1979-2016intimation to SRPC. The status regarding the same shall be discussed in meeting. Review...
Transcript of 1979-2016intimation to SRPC. The status regarding the same shall be discussed in meeting. Review...
Agenda for the 90th
Meeting of PCSC scheduled to be held on 27
th May, 2020 (through VC/Online) Page 1
Southern Regional Power Committee Bengaluru
Agenda for the 90th Meeting of Protection Coordination
Sub-Committee of SRPC to be held on 27th May, 2020 through VC/Online
1. Introduction
2. Confirmation of Minutes of last PCSC meeting
Confirmation of minutes of 89th Protection Coordination Sub-Committee meeting held on 13-14 February 2020.
3. Grid Occurrences
3.1 Grid Disturbances (GD), Grid Incidences (GI), trippings due to failure of Auto-reclosing
(A/R) and mal-operation of PLCC equipment that occurred during the period January - March, 2020, given at Annexure-I, would be discussed in the PCSC meeting.
Constituents are requested to furnish the following information in respect of the above grid occurrences to have fruitful discussions:
(a) Detailed analysis of the events along with SLD or equivalent pictorial
representation clearly showing (i) Location of the fault, and (ii) Bus-bar
arrangement/ Configuration of feeders and other connected equipment with
proper CB positions (OPEN/ CLOSE) at the time of occurrence of the fault along
with records of Event loggers, Disturbance recorders.
(b) Remedial Action(s) taken.
(c) Relay setting details.
Constituents are requested to furnish full particulars of the tripping events pertaining to their system, preferably in the form of power point presentation, well
in advance (latest by 22-05-2020) to the scheduled meeting date, to take up for
discussion in the meeting.
3.2 In compliance of Regulations 5.2 (r) of IEGC, the Constituents are required to furnish the following information in respect of Grid Occurrences within 24 hr. of occurrence of the same to SRLDC/ SRPC: (a) First Information Report (FIR) (b) Event Logger (EL) output (c) Disturbance Recorder (DR) output (d) Trip event analysis report (with pre and post fault system conditions) Non-furnishing of tripping details (FIR/DR/EL/TR) for the period 16.01.2020 – 30.04.2020 had been brought to Constituents’ notice vide the following SRPC letters: (i) No. SRPC/ SE-III/ PCSC/ 2019-20/ 642 - 52 dated 24.01.2020,
Agenda for the 90th
Meeting of PCSC scheduled to be held on 27
th May, 2020 (through VC/Online) Page 2
(ii) No. SRPC/ SE-III/ PCSC/ 2019-20/ 1051 - 62 dated 11.02.2020, (iii) No. SRPC/ SE-III/ PCSC/ 2019-20/1219 - 32 dated 25.02.2020, (iv) No. SRPC/ SE-III/ PCSC/ 2019 - 20/1670 - 77 dated 12.03.2020, (v) No. SRPC/ SE-III/ PCSC/ 2019 - 20/1832 – 43 dated 23.03.2020, (vi) No. SRPC/ SE-III/ PCSC/ 2019 - 20/ dated 15.04.2020, (vii) No. SRPC/ SE-III/ PCSC/ 2020/1864 - 76 dated 21.04.2020 and (viii) No. SRPC/ SE-III/ PCSC/ 2020/1912 - 23 dated 08.05.2020,
Non-compliance in this regard would be discussed in the meeting.
4. Submission of Reports/ Compliance by Constituents
4.1 Status of implementation of Recommendations of Protection Coordination
Sub-Committee (PCSC)-89 Status of implementations of recommendations of PCSC-89 shall be presented by
constituents in forthcoming PCSC. 4.2 Status of implementation of Recommendations Protection Coordination
Sub-Committee (PCSC), which are pending
The status of implementation of PCSC recommendations (up to 89th PCSC meeting), which are pending is given at Annexure-II. The latest status on the same may please be sent latest by 20.05.2020, to place the same before the sub-committee.
4.3 Remedial measures for "Transmission Elements under Forced Outage"
The Constituents are requested to furnish the remedial measures/ actions taken by them for the tripping events, as circulated vide this office emails (Annexure-III), to discuss the same.
The tripping events are based on the daily reports at SRLDC website http://srldc.in/Reports.aspx under the menu: Reports->Daily-> "TL under Forced Outage").
4.4 Certificate for Healthiness of Batteries
As per the MoP direction, given in pursuant to recommendations of the Enquiry Committee (NEW grid disturbance on 30th & 31st July, 2012), the monthly certificate for healthiness of batteries, installed at 220 KV and above voltage level Substations (for power supply to Relays, RTUs and PLCC equipment) are required to be obtained by RPCs from their respective Constituents and furnish the same to CEA/ MoP.
With reference to above, the Constituents have been requested to submit the certificate on healthiness of batteries on monthly basis (i.e. status for a month shall be sent by the 7th day of the following month) to SRPC Secretariat.
The sought status for the month of January - April, 2020 is awaited from the following SR-Constituents:
January : UPCL and SEL February: NTPC (Rmgdm, Kymklm and Simhadri), UPCL and NTECL March : APGENCO (Thermal), KPTCL,TPCIL, MEPL, NTPL and NTPC (Rmgdm)
The non-reporting of status of healthiness of batteries may be discussed.
Agenda for the 90th
Meeting of PCSC scheduled to be held on 27
th May, 2020 (through VC/Online) Page 3
5. Protection Management system (PMS) project
Protection Database Management System (PDMS) portal of PMS project achieved “Go-
Live” on 20th
January 2020. The same was communicated to constituents vide SRPC mail
dated 20.01.2020. It was also requested to scrutinize the relay settings uploaded in PDMS
constituents. All constituents were to communicate the feedback to SRPC and intimate the
changes through DMNS. In this regard reminder mail was send vide SRPC mail dated
17.04.2020. Consolidated comments regarding relays settings of all substations have been
received only from KSEBL.
Constituents are requested to scrutinize the PDMS data on priority and
communicate correctness of data through mail to PRDC & SRPC before 20th
May 2020
and discrepancies in the data noticed, if any, shall be submitted through DMNS, with
intimation to SRPC. The status regarding the same shall be discussed in meeting.
Review meeting of PMS to verify the pending SAT features of PSCT was held in SRPC
Bengaluru on 12.03.2020 and 18.03.2020. During the meeting PRDC demonstrated
transient simulation for the following protection functions on Bus branch database of SR
network:
Bus Bar Differential Protection
Line/Cable Differential Protection
Transformer over fluxing Protection
Transformer Restricted Earth Fault Protection
Generator Differential Protection
Generator Reverse Power Protection
Generator Negative Sequence Protection.
Distance relay performance during power swing – This was demonstrated on test
system
As per the Record Notes of meeting PRDC shall be attending two pending features and 28
pass with remarks features immediately.
On completion of the two pending features and 28 pass with remarks features the project
could Go-Live. Hence, all utilities/users are requested to verify the data as well as
PSCT features thoroughly and report the same on urgent basis so that shortcomings, if
any, may be brought to the notice of the project implementer (i.e., M/s. PRDC) for
necessary correction/tweaking before the project is Going Live.
6. Protection Audit
6.1. Protection Audit of various 220kV & above stations in Southern Region
The recommendations of protection audit of various 220kV & above stations in
Southern Region held during October – December 2019 were compiled and were
circulated, utility wise, vide SRPC mail dated 21st April 2020. It was brought to the
notice of constituents that the observations/ Recommendations were categorised by
the PCSC as “To be implemented”, “Desirable”, “Optional” and “Drop” taking into
account primacy of system protection aspects.
The constituents were requested to comply the recommendations categorised as “To
be implemented” in a time bound manner and report to SRPC, so that the
compliance of the same could be submitted to CERC, through periodic (bi-monthly)
reports. Status regarding the compliance of such recommendations may please be
informed by 15th
May 2020.
Agenda for the 90th
Meeting of PCSC scheduled to be held on 27
th May, 2020 (through VC/Online) Page 4
It was also informed that the observations/recommendations categorised as “Drop”
were generally the aspects which, are consistent with best practice and already
available/implemented in the substation. The categorisation no way implied that the
observations/recommendations are disregarded.
The utilities were requested to make sincere efforts to comply with the
recommendations categorised as “Desirable” and “Optional”, as the same are the
considered recommendations of the audit team to facilitate the faultlessness of the
substations/switchyards. It was requested that compliance of such recommendation be
reported to SRPC for compiling the same for records and reference.
6.2. Updating of Protection audit format
All SR constituents were requested to share suggestions/ modifications/ deletions
required in the protection audit format, vide SRPC mail dated 02.08.2019, so as to
update the same as per recent trends followed in the industry. Inputs have been
received from TSTRANSCO only. All constituents are requested to furnish the inputs
in this regard before 15.05.2020 for further discussion in the forthcoming PCSC
meeting.
7. Review of Islanding Scheme of Southern Region
A meeting to review Islanding Schemes in SR, taking into consideration the network
changes, was held on 27.01.2020 at SRPC, Bangalore and Record Notes of the same
was circulated vide SRPC mail dated 27.01.2020. As per the same SR constituents
were requested to furnish the following information:
i. Low and high frequency set points of all generators (including RE) in the
existing/proposed Islanding Schemes.
ii. Frequency at which generators are taken to house load operation.
iii. Stage wise mapping of df/dt and AUFR relays in PSSE case file.
iv. All network changes/updates.
v. Implemented islands, and details of lines crossing islanding schemes and
network changes within islands.
vi. New generation additions proposed up to 31.3.2021.
vii. Renewable Generators (i.e. Solar & Wind) set points w.r.t to Under Frequency
and Over Frequency tripping and their location in PSSE case file.
viii. Critical loads within islands and their location in PSSE case file.
Details in this regard has been received from KSEBL, TANTRANSCO, PED, and
TANGEDCO. The details are consolidated at Annexure – IV. Details of House load
operation details of generators were also sought vide SRPC mail dated 17th
March
2020. The information received in this regard is also available in Annexure –IV.
The utilities, which are yet to furnish the above information are requested to furnish
the same by 20th
May 2020.
8. SPS for 400 kV Nellore PS-Nellore D/C lines
SPS for 400kV Nellore PS – Nellore DC lines operated on 22.02.2020 at 12:07 hr. and
400kV Nellore PS-Nellore line II tripped. During antecedent condition, 400 kV Nellore
PS-Nellore lines were connected directly to 400 kV Thiruvalam through the Tie-breaker
at Nellore. It was intended to take LC on 400 kV Nellore-NPS line-2 on 22.02.2020.
While taking LC, main breaker of Nellore-Thiruvalam line-2 was closed at Nellore end.
Since 400 kV Nellore- NPS is a short line, there was sudden inrush of power immediately
Agenda for the 90th
Meeting of PCSC scheduled to be held on 27
th May, 2020 (through VC/Online) Page 5
after closing the main breaker. Due to this SPS at Nellore operated resulting in the
tripping of line 2 at Nellore end and DT was send to NPS end.
SPS Logic implemented is: Tripping current setting = 2580A with Time Delay 5 Sec.
The issue may be discussed is meeting
9. Status of Insulator replacement in the following lines of KPTCL
a. 400kV Hassan – Nelamangala
b. 400kV Nelamangala –Talaguppa.
As per information from KPTCL, during September - October 2019, the lines were kept
in non-auto mode due to insulator replacement works. However, auto reclose function in
the lines is still in disabled condition which is a matter of concern. Status of the work and
matter of enabling of auto reclosure in the lines may be discussed in the meeting.
10. Review of Distribution of Loads and Signal Paths of Raichur – Sholapur SPS,
Talcher – Kolar SPS, and Kudankulam (Unit-I & II) SPS
As per decisions in the 164th
OCC meeting SPS mock testing was required to de done on
27th
February 2020. However, subsequently TANTRANSCO, vide letter dated 21st
February 2020 requested to reschedule the mock test in view of pending works.
SRPC vide letter dated 24.02.2020 (Annexure-V) had taken up the matter regarding SPS
schemes implementation and mock testing was scheduled on 04.03.2020. However, the
scheduled mock test on 4th
March 2020 could not be carried out due to the pending
works. Moreover, certain discrepancies were also noted w.r.t DTPC port confirmation
matrix provided by PGCIL as compared with the deliberations in the 77th
PCSC meeting
and the wiring diagrams provided by states. The status of completion of works may be
deliberated in the meeting.
11. Review of Distribution of Tripping of Kudankulam Unit#1 - Non-extension of SPS
trip signal to Karnataka and Andhra Pradesh
SPS for tripping of Kudankulam U#1 had operated on 7th
February at 18:00 Hr. and on
30th
April at 12:35 Hrs. However, the trip signal was not received at Karnataka on both
the occasions. Trip signal was not received at Andhra Pradesh during SPS operation on
30th
April 2020 and hence there was no load relief. As confirmed by PGCIL the SPS trip
signal was generated at Kolar end. Non-receipt of trip signal at Karnataka and Andhra
Pradesh shall be discussed in meeting.
12. Status of Implementation of Line Differential Protection
The following updates were furnished during 89th
PCSC Meeting of SRPC held on 13-02-2020
at SRPC, Bangalore:
NTPC had informed that advance payment of Rs. 30 lakh had been released for retrofitting
of distance relays at Simhadri with Line differential relays.
PGCIL (SR-1) had intimated that work would be started soon and expected to be completed
by March 2020. They also requested NTPC to expedite release of remaining payment.
Status of LDP shall be discussed in the meeting.
PGCIL (SR-1) is requested to furnish regarding status of implementation of Line
Differential Protection at Simhadri complex.
-Status Update
Agenda for the 90th
Meeting of PCSC scheduled to be held on 27
th May, 2020 (through VC/Online) Page 6
13. Other Protection Issues, if any, with the permission of the Chair
14. Sending Agenda items for the PCSC meetings
As per the Guidelines of CEA/MOP, it has been decided to conduct the PCSC meetings on monthly basis. It is requested that Agenda Items for the PCSC meetings, if any, may please be sent latest by 5th working day of the month to SRPC Secretariat to compile and circulate the same so as to have fruitful discussions in the PCSC meetings.
15. Date of next PCSC meeting
The date of 91st meeting of PCSC will be decided in due course.
*****
Grid Occurrences to be discussed in the 90thMeeting of PCSC scheduled to be held on 27th May 2020 1/10
Grid Occurrences - 90
For all tripping events, Constituents are requested to kindly furnish the detailed analysis of the events along with SLD or equivalent pictorial representation clearly showing (i) Location of the fault, and (ii) Bus-bar arrangement/ Configuration of feeders and other connected equipment with proper CB positions (OPEN/ CLOSE) at the time of occurrence of the faultalong with records of Event loggers, Disturbance recorders. The constituents are also requested to submit presentation of the analysis which may be required to be presented by the constituents in the event of meeting being conducted through VC.
I. Details of Grid Disturbances:
Sl.
No.
Details of Event Date &Time Reason Remarks Category
1
Complete loss of
supply at 220kV
EDC, 220kV
NIMHANSand
220kV HAL
stations of KPTCL
29-01-2020
at 16:35 Hr.
Triggering incident was
lightning arrestor flashover in
220kV Hoody - HAL Line-1.
Subsequently 220kV Hoody -
HAL Line-2 tripped on
overloading. On tripping of
both source feeders there was
complete loss of supply at
220kV HAL, 220kV EDC and
220kV NIMHANS stations.
400 MW GD-1
2
Complete outage of
220kV EPIP and
ITPL stations of
KPTCL
20-02-2020
at 00:30Hr.
Triggering incident was
tripping of 220kV ITPL -
Hoody line on Y-phase cable
termination fault. Tripping of
incoming feeder resulted in
complete loss of supply at
220kV EPIP and 220kV ITPL
stations.
Load Loss:
125 MW GD-1
3 Partial Blackout in
Karnataka and
North Kerala
01-03-2020
at 13:57 Hr.
400kV Mysore - Nelamangala
D/C was under planned
shutdown in the antecedent.
Triggering incident was BN
fault in 400kV Neelamangala
Hassan line. Since A/r was not
in auto mode due to insulator
replacement works, line tripped
on operation of Zone-1 distance
protection at both the ends.
Subsequently, 400kV
Talaguppa - Hassan line tripped
only at Talaguppa end on
operation of OC protection.
400kV Nelamangala -
Talaguppa tripped on Zone-1
distance protection at both the
ends due to RN fault. A/r was
not in auto mode due to
insulator replacement works.
This resulted in complete loss
Load Loss:
2380 MW
& Gen loss:
1754 MW
GD-1
Grid Occurrences to be discussed in the 90thMeeting of PCSC scheduled to be held on 27th May 2020 2/10
of supply at 400kV stations viz.
UPCL, Talaguppa, Hassan,
Mysore, Kozhikode and 37 nos.
220kV stations in Karnataka
and 6 nos. 220kV stations in
Kerala.
4 Complete outage of
220kV Edappon
station of KSEB
03-03-2020
at 07:43 Hr.
Triggering incident was failure
of 220kV B-phase CT of Bus
coupler. This led to operation
of bus bar protection resulting
in tripping of all connected
elements.
Load Loss:
67 MW GD-1
5
Complete Outage of
230kV
Checkanurani SS of
TANTRANSCO
12-03-2020
at 01:20 Hr.
Triggering incident was failure
of Y phase CT of Bus Coupler
at 230kV Checkanurani SS.
Bus-1 and Bus-2 Busbar
Protection operated resulting in
the tripping of all connected
elements. However, ICT#3 was
not tripped. Since the failed CT
was near Bus-1 side, due to
non-tripping of ICT#3 which
was connected to Bus-2, there
was no fault feed after the
isolation of Bus-1.
Subsequently, ICT#3 was hand
tripped.
------ GD-1
6
Complete outage of
220kV Kolar,
220kV Malur,
220kV Sarjapur and
220kV VTP SS of
KPTCL
14-03-2020
at 16:30 Hr.
During antecedent conditions,
220kV Kolar KA, 220kV
Malur, 220kV Sarjapur and
220kV Vikas Tech Park (VTP)
are radially fed from 220kV
Kolar PG SS. Triggering
incident was tripping of 220kV
Kolar PG- Kolar KA line-1 at
Kolar KA end on pole
discrepancy during testing of
newly commissioned SPS
scheme. After the tripping of
220kV Kolar PG-Kolar KA-1,
220kV Kolar PG-Kolar KA-2
got over loaded and tripped at
Kolar PG end.This resulted in
complete loss of supply at
220kV Kolar KA, 220kV
Malur, 220kV Sarjapur and
220kV Vikas Tech Park (VTP)
SS.
380 MW GD-1
6
Complete outage of
220kV Kolar,
220kVMalur,
220kV Sarjapur and
220kV VTP SS of
KPTCL
09-05-2020
at 22:41Hr
During antecedent conditions,
220kV Kolar(Kar), 220kV
Malur, 220kV Sarjapur and
220kV VikasTech Park (VTP)
SS are radially fed from 220kV
Kolar PG SS. Triggering
incident was YB fault in220kV
Kolar PG- Kolar(Kar) line-1.
Load Loss:
360 MW GD-1
Grid Occurrences to be discussed in the 90thMeeting of PCSC scheduled to be held on 27th May 2020 3/10
After tripping of 220kV Kolar
PG-Kolar(Kar) line-1, 220kV
Kolar PG-Kolar(Kar) line-2 got
overloaded and tripped at
Kolar(Kar) end due to
operation of non-directional OC
protection. Due to tripping of
220kV Kolar(PG)-Kolar(Kar)
line-1 and 2, there was
complete loss of supply
at220kV Kolar(Kar), 220kV
Malur, 220kV Sarjapur and
220kV Vikas Tech Park (VTP)
SS.
Note: It may be noted that the
event is repeated for the third
time since January 2020. Also,
SPS is put in service on 07-02-
2020 in the 220kV Kolar (PG)–
Kolar(Kar) linesto avoid
cascaded tripping of the lines
bytripping 66kV loads at Malur
and Kolar SS. However, during
the above event the SPS did not
operate.
II. Details of Grid Incidents:
Sl.
No. Details of Event Date &Time Reason Category
1 Tripping of Bus-2 at
400kV Raichur
10-02-2020 at
03:31Hr.
Bus-2 at 400kV Raichur tripped on
operation of bus bar protection due
to heavy surface conduction at
switchyard. 400kV Raichur-
Mahbubnagar, 400kV Raichur -
BTPS and 400kV Raichur -
Munirabad lines tripped during the
event.
GI-2
2
Complete outage at
400kV side of
400/220kV Guttur
station of KPTCL
17-03-2020 at
20:00 Hr.
All elements at 400kV side of
400/220kV Guttur station tripped
on operation of LBB protection of
400kV Kaiga - Guttur line-2. As
reported P437 relay maloperated
which led to the operation of LBB
resulting in tripping of all
connected 400kV elements.
GI-2
3
Tripping of 220kV
Bus-2 at 220kV
Vizag switching
station (VSS) of
APTRANSCO
22-03-2020 at
15:45 Hr.
Triggering incident was failure of
B-phase Lightning Arrester on
220kV VSS - Kakinada line. This
resulted in operation of Bus bar
protection of bus-2 at 220kV VSS.
400/220kV, 315 MYA ICT-1 and
ICT-2 also tripped during the
incident.
GI-1
Grid Occurrences to be discussed in the 90thMeeting of PCSC scheduled to be held on 27th May 2020 4/10
4
Multiple Tripping in
230kV Kadaperi SS
of TANTRANSCO
29-03-2020 at
04:04 Hr.
Triggering incident was failure of
B ph CT of 230kV Alandur -
Kadaperi line and R ph CT of
230kV Sriperumpudur -Kadaperi
line-2 at 230kV Kadaperi end. This
resulted in bus fault at 230kV
Kadaperi SS and Bus bar
protection operated resulting in the
tripping of all the elements
connected at 230kV Kadaperi SS
since 230kV Kadaperi SS has
single bus configuration. There
was no interruption at 110kV level.
GI-1
5
Tripping of
400kV/230kV
NTPL ICT-1
12-01-2020 at
16:45 Hr.
As per the report submitted, ICT#1
at NTPL got tripped on operation
of SF6 Gas Pressure Low Trip.
GI-2
6
Tripping of 400KV
Vemagiri -
Sattenapally
14-01-2020 at
14:29 Hr.
Line tripped on operation of LBB
protection at Vemagiri end and DT
was received at Sattenapalli end.
There was no fault during the
event.
GI-2
7
Tripping of 400kV
Bus-2 at 400kV
Salem(PG) station
23-01-2020 at
11:13Hr.
Bus bar protection of 400kV Bus-2
maloperated at Salem (PG) station.
This resulted in tripping of 400kV
Hosur - Salem ckt-2.
GI-2
8 Multiple trippings at
400kV Sundilla
23-01-2020 at
22:10 Hr.
Triggering incident is R-N fault in
400kv Nirmal- Sundilla feeder.
Zone 1 pick up at Sundilla end and
A/R is not operated. Due to this
fault, there is a reverse zone 4
pickup observed in Singareni-
Sundilla 1,2 at Sundilla end.
Instantaneous zone 4 operation for
both circuits of 400kv Sundilla-
Singareni at Sundilla end needs
review.
GI-2
9
Tripping of 400/220
kV ICT-2 AT
Mysore
25-01-2020 at
03:23 Hr.
ICT#2 at Mysore got tripped on
mal-operation of PRD protection GI-2
10
Tripping of 400/220
kV ICT-4 AT
Gajwel
25-01-2020 at
05:13 Hr.
ICT#4 at Gajwel got tripped on
spurious operation of 86B and the
same needs review. There was no
fault during the event.
GI-2
11
Tripping of 400/
110kV Kamuthi
ICT 3 & 4
27-01-2020 at
14:44 Hr.
Triggering incident was fault in
110kV bus 2 due to melting of
incoming B Phase female isolator
of ICT 4 connected to Bus 2. Bus
bar operated in 110 KV Bus 2 and
this lead to tripping of ICT 3 and
ICT 4. It was reported and further
verified from SCADA Data that
there was 200MW loss of Solar
generation.
GI-1
Grid Occurrences to be discussed in the 90thMeeting of PCSC scheduled to be held on 27th May 2020 5/10
12
Multiple Tripping in
220kV Vizag
Switching Station of
APTRANSCO
31-01-2020 at
14:14 Hr.
During tower erection works at
Loc 460-471, substation Earth wire
got pulled and fell on Bus 2
inadvertently at 220kV VSS. This
resulted in Bus fault and hence
220kV Bus-2 Bus Bar Protection
(BPP) operated resulting in the
tripping of all elements connected
to Bus-2 of 220kV VSS.
400/220kV ICT-2 at Gajuwaka
also got tripped during the event.
From PMU plots, delayed fault
clearance of 400ms was observed
and the same needs review.
GI-1
13
Tripping of
400/220kV ICT-4 at
Uravakonda
10-02-2020 at
10:14 Hr.
ICT#4 at Uravakonda got tripped
on suspected maloperation of PRV
protection and the same needs
review.
GI-2
14 Tripping of 400/220
kV ICT-2 at Gajwel
11-02-2020 at
07:13Hr.
ICT#2 at Gajwel got tripped on
maloperation of Buchholz relay
and the same needs review.
GI-2
15 Tripping of 400/220
kV ICT-2 at Trichur
13-02-2020 at
17:40 Hr.
LV side of ICT#2 at Trichur got
tripped during charging of
downstream 220kV/132kV
200MVA transformer and the same
needs review.
GI-2
16
Tripping of 400kV
Ramagundam -
Malkaram
07-03-2020 at
04:38 Hr.
Triggering incident was Y N fault
in the line. At Ramagundam end,
fault was sensed in Zone-1, A/r
operated and line tripped due to
persistent fault. As per the report
submitted at Malkaram end, it was
mentioned that line was in service;
the same needs review.
As per the report submitted by
Ramagundam it was mentioned
that, analog module of relay
maloperates intermittently and the
same needs review.
GI-2
17
Tripping of 400kV
Guttur –Hiriyur
Line-2
15-03-2020 at
18:03Hr.
Line tripped on operation of OV St-
1 protection operation at Hiriyur
end and was holding at Guttur end.
From DR of Hiriyur end, voltages
observed are: Vr-251kV, Vy-
248kV and Vb-248kV. Non
tripping of line at Guttur end needs
review.
GI-2
18
Tripping of
400/220kV
Julurpadu ICT-1
16-03-2020 at
10:40Hr.
ICT at Julurpadu got tripped on
operation of gas pressure lockout.
Non operation of Alarm needs
review.
GI-2
19
Tripping of 400kV
Dichipally – Nirmal
line-2
24-03-2020 at
13:11 Hr.
Line tripped on operation of OVR
stage-1 protection at Dichipally end
and DT received at Nirmal end.
From Dichipally end DR voltages
GI-2
Grid Occurrences to be discussed in the 90thMeeting of PCSC scheduled to be held on 27th May 2020 6/10
recorded are Vr-254.8kV, Vy-
234.7kV & Vb-226.3 kV.
Difference of around 20kV in R
and Y phase voltages was observed.
20 Tripping of 220kV
Kochi Kalamaserry
line-2
29-Dec-2019
at 00:06:00 Hr.
Triggering incident was failure of
PT of 110kV Kalamassery-
Carborandum line and CT failure
of 110kV Kalamassery-
Perumbavoor line at Kalamassery
s/s end. 220kV Kochi -
Kalamaserry line-2 tripped only at
Kochi end on Zone 4 reverse
operation. This needs review.
GI-1
21 Tripping of 400kV
Vallur – NCTPS
line-1
19-Mar-2020
at 12:05 Hr.
Shutdown for 400kV Vallur-
NCTPS line-1 was planned from
09 hr. -1700 hr. on 19.03.2020.
While closing NCTPS line 1 Earth
switch at NTECL end, heavy
voltage dip was experienced and
all the three running units of Vallur
tripped on Low Forward Power
Protection at 12:05 hr. Earth switch
of the line was closed at Vallur end
without opening of remote end
breaker, which resulted in three
phase to ground fault in 400kV
Vallur NCTPS line-1 at Vallur end. Gen Loss: 1893 MW
GI-2
III. Details of Trippings due to Failure or Non-operation of Auto-Reclose:
Sl.
No. Element Date & Time Reason
1 Tripping of 400kv
Kochi-Tirunelveli
13-01-2020 at
23:34 Hr.
Triggering incident is B phase to ground fault
in 400kv Kochi - Tirunelveli feeder. At both
the ends, Forward distance Zone 1 protection
operated.At Kochi end, A/R did not attempt,
the same needs review.AtTirunelveli end, A/r
operated and line tripped due to persistent fault.
2
Tripping of 400KV
Vemagiri (AP) -
Simhadri-II
14-01-2020 at
14:29 Hr.
Triggering incident was R-N fault in the line.
As per the report submitted at Vemagiri end, it
was mentioned that A/r operated and line
tripped due to persistent fault. But from DR, it
was observed that immediately after the
opening of R pole, Y and B pole also got
opened. As per the report submitted at
Simhadri end, it was mentioned that A/r not
operated due to receipt of DT from Vemagiri
end. Non operation of A/r and sending of DT at
Vemagiri end needs review.
3
Tripping of 400kV
Hinduja - KV Kota
Line-2
20-01-2020 at
01:35 Hr.
Triggering incident was RN fault in the line.
A/r not operated at KV Kota end due to carrier
fail. At Hinduja end, A/r operated and line
tripped due to persistent fault. Non operation of
A/r at KV Kota end needs review.
Grid Occurrences to be discussed in the 90thMeeting of PCSC scheduled to be held on 27th May 2020 7/10
02-02-2020 at
11:36 Hr.
Triggering incident was BN fault in the line. At
Hinduja end auto reclose attempted and
successful but the line tripped on SOTF. At KV
Kota end, auto reclose did not operate and
tripped on Zone-2 distance protection.
4 Tripping of 400kV
Vemagiri_PG -
Vemagiri_AP line
14-02-2020 at
15:32 Hr.
Triggering incident was BN fault in the line. At
Vemagiri_AP end line tripped on Zone-1
distance protection. Auto reclose operated at
Vemagiri_AP end and locked out due to
persistent fault. At Vemagiri_PG end Zone-2
carrier aided trip observed from DR. Auto
reclose did not operate at Vemagiri_PG end,
the same needs review.
5 Tripping of 400kv
Kurnool- Srisailam
feeder.
15-02-2020 at
13:18 Hr.
Triggering incident was B N fault in the line.
Non operation of A/R at both the ends needs
review.
6 Tripping of 400kV
NNTPP- Pondy line-1 17-02-2020 at
13:38 Hr.
Triggering incident was B phase to Earth fault
in the line. Fault was sensed in Zone-1 at both
the ends. At Pondy end, A/r operated
successfully and line was holding. At NNTPP
end, A/r not operated.
7 Tripping of 400kV
Kurnool AP - Gooty
line
18-02-2020 at
17:08 Hr.
Triggering incident was Y N fault in the line.
At Gooty end, A/r operated successfully and
line was holding. At Kurnool AP end, Y pole
breaker opened after 100ms and subsequently
R and B pole breakers also opened after 300ms
(after opening of Y pole). Non operation of A/r
at Kurnool AP end needs review.
8 Tripping of 400kV
Narnoor -Srisailam
Left Bank
06-03-2020 at
18:00 Hr.
Triggering incident was Y N fault in the line.
At Srisailam end, A/r not operated and line
tripped on operation of Zone-1 distance
protection. At Narnoor, from DR, opening of Y
phase pole was observed and from EL, P/d
operation was observed. Non operation of A/r
at both the ends review.
9 Tripping of 400kV
Khammam- Asupaka
line
16-03-2020 at
11:31Hr.
Triggering incident wasB N fault in the line. At
Khammam end, A/r operated successfully and
line was holding. At Asupaka end, line tripped
on operation of Zone-1 distance protection and
A/r not operated. Non operation of A/r at
Asupaka end needs review.
18-03-2020 at
13:11Hr.
Triggering incident was B N fault in the line.
At Khammam end, A/r operated successfully
and line was holding. At Asupaka end, line
tripped on operation of Zone-1 distance
protection and A/r not operated. Non operation
of A/r at Asupaka end needs review.
10 Tipping of 400 kV
Guttur - Hiriyur - 2 17-03-2020 at
13:06Hr.
Triggering incident was B N fault in the line.
At Hiriyur end, A/r operation was successful
and line was holding. At Guttur end, A/r not
operated.
11 Tripping of 220kV
Udumalpet – Idukki
Line-2
18-03-2020 at
06:52Hr.
Triggering incident was fault in Y phase of
220kv Udumalpet-Idukki feeder. A/R operated
at Idukki end and A/R did not operate at
Udumalpet end; the same needs review.
Grid Occurrences to be discussed in the 90thMeeting of PCSC scheduled to be held on 27th May 2020 8/10
12 Tripping of 220kV
Udumalpet - Idukki
line-1
23-03-2020 at
07:37Hr.
Triggering incident was Y N fault in the line.
At Udumalpet end, fault was sensed in Zone-1,
A/r operated and line tripped due to persistent
fault. At Idukki end, Zone-2 distance protection
operated. Failure of carrier aided protection
and non-operation of A/r at Idukki end need
review.
13 Tripping of 400kV
Raichur- Munirabad
line
28-03-2020 at
07:11 Hr.
Triggering incident was R N fault in the line.
A/r operated at both the ends and line tripped
due to occurrence of subsequent fault during
A/r reclaim time. As per the report submitted, it
was mentioned that tie didnot attempt A/r at
Raichur end and the same needs review.
14 Tripping of 230kV
Theni-Mooziyar
06-11-2019 at
11:11:00 Hr.
Triggering incident was B-phase to Earth fault
in the line. At Theni end, fault was sensed in
Zone-1, A/r operated and line tripped due to
persistent fault. At Sabarigiri end, A/r not
operated. Non operation of A/r at Sabarigiri
end needs review.
15
Tripping of 400kV
Hinduja KV Kota
line-1
06-11-2019 at
11:33:00 Hr.
Triggering incident was R phase to Earth fault
in the line. Fault was sensed in Zone-1 at both
the ends. A/r operated successfully at HNPCL
end and line was holding. At KV Kota end, A/r
not operated and the same needs review.
16 Tripping of 220 kV
Kayamkulam-
Punnapura line-2
24-12-2019 at
05:25:00 Hr.
Triggering incident was B phase to Earth fault
in the line. At Kayamkulam end, fault was
sensed in Zone-1, B-pole opened but didn't
reclose. At Punnapura end, Zone-2 carrier
aided protection operated and A/r operation
was successful. Non operation of A/r at
Kayamkulam end needs review.
17 Tripping of 220kV
Udumalpet-Idukki
line-1
03-01-2020 at
06:30:00 Hr.
Triggering incident was Y N fault in the line.
At Udumalpet end, fault was sensed in Zone-1,
A/r operated and line tripped due to persistent
fault. At Idukki end, Zone-2 distance protection
operated. Failure of carrier aided protection
and non-operation of A/r at Idukki end need
review.
IV. Details of Trippings due to PLCC mal-operation:
Sl.No Element Date &
Time
Reason
1 Tripping of 400kV Guttur –
NarendraLine-2 16-01-2020
at 11:03 Hr. Line tripped only at Guttur end on DT Receipt due to
suspected maloperation of PLCC.
2
Tripping of 400 kV Kolar -
Hoody 1
17-02-2020
at 23:59 Hr.
Line tripped on operation of OV St-1 protection at
Kolar end and DT was sent to Hoody end. But line
didnot trip at Hoody end. Non-tripping of line at Hoody end on DT received
needs review.
3 Tripping of 400kV Neyveli 2
(Exp) - Pugalur line 30-03-2020
at 15:10Hr.
Triggering incident was Y-phase to ground fault in the
line. Line tripped on Zone-1 distance protection.Auto
reclose attempted but locked out due to persistent
fault. At Pugalur end, DT was received resulting in
3phase trip. DT sent from Neyveli end needs review.
Grid Occurrences to be discussed in the 90thMeeting of PCSC scheduled to be held on 27th May 2020 9/10
V. Frequent tripping of 220kV KTPS-Lower Sileru line-1 and 220kV KTPS V- Lower
Sileru line-2 during February 2020 to April 2020.
S.NO. ELEMENT NAME TRIPPING
DATE
TRIPPING
TIME REMARKS
1 220kV KTPS V- Lower Sileru-2 16-Feb-20 11:54 BN fault
2 220kV KTPS V- Lower Sileru-2 15-Feb-20 13:29 BN fault
3 220kV KTPS V- Lower Sileru-2 10-Feb-20 11:34 BN fault
4 220kV KTPS V- Lower Sileru-2 08-Feb-20 12:35 SLG fault
5 220kV KTPS - Lower Sileru-1 29-Mar-20 12:22 BN fault
6 220kV KTPS V- Lower Sileru-2 27-Mar-20 12:05 RN fault
7 220kV KTPS V- Lower Sileru-2 22-Mar-20 11:16 BN fault
8 220kV KTPS - Lower Sileru-1 22-Mar-20 10:15 BN fault
9 220kV KTPS - Lower Sileru-1 18-Mar-20 12:25 BN fault
10 220kV KTPS - Lower Sileru-1 15-Mar-20 12:04 RN fault
11 220kV KTPS V- Lower Sileru-2 11-Mar-20 14:05 BN fault
12 220kV KTPS - Lower Sileru-1 07-Mar-20 13:25 SLG fault
13 220kV KTPS V- Lower Sileru-2 05-Mar-20 12:00 SLG fault
14 220kV KTPS - Lower Sileru-1 29-Apr-20 12:43 BN fault
15 220kV KTPS V- Lower Sileru-2 27-Apr-20 12:38 3 phase fault
16 220kV KTPS V- Lower Sileru-2 25-Apr-20 16:55 RB fault
17 220kV KTPS - Lower Sileru-1 12-Apr-20 15:23 RN fault
18 220kV KTPS V- Lower Sileru-2 11-Apr-20 12:19 SLG fault
19 220kV KTPS - Lower Sileru-1 02-Apr-20 12:17 BN fault
VI. Frequent tripping of 220kV KTPS Nunna line during Feb 2020 to April 2020.
S.NO. ELEMENT NAME TRIPPING
DATE
TRIPPING
TIME REMARKS
1 220kV KTPS-NUNNA 05-Mar-20 13:44 BN fault
2 220kV KTPS-NUNNA 25-Apr-20 17:20 BN fault
3 220kV KTPS-NUNNA 25-Apr-20 12:05 RN fault
4 220kV KTPS-NUNNA 23-Apr-20 13:37 BN fault
5 220kV KTPS-NUNNA 18-Apr-20 15:50 RN fault
6 220kV KTPS-NUNNA 11-Apr-20 15:03 RN fault
7 220kV KTPS-NUNNA 10-Apr-20 08:28 RN fault
8 220kV KTPS-NUNNA 08-Apr-20 16:53 RN fault
9 220kV KTPS-NUNNA 06-Apr-20 13:39 SLG fault
VII. HVDC Pole Trippings
Sl.No ELEMENT NAME TRIPPING
DATE/ TIME
REVIVAL
DATE/ TIME RMEARKS
1 HVDC 500KV BHADRAVATHI Pole 2
27-01-2020/09:34 27-01-2020/14:40
THYRISTOR FAILURE
2 HVDC 500KV KOLAR_DC Pole 2 17-02-2020/23:59
17-02-2020/00:36
DUE TO HVDC LINE FAULT
3 HVDC 500KV KOLAR_DC Pole 2 17-02-2020/17:38
17-02-2020/18:33
DUE TO HVDC LINE FAULT
4 HVDC 500KV GAZUWAKA Pole 1 03-03-2020/11:39
03-03-2020/17:09
Thyristor redundancy failure
Grid Occurrences to be discussed in the 90thMeeting of PCSC scheduled to be held on 27th May 2020 10/10
5 HVDC 500KV GAZUWAKA Pole 1 04-03-2020/12:28
04-03-2020/04:01
Thyristor side problem
6 HVDC 500KV BHADRAVATHI Pole 2
18-03-2020/11:48 18-03-2020/12:37
Failure of PLC 4901 processors
7 HVDC 500KV BHADRAVATHI Pole 2
18-03-2020/11:48 18-03-2020/12:37
Failure of PLC 4901 processors
8 HVDC 500KV BHADRAVATHI Pole 1
18-03-2020/11:48 18-03-2020/12:46
Failure of PLC 4901 processors
9 HVDC 500KV GAZUWAKA Pole 2 21-03-2020/12:15
21-03-2020/14:25
AUXILIARY POWER FAILURE
VIII. Gazuwaka Oscillations
2X 500 MW HVDC Gazuwaka Back to Back is an important inter-regional link for transfer of
power between Southern and Eastern Regions. During January and February 2020, fluctuations
in AC side voltage have been observed at Gazuwaka. A total of 24 number of incidents were
observed from PMU signals (list given below). These fluctuations continued for a significant
duration of time and occurred repeatedly on some days. Such fluctuations in power system
parameters is a serious issue and is a threat to reliable power system operation.
List of incidents involving fluctuations in AC side voltage at HVDC Gazuwaka station is as
below:
***
Meeting
No /
Index
Details of Event Date & Time Reason PCSC Recommendations Utility responsible for Implementation Status of Implementation of PCSC Recommendations Remarks Latest Status
(To be filled up by the Constituent)
Status of Pending Implementation of PCSC Recommendations as on 08.05.2020 (up to 90th Meeting)
KPTCL Mail dated 27-05-2015:
1. KPTCL has taken action to provide bus bar protection to 220kV buses. ---
Pending
2. Over current relay Settings of ICTs to be reviewed by PGCIL.
--- Pending
3. --- Pending
KPTCL Mail dated 29-07-2015:
1. Initial Tendering stage. --- Pending
2. --- Pending
3. --- Pending
KPTCL Mail dated on 23-01-2016:
1. Detailed estimate prepared for taking up the work. CEE, Transmission Zone,
Gulbarga will take up necessary procurement and further execution. --- Pending
2. --- Pending with PGCIL (SR-I).
3. --- Pending
PGCIL (SR-I) Mail dated 14.07.2016:
2. Relay settings of all the stations in SRTS-1 were derived as per Ramakrishna
Commettee recomendations and implemented" --- Completed.
KPTCL Mail dated 16.12.2017:
1) & 3). DPR is approved. Tender is to be called by CEE,TZ Kalaburgi ---
Pending
Review Meeting dated 19.12.2017:
1. KPTCL informed that Tenders for providing BBP would be called in Jan-Feb,
2018; Supply of the same is targeted by September, 2018; Erection &
Commissioning is targeted by January, 2019
--- Pending
3. PGCIL (SR-I) informed that time-synchronization of 220 kV side is in place. ---
Completed.
KPTCL mail dated 19.12.2018:
1. DPR preapared for the work of providing Bus Bar Protection to 220kV buses
at Guddadahally is approved. Tender is to be invited by CEE,TZ .
Review Meeting dated 20.12.2018:
1. Tender would be floated in January 2019. Works would be completed in 6
months after awarding PO.
Review Meeting dated 27.06.2019:
1. KPTCL informed that the work is expected to be completed by December
2019.
16-07-201434/I/6 400/220 kV ICT-1 & 2 at
Munirabad
As reported directional over current relay of ICT’s
operated due to snapping of line jumper in
220kV Lingapur line.
1. Bus bar protection shall be provided by asset owner ( i.e KPTCL).
2. Settings for main distance protection & Overcurrent protection shall be
examined and reviewed.
3. Time synchronization of the Substation shall be ensured.
KPTCL/
PGCIL (SR-I)
Pending
(with KPTCL)
Multi-Utilities
Annexure-II
Page 1 of 39
NTPC mail dated 07.12.2017:
1. High set DEFR on 220 KV lines is disabled ----Completed
2. ---- Pending
Review Meeting dated 19.12.2017:
TSTRANSCO informed that the works are under progress, and are targeted to be
completed in 3 months time.
TSTRANSCO MAIL DATED 20.01.2018:
Line Differential Protection will be provided within 3 months i.e., by end of
March, 2018.
TSTRANSCO MAIL DATED 20.04.2018:
Line Differential Protection relays are under procurement and will be provided by
end of May, 2018.
TSTRANSCO MAIL DATED 17.05.2018:
Line Differential relays will be supplied to site by manufacturer by end of May,
2018 and erection will be completed by end of June, 2018.
TSTRANSCO MAIL DATED 12.10.2018:
Inspection of the relays is completed and the relays are received at stores. Relays TSTRANSCO MAIL DATED 22.01.2019:
Relays will be commissioned by end of February, 2019.
TSTRANSCO mail dated 22.06.2019:
2. Relay erection work is under progress and will be completed by end of July,
2019.
TSTRANSCO mail dated 30.10.2019:
LDP relays are available but commissioned was not done bue to non availability
of carrier communication cable and will be done in 2 months i.e., by December,
2019.
TSTRANSCO mail dated 18.01.2020:
LDP relays are available at site. carrier communication cable laying between the
LDPs is procured and laying work is under progress and will be completed by end
of January,2020.
Commissioning of LDPs will be done by 2nd week of February, 2020.
11-06-2017
at 19:46hrs
NTPC-Ramagundam/ TSTRANSCO PendingTriggering incident was failure of 220 kV
B-phase LA in ICT-3 LV extension feeder (220KV
line-2) at Malayalapalli substation
1. NTPC to disable high-set of DEFR on the 220 kV lines emanating from their
Ramagundam STPS.
2. NTPC/ TSTRANSCO to provide Line Differential Protection (with or without
pilot) on 220 kV Ramagundam – Malayalapalli lines – 1 & 2 & 3.
66/ II/
10
Tripping of 400/ 220 kV
ICT’s – 3 & 4 at
Ramagundam STPS
Annexure-II
Page 2 of 39
Review Meeting dated 19.12.2017:
PGCIL (SR-I) informed that they are waiting for written confirmation from TPCIL
to complete procurement of LDP relays. To this, PCSC forum asked TPCIL to
submit written confirmation to PGCIL (SR-I) by 29.12.2017. PGCIL (SR-I)
assured that with receipt of above confirmation from TPCIL by Dec, 2017, they
would be able to complete the work by February, 2018.
APTRANSCO informed that they would be able to implement LDP from their &
APGENCO side by April, 2018.
In this regard, PCSC forum made it clear that the recommendation is about
providing LDP as both Main-I & Main-II relays on all stated lines in Nellore
Complex, ans asked all stakeholders to ensure & comply with the same.
PGCIL (SR-I) mail dated 20.06.2018:
2. PGCI(SR1) procuring LDP relays for retrofitting of Main-1&2 distance relays.
Tenders are invited from bidders & tender floated. Technical bid opening in this
week.
PGCIL (SR-I) mail dated 10.12.2018:
2. PO placed on M/s GE & TD India Ltd on 24.09.2018. Supply of relays will be
completed by Jan'2019 and commissioning by Mar'19.
Review Meeting on 20.12.2018 & 27.06.2019:PGCIL (Sr-1) mail dated 31.10.2019:
Retrofitting works completed in NPS-NCC-1&2, NPS-Nellore-1&2 Main-1 relay,
NPS-TPCIL-1&2 lines completed.
Confirmation for retrofitting of Main-2 relay in NPS-Nellore-1&2 lines to be
received from SRPC. Presently both lines are bypassed at Nellore Bus-1&2 and
connected to Tiruvalam SS by closing Tie CBs at Nellore end. Now lines are long
lines as 400kV NPS-Tiruvalam-1&2. The same was discussed in 84th PCSC
meeting. SRPC has to give concurrence.
PGCIL -SR-1 maild ated 17.12.2019:
Retrofitting works completed in NPS-NCC-1&2, NPS-TPCIL-1&2 lines for both
Main-1&2 relays. Issue to be closed
APTRANSCO maild ated 30.01.2018:
1. Pending...
2.A/R scheme on 400kV Kurnool (PGCIL) feeder-2 will be checked after getting
LC.
APTRANSCO maild ated 24.04.2018 & 24.05.2018 & 26.06.2018:
1. Pending...
APTRANSCO Mail Dated 18.12.2018:
1) Bays and lines pertains to PGCIL .
2) ---Completed.
PGCIL (SR-I) mail dated 20.12.2018:
1) PO placed on M/s GE & TD India Ltd on 24.09.2018. Supply of relays will be
completed by Jan'2019.
APTRANSCO MAIL DATED 22.01.2019:
Pending [with PGCIL (SR-I)]
PGCIL (SR-I) mail dated 07.06.2019:
PGCIL(SR-1):
This issue of retrofitiing of distance relays with LDP relays in Kurnool(PG) –
Kurnool(AP) D/C lines has been discussed with our management. Our
management is seeking approval for the same. You are requested to takeup this
LDP issue in next TCC meeting.
PGCIL (SR-I) mail dated 30.10.2019:
This issue of retrofitiing of distance relays with LDP relays in Kurnool(PG) –
Kurnool(AP) D/C lines has been discussed with our management. Our
management is seeking approval for the same. You are requested to takeup this
LDP issue in next TCC meeting.
PGCIL -Sr-1 mail dated 17.12.2019:
This issue of retrofitiing of distance relays with LDP relays in Kurnool(PG) –
Kurnool(AP) D/C lines has been discussed with our management. Our
management is seeking approval for the same.
SRPC/PCSC may please allow the POWERGRID to book the expenditure in any
ongoing/upcoming projects.
PCSC on 18.12.2019:
PCSC forum decided to forward the issue to SRPC TCC meeting
TPCIL/
PGCIL (SR-I)
1. TPCIL to configure DEF protection such that it remains in blocked condition
as long as Distance Protection is active, and becomes active only when distance
protection does not pickup.
2.PGCIL (SR-I) to ensure healthiness of Carrier communication, and the set PUP
mode of carrier aided scheme operates reliably on TPCIL lines 1 & 2.
400kV TPCIL - Nellore line-1 got tripped at TPCIL
end during failure of LA of Station Transformer-2 at
TPCIL. Running Units at TPCIL got tripped due to
loss of evacuating line. 400kV TPCIL - Nellore PS
line-2 was under emergency shutdown
30-10-2017 at
21:37 hrs
Pending [With
TPCIL]
Pending [with
PGCIL (SR-I)]
APTRANSCO/
PGCIL (SR-I)
1) PGCIL (SR-I) and APTRANSCO to provide for Line Differential Protection
as both the Main protections on 400 kV Kurnool (AP) – Kurnool (PG) lines 1 &
2 lines.
2) APTRANSCO to furnish an action taken report w.r.t. resolving A/R non-
operation at Kurnool-AP end for the subject trippings and configure EL for
capturing PDR operation at their 400 kV Kurnool-AP SS.
Complete outage of 400kV
TPCIL station
69/I/2
02-10-2017 at
02:03 hrs
Tripping of 400 kV
Kurnool(PG) –
Kurnool(AP) line-2
69/III/3 Line tripped on B-ph to ground fault. A/R was
unsuccessful at both Kurnool (AP) and Kurnool
(PG) ends.
Annexure-II
Page 3 of 39
APTRANSCO maild ated 15.12.2017:
APTRANSCO would extend support and requirements if any ,for the
rectification proposed by KPTCL.
Review Meeting dated 19.12.2017:
It was noted that the original Gooty - Lingapur line got LILOed at BTPS, Alipura,
and Ragulapadu. It was also noted that Phase Discrepancy is being observed in
Ragulapadu - Alipira section only. When enquired about the same, KPTCL
informed that they would examine the issue in detail, and would inform the
action lan proposed by next PCSC-71 meeting. On this, APTRANSCO was also
asked to render all help required from their side to KPTCL.
APTRANSCO maild dated 30.01.2018:
APTransco world extend required support .
APTRANSCO maild dated 24.04.2018 & 24.05.2018 & 26.06.2018:
AP Transco would extend required support for attending, phase discrepancy issue
in ragulapadu-Alipura line by KPTCL.
APTRANSCO Mail Dated 25.07.2018:
To be attended by KPTCL as discussed in 75th PCSC meeting.
KPTCL mail dated 19.12.2018:
Phase mis match issue is to be sorted out jointly by KPTCL/ APTRANSCO/
KPCL.
Review Meeting on 20.12.2018:
PCSC forum decided that concrete action in this respect to be initiated in 2
months by KPTCL alongwith APTRANSCO.
APTRANSCO MAIL DATED 22.01.2019:
Pending [with KPTCL ]
Review Meeting on 27.06.2019:
KPTCL informed that the work is expected to be completed by August 2019.
KPTCL mail dated 12.02.2020:
Correction is to be incorporated in the primary side, procurement of required
materials under progress.
KPTCL mail dated 19.12.2018:
3). Nagzari-Bidnal PLCC link is healthy --- Completed.
1.--- Pending
2. --- Pending
Review Meeting on 20.12.2018:
1. & 3. Completed
2. Pending
KPCL mail dated 24-12-2018:
1) --- Completed
2) Proposal will be taken up for replacement of existing PZ1000 relays with new
version Numerical Line protection relays having IEC61850 shortly, after availing
necessary admnistrative approval...Pending
3) Completed
KPCL mail dated 23.01.2019:
1. Completed
2. Letter addressed to site to take up the proposal for replacement of PZ1000 line
distance relays.
APTRANSCO/ KPTCL
Tripping of 230 kV
Thiruvalam - Chittoor line
1) TANTRANSCO Mail dated 29.08.2018 & 11.09.2018:
Material supplied and work to be taken up ---Pending
2) APTRANSCO Mail dated 24.09.2018:
The static relays were replaced with Numerical relay on all 220 kV feeders at 220
kV SS chittoor.---Completed
TANTRANSCO Mail dated 11.12.2018:
Due to space constraint, the equipments could not be erected.
Review Meeting on 20.12.2018:
In view of Tiruvalam being inter-state sustation, TANTRANSCO was asked to
prvodie double-bus operation at their 230 kV Tiruvalam SS.
APTRANSCO MAIL DATED 22.01.2019:
Pending [with TANTRANSCO]
TANTRANSCO MAIL DATED 23.01.2019 & 19.03.2019:
Feasibility for providing hybrid breaker / shifting of bays will be studied & action
will be taken. Time upto Sep 2019
TANTRANSCO MAIL DATED 13.06.2019:
1. Bus segregation will be ensured by providing bus coupler bay by extending the
existing Bus.Time line 31.12.2019.
TANTRANSCO mail dated 18.07.2019 & 26.07.2019:
1. Bus segregation will be ensured by providing bus coupler bay by extending the
existing Bus.Time line 31.12.2019.
TANTRANSCO mail dated 12.02.2020:
1. Bus segregation will be ensured by providing bus coupler bay by extending the
existing Bus.Time line rquested upto 31.12.2020.
Pending [with
TANTRANSCO]
Tripping of 220 kV
Ragulapadu – Alipura line
12-10-2017 at
01:30 hrs
1) TANTRANSCO to provide double-bus operation at their 230 kV Thiruvalam
SS.
2) APTRANSCO to replace the existing static relays with suitable numerical
relays for various line protections at their 220 kV Chittoor SS.
Pending
[with KPTCL ]
Y-phase to earth fault occurred in line. At 230 kV
Tiruvalam end, breaker was under lockout leading
to operation of LBB protection.
KPTCL and APTRANSCO to sort out issues relating to incongruence in
denoting R, Y, B phases of the electric supply on their respective sides.
TANTRANSCO/ APTRANSCO13-06-2018 at
18:55hrs
Line tripped on B-Ph to earth fault. A/R was
successful at Regulapadu and breakers at Alipura
end got tripped.
69/III/7
76/II/9
1. SLDC/KPTCL to be pro-active in issuing necessary directions that help in
expeditious restoration of the tripped lines based on the prevailing conditions
and grid security.
2.KPCL to implement A/R enabled on all 220 kV lines emanating from their
220 kV Nagjheri PH, with the help of KPTCL, by December, 2018. In the event
of non-amenability of the existing PZ1000 relays in providing A/R feature,
KPCL shall take steps to retrofit them with suitable relays that support A/R.
3. KPTCL to restore PLCC carrier communication on 220 kV Nagjheri – Bidnal
line at the earliest
220kV lines connected to Nagjheri PH got tripped
due to successive transient faults. Running Units #3
and #4 at Nagjheri got tripped on over frequency
protection operation due to loss of evacuating lines
resulting in complete outage of 220 kV Nagjheri.
220 kV Nagjheri being the only source to 220kV
Ambewadi station, since 220kV Ambewadi
Narendra line 1&2 were under shutdown during
antecedent condition, tripping of Units at 220 kV
Nagjheri resulted in the loss of supply to 220 kV
Ambewadi SS.
17-09-2018 at
14:37hrs
Complete outage of 220 kV
Nagjheri PH and 220/110
kV Ambewadi Substation.
78/I/2 KPCL/ KPTCL Pending
Annexure-II
Page 4 of 39
KPCL mail dated 23.03.2019:
1). COMPLETED
2) Proposal will be taken up for replacement of existing PZ1000 relays with new
version Numerical Line protection relays having IEC61850. Prepration of
specification is under progress.
3) COMPLETED
KPCL mail dated 13.05.2019:
1) & 3) Completed
2) Budgetary offer obtained for replacement of existing PZ1000 relays with new
version Numerical Line protection relays having IEC61850. Preparation of
estimation and specification is under progress.
KPCL mail dated 25.06.2019:
1) & 3) Completed
2) Replacement of existing PZ1000 relays with new version Numerical Line
protection relays having IEC61850 is included in PSDF Phase-II DPR. Approval
of NLDC for DPR is awaited. Further, availing administrative approval for issue
of NIT for replacement of existing PZ1000 relays with new version Numerical
Line protection relays having IEC61850 and preparation of estimation and
specification is under progress.
Review Meeting on 27.06.2019:KPCL mail dated 16.07.2019:
1) & 3) Completed
2) Replacement of existing PZ1000 relays with new version Numerical Line
protection relays having IEC61850 is included in PSDF Phase-II DPR. Approval
of NLDC for DPR is awaited. However, administrative approval for issue of NIT
for replacement of existing PZ1000 relays with new version Numerical Line
protection relays having IEC61850 obtained. Preparation of technical
specification is under progress.
KPCL mail dated 30.10.2019:
2)Replacement of existing PZ1000 relays with new version Numerical Line
protection relays having IEC61850 is included in PSDF Phase-II DPR. Approval
of NLDC for DPR is awaited. NIT issued through e-portal on 16.09.2019. Pre-
bid meeting was held on 10.10.2019. Finalising of replies to pre-bid queries is in
progress.
KPCL mail dated 17.12.2019:
2) Replacement of existing PZ1000 relays with new version Numerical Line
protection relays having IEC61850 is included in PSDF Phase-II DPR. Approval
of NLDC for DPR is awaited. NIT issued through e-portal on 16.09.2019. Cover-
1 opened on 02.12.2019. Technical evaluation is in progress.
KPCL mail dated 11.02.2020:
2) Replacement of existing PZ1000 relays with new version Numerical Line
protection relays having IEC61850 is included in PSDF Phase-II DPR. Approval
of NLDC for DPR is awaited. NIT issued through e-portal on 16.09.2019. Tender
evaluation is in progress.
Review Meeting on 20.12.2018:
1. KPTCL I formed that SPS scheme finalisation shall be completed in one month
time --- Pending
KPCL mail dated 24-12-2018:
2) Time delay of operation is not changed. However, the external NCT is used for
REF protection against earlier internal NCT for REF, to avoid tripping due to
malopration --- Completed.
KPCL mail dated 23.01.2019:
1) It shall be reviewd and Implemented by KPCL in coordination with KPTCL.
2)....Completed.
KPCL mail dated 23.01.2019:
1) It shall be reviewd and Implemented by KPTCL in coordination with KPCL.
KPCL mail dated 10.05.2019 & 25.06.2019 & 30.10.2019:
1) Letter addressed to KPTCL RT dated: 25.03.2019 for review and
implementation of SPS at NPH. Reply is awaited.
Review Meeting on 27.06.2019:
1. KPTCL informed that Nagjheri SPS has to be studied in the event of
configuration changes and outcome of the same will be intimated soon .KPCL mail dated 16.07.2019 and 17.12.2019 and 11.02.2020:
1) Letter addressed to KPTCL RT dated: 25.03.2019 for review and
implementation of SPS at NPH. Reply from KPTCL is awaited.
2)Completed.
KPTCL mail dated 12.02.2020:
The logic is being reviewed by SRLDC by conducting system studies for the
changed network configuration
31-08-2018
at 11:49 hrs
1)KPTCL to examine the reasons for tripping of more than one Unit (Units – 3
& 6) on SPS operation at Nagjheri PH during subject trippings, and furnish a
report on the same along with remedial action taken to PCSC forum.
2)KPCL to employ a suitable time delay of 50 – 60 msec in operation of REF
protection for the GT of Unit-2 at their Nagjheri PH.
78/II/16 Multiple trippings at
220kV Nagjheri PH
Triggering incident was B-E fault in 220 kV
Nagjheri - Ambewadi line-1. As per the information
received, after tripping of 220 kV Naghjeri -
Ambewadi line-1, 220 kV Naghjeri Ambewadi
line#2 got overloaded. This resulted in the tripping
of Nagjheri Generating Units #3 and 6 on SPS
operation. At the same time, Unit #2 got tripped on
REF operation.
1. SLDC/KPTCL to be pro-active in issuing necessary directions that help in
expeditious restoration of the tripped lines based on the prevailing conditions
and grid security.
2.KPCL to implement A/R enabled on all 220 kV lines emanating from their
220 kV Nagjheri PH, with the help of KPTCL, by December, 2018. In the event
of non-amenability of the existing PZ1000 relays in providing A/R feature,
KPCL shall take steps to retrofit them with suitable relays that support A/R.
3. KPTCL to restore PLCC carrier communication on 220 kV Nagjheri – Bidnal
line at the earliest
220kV lines connected to Nagjheri PH got tripped
due to successive transient faults. Running Units #3
and #4 at Nagjheri got tripped on over frequency
protection operation due to loss of evacuating lines
resulting in complete outage of 220 kV Nagjheri.
220 kV Nagjheri being the only source to 220kV
Ambewadi station, since 220kV Ambewadi
Narendra line 1&2 were under shutdown during
antecedent condition, tripping of Units at 220 kV
Nagjheri resulted in the loss of supply to 220 kV
Ambewadi SS.
17-09-2018 at
14:37hrs
Complete outage of 220 kV
Nagjheri PH and 220/110
kV Ambewadi Substation.
78/I/2
KPTCL/ KPCL Pending
KPCL/ KPTCL Pending
Annexure-II
Page 5 of 39
TANTRANSCO Mail dated 11.12.2018:
1. TANTRANSCO: Estimate sanctioned for replacement of defective isolator
status feedback. Work under progress. ......Pending
2.Earth value of 110kV earthmat has been improved & 230kV side earthmat
work under progress. Lightning mask earthing renovation under
execution............Pending
3.......Pending
APTRANSCO Mail Dated 18.12.2018:
Relays settings reviewed and need to be revised due to change of line length DR
& EL's of Main-1 (P444) relay configured properly. Main-2 (D60) relay to be
configured.
Review Meeting on 20.12.2018:
1 & 2). TANTRANSCO informed that Work will be completed by March 2019.
3. APTRANSCO informed that work will be completed by February 2019.
APTRANSCO MAIL DATED 22.01.2019:
Collecting the details of adjacent feeders connected to Gummadipudi for
computing revised relay settings.
TANTRANSCO MAIL DATED 23.01.2019:APTRANSCO mail dated 15.03.2019:
3. Revised relay settings were implemented on 16/02/2019 ---Completed
TANTRANSCO MAIL DATED 19.03.2019:
New 230kV isolators have been allotted for replacement of defective isolators.
Hence time line requested upto June.2019.
TANTRANSCO MAIL DATED 13.06.2019:
1. New 230kV isolators have been allotted for replacement of defective isolators.
Hence time line requested upto Sep.2019.
Review Meeting on 27.06.2019:
1. New 230kV isolators have been allotted for replacement of defective isolators.
Hence time line requested upto Sep.2019.
2. & 3. Completed
TANTRANSCO mail dated 18.07.2019 & 26.07.2019:
1. 1New 230kV isolators have been allotted for replacement of defective
isolators. Hence time line requested upto Sep.2019
TANTRANSCO mail dated 12.02.2020:
New 230kV isolators have been allotted for replacement of defective isolators.
Hence time line requested upto March 2020.
81/IV/3 Tripping of 400 kV
Warangal - Bhoopalapalli
line-2
15-12-2018 at
20:42 hrs
Line tripped at Bhoopalapalli end only and was
holding from warangal s/s. FIR, DR and EL of
Bhoopalapally were not furnished.
For the line under consideration, the following shall be carried out by
TSGENCO in coordination with PGCIL (SR-I):
(i) End-to-end communication for DT/ permissive & other signals may be
ensured by testing at both the ends.
(ii) Healthiness of PLCC system components (hardware and software) at both
ends shall be checked and faulty components shall be repaired/ replaced.
TSGENCO/ PGCIL (SR-I) PGCIL (SR-I) mail dated 07.06.2019:
PGCIL-SR1: Presently WGL-Bhopalapalli-2 line PLCC Ch-1 is unhealthy same
was informed to TSGENCO for rectification. The Ch-1 is out of service from last
50 days onwards. Both ends PLCC belongs to TSGENCO
TSGENCO mail dated 24.06.2019:
TSGENCO is cordinating with TSTRANSCO for testing of End-to-End
communication for DT/permissive & other signals; checking of Healthiness of
PLCC system components and also for replacing of faulty components .
Review Meeting on 27.06.2019:
TSGENCO informed that PLCC has to be replaced and will be done by December
2019.
TSGENCO mail dated 10.02.2020:
PLCC panels of Warangal Bhoopalpalli line-2 are replaced with new CGL make
panels from 05.11.2019 to 07.11.2019. Hence requested to drop the point
Complied
83/I/1 Complete outage of 230kV
Veeranam substation of
TANTRANSCO
11-03-2019
at 00:55Hrs
Triggering incident was Y-phase CT blast in 230kV
Tirunelvelli (Abhishekpatty) – Veeranam Ckt-1.
230kV Trirunelvelli – Veeranam Ckt-1 and 2
tripped. Two faults were observed from the PMU
plot. During the second fault, delayed fault
clearance of 400ms was observed. As reported, other
connected feeders 230kV Veeranam – Kodikur ckt-
1&2 and 230kV Veeranam – Kayathar tripped on
Zone -2 protection.
1. TANTRANSCO is recommended to submit action plan to provide Multi-Bus
operation/ Hybrid breakers at 230kV Veeranam SS with clear timelines.
2. TANTRANSCO to revise the distance zone settings at Tiruneveli SS for
230kV Veeranam – Tirunelveli line to overcome the problem of relay overreach
and share the same with SRPC.
3. TANTRANSCO to take definite measures ensure the time synchronization of
relays at Tirunelveli end.
4. TANTRANSCO to submit equipment failure report of the failed CT to CEA.
TANTRANSCO TANTRANSCO MAIL DATED 13.06.2019:
1.Provision of bus coupler breaker is not feasible due to space constaint.
2&3. Tirunelveli end maintained by PGCIL.
4. Report will be sent.
Review meeting on 27.06.2019:
1.Provision of bus coupler breaker is not feasible due to space constaint.
2. Will be informed
3. Time synchronisation will be ensured.
4. Report will be sent.
TANTRANSCO mail dated 19.07.2019 and 12.02.2020:
1.Provision of bus coupler breaker is not feasible due to space constaint.
2&3. Tirunelveli end maintained by PGCIL.
4. Report sent to CEA. -- Completed
Pending[PGCIL-
SR-II]
Triggering incident was B-phase fault at 230kV
Gummidipoondi Substation due to which 230kV
Bus-1 Bus-bar protection operated. 230kV
Gummidipoondi Station was under single bus
operation, hence operation of Bus-bar protection
resulted in tripping of all connected elements.
05-10-2018 at
00:42 hrs
Complete outage of 230/
110 kV Gummidipoondi
Substation
79/I/2 TANTRANSCO/ APTRANSCO1) TANTRANSCO to take steps to implement multi-bus, multi-zone operation
(Double-bus operation) at their 230 kV Gummidipooindi SS by December,
22018.
2) TANTRANSCO to check if the Gummidipoondi substation is adequately
protected from lightning-strokes by providing requisite no. of lightning masts
and/ or earth-wire caging.
3) APTRANSCO was asked to verify & correct the settings employed for
distance protection at Sullurpeta and configure DR’s & EL’s of all Protection
Relays at their Supllurpet SS properly for recording only the mandated
protections & digital signals.
Pending [with
TANTRANSCO]
Annexure-II
Page 6 of 39
83/I/6 Complete outage of 220kV
Hubli substation of KPTCL
and 220kV
Nagjheri Power station of
KPCL
10-04-2019
at 18:09Hrs
Y and B-phase earth isolator switch blades of
220kV Hubli-Bidnal ckt-1, got closed due to failure
of locking mechanism during heavy wind and rain
conditionsresulting in bus fault. Bus bar protection
operated and all connected elements tripped. There
was
complete loss of supply at 220kV Hubli station since
the station was on single bus operation. At thesame
time, 220kV Nagjheri-Ambewadi ckt-1 and 220kV
Nagjheri – Bidnal tripped on overcurrent
protection. Since 220kV Nagjheri – Ambewadi ckt-2
and 220kV Nagjheri-Kodasalli ckt-1 &2 wereunder
shutdown in the antecedent due to maintenance,
running units #1,4,5 and 6 tripped due to
loss of evacuating lines. This resulted in complete
loss of supply at 220kv Nagjheri station.
1. KPTCL is recommended to revise the SPS at Nagjheri, (to accommodate a
new condition with high flow and low time delay) in consultation with SRPC
and SRLDC.
2. KPCL in coordination with KPTCL is recommended to provide at least one
main protection as carrier aided three zone distance protection on the 220kV
lines emanating from Nagjheri GS.
KPTCL/ KPCL KPCL mail dated 25.06.2019:
2) Carrier aided protection is enabled on all 220kV lines emanating from NPH
___Completed
Review Meeting on 27.06.2019:
1. KPTCL informed that Nagjheri SPS has to be studied in the event of
configuration changes and outcome of the same will be intimated soon
KPCL mail dated 16.07.2019 & 30.10.2019:
1. under progress
2. Completed
KPCL mail dated 17.12.2019 and 11.02.2020:
1) To be furnished by KPTCL
2)Completed.
KPTCL mail dated 12.02.2020:
The logic is being reviewed by SRLDC by conducting system studies for the
changed network configuration
Pending
83/II/9 Tripping of 400 kV
GUTTUR - NARENDRA -
1
10-03-2019 at
18:03hrs
Line tripped on operation of overvoltage stage-1
protection at Guttur end and DT received at
Narendra end. Voltages at Guttur end: Vr-254kV,
Vy-252kV, Vb-246kV. As per voltage grading,
400kV Guttur Narendra line-2 should trip first.
PGCIL (SR-II) to submit action plan regarding replacement of CT’s for 400Kv
Guttur Narendra line -1 at Guttur end. PGCIL (SR-II) to sort out the time sync
issues in DR and EL at Narendra end.
PGCIL (SR-II)/ KPTCL PGCIL (SR-I) mail dated 07.06.2019:
Line belongs to PGCIL(SR-2)
Review meeting on 27.06.2019:
PGCIL(SR-II) informed that R & Y ph CVT replaced on 25.05.2019. Time
syncronisation has to be attended by KPTCL.
Pending
84/I/1 Complete outage of 230kV
NCTPS Generating Station
of TANGEDCO
18-05-2019 at
04:39 hr.
Triggering incident was Y phase to Earth fault in
220 kV NCTPS Tondiarpet line-2. Due to mal-
operation of LBB protection (of Tondiarpet line-2)
at NCTPS end, all the connected elements of bus
zone-3 got tripped. Due to loss of evacuating lines,
running units at NCTPS unit#1 and 2 got tripped.
1.TANTRANSCO may take immediate measures to attend the problem in LBB
wiring that is extending trip during A/R within one month.
2. TANTRANSCO is recommended to send a detailed report regarding the A/R
status (availability /enabling)on all lines emanating from 230kV NCTPS GS and
enable A/R in all lines emanating from 230kV NCTPS GS.
3.TANGEDCO in coordination with TANTRANSCO may take definite
measures to ensure time synchronization of all relays with GPS signal at NCTPS
end and remote ends at the earliest.
4. It was also suggested that possibility of backing down of generation, in the
event of unavailability of many feeders, in particular when radial feeders only
are in service, may be looked at.
TANGEDCO/ TANTRANSCO TANTRANSCO mail dated 26.07.2019:
1 & 2.Inbuilt LBB function will be enabled in the new distance relays.
3. will be ensured.
4.230kV Kilpauk was operated radially for avoid overloading in the adjacent
feeders due to cable fault in the area.Normally all feeders are operated as grid
feeders.
TANTRANSCO mail dated 12.02.2020:
1. LBB wiring set right and operation of the same has been verified for its
healthiness. -- Completed
2. Since the CBs and the Control & Relay Panels (CRP) are very old and
commissioned during 1993. The Distance relays even though are numerical due to
ageing its display and resetting keys are faulty. Hence it is proposed to replace
the CBs & CRPs with new CBs and Protection relay panel with SAS. A.R will be
put into service after replacing the CB & CRP.
3. Time synchronisation of Protection relays is being carried out . The work is
under progress.
Pending
84/I/2 Complete outage of 230kV
NCTPS Generating Station
of TANGEDCO
19-05-2019 at
22:44 hr.
230kV lines connected to NCTPS got tripped due to
fault in lines. Running units#1,2 and 3 at 230kV
NCTPS also got tripped due to loss of evacuating
lines.
1. TANGEDCO in coordination with TANTRANSCO to take definite measures
to ensure time synchronization of all relays with GPS signal at NCTPS end and
remote ends at the earliest.
2.The PCSC noted frequent jumper cut/conductor snap instances in the area, of
late; accordingly, it was suggested to have adequate condition monitoring and
preventive maintenance measures.
3.TANTRANSCO to communicate
(i) the schedule of replacement of balance porcelain insulators with polymer
insulators in evacuation lines from NCTPS.
(ii) schedule of insulator washing
4.NCTPS /TANGEDCO to inform regarding house load operation capability of
Generators at NCTPS.
TANGEDCO/ TANTRANSCO TANTRANSCO mail dated 26.07.2019:
2& 3.wedge connector have been provided in order to avoid jumbercut.
4. Replacement of porcelain insulators by polymer insulatos in all 230kV &
400kV feeders in North Chennai area has been completed
TANTRANSCO mail dated 12.02.2020:
1. Time synchro nisation of Protection relays is being carried out on part of S.R &
E.L project. The work is under progress.
2. Preventive maintenance has been carried out by Jumper strengthening with
provision of wedge clamps.
3. 3. (i). Polymer insulators has been provided in all the 400 kV evacuation lines
from NCTPS end up to 5 KMs. Replacement of Polymer insulator in 230 kV lines
are under progress for the 230 kV lines emanating from NCTPS.
(ii). Hotline washing 400 kV & 230 kV Line insulators in the NCTPS area will
be started during last week of February, 2020.
4. Already the backing of generation is being carried out during tripping of more
than two feeders in consultation with LD Centre.
Pending
84/II/4 Tripping of 230kV
Sulurupet-Gumudipoondi
line
11-04-2019 at
16:05 hr.
Triggering incident was B-N fault in 230kV
Gummudipoondi-NCTPS line. 230kV Sulurupet -
Gummudipoondi line tripped on operation of zone-2
distance protection at Sulurpet end and reverse zone
protection at Gummudipoondi end.
1.TANTRANSCO to check the resistive and reactive reach settings of 230kV
Gummudipoondi-NCTPS line at Gummidipoondi end.
2. APTRANSCO to ensure time synchronization of DR and EL at Sulurupet
end. Also in coordination with TANTRANSCO sort out the time synchronization
issue in 230kV Sulurupet-Gumudipoondi line.
3. TANTRANSCO to check the SOTF settings at Gummidipoondi end for
230kV Gummudipoondi-NCTPS line .
TANTRANSCO/ APTRANSCO APTRANSCO mail dated 30.07.2019:
2. GPS not available at 220KV Sullurpet SS.Manually set the timing on
29/07/2019 -- Completed
TANTRANSCO mail dated 26.07.2019:
1. & 3. Will be reviewed
TANTRANSCO mail dated 12.02.2020:
Complied
Complied
84/II/29 Frequent tripping of 220
kV KTPS –Lower Sileru
line
01-05-2019 at
16:04 hr.
04-05-2019 at
14:48 hr.
05-05-2019 at
11:29 hr.
06-05-2019 at
13:14 hr.
B-N FAULT
B-N FAULT
B-N FAULT
B-N FAULT
R-N FAULT
R-B FAULT
R-B FAULT
B-N FAULT
It was noted that no representative of APGENCO attended the meeting.
For the subject line, the following shall be carried out by TSGENCO in co-
ordination with APGENCO:
(i) End-to-end communication for DT/ permissive & other signals may be
ensured by testing at boththe ends.
(ii) Healthiness of PLCC system components (hardware and software) at both
ends shall be checked and faulty components shall be repaired/ replaced.
APGENCO in coordination with TSGENCO to ensure frequent patrolling and
APGENCO/ TSGENCO Yet to be informed Pending
Annexure-II
Page 7 of 39
85/II/14 Tripping of 230kV Theni-
Sabarigiri line
29-05-2019 at
18:39 hrs
3 phase to earth fault occurred in line. Tripped on
ground over current protection 67N at Sabarigiri and
Zone-2 at Theni end.
For the subject line, the following shall be carried out by TANTRANSCO in
coordination with KSEBL:
(i) End-to-end testing for DT/ permissive & other signals may be ensured by
testing at both the ends.
(ii) Healthiness of PLCC system components ( hardware and software) at both
the ends shall be checked and faulty components shall be repaired/ replaced .
TANTRANSCO/ KSEBL TANTRANSCO mail dated 12.02.2020:
The PLCC link between 230KV Theni – Moozhiyar feeder is healthy condition
and non-actuation of Carrier Protection during the fault on 29-05-2019 at 18:39
Hrs was due to the fault sensed in Zone-2 reach at Theni SS and Earth fault at
Moozhiyar SS.
KSEBL mail dated 11.02.2020:
PLCC system in SBTN feeder at Sabarigiri is not working well. Purchase process
for the new panel is under progress.It will be commissioned by April 2020.
Pending
85/II/20 Tripping of 220kV Idukki-
Udumalpet line
05-06-2019 at
15:13 hrs
Triggering incident was R-Y-Earth fault in the
line. Carrier aided protection not operated at
Udumalpet end.
For the subject line, the following shall be carried out by TANTRANSCO in
coordination with KSEBL:
(iii) End-to-end testing for DT/ permissive & other signals may be ensured by
testing at both the ends.
(iv) Healthiness of PLCC system components ( hardware and software) at both
the ends shall be checked and faulty components shall be repaired/ replaced .
KSEBL/ TANTRANSCO TANTRANSCO mail dated 12.02.2020:
Carrier set healthy at Udumelpet end. Healthiness of link will be checked after
getting confirmation from KSEB
KSEBL mail dated 11.02.2020:
PLCC system in IDUD feeder at Idukki is not working well. Purchase process for
the new panel is under progress.It will be commissioned by April 2020.
Pending
85/II/26 Tripping of 400kV
Vemagiri-GMR line-1&2
14-06-2019 at
09:33 hrs
Line-1 tripped on Y-Phase to earth fault due to Y-
Phase LA failure at Vemagiri end. Line-2 tripped at
GMR end only
1. APTRANSCO is recommended to submit Equipment failure report (LA
failure) to CEA.
2.GMR is recommended to submit a report regarding tripping of 400kV
Vemagiri-GMR line-2 at GMR end along-with the related tripping files.
APTRANSCO/ GMR APTRANSCO maild ated 03.10.2019:
1. Equipment (LA failure) Failure report submitted to CEA on 12.07.19.
---Completed
2. Pending
Pending
86/II/7 Tripping of 220 kV KTPS -
Lower Sileru-1
8-7-2019 at
10:45 hrs
Line tripped on B-phase to earth fault. As per FIR,
there was zone-2 operation at KTPS
For the subject line, the following shall be carried out by APGENCO in
coordination with TSGENCO:
i. End-to-end testing for DT/ permissive& other signals may be ensured by
testing at both the ends.
ii. Healthiness of PLCC system components (hardware and software) at both the
ends shall be checked and faulty components shall be repaired/ replaced .
APGENCO/ TSGENCO Yet to be informed Pending
87/II/3 Tripping of 220 kV KTPS-Lower
Sileru line-1
15-08-2019 at 13;04
hr.;
20-08-2019 at 11:23
hr.;
26-08-2019 at 13:43
hr.;
28-08-2019 at 11:17
hr.
Frequent Line tripping due to transient fault in R & Y phase APTRANSCO and TSTRANSCO are requested to take necessary actions to ensure proper tree
clearances and right of way for the subject line.
APTRANSCO/ TSTRANSCO TSTRANSCO mail dated 18.01.2020:
Patrolling has been carried out and tree clearance problem was rectified and the details are
submitted in 88th PCSC meeting.
Pending
87/III/1 Tripping of 230 KV-Neyveli TS
II - Karaikal line-1
17-08-2019 at
00:28hr.
B phase to Earth fault in the line. At Neyveli end A/R not
operated.
NLCIL and PED to submit a report regarding failure of A/R and the reason for the same NLCIL / PED PED letter dated 16.12.2019:
For Zone-1 fault occurred on the line at 00:27:46.448 at Karaikal SS A/R acted and B-pole of the
breaker got opened at 00:27:46.494. While A/R was in running condition, carrier aided trip was
received from TS II, Neyveli at 00:27:46.468 and breaker got opened with A/R lockout relay
getting operated at 00:27:47.407. DR & EL of the incident recorded at karaikal SS is attached
herewith
PED mail dated 21.01.2020:
It has been programmed to test the Auto Reclosure scheme on 230KV Neyveli TS – Karaikal line
and 230KV Karaikal – Bahour line at Karaikal SS with the coordination of M/s.Power Grid
Corporation of India Limited by conducting special testing within this month and on conclusion a
report in this respect will be submitted within a fortnight.
PED mail dated 12.02.2020:
A meeting was convened between M/s.Power Grid Corporation of India Limited and Puducherry
Electricity Department at Head Quarters of this department, Puducherry on 10.02.2020 and the
failure of Auto Reclosure for Tripping of 230 KV Neyveli TS II - Karaikal line-1 on 17-08-2019 at
00:28hr at Karaikal SS was discussed. In the meeting, M/s.PGCIL informed that the PLCC links of
230KV Bahour Auto SS and 230KV Karaikal Auto SS was tested and normalised on 01.02.2020
and there would not be any failure of Auto Reclosure in future. It was also informed that Auto
Reclosure was functional in the 230KV Karaikal - Neyveli Line and there was no communication
link failure so for. Further, M/s.PGICL has consented to conduct testing on 230KV Karaikal -
Neyveli Line and 230KV Karaikal - Bahour LIne at Karaikal SS during the period of Line Clear at
the earliest.
Pending
88/1/1 Complete outage of 220kV
Lower Sileru GS of
APGENCO
22-10-2019 at
05:20Hr.
Triggering incident was fault in 220kV Lower Sileru
– Donkarai line. LBB of both bus-1 and bus-2
operated resulting in complete outage at 220kV
Lower Sileru generating station.
1. APGENCO to submit a detailed report on or before 15th
January 2019, regarding complete
outage of Upper Sileru and Lower Sileru, clearly indicating the protections which operated at
both ends of all the lines which tripped.
2. APGENCO to conduct breaker timing tests and ensure healthiness of all breakers in their
switchyard and if found unhealthy action shall be taken to replace the same.
3. APTRANSCO to furnish a report on factual configuration and settings of the PD and A/R
relays.
APGENCO/ APTRANSCO Pending
Annexure-II
Page 8 of 39
88/IV/4 Tripping of 220kV Chillakallu
Suryapet line-1
17-10-2019 at 13:30
Hr.
Triggering incident was Y phase to B phase fault in the line. At
Chillakallu end, as per the report submitted it is mentioned that
Zone-1 distance protection operated. However, DR is not
available to verify the same. At Suryapet end, Zone-2 distance
protection operated and carrier was not received. Failure of
carrier aided protection at Suryapet end needs review.
The following shall be carried out by TSTRANSCO in coordination with APTRANSCO:
a) End-to-end testing for DT/ permissive & other signals may be ensured by testing at both the
ends.
b) Healthiness of PLCC system components (hardware and software) at both the ends to be
checked and faulty components to be repaired/ replaced.
c) Time synchronization of relays at both ends.
TSTRANSCO,/ APTRANSCO TSTRANSCO mail dated 11.02..2020:
At our end MRT & Telecom wing are ready to carry out end to end testing.
Waiting for confirmation from APTRANSCO end to carry out testing.
Pending APTRANSCO to coordinate with TSTRANSCO
89/I/6 Complete loss of supply at 220
kV Kolar, 220 kVMalur and 220
kV Sarjapur stations.
16-01-2020 at
09:58 Hr.
• Triggering incident was Y-phase jumper cut in 220
kV Kolar (KAR) – Kolar (PG) line-1.
• 220 kV Kolar (KAR) – Kolar (PG) Line-2 tripped
at Kolar (KAR) end only.
• There was complete loss of supply at 220 kV
Kolar, Malur and Sarjapur stations.
i. PGCIL (SR-2) to disable Broken conductor trip and enable Broken conductor alarm.
ii. KPTCL to configure all DR digital channels in relay DR and submit the SPS scheme
implemented at 220 kV Kolar (KAR) SS.
PGCIL (Sr-2)/ KPTCL Yet to be informed Pending
89/IV/3 Tripping of 400kV Warangal –
Bhoopalapally line-114-12-2019 at
19:03 Hr.
• Line tripped at Bhoopalapally end only on DT
received.
• Line was holding from Warangal end.
TSTRANSCO and TSGENCO to expedite the process of replacing PLCC of 400kV Warangal –
Bhoopalapally line-1 and intimate completion of the same to SRPC.
TSGENCO/ TSTRANSCO Yet to be informed Pending
89/IV/4 Tripping of 400kV Dhoni –
Munirabad Line04-01-2020 at
09:32 Hr.
• Line tripped at Dhoni end only on receipt of DT
from Munirabad end.
• Line was holding at Munirabad end.
PGCIL (SR-1) in coordination with KPTCL to replace the faulty auxiliary relay (for sending of
DT during hand tripping) and intimate the same to SRPC.
PGCIL (SR-1)/ KPTCL KPTCL informed vide mail dated 17./03.2020 that the problem with faulty
auxiliary relay (for sending of DT) has been rectified
Complied
86/II/1 Tripping of 400 kV
Krishnapatnam-Nellore-1
01-07-2019
at 03:40 hrs,
03-07-2019
at 3:42 hrs,
19-07-2019
at 2:25 hrs, 21-
07-2019
at 2:27 hrs, 28-
07-2019
at 1:40 hrs, 28-
07-2019
at 23:39 hrs
Line tripped on operation of over voltage stg-1
protection at Krishnapatnam and direct trip was
received at Nellore. The Y –phase CVT voltage at
Krishnapatnam end was observed to be 8 to 10 kV
higher than the R & B phase voltages
1. APGENCO to configure both OVR start and trip signal in DR or EL.
2. APGENCO in coordination with APTRANSCO to sort out the time sync
issues between Krishnapattanam and Nellore.
APGENCO APGENCO vide letter dated 29.10.2019
The line CVT was tested for secondary voltages, tandelta values and found them
on higher side. Drift in capacitance value observed. Y-ph CVT was replaced with
spare available and voltages found normal compared to other phases.
OVR config and time sync?
Pending
86/II/10 Outage of Bus-2 at 400 kV
RYTPP station of
APGENCO
18-07-2019
at 3:30 hrs
Bus bar protection of 400 kV Bus-2 operated due to
malfunctioning of CT supervisory circuit. All
elements connected to Bus-2 tripped
APGENCO to revise the CT circuit supervision circuit monitoring and tripping
of Busbar at RYTPP.
APGENCO Yet to be informed Pending
87/I/1 Complete outage of 220 kV
Lower Sileru GS of
APGENCO
23/08/2019 at
18:52 hr.
Malopertion of Bus-1 and Bus-2 bus bar protection
lead to tripping of all connected elements at 220 kV
Lower Sileru resulting in complete loss of supply at
220 kV Lower Sileru station.
1. APGENCO to ensure that shift engineers and operators strictly adhere to
operational procedure.
2. APGENCO may explore the possibility of providing proper interlock between
Buscoupler and isolator (i.e., In the event of an element connected to one bus
through respective bus isolator the interlock is intended to disallow closing of
other Bus isolator if Bus coupler is in open condition).
APGENCO Yet to be informed Pending
84/II/9 Tripping of 220kV Bus 2
and connected elements at
220kV Gazuawaka
Substation.
17-04-2019 at 5:40 hr.Triggering incident was Y-phase to earth fault in
220kV Gazuwaka Bus-2. This resulted in tripping of
220 kV elements and 400/220 kV ICT-2
1. APTRANSCO to submit a detailed report regarding the subject tripping at
220 kV Gazuawaka Substation along with the remedial measures taken.
2. For all lines emanating from Gazuwaka SS, RTV coating shall be taken up.
APTRANSCO APTRANSCO mail dated 30.07.2019:
1. The report submitted vide mail dated 29.07.2019 -- Completed
2. Pending
APTRANSCO mail dated 03.10.2019 and 29.10.2019:
2).Tenders is under process for RTV coating of all the lines emanating from
Vizag Switching Station.(VSS) -- Pending
Pending
86/I/3 Complete outage of 220
kV/132kV Paravada SS of
APTRANSCO
08-08-2019 at
11:34 hrs
Triggering incident was failure of Y-ph LA of 220
kV Paravada- VSS (Vizag Switching Station) line at
Paravada end.
1. APTRANSCO to submit equipment failure report to CEA,in respect of the
failed Lightning arrester, and to ensure healthiness of Lightning arresters in
other phases.
2. APTRANSCO shall also regularly perform third harmonic current
measurement (THRC) and measurement of LA stack temperature to monitor
healthiness of LA’s.
APTRANSCO APTRANSCO mail dated 29.10.2019:
1. Equipment failure report to CEA in respect of the failed Lightning arrester will
be sent soon, and healthiness of Lightning arresters in other phases are already
checked on 08-08-2019.
2. Third harmonic current measurement (THRC) kit not available with
APTRANSCO. Measurement of LA stack temperature to monitor healthiness of
all LA’s is done every month along with other equipment and this month testing
is scheduled on 02-11-2019 . --Completed
Pending
Andhra Pradesh
Annexure-II
Page 9 of 39
86/II/19 Tripping of 400 kV
Simhadiri-Kalpakka line-
1,2&3; 400 kVKalpakka-
Asupaka line-1 &400
kVKalpakka-Gazuwaka
line-2
5-08-2019 at
13:37 hr.
Triggering incident was failure of R-phase LA in
400 kV Kalpakka-Asupaka line.
APTRANSCO to implement line differential protection for 400 kV Simhadri-
Kalpakka line immediately and required OFC/OPGW may be arranged within a
week
APTRANSCO APTRANSCO mail dated 29.10.2019:
The line differential protection was enabled in 400 kV kalapaka
PGCIL(Gajuwaka) I & II feeders, 400 kV kalapaka HNPCL I & II feeders. LC
was programmed on 15.10.2019, 17.10.2019 and 18.10.2019 for testing and
enabling the differential feature in 400 kV Kalapaka Simhadri-2,3, &, 4 feeders.
clearance for testing was not accorded from M/s NTPC. As and when the
clearance is accorded from M/s NTPC the differential feature will be enabled in
400 kv kalapaka Simhadri-2,3&4.
87/1/2 Complete Outage of 220 kV
Vizag Switching Station
and 220 kV Parawada SS of
APTRANSCO
28/08/2019
at 15:3
a. Bus-1 and Bus-2 Bus Bar Protection operated due to
snapping of R-phase dropper jumper at 220 kV VSS r
esulting in the tripping of all the connected elements. b. 400
kV/220 kV ICT#1 and 2 at Gazuwaka also got tripped during
this event.
c.220 kV Paravada SS was radially fed from 220 kV VSS
during antecedent conditions.
1. APTRANSCO to investigate whether ageing or tension led to failure of R-Phase dropper from
Jack bus to bridge which led to complete outage of 220 kV VSS and Parawada.
2. Healthiness of other jumpers at 220 kV VSS shall
be ensured and a report shall be furnished to SRPC. APTRANSCO to submit Thermovision
scanning reports of 220 kV VSS during past 6 months and ensure time sync at 220 kV VSS.
APTRANSCO Yet to be informed Pending
87/III/3 Tripping of 400 kV
Maheshwaram-Narnoor line
22-08-2019 at 4:00
hr.
B-phase to earth fault occurred in line. Auto-reclose was
successful at Mahshwaram and A/R not operated at Narnoor
1. APTRANSCO to submit a report after checking A/R operation.
2. APTRANSCO to configure OVR start in EL.
APTRANSCO Yet to be informed Pending
88/1/4 Complete Loss of Supply at
400/220kV Narnoor station29-11-2019 at
20:08 Hr.
Triggering incident was fault in 400kV Narnoor -
Srisailam line. LBB of Bus-1 operated and all
elements connected to Bus-1 tripped. Since there
was no other infeed to Narnoor station, there was
complete loss of supply at 400/220kV Narnoor
station. In the antecedent, Main breaker of 400kV
Narnoor-Srisailam was in lockout condition and
220kV Narnoor -Somyzulpalli line-1 &2 was in idle
charged condition.
APTRANSCO to ensure proper segregation of loads, generators and ICTs on both
buses in case of one and half breaker scheme while planning of substations
APTRANSCO Yet to be informed Pending
88/II/19 Tripping of 400kV Kalpakka
Vemagiri line-1
28-10-2019 at 09:51
Hr.
Triggering incident was R-N in the line. Fault was sensed in
Zone-1 at both the ends. At both the ends A/R operated and line
got tripped due to persistent fault. But at Kalpaka end, after
A/R operation even though the fault was sensed in zone-1 there
was delayed opening of all 3 ph breakers for around 250ms.
APTRANSCO to submit a report, after consultation with OEM, regarding the delay in tripping of
400kV Kalpakka Vemagiri line-,1 inspite of the fault being detected in Zone-1.
APTRANSCO Yet to be informed Pending
88/II/24 Tripping of 400/220kV ICT-1,
ICT-2 and ICT-3 at Vemagiri
18-11-2019 at 21:54
Hr.
Triggering incident was ICT-2, B-phase LA flashover. ICT -2
tripped on differential protection and ICT-1 and ICT-3 tripped
on over current protection.
APTRANSCO to devise SPS scheme, designed to trip some loads in the event of tripping of any
of the 400/ 220kV ICT’s at Vemagiri, to prevent cascaded tripping of all ICT’s due to overload in
the event of outage of one ICT.
ii. Also APTRANSCO to configure standalone EL with contacts wired from all static relays.
APTRANSCO Yet to be informed Pending
89/1/3 Complete outage of 220 kV
Bommuru SS of APTRANSCO
01-01-2020 at 11:40
Hr.
• Bus bar protection operated resulting in complete outage of
220 kV Bommuru SS.
i. APTRANSCO to enable auto-reclosure in all lines emanating from 220 kv Bommuru SS.
ii. APTRANSCO to ensure time synchronization of relays with GPS at 220 kV Bommuru SS and
220 kV Vemagiri SS.
APTRANSCO Yet to be informed Pending
89/II/17 Tripping of 400 kV Vemagiri –
Sattenapally line of
APTRANSCO
10-01-2020 at 13:59
Hr.
• As reported, bus bar protection of 400 kV Bus-2 operated at
Vemagiri resulting in tripping of 400 kV Vemagiri –
Sattenapalli line.
APTRANSCO to expedite the process of replacing Static BBP at 400kV Vemagiri SS with
numerical BBP, to prevent mal-operations of BBP at Vemagiri SS.
APTRANSCO Yet to be informed Pending
Annexure-II
Page 10 of 39
82/II/1 Tripping of 400kV KTPS
VI- KTPS VII
05-01-2019
at 10:17hrs
Line tripped at KTPS VI end due to suspected mal-
operation of over-voltage protection. Line was in
service from KTPS VII., BUS CVT secondary R
PHASE got grounded at KTPS VI
1) TSGENCO to configure OVR_start and OVR_tripin EL at KTPS-VI end and
sent a report after completion of works related to DT communication channel
between KTPS-VI and KTPS-VII
TSGENCO TSGENCO mail dated 24.06.2019:
The issue is referred to M/s BHEL ( EPC vendor ) and the study on feasibility
for providing the communication with the existing available system is under
process and will be completed during the availability of next shutdown.
Review meeting on 27.06.2019:
TSGENCO informed that the recommendations will be completed in September
2019
TSGENCO mail dated 10.02.2020:
DT communication between KTPS-VI stage and KTPS-VII stage has been
provided on 09.08.2019. Hence, it is requested to drop the point,
Pending OVR_start and OVR-trip configured
in EL at KTPS VI ?
83/III/6 Tripping of 400kV
Julurpadu - Manuguru line-
2
14-03-2019 at
06:10:00
Triggering incident was R-ph fault in the line. At
Julurpadu end, fault was sensed in Zone-2 and
carrier was received but due to DT Receive from
manuguru end, A/r not operated and line got
tripped. FIR, DR and EL of Manuguru end are not
available.
It was noted that no representative of TSGENCO attended the meeting.
TSGENCO is recommended to submit a report on the tripping and to furnish
equipment failure report to CEA.
TSGENCO TSGENCO mail dated 24.06.2019:
FIR, DR and EL was uploaded in SRLDC website.Trip Report was also
submitted.
Review meeting on 27.06.2019:
TSGENCO informed that Equipment failure report will be sent to CEA.
Pending
84/II/28 Frequent tripping of 220
kV KTPS –Nunna line
05-04-2019 at
12:55 hr. B-N
FAULT
15-04-2019 at
13:20 hr. Y-N
FAULT
16-04-2019 at
In 155thOCC meeting of SRPC, APTRANSCO
informed that the tripping was due to clearance
issues in the ROW caused by mango tree. It was
cleared and issue was rectified. However, frequent
tripping of line is still persistent.
1. TSGENCO to check the non-operation of carrier aided trip, when fault is
detected at KTPS end in Z-2 and carrier is also received, and submit a report
regarding the same.
2. TSGENCO and APTRANSCO to ensure that ROW is cleared periodically.
3.APTRANSCO & TSGENCO may consider raising the height of towers if the
line is planned to be used in future.
4.TSGENCO to consider replacement of old pneumatic CB’s at KTPS if 220kV
TSGENCO Yet to be informed Pending
87/II/5 Tripping of 220 KV-Srisailam
Right Bank-Nagarjunsagar TS-1
18-08-2019 at 4:23
hr.;
05-09-2019 at 13:50
hr
Suspected mal-operation of Main-2 distance protection relay at
Nagarjunsagar TS-1. Line was holding from Srisailam right
bank.
TSGENCO to carry out the following for tripping of the subject line:
1.Check the SOTF settings and breaker contacts. 2.SOTF auto-initiation shall be kept off (in
settings).
3.Submit a disturbance recorded file after changing the DR time scale to capture 500msec pre
fault and 2 sec post fault events.
TSGENCO Yet to be informed Pending
88/II/3 Tripping of 220kV KTPS-Nunna 27-09-2019 at 14:41
Hr.
· Line tripped at Nunna end only on operation of Zone-2
distance protection.
· It was further mentioned in the report that there was bus
fault at KTPS end.
• Non operation of protection at KTPS end needs review
TSGENCO to verify the relay DRs and EL corresponding to the event and submit a report to
SRPC regarding the event.TSGENCO Yet to be informed Pending
84/II/27 Multiple tripping at 220 kV
Ghanapur station
27-05-2019 at
02:04 hr.
Triggering incident was failure of B-phase CT of
bus coupler of Bus-2. Bus bar protection of 220 kV
Bus-2 operated resulting in tripping of all elements
connected to Bus-2.
1.TSTRANSCO is recommended to submit Equipment failure report to CEA
regarding the blast CT.
2.TSTRANSCO to inform if any old CTs exist in Ghanapur SS and ensure
healthiness of the same to
TSTRANSCO TSTRANSCO MAIL DATED30.10.2019:
1. Informed our transmission wing to submit the Equipment failure report to
CEA.
2. All the existing old CTs are replaced with new one.
Pending
89/II/3 Tripping of 400/220 kV Janagaon
ICT-1 of TSTRANSCO
02-12-2019 at 13:28
Hr.
· ICT tripped due to suspected maloperation of PRV
protection. TSTRANSCO informed that the faulty PRV was replaced on 10.12.2019. TSTRANSCO Yet to be informed Pending
89/II/8 Tripping of Bus-2 at 220 kV
Malyalappali (Ramagundam)
station.
21-12-2019 at 03:10
Hr.
• Triggering incident was B-N fault in 220 kV Malyalapalli-
Ramapur line.
• LBB of Bus-2 operated since B-phase CB of 220 kV
Malyalappali-Ramapur line did not open due of damage in trip
coil
TSTRANSCO to ensure A/R functionality on all lines emanating from 220 kV
Malyalapalli SS and to ensure time synchronization of relays between Rampur
and Malyalapalli.
TSTRANSCO Yet to be informed Pending
89/III/4 Tripping of 400kV
Kethyreddypalli – Shankerpally
Line-1
08-01-2020 at 23:36
Hr.
• Triggering incident was B-N fault in the line. AR operated and
successful at Kethyreddypalli end
• AR not attempted at Shankerpally end
TSTRANSCO to investigate and submit the reasons for delayed opening of TIE
CB Y-ph and B-ph in spite of 3-ph trip issued by relay. Pole discrepancy timing
of TIE CB may also be checked.
TSTRANSCO Yet to be informed Pending
Telangana
Annexure-II
Page 11 of 39
Mail received on 21-10-2015:
1) Anti-pumping contactors of all the nine 220KV Lines are in circuit and tested
periodically during AOH works of lines along with other protections.
2) Completed.
3) Possibility to use both the 220kV buses as main bus under normal operation is
under review.
Mail recieved on 23-11-2015:
1) Completed
3) Two bus operation for 220kV buses : In place of existing CT switching relays,
High speed manual heavy duty change over switch of sufficient current capacity
will be retrofitted to all feeders at 220kV station and same will be operated
manually during changeover of feeder by one bus to the other and this
arrangement may facilitate to put both buses in service. Time required for this
retrofit is around 90days . However, this work will be taken up only after
retrofitting of electromagnetic relays with numerical relays for Main-2 protection
of all 220kV lines, for which work is in progress.
Status received vide mail dated 10-07-2017:
1) --- Completed.
2) --- Completed.
3) Two Bus operation for 220kV bus is being carried out whenever required.
However scheme for tripping of one bus during LBB/fault and maintaining the
other bus intact by tripping B/C breaker will be taken up in R&M works. --- Status received vide KPCL mail dated 14.12.2017:
3) DPR for implementation of Two Bus operation for 220kV bus system has been
prepared and proposal is placed for funds from PSDF. After the approval of the
DPR, the work is proposed to be taken up.
Review Meeting dated 19.12.2017:
3) KPCL informed that DPR for implementation of Two Bus operation for 220kV
bus system has been prepared and proposal is placed for funds from PSDF. After
the approval of the DPR, the work is proposed to be taken up. Time frame
requested for is 2 yrs.
KPCL mail dated 19.12.2018:
3) Work proposed to be taken up under PSDF. Approval from Nodal agency is
awaited. However, arrangements have been made to issue NIT.
Review Meeting on 21.12.2018:
KPCL informed that Tender would be floated in 1 month and work would be
completed in 2 years.
KPCL mail dated 23.03.2019:
Arrangements have been made to issue NIT and Tender for the work proposed to
be floated during May- 2019.
KPCL mail dated 10.05.2019:
NIT will be issued during May- 2019.
KPCL mail dated 25.06.2019:
1. & 2. Completed
3) Preparation of technical specification is in progress. NIT will be issued during
July- 2019.
Review meeting on 27.06.2019:
KPCL informed that timeline for completion of work is December 2019.
KPCL mail dated 16.07.2019:
1. & 2. Completed
3) Preparation of technical specification is in progress. NIT will be issued during
July- 2019. timeline for completion of work is December 2019.
KPCL mail dated 30.10.2019 and 17.12.2019 and 11.02.2020:
1. & 2. Completed
3) NIT issued during Aug- 2019. Timeline for completion of work is December
2020.
Status received vide KPCL mail dated 10.07.2017:
1. (ii) Hot line water washing stopped and off line water washing is carried out
whenever the 400 KV Unit or line is under tripped condition / Shutdown
condition. --- Completed
1. (iii) Silicon coating for Unit#8 main & tie breakers carried out in Sep'16 and
same is under observation. Till today in order and good condition. For remaining
breakers, since it is big order, approval for the same is under process. ---
13-04-2016 at
21:12 hrs
Tripping of 400kV Raichur
TPS
Bus-2
46/II/21 Trippings at 220kV Raichur
TPS
07-06-2015 at
01:35 hrs
1. KPCL to check the operation of anti-pumping relay on 220 kV side and keep
it in healthy condition.
2. KPCL to provide manual reset to the 220 kV side master trip relay.
3. KPCL to use both the 220 kV buses as main buses under normal operation,
and should go for single bus operation only during emergencies.
54/II/9 Y-ph Pole of Tie-breaker of Unit-4 at RTPS failed.
Unit-4 got tripped on operation of Generator
Differential, Reverse power & LBB protection.
Operation of LBB protection led to tripping of BUS-
2 at RTPS
Karnataka
1.KPCL to undertake the following remedial measures to avoid breaker
flashovers:
(i) Replacing all porcelain insulators with composite insulators
(ii) Carrying out hot-line water washing of all insulators on regular basis.
(iii) Applying Room Temperature Vulcanizing (RTV) Silicone high voltage
insulator coatings to all bus-connected ceramic insulators of equipment like CT,
PT, CB, Isolators etc.
2.KPCL to take steps to provide dedicated breaker flashover protection to all
breakers at Raichur TPS at the earliest.
Pending
PendingKPCL
KPCL
Annexure-II
Page 12 of 39
Review Meeting dated 19.12.2017:
1 (iii) As upgradation of 400kV switchyard equip's to be taken under PSDF
funds, Silicon rubber coating for breakers is deffered till then. --- Pending
2. Replacement by Num relay for Units - 5,6 & 7 completed in the month of Oct-
2017. Main-I is Seimens make and Main-II is ABB make. --- Pending
KPCL mail dated 19.01.2018:
2. Replacement of Numerical relays for Units-5, 6 & 7 have been completed.
Referred to OEM for providing the Breaker flashover protection for all the
breakers.
KPCL mail dated 19.12.2018:
2. Reply is awaited from OEM of Numerical relays for providing Breaker
Flashover protection for all the breakers --- Pending
Review Meeting on 21.12.2018:
1. KPCL assured that porcelain insulator replacement will be taken care in tender
floated for RTPS Busbar modification --- Pending
KPCL mail dated 23.01.2019:
1) i) Being discussed with other utilitis.
2) Reply is awaiting from OEM to implement the Breaker flash over protection in KPCL mail dated 23.03.2019:
1) (i) & (iii)- Arrangements have been made to issue NIT and Tender for the
work proposed to be floated during May- 2019.
2) Reply is awaiting from OEM to implement the Breaker flash over protection in
the Numerical relays in 400KV station. & Being discussed with other utilities.
It is requested to furnish Necessary logic and settings to implement the breaker
flashover protection
KPCL mail dated 10.05.2019:
1) (i) & (iii)- NIT floated on 01.03.2019
2) Reply is awaiting from OEM to implement the Breaker flash over protection in Review meeting on 27.06.2019:
SRPC informed that referenc of necessary logic and settings to implement the
breaker flashover protection will be shared soon.
KPCL mail dated 16.07.2019:
1) (i) & (iii)- NIT floated on 01.03.2019. Cover-I opened. Technical evaluation is
in progress. Approval from Nodal Agency for PSDF funds is awaited.
2) As confirmed during 84th PCSC meeting, SRPC may suggest/furnish referenc
of necessary logic and settings to implement the breaker flashover protection.
reply in this regard is awaited.
KPCL mail dated 30.10.2019 and 17.12.2019 and 11.02.2020:
1) (i) & (iii)- NIT floated on 01.03.2019. Tender evaluation is completed.
Approval from Nodal Agency for PSDF funds is awaited for placing PO on L1
agency.
2) As confirmed during 84th PCSC meeting, SRPC may suggest/furnish referenc
of necessary logic and settings to implement the breaker flashover protection.
reply in this regard is awaited.
13-04-2016 at
21:12 hrs
Tripping of 400kV Raichur
TPS
Bus-2
54/II/9 Y-ph Pole of Tie-breaker of Unit-4 at RTPS failed.
Unit-4 got tripped on operation of Generator
Differential, Reverse power & LBB protection.
Operation of LBB protection led to tripping of BUS-
2 at RTPS
1.KPCL to undertake the following remedial measures to avoid breaker
flashovers:
(i) Replacing all porcelain insulators with composite insulators
(ii) Carrying out hot-line water washing of all insulators on regular basis.
(iii) Applying Room Temperature Vulcanizing (RTV) Silicone high voltage
insulator coatings to all bus-connected ceramic insulators of equipment like CT,
PT, CB, Isolators etc.
2.KPCL to take steps to provide dedicated breaker flashover protection to all
breakers at Raichur TPS at the earliest.
PendingKPCL
Annexure-II
Page 13 of 39
Status received vide KPCL mail dated 10.07.2017 & 14.12.2017:
Two Bus operation for 220kV bus is being carried out whenever required.
However scheme for tripping of one bus during LBB/fault and maintaining the
other bus intact by tripping B/C breaker will be taken up in R&M works.
Review Meeting dated 19.12.2017:
3) KPCL informed that DPR for implementation of Two Bus operation for 220kV
bus system has been prepared and proposal is placed for funds from PSDF. After
the approval of the DPR, the work is proposed to be taken up. Time frame
requested is 2 yrs.
KPCL mail dated 20.12.2018 & 23.01.2019:
Work proposed to be taken up under PSDF. Approval from Nodal agency is
awaited. However, arrangements have been made to issue NIT.
KPCL mail dated 10.05.2019:
NIT will be issued during May- 2019.
KPCL mail dated 25.06.2019:
Preparation of technical specification is in progress.
NIT will be issued during June/July- 2019.
Review meeting on 27.06.2019:KPCL mail dated 16.07.2019 & 30.10.2019:
NIT will be issued during July- 2019. Time line for completion of work is Dec-
2020.
KPCL mail dated 17.12.2019 and 11.02.2020 :
NIT issued during Aug-2019.
Time line for completion of work is Dec-2020.
54/II/13 Tripping of Units at 220 kV
Raichur TPS
KPCL In view of the availability of two buses along with healthy bus-coupler at 220
kV RTPS, KPCL is recommended to put in service the double-bus operation at
220 kV RTPS by suitably distributing loads within 15 days.
During testing of retrofitted distance protection in
400kV Raichur-2 feeder, LBB protection trip DC
got extended to Bus trip. This resulted in tripping of
220kV bus at RTPS and all connected 220 kV
elements. Unit-4 which is connected to 400 kV Bus
got tripped due to tripping of Station Utility
Transformer that is connected 220 kV bus
Timeline?15-04-2016 at
15:36 hrs
Pending
Annexure-II
Page 14 of 39
Status received vide KPCL mail dated 14.06.2017:
1. All logics checked and found normal. LBB timing checked and found 200msec
as per KPTCL MRT recommendation. - Completed
2. Work Under Progress ---- Pending
3. New GPS System commissioned along with new numerical and synchronised
with GPS system - Complied
4. Work Under Progress ---- Pending
Status received vide mail dated 14.12.2017:
1),3),4) Completed
2. Auto Start of DG set is taken up --- Pending
Review Meeting dated 19.12.2017:
2. KPCL informed that for AMF of DG, Scheme prepared & material
procurement under process. The AMF scheme will be implemented in January
2018. --- Pending
3. The GPS system commissioned on Nov 2016 & all the numarical relay time
synchronised with GPS ---- Completed
Review Meeting on 21.12.2018:
KPCL informed that Tender for the work would be floated by January 2019 and
work would be completed in 1 year.
KPCL mail dated 23.01.2019:
1) Completed.
2) Tender for the work would be floated by February 2019 and work would be
completed in 1 year....Pending
3) Completed.
4) Tender for the work would be floated by Feb, 2019, and work would be
completed in 1 year....Pending
KPCL mail dated 23.03.2019:
2) Tender for the work proposed to be floated during May- 2019 after model code
of conduct and work would be completed in 1 year .
4) Tender for the work proposed to be floated during May- 2019 after model
code of conduct and and work would be completed in 1 year.
KPCL mail dated 10.05.2019:
Tender will be floated during 3rd week of May- 2019.
KPCL mail dated 25.06.2019:
1 & 3) Completed.Review meeting on 27.06.2019:
.1 & 3) Completed.
4) Tender published on 21.06.2019 and time line in June 2020.
2. tender has to be issued. Timeline requested upto December 2020.
KPCL mail dated 16.07.2019 :
1 & 3) Completed.
2 ) NIT will be issued during Aug-2019.
4) Tender published on 21.06.2019. Time line for completion of Work is Dec-
2020.
KPCL mail dated 30.10.2019 and 17.12.2019:
1 & 3) Completed.
2 ) NIT issued during Sept-2019.
4) Tender published on 21.06.2019. Time line for completion of Work is Dec-
2020.
KPCL mail dated 11.02.2020:
1 & 3) Completed.
2 ) NIT issued during Sept-2019. Tender evaluation is inprogress.
4) As per the directions of TESG of NLDC i..e. Numerical relays are being
provided for all Units and Lines, the proposal of providing Disturbance recorder
is excluded from DPR submitted for availing funds from PSDF - Issue may be
dropped. --- Dropped
Status received vide mail dated 25.07.2018:
Numerical Generator protection relay replacement proposed to be taken up
alongwith SCADA work.
KPCL mail dated 20.12.2018:
Will be taken up along with SCADA work. NIT to be issued on Jan-2019
Review Meeting on 21.12.2018:
KPCL informed that Tender for the work would be floated by March, 2019, and
work would be completed in 1 year.
KPCL mail dated 23.01.2019:
Tender for the work would be floated by February-2019 and work would be
completed in 1 year.
KPCL mail dated 23.03.2019:
Tender for the work proposed to be floated during May- 2019 after model code of
conduct and work would be completed in 1 year
KPCL mail dated 10.05.2019:
Tender will be floated during 3rd week of May- 2019.
KPCL mail dated 25.06.2019:
Tender published on 21.06.2019.
Review meeting on 27.06.2019:
1) KPCL to check settings of LBB protection in all relays from which it was
implemented, and ensure that their configuration, logic, and timing are in order
at their 220 kV Kadra PH.
2) KPCL to furnish details regarding the existing LT auxiliary supply
arrangement at their 220 kV Kadra PH, and take steps to provide a suitable Auto-
Main-Fail (AMF) panel for DG set to effect its auto-starting in case of failure of
LT supply.
3) KPCL to ensure time-sync of all relays (DR’s & EL’s) with GPS at their 220
kV Kadra PH.
4) KPCL to provide stand-alone Event Logger at their 220 kV Nagjheri PH.
LBB of 220kV Kodasalli breaker at Kadra end got
operated which resulted in tripping of Bus at Kadra
and in turn led to tripping of all elements
06-09-2016
at 14:40 hrs
KPCL to take steps to replace the existing static protection relays for Generator
Units and Generating Transformers (GT’s) with suitable Numerical relays at
their 220 kV Kadra PH.
While de-synchronising of Unit-2, B-phase pole of
GCB did not open and pole descrepancy relay
operated. Hence all 220KV lines CB hand tripped.
58/I/3
(GD)
69/II/8 Tripping of 220 kV Kaiga-
Kadra line-1
Pending
Complete outage of 220 kV
Kadra power station of
KPCL
06-10-2017 at
22:22 hrs
PendingKPCL
KPCL
Annexure-II
Page 15 of 39
KPCL mail dated 16.07.2019:
Tender published on 21.06.2019. Time line for completion of Work is Dec-2020.
KPCL mail dated 30.10.2019 and 17.12.2019 and 11.02.2020:
Tender published on 21.06.2019. No bids received for the tender. Hence, it is
proposed to refloat fresh tender with revised PQR and scope of work. Avaialing
approval in this regard is in progress.
72/I/4 Complete outage of 220kV
Sedam, Shahapur,
Shahabad, Kapanoor,
Humnabad and Halabarga
Stations of KPTCL
01-02-2018
at 17:46 hrs
High resistance fault occurred in 110kV Sedam-
Chittapur line near Sedam end. Line DEF operated
and backup OC protection of 100MVA transformer
operated at Sedam end. But line breaker and
transformer HV breaker didn’t open due to problem
in trip circuit. This resulted in cascade tripping of
upstream feeders and power supply was lost to six
220kV stations of KPTCL.
KPCL to disable GFC protection on all lines emanating from their generating
stations.
KPCL Review Meeting on 21.12.2018
KPCL informed that compliance w.r.t. Implementing the recommendation would
be furnished soon.
KPCL mail dated 23.03.2019:
'GFC protection will be disabled in all lines in coordination with M/s.KPTCL
KPCL mail dated 10.05.2019 & 25.06.2019:
Letter addressed to CE, RT, KPTCL dated: 10.04.2019 to disable GFC
protection in all 220kV lines . Reply is awaited.
KPCL mail dated 16.07.2019 & 30.10.2019 & 17.12.2019 & 11.02.2020:
Letter addressed to CE, RT, KPTCL dated: 10.04.2019 to disable GFC
protection in all 220kV lines . Reply is awaited.
Pending
73/I/5 Complete outage of 220kV
Varahi power station
15-03-2018 at
22:36 hrs
There was Y-phase to ground fault on 220 kV
Varahi - Shimoga line-2. Consequent to persisting
fault in ‘Y’ phase, the breaker failure protection
operated resulting in operation of 220KV bus bar
protection at Varahi, tripping all the connected lines
and Varahi running units.
KPCL to take steps to put double-bus operation into service at their 220 kV
Varahi PH.
KPCL Status received vide mail dated 25.07.2018:
Under Implementation.
KPCL mail dated 20.12.2018 & 23.01.2019 & 23.03.2019:
Retrofitting of 220kV Bus Isolators is under progress. Proposed to be in service
after April-2019
KPCL mail dated 10.05.2019:
4 Set of Isolators of VS1, VS2 & VM2 bay of North Bus were cmpleted.
Remaining bays will be completed after Concurrence of LC from LDC
KPCL mail dated 25.06.2019 & 16.07.2019 & 30.10.2019:
4 Set of Isolators of VS1, VS2 & VM2 bay of North Bus were cmpleted.
Remaining bay will be completed after monsoon season i.e during November -
2019
KPCL mail dated 17.12.2019 and 11.02.2020:
4 Set of Isolators of VS1, VS2 & VM2 bay of North Bus were cmpleted. Several
times LC is requested for carrying out work for remaining bay. However, LC is
awaited from SLDC.
Pending
78/I/1 Complete Outage of 220 kV
Varahi UGPH.
24-08-2018 at
11:00 hrs
Due to suspected mal-operation of 220KV bus bar
protection at Varahi, all the connected lines and
Varahi running Units got tripped. (6 nos 220kV
lines and 4 nos Varahi generating station running
Units). This resulted in complete outage of 220kV
Varahi UGPH
1. KPCL to take steps to put double-bus operation into service at their 220 kV
Varahi UGPH by December, 2018.
2. KPCL to employ correct operational practices like keeping DC fuses of B/C
CB intact during bus changeover works, disabling back-up protections of B/C
CB during bus changeover works & enabling them with proper settings only
when it is used as Main-CB of the grid elements.
KPCL KPCL mail dated 20.12.2018 & 23.01.2019:
1. Retrofitting of 220kV Bus Isolators is under progress. Proposed to be in service
after April-2019 --- Pending
2. ---- Completed.
KPCL mail dated 23.03.2019:
1) Retrofitting of 220kV Bus Isolators is under progress. Proposed to be in
service after April-2019
KPCL mail dated 10.05.2019:
4 Set of Isolators of VS1, VS2 & VM2 bay of North Bus were cmpleted.
Remaining bays will be completed after Concurrence of LC from LDC.
KPCL mail dated 25.06.2019 & 16.07.2019 & 30.10.2019:
4 Set of Isolators of VS1, VS2 & VM2 bay of North Bus were cmpleted.
Remaining bay will be completed after monsoon season i.e during November -
2019
KPCL mail dated 17.12.2019 and 11.02.2020
4 Set of Isolators of VS1, VS2 & VM2 bay of North Bus were cmpleted. Several
times LC is requested for carrying out work for remaining bay. However, LC is
awaited from SLDC.
Pending
KPCL mail dated 10.03.2019:
1) Preparation of technical specification is completed. Tender will be floated
during 3rd week of May- 2019 for control & protection system along with
SCADA.
2) English Electric make static type relay is used for NPS protection system at
Unit no.2. The detailed report shall be furnished shortly.
KPCL mail dated 25.06.2019:
1) Preparation of technical specification is completed. Tender will be floated
during 1st week of July 2019 for control & protection system along with SCADA.
2) Existing relays are English Electric Static typeKPCL mail dated 16.07.2019:
1) Tender published on 21.06.2019. Time line for completion of Work is Dec-
2020.
2) Completed.
KPCL mail dated 30.10.2019 & 17.12.2019 & 11.02.2020:
1) Tender published on 21.06.2019. No bids received for the tender. Hence, it is
proposed to refloat fresh tender with revised PQR and scope of work. Avaialing
approval in this regard is in progress.
2) Completed.
KPCL to take steps to replace the existing static protection relays for Generator
Units and Generating Transformers (GT’s) with suitable Numerical relays at
their 220 kV Kadra PH.
While de-synchronising of Unit-2, B-phase pole of
GCB did not open and pole descrepancy relay
operated. Hence all 220KV lines CB hand tripped.
1) KPCL to ensure that DR and EL for all events are made available. If Static
relays with no DR are present in Station, standalone Disturbance recorder and
Event logger should be provided.
2) KPCL to investigate the operation of Negative sequence relay and report to
SRPC since the operation of Negative sequence relay due to stuck breaker
condition is not proper as per protection philisophy
82/I/3 KPCLComplete Outage of 220kV
Kadra Power House of
KPCL & 220kV Karwar SS
of KPTCL
69/II/8 Tripping of 220 kV Kaiga-
Kadra line-1
Pending
Pending06-10-2017 at
22:22 hrs
During de-synchronising of Kadra unit#2, R-pole
didn’t open due to struck breaker condition. Pole
Discrepancy operated. All the connected 220kV
lines at Kadra end were hand tripped.
04-02-2019 at
20:19 hrs
KPCL
Annexure-II
Page 16 of 39
87/I/3 Complete Outage of 220kV
Kemar, MSEZ,
Puttur&Kavoor stations of
KPTCL
29-09-2019 at 11:31
hrs
a. Single line to ground fault occurred in 220kV Kemar –
Varahi line-2 due to R-phase insulator flashover and the line
tripped on Zone-1 distance protection. Simultaneously, 220kV
Kemar – Varahi line-1 tripped at Kemar end only.
b. 220kV Kemar –Varahi line-3 tripped due to overloading.
This resulted in complete loss of supply at 220kV Kemar since
all the three source feeders tripped.
c. In addition there was complete loss of supply at 220kV
MSEZ, 220kV Kavoor and 220kV Puttur stations since these
stations were radially fed from 220kV Kemar station.
KPCL to check A/R functionality for all lines emanating from 220 kV Varahi GS and submit a
report regarding the same.
KPCL Yet to be informed Pending
Mail received on 28-04-2015:
1. In view of operating 220kV Ambewadi SS in split bus mode, action is being
taken up by KPTCL. Problem in the 220kV bus coupler breaker is attended and
isolator overhauling work is under progress. Spilt bus operation at Ambewadi
will be made possible at the earliest. --- Pending
2. ICT Protection system at Ambewadi and trippings occured at Supa GS during
the instance is checked up and remedial measures already furnished in this
regard. KPTCL Mail dated 16.12.2017 & Review Meeting dated 19.12.2017:
1. Recommended works at Ambewadi have not been taken up due to various
problems faced due to poor response from the turn key agency M/s ERL. A site
meeting is planned during this month to discuss about further plan of action for
attending SRPC recommendations pertaining to the Sub station.
The issue was discussed in the review meeting. Considering the importance of the
substation and delay in executing the works, it was decided to escalate all
pending issues relating to Ambewadi SS to KPTCL top Management for early
completion.
KPTCL mail dated 20.12.2018:
1. The outstanding protection issues pertaining to Ambewadi were appraised to
the management and proposal for construction of new GIS SUb stations has been
approved by KPTCL management. In view of attending protection audit
recommendations pertaining to Ambewadi SS without linking with new Station
proposal, action has been taken to include the works in extended scope of R&U
project awarded to M/s GE T&D India Limited. Addition materials required are
yet to be supplied by M/s GE.
Review meeting on 27.06.2019:
1. KPTCL will inform the status on progress of work.
KPTCL mail dated 12.02.2020:
1. BBP provided at Ambewadi SS. - Completed
Mail received on 28-04-2015:
Procurement of Bus bar and LBB protection is in the final tendering stage. 2.
Action is being taken to restore the carrier protection for 220kV Sedam-Tandoor
line. AR will be enabled.
Mail received on 29-07-2015:
1. Procurement of Bus bar and LBB protection is in the final tendering stage.
2. Action is being taken to restore the carrier protection for 220kV Sedam-
Tandoor line. AR will be enabled after restoration of PLCC.
KPTCL mail received on 23-01-2016:
1. Bus bar protection panels pocured and erected at Sedam. Wiring , testing
,commissioning is being taken up.Planned to complete by April 2016.
2. Action is being taken to restore the carrier protection for 220kV Sedam-
Tandoor line. AR will be enabled after restoration of PLCC.
KPTCL Mail recieved dated 22-11-2017:
1 & 2). Bus Bar Protection panel and required Wave traps are supplied under
R&U. Wave trap to be commisioned in Tandoor line and PLCC to be
restored.Once PLCC is restored AR will be enabled. The Wave traps required are
supplied under R&U project and the same is to be commisioned at Sedam end for
restoration of PLCC.
KPTCL Mail dated 16.12.2017:
1 & 2) Replacement of Bus Bar Protection is included under R&U project.
Awarded to M/s GE Ltd. Panels have alredy been supplied by the Agency. The
work will be taken up on top priority.
Review Meeting dated 19.12.2017:
KPTCL informed that the works relating to put A/R in service are going on at
their Sedam SS, and assured that it would be put into service by February, 2018.
KPTCL mail dated 20.12.2018:
1). Bus Bar Protection Work is under progress. Work will be completed in 2
months.
---- Pending
2). ---A/R was enabled from Sedam end on 03.11.2018 ----Completed.
Review meeting on 27.06.2019:
1. Timeline - September 2019
2. Completed
GD-1 at 220kV Ambewadi
Station of KPTCL
Complete outage at 220kV
Sedam Substation of
KPTCL (GD-1)
Triggering incident was B-phase to earth fault in
220kV Ambewadi- Nagzari line-1. B-pole of breaker
did not open at Ambewadi end. LBB protection not
available at Ambewadi end. All elements tripped on
Zone-2 from remote ends.
22-12-2014
at 21:22 hrs
40/I/1
R-Phase to ground fault occurred on 220kV Sedam-
Shahpur line. Fault not cleared from Sedam end due
to stuck-breaker condition. While the Sedam-
Sahapur line tripped from Shahapur end in Zone-1,
the other 220 kv lines from Sedam tripped at remote
ends in Zone-2. This caused complete outage of
220kV Sedam substation.
27-01-2015 at
8.00 hrs
41/I/4
1. Till the completion of R&M works for bus bar and LBB protection, KPTCL
shall explore the possibility of having split bus operation at Ambewadi and
submit the details of the same to PCSC forum.
2. KPTCL shall provide the details of the tripping of Supa hydro station
connected downstream from 110 kV bus.
Pending 1. Status?KPTCL 1. KPTCL to provide Bus bar and LBB protections for 220 kV bus at Sedam
S/s.
2. KPTCL to implement A/R feature on 220 kV Sedam-Tandur inter-state
line.
KPTCL Pending
Annexure-II
Page 17 of 39
KPTCL mail dated 12.02.20220:
1. The work is under progress, expected to be put in to service before end of
February 2020
2. AR was implemented. But due to problem with single phase trip relays the
same was disabled. Now the same has been attended and expected to be put in to
service before end of February 2020
R-Phase to ground fault occurred on 220kV Sedam-
Shahpur line. Fault not cleared from Sedam end due
to stuck-breaker condition. While the Sedam-
Sahapur line tripped from Shahapur end in Zone-1,
the other 220 kv lines from Sedam tripped at remote
ends in Zone-2. This caused complete outage of
220kV Sedam substation.
27-01-2015 at
8.00 hrs
41/I/4 Pending 1. Status?KPTCL 1. KPTCL to provide Bus bar and LBB protections for 220 kV bus at Sedam
S/s.
2. KPTCL to implement A/R feature on 220 kV Sedam-Tandur inter-state
line.
Annexure-II
Page 18 of 39
Mail received on 27-05-2015:
1. Bus Bar protection will be provded under R&U.
2. A/R yet to be enabled.
Mail received on 29-07-2015:
1. Procurement of Bus bar and LBB protection is in the final tendering stage.
2. Action is being taken to restore the carrier protection for 220kV Sedam-
Tandoor line. AR will be enabled after restoration of PLCC.
KPTCL Mail Recieved dated 22-11-2017:
Bus Bar Protection panel and required Wave traps are supplied under R&U.
Wave trap to be commisioned in Tandoor line and PLCC to be restored.Once
PLCC is restored AR will be enabled.
KPTCL Mail dated 16.12.2017:Review meeting on 27.06.2019:
1. Timeline - September 2019
2. Completed
KPTCL mail dated 12.02.20220:
1. The work is under progress, expected to be put in to service before end of
February 2020
2. AR was implemented. But due to problem with single phase trip relays the
same was disabled. Now the same has been attended and expected to be put in to
service before end of February 2020
Mail received on 29-07-2015:
1. Procurement of Bus bar and LBB protection is in the final tendering stage.
2. Action is being taken to restore the carrier protection for 220kV Sedam-
Tandoor line. AR will be enabled after restoration of PLCC.
KPTCL Mail Recieved dated 22-11-2017 & 16.12.2017:
1.Enabling the AR feature was discussed during PCSC meetings and since
Ambewadi-Ponda and Ambewadi-Xeldom lines are radial lines, it was decided
that enabling AR is not required. To clear the faults in the abovelines early, the KPTCL mail dated 20.12.2018:
The protection issues pertaining to Ambewadi was appraised to the
management and proposal for construction of new GIS SUb stations has been
approved by KPTCL management. Further as per SRPC directions and in view of
attending protection audit recommendations pertaining to Ambewadi SS without
linking with new Station proposal, action has been taken to include the works in
extended scope of R&U project awarded to M/s GE T&D India Limited. Addition
materials required are yet to be supplied by M/s GE. work expecnted to be
completed in 5 months.
Review meeting on 27.06.2019:
1. Since 220kV Ambewadi -Ponda line is radial, this recommendation is dropped.
2. Timeline will be in timated by KPTCL
KPTCL mail dated 12.02.2020:
1. 220kV line breaker replacement work under progress at Ambewadi. AR will
implemented after replacement of CBs -- Pending
2. BBP provided at Ambewadi -- Completed
42/I/1
42/I/2
(GD)
Complete outage of 220 kV
Ambewadi substation of
KPTCL
12-03-2015 at
7:51 hrs
Fault occurred in 220kV Sedam-Shahpur line15-02-2015
at 14:24 hrs
Complete outage of 220kV
Sedam substation of
KPTCL
Fault in 220kV Ambewadi-Nagjheri line-2
1. KPTCL to provide Bus Bar protection and LBB protection at Sedam S/s and
furnish the status of their implementation to PCSC forum.
2. KPTCL to implement A/R feature on 220 kV Sedam-Tandur inter-state line.
PendingKPTCL
PendingKPTCL1. KPTCL shall provide A/R feature on Ambewadi – Ponda 220 kV D/C inter-
state line.
2. Till the completion of R&M works for bus bar and LBB protection, KPTCL
shall explore the possibility of having split bus operation at Ambewadi and
submit the details of the same to PCSC forum.
Annexure-II
Page 19 of 39
KPTCL mail received on 23-01-2016:
Will be complied in a months time.
KPTCL Mail Recieved dated 22-11-2017:
Enabling the AR feature was discussed during PCSC meetings and since
Ambewadi-Ponda and Ambewadi-Xeldom lines are radial lines, it was decided
that enabling AR is not required. To clear the faults in the abovelines early, the
timings of the Zone 2 was reduced to 150mS and the Back Up EFR timings have
been reducedto 150mS.
KPTCL Mail dated 16.12.2017:
Enabling the AR feature was discussed during PCSC meetings and since
Ambewadi-Ponda and Ambewadi-Xeldom lines are radial lines, it was decided
that enabling AR is not required. To clear the faults in the abovelines early, the
timings of the Zone 2 was reduced to 150mS and the Back Up EFR timings have
been reduced to 150mS. In view of the above, it is requested to drop the issue KPTCL mail dated 20.12.2018:
The protection issues pertaining to Ambewadi was appraised to the
management and proposal for construction of new GIS SUb stations has been
KPTCL KPTCL to fast-track providing A/R on all 220 kV lines emanating from
Ambewadi SS to prevent Station shut-down on temporary faults.
Outage of 220kV
Ambewadi station in
Karnataka
220kV Ambewadi-Nagjheri line-2 tripped on B-
phase to earth fault. This resulted in loss of supply
to 220kV Ambewadi bus. 220kV Ambewadi-Ponda
line-1&2 were hand tripped after deenergization of
bus at Ambewadi.
30-09-2015 at
10:41 hrs
48/I/3 Status?Pending
Annexure-II
Page 20 of 39
KPTCL Mail received dated 25-04-2017:
Replacement of existing BBP by new BBP with 4 zone protection is being taken
up under R&U.
KPTCL Mail Recieved dated 22-11-2017:
GE Ltd has already supplied the necessary Bus Bar protection panels for
replacement of the existing static type BBP by new numerical BBP with 4 zone
protection under R&U project. The work of commissioning the same will be
taken up shortly.
KPTCL Mail dated 16.12.2017:
Due to operational constraints two/ multi bus operation is not being implemented.
Review Meeting dated 19.12.2017:
It was noted that Shimoga SS is having required configuration for providing
double-bus operation. However, due to large no. of feeders (15 in no) with
variable gneration at certain remote ends like Varahi, the flows on these lines are KPTCL mail dated 20.12.2018:
Bus sectionaliser breakers have to be provided for operating Shimoga in multi
bus mode. Estimates have to be prepared by CEE,TZ,Hassan. Work expected to
be completed in 1 year.
KPTCL mail dated 12.02.2020:
After commissioning of numerical BBP bus split trial operation was made.
However for providing more reliability, action is being taken for providing
bussectionaliser breakers.
KPTCL mail received dated 25.04.2017:
Numerical BBP is being provided under R&M works
KPTCL Mail Recieved dated 22-11-2017:
Tesing & Commissioning of numerical BBP at Somanahalli is under progress.
There was some technical issue wth BBP scheme supplied to Somanahally which
is being finalised in consultation with OEM SIFANG. Numerical BBP will be
commissioned at Somanahally within a month's time.
KPTCL Mail dated 16.12.2017:
Numerical Bus Bar protection Scheme will be commissioned at Somanahally
before end of December 2017.
KPTCL mail dated 20.12.2018:
The work of providing Bus Bar Protection to 220kV buses is incuded under
R&M works envisaged at Somanahally. The R&M work is expected to be
completed before end of March 2019 ----- Pending
Review meeting on 27.06.2019:
status of work and timeline will be given by KPTCL
KPTCL mail dated 12.02.2020:
The work is to be executed by the R&M turn key agency
74/I/2 Complete outage of 220 kV
Ambewadi station
02-04-2018 at
13:46hrs
Loss of supply occurred to 220 kV Ambewadi
station due to tripping of 220kV Nagzhari-
Ambewadi line-2 (Source) from Nagzhari power
station. After bus dead, Ambewadi-Ponda lines – 1
& 2 were hand-tripped. In antecedent conditions,
220kV Ambewadi - Nagjheri ckt-1, 220kV
Ambewadi-Narendra Ckt-1 &2 were out of service.
1). KPTCL to review operation of SPS at NPH for proper functionality and
changed network conditions (reduction of generation with tripping of evacuating
lines) and put it into service at the earliest.
2). KPTCL to furnish equipment failure report of the current incident (R-phase
CT in Nagjheri – 1 bay at Ambewadi SS) to PSE&TD Division of CEA with a
copy marked to SRPC.
KPTCL KPTCL mail dated 20.12.2018:
1). To be reviewed. Expected to be completed in 1 month.---- Pending
2), Being followed ----- Pending
Review meeting on 27.06.2019:
1. Nagjheri SPS shall be studied in view of changed system configuration
2. Completed
KPTCL mail dated 12.02.2020:
The logic is being reviewed by SRLDC by conducting system studies for the
changed network configuration
Pending
74/II15 Multiple Trippings at
400/220kV Guttur station
21-04-2018 at
12:50 hrs
Triggering incident was fault in 220 kV Davanagare
- Shimoga line. Bus bar protection operated at
Guttur resulting in tripping of all the connected
elements. 220 kV Guttur was on single bus
operation due to CVT problem in Bus-2.
KPTCL to put double-bus operation at their 220 kV Guttur substations by
attending to Bus-2 CVT problem.
KPTCL KPTCL mail dated 20.12.2018:
Bus-2 CVT problem is attended. However due to breaker replacement works,
220kV side operated in single bus mode.
Review Meeting dated 20.12.2018:
KPTCL informed that double-bus operation at their 220 kV Guttur would be
provided within two months.
Review meeting on 27.06.2019:
Timeline will be communicated by KPTCL
Pending
79/III/9 Tripping of 400 kV JSWEL
–Guttur line
29-09-2018
at 11:30 hrs
R-phase to earth fault occurred in line. Auto-reclose
was not attempted at JSWEL due to DT receive. At
Guttur end auto-reclose could not be validated with
DR/EL.
KPTCL to furnish a detailed report on tripping event bringing out reasons for
DT sending from Guttur end to JSWEL on 400 kV Guttur - JSWEL line along
with remedial action taken to PCSC forum.
KPTCL Review Meeting on 21.12.2018:
KPTCL was aksed to furnish status of implementation of the recommendation
given at the earliest.
Review meeting on 27.06.2019:
report will be submitted by KPTCL
Pending
62/II/5 PendingKPTCLKPTCL to provide numerical Busbar Protection at their 220 kV Somanahalli SS
at the earliest.
Triggering incident was fault in 66 kV Somanahalli -
Bannerghatta line and fault was cleared by operation
of Back-up OCR at Somanahalli end.
52/I/3 Complete outage of 220 kV
Shimoga substation
20-01-2017 at
14:34 hrs
Tripping of 220 kV South
Bus and connected
elements (220kV HSR,
220kV Nagnathpura, 220
kV Harohalli, 220 kV
Subramanyapura, 220 kV
Tataguni, 220 kV Mallur
and 400/220kV ICT-2 and
3) at 400/220kV
Somanhalli substation of
KPTCL
(Load loss: 850 MW)
KPTCLKPTCL to operate 220 kV Shimoga on multi-bus operation under normal
conditions, and put it on single-bus operation only under emergency conditions.
220kV Bus Bar protection operated during failure of
R phase CT in DVG-2 line bay.
22-02-2016 at
15:03 hrs
Pending
Annexure-II
Page 21 of 39
80/II/7 Tripping of 400 kV JSWEL-
Guttur line
17-10-2018 at
02:04 Hrs
Triggering incident was R-phase to earth fault in
line. At Guttur end there was operation of pole
discrepancy and resulted on tripping of Y & B pole
after a duration of 2 seconds from the occurrence of
fault. FIR, DR & EL of Guttur end were not
furnished.
KPTCL to examine the reasons for sending of DT from Guttur end to JSWEL
end, and furnish an action taken report including remedial measures taken to
rectify the same.
KPTCL Review meeting on 27.06.2019:
report will be submitted by KPTCL
Pending
82/I/4 Complete Outage of 220kV
Ambewadi Station of
KPTCL
06-02-2019 at
14:51hrs
Fault occurred while test charging of 220kV
Ambewadi – Nagjheri Line -2 from Ambewadi end.
Suspected stuck breaker condition at Ambewadi
end) led to clearing of fault by tripping of remote
end breaker in Zone-2. LBB protection is not active
at 220kV Ambewadi station.
KPTCL to investigate the reason for non-tripping of 220kV Ambewadi -
Nagjheri line-2 on operation of SOTF and submit a report regarding the same to
SRPC. Also KPTCL to take necessary measures in order to ensure healthiness of
breaker before testcharging of any line.
KPTCL Review meeting on 27.06.2019:
report will be submitted by KPTCL
Pending
82/II/12 Tripping of 400kV Kaiga-
Guttur line-1&2
07-02-2019
at 11:49 hrs
Line-1 tripped due to insulator flashover. Line-2
tripped due to zone-3 operation at Kaiga and Direct
trip receive at Guttur
KPTCL is recommended to take necessary measures to ensure that Main-I and
Main-II at Guttur end shall be of different types (make and model) coherent with
the general protection philosophy followed in SR region.
KPTCL Review meeting on 27.06.2019:
KPTCL informed that the recommendation has been included as part of R & M
work. Timeline will be informed
Pending
84/II/12 Tripping of 400kV DHONI
GUTTUR line- 1
18-04-2019 at
18:59 hr.
Triggering incident was failure of B-ph CB of
400kV Dhoni-Guttur line at Dhoni end. This
resulted in the operation of LBB of bus-1 and DT
was sent to Guttur end
1. KPTCL to send equipment failure report, corresponding to the failed CB at
Dhoni SS, to CEA.
2. KPTCL to ensure time synchronization at Guttur end.
KPTCL Yet to be informed Pending
84/II/16 Tripping of 400 kV
Nelamangala-Mysore line-2
01-05-2019 at 02:29 hr.Line tripped on operation of over voltage stg-2 at
Nelamangala end
KPTCL to ensure time synchronization of DR and EL with GPS signal at
Nelamangala end.
KPTCL Yet to be informed Pending
84/II/24 Tripping of 400/220 kV
ICT-1&3 at Hoody
Substation
13-05-2019 at
15:35 hr.
ICT-3 tripped on operation of 59N neutral
displacement relay. ICT-1 tripped on OCR.
KPTCL to inform PCSC forum regarding the changes implemented in Hoody
ICT SPS and to ensure time synchronization of relays at Hoody SS.
KPTCL Yet to be informed Pending
85/I/4 Tripping of 220kV Sedam-RTPS
line-1&2 and 220kV Sedam-
Tandur line
14-06-2019
at 02:00 hrs
Tripped on Directional Earth Fault indications in
Main-2 relay at Tandur end for fault at Raichur end.
Sedam end details not furnished.
1. KPTCL is recommended to enable A/R on all lines emanating from 220kV
Sedam SS.
2.KPTCL is recommended to commission BBP at 220kV Sedam SS
immediately.
KPTCL KPTCL mail dated 12.02.20220:
The work is under progress, expected to be put in to service before end of
February 2020
Pending
85/II/5 Tripping of 400/220 kV ICT-3 at
Nelamangala substation19-05-2019
at 16:11 hrs
As per FIR, ICT-3 got tripped on operation of High
Set Over current trip on 400kV side
1. KPTCL is recommended to enable auto-reclosure on all lines emanating
from 400/ 220kv Neelamangala SS and to ensure time synchronization of relays
at Neelamangala SS.
KPTCL Yet to be informed Pending
85/II/11 Tripping of 400kV Hoody-
Yelahanka line-125-05-2019
at 20:41 hrs
Line tripped at Hoody end only and was holding
from Yelahanka.
KPTCL is recommended to check the spurious operation of SOTF protection at
Hoody SS and submit a report to SRPC regarding the same .
KPTCL Yet to be informed Pending
85/II/12 Tripping of 400/220 kV ICT-1at
Guttur Substation26-05-2019
at 10:00 hrs
LV side of 400kV/220kV 315MVA ICT#1 Guttur
got tripped due to CB lockout (B phase)because of
low SF6 gas in the CB
1. KPTCL is recommended to submit a report to SRPC after the CB pressure
leakage problem is attended by OEM.
2.. KPTCL to ensure that during recharging of Circuit breakers, cylinders with
Non-return valve only are used to prevent sudden pressure drop in Circuit
breakers.
KPTCL Yet to be informed Pending
85/II/22 Tripping of 400kV Dhoni-
Munirabad line06-06-2019
at 02:01 hrs
Line got tripped at Dhoni end. From DR Zone-3
start, PSB and A/r block was observed.
KPTCL is recommended to submit a report regarding PSB maloperation along-
with the RM suggested by OEM. Proper legends shall be ensured for digital
signals at Doni end.
KPTCL Yet to be informed Pending
85/II/27 Tripping of 400/220kV ICT-2 at
Hoody substation16-06-2019
at 19:20 hrs
ICT-2 got tripped on operation of over-flux
protection
KPTCL is recommended to adopt v/f settings as per manufacture suggested
curve.
v/f setting for alarm: 1.1 time Vnominal; Time delay 10 seconds;
v/f trip setting : v/f is 1.2 time Vnominal;Time delay 60 seconds
KPTCL Yet to be informed Pending
Annexure-II
Page 22 of 39
85/II/29 Tripping of 400kV Hiriyur-
Nelamangala line-1 and 400kV
Gooty-Nelamangala line
22-06-2019 at
04:06hrs
400kV Hiryur-Nelamangala line-1 : 'Y' phase
bushing of Hiriyur line-1 reactor failed at
Nelamangala end resuting in a R-Y phase fault.
Direct trip was sent to Hiryur.
400kV Gooty-Nelamangalaline : Line tripped at
Nelamangala end only due to mal-operation of Main-
2 distance protection relay (THR).
KPTCL is recommended to submit equipment failure report to CEA regarding
the reactor bushing failure and also to sort out time synchronization issues of
400kV Hiriyur-Nelamangala line.
KPTCL Yet to be informed Pending
85/II/30 Tripping of 400/220kV ICT-1&2
at Munirabad substation24-06-2019
at 20:50 hrs
400/220kV ICT-1&2 at Munirabad end got tripped
due to operation of High set of backup earth fault
relay during failure of Y phase CT in 220kV
Munirabad-Kalyani steel feeder at Kalyani steel end
KPTCL is recommended to submit equipment failure report to CEA regarding
the CT and PT failure.
KPTCL Yet to be informed Pending
86/II/9 Tripping of 400 kV Neelamangala-
Mysore line-2
15-07-2019
at 2:02 hr
line tripped on operation of OV st-1 protection at
Neelamangala end and DT was received at Mysore end. DR of
Nelamangala end was not available for validation of OV
protection operation
KPTCL to configure both OVR start and OVR trip in DR or EL at 400 kV Neelamangala SS. Time
sync issues at 400 kV Neelamangala SS shall also be sorted out immediately.
KPTCL KPTCL mail dated 30.10.2019:
DR triggering has been done for OVR stage-1 operation in Mysore-2 line . GPS time
synchronisation of Power Grid bays will be taken up along with panel replacement work
envisaged under R&M.
OVR_start also to be configured.
Pending
Annexure-II
Page 23 of 39
KPTCL Mail Recieved dated 22-11-2017:
1. coordination of KPCL has been requested for enabling AR lines terminated to
Nagajari.
2. AR will be enabled at Ambewadi end for lines other than Ponda and Xeldom
lines during retrofitting of Back Up protection by Distance protection relay at
Ambewadi.
KPTCL Mail dadted 16.12.2017 & Review Meeting dated 19.12.2017:
1. KPTCL informed that Coordination of KPCL has been requested for enabling
AR lines terminated to Nagajari.
--- Pending
2. KPTCL informed that AR would be enabled at Ambewadi end for lines other
than Ponda and Xeldom lines during retrofitting of Back Up protection by
Distance protection relay at Ambewadi. -- Pending
KPTCL mail dated 20.12.2018:
2). Readiness from KPTCL for implementing AR is already confirmed to KPCL.
Decision pending from KPCL end.
KPCL mail dated 23.03.2019:
1) Proposal will be taken up for replacement of existing PZ1000 relays with new
version Numerical Line protection relays having IEC61850. Prepration of
specification is under progress.
KPCL mail dated 13.05.2019:
1) Budgetary offer obtained for replacement of existing PZ1000 relays with new
version Numerical Line protection relays having IEC61850. Preparation of
estimation and specification is under progress.
KPCL mail dated 25.05.2019 & 16.07.2019:
1) Replacement of existing PZ1000 relays with new version Numerical Line
protection relays having IEC61850 is included in PSDF Phase-II DPR. Approval
of NLDC for DPR is awaited. Further, availing administrative approval for issue
of NIT for replacement of existing PZ1000 relays with new version Numerical
Line protection relays having IEC61850 and preparation of estimation and
specification is under progress. Timeline for completion of work is July 2020.
KPCL mail dated 30.10.2019
1) Replacement of existing PZ1000 relays with new version Numerical Line
protection relays having IEC61850 is included in PSDF Phase-II DPR. Approval
of NLDC for DPR is awaited. NIT issued through e-portal on 16.09.2019. Pre-
bid meeting was held on 10.10.2019. Finalising of replies to pre-bid queries is in KPCL mail dated 17.12.0219 and 11.02.2020:
1) ) Replacement of existing PZ1000 relays with new version Numerical Line
protection relays having IEC61850 is included in PSDF Phase-II DPR. Approval
of NLDC for DPR is awaited. NIT issued through e-portal on 16.09.2019. Cover-
1 opened on 02.12.2019. Technical evaluation is in progress.
Status informed during Special Meeting held on 03.06.2016:
1. KPTCL informed that the matter had been taken up with concerned Line
Operation and Maintenance wing to carry out corridor clearance and maintenance
as per schedule to avoid frequent line faults in this corridor. A letter had also
been addressed to Chief Engineer, Bhagalkot zone, to ensure lines in & around
Kali complex are maintained in healthy condition. --- Completed
2. KPTCL assurd that the final modified SPS would be implemented at Nagjheri
PH at the earliest. ------ Pending
3. KPCL informed that Nagjhari- Kodasalli Lines 1 & 2 had been kept in service
since 23.05.2016 @ 08.06hrs.
--- Completed
KPTCL Mail received dated 28-06-2016:
2. Modifications to be carried in Nagzari SPS logic is submitted to
SRLDC/SRPC for verification and approval
Status received vide KPCL mail dated 14.06.2017:
1. Will be reviewed in consultation with EE(RT), KPTCL, Hubli.
3. Both the lines are in charged condition.
KPTCL Mail Recieved dated 22-11-2017:
1) & 3) --- Completed
2). Proposed revision in existing SPS scheme is already submitted to
SRLDC/SRPC., Yet to be discussed and approved by the SRPC forum. --- KPTCL Mail dated 16.12.2017:
1) & 3). --- Completed.
2). Proposed revision in existing SPS scheme is already submitted to
SRLDC/SRPC., yet to be discussed and approved by the SRPC forum ---
PendingKPCL mail dated 16.07.2019:
1 & 3) Completed.
2) Letter addressed to KPTCL RT dated: 25.03.2019 for review and
implementation of SPS at NPH. Reply from KPTCL is awaited.
KPCL mail dated 30.10.2019 and 17.12.2019 and 11.02.2020:
1 & 3) Completed.
2) KPTCL informed that Naghjeri SPS need to be revisited in view of changes in
system configuration. Reply from KPTCL is awaited
KPTCL mail dated 12.02.2020:
1 & 3) Completed.
2. The logic is being reviewed by SRLDC by conducting system studies for the
changed network configuration
220kV Nagjheri-Ambewadi line-1 tripped at 13:33
hrs due to B phase to earth fault. Ambewadi was
radially fed from Nagjheri power station through
220kV Nagjheri-Ambewadi line-2. Tripping of this
line caused 220kV Bus shut down at Ambewadi and
remaining lines and transformers were hand tripped
51/I/3
Complete outage of 220kV
Ambewadi Substation of
KPTCL
220kV lines from Nagjheri power house started
tripping from 11:00 hrs due to fault in lines. The
sequence of tripping is shown in SOE list. At 12:33
hrs, 220kV Narendra-Ambewadi lines-1&2 got
tripped which resulted in loss of evacuation path to
Nagjheri station resulting in tripping of running
Units and complete outage at Nagjhheri power
station. 220kV Ambewadi station also got de-
energized due to tripping of source feeders i.e.
220kV Narendra-Ambewadi-1&2 and 220kV
Nagjheri-Ambewadi-1&2.
Complete outage of 220 kV
Nagjheri power station and
220 kV Ambewadi
substation of KPTCL
49/I/3 29.10.2015 at
14:34 hrs
Pending
1. To avoid tripping of transmission lines on transient faults, KPCL/ KPTCL is
recommended to carry out periodic patrolling of lines, and ensure their proper
maintenance by carrying out jungle/ bushing clearance and trimming of tree
branches within the RoW of transmission lines as per the SRPC transmission
line patrolling guidelines (available under the menu item "All Uploads/
Operation/ Miscellaneous/ Transmission Line Patrolling Protocol / Guidelines
for Southern Region" on SRPC website).
2. KPCL/ KPTCL to review operation of SPS at NPH for functionality
(reduction of generation with tripping of evacuating lines) and healthiness.
3. KPCL to put 220 kV Kodasalli - Nagjheri D/C lines into service if more than
200 MW generation from Kali Complex (with Nagheri Contribution not less
than 50 MW) is ensured on sustained basis.
PendingKPCL/ KPTCL22-02-2016 at
12:36 hrs
KPCL/ KPTCL1. KPCL to provide A/R on all 220 kV lines emanating from Nagjheri PH.
2. KPTCL to provide A/R on all 220 kV lines emanating from Ambewadi SS.
Annexure-II
Page 24 of 39
KPCL mail dated 23.01.2019 & 23.03.2019:
1) …Completed.
2) It shall be reviewd and Implemented by KPCL in coordination with KPTCL.
3) …Completed.
KPCL mail dated 10.05.2019 & 25.06.2019:
1. & 3. Completed
2) Letter addressed to KPTCL RT dated: 25.03.2019 for review and
implementation of SPS at NPH. Reply is awaited.
Review meeting on 27.06.2019:
2. KPTCL informed that Naghjeri SPS need to be revisited in view of changes in
system configuration.
KPCL mail dated 16.07.2019 & 30.10.2019 & 17.12.2019 & 11.02.2020:
1 & 3) Completed.
2) Letter addressed to KPTCL RT dated: 25.03.2019 for review and
implementation of SPS at NPH. Reply from KPTCL is awaited.
KPTCL mail dated 12.02.2020:
1. & 3. Completed
2. The logic is being reviewed by SRLDC by conducting system studies for the
changed network configuration
87/II/25 Tripping of 400 kV
Nelamanagala-Mysore line-2
28-09-2019 at 1:38
hr.
Line tripped on operation of over voltage stg-2 protection at
Nelamangala and direct trip received at Mysore
KPTCL to ensure relay pickup to drop off ratio of 0.98 and above for relays configured for
overvoltage protection.
KPTCL Yet to be informed Pending
88/II/13 Tripping of 400kV Talaguppa
–Nelamangala line
19-10-2019 at 16:22
Hr.
Line tripped on operation of OV St-1 protection at
Nelamangala end and DT was sent to Talaguppa end.
KPTCL to configure OVR_start in DR or EL and to sort out time synchronization issues between
Talaguppa and Nelamanagala ends.
KPTCL Yet to be informed Pending
88/II/14 Tripping of 400/220kV ICT-2 at
Guttur
22-10-2019 at 02:12
Hr.
ICT#2 at Guttur got tripped on operation of Buchholz
protection due to suspected moisture entry during rain.
KPTCL to provide shielding for Buchholz relay to prevent such mal-operations. KPTCL Yet to be informed Pending
89/1/1 Complete loss of supply at 220
kV Hubli SS, 220 kV Bidnal SS
of KPTCL and 220 kV Nagjheri
GS of KPCL
14-12-2019 at 10:56
Hr.
• Triggering incident was fault in 220 kV Hubli-Narendra Line-
2.
• Due to cascaded tripping of connected lines and loss of
evacuation, there was complete loss of supply at:
220 kV Hubli SS &
220 kV Bidnal SS of KPTCL and
220 kV Nagjheri GS of KPCL
i. KPTCL to ensure A/R is in service in all 220 kV lines emanating from 220kV Hubli SS and
220kV Bidnal SS.
ii. KPTCL was requested to ensure proper planning of outages of transmission lines (i.e., outage
planning should be as per N-1 contingency planning and not to cause stress on the system to
avoid complete outages due to fault in the Nagjhari- Hubli corridor.
iii. KPTCL to explore the possibility of split bus operation at 220 kV Hubli SS, in the event of
outage of any of the 220 kV Hubli – Narendra line, to prevent overloading of other line (Narendra
line) and 220kV Bidnal – Narendra line.
iv. KPTCL to submit the SPS for shedding of loads planned at 220kv Hubli SS.
v. KPTCL to expedite finalization of SPS at 220kV Nagjheri SS considering LILO of one circuit
of 220kV Haveri-Narendra line at Bidnal as part of RE evacuation and submit the study to SRPC
and SRLDC for scrutiny/ finalisation.
vi. KPTCL to ensure time synchronization of relays at 220kV Hubli, 220kV Bidnal, 220kV
Soundatti and 220kV Harthi.
vii. KPTCL to explore the possibility of conductor strengthening in Nagjheri – Hubli- Bidnal and
surrounding areas.
KPTCL Yet to be informed Pending
1. KPCL to furnish a report on the reasons for Unit-6 tripping at Nagjheri PH.
2. KPCL/ KPTCL to modify suitably the SPS at Nagjheri Power House such that
it would also factor in the over loading of Ambewadi-Narendra lines.
3. KPCL to put 220 kV Kodasalli - Nagjheri D/C lines into service if more than
200 MW generation from Kali Complex (with Nagheri Contribution not less
than 50 MW) is ensured on sustained basis.
Complete outage of 220kV
Ambewadi station of
KPTCL and 220kV
Nagjheri of KPCL
18-03-2016 at
14:40 hrs
KPTCL Mail received dated 28-06-2016:
Modifications to be carried in Nagzari SPS logic is submitted to SRLDC/SRPC
for verification and approval
Status received vide KPCL mail dated 14.06.2017:
1. Tripped since there was evacuation problem and there were only two lines NA-
1 and NA-2 ---- Completed
2. Will be reviewed in consultation with EE(RT), KPTCL, Hubli. --- Pending
3. Both the lines are in charged condition. --- Completed.
KPTCL Mail Recieved dated 22-11-2017:
2. Proposed revision in existing SPS scheme is already submitted to
SRLDC/SRPC., yet to be discussed and approved by the SRPC forum. ---
Pending
KPTCL Mail dated 16.12.2017:
1) & 3). --- Completed.
2). Proposed revision in existing SPS scheme is already submitted to
SRLDC/SRPC., yet to be discussed and approved by the SRPC forum ---
Pending
Review Meeting dated 19.12.2017:
2. The SPS proposed by KPTCL was discussed and the PCSC forum suggested
certain changes for suitable incorporation. KPTCL agreed to look into the same
and assured that the modified SPS would be furnished by January, 2018.
Review Meeting on 21.12.2018:
KPTCL informed that Nagjheri SPS shall be finalised in 1 month.
53/I/3 Ambewadi Narendra line-2 tripped on fault and
220kV ambewadi Narendra line-1 tripped due to
over-loading. Running Units at Nagjheri also tripped
during the event due to tripping of evacuating lines
PendingKPCL/ KPTCL
Annexure-II
Page 25 of 39
89/1/2 Complete loss of supply at 220
kV Shimoga SS of KPTCL.
25-12-2019 at 17:44
Hr.
Triggering incident was line to line fault in 220 kV Shimoga-
Sharavathi line -4.
Bus-1 Bus bar protection operated at 220 kV Shimoga
resulting in complete loss of supply since all the elements were
connected to Bus-1 during antecedent conditions.
i. KPTCL to ensure Double Bus operation at 220 kV Shimoga SS to ensure reliability to prevent
complete outage of Substation.
ii. KPTCL, in coordination with KPCL, to enable A/R in 220 kV Shimoga – Sharavathy lines.
KPTCL Yet to be informed Pending
89/II/5 Tripping of 400/220 kV ICT-1 at
Talaguppa of KPTCL
13-12-2019 at 16:27
Hr.
· During replacement of 220 kV faulty relay ICT-1 at
Talaguppa tripped without any relay indication.
KPTCL to instruct substation maintenance personnel to be cautious while carrying out
maintenance activities, so that similar trippings could be avoided.
KPTCL Yet to be informed Pending
89/III/1 Tripping of 400kV Kaiga –
Guttur Line-2
11-10-2019 at 08:49
Hr.
And
26-10-2019 at 12:42
Hr.
• Triggering incident was Y phase to Earth fault in the line.
• At Kaiga end, fault was detected in zone-1, A/r operated
successfully.
• At Guttur end, fault was sensed in zone-1 and A/r not
operated.
• Non operation of A/r at Guttur end needs review.
• KPTCL to study the A/R block signal issued due to misinterpretation of single phase fault as
multi phase fault by distance relay (P442) and take suitable remedial actions.
KPTCL Yet to be informed Pending
Mail dated 18.07.2019
2) Tender has been lodged two times. New indent was reaised on 06.07.19. and
tender floating is expected by August 2019. 3) Tender has
been lodged on 15.07.19 and new indent would be raised for the same shortly.
TANGEDCO mail dated 17.12.2019 and 12.02.2020:
2) e - tender has been opened on 26.11.19 and placing of purchase order is
expected by January 2020.
3) New Indent was raised on 26.08.19 and procurement is undr progress.
TANGEDCO mail dated 12.02.2020:
2)For busbar protection relays: Placing of purchase order is expected by the end
of this month and delivery period is 80 days from the date of issuing of PO.After
the supplying of materials, the replacement work will be taken up during possible
230kV Bus LC. --Pending
3) For Stanalone Disturbance Recorder: Specification approval has been sought
from our HQ for floating of the tender on 23.12.2019. Again,Reply was sent on
03.02.2020 for the clarification raised by HQ. After obtaing of the approval from
HQ, tender will be floated. - Pending
1. TANGEDCO to replace existing Check-Zone relay with a new one possessing
required performance.
2. TANGEDCO to take steps to provide numerical busbar protection at their 220
kV Tuticorin TPS. TANGEDCO may also explore providing dual CT’s (on
either side) for all B/S breaakers at the time of commissioning of numerical
BBP, if there were no space constraints.
3. TANGEDCO to take steps to provide for standalone Event Logger (EL) and
standalone Disturbance Recorder (DR) with automatic downloading facility to a
centralized server.
Failure of Bus Section-I Y-ph CT resulted in
operation of bus-bar protection for Bus Sections -I &
II. Running Units#1, 4 and 5, 230 kV Kayathar,
230kV Kudankulam, 230kV Sterlite, Station
Transformer-1, 2 & 3 got tripped during the
incident. Unit – 2 & 3 were not in service.
Tamil Nadu
62/II/7 25-01-2017 at
22:36 hrs
Tripping of running Units
& 230kV feeders at
Tuticorin TPS of
TANGEDCO
(Gen Loss: 640 MW)
PendingTANGEDCO mail dated 15.04.2017:
1) New Relay is tested and ready for replacement.Now all 5 units are in
service.The relay will be replaced when lesser units are in service. --- Pending
2.a)Steps are taken to renovate & mordernization of all the control panel into
Numerical based control panels. --- Pending
2.b) Since 230 KV indoor switchyard has no spare space providing dual CT`s is
not fessible. -- Completed
3) Procurement of EL & DR is under progress. --- Pending
TANGEDCO mail dated 26.04.2017:
1) Check zone New Relay is replaced on 17.04.2017 -- Completed.
2. --- Pending
3. --- Pending
TANGEDCO mail dated 13.12.2017:
2).P & C wing gives clearance to TTPS to procure the Bus bar protection relays
and protection relays and SER / DR system vide
Lr.CE/P&C/SE/D/EEPC4/AEE3/F.TECH/D.27/17 Dated: 05.10.2017. To get
administrative approval budgetary offer has bar protection relay from various
companies ----Pending
3). SRPC vide Lr: SRPC/SE- III/CEA/2017/6450/DT:27.10.2017 gives features
of SER/DR. Budgetary offer will be called for SER / DR having above features.
---Penidng
Review Meeting dated 19.12.2017:
2) & 3) The issue was discussed and TANGEDCO was asked to provide time-line
for implementing the recommendations.
Mail dated 29.01.2018:
Procurement work is under progress and will be completed by December 2018.
Review Meeting on 21.12.2018:
TANTRANSCO informed that Tender would be floated by January 2019 and
Procurement is expected by APril 2019. Works would be completed by December
2019.
Review meeting on 27.06.2019:
2. Tender issued. Timline- July 2020.
3. Tender has to be issued. Timline- July 2020.
TANGEDCO Status?
Annexure-II
Page 26 of 39
TANTRANSCO Mail received on 19-02-2016 and 24-03-2016:
Revision of Bus Bar Protection setting was carried out. The stabilizing voltage
setting was raised from 410 to 450 volts. After completing the necessary test, the
bus bar protection put in to service on 29.12.2015.
Mail Received on 27-04-2016 ,16-06-2016,25-07-2016 & 24-09-2016:
Revision of Bus Bar Protection setting was carried out. After completing the
necessary test, the bus bar protection put in to service on 29.12.2015.
Mail received on 10-11-2016 & 20.12.2016:
Provision of Bus Coupler bay arrangement was included in the Upgradation
works proposed and the same was sanctioned by MoP through PSDF.
Numerical relay allotted and being commissioned.
Mail received on 20-02-2017:
Numerical BBP relay was commissioned on 02.02.2017Status received vide mail dated 18-09-2017 & 31-20-2017:
Numerical BBP relay was commissioned on 02.02.2017. Provision of CT in Bus
Coupler bay is arranged and zone segregation will be provided.
Status received vid email dated 12-12-2017:
Numerical BBP relay was commissioned on 02.02.2017. Provision of CT in Bus
Coupler bay has been allotted. Zone segregation will be provided after
commissioning of CT.
Review Meeting dated 19.12.2017:
TANTRANSCO informed that the recommendation would be complied with by Status received vid email dated 11-12-2018:
Civil work completed & CT will be commissioned after strengthening Bus .2
conductor jumpers.Awaiting Bus LC Time line before January 2019.
TANTRANSCO MAIL DATED 23.01.2019:
Erection under progress will be completed before 31.01.2019
TANTRANSCO MAIL DATED 19.03.2019:
Buscoupler bay will be commissioned by June 2019
TANTRANSCO MAIL DATED 13.06.2019:
Buscoupler bay configuation in BBP will be completed by June 2019. Bus
segregation will be ensured by 31.12.2019 after attending Isolator status
feedback.
TANTRANSCO MAIL DATED 18.07.2019:
Buscoupler bay configuation in BBP will be completed by June 2019. Bus
segregation will be ensured by 31.12.2019 after attending Isolator status
feedback.
TANTRANSCO mail dated 12.02.2020:
Busbar protection with Zone segregation work have been completed . Double bus
operation can be done after strengthening of bus (Twin Moose to Quad Moose).
Time line requested upto 30.06.2020.
Mail recieved on 25-07-2016 & 24-09-2016:
TANTRANSCO: Auto Transformer-2 HV side Bus isolator 'C'-phase support
insulator of 230kV Southern Bus was replaced and Bus Bar Protection scheme
was restored on 12.05.2016.
Status received vide mails received on 10-11-2016 & 20.12.2016 & 12.04.2017
& 01.06.2017 & 15-06-2017 & 04.08.2017 & 18.09.2017:
CT is not available in the Bus Coupler bay for zone segregation. CT latch relay is
to be provided for all bays for zone segregation.
Status received vide mails received on 31-10-2017 & 12-12-2017:
Numerical Bus bar protection panel allotted and will be commissioned with zone TANTRANSCO MAIL DATED 22.05.2018 & 08.06.2018:
Numerical Busbar protection relay commissioned on 14.05.2018
TANTRANSCO MAIL DATED 23.07.2018:
Control & Status of isolator feedeback to be provided by replacement of Drive
Mechanism box.
TANTRANSCO MAIL DATED 29.08.2018:
Control & Status of isolator feedeback to be provided by replacement of Drive
Mechanism box.
TANTRANSCO MAIL DATED 11.09.2018:
Control & Status of isolator feedeback to be provided by replacement of Drive
Mechanism box. Timeline requested upto Dec 2018.
Status received vid email dated 11-12-2018:
1. TANTRANSCO: Estimate sanctioned for replacement of defective isolator
status feedback. Work under progress. Lightning mask work under progress will
be completed within three days.
Review Meeting on 21.12.2018:
TANTRANSCO informed that Double bus operation would be provided by
March, 2019.
TANTRANSCO MAIL DATED 23.01.2019:
Isolator status will be ensured by March 2019
TANTRANSCO TANTRANSCO to take steps to provide double-bus operation at their 230 kV
Gummidipoondi SS.
50/I/3 Pending
55/I/1
(GD)
Pending
TANTRANSCOTANTRANSCO to examine the feasibility of providing two main-zone operation
for bus bar protection by exploring various alternatives like replacing existing
bus-coupler CB with a hybrid bus-coupler CB that comes with inbuilt CT,
replacing existing BBP relay with another suitable relay that supports two main-
zone operation, and implement the same.
Busbar protection got operated for a fault in 230kV
Mywadi-Anaikadavu line
21-12-2015 at
6:28 hrs
Complete outage of 230kV
Mywadi station of
TANTRANSCO
Complete outage of 230 kV
Gummidipoondi Station of
TANTRANSCO
12-05-2016 at
12:15 hrs
Flashover of Auto Transformer- 2 HV
B-phase Isolator supporting insulator of 230kV
Southern Bus occurred at Gummidipoondi station.
At the time of fault, Bus bar protection relay was not
in service for pre-commissioning testing of Auto
Transformer-2. All feeders got tripped due to
operation of zone-2 protection from remote ends.
Annexure-II
Page 27 of 39
TANTRANSCO MAIL DATED 19.03.2019:
New 230kV isolators have been allotted for replacement of defective isolators.
Hence time line requested upto June.2019.
TANTRANSCO MAIL DATED 13.06.2019 & 18.07.2019:
New 230kV isolators have been allotted for replacement of defective isolators.
Hence time line requested uptoSep.2019
TANTRANSCO MAIL DATED 12.02.2020:
New 230kV isolators have been allotted for replacement of defective isolators.
Time line requested upto March 2020.
TANTRANSCO TANTRANSCO to take steps to provide double-bus operation at their 230 kV
Gummidipoondi SS.
55/I/1
(GD)
PendingComplete outage of 230 kV
Gummidipoondi Station of
TANTRANSCO
12-05-2016 at
12:15 hrs
Flashover of Auto Transformer- 2 HV
B-phase Isolator supporting insulator of 230kV
Southern Bus occurred at Gummidipoondi station.
At the time of fault, Bus bar protection relay was not
in service for pre-commissioning testing of Auto
Transformer-2. All feeders got tripped due to
operation of zone-2 protection from remote ends.
Annexure-II
Page 28 of 39
The issue was discussed in PCSC-58 meeting held on 18.10.2016, when PCSC
forum agreed to de-link the implementation of the Item from the scope of
Protection Audit Recommendations (PAR), and pursue it as part of PCSC
Recommendations.
Status received vide mails dated 10.01.2017 & 12.04.2017 & 01.06.2017 &15-
06-2017 & 04.08.2017 & 18.09.2017 & 31-10-2017& 12-12-2017:
Different make Relays will be provided for Main-I & II relays at
Sunguvarchatram end in a phased manner.
TANTRANSCO MAIL DATED 22.05.2018:
TANTRANSCO informed that the recommended works of providing different
make Relays for Main-I & Main-II are targeted to be completed by September,
2018.
TANTRANSCO MAIL DATED 08.06.2018:
provision of Different make Relays for Main-I & Main-II will be completed by
September, 2018.
TANTRANSCO MAIL DATED 23.07.2018:
Different make Relays will be provided for Main-I & II relays at
Sunguvarchatram end in a phased manner. Timeline: September-2018.
TANTRANSCO MAIL DATED 29.08.2018 & 11.09.2018:
Different make Relays will be provided for Main-I & II relays at
Sunguvarchatram end in a phased manner. Timeline: September-2019.
TANTRANSCO MAIL DATED 11-12-2018:
Different make Relays will be provided for Main-I & II relays at
Sunguvarchatram end in a phased manner. Timeline: September-2019
TANTRANSCO MAIL DATED 23.01.2019:
Different make Relays will be provided for Main-I & II relays at
Sunguvarchatram end in a phased manner. Timeline: September-2019.
TANTRANSCO MAIL DATED 13.06.2019 & 18.07.2019:
Different make Relays will be provided for Main-I & II relays at
Sunguvarchatram end in a phased manner. Timeline: September-2019
TANTRANSCO MAIL DATED 12.02.2020:
Different make Relays will be provided for Main-I & II relays at
Sunguvarchatram end in a phased manner. Timeline: June 2020.
14-09-2016 at
11:13Hrs
Bus Bar Protection (Zone-2) of 230 kV Bus-B got
operated at Alamathy Station during fault in 230 kV
Alamathy-Korattur feeder.
Pending
15-09-2016 at
22:14 hrs
58/II/17 Multiple tripping at 230 kV
Alamathy Station
TANTRANSCO
58
1. TANTRANSCO to check the healthiness of BBP relay by conducting stability
test, and take appropriate remedial action like increasing voltage settings,
ensuring the healthiness of CT’s, using CT’s with similar characteristics (equal
saturation effects & equal winding resistances) etc. at their 230 kV Alamathy
SS.
2. TANTRANSCO to replace the existing high-impedance BBP relay with its
low-impedance/ numerical variant so as to accommodate variation in CT
characteristics at their 230 kV Alamathy SS.
Different type and Make of distance protection relays to be provided for Main-I & Main-II protection for 230kV feeders at 400 kV Sunguvarchathiram & 230 kV Sunguvarchathiram
Substation [Carry-Over from Protection Audit Recommendations]
Mail received on 10-11-2016 & 20.12.2016:
1. The Bus Bar Protection scheme will be tested for healthiness including the CT
circuits.
2. High impedance BBP relay will be replaced by Numerical relay.
Status received vide mails dated 10.01.2017 & 12.04.2017 & 01.06.2017 & 15-
06-2017:
1. The Bus Bar Protection scheme was tested for healthiness including the CT
circuits. AREVA make CTs in Alamathy SS are having different kneepoint
voltage for the cores. CT cores of higher knee point voltage has been choosen for
BBP in 230kV Korattur, 230kV OPG-1 & 230kV OPG-2 feeders on 29.11.2016. --
-- Completed.
2. High impedance BBP relay will be replaced by Numerical relay. --- Pending,
Status received vide mails dated 04.08.2017 & 18.09.2017 & 31-10-2017 & 12-
12-2017.
1. ---- Completed
2. High impedance BBP relay will be replaced by Numerical relay. --- Pending
Review Meeting dated 19.12.2017:
2) TANTRANSCO informed that Numerical BBP would be provided by April,
2018 --- Pending
TANTRANSCO mail received on 25-01-2018:
1. --- Complied.
2. High impedance BBP relay will be replaced by Numerical relay. Timeline:
April-2018.
TANTRANSCO MAIL DATED 22.05.2018 & 08.06.2018 & 23.07.2018:
2.Numerical BBP relay will be provided. Timeline: Sep-2018.
TANTRANSCO MAIL DATED 29.08.2018 & 11.09.2018:
1. Complied
2.Numerical BBP relay will be provided. Timeline: Sep-2018.
Bus Bar Protection (Zone1) of 230kV Bus-A got
operated at Alamathy Station during fault in 230 kV
Alamathy-OPG-1 feeder.
TANTRANSCO
Pending
Annexure-II
Page 29 of 39
TANTRANSCO MAIL DATED 11-12-2018:
Numerical BBP relay to procured. Timeline: Sep-2019.
TANTRANSCO MAIL DATED 23.01.2019:
Numerical BBP relay to be procured. Timeline: Sep-2019.
TANTRANSCO MAIL DATED 19.03.2019 & 13.06.2019 & 18.07.2019:
Numerical BBP relay to be procured. Timeline: Sep-2019.
Review meeting on 27.06.2019:
Timeline requested upto July 2020.
TANTRANSCO MAIL DATED 12.02.2020:
Timeline requested upto July 2020.
15-09-2016 at
22:14 hrs
58/II/17 Multiple tripping at 230 kV
Alamathy Station
TANTRANSCO1. TANTRANSCO to check the healthiness of BBP relay by conducting stability
test, and take appropriate remedial action like increasing voltage settings,
ensuring the healthiness of CT’s, using CT’s with similar characteristics (equal
saturation effects & equal winding resistances) etc. at their 230 kV Alamathy
SS.
2. TANTRANSCO to replace the existing high-impedance BBP relay with its
low-impedance/ numerical variant so as to accommodate variation in CT
characteristics at their 230 kV Alamathy SS.
Bus Bar Protection (Zone1) of 230kV Bus-A got
operated at Alamathy Station during fault in 230 kV
Alamathy-OPG-1 feeder.
Pending
Annexure-II
Page 30 of 39
64/1/4 Complete outage of North
Chennai TPS STG-1
26-03-2017
at 23:14hrs
Tripping of evacuating lines due to fault led to
tripping of running Unit at NCTPS Stg-1
1. TANTRANSCO to take steps to complete insulator replacement works on the
230 kV lines owned by them in NCTPS area within 6 months.
2. TANTRANSCO to take steps to implement A/R on all 230 kV lines
emanating from NCTPS-I at the earliest.
TANTRANSCO Status received vide mails dated 04.08.2017 & 18.09.2017 & 31-10-2017:
1. All the Porcelain insulators were replaced with Polymer insulators in 230kV
NCTPS-I - Tondiarpet feeders - 1 & 2.
---- Completed
2. AR will be implemented on all 230kV lines emanating from NCTPS-I. ---
Pending
Status received vid email dated 12-12-2017:
1. Completed
2. The scheme needs modification to enable AR, since AR was not envisaged for
this station during commissioning. AR will be implemented on all 230kV lines
emanating from NCTPS-I within six months. --- Pending
Review Meeting dated 19.12.2017:
2) TANTRANSCO informed that A/R would be implemented on all 230 kV lines
emanating from NCTPS-I by June, 2018.
TANTRANSCO mail received on 25-01-2018:
1. Complied.
2. The scheme needs modification to enable AR, since AR was not envisaged for
this station during commissioning. AR will be implemented on all 230kV lines
emanating from NCTPS-I within six months. Timeline:June-2018.
Pending
TANTRANSCO MAIL DATED 22.05.2018:
2. The scheme needs modification to enable AR, since AR was not envisaged for
this station during commissioning. AR will be implemented on all 230kV lines
emanating from NCTPS-I Timeline:Sep -2018.
TANTRANSCO mail received on 08-06-2018:
1. Complied.
2. The scheme needs modification to enable AR, since AR was not envisaged for
this station during commissioning. AR will be implemented on all 230kV lines
emanating from NCTPS-I Timeline:Sep -2018.
TANTRANSCO MAIL DATED 23.07.2018:
AR implemented for 4 feeders and remaining lines will be provided with AR
subsequently.
TANTRANSCO MAIL DATED 29.08.2018:
1. Complied
2. AR enabled for 3 feeders.
TANTRANSCO MAIL DATED 11.09.2018:
1. Complied
2. AR enabled for 5 feeders.
TANTRANSCO MAIL DATED 11-12-2018:
2. Enabling AR pending for 3 feeders. ( Sriperumpudhur end breaker problem,
Tondiarpet & Alamathy feeder . static relay to be replaced. Timeline - 1 year
TANTRANSCO MAIL DATED 23.01.2019:
Enabling AR pending for 3 feeders. ( Sriperumpudhur end breaker problem,
Tondiarpet & Alamathy feeder . static relay to be replaced. Timeline -Sep 2019
TANTRANSCO MAIL DATED 19.03.2019 & 13.06.2019 & 18.07.2019:
Enabling AR pending for 3 feeders. ( Sriperumpudhur end breaker problem,
Tondiarpet & Alamathy feeder . static relay to be replaced. Timeline -Sep 2019
TANTRANSCO MAIL DATED 12.02.2020:
1. (i). Polymer insulators has been provided in all the 400 kV evacuation lines
from NCTPS end up to 5 KMs. Replacement of Polymer insulator in 230 kV lines
are under progress for the 230 kV lines emanating from NCTPS.
2. Enabling AR pending for 3 feeders. ( Sriperumpudhur end breaker problem,
Tondiarpet & Alamathy feeder . static relay to be replaced. Since the CBs and
the Control & Relay Panels (CRP) are very old and commissioned during 1993.
The Distance relays even though are numerical due to ageing its display and
resetting keys are faulty. Hence it is proposed to replace the CBs & CRPs with
new CBs and Protection relay panel with SAS. A.R will be put into service after
replacing the CB & CRP.
77/II/9 Multiple trippings at
400 kV Manali Substation
TANTRANSCO to refer the issue of selective tripping of 400 kV side breakers,
and non-tripping of 230 kV side breakers due to operation of Densimeters on
low pressure in the instant case to their OEM, and share OEM’s advice/ remedy
in this regard.
TANTRANSCO mail dated 11.09.2018:
OEM will be referred
Review Meeting on 21.12.2018:
TANTRANSCO was asked to update the status.
TANTRANSCO MAIL DATED 23.01.2019, 19.03.2019 & 13.06.2019:
The issue was referred with OEM & reply awaited.
Review meeting on 27.06.2019:
OEM reply shall be communicated by end of July 2019
TANTRANSCO mail dated 18.07.2019:
The issue was referred with OEM & reply awaited
TANTRANSCO MAIL DATED 12.02.2020:
The issue was referred with OEM & reply awaited.
Pending
Annexure-II
Page 31 of 39
79/I/3 Complete outage of 230 kV
Thiruvalam Substation
05-10-2018 at
14:32 hrs
Bus-1 got tripped at 230 kV Thiruvalam substation
due to spurious LBB relay (independent) operation
of 230kV Thiruvalam Chittoor line. 230kV
Thiruvalam substation was under single bus
operation; hence operation of LBB protection
resulted in tripping of all connected elements
resulting in the complete outage
TANTRANSCO to take steps to implement multi-bus, multi-zone operation
(Double-bus operation) at their 230 kV Thiruvalam SS by December, 2018.
TANTRANSCO TANTRANSCO MAIL DATED 11-12-2018:
Due to space constraint, the equipments could not be erected.
Review Meeting on 21.12.2018:
It was noted that the station was on a single (Main) bus and there was not even
transfer bus. In view of the importance of 230 kV Thiruvalam SS,
TANTRANSCO was asked to take steps to provide dobule-bus operation at their
230 kV Tiruvalam SS.
TANTRANSCO MAIL DATED 23.01.2019 & 19.03.2019:
Feasibility for providing hybrid breaker / shifting of bays will be studied & action
will be taken. Time upto Sep 2019
TANTRANSCO MAIL DATED 13.06.2019 & 18.07.2019:
Bus segregation will be ensured by providing bus coupler bay by extending the
existing Bus.Time line 31.12.2019.
TANTRANSCO MAIL DATED 11.11.2019 and 12.02.2020
Bus segregation will be ensured by providing bus coupler bay by extending the
existing Bus.Time line 31.12.2020.
Pending
TANTRANSCO MAIL DATED 13.06.2019:
1. At present Duobias relay avaiable I/O configuration could not be carried
out.after changing the relay Digital signals will be configured
2.COMPLIED
3.Provision of Numerical BBP relay covered under R&M work. Tender under
progress.
4.out of 30 CTs, 21 No CTs have been replaced with new one.
Review meeting on 27.06.2019:
1. , 3. Timeline requested upto July 2020.
2. Complied
4. Timeline requested upto September 2019.
TANTRANSCO mail dated 18.07.2019:
1. At present Duobias relay avaiable I/O configuration could not be carried
out.after changing the relay Digital signals will be configured
2.COMPLIED
3.Provision of Numerical BBP relay covered under R&M work. Tender under
progress.
4.out of 30 CTs, 21 No CTs have been replaced with new one.
TANTRANSCO mail dated 11.11.2019 and 12.02.2020:
1. At present Duobias relay avaiable I/O configuration could not be carried
out.after changing the relay Digital signals will be configured
2.COMPLIED
3.Provision of Numerical BBP relay covered under R&M work. Tender under
progress.
4.out of 3 CTs, 27 No CTs have been replaced with new one.
85/II/1 Tripping of 400/230kV
MANALI ICT-3
13-05-2019 at
2:42 hrs
ICT-3 got tripped on the activation of HV REF
protection. During test charging of 110 kV Manali-
ETPS -1 , the 110 kV ETPS -1 got tripped on the
activation of Back up relay and Distance relay failed
to act
1. TANTRANCO is recommended to sort out the malfunctioning of ICT Ref
protection in consultation with OEM and submit a detailed report regarding the
same in 1 month time.
2. TANTRANSCO is recommended to ensure proper labelling of all digital
signals in Disturbance recorders of lines and ICTs at Manali SS.
TANTRANSCO TANTRANSCO mail dated 11.11.2019:
1. The issue was addressed to OEM reply awaited.
2. Uniform Labelling of Digital signal will be ensured.
TANTRANSCO mail dated 12.02.2020:
1. The issue was addressed to OEM reply awaited.
2. Proper labeling of D.R has been implemented.
Pending
87/II/7 Outage of 230 kV Bus-1 at
400/230 kV Madurai station of
TANTRANSCO
19-08-2019 at 12:28
hr.
Triggering incident was jumper cut of 230 kV Madurai-
Ranganathapuram feeder. Bus bar protection of Bus-1
operated resulting in tripping of all elements connected to
230 kV bus-1.
1.TANTRANSCO to submit a report regarding non-operation of A/R at Renganathapuram and to
change the digital signal legend from carrier fail to carrier healthy.
2. TANTRANSCO to configure digital signals corresponding to CB status in DR and sort out time
synchronization issues at 230 kV Checkanurani SS.
TRANTRANSCO TANTRANSCO mail dated 12.02.2020:
1. Complied
2.Complied
Pending Report when sent?
87/II/18 Multiple Tripping at 230kV
Checkanurani S/s of
TANTRANSCO
10-09-2019 at 13:24
hr.
Triggering incident was B phase to Earth fault in 230 kV
Checkanurani - Renganathapuram line. Persistent fault current
resulted in the operation of LBB protection and all the elements
connected at Bus-1 got tripped since 230 kV Checkanurani-
Renganathapuram line was connected at Bus-1 during
antecedent conditions
1.TANTRANSCO to submit a report regarding non-operation of A/R at Renganathapuram and to
change the digital signal legend from carrier fail to carrier healthy.
2.TANTRANSCO to configure digital signals corresponding to CB status in DR and sort out time
synchronization issues at 230 kV Checkanurani SS
TANTRANSCO TANTRANSCO mail dated 12.02.2020:
1. Complied
2.Complied
Pending Report when sent?
88/II/10 Tripping of Bus-A at 230kV
Alamathy station
13-10-2019 at 11:29
Hr.
· Triggering incident was R-N fault in 230kV Alamathy –
OPG2 feeder.
• Simultaneously jumper got cut in 230kV Alamathy-OPG1
connected to Bus-A.
• Bus bar protection of Bus-A operated.
i. TANTRANSCO to configure DR and EL legends properly and submit a complete DR at
Almathy end clearly showing A/R operation.
ii. TANTRANSCO to ensure time synchronization of relays at Almathy and Almathy_OPG.
TANTRANSCO TANTRANSCO mail dated 12.02.2020:
CompliedPending Complete DR when submitted?
Failure of ‘R-phase’ HV side Current transformer
(CT) of 315MVA 400/230kV ICT-3 at 400kV
Sriperumbudur substation (400kV TANTRANSCO
switchyard).
28-01-2019
at 01:15 Hrs
PendingTANTRANSCO1) TANTRANSCO to ensure proper legends for DR Digital signals and all
required events(including CB status, Type of protection operated) are captured
in Event logger.
2) TANTRANSCO to extend BBP trip from BusBar relay to 86A (with source-1
DC) in addition to 86B (with source-2 DC), or to provide Common trip relay 96
with redundant DC supply.
3) TANTRANSCO to inform the action plan with timelines for providing
Numerical BBP at Sriperumbdur SS .
4) TANTRANSCO to check the healthiness of all CT’s in the stationand submit
a report regarding the same to SRPC to prevent any such occurrence in future.
Complete outage of 400kV
Sriperumbudur station
82/I/1
Annexure-II
Page 32 of 39
88/III/2 Tripping of 220kV Idukki –
Udumalpet line
05-10-2019 at 16:35
Hr.
Line tripped on B-N fault. Line tripped at Idukki end on Zone-
1, distance protection and at Udumalpet end on Zone-2. A/R
was attempted at Idukki end but locked out due to persistent
fault. A/R did not operate at Udumalpet end.
For the subject line, the following shall be carried out by KSEBL in coordination with
TANTRANSCO:
i. End-to-end testing for DT/ permissive& other signals may be ensured by testing at both the ends.
ii. Healthiness of PLCC system components (hardware and software) at both the ends shall be
checked and faulty components shall be repaired/ replaced.
TANTRANSCO TANTRANSCO mail dated 12.02.2020:
Carrier set healthy at Udumelpet end. Healthiness of link will be checked after getting confirmation
from KSEB
KSEBL mail dated 11.02.2020:
PLCC system in IDUD feeder at Idukki is not working well. Purchase process for the new panel is
under progress.It will be commissioned by April 2020.
Pending
89/II/2 Tripping of 400/230 kV ICT-2 at
Sungavarchatram SS of
TANTRANSCO
28-11-2019 at 10:43
Hr.
• 400 kV SVC SS-ICT2- R phase tripped on percentage
Differential & REF protection.
• During test charging of 110 KV Oragdam-SP Koil-1# at 230
KV Oragadam SS the feeder got tripped on SOTF due to R
phase CT blast.
i. TANTRANSCO to test all CTs (secondary voltage measurement and Tandelta measurement)
and replace if CTs found mal-operating. CT cable also needs to be tested.
ii. TANTRANSCO to furnish the OEM findings regarding the tripping at the earliest .
TANTRANSCO Yet to be informed Pending
Annexure-II
Page 33 of 39
KSEB Mail received vide dated 17.01.2017:
1. 110 kV bus bar protection progressing ----Pending
2. Connection of 220kV earth mat and 110 kV plate earthing system completed.---
- Completed
3. Redundancy of 110V DC system in progress. Complete independent
redundancy is not practical for the time being. 48 V DC redundancy was already
there. ----Pending
4. Instead of stand alone event logger, SCADA system of 110 kV feeder is
Status received vide mail dated 12-12-2017:
1. Detailed engineering of the scheme has been completed. Material procurement
is in progress. ---Pending
2.,3. ---- Completed
4. The SOE and DR are available with time stamping from the numerical relays.
Hence stand alone event logger is not necessary ----- Completed
Status received vide mail dated 11-12-2018:
Work has been already tendered. It is expected that purchase process will
completed within three months.
Status received vide mail dated 17.01.2019:
At the time of bid only one bidder participated and the work has been retendered.
Status received vide mail dated 19.03.2019:
Status as on 18.03.2019: Based on the retender, have received two offers from 1) Status received vide mail dated 03.05.2019:
Sanction to issue purchase order in progress. Time Frame is January 2020 .
Review meeting on 27.06.2019.
1. BBP will be commissioned by December 2019.
2.,3.,4. Completed
KSEBL mail dated 16.12.2019:
1)The station authorities have already initiated action to implement the same by
June 2020.
2.,3.,4. Completed
KSEBL mail dated 11.02.2020:
1)The station authorities have already initiated action to implement the same by
April 2020.
2.,3.,4. Completed
Status received vide mail dated 11-12-2018:
1) Present setting is 180ms.OEM(ABB) suggests that it will give around 200ms
delay as it is having inherent delay is of around 20ms(ie, 180ms +20ms
=200ms).With this setting the fault clearence is found after 220ms.So further
revision may be carried out after discussion.
2)Breaker status will be ready only after completing the GOOSE network as part
of renovation of all feeder panels and Idukki first stage units by June 2019 .
Status received vide mail dated 03.05.2019:
1) Pending.....
2)Breaker status will be ready only after completing the GOOSE network as part
of renovation of all feeder panels and Idukki first stage units by January 2020
....Pending
Review meeting on 27.06.2019.
1. 2. work under progress
KSEBL mail dated 30.10.2019:
1. As recommended, LBB time setting is changed to 200ms on 22.10.2019
Triggering incident was conductor snapping in 110
kV Kalamassery- Kaloor feeder
1). KSEBL to check & correct the LBB time setting employed at their Idukki PH
to 200 msec.
2). KSEBL o ensure that DR’s & EL’s of all Protection Relays (PR’s) at their
Idukki PH are configured for recording all mandated protections & signals.
Triggering incident was R-Ph fault in 220kV Idukki-
Kalamassery line-2. R-phase pole of breaker didn’t
open at Idukki end. LBB of Bus-2 operated resulting
in tripping of all connected elements along with
running Unit#4 at Idukki and 50MVA station
transformer. At the same time, 220kV Idukki
Kalamassery line-1 also got tripped at Idukki end.
Subsequently running Units 1 and 2 also tripped on
Governor oil Low Pressure due to loss of AC supply.
This resulted in complete outage of Idukki PS.
01-10-2018 at
04:16 hrs
Complete Outage of 220 kV
Idukki Power Station
79/I/1
KSEB to take steps to provide the following at their 220/ 110 kV Kalamassery
SS:
1. Busbar protection at 110 kV level
2. Connecting 220 kV and 110 kV sides on to a common earthmat
3. Redundant DC supply for both protection (220 V) and communication (48 V)
applications
4. Stand-alone Event Logger
KSEB Pending
PED
KSEBL Pending
23-08-2016
at 11:20 hrs
Complete outage of 220 kV
Kalamassery Substation
Kerala
58/I/1
(GD)
Annexure-II
Page 34 of 39
KSEBL mail dated 15.01.2020
1. Completed
2)Breaker status will be ready only after completing the GOOSE network as part
of renovation of all feeder panels and Idukki first stage units by March 2020 ---
Pending
KSEBL mail dated 12.02.2020:
1) Completed
2)Breaker status will be ready only after completing the GOOSE network as part
of renovation of all feeder panels and Idukki first stage units by June 2020.
Multiple trippings at 220
kV Madakathra station
Status received vide mail dated 11-12-2018:
In progress
Status received vide mail dated 19.03.2019:
Status as on 18.03.2019: Estimate sanctioned by CE(Transmission North ) and
have prepared the technical specifications.Tendering procedures are yet to get
started.
Status received vide mail dated 03.05.2019:
At the time of bid only one bidder participitated and the work has been
retendered.
Status received vide mail dated 07.06.2019:
Retendering process in progress. Time Frame is January 2020 .
Review meeting on 27.06.2019.
work has been awarded
KSEBL mail dated 16.12.2019:
Drawing varification is under progress.Work will be completed by the end of
March 2020
KSEBL mail dated 11.02.2020:
Work will be completed by the end of June 2020
82/I/5 Complete Outage of 220kV
Bhramapuram substation of
KSEB
08-02-2019 at
10:28 hrs
Complete outage of 220kV Brahmapuram SS
occurred due to suspected mal operation of Bus Bar
protection.
1) KSEBL to furnish detailed report regarding the healthiness of BBP operation
at 220kV Brahmapuram after testing of the same on 12th April 2019.
2) KSEBL to submit the action plan regarding
(i) Replacing of the Static High impedance BBP (using CRM relays) with
Numerical BBP.
(ii) Replacement of CRM relays and relays with no Disturbance recording
facilitites.
KSEBL Status received vide mail dated 03.05.2019 & 11.202.2020:
1) Detailed report sent on 02.05.2019…..Completed.
2) As reported earlier in this regard, the permanent solution to this problem is to
replace the existing high impedance static relay with a low impedance numerical
relay. The station authorities have already initiated action to implement the same
by June 2020.
Pending
84/I/3 Complete outage of 220 kV
Edamon SS of KSEB
27-05-2019 at
12:30 hr.
Triggering incident was three phase to earth fault in
220 kV Edamon Bus 1 and 2. Bus 1 and 2 Bus bar
protection operated resulting in the tripping of all
connected elements.
1.KSEBL may develop proper operational code for procedures to be followed
while performing operations in switchyard and sensitize their operators to reduce
operational errors. 2.ksEBL to ensure time synchronization of relays at
220 kV Edamon SS.
KSEBL KSEBL mail dated 30.07.2019:
1. proper operrational code is avilalable in 220kV SS Edamon
2. All 220KV relays of Edamon substation are synchronized with GPS clock . Out
of this, 3 relays are having hardware issues with time synchronisation switch .
This problem will be resolved by August 2019 itself.
KSEBL mail dated 28.08.2019
2. By August 2019, could rectify the hardware issue with 2 relays. Other will be
done by September 2019.
KSEBL mail dated 30.10.2019:
Have taken steps to rectify the hardware issue with the 3rd relay and will be
completed by end of December 2019
KSEBL mail dated 16.12.2019:
Have taken steps to rectify the hardware issue with the 3rd relay and will be
completed by end of March 2020
KSEBL mail dated 11.02.2020:
Have taken steps to rectify the hardware issue with the 3rd relay and will be
completed by end of April 2020
Pending
87/II/14 Tripping of 400/220 kV
ICT-3 at Trichur
29-08-2019 at
16:32 hr
ICT-3 got tripped during testing of busbar protection KSEBL to submit a report after providing separate breaker failure relays for
ICT-3 and sorting out the time synchronization issues of relays at 400 kV
Madakkathara SS.
KSEBL KSEBL mail dated 16.12.2019:
1) Relay purchase is expected to be completed by Feb 2020. Report will be
complted by March 2020.
2) GPS connection issues were resolved
KSEBL mail dated 11.02.2020:
1)Work will be completed by the end of June 2020
2) completed.
Pending
88/II/1 Complete loss of supply at 220kV
Idukki GS of KSEB
03-11-2019 at 15:05
Hr.
Triggering incident was bus fault at Bus-2 of 220kV Idukki
station.
• This led to operation of bus bar protection at Idukki resulting
in complete loss of supply at Idukki station.
1. KSEBL to submit a report after detailed inspection of Busbar relay regarding reason for
operation of checkzone during through fault.
2. KSEBL to ensure equal distribution of feeders on both buses to reduce supply interruption in
case of BBP operation of one Bus.
3. KSEBL to rectify time sync issue at 220kV Idukki GS.
KSEBL KSEBL mail dated 11.02.2020:
1)It was noticed that Bus coupler CT input was wrongly connected to bus bar protection. Rectified
the maloperation issues.Disconnected Bus coupler CT input to Busbar protection.Now working Ok.
-- Completed 2) Instructions have already been conveyed
for equal distribution of feeders and generators in both buses. -- Completed
3)Time suncronization will be rectified after RMU of Idukki feeders & 1st stage generatos by June
2020. --Pending
Pending
PendingKSEBLKSEBL to take steps to replace the existing static (high impedance type) 220 kV
BBP with numerical Busbar protection at their 220 kV Madakathara SS.
Triggering incident was Y-phase to ground fault in
220kV Madakathra – Palakkad_KL (Ellapully) line
due to flashover of pilot insulator string. Auto-
reclose was successful at Madakathra end. At the
same time bus differential relay Zone-C mal-
operated resulting in tripping of all elements
connected to the bus.
15-10-2018 at
08:57 Hrs
80/II/5
1). KSEBL to check & correct the LBB time setting employed at their Idukki PH
to 200 msec.
2). KSEBL o ensure that DR’s & EL’s of all Protection Relays (PR’s) at their
Idukki PH are configured for recording all mandated protections & signals.
Triggering incident was R-Ph fault in 220kV Idukki-
Kalamassery line-2. R-phase pole of breaker didn’t
open at Idukki end. LBB of Bus-2 operated resulting
in tripping of all connected elements along with
running Unit#4 at Idukki and 50MVA station
transformer. At the same time, 220kV Idukki
Kalamassery line-1 also got tripped at Idukki end.
Subsequently running Units 1 and 2 also tripped on
Governor oil Low Pressure due to loss of AC supply.
This resulted in complete outage of Idukki PS.
01-10-2018 at
04:16 hrs
Complete Outage of 220 kV
Idukki Power Station
79/I/1 KSEBL Pending
Annexure-II
Page 35 of 39
89/1/5 Complete loss of supply at 220
kV Kanhirode, 220 kV
Ambalathara, 220 kV Mylatty,
220 kV Thaliparamba and 220
kV Orkattery SS of KSEB
08-01-2020 at 14:22
Hr.
• Triggering incident was conductor snapping of 220 kV
Kanhirode – Ambalathara feeder.
• Bus bar protection at 220 kV Kanhirode SS operated resulting
in tripping of all connected elements.
• There was complete loss of supply at 220 kV Ambalathara,
Mylatty, Thaliparamba and Orkattery SS of KSEB since these
station were radially fed from 220 kV Kanhirode station.
KSEBL to replace existing high impedance BBP and mal-operating check Zone relay with Low
impedance BBP at 220kV Kanhirode SS.KSEBL Yet to be informed Pending
89/II/1 Tripping of Bus-1 and Bus-2 at
220 kV Brahmapuram station of
KSEB
26-11-2019 at 09:04
Hr.
• Bus bar protection of Bus-1 operated resulting in tripping of
all elements connected to Bus-1 at 220 kV Brahmapuram.
KSEBL to expedite the process of providing numerical BBP in place of mal-operating CRM
relays at 220 kV Brahmapuram SS.KSEBL Yet to be informed Pending
85/II/16 Tripping of 400kV Tumkur-
Bidadi line-1&2, 400kV
Tumkur-Cuddapah line-2,
400kV Tumkur-Pavagada
line-2
29-05-2019 at
6:11 hrs
Lines tripped due to Y-N & Y-B phase to earth fault PGCIL (SR-2) is recommended to submit Equipment failure report to CEA
regarding the failed LA.
PGCIL (SR-II) Yet to be informed Pending
84/II/15 Tripping of 400kV Bus-1
and connected elements at
400kV Bidadi substation
25-04-2019 at 08:01 hr.Triggering incident was failure of R-ph CB of bus
reactor at 400kV Bidadi. Bus bar protection of Bus-
1 operated resulting in the tripping of all elements
connected to Bus-1
1. PGCIL (SR-II) was requested to send the equipment failure report to CEA.
2.PGCIL (SR-II) is recommended to share the feedback of OEM regarding
decomposition of SF6 gas.
PGCIL (SR-II) PGCIL (SR-2) mail dated 16.12.2019:
Report from OEM is yet to be received.
Pending
88/II/11 Tripping of 400kV Ramagundam-
N’Sagar-1
16-10-2019 at 02:56
Hr.
· Line tripped on operation of OV St-1 protection at N'Sagar
end and DT was received at Ramagundam end.
• From DR of N'Sagar end, Vb-254kV.
• Tripping is not as per OV grading at N'Sagar end.
1. PGCIL-SR-1 to submit Event logger for the incidence clearly showing OVR_start and
OVR_trip.
2. PGCIL-SR-1 to check the OVR gradings adopted at 400kV N’Sagar SS.
PGCIL-SR-I Yet to be informed Pending
Others
PGCIL (SR-I) & PGCIL (SR-II)
Annexure-II
Page 36 of 39
69/I/1 Complete outage of 400kV
TPCIL station
25-10-2017 at
19:33 hrs
400 kV TPCIL-Nellore PS line-1 got tripped from
TPCIL end during fault in 400kV Nellore-Nellore
PS line-2. Running units at TPCIL got tripped due
to loss of evacuating line. 400kV Nellore PG -
Nellore PS line-2 and 400kV TPCIL - Nellore PS
line-1 were under shutdown.
TPCIL to configure DEF protection such that it remains in blocked condition as
long as Distance Protection is active, and becomes active only when distance
protection does not pickup.
TPCIL Review Meeting on 21.12.2018:
It was noted that no TPCIL representatives had come to attend the meeting
Review meetinmg on 27.06.2019:
No representative from the utility attended meeting and it is requested to submit
status regrading the recommendation at athe earliest.
Pending
1.MAPS to furnish a detailed report on the tripping of SP Koil – MAPS lines 1
& 2 at MAPS end with focus on the correctness of the settings of Main-I & Main-
II relays (for primary & back-up protections) on both the lines.
2.MAPS to take steps to provide down-loading facility for DR & EL from Main-I
& Main-II relays on all 230 kV lines emanating from MAPS.
Status revided vide MAPS mail dated 06.12.2016;
1. The settings given by M/s TANTRANSCO were adopted for Main –I & Main-
II relays for both the lines. The same settings were verified to be same.
Subsequently calibrated was done and no drift was observed. --- Completed
2. From May 2016 onwards, the DR, EL and trip report are being sent by mail to
SRLDC, Bengaluru by MAPS. --- Completed
B-phase CT failure occurred in 230 kV S.P.Koil -
MAPS line-1. Busbar protection got operated at
SP.Koil station. All elements except 230kV
Oragadam and 230kV Kalivandapattu got tripped at
230kV S.P.Koil station. ‘Y’ phase CT and support
insulators also got damaged.
54/I/1 Complete outage of 230 kV
S.P.Koil Station of
TANTRANSCO
PendingNPCIL (MAPS)02-04-2016 at
17:08 hrs
Annexure-II
Page 37 of 39
78/II/2 Tripping of 400 kV Neyveli
TS2Exp -Pugalur line
01-08-2018
at 11:56 hrs
Triggering incident was failure of R-ph tension
insulator string/ flashover in 400 kV Bus-1 at NLC
TS2Exp end. Busbar protection had operated
resulting in tripping of all main breakers connected
to 400kV Bus-1 at Neyveli TS2 Exp. In 400kV NLC
TS2Exp - Pugalur line, fault was sensed in Zone-1,
R-N at Pugalur end resulting in a single phase trip.
Direct Trip was received at Pugalur end due to
operation of over voltage Stg-2 at NLC TS2Exp.
1. NLCIL to furnish a report along with a suitable SLD on the tripping event
explaining the observed discrepancies [DPR, Z1 operation, instantaneous
operation of OVR-II operation], and remedial action taken to attend the same.
2. NLCIL to configure DR’s & EL’s of all protection relays at their NLC TS-
IIExp station for all mandated protections & signals.
NLCIL Review Meeting on 21.12.2018:
NLCIL was asked to furnish the status of implementation of the recommendation
given at the earliest.
Review meetinmg on 27.06.2019:
No representative from the utility attended meeting and it is requested to submit
status regrading the recommendation at athe earliest.
Pending
79/II/8 Tripping of 400 kV NLC
TS-2 (Exp) – Pugalur line
10-09-2018 at
20:57 hrs
Line tripped on B-N fault. Auto-reclose was not
attempted at Pugalur end due to DT receipt from
NLC TS2Exp end. At NLC TS2Exp end, V>2 trip
was observed in DR. Analog voltages recorded in
DR were observed to be less than that required for
O/V Stage-II operation.
NLCIL to furnish a detailed report on tripping event explaining the observed
discrepancies , and proper reasons for tripping of the line considering both the
Main-relays including remedial action taken w.r.t. healthiness/ replacement of
Main protection relays on 400 kV NLC TS2Exp–Pugalur line.
NLCIL Review Meeting on 21.12.2018:
NLCIL was asked to furnish the status of implementation of the recommendation
given at the earliest.
Review meetinmg on 27.06.2019:
it is requested to submit status regrading the recommendation at athe earliest.
Pending
80/II/17 Tripping of 400 kV Nellore
PS – SGPL line-1
14-11-2018 at
20:20 hrs
Y- ph to earth fault occurred in line due to snapping
of GIS to Air bushing conductor at SGPL
switchyard. The conductor got grounded such that
the fault was being fed by NPS bus and there was
earth fault and broken conductor start at SGPL end.
NPS end got tripped in Zone-2 due to non-receipt of
carrier resulting in a 3-ph trip at NPS. After 500ms,
earth fault occurred at SGPL end resulting in Zone-1
operation and 3 phase trip. A/R was not attempted
at SGPL end
SGPL to examine the reasons for no-operation / failure of Auto-reclosure from
their end for the subject tripping, and furnish an action taken report detailing
remedial measures taken to PCSC forum.
SGPL Review meetinmg on 27.06.2019:
No representative from the utility attended meeting and it is requested to submit
status regrading the recommendation at athe earliest.
Pending
80/III/6 Tripping of 400 kV
Neyvelli TS2 (Exp) -
Pugalur line
07-11-2018 at
05:50 Hrs
400 kV Neyvelli TS2Exp - Pugalur tripped on
B-phase to ground fault due to DPR, Z1 operation.
Auto-reclose was successful at Pugalur end and the
line tripped at Neyveli TS2Exp end only. Auto-
NLCIL to furnish a detailed report on the reasons for A/R non-operation for the
subject tripping at their NLCTS2Exp station including remedial measures taken
to PCSC forum.
NLCIL Review meetinmg on 27.06.2019:
No representative from the utility attended meeting and it is requested to submit
status regrading the recommendation at athe earliest.
Pending
83/III/1 Tripping of 220 kV
Kayamkulam –Punnapura-2
24-02-2019 at
03:05hrs
Line tripped on B-phase to earth fault. Auto-reclose
was successful at Punnapura. A/r was not attempted
at Kayamkulam and there was pole discrepancy
operation resulting in tripping of R and Y pole of
CB.
It was noted that no representative of NTPC attended the meeting.
NTPC (Kayamkulam) to furnish detailed report regarding failure of Auto-
reclosure at Kayamkulam end for Kayamkulam –Punnapura line-2.
NTPC (KYKLM) Review meeting on 27.06.2019:
No representative from the utility attended meeting and it is requested to submit
status regrading the recommendation at athe earliest.
NTPC mail dated 13.05.2019:
Trip report for Tripping of 220 kV Kayamkulam –Punnapura-2 submitted , but
for submitting detailed report for Auto-reclosure at Kayamkulam end not
operating for Kayamkulam –Punnapura line-2 , half day shutdown of
Pending
83/III/2 Tripping of 220 kV
Kayamkulam –Punnapura-2
05-03-2019 at
00:30hrs
220kV Kayamkulam-Punnapura -2 tripped on Zone-
1 distance protection due to R-N fault. Auto reclose
operated and successful at Punnapara end but didnot
operate at Kayamkulam end.
It was noted that no representative of NTPC attended the meeting.
NTPC (Kayamkulam) to furnish detailed report regarding failure of Auto-
reclosure at Kayamkulam end for Kayamkulam –Punnapura line-2.
NTPC (KYKLM) Review meeting on 27.06.2019:
No representative from the utility attended meeting and it is requested to submit
status regrading the recommendation at athe earliest.
NTPC mail dated 13.05.2019:
Trip report for Tripping of 220 kV Kayamkulam –Punnapura-2 submitted , but
for submitting detailed report for Auto-reclosure at Kayamkulam end not
operating for Kayamkulam –Punnapura line-2 , half day shutdown of
Kayamkulam –Punnapura line is required to check reason for failure . May please
approve half day outage of Kayamkulam –Punnapura line and intimate us atleast
Pending
84/I/5 Complete outage of 400kV
NLC1
Expansion(NLC1EXP)
05-06-2019at 18:51 hr.Triggering incident was failure of Y-phase CT of GT-1 (Generator Transformer) at 400kV NLC1EXP. Bus-1 Bus bar protection operated resulting in the tripping of NLC1EXP U#1 and 400kV NLC1EXP- Nagapattinam line 1. NLCIL to check the healthiness of R & B ph CT of Unit-1 at NLC TS1(Exp)
and if found unhealthy replace the same alongwith replacement of Y-ph CT. CT
replacement plan and timeframe shall be informed to SRPC.
2.NLCIL in coordination with PGCIL(SR-II) to resolve the time syncronisation
issues in 230kV NLC TS1(Exp) – Nagapattinam line.
3. NLCIL was also requested to investigate the reason of unwarranted DT sent to
NLC TS1 (Exp) end from NLC TS2 end and resolve the same.
NLCIL NLCIL mail dated 09.07.2019:
AT TS2 Side Siemens 7SA52 & Micromho relay are used for distance protection.
During the incident Micromho has sensed the CT blast as a Zone-1 fault and
tripped the feeder. Adt signal was send to TS1 Exp end. The relay will be tested
during the next shut down.
NLCIL mail dated 11.01.2020:
3. Michro mho Relay Testing was carried out at TS2 end on 15/11/19 and found
the relay was normal.Proposal has already been initiated to replace distance
relays with line differential relays. It is also proposed to replace the PLCC panels
at both ends. -- Completed
Pending
85/II/19 Tripping of 400kV JSW-
Guttur line
02-06-2019 at
18:17 hrs
Line tripped due to OV St-1 protection operation at
JSW end and DT was sent to Guttur end. At Guttur
end B ph voltage was observed to be lesser
comparing to R ph and Y ph(Vr-249kV, Vy-255kV
and Vb-230kV).
JSWEL is recommended to monitor the B-ph CVT of 400kV JSWEL-Guttur
line (due to lower B-ph voltage compared to other two phases). The same shall
be replaced if the issue persists.
JSWEL Yet to be informed Pending
85/II/21 Tripping of 400kV JSW -
Guttur line and 400 kV
Kaiga - Guttur line-2
05-06-2019 at
18:27 hrs
Y-phase to earth fault occurred in 400kV Kaiga-
Guttur line-2. A/r was successful at Guttur end. At
Kaiga end A/r was not attempted and breakers got
tripped due to operation of Pole discrepancy (1.65
Sec). 400kV JSW-Guttur line tripped on operation
of over-voltage at Guttur and direct trip was
received at JSW. From DR of Guttur, it is observed
that there was swell in R & Y phase voltage for few
cycles
1. NPCIL (KGS) is recommended to identify the issue related to unsuccessful
A/R attempt of 400kV Kaiga – Guttur line and non-opening of R-pole CB. It is
recommended to check the healthiness of all breakers including breaker timing.
2. Time synchronization of DR and EL at Kaiga end shall be ensured.
NPCIL (KGS) NPCIL mail dated 13.12.2019:
During the event Distance Protection Main-2 detected Y-ph fault and opened the
Y-ph pole and initiated A/R to process.
subsequent to that IN> started for B-ph. Actuation of IN> during the dead time
leads to A/R lockout. So pole discrepancy operated at kaiga end as per the
scheme.
DR and EL are already GPS synched at Kaiga end.
NPCIL mail dated 18.03.2020:
Event is forwarded for Designer review
Pending
85/IV/7 Tripping of 400kV
Ramadugu-Singareni line
11-06-2019 at
08:24 hrs
Line tripped due to Direct Trip receive at Ramadugu
end
Singareni STPP is recommended to submit a detailed report regarding sending
of DT from singareni end that resulted in tripping of 400kV Ramadugu-
Singareni line.
Singareni TPP Yet to be informed Pending
Annexure-II
Page 38 of 39
86/III/2 Tripping of Kaiga-Gutur
line -2
22-07-2019 at
17:47hr.
Line tripped on B-phase to earth fault. Line did not
auto-reclose.
NPCIL (KGS) to ensure time sync between DR and EL at Kaiga end. NPCIL NPCIL mail dated 13.12.2019:
DR and EL are already GPS synched at Kaiga end.
During the event Auto reclose was successful from KGS end. Due to existence of
fault on B-phase, within 9 mili sec of closure, line CB-2B again tripped. As per
information from Guttur end, insulator flash over took place at tower No:103.
Pending
87/III/4 Tripping of 400 kV Kaiga-
Narendra line-2
06-09-2019 at 4:33
hr.
Line tripped on Zone-1 distance protection operation due to R-
phase to Y phase fault. At Kaiga end line auto-reclosed.
NPCIL (KGS) to review A/R scheme at Kaiga GS. As per A/R logic, any phase to earth fault
detection should lead to opening of the faulted phase and reclosing after dead time. But during
dead time if any subsequent fault occurs it should block A/R and 3-ph trip should be extended.
NLCIL (KGS) NPCIL mail dated 13.12.2019:
Distance protection of Main-2 detected R-ph fault and opened the R-ph pole, initiated A/R to
process.Subsequent to that Y-ph fault detected by Main-1 distance protection within 71 m.sec of
Rph fault and opened the Yph-pole.
Since Y-pole opened within the dead time and main-2 relay extended the close command to both
the pole after laps of dead time as per scheme
Pending
88/III/7 Tripping of 400kV NLC TS-2
Exp- Pugalur line
29-10-2019 at 16:43
hr.
Triggering incident was Y phase to Earth fault in the line. At
Pugalur end, fault was detected in Zone-1 and A/R operated
successfully. At Neyveli TS-2 Exp end, fault was detected in
Zone-1 and A/R not operated.
NLCIL to submit a detailed report regarding the reason for failure of A/R in consultation with
OEM.
NLCIL Yet to be informed Pending
Annexure-II
Page 39 of 39
Sl.No. Element Name Outage date/time Revival date/time Reason for outage Sender/ Receiver Remedial Measures/ Actions taken Remarks
1400KV-NELAMANGALA-TALGUPPA-1 08-09-2019/11:50:00 DISTANCE PROTECTION KPTCL To-be-discussed
2400KV-NELAMANGALA-TALGUPPA-1 19-09-2019/09:04:00 DISTANCE PROTECTION KPTCL To-be-discussed
3220KV-AMBEWADI-XELDEM 24-09-2019/16:59:00 TRIPPED ON C-N FAULT KPTCL/ GED To-be-discussed
4220KV-AMBEWADI-XELDEM 25-09-2019/17:17:00 TRIPPED ON B-N FAULT KPTCL/ GED To-be-discussed
5220KV-AMBEWADI-XELDEM 29-09-2019/13:57:00
TRIPPED DUE TO B-N LINE
FAULTKPTCL/ GED To-be-discussed
6400KV/220KV GUTTUR-ICT-2 04-10-2019/12:27:00 04-10-2019/13:02:00
DIFFERENTIAL PROTECTION
ACTEDKPTCL To-be-discussed
7400KV-BTPS-HIRIYUR-2 11-10-2019/01:47:00 phase to phase fault KPCL/ PGCIL (SR-2) Line owned and maintained by KPTCL
8
220KV-SRISAILAM_RIGHT_BANK-
NAGARJUNSAGAR12-10-2019/12:32:00 12-10-2019/13:14:00 DISTANCE PROTECTION APGENCO/ PGCIL (SR-1) To-be-discussed
9
132KV-KONAJE-MANJESWAR-1 15-10-2019/13:30:00 15-10-2019/14:02:00 DISTANCE PROTECTION KPTCL/ KSEBL
KSEBL: Feeder not tripped at Manjeshwaram
110kV ss.Feeder tripped at Konaji end with
distance protection (Distance 12.63 km from
Konaje end)
10220KV-AMBEWADI-PONDA-2 17-10-2019/14:11:00 TRIPPED ON B-N FAULT KPTCL/ GED To-be-discussed
11400KV-NELAMANGALA-TALGUPPA-1 17-10-2019/18:35:00 TRIPPED ON R-N FAULT KPTCL To-be-discussed
12220KV-KOTHAGUDEM_TPS_V-LOWER_SILE .. 18-10-2019/11:39:00 18-10-2019/12:16:00 TRIPPED ON B-N FAULT TSGENCO/ APGENCO Line not tripped at KTPS end
13220KV-REGULAPADU-ALIPUR-1 29-10-2019/14:02:00 29-10-2019/14:23:00
TRIPPED ON RELAY MAL
OPERATIONAPTRANSCO/ KPTCL
APTRANSCO: Feeder not tripped at Regulapadu
end.
14400KV/230KV NNTPP-ICT-2 29-10-2019/12:24:00 29-10-2019/18:04:00
PRESSURE RELIEF DEVICE
OPERATEDNLCIL To-be-discussed
15220KV-AMBEWADI-PONDA-2 31-10-2019/10:34:00 31-10-2019/12:20:00
TRIPPED DUE TO B-N LINE
FAULTKPTCL/ GED To-be-discussed
16
220KV-SRISAILAM_RIGHT_BANK-
NAGARJUNASAGAR TS04-11-2019/16:34:00 14-11-2019/18:18:00
TRIPPED DUE TO B-N LINE
FAULTAPGENCO/ TSGENCO To-be-discussed
17HVDC 500KV KOLAR_DC Pole 05-11-2019/10:55:00 05-11-2019/13:22:00 ESOF PGCIL (Sr-2) To-be-discussed
18220KV-KOTHAGUDEM_TPS_V-LOWER_SILE .. 05-11-2019/12:13:00 25-11-2019/12:52:00
TRIPPED DUE TO B-N LINE
FAULTTSGENCO/ APGENCO TSGENCO: Line not tripped at our end.
19400KV-KALVENDAPATTU-PUGALUR-2 07-11-2019/12:21:00 07-11-2019/19:55:00 TRIPPED ON B-N FAULT PGCIL (Sr-2)/ TANTRANSCO Line owned and maintained by TANTRANSCO
20220KV-KAIGA-KODASALLY-1 07-11-2019/13:39:00 TRIPPED ON LA BLAST NPCIL (KGS)/ KPTCL To-be-discussed
21220KV-KOTHAGUDEM_TPS_V-LOWER_SILE .. 10-11-2019/10:26:00 TRIPPED ON R-N FAULT TSGENCo/ APGENCO
TSGENCO: KTPS-V to Lower Sileru Feeder not
tripped at KTPS end
22400KV-NELAMANGALA-TALGUPPA-1 11-11-2019/13:09:00 TRIPPED ON R-N FAULT KPTCL To-be-discussed
23400KV-KALVENDAPATTU-VALLUR-1 25-11-2019/12:34:00 25-11-2019/14:29:00 Earth Fault PGCIl (Sr-2)/ NTECL To-be-discussed
Pending Remedial Measures/ Actions taken for the Critical Tripping Incidents (as on 01.05.2020)
Annexure-III
Page 1 of 11
24400KV/220KV TALGUPPA-ICT-2 26-11-2019/21:58:00
Tripped due to Non
availability of TBKPTCL To-be-discussed
25
400KV-SRISAILAM_LEFT_BANK-SATTENPALLI 28-11-2019/09:52:00 28-11-2019/10:44:00 B PHASE TO GROUND TSGENCO/ APTRANSCO
APTRANSCO:Test charged and feeder stood ok.
Status of A/R?
26220KV-AMBEWADI-PONDA-1 04-12-2019/08:23:00
TRIPPED ON SINGLE PHASE
TO GND FAULTKPTCL/ GED To-be-discussed
27400KV/220KV TALGUPPA-ICT-2 04-12-2019/23:10:00
Tripped due to Non
availability of TBKPTCL To-be-discussed
28
400KV/220KV TALGUPPA-ICT-2 07-12-2019/17:48:00
Tripped during hand tripping
of Nelamangala- talaguppa
line
KPTCL To-be-discussed
29220KV-SEDAM-TANDUR-1 08-12-2019/01:38:00 08-12-2019/02:01:00 TRIPPED ON Y-N FAULT KPTCL To-be-discussed
30 400KV-KOLAR_AC-THIRUVALAM-1 28-12-2019/14:10 28-12-2019/19:29 TRIPPED ON Y-N FAULT PGCIL (SR-2)/ PGCIL (SR-1) Fault in SR-I portion of the line.
31 400KV-KOLAR_AC-THIRUVALAM-1 28-12-2019/13:25 28-12-2019/13:58 Y-PHASE FAULT PGCIL (SR-2)/ PGCIL (SR-1) Fault in SR-I portion of the line.
32 220KV-AMBEWADI-XELDEM 30-12-2019/22:22 TRIPPED ON B-N FAULT KPTCL To-be-discussed
33 400KV-GAZUWAKA-VEMAGIRI_PG-1 03-01-2020/10:51 03-01-2020/11:30 TRIPPED ON Y-N FAULT PGCIL (Sr-1) To-be-discussed
34
220KV-AMBEWADI-XELDEM 07-01-2020/12:27 07-01-2020/20:11
H/T due to heavy spark was
observed in Rph limb of the
CB
KPTCL To-be-discussed
35 765KV-SRIKAKULAM-ANGUL-1 08-01-2020/15:17 08-01-2020/16:33 tripped on R-B fault PGCIL (SR-1) To-be-discussed
36 400KV-NELAMANGALA-TALGUPPA-1 08-01-2020/21:24 TRIPPED ON R-N FAULT KPTCL To-be-discussed
37220KV-REGULAPADU-ALIPUR-1 10-01-2020/03:32 10-01-2020/01:57 110KV SIDE PROBLEM APTRANSCO/ KPTCL APTRANSCO: Feeder not tripped at this end.
38
220KV-KOTHAGUDEM_TPS-LOWER_SILERU-1 10-01-2020/14:38 10-01-2020/14:56TRIPPED ON SINGLE
PHASE TO GND FAULTTSGENCO/ APGENCO
TSGENCO: On 10.01.2020 at 14:38 hrs 220KV
KTPS-Lower Sileru1 Feeder was tripped on C
Phase to Ground fault at a distance of 64.64Kms.
After getting clearance from SLDC, line charged
at 14:56 Hrs. Line stood ok.
39 400KV/230KV NTPL-ICT-1 12-01-2020/16:45 12-01-2020/17:56 tripped due to SF6 low NTPL To-be-discussed
40 400KV-NELAMANGALA-HASSAN-1 12-01-2020/06:39 12-01-2020/17:34 TRIPPED ON R-N FAULT KPTCL/ PGCIL (SR-2) To-be-discussed
41400KV-VTPS_IV-SURYAPET-1 12-01-2020/13:58 12-01-2020/15:19 TRIPPED ON B-N FAULT APGENCO/ TSTRANSCO
Fault not in TSTRANSCO jurisdiction. Tree
clearance was done at APTRANSO end.
42 400KV-NELAMANGALA-TALGUPPA-1 12-01-2020/17:15 distance protection KPTCL Fault in KPTCL portion of the line.
43400KV-SIMHADRI_STG2-VEMAGIRI_AP-1 14-01-2020/14:29 14-01-2020/16:12 TRIPPED ON R-N FAULT NTPC(SHM)/ APTRANSCO APTRANSCO:Test charged and feeder stood ok.
44400KV-VEMAGIRI_AP-SATTENPALLY-1 14-01-2020/14:29 14-01-2020/15:21 TRIPPED ON R-N FAULT APTRANSCO APTRANSCO:Test charged and feeder stood ok.
45220KV-REGULAPADU-ALIPUR-1 16-01-2020/13:48 17-01-2020/02:34 RELAY MALOPERATION APTRANSCO/ KPTCL APTRANSCO: Feeder not tripped at this end.
46 400KVNELAMANGALA - HASSAN 21-01-2020/16:32 Tripped on R-N fault KPTCL/ PGCIL (SR-2) Fault in KPTCL portion of the line.
47400KV CHITTOOR KRISHNAPATTANAM 22-01-2020/12:24 22-01-2020/14:49 Tripped on B-N fault APTRANSCO/ APGENCO APTRANSCO:Test charged and feeder stood ok.
48400KV-VIJAYAWADA-NELLORE_AP-1 26-01-2020/13:14 26-01-2020/16:23 Tripped on Y-B Fault APTRANSCO/ PGCIL (SR-1)
APTRANSCO:FAULT not in APTRANSCO
jurisdiction.
49 400KV/110KV KAMUDHI-ICT-3 27-01-2020/14:44 27-01-2020/16:08 LV B-Ph isolator Problem TANTRANSCO To-be-discussed
50 400KV/110KV KAMUDHI-ICT-4 27-01-2020/14:44 28-01-2020/01:32 LV B-Ph isolator Problem TANTRANSCO To-be-discussed
51 HVDC 500KV BHADRAVTAHI Pole 2 27-01-2020/09:34 27-01-2020/14:40 THYRISTOR FAILURE PGCIL (Sr-2) To-be-discussed
Annexure-III
Page 2 of 11
52400KV-HINDUJA-KV_KOTA-2 27-01-2020/08:52 27-01-2020/13:38
TRIPPED ON SINGLE
PHASE TO GND FAULTHNPCL/ APTRANSCO
APTRANSCO:Patrolling done and no visible fault
found.
53765KV-CUDDAPAH-THIRUVALAM-2 28-01-2020/15:21 28-01-2020/16:13
TRIPPED DUE TO R-N
FAULTPGCIL (SR-1)/ PGCIL (SR-2) To-be-discussed
54400KV/230KV NNTPP-ICT-1 28-01-2020/09:32
PRESSURE RELIEF DEVICE
OPERATEDNLCIL To-be-discussed
55
220KV-KOTHAGUDEM_TPS-LOWER_SILERU-1 28-01-2020/13:06 28-01-2020/13:41 TRIPPED ON B-N FAULT APGENCO/ TSGENCO
TSGENCO: On 28.01.2020 at 13:06 hrs 220KV
KTPS-Lower Sileru1 Feeder was tripped on C
Phase to Ground fault at a distance of 54.76Kms.
After getting clearance from SLDC, line charged
at 13:41 Hrs. Line stood ok.
56220KV-THENI-MOOZIYAR-1 30-01-2020/16:24 30-01-2020/20:19 Tripped on Y-B Fault TANTRANSCO/ KSEBL
KSEBL: Feeder tripped onY-B, Zone-1 fault
,Distance – 104.8 km
57220KV-THENI-MOOZIYAR-1 30-01-2020/14:50 30-01-2020/15:30
TRIPPED DUE TO R-N
FAULTTANTRANSCO/ KSEBL
KSEBL: Feeder tripped on R phase to ground
Zone-1 fault ,Distance – 45.4 km
58 400KV/220KV GAZUWAKA-ICT-2 31-01-2020/14:14 220KV SIDE PROBLEM PGCIL (SR-1) To-be-discussed
59400KV-NELAMANGALA-HASSAN-1 31-01-2020/20:31
TRIPPED ON DISTANCE
PROTECTIONKPTCL/ PGCIL (SR-2) To-be-discussed
60 400KV-HOSUR-KOLAR_AC-2 02-02-2020/18:34 02-02-2020/21:01 Tripped on Y-B Fault PGCIL (SR-2) To-be-discussed
61 400KV-KALVENDAPATTU-PUGALUR-2 02-02-2020/14:16 02-02-2020/20:05 Tripped on Y-nFault PGCIL (SR-2) To-be-discussed
62400KV-HINDUJA-KV_KOTA-2 02-02-2020/11:36
TRIPPED DUE TO B-N LINE
FAULTHNPCL/ APTRANSCO To-be-discussed
63400KV-NCTPS_STAGE_II-SUNGAVARACHAT . 03-02-2020/0 00:51
TRIPPED DUE TO R-N
FAULTTANGEDCO/ TANTRANSCO To-be-discussed
64400KV-NELAMANGALA-HASSAN-1 03-02-2020/17:03
R PHASE INSULATOR DE
CAPKPTCL/ PGCIL (SR-2) To-be-discussed
65400KV-NCTPS_STAGE_II-SUNGAVARACHAT . 05-02-2020/12:07 05-02-2020/16:14 TRIPPED ON C-N FAULT TANGEDCO/ TANTRANSCO To-be-discussed
66 400KV-NELAMANGALA-HASSAN-1 05-02-2020/17:48 TRIPPED ON Y-N FAULT KPTCL/ PGCIL (SR-2) To-be-discussed
67400KV-SRISAILAM_LEFT_BANK-SATTENPALLI 06-02-2020/17:48
DT received at sattenapally
endTSGENCO/ APTRANSCO APTRANSCO:Feeder tripped on DT receive.
68 400KV-SRISAILAM_LEFT_BANK-DINDI-2 07-02-2020/23:36 TRIPPED DUE TO B-N LINE TSGENCO/ TSTRANSCO To-be-discussed
69
220KV-KOTHAGUDEM_TPS_V-LOWER_SILERU 08-02-2020/12:35 08-02-2020/12:59TRIPPED AND REASON
AWAITEDTSGENCO/ APGENCO
TSGENCO: On 08.02.2020 at 12:35 hrs 220KV
KTPS V-Lower Sileru Feeder was tripped on C
Phase to Ground fault at a distance of 61.67Kms.
After getting clearance from SLDC, line charged
at 12:59 Hrs. Line stood ok.
70400KV-NELAMANGALA-HASSAN-1 08-02-2020/02:03
TRIPPED DUE TO R-N
FAULTKPTCL/ PGCIL (SR-2) To-be-discussed
71400KV-KALVENDAPATTU-THIRUVALAM-1 09-02-2020/15:42 09-02-2020/16:38
TRIPPED DUE TO R-N
FAULTPGCIL(SR-2) To-be-discussed
72400KV-MEHBOOBNAGAR-RTPS-1 10-02-2020/04:21
TRIPPED AND REASON
AWAITEDKPCL/ TSTRANSCO To-be-discussed
73 220KV-AMBEWADI-XELDEM 10-02-2020/14:54 10-02-2020/18:44 TRIPPED ON B-N FAULT KPTCL/ GED To-be-discussed
74220KV-AMBEWADI-XELDEM 10-02-2020/11:02 10-02-2020/11:18 Tripped at Xeldom end only KPTCL/ GED To-be-discussed
Annexure-III
Page 3 of 11
75
220KV-KOTHAGUDEM_TPS-LOWER_SILERU-1 10-02-2020/11:34 10-02-2020/11:52 TRIPPED ON B-N FAULT TSGENCO/ APGENCO
TSGENCO: On 10.02.2020 at 11:34 hrs 220KV
KTPS-Lower Sileru Feeder was tripped on B Phase
to Ground fault at a distance of 40.61Kms from
KTPS end. After getting clearance from SLDC, line
charged at 11:52 Hrs. Line stood ok.
76400KV-MUNIRABAD-RTPS-1 10-02-2020/03:31
TRIPPED AND REASON
AWAITEDKPCL/ PGCIL (SR-1) To-be-discussed
77400KV-RTPS-BTPS-1 10-02-2020/04:20
TRIPPED AND REASON
AWAITEDKPCL To-be-discussed
78400KV/220KV GAJWEL-ICT-2 11-02-2020/07:13
TRIPPED ON BUCCHOLZ
RELAY OPERATIONTSTRANSCO To-be-discussed
79
220KV-THENI-MOOZIYAR-1 11-02-2020/13:19 11-02-2020/14:16Tripped on B-Phase to ground
faultKSEBL/ TANTRANSCO
KSEBL: Feeder tripped on B phase to ground
Zone-1 fault ,Distance – 61 km
80
400KV/220KV MADAKKATHARA-ICT-2 13-02-2020/17:40 13-02-2020/19:40Tripped on LV Side backup
protectionKSEBL
KSEB: When primary side of 200MVA#1 at
Madakkathara end was charged, ICT#2
tripped.Yard inspected and found no
abnormalities.
81220KV-CHILLAKALLU-SURYAPET-1 13-02-2020/19:20 13-02-2020/19:54
TRIPPED DUE TO R-N
FAULTAPTRANSCO/ TSTRANSCO APTRANSCO:A/R successful at chillakallu end.
82400KV/220KV VEMAGIRI_AP-ICT-1 14-02-2020/15:32 15-02-2020/23:04 Y-ph Insulator stack failure APTRANSCO
APTRANSCO:At Loc no.528 insulator stack failed
and replaced.
83400KV-VEMAGIRI_PG-VEMAGIRI_AP-1 14-02-2020/15:32 15-02-2020/21:03 TRIPPED ON Y-N FAULT PGCIL (SR-1)/ APTRANSCO
APTRANSCO:At Loc no.528 insulator stack failed
and replaced.
84
220KV-KOTHAGUDEM_TPS-LOWER_SILERU-1 15-02-2020/13:29 15-02-2020/16:40 BN fault APGENCO/ TSGENCO
TSGENCO: On 15.02.2020 at 13:29 hrs 220KV
KTPS-Lower Sileru Feeder was tripped on B Phase
to Ground fault at a distance of 89.95Kms from
KTPS end. After getting clearance from SLDC, line
charged at 16:40 Hrs. Line stood ok.
85
400KV-NARNOOR-SRISAILAM_LEFT_BANK-1 15-02-2020/13:18 15-02-2020/14:28 Y phase pole discrepancy APTRANSCO/ TSGENCO
APTRANSCO:Feeder tripped on R ph,G
,momentary fault ,Feeder test charged and stood
ok.
86
220KV-NAGARJUNASAGAR_AP-
NAGARJUNASAGAR_TS15-02-2020/01:15 15-02-2020/02:09 RELAY MALOPERATION APTRANSCO/ TSTRANSCO APTRANSCO:Feeder not tripped at Tallapalli end.
87
220KV-KOTHAGUDEM_TPS_V-LOWER_SILERU 16-02-2020/11:54 16-02-2020/12:18TRIPPED DUE TO B-N LINE
FAULTTSGENCO/ APGENCO
TSGENCO: On 16.02.2020 at 11:54 hrs 220KV
KTPS V-Lower Sileru Feeder was tripped due to
Momentary Ground . After getting clearance
from SLDC, line charged at 12:18 Hrs. Line stood
ok.
88 400KV-DONI-GUTTUR-1 16-02-2020/14:24 16-02-2020/21:17 b-n fault KPTCL To-be-discussed
89400KV/132KV RAMAGUNDAM-ICT-1 16-02-2020/17:39 16-02-2020/19:25
CT BLAST AT
MALYALAPALLY SSNTPC- RMGDM To-be-discussed
90 HVDC 500KV KOLAR_DC Pole 2 17-02-2020/23:59 17-02-2020/00:36 DUE TO HVDC LINE FAULT PGCIL (SR-2) To-be-discussed
91220KV-KOLAR_AC-CHINTAMANAI-1 17-02-2020/23:59 18-02-2020/00:26
TRIPPED DUE TO SPS ON
POLE TRIPPINGKPTCL/ PGCIL (SR-2) To-be-discussed
92
400KV-NP_KUNTA-KOLAR_AC-1 17-02-2020/23:59
Tripped on OV DUE TO
TRIPPING OF KOLAR POLE
2
PGCIL (SR-1)/ PGCIL (SR-2) To-be-discussed
93 400KV-NELAMANGALA-HASSAN-1 17-02-2020/16:05 TRIPPED ON Y-N FAULT KPTCL/ PGCIL (SR-2) To-be-discussed
Annexure-III
Page 4 of 11
94220KV-KOLAR_KAR-KOLAR_AC-2 17-02-2020/23:59 18-02-2020/00:23
TRIPPED DUE TO SPS ON
POLE TRIPPINGKPTCL/ PGCIL (SR-2) To-be-discussed
95220KV-KOLAR_KAR-KOLAR_AC-1 17-02-2020/23:59 18-02-2020/00:23
TRIPPED DUE TO SPS ON
POLE TRIPPINGKPTCL/ PGCIL (SR-2) To-be-discussed
96220KV-KOLAR_AC-CHINTAMANAI-2 17-02-2020/23:59 18-02-2020/00:26
TRIPPED DUE TO SPS ON
POLE TRIPPINGKPTCL/ PGCIL (SR-2) To-be-discussed
97 400KV-NNTPP-PUDUCHERRY-1 17-02-2020/13:38 17-02-2020/14:04 distance protection NLCIL/ PED To-be-discussed
98 220KV-KOLAR_KAR-KOLAR_AC-2 17-02-2020/17:38 17-02-2020/18:12 SPS OPERATED KPTCL/ PGCIL (SR-2) To-be-discussed
99 220KV-KOLAR_KAR-KOLAR_AC-1 17-02-2020/17:38 17-02-2020/18:10 SPS OPERATED KPTCL/ PGCIL (SR-2) To-be-discussed
100 220KV-KOLAR_AC-CHINTAMANAI-1 17-02-2020/17:38 17-02-2020/18:08 SPS OPERATED KPTCL/ PGCIL (SR-2) To-be-discussed
101 HVDC 500KV KOLAR_DC Pole 2 17-02-2020/17:38 17-02-2020/18:33 DUE TO HVDC LINE FAULT PGCIL (SR-2) To-be-discussed
102 220KV-KOLAR_AC-CHINTAMANAI-2 17-02-2020/17:38 17-02-2020/18:08 SPS OPERATED KPTCL/ PGCIL (SR-2) To-be-discussed
103
220KV-SRISAILAM_RIGHT_BANK-
NAGARJUNASAGAR18-02-2020/ 13:26 18-02-2020/19:23 MALOPERATION APGENCO/ TSGENCO To-be-discussed
104
400KV-GOOTY-NARNOOR-1 18-02-2020/17:08 18-02-2020/17:47 TRIPPED ON Y-N FAULT APTRANSCO/ PGCIL (SR-1)
APTRANSCO:Feeder tripped on Y ph,G
,momentary fault ,Feeder test charged and stood
ok.
105
220KV-KADAKOLA-KANIYAMPETTA 21-02-2020/ 02:50 b-n fault KPTCL/ KSEBLKSEBL: Tripping is due to decapping of insulator
at tower location: 184( LMS Kadakola-KPTCL )
106400KV-KALPAKKA-ASUPAKA-1 21-02-2020/13:21 21-02-2020/13:54
TRIPPED DUE TO B-N LINE
FAULTAPTRANSCO/ TSTRANSCO APTRANSCO:A/R successful at Kalapaka end.
107400KV-NELLORE_PG-THIRUVALAM-2 22-02-2020/12:07 22-02-2020/13:05
TRIPPED DUE TO B-N LINE
FAULTPGCIL (SR-1)/ PGCIL (SR-2) To-be-discussed
108 400KV-NELLORE_PG-NPS-2 22-02-2020/12:07 22-02-2020/13:05 B-N FAULT PGCIL (SR-1) To-be-discussed
109 400KV-KOCHI-TRICHUR-2 23-02-2020/14:50 23-02-2020/15:07 TRIPPED ON B-N FAULT PGCIL (SR-2) To-be-discussed
110220KV-CHIKKODI-MUDASANGI-1 23-02-2020/15:04 23-02-2020/19:45
TRIPPED DUE TO R-N
FAULTKPTCL/ WR To-be-discussed
111400KV/220KV GAJWEL-ICT-2 23-02-2020/06:13 23-02-2020/18:39
TRIPPED ON BUCHHOLZ
RELAY OPERATIONTSTRANSCO To-be-discussed
112400KV/110KV KANARPATTI-ICT-4 24-02-2020/09:56
DIFFERENTIAL
PROTECTION ACTEDTANTRANSCO To-be-discussed
113220KV-REGULAPADU-ALIPUR LINE-1 26-02-2020/03:54 26-02-2020/04:16
TRIPPED ON DISTANCE
PROTECTIONAPTRANSCO/ KPTCL To-be-discussed
114 400KV/220KV GAJWEL-ICT-4 27-02-2020/10:45 27-02-2020/19:48 RELAY MALOPERATION TSTRANSCO To-be-discussed
115
220KV-SRISAILAM_RIGHT_BANK-
NAGARJUNASAGAR27-02-2020/06:25 27-02-2020/07:10 TRIPPED ON B-N FAULT APGENCO/ PGCIL(Sr-1) To-be-discussed
116 400KV-GVK-VEMAGIRI_AP-1 27-02-2020/18:10 27-02-2020/19:01 MANUAL ERROR TRIPPING GVK/ APTRANSCO To-be-discussed
117 400KV-KAIGA-GUTTUR-2 28-02-2020/11:49 28-02-2020/13:50 ISOLATOR BREAK DOWN NPCIL (KGS)/ KPTCL To-be-discussed
118 765KV-NIZAMABAD-WARDHA-2 28-02-2020/07:13 28-02-2020/20:18 TRIPPED ON R-Y FAULT PGCIL (SR-1) To-be-discussed
119 400KV-HASSAN-MYSORE-1 01-03-2020/13:57 01-03-2020/16:00 CASCADE TRIPPING PGCIL (SR-2) To-be-discussed
120 220KV-KOZHIKODE-AREACODE-2 01-03-2020/13:57 01-03-2020/14:42 CASCADE TRIPPING PGCIL (SR-2)/ KSEBL To-be-discussed
121 220KV-KOZHIKODE-AREACODE-3 01-03-2020/13:57 01-03-2020/14:42 CASCADE TRIPPING GCIL (SR-2)/ KSEBL To-be-discussed
122 220KV-HASSAN-MRS SHIMOGA-1 01-03-2020/13:57 01-03-2020/14:42 CASCADE TRIPPING KPTCL To-be-discussed
123 220KV-HASSAN-YECHANAHALLI-1 01-03-2020/13:57 01-03-2020/16:29 CASCADE TRIPPING KPTCL To-be-discussed
124 220KV-KADAKOLA-KANIYAMPETTA 01-03-2020/13:57 01-03-2020/18:58 CASCADE TRIPPING KPTCL/ KSEBL To-be-discussed
125 220KV-KOZHIKODE-AREACODE-1 01-03-2020/13:57 01-03-2020/14:30 CASCADE TRIPPING PGCIL (SR-2)/ KSEBL To-be-discussed
126 132KV-KONAJE-MANJESWAR-1 01-03-2020/13:57 01-03-2020/18:44 CASCADE TRIPPING KSEBL/ KPTCL To-be-discussed
127400KV-NELAMANGALA-TALGUPPA-1 01-03-2020/13:57 01-03-2020/14:47
TRIPPED ON
OVERLOADINGKPTCL To-be-discussed
128400KV/220KV KOZHIKODE-ICT-1 01-03-2020/13:57 01-03-2020/14:49
TRIPPED DUE TO
EVACUATION OF LINESPGCIL (SR-2) To-be-discussed
Annexure-III
Page 5 of 11
129 400KV-MYSORE-KOZHIKODE-2 01-03-2020/13:57 01-03-2020/17:13 CASCADE TRIPPING PGCIL SR-2 To-be-discussed
130 400KV-UPCL-HASSAN-2 01-03-2020/13:57 01-03-2020/16:00 CASCADE TRIPPING UPCL/ PGCIL (SR-2) To-be-discussed
131400KV/220KV MYSORE-ICT-3 01-03-2020/13:57 01-03-2020/17:19
TRIPPED DUE TO
EVACUATION OF LINESPGCIL (SR-2) To-be-discussed
132400KV/220KV MYSORE-ICT-2 01-03-2020/13:57 01-03-2020/16:24
TRIPPED DUE TO
EVACUATION OF LINESPGCIL (SR-2) To-be-discussed
133400KV/220KV MYSORE-ICT-1 01-03-2020/13:57 01-03-2020/16:20
TRIPPED DUE TO
EVACUATION OF LINESPGCIL (SR-2) To-be-discussed
134400KV/220KV KOZHIKODE-ICT-2 01-03-2020/13:57 01-03-2020/17:05
TRIPPED DUE TO
EVACUATION OF LINESPGCIL (SR-2) To-be-discussed
135400KV/220KV HASSAN-ICT-2 01-03-2020/13:57 01-03-2020/17:00
TRIPPED DUE TO
EVACUATION OF LINESPGCIL (SR-2) To-be-discussed
136400KV/220KV HASSAN-ICT-1 01-03-2020/13:57 01-03-2020/15:52
TRIPPED DUE TO
EVACUATION OF LINESPGCIL (SR-2) To-be-discussed
137400KV/220KV TALGUPPA-ICT-3 01-03-2020/13:57 01-03-2020/14:47
TRIPPED DUE TO
EVACUATION OF LINESKPTCL To-be-discussed
138400KV/220KV TALGUPPA-ICT-2 01-03-2020/13:57 01-03-2020/14:47
TRIPPED DUE TO
EVACUATION OF LINESKPTCL To-be-discussed
139400KV/220KV TALGUPPA-ICT-1 01-03-2020/13:57 01-03-2020/17:28
TRIPPED DUE TO
EVACUATION OF LINESKPTCL To-be-discussed
140400KV/220KV UPCL-ICT-2 01-03-2020/13:57 01-03-2020/17:28
TRIPPED DUE TO
EVACUATION OF LINESUPCL To-be-discussed
141400KV/220KV UPCL-ICT-1 01-03-2020/13:57 01-03-2020/17:28
TRIPPED DUE TO
EVACUATION OF LINESUPCL To-be-discussed
142 400KV-MYSORE-KOZHIKODE-1 01-03-2020/13:57 01-03-2020/15:00 CASCADE TRIPPING GCIL (SR-2) To-be-discussed
143400KV/220KV KOZHIKODE-ICT-3 01-03-2020/13:57 01-03-2020/17:17
TRIPPED DUE TO
EVACUATION OF LINESPGCIL (SR-2) To-be-discussed
144 400KV-NELAMANGALA-HASSAN-1 01-03-2020/13:57 01-03-2020/15:55 TRIPPED ON B-N FAULT KPTCL/ PGCIL (SR-2) To-be-discussed
145400KV-TALGUPPA-HASSAN-1 01-03-2020/13:57 01-03-2020/17:43
TRIPPED ON
OVERLOADINGKPTCL/ PGCIL (SR-2) To-be-discussed
146 400KV-UPCL-HASSAN-1 01-03-2020/13:57 01-03-2020/18:37 CASCADE TRIPPING UPCL/ PGCIL (SR-2) To-be-discussed
147 400KV-HASSAN-MYSORE-2 01-03-2020/13:57 01-03-2020/17:14 CASCADE TRIPPING PGCIL SR-2 To-be-discussed
148HVDC 500KV GAZUWAKA Pole 1 03-03-2020/11:39 03-03-2020/17:09 Thyristor redundancy failure PGCIL (SR-1) To-be-discussed
149
220KV-SRISAILAM_RIGHT_BANK-
NAGARJUNASAGAR03-03-2020/16:38 03-03-2020/21:27 Distance Protection APGENCO/ TSGENCO To-be-discussed
150220KV-EDAMON-EDAPPON-1 03-03-2020/07:43 03-03-2020/10:21 tripped on bus bar operation KSEBL To-be-discussed
151220KV-EDAPPON-KAYAMKULAM-1 03-03-2020/07:43 03-03-2020/09:13 tripped on bus bar operation KSEBL/ NTPC (KYMKLM) To-be-discussed
152400KV-NAGARJUNASAGAR_PG-RAMAGUNDAM 03-03-2020/17:16 TRIPPED ON Y-N FAULT
PGCIL (SR-1)/
NTPC(RMGDM)To-be-discussed
153 132KV-KODADA-CHIKALLU-1 04-03-2020/00:05 04-03-2020/00:22 TRIPPED ON R-N FAULT APTRANSCO To-be-discussed
154 HVDC 500KV GAZUWAKA Pole 1 04-03-2020/12:28 04-03-2020/04:01 Thyristor side problem PGCIL (SR-1) To-be-discussed
155 400KV-NELAMANGALA-TALGUPPA-1 04-03-2020/06:06 Tripped on R - N Fault KPTCL To-be-discussed
156400KV-NAGARJUNASAGAR_PG-RAMAGUND 05-03-2020/02:22 Tripped on Y- N Fault
PGCIL (SR-1)/ NTPC
(RMGDM)To-be-discussed
157 220KV-KOTHAGUDEM_TPS-NUNNA_AP-1 06-03-2020/14:20 06-03-2020/15:06 TRIPPED ON B-N FAULT TSGENCO/ APTRANSCO To-be-discussed
158400KV-SRIPERUMBADUR-CHITTOOR-1 06-03-2020/15:49 06-03-2020/16:12 TRIPPED ON B-N FAULT TANTRANSCO/ APTRANSCO To-be-discussed
159400KV-NARNOOR-SRISAILAM_LEFT_BANK-1 06-03-2020/18:00
TRIPPED DUE TO JUMPER
CUTAPTRANSCO/ TSTRANSCO To-be-discussed
Annexure-III
Page 6 of 11
160400KV-MALKARAM-RAMAGUNDAM-1 07-03-2020/04:38 trip coil alarm TSTRANSCO/ NTPC(RMGDM) To-be-discussed
161220KV-KOTHAGUDEM_TPS-LOWER_SILERU-1 07-03-2020/13:25 single phase to ground TSGENCO/ APGENCO To-be-discussed
162220KV-KOTHAGUDEM_TPS-LOWER_SILERU-1 07-03-2020/13:25 single phase to ground TSGENCO/ APGENCO To-be-discussed
163400KV-GOOTY-KURNOOL_PG-1 08-03-2020/19:29
TRIPPED DUE TO B-N LINE
FAULTPGCIL (SR-1) To-be-discussed
164 400KV-NIZAMABAD-SHANKARAPALLY-1 08-03-2020/16:34 08-03-2020/20:04 TRIPPED ON Y-N FAULT TSTRANSCO/ PGCIL (SR-1) To-be-discussed
165400KV-NAGARJUNASAGAR_PG-RAMAGUNDAM 08-03-2020/09:35 08-03-2020/13:56 TRIPPED ON B-N FAULT
PGCIL (SR-1)/ NTPC
(RMGDM)To-be-discussed
166
132KV-KONAJE-MANJESWAR-1 09-03-2020/07:59 09-03-2020/08:19
Tripped on over current (Due
to
traction load)
KSEBL/ KPTCL To-be-discussed
167 400KV-KALVENDAPATTU-PUGALUR-1 09-03-2020/09:54 09-03-2020/10:04 relay maloperation PGCIL (SR-2) To-be-discussed
168230KV-KUDANKULAM-TTPS 10-03-2020/06:33 10-03-2020/07:12 TRIPPED ON Y-N FAULT
NPCIL (KKNPP)/
TANTRANSCOTo-be-discussed
169400KV-GAUTAMI-VEMAGIRI_AP-1 11-03-2020/14:53 to avoid circulating currents GMR/ APTRANSCO To-be-discussed
170400KV/220KV JULURUPADU-ICT-2 11-03-2020/18:12
OVER FLUX PROTECTION
RELAY OPERATEDTSTRANSCO To-be-discussed
171132KV-KONAJE-MANJESWAR-1 11-03-2020/18:30 11-03-2020/18:49
TRIPPED ON
OVERLOADINGKPTCL/ KSEBL To-be-discussed
172220KV-KOTHAGUDEM_TPS_V-LOWER_SILERU 11-03-2020/14:05 11-03-2020/15:43 BN fault TSGENCO/ APGENCO To-be-discussed
173 400KV-PAVAGADA-HIRIYUR-2 12-03-2020/10:13 SWAPPING PGCIL (SR-2) To-be-discussed
174 400KV-BHADRAVATHI-RAMAGUNDAM-1 12-03-2020/14:43 12-03-2020/18:37 distance protection NTPC(RMGDM)/ WR To-be-discussed
175
400KV/230KV MADURAI-ICT-3 12-03-2020/02:20 12-03-2020/05:18
LV SIDE H/T TO ISOLATE
BUS (230KV BUS COUPLER
BREAKER Y-PHASE CT
BLASTED)
PGCIL (SR-2) To-be-discussed
176
400KV/230KV MADURAI-ICT-1 12-03-2020/01:20 12-03-2020/04:56
230KV BUS COUPLER
BREAKER Y-PHASE CT
BLASTED
PGCIL (SR-2) To-be-discussed
177
400KV/230KV MADURAI-ICT-2 12-03-2020/01:20 12-03-2020/05:06
230KV BUS COUPLER
BREAKER Y-PHASE CT
BLASTED
PGCIL (SR-2) To-be-discussed
178132KV-KUZHITHURAI-PARASSALA-1 13-03-2020/12:08 13-03-2020/14:50
TRIPPED ON DISTANCE
PROTECTIONTANTRANSCO/ KSEBL To-be-discussed
179 400KV-BIDADI-TUMKUR-1 14-03-2020/11:52 14-03-2020/12:41 R-N FAULT PGCIL (SR-2) To-be-discussed
180220KV-KOLAR_KAR-KOLAR_AC-1 14-03-2020/16:30 14-03-2020/17:32
MAL OPERATION OF POLE
DISCREPANCY RELAYPGCIL (SR-2)/ KPTCL To-be-discussed
181220KV-KOLAR_KAR-KOLAR_AC-2 14-03-2020/16:30 14-03-2020/16:58
OPERATION OF BACK UP
OVER CURRENT RELAYPGCIL (SR-2)/ KPTCL To-be-discussed
182220KV-KOTHAGUDEM_TPS-LOWER_SILERU-1 15-03-2020/12:04 15-03-2020/12:33
TRIPPED DUE TO R-N
FAULTTSGENCO/ APTRANSCO To-be-discussed
183400KV/220KV JULURUPADU-ICT-1 16-03-2020/10:40 16-03-2020/12:18
ICT LV BREAKER TRIPPED
DURING SF6 GAS FILLINGTSTRANSCO To-be-discussed
184 400KV-KHAMMAM-ASUPAKA-1 16-03-2020/11:31 16-03-2020/12:50 TRIPPED ON B-N FAULT APTRANSCO/ PGCIL (SR-1) To-be-discussed
185132KV-ASWAROAPET-KAMAVARAPU_KOTA 16-03-2020/12:30 16-03-2020/12:50
OVER CURRENT RELAY
OPERATEDAPTRANSCO/ TSTRANSCO To-be-discussed
186 400KV-KALPAKKA-ASUPAKA-1 16-03-2020/11:55 16-03-2020/12:50 TRIPPED ON B-N FAULT APTRANSCO/ TSTRANSCO To-be-discussed
Annexure-III
Page 7 of 11
187400KV-GUTTUR-HIRIYUR-1 17-03-2020/20:00 17-03-2020/21:47 Bus bar protection operated KPTCL/ PGCIL (SR-2) To-be-discussed
188400KV-KAIGA-GUTTUR-2 17-03-2020/20:00 17-03-2020/15:31 Bus bar protection operated KPTCL/ NPCIL (KGS) To-be-discussed
189 400KV-PALAKKAD-TRICHUR-2 17-03-2020/15:10 17-03-2020/15:31 TRIPPED ON Y-N FAULT PGCIL (SR-2) To-be-discussed
190400KV-GUTTUR-HIRIYUR-2 17-03-2020/13:06 17-03-2020/13:23
TRIPPED DUE TO B-N LINE
FAULTKPTCL/ PGCIL (SR-2) To-be-discussed
191400KV-NARENDRA-GUTTUR-2 17-03-2020/20:00 17-03-2020/21:38 Bus bar protection operated KPTCL/ PGCIL (SR-2) To-be-discussed
192400KV-NARENDRA-GUTTUR-1 17-03-2020/20:00 17-03-2020/21:25 Bus bar protection operated KPTCL/ PGCIL (SR-2) To-be-discussed
193400KV-GUTTUR-JINDAL-1 17-03-2020/20:00 17-03-2020/22:18 Bus bar protection operated KPTCL/ JSWEL To-be-discussed
194400KV-DONI-GUTTUR-1 17-03-2020/20:00 17-03-2020/21:12 Bus bar protection operated KPTCL To-be-discussed
195220KV-KADAKOLA-KANIYAMPETTA 17-03-2020/13:44 17-03-2020/14:10
TRIPPED DUE TO B-N LINE
FAULTKPTCL/ KSEBL To-be-discussed
196220KV-AMBEWADI-XELDEM 17-03-2020/12:41 17-03-2020/16:21
TRIPPED DUE TO B-N LINE
FAULTKPTCL/ GOA To-be-discussed
197400KV/220KV GUTTUR-ICT-2 17-03-2020/20:00 17-03-2020/21:40 Bus bar protection operated KPTCL To-be-discussed
198400KV/220KV GUTTUR-ICT-1 17-03-2020/20:00 17-03-2020/21:40 Bus bar protection operated KPTCL To-be-discussed
199400KV-GUTTUR-HIRIYUR-2 17-03-2020/20:00 17-03-2020/22:01 Bus bar protection operated KPTCL/ PGCIL (SR-2) To-be-discussed
200400KV-KAIGA-GUTTUR-1 17-03-2020/20:00 17-03-2020/21:55 Bus bar protection operated KPTCL/ NPCIL (KGS) To-be-discussed
201HVDC 500KV BHADRAVTAHI Pole 2 18-03-2020/11:48 18-03-2020/12:37
Failure of PLC 4901
processorsWR To-be-discussed
202220KV-KOTHAGUDEM_TPS-LOWER_SILERU-1 18-03-2020/12:25 TRIPPED ON B-N FAULT APGENCO/ TSGENCO To-be-discussed
203 400KV-KHAMMAM-ASUPAKA-1 18-03-2020/13:11 18-03-2020/14:06 TRIPPED ON B-N FAULT APTRANSCO/ TSTRANSCO To-be-discussed
204 132KV-ASWAROAPET-KAMAVARAPU_KOTA 18-03-2020/07:22 18-03-2020/08:02 Tripped on Y-B Fault TSTRANSCO/ APTRANSCO To-be-discussed
205HVDC 500KV BHADRAVTAHI Pole 2 18-03-2020/11:48 18-03-2020/12:37
Failure of PLC 4901
processorsWR To-be-discussed
206HVDC 500KV BHADRAVTAHI Pole 1 18-03-2020/11:48 18-03-2020/12:46
Failure of PLC 4901
processorsWR To-be-discussed
207 220KV-UDUMALPET_TN-IDDUKKI-1 18-03-2020/06:52 18-03-2020/07:38 TRIPPED ON Y-N FAULT TANTRANSCO/ KSEBL To-be-discussed
208 220KV-CHILLAKALLU-SURYAPET-1 19-03-2020/23:14 19-03-2020/23:42 R-N FAULT APTRANSCO/ TSTRANSCO To-be-discussed
209 400KV-NARNOOR-SRISAILAM_LEFT_BANK-1 19-03-2020/13:32 19-03-2020/19:34 Tripped on Y-B Fault APTRANSCO/ TSGENCO To-be-discussed
210 400KV-JEYPORE-GAZUWAKA-EAST-1 19-03-2020/19:57 19-03-2020/20:41 TRIPPED ON Y-N FAULT PGCIL (SR-1) To-be-discussed
211 400KV-KURNOOL_PG-NAGARJUNASAGAR_P 19-03-2020/12:12 19-03-2020/12:56 tripped on r-n fault PGCIL (SR-1) To-be-discussed
212220KV-THENI-MOOZIYAR-1 20-03-2020/11:39 20-03-2020/12:05 TRIPPED DUE TO R-N FAULT TANTRANSCO/ KSEBL To-be-discussed
213400KV-RTPS-BTPS-1 20-03-2020/02:11 20-03-2020/03:35
TRIPPED ON SINGLE
PHASE TO GND FAULTKPCL To-be-discussed
214
220KV-NAGARJUNASAGAR_AP-
NAGARJUNASAGAR_TS20-03-2020/18:47 20-03-2020/20:06
TRIPPED ON DISTANCE
PROTECTIONAPTRANSCO/ TSTRANSCO To-be-discussed
215220KV-NAGARJUNASAGAR_AP-CHALAKURTHY 20-03-2020/18:47 20-03-2020/19:59
TRIPPED ON DISTANCE
PROTECTIONAPTRANSCO To-be-discussed
216132KV-KONAJE-MANJESWAR-1 20-03-2020/07:41 20-03-2020/08:00
Tripped due to traction
overloadKPTCL/ KSEBL To-be-discussed
Annexure-III
Page 8 of 11
217400KV-MAHESHWARAM_TG-SHANKARAPALLI 20-03-2020/13:38 20-03-2020/17:20 TRIPPED ON B-N FAULT PGCIL (SR-1)/ TSTRANSCO To-be-discussed
218400KV-RTPS-BTPS-1 21-03-2020/02:11 21-03-2020/03:35
TRIPPED ON SINGLE PHASE
TO GND FAULTKPCL To-be-discussed
219
400KV/230KV KUDANKULAM-ICT-1 21-03-2020/12:11 21-03-2020/19:51To control load flow of 230kV
KKNP- S R Pudur lineNPCIL (KKNPP) To-be-discussed
220HVDC 500KV GAZUWAKA Pole 2 21-03-2020/12:15 21-03-2020/14:25
AUXILIARY POWER
FAILUREPGCIL (SR-1) To-be-discussed
221 400KV-GUTTUR-HIRIYUR-2 21-03-2020/13:06 21-03-2020/19:03 TRIPPED ON B-N FAULT KPTCL/ PGCIL (SR-2) To-be-discussed
222 400KV-MADURAI-TIRUNELVELI-2 21-03-2020/14:26 21-03-2020/14:40 TRIPPED ON B-N FAULT PGCIL (SR-2) To-be-discussed
223400KV/220KV GAZUWAKA-ICT-1 22-03-2020/15:45 22-03-2020/17:17
BUS BAR PROTECTION
OPERATED AT LV SIDEPGCIL (SR-1) To-be-discussed
224132KV-KHAMMAM_TS-CHIKALLU-1 22-03-2020/05:00 23-03-2020/05:17
TRIPPED DUE TO R-N
FAULTAPTRANSCO/ TSTRANSCO To-be-discussed
225400KV-NCTPS_STAGE_II-SUNGAVARACHAT 22-03-2020/11:24 TRIPPED ON B-N FAULT TANGEDCO/ TANTRANSCO To-be-discussed
226 400KV-GUTTUR-HIRIYUR-2 22-03-2020/13:07 TRIPPED ON Y-B FAULT KPTCL/ PGCIL (SR-2) To-be-discussed
227400KV-MAHESHWARAM_TG-SHANKARAPALLI 22-03-2020/14:08 22-03-2020/19:02 TRIPPED ON B-N FAULT PGCIL (SR-1)/ TSTRANSCO To-be-discussed
228400KV-MAHESHWARAM_TG-SHANKARAPALLI 22-03-2020/12:36 22-03-2020/13:12 TRIPPED ON B-N FAULT PGCIL (SR-1)/ TSTRANSCO To-be-discussed
229220KV-KOTHAGUDEM_TPS_V-LOWER_SILERU 22-03-2020/11:16 22-03-2020/11:38 TRIPPED ON B-N FAULT TSGENCO/ APGENCO To-be-discussed
230400KV/220KV GAZUWAKA-ICT-2 22-03-2020/15:45 22-03-2020/18:34
BUS BAR PROTECTION
OPERATED AT LV SIDEPGCIL (SR-1) To-be-discussed
231220KV-KOTHAGUDEM_TPS-LOWER_SILERU-1 22-03-2020/10:15 22-03-2020/18:03 TRIPPED ON C-N FAULT APGENCO/ TSGENCO To-be-discussed
232 220KV-UDUMALPET_TN-IDDUKKI-1 23-03-2020/07:37 23-03-2020/12:26 TRIPPED ON Y-N FAULT TANTRANSCO/ KSEBL To-be-discussed
233 400KV-SATTENPALLY-VTPS_IV-2 24-03-2020/12:38 TRIPPED ON R-N FAULT APTRANSCO/ APGENCO To-be-discussed
234 220KV-SEDAM-TANDUR-1 24-03-2020/13:38 24-03-2020/16:43 TRIPPED ON R-N FAULT KPTCL/ APTRANSCO To-be-discussed
235400KV-ALAMATHY-SUNGAVARACHATRAM-2 25-03-2020/12:05 25-03-2020/17:02
TRIPPED DUE TO B-N LINE
FAULTTANTRANSCO To-be-discussed
236400KV-ALAMATHY-SUNGAVARACHATRAM-2 26-03-2020/12:26 26-03-2020/18:57
TRIPPED DUE TO B-N LINE
FAULTTANTRANSCO To-be-discussed
237220KV-KOTHAGUDEM_TPS_V-LOWER_SILERU 27-03-2020/12:05 27-03-2020/14:40 TRIPPED DUE TO R-N FAULT TSGENCO/ APGENCO To-be-discussed
238400KV-GUTTUR-JINDAL-1 27-03-2020/13:12 27-03-2020/19:04 TRIPPED DUE TO R-N FAULT JSWEL/ KPTCL To-be-discussed
239400KV-MUNIRABAD-RTPS-1 28-03-2020/07:11 28-03-2020/08:07 TRIPPED DUE TO R-N FAULT PGCIL (SR-1)/ KPCL To-be-discussed
240400KV-NCTPS_STAGE_II-SUNGAVARACHAT 29-03-2020/09:28 29-03-2020/10:38
TRIPPED ON SINGLE
PHASE TO GND FAULTTANGEDCO/ TANTRANSCO To-be-discussed
241400KV-SRISAILAM_LEFT_BANK-SATTENPAL 29-03-2020/11:33 29-03-2020/10:38
TRIPPED ON SINGLE
PHASE TO GND FAULTTSGENCO/ APTRANSCO To-be-discussed
242220KV-KOTHAGUDEM_TPS-LOWER_SILERU-1 29-03-2020/12:22 29-03-2020/13:19
TRIPPED ON SINGLE
PHASE TO GND FAULTTSGENCO/ SPTGENCO To-be-discussed
243 400KV-VTPS_IV-SURYAPET-1 30-03-2020/13:28 30-03-2020/14:14 TRIPPED ON B-N FAULT APGENCO/ TSTRANSCO To-be-discussed
244 400KV-NEYVELI_TS2_EXP-PUGALUR-1 30-03-2020/15:10 30-03-2020/15:53 TRIPPED ON Y-N FAULT NLCIL/ PGCIL (SR-2) To-be-discussed
245 400KV-HINDUJA-KV_KOTA-1 31-03-2020/12:36 TRIPPED ON Y- N FAULT HNPCL/ PGCIL (SR-1) To-be-discussed
246 400KV-UPCL-HASSAN-1 31-03-2020/14:13 Earth fault Relay Operated UPCL/ PGCIL (SR-2) To-be-discussed
Annexure-III
Page 9 of 11
247400KV-NEYVELI_TS2_EXP-PUGALUR-1 01-04-2020/13:41 01-04-2020/14:13 Single Phase to ground fault NLCIL/ PGCIL (SR-2) To-be-discussed
248400KV-KAIGA-GUTTUR-1 01-04-2020/18:04
tripped due to CT-blast @
kaigaNPCIL (KGS)/ KPTCL To-be-discussed
249400KV-KAIGA-GUTTUR-2 01-04-2020/18:04
tripped due to CT-blast @
kaigaNPCIL (KGS)/ KPTCL To-be-discussed
250220KV-KOTHAGUDEM_TPS-LOWER_SILERU-1 02-04-2020/12:17 02-04-2020/12:37 TRIPPED ON B-N FAULT TSGENCO/ APGENCO To-be-discussed
251 400KV-GOOTY-NARNOOR-1 02-04-2020/13:34 02-04-2020/14:20 TRIPPED ON B-N FAULT PGCIL (SR-1)/ APTRANSCO To-be-discussed
252
220KV-HIRIYUR-GOWRIBIDANUR-1 04-04-2020/14:16 04-04-2020/16:37
TRIPPED DUE TO
BREAKER LOCK OUT AT
GOWRIBIDANUR
KPTCL To-be-discussed
253
220KV-HIRIYUR-GOWRIBIDANUR-2 04-04-2020/14:16 04-04-2020/16:38
TRIPPED DUE TO
BREAKER LOCK OUT AT
GOWRIBIDANUR
KPTCL To-be-discussed
254220KV-PAVAGADA-KSPDCL4 04-04-2020/08:46 04-04-2020/09:26
TRIPPED DUE TO R-B
FAULT IN 33KV FEEDERPGCIL (SR-2)/ KSPDCL To-be-discussed
255 HVDC 500KV BHADRAVTAHI Pole 1 04-04-2020/21:25 04-04-2020/22:40 AC UNDER VOLTAGE WR To-be-discussed
256HVDC 500KV BHADRAVTAHI Pole 2 04-04-2020/13:47 04-04-2020/21:51
AUXILIARY POWER
FAILUREWR To-be-discussed
257
230KV-TTGS-GREENINFRA-1 05-04-2020/21:00 05-04-2020/21:21
High frequency relay
operated
50.20
TANTRANSCO To-be-discussed
258
230KV-TTGS-MYTRAH-1 05-04-2020/21:00 05-04-2020/21:25
High frequency relay
operated
50.20
TANTRANSCO To-be-discussed
259
230KV-TTGS-ORANGESIRONJ-1 05-04-2020/21:00 05-04-2020/21:24
High frequency relay
operated
50.20
TANTRANSCO To-be-discussed
260
230KV-TTGS-BETAMWIND-1 05-04-2020/21:00 05-04-2020/21:22
High frequency relay
operated
50.20
TANTRANSCO To-be-discussed
261 400KV/110KV KAYATHAR-ICT-1 05-04-2020/14:46 05-04-2020/23:08 OIL SURGE RELAY ACTED TANTRANSCO To-be-discussed
262
132KV-KUZHITHURAI-PARASSALA-1 05-04-2020/21:00 05-04-2020/16:22
Tripped at Kuzhutarai end
and
code given to H/T at Parsala
end
KSEBL/ TANTRANSCO To-be-discussed
263 400KV-SRISAILAM_LEFT_BANK-DINDI-1 06-04-2020/14:14 single phase to ground TSGENCO/ TSTRANSCO To-be-discussed
264 220KV-KOTHAGUDEM_TPS-NUNNA_AP-1 06-04-2020/13:39 06-04-2020/17:37 single phase to ground TSGENCO/ APTRANSCO To-be-discussed
265 220KV-SRISAILAM_RIGHT_BANK-DINDI-2 06-04-2020/13:16 06-04-2020/15:55 single phase to ground APGENCO/ TSTRANSCO To-be-discussed
266 400KV-NARNOOR-GHANI-1 06-04-2020/19:07 06-04-2020/21:20 red hotspot APTRANSCO To-be-discussed
267 400KV-NARNOOR-GHANI-2 06-04-2020/19:07 06-04-2020/21:20 single phase to ground APTRANSCO To-be-discussed
268
220KV-UDUMALPET_TN-IDDUKKI-1 06-04-2020/20:05
h/t due to heavy glow at
UDPT
end
TANTRANSCO/ KSEBL To-be-discussed
269400KV-GUTTUR-JINDAL-1 07-04-2020/16:10 08-04-2020/02:53
TRIPPED ON CONDUCTOR
CUTKPTCL/ JSWEL To-be-discussed
270400KV-GOOTY-RAICHUR_PG-1 07-04-2020/19:04 08-04-2020/02:53
LA BLAST AT RAICHUR
(PG)PGCIL (SR-1) To-be-discussed
271400KV-GOOTY-RAICHUR_PG-2 07-04-2020/19:04 07-04-2020/19:54
LA BLAST AT RAICHUR
(PG)PGCIL (SR-1) To-be-discussed
Annexure-III
Page 10 of 11
272400KV-RAICHUR_PG-RTPS-1 07-04-2020/19:04 07-04-2020/20:04
LA BLAST AT RAICHUR
(PG)PGCIL (SR-1)/ KPCL To-be-discussed
273400KV-RAICHUR_PG-RTPS-2 07-04-2020/19:04 07-04-2020/20:08
LA BLAST AT RAICHUR
(PG)PGCIL (SR-1)/ KPCL To-be-discussed
274 400KV-NARNOOR-MAHESHWARAM_PG-1 08-04-2020/15:30 08-04-2020/15:52 TRIPPED ON B-N FAULT APTRANSCO/ PGCIL (SR-1) To-be-discussed
275 400KV-ANAIKADAVU-THAPPUKUNDU-1 08-04-2020/17:42 TRIPPED ON R-Y FAULT TANTRANSCO To-be-discussed
276 220KV-KOTHAGUDEM_TPS-NUNNA_AP-1 08-04-2020/16:53 08-04-2020/17:13 TRIPPED ON R-N FAULT TSGENCO/ APTRANSCO To-be-discussed
277 132KV-ASWAROAPET-KAMAVARAPU_KOTA 08-04-2020/13:20 08-04-2020/17:49 Tripped on Y-B Fault TSTRANSCO/ APTRANSCO To-be-discussed
278 132KV-ASWAROAPET-KAMAVARAPU_KOTA 08-04-2020/07:46 08-04-2020/11:34 Tripped on Y-B Fault TSTRANSCO/ APTRANSCO To-be-discussed
279 132KV-ASWAROAPET-KAMAVARAPU_KOTA 08-04-2020/13:30 08-04-2020/17:19 Tripped on Y-B Fault TSTRANSCO/ APTRANSCO To-be-discussed
280132KV-ASWAROAPET-KAMAVARAPU_KOTA. 09-04-2020/11:54 09-04-2020/16:35 PHASE TO PHASE FAULT TSTRANSCO/ APTRANSCO To-be-discussed
281 230KV-KALVENDAPATTU-THARAMANI 09-04-2020/18:22 B-N FAULT TANTRANSCO To-be-discussed
282400KV-KAIGA-GUTTUR-1 09-04-2020/11:59
TRIPPED ON DISTANCE
PROTECTIONNPCIL (KGS)/ KPTCL To-be-discussed
283400KV-NCTPS_STAGE_II-MANALI-1 09-04-2020/15:10 R-N FAULT TANGEDCO/ TANTRANSCO To-be-discussed
284 230KV-NNTPP-NEYVELI_TS_II-1 09-04-2020/00:12 TRIPPED ON B-N FAULT NLCIL To-be-discussed
285132KV-ASWAROAPET-KAMAVARAPU_KOTA. 09-04-2020/13:51 09-04-2020/18:55 PHASE TO PHASE FAULT TSTRANSCO/ APTRANSCO To-be-discussed
286 220KV-KOTHAGUDEM_TPS-NUNNA_AP-1 10-04-2020/08:28 10-04-2020/14:03 TRIPPED ON R-N FAULT TSGENCO/ APTRANSCO To-be-discussed
Annexure-III
Page 11 of 11
Frequency Set points and House load Operation Details furnished by constituents
Sl.NoPlant Name Utility Name Description Machine Unit No Set Point (low frequency) Set Point (High Frequency)
whether House load operation
capability exists
Genetator-1 & 2
(600MW)
51.50 Hz
2.0 Sec
Genetator-2
(600MW)
51.50 Hz
2.0 Sec
Genetator-1
(600MW)
48.5Hz /2.5 Sec
& 47.5Hz/ 2.0 Sec
Genetator-2
(600MW)
48.5Hz /2.5 Sec
& 47.5Hz/ 2.0 Sec
Genetator-1
(210MW) 47.6Hz/ 1Sec -----
Genetator-2
(210MW) ----- -----
Genetator-3
(210MW) 47.6Hz/ 1Sec 51.7Hz/ 1sec
Genetator-1
(210MW) 47.5Hz/ 3sec. -----
Genetator-2
(210MW) 47.5Hz/ 3sec. -----
Genetator-3
(210MW) 47.5Hz/ 3sec. 51.8Hz/ 1sec
(i) Low and high frequency set points of all generators (including RE) in the
existing/proposed Islanding Schemes. All units 47.5Hz for 28sec -Trip 52Hz for 120 sec. -Trip
(ii) Frequency at which generators are taken to house load operation. All units 47.5Hz for 25sec 52Hz for 100 sec.
Generator-1
210 MW 47.50 Hz /2 sec Not Adopted
Generator-2
210 MW 47.50 Hz / 2 sec Not Adopted
Generator-3
210 MW47.50 Hz / 2 sec Not Adopted
Generator-4
210 MW48.5 Hz / 5 sec 50.75 Hz / 5 sec
Generator-5
210 MW47.6 Hz / 2 sec Not Adopted
Generator-1
210 MW
47.00 Hz / 5 sec
( unit trip)Not Adopted
Generator-2
210 MW47.00 Hz / 5 sec
( unit trip)Not Adopted
Generator-3
210 MW47.00 Hz / 5 sec
( unit trip)Not Adopted
Generator-4
210 MW
47.00 Hz / 2 sec
(House load) Not Adopted
4
TANGEDCO
TANGEDCO
NPCIL
TANGEDCO
House load operation capability not
available for Units -I, II & II and
Available for Iv & V.
Available for all units
Available for all units
2
NCTPS - I
(ii) Frequency at which generators are taken to house load operation.
(i) Low and high frequency set points of all generators (including RE) in the
existing/proposed Islanding Schemes. ( Alarm only)
(i) Low and high frequency set points of all generators (including RE) in the
existing/proposed Islanding Schemes. ( Alarm only)
(ii) Frequency at which generators are taken to house load operation.
NCTPS - II
1
KKNPP3
(i) Low and high frequency set points of all generators (including RE) in the
existing/proposed Islanding Schemes. ( Alarm only)
(ii) Frequency at which generators are taken to house load operation.
TTPS
Annexure-IV
Page 1 of 2
Generator-5
210 MW
47.00 Hz / 2 sec
(House load) Not Adopted
5 NTPC_Simhadri NTPC Frequency low
48.5 Hz , 5 sec delay (Alarm only)
47.4 Hz , 2 sec (trip and unit taken on
house load)
Yes
6 BTPS KPCL No house load operation
7 T(G)TPS GS TANGEDCO No house load operation
8 UPCL UPCL Frequency low and High Frequency set points
48.5Hz, 2sec (Alarm only)
47.7Hz, 2sec (Trip)
47.5Hz, 0.5sec (Trip)
52.1 Hz, 2 sec (Trip)
9Srisailam Right Bank Power
House 220kV APGENCO 7x110=770 MW Yes
10 Lower Sileru PH 220kV APGENCO 4x115=460 MW Yes
11 Donkarayi Canal PH 220kV APGENCO 1x25 =25 MW Yes
12 Upper Sileru PH 220kV APGENCO 4x60=240 MW Yes
13 Machkund PH 132kV APGENCO 3x17+3x23=120 MW Yes
14Nagarjunasagar Right Canal PH
132kVAPGENCO 3 x 30=90 MW Yes
15Nagarjuna Sagar Tail Pond
Power House 132kVAPGENCO 2 X 25=50 MW Yes
16 Penna Ahobilam HES 132kV APGENCO 2 x 10=20 MW Yes
17 Tunga Bhadra Dam PH 66kV APGENCO 4 x 9=36 MW Yes
18 Hampi PH 66kV APGENCO 4 x 9=36 MW Yes
U#l 48Hz(2I) ,47.5Hz(1") 51Hz(1") ,51.5Hz(0.1")
U#2 48Hz(2") ,47.5Hz(1") 51Hz(1I) ,51.5Hz(0.1")
U#3 48Hz(2I) ,47.5Hz(1") 51Hz(1" ) ,51.5Hz(0.1")
U#4 NA NA
U#5 NA NA
U#6 NA NA
U#l 48Hz(5") ,47.5Hz(0.5") 51Hz(2") ,52Hz(0.5")
U#2 48Hz(5" ,47.5Hz(0.5") 51Hz(2") ,52Hz(0.5")
U#3 48.5Hz(5") ,48Hz(2") 51Hz(5") ,51.5Hz(2")
U#1 48Hz(10") ,47.5Hz(2") 52Hz(5") ,53Hz(3")
U#2 48Hz(10") ,47.5Hz(5") 52Hz(5") ,53Hz(3")
U#3 4.8Hz(10") ,47.5Hz(5") 52Hz(5") ,53Hz(3")
U#4 48Hz(10") ,47.5Hz(5") 52Hz(5") ,53Hz(3")
U#5 48Hz(10") ,47.5Hz(5") 52Hz(5" ) ,53Hz(3")
U#6 48Hz(10") ,47.5Hz(5") 52Hz(5") ,53Hz(3")
U#l 46.5Hz(5") ,46Hz(2") 53Hz(5") ,54Hz(1)
U#2 46.5Hz(5") ,46Hz(2") 53Hz(5") ,54Hz(1)
U#l 43Hz(1") 51.6Hz(0.5")
U#2 43Hz(1") 51.6Hz(0.5")
U#l 47.25Hz(5") , 47Hz(1") 52Hz(2"),52.5(0.2")
U#2 47.25Hz(5" ) , 47Hz(1") 52Hz(2"),52.5(0.2")
U#3 47.25Hz(5") , 47Hz(1") 52Hz(21),52.5(0.2")
NES 47Hz(20") , 46.5Hz(1") 52Hz(1" ),52.5Hz(0.5")
U#l 47.5Hz(5" ) , 47Hz(1") 51.5Hz(5"),52Hz(1")
U#2 47.5Hz(5") , 47Hz(1") 51.5Hz(5"),52Hz(1")
U#l 47.5Hz(1") , 47Hz(0.1") 52Hz(21"),52.5Hz(0.2" )
U#2 47:5Hz(1") , 47Hz(0.1") 52Hz(2"),52.5Hz(0.2")
U#3 47.5Hz(1") , 47Hz(0.1") 52Hz(2"),52.5Hz(0.2")
U#4 47.5Hz(5") , 47Hz(1") 52Hz(2"),52.5Hz(0.1")
U#5 47Hz(10" ) , 40Hz(1") 52Hz(2"),52.5Hz(0.1")
U#6 47Hz(10 ") , 40Hz(1") 52Hz(2"),52.5Hz(0.1")
U#l 45Hz(3"),40Hz(1") 52Hz(2"),52.5Hz(0.1")
U#2 48Hz(5"),47.5Hz(5") 52Hz(2" ),52.5Hz(0.1")
U#3 47.5Hz(5"),47Hz(1") 52Hz(2"),52.5Hz(0.1")
U#4 47.5Hz(5" ),47Hz(1") 52Hz(2"),52.5Hz(0.1" )
Not Available
Not Available
Not Available
Not Available
Not Available
Not Available
Not Available
Not Available
Frequency low and High Frequency set pointsKSEBLSengulam
27
Not Available
Panniar25
KSEBL Frequency low and High Frequency set points
Frequency low and High Frequency set pointsKSEBLPallivasal
26
23Idamalayar KSEBL Frequency low and High Frequency set points
Frequency low and High Frequency set pointsKSEBLNeriamangalam
24
Frequency low and High Frequency set pointsKSEBLSabarigiri
21
Kakkad KSEBL Frequency low and High Frequency set points22
Idukki KSEBL Frequency low and High Frequency set points
19
Frequency low and High Frequency set pointsKSEBLLowr Periyar
20
4
TANGEDCO
House load operation capability not
available for Units -I, II & II and
Available for Iv & V.
(ii) Frequency at which generators are taken to house load operation.
TTPS
Annexure-IV
Page 2 of 2
m-R'tfts tTIR: IFAX/SPEEDPOST
'lrn:<f 'H('{> I(
It Government of India~f<twr~ Central Electricity Authority~~ f<twr ufilfct Southern Regional Power Committee
~ - 560 009 mrtn"f~Bengaluru - 560 009
"Web site: www.sroc.kar.nic.in e-mail: [email protected] Ph: 080-22287205 Fax: 080-22259343~/No . ISRPC/SE(O)/20201 ~/Date 24.02.2020
I. Chief Engineer, SLDC, APTRANSCO, Vijayawada2. Chief Engineer, SLDC, KPTCL, Bengaluru3. Chief Engineer (SO), KSEBL, Kalamassery4. Chief Engineer (0), TANTRANSCO, Chennai5. Chief Engineer (P&C), TANTRANSCO, Chennai6. Chief Engineer, SLDC, TSTRANSCO, Hyderabad7. Superintending Engineer- I cum HOD, Puducherry ED, Puducherry8. COM, SR-I, POCIL, Hyderabad9. COM, SR-II, POCIL, Bengaluru10. Executive Director, SRLDC, Bengaluru
Sir,
Sub: SPS schemes implcmentation and mock testing-reg,R ef: CE (P&C), TANTRANSeO letter dated 21.02.2020 (copy enclosed)
The SPS is of paramount importance for secured grid opera tion. The new DTPCs were
commissioned by POCIL at the locations from where the signal was to be extended to the new I
existing identified load reliefs by the states for the Talcher-Kolar, Raichur-Sholapur and
KKNPP-I&2 S1'S schemes. The DTPC commissioning was completed by POCIL in the IS'
quarter of 2019.
The S1'S Distribution Matrix was finalized in the 77lh meeting of 1'CSC held on
21.08.2018 .
Despite sustained follow-up in the ace I 1'CSC meetings, some of the SPS nodes are
yet to be armed which is a matter of serious concern.
In the 164'hOCC meeting held on 11.02.2020, it was noted that all the works except few
nodes in K1'TCL in respect of SPS were completed. 111e works were planned to be completed
by 26.02.2020 and therefore mock test was planned on 27.02.2020. In the 89'h 1'CSC meeting
held on 13.02.2020, it was noted that there were some pending works in respect of nodes of
TANTRANSCO (port confirmation) and KPTCL (wiring issues). TANTRANSCO vide letter
under reference has pointed out that port confirmation in respect of nodes of TANTRANSCO
was yet to be received from SR-II, 1'OCIL and requested for reschedule of the mock test.
This urgent matter needs to be addressed immediately by taking following steps:
Annexure-V
Page 1 of 16
I. All pending works to be completed by states/POCIL by 29.02.2020 (Saturday) .
States/POCIL to coordinate with each other.
2. SPS Distribution matrix is annexed to the 77lh pCSC minutes (available on SRI'C
website).
3. Final mapping / wiring diagram may be furnished by states/I'OCIL along with
modified reliefs, if any.
4. Mock test to be held on 04.03.2020 (Wednesday)
It is kindly requested to issue suitable directions to ensure completion of this urgent
long pending issue.
tj.-<j em:; !Thanking you,
~ I Yours faithfully
mnr: <r~ / End: As above
Copy for kind information:
I. Director (Or.&TM), APTRANSCO, Vijayawada2. Director (Transmission) , KPTCL, Bengaluru3. Director (Tr, SO & S), KSEBL, Thiruvananthapuram4. Director (Operation), TANTRANSCO5. Director (Orid Operations), TSTRANSCO, Hyderabad
Annexure-V
Page 2 of 16
Fron:f.r . S.SEKl(ILAR,B.E"Chief Engineer,Protection and Communication.TI\NTRANSCO,First Floor, 55-Block,144, Anna Salai, Chen na i - 600 002,
TI\NTRflN5CO
~0 7, ....The rviernber seuclilryJ Southern Region Pm':er Commi tte," ( SRPC)
No.29,RzKe COll IS~ cross HOCld,Bengaluru- 560 009
The Execut ive DirectorSouthern Region load Dispatch Centre ( SR1DC)No. ;~9 , R3ce Course cross Road,Ben9aluru- ~()O Oar;
Lr, No. Cl'.jPfl, Cj SEjD/I:PC-4 / AI'.E-S / F.5 I'S SCHEHES/D. No. 'r /20, date d : '~U) 7. . 20 7.0 .
Sir,
Sub: TANTRANSCO - SPS SCHEI'lES ... implementat ion 0 ' Sf'S schemes in TilmilNadu as pel ?eSC77 deliberations - port confirmation req uested to pee!!. -- rc~: .
Ref: l.PCSC 'rr deliberations for SPS schemes.LLr.No.CE/ P&C/SE/D/ EPC-4/ M ,E-5{then Af:E. 3 )!f, SP~; SClIEi"I!:S!D. No.0 3/ ! 9, dated:2ii , i 2, ! 9 .
The port termination to DTPC are still pending for want of port ccnfi rmation (rom PGCJL. The Issuewas addressed to you vide ref cited 2 ami also discus sed if' the :>9'" PCSC 1I j(~eti~g held on 14.02 .20 20 a~
SRPC, BengalunJ. In the, PCSC 891" meetin q, r'1/s. PGCii. assured to Iu rmsh the deteils by 11.02 .2020 bur
the port confi rmation details are not yet received.
A mock lest (or all SPS schemes has been programmed by '; :~.LDC on 27.02.2020 . The receipt of aaSPS 519n;]1at load point car, be ensured on ly aftcr termlnaliou of \,/;";n9 from DTPC loc~ l ion to load point,
Hence it is requested that necessary arranqement mu'{ be fI1~ue to r port cont irrnat ion of each DTPC$of Tamil Nadu and also requested to reschedule the mock test " fler com plet ion of above work.
.- "; • ~_ .. . • . ... I \ . -c
-~~-,,!- _;'~"" >" \ r,). .-\ F-' ,,··· ' .l J ! f .l_ \ bO
- ~_
Chief Engineerl . {':.e
Copy by mail:Copy submit ted to the Direcl or Operatio n / Tr,NTRANSCOCOliI' to th e Chief Engim:er / Grid operat ion I ChenneiCopy to the Chief Engineer / System Operat ion / Cheuna: e•.Tri chy .
. Copy to the Superintending Engineer / LD S, GO / Operation & EXl'cu!,ive Engineers/ I.DC ( by email)Copy to " II the Superin tending Engineers & all Executive cn;j ill cers / Pf,C ( by ernail )
It is requested to ensure the 'Niring from DTPC to load POillt ,,5 per rd cited t&2 and also req ue~~t t?(j
£0 make necessary al l"angernenls for tenn inatlon of wiring to DTPC POlt .
Annexure-V
Page 3 of 16
Raichur-Solapur feeders- Special protection scheme
F.O
F.O
F.O
F.O
F.O
Signal from raichur
Through DTPC i.e RS1
Kolar HVDC
Signal from raichur
Through DTPC i.e RS2
Kolar HVDC
Mysore 400KV
Signal from raichur
Through DTPC i.e RS3
Kolar HVDC
Mysore 400KV
Annexure-V
Page 4 of 16
SPS scheme implementation at Raichur SS
5P -2..
- ~ or ~.,;. - - - -SPS-1B RS-1 2 ssqmm cu cable ,
I&
SPS-3 I\ \
\ IFa HVDC Kolar
/n-
SPS-1A(1) RS-2 2.ssqmm cu cable ~or • I
SPS-3 L DB2s, ,& , DTPC
SPS-1Bt DIP MUX I,
5000 FaI Mysore...---L-
, , Fa .> 400KV SS, ,...---,\
)
SPS-1A(2) RS-3 2.ssqmm cu able
or'l'
SPS-3 J Lor \
SPS-1B I- - .. - .--. - - --- - - - - -DTPC
- MUX r--
Valiant
SPS-1A (1) ---- summated flow of both RCR-SLP is more than 3000MW (import) for ssec.
SPS-1A (2) ---- summated flow of both RCR-SLP is more than 3000MW (import) for 7.ssec.
SPS-1B-------- summated flow of both RCR-SLP is more than 3s00MW (import) for 2.ssec.
SPS-3----------loss of RCR-SLPD/C line more than ls00MW(import) due to tripping of both lines
Annexure-V
Page 5 of 16
Annexure-V
Page 6 of 16
PORT NUMBER at Source/Destination DTPCs provided by PGCIL (SR-2)
S. No Destination Source
DTPC
DTPC
MakeRS1 RS2 RS3 TK1 TK2 TK3 KK1 KK2
1 Ananthapur Kolar DIP5000 1 2
2 Chinakampalli Kolar DIP5000 1 3 4
3 Somayajulapalli Kolar DIP5000 1
4 Kurnool Kolar DIP5000 1
5 Gooty Kolar DIP5000 1 4
6 Gazvel Kolar DIP5000 1
7 Mahboob Nagar Kolar DIP5000 1
8 Budidampadu Kolar DIP5000 1
9 Ramagundam Kolar DIP5000 1
10 Kolar Kolar PLCC
11 Hoody Kolar PLCC
12 Soman Halli Kolar DIP5000 1 4 2
13 Nelamangala Kolar ABB 1 2 3 4
14 Mysore Raichur Valient 1 2
15 Hassan Salem Valient 1
16 Guttur Salem Valient 1
17 Trichur Kolar DIP5000 3 1
18 Kannur Kolar DIP5000 1
19 Pallam Kolar DIP5000 3
20 Edappon Kolar DIP5000 3 4
21 Shornur Salem Valient 1
22 Chalakudy Salem Valient 1
23 Kundra Salem Valient 1
24 Edamon Salem Valient 1
25 Pothencode Salem Valient 1
26 Areacode Salem Valient 1
27 Malaparamba Salem Valient 1
28 Hosur Kolar PLCC 1
29 Madurai Kolar DIP5000 3 1 2 4
30 Karaikudi Kolar DIP5000 1 4
31 Thiruvarur Kolar DIP5000 3 1 4 2&1
32 Trichy Kolar DIP5000 3 1 4 2
33 Arasur Raichur Valient 1 2
34 Salem 400 Kolar DIP5000 2 1 3 4
35 Sriperambadur Kolar DIP5000 1 3 4 2
36 Myvady Salem Valient 1
37 Cuddalore Salem Valient 1
38 Alamathy Salem Valient 1
39 Shoolagiri Kolar PLCC 1
40 Ingur Salem Valient 1
41 Ingur Kolar DIP5000 3 1 4 1
42 Karekal Salem Valient 1
43 Salem 400Kudankula
mValient
1,2,3
,4
5,6,7
,8
44 Kolar Raichur DIP5000 1 2 3 4
45 Kolar Gooty DIP5000 1
46 Kolar NelamangalaDIP5000 1
47 Kolar Madurai/UDPT DIP5000 1 2
PORT NUMBER at
Source/Destination DTPCs
Annexure-V
Page 7 of 16
Talcher-Kolar
Signal -1
220kV Kolar Line 1 & 2
66kV ITI
66kV Pottery Road
66kV Shantiniketan
Talcher-Kolar
Signal -2
66kV Kumbalgod
66kV Jigani 1&2
66kV Kanakpura 1&2
Talcher-Kolar
Signal -3
220kV Chintamani Line 1 & 2
Through PLCC
Hard wiring
WIRING DIAGRAM EXISTING & PROPOSED FOR TALCHER - KOLAR SPS SIGNAL 1, 2 AND 3
Received at 400kV PGCIL Kolar DTPC
Received at 400kV Hoody
Received at 400kV PGCIL Kolar DTPC
Received at 400kV
Somanahalli PGCIL
220kV Hoody
220kV Somanaha
lli
Received at 400kV PGCIL
Kolar DTPC
Annexure-V
Page 8 of 16
66kV Mattanavile
66kV S Belagola
RS-2 Signal66kV
G. Ukkada
66kV
Madeshwa
rapura
66kV Bogadhi
66kV Elwala
66kV
Akkurmole
RS-3 Signal
66kV DK Maidan 66kV Honnali
66kV RK Nagar
66kV CR Patna
66kV Mysore 1
66kV Mysore 2
Through PLCC
Hard wiring
WIRING DIAGRAM EXISTING & PROPOSED FOR RS-2 & RS-3 SPS SIGNALS
Received at 400kV PGCIL
Bastipura DTPC
Received at 400kV PGCIL
Bastipura DTPC
220kV Hootagalli
220kV Hootagalli
220kV Toobinaker
e
220kV K.R. Pete
220kV C.R. Patna
220kV Vajamangal
a
220kV Vajamang
ala
220kV Kadakola
220kV Chamaraj
nagara
220kV Gopalapur
a
220kV HN Pura
Annexure-V
Page 9 of 16
Anchepalya-2
66kV T.G Halli
66kV Huliyur Durga 110kV K.G Temple
66kV Amruthur 110kV Gubbi
KK-1 Signal
110kV Turuvekere
66kV Chelur 110kV Mayasandra
66kV Peresandra
66kV Kanaswadi 66kV Bagepalli line-1
66kV Davanagere 66kV Savalanga
66kV Yeragunta
66kV AvaregereKK-2
Signal
110kV Nagenahalli
110kV Tangli
110kV Neralekere
66kV DVG-1
66kV DVG-2
66kV Chikkamagalur
66kV Hiremaglur
66kV CR Patna line2
Through PLCC
66kV Banavara
Hard wiring 66kV Arasikere
WIRING DIAGRAM EXISTING FOR KK-1 SPS SIGNAL
PROPOSED WIRING DIAGRAM FOR KK-2 SPS SIGNAL
Received at 400kV PGCIL Nelamangala
DTPC
Received at 400kV PGCIL Guttur DTPC
220kV Davanager
e
220kV DB Pura
220kV Anthrasana
halli
220kV Nittur
220kV Honnali
220kV MRS Shivmoga
220kV Kadur
Received at 400kV PGCIL Shantigrama
DTPC
220kVChikkamang
alur
220kV Hassan
220kV Gowribidn
ur
220kV Anchepal
ya
220kV KB Cross
220kVArasikere
Annexure-V
Page 10 of 16
Sl.No.Name of the SPS Trip
Signal
Quantam of
Load relief by
KPTCL in MW
DTPC LocationTripping of loads envisaged at Sub
Stations220kV/110kV/66kV Feeders List Remarks
1Talcher-Kolar SPS
Trip Signal 1 - TK1250 400kV PGCIL Kolar 400/220kV at Kolar PGCIL Station 220kV Kolar 1&2 lines
2Talcher-Kolar SPS
Trip Signal 2 - TK2200
400kV PGCIL Kolar
400kV PGCIL
Somanahalli
From 400kV PGCIL Kolar signal transmitted
to 400kV Hoody then to 220kV Hoody to
trip 66kV feeders
From 400kV PGCIL Somanahalli signal
transmitted to 220kV Somanahalli to trip
66kV feeders
66kV ITI
66kV Pottery Road @ Hoody 220kV
66kV Shantiniketan
66kV Kumbalgod
66kV Jigani 1&2 @ Somanahalli 220kV
66kV Kanakpura 1&2
3Talcher-Kolar SPS
Trip Signal 3 - TK3109 400kV PGCIL Kolar 400/220kV at Kolar PGCIL Station 220kV Chintamani 1 & 2 lines
4Raichur - Sholapur
Trip Signal 2 - RS2100 400kV Bastipura
From 400kV Bastipura, signal transmitted
to 220kV Hootagalli, Tubinakere, K.R.Pet,
C.R. Patna through PLCC to trip 66kV
feeders
66kV Bogadi & Elwala @ 220kV Hootagalli
66kV G.Ukkada @ 220kV Tubinakere
66kV Madeshwarapura@ 220kV KR Pet
66kV Mattanavile & S Belagola @ 220kV CR Patna
5Raichur - Sholapur
Trip Signal 3 - RS397 400kV Bastipura
From 400kV Bastipura, signal transmitted
to 220kV Hootagalli, TK Halli, Kadakola,
Chamarajnagar, Holenarasipura through
PLCC to trip 66kV feeders
66kV Akkurmole @ TK Halli
66kV DK Maidan & RK Nagar @ Kadakola
66kV Honnali @ Chamarajnagar
66kV CR Patna, Mysore 1 &2 @ HN Pura
6Kudankulam Unit I
SPS Signal I - KK1193 400kV Nelamangala
From 400kV Nelamangala, trip signal
transmitted to 220kV Anchepalya, Nittur,
KB Cross, Anthrasanahalli,
Doddaballapura, Gowribidnir through
PLCC to trip 66kV feeders
66kV Anchepalya-2, Huliyur Durga,
66kV T.G Halli & Amruthur @ 220kV Anchepalya
110kV K.G Temple & Gubbi @ 220kV Nittur
110kV Turuvekere & Mayasandra @ KB Cross
66kV Chelur line @ 220kV Anthrasanahalli
66kV Kanaswadi line @ 220kV Doddaballapura
66kV Peresandra & Bagepalli line-1 @ 220kV
Gowribidnur
400kV Guttur
From 400kV Guttur trip signal transmitted
to 220kV Daavanagere and Honnali
through PLCC to trip 66kV feeders
66kV Davanagere, Yaragunta & Avaregere @ 220kV
Davanagere
Savalanga @ 220kV Honnali
Cable should be laid
between DTPC and to
Davanagere & Honnali
PLCC Cabinet
400kV Shantigrama
From 400kV Shantigrama trip signal
transmitted to 220kV Shimoga,
Chikkamangalur, Kadur, Arasikere and
Hassan through PLCC to trip 110kV and
66kV feeders
66kV DVG 1 &2 @ 220kV MRS Shimoga
110kV Nagenahalli, Tangli & Neralekere @ Kadur, 66kV
Chikkamagalur & Hiremagalur @ 220kV
Chikkamangalur,
66kV Arasikere & Banavara @ 220kV Arasikere,
66kV CR Patna -2 line @ 220kV Hassan.
Cable should be laid
between DTPC and
Shimoga & Hassan PLCC
Cabinet
DETAILS OF SPS TRIP SIGNALS AND LOAD RELIEF AT KARNATAKA
Wiring should be
changed from
Nelamangala PLCC
cabinet to DTPC
7Kudankulam Unit II
SPS Signal II - KK2174
Annexure-V
Page 11 of 16
Sl.No.Name of the SPS Trip
Signal
Quantam of Load
relief by KPTCL in MWDTPC Location
Tripping of loads envisaged at Sub
StationsRemarks
1Talcher-Kolar SPS Trip
Signal 1 - TK1250 400kV PGCIL Kolar 400/220kV at Kolar PGCIL Station
2Talcher-Kolar SPS Trip
Signal 2 - TK2200
400kV PGCIL Kolar
400kV PGCIL Somanahalli
From 400kV PGCIL Kolar signal transmitted
to 400kV Hoody then to 220kV Hoody to
trip 66kV feeders
From 400kV PGCIL Somanahalli signal
transmitted to 220kV Somanahalli to trip
66kV feeders
3Talcher-Kolar SPS Trip
Signal 3 - TK3109 400kV PGCIL Kolar 400/220kV at Kolar PGCIL Station
4Raichur - Sholapur Trip
Signal 2 - RS2100 400kV Bastipura
From 400kV Bastipura, signal transmitted
to 220kV Hootagalli, Tubinakere, K.R.Pet,
C.R. Patna through PLCC to trip 66kV
feeders
5Raichur - Sholapur Trip
Signal 3 - RS397 400kV Bastipura
From 400kV Bastipura, signal transmitted
to 220kV Hootagalli, TK Halli, Kadakola,
Chamarajnagar, Holenarasipura through
PLCC to trip 66kV feeders
6Kudankulam Unit I SPS
Signal I - KK1193 400kV Nelamangala
From 400kV Nelamangala, trip signal
transmitted to 220kV Anchepalya, Nittur,
KB Cross, Anthrasanahalli,
Doddaballapura, Gowribidnir through
PLCC to trip 66kV feeders
No Change
400kV Guttur
From 400kV Guttur trip signal transmitted
to 220kV Daavanagere and Honnali
through PLCC to trip 66kV feeders
Work Completed
Signal extended from newly
commissioned DTPC to
Davanagere & Honnali PLCC
panels@ Guttur, Downstream
wiring is ready from KPTCL.
400kV Shantigrama
From 400kV Shantigrama trip signal
transmitted to 220kV Shimoga,
Chikkamangalur, Kadur, Arasikere and
Hassan through PLCC to trip 110kV and
66kV feeders
Signal should be extended from
newly commissioned DTPC to
Shimoga & Hassan PLCC Cabinet
@ Shantigrama by PGCIL,
Downstream wiring is ready from
KPTCL.
DETAILS OF SPS TRIP SIGNALS AND LOAD RELIEF AT KARNATAKA
Work Completed
Signal extended from newly
commissioned DTPC @ Bastipura.
Earlier signal was received @
Nelamangala and transmitted to
Bastipura through PLCC.
Downstream wiring ready from
KPTCL
7Kudankulam Unit II SPS
Signal II - KK2174
Rearrangement of SPS signals @
Kolar PGCIL has to be done as the
load relief is much higher than
the schedule given for karnataka
for TK1 signal. Requested vide
this office letter dated 31.08.2019
(enclosed)
Annexure-V
Page 12 of 16
1
KERALA STATE ELECTRICITY BOARD LTD.(lncorporated under the lndian Companies Act, 1956)Office of the Chief Engineer (Transmission SystemOperation)LD Centre, H.M.T.Colony P.O., Kalamassery - 683 503.Phone: 0484 2555965,2543850, 9496019100 Fax: 04842555950Email : [email protected], [email protected] : www.kseb.in. C IN : U40 1 00KL20 11 S G C027 424
No.CESO/EELD1/AEGS/SPS/2019-201 I I 5'&
'l'o
General Manager(ULDC), SR-II,
PGCIL, Bangalore
Date: 5 108119
Sir,
Sub: Review of Distribution of Loads and Signal Paths of Raichur -SholapurSPS,
Talcher-Kolar SPS, Kundankulam (Relocation of SPS schemes)- reg:
Ref: SRPC/ SE-III IPCSC-761 201815769-804 dated 06.09.2018(Minutes ot l7h
PCSCI meeting )
Wiring from DTPC to Relay on account of the SPS relocation at all location
has been completed. But there is ambiguity regarding the input to be connected at the
DTPC end . So we need the assistance of PGCIL-SR II for completing this task. All
other works from KSEB side has been completed and is ready for end to end testing. It
is requested that necessary steps may taken to complete the same.
\ Chief
ryCopy submitted to : The Member Secretary, SRPC, Bangalore.
Copy to:
1 ) The Deputy Ch i ef E ng i neers,SOC, Ka la massery/Ka n n ur/Th i ruvanatha puram
2 )The Assistant Executive E ng i neer,TNMS, Kala massery.
Yours faithfully,
Annexure-V
Page 13 of 16
Annexure-V
Page 14 of 16
Annexure-V
Page 15 of 16
Annexure-V
Page 16 of 16