It has been shown that 'there are more than one. i .
In this' chapter a simple river system, one m?in bnnch ",hich splits into two co"mstream
CHAPTER-3
THEORETICAL CONSIDERATION
3.1 GENERAL .CONSIDERATIONS
branches can be neglected.
7) The lengths of the two downstream branches are' relatively short, so that the time needed
for the wave caused by the disturbances at the bed to travel through the branches is much
smaller than the morphological time scale of the system.
I) A steady flow is taken into account.
2)
3)
4)
1) .'Themomentum equation for the waterri-lovement
, ,Assumptions
In the experiment it was seen that Engelund and Hansen sediment transport formula fits best.
(3.1 )
(3.2)
(3.3)
(3.4)
(3.(i)
(3.5)
oz as-+-=0at ax
8, = (B2)""'(Q,)'"83 B3 ~3
S = feu)
au au oh oz, ulul-+u-+ g-+ g- = -g--at Ox ax ax C'h
2) The mass balance for the water movement
oh oh au-+u-+h-=Oat Ox Ox
3) The sediment transport equation
From power law the above equation can be substituted as
S=BMu" ,
andn=5
4) The mass balance for the sediment movement'!
.084M=-----Dso fi /',.'c3
So, in Eq. (3.3)'.
12
5) The general nodal point relation which was considered in this experiment
8,= ~(Q2)'"83 ,Q3
where k is a function of the channel width ratio.
So, the equation is-
According to the Engelund-Hansen power law, the amount of sedimen! transported by the
main channel is
. 3.2. THEORETICAL ANALYSIS
The above is, the actual sed,iment transport in channel 2 supplied, by the main channel
according to the nodal point relation.
1. Now, the equilibrium transport through the channel 2 is
(3.7)
(3.8)
(3.9)
13
. 8hiB;L'at = -(S,-S,,)
= (B,)/''''(Q,)"' M Q;/5s, B 'Q ' B'h5. .' / I J
", _(B,)/''''(Q'J'''S, -. B1
Q1
SI
Substituting th~ value ofS2, from Eq. (3.6)
Here
Lj = length of the branch
Sj = sediment transport rate into the branch determined by the node point relation.
Sie= sediment transport capacity of the branch which is equal to the outflowing transport
at the downstream end .
Since the water level at the downstream boundary of the system does not change, the changes'
of the water depths in the branches can be expressed by the following equation
( y.m(Q "mS, B, ) ')SI = B1• Q
1
Now from equation (3.5) if branch 1 and branch 2 is considered
So, Eq. '3.9 for branch 2
8h,B, L28(= -(S,- S2')
8h2 18(=- B
2L/S,-S,,)
hi = height of the branch.
. Now for simplicity it was considered that the main channel bifurcates into two equal width
branches, whose widths are half the width of the main channel, i.e., B 2 = BJ = 1/2 B1•
'B = width of the branch,. ,
. t = time
,}
j
14
(3.1 0)
(3.11)
. 'Q5 1 312ah, _ M I BI l'+.{ ~,h, )m (BI)'at -B; L, [( B, hi ~ ,hill + ~ ,hjll - BJ
1 ~ 2 hjll 5
hJ{ ~ ,hjll + ~ ,hj!'} ]
M = Tr~sport coefficient
m = Power in the nodal-point relation
~; = B,I Lt'
Here
The above two differential equations ( Eq. 3.10 &3.11 ) describe the morphological
behaviour at a bifurcation. These are too complicated to sQlve analytically, but it is possible to
gain qualitative insight in the behaviour of these equations by studying the nature. of the
singular points. As these differential equations contain two variables h2 and hJ, hence these are
cailed planner differential equations. A point (h2>hJ) in the plane is called a singular poirlt if. .both the derivatives vanishes. From the .classical ta\c0r6!"i; .af Paincare and Bendixson, it is
known that the global behaviour of planner differential equations depends entirely on the., I
nature of the singular points. The singular points represent the equilibrium of the system. They
are either stable, neutrally stable or unstable. The mathematical analysis consists of two parts.
First part is' to find the singular points of the equations and second part is to determine
whether they are stable or not.
3.2.1 SINGULAR POINTS
It has already been considered for simplicity that the geometry is symmetric, i.e., B2 = BJ, i2=, .,iJ. It Lz = LJ, then the differential equations simplify considerably and it becomes
straightforward to compute the singular points.
"1 Similarly
(3.12)
(3,13)
(3.14)
So,
15
So, the three singular points are
h2 = 0, h3 = ° and 1\2= h3
Now it is assumed that the width de~ends linearly on the depth, i.e"I,
B2 = a2 h2 and B3 = a3 113
Dividing Eq 3.12 by Eq, 3,13 the following equation is obtained,
The stability' of the singular points depend on the eigenvalues of the Jacobian of the
differential equation, Sy,mbolically the differential equation can be represented as
oh,at = f(h"h])8h]at = f(h], h,)
B, a ,h,-=--B] a ]h]
h,- [Assumed a, = a ,}~ h,
Putting the value of B/B3 in Eq, 3.14, ,
,~,
,'" 3.2.2 THE STABILITY OF THE SINGULAR POINTS
J=
3m+54
15 -3m4
3m+54
15 - 3ni4
af 8f-+-ah, ah,
3m-5-5 ---, 2
If both eigenvalues are' negative, the singular point is stable, but if one of the eigenvalues is
positive it is not. , First the equilibrium state with both branches open is looked at. This
equilibriilm is represented by the singular point (~2,h3)in the general case, For the simple case
B2=B3=(1/2) BI ~d L2 = L3 the singular point is determined at (hI , hi)' The Jacobian at the
point (hJ,hl) is equal to
MQ;32hjBjL,
The eigenvalues are
afah,
The second eigenvalue is dependent on the value of the power m, In the case m <5/3, one
eigenvalue is positive. The singular point at (hJ,h)) is then a saddle point resulting in an
unstable equilibrium. In case m>5/3, both' eigenvalues are negative. The singular point at
(hJ,hl) in now a sink representing a stable equilibrium with both branches open. The two
equilibrium in which one' of the branches closes and all the water and sediment goes through
the remaining channel are represented by the respective singular points (h2'O) and (O,h3). For
these points again the Jacobian are calculated and it can be shown that both equilibrium are
stable incase m<5/3 and unstable when m >513, Figure 3.1, and 3.2 are set up under the
special assumption B2 = B3 =(1/2)B I and L2 = L3 leading to the fact that the line h2 = h3represent a line of saddle points and sinks, respectively, For general values of B2, B3, L2 and
L3 the analysis and figures are more complicated, but do not change qualitatively.
16
It~ eigenvalues are
8f 8f[ah, ah,
The Jacobian is equal to
The above are all for the special case in which the widths and the lengths of the two channels
were exactly the same, as was the bottom roughness. For general values of B2> B3, L2 and L3
the analysis imd figures are more complicated but the do not change qualitatively. Now it is,required to prove that they do not change qualitatively.
the general case may be thought of as a deformation of the symmetric case. For a given
channel network, start out with a symmetric situation and slowly deform the channels until it
reaches the situation as given. During the deformation there are no abrupt changes in the
equilibrium positions. There are three equilibrium, two of which are trivial. If an equilibrium
is stable in the symmetric case, it is stable in the given geometry as well.
This deformation idea can be made precise mathematically. Again' we compute the singular
points. The quotient now'must be
h2 = (i2)5(h2)512(:k. 3)' = (B2)5(L3)512(h2)512(B3)'h3 P 3 h3 B2 B3 L2 h3 B2,
B2)(L3)512(h2)512 '= (~)(h2)712(L3)512B3 L2 h3 a 3 h3 L2
There are two trivial solutions, for which one of the depths is zero, and there is one non"trivial,solution. The differential equation. has three singular points regardless the choice of the
parameters B, L, h. This means that there are no abrupt changes when the geometry of the
channels is defonned, i.e. when the parameters .8, L, h change, stable eq1lilibriu..mremain.stable, unstable equilibrium remain unstable. So, the general case is qualitatively the same as
the symmetric case.
So, it can be seen from the analysis that there are three possible equilibriums. Two equilibrium
situation in which one of the downstream branches is closed and one equilibrium state in
which both the branches are open. It is also clear that tlie value m of the nodal point relation
plays an important role in creating stable and unstable conditions. When m<5/3 the situation
with two branches open is unstable and only a small disturbance is enough to close one of the
branches. When m>5/3 the system always stabilise with two branches open.
17
CHAPTER-4
EXPERIMENTAL SET-UP
The experimental model described herein was constructed on the sand bed in the
hydraulic laboratory of the Water Resources Engineering Department of the Bangladesh
University of Engineering and Technology, Dhaka, during the period of July 1993 to July.
1994. The idea of having the bifurcation set-up was initiated by Prof. M. Vries of Delft
University of Technology with the intention to understand the physics of the phenomena
of sediment transport at bifurcation. The detail of the experimental set-up as well as the .
. measuring techniques are described in the following. articles. General layout plan of the
set-up is shown in Fig. 4.1
" I
4.1 EXPERIMENTAL SET-UP
The experimental set-up consists of two. separate parts, a temporary part and a permanent
part. The permanent part is the experimental facility necessary for the storage and
regulation of the water circulating through the model and the guidance part, The
temporary part contains the actual experimental mobile-bed model of a bifurcation in a
river. It is possible to change the' configuration of this part as and when needed for
carrying out further research on bifurc~tion, using the permanent part of the model
without any drastic constructive changes. The temporary and the permanent part of the
model are shown in Fig. 4.2.
4.1.1 THE TEMPORARY PART
The model of the bifurcated river is built in the temporary part of the set-up. It is a
mobile-bed model with fixed banks. The layout of the channel comprises of a main
branch (denoted as branch 1) which bifurcates into two separate branches, branch 2 and
branch 3. Branches 2 and 3 have different widths. A sediment trap is situated at the end of
each of these two branches, followed by a tail gate for the control of water levels. A detail
)
each of these two branches, followed by a tail gate for the control of water levels. A detail
drawing of the temporary part is shown in Fig. 4.3. In the following sections all elements
of the temporary part are described in detail.
4.1.1.1 INFLOW ZONE
An inflow section and an inflow branch of considerable length are needed to insure equal
distribution of sediment transport, and stable flow conditions before the water reaches the
bifurcation. Water flows from the upstream reservoir to branch I (the main branch) via
the inflow section. PVC tubes (D=2.7 em; L=30 em) are placed over the width of the
entrance to get rid of the larger eddies present in the water coming from the upstream
reservoir and thus the flow is stabilized (Fig. 4.4 and Plate 4.1 ). Immediately after the
arrangement of such flow stabilizing tubes a sandfeeder distributes sand over the width of
the channel . The distributioJ of sand over the width of the channel is done by a wooden, .1
structure which is shown in Plate 4.2.,
4.1.1.2 THE CHARACTERISTICS OF THE MAIN BRANCH
Length (L1) : Before the waterreaches the bifurcation, the sediment from the sandfeeders
should be well-distributed over the width of the branch in a stable flowing conditions.
From experimental experience it is known that a minimum adaptation length L1 ~ 40xh
.(where h is the water depth) is needed to meet this requirement of sediment distribution.
Expected water depth in branch I is chosen to be 10 em which leads to the channel
adaptation length L1 ~ 4.0 m. To make room for the tubes and the supports of the
sandfeeder the branch is made a little longer: L1=4.55 m ( Fig. 4.4 ).
Width (B1): From experimental experience it is known that B ~5xh have the condition of. ,disregarding the influence of the walls. Based on this branch 1 is 1 m wide.
19
4.1.1.3 THE CHARACTERISTICS OF BRANCH 2AND 3
At the bifurcation branch I splits into branches 2 and 3. The radius, length and width of
these curved branches are given below (Fig 4.5).
, Width (B) , Branch I which is' I m in width splits into branch 2 & 3 having an width of
b.4 and 0.6 m respectively.
Radius (R) : To minimize secondary flow inthe bends of these branches the radius R was
selected on the basi~ of criteria R ~5x B and as per discussion with Prof. M. de Vries.
Based on that the values are R2=23.5 m and R)=25.5 m.
Length (L) : The length ofth~ two d'ownstream branches are L2=8.6 m and L3=8.4 m."
-4.1.1.4 CONFIGURATION OF THE BIFURCATION
, The distribution of the sediment transport rate to the downstream branches is governed by, ,
th'e local floW pattern at the bifurcation. From here i~ is seen that the geometry of the
bifurcation plays an important role in this distribution. Therefore the "tip" or "nose" of
, the bifurcation is implemented as a flexible component of the model. The entire model is
made' of brickwork and the nose is made of wood. Three different shapes of noses were
constructed for the this set-up which are shown in Fig. 4.6.
4.1.1.5 SANDTRAPS,
The sandtraps are located at the end of branch 2 and branch 3. The sandtraps intercept all
, the sediment transported through the branches. They 'also prevent the sand to enter into
the permanent part of the model.
The length Ls' of the sand traps is governed by the following equation:
20
The maximum flow velocity in the ,model is determined by the criterion for which only
bed-load transport occurs:
(4.1 )
(4.2)
(4.3)
(4.5)
(4.6)
h W1,. U
=
U. 1-<W-
cU=U.-;g
CUm", =W ;g
C hm",1.,= ;g
,
= flow velocitY;I,
= shear velocity;,u.
u
21
with
Where
C = Ch6zy-coefficient;
W= fall velocity;
This results in an expression for the maximum flow velocity:,
Combining Eq.(4.1) with Eq. (4.4) yields:
The maximum water depth occurs in the C:lse that branch 3 is closed to siltation. In that
case branch 2 conveys all the water, and from Eq. (4.6) it follows that:
;'
22
4.1.1.6 OUTFLOW SECTION
(4.7). - ,-, ,) '-,.fll -V • .(..1ffl
= (BII~B,)
I. Sand trap 2 (corresponding to branch 2): Vs2=0.63m3;
2. Sand trap 3 (corresponding to branch 3): Vs3=0.72m3., ,
The resulting length of the sand traps are (with C=30 m'/2/s): Ls=2.0 m. The sandtraps do
not have a constant width. The widths of the sand traps increase gradually. At the
upstream end they have the width (0.4 and 0.6 m) of the corresponding branch and at the,
downstream end they have the width of tail gate (Bs=I.O m ), Fig. 4.7. The storage
capacity of the sand traps is determined by their length, width and depth,. The available
depth for storage in the sand trap depends on the bed level immediately upstream of the
sand trap. The minimum available depth occurs when the bed level is at its lowest level.i!
Th<:ininimum storage capaciiies of the sand traps are,
a) They regulate the water level in the branch, and
b) They prevent the ~and bed from running dry if a power failure occurs during
experimentation or when it becomes necessary to stop the run for some reason (Fig.
4.8 and Plate 4.3 ).
At the downstream end of the model, the water in each branch flows over a tail gate into
the permanent part of the model. The discharge is measured before spilling into the
downstream reservoir. The tail gates have two functions,
4.1.2 THE PERMANENTPART.'
The permanent part is the hardware 'of the set-up. It acts aS8 facility to conduct all
different types of experiment in the sand bed. The components of the permanent part aregiven below:
.1. Downstream Reservoir
II. Pump
III. Pipe line,
IV. Upstream Reservoir
V. The Regulating arid Measuring System
The components of the permanent part are described below in brief.,
4.1.2.1 DOWNSTREAMRESERVOIR
The doWnstream reservoir (I'!g. 4.9 ) serves as storage reservoir. The volume is II.5m3•
The maximum water level C.ln be at 6.77 m elevation with respect to reservoir bottom.
There is a spillway at the end of the downstream reservoir for excess water to spill out. In
everyone or two weeks the tank had to be cleaned and emptied. The fine particles of the
sediment that are deposited at the bottom are removed through a valve placed at the
lowest level of overflowing spillway.
4.1.2.2 PUMP
The circulating pump near the measuring flume draw water from the downstream.
reservoir. The pump has a maximum delivery of up to 90 Usec and head of 7 m .
.4.1.2.3 PIPE LINE
The lay-out ofthe pipe line is shown in Fig. 4.10. The pipeline has three parts.
(I) Suction pipe line
(2) Delivery pipe line and
(3) Excess discharge pipe line
23
":'
The rate of water flow is taken care of by the pipe line system. The pump sucks the water
from the downstream reservoir irito the pipe line. The T-joint on top of the pump divides
the water over the excess pipe and the delivery or supply pipe, depending on the
regulation of the valves in the respective pipes. As the pump delivers a constant
discharge, the required discharge through the model must be regulated by these valves.
(I) Suction pipe line: It draws water from the downstream reservoir to the pump. It is
1.63m long and the dia of the pipe is a.2m. The suction pipe line is made up by three
pipes. The mouth of the suction pipe is placed .2 m above the floor of the downstream
reservoir (Fig. 4.11 a).
(2) Delivery pipe 'line: The purpose of delivery pipe line is to deliver water from the
pump to the upstream reserv~ir: The length of the delivery pipe is 14.27m and dia of theIi
pipe is a.2m. It has a valve to control water discharge through the model.
(3) Excess discharge pipe line: Its purpose is to discharge the excess water into the
downstream reservoir with the help of the valve which controls the excess water
discharge amount. It is 9.61m long and of dia a.2m.
So, the pipe line consists of three parts. The flow in the channel is controlled with the
help of two valves, one in the delivery pipe and another in the excess discharge pipe.
When more discharge is required in the channel the valve in the delivery pipe line had to
be opened and the other valve has to be closed accordingly. In this way flow of water is
controlled in the channel. The detail of the pipe line are shown in Fig. 4: 12 and Fig. 4.13.
4.1.2.4 UPSTREAM RESERVOIR
The pump draws water from the downstream reservoir and discharge into this reservoir
through the pipe line system. The volume of the upstream reservoir is 4.8 rn3. The
maximum v,:ater depth in the upstream reservoir can be 1.25 m. It has two' chamber one
big and the other is small. Water is dropped into the small chamber of the reservoir from
the delivery pipe line. The main purpose of making the small chamber is to dampen the
24
the following:
The Tail Gates
the delivery pipe line. The main purpose of making the small chamber is to dampen the
turbulence in the water. This small chamber is separated by a wall (with a number of
opening in it) from the large chamber of the upstream reservoir (Fig. 4.14). This is done
to create a smooth inflow into the. big chamber. As undisturbed water is wanted in' the
channel a number of plastic pipes are placed in such a way that water ~asses through
them before going into the main channel (Fig. 4.4). In this way the disturbance w,as
removed. For maintenance purpose the upstream reservoir can be emptied through a
small regulated opening placed at the lower level of the reservoir wall. This also acts as aI, •
storage reservoir.
4.1.2.5 THE REGULATING AND MEASURING SYSTEM
The regulating and measurink system (Fig. 4.15 and Fig. 4.16) of the model consists ofI,,
The stilling Basin Am! Transition Flumes
The Guiding Vanes And Tubes,
The Approach Channel And The Rehbock Weir
The Stilling Basins Connected With Rehbock Weirs
4.1.2.5.1 THE TAIL GATES
At the dis end of the sandtrap of each bifurcated channels the tail gates are placed. The
detail of the tail gates are shown in Fig. 4.8 and Plate 4.3. It is made of cast iron and
encircled with rubber flaps, so that water flows only over the gates. It also has steel'plates
, on both sides for guidance of flow. Ventilation tubes are provided under both tailgates .•
The ventilating tube has a valve at the middle of the tube so that if water gets inside the
.tube it can be drained out. The dis regulation is performed by the tailgates. The flow over
the tan gate is expressed by the following equation.
25
26
4.1.2.5.3 THE GUIDING VANES AND TUBES
(4.8)2"~'q=mB-H -gH.33
4.1;2.5.4 THE ApPROACH CHANNEL AND THE REHBOCK WEIR
To ensure a more smooth flow towards the Approach channels guiding vanes are placed
between the transition flumes and the approach chanp.els which are at right angle to each
other as shown in Fig. 4.16. These v!!lles guide the water around the corner. In order to
prevent 'creation of extra unwanted turbulence in the approach channels, PVC tubes are
used on both the upstream and downstream side of the guiding vanes.
stilling basins as.wellas the transition flumes help destroy turbulence.
The enlargement of the downstream'width of the, sand traps (LOOm for both sandtraps
although the effective width of a tail gate is approximately 0.9 m due to the rubber flaps)
also has positive consequences for the water height over the tail gates, which can be seen
from the above relation.
Behind the tail gates water falls into a stilling basin. In case of branch 2 the stilling basin
is larger than in case of branch 3. This difference is caused due to the available space. The
water from branch 3 has to f~lIow a more n~ow turn (Fig. 4. I 6). This also holds for the .I
transition. flumes. The flume behind branch 2 is much longer. The width of these': ,
transition flumes is equal to the width of the approach channels which is 0.50 m in both
cases. Besides transporting water to the measuring part of the permanent facility, the, .
4.1.2.5.2 THE STILLING BASIN AND TRANSITION FLUMES
The water flows over the tail gate downstream of the sand trap into the stilling basin
before entering 'the approach channel. The approach channels are 5.27 m and 6.12 m long
and both are .50m wide. The approach channel and Rehbock weir are designed according
•••
buffer (Fig. 4.17 and Plate 4.4).
27
THE STILLING BASINS CONNECTED WITH REHBOCK(1.2.5.5WEIRS
4.2 THE WATER CIRCUIT
The water circuit is a closed system'in which water is recirculated. From the Downstream
Reservoir water is pumped to the Upstream Reservoir through the .2 mdiameter pipeline.
Before water enters into main chaimel it passes through the plastic pipes to remove the
turbulence and ultimately passes through the branch 2 and 3. After that water flows
through the measuring flumes back into the Downstream Reservoir.
For the measurement of the «rater height above the Rehbock weirs two stilling basins are
built along the downstream rJservoir. Due to lack of space it was not possible to contract
them next to the weirs. According to ISO 1975, the water level has to be measured at a
upstream position 3 to 4 tim~s the maximum level above the crest of the weir. Hence at• t , ,
such location in each channel a small hole is made in the floor of the approach channel
through which a pipe line was fixed. This pipe line (d=1.5 m) connects the approach
channel with the stilling basing (Fig. 4.17)., The water levels in the stilling basins are
representatives for the water levels at the Rehbock weirs. In the Stilling basin the water
level is measured with 'a point gauge.
to ISO standards, thus avoiding an extra cumbersome calibration. These standard can be
found in the ISO standard Handbook 16, ISO 1438-1975 (E) an.d ISO 1430/1-1980 (E).
The: approach channel should have a miniiiium length of ten iimt:s the width of the
.channel and must be straight and. must have smooth walls, all these conditions are
fulfilled here. The dimensions for the Rehbock weir can be found from Appel)dix A. In
order to measure the water height above the two Rehbock weirs, two stilling basins are
built and point gages are also installed there. The water spills over the Rehbock weir into
.• the reservoir which was made as large as space permits to maximize. the available
,4.3 SEDIMENT CIRCUIT
During the experiment the sediment will be supplied from the sand feeder into the bed at
a suitable rate to avoid local erosion or deposition at the upstream part of the movable
bed, After passing through the main channel and the two branches the sediment will fall
in the. floor of the sand strap, The sediment accumulated in the two sandstraps will be
.weighed, After weighing the sediment it will be left for a certain period to dry and
subsequently will be transported into the silo of the sediment hopper. This recirculating
procedure will be repeated every time,
4.4 SAND FEEDER
To feed sediment and to maintain an equilibrium state in the main channel a sediment
hopper or sand feeder was i~stalled, A sediment feeder is a mechanical device run by
electrical power which feeds sediment into streams of flow of water at measured rates,
and is used for model studies. of rivers. A details drawing of the sand feeder is given in
Fig, 4.18, It is composed of h rectifier, a varia, a DC motor, a gearbox, a gear plate, a
hopper and a sand bucket. The hopper just holds a large amount of sand within it. There
is a narrow slit at the front base of the hopper through which the sand passes out and,
garhers at the rim of the gear plate. As the sand gathers and grow in amount they finally
falls into the sand bucket at measured rates depending on the rotation speed of the gear
plate. The sediment that is feed by the sediment feeder is the same as that of the channel
bed materia!. The calibriltion curves of the feeders are presented in Fig. 4, 19a & 4.l9b,
The sediment falls from the sediment feeder into the wooden structure which dist~ibute
the sediment uniformly over the main channel width.
4.5 SEDIMENTS
The sediment that is specifically chosen for this experiment was bought from the market.
,Then .it was washed, with water so that there is no dirt in it. Several samples was taken
from the washed and unwashed sand for sieve analysis in order to find the grain size
28
distribution. The grain size distribution of washed and unwashed sand can be seen from
Fig. 4.20.
4.6 THE MEASURING TECHNIQUES
In this section the measurements to be made during experimentation are discussed.
Measurements will have to be made of the parameters describing a bifurcation. One of the
aims of the experiments is to study the distribution of the sediment transport rates at a
bifurcation. For this reason a relation was taken into consideration which is given below:
(4.9)
The unkno~ parameters S2, SJ ,Q2 and QJ have to be measured. The measurement of the
waterlevel and of the bed level are also necessary to be measured.'
The factor m is dependent on the geometry of the bifurcation.: !
The factor k is dependent on the widths and also on the value of m (Chapter-3).
The morphological behaviour of the, branches, as a function of the shape of the
bifurcation, is of great interest. For this reason the bed level in the branches must be
measured.
The measurements of the water at the ends of branches 2 and 3 are necessilry for the
setting of the downstream boundary c~nditions.
'4.6.1 DISCHARGE MEASUREMENTS
The discharge is measured at the Rehbock weirs. The individual discharges of branches 2
and 3 are me,asured with the respective Rehbock weirs. These weirs were made according
to the specifications mentioned in ISO (I975). Details of the Rehbock Dimensions are
29
given in Appendix A. The water level at the crest of the weirs is measured in stilling
basins with point gauges, with an accuracy of 0.05 mm. The zeros of ,the point gauges
were set by fiJ.lingthe two approach channels with water up to the crest level of the weirs ..
The point gauges were then adjusted and in this. way the zeros were fixed. The Rehbock
weirs each can measure the discharge properly up to a discharge of 60 lis, with an
accuracy (in the worst'case) of 1.8%. This is detailed in App~ndixB.
4.6.2 . SEDIMENT TRANSPORT MEASUREMENTS
The sediment transport rates in branches 2 and 3 are determined with the help of the sand
traps located at the end of each branch. These sand traps intercept all sediment,transported through the bran6hes. Once a sand trap is emptied and its content measured,
the average sediment transplrt rate for the preceding branch is computed for the time-
interval observed. This is dohe by dividing the amount of sediment by the time elapsed.
The sand traps do not have to be filled completely. It is strongly recommended not to do
so, since the value for the tate obtained would be insignificant. The shorter the time,interval, the more information is obtained on the sediment transport. The sand traps can
be emptied once the model is put to a standstill. Water is always present in the model., ,
The way of removing sediment from the sand traps is to place stop logs in the slots
directly upstream of the sand traps, siphon out the water, and then scoop out the sediment
by hand (Plate 4.5). The method is time-consuming but still this is ,the method which has
been followed here. After the water. is siphoned out, the sediment is taken out from the
sand trap with the help of buckets. Six buckets were used and they were numbered. For
each bucket a chart was developed for weight Vs water weight (Appendix C). So if
weight of water is known the weight of sediment can be easily known. For measuring the
amount of sand in the sandtraps the following procedure is followed. Buckets filled with
sand and water are compared with buckets filled with only water. In this way the
submerged weight of sand was found out. After that the sediment is spread in a thin layer
.across the floor of the laboratory to let it dry. Drying takes about three days. This weight. ,
is translated into a volume (density of sand ps=2650 kg/mJ, porosity p=40%). It is useless
30
31
4.6.3 WATER LEVEL MEASUREMENTS
,for the time interval chosen. The tra.'l~part m:e will varj continuously, but it is not
possible to measure these variations. The only way to get more detailed information on.i
the change in transport rates is to shorten the time intervals for which the sediment
transport rates are determined.
. to define an accuracy for the sediment transport because the tra.."J.3pc~rate is an average
•be measured with it. As can be seen in Plate 4.6b the stilling basin is completely closed,
i.e. there is no connecting hole from basin to branch. The water is siphoned into the
stilling basin via a Pitot tube mounted on a frame laid "cross the width of the channel.
The pitot tube can be moved to different spots in the channel so that it is possible to
measure the water level at different places near the bifurcation.' This may be necessary if
different shapes of "noses" are applied which each induce different local flow patterns ..It
must be that the pitot tube is merely used as a siphon and not as a measuring device; The
readings are taken with a point gauge in the stilling basin which gives more accurate
reading. The water level reading at four stilling basins are taken at every 30 minutes
intervals during experimentation in order to ensure the correct boundary conditions.
The water level was measured at four places in the modeJ. The 'stilling basins are placed. ,
at the beginning and end of each branch (Fig. 4.2 I). The stilling basins I, III and IV are
fixed stilling basins. They render the water level present in a fixed place of the adjacent
branch, namely the water le~il immediately in front of it. It can be seen from plate 4.6aIi
that water passes through a Hole in a wooden palate fixed in the wall of the branch. This' , .
wooden plate can be moved up and. down to ensure that the seepage hole is always
located between the water level and bed level. Stilling basins III and IV are placed
directly upstream of the sand traps. They are used together with the tail gates to regulate
the stream water level. Stilling basin II, which is located near the bifurcation, is a flexible
stilling basin. The water levels at different places in the '1icinity of the stilling basin can
The water level in'a stilling basin is r"eii5llicd .wi;I-, ii jJ01nt gauge. The zeros of the four
point gauges were set by tilling the branches of the model with water which made a
horizontal ~eference level to which all four gauges were related. The accuracy of the
water level measurements is determined by the accuracy with which t~e zero was set. The
error in h is defined as:
The bed level 'was measured with a point gauge in which a .special pin is used. A square,
plate of 2x2 cm2is fixed to the point of the pin to prevent it from sinking into the sand
bed (Fig: 4.22),. The gauge is mounted on a frame which is laid across the channel on the.
branch walls. The bed level is measured at intervals of 0.5 m, in 39 marked cross-sections
of the three branches (Fig. 4.23). In the main branch the bed level is measured at 10
(4.10)
32
er is the error made in the reading;,
ez is the error ~ade in the setting of the zero;
2sm is the errohn the mean of the ;eadings.
.J2 2 2Eh = Er+C:z+4cr'
ll
where
i ".The point gauges have a Vernier scale, so er=0.05 mm and ez = 0.05 mm.
The'standard deviation in the mean often readings was Sm= 0.03 mm.
As a result the water level can be measured with an accuracy eh = 0.09 mm.
. . ,4.6.4 BED LEVEL MEASUREMENTS
,points at each cross-section. In branches 2 and 3 the bed level was measured at 5 points at
each cross-section. The bed level is measured two times in a run, one before starting- the
pump and the other after stopping the pump. The measuring gauge is placed on a wooden
frame which is laid across the width of the channel at one ofthe'croS's-sections previously
mentioned (Plate 4.7). The gauge can slide on the frame across the width of the channel
in order to make a measurement at the desired point of the cross-section. The frame is
made of wood, which deflects slightly' when placed across the channel. This deflection is
"
with which the bed level is measured. The supporting frame is placed on the walls of thebranches.
4.7 TEST RUNS, '
To check the efficiency of the model some test IllilS were made. The test runs were
carried out with the help of a particular type of seed which was selected from a large
variety of seeds. This particular type of seed moves by rolling along the bed of the, .
channel. This movement of tile seed demonstrates the bed load transport which is desired
in the experiment. At least 2Qtest runs with four different discharges were carried out and' !I
the results as shown in Fig. 41.24show that the model is acceptable..• I'
I
33
CHAPTER-S
EXPERIMENTAL PROCEDURE
First the model was constructed as per requirement of the. objective of the experiment
keeping in mind the flexibility needed in such experimental, set-up t,o carry out further
studies in future. The construction period was nearly one. year. For conducting the
experiment the following pro~edure was followed. Running the experiment and collecting
data required not only a great ~eal of physical work but also a careful observation.
5.1 BEFORE STARTING THE MODEL FOR ,EXPERIMENT THEFOLLOWING TmNGS WERE DONE
STEP} :
Sand of grain size of d.3l=300 ~m was selected from the market and washed with water so
that there is no dirt in it. After that sieve. analysis was done in ord~Tto find t.h~llTHinsi7.e, . ' ••....
distribution. From the lot of the sand ,ten samp!~s were taken at rarldom in order to find the
grain size distribution. The results of the ten samples were very close and with the average
value the grain size distribution curve was drawn (Fig. 4.20).
STEP 2 :
Before running.the rhodel several runs were needed in order to find whether the Engelund-
Hansen equation carl be used for this model. This is required for estimating the amount of
sand that should be fed from the sand feeder during the experiment.
STEP3 :
The efficiency of the sandtraps were tested by running the model several times. This is a
very important item. The main purpose of the experiment was to know the amount of the
sediment being transported in branch 2 and 3. If considerable amount of sediment passes
o,ier the two tailgates t'1en it is not possible to know correctly, how much sand actually, ,,passes through the two branches. It hilS been seen that if the discharge is less than 45 Vsec
through each branch of about, 4% sediment passover the tailgate. The data below will give aclear idea about this statement.
STEP 4
All the items such as stilling basms; hook gauges, point gauges, tail gates, stop locks and
other items Were checked whether they were working well and whethe~ these were in theright place of the model.
,STEPS
A method is developed for relating all water level and bed level measurements to a specific
reference level. First the model 'will be filled with water to a certain arbitrary level (z)
above the laboratory floor. In case of no water movement this should provide a perfectly
horizontal reference level. This reference level will be measured with the equipment which
will be used for measuring water levels and bed levels during the experiments. There is no
need to adjustthe zero's of the measuring instruments to this arbitrary reference level. For
each measuring instrument a reading (r) will be obtained corresponding to a water level or
. ,
35
).
,~
bed level, having an elevation ofz meters above the laboratory floor. For any other reading
, (reDthe elevation of the water or bed level above the laboratory floor can be computed using. ,
Eq. given below
elev.= Z - r+rd
STEP 6 :
Calibrating the instruments :
(1) Sand feeder, The sandfeeders have different speeds. At different speeds the rate of
sand outflow was measured td a caljbration curve was developed, For each speed three
measurement was carried out 10 make the calibration curve more accurate. The calibration
curves of the two'sandfeeders were given in Fig. 4.19.
(2) Discharge of water will be measured by two Rehbock weirs. The calibration chart of
the tWoRehbock weirs was made by a standard equation. For detail see appendix A.
, .,
(3) Two valves in the pipe line was calibrated in order to attain desired discharge for a
particular rUn.
, 5.2 DURING, THE EXPERIMENT THE FOLLOWING THINGS WEREDONE:
In order to have good experiments proper handling of both the temporary and permanent
part of the model is required. After the construction of the model considerable time was
spent in order to get knowledge how to run the model properly. A sort of manual has been
resulted from both the knowledge gathe{ed from running the present model as well as with
the advice and remarks from experienced people in this field.
In a particular run of certain discharge for a particular shape of nose or tip, the following
steps have been followed.
36
STEP ONE :
The first step is the fixation of the discharge. Both the excess and the supply pipe line have
valves for the regulation of the discharge. A valve influences the flow rate by changing the
flow area locally. It.is done by the vertical movement of a round steel plate inside the valve.
A wheel on top of the valve is turned to determine the vertical position of tpe steel plate.
Before starting the purnp the valves in the excess and the qelivery pipe line should be
closed. Sufficient depth of water in the downstream reservoir should be present before
. starting the pump. After that by adjusting both the valves, the desired flow rate through the
model was achieved. When the desired discharged was achieved the key from both theI .
valves were removed so that n\Jbody can tum the keys anymore.
STEP TWO:
After selecting. the discharge the pump should be stopped and the sand feeder should be
checked. Even though the sand feeders were calibrated it should be checked before every
run to check whether they feed sand according to the calibration charts. From the Englund-
Hansen formula, the amount of sand that a certain discharge would carry can be calculated.
From the calibration chart, the speed of the s2.nd.feeder was found '.'lith respect to the
calculated amount of the sand. Then .the sand feeder was checked thTee times, whether at
that speed it drops the desired amount bf sediment. After that the sand feeder was stopped
arid water was allowed to drain out from the temporary part of the model. This was done to
dry the. sand lying on the channel bed.
STEPTHREE:
After completing the above two steps the next step was to siphon water from the two sand
traps. This was done by the help of two one inch dia rubber pipes. The siphoning process. ,normally takes 3 to 4 hours.
STEP FOUR :
aefore doing an experiment on the model of bifurcation it is very important to prepare the
bed. The bed preparation has always been done after fixing the discharge, because in this
37
way, the prepared bed will not be disturbed. If the bed is prepared before fixing the,
discharge, ,the bed may be completely destroyed while adjusting the desired discharge.
Another thing should be' kept in mind that one should not do the experiment with an
, arbitrary bed, because more than ten rUns were given with arbitrary bed in which six runs
gave tlldesired results. In that six runs sediment was transported only in one branch, but the
goal of the experiment is to find both S2 and S3' So it is advised, not to work with any"
arbitrary bed level because in that case, one may lose valuable time with no desired re,suIts.
So, before doing experiment with the model, it is necessary to have some idea of the
normal depths of th~ branche~ for a certain discharge. In fact it is impossible to predict the
normal depths because of the' fact that at this time the distribution of sediment in the two
downstream branches of a bifurcation is not known. A method has beel) developed by, '! ,which one can guess the normal depths by taking some assumed value of ni and k, since
normal depths has very little dfect by the variation of m and k. This method is much better
, ,because at least one has som~ idea about what will happen in the model. These calculatedi
depths should be provided in the model. The normal depths were calculate,d by using the. I .
following eight equations:
).
Where,
h = Q 8 (-115) B (-4/5) M(1I5)2 2' ,2 • 2 •
h =' Q 8 (-115) B (-4/5) M{1I5)J J' J . J .
. =Q (-1) 8 (J/5) B (215)'M(-J/5) C(-2)12, 2 • 2 • 2' •
. - Q (-I) 8 (J/5) B (2/5) M(-3/5) C(-2)IJ - 3 • J • 3' •
QI =Q2 +Q3
8( = 82 + 83
i2.L2 = iJ.LJ
82/8J = k. (Q2/Q3t
M = M as used in the sand -transport formula S =BM.un
C = Chezy value
B = Width of the channel branch
38
•
(5.1)
(5.2)
(5.3)
(5.4)
(5.5)
(5.6)
(5.7)
(5.8)
First the upstream discharge was chosen and then the ratio Q~/Q3was chosen. From QZ/Q3. I . ,
and Q, the value of Qz and Q3 was found. Than by solving eight equations simultaneously
the normal depths in the three branches were found. A program' has been developed in
QBASIC to find ,the normal depths by solving the eight equations simultaneously
(Appendix D). This method also helps in checking whether the velocities in the ,branches
dominate only bed load transport or not. It has been found that if the velocity in all the
branches are more than .22 m/sec, then for dso=.027 mm the bed 'load transport
predominates. When the normal depths of the branches has been found the next thing is to
cal~ulate the d~pths of bed fot all 39 sections. Now from the calculated depth, at differentI
sections; the bed was preparetl. During the preparation of the bed the sediment should be
dry enough otherwise, it is nbt possible to prepare the desired bed level. For that reason
after draining water from the channels at least 10-15 hours time should be, given to let the
sediment in the channel to dry. When preparing the bed the depth of water in the upstream
reservoir should not be greater than 0.7 m otherwise water will enter into the main channel. .
STEPS
After preparing ,the bed the tail gates were lifted to its maximum position. This is done
because, the next thing is to fill the temporary part of the model with water, so, no water
should be allowed to' pass over the tail gates. '
STEP6 :
Once the bed is prepared, the channels will be filled with water. This step has to be done
very carefully because a slight mistake can damage the prepared bed.By the help of a half
horse power pump both the sandtraps were filled simultaneously upto the concrete floor of
the channels. When. the water level reaches the floor level of the' branches the sandtraps
were filled very slowly so that the bed is not disturbed. First the sand will be wet and after
that water will move slowly towards the nose of the bifurcation. Attention should be paid,
so that water in both the branches moves toward the bifurcation point simultaneously. When
water reaches the nose from both the branches, the upstream reservoir was very slowly
, filled with water, With the plastic pipe, which was connected to a tap near the upstream
39
or less at the same time.
,~,filled with water, with the plastic pipe, which was connected to a tap neat the upstream. ,reservoir. The upstream reservoir should be filled in such a way that when .water coming
from both the sandtraps reaches section- I ,water from upstream reservoir should also reach,section~I. This' filling process continued until the depth of watt<r in the branches reached
. ISm. By this process the disturbance in the bed was removed. In order to develop this
te~hnique which is very important a loi of time was spent.
, STEP 7: , I' . ..,When the channels are filled with water upto .ISm, 2 to 3 hours time have been given for
the water to settle. After that all the water level measuring instruments were checked,, .
whether these were working well with reference to any arbitrary water level. The pitot tube
of stilling basin 2 was checked and also the silo of the sand feeder was checked whether it is
filled with sand or not.
STEPS
Now it is time to take the initial bed level reading. This initial bed level reading should
however. be taken at least 2 to 3 hours after filling channels. The bed level reading was
taken by point gauges. For sections I to 12, 10 readings were taken at each section and for" '
sections 13 to 39, S'readings were taken at each section.
STEP 9,
Now.the pump was, ~tarted and water was allowed to rise in the temporary part of the
model upto .20 m. Care was taken so that the pump and the sand feeder were started more,
STEP 10
When water depth reach near .20 m in the branches the tail gates were opened very slowly
to the desired level. The tail gates should be opened at the same time and with care so that
there is no sudden disturbance in the bed of the branches.
40
,r
STEP 11\ ,
After setting the tail gates to their desired levd the depths Of w~ter in the branches were
checked by the help of four stilling basins; It was also checked whether the sediment
movement occurs in both, the downstream branches. Readings, of the Rehbock weirs were
taken after about 20 min. of running the model and the discharge was checked whether the, .model was running with the desired discharge. If the discharge is not very close to the
desired discharge; the tail gates were lifted and the model ~as stopped. Then the steps I to
II were repeated until the model was found running with desired discharge.
STEP 12 : '
The readings of the stilling basins and the Rehbock weirs were taken at every half an hour.' ,
and quarter hour intervals, respectively. The first readings were taken after half an hour of
running the model.
STEP 13 :
After completing the eleven steps the model was allowed to n,m for 8 to 10 hours and data
wascollected as per step 12. From practice, it was seen tha~ by this time good amount of, .sediment stores in the sand traps.
STEP 14 :
After running the model for about 8 to 10 hours, the tail gates were raised simultaneously to
their maximum position very slowly and then the pump was stopped. The tail gates were
raised ,;ery slowly so that there was no disturbance in the char1nel beds. The sand feeder
was also stopped at the same time.
STEP 15 :
When the model was stopped\ about 2 to 3 hours time was given for the water lev~1 to,settle. Then the bed level reading was taken. This was done in the same process as before. .(step 8) and that gave the final bed level reading.
41
42
STEP IT
.CONSTRUCTION,
STEP 18 :
,After the bed level readings were taken the stop locks were placed in its position. After
plaCing the stop locks,' two rubber tubes were placed between' the stop locks" and the
concrete walls."Then the tubes were air pumped by a pumper so that no water or sediment,passes through the 'stop locks. This was done because the main purpose was to measure the
sediment in the sand traps.
When the stop locks are water tight water from the sand traps were siphoned by the help of
two plastic pipes. Care was taken so that no sediment was siphoned out. After the water was
siphoned out from the sand traps the sediment was collected and weighed. This was the
amount of sediment that passed through the two channels for that particular runtime.
STEP 16':
After weighing the sediment from the sand traps the sand was allowed to dry for several
days and'then they were ready for the next run.
i) Instrument Fabrications :
In designing the'Rehbock weirs, Guidevanes, Tailgates and Stoplocks various kinds of
problems were faced. It was very difficult to build them according to the ISO specification
because of scarcity of required materials and inadequacy of experience in such field.
1.. DURING CONSTRUCTION OF THE MODEL
,S.3 PROBLEMS FACED DURING MODELOBSERVATION AND DATA COLLECTION
'ii) .Civil Work :
It is' obvious that skilled mAson .will not be available. Normally the masons are all
experienced in constructing buildings and other structures where aq;uracy is not so much
important. They are not expelienced in constructing a physical model where in some places
accuracy of less than' 0.5 % is required. So, due to this the construction of the model took a' ,
long time. Also it was seen that the model was not water tight,in many places. To make the
model water tight a considerable amount of time was spent.
iii) Inaccurate Measurements :,
Duling constructing .of the model VaJ10USproblems were faced with many components
made of steel. Initially a lot errors were made while constructing these components in the
workshops. So, it was decided that a prototype of exactly s~e size of all steel structures
will be prepared with cartoon paper and then it was supplied to the workshop for
construction. This process also took much of the time but the result was very good.
2. PROBLEMS AROSE DURING CALIBRATING THE SANDFEEDER :
i) Duling the. time. of construction of the model attempts were taken to cfllibrate the
sandfeeders. Sandfeeders were lying in the laboratory for a long time and needed substantial ', ,
repair work, before calibrations. So, both the sandfeeders were sent to the workshop for
repair work that also took a long time., ,
Ii) When the sandfeeders were, ready, they were tested and it was seen that at a particular
speed the sandfeeders were giving different outp4ts. Soon.it was realized that this problem
was due to the different ~oisture contents of the sand. To get lid of this problem the sand
was dlied and kept in a particular storillg place constructed within the laboratory. This gave
, good results.
3. PROBLEMS WITH THE SAND
The problem with the sand i'as that it contains a large amount of dirt. At the beginning
. several runs were carried out with un-washed sand. The problem with unwashed sand was
that the bed and the sandtraps could not be seen clearly. There were also problems with
Rehbock weirs because of the facts that a large amount of dirt was passing over the
43
permanent part a'ld small holes were' clogged ".•.ith dirt. So, after running the model for five
to six hours, the stilling basins, readings of the Rehbock weirs were different from the initial
readings. Another problem is that after every run the whole model has to be cleaned which
is a very difficult and time-consuming task. It was tried to see how the running of the.model
with unwashed sand will help to rem~ve the dirt. It was observed that this process will
takes' much longer time than washing at first. To overcome these difficulties it was decided
, that first the sand will be washed and then it will be used.
4. PUMP:
i) The problem with the pump was that it was not running according to its specification.
The discharge was not more than 25 Usec even though as per specification' it should have
been much more. So, the pump was tested in the laboratory of the Mechanical Engg.
Department and was found not suitable. So, after detail calculation taking into account the
present and future research requirement a pump of90 Usec capacity was purchased.
ii) ,.The next problem with the pump was when it was sucking water, due to less depth of
wat~r (.77m) in the downstream reservoir, a vortex was created. The vortex made a big
fluctuation in the discharge due to time to time air sucking through this vortex. In order to, "
get rid of such vortex some wooden' frames were placed on the water surface as a easier,
solution. This did not improve the situation substantially. Hence a portion of the
downstream floor (1.5 x 1.5 m2) was lowered by 1.5 m to give sufficient submergence of
suction pipe of the pump (Fig. 4. I la). This gave good results.
5, PIPELINE:
If the layout of the pipeline is not proper various kinds of problem may arise. In the model
the first layout of the pipeli~e (Fig. 5.1) was not proper and this resulted in negative
pressure at certain location of the pipe line. This also created too much disturbance in the
upstream reservoir when the water drops from the pipe ,line. So, it was decided to lower the
layout of the pipeline. The pipe line was then lowered and this gave good results.
6. WATER:
There was some problem with availability of water. The storage capacity of the downstream
reservoir was constructed as big as possible with the available. storage space keeping in
mind the functioning of various components of the experimental set-up. The storage
capacity thus created was not enough to run the model without adding water from the direct
line atth~ starting of the experiment to fill-up the channels, sandtraps etc. This requirement
of additional quantitY of water from direct line could not be met most of the time. In order
to solve this problem all the storage tanks in the laboratory were checked and it was found
that the storage t~ of the 70 feet flume may be used for this purpose. Accordingly every
day at night the 70 feet flume's reservoir tank was filled with water and later on with the
help of a half horse power pump water was supplied to the model from that tank ( Plate.
5.1). Thus the problem was solved.
7. DISTRIBUTION OF SAND OVER THE WIDTH OF THE CHANNEL:
To ensure proper distribution of sand that is fed from the sandfeeder over the width of the
channel was a difficult task. First attempts were made with a 0.10 m dia. plastic tube. The
plastic tUbe was cut into halves along the length and then on the periphery of one half, holes
were made and then it was placed in an inclined position to distribute the sand across the
width. This process did not serve the purpose properly. After that another attel)1ptwas made
with that plastic pipe but this time the holes were made in such a way that when the half.. .section was placed in an inclined position the smaller holes were at higher elevation and the
bigger ones were at the lower elevation. This improved the distribution of sand over the
width but did not satisfy the requirement. At last a wooden structure was constructed by
trial and error method to help distribute the sand and this gave the desired result (plate 4.2).
45
, '.
CHAPTER-6
DATA .ANALYSIS, RESULTS AND DISCUSSION
, Data on sediment movement and distribution over the two downstreanl branches of a
bifurcation were collected from the laboratory model which was developed for this. , .
'purpose. The intention was to understand the physics of the phenomena of sediment
transport at a bifurcation. The data were collected mainly relating to
(a) Anabranch discharges Qz and Q3'
(b) Anabranch average sediment discharges Sz and S3'
(c) Average water level of all the three branches.
(d) Initial and final bed level readings of a run at all the 39 sections.
These are all described is detail in article 4.6. For the purpose of data collection, two
sets of runs were carried out. In the first set there are 2! ru..'!s a..'!dirr t.~e secorrd set t.h.ere
are 20 runs. The first set is with the reference nose and the second set is with the second
nose.
The. 21 runs with the first nose is divided into three groups. The first group contain 8
runs with discharge around 30 lis. The second and third group, contains 6 and 7 runs
with discharge close to 40 and 20 lis respectively. The 20 runs with nose 2 again were
divided in three groups. The first group contains 9 runs with',discharge 30 I/s. The
second and third group contains 6 and 5 runs with 40 and 20 lis respectively. In all the
runs of a group it was tried to keep the total discharge and the sediment input rate
constant. The main purpose of all the' runs were to study whether the value of m and k.1.
in Eq. 3.5 vary with discharge or not, for a particular nose. Visual obserVations were. .!
made during the period with a view to study the pattern and the process in channel
. bifurcation, evolution and morphology of the bifurcation of model channels.
Photographs were also taken during the run.
. 'I'
6.2 INCIPIENT MOTION
(6.2)
(6.1 )
. .
4-7
uJgU.=-:-
:C
and
6.1 COMPILATION OF DATA
6.2.1 MODE OF TRANSPORT
Froin all the experiments the value of 1:. and R. were calculated and they were found
within the range of .09 to .25 and 86.54 to 195.31 respectively. This shows tlUtt they
were all above the Shields curve( Fig. 2.4 ). So, it can be said that in the present study
flow range were sufficient to make sediment in motion.
, .To check wh.ether the transports are bed load or not. For all the runs, .U./W was
calculated and they were found less than 1 which indicates that all the transport in all
the branches of all the runs were moved as bed load.
Here
The present research was aimed to understand the physics of the phenomena of sediment
transport at a' bifurcation and to try' to develop an empirical 'relation to calculate
sediment transport rate in the two downstream channels at, bifurcation. To do this a
, nodal point relation was assumed (Article-3.1) in which there were. two constants m and
k. Accordingly laboratory experiments were carried out for different sets of conditions.
A total of 41 runs were conducted. The bed level evolution at different sections of all the
runs or'the three branches are shown in Fig. 6.1-6.41. Fig: 6.1-6:21 is for the first nose
and Fig. 6.22-6.41 are for the second nose. The variation of discharges with run time of
, all the three branches of the 41 runs are shown in Fig. 6.42-6.47. Fig. 6.42-6.44 are for
the first nose and 6.45-6.47 is for the second nose. In the following articles detail
discussion on observation and results are made.
j,
6.3 BED LEVEL EVOLUTION
The bed level evolutiop of the three branches of all the runs are shown in Fig. 6.1 - 6.41:
As it was mentioned in Chapter-5 that before starting the model for a particular run the
bed wasp'repared with 'the normal depths. These calculated normal depths are not the
accurate depths because here the value of m and k are assumed aild it is still not known
how the sediment will be distributed at a bifurcation. This method is used just to get an
idea whether the model normal depths are near the ,calculated depths or not and also to
save time so that there is no run in which szls) is very large or zero. Run NO.2 is an
example where s2/s) is negative in value. So, this run can not be used since unrealistic
result occurred. The problem with Run NO.2, was that in branch 2 bed level was 25
cm lower and branch 3 was 15 cm higher than the normal depths respectively, so all the
sediment went through branch 2 because it was lower than the normal depths at the
beginning. 'Branch 3 at the beginning had a lot of sand in it. So, from this it is learnt that
one should not deviate much from the normal depths otherwise undesired result may
occur. It should be noticed that in all the fW1S branch; had the least change (Table 6.1
to 6.6 ) of bed level because it is upstream of the bifurcation point. The main objective
, was to keep the main branch (I ) more, or less in equilibrium and to. pass as much as
possible the amount of sediment that is being supplied by the sandfeeder. In all the runs
more or less it was achieved. For the first nose except Run No.2, in all the runs one of
the two downstream branches were kept only a few cm higher than normal depth and
other was a few cm lower than normal depths. In all the runs of nose I it can be seen that
deposition occurred in the branch which was lower than the normal depths, and scouring
or' erosion occurred in the branch which was higher than the ~orrhal depths. So, from
this it can be said that the assumpted nomal depths were not very far from actualI
normal depths.
In case of second nose it can be seen 'that the normal depths relation was no longer,
helpful. In all the run of Nose 2 it can be seen from Fig. 6.22-6.41 that the bed level of
branch 2 was getting higher and higher and most of sediment that was fed by the sand
feeder was being ,carried by branch 3. This behaviour was different from nose-I and the
calculatea normal depths were completely different. The reason behind this is, in the
first nose .the ratio of the widths of the two branches at the nose was the sameo! the ratio
48
. Run NO.1 to 8 were with 30 IIsec. In Run No. I branch 2 was higher than calculated
normal depths and branch 3 was kept lower than the normal depths. It was observed in
this run that there i'sdeposition in branch 3 and erosion in branch 2. In Run NO.2 branch
2 , was lowered and branch 3 Iwas kept quite high. In this run almost all the discharge"and sediinent wen~ through th6 smaller branch. From observation of these two runs itI .
was concluded that this type of run will not give required result. So, in all the runs from
3-7 the channel bed was fixed jn such a way that depth of flow was more or less same asI
6. 3.1 RUNS WITHTHE FIRST NOSE ( BED LEVEL EVOLUTiON)
49I
the calculated depths. All these runs gave realistic data. After completing 7 runs, data
obtained from six runs neglecting Run NO.2 were used and the value of m and k were/' : .
comP'lted. With results so obtained the bed of Run No 8 was prepared and experiment
was carried out. From Fig. 6.8, it can be seen that there is no change in bed levels in all
the three branches. In Run NO.8 at the beginning of experiment the average depths in
branches 2 and 3 were 261.5 and 263.13 mm and at the end they were almost the same.
So, it can be inferred that the equation of nodal point well fits with the situation.
,first.nose the ratio of the widths of the two branches at the nose was the same of the ratio
of widths of the two downstream branches but for the case of the second nose it was not.
Due to this an additional disturbance was there. In order to encounter this sit)lation there
should be some change in the nodal point relation or the branches widths should be 20
and 80 cm respectively of branch 2 and 3. So, the bed level changes due to nose-I can
not be compared with those due to nose-2 since the situatio,n are different. Also in
branch I of all the runs except for the 20 lis runs section I-I at the end of the run, goes
far below from the initial position. Section I-I is just 0.8 m below the point where water
enters into the model from upstream reservoir and just 0.5 m below the section where
sand was falling into the model. When water enters into the model from the upstream
reservoir in case of 30 and 40 lis ,due to initial disturbance the bed level goes down in
section I-I. Also it has been seen that section 1-1 goes down to a certain point for a
particular run and after that it does not go down any more. This can be seen in run no 3,
4,6,7 and 8.
, c
"
Run 9 to 14 were with 40 Usee. In Run NO.9 branch 2 was,kept much higher than, ,
normal depth and branch 3 was kept much lower than normal depth. In this run it was
seen that bran~h 2 was eroded and branch 3 deposited, In run 10 and II the bed levels'
were kept more or less near the calculated normal depths, It can be seen that there were
less changes of bed level ( Table 6.2 ). In Run No. 12 branch 2 was made lower and
branch 3 was higher than the calculated depths which was just the opposite of run no. 9.
Here it can be seen that there was erosion in branch 3 and deposition in branch 2 (Table
6.2). This proves that the actual normal depths are very close to calculated normal
depths. In Run No. 13 and 14 in both the downstream branch, instead of making whole
branch higher or lower then the calculated nonna! depths only same se<;;tionswere made
higher or lower. In these two runs the tot?J hed level cha.!lge in volume. of the two
branches were not much but the sudden ups and downs in some sections caused
irregular final bed level.
Run no 15 to 21 were carried out with 20 Usee. Run No. 15-19 were carried out in the
same process as before ( earlier runs) and the similar results were observed. Relating to
runs with 20 l/s, it may be mentioned that section 1-1 did not go down like the
previous runs with 30 and 40 Us.This is because here the discharge is less and hence the
'disturbance at the inflow zone was small enough not to cause any scour. After
completing the 5 runs (15-19) the value of m and k were determined and the initial bedI '
level of Run No. 20 was preP1rredwith these values. It can be seen from Table 6.3 that" ,
minimum bed level change pccurs and almost all the sand that was being fed were
carried a:way. After that another run was carried out with different QiQ3 ratio to see if
the value of calculated m and k vary much but it did not. So, the calculated .value of m
and k were c<;Jnsideredto be correct for 20 Us discharge.
'6.3.2 RUNS WITH THE SECOND NOSE (BED LEVEJL,EYOLVTION);
Run no 22 to 30 are done for 30 Usee. After running the 22nd run it was seen that it was
not behaving like the previous runs. In this run the bed level of branch 2 was getting
higher with run time and the discharge in this branch was getting lower and lower as the
time goes on. The reverse thing happened in branch 3 but here the bed level was not
'lowered rather little deposition occurred in it (Table 6.4). This result provoked to'
50
;'
'lowered rather little deposition occurred in it (Table 6.4), This result provoked to
continue the same run for longer period, So, Run No, 2~ ,to 26 was carried out as
continuation of Run No, 22. It can be seen from Fig. 6.23 and 6.24 that the bed level of
branch 2 was increasing and the amount of sediment trapped in trap 2 was de~reasing.
On the other hand the sediment in 'trap 3 and also the discharge of branch 3 was
increasing from run to run. In Run No. 25 and 26 it was seen that there was no change is
bed level and discharge. So, the run was stopped and it was decided to continue with a
new prepared bed with different Q/Q3 ratio. Rim No. 27 to ~O was done for this
purpose and siI?ilar evolution in bed level had been observed like Run No. 22 to 26.
So, tills gives all idea that the nodal point reiation was no ionger appropriate for this
situation because there is an extra disturbance due to additional restriction imposed by
the nose. In the same way for 40 and 20 Usec run were carried out is order to see what
happens for the value of m and k.
Run No. 31 to 36 were done with 40 Usec. In this runs 3 I to 33 and 34 to 36 was done
with two different initial bed. In these runs the same thing happened as with the ,runs
with 30 l/sec but here the changes were faster which can be seen from Table 6.5.
Run no 37 to 41 were done with 20 'usec. Here also same this happened. So, all these
runs proved that the effect of, nose 2 are completely different than that of nose I. The
results of nose-2 can possibly~e compared if the widths of branch 2 and 3 are 20 and 80
cm respectively.
6.4 DISCHARGE VARIATION WITH TIME
Discharge variation with run time for all the three branches and for all the runs are
shown in Fig. 6.42 to 6.47. From Fig. 6.42 to Fig. 6.44 it can be observed that there is
very little change of discharge with time in all the three branches of all the runs for the
first nose. It is however observed that in case of the second nose there is a great variation
of discharge with time both in case of branch 2 and 3 even though the total or main
branch, discharge remained the same. This can be seen from Fig. 6.45-6.47. The
following paragraph explains the phenomena with example.
51
52
6.5 PHYSICS OF THE PHENOMENA
more or less constant. On the other hand in case of second nose for run no 22 it can be
seen that at the beginning the discharge in branch 2 and 3 were 8.5 and 20.6 Us• ' I •
respectively. At the end of the 22nd run the discharges in brarich 2 and 3 were 5.07 and
24.31 lis respectively. In all the runs of nose 2 such variation of discharge occurred. In
the discussion of bed-level evolution it was mentioned that bed level of branch 2 was
rising gradually. This rise of bed level caused decrease in discharge. In branch 3 the
opposite phenomena occurred. Run no 22 to 26 was carried out starting from the same
initial bed and the initial discharge. At thy beginning of Run No. 22 the discharge in
branch 2 and 3 was 8.5 and 20.6 respectively. At the end of23rd, 24th and 25th runs the
discharges in branch 2 and 3 were'3.76 and 24.53 lis, 3.26 and 25,18 Us and 3.04 and, ,
, 25.54 Us respectively. At the end of the 26th run the discharge values were almost the
same as at the end of 25th run. Similar phenomena can also be seen in run no 27 to 30,
.31 to 33, 34 to 37, and 37 to 41. In all the cases the discharge in branch 2 decreased and
discharge in branch 3 increased.
In case of the first nose i.e. Run No I to 21 the discharges in all the three branches are, "
It was observed from the experiments with first nose that erosIOn occured in the
downstream branches in whidh the bed level was higher than the normal depths and
deposition occured in the downstream branch in which bed level was lower than normal
level. When the bed level in both the downstream branches were very close to normal
level only small changes occured. However near the circumference of the nose some
erosion occured (approximately 3 cm to 4 cm in depth) due to, disturbance in flow.
From the experiment with the second nose a different phenomena was observed. Here
the bed level of, branch 2 was getting higher and higher irrespective of its initial bed
level. In this case the bed level changes were influenced due to expansion of flow' in the, "
second branch and contraction 'of flow in the third branch immediately below
bifurcation. Here also near the circumference of the nose scour occured (5 cm to 6 cm in
depth). In this case the amount of scour was greater than 'nose I because of more,. disturbance. This phenomena has been explained elaborately in Article 6.3 & 6.4.
:~
.,
6.6 SEDIMENT MEASURED IN SANDTRAPS
The method of measuring the amount of sediment trapped in the sandtraps of branch 2,
and 3 were discussed in detail in article 4.6.2. TIle amount of sediment trapped in sand
trap 2 and 3 can be seen from Table 6.1 to 6.6. From the tables it can be observed that in
case of the first nose or the reference nose each of the sand traps trapped appreciable,amount of sand. But in case of second nose trap 2 collected very little amount of
sediment compared to trap 3. In case of the second nose the amount of sand that was
entering branch 2, most of them were deposited in the branch. The change in volume of
sand of all the b~itnches of all the runs can be seen from Table 6.1 to 6.6.
6.7 ERROR IN DATA ACQUISITION
The main objective of the experiment is to have. some idea of sediment distribution at
bifurcation. In this respect the majn, ratio that are required to express a relation are
CJ2/'lJ and' S/S3' Now it is very essential to know how much accurate these measured
values are.
IN CASE OFO;iQ;>l
!The discharge are measured ~t the two Rehbock weirs and it was found that they are,capable ofn:easuring with arl accuracy of 98.2 %. This is detailed in Appendix B.
IN CASE OF szLs;>l. ,
'The sources of error may c01l1efrom following:
a) The sandfeeder
b) The bed level measurements,
c) The sandtraps, ,
d) The buckets
From the sandfeeder it was seen that due to the machine and the ,difference in moisture
content of sand, maximum amount of sediment measurement errors are around 7%. In
case of bed level measurement the amount of error are 3% due to point gauge reading
53
and accurate bed level detection. During the collection of sand from the sandtraps the
amount of sediment lost is about 6% (maximum). During the time of weighing with. ,buckets the error is around 3% due to the deformed shape of the buckets. So, in total
the error may be to the amount of 19%. But from Table 6.1 to 6.2 it can be seen that
except for Run No. 12 all are with in that range of 19 % tha( means the results may
be considered to be acceptable.
After doing necessary calculation s2/s] and 'h/q, were plotted for both the noses for
different discharges and these are shown in Fig., 6.48 to 6.53. It need to be mentioned
that the ratio of szls] was on the 'basis of average values since they were calculated from
data measured at the beginning and end of the run time. For that reason 'l2/'b ratio was
also calculated on the basis of average value of'l2 and 'b. Fig. 6.48 to 6.50 show how
,szls] varies with 'l2/'b for the first three sets of experiments using nose I for three
different total discharges, 30, 40 and 20 lis respectively. From each figure it is evident
that as 'l2/q] increases szls] also increases. This is obvious due to the fact that as 'l2/'b
increases, 'l2 increases' and '13 decreases resulting in an average trend of increase in S2
and decrease in S]. From the ~lotted points in these figures it is observed that the pointsI
are relatively more scattered in Fig. 6.50 which is for lowest total discharge of 20 lis.
The low discharge is associated with low velocities which in case of 20 lis may be too
lowto cause sediment move~ent properly. Figl1fes 6.51 to 6.53 show variation of $zls]I • _ •
with qzlq] fo~ second three sets of experiments with discharges 30, 40 and 20 lis using
second nose. It is to be mentioned here that in case of second nose the nose
configuration is such that in the second channel flow expands downstream of the n~se,and in the third channel flo~ accelei'ates do",,,,",sti'cu';;:;of the nose. This u'dditional
influence of nose on flow parameter obviously will have additional impacts on sediment
distribution in the two downstream channels as compared to' effect of the 1st nose for
the same discharge ratio.
Results from this set of experiments also shows increasing trend of in szls] ratio with
the increase of'l2/'b ratio as normally expected. It is observed from Fig. 6.51'to 6.53 that. . ,
the plotted points are more scattered in case of experiments with second nose. This
6.8.1 DEVELOPED RELATION BETWEEN SEDIMENT AND FLOW
The general. form of equ~tion have been determined from the best fit lines in Figs. 6.48
to 6.53. The six,different equations corresponding to six different sets of experiments are
given below. '
(6.5)
(6.3)
(6.6)
(6,7)
.(6.4)
(6.8)
55
For Q= 40 lis". . 2.958
sis) =2.411 (~/~)
For the second nose'
For Q= 20 lis2.4928siS3 = 1.25213 (~/~)
F~rthe first nose' '
For Q= 30 lis
~/S3 = 1.39202 (~/~)4.71315
'may be due to the configuration of'the 2nd nose which created additional impact on
flows 'in doWnstream channels or due to the low flow which causes inconsistent
sediment transport or combination of both, Fig. 6.52 shows less scattered data where
the flow is higher compared to other runs. May be in this case the additional impact
due to nose configuration was relatively less.
For Q= 30 lis
S2/s3 = 1.14463 (~/~/,54414
For Q'" 20 lis.. I 19381
sis) = 1.87398 (~/~) ,
'FOr Q= 40 lis ,5.6545
. S2/s3 = 2.0148 (~/~)
"
6.8.2 VALUES OF ill AND k
NOSE 1 NOSE 2DISCHARGE (lis) DISCHARGE (lis)
20 30 40 20 30 40, ,m 2.4928 4.71315 5.6545 1.9381 2.54414 2.958k 1.25213 1.39202 2.0148 1.87398 1.14463 2.411, ,
From the above table it is observed that for both the noses the values ofm increases'with
increase in discharge. This may be due to relatively more increase in velocity in channel
2 for higher CJ2/<J.J ratios for higher discharges. This results in greater increase of '
sediment discharge in channel 2 for higher CJ2/<J.J ratios at higher discharges. From the,
study of m values in equations mentioned before it is observed for equal discharge m
values for the second nose are lower, than the corresponding mvalues for the 1st nose.
This may be due to additional impact on flow in downstream channel due to flow
expansion 'in second channel resulting in rise of bed level in the, earlier part bf
experiment with each CJ2/<J.J value. However it is felt that such a comparison on the effectI
of two different noses need not be attempted with limited data available at this stage.
6.9 SIMULATIONS WITH I-D MODEL (WENDY). ,
From experimental data relations have been obtained for sediment distribution at' ~
bifurcation. These relations are for three different discharges corresponding to each ofi '
, the two different noses used in the experiment. Jhe general form of the relation is as
follows:
, '()'"S2 = k q2
S3 q3
The m and k values have heen found different not only for different noses but also for
different discharges. For the discharge of 30 lis with the first nose the above general
56
57
(6.9)
(6.10)
Eq. 6.2 can be brought in the following form ofnodRl p(,int relation as ShO"iIl below
In WENDY the no~aI point relation has been built as follows
k=4.71 and r=-4.529
J
( )
471
s2=1.392 q2s] q],
.82= 1.392(B2)/'47Jl/ Q2)".'/J8] B] Q]
I
Comparision :of equation (6.9) & (6.10) gives
Thus in the nodal point relation in,WENDY the value ofr=-4.529 and k=4.71 need to be
entered for the first nose and for a discharge of 30 lIsec. The values of k and r to be
entered in the nodal point relation in the WENDY for different conditions shown below.
NOSE I: NOSE 2
DISCHARGE (lis) DISCHARGE (lis)
20 30 40 20 30. 40m 2.49 4.71 5.65 1.93 2.54 2.95.r -2.05 -4.53 -6.33 -1.39 -1.64 -2.59
.. 1-
In order to see whether it is possible to carry out numerical solutions of a bifurcating
river, the configuration of the experimental model and the found out nodal point
relations need to be used as input for simulations with WENDY. Then simulations are to
be carried out for the experiments. If the results of these simulations come out as
comparable to the measured data (such as discharge, bed level,.water level etc.) from the
experiments it will be concluded that a good nodal point relation has been obtained and
hence a good simulation of a bifurcating river can be carried' out. It is t<;>be mentioned
)
here that the nodal point relations which have been worked out will be valuable only for
the specific conditions of the experiment. The ultimate goal is however to get a relation
which can be used in all circumstances, Hence much more research are to be carried out
to reach the ultimate goal.
6.10 SOME GENERAL DISCUSSION
The experime~tal study, on channel bifurcation has provided some insight knowledge
into the physical phenomena of channel bifurcations: Although the model channels were
qmch smaller than natural rivers, the bifurcation phenomena are similar in many, .
respects to those in natural channels. So, the results obtained in the experiment may be
qualitatively' extended to field conditions keeping in mind that rigorous scaling
procedure were not followed in the experiment.
The experi;nental study has been especially valuable because it has provided some
information about geomorphic phenomena which, for one reason or another are very,difficult to study in the field', By reducing, the field problems to a manageable size, detail'
information may be obtained ,in the laboratory to be relevant to natural conditions. But. I
this will need extensive anq elaborate laboratory experiments which must proceed, , ,systematically taking into considerati\ln the results of previous experiment. Thus it is to
be kept in mind that this is the begirming of the study in this field and hence this is not
the time to make any more remarks without more experiments. After further study over
years it will be possible to better understand the sediment distribution phenomena into
the two downstream branches.
58
7.1 CONCLUSION
compared with the first nose because the situation in the t\:vo cases arc different.
same for the
The nodal point relation has been found to fit well ( upto the expectation) for
I. The value of m and k1in the relation ( s, = k(q 2J'" ) are not the. . s, q,
same. nose for different discharges. For each nose it has been found that m value, .
CHAPTER-7
The following conclusions may be drawn from the present investigation.
Sediment distribution at bifurcation is not well understood because the processes are
complex and difficult to study both in the laboratory and in the field. Reviewing the
few research work that have been done in the past, one can understand the necessity to
get the solution of this problem, but unfortunately there are no tools available at present
to predict sediment distribution at bifurcation. As an effort to improve this situation,
the investigation in the present study is most useful. All results and conclusions listed
he~eafter of course refer exclusively to situations where hydraulic and sediment
parameters are situated in the range considered in this study.
CONCLUSION AND RECOMMENDATION
increases with increase in discharge. However for certain discharge the m values has
been found hi.gher for nose I than for nose 2 for corresponding discharge.
2. From observation it is evident that the results of second nose can not be
3.
the first nose. The value of m was found greater than 5/3 for all the three discharges ,.ffi-Jditwas observed that both the branches remained open. It can therefore be inferred
that it fits well with the theoretical analysis.
4. The relationship developed from the present investigation between sediment
transport ratio and discharge ratio shows evidence of existence' of relations among them" ! I
(Eq. 6.3- 6.8) ..
2. ' A second set of experiments can be conducted with the same nose but different
sand size. This experiment will help, to understand the effect of sand size.
6. The present study was done under non tidal condition. So, one can do the
experiment under tidal condition which is also very complex., ,
,The present study do not represent any particular river bifurcation problem. It
60
of discharge and sand sizes.
3. Experiments relating to second nose should be conducted for similar conditions,
7.2 'RECOMMENDATION FOR ,FURTHER STUDY
The present study has given valuable information to plan and guide future studies
relating' to channel bifurcation. It is expected that each future study as recommended
below will not only give more information about bifurcation phenomena but also help to
plan better for the next studies. Th~'following recommendations are therefore made:
I. Exp,eriments with nose I should be conducted at least for five different
discharges and for more 'l2/<!.J ,ratio for each discharge in order to understand the
problem in more detail.
. i '4. Further study can be !carried out with suspended sediment. This will require
some changes in the model.
5.
deals With laboratory cases and the relations developed herein have not been compared
to field cases. So model study of a particular river bifurcation is needed and the relation
, from the present study may be used to test the accuracy in predicting sediment
distribution for field condition.
REFERENCESAckers, P. (1990), " Dimensional Analysis, Dynamic Similarity, Process Functions,
Empirical Equations and Experience - How Useful Are They?" H. W. Shen(ed.), Movable
Bed Models, pp. 23-30.
Best, J: L. & Bristow, C. S. (1993), " Braided Rivers ", Geological Society Special
Publication No. 75.. ,.
Bridge, J. S. (1993), "The Interacti~n between Channel Geometry, Water Flow, Sediment
Transport and Deposition in Braided Rivers''', Geological Society Special Publication
No.75, pp. 13-71.
Dekker, P. den and Voorthuizen J. M van (1994), " Resean!h on the morphological
behaviour of bifurCation in rivers ", M.Sc. Thesis TO Delft 1994.
Fokkink, R. 1., Wang, Z. B., Iand Schropp, M. H. I (1995)," On I D Morphodynamic,Network Models ", Proc. (If the XXVI th Congress of the Int. Association for
Hydraulic Research, 11-15 September. 1995, London.
Gasser, M. M., Ahmed, A. F.,' and Gaweesh, 'M. T. K., (1989), " Movable Bed Model
Study of the Navigation Difficulties in the Nile River at Beni- Mazzar." Report, The Hydr.
and sediment Res. Institute, delta Barrage, Egypt.
ISO (1975), " Liquid Flow MeasuremeJ;lt in Open Channels Using Thin -Plate Weirs and
Venturiflumes", ISO, Geneva.
ISO (1980) , " Measurement Method of Fluid Flow .by Means of Orifice Plates, Nozzles
and Venturi Tubes Inserted in Circular Cross-Section Conduits Running Full ", ISO,
Geneva.
Klaassen, G. 1. aI1dK. Vermeer (1988), "Channel CharacteristiCs of the Braiding Jamuna .
River, Bangladesh ", Proc. Int. Conf. River Regime, 1988, Walingford.
61
Klaassen, G.J. and K. Vermeer (1988), "ConfluenceScour in Large Braided Rivers with
Fine Bed Material", Proc. Int. Conf. Fluvial Hydraulics, 1988 .Budapest.
Richardson, W. R.R: and Thome, C. R. .(1995)," Study of Secondary Currents and
Morphological .Evolution in a Bifurcated Channel" Draft Final Report, FAP 24 &,University of Nottingham Joint Study.
" River Morphology and Thresholds" , (1985), Journal of the Hydraulics Division, ASCE,
Ill, pp. 503-519.
Struiksma, .N. (1980), "Recent Development on Design of River Scale Models with
Mobile Bed ", IAHR Symposium, Belgrade and Delft Hydraulics laboratory
Publication No. 23 pp. 6 -II.
, .Schropp, M. H. 1. (1995)," Principles of Designing Secondary Channels Along The RiverRhine for the Benefit of Ecological Restoration", Wat. Sci. Tech. Vol. 31, NO.8. pp.379-382.
Vries, M. de, (1973). "App,lication of Physical and Mathematical Models for River• I .
Problems ", Delft Hydrauhc f-aboratory No. 112, Delft, The N~therlands.
Vries, M. de, (1992)," River Engineering Lecture Note flO ", Delft University of
Teclmology, .Faculty of Civil Engineering.
Vries,M. de, (1993); Note on River Engineering for Braided Rivers, Delft University of
Engineering, Faculty 'of Civil Engineering Workshop on River Engineering, Dhaka,
Bangladesh, January 1993.
Vries, M. de, (1975), " A Morphological Time Scale for Rivers" Proe. IAHR, Sao
Paulo, Vol. 2; pp 17-23
Vries, M. de, G. J. Klaassen and N. Struiksme (1990) "On the Use 'of Movable Bed
Models. for River Problems: A State of the Art ", Int. j~umal of sediment research, Vol-5,
No-I pp. 35-47 ..
62
.Williams, P. F. & Rust, B. R. 1969," The Sedimentology ofa Braided River ", Journal of
Sedimentary Petrology, 39, pp.649-679.
Valin, M. S..(l971)," Theory of Hydraulic Models ", Macmillan Press, London.
Valin, M. S. (1972), "Mechanics of Sediment Transport", Pergamon Press, Oxford.
TABLE 2.1 HYDRAULIC AND SEnJMENT PARAMETERS OFTHE NILE RIVER AT BENI-MAZZAR .
PARAMETER PROTOTYPE MODEL. SCALINGVALUE. VALUE RATIO
Length (m) 6000 40 150.
Width (m) 480 3.20 150
Water depth (m) 3.0 0.068 43.5
Water slope (m/Km) 0.085 3.26 0.026,
!, ;Flow velocity (m/s) 0.825 0.419 1.97
3 .1160 0.0900 12850Discharge (m Is)
Chezy C (mos/s) 52 28 1.86,
Sediment Dso (mm) 0.34 0.30 1.13
64
AVE. -RUN AVE. AVE. AVE.NO. i, " h h, h, U, '13 U2/U3 h'/h, Q'/Q, q,/q,
(m) . (m) (m/s) (m/s) .
I .0017 .. 00143 .00200 .079 .083 .3197 .3857 .8288 .9606 .53082 .796242 .0015 .00148 .00152 .117 .057 .3945 .. 2782 1.418 2.058 1.9463 2.91943 .0019 .00189 .00187 .068 .092 .3397 .3928 .8648 .74216 4279 .64184 .0016 '.00182 .00131 .073 .099 .3464 .3427 1.0 II .7382 4974 .74615 .0017 .0015 J .00194 .086 .081 .3427 . .3756 .9125 1.065 .6482 .97228,6 .0017 .00163 .00167 .089 .086 .3623 .3597 1.007 1.039 .6979 1.0468I7 .0017 .00163 .00178 .087 .086 .3571 .3717 .9608 1009 .6466 .96986"8 .0018 .00157 .00206 .081 .081 .3557 .3884 .9158 1.096 .6694 1.0041
CHANGE CHANGE CHANGERON IN IN IN AT THE AT THE MEASURED FEEDED DlF.NO. BRANCH BRANCH BRANCH NOSE S, NOSE S, S'/S3 Sz/S3 SAND SAND IN %NO. I NO.2 NO.3 I
(m') (m') (m') (m') (1113) (111') (111')I -.0176200 -.029770 .01413 I .046325 .120354 .384904 .57735 .149057 .15842. 5.9522 -.0027500 .001417 -.049590 .218589 -,O~959 , -'''!.t107:, I -6.6i j .166200 I .i97484 15.823 -.0148280 -.028653 .006246 .019923 .166498 I .11970 17950 .171590 .197484 13.1 I4 -.0093500 -001620 -.014270 .018582 .099217 .18729 .28093 .108444 .128302 , 15485 .0201534 -.006594 .037457 .074861 .095336 .78523 1./778 .190350 .18113 5.096 -.0077700 .023653 .001424 074208 .06767 1.0966 1.6450 .134106 .16 16.187 -.0003700 .008280 .001656 .073987 .09031 .81923 1.2280 .163930 .16 2468 -.0116620 -.002 J 91 -.005306 .074839 .07538 .99282 14892 .138560 .16 1340
Sediment discharge per IInit widthof oranch 2 & 3
52' 5J = Sediment discharge at the nose ofbrnnch 2 & 3
65
TAIlLE 6.1 RESULTS OF THE FIRST NOSE (30 lIs)"
READING READING READINGRUN. OF OF OF AT SAND TRAP AT SAND TRAPNO. STILLING STILLING STILLING AVE.Q, AVE.Q3 NO.2 NO.3BASINNO. BASINNO. BASIN NO.
I 3 4 .
(m) (m) (m) (lIs) (II s) (K.~.) I (111') (Kz) (m')I .3539 .3339 .. 3294 10.160 19.14 7533 107609 10516 .106222 .3525 .3330 .3330 184/0 I 94573 I 215 .21717 2 0.0023 .35g0 .3330 .3338 9.231 21.573 48.09 .04857 158.65 .160254 .3560 .3330 .3379 10.156 20418 20 .02020 112.35 .113485 .3593 .3386 .3353 . 11.837 18.261 80.64 .08145 57.3 .057886 .3650 .3435 .3435 . 12.941 18.543 50.05 .05055 65.58 .066247 .3664 .3447 .3437 12416 19.202 65.05 .06570 87.77 .088668 .3664 .3447 .3409 12.708 18.985 76.26 .07703 79.88 .08068
h2, 11) = Der1h of wafer in lmlnch 2 & 3
i = Bcd slore
02, OJ = Discharge in hranch 2 & 3
tl2, tI) = Velocity of branch 2 & 3
Q2, ell = Flow rate in branch 2 & 3
TABLE 6.2 RESULTS OF THE FIRST NOSE (401/s)
Sediment discharge per unit widthof branch 2 & 3
52. S3 = Sediment discharge at the nose ofbranch 2 & 3
66
"
READING READING READINGRUN OF , OF OF AT SAND TRAP AT SANDTRAFNO, :: STILLING STILLING STILLING AVE, Q2 AVE. Q, NO.2 NO.3BASIN NO, BASIN NO, BASIN NO.
I 3 4(m) (m) (m) (IIs) (lIs) (K~.) (m') (K,s() (m')
9 ,36635 .3447 ' ,3408 12.566 26,036 84.97 ' .08583 160,83 ,1624510 .3758 .3583 .3587 13.658 I 24.988 63.59 .06423 114.35 .11550I I .37755 .3585 .3598 13.093 .25.208 55.21 ,05577 \17.39 .1\85812 ,37755 .3585 .3598 15.575 22.848 90.\ .09101 120.57 ,12\7913 .3785 .3592 ,3573 14.444 24 70.58 ,07129 131.89 .\332214
"
.3779 ,3583 .3583, 14.371 24.178 76.96 .07774 114.25 .11540
Q, ,Qj. ~ Discharge in branch 2' & 3
i ~ Bed slope
U" u, ~ Velocity of branch 2 & 3 .
q,. q, ~ Flow rate in branch 2 & 3
h,. h, ~ Depth of water in branch 2 & 3
RUN AVE, AV.E. AVE. AVE. ,NO.t
-j'] i2 ;, h2 h, U2 U, Uz/U3 thz/h3 Q2/Q, q2/q,(m) (m) (mls) (ml s)
9' ,0018 .0016 .0021 .089 .100 ,3542 .4323 .8195 .8834 .4827 .723910 .0013 .0013 .0013 .099 .113 .3449 .3677 .9379 , .8741 .5466 .8199I 1 ' .0014 .0015 .0014 .093 .113 .3513 .3712 .9464 .8232 .5194 .7791 ..12
'I
.0014 .0015 .0014 .105 .106 .3722 .3592 1.036 .9868 .6817 1.022513 .0016 .0'014 ,0017 ,101 .102 .3592 .3935 .9127 .9891 .6018 .9027514 .0015 .0015 .0015 .. 099 .106 .3636 .3813 .9535 .9351 .5944 .8916
CHANGE CHANGE CHANGE. . .
RUN IN IN IN AT THE AT THE MEASURED FEEDED DIF.NO, BRANGI BRANCH BRANCH NOSE NOSE S2/S, 5Z/ S3 SAND SAND IN%NO. ,1 NO.2 NO.3 S2 • S,(m') (m ') (m') (m') (m') (m') (m')
9 -.032226 -,06199 .004322 .0238 .16677 .1429 .2143 .15838 .172075 7.9610 -,014213 -.00339 .0020618 .0608 .11756 .5175 .7763 .164197 .171824 4.4411 .00061 .01479 .008929 .0705 .12750 .5534 .8300 .19867 .17610 12.8212 -.05344 .018125 -.050586 .1091 .0712 1.533 2.299 .126892 .16604 23.5713 .006374 .007249 -.004712 .0785 .12851 I .6111 .. 9166 .213428 I .191\95 11.6314 -.01806 -.01127 -.013551 .0664 .10185 .6525 .9788 ' .150253 .169056 11.12
••
TABLE 6.3 RESULTS OF THE FIRST NOSE ( 201/s)
Sediment discharge per unit widthor branch 2 & 3
S, ,S, ~ Sediment discharge at the nose ofbranch 2 & 3
67
I
Q, ,QJ ~ Discharge in branch 2 & 3'
i ~ Bed slope
"" ", ~ Velocity orbranch 2 & 3
h" h, ~ Depth of water in branch 2 .& 3
q" q, = Flow rate in branch 2 & 3
Iii
READING READING READINGRUN OF. OF OFNO. STiLLING STILLING STILLING AVE.Q, AVE.Q, AT SANDTRAPNO. AT SANDTRAPBASIN. BASIN BASIN 2 NO.3I NO. I NO.3 NO.4
I (m) (m) (m) (IIs) (1/ s) (K.\1..) (m') (K.\1..) (m')15 .33615 .30723 .30282 5.087 13.639 , 36.32 .05668 'i46.G8 .1481616 .32980 .30723 .29267 8.8563 9.7093 159.78 .16 I39 24.91 .0251617 .33000 .28178 .28147 10.9 7.382 168.78 .17048 6.19 ..00625. 18 .33185 .28220 .28173 7.4081 10.961 36.24 .03660 153',34 .15489,19 .32685 .29486 .29486 6.614 11.77 57.71 .058i9 111.16 .1122820 .32535 .2n26 . .29348' 6.116 12.i93 4.3.5 .04394 126.6 .1i78821 .32471 .29426 .29788. 4.9433 13.727 5.82 .00588 135.58 .13695
RUN AVE. AVE. AVE. AVE.NO. iI ;, h h, h, u, u, UZ/U3 h,lh, Qz/Q, q,/q,
" (m) (m) (m/s) (mls)15 .0024 .0021 .0027 .0440 .0598 .289 .380 .7604 .7358 .3730 .559516 .. 0023 .0014 .0032 .0726 .0450 .305 .359 .8~82 1.613 .9121 1.36817 .0037 .0037 .0038 .0608 .0354 .448 .347 1.289 1.718 1.477 2.21518 .0038 .0038 .0039 .0466 .0456 .397 .401 .9918 ' 1.022 .6758 . 1.01419 .0025 .. 0024 .0025 .0499 .0556 .331 .353 .9372 .8993 .5619 .842920 .0025. .0025 .0025 .04671 ' .0572 .327 .355 .9198 .8180 .5016 .752421 .0022 .0024 .0020 .0414, .0661 .298 .346 .8619 .6267 .3601 .5402
CHANGE CHANGE CHANGERUN IN IN IN ATTHE ATTHE MEASURED FEEDED DIF.NO.. BRANCH BRANCH BRANCH NOSE NOSE Sz/S, 82/53 SAND SAND IN%
NO.1 NO.2 NO.3 S, S,.(m') (m') (m') (rh') (m') • (m') (m')
15 -.02 -.01911 -.01423 .01'758 .13393 .13124 .19686 .131507 .145912 9.8716 -.02045 -.06653 .030393 .09486 .0555 1.7076 2.5614 .129967 .152122 14.5617 -.01146 -.03615 .019094 .13434 .025346 5.2999 7.9498 .148245 :163522 9.3518 -.00483 .057799 -.09106 .09441 .0638211.4791 2.2186 .153396 I ~163522 6.'1919 .-.01669 .006684 -.00847 .06498 .103815 I .62:189 .9388 .15210 .15195 , .10020 .012385 -.00747 .002907 .03646 .130785 .2788 .4182 .1796351 I .15195 18.2221 .006485 .02745 -.00352 .03333 .133429.2498 .3747 .173245 .156604 10.63
TABLE 6.4 RESULTS OF THE SECOND NOSE (30 I/s)
RUN AVE. AVE. AVE. AVE.NO. I' i,- i, ;, h2 h, U2 U, Uz/U3 h2/h, Q2IQ, ' q2/q,
(m) (m) (mls) (mls)22 .00165 ,00157 .00174 .0570 .0961 .2842 .3874 .7337 .5933 .29024 1.161 '23 .00188 .00184 .00193 .0424 .0969 .2648 04107 .6448 04374 .1880 .752024 .00175 .00199 .00149 .0375 .1078 .2596 .3808 .68 I 7 .3478 .1581 .632325 .00188 .00197 .00178 .0342 .1029 .2464 04063 .6065 .3319 .1342 .5367 '26 ' .00194 .00196 .00192 .0342 .1004 .2456 A I 62 .5901 ' .3406 .1339 .535927 .0015 .00136 .00164
.0811 .0839 .3151, .3523 .8944 .9672 .5767 2.30728 .00165 .00149 .00181 .05,7 .0924 .2838 .3883 .73 I I .6464 .3150 1.26029 .00192 .00186 .00198 .04 t 9 .0961 .2646 A I38 .6394 04359 .1858 .743330 .00195 .00191 .00199 .0387 .0973 .2582 04171 .6191 .3979, I, .1642 ' .6570
Sediment discharge per unit widthof branch 2 & 3
S2' S3 = Sediment discharge at the nose ofbranch 2 & ,3
68
READING READING READINGRUN or or orNO. . STILLING STILLING . STILLING AVE.Q2 AVE.Q3 ATSANDTRAP ATSANDTRAPBASIN BASIN BASIN NO.2 NO.3NO.1 NO.3 NO. 4
(m) (m) (m) (1/ s) , (I/s) {~.) {ni3) {~) {m3}22 .37615 .35517 .354134 I' 60484 22.34 7.38 .00745 W5.8 .1674723 .3782 .35392 .353484 40494 23.904 3 .00303 137.74 .1391324 .37975 .35472 .359334 3.8972 24.654 4.14 .00418 154.02 .1555725 .37856 .35312 .355134 3.3678 25.097 1.75 .00177 149049 .151026 .37926 .35368 .354434 3.361 25.083 4.68 .00473 147. I6 .1486527 .38055 .36210 .359984 10.228 17.734 3.25 .00328 70.25 .0709628 .38290 .36257 .360234, 6.785 21.5378 1.69 .00171 138.5 .1398929 .38560 .36100 .360334 '40434 23.8(>2 .14 .00014 114.19 .1153430 .38650 .36127 .361034 4.00 24.353 3.78 .003,82 123.9 .12515
-hi, h) = Dcrth of \Voter in brAnch 2 & 3
Q2 ,QJ = Discharge in branch 2 & 3
i = Bed slope
Q2' qJ = Flow rate in branch 2 & 3
Uz, tI) = Velocity of branch 2 & 3
CHANGE CHANGE CHANGE ATHIE ATTHERUN IN IN IN NOSES2 NOSES, MeASURED rEEDED DIP.NO. BRANCH BRANCH BRANCH S2IS3 82/83 . SAND SAND IN%NO. I NO.2 NO.3
(m') (m') (m') (m') (m') (m3) (m3)22 -.01735 .072973 -.02 I95 .08043 .14552•.5527 2.21 I , ,.20860 .! 7962 16. I323 .01001 I ,020720 .020199 .02375 .I 5933 ,1491 .5964 .19309 .16407 17.6821 -.00517 ,005665 -.02086 .00985 .13471 .073 I .2924 .13909 . !6825 17.3325 -.01231 .007745 -.00813 .00951 .14287 .0666 .2664 .14007, . I 6729 16.2726 .000934 .001275 -.00395 .00600 .14469 .04 I 5 .166 . I5163 .15476 2.02727 .076726 .058564 -.03408 .06184 .03688 1.677 6.708 .17545 .16100 8.97328 .019848 .072918 -.02387 .07463 .1 1603 .6431 2.572 .21050 .18113 16.2129 .001499 .028753 -.00914 .02889 .1062 I .272 1.088 , .13660 . I 5723 13.1230 .006136 .003844 .006886 .00766 .13204 .058 .232 .14584 .16151 9.705
••
TABLE 6.5 RESULTS OF THE SECOND NOSE ( 40 I/s)
RUN AVE. AVE. AVE. AVE.NO. I, i, h' h, h3 U, U3 uz/u:\ h2/h3 Q,/Q3 qzlq,
(m) (m) (mls) (mls) .
31 .00194 .00196 .00192 0562 .1126 .33 I 7 .44088 .7524 .5536 .2777 1.110732 .00348 .00348 .00347 .0415 .0982 .3607 .55430 .6508 .4227 .1834 .7336933 .00225 .00215 .00234 .0484 .1118 .3062 .48554 .6306 .4332 .1821 .72848" .0958. .3527 .42654 1.009 '34 .00176 .00143 .00211 0~67 .8269 .5568 2.227235 .00177 .00128 .00227 .0,88 .1038 .3013 .46025 .6547 .7591 .3314 1.325536 .00188 .00144 .00233 .0629 .1086 .2850 .47772 .5967 .5798 .2307 .92272
Sediment discharge per unit widthof branch 2 <;0 3
82 • SJ = Sediment discharge at the nose ofbr~nch 2 & 3
69
READING READING READINGRUN or or orNO. STILLING STILLING STILLING AVE.Q, AVE. Q3 AT SAND TRAr AT SANDTRArBASIN BASIN BASIN NO.2 NO.3NO.1 NO.3 NO. 4
(m) (m) (m) (II s) (II s) (Kg.) (m') (K.I() l(m3)31 .37926 .35368 .35443 8.2747 29.799 32.17 .03249 97.54 .09853 •32 .39926 ., .35368 .35443 5.9940 32.679 31.50 .03182 183.65 .1855033 .39508 .36648 .36529 5.9320 32.572 37.36 .03774 170.90 .1726334 .39165 .37142 .3659'8 13.651 24.517 88.76 .08966 127.73 .1290235 .39193 .37297 .36493 ,9.5013 28.673 53.64 .05418 108.70 .1097936 .39275 . .37197 .36468 7.1815 31.132 40.46 .04087 84.64 .08546
Q, , Q, ~ Discharge in branch 2 & 3
h" h) ~ Depth of water in branch 2 & 3
i ~ Bed slope
U" 11) ~ Velocity ofbronch 2 & 3
Q2, q) = Flow rate in branch 2 & 3
CHANGE CHANGE CHANGE AT THE ATTIIE. RUN IN IN .IN NOSE NOSE MEASURED rEEDED Dlr.0
NO. BRANCH BRANCH BRANCH S, S, SzlS3 szlS3 SAND SAND IN%NO. I NO.2 NO.3(~13) (m3) (m3) (m3) (m3) (m3) (m3)
31 .047977 .050040 .0053608 .08253 .10,'3g8 ,7945 , 3. i78
I.234399 , "),,",ooc , !L53
I..L..Vvvv
32 -.001699 ,022620 .0073905 .05444 .19289 I .2822 1.1288 .245635 I .22843 7.5333 .006962 -.004295 -.010655 .03344 . i6i97 .2065 .82588 .2023758 .21066 3.9334 .047491 .076256 -.102901 . I 6591 .02612 6.352 25.408 .239523 .20996 14.0835 -.00798 .054798 ,.036038 .10898 .07376 1.4775 5.91 .174759 .20126 13.1636 .00235 -.000577 .0027776 .04029 .08824 .4566 1.8264 .130888 . I 5834 17.34
TABLE 6.6 RESULTS OF THE SECOND. NOSE (20 lIs)
RUN' AVE. AVE. AVE. AVE.U,NO. i, iz ;, . h2 h, U, uZ/U:l h,lh, Q,/Q, q,/q,
(m) (m) (mls) (ml s)37 00238 00190 .00287 04635 .06056 28184 .39567 .71231 .76528 .36341 1.4536. 38 .00224 .00176 .00273 .04293 .06389 .26097 .39646 .65826 .67197 .29488 1.179539 .00195 .00246 .00350 .03579 .05979 .28175 .43414 64899 .59867 .25902 1.036140 .00211 .00277 .00371 .03178 .05880 .28125 .44343 .63425 .54042 .22851 .9140341 .00216 .00279 .00382 02988 .05957 .27394 .45235 .60558 .50 I58 .20249 .80999
Sediment discharge per unit widthor branch 2 & 3
Sz:, S) = Sediment discharge at the nose ofbranch 2 & 3
70
READING READING READING
I ,-'"'''".'''RUN or or or!NO. STILLING STILLING STILLING AVE.Q, AVE.Q, AT SAND.TRAPBASIN BASIN BASIN NO.2 NO.3NO. I NO.' 3 NO.4
(m) (m) (m) (IIs) (IIs) (10.) (m') (K.) (m')37 .34933 .32223 .31448 5.225 14.377 49.24. .04974 94.~)4 .0958938 .34708 .32183 .31403 4.482 15.199 24.02 .02426 70.12 .0708339 .34359 .32239 .3'1417 4.034 15.574 18.22 .01840 55.13 .0556840 .34533 32155 .3 I 412 3.575 15.645 17.34 . .01752 59.50 .0601641 .34612 .32212 .31406 . 3.274 16.168 10.50 .01061 59.20 .05978
liZ, ll)'= Velocity ofbraneh 2 & 3
0, . OJ ~ Discharge in branch 2 & 3
q" q, ~ Flow rate in' branch 2 & 3
h2, hJ = Depth of water i!l branch 2 & 3
CHANGE CHANGE CHANGERUN IN IN IN ATTIlE ATTHE MEASURE rEEDED DlLNO. BRANCH BRANCH BRANCH NOSE NOSE S,IS, Sz/S3 DSAND SAND IN%NO. I NO.2 NO.3 S, S,
(m') (m') (m') (m') (m') (mi) (m')37 0.02132 -.01357 '.044519 .036161 f"\~lQ7c.a ""'('l"..z~ , 2.8152 I . I08864lI.097225 11.97.vv ••...' "
I.1 v •...••..
38 -.00146 0.01898 -.0/371 I .043251 .057117 .7572 3.0288 .0989093 .090975 8.7239 0.00863 0.00695 -.027061 .025359 .028626 ..8859 3.543 .0626186 .077146 18.8340 -.00016 0.00273 -.002308 .020249 .057793. .3504 1.4015 .0778793 .077146 .950741 .005524 0.00251 -.003286 .013116 ,056512 .232 I .92839 .0751532 .077146 2.583
). i ~ Bed slope
--JI\)
" -.•..'
~
".
q 1 T ~ t 1m
•• ....
I
17 18 19 2b 2\2
..
23 24 .25
Outflow--.
Fig. 2.1 MODEL OFTHE BENI-MAZZAR REACH OF THE NILERIVER.
C/)..JWZZ
~(JClWC>Cl'wn::Cl
wwn::J:I-WJ:l-Ll..oI-Z••••....2zC>:J«N~
.~LI..
E
oN,....,
oco
o'"NI
, .
'c"
,..,''" ' -c.: I' ~
. - ".::- ~w ~- ,~~ i:l.,~ I", :>,.., ,~~.
73
,\\\
\\\\,,,,
; .
J IS"
liT, .
1.1,. )
••Iri
I=!,
CI
1
500 1000
00
So
=.~.=~
Main channel
Secondary channel
2 4 6 8 10 20 40 100 200
U* dBoundary Reynolds number, R* = -v-
Fig. 2.4 SHIELDS DIAGRAM FOR INCIPIENT MOTION
74
0406 1.0
"I
I, ''''
Ps' in gm
'b Ambe'}
per cu em1.06
• lignite (Shieldsl 1.27o Granite 2.7o Barite . 4.25, Fully developed turbulent velocity profile S C
2.65II I I I ! I I I. i I I * and ( asey)IIIII I . + Sand (Kramer) 2.65. : I ~ Sand(U.S. WES.) 2.65
Sand (Gilbert) . 2.65{. Sand (While). 2.61
Turbulent boundary I~yer' 0 Sand in air (White) 2.10'1 • i", "(T 1 "" Sleel shot (White) 7.9,
Value 01.2.. j 0.1 ( Y s .1) gdl' v Y"-
2 4 6 8 10 2 4 6 100 2 4 611000•
--A / / / 1// II / J../ -,fftTl..I ,,,''It ..-..: \ 0
I I v ~ Shtldf frve
0.10080.060050040030.02
02
Fig. 2.3 SCHEMATIZED MAIN AND SECONDARY CHANNEL'SYSTEM
(f)(f)Q)~~(f)
(f)(f)Q)
co(f)cQ)
Eo
u,s.:- 10
1:'.0806
II 0.5~ 04
0.3
)
1m <5/3 I
unstable:
. c:=::C> saddle point
==t>sink
75
!
Fig. 3.1 PHASE DIAGRAM IN CASE OF m < (5/3)
Fig. 3.2 PHASE DIAGRAM IN CASE ,OF m > (5/3)
"
'.
..•. ~ .(. .•.. '0- I-
>:•••w'"l-V>0..=>
'"o5:wVl"-''"
o
STILLING BASIN
OOWNSTREAMRESERVOIR
=,..~~1'-'
"
REHBOCK WEIR
<==FLOW OIRECTION
i1.' -
J-'
--..J(J\
-PIPE LINE
.Fig. 4.1 GENERAL LAYOUT OF THE SET-UP
"'I•• I4.55m
FLOW DIRECTION
WOODEN NOSE,
1489 m
' .•• I ).15m •. I ••6.19m
BRANCH 2
BRANCH 3 .
Fig. 4.3 LAYOUT OF THE TEMPORARY PART
78
, '
, .'
SANDTRAPS
I ~1,2.00m I.
TUBES.
12 JJ I
<--FLOW DIRECTION
2.0m ~OJ
I ~---,0.5
BRANCH 2
8'6m'
37
8 7 5 5 4 3
5
~ 2.25m .1.II STILLING BASIN
~ 25
,SANDFEEDER SUPPORTS
79
!1.0m
I
STILLING BASIN IV
Fig. 4.5 DETAIL OF BRANCH 2 AND BRANCH 3
STILlING'BASIN III
STILLING BASIN
l Fig. 4.4 DETAIL OF THE INFLOW ZONE AND BRANCH 1
III
II
IIIIII
I.OOm
branch 1,
I.OOm
branch 1
ILOOm I
I.1
'.
branc,h 1
~O.BOm
.20m
O.30m
,
IO.70m •~
NOSE-l
NOSE -' 2
NOSE- 3
2
2
Fig. 4.6 DETAIL OF THE NOSES
80
,
),
, ,.\"'~I'.:' I: ~
- I
Om lI
.1I
fml SAND
o CONCRETE
~ BRICK-WORK
==-FLOW DIRECTION
SANDTRAP
2.00m
TAIL GATES
2.00m '1PLAN
SA":lDTRAP 3
r-2"OOm, .
I-
I-SIDE VIEW
T'.OOm
-l
81
Fig. 4.7 DETAIL OF THE SANDTRAPS
I, " , ", ,
::5AND',BED: :
T:, '
O.80m'
LiI,L.B. F. , •
. V I."
I
MIN WATER LEVEL
TO.~5m
1
MAX WATER LEVEL
RUBBER FOIL
STEELPLAfE FORGUIDANCE OF FLOW
• I
C.5Cm
•• •••• () iii• •
O.17m'
SIDE V lEW
C.35m
VENTILATIONTUllE 038m
FRONT VIEW
•
• •. .
OJ5m
82
III 'I II I: TAIL GATEI 'II
I1III
Fig. 4.8 CONFIGURATION OF A TAIL GATE
DETAILTAILGATE
0.55 LBF
1.20 L B F
,FREEBOAR D 0.10HEAD LOSS 0.0
HEAD OVER TAILGATE 0.12
0.95LBF
)
DRAIN
/
O. &0 rTI
PILLAR
DOWNSTREAM RESERVOIR
SPILLWAY
,STILLING BASINS
Fig. 4.10 CROSS-SECTION OF THE SPILLWAY
83
=PUMP
..
Fig. 4.9 DOWNSTREAM RESERVOIR
0.77 LBF
DRAIN
a 0
APPROACH
CHANNELS
'"' ' .•, ,..'"" ".,
o
~D
•
SUPPLY PIPE LINEBJ
~PILLAR
I.. 12.90m :~D:rt-_
t l.h"" ,Bd, ) '.t::1? ~E:C:S:p:p:r;" ,4, , , , , , , ,II~~
Fig. 4.11 . LAYOUT OF THE PIPE LINE
,T'82m
0.2m
0.4m
0.6m
85
PUMP
SECTION A-A
SECTION 8-8
0.40.85
LABORATORY FLOOR
Fig. 4.12 SECTION A-A ANDB-B OF THE PIPE LINE
, PILLAR
}
,'
)c t "
0.4m .~+- 'ra0.46m
7.90m
~r• Io I
b 1.60m
, .. 1
o
o.'o
oQ. ""F:
86
o
o 0o 0,
o 0o 000
SECTION D-D
SECTION C-C
.22.15 Eil.20
. 1.25m
~.50mI~
I.
, '
Fig. 4.13 SECTION C-C AND D-D OF THE PIPE LINE
. I
Ti m
--1'~~J
PVC TUBES
6.87m
DRAIN
Fig. 4.14 DETAlL OF THE UPSTREAM RESERVOIR
PIPE LINE
1_' _S_T_I_L L_I_N_G~R__ESE_R_V_O_IR__ ----'--_
Fig. 4.15 THE REGULATING AND MEASURING FACILITIES.
CJ ,
PIPE LINE
., '
88
, "
" .
DOWNSTREAM.~
l6Ji
REGULATING AND MEASURIN~FACILITIES
REHBOCKWEIRS
R,..,.... . ..~.,
,~"• :. • •• ' •• ': •• ol,."',,'
•• { / : I<== /':; PIPELINESI / 1\, I,
TAil GATE
STilLING BASIN
TUBES
.'
STilliNG BASIN
TAil GATE
PUMP
CHANNELS
APPROACH
STilLING BASINS
. . '.. ,'. ' ,' .. : ..
.. ' .. " ' ....
89
II1;.
TUBES
GUIDINGVANES
TRANSITIONFLUMES
Fig. 4.17, THE APPB,OACHCHANNELS AND THE REHBOCKWEIRS
Fig. 4.16 DETAlL OF THE REGULATING AND MEASURINGSYSTEM
\ '
FOOT RESTBASE PLA TE
f10PPER
VA~I.t..( .DC MOYORGEAR BOX
GEAR PLATEPINIUM
SAND BUCKET
,.I..'
90
o
Fig. 4.18 D1AGRAMATIC VIEW OF SAND FEEDER
0000o
91
__ 70 - ---~---------~------~-------~ _
90 - -- -~-~ . - -- -- -- -- c -- -- -- -- - r;:-SAND-FEEDEI~-r;:io.-:q80 - -------~ .•. ---- ---------.---------- __. . _
--------------.70 ">---
6 O' - - - - - - - - :-- -•• - - - _.- - .~,~-~: : :: - - - - - • : : • : - - - : . : - - _:.: : . - -- - . - .~
50 . - - - - - - - _.. - - - - - - - - - - - - - - - - - - - - - - '-- - ~'----'-- _- - '- - __ _~,
40 . _. - - - - - - - - - - , - - - - - - - - - - - - - - - , - - - - ~_ . _.: _
30 . - - - - - - - - - - - - - - - - - - - - - - - - - - - . __ _ .• ~ . __ _ _ __
~~ _-.:::. _::: ---. : -:::. : --:-:: - -:. _ --il~~ __
Fig. 4.19 a CALIBRATION CURVE FOR SAND FEEDER NO.1
.Fig. 4.19b CALIBRATION CURVE FOR SAND FEEDER NO.2
--::- 100 - ---------.------------~~~---. --.------- .__.. .L...c-OJ~---I-:J~I-:JoI-Zill~
oillen O---t-.1----1--j~t---~.------~--'.c.--t----t--.--~--'
VARIABLE SPEED GEAR READING
L...c
. ~6 0 ---,--_--------------- -------: --------------.r::~:-SA-ND.FEEDERNQ1-1- --- - --- - ----I- 50 --.---------.. -.-. -- ---------------------.--------- -------c' ... - - - ~o"- -----_ •..-_....-.:J ..---~ -~40 - -- .-- - - - - - - -- - - - - - - - - - - - - -._.- - - . .,,-. _"__.. . _I- .-~:J -•.------------
-~a 30 .. _..._.._..- - . - - ..._..-~~;.?-~~~------------_.---_..----._...I- ~~~ 20 --7-------------------------- ------
•o 10,-. ---.---- .-------------------------------- .. _--.--.--.------_. -----illen
92
- ,
DIAMETER (mm)
,,-' I -I
Ii .
I.
. ,-
,ASf-.- m FORE IN
~. \111 cr<
A0rliN'
I ,0.000.01
10.00
Li0 ..00
50.00
60.00
]0.00
30.00
100.00
90.00
GRAIN SIZE DISTRIBUTION
.20.00
110.00
0': 80.00W.zH
LLf-'ZWU0':WCL
. Fig. 4.20 THE GRAIN sIZE: DISTRIBUTION OF WASHED ANDUNWASHED SAND
BED-FORM
93
SAND BED,
PIN!r SQ~ARE PLATE
----- ------- ---~ -----,I1IIII1
IIII
I, I,
Fig. 4.22 DETAIL OF THE SPECIAL PIN
Fig. 4.21 DETAIL OF THE 'STILLING BASINS
BRANCH 3STILL ING BASIN III
I ,
STILLING BASIN IV BRANCH
~FLOW DIRECTION
1-, --IIIIIIII
IIIIIII
IIIIIIIII
Fig. 4.23 DETAIL OF THE BED LEVEL MEASU.REMENTS,POINTS
11 11
CROSS- SECTION
87654321
., 1110
, ,
94
. "
. <:==.FLOW DIRECTION
•
i!
25 226 24
'>if
1.00
,." ",' , 'liOi--- ...::.- ~J
N
V1 '0.1I0-~V1--~0'
~ 0:60r.
"~•...-cE 0.. 40"'0~ .,\J"IV1.,.:= 0.20-".,0::
0.000.40
••
I I I I
0.52 0.64 0.76 0.88.
Relative Dis~harge (Ql/Q2 )
. Fig. 4.24 RESULTS OF THE TEST RUNS'
.J
--'.'1.00
~Z
, """....:l~;::.~
~~f-<~o'f-;~o>,~~
W0-0-
96
,o,
a.a_<:::>_"'" Q.. ~",
Ew 00- a>0- N
::;0-0-::JIf)
1______.
BRANCH 2
97,
BRANCH 3
BRANCH 1
BED LEVEL EVOLUTION
RUN NO.1
350
'SO
E 300
5- 250..JfOl:> 200
fOl.J 150'Q~ 100CQ
SO
8300
5- 250..JfOl> 200fOl~ 150Q~ 100CQ
Fig. 6.1
~e 300
5- 250..JfOl
200:>fOl..J 'SOQfOl 100CQ
SO
.;
BRANC:: j
98
BRANCH 2
BRANCH 3
BED LEVEL EVOLUTION
RUN NO.2
50
50
_ 350
E 300E:; 250
W 200
1U...J 150
C 100WlD 50
350
E 300E::J" 250
~..J 200150
oW 100lD
350
E 300E-'250..JW 200
1U...J 150oW 100lD
Fig. 6.2
BRANCH 1
BRANCH 2
BRANCH 3
"
E 300
!- 250...<
"";;> 200
""~ ISOCl
""~ 100
350
350
"
S 300
8-- 250...<~ 200
""...:l ISO
Cl~ 10(1o:l
RUN NO.3,
350
"
- 3008.5 250
...<~ 200;>-
""...J ISOCl
""CQ 100
Fig. 6.3 BED LEVEL EVOLUTION
BRANCH 2
BRANCH 3
BED LEVEL EVOLUTION
RUN NO.4I
__ JIlO
Eg 250
..l'-'l> 200
'-'l..J I SO
o'-'lQ:l 100
3"
"
"
E JIlIl
g 250..l~ 200
'-'l....J l!'ill
o~ 100"l
3"
_ 300
E5250..l'-'l> 200
'-'l....J lSI)
fJl:l:l 100
3"
Fig. 6.4
101
RUN NO.5
3"
300...l
"" 25.>"" '00...lCI 15.""~
10.
"
BRANCH 2
3"
300
...l
"" 25.>"" 20'...lCI
"" 15'~
10.
"
BRANCH 3
35.
300
...l""..,
>..,20'...l
CI.., 15.~'00
"
Fig. 6.5 BED LEVEL EVOLUTION
BRANCH 1
BRANCH 3
BRANCH 2
JSO
SO
E 300
5250...:I~ 200;;-
'"~ 150~'"~ 100
SO
102
JSO
RUN NO.6
350
_ 300e!. 250...:I'";;... 200
'".....:l ISO
~'"~ 100
Fig. 6.6 BED LEVEL EVOLUTION
8' 300e- 250...:I'" '00;;-'"...:I ISO~'" 100o:l
SO-f.
Final Bed Level
BRANCH 1
BRANCH 2
BRANCH 3
,so
so
e 300
e- 250
•••<-l;> 200
<-l~ 150~~ 100
""
SECTION
e 300
e- 250
•••<-l;> 200
<-l~ 150
~~ lOll
""
103
so
350
e 300
e- 250
•••s:: 200
<-l...J 150
~~ 100
""
so
,so
RUN NO.7
Fig. 6.7 BED LEVEL EVOLUTION
BRANCH 1
BRANCH 2
BRANCH 3
'"
50
104
__ 300
5g 2S0
..l
'";> 200
'"~ 150Cl
'"c::l 100
350
RUN NO.8
350
- JOO5.e. 250
..l
'";> 200
'"~ ISOCl
'"~ 100
Fig. 6.8 BED LEVEL EVOLUTION
E 300
5-- 2S0..l
'" 200>-'"..l 150Cl
'" 100o:l50
'"
"
BRANCH!
BRANCH 2
BRANCH 3350
50
RUN NO.9
_ JOO
e5250...J'"> 200
'"....J 150Q
'"= 100
105
8' ;lOO
e- 250...J'"> 200
'"~ ISOQ~ Ion<:Q
350
350
50
_ 300
e-! 250...J'"> 200
'".J ISOQ
'"l%l 100
Fig. 6.9 BED LEVEL EVOLUTION
BRANCH 3
350
so
106
12 27 2829 30 31
32 33 3••SECTION 35 " ,
"
E 300
e-- 250...l~ 200
~- 150o~ 100
350
RUN NO~10
SECTION
"
~E3 300
e'-' 250...l~ 200;>'"..J 150
oW 100<Xl
350
BRANCH I
e 300
e-- 250...l'";> '00
'"~ 150
oW 100<Xl
Fig. 6.10 BED LEVEL EVOLUTION
BRANCH 1
BRANCH 2
__ 300
eg 250
.l<-l;> 2011
<-l.....:l 150
Cl<-lCO; 100
50
BRANCH 3
50
SECTION
107
350
e JOO
e'-' 2.!iO.l<-l;> 200
<-l~ 150Cl~ 100=
350
350
RUN NO. 11
_ 300e,g 150
.l~ 200
j ISOCl<-l.co. 100
Fig. 6.11 BED LEVEL EVOLUTION
••
BRANCH 1
BRANCH 2
BRANCH 3
108
e 300
e-- 250
'"~ 200
~_ 1.50
Q~ 100<Xl
JSO
JSO
RUN NO. 12
so
350
e 3{10e'-' 250
'"<-l;;> 200
<-l~ I~O
Qw 100<Xl
~E 300
e- 250
'"<-l;> 200
<-l.....J 150Q~ 100<Xl
Fig. 6.12 BED LEVEL EVOLUTION)
BRANCH!
BRANCH 2
BRANCH 3
,so
so
so
17 18 19 •20 21
SECTION U 2J 24 25
109
__ 300
e! 250
..lOJ:> 201)OJ~ 150CiOJCQ 100
SECTION
'so
e 300
e'-" 251)..lOJ;;> 200
OJ~ 150Ci~ 100
>50
,so
RUN NO. 13
5' 300
! 250..lOJ;;> 200
eJ ISOCiOJ!Xl 100
Fig. 6.13 BED LEVEL EVOLUTION
BRANCH I
BRANCH 2
BRANCH 3
'"
.- 300E!. 2S0...l~ 200
'"..J 150CI'"Cl:l 100
110
"
'SO
RUN NO. 14
,so
.- JOUES2S0...l'">- 200
'"~ ISOCI
'"Q:l 100
Fig. 6.14 BED LEVEL EVOLUTION
5' 300
E-- 250...l"" 200;;.
'"...l 'SOCI'" 100Ol
"J
BRANCH I
BRANCH 2
BRANCH 3
3SO
50
E 300
Ei- 250...l~ 100
~150
Q
'"~ 100
so
111
50
5' 300Ei-- 150...l~ 200
~ 150
Q.c.:l 100>ll
350
350
RUN NO. 15
E lOll
Ei'-' ISO...l'";> 200
'"...l 150
Q
'"~ 100
Fig. 6.15 BED LEVEL EVOLUTION
BRANCH 2
50
RUN NO. 16
BRANCH 3
BRANCH 1
112
50
_ 350
E '300E:;- 250
W 200>W-J 150
o 100WCD 50
'50
E 300E- 250'...JW 200>W-J 150,
oW 100CD
, 350
,E 300E:; 250
~ 200
..J 150
oW 100CD.
Fig .. 6.16 BED lEVEL J:VOLUTION
113
50
12 13 14 .15 16 17
18 19
SECTION
Fig. 6.17 BED LEVEL EVOLUTION
300E..s 250
--'W 200>W--'o 150WOJ 100
RUN NO. 17BRANCH 1
350
_ 300
ES 250
--'W 200>W--'0
150WOJ 100
50J
36 7
SECTION •
350
300E
~j ..s 250
--'W 200>W--'0 150WOJ 100
50
32 33
1 SECTION 38
BRANCH 3
350
50
350
BRANCH 3
SECTION
SECTION
350
E 300E- 250..J~ 200W...J 150oW 100lD
BRANCH 2
BRANCH 1
114
RUN NO.18
E 300E- 250..J
~ 200W...J 150o~ 100
50
350
E 300
g 250..J
. ~ 200
. ...J 150o~ 100
50
Fig. 6.18 BED LEVEL EVOLUTION
BRANCH 1
BRANCH 2
BRANCH 3
.50
_ 300E..s250...JW 200>W...J 150oWCO 100
350
RUN NO. 19
_ 300
Eg 250
...JW 200>W...Ja 150wOJ 100
•SECTION
50
350
115
50
Fig. 6.19 BFD LFVFL EVOLUTION
_ 30Q
Eg 250
...JW 200>W...Jo 150WOJ 100
,so
so
so
116
,so
RUN NO. 20
..- 300ES 250...:l'-'l;> 200
'-'l...:I 150Q'-'l=: 100
8' 300
E- 250...:l~ 200
'-'l~ ISOQ~ 100~
-. 300E.!250...:l~ 200•••'-'l...:I 150
.f;j.=:l; 100
Fig. 6.20 BED LEVEL EVOLUTION
BRANCH I
BRANCH 2
BRANCH 3
117
BED LEVEL EVOLUTION
_ 300e!, 250...l~ 200
,J 150Q
'"~ 100
50
350
E 30G
!, 250...l~ 200
'"~ 150Q~ 100~
350
350
RUN NO. 21
'5300
5250...l~ 200;;.~ 150Q
'"~ 100
F'g 1::.2".I • v
BRANCH 1
50
'50
E 300E::i' 250
g; 200W..J 150
oW 100[J)
BRANCH 3
50
118
BRANCH 2
_ 350
EE 300
:; 250
~ 200W...J 150
Q 100W[J) 50
_ 350
E 300E- 250..JW 200>W...J 150
o 100WCll
RUN NO. 22
Fig. 6.22 BED LEVEL EVOLUTION
BRANCH 1
119
RUN NO. 23
350
50
_ 300
E..s 250...JWiii 200...Jo 150
WlD 100
6SECTION
BRANCH 2350
300E.s 250...J
~ 200W...J
0 150Wm 100
50
2629 30 31
32 33
SECTION 38
BRANCH 3350
300E.s 250...JW> 200W...J
0 150Wm 100
50
16 17 18____ . ~~ 20 21.:-~'_- ! !(l!'l
Fig. 6.23 BED LEVEL EVOLUTION
BRANCH 2
BRANCH 3
SECTION
50
350
E 300E- 250...J
~ 200
...J 150oW 100m
50
SECTION
RUN NO. 24
BRANCH 1
50
350'
E 300E:; 250
g! 200W-J 150oW 100m
120
350
E 300E- 250...JW 200>W...J 150oW 100m
Fig. 6.24 BED LEVEL EVOLUTION
BRANCH 3
121
50
50
BRANCH 2
350
E JOOE- 250...J~ 200W-I 150oW 100III
RUN NO. 25
350
E JOOE- 250...JW 200Gj...J 150oW 100III
Fig. 6.25 BED LEVEL EVOLUTION
'" BRANCH 1
350
E 300E::i' 250W 200>W...J 1500 100WIII 50
i6 7
SECTION
50
BRANCH 2
BRANCH 3
• "11 122728' 2930313233343536 .
SECTION 37 38
50
50
BRANCH 1
122
RUN NO. 26
350E 300E:; 250
~ 200
W...J 150
CW 100lD
350
E 300E- 250...J
~ 200W...J 150CW 100OJ
350
E 300E- 250...J
~ 200
...J 150
CW 100OJ
Fig. 6.26 BED LEVEL EVOLUTION
I
50
RUN NO. 27
350
910111213141516
17181920 -
SECTION 21 22 232425
BRANCH 3
50
50
BRANCH 1
350
123
SECTION
E 300
E- 250-oJW 200[ij..J 150oW 100m
350
910111227 28 29
30 31 3233 34 35
SECTION 36 37 38
E 300
g 250-oJW 200[ij-oJ 150oW[Q 100
E 300
~ ,250
-oJW 200[ij-J 150oWCO 100
Fig. 6.27. BED LEVEL EVOLUTION
124
RUN NO. 28BRANCH 1
350
_ 300
Eg 250
-'W 200>W-'0 150Wm 100
50
6
SECTION
BRANCH 2
350
300
Sf g 250
-'W 200>W-'0 150Wm 100
50
33
SECTION
BRANCH 3
350
300
Sg 250
-'W 200>W-') 0 150Wm
100
50
19SECTION
Fig. 6.28 BED LEVEL EVOLUTION
Final Bed Level
BRANCH 3
9 10111".<.1314,'5
16171819 202122SECTION 23 24 25
6 10 11 12272829303132333435SECTION 36 37 36
50
125
50
E 300
E- 250..JW 200
iii...J 150oW 100al
350
50
BRANCH 2
6
SECTION
350
E 300E- 250..JW 200>W...J 150oW 100al
RUN NO. 29
BRANCH 1
350
E 300
E- 250..JW 200>W...J 150
oW 100al
Fig. 6.29 BED LEVEL EVOLUTION
;
t
9
, 1
, I
I
BRANCH 1
!
.11.
BRANCH 2
BRANCH 3
5
,.
47
SECTION
3
i ..9 10 .;, i11122728 ' . , .
29 30 31 32 nWal Bed Level333435 ISECTION 363738 Flna Bed Level
50
50
350
E 300E- 250-'W 200>W...J 150aW 100W
350
E 300E- 250-'W 200>W..J 150aW 100W
50
126
RUN NO. 30
350
E 300E:; 250
~ 200W-I 150aw 100W
Fig. 6.30 BED LEVEL EVOLUTION
1
1
s.
BRANCH 2
BRANCH 3
s.
35.
E 300E- 250..JW 200
Gi...J 150CW 100lD
BRANCH 1
127
s.
RUN NO. 31
350E 300E:; 250
~ 200
..J 150
~ 100lD
35.
E 300E- 250..JW 200
Gi..J 150CW'00lD
Fig. 6.31 BED LEVEL EVOLUTiON
50
BRANCH 2
BRANCH 3
50
350
E 300E- 250..J
~ 200
...J 150aw 100en
BRANCH 1
128
50
RUN NO. 32
350 i
E 300E:; 250
~ 200W...J 150
aw 100en
350
E 300E- 250..JW 200>W...J 150aw 100en
Fig. 6.32 BED LEVEL EVOLUTION
'0
129
'0
RUN NO. 33
'0
tlRANCH 1
350
E 300E- 250-JW 200>W-' 150CW 100CO
BRANCH 3
BRANCH 2
350E 300E3' 250~ 200W...J 150
fa 100CO
350
E 300'
E- 250-JW. 200(tj-' 150CW 100CO
Fig. 6.33 BED LEVEL EVOLUTION..•
BRANCH 1
BRANCH 3
BRANCH 2
50
9 10 11 1213 14 15
161718 19 20 21SECTION 22 23 24 25
50
130
350
350
RUN NO. 34
SECTION
50
E 300
.s 250
--'W 200>W...J 150Q
W 100[l]
350
- 300E.s.. 250--'W 200fij...J 150QW1JJ 100
E 300
..5.. ~50
--'W 200fij...J 150QWen 100
Fig. 6.34 BED LEVEL EVOLUTION
3••
BRANCH 2
BRANCH 3
,.
...JW 250>~ 200
Cl 150WlD 100
300
,.
,.
, 7
SECTION
360
131
..J 300
~ 250
~ 200
Cl 1"50WCO 100
BRANCH 1
RUN NO. 35
...JUJ 250>~ 200
o 150WCO 100
Fig. 6.35 BED LEVEL EVOLUTION
Final Bad Level
1011 1227282930
3132333435SECTION ." 37 36
810111213141516 1718'9 .202122
SECTION 232425
350
50
50
50
350
"E' 300E
::; 250
W 200>W-i 150CW 100Cl
BRANCH 1
E 300E- 250...JW> 200W...J 150CW 100Cl
BRANCH 2
7SECTION
132
RUN NO. 36
350
E 300
E- 250-JW 200[jj...J 150CW 100Cl
Fig. 6.36 BED LEVEL. EVOLUTION
,
50
50
BRANCH 3
910111227282930 31 3233
343536SECTION . 37 38
50
7SECTION
,"0E 300E:; 250
~ 200W-J 150oW 100OJ
BRANCH 1
BRANCH 2
350
.E 300E- 250..JW 200>W...J 150
oW 100OJ
133
RUN NO. 37
350
E 300E- 250..JW 200[jj...J 150oW 100OJ
Fig. 6.37 BED LEVEL EVOLUTION
50
350
BRANCH 2
BRANCH 3
9101112272829 30313233
343536SECTION 3738
50
350
E 300
E- 250..J~ 200W..J 150CW 100Cll
50
6SECTION
350
134
RUN NO. 38
BRANCH 1
E 300
.s 250
..J
~ 200
...J 150CWIII 100
E 300
g 250..J~ 200W...J 150CWCD 100
Fig. 6.38 BED LEVEL EVOLUTION
I
50
910111213 '14 15 16
1718192021SECTION 22 23 24 25
135
50
BRANCH 3
910111227 28 29
30 31 3233 34 35
SECTION 36 37 38
50
350
350
350
BRANCH 1
BRANCH 2
SECTION
RUN NO. 39
E 300
E- 250..JW 200>.W...J 150oW 100m
E 300
.s 250
..JW 200ru...J 150oWCC 100
E 300
g 250..JW 200ru..J 150oWCO 100
Fig. 6.39 BED LEVEL EVOLUTION
5'
50
E 300
..s 250
..JW 200>W...J 150oWlD 100
350
136
10 11 12 '.131415 16 17 18
," 192021SECTION 22232425
12 27 2829 30 31
32 33 34SECTION 35 36 37 38
50
350
BRANCH 3
BRANCH 2
SECTION
E 300
S 250..JW 200
iii..J 150oW 100aJ
BRANCH 1
- 300E..s 250..Jw 200>W...J 150oWa:I 100
RUN NO. 40
Fig. 6.40 BED LEVEL EVOLUTION
E 300
E- 250..JW 200>W..J 1500W 100CD
I"
RUN NO. 41
'"
9 10 11 1213 14 15
16 17 18 ••, _~_
SECTlo'N"'" 11 22 23" 2425
BRANCH '3
"
BRANCH 1
"
137
'"
'"
BRANCH 2
SECTION 9
12 27 2829 30 31
32 33 34SECTION 35 38 37 38
E 300
.s 250
..JW 200Gj...J 150oWCC 100
E 300
g 250..JW 200Gj...J 150oWIII 100
Fig. 6.41 BED LEVEL EVOLUTION
-.
,.,
,..
5•
•
•
._ _-_ ..-
•
• • •RUN TIME (hi
__ TOTAL I
RUN NO.6
•
, • 5RUN TIME (h)
RUN NO.4
.-.
eO- •.•• •.•
RUN NO.8
. 6 . S 4. .RUN TIME (h)
1 ...• _02
1~~Ql
,.
. 51.3.5 .54.3.5RUNTIME (h)
.' .
......------...-.,._.•.•.'-,•.••~----_.------
-'~--_ ••"•••_.- __ ~~ ••_•••H._.• - __
•
"RUN NO.2
"
"
••lJOW
Ii!~ 20UU>is 10
""
138
FIRST NOSE (30 lis)
VARIATION OF DISCHARGE WITH TIMEFig. 6.42
. -
. 5 7.3
....
. 5 7.3
. 5 7.3
• •• 0
......-.
RUN NO. 10
...---•........,...
. 5 4.3 . 5RUN TIME (h)
RUN NO.12
••• I I "_ ••
. 6 . 5 ~3 . 5RUN TIME (h)
,.
.••~-"'-'--"~~~ ••__~'H~ .••' •••• " __
....... -.-.
10.5 1.3 .5
"
,.
5.
RUN NO. 14
. 6 1.3 . 5 .45 4.3 . 5RUN TIME (h)
,.
_ 40 • --------______...
~w
'"~ 30
U!!1c 2•
7.3
.. .
. 5 7.
. 5 7.3 . 5
• •
.....-----
' ..
__ Q3 .:..•....TOT~q
139
. 5 4. . 5RUN TIME (h)
RUN NO. 11
. 5. 5 1.
Fig. 6;43 VARIATION OF DISCHARGE WITH TIME
RUN NO.13
. 5 1.3 . 5 . 5 4.3 . 5RUN TIME (h)
.51.3.5 .54.3.5RUNTIME (h)
-~ ..
. .. ~._.~.H._. _
.-..--...
FIRST NOSE (40 lis)
"
RUN NO. 9
"
10
10.
"
10
_ 40 . _-- -- .' •.••••••••..•..•..•.•.•. ~
~
"_40
•• !w
'""'30••J:U<IIis 20
• 5
.. .•.
.5
_0'..• .
RUN NO. 16
RUN NO. 20
2.3.5 4. 5.RUN TIME (h)
2.3.5 4. 5.3.5RUNTIME (h)
1.
1.
.-__ • eo '_o'.
HO
__ •••
B
::-:::.:::::---_._. ---_._-........ .• ' ....•.•..•..•.•..• ..-.•.-
_____ ~_~ __ O".O~.__ ~_~ __ .HO•._O_
~---..•.•........
o0.50.51.51. 2.52 3.53.454.54. 5.5556.56. 7.5
RUN TIME (h)
RUN NO. 18
o o.
"
"
oO. 5
""
""
. ....2.. 5 4. 5.3 .5
RUNTIME (hI1.
•. . ....
. ..•.
--,.e._.__ ~ ._. _0' _
o .. ,
"
1D
*- •.
... ......--.-- .....-
140
RUN NO. 21
"
.. .•
2.3.5 •• 5.3 .5RUN TIME (h)
,.
Fig. 6.44 VARIATION OF DISCHARGE WITH TIME
_.oe'~o"o ~ __ eo~o.'~o.oeo ~ ~1
a.a •••.•..••
-_....... . •.•......•....•...
FIRST NOSE (20 lis)RUN NO.15
" r------;::.,~.:~Q;.';.=.~':f_:..:.~~~3=:.:_:,;.;"~O;TP.;l;:;-I----1
RUN NO.19
o~5~51.51. ~5~ 3.5~ ~5~ L5L ~5L ~5RUN TIME (h)
"
o o.
""
,. 5
.-
. 5
•. ..---
. 5
...
.--5.'
4iITOTA~:1
RUN NO. 27
. Ii 4.RUN TIME (h)
.5 4.55.3.5RUN TIME (h)
.5 4.56.3.5RUN TIME (h)
RUN NO. 25
2.'
I~:Q2 ;'" ~__Q3
,. 5
••• ,-O_.~ ~.'•.•.•
1. Ii 2.
1. 5 2.
._--~-_.--..
DISCHARGE WITH TIME
- .•.--~~_. ••_••OHo~O_OHO_._••_••O~.~.-----.~._--~--_.__._-~-~
--_ ..•.-----_.~~-.~..-- .............•..
..• ..
••. 5
••. 5
••
141
RUN NO. 23••
••
_40~w"li1~ 20o'"B 10
A5
. 5
.._ .•...
VARIATION OF
.5 4.55 .. 5RUN TIME (h)
RUN NO. 26
-.- ..
~"OH._~_H,_'H'_~ __ -_
RUN NO. 24
[--:92" '1~~'P3' ~TOTALI
1.52.3,5 4.55.3.5RUN TIME (h)
1. 5 2.3 . 5 4. 5 6.3 . IiRUNTIME (~)
Fig. 6.45a
_~'~'_O__ ~_""'HO_O__ ~.OHoo .•. _
___ • '"O-._.H._._. '"._•••_._OHO•.__.___- ... e.
SECOND NOSE ( 30 lIs)
RUN NO. 22
••. 5
.•.-_•.....•....•....-.-~~~---.-.-.-.•O. 5 1. 5 2.3
••
••~40
W"li1~ 20o'"is 10
••
• •
......
..........
ok •••••••••••
.....
.....
1 • •••• •
•• •••• e
. RUN NO. 29
I.=;:: ~~:""~:';:;::,Q3-:-:'---:g.: ferAL I
I:;::'Q2,1~:;;: Q3iF ...*TOTAL I
1. 2.3 . 5 4. 5 5.3 . 5RUN TIME (h)
1.5 U 15 ~5 a3 L6RUN TIME (h)
....
___ .w' w-.... .
--,-.~.~.--.-.-•.._~-.-.-.-.~..~--.-..~
oO.5 1. 5 2. . 5 4. 5 5.3 . 5
RUN TIME (h)
o o.•
RUN NO. 30
.0
o o.•
.0
142
RUN NO. 28
•• •••• •• ok •• _-' •••••••••••••• _ •..•••••••••...•••
60
-40
~W 30
~~ 20oU>C 10
[40W 30
~~ 20oU>is 10
SECOND NOSE (30 ils )
Fig. 6.45b VARIATION OF DISCHARGE WITH TIME
. 5
• •
..
-_\TOTAL::I
RUN NO.3S
-_ .
RUN NO. 34
1"-' 02....
.--•..•-.--.-.-.----------~_......•-
..
1.5 U.5 ~5 U .5RUNTIME (h)
1. 5 2.3 . 5 4. 5 6. 6. 5RUN TIME (h)
1. 5 2.3 . 5 4. 5 5.3 . 5RUN TIME (h)
..
___ .------~-. _ ...•..•• I
..
oO••
RUN NO. 32
••
oO••
60
o o.•
60
40
~w"~ol;:1:"o'"25 10
..
..
...
..
...
~_.•.•...
SECOND NOSE (40 lIs)
>~~~TALI
... -.. ..
..
RUN NO. 31
RUN NO. 33
RUN NO. 35
1.52.3.5 4.55.3RUN TIME (h)
..
1. 5 2.3 . 5 4. 5 5.3 . 5RUN TIME (h)
_.-.~.-.~.-.~.-.----,~.~._~~~.~.---... ..
..... -------------- ..
.. .
__ ._~ •.• ".__ ~-",-----",- ••• I I....................---...-- ..
oO••
o o .•
60
00.150.51.51.52.52.53.53.54.54.55.55. 6.58.5.5RUN TIME (h)
w"~~ 20o!!l010
40
Fig. 6.46 VARIATION OF DISCHARGE WITH TIME
60
143
w"~:<20
11l°10
40
60
~w"~ol;:1:"o'"l5
10
• •
• •2.. 5 4.55.3RUN TIME (h)
RUN NO. 40
•
1.
.. ....--......-.--------.. . . . ..... 1-----1. 5 2. . 5 4. 5 5.
RUN TIME (h)
• •••• -_.~" ~_~. w
RUN NO. 38
......
---"-"-"-' ---~_.~----~-"~.."••••
••
••• •
••_40e.~ 30a::2 20
" I IU)a 10
• G
..
1.52.3.5 4.55.3RUN TIME (h)
......
.1' •• '
SECOND NOSE (20 lIs)
••••
••RUN NO. 41
W 3.
~""J: 2."U)
C 10 .
RUN NO. 37
RUN NO. 39
1. 5 2.3 . 5 4 5 5.3 . 5RUN TIME (h)
.-.~.~._.~.".~.~..~~".~.~._.~.-.~.~._.~--~-.
Fig. 4.47 VARIATION OF DISCHARGE WITH TIME
144
••••
••
a
J;';:':';:;:'~'~';:'::':'~'~';;:'='::;'::,;:~';;'=';;,;'~';:':;':'j'00. 5 ''I '1,'5 2.'3 '3:15 .•• 4.45 5.3 6.15 '1RUN TIME (h)
~40
W 3.
~
~ 20 t::::::::":"::":"::":":"::"::":"::":":":":":":"::":"::":"::"1.•, ••••• 1.Q 10
0.1
I
s2/s3 Vs q2/J3 FOR THE FIRST NOSE (30 I/s)
105 6 7 8 9J2
1q2/q 3
5"6,789J2
145
. ,Fig. 6.48 RELATION BETWEEN SEDIMENT TRANSPORTRATIO AND DISCHARGE RATIO
•
0
0
• 0 ,
i, , I
II
II I
t- o
0
0..
o I)
I
I,
* I,
2
J
5
6
7
7
8
2
J
5
6
9
I
I
10
"II
0. 1
r ..'\,'
M(f)
" 1(\J 9(f) II 8
t
"
s2/sJ Vs. q2/qJ fOR THE FIRST NOSE ( 40 I/s)
0.1 105 6 7 8 975 6 ,7 8 9
. 1q2/q 3
146
2
•
,.
..
. ,
I .I,,
.
,
I
, , ,
J .
I ,
..,
I ,
Fig. 6.49 RELATION BETWEEN SEDIMENT TRANSPORTRATIO AND DISCHARGE RATIO
2
6
5
8
6
9
7
2
5
. '
10
0. 1
M(j)
" 1C\J 9(j) 8
•
s2/s3 Vs 'q2/q] FOR THE FIRST NOSE (20 I/s)
105.6789j25 ,6 7 8 9j ,2
III ' .
" j
//I
, I ' I
/,,
/•j
/I,
/ ••I ' ,
i,
,
, ,
,I .I I I
s
147
9
8
7
8
6
9
7
6
s
0,1
Fig. 6.50 RELATION BETWEEN SEDIMENT TRANSPORTRATIO AND DISCHARGE RATIO
10
0,1
M(j)
'..C\J(j)
(
s2/s3 Vs q2/q3 FOR THE SECOND NOSEC 30, I/s)
J , 52
102 J " 5, 6 7 8 9:3 ~S67a92
I!
--~-~
>
./
I //
, :/>
I*
17 ,
,
11 *
*I
, I , I I ,I I I I I
J
Fig. 6.51 RELATION BETWEEN SEDIMENT TRANSPORTRATIO AND DISCHARGE RATIO
5
98
148
2
5
0. 1,
J
'2
2
J
,
'6
109
87
6
0, 1
M(j)'..,
C\J(j)
1 '
(
s2/sJ Vs q2/q] FOR THE SECOND NOSE( 40 I/s),
,::: ]: , s:101 .
3 ~56789
5
J
2
5
6
149
i
J
, Fig. 6.52 RELATION BETWEEN SEDIMENT TRANSPORTRATIO AND DISCHARGE RATIO
2
6
98
2
.
!
/, , I ,
I, I. '
,
I
!,/
I
,
** I ,,
1
.5
,,. ,
J
II I
.',
, " " - "0,1
109
82
0. 1
M(fJ
"-C\I(fJ
(
s2/sJ Vsq2/qJ FOR THE SECOND NOSE(20 I/s)
2 J .• 5
1023 i56789
, 12 J "56789
Fig. 6.53 RELATION BETWEEN SEDlMENT TRANSPORTRATIO AND DISCHARGE RATIO .
150
0.1
2
5
98
7
6
2
J
,
.
I . . ,-c-
/, /'
I
~
.
II: I
I I
I.
T I
,
5
2
.5
1098
7
6
0.1
M(j)
"C\I(j)
G
APPENDIX A.".... .- . . - ","If
DETAIL OF THE REHBOCK WEIRS
The discharge distribution over the two branches downstream of the bifurcation is measllredby the use of two Rehbock weirs. The discharge equation of a Rehbock weir is (ISO, 1975):
with
he = h+h = h+0.0012
Ce = 0.602+0.083h/p
where
QR = is the discharge measured over the Rehbcck weir;
Ce = is the coefficient of discharge;
b = is the measured width of the weir;
he = is the effective piezometric head witli respect to the level of the crest;
h = is the measured head;
h = is an experimentally detdmined quantity which compensates for the influence.of surface tension and viscosity; ..
p = is the apex height in meters.
THE WIDTH AND TlIE APEX HEIGI.IT OF BOTH TIlE RWBOCK wEiRS AKE GIVEN BELOW:
THE RIGIIT RWBOCK WEIR
p=0.1719mb = 0.4969 111
THE LEFTREIIBOCK WEIR
p = 0.1753mb = 0.4978 m
Calibration charts of the Rehbock Weirs were made '.-,-i:lo :biG eq:.:&tionfrom which directiythe discharge was derived dependent Qnthe measured head h.
A-1
(B. I)
(B.Z)
..
B-1
Co = is the coefficient of discharze;
b = is the measill'ed width of the weir;
The sources of possible error can be identified by examininz Eq.(5 Ii; these sources are:
p = is the apex heizhtin meters. '
h = is the measured head;
he = is the effective piezometric head with respect to the level of the crest;
B.2 SOURCES OF j'OSSIBLE ERROR
kJ,= is an experimentally determined quantity which compensates for the influenceof surface tension and viscosity;
B.l DISCHARGE EQUA nON OF A REHBOCK WEIR IS (ISO, 1975):
ACCURACY OF THE REHBOCK WEIRS
i
APPENDIX B. ,
where
C, ';' 0.60Z+0.083h/p
with he = h+kh = h+0.001Z
1. the discharze coefficient Cc;Z. the dimensional measurement of b;3.. the measured head h;4. the corrective termkh ..
The total error results from'a contribution of'all these errors, According to the quadratic errorpropagation method the relative erro,"on.the rate of flow is calculated with:
"
! QJl = is the discharze nleasured over the Rehbock weir;
The,accuracy of the Rehbock weirs were determined with the help of well-known statisticalI' methods.
r
(B.3)
(BA)
eb = +0.5 mm. ,i, I
From Eq.(B3) it can now be found tnat Xb=+(0.5/500)= +0.1 %.
In Eq. (B2) the relative error in he is-used:
Error in he:
Error in b:
As can be seen in Eq. (B2) the total relative error can be calculated once the individual relativeerrors are found.
The width b was measured with a ruler divided into I nll11intervals; therefore
wh'ere ebcii th'e error in t1;e measurement of width b.
, '
B-2
In Eq. (B2) Xb is defined as:
Error in Ce:, .
In ISO (1975) it can be found that the relative error in the coefficient of discharge can beexpected to be XCe= + 1.0 %,
where
Xh,= is the relative, error in he;
XQR= is the relative error in QR;
B.3 ESTIMATE OF THE TOTAL ERROR
XCe= is the relative error in Ce;
Xb= is the relative error in b;
where
ehl, ehZ,... = are the errors in the measurement ,?f head h;
Given ihis smail value, the contribution of Xb to the total error (see Eq.B2) is considered to be,negligible. "
'. ekh= is the error in the h term;. ,,I,J
\{'-"LJ,1.•.•.~
rI.
20-",=,is the error in the mean of the readings of the head measurement.
According to'ISO (] 975): ekh= 0,3 n1l11.,
The head-!l1easuring device was divided into 0.1 n1l11intervals.
The head h was therefore read to ehl = + 0.05mm; the zero was set to within eh2 = + 0.05' .111111.
The standard deviation in the mean df ten head measurements proved to be d", = 0:03 nllll.I . .r "
It should be realized that Xhe,and tllerefore also XQR, isnot single-valued for a weir: it. willvary with the discharge. A worst-~ase value can however be given: ISO (] 975) sets aminimum value for h: h>0.03 m. As it result:
he 2:0.03+0.0012 = 0.0312 m= Xhe~ + 1.0 %.
Total error:
With the results of the various contributions, the total relative error made for the rate of flow(in the worst-case) can now be calculated using Eg. (HZ).
(B.5)
, ,
B-3
CALIBRAnON CHART OF THE BUCKETS
BUCKET 1 BUCKET BUCKET BUCKET 4 BUCKET 5 BUCKET 6READIN WEIGHT REAOIN WEIGHT READIN WEIGHT READIN WEIGHT READIN WEIGHT READIN WEIGHT(em) (kg) (em) (kg) (em) (kg) (em) (kg) (em) (kg) (em) (kg)
7.500 24.568 7.500 25.369 7.500 24 648 7.500 24.452 7.500 23.053 7.500 22.0847.600 24.673 7600 25.477 7.600 24.752 7,600 24.559 7.600 23.147 7.600 22.1777.700 24.779 7,700 25.585 7.700 24.856 7.700 24.667 7.700 23.241 7.700 22.2707.800 24.884 7.800 25,693 7.800 24,960 7.800 24.774 7.800 23.334 7.800 22,3637,900 24.989 7.900 25,801 7.900 25.064 7.900 24.882 7,900 23.428 7.900 22.4568.000 25.094 8.000 25,909 8.000 25.167 8.000 24.989 8.000 23.521 8.000 22.5498.100 25.199 8.100 26,017 8.100 25.271 8.100 25.097 8.100 23.615 8.100 22.6428,200 25,304 8,200 26,125 8.200 25.375 8.200 25,204 8,200 23.709 8.200 '22.7348.300 25.409 8300 26,233 8,300 25.479 8.300 25.312 8.300 23.802 8.300 22.8278400 25514 8.400 26,342 8,400 25.582 8.400 25.420 8,400 23.896 8.400 22.9208,500 25,619 8.500 26,450 8,500 25.666 8.500 25.527 . 8.500 23,990 8,500 23,0138.600 25,724 8.600 26.558 8,600 25.790 8.600 25.635 8.600 24.083 8600 23.1068.700 25.829 8.700 26.666 8,700 25.894 8.700 25,742,. 8.700 24.177 8.700 23.1998.600 25.935 8,800 26.774 6.600 25.996 8.800 25.850, 8.800 24.270 8.800 23.2926.900 26.040 8.900 26.882 8.900 26.101 8.900 25,957 8.900 24.364 8.900 23.3859.000 26,145 9.000 26.990 9.000 26,205 9.600 26.065 9.000 24.458 9.000 23.4789.100 26.250 9.100 27.098 9.100 26.309 9.100 26.172\ 9,100 24.551. 9.100 23.5719.200 26.355 9.200 27.206 9.200 26.413 9.200 26.280 9.200 24.645 9.200 23.6649.300 26.460 9.300 27.314 9.300 26.517 9.300 26.387 9.300 24.739 9.300 23,7579,400 26.565 9.400 27.422 9.400 26.620 9.400 26.495 9.400 24.832 9.400 23.8509.500 26.670 9.500 27.530 9,500 26.724 9.500 26.602 9.500 24.926 9.500 23.9439.600 26,775 9.600 27.638 9.600 26.828 9.600 26.710 9,600 25.019 9.600 24.0369.700 26.880 9.700 27.746 9.700 26.932 9.700 26.817 9.700 25.113 9.700 24.1299.800 26,985 9.800 27.854 9.800 27.036 9,800 26.925 9.'800 25.207 9.800 24.2229.900 27.091 9.900 27.963 9.900 27.139 9.900 27,032 9.900 25.300 9.900 24.31510.000 27.201 10.000 28.071 10.000 27.243 10.000 27,150 10.000 25.394 10.000 24.40810.100 27.320 10,100 28.179 10.100 27.361 'V.IVV ::-,274 .", _n", ::::;,.488 10.100 24.501P•.• ~.
10.200 27.438 10.200 28.288 10.200 27.480 10.20'0 27.398 10.200 25.605 10.200 24.59410.300 27.557 10.300 28.400 10.300 27,598 10.300 L' .'JLL 10.300 25.725 10,300 24.70810.400 27.675 10.400 28.513 10,400 27.717 10.400 27.646 10.-400 25.846 10.-400 24.82510.500 27,793 10.500 28,625 10.500 27.836 10.500 27.771 10.500 25.967 10.500 24.94110.600 27.912 10.600 28.737 10.600 27.955 10.600 27.895 10.600 26.087 10.600 25.05710.70,0 28,030 10.700 28.849 10.700 28.073 10.700 28.019 10.700 26,208 10.700 • 25.17310.800 28.148 .10.800 28.961 10.800 28.192 10.800 28.143 10.800 . 26.329 10.800 25.26910,900 28.267 10.900 29.073 10.900 28.311 10.900 26,267 19.900 26.449 10.900 25.40611.000 28.385 11.000 29.186 11.000 28.430 11,000 28.391 11.000 26.570 11.000 25.52211.100 28.504 11.100 29.298 11.100 28.548 11.100 28.518 11.100 26.691 11.100 25,63811.200 26.622 11.200 29.410 11.200 28.667 11,200 28.640 11.200 26.611 11.200 25.75411.300 26.740 11.300 29,522 11.300 28.786 11.300 28.764, 11.300 26.932 11.300, .25,87011.400 26.859 11.'100 29,634 11.400 28.905 11.400 28.888 11,400 27.053 11.400 25.98611.500 28,977 11.500 29.747 11.500 29.023 11.500 29.012, 11.500 27.173 11.500 26.10311.600 29.096 11,600 29.859 11.600 29.142 11.600 29.136 11.600 27.294 11.600 26.21911.700 29.214 11.700 29.971 11.700 29.261 11.700 29.261 1,1.700 27.415 11.700 26.33511,800 29.332 11.800 30.083 11.800 29.360 11.800 29.385 11.800 27.535 11.800 26.45111.900 29.451 11.900 30.195 11.900 29,498 11.900 29.509 11.900 27.656 11.900 26.56712.000 29.569 12.000 30.306 12.000 29,617 12.000 29.633 12.000 27.777 12.000 26.68412.100 29.688 12.100 30.420 12.100 29.736 12.100 29.757 12.100 27.897 . 12.100 26.80012.200 29.806 12.200 30.532 12.200 29.855 12.200 29.682 12.200 28.016 12.200 ,26.91612.300 29.924 12.300 30.644 12.300 29.973 12,300 30.006 12.300 28.138 12,300 27.03212.400 30.043 12.'100 30.756 12.'100 30.092 12.400 30.130 12.400 28.259 12,400 27.14812.500 30.161 12.500 30,866 12.500 30.211 12,500 30.254 12.500 28.380 12.500 27.26512.600 30.279 12.600 30,981 12.600 30.330 12,600 30.378 12.600 28.500 12.600 27.38112,700 30,398 12.700 31.093 12.700 30.446 12.700 30.50212.800 .30.516 12.800 31.205 12,800 30.567 12.800 30.62712.900 30.635 12900 31.317 12.900 30.686 12.900 30.75113,000 30.753 13.000 31.429 13.000 30.805 13.000 30.87513.100 30.871 13.190 31.542 13.100 30.923 13.100 30.99913.200 30.990 13.200 31.654 13.200 31.042 13.200 31.12313.300 31.108 13.300 31.766 13.300 31.161 13.300 31.24713.400 31.227 13.400 31.878 13,400 31.280 13.400 31.37213.500 31.345 13.500 31.990 13.500 31.398 13.500 31.49613.600 31,463 13600 32.103 13,600 31.517 13.600 31.62013.700 31,582 13,700 32.215 13700 31636 13.700 31.74413.800 31.700 13,800 32.327 13.60q 31:755 13.800 31.86813.900 31.819 13.900 32.439 .13,900 31.873 13.900 31.993
14.000 32.551 14.000 31.992 14.000 32.11714.100 32.663 14,100 32,1.11 14.100 32.24114.200 32.776 14.200 32.230 14.200 32.36514,300 32.888 14.300 . 32,348 14.300 32.-46914.400 33,000 14.400 32.'167 14,400 ~2.o'i'S i:
14.500 32.586 14.500 32.73814.600 . 32.7051(700 32.82314.800 32.94214.900 33.061
C-2
APPENDIX D
:PROGRAM ill CALCULATE THE NORMAL DE:PTHS
5 Cl810k=59320 m = 4.425 B1 = 130 b2 = .440 M2 = .0013545 M1 = .0013550 C2 = 3055 C1 = 3060 l2 = 8.470 b3 = .680 M3 = .0013585 C3 "' 3090 l3 = 8.691 q1 = .0393 R = 094 W81 = 30.9581 = ((W81 12650) * (10 16)) 13600
• I •
100 qualq = EXP((-31 (3 * m - 5)) *LOG(k)) * EXP((-21 (3 *m-5))* lOG(b21 b3)) * EXP((51 (3 * 1m - 5)) * LOG((I_3 .;. R)/L
2))
110 PRINT "81= "; 811180 q3 = q1 I (qualq + 1)1185 PRINT "03="; q32100 q2 = q 1- q32105 PRINT "02="; q2
. 2120 quaIs = EXP((m) * lOG(qualq)) * k2140 S3 = 811 (quaIs +'1)2145 PRINT "83="; S3216082 = 81- S32165 PRINT "82="; 822180 h2 = q2 * EXP((-1/5) * lOG(82)) * EXP((-4/5) * lOG(b2))*EXP((1/5)*lOG(M2))
2185 PRINT "h2="; h2
3100 h3 = q3 * EXP((-1/5)*lOG(s3)) * EXP((-4/5) *lOG(b3))*EXP((1/5)*lOG(M3))
D-1 '
3105 PRINT "h3="; h3,3120 i2 = (1 I q2) * EXP((3/5) * LOG(S2)) * EXP((2/5) *LOG(b2)) * EXP((-3 I 5) * LOG(M2)) * EXP((-2) * LOG(C2))3125 PRINT "i2="; 123140 i3= (1 I q3) * EXP((315) * LOG(S3)) * EXP((2/5) *LOG(b3)) * EXP((-3/5) * LOG(M3)) * EXP((-2) * LOG(C3))3145 PRINT "i3="; 133160 u2= q2 I (b2,* h2)3170 u3 = q31 (b3 * h3)3180 PRINT "U2=";U24100 PRINT "u3="; u34120 PRINT "Delta h=";4130 IF R <> 0 THEN PRINT (13 * R) ELSE PRINT "0"4140 REM if delta h larger then zero then the water level inbranch 3 is higher.4150 PRINT "02/03="; quatq4160 PRINT "SiS3="; quats'4180 h1= q1 * EXP((-1 15) * LOG(S1)) * EXP((-4/5) *LOG(B1)) * EXP((1 15) * LOG(M1))4190 '1 = (1 I q1) * EXP((3/5) * LOG(S1)) * EXP((2 15) *LOG(B1)) * EXP((-3/5) * LOG(M1)) * EXP((-2) * LOG(C1))4200 PRINT "h1 = "; h14210 PRINT"i1 ="; i14220 U1= q11 (h1 *.1)4230 PRINT "U1= "; u1END
D-2
, ,