1 REVIEW OF RAPDRP PART A PROGRESS IN KARNATAKA 21.07.2014 RESTRUCTURED ACCELERATED POWER...

7
1 REVIEW OF RAPDRP PART A PROGRESS IN KARNATAKA 21.07.2014 RESTRUCTURED ACCELERATED POWER DEVELOPMENT AND REFORMS PROGRAMME (R-APDRP)

Transcript of 1 REVIEW OF RAPDRP PART A PROGRESS IN KARNATAKA 21.07.2014 RESTRUCTURED ACCELERATED POWER...

Page 1: 1 REVIEW OF RAPDRP PART A PROGRESS IN KARNATAKA 21.07.2014 RESTRUCTURED ACCELERATED POWER DEVELOPMENT AND REFORMS PROGRAMME (R-APDRP)

1

REVIEW

OF

RAPDRP PART A PROGRESS

IN KARNATAKA

21.07.2014

RESTRUCTURED ACCELERATED POWER DEVELOPMENT AND REFORMS PROGRAMME (R-APDRP)

Page 2: 1 REVIEW OF RAPDRP PART A PROGRESS IN KARNATAKA 21.07.2014 RESTRUCTURED ACCELERATED POWER DEVELOPMENT AND REFORMS PROGRAMME (R-APDRP)

Go-Live Status of ESCOM’s of Karnataka

Town Integration Energy Audit Schedule

Month

Up to

Jan’ 13

Up to

Feb’ 13

Up to

Mar’ 13

Up to

Apr’ 13

Up to

May’ 13

Up to

Jun’ 13

Up to Jul’ 13

Up to

Aug’ 13

Up to

Sep’ 13

Up to

Oct’ 13

Up to

Nov’ 13

Up to

Dec’ 13

Up to

Jan’ 14

Up to

Feb’ 14

Up to

Mar’ 14

Up to

Apr’ 14

Up to

May’ 14

Up to

Jun’ 14

Up to Jul’ 14

Up to

Aug’ 14

Up to

Sep’ 14

Target 10 18 40 40 50 50 50 50 53 55 75 91 98 98 98 98 98 98 98 98 98Achieved 6 10 31 31 46 46 46 46 46 46 46 51 51 60 60 60 60

Scheduled date for Go live / integration of all towns : Sep 2014

RESTRUCTURED ACCELERATED POWER DEVELOPMENT AND REFORMS PROGRAMME (R-APDRP)

ESCOM MBC live(100% implementation in

Karnataka)

Full Stack with Energy Audit

BESCOM 25 16

CESC 12 6

GESCOM 21 11

HESCOM 29 26

MESCOM 11 1

TOTAL 98 60 2

Page 3: 1 REVIEW OF RAPDRP PART A PROGRESS IN KARNATAKA 21.07.2014 RESTRUCTURED ACCELERATED POWER DEVELOPMENT AND REFORMS PROGRAMME (R-APDRP)

RESTRUCTURED ACCELERATED POWER DEVELOPMENT AND REFORMS PROGRAMME (R-APDRP)

Module wise / ESCOM’s Wise Status as on May 2014% progress taken SDO wise

CCC Operational across All ESCOMs

ESCOM Total Town

s

Total SDOs

Office Infrastructu

re

Primary Network

Secondary Network

MBC Go Live

GIS Network

Approved

GIS Consumer Approved

Meter-installed

Modems installed

Full Stack Go-Live

BESCOM 25 74 74 100% 74 100% 43 70% 74 100% 74 100% 74 100% 29 40% 1 1% 16 22%

CESC 12 19 19 100% 19 100% 19 100% 19 100% 19 100% 19 100% 10 53% 6 32% 6 32%

GESCOM 21 23 23 100% 23 100% 21 91% 23 100% 23 100% 23 100% 23 100% 21 60% 11 48%

HESCOM 29 37 37 100% 37 100% 26 70% 37 100% 37 100% 37 100% 37 100% 34 92% 23** 70%

MESCOM 11 17 17 100% 17 100% 15 88% 17 100% 5 30% 4 24% 11 65% 1 6% 1 5%

Total 98 170 170 100% 170 100% 124 84% 169 100% 158 86% 157 85% 110 72% 63 38% 34 35%

• *Only for 26 towns modems are installed and all 29 towns DTC meter DLMS meters installed.

• ** 23 towns FS go-live ( Hubli-dharwad, Belgaum, Bijapur, Gadag, Bagalkot & Ranebennur pending). Only 19 towns DTC SIMs are activated, balance 4 towns DTC SIMs activation is under progress by RCOM. SIMs are communicating in 12 towns only i.e. also about 30% only & SIMs in balance 7 towns are not actually communicating. Out of 4852 only 701 no.s of modems are communicating.

Page 4: 1 REVIEW OF RAPDRP PART A PROGRESS IN KARNATAKA 21.07.2014 RESTRUCTURED ACCELERATED POWER DEVELOPMENT AND REFORMS PROGRAMME (R-APDRP)

CRITICAL ISSUES OF PROJECT IMPLEMENTATION Issues Resolution

Network issues / Performance and availability

1. Increase of Bandwidth from 2Mbps to 4Mbps at each SDO of BESCOM, with Optical fiber as

the last mile connectivity.

2. ITIA to confirm on the application stability after up gradation of the network to 4Mbps.

3. Reliance Links going down early during office hours and restoration after office hours

4. At many sites tickets are not getting resolved within 24hrs as per SLA

5. Links frequently going down due to Packet drops , Latency , fibre cuts, Link Flapping and no

proper power back up for the Base Transceiver Station(BTS) towers of RCOM

6. BSNL links being integrated by ITIA in some sites as an alternate to meet the targets.

GIS • Deployment of GIS based integrated Network analysis Module NEPLAN pending by ITIA.

• Incremental data updates on Network and Consumers incorporated by ITIA at Mulbagil town

only

• Poor performance of GIS Online application, ITIA has informed the same is due to license

issues. A committee formed y BESCOM comprising directors of IEEE to deliberate on the

same, the committee has opined addition of hardware and requisite software will only

provide marginal increase in performance and not in an order of magnitude, with the

following recommendations

• Committee has suggested changes / implants to GIS architecture and ITIA to incorporate the

same. 4

RESTRUCTURED ACCELERATED POWER DEVELOPMENT AND REFORMS PROGRAMME (R-APDRP)

Page 5: 1 REVIEW OF RAPDRP PART A PROGRESS IN KARNATAKA 21.07.2014 RESTRUCTURED ACCELERATED POWER DEVELOPMENT AND REFORMS PROGRAMME (R-APDRP)

CRITICAL ISSUES OF PROJECT IMPLEMENTATION RESTRUCTURED ACCELERATED POWER DEVELOPMENT AND REFORMS PROGRAMME (R-APDRP)

Module: GIS based Consumer Indexing and Asset mapping

Benefits of Bypass GIS online for loads up to 10HP/ 7.5kW: •As a measure to simplify the process in RAPDRP end-to-end application and in accordance with KERC regulation, online GIS application is bypassed for Customer loads up to 10HP/ 7.5kW where there is no extension of network. This process is deployed w.e.f 17.04.2014.•Speedy disposal of New Connection cases using By-Pass GIS On-line option: For a single connection, users are able to save 20-25 minutes in the end-to-end process.•Currently, BYPASS GIS option is built for SINGLE NEW CONNECTIONS. This option is to be built for “LOAD ENHANCEMENT”, “LOAD REDUCTION” and “MULTIPLE CONNECTION” cases by ITIA.

Page 6: 1 REVIEW OF RAPDRP PART A PROGRESS IN KARNATAKA 21.07.2014 RESTRUCTURED ACCELERATED POWER DEVELOPMENT AND REFORMS PROGRAMME (R-APDRP)

CRITICAL ISSUES OF PROJECT IMPLEMENTATION Issues Resolution

GIS i. Feature restriction to be done immediatelyii. MAP slicing to be done at division level.iii. Explore switchover from web editing mode to client editing mode.iv. Optimise On-line GIS by-pass for other use casesv. Carryout an exercise by executing a live case of Asset creating in GIS at Data Centre

and observe the performance of the application and check all the logs in the system process-wise.

vi. Committee felt it is not very confident that procurement of licenses will be very helpful unless the above issues are taken care. Hence ITIA is asked to implement the suggestions as above

MDAS • The legacy meter replacement to DLMS meters are in progress.• 44295 No’s of meters already fixed and commissioned and balance 9589 Nos yet to be fixed

BESCOM.• 17251 modems installed by ITIA as on date 21115 modems yet to be installed.

Energy Audit • SIM card not communicating.• Gaps in GIS Incremental update and PART B network upgradation.• Modems burnt out issue• Additional Chief Secretary to conduct a meeting with ITIA and Modem Vendor.

New Connection • Process simplification by introducing bypass of GIS online for loads up to 10HP/ 7.5kW

Asset and Maintenance Management

• WAMS system down since 01 June 2014, manual updation in progress till the system stabilizes

6

RESTRUCTURED ACCELERATED POWER DEVELOPMENT AND REFORMS PROGRAMME (R-APDRP)

Page 7: 1 REVIEW OF RAPDRP PART A PROGRESS IN KARNATAKA 21.07.2014 RESTRUCTURED ACCELERATED POWER DEVELOPMENT AND REFORMS PROGRAMME (R-APDRP)

RAPDRP PART-A FINANCIAL PROGRESS

Rs in Crores

RESTRUCTURED ACCELERATED POWER DEVELOPMENT AND REFORMS PROGRAMME (R-APDRP)

ESCOMNO.OF

TOWNSTOTAL

PROJECT COST

LOAN SANCTIONED (Convertible to

Grant )

PFC DISBURSEMENT

DETAILS

TOTAL EXPENDITURE INCURRED

FROM PFC FUNDS

FROM OWN FUNDS

TOTAL

BESCOM 25 282.70 261.36 146.65 101.27 24.62* 125.89

MESCOM 11 25.33 12.07 7.24 7.24 7.19 14.43

CESC 12 27.80 27.73 16.64 11.7 0 11.7

HESCOM 29 53.30 52.62 15.78 15.78 22.26 38.04

GESCOM 21 38.70 37.36 11.21 10.53 - 10.53

TOTAL 98 427.83 391.14 197.52 146.52 54.07 200.59

7

* Rs. 24.62 crores spent for metering out of BESCOM funds