04(Equipment Sizing)

download 04(Equipment Sizing)

of 26

Transcript of 04(Equipment Sizing)

  • 8/13/2019 04(Equipment Sizing)

    1/26

    Equipment Sizing

    Preliminary Equipment Sizing forCapital Cost Estimation

  • 8/13/2019 04(Equipment Sizing)

    2/26

    The Need for Equipment Sizing

    Before one can carry out capital costestimates on process equipment, the

    process engineer must carry out apreliminary sizing of the equipment.

    Although each process will have some

    unique pieces of equipment there aresome general categories applicable tomost designs

  • 8/13/2019 04(Equipment Sizing)

    3/26

    Equipment Types

    Towers

    Heat Exchangers

    InstrumentationTanks

    Vessels

    Pumps

    Compressors

    Fired Heaters

    Others

  • 8/13/2019 04(Equipment Sizing)

    4/26

    Towers

    Size (height anddiameter),Pressure,Temperature

    Number and Types of TraysHeight and Type of Packing

    Materials of Construction

    Unique Characteristics, SwagedColumns

  • 8/13/2019 04(Equipment Sizing)

    5/26

    Heat Exchangers

    Type;Vapour-Vapour,Vapour-Liquid,Condenser,Vapourizer,Evaporators

    Process Duty, Area, Temperature andPressure for all streams

    Type, Shell and Tube, Air-Cooler, Tube andTube etc. Cooling Towers

    Number of Shells and and Tube passes

    Materials of Construction

  • 8/13/2019 04(Equipment Sizing)

    6/26

    Instrumentation

    Pressure, Temperature, Flow and Level

    Analytical, Gc, IR etc

    Computer Control, Central orDistributed

  • 8/13/2019 04(Equipment Sizing)

    7/26

    Tanks

    Type of Tank and Service, StandardAPI, Floating roof, Blanketed etc.

    Materials of Construction

  • 8/13/2019 04(Equipment Sizing)

    8/26

    Vessels including Reactors

    Height/Length,Diameter,Orientation

    Pressure, Temperature

    Materials of Construction

  • 8/13/2019 04(Equipment Sizing)

    9/26

  • 8/13/2019 04(Equipment Sizing)

    10/26

    Compressors

    Actual Inlet FlowRate,Temperature,Pressure,Driver

    Type,Shaft PowerType of Compressor, Centrifugal, Singleor Multi-Stage,Reciprocator

    Materials of Construction

  • 8/13/2019 04(Equipment Sizing)

    11/26

    Fired Heaters

    Type,Tube Pressure,TubeTemperature,Duty,Fuel

    Materials of Construction

  • 8/13/2019 04(Equipment Sizing)

    12/26

    Other Equipment

    Filter,Blenders,Mixers, Kneaders

    Centrifugal Separators,Crystallizers

    Crushers and Grinders,Dust Collectors

    Electrostatic Precipitators

    Conveyors

    (This is by no means an exhaustive list)

  • 8/13/2019 04(Equipment Sizing)

    13/26

    Sizing Procedures - Towers

    Flow Sheet Simulators such as PRO/II and HYSYS have built in sizing

    routines for most type of mass transferdevices such as Fractionation Towersand Liquid-Liquid Extraction Towers.

    Unique devices such as Rotating DiskContactor would require a specificprocedure.

  • 8/13/2019 04(Equipment Sizing)

    14/26

    Towers Continued

    For Fractionations, the designer mustdetermine the number of theoretical

    stages required for a certain reflux andboil-up rate in order to achieve therequired separation. The appropriate

    type of Mass Transfer device must bechosen, I.e. Trayed Tower, PackedTower etc.

  • 8/13/2019 04(Equipment Sizing)

    15/26

    Towers Continued

    If a trayed tower is selected, the type oftrays must be specified, bubble-cap,

    seive or valve trays. For packed towersthe type of packing must be selected.

    There are many types of towers, Simple

    Absorbers, Rectified Absorbers,Reboiled Strippers, Steam Strippers etc.

  • 8/13/2019 04(Equipment Sizing)

    16/26

    Heat Exchangers

    The most common type of heatexchanger is the shell and tube. Shell

    and tube exchangers come in manyconfigurations, however as in the casewith fractionators most simulators suchas HYSYS can carry out a rigourous

    exchanger design. Condensers andThermosyphon Reboilers are tediouscalculations best done by a computer.

  • 8/13/2019 04(Equipment Sizing)

    17/26

  • 8/13/2019 04(Equipment Sizing)

    18/26

    Instrumentation

    For the purpose of preliminaryestimates instrumentation is usually

    costed simply as a factor of majorcapital.

    Instrumentation (Process Control) has

    become increasingly more sophisticatedand costly.

  • 8/13/2019 04(Equipment Sizing)

    19/26

    Instrumentation continued

    Although a factor approach may besuitable for a preliminary estimate, a

    better definition is required for adefinitive estimate. Some units have avery sophisticated plant-wide

    supervisory control which is based oncomplex computer technology.

  • 8/13/2019 04(Equipment Sizing)

    20/26

  • 8/13/2019 04(Equipment Sizing)

    21/26

    Vessels

    This category covers a wide range ofequipment from reactors to flash drum,

    overhead accumulators, flare drumsetc. Some of this equipment can bereadily sized by heuristic residence time

    considerations. Reactor design can bea simple residence time consideration,or a very complex design problem.

  • 8/13/2019 04(Equipment Sizing)

    22/26

    Vessels continued

    CSTRs are usually a relatively simplevessel with an agitator, although heat

    removal problems may complicate thedesign. Other reactors are considerablymore complex, for example catalytic

    fluid bed cracker reactors andregenerators, and trickle phasereactors.

  • 8/13/2019 04(Equipment Sizing)

    23/26

    Pumps

    The major concern with pump sizing isselecting the particular type of pump for

    the service. Although centrifugal pumpsare the most common, other types areoften required, reciprocating, gear

    pumps and so on. You will be providedwith a spread-sheet for the sizing ofpumps.

  • 8/13/2019 04(Equipment Sizing)

    24/26

    Compressors Expanders

    Flowsheet simulators such as HYSYS haveroutines that are to be used for sizingcompressors (and expanders).

    One common error that students in thedesign course make is specifying acompressor to move liquid. Compressors are

    used for vapour, pumps for liquids.Compressors can be destroyed by slugs ofliquid in the feed.

  • 8/13/2019 04(Equipment Sizing)

    25/26

    Fired Heaters

    This is a relatively complex sizingproblem, and fortunately we dont have

    to deal with it in the design exercise.Direct fired reboilers are notuncommon, particularly in the

    petroleum industry, however we haveavoided the need for such a unit in thedesign project

  • 8/13/2019 04(Equipment Sizing)

    26/26

    Others

    There are a great deal of unitoperations that fall into this category,

    all with their own unique sizingprocedures. Solids handling is a fairlybroad field, as is the equipment used

    for bioseparations.