08_ ESP Tech Ops _Install Overview

33
Downhole Unit Installation & Pulling Overview Educational Development Center SPH Chapter 20

description

08_ ESP Tech Ops _Install Overview

Transcript of 08_ ESP Tech Ops _Install Overview

Page 1: 08_ ESP Tech Ops _Install Overview

Downhole Unit Installation & Pulling Overview

Educational Development Center

SPH Chapter 20

Page 2: 08_ ESP Tech Ops _Install Overview

This presentation is meant to be an overview only

This presentation is not meant to replace manufacturer’s

approved procedures for installation and pulling of submersible

pumping systems

Slight deviations in the following procedure can and do occur

due to equipment &/or well site variations

Considerations

Page 3: 08_ ESP Tech Ops _Install Overview

HS&E

Proper Tooling

Pre-installation Checks

Installation

Commissioning

Pulling

Guidelines / Content

SPH Chapter 20

Page 4: 08_ ESP Tech Ops _Install Overview

Installation crews must comply with all BHI and operator HS&E directives

Correctly designed and certified tooling should be used to install & pull the system

Proper lifting procedures should be used so as not to damage the equipment or risk the safety of the installation crew

At any time if a condition exists that would compromise the health and safety of the crew, the job should be stopped and the condition addressed before continuing

Health & Safety

SPH 191

Page 5: 08_ ESP Tech Ops _Install Overview

All tools used should be of the proper design and in

good working order

Use properly designed and certified lifting clamps

and slings

Meters should be in good condition and regularly

calibrated to insure accuracy

Proper Tooling

SPH 191

Page 6: 08_ ESP Tech Ops _Install Overview

All tools used should be of

the proper design and in

good working order

Proper Tooling

SPH 191

Page 7: 08_ ESP Tech Ops _Install Overview

Use properly designed and certified lifting clamps and slings

Proper Tooling

Serial Number and

Certification Date

Appropriate

Equipment for

Clamp Design

SPH 191

Page 8: 08_ ESP Tech Ops _Install Overview

Meters should be in good

condition & regularly

calibrated to insure

accuracy

Proper Tooling

SPH 191

Page 9: 08_ ESP Tech Ops _Install Overview

Locate and verify equipment

Position equipment for lifting

Document serial numbers & specifications

Do pre-install equipment checks

Assess site risks

“Tool Box Talk”

Prepare work site

Pre-Installation

SPH 191

Page 10: 08_ ESP Tech Ops _Install Overview

Locate and verify equipment

Position equipment for lifting

Pre-Installation

SPH 191

Page 11: 08_ ESP Tech Ops _Install Overview

Document serial numbers & specifications

Pre-Installation

SPH 191

Page 12: 08_ ESP Tech Ops _Install Overview

Do pre-install equipment checks

Motor electrical checks

Cable electrical checks

Shaft extension checks

Pre-Installation

SPH 191

Page 13: 08_ ESP Tech Ops _Install Overview

Assess site risks

“Tool Box Talk”

Prepare work site

Pre-Installation

SPH 191

Page 14: 08_ ESP Tech Ops _Install Overview

Lift motor to servicing position

Fill motor with oil

Lower motor into well to connecting position

Lift seal servicing position and connect to motor

Fill seal with oil

Lower seal to assembly position

Lift pump / intake to servicing position and connect to seal

Lower pump to assembly position and connect tubing

Reposition unit, connect and band MLE

Installation Overview

SPH 193

Page 15: 08_ ESP Tech Ops _Install Overview

Lift motor to servicing position

Fill motor with oil

Lower motor into well to connecting position

Installation Overview

SPH 194

Page 16: 08_ ESP Tech Ops _Install Overview

Lift seal to servicing position and connect

to motor

Fill seal with oil

Lower seal to assembly position

Installation Overview

SPH 194

Page 17: 08_ ESP Tech Ops _Install Overview

Seal Filling

Page 18: 08_ ESP Tech Ops _Install Overview

r

Seal Filling

Page 19: 08_ ESP Tech Ops _Install Overview

r

Motor

Fill

Valve

Seal Filling

Page 20: 08_ ESP Tech Ops _Install Overview

r

Motor

Fill

Valve

Seal Filling

Page 21: 08_ ESP Tech Ops _Install Overview

r

Motor

Fill

Valve

Seal Filling

Page 22: 08_ ESP Tech Ops _Install Overview

r

Motor

Fill

Valve

Seal Filling

Page 23: 08_ ESP Tech Ops _Install Overview

r

Middle Guide Fill

Valve,

(Repeat Process for

Upper Guide also)

Seal Filling

Page 24: 08_ ESP Tech Ops _Install Overview

Lift pump / intake to servicing

position and connect to seal

Lower pump to assembly position

and connect tubing

Installation Overview

SPH 194

Page 25: 08_ ESP Tech Ops _Install Overview

Reposition unit, connect & band

MLE

Installation Overview

SPH 194

Page 26: 08_ ESP Tech Ops _Install Overview

Run rate should be steady, but allow time for cable banding / clamping

If a field cable splice is required, the process should be done per manufacturer’s specifications using proper components

Electrical readings should be taken periodically to insure insulation integrity

Care should be taken not to damage the cable in the slips

Running In Hole

SPH 195

Page 27: 08_ ESP Tech Ops _Install Overview

Run rate should be steady,

but allow time for cable

banding / clamping

Running In Hole

Cable / By-pass

Tubing Clamp

SPH 195

Page 28: 08_ ESP Tech Ops _Install Overview

If a field cable splice is required, the process should be done by certified personnel using the manufacturer’s approved procedures & components

Running In Hole

SPH 195

Page 29: 08_ ESP Tech Ops _Install Overview

Electrical readings should be taken periodically to insure

insulation integrity

Running In Hole

SPH 195

Page 30: 08_ ESP Tech Ops _Install Overview

Commissioning & Start-up

Final electrical connection of the downhole cable should be done at the junction box

Motor controller protection (voltage and current) should be set per manufacturer’s recommendation

High & low current settings may have to be disabled during startup but current should be monitored at all times

Under and over current protection should be reset after unit stabilizes

SPH 198

Page 31: 08_ ESP Tech Ops _Install Overview

A unit that has shut down and does not restart should be analyzed at the surface to determine if the problem can be linked to a downhole equipment failure or surface condition

If the downhole unit has failed, pulling of the unit should be done with the same care and attention that is given to the installation

Valuable information can be collected during the pulling operation that could be used when the equipment is analyzed after the pull

Pulling

SPH 198

Page 32: 08_ ESP Tech Ops _Install Overview

Data recorded on the pulling report should include …

– Electrical readings of cable & motor

– Any holes in tubing

– Condition of equipment outer surfaces and cable armor

– Debris in pump discharge or intake

– Pump, Seal, and Motor shaft rotation and play

– Condition of oil in seal section & motor

Pulling Report

SPH 198

Page 33: 08_ ESP Tech Ops _Install Overview

Summary

Any Questions?