* = Peak Load in Megawatts

16
Building the Energy Markets of Tomorrow . . . Today SM The Effects of Integrating Wind The Effects of Integrating Wind Power Power on the Reliability, Planning on the Reliability, Planning and and Operations of the Operations of the New York State Power System New York State Power System John M. Adams John M. Adams Director, System and Resource Planning Director, System and Resource Planning

description

The Effects of Integrating Wind Power on the Reliability, Planning and Operations of the New York State Power System John M. Adams Director, System and Resource Planning. Hydro Quebec 35,137 MW*. ISO - New England 25,348 MW*. IMO 25,414 MW*. 1050 MW. 1000 MW. 1500 MW. 1325 MW. - PowerPoint PPT Presentation

Transcript of * = Peak Load in Megawatts

Page 1: * = Peak Load in Megawatts

Building the Energy Markets of Tomorrow . . . TodaySM

The Effects of Integrating Wind Power The Effects of Integrating Wind Power on the Reliability, Planningon the Reliability, Planning and Operations and Operations

of theof theNew York State Power SystemNew York State Power System

John M. AdamsJohn M. AdamsDirector, System and Resource PlanningDirector, System and Resource Planning

Page 2: * = Peak Load in Megawatts

2

Page 3: * = Peak Load in Megawatts

3

* = Peak Load in Megawatts

IMO25,414 MW*

Hydro Quebec35,137 MW*

ISO - New England25,348 MW*

NYISO31,741 MW*

1325 MW1325 MW

1500 MW1500 MW

1500 MW1500 MW1000 MW1000 MW

1050 MW1050 MW

975 MW975 MW

2375 MW2375 MW

2625 MW2625 MW

PJM / PJM West131,330 MW*

Page 4: * = Peak Load in Megawatts

4

NY’s Renewable Portfolio Standard NY’s Renewable Portfolio Standard (RPS)(RPS) 25% of energy retailed in NY should come from eligible

renewable resources by 2013 Current level is about 19.5% RPS estimates that this need will be met by:

2,779 MW of NY-based Wind Farms 1,350 MW of Imports (including 250 MW of Wind in PJM) 294 MW of Biomass Co-Firing w/Coal 121 MW of Landfill Gas

Initial RECs awards made to 7 renewable facilities – 820,000 MWh contracted for 2006 – first-year payments estimated at roughly $18 million

Page 5: * = Peak Load in Megawatts

5

NY Energy by Fuel TypeNY Energy by Fuel Type

05000

1000015000200002500030000350004000045000

GW

h2004 2013 projected

Page 6: * = Peak Load in Megawatts

6

NY’s Wind Generation Interconnection QueueNY’s Wind Generation Interconnection Queue

Zone AB = 14, 1856T = 14, 1856

Zone CA = 1, 30B = 11, 959T = 12, 989

Zone DB = 7, 726T = 7, 726

Zone EA = 1, 11.5B = 12, 1429T = 13, 1441

Zone FB = 1, 100T = 1, 100

Zone KB = 1, 140T = 1, 140

Key:A = # Projects In-Service, #MWB = # Projects Proposed, #MWT = Total # Projects, #MW

Total NYA = 3, 48 MWB = 46, 5210 MWT = 49, 5258 MW

Zone BA = 1, 6T = 1, 6

Page 7: * = Peak Load in Megawatts

7

How Will RPS Impact System How Will RPS Impact System Reliability?Reliability?GE Energy Consulting engaged by NYSERDA

and NYISO to evaluate reliability needs of RPS

Looked at 3300 MW of wind resources connected to NY system by 2008

Phase II study results released on Feb. 10, 2005 – available at www.nyserda.com/rps

Page 8: * = Peak Load in Megawatts

Building the Energy Markets of Tomorrow . . . TodaySM

Page 9: * = Peak Load in Megawatts

9

Study ObjectiveStudy Objective

To produce empirical information that will assist the NYISO in evaluating the reliability implications of the large scale integration of wind generation

Phase 1: Preliminary Overall Reliability Analysis

Phase 2: System Performance Evaluation

Page 10: * = Peak Load in Megawatts

10

Time Scales for Time Scales for System System PlanningPlanningand Operation and Operation

ProcessesProcesses Unit Commitment

andDay- Ahead Scheduling

Load Following(5 Minute Dispatch)

Frequency and Tie- Line Regulation

(AGC)

Day- ahead and Multi-Day

Forecasting

Fas

ter

(sec

on

ds)

Tim

e F

ram

e

Slo

wer

(Y

ears

)

Planning and Operation Process

TechnologyIssues

Hour- Ahead Forecasting

and Plant Active Power Maneuvering and

Management

Resource andCapacity Planning

(Reliability)

Unit Dispatch

0

100

200

300

400

500

600

700

0 2000 4000 6000 8000

Hour

MW

Real- Time and Autonomous Protection and Control Functions

(AGC, LVRT, PSS, Governor, V-Reg , etc.)

Capacity Valuation(UCAP, ICAP)

andLong- Term Load

Growth Forecasting

2001 Average Load vs Average Wind

0

5,000

10,000

15,000

20,000

25,000

30,000

1 6 11 16 21

Hour

NY

ISO

Lo

ad (

MW

)

0

200

400

600

800

1,000

1,200

1,400

1,600

Win

d O

utp

ut

(MW

)

July load August load September load

July wind August wind September wind

0

500

1000

1500

2000

2500

3000

1 61 121

Minutes

MW

September Morning August Morning May Evening October Evening April Afternoon

1 Year

1 Day

3 Hours

10 Minutes

Operation and Operation and Planning Data Planning Data Spanning All Spanning All These Time These Time Frames Was Frames Was Compiled for Compiled for This StudyThis Study

Page 11: * = Peak Load in Megawatts

11

Study Findings – Interconnection Study Findings – Interconnection Req.Req. If state of the art wind technology is utilized, the

NYSBPS can reliably interconnect wind generation on a large scale with only minor adjustments to its existing planning, operation, and reliability practices.

State of the art wind generators would have the following features/capabilities: Low-Voltage Ride Through Leading/Lagging Power Factor Range SCADA

Ratings of wind farms would need to be within the capacity of local transmission facilities and subject to congestion management: Power Curtailment Capability

Page 12: * = Peak Load in Megawatts

12

Study Findings – Planning and Study Findings – Planning and OperationsOperations

Time Scale Technical

Issue Without Wind

Generation With Wind Generation

Comments

Years UCAP of Wind Generation

UCAP land-based 10%

UCAP offshore 36% (one site in

Long Island)

UCAP is site-specific

Simple calculation method proposed

Days

Day-Ahead Forecasting and Unit Commitment

Forecasting error:

700-800 MW

Forecasting error:

850-950 MW

Incremental increase can be accommodated by existing processes and resources in NY State

Even without forecasts, wind energy displaces conventional generation, reduces system operating costs, and reduces emissions.

Accurate wind forecasts can improve results by another 30%

Hourly Variability = 858 MW = 910 MW

Incremental increase can be accommodated by existing processes and resources in NY State

Hours Largest Hourly Load Rise

2575 MW 2756 MW Incremental increase can be accommodated by existing processes and resources in NY State

Minutes Load Following

(5-min Variability)

= 54.4 MW = 56.2 MW Incremental increase can be accommodated by existing

processes and resources in NY State

Regulation 225 to 275 MW

36 MW increase required to

maintain same performance

NYISO presently exceeds NERC criteria

May still meet minimum NERC criteria with existing regulating capability

Spinning Reserve

1200 MW 1200 MW No change to contingency that sets spinning reserve requirement Seconds

Stability 8% post-fault voltage dip

(typical)

5% post-fault voltage dip

(typical)

State-of-the-art wind generators do not participate in power swings, and improve post-fault response of the interconnected power grid.

Page 13: * = Peak Load in Megawatts

13

Study Findings – Capacity ValueStudy Findings – Capacity Value

Based on rigorous LOLP calculations using 2001 - 2003 load and wind profiles: Inland Wind Sites:

Capacity factors ~ 30%Effective capacity, UCAP ~ 10%

Offshore Wind Site:Capacity factors ~ 40%Effective capacity, UCAP ~ 39

Developed approximate calculation method:UCAP ~ On-Peak Capacity Factor for 1:00-5:00pm,

June-August

Page 14: * = Peak Load in Megawatts

14

2001 Average Load Vs Average Wind2001 Average Load Vs Average Wind

0

5,000

10,000

15,000

20,000

25,000

30,000

1 6 11 16 21

Hour of Day

NY

ISO

Lo

ad

(M

W)

0

200

400

600

800

1,000

1,200

1,400

1,600

Win

d O

utp

ut

(MW

)

July load August load September load

July w ind August wind September w ind

August

July

September

Page 15: * = Peak Load in Megawatts

15

One week in July 2002One week in July 2002

0

5000

10000

15000

20000

25000

30000

35000

1 25 49 73 97 121 145

Hour of Week

NY

ISO

Lo

ad (

MW

)

0

500

1000

1500

2000

2500

3000

Win

d O

utp

ut

(MW

)

NY Loads

WIND

Page 16: * = Peak Load in Megawatts

16

Market-Related Wind Issues – Schedule Market-Related Wind Issues – Schedule for Market Participant Discussionsfor Market Participant DiscussionsThe NYISO is developing straw proposals

addressing a number of market-related issues:

Centralized wind forecasting system

Interim market rules clarification of 500 MW limit

End-state market rules

NYISO expects to discuss these proposals within the Market Structures Working Group in the July/August timeframe