1 PHARE Achievements Dr. H. Schröter PHARE Programme Manager EUROCONTROL version 1.1, 31.5.99.
-
Upload
wyatt-barnes -
Category
Documents
-
view
221 -
download
7
Transcript of 1 PHARE Achievements Dr. H. Schröter PHARE Programme Manager EUROCONTROL version 1.1, 31.5.99.
![Page 1: 1 PHARE Achievements Dr. H. Schröter PHARE Programme Manager EUROCONTROL version 1.1, 31.5.99.](https://reader036.fdocuments.us/reader036/viewer/2022082701/55154d735503465e608b6553/html5/thumbnails/1.jpg)
11
PHARE AchievementsPHARE Achievements
Dr. H. SchröterDr. H. Schröter
PHARE Programme ManagerPHARE Programme Manager
EUROCONTROLEUROCONTROL
version 1.1 , 31.5.99version 1.1 , 31.5.99
![Page 2: 1 PHARE Achievements Dr. H. Schröter PHARE Programme Manager EUROCONTROL version 1.1, 31.5.99.](https://reader036.fdocuments.us/reader036/viewer/2022082701/55154d735503465e608b6553/html5/thumbnails/2.jpg)
22
PHARE’s AchievementsPHARE’s Achievements
Outline the Achievements of PHAREOutline the Achievements of PHARE Specific results and lessons learnt are covered in Specific results and lessons learnt are covered in
other presentationsother presentations Spin-offs from PHARE for early implementation Spin-offs from PHARE for early implementation
and further developmentand further development Highlight the successes, not hiding the items Highlight the successes, not hiding the items
which did not workwhich did not work Influence on the future ATM R&D in EuropeInfluence on the future ATM R&D in Europe ATM R&D coordinationATM R&D coordination
![Page 3: 1 PHARE Achievements Dr. H. Schröter PHARE Programme Manager EUROCONTROL version 1.1, 31.5.99.](https://reader036.fdocuments.us/reader036/viewer/2022082701/55154d735503465e608b6553/html5/thumbnails/3.jpg)
33
Potential ATM Research Issues as seen in 1990
Potential ATM Research Issues as seen in 1990
Airborne and ground systems interaction Airborne and ground systems interaction The possible and acceptable level of The possible and acceptable level of
automation supportautomation support The man-machine interactionThe man-machine interaction The influence of airspace organisation and The influence of airspace organisation and The procedures applied by ATCThe procedures applied by ATC
![Page 4: 1 PHARE Achievements Dr. H. Schröter PHARE Programme Manager EUROCONTROL version 1.1, 31.5.99.](https://reader036.fdocuments.us/reader036/viewer/2022082701/55154d735503465e608b6553/html5/thumbnails/4.jpg)
44
Key PHARE Research Topics
Key PHARE Research Topics
Full use of the capabilities of the aircraft’s Full use of the capabilities of the aircraft’s systems , Development of the Experimental systems , Development of the Experimental Flight Management SystemFlight Management System
Advanced automation support for controllers Advanced automation support for controllers Ground Human Machine Interface for operating Ground Human Machine Interface for operating
such automation supportsuch automation support Use of datalink for the exchange of information Use of datalink for the exchange of information
between air and ground, in particular for the between air and ground, in particular for the process of trajectory negotiationprocess of trajectory negotiation
Better meteorological forecasting to improve the Better meteorological forecasting to improve the trajectory predictiontrajectory prediction
Use of common methodology and standard tools/ Use of common methodology and standard tools/ procedures for validation.procedures for validation.
![Page 5: 1 PHARE Achievements Dr. H. Schröter PHARE Programme Manager EUROCONTROL version 1.1, 31.5.99.](https://reader036.fdocuments.us/reader036/viewer/2022082701/55154d735503465e608b6553/html5/thumbnails/5.jpg)
55
The PHARE ProgrammeThe PHARE Programme
Progressive increased collaboration :Progressive increased collaboration : Exchange of information and harmonisation of toolsExchange of information and harmonisation of tools Formulation of common goals and exchange of resultsFormulation of common goals and exchange of results Definition and execution of shared and commonly Definition and execution of shared and commonly
financed activitiesfinanced activities
Merging of “bottom-up” and “top-down”, definition of Merging of “bottom-up” and “top-down”, definition of a structured research programmea structured research programme
11 Projects with defined timescale and budget frame11 Projects with defined timescale and budget frame Basic PHARE Agreement complemented by a special Basic PHARE Agreement complemented by a special
agreement for each projectagreement for each project
![Page 6: 1 PHARE Achievements Dr. H. Schröter PHARE Programme Manager EUROCONTROL version 1.1, 31.5.99.](https://reader036.fdocuments.us/reader036/viewer/2022082701/55154d735503465e608b6553/html5/thumbnails/6.jpg)
66
PHARE StudiesPHARE Studies
““Medium Term Scenario 2000-2015” Medium Term Scenario 2000-2015” Description of the PHARE ConceptDescription of the PHARE Concept
Complemented by :Complemented by :Detailed operational specifications and Detailed operational specifications and scenario descriptions for each of the scenario descriptions for each of the PHARE DemonstrationsPHARE Demonstrations
““Operational experiments within PHARE”Operational experiments within PHARE” ““The role of the man within PHARE”The role of the man within PHARE” ““PHARE Air-Ground Data Exchange”PHARE Air-Ground Data Exchange”
![Page 7: 1 PHARE Achievements Dr. H. Schröter PHARE Programme Manager EUROCONTROL version 1.1, 31.5.99.](https://reader036.fdocuments.us/reader036/viewer/2022082701/55154d735503465e608b6553/html5/thumbnails/7.jpg)
77
Airborne Programme (1)Airborne Programme (1)
Airborne Programme: two closely relatedAirborne Programme: two closely related projectsprojects
1.1. Experimental Flight Management System Experimental Flight Management System (EFMS)(EFMS)2.2. Airborne Human Machine Interface (AHMI)Airborne Human Machine Interface (AHMI)
EFMS DevelopmentEFMS Development to demonstrate the capabilities of advanced 4D FMSto demonstrate the capabilities of advanced 4D FMS to negotiate “User preferred trajectories”to negotiate “User preferred trajectories” to guide the aircraft on that trajectory in space and timeto guide the aircraft on that trajectory in space and time
AHMIAHMI to allow pilots (of live research aircraft) in a realistic cockpit environment to to allow pilots (of live research aircraft) in a realistic cockpit environment to
participate in the real-time simulation experimentsparticipate in the real-time simulation experiments
![Page 8: 1 PHARE Achievements Dr. H. Schröter PHARE Programme Manager EUROCONTROL version 1.1, 31.5.99.](https://reader036.fdocuments.us/reader036/viewer/2022082701/55154d735503465e608b6553/html5/thumbnails/8.jpg)
88
EFMS and AHMI deployed inEFMS and AHMI deployed in VFW VFW (Advanced Technology Testing Aircraft)(Advanced Technology Testing Aircraft) of DLR of DLR (Germany)(Germany) CESSNA CITATION II of NLR (The Netherlands)CESSNA CITATION II of NLR (The Netherlands) BAC1-11 of NATS/DERABAC1-11 of NATS/DERA the Multi-Cockpit Simulator (Boeing 747) of EUROCONTROL Experimental Centre the Multi-Cockpit Simulator (Boeing 747) of EUROCONTROL Experimental Centre (Brétigny, (Brétigny,
France)France)
Airline pilots participated inAirline pilots participated in specific evaluation of these systemsspecific evaluation of these systems PHARE DemonstrationsPHARE Demonstrations
Overall great successOverall great success Concept of 4D Navigation readily achievableConcept of 4D Navigation readily achievable Direct manipulation of trajectories appreciatedDirect manipulation of trajectories appreciated Trajectory negotiation quickly assimilatedTrajectory negotiation quickly assimilated
Airborne Programme (2)Airborne Programme (2)
![Page 9: 1 PHARE Achievements Dr. H. Schröter PHARE Programme Manager EUROCONTROL version 1.1, 31.5.99.](https://reader036.fdocuments.us/reader036/viewer/2022082701/55154d735503465e608b6553/html5/thumbnails/9.jpg)
99
PHARE Common Modular Simulator (CMS)
PHARE Common Modular Simulator (CMS)
Aimed at providing an environment for interfacing software Aimed at providing an environment for interfacing software components from the different partners and providing a components from the different partners and providing a platform for initial testingplatform for initial testing
Definition of an open modular architecture and Application Definition of an open modular architecture and Application Programming InterfacesProgramming Interfaces
Prototype development of such common platform showing Prototype development of such common platform showing the technical feasibility of its approach , successfully achievedthe technical feasibility of its approach , successfully achieved
Full application for PHARE Demonstrations has not been Full application for PHARE Demonstrations has not been achievedachieved
CMS project has contributed significantly to the present CMS project has contributed significantly to the present definition of a European ATM integration platformdefinition of a European ATM integration platform
![Page 10: 1 PHARE Achievements Dr. H. Schröter PHARE Programme Manager EUROCONTROL version 1.1, 31.5.99.](https://reader036.fdocuments.us/reader036/viewer/2022082701/55154d735503465e608b6553/html5/thumbnails/10.jpg)
1010
PHARE Advanced Tools (PATs) set
PHARE Advanced Tools (PATs) set
Common Definition and Development of nine Common Definition and Development of nine Advanced Tools by separate teams of the partnersAdvanced Tools by separate teams of the partners
No missing functionality or tool was found in the No missing functionality or tool was found in the experimental trials, however some conceptual experimental trials, however some conceptual mismatchesmismatches
The objective of each tool was achieved and all were The objective of each tool was achieved and all were used in one or the other PHARE trialused in one or the other PHARE trial
The objective to use The objective to use all tools together in one tool-setall tools together in one tool-set in the PD/3 trials was not successfully achievedin the PD/3 trials was not successfully achieved
The Demonstrations showed that some tools provided The Demonstrations showed that some tools provided considerable advantages even without data link and considerable advantages even without data link and 4D trajectories4D trajectories
![Page 11: 1 PHARE Achievements Dr. H. Schröter PHARE Programme Manager EUROCONTROL version 1.1, 31.5.99.](https://reader036.fdocuments.us/reader036/viewer/2022082701/55154d735503465e608b6553/html5/thumbnails/11.jpg)
1111
PHARE Ground Human Machine Interface (GHMI)PHARE Ground Human
Machine Interface (GHMI)
Elaboration of Human-Machine Interface Elaboration of Human-Machine Interface specifications by an international team of specifications by an international team of human factors specialist, engineers, human factors specialist, engineers, operational expertsoperational experts
Advanced features used : Colour, windowing, Advanced features used : Colour, windowing, features of standard software toolsfeatures of standard software tools
Highly successful, major contribution to a Highly successful, major contribution to a quasi standard future HMIquasi standard future HMI
![Page 12: 1 PHARE Achievements Dr. H. Schröter PHARE Programme Manager EUROCONTROL version 1.1, 31.5.99.](https://reader036.fdocuments.us/reader036/viewer/2022082701/55154d735503465e608b6553/html5/thumbnails/12.jpg)
1212
PHARE Aeronautical Telecommunications Network (PATN)
PHARE Aeronautical Telecommunications Network (PATN)
Datalink is a key element of the PHARE conceptDatalink is a key element of the PHARE concept PHARE Demo 1 used enhanced Mode-S capabilitiesPHARE Demo 1 used enhanced Mode-S capabilities PHARE Demo 2 used a dedicated high speed VHF data linkPHARE Demo 2 used a dedicated high speed VHF data link For PHARE Demo 3 an experimental Aeronautical For PHARE Demo 3 an experimental Aeronautical
Telecommunication Network (using the SATCOM Telecommunication Network (using the SATCOM subnetwork) was set-upsubnetwork) was set-up
Disappointing performance of the SATCOM subnetworkDisappointing performance of the SATCOM subnetwork More work needs has to be done (and has started) using More work needs has to be done (and has started) using
commercial data link to demonstrate their capabilities for commercial data link to demonstrate their capabilities for future ATM applicationsfuture ATM applications
![Page 13: 1 PHARE Achievements Dr. H. Schröter PHARE Programme Manager EUROCONTROL version 1.1, 31.5.99.](https://reader036.fdocuments.us/reader036/viewer/2022082701/55154d735503465e608b6553/html5/thumbnails/13.jpg)
1313
PHARE Meteorological projectPHARE Meteorological project
Additionally contracted Partners :Additionally contracted Partners : UK MET officeUK MET office METEO FranceMETEO France
Successful development and test of a numerical Successful development and test of a numerical prediction model using aircraft derived down-linked prediction model using aircraft derived down-linked data to achieve an improved weather “nowcast”data to achieve an improved weather “nowcast”
Not used in real-time as component of the PHARE Not used in real-time as component of the PHARE DemonstrationsDemonstrations
Considered as a potential solution for future Considered as a potential solution for future implementationimplementation
![Page 14: 1 PHARE Achievements Dr. H. Schröter PHARE Programme Manager EUROCONTROL version 1.1, 31.5.99.](https://reader036.fdocuments.us/reader036/viewer/2022082701/55154d735503465e608b6553/html5/thumbnails/14.jpg)
1414
PHARE Validation projectPHARE Validation project
Development of a common methodologyDevelopment of a common methodology Production of recommended Measures of Merit for Production of recommended Measures of Merit for
evaluating trials resultsevaluating trials results Production of analytical methods for assessing trials Production of analytical methods for assessing trials
measurementsmeasurements Successful application of these principles in the PHARE Successful application of these principles in the PHARE
DemonstrationsDemonstrations Major contribution to the definitions in the “EATMS Major contribution to the definitions in the “EATMS
Validation Strategy Document” which is considered the Validation Strategy Document” which is considered the basis for ongoing validation activities within the European basis for ongoing validation activities within the European ATM R&DATM R&D
![Page 15: 1 PHARE Achievements Dr. H. Schröter PHARE Programme Manager EUROCONTROL version 1.1, 31.5.99.](https://reader036.fdocuments.us/reader036/viewer/2022082701/55154d735503465e608b6553/html5/thumbnails/15.jpg)
1515
PHARE Demonstration ProgrammePHARE Demonstration Programme
1993 1994 1995 1996 1997 1998 1999
Development& Integration
En-Route
TMA
ProjectDefinition
En-Route, TMA @ 3 sites
PD1
PD2
IOCPs, Development& Integration PD3
Development& Integration
ValidatedOptions for
EATMS
PD1+
PD2+
PD1++PC/TC
PD3CT
![Page 16: 1 PHARE Achievements Dr. H. Schröter PHARE Programme Manager EUROCONTROL version 1.1, 31.5.99.](https://reader036.fdocuments.us/reader036/viewer/2022082701/55154d735503465e608b6553/html5/thumbnails/16.jpg)
1616
PHARE Demonstration ResultsPHARE Demonstration Results
PD/1PD/1 & PD/2: Significant results. Potential for increase in traffic & PD/2: Significant results. Potential for increase in traffic throughput/reduction of controller workload throughput/reduction of controller workload
PD/3PD/3: Did not fully satisfy expectations. : Did not fully satisfy expectations.
In general, the PHARE Demonstrations confirmed :In general, the PHARE Demonstrations confirmed : feasibility of PHARE Conceptfeasibility of PHARE Concept assumption of high accuracy flying of 4D trajectoriesassumption of high accuracy flying of 4D trajectories possibility of de-conflicting of aircraft up to about 30 min. aheadpossibility of de-conflicting of aircraft up to about 30 min. ahead acceptability of automation toolsacceptability of automation tools benefits even in a mix of not fully 4D FMS equipped aircraftbenefits even in a mix of not fully 4D FMS equipped aircraft requirement for good performance data link for achieving full benefitrequirement for good performance data link for achieving full benefit
![Page 17: 1 PHARE Achievements Dr. H. Schröter PHARE Programme Manager EUROCONTROL version 1.1, 31.5.99.](https://reader036.fdocuments.us/reader036/viewer/2022082701/55154d735503465e608b6553/html5/thumbnails/17.jpg)
1717
Spin-offsSpin-offs
Spin-offs relate to the Spin-offs relate to the
progressive alignment of progressive alignment of understanding on a possible advanced understanding on a possible advanced ATM conceptATM concept
deliverables and products developeddeliverables and products developed
orientation and co-ordination of orientation and co-ordination of ATM Research and DevelopmentATM Research and Development
![Page 18: 1 PHARE Achievements Dr. H. Schröter PHARE Programme Manager EUROCONTROL version 1.1, 31.5.99.](https://reader036.fdocuments.us/reader036/viewer/2022082701/55154d735503465e608b6553/html5/thumbnails/18.jpg)
1818
Influence on ATM R&D and
Co-operation
Influence on ATM R&D and
Co-operation
European understanding and mind-setting European understanding and mind-setting PHARE-X AssociationPHARE-X Association Development of an R&D Strategy in support of Development of an R&D Strategy in support of
EATCHIPEATCHIP Set-up of European ATM R&D Programme Review Set-up of European ATM R&D Programme Review
Group, Prioritisation of R&D topics contributing to Group, Prioritisation of R&D topics contributing to ATM2000+ StrategyATM2000+ Strategy
Stimulation of co-operation between the European Stimulation of co-operation between the European Commission and EUROCONTROL Commission and EUROCONTROL
Co-operation with the US FAA and NAV CanadaCo-operation with the US FAA and NAV Canada
![Page 19: 1 PHARE Achievements Dr. H. Schröter PHARE Programme Manager EUROCONTROL version 1.1, 31.5.99.](https://reader036.fdocuments.us/reader036/viewer/2022082701/55154d735503465e608b6553/html5/thumbnails/19.jpg)
1919
Outlook
““CARE” (CARE” (CCo-operative o-operative AActions of ctions of RR&D in &D in EEUROCONTROL)UROCONTROL)
Co-operation has valueCo-operation has value Areas of improvement identified and to be applied in Areas of improvement identified and to be applied in
“CARE”“CARE” PHARE has found its successorPHARE has found its successor PHARE achievements will contribute to the success of PHARE achievements will contribute to the success of
“CARE”.“CARE”.
![Page 20: 1 PHARE Achievements Dr. H. Schröter PHARE Programme Manager EUROCONTROL version 1.1, 31.5.99.](https://reader036.fdocuments.us/reader036/viewer/2022082701/55154d735503465e608b6553/html5/thumbnails/20.jpg)
2020
PHARE AchievementsPHARE Achievements
Dr. H. SchröterDr. H. Schröter
PHARE Programme ManagerPHARE Programme Manager
EUROCONTROLEUROCONTROL
version 1.1 , 31.5.99version 1.1 , 31.5.99