1 SCOPE OF THE PRESENTATION Grid operation - overview Availability Based Tariff Benefits to Region &...
-
Upload
roland-smith -
Category
Documents
-
view
217 -
download
1
Transcript of 1 SCOPE OF THE PRESENTATION Grid operation - overview Availability Based Tariff Benefits to Region &...
11
SCOPE OF THE PRESENTATIONSCOPE OF THE PRESENTATION
• Grid operation - overview• Availability Based Tariff• Benefits to Region & it’s
constituents • Intra_state ABT – it’s necessity• Issues• How to implement?
22
GRID STATUS – PRE - ABTGRID STATUS – PRE - ABT• Very wide Frequency fluctuations
48.0Hz to 52 Hz. • Low Grid Voltages
400kV going down up to 330kV• Frequent Grid Disturbances• Sub-Optimal Operation• High Technical loss• Overdrawals at low frequency – might is right
Grid Operation on fire fighting instead of Optimisation
& Economy
33
AVAILABILITY BASED TARIFFAVAILABILITY BASED TARIFFSpearheaded by POWERGRID Features:Unique commercial mechanism linked with
frequencyFixed Charges i.e. Capacity charges
As per Plant Availability.Variable Charges i.e. Energy charges
As per Schedule.Unscheduled Inter change (UI) i.e. deviations from
schedule ( Schedule – Actual) Price as per prevailing system frequency
SCH-ACT GRAPHS
44
0
100
200
300
400
500
600
700UI RATE
Current Rate of Unscheduled Drawal/InjectionFrequency (Hz) Rate (p/u)
Above 50.5 0
50.0 150
49.8 210
49.0 and below 570
Till 31.03.2004
From 01.10.2004 to till date
From 01.04.2004 to 30.09.2004
55
• Achievements
– Implemented between July 2002 and Nov.’2003 – Improved quality of supply.– Unutilised capacity harnessed-Pumped Storage– Merit order Operation.– Grid discipline – Emphasis on load forecasting– Discourage overdrawals during low frequency – Facilitate bi-lateral trading
– Maximisation of generation availability
AVAILABILITY BASED TARIFF
66
Need for intra-State ABTNeed for intra-State ABT
• Accountability of utilities after reforms• Passing on UI payment
– Intra State ABT to identify agencies responsible for overdrawal/underdrawal, overgeneration/ undergeneration, resulting in UI payment to regional pool.
• Proper Demand forecast and load management by DISCOMs
• To establish a framework for bilateral trading at intra-State level
• To achieve overall merit order operation.
•ISGS: Inter State Generating Stations•SGS: State Generating Stations•CTU: Central Transmission Utility•STU: State Transmission Utility
Inter-State ABT
Intra-State ABT
•Distribution Control Centre – One for each Discom
IPPs CPPs
Non-conventional source of energy e.g., wind energy
ISGS-1 ISGS-2 ISGS-3
CTU / ISTS SYSTEM RLDC CORDINATES
INTER- STATE
INTRA STATE
STU/INTRA STATE SYSTEM
SGS-1 SGS-2 SGS-3
DISCOM-1 DISCOM-2 DISCOM-3
SLDC CO-ORDINATES
OPEN ACCESS CUSTOMER
~ ~ ~
~ ~ ~
88
Intra-state ABT Intra-state ABT ..what it achieves ?what it achieves ?
. Unbundling of Vertically Integrated State Utilities• Mechanism to price power based on
Demand/Supply• Harness surplus generating capacity available in
state with CPPs/IPPs• Operation of grid on economic principles –Merit
Order Despatch • Open Access in Intra-state Transmission and
Distribution.
99
Intra state ABT Intra state ABT
• Pre – requisites– Allocations from ISGS/ other state owned generators to
various Discoms by State Govt
– control centres in each Discom
– Rtus at required locations
- generating stations, drawal points from state transcos
- on various tie-lines lines, various other critical lines
-scada information to discom control centres
-SEMs at required locations
1010
Intra-state ABT Intra-state ABT ––what it achieves ?what it achieves ?
• Generate signals for efficient grid operation at the intra-state level.– Overdrawals at low frequency by Discoms duly priced.– Encourage serving of higher consumer demand – Encourage maximisation of generation during deficit
conditions.– Each Discom and state generating station
responsible for its actions – a profit centre– Commercial signals available to large consumers
capable of regulating drawal
1111
……Intra-state ABT Intra-state ABT – what it – what it achieves ?achieves ?
• UI mechanism at the intra-state level.– UI to be applied on the deviations from the
schedules of the DISCOMS/State generators/IPPs/CPPs.
– State Utilities to be collectively liable for the States’ liabilities with the regional UI pool account.
– Achieves merit order operation for all the entities under ABT
– Commercial viability of running Pumped Storage Stations.
1212
Issues needs to be addressed for Issues needs to be addressed for intra-State ABTintra-State ABT
• Restructured SEBs• Identification of entities for intra-State ABT• Scheduling Principles & Procedures• Commercial Principle
– Metering Philosophy• Treatment of existing Agreements• Organisational Development• Regulatory Issues
1313
INTRA-STATE ABTINTRA-STATE ABTCOMMUNICATION REQUIREMENTSCOMMUNICATION REQUIREMENTS
• SLDC TO DISCOM COMMUNICATION TO BE ON A STRONG REDUNDANT BACKBONE
• VISIBILITY OF DATA TO SYSTEM OPERATOR– INTERCHANGE FLOWS– EMBEDDED GENERATORS– WIND FARMS, MINI HYDEL, CPP TO BE
TELEMETERED IN STAGES– AND FINALLY, DMS SYSTEM FOR LOAD
MANAGEMENT
• DATA ARCHIVAL AND ANALYSIS COULD HELP IN ACCURATE SCHEDULING
1414
The main steps involved to implement intra-State ABT are:
• Listing of entities on which ABT/UI mechanism to be applied
• Listing of Metering locations and assess the requirement of meters and accessories
• Finalize the specifications for meters and accessories
• Presentation of the mechanism to all concerned
• Finalisation of the tariff for all generating stations in ABT format.
Implementation of intra-State Implementation of intra-State ABTABT
1515
Implementation of intra-State ABTImplementation of intra-State ABT
• Finalisation of shares of each distribution zones and other commercial arrangements
• Organize installation & commissioning of meters and accessories.
• Organising meter reading, data transfer and computation at SLDC
• Establishment of the scheduling process along with scheduling software
• Presentation/training to all concerned
1616
Implementation PlanImplementation Plan• 1st Phase Activities
– Finalisation of listing of entities– Listing of Metering locations– Finalisation of quantities of SEMs,
DCDs/MTEs– Finalisation of technical specifications of
SEMs/DCDs– Initiate tendering process for procurement
of meters
1717
• 2nd Phase Activities – Finsalisation of Tariff of State Generating
Stations as per ABT parameters/norms– Finalisation of Reactive Charge scheme– Finalisation of commercial mechanism for
CPPs, Wind farms, Wheeling and banking, Open Access Customers etc.
– Determination of Allocations of different Discoms in State Genco/ ISGS/ IPPs.
Implementation PlanImplementation Plan
1818
• 3rd Phase Activities – Supply and commissioning of meters at
different locations– Installation of software for data processing – Installation of software for scheduling /
energy accounting– Training– Estimate time for implementation – 12 to
18 months
Implementation PlanImplementation Plan
1919
Some of the features of New National Some of the features of New National
Electricity Policy – Feb.’05Electricity Policy – Feb.’05
• Appropriate Commissions to undertake development of power market
• SERCs to notify GRID CODE by September 2005, if not yet notified
• State Commissions to ensure upgradation of SLDCs by June 2006
• SERCs are advised to introduce ABT regime at the State level within one year i.e. by February 2006.
2020
Status on intra-State ABTStatus on intra-State ABT• Many SEBs restructured, others in process• State Utilities looking for benefits of intra-
State ABT• Gujarat took lead for intra-State ABT• Punjab took lead in Northern Region• Road-map for Maharashtra is ready• POWERGRID assisting these States by
providing consultancy• Other States like MPSEB & Haryana to
follow.
2222
……Current IssuesCurrent Issues
• Market model for power procurement by Discoms
• Single Buyer Model • Multi Buyer Model
• ABT parameters/norms
• Treatment for Open Access Transactions– CPP/IPP/Wind Farms/Banking transactions
and Bulk consumers
2323
West DISCOM
GUJARAT STATE POWER POOL : Single Buyer Model
GEN 1
GEN 2
GEN 3
IPP 1
IPP 2
SouthDISCOM A
CentralDISCOM
North DISCOM
External Purchases
s
STATE GENCO
SELLS THROUGH GETCO SYSTEM
RESIDUAL GEB/TRADECO TO POOL ALL GENERATION
ISGS Allocations
SEC
AECo
Power Purchases/Sales
2424
GUJARAT STATE POWER POOL : Multiple Buyer Model
GEN 1
GEN 2
GEN 3
IPP 1
IPP 2
TRANSMISSION SYSTEM OF GETCO
STATE GENCO
SouthDISCOM A
CentralDISCOM
North DISCOM
West DISCOM
SEC
AECo
TRADECO
External Purchases
Power Purchases/Sales
2525
Metering philosophy Metering philosophy
GENCO Power Stations• One main meter for each Generator Transformer/ Station
Transformer • One (standby) meter for each outgoing feederLines connecting Discom-Discom• One meter each at both endsIPPs• One Meter (main) at IPP-end• One meter (standby) at Discom endOpen Access Customers• One Meter (main) at Injection-end• One meter (standby) at customers end
2626
Meter Location - philosophyMeter Location - philosophyLines connecting CPP-Discom• One meter (main) at CPP end• One meter (standby) at Discom endLines connecting embedded licensees with Discom• One meter (main) at Discom end• One meter (standby) at licensee’s endLines connecting CTU and STU points • Meters already provided
2727
Assessment of Meters/DCDs Assessment of Meters/DCDs - Alternatives- Alternatives
Alternative 1 :• Discom boundary at 11 kV feeder from 66/11 kV X’ers
– Metering at 11 kV side of 66/11 kV Xers.– More meters and data recording at lower voltage level would
add to inaccuracies.– Data collection would be exhaustive and unnecessary. Since
66kV network is owned by GETCO, proportionate losses would be borne by all Discoms.
– Lot of bulk customers are connected above 11kV and are consumers of Discoms. Metering requirement would be high.
– No. of meters exceed 3600 Nos. (incl 20% spares)– No. of DCDs/MTEs would be high
2828
DISCOM B
DISCOM A
400kV
220kV
132kV
66kV
11kV
M
Alternative 1: Metering at electrical Discom boundaries
MM
M
GENCO
CPP
GETCO/ ISTS Ties
GETCO/ ISTS Ties
S S
M
S
M
SM
S
M
S
No of meters>3600
2929
Assessment of Meters/DCDs Assessment of Meters/DCDs - Alternatives- Alternatives
Alternative 2 :
• Metering at 66kV side of X’ers of 220/66kV, 132/66kV.– Losses in 66kV transmission network included in actual
drawal.
– Inter-discom lines 66kV and below to be metered.
– Customers connected at 132kV and above to be metered ….?
– No. of meters 1195 (incl 20% spares)
– No. of DCDs 203 ( incl 20% spares)
3030
No of meters = 1195
DISCOM A
CPP
DISCOM B
400kV
220kV
132kV
66kV
11kV
Alternative 2: Metering at 66kV side of Xers
MM
M
GENCO
GETCO/ ISTS Ties
GETCO/ ISTS Ties
S S
M
S
M
S
M
S
M
S
LB
L = Losses in 66kV GETCO system borne by DISCOM , would be included in drawal of Discom
M
M
3131
Assessment of Meters/DCDs Assessment of Meters/DCDs - Alternatives- Alternatives
Alternative 3 :
• Metering at 220kV side of 220/66kV, 220/132kV X’ers .– Inter-discom lines at 132kV and below to be metered.
– Bulk customers connected at 220kV to be metered.
– Losses below 132kV and 66kV network included in the drawal
– No. of meters 772 (incl 20% spares)
– No. of DCDs 133 (incl 20% spares)
3232
No of meters = 772
DISCOM B
400kV
220kV
132kV
66kV
11kV
Alternative 3: Metering at 220kV side of220/132 and 220/66 Xers
MM
M
GENCO
GETCO/ ISTS Ties
GETCO/ ISTS Ties
S S
LB
M
S
M
S
M
S
M
S
M
M
3333
Assessment of Meters/DCDs Assessment of Meters/DCDs - Alternatives- Alternatives
Alternative 4 : RECOMMENDED ALTERNATIVE• Metering at Discom’s boundaries (the network dedicated to Discom)
– Metering at GETCO (Dedicated to Discom) – GETCO (dedicated to other discom)
– Metering at inter-Discom, Discom-to-Genco, Discom-to-IPP, Discom-to-CPP feeders
Advantages– Cost of metering and infrastructure for data communication would reduce
drastically.– Losses of dedicated overlayed GETCO network included in Discom drawal,
which anyway has to be apportioned. – Losses of common GETCO network shall be pooled.– As such differences between estimated and actual losses becomes
negligible.– No. of meters reduces to 614 (incl 20% spares)– No. of DCDs 114 (131 with 20% spares 131)
3434
No of meters = 614
L = Losses in GETCO system to be borne by DISCOM , would be included in drawal of Discom
DISCOM B
DISCOM A
400kV
220kV
132kV
66kV
11kV
M M
M
M
M
Alternative 4: Proposed Alternative Metering at notional Discom boundaries
M
MM
M
GENCO
CPP
MMGETCO/ ISTS Ties
GETCO/ ISTS Ties
L
S S
3535
Summary of Meter requirement for intra-state ABT in GujaratAlternative-4
No. DCDs
Main Standby Check Total
GSEC Power Stations 66 82 0 214 12
IPPs 21 0 0 21 5
DISCOMs
DGVCL 59 20 0 79 26
MGVCL 48 1 0 49 20
UGVCL 27 16 0 43 19
PGVCL 29 34 0 63 26
AECo 6 0 0 6 2
SECo 15 0 0 15 10
Windfarms 11 11 0 22 11
Sub-total 195 82 0 277 114
TOTAL 282 164 0 512 131
20% spares 102
Total 614
No. of Meters
3636
Intra-State ABT Intra-State ABT Parameters/norms…Parameters/norms…
– UI rate• Same as inter-state UI rate• Higher than inter-state UI rate• Lower than inter-state UI rate
– UI rate curve - slope• Multi-slope Curve
Options Option 1 : Two-part tariff with UI mechanism
• Capacity Charges – linked to availability• Variable Charges – linked to schedule• UI Charges – linked to deviations
Option 2 : Single part tariff with UI mechanism• GENCO to recover its costs through single-part (CC+VC) – linked to
schedule. In such a case, merit order suffers.• UI Charges – linked to deviations
3737
1. Higher UI Rate than region
2. Lower UI Rate than region
3. Differential UI Rate (Different UI rates for injection and drawal)
4. Regional UI Rate
Recommended UI Rate :
“Regional UI Rate” to start with
Options for UI Options for UI RateRate
3838
0
50
100
150
200
250
300
350
400
450
500
550
600
650
48.9 49 49.1 49.2 49.3 49.4 49.5 49.6 49.7 49.8 49.9 50 50.1 50.2 50.3 50.4 50.5 50.6 50.7 50.8 50.9 51
Frequency ----------->
UI ra
te
-----
------
------
>
Below 49.0 Hz UI rate =570 p/u
At 50.0 Hz UI rate =150 p/u
At 49.8 Hz UI rate =210 p/u
Above 50.5 Hz UI rate =0 p/u
UI RATE
Rate of Unscheduled Drawal/InjectionFrequency (Hz) Rate (p/u)
Above 50.5 0
50.0 150
49.8 210
49.0 and below 570
3939
Options for UI Options for UI RateRate
Rationale:1. It is important that we avoid the problem of different and
inconsistent mechanisms at inter-state and intra-State levels. The uniformity in two mechanisms are stressed for the following reasons:
• Intra-State balancing mechanism should result in matching UI charges to be paid/received to/from State UI pool from/to regional UI Pool.
• Pricing signals received from inter-State balancing and spot market should be passed downward to intra-State level so as to avoid seams across State boundaries. Different State and regional commercial mechanisms would cause host of other issues caused by inconsistent mechanisms.
• The electricity available within the State should not be priced in a different manner so that one is preferred over another specially when the cost of generation is the same.
4040
– Allocations to Discoms from shared generating plants -to be notified by State government
• State generators• Central Sector generators• IPPs
– Criteria to be finalised • In percentages, not in MW terms• No capacity to remain unallocated
Intra-State ABT Parameters/norms…
4141
– STU’s role in collection and disbursement of
• STU’s transmission charges• CTU’s transmission charges • Intra-State UI charges• Regional UI charges• Intra-State Reactive Energy charges• Regional Reactive Energy charges• RLDC fees and charges
Intra-State ABT Intra-State ABT Parameters/norms…Parameters/norms…
4242
– Tariff norms for State Generating Plants
• Financial Norms – similar to ISGS – Depreciation, Rate of return, O&M Cost,
Debt : Equity ratio, etc.• Operational Norms – similar to ISGS
– Auxiliary power consumption– Target availability
• Can be reviewed in 5 years.• Scheme for incentives – based on plant
availability.
Intra-State ABT Intra-State ABT Parameters/norms…Parameters/norms…
4343
– Re-negotiation of existing contracts with IPPs….?
• Financial Norms – as per ISGS – Depreciation, Rate of return, O&M Cost, D:E ratio etc.– Incentives
• Operational Norms – as per ISGS – Auxiliary power consumption– Target availability 80%
Intra-State ABT Intra-State ABT Parameters/norms…Parameters/norms…
4444
Scheme for Reactive Energy ChargeScheme for Reactive Energy Charge
Proposal 1: Similar to scheme for Regional ISTS• Discom pays/receives for VAR drawal/absorption for Var
exchanges at inter-utility connection point – Pays for Var drawal when voltage is below 97%.– Receives for VAR return when voltage is below 97%– Receives for VAR drawal when voltages above 103% and– Pays for VAR return when voltages above 103%.– No charges for VAR drawal/return between 97%-103%
• Charges payable/receivable by IPPs/ State Genco – variation from Regional scheme – so as to incentivse them to inject/absorb for better system operation
• Use 0.5 class meters being installed by SML/Elster/L&T. As per Option 4, metering is proposed at notional boundaries of Discom network and not at actual drawal points.
• Pricing at about 10p/kVarh to incentivise installation of HT Capacitors
4545
Scheme for Reactive Energy ChargeScheme for Reactive Energy Charge
Proposal 2: Hybrid Scheme
• Payment of Var charges to ISGS as per Regional scheme – Use ABT meters at SGS-Discom tie-points
• Payment of Var charges by Discoms to Transco as per scheme similar to HT consumers.– Use normal meters at Transco-Discom tie-points
4646
Category 1 :
– CPPs having net injectable capacity > 5MW would be under ABT/UI mechanism
– Net Injection = Injection –(Consumption + Wheeling Losses)
Wheeling losses will depend on voltage level of connection points. Typical cases
Case 1 : When Injection and Consumption at the same bus – Wheeling Loss = 0
Case 2 : When Injection and Consumption in same Discom
Wheeling Losses = Average Distribution Loss of Discom
Case 3 : When Injection and Consumption points at Transco
Wheeling Losses = Average Transmission Loss of Transco
Proposed Scheme for CPPs
4747
– CPPs divided in two Categories for their applicability for ABT
Category 1: CPPs having net injection > 5MW– All deviations to be treated at UI rates, ABT Meters would
be required.
Two Proposals for accounting for CPPs
Proposal 1• Consider pre-fixed Schedules at both connection points as NIL• Measure Actual Injection at Injection-point (time-block wise)• Actual Consumption at Consumption-point (time-block wise)• Fix Post-facto Schedule at Injection-point = Actual
Consumption +Wheeling Losses• Calculate UI = Actual Injection at Injection-point - Post facto
Schedule at Injection point
Proposed Scheme for CPP
4848
Proposal 2
– Fix Schedules as given by CPP
– We may decide the procedure for fixing schedule production and consumption ends
• Whether schedule to be collected every day? And allow different schedules at different times of day? OR
• Fixed schedule for a period (say 3 months) and no change within day and during currency of transaction allowed.
OR• Treat as Open Access Transaction to be approved by SLDC
and all wheeling and Scheduling/Operation charges collected by SLDC in advance
Proposed Scheme for CPP
4949
Category 2 : CPPs having net injection < 5MW including those whose drawal > injection
• Existing commercial mechanism• HT rates of GEB • Ordinary meters would be sufficient
Proposed Scheme for CPP
5050
Large Consumers
1. Large Consumers >20MW not desiring Open Access• ABT/UI mechanism to apply.
• Rationale: Consumers with demand more than 1% of average Discom (average load 2000MW) would affect the UI of Discom.
2. Large Consumers <20MW not desiring Open Access• Same as at present.
Wind Farms not desiring Open Access • Not under UI
• Renewable Energy Obligations under GERC regulations would apply.
Commercial Mechanism for Commercial Mechanism for Large Consumers / Wind FarmsLarge Consumers / Wind Farms
5151
a) Treatment of Existing Banking Transactions
• Injection and drawals would be treated at prevailing UI rates
• Netting of injection and drawals not in terms of enrgy but in rupees terms
• Payment receivable by the agency for its Injection = 0.9 x UI charges for injection
• Payment payable by the agency for its Drawal = 1.1 x UI charges for drawals
• 10% will go towards wheeling since no such wheeling charges are being charged. Schedule = 0.
Net payment would be the sum of above two charges.
b) Treatment for new Banking Transactions
• To be discouraged and
• other stipulations for CPP/Co-gen would apply.
Commercial Mechanism for Banking Arrangements
5252
Implementation PlanImplementation Plan
• 1st Phase Activities By end October,04– Finalisation of listing of entities– Listing of Metering locations– Finalisation of quantities of SEMs, DCDs/MTEs– Finalisation of Reactive Charge scheme– Finalisation of technical specifications of SEMs/DCDs– Initiate tendering process for procurement of meters– Explanation of Intra-state ABT
5353
Implementation PlanImplementation Plan
• 2nd Phase Activities By end December,04– Finsalisation of Tariff of State Generating Stations as
per ABT parameters/norms– Determination of Allocations of different Discoms in
State Genco/ ISGS/ IPPs.– Formulation of market structure – Conversion of existing PPAs into ABT-compliant form– Finalisation of commercial mechanism for CPPs,
Wind farms, Wheeling and banking, Open Access Customers etc.
5454
Implementation PlanImplementation Plan
• 3rd Phase Activities By end March,05
– Supply and commissioning of meters at different locations
– Training the field staff for meter reading/data collection
– Installation of software for data processing – Installation of software for scheduling– Organising UI and REC Pool Account Operation
5555
Concluding remarks…Concluding remarks…
• Listing of Entities for ABT Implementation
• Finalise the State Power Pool – Single/Multi Buyer
• Alternative for Metering Scheme
• Meter Data Collection Mechanism – Manual/AMR
• Generation Tariff Notification by GERC
5656
Concluding remarks…Concluding remarks…
• Open Access Notification by GERC
• UI Rate for Intra-State ABT
• Renegotiation of Existing Contracts with IPPs/CPPs
• Meter procurement process to commence at the earliest
• Listing of SEMs to be checked by GEB
5757
0
50
100
150
200
250
300
350
400
450
500
550
600
650
48.9 49 49.1 49.2 49.3 49.4 49.5 49.6 49.7 49.8 49.9 50 50.1 50.2 50.3 50.4 50.5 50.6 50.7 50.8 50.9 51
Frequency ----------->
UI ra
te
-----
------
------
>
Below 49.0 Hz UI rate =570 p/u
At 50.0 Hz UI rate =150 p/u
At 49.8 Hz UI rate =210 p/u
Above 50.5 Hz UI rate =0 p/u
UI RATE
Rate of Unscheduled Drawal/InjectionFrequency (Hz) Rate (p/u)
Above 50.5 0
50.0 150
49.8 210
49.0 and below 570
5858
Schedule Vs Actual Injection at ISGSSchedule Vs Actual Injection at ISGS
Declared Capability ά Capacity Charges
Schedule ά
Energy Charges
Actual InjectionU I
Frequency
NEXT
5959
Schedule Vs Actual Drawal by StateSchedule Vs Actual Drawal by State
Entitlement ά
Capacity Charges
Schedule ά
Energy Charges
Actual Drawal
Frequency
U I
6060
Schedule Vs Drawal by GEBSchedule Vs Drawal by GEB
600
800
1000
1200
1400
1600
1800
2000
2200
00:00
00:45
01:30
02:15
03:00
03:45
04:30
05:15
06:00
06:45
07:30
08:15
09:00
09:45
10:30
11:15
12:00
12:45
13:30
14:15
15:00
15:45
16:30
17:15
18:00
18:45
19:30
20:15
21:00
21:45
22:30
23:15
SCHLD DRAWL ENTIT
Frequency & GEB Schedule / Drawal(27.07.2002)
WRLDC MUMBAIMW
47.5
49
50.5
FREQ
Frequency
Drawal
Schedule
Overdrawal at High Frequency
UI
6161
Flattening of Load CurveFlattening of Load Curve
5000
5500
6000
6500
7000
7500
80001 3 5 7 9
11
13
15
17
19
21
23
Hrs
De
man
d in
Mw
GUJ DEM ON 20.06-02 GUJ DEM ON 20.09.02
Demand Curve in Sep,02
Demand Curve in June,02
6262
Open Access Open Access Within Discom :Within Discom :
Captive Generation Load
Open Access within Discom
Discom Boundaries
Issue:To ensure X = Y+ Wheeling LossesAnd Method for pricing deviations
X Y
6363
Within Discom :• Issues:
– Wheeling Charges to be decided by SERC
– Wheeling losses to be decided by SERC
– Pricing of deviations between X (injection into grid) and sum of Y(drawal from grid) +Wheeling Losses
– Pricing of deviations depending on ‘Size’ ?
– Metering similar to SEMs installed for ABT
ABT for embedded utilities -ABT for embedded utilities -
6464
Open Access Open Access Across Discoms :Across Discoms :
Captive Generation Load
Open Access across Discoms
Discom A Discom B
X Y
6565
Open Access and ABT for embedded Open Access and ABT for embedded utilities - Case Studies utilities - Case Studies
Across Discoms :• Issues:
– Wheeling Charges to be decided by GERC– Wheeling losses payable to STU/Discoms as
decided by SERCs– Scheduling by SLDC– Pricing of deviations between X (injection into grid)
and sum of Y(drawal from grid) +Wheeling Losses.– Pricing of deviations depending on ‘Size’ ?
6666
EXISTING STU TARIFF (effective from 21.07.2004)EXISTING STU TARIFF (effective from 21.07.2004)
• Applicable to all ST consumers having contracted demand more than 100 KVA
1. Demand Charges
1.1 For billing demand upto contract demand:
For first 500 KVA of billing demand Rs.89.25 per kVA per month
For next 500 kVA of billing demand Rs.126 per kVA per month
For next 1500 kVA of billing demand
Rs.189 per kVA per month
For billing demand in excess of 2500 kVA
Rs.215.25 per kVA per month
1.2 For billing Demand in Excess of Contract Demand:
For billing demand in excess over the contract demand
Rs.335 per kVA per month
6767
PLUS
Energy Charges
For entire consumption during the month
Upto 1000 kVA contract demand 380 paise per unit
For 1001 kVA to 2500 kVA contract demand
400 paise per unit
Above 2500 kVA contract demand 410 paise per unit
PLUSTime of Use Charges(These charges shall be levied from a consumer having contract demand or actual demand of 500 kVA and above):
For energy consumption during the two peak periods, viz., 0700 Hrs to 1100 Hrs and 1800 Hrs to 2200 Hrs
75 paise per unit
6868
Billing Demand
The billing demand shall be the highest of the following:
• Actual maximum demand established during the month
• Eighty-five percent of the contract demand
• One hundred kVA
• Power Factor– Power Factor Adjustment Charges:
• The power factor adjustment charges shall be levied at the rate of 1% on the total amount of electricity bills for the month under the head “Demand Charges” and “Energy Charges” for every 1% drop or part thereof in the average power factor during the month below 90% upto 85%.
• In addition to the above clause, for every 1% drop or part thereof in average power factor during the month below 85% at the rate of 2% on the total amount of electricity bill for that month under the head “Demand Charges” and “Energy Charges” will be charged.
6969
49.0 49.8 50.249.4 50.6 Hz
Incremental Cost (Paise/kWH)U
I
Pri
ce
System Frequency
Sta
tion
Gen
erat
ion
75 %
25 %
0 %
50 %
420
280
140
0
100 %
Pool Price
MA
NU
AL
LO
AD
-SHE
DD
ING
DIE
SEL
GE
NR
, DE
PLE
TE
D H
YD
RO
GA
S - TU
RB
INE
NO
RM
AL
HY
DR
O
LO
AD
-CE
NT
ER
CO
MB
INE
D C
YC
LE
PIT - H
EA
D
NU
CL
EA
R
OV
ER
FLO
WIN
G H
YD
RO
Typical Graph Depicting Pricing of Unscheduled Interchanges Typical Graph Depicting Pricing of Unscheduled Interchanges w.r.t. System Frequencyw.r.t. System Frequency
7070
AP KAR KER TN PONDY
Total UI exported(-) /
Imported(+) in MUs
-4441 4132 1210 1163 -140
Total amount paid in Crores
Rs.-899 768 204 344 28
Average rate of UI in paise/unit 202 186 169 296 203
SUMMARY OF UI – 124 WKSSUMMARY OF UI – 124 WKS
7171
UI IN SRUI IN SR
• TOTAL UI TURNOVER :- 7792 MU
• TOTAL UI AMOUNT DISBURSED:- 1600 CR
• AVG WEEKLY TRANSACTION:- 63 MU
• AVG WEEKLY UI AMOUNT DISBURSED:- 13 CR
ABT, Intra-State ABT, Intra-State ABTABT
SRLDCSRLDC
Power Grid Corporation of India Ltd.Power Grid Corporation of India Ltd.
BANGALOREBANGALORE