15 June 2020 Consultation plan - APA Group
Transcript of 15 June 2020 Consultation plan - APA Group
Document No 18027-PL-A-0001
Rev Date Status Originated/
Custodian Checked Approved
7 29/05/2020 Issued for Use
Kim Stewart Matt Baker Phillip McCutcheon
A&A Lead - VIC Project Manager A&A Manager – VIC, SA
& WA
6 13/09/2019 Issued for Use Bryan Devine Matt Baker Phillip McCutcheon
A&A Lead – VIC Project Manager A&A Manager – VIC, SA
& WA
5 07/01/2019 Issued for Use James Beckett Matt Baker Phillip McCutcheon
A&A Lead – VIC & SA Project Manager A&A Manager – VIC, SA
& WA
4 02/03/2018 Issued for Use James Beckett Matt Baker Phillip McCutcheon
A&A Lead – VIC & SA Project Manager A&A Manager – VIC, SA
& WA
3 30/11/2017 Issued for Use James Beckett Matt Baker Phillip McCutcheon
A&A Lead – VIC & SA Project Manager A&A Manager – VIC, SA
& WA
Consultation plan Crib Point Pakenham Pipeline Project
15 June 2020
i
Consultation plan
Crib Point Pakenham Pipeline Project
Contents
1 Introduction 1
1.1 Purpose and scope 2
1.2 Abbreviations 3
1.3 Document references 4
2 Project overview 5
2.1 The Project 5
2.2 Timeframe 5
2.3 Proponent 8
2.4 Project justification 8
3 Consultation and Engagement approach 9
3.1 APA Policy 9
3.2 Consultation and Engagement Principles 10
3.3 Consultation objectives 11
3.4 Engagement Objectives 12
3.5 Communications Working Group 12
3.6 Consultation outcomes and reporting 13
3.7 Communication tools and techniques 14
3.8 Roles and responsibilities 15
3.9 COVID-19 Response 17
4 Identification of relevant stakeholders 18
4.1 Stakeholder interest level 18
5 Pipeline development and stages of consultation 20
5.1 Phase 1: Initial stakeholder engagement 22
5.2 Phase 2: Obtaining access for surveys 22
5.3 Phase 3: Agreement of pipeline corridor 23
5.4 Phase 4: Completion of regulatory approvals 23
5.5 Phase 5: Pipeline construction 23
5.6 Handover / closeout phase 27
ii
Consultation plan
Crib Point Pakenham Pipeline Project
5.7 Operation and maintenance 28
6 Media 32
6.1 Escalation of media enquiries 32
7 Management of potential impacts 34
8 Compulsory acquisition of land 36
8.1 Pipelines Act 36
8.2 Land Acquisition and Compensation Act 36
9 Project timeframes 38
10 Records management 39
10.1 Personal Information 39
11 Further information 40
11.1 Proponent 40
11.2 Regulatory agencies 41
11.3 Other reference documentation 42
12 Information for the Public (Questions and
Answers) 43
13 Implementation Plan 46
A Glossary 49
B Stakeholder engagement matrix 52
C Project information brochures 56
iii
Consultation plan
Crib Point Pakenham Pipeline Project
Revision history:
Version No. Amended
Summary of amendment(s) Date
0 Section 3.4 – Inclusion of regulatory reporting and reporting template
included in Attachment C.
13/10/2017
1 Section 5.1 – Removal of text in relation to confirmation of route options
prior to consultation.
Section 5.4.2 Inclusion of the ‘Water Minister’ as a key stakeholder.
Section 5.5.4 – Clarification on complaint escalation.
Section 9 – Amendment to indicative timing of project stages in Table 9.1.
Section 11.2.1 – Update to DELWP contact details.
Section 11.2.2 – Update to description of ESV.
Section 11.3 – Update to Australian Standard reference in Table 11.2.
Attachment E – Inclusion of updated project hand-out.
17/10/2017
2 Section 3.4 – clarification to reporting timeframes of consultation events to
DELWP.
Section 11.2.1 – Update to DELWP contact details.
Attachment E – revised consultation materials appended.
30/11/2017
3 Section 2.3 – Enhancement of project justification.
Section 2.3.2 – Clarification on requirement for connection to the VTS at
existing facility.
01/03/2018
4 Title – Change to project name (removal of ‘to’)
Section 2.1 – Addition of greater project definition and schedule update
Section 2.3.2 – Clarification on pipeline route selection process
Section 3.4 – Clarification on acceptance of management documentation
(end of reporting obligations)
Section 5.4 – Update to regulatory requirements and consultation for EES
Section 6 and 7 – Creation of new heading structure and updated
reference to media management (Section 7) and complaint (Section 7)
protocols
Section 10 – updated project timeframes
Section 12 – update to contact details of APA and DELWP
07/01/2018
6 Whole of document revision to reflect changes to project timeline
concerning planning and approvals stage.
12/09/2019
7 Whole of document revision to meet requirements for Pipeline Licence
application, Construction and warranty.
29/05/2020
Note: Changes prior to Revision 0 are not recoded in the revision history.
1
1 Introduction APA Transmission Pty Limited, a subsidiary of the APA Group (APA), is
constructing a new pipeline to facilitate the importation of gas into existing
gas markets in Victoria. The gas importation pipeline will originate in Crib Point,
West Gippsland, and connect to the Victorian Transmission System (VTS) near
Pakenham (the Project).
The Project supports the Gas Import Jetty Project, by AGL Energy Limited (AGL)
which is being developed to ensure the cost effective and secure supply of
gas to customers in Australia (together, the Gas Import Jetty & Project). The
Gas Import Jetty and Project will increase the energy security and supply for
AGL’s customers in south-eastern Australia.
APA has prepared this Consultation Plan to reflect various stages of the project
lifecycle. The overarching intent of the Plan is to address how APA proposes to
consult and interact with stakeholders, particularly landowners and occupiers,
likely to be affected by the Project.
The Plan outlines the program of communications and engagement activities
required to support the ongoing implementation of regulatory processes, such
as completion of the EES, to post-construction and commissioning of pipeline
stages, to minimise project impacts on stakeholders through the project
lifecycle.
All activities performed in accordance with this Consultation Plan shall comply
with the relevant acts, regulations, standards and codes of practice of all
regulatory authorities having jurisdiction over the activities. When conflict exists
between various applicable documents, the following order of preference
shall apply, in decreasing order of precedence:
Acts of law or other legislation;
Government licenses and permits;
APA Standards; and
Local standards.
Where APA requirements are more stringent, they shall take precedence. Any
identified discrepancies in this Consultation Plan should be reported to the
document owner for remedy. If you are reading a hard copy of this document,
please consider it uncontrolled.
2
1.1 Purpose and scope
This Consultation Plan was initially prepared in accordance with Part 4 – Pre-
Licence Process, Division 1 – Consultation Plans of the Victorian Pipelines Act
2005 (Pipelines Act) and requirements of the Pipelines Regulations 2017
(Pipelines Regulations).
This Consultation Plan is also prepared in accordance with Objective 3c and
Sections 128(1) and 135(1) of the Pipelines Act, which set out requirements for
the licence holder to develop sound consultative processes and to consult
any person who owns, occupies or manages the land for the construction and
operation of the pipeline.
The consultation plan meets these requirements by:
Outlining the communication and engagement principles, objectives
and delivery commitments;
Identifying the key Project stakeholders and analysing the key messages
and engagement and communication tools to reach those
stakeholders;
Detailing roles and responsibilities required to carry out the Plan;
Detailing process to monitor and review the consultation performance
and continually improve.
The Consultation Plan is based on the intent of the following guidance
documents:
The Australian Pipelines and Gas Association (APGA) Stakeholder
Engagement Guidelines (2015);
The International Association for Public Participation Australasia (IAP2’s)
Public Participation Spectrum (2014); and
The Victorian Auditor-General’s Office Auditing in the Public Participation
in Government Decision-making – Better practice guide (2015).
These guidelines intend to promote best practice and a positive relationship
between landowners, occupiers and pipeline companies and meeting
relevant regulatory requirements for the content requirements of a
consultation plan.
3
1.2 Abbreviations
The abbreviations used in this document are listed in Table 1-1. A glossary of
commonly utilised pipeline industry terminology has been attached as
Attachment A.
Table 1-1: Abbreviations
Item Definition Item Definition
AGL AGL Energy Limited FSRU Floating storage and
regasification unit
APA APA Group, specifically
APA Transmission Pty
Limited
HSE Health, safety and
environment
APGA Australian Pipelines and
Gas Association
LNG Liquefied Natural Gas
CWG Communications Working
Group
Pipelines
Act
Pipelines Act 2005 (Vic)
DELWP Victorian Department of
Environment, Land, Water
and Planning
Pipelines
Regulations
Pipelines Regulations
2017 (Vic)
EE Act Environment Effects Act
1978 (Vic)
PJ Petajoules
EES Environment Effects
Statement
SMP Safety Management
Plan
EMP Environmental
Management Plan
The Project Crib Point Pakenham
Project
EPBC
Act
Environment Protection
and Biodiversity
Conservation Act 1999
(Cth)
VTS Victorian Transmission
System
ESV Energy Safe Victoria
XIC X-Info Connect
4
1.3 Document references
All work performed in accordance with this Consultation Plan shall be in
conformance with the current issue, including amendments, of those national
and international standards, codes of practice, guidelines and APA
documents listed in Table 1-2.
Table 1-2: APA referenced documents
Item Definition
120‐PR‐QM‐0001 Document Control Procedure
18027-PL-A-0003 Gas Import Jetty and Project Media Management Plan
18027-PL-A-0008 Environment Effects Statement Consultation Plan – Gas
Import Jetty and Pipeline
320-PL-HEL-0015
320-PL-HEL-0016
320-PL-HEL-0017
320-PL-HEL-0018
Operating Environmental Management Plan – VIC
560-PR-QM-0001 Landowner Engagement Procedure
560-PR-QM-0004 Authorised Third Party Works Management Procedure
GD-A-1051 Community Consultation Planning Guide
POL-A-2010 Community Consultation Policy
5
2 Project overview
2.1 The Project
The Project will comprise of a bi-directional gas transmission pipeline to
transport gas from the Crib Point Receiving Facility to the VTS east of
Pakenham. The pipeline will be approximately 57 kilometres long with a
nominal diameter of 600 millimetres. The pipeline will be buried with a
minimum of 1200mm of cover from the top of the pipeline and a minimum 30
metre right of way will predominantly be in place during the construction
phase of the project.
Key components of the Pipelines Works proposed to be undertaken by APA
include:
an underground gas pipeline approximately 57 kilometres (km) long,
between Crib Point and the Victorian Transmission System (VTS) (the
existing gas pipeline network) east of Pakenham
an above ground receiving facility located on land immediately
adjacent to the Crib Point Jetty (Crib Point Receiving Facility)
o The Crib Point Receiving Facility will be used to inject mercaptan
(odourant) into the natural gas to meet VTS gas quality
specifications.
two above ground mainline valve (MLV) stations to be situated along the
pipeline alignment, which will allow for isolation of the pipeline in an
emergency situation
Pakenham Delivery Facility situated in Pakenham East
buried End Of Line Scraper Station (EOLSS) located at the connection
point to the VTS, north of the Princes Highway in Pakenham.
The pipeline and all the associated facilities will be designed, constructed,
commissioned and operated in accordance with AS2885.1 Pipelines – Gas
and liquid petroleum – Design and construction and a Pipeline Licence, which
would be required pursuant to the Pipelines Act.
2.2 Timeframe
The works will be undertaken across an approximately 24 month works
programme commencing in Q3, 2021. The proposed schedule for the project
activities are further detailed in Table 2-1 and Table 2-2.
6
Table 2-1 Pakenham Delivery Facility indicative construction schedule
Construction activity Work period Duration
Mobilisation and site set up Q3 2021 1 month
Bulk earthworks, piling (if
required) and civil
foundations
Between Q3 and
Q1 2022
9 months
Structural, mechanical,
piping and electrical and
Instrumentation installation
Between Q3 2021
and Q4 2022
18 months
Roads, landscaping and
reinstatement
Q3 2022 1 month
Pre-commissioning and
commissioning
Between Q3 2022
and Q4 2022
6 months
Final demobilisation Q4 2022 1 month
Overall timeframe Approximately 18 months construction
and 6 months of commissioning
Table 2-2 Pipeline indicative construction schedule
Construction activity Work period Duration
Mobilisation Q3 2021 1 month
Pipeline construction Between Q3 2021
and Q4 2022
15 months
Hydrostatic testing Between Q3 2022
and Q4 2022
4 months
Reinstatement Between Q4 2021
and Q4 2022
6 months
Commissioning Q4 2022 2 months
Demobilisation Q1 2023 1 month
Overall timeframe Approximately 18 months construction
and 2 months of commissioning
8
2.3 Proponent
APA is Australia’s largest natural gas infrastructure business, owning and/or
operating approximately $19 billion of energy assets. Its gas transmission
pipelines span every state and territory in mainland Australia, delivering
approximately half of the nation’s gas usage. APA has direct management
and operational control over its assets and investments.
APA also has ownership interests in, and operates the Allgas gas distribution
network, as well as operating the Australian Gas Networks (formerly Envestra
Limited), which together have approximately 27,000km of gas mains and
approximately 1.3 million gas consumer connections.
APA currently owns and operates 15,000km of natural gas pipelines, as well as
owning or having interests in gas storage facilities, gas-fired power stations and
wind/solar farms. Further information on APA operations and activities is
available on the APA website: https://www.apa.com.au/
2.4 Project justification
The Victorian economy is highly reliant on gas. The state accounts for more
than 50% of the south-eastern gas demand due to heating during cold winters
and significant, gas-intensive manufacturing plants. Furthermore, New South
Wales and South Australia rely on Victorian gas to top up their supply.
The Australian Energy Market Operator (AEMO) has forecast that Victoria
could experience significant gas shortages, within three years. This is despite
falling state gas consumption. AEMO has identified a need for new gas
reserves and additional gas supply infrastructure to replace declining Bass
Straight reserves or bolster supply from Queensland reserves.
The South West Queensland Pipeline is currently the only pipeline that
connects Queensland to the southern states. Built in 1996, the pipeline has a
maximum capacity of 384TJ/day, which means it is already close to reaching
operational capacity during Australia’s winter months.
Limited by these pipeline constraints, the gas from the Queensland coal seam
gas resources won’t be able to meet demand – even if the currently exported
gas was made available.
9
3 Consultation and Engagement approach
3.1 APA Policy
APA has a Community Consultation Policy (POL-A-2010) that serves to explain
APA’s approach to community consultation. The policy applies to all staff and
contractors of the entities that make up APA Group and/or represent APA in
the community. As such, the Project will be developed in accordance with
the Community Consultation Policy.
The Community Consultation Policy outlines the following values and
commitment with respect to consultation processes:
“APA values and respects its relationships with the communities in which
its assets and operations exist and focuses on ensuring that it remains
engaged with its stakeholders to inform and engage them in meaningful
ways on the activities it undertakes.
APA recognises that every community has insights, knowledge and
experiences that can add value to, or improve the outcomes of,
proposed activities it may take in a location. By tapping into these
insights, knowledge and experiences, APA can improve its decision-
making processes and develop better ongoing sustainable solutions.
APA is committed to meeting all applicable regulatory and legislative
requirements and working with regional government group to fully
communicate its approach and principles.
APA is also committed to building and maintaining relationships with all
its stakeholders and ensuring each stakeholder community is recognised
and listened to as appropriate to its ongoing work or specific projects.”
In addition, APA has developed a Community Consultation Planning Guide
(GD-A-1051), which assists staff to adhere to the above policy when identifying
the appropriate approach and level of consultation for the activity they are
to undertake. In addition to external guidance documents, this guide has
been relied upon in the preparation of this Consultation Plan.
10
3.2 Consultation and Engagement Principles
The following key principles will guide APA’s understanding and application of
this plan for construction of the Project.
The key principles are:
Community engagement and communications – APA will ensure a
proactive, and responsive approach for all communications regarding
the Project to key stakeholders, including (but not limited to),
Commonwealth, State and Local government, stakeholders and owners
and occupiers.
Disruption notification – APA will ensure to provide stakeholders with
details of extent and expected timeline for disruptions. APA will
proactively plan construction to minimise negative impacts to the local
community, communicate impacts to the local community during
disruption to manage community expectations and notify and thank
community for patience on completion of disruptive work.
Community complaints – APA will ensure community complaints
protocols and procedures are implemented as part of the consultation
including response timing for complaints. APA will agree to raise any
community complaints or issues directly with the Corporate
Communications team so that as needed, an engagement approach
and response time can be agreed.
Media – Should media issues occur which relate to the project, APA staff,
contractors will ensure those issues are shared with APA Media contact
and, if relevant, the AGL Media contact in a timely manner (i.e. as soon
as practicable, and generally no more than one hour after receipt) and
all statements made in relation to the Pipeline are agreed between the
Project team and Corporate Communications team before being
issued.
Media contacts – APA will designate key media contacts to enable
timely preparation and release of responses. Refer to Section 6
Designated media contact.
Land access – APA commits to provide prior notice as formally agreed
with landholders when access is required and to be respectful of private
property.
11
3.3 Consultation objectives
The primary objectives of the consultation activities proposed under this
Consultation Plan are to:
Be consistent: Ensure a consistent consultation approach is adopted
during the Project.
Meet expectations: Meet the statutory requirements and expectations of
regulatory agencies in relation to the consultative processes used by the
Project for landowners and occupiers.
Be timely: Ensure that consultation activities enable landowners and
occupiers to better understand the Project through the timely distribution
of project information that is presented in an understandable format.
Be genuine: Ensure that APA is able to understand the views of
landowners and occupiers.
Be transparent: Ensure landowners and occupiers are sufficiently
informed about the Project, the aspects that they can influence, and
their rights.
Be clear on the negotiables: Allow landowners and occupiers to have
input into those aspects of the Project that could affect them.
Have an open process: Outline the process of consultation with
landowners and occupiers, to ensure consistency with regulatory
requirements.
This Consultation Plan is an action document that guides staff in undertaking
and reporting on community consultation and engagement for the Project. It
sets out strategies and activities that need to be taken and aligned to the
project development timeframe.
12
3.4 Engagement Objectives
APA values and respects its relationships with stakeholders and communities
within which our assets and operations exist. We are committed to building
and maintaining long term relationships with all stakeholders of the Project, as
well as meeting all applicable regulatory and legislative requirements.
The approach to stakeholder engagement will be guided by the following
objectives:
No surprises: Inform and engage community members and key
stakeholders early in the process, and ensure they remain fully informed.
Be inclusive: Ensure the community has easy access to clear and concise
information about the Project, ensuring all communications use
language (e.g. non-technical language) appropriate to each
audience.
Be honest and act with integrity: Always use facts and speak the truth. If
the answer is not known then the question will be taken on notice, the
appropriate stakeholder spoken with and a response delivered
promptly.
Be responsive: Respond to all stakeholder contact in a timely manner
and make every effort to resolve issues to the satisfaction of all involved.
Be a part of the community: Use the Project to contribute to stronger local
communities and provide economic and social benefit.
Honour all obligations: Deliver on commitments made to the community
and stakeholders.
3.5 Communications Working Group
As APA’s pipeline connects to AGLs Gas Import Jetty Project it is important that
stakeholders with interests in both components are appropriately engaged by
APA and AGL consultation. While APA undertook its own program of
consultation on the planning of the Project, it also joined AGL to deliver a
comprehensive communications and engagement program with project
stakeholders on the broader project process.
To support a consistent approach to communications and engagement
activities on the Project and the Gas Import Jetty project, APA and AGL
formed a Communications Working Group (CWG), which includes
participation of key APA and AGL personnel.
13
The CWG will actively manage key messaging statements, communications
and Frequently Asked Questions and update these in line with developments
and relevant customer, media or other stakeholder reactions or feedback.
3.6 Consultation outcomes and reporting
APA is focused on achieving positive community consultation outcomes as
part of its business activities. As such, the following consultation outcomes will
be utilised to monitor the progress of consultation activities completed as part
of the Project:
Positive relationships formed between APA and affected stakeholders;
Affected stakeholders are appropriately notified and engaged before
any activity starts that may or will impact them or their environment;
Clear and transparent information provided to allow the community to
engage and respond appropriately to our consultation processes;
Appropriate forums offered and provided to ensure full understanding of
the impact APA may have on community activity, the environment or
land; and
APA is seen as a business of integrity that is respectful of the communities
within which it operates, while being fully engaged and accountable for
its activities.
Specific criteria with respect to desired outcomes have been developed for
each phase of the consultation programme. These criteria are outlined in
Section 5.
14
3.7 Communication tools and techniques
The following tools and techniques will be used by APA to engage with
stakeholders and the wider community during construction phase, if required.
Table 3 Communication tools and techniques
Digital and print communication
Direct
correspondence
(email or post)
Individually addressed letters delivered to impacted stakeholders to
inform them of specific Project information
Fact sheets and
brochures
A suite of material: from initial overview, history, field investigations,
design progress through to statutory planning and construction.
Available online (in an accessible, HTML format) and in hard copy for
face to face events and distribution to community outlets.
Posters and
signage
Posters, banners and signage to help increase local awareness of the
Project.
Media update Local print, digital advertising and radio to help inform people about the
Project and feedback opportunities.
Website Dedicated Project webpage which will be updated promptly as new
information becomes available. Content prepared in line with
accessibility guidelines (WCAG 2.1).
Milestone updates Sent at regular intervals (milestone triggers) to keep stakeholders and
landowners and occupiers informed of Project information.
Engagement
Owners and
occupiers
Regularly communicating with landowners and occupiers located within
the proposed pipeline route. Includes door-knocking activities.
Stakeholder
meetings
Face-to-face communication through meetings and briefings, targeted
and on request.
Community hub/
drop-in facility
The leasing of a shop or office space that remains open during general
business hours to provide an easily accessible forum to ask questions
and learn about the Project. Estimated opening in Q3 2020.
Community
presentations
Presentations to identified interest groups of the Project such as councils,
stakeholders or government representatives.
Email and
telephone
Receiving and responding to enquiries via a 1800 phone number and
community email address for queries. All calls, responses and actions
required are to be recorded in an accredited stakeholder database.
15
3.8 Roles and responsibilities
APA will provide clear and accessible information to the community for the
pipeline Project and who involved with delivery of the Project should be
contacted for queries and information. Confusion over these matters can
cause stakeholder frustration, leading to a breakdown in communication and
potential loss of trust with the overall Project.
3.8.1 Stakeholder Engagement Responsibilities of APA
It is the responsibility of APA to undertake the following in relation to
engagement with stakeholders: prepare and comply with this plan;
create and provide Project information materials, such as milestone
updates or notifications;
establish and undertake contact with all identified stakeholders in
accordance with the Stakeholder Engagement matrix (Attachment B);
conduct stakeholder engagement to facilitate the construction and
permitting of the Project;
prepare contact notes for all external engagement in relation to
the Project;
provide land access / communication-specific introductions for any
contractors and consultants engaged to conduct stakeholder relations
activities;
review and authorise all formal contact materials that are available to
the community, stakeholders, subcontractors and consultants
review and authorise all official communications on the Project; and,
Refer complaints or requests for consultation on matters regarding Jetty
Works or installation of the FSRU to AGL.
16
3.8.2 Stakeholder Engagement Responsibilities of Construction Contractors
It is the responsibility of the construction contractor to undertake the following
in relation to engagement with stakeholders in the lead up to and during the
construction stage: develop a Construction Landowner and Stakeholder Interface Plan, or
the like, which outlines procedures on potential risks, impacts, mitigations
and accountabilities in compliance with this Plan
conduct any ad hoc stakeholder engagement in a responsible manner,
representing the Project, using the Key Messages and materials provided
in this Consultation Plan;
refer any third-party enquiries or requests for information to relevant APA
representative; and,
refer any complaints from stakeholders to an APA representative within
2 hours so that immediate action can be taken. Contractors and
consultants should address immediate safety concerns from
stakeholders but otherwise must await guidance from APA before
responding to complaints.
3.8.3 Stakeholder Engagement Responsibilities of AGL
It is the responsibility of AGL staff, contractors or consultants to undertake the
following in relation to engagement with stakeholders: Conduct stakeholder engagement to facilitate the construction and
operation of the Jetty Works and installation of the FSRU only; and,
Where a stakeholder makes a complaint to AGL regarding Pipeline
Works or matters relating to construction of the pipeline, the complainant
should be delegated to an APA representative within 2 hours to allow a
timely response to that complaint.
17
3.9 COVID-19 Response
As at April 2020, due to the coronavirus (COVID-19) pandemic, the Federal
Government has enforced the following to contribute to minimising the spread
of the virus:
Essential travel only – Everyone to work from home where possible, and
only leave your house for exercise, work and medical care.
Social Distancing – maintain a distance of 1.5m from any individual you
do not reside with until further notice.
At the time of writing this document, a Review to APA’s Landholder
Engagement strategy has been developed as a consistent approach to
alternative landholder and external party engagement during the COVID-19
pandemic. APA would comply with the latest Government guidelines on
public restrictions. During this time, APA encourages offering digital
communications (such as video meetings) or text message, to maintain
communication, but to avoid face-to-face contact as far as practicable.
Continuing negotiations during times of COVID-19
As the project prepares for approvals during the ongoing uncertainty of the
COVID-19 health and economic crisis, APA recognises that land negotiations
can be complex and may cause additional concern to some landholders.
All Landholders will be treated in a sensitive and respectful manner. If
Landholders express feelings of additional stress and hardships, the team will
encourage the Landholder to seek free confidential support through
counselling services such as Beyond Blue or Lifeline Australia, which can be
accessed by calling:
Beyond Blue: 1300 22 4636
Lifeline Australia: 13 11 14
18
4 Identification of relevant stakeholders This Consultation Plan has been prepared to engage and consult with
stakeholders that may be impacted by the Project. The Consultation Plan
generally seeks to engage with stakeholders such as the general community,
private and public landowners, land occupiers, businesses, regulatory
agencies, indigenous groups and local interest groups directly impacted by
the Project.
As a minimum, stakeholders that are to be engaged as part of this
Consultation Plan are identified in Attachment B. The matrix in Attachment B
also includes responsibilities for engagement and ongoing relationship
management. It is with these parties that APA seeks to build an open, ongoing
relationship to facilitate clear channels of communication and feedback. APA
will be responsible for all consultation in relation to the development of the
pipeline. APA will liaise with AGL in regards to any broader consultation
regarding the importation of gas or the operation of the port or jetty
component as it is the responsibility of AGL.
4.1 Stakeholder interest level
The stakeholders identified in Attachment B will have varying levels of interest
in the Project and as such will require tailored engagement and consultation
approach to ensure issues are identified and managed appropriately.
A stakeholder can be identified as anyone who is interested in the project, is
impacted by the project or has influence in the decision-making process. For
the Project, stakeholders have been grouped into one of three categories to
ensure the appropriate engagement approach is utilised:
Approvers: those who are directly involved in the approvals and ongoing
regulatory requirements
Influencers: Those who influence the project outcomes but are not
directly involved in the decision-making process
Interested parties: those who have an interest in the project but are not
directly involved or impacted.
Stakeholders are grouped in the identified categories in the Table 4-1.
19
Table 4-1 Stakeholders
Approvers Influencers Interested Parties
Department of the
Environment and Energy
Minister for Environment,
Energy and Climate
Change
Energy Safe Victoria
Mornington Peninsula Shire
Council
City of Casey Council
Cardinia Shire Council
Landowners and
occupiers impacted by
the pipeline
Neighbouring landowners
and occupiers
Department of
Environment, Land, Water
and Planning
Relevant local, State and
federal members of
Parliament
Bunurong Land Council
Aboriginal Corporation
(and others as notified by
Aboriginal Affairs Victoria)
South East Water
VicRoads
VicTrack
Telstra
Save Westernport
Preserve Westernport
Action Group
Crib Point Advisory Group
Environment Victoria
Bass Coast Shire Council
20
5 Pipeline development and stages of consultation The Consultation Plan has been developed around different stages of the
Project’s development. These stages form logical phases of consultation, with
distinct aspects in relation to the provision of information, the method of
consultation and level of engagement required with relevant landowners and
occupiers for each stage. The relevant stages along with a description of the
likely consultation requirements for each stage are illustrated in Figure 5.1.
The identified stages of development and phases of consultation have been
identified as follows:
1. Initial stakeholder engagement;
2. Obtaining land access for surveys;
3. Agreement on pipeline corridor;
4. Completion of regulatory approvals;
5. Pipeline construction; and
6. Pipeline operation.
These stages generally follow the APGA Stakeholder Engagement Guidelines
(2015); stages of planning, design, construction, operation and
decommissioning. The following sections of this Consultation Plan provide
greater detail on the purpose, means and timing of each stage of the Project’s
development. The proposed schedule of each of these stages for the Project
is detailed in Section 9.
Throughout the development of the Project, landowners and occupiers have
been encouraged to actively participate in discussions with APA
representatives and raise questions where they may have concerns. Where a
query cannot be addressed by APA personnel (generally experienced land
access officers) to the satisfaction of the landowner or occupier, a more
detailed response has been provided from an appropriate level of expertise.
21
Figure 5.1: Summary of project stages
Initial Stakeholder Engagement
•Establishment of landowner database (e.g. title searches, landowner addresses, etc.) and engagement of affected landowners - Once Department has approved the Consultation Plan
•Meeting with regulatory agencies and other related stakeholders
•Provision of project related information, discussion on project and collection of information to populate the landowner database
Obtaining Land Access for Surveys
•APA to seek agreement for land access from affected private and public landowners for studies (e.g. geotechnical, environmental and cultural heritage)
•Clarification of any specific conditions or constraints in relation to land access
•APA to issue of Notice of Intention to Enter Land for Survey (as required by the Pipelines Act)
•Underake required surveys in accordance with any landowner agreements
Agreement on Pipeline Corridor
•APA to issue Notice of Pipeline Corridor (as required by the Pipelines Act) to affected landowners
•APA to consult with affected landowners to negotiate an easement to allow for construction and operation of the pipeline
•Easement negotiations likely to include discussions relating to pipeline route, constuction access arrangements , compensation, rehabilitation of construction disturbance and ongoing access requirements
Completion of Regulatory Approvals
•APA undertakes the Pipeline Licence application process - requires public notification of the Pipeline Licence application (in regional newspaper) and issue of Notice of Pipeline Licence Application to affected landowners, occupiers and stakeholders once application has been lodged
•APA completes Environment Effects Statement and EPBC Act assessment processes
•APA receives Pipeline Licence, regulatory approval of SMP and EMP and completes any other secondary approvals as directed by the Minister for Planning
Pipeline Construction
•APA will engage a suitably experienced construction contractor to complete the Pipeline Project
•Construction is proposed to commence once APA has received all requlatory approvals and has obtained required land tenure agreement with landowners, occupiers and other affected parties
•Following construction the pipeline will be tested, commissioned and disturbance area will be rehabilitated
Pipeline Operation and Maintenance
•Following construction and rehabilitation access requirements are only for infrequent and periodic inspections and maintenance (as required)
•Anticipated operational period of the asset is likely to be in the order of 60 years
•APA will be required to consult with the government and other stakeholders in the future regarding the decommissioning of the asset
22
5.1 Phase 1: Initial stakeholder engagement
This phase of consultation is the first time landowners and occupiers have
contact with APA.
As part of the project establishment processes, APA developed a landowner
database and a process for recording consultation with landowners and
occupiers who have or may have the pipeline construction works on their
property.
A letter explaining APA’s intended approach for dealing with landowners and
outlining the various phases of the Project initiated the consultation process.
This correspondence was intended to provide an overview of the
development of pipelines. Follow up consultation activities aimed to provide
greater detail on the development of pipelines and answer any queries
landowners and occupiers had regarding gas pipelines.
As part of the initial stakeholder engagement, APA also liaised with key
regulatory approval authorities and interested stakeholders, such as
indigenous groups to inform them of the project activities and likely
timeframes.
5.2 Phase 2: Obtaining access for surveys
Following the initial engagement and introduction to the Project, APA
negotiated access to land for necessary field studies (e.g. geotechnical,
environmental and cultural heritage). Access to both private and public land
was negotiated in this phase. These surveys were necessary for APA to
understand any potential constraints in relation to construction and operation
of the pipeline and to inform the specialist studies necessary for the
preparation of management plans.
Depending on the level of comfort that affected landowners had with the
introduction to the Project and initial engagement (refer to Section 5.1), the
request to access land for surveys may have formed part of the initial
landowner meeting. For some affected landowners and revealed occupiers,
multiple meetings to discuss the Project and subsequently to discuss the
requirements of surveys were required.
23
5.3 Phase 3: Agreement of pipeline corridor
Following completion of the required surveys, APA had an indication of
constraints and minor alterations required to the pipeline route from a
technical and environmental perspective Alterations to the initial pipeline
corridor occurred as a result of consultation and engagement of landowners
and occupiers in relation to impacts to potential impacts on property
management.
This phase of the consultation informed an agreement with landowners and
occupiers on the location of the pipeline and any relevant arrangements that
the parties agreed on to minimise impacts from the construction and
operation of the Project.
Consultation in this phase will also focus on identifying any property specific
requirements which, once the project is approved, need to be
communicated to the construction contractor.
5.4 Phase 4: Completion of regulatory approvals
As part of the regulatory approval process, APA will be required to obtain any
necessary State and Commonwealth approvals applicable to the Project.
At a State level, APA is to obtain a Pipeline Licence under the Pipelines Act
following the completion of the Environment Effects Statement (EES) under the
Environment Effects Act. At a federal level, the Project was determined to be
a controlled action under the Environment Protection and Biodiversity
Conservation Act 1999 (EPBC Act) (EPBC 2018/8297) and will undergo
assessment and approval under the EPBC Act. The Project will be assessed
under the assessment bilateral agreement with Victoria.
5.5 Phase 5: Pipeline construction
Pipeline construction will be completed on a production line basis with a
sequence of activities progressing along the pipeline route. It is expected
there will be localised access and amenity impacts during the construction of
the pipeline. Eight social mitigation measures have been developed that
address site access, traffic management, community, stakeholder
management, business and visual amenity (noise, vibration, air quality, light
and visual) during construction.
24
APA will engage a suitably experienced construction contractor to undertake
construction of the Project. The consultation associated with this phase will
provide landowners and occupiers with sufficient information to ensure they
are fully aware of the likely activities prior to the commencement of
construction.
During construction it is important that landowners and occupiers are
provided with details of communication paths to notify and communicate
with construction personnel. APA will do appropriate introductions to
Construction Land Liaison team. Following construction, communication will
be relevant to the reinstatement and rehabilitation of disturbed areas.
5.5.1 Purpose of the consultation
The purpose of the consultation associated with this phase is as follows:
1. To advise landowners and occupiers of the construction commencement
and details of the proposed construction program;
2. To introduce the construction contractor’s representative to the
landowner and occupier;
3. To advise the landowner and occupier of the appropriate communication
protocols with both APA and the construction contractor during the
construction period;
4. To confirm with the landowner, occupier and the construction contractor
property specific requirements that are to be followed with respect to
individual property requirements, to minimise project risks;
5. To provide timely construction information and notifications in order to
inform and minimise impacts on landowners and occupiers (where
required);
6. Address enquiries, issues and complaints that may arise during the
construction program; and
7. Inspection of the reinstated areas following construction and rehabilitation
to obtain landowner and occupier sign-off on the reinstatement (damage
release).
5.5.2 Means of consulting with stakeholders
5.5.2.1 Pre-construction
As per previous phases of consultation, face-to-face consultation will continue
to be the primary form of communication, with the provision of additional
information resources (e.g. print or digital handouts and brochures)
undertaken as necessary. APA will provide landowners and occupiers with
25
relevant information confirming that the Project is planned to proceed and
the likely dates for construction of the pipeline. This notice will also include
reference to the engaged construction contractor.
APA will introduce the landowner and occupier to the construction
contractor’s representative for the works. In addition to introducing the parties,
the construction contractor will complete a property inspection report that
details the contact information for the landowner and occupier, any above
or below ground assets potentially impacted, and any operational
requirements that need to be addressed by the construction contractor. This
meeting ensures that these matters have been communicated effectively
and to the satisfaction of the landowner, occupier and APA.
5.5.2.2 Construction
APA and the construction contractor will also formalise and communicate the
appropriate communication paths for landowners and occupiers to follow
during construction. The construction contractor is responsible for answering
direct enquiries with landowners and occupiers regarding scheduling of
activities and other minor issues, though APA representatives will continue to
be involved in preparing general communication or notifications. APA
personnel will investigate and respond to any landowner or occupier claims
or losses as necessary in consultation with the construction contractor.
Notifying owners, occupiers and stakeholders
Notifications will be sent to owners, occupiers and stakeholders to ensure
construction is undertaken as efficiently as possible, while ensuring the owner,
occupier or stakeholder can conduct their normal operations and activities
with as little disturbance as possible. Communications may relate to changes
to project updates, schedule changes, advising of stand down periods, and
where to call for assistance.
5.5.2.3 Reinstatement and Rehabilitation
APA and the construction contractor will also liaise with landowners and
occupiers to ensure that they are satisfied with the reinstatement of soil,
landforms and vegetation along the construction footprint required for
rehabilitation of the area. This process will be undertaken by both parties for a
final clearance of the disturbed areas with the landowner and occupier. APA
will then provide any relevant payment of damage releases and seek sign-off
of a damage release form indicating that the restoration of land has been
completed to an acceptable standard and the landowner and occupier are
prepared to accept the disturbed area.
26
5.5.3 Timing of consultation
5.5.3.1 Pre-construction
Upon completion of regulatory approvals and the construction contract is
awarded, APA would provide relevant information to all landowners and
occupiers advising them of the appointment of the Construction Contractor.
The notification will provide landowners and occupiers a program of the works
to be carried out and the timeframes.
APA would contact landowners and occupiers to schedule a meeting for
more specific timeframes for the upcoming works. Material would be provided
outlining the construction program and phases that would be followed.
Pre-construction condition photos
Pre-construction condition photos would be taken during this stage to capture
the condition of significant infrastructure located on properties that will be
affected by the construction corridor. The purpose of these photos is to inform
the development of the Property Management Plans port and guide the
rehabilitation process.
Property Management Plans
Property Management Plans record essential information, such as the location
of underground assets and essential property operation assets, agreed
reinstatement details and preferred contact details. This is an APA standard
document for recording property information.
The Construction Contractor would utilise the Property Management Plan and
include details of typical construction activities as a general advice statement
to the landowner or occupier.
5.5.3.2 Construction
Initial meetings for introductions of Construction Contractors to landowners,
occupiers and stakeholders will be arranged and attended by APA. Once the
initial meeting is carried out, the Construction Contractor Land Liaison team is
then authorised to communicate with landowners, occupiers and
stakeholders affected by the project.
Landowners and occupiers will be requested to communicate with the Project
primarily through their dedicated Construction Contractor Land Liaison Officer
during the period of construction.
27
5.5.3.3 Commissioning phase
Landowners and occupiers will be informed of the works involved in the
commissioning and hydro-testing of the assets, and what to expect with
regards to noise, personnel movement and other such activities.
5.5.3.4 Rehabilitation phase
Landowners and occupiers will again be consulted to re-confirm re-seeding
specifications and other rehabilitation practices.
5.6 Handover / closeout phase
The Construction Contractor will contact landowners and occupiers for final
clearance to confirm a satisfactory restoration process has been
implemented. Accompanied by an APA representative, the Construction
Contractor will perform an inspection of the restored easement to identify any
defects requiring attention prior to project close-out and damage releases
being sought.
5.6.1 Monitoring and verification
The effectiveness of the consultation undertaken in this phase will be verified
against the following criteria:
All enquiries, feedback and complaints are recorded and documented
in the landowner database;
No complaints are received from landowners or occupiers regarding
impacts from construction activities that were not adequately
communicated prior to construction; and
All reportable incidents will be investigated in line with APA’s Incident
Investigation and Analysis Procedure (APA HSE GP 07.02).
28
5.7 Operation and maintenance
The operation of high pressure gas pipelines typically has a very low impact
on landowners, occupiers and other third parties and, as the pipeline
operation phase typically extends over decades, it is necessary to take steps
to ensure that awareness of the gas pipeline is maintained. Given that a
pipeline is a long-term infrastructure investment, it is in the interest of APA to
develop and maintain a sound relationship with landowners and occupiers.
APA will also implement an easement maintenance program in order to
maintain line of sight between established pipeline markers, ensure access
along the easement is preserved and to manage physical land changes that
may threaten the pipeline (e.g. erosion).
The operation and maintenance of the pipeline will be undertaken in
accordance with APA’s Landowner Engagement Procedure (560-PR-QM-
0001) and the Authorised Third Party Works Management Procedure (560-PR-
QM-0004). The Landowner Engagement Procedure identifies awareness
objectives that are to be met and provides confidence that key messages are
being communicated to external stakeholders, including landowners and
occupiers.
5.7.1 Purpose of the consultation
The purpose of the consultation associated with this phase is as follows:
1. To raise awareness of how APA operates its gas pipelines;
2. To provide information of pipeline infrastructure and the associated
pipeline corridor;
3. To outline unauthorised activities and detail the approval process for
undertaking work in the easement;
4. To provide information and support to mitigate land-use changes
altering existing location classifications;
5. Ensure that third parties are informed of APA’s planned activities with
regards to their interests; and
6. Provide knowledge to identify an emergency situation and what to do
in such an event.
7. To provide APA with information regarding any proposed changes in
land use or other activities with implications for separation distance.
29
5.7.2 Means of consulting with stakeholders
APA will facilitate a handover of the pipeline asset from APA’s Project
personnel to the APA personnel that are responsible for operating and
maintaining the asset (Field Services and Infrastructure Protection Teams). This
handover process will occur within six (6) months of commencing operation of
the pipeline, or following rehabilitation of the pipeline construction corridor as
outlined in the EMP.
The frequency of pipeline awareness activities is determined through a Safety
Management Study (SMS) for the pipeline asset, which includes a stakeholder
risk assessment. Minimum consultation requirements have been determined as
follows:
All landowners will be provided with an information pack on an annual
basis, which contains an information booklet, landowner brochure and
guidance for landholder activities in proximity of the pipeline. This
includes the Dial Before You Dig campaign and asset management
information from APA.
Notification to landowners and occupiers regarding the
commencement of different stages of the project, including
construction, commissioning and operation. All landowners will have a
face-to-face visit at a minimum of every three years by an APA
representative; and
Notification to landowners and occupiers regarding non-routine
maintenance activities (e.g. chemical vegetation and weed control,
excavations, etc.)
Access is undertaken by APA representatives as necessary to maintain
vegetation (for line of sight), ensure access along the easement is preserved
and to manage physical land changes that may threaten the pipeline (e.g.
erosion). Noting this excludes easement areas where the pipeline crosses
underground at a greater depth such as trenchless and HDD crossings to
avoid sensitive vegetation or other surface features. Generally, once
arrangements with landowners and occupiers are established, this routine
maintenance does not require landowner or occupier consultation.
An information booklet will be provided annually as part of the information
pack will contain key messages such as when to contact APA, APA contact
details, emergency contact details, explanation of pipeline markers,
guidelines for appropriate activities near pipelines, activities that may result in
30
damage to the pipelines and methods of recognising threats to the pipeline
and what to do in an emergency.
Where landowner or occupier activities have been identified as being high
risk through the SMS process, they will be contacted via face-to-face visits at
a frequency that best addresses the individual risk factors identified in the SMS.
For these landowners and occupiers the minimum frequency of visits from an
APA representative is annually.
In addition, APA shall facilitate meetings with regulatory and planning
authorities (including local governments) that have jurisdiction over land in
which APA has assets located annually.
Each landowner visit will be recorded on an operational landowner contact
form, which is then included in the stakeholder management database, X-Info
Connect (XIC). The XIC database forms the basis of the operational
stakeholder management systems within APA.
5.7.3 Timing of consultation
Handover of the asset from APA project personnel to the Field Services and
Infrastructure Protection Teams will occur within six (6) months of commencing
operation of the pipeline, or following rehabilitation of the pipeline
construction corridor as outlined in the EMP.
Engagement of landowners and occupiers will occur for the life of the asset,
at the frequency identified in Section 5.7.2 or on an as needs basis in the event
of an enquiry, complaint or incident.
31
5.7.4 Monitoring and verification
APA will monitor the effectiveness of the Landowner Engagement Procedure
and the Authorised Third Party Works Management Procedure, through the
review processes outlined in these procedures. Compliance with these
procedures is integral to confirm the suitability of the procedures in reducing
the risk posed by third parties to APA’s assets and management of external
interface activities.
The operational procedures will document and confirm that:
The landowner database of third parties is accurate and current;
The procedures are being implemented in a timely fashion;
SMS outcomes have been incorporated into the plans;
The number of third parties that have been contacted as part of APA’s
activities; and
Actions relating to any reported incident have been completed.
These processes will also be formally audited as part of APA’s existing internal
procedures. The requirement to have formal audits of these systems will be
tracked in the APA Management of Audits, Regulatory Compliance and
Operations Incidents System.
32
6 Media All media enquiries will be directed to a dedicated person within APA’s Media
and Communications Group responsible for handling media enquiries on
behalf of the Project. The management and response to media enquiries will
be in accordance with the Gas Import Jetty and Project Media Management
Plan (18027-PL-A-0003).
All media enquiries relating to the Project should be directed in the first
instance to the respective designated media contact within APA, who are
outlined in Table 6-1. It will be necessary to ensure Project team, construction
contractors and consultants are briefed about the media contacts.
Table 6-1 Media Contacts
Organisation Name Contact details
APA Todd Hayward,
Project Communications Manager
M: 0412 205 151
AGL Mike Duffy,
Group Manager, Media Relations
M: 0499 005 912
6.1 Escalation of media enquiries
Once a media enquiry has been received and contact made with the
journalist, the following steps should be taken to advise all relevant parties:
The Project team members or Construction Contractor who receives any
media enquiry, should notify the designated media contact. Notification
should be in the form of an email with a text message sent to alert
recipients to check their inbox;
Notification should occur as soon as practicable and within 24 hours of
receiving the media inquiry;
The following minimum summary details should be included in the email:
a. Journalist name and media outlet
b. Question(s)
c. Response deadline
d. What information is requested and in what format?
e. Any relevant background to the request
f. Initial assessment as to whether the response can be managed with
existing project content or requires the generation of new content.
g. Initial assessment as to whether all or part of the enquiry should be
referred to AGL or APA;
33
If it is unclear, the notification should include a recommendation as to
whether AGL or APA should lead the response, or whether there is a
requirement for both parties to respond where various issues have been
raised; and
A summary of the likely issues and topics of media interest shall be used
as a guide in the decision making for the party responsible for responding
to media enquiries is presented in Table 4.
Table 6-2 Lead response guide
General Issue/Topic Response Lead
Jetty Works Project rationale AGL
Jetty facilities/upgrade
Operation of FSRU
Timeline
Local action groups
Pipeline Works Project rational
Pipeline alignment
Right of Way
APA
Construction
Progress / Timing
Design
Safety
Industrial relations
Local employment
Stakeholder
Engagement
Community of Crib Point/Hastings AGL
Stakeholders / owners and occupiers APA
East Coast Gas
Market
Driver for Project – constraints and
opportunities
AGL, with APA input
as required
34
7 Management of potential impacts Potential adverse impacts on private and public land are to be avoided by
pre-disturbance surveys of the land, consultation with landowners and
occupiers, recommendations of specialist investigations and access and
construction requirements developed in consultation with the landowner and
occupier. Where adverse impacts cannot be reasonably avoided the residual
impacts will be minimised and then compensation for the impacts will be
agreed with the landowner and occupier.
Potential adverse impacts on health, safety and the environment (HSE) will be
managed within the framework of APA's HSE Management System, known as
Safeguard. Safeguard is designed to ensure that information on health, safety
and environmental requirements is provided to personnel in a relevant,
accessible and understandable form. The broad relationships and linkages
between the project’s management plans and APA’s HSE Management
System are represented diagrammatically in Figure 7.1.
Figure 7.1: APA’s HSE Management System, Safeguard
35
Safeguard is implemented at all levels of the business through position
descriptions, operational and HSE management processes and procedures.
Information, training and awareness is provided to APA’s employees and
contractors to ensure that they are aware of APA’s commitment and of their
responsibility to comply with quality management and HSE management
requirements.
Management documents prepared in relation to the Project will set out the
plans, roles, responsibilities, procedures, and specific commitments required to
carry out the project in accordance with APA HSE Policy. In addition to this
Consultation Plan, the following key management documents have been
prepared to the satisfaction of the relevant regulatory agencies:
Environmental Management Plan - An EMP that sets out systems and
standard to protect the environment and provides construction
methodologies to minimise environmental impacts.
Safety Management Plan - A SMP details the systems and processes to
be implemented including hazard alert protocols, incident reporting,
safety meetings and hazard analysis processes.
Cultural Heritage Management Plan - A Cultural Heritage Management
Plan that details the construction methodologies to minimise
construction and ongoing operation impacts on sensitive cultural
heritage areas.
Operations Environmental Management Plan - An Operations
Environmental Management Plan that supports the operation of the
pipeline and work practices defined to minimise impacts on the
environment.
Operations Safety Management Plan - An Operations Safety
Management Plan to provide an integrated safety management
approach in line with APA’s existing safety management policies and
practices for pipeline operations.
36
8 Compulsory acquisition of land
8.1 Pipelines Act
The Pipelines Act and the Pipeline Regulations detail a process which has
been described in the preceding pages to ensure that landowners and
occupiers are engaged in a structured and respectful process leading up to
the negotiation of easement rights. APA is committed to providing fair,
adequate and equitable compensation to impacted landowners and
occupiers for disturbance and loss of production in accordance with the
Pipelines Act.
The Pipelines Act includes a provision that enables a proponent to apply to
the Minister responsible for the Pipelines Act to permit compulsory acquisition
of the required easement, providing the proponent is able to clearly
demonstrate adherence to the required procedures, for the purposes of
constructing and operating the pipeline.
It is noted that if APA cannot negotiate an easement agreement with a
landowner, APA are not able to approach the Minister to seek the Minister’s
consent to compulsorily acquire the easement for a period of six months from
issuing the landowner and occupier with the Notice of Pipeline Corridor (unless
the Minister agrees to abridge this timeframe under Section 90(4) of the
Pipelines Act).
Landowners and occupiers affected by the Project are encouraged by APA
to seek independent legal advice on any concerns they may have with
regard to legal implications of the Project which could include the project’s
potential impact on their land and its use or any other legitimate concern. Pre-
defined and agreed reasonable costs incurred in seeking advice in relation to
the Project will be reimbursed by APA.
8.2 Land Acquisition and Compensation Act
The Land Acquisition and Compensation Act 1986 and the Land Acquisition
and Compensation Regulations 2010 detail the process of compulsory
acquisition having secured consent from the Minister responsible for the
Pipelines Act.
Following compulsory acquisition of the required easement, this Act also
details how claims are made, how compensation is assessed and how issues
and disputes are resolved. It also details the rights and obligations each party
has with respect to the compulsory acquisition of an interest in land.
37
This Act provides for the securing of temporary occupation of land and
permanent easements for the pipeline for the purposes of the Special Act,
being the Pipelines Act.
If compulsory acquisition is required, APA will develop a Land Acquisition and
Compensation document to navigate the process and would comply with
this Consultation Plan and respective sections of the Pipelines Act.
38
9 Project timeframes The proposed timeframes for each stage of the Project’s development is
summarised in Table 9-1. These stages are consistent with the phases of
consultation that are further described in Section 5.
Table 9-1: Development timeframes of the Project
Stage Activities Indicative Timing
Phase 1:
Initial Stakeholder
Engagement
Database establishment, Consultation with
regulatory agencies and initial landowner
meetings
Q4 2017 –
Ongoing
Phase 2:
Obtaining Land
Access for Surveys
Seek agreement for land access, issue
Notice of Intention to Enter Land for Survey
and undertake necessary field surveys
Q4 2017 –
Ongoing
Phase 3:
Agreement of
Pipeline Corridor
Issue Notice of Pipeline Corridor, seek
easement agreements and any required
crossing agreements with third parties
Q4 2018 – Q22020
Phase 4:
Completion of
Regulatory
Approvals
Make application for a Pipeline Licence
(including other approval applications if
required), issue Notice of Pipeline Licence
Application, obtain relevant State and
Commonwealth regulatory approvals
Q3 2018 – Q4
2020
Phase 5:
Pipeline
Construction
Construction of the pipeline – clear and
grade, trenching, pipe stringing, welding,
special crossings, lowering in, backfill and
reinstatement
Q3 2021 – Q4
2022
Commissioning Q3 2022 and Q4
2022
Final release – acceptance of level of
reinstatement (rehabilitation and damage
releases to continue into operation of the
pipeline)
Q4 2022 – Q4
2023
Phase 6:
Pipeline Operation
Operate the pipeline for the life of the
asset
60 year design life
39
10 Records management APA will maintain a stakeholder management database for the life of the
Project to retain information relevant to the development of the project, which
is to include copies of data gathered in the field and from title searching,
copies of correspondence, relevant discussion records and agreements for
each landowner and occupier. The stakeholder management database, XIC,
will also record enquiries, feedback and complaints raised and details of the
relevant response resolution.
XIC will be used to record all external communications and stakeholder
engagement activities. Consultation during the construction phase will be
required to be recorded by the construction contractor utilising an equivalent
system. Incidents affecting landowners or occupiers arising from the
construction phase will be notified to APA and recorded for follow-up action
by the construction contractor.
Copies of any agreements and discussion records will be left with landowners
or occupiers at the time of meeting or alternatively records will be made
available to landowners, occupiers or their legal representation on request.
10.1 Personal Information
APA is committed to handling and protecting personal information in
accordance with Australian Privacy Principles set out in the Commonwealth
Privacy Act 1988. Information collected in discussions with landowners and
occupiers will solely be used by APA, its representatives and the engaged
contractors for project purposes.
All personal information received by APA is held either in electronic files on
APA’s computer systems or in physical files stored at APA’s premises. Only APA,
its representatives and contractors involved in relevant land access and
project management work, will have access to this personal information. APA
takes reasonable steps to protect all personal information it holds by using
necessary technology (i.e. firewalls) and systems to reasonably ensure that the
information is secure from misuse, interference and loss, and from
unauthorised access, modification or disclosure.
40
11 Further information
11.1 Proponent
A summary of the relevant company information and the details of the
company representatives are presented in Table 11-1.
Table 11-1: Company’s details
Details Organisation
Entity APA Transmission Pty Limited
ACN 603 054 404
Office Location Head Office:
Level 19, 580 George Street
Sydney NSW 2000
Project Office:
Level 14, 60 City Road
Southbank VIC 3006
Website https://www.apa.com.au/about-apa/our-projects/crib-
point-to-pakenham-pipeline/
Representative Mr Matt Baker
Project Manager, Crib Point Pakenham Pipeline
Phone: +61 436 656 936
Email: [email protected]
41
11.2 Regulatory agencies
11.2.1 Department of Environment, Land, Water and Planning
The chief approval to enable construction and operation of a transmission
pipeline is a Pipeline Licence, which is issued by the Minister for Energy,
Environment and Climate Change.
DELWP, among other functions, is responsible for maintaining a licencing
system for certain gas pipelines and regulates the pipeline industry in Victoria
to ensure that environmental management standards are met. The chief
approval to enable construction and operation of a transmission pipeline is a
Pipeline Licence, which is issued by the Minister.
The contact details for DELWP are as follows:
Pipeline Regulation
Department of Environment, Land, Water and Planning
PO Box 500
East Melbourne VIC 8002
Phone: 0439 799 598
Email: [email protected]
11.2.2 Energy Safe Victoria
Energy Safe Victoria (ESV) is the independent technical regulator responsible
for electricity, gas and pipeline safety in Victoria. Under the Pipeline
Regulations, ESV's role is broad and ranges from accepting industry’s safety
cases and safety management schemes for the design, construction and
maintenance of electricity, gas and pipeline networks across the State to
regulating against standards and administering regulations covering gas and
electrical appliances and installations and energy efficiency.
The relevant contact details for ESV are as follows:
Gas and Pipeline Infrastructure Safety Division
PO Box 262
Collins Street West VIC 8007
Phone: (03) 9203 9700
Fax: (03) 9686 2197
Website: www.esv.vic.gov.au
42
11.3 Other reference documentation
Other information sources that may be helpful for landowners and occupiers
to understand high pressure gas pipelines and context of the Project are
identified in Table 11-2.
Table 11-2: Reference documents
Information Type Document (and location)
Relevant Legislation Commonwealth: www.comlaw.gov.au
Victorian: www.legislation.vic.gov.au
Australian Standards AS 2885.1-2012 Pipelines - Gas and Liquid
Petroleum – Design & Construction
AS 2885.3-2012 Pipelines - Gas and Liquid
Petroleum – Operation & Maintenance
Guidelines and Codes of
Practice
APGA Stakeholder Engagement Guideline
(October 2015)
APGA Code of Environmental of Environmental
Practice – Onshore Pipelines (September 2017)
APGA/VFF Pipeline Easement Guideline (2009)
Guidelines for the Preparation of Pipeline
Consultation Plans – Pipelines Act 2005
International Association for Public Participation
Australasia (IAP2S) Public Participation Spectrum
(2014)
Victorian Auditor-General’s Office Auditing in the
Public Participation in Government Decision-
making – Better practice guide (2015)
43
12 Information for the Public (Questions and Answers) APA commit to ensuring the Project team who may come into contact with
stakeholders and the wider community have a good knowledge and
understanding of the Project and is well acquainted with the key stakeholder
engagement messages.
The following project messages can be used by those authorised
representatives as a basis for external communication or answering
stakeholder and wider community queries:
General
What is AGL’s Crib Point
Gas Import Jetty
project?
AGL’s proposed project would source gas at competitive
prices from Australian and international suppliers for its gas
customers in south-eastern Australia. Gas in the form of
Liquefied Natural Gas (LNG) would be transported on LNG
ships and would be transferred to a floating storage and
regasification unit (FSRU), to be moored at the existing jetty at
Crib Point. The FSRU is a vessel that can store and re-gasify
LNG for distribution as required to meet gas demand
requirements.
AGL is to commence operations with around 12 ships a year.
This could however increase to 40 ships per year depending
on market demand. This compares with about 130
commercial vessels currently entering Western Port each
year. The use of LNG ships is an efficient way to safely transport
large volumes of gas, over long distances where pipelines are
not economically viable.
For further information, please visit AGL’s project website at:
www.agl.com.au/cribpoint
Timing
How long will pipeline
construction occur?
The works will be undertaken across an approximately 24
month works programme commencing in Q3, 2021, followed
by a further 12 month period for the completion of
reinstatement and rehabilitation works.
When is pipeline
operation and
importation of LNG set
to occur?
Once construction is complete, first gas is expected in the
second half of-2022 and the pipeline will operate for the life
of the Gas Import Jetty Project, which is estimated to be 10-
20 years. Operation of the pipeline may extend beyond
importation of gas as the economic life of pipeline is approx.
60 years and can be used as bi-directional.
44
Environment
What planning
assessments has this
project undergone to
be approved?
The Gas Import Jetty and Project has completed an
Environment Effects Statement, Pipeline Licence Application,
Works Approval and Approval under the Federal EPBC Act.
You can view the results of these planning assessments on the
website.
www.gasimportprojectvictoria.com.au
How are pipeline
construction impacts to
the environment being
minimised?
APA has minimised impacts to local environment, native
vegetation and fauna. Approximately 12 hectares of native
vegetation would be removed with construction of the
project. APA has committed to rehabilitate land after
construction to the greatest extent possible, by reseeding
grass and planting vegetation in accordance with Pipeline
Licence terms and conditions.
APA is offsetting the removal of native vegetation, as per
the Department of Environment, Land, Water and Planning
(DELWP) requirements. A sum of money has been provided
as guarantee to the Pipeline Regulator against impacts
beyond those sanctioned for the pipeline component.
What has APA done to
minimise impacts on
agriculture, food
production and fertile
soil along the pipeline
alignment?
APA have minimised the impact on agricultural land by
working with landholders on a preferred pipeline alignment. It
is estimated that during the six-month period planned for
pipeline construction approximately 124 hectares of
agricultural land would be temporarily impacted. This would
include about 3.5 hectares of horticultural land, which
accounts for 0.08% of Melbourne’s inner food bowl used for
seasonal vegetable production.
Cultural Heritage
What has APA done to
minimise impacts on
sensitive Aboriginal and
historic cultural
heritage?
APA worked with the Bunurong Land Council to develop a
Cultural Heritage Management Plan (CHMP) for areas where
Registered Aboriginal Parties (RAP) are the approval
authority. This area expands from Crib Point to Pearcedale. A
CHMP for non-RAP areas covering the northern part of the
Project alignment is to be completed after coordination with
Aboriginal Victoria.
45
Stakeholder Engagement
How are landowners
and occupiers being
notified of these works?
Landowners and occupiers will receive notice at least one
week prior to the site works beginning. Formally agreed
engagement will occur with stakeholders.
I would like my business
to be considered to
supply products and/or
services for construction
of the Project.
The Project is committed to sourcing supplies and services
local to the Project area where feasible.
Please send your business details and capabilities to supply
products or services to the project email address for
consideration.
Email: [email protected]
Contact information (for further questions or complaints)
APA Crib Point
Pakenham Project
Hotline:
Email:
Websites:
1800 531 811
https://www.apa.com.au/about-apa/our-
projects/crib-point-to-pakenham-pipelineor
www.apa.com.au
AGL Gas Import Jetty
Project
Phone:
Email:
Website:
1800 039 600
https://www.agl.com.au/about-agl/how-we-
source-energy/gas-import-project
46
13 Implementation Plan The following table provides a high-level overview of required engagement
actions to support the construction phase of the Project.
Target Date or Requirement
Engagement Activity Target Audience Status Responsibility
Ongoing for project lifespan
Ongoing Send direct
correspondence
where required
All
stakeholders
and
community
APA
Ongoing Provide Fact
sheets and
brochures
Impacted
Landholders
Wider
community
APA
Ongoing Install Posters
and signage
Impacted
Landholders
Wider
community
APA /
Construction
Contractors
Ongoing Send media
updates
Media outlets APA
Ongoing Update project
website
All
stakeholders
and
community
APA
Ongoing Send news
updates
Registered
parties
APA
Ongoing Hold meetings
with impacted
landholders
Impacted
landholders
APA/Construction
contractor
Ongoing Undertake
Community
Presentations
Interested
parties
APA
Ongoing Brief key
stakeholders
All levels of
government
Third party
asset owners
APA/Construction
contractor
47
Target Date or Requirement
Engagement Activity Target Audience Status Responsibility
Pre-Construction
Provide works
commencement
notice
Impacted
landholders
APA
Hold contractor
introduction
meeting
Impacted
landholders
APA /
Construction
contractor
Develop
property
interaction
reports
Impacted
landholders
Construction
contractor
Provide
construction
induction packs
Impacted
landholders
APA /
Construction
contractor
Install localised
signage and
posters as
required
Wider
community
Construction
contractor
Construction
Implement
Property
Interaction
Reports
Impacted
landholder
Construction
contractor
Follow issues or
complaints
management
procedures as
required
Impacted
landholders
APA /
Construction
contractor
Respond to
general
landholder
enquiry
Impacted
landholders
Construction
contractor
Produce
monthly Activity
Reports
DEWLP APA /
Construction
contractor
48
Target Date or Requirement
Engagement Activity Target Audience Status Responsibility
Commissioning
Provide with
Information
packs
Impacted
landholders
Construction
contractor
Provide with
formal notice of
testing
Impacted
landholders
Construction
contractor
Rehabilitation
Provide with
formal
rehabilitation
notification
Impacted
landholders
Construction
contractor
Hold close out
meeting
Impacted
landholders
APA /
Construction
contractor
Operation
Yearly from
date of
handover
Provide with
Safety
Management
Information
Packs
Impacted
landholders
APA
Three yearly Undertake safety
Inspections
Impacted
landholders
APA
As required Provide with
maintenance
notifications
Impacted
landholders
APA
As required Hold
maintenance
meetings
Impacted
landholders
APA
Yearly Hold safety
meeting
Impacted
landholders
APA
49
A Glossary
Term Definition
APGA The Australian Pipelines and Gas Association Ltd (APGA) is the
peak body representing Australasia’s pipeline infrastructure, with a
focus on gas transmission, but also including transportation of other
products, such as oil, water, slurry and carbon dioxide. Our
members include constructors, owners, operators, advisers,
engineering companies and suppliers of pipeline products and
services.
AS2885 You will be required to comply with this Australian Standard if you
intend to design and construct pipelines that transport gas and
liquid petroleum. This Standard is intended for pipelines
constructed from steel pipe used for the transport of gas or liquid
petroleum.
AS2885 has been accepted by the Council of Australian
Governments (COAG) as the single and sufficient standard for the
technical regulation of pipelines in all Australian jurisdictions. The
AS2885 set of standards comprises five parts covering all aspects
of pipeline design, construction, operation and maintenance.
Cadastral
Survey
To prepare a Pipeline Corridor plan and easement plans it is
necessary to complete a detailed survey of the proposed route.
This will entail matching the position of the pipeline to the proposed
easement and title boundaries. In doing so it is often necessary for
the survey party to leave the easement area to locate a known
title position.
Compensation The underlying concept of compensation is to place the party who
has suffered a loss of some kind in a position as close as possible to
that prior to the loss. For practical reasons, society has accepted
that in most instances compensation is made in a financial form.
With respect to pipeline easements, compensation is paid in two
parts:
Easement Compensation: a one off payment usually
assessed by a professional valuer and is a payment in return
for the easement rights and restrictions placed on the land
by the easement; and
Damages Compensation: Paid following pipeline
construction for losses which may have been sustained as a
result of pipeline construction. This compensation will also
50
include an occupation payment for the use of temporary
working area land (refer to Damage Release).
Where a significant construction related loss is sustained by a
landowner or occupier and it is considered unreasonable to wait
until Damage Release, a Partial Release may be used as a
mechanism to clear the liability.
Creation of
Easement /
Restrictive
Covenant
This document describes the rights and obligations the Pipeline
Company has and the restrictions imposed on the use of the
easement land (sometimes known as the ‘pink document’). The
rights allow the Pipeline Company to enter the easement land for
the purpose of construction and operation of the proposed or
existing pipelines. The Pipeline Company is required to restore the
land to a condition similar to that prior to construction and pay
compensation for damages which may arise as a result of
exercising the rights (refer to Damage Release).
The main points to note with respect to restrictions within the
easement are that excavation of greater than 300mm is not
permitted without written consent of the Grantee (Pipeline
Company) and structures are not permitted with similar conditions.
Normal farming practices such as cereal cropping, and cultivation
can be followed without reference to the Grantee. The easement
does not prevent subdivision, although it may influence the layout
of a subdivision to maximise lot yield.
Landowners will be asked to execute a similar document, as will
any mortgagees or other parties known to title, in order to register
the easement. Upon receipt of title and executed documents, the
balance of compensation is paid. Any reasonable legal costs
incurred during the easement acquisition process will be met by
the Pipeline Company.
Crown Land Land which is held and managed by the Government. The
Government may licence the use of such land for specific
purposes (e.g. Grazing Licence, delegation of the land to road
authorities) or may alienate the land by selling or leasing.
Cultural
Heritage
Survey
A cultural heritage survey will be conducted, usually by members
of a local indigenous group and personnel with an understanding
of regional historical matters. The purpose of this survey is to identify
any significant material which is likely to be lost or destroyed by the
proposed pipeline and either make arrangements for its
preservation or alter the pipeline route. The methods in which
these surveys are conducted are by visual inspection and by
51
scraping away the first few millimetres of topsoil. If a significant site
is located, excavation of an area may be greater.
Pipeline Route The pipeline route is the proposed location of the pipeline,
following the securing of necessary easements and approvals
pursuant to the Pipelines Act. Any potential variation to the
approved route would be subject to agreement with the Pipeline
Regulator.
53
Consultation plan
Crib Point Pakenham Pipeline Project
Stakeholder Group Example of Stakeholders Responsibility Contact Schedule Contact Method Desired Outcomes
Landowners and
occupiers
Owners and occupiers
impacted by the
pipeline
construction/operation
Initial – APA (land
access reps)
Ongoing – APA (land
access reps)
As per Section 5 of
Consultation Plan
As per Section 5 of
Consultation Plan
As per Section 5 of
Consultation Plan
Asset/infrastructure
owners impacted
by pipeline route
South East Water,
Melbourne Water,
VicRoads, VicTrack
(owners of land)
Initial – APA (land
access reps)
Ongoing – APA (land
access reps)
Ongoing
Obtaining land access
for surveys, agreement
of pipeline corridor,
construction, operation
Email, phone and
face-to-face
Agreement of pipeline
corridor and
construction
specification
Telstra, Water service
providers
Initial – APA’s
Construction
Contractor
Ongoing – APA’s
Construction
Contractor
Prior to construction
and finalisation of
detailed
design/construction
Email and phone Construction
specification
Regulatory
authorities (State)
DELWP and ESV Initial – APA and AGL
(introduction to
broader components)
Ongoing – APA (for
pipeline)
Ongoing
Completion of
regulatory approvals
process, construction,
operation
Email, phone and
face-to-face
All regulatory
requirements met prior
to construction and
compliance with
approval documents
Regulatory
authorities
(Commonwealth)
Department of the
Environment and
Energy
Initial – APA and AGL
(introduction to
broader components)
Ongoing – APA (for
pipeline)
Ongoing
Completion of
regulatory approvals
process, construction,
operation
Email, phone and
face-to-face
All regulatory
requirements met prior
to construction and
compliance with
approval documents
54
Consultation plan
Crib Point Pakenham Pipeline Project
Stakeholder Group Example of Stakeholders Responsibility Contact Schedule Contact Method Desired Outcomes
Registered
Aboriginal Parties
and Traditional
Owner Groups
Bunurong Land Council
Aboriginal Corporation
(and others as notified
by AV)
Initial – APA
Ongoing – APA
Ongoing
Completion of
regulatory approvals
process, construction,
operation
Email, phone and
face-to-face
All regulatory
requirements met prior
to construction
(negotiation of CHMP)
and compliance with
approval documents
Elected
Representatives –
All levels
Relevant local, State
and federal members
of Parliament
Initial – APA and AGL
(introduction to
broader components)
Ongoing – APA and
AGL (separately for
pipeline and port/jetty)
Initial meeting and
progress updates at
key milestones
Letter and face-to-
face
Members fully informed
and supportive of
Project
Local councils As owners of land and
specialist input
Initial – APA (land
access)
Ongoing – APA (land
access/engineering)
Ongoing
Obtaining land access
for surveys, agreement
of pipeline corridor,
construction, operation
Email, phone and
face-to-face
Agreement of pipeline
corridor and
construction
specification
CEO and high-level
personnel
Initial – APA and AGL
(introduction to
broader components)
Ongoing – APA and
AGL (separately for
pipeline and port/jetty)
Initial meeting and
progress updates at
key milestones
Letter and face-to-
face
Council is fully informed
and supportive of
Project
55
Consultation plan
Crib Point Pakenham Pipeline Project
Stakeholder Group Example of Stakeholders Responsibility Contact Schedule Contact Method Desired Outcomes
Community,
Environment and
Action Groups
Preserve Westernport
Action Group, Crib
Point Advisory Group,
GetUp!, etc.
Initial – AGL (already
undertaken prior to
Consultation Plan)
Ongoing – AGL (and
APA where specialist
pipeline engagement
is required – note APA
to lead if pipeline
specific issues)
As part of broader
community
consultation then as
required
Letter, email, phone
and face-to-face
Group is fully informed
and supportive of
Project
Media News organisations –
print, television, digital
Communications
Working Group and/or
APA and AGL
(separately for pipeline
and port/jetty)
As required – response
to requests
Letter, email and
phone
News organisations are
fully informed of the
Project and have
balanced reporting
56
Consultation plan
Crib Point Pakenham Pipeline Project
C Project information brochures
Figure 2. December 2019 information brochure, page 1