1 Status of infrastructure MICE Collaboration Meeting, Frascati, June 26-29, 2005 Yury...

30
1 Status of infrastructure Status of infrastructure MICE Collaboration Meeting, Frascati, June 26-29, 2005 Yury Ivanyushenkov Applied Science Division, Engineering and Instrumentation Department RAL

description

3 MICE layout

Transcript of 1 Status of infrastructure MICE Collaboration Meeting, Frascati, June 26-29, 2005 Yury...

1

Status of infrastructureStatus of infrastructure

MICE Collaboration Meeting, Frascati, June 26-29, 2005

Yury Ivanyushenkov

Applied Science Division,Engineering and Instrumentation Department

RAL

2

• Layout

• Hydrogen system

• Shielding

• Support system

Scope

3

MICE layout

4

MICE phase I initial

5

MICE phase I final

6

Tchill

Pressuregauge

Non-return valveP P VP Vacuum pumpBursting diskPressure

relief valveValvePressureregulator

CoolantOut In

Test absorber assembly

Metal Hydride storage unit

(20m3 capacity)

Purge valve

0.5 bar

0.9 bar

H2 Detector

P

P

VP1

VP2

Purge valve

Chiller/Heater

Unit

1 bar

PP

0.5 bar

0.9 bar Helium supply

Hydrogen supply

High level vent

Buffer vessel

Vent outsideflame arrester

Extract hoodH2Detector

PP

Nitrogen supply

PP

PP

1 m3

Hydrogen zone 2

Vent manifold Vent manifold

P1

PV1

PV7

PV8

PV2

PV3

PV4

HV1

Fill valve

Tbed

HV2

HV3

P3

P

P2

PV6

High level vent

Non return valve

0.1 bar

Hydrogen system test rig

Mass spectrometer

M. F.M.

Mass flow meter

7

MICE hydrogen system PID

8

MICE hydrogen system layout: Principle

• Argon jacketing of pipework is proposed in outside the hood. Basic philosophy is shown below

Hood

MICE

Cabinet for hydride bed and pipework

H2sensorArgon Jacketing

Safety area

1m3

9

MICE hydrogen system layout (2)

10

• WP1 Initial design -> Internal safety review• WP2 Detailed design and procurement • WP3 Installation and commissioning • WP4 Test Programme

Hydrogen system R&D: Work packages

11

Hydrogen R&D: Layout

12

Hydrogen R&D: Layout (2)

13

Hydrogen test cryostat: Concept

T H

T H

• Instrumentation mimics what we will need on the absorber for the control system and interlocks

• Heater will regulate temperature of cryocooler – need redundancy and interlock with compressor

• Dia.Reservoir =height=290mm

14

Hydrogen Test Cryostat Outline

1120

Ø 580

15

Hydrogen test cryostat

Condenser

LH2 dummy absorber

Level sensors

Cryocooler SRDK-4151.5 W @4.2K35/45 W @50K

Radiation shield

Hydrogen inlet and outlet

He inlet and outlet

Cu bottom plate with heat exchanger

16

Hydrogen test cryostat (2)

Cu bottom plate with heat exchanger

Cartridge heaters

Finned top plateof condenser

17

Outline Schedule•WP1 Initial design: May – August 05

with Review in September 05 •WP2 Detailed design and procurement: Aug 05 – Feb 06•WP3 Installation and commissioning: Jan – April 06•WP4 Test Programme: June – Oct 06

Hydrogen system R&D – Schedule

18

Radiation shielding

• No changes in the layout • Paul is working toward a much more reasonable (and cost effective) shielding arrangement.

19

Magnetic shielding

• No changes in the layout • Part of magnetic shielding wall will be installed and used as a support for hydrogen R&D test area platform.• Another round of magnetic modelling is required for a full MICE magnetic shielding once position of MICE in the hall is frozen.

20

Support structure – Layout and sequences

Add spacer

21

Support structure - Required rail positions

MICE Stage IV MICE Stage V

Rail positions of downstream detector for Stages IV & V will overlap with final stage VI rail positions

22

Support structure – Super-module

Module to module joints to react forces in Z

CC/RF module with stiff support structure

23

Support structure – Rail and Force transfer concept

Y

XZ

Magnetic force

Traverse in X on rail system to give location to +/- 2mmJack from rail and position in x-y-z to survey targets on vacuum vesselShim to blocking plates to locate in x-y-z and react forces

Module

Jacks

Rollers

Rails

Floor Plate

Y support location

Shim

Beam Axis

Survey Target

24

Support structure – Rail-mounting concept

25

Support structure – Force transfer concept - Y

26

Support structure – Force transfer concept - Z

27

Possible MICE rail system

28

• Requirements/specification: - to move (all) MICE modules out the beam (to the side direction) for various MICE stages• Accuracy/tolerances: - along the beam +/- 1 mm - across the beam +/- 1 mm• Adjustment: - adjustment possibility is required.• Locking mechanism: - required.• Loads: - max load is 6.65 tonnes.• Force transfer function: - gravity force to the floor; - module-to-module axial force to the floor ?

MICE support structure - Specification

29

Module Weight, kg

AFC module 1700

RF module 4636

Radiation shield 310

Tracker module 6650(including 1200 kg of magnetic shield)

MICE support structure - Module weights

30

MICE support structure – Next steps• Revise support structure requirements/specs for full MICE - include and analyze requirements of access to every module ( collect information from all technical supervisors)

• Suggest support structure for Stage 2 (is it different from the one for complete MICE ?)

• Discuss revised version of support structure at RAL meeting