· PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or...

276

Transcript of · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or...

Page 1: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final
Page 2: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final
Page 3: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final
Page 4: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

DIVISION 20 – FEDERAL AVIATION ADMINISTRATION SPECIFICATIONS

Item L-100 General Provisions and Requirements for Electrical Work

Item L-104 General Electrical Safety Requirements and Temporary Airfield Lighting

Item L-105 Alterations, Removal and Demolition

Item L-108 Power Cable for Airports

Item L-110 Airport Electrical Duct Banks and Conduits

Item L-111 Airfield Lighting System Testing

Item L-121 Obstruction Lights

Item L-131 Demonstrations and Tests

Page 5: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

METROPOLITAN WASHINGTON AIRPORTS AUTHORITY RONALD REAGAN WASHINGTON NATIONAL AIRPORT

RUNWAY 1-19 SAFETY AREA IMRPOVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 CONSTRUCTION PACKAGE

Airport Design Consultants, Inc Responsibility for Specifications Include:

01 71 13 Mobilization/Demobilization

DIVISION 01 – GENERAL REQUIREMENTS

Item P-152 Excavation and Embankment

DIVISION 20 – FEDERAL AVIATION ADMINISTRATION SPECIFICATIONS

Item P-610 Structural Portland Cement Concrete

312514 Stormwater Pollution Prevention

DIVISION 31 – EARTHWORK

323113.80 Blast Protection Fence

DIVISION 32 – EXTERIOR IMPROVEMENTS

sjohnson
Stamp
Page 6: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final
Page 7: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

CONTENTS 000110 - 1

METROPOLITAN WASHINGTON AIRPORTS AUTHORITY RONALD REAGAN WASHINGTON NATIONAL AIRPORT

RUNWAY 1-19 SAFETY AREA IMRPOVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 CONSTRUCTION PACKAGE

Table of Contents

DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS

00 73 00 Supplementary Conditions

DIVISION 01 – GENERAL REQUIREMENTS

01 10 00 Summary

01 22 00 Unit Prices

01 22 10 Measurement and Payment

01 29 00 Application for Payment

01 31 00 Project Management and Coordination

01 32 00 Construction Progress Documentation

01 32 33 Photographic Documentation

01 33 00 Submittals

01 40 00 Quality Requirements

01 42 00 References

01 50 00 Temporary Facilities and Controls

01 60 00 Product Requirements

01 71 13 Mobilization/Demobilization

01 73 00 Execution

01 77 00 Project Closeout

01 78 39 Project Record Documents

Page 8: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

CONTENTS 000110 - 2

DIVISION 20 – FEDERAL AVIATION ADMINISTRATION SPECIFICATIONS

Item P-152 Excavation and Embankment

Item P-610 Structural Portland Cement Concrete

Item L-100 General Provisions and Requirements for Electrical Work

Item L-104 General Electrical Safety Requirements and Temporary Airfield Lighting

Item L-105 Alterations, Removal and Demolition

Item L-108 Power Cable for Airports

Item L-110 Airport Electrical Duct Banks and Conduits

Item L-111 Airfield Lighting System Testing

Item L-121 Obstruction Lights

Item L-131 Demonstrations and Tests

DIVISION 31 – EARTHWORK

312514 Stormwater Pollution Prevention

DIVISION 32 – EXTERIOR IMPROVEMENTS

323113.80 Blast Protection Fence

Page 9: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON EXPANSION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

SUPPLEMENTARY CONDITIONS 007300 - 1

SECTION 007300 — SUPPLEMENTARY CONDITIONS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings, Contract Provisions, Special Provisions, and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. The articles and paragraphs of this Section represent supplements or additions to the Contract Provisions or the Special Provisions.

1.3 WORK UNDER OTHER CONTRACTS

A. During the period of this Project, the Authority anticipates that other construction contracts may be underway at or near the site of work of this Contract. A list of adjacent construction activities follows:

1. Runway 1-19 Safety Area Improvements and Runway 1 Hold Apron Modification – General Construction Package.

2. Runway 1-19 Safety Area Improvements and Runway 1 Hold Apron Modification – ALSF-2 Construction Package.

3. Runway 1-19 Overlay and Taxiways Rehabilitation Project. 4. FAA Pier Rehabilitation Project.

1.4 PERMITTING

A. Comply with all requirements set forth in the Authority's “Building Codes Manual”. This manual describes Building Codes organization, Building Code inspection process, Certificate of Occupancy requirements, and information regarding elevators, escalators, and moving walks. The Authority will file for and provide the construction permit.

1.5 MAINTENANCE OF PEDESTRIAN AND VEHICULAR TRAFFIC

A. Maintain adequate pedestrian and vehicular traffic flow and safety along the service roads, sidewalks, parking lots and other roadways on Airport property. In addition, this requirement applies to crossroads, approaches, and entrances affected by or made necessary by the Work. Coordinate activities throughout the project in a manner that allows emergency access, without delays to emergency response vehicles, to all areas of the Project that are occupied by employees.

B. Comply with requirements indicated in the Traffic Maintenance Plan provided in the contract documents. Obtain COTR's written approval prior to implementing any deviations from the provided plan.

Page 10: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON EXPANSION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

SUPPLEMENTARY CONDITIONS 007300 - 2

C. Provide and maintain temporary signage, "Jersey barriers," and such other traffic control devices or personnel as required complying with approved Traffic Maintenance Plan.

D. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final acceptance of the project. The maintenance shall constitute continuous and effective work prosecuted day by day with adequate equipment and forces to the end of project to ensure that roadways and structures are maintained in satisfactory condition at all times, including barricades and warning signs as necessary for performance of the work.

E. Keep the portions of the project being used by public, pedestrian, aircraft, and vehicular traffic, whether it is through or local traffic, in such condition that traffic will be adequately accommodated. Remove snow and control all ice within the project boundaries. Removal of snow and ice for the benefit of the traveling public will be performed by the Authority. Bear all cost of maintenance work during construction and before the project receives a Certificate of Occupancy for constructing and maintaining approaches, crossings, intersections and other features as may be necessary.

F. Keep the portions of the road and aircraft pavement surfaces being used by the public free from irregularities, obstructions, mud, dirt, snow, ice, and any characteristic that might present a hazard or annoyance to traffic in such condition that traffic will be adequately accommodated. Maintain a vacuum/sweeper and flusher truck at the site at all times to clean roadway and aircraft surfaces affected by construction traffic at the request of Airport Operations or the COTR.

1.6 AIRFIELD AND TERMINAL BUILDING OPERATIONAL REQUIREMENTS

A. The Work, or a portion thereof, will be performed in proximity to the Air Operations Area (AOA), including, active runways, taxiways, and aprons. Normal airport operations will continue adjacent to the Work during all phases of the Project. These activities include:

1. Aircraft movement on runways, taxiways, aprons; aircraft landing and takeoff operations. 2. Aircraft parking, refueling and other aircraft servicing. 3. Apron maintenance, snow removal and ice control.

B. Phase construction activities as necessary to accommodate all airport operations without disruption. Adhere to all current Airport Orders and Instructions (O & Is), Airport Bulletins, and Airport Advisories. The Authority will provide relevant Orders and Instructions to Offerors in the Solicitation Package. Bulletins and Advisories will be provided to the offeror by the Authority as they are issued.

1.7 ENVIRONMENTAL PROTECTION

A. Comply with all Federal, state and local laws and regulations controlling pollution of the environment. Take necessary precautions to prevent pollution of streams, rivers, lakes, ponds, and reservoirs with fuels, oils, bitumens, chemicals, or other harmful materials and to prevent pollution of the atmosphere from particulate and gaseous matter.

Page 11: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON EXPANSION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

SUPPLEMENTARY CONDITIONS 007300 - 3

B. Notify COTR immediately in the event that abnormalities, discolorations, odors, oil, or other signs of potential contamination by hazardous materials are encountered during excavation or other construction activities. Follow with written notice within 24 hours, indicating date, time, and location of potential contaminants encountered. The COTR will provide further direction to Contractor regarding disposition of materials encountered.

C. All painted surfaces are assumed to contain lead-based paint. The Contractor shall maintain the necessary health and safety requirements for all personnel in accordance with OSHA regulations to work in these conditions. The removal and disposal of lead-based paint is part of this contract.

D. Aircraft deicing fluids will be encountered in the water (including utility manholes) and in the soils. Concentrations of aircraft deicing fluids in water and soils will range from non-detect to saturation. Aircraft deicing fluids are propylene based Type I and Type IV fluids. The fluids emit an unpleasant odor when the breakdown (biodegradation) is occurring. Follow OSHA requirements while working in aircraft deicing impacted areas. Coordinate with the COTR for obtaining Material Safety Data Sheet (MSDS) for aircraft deicing fluids.

E. Contaminated soil and water will be encountered during this construction project. Contaminants may include low level metals, semi-volatiles, volatiles, PCBs, and dioxins/furans. A copy of the Authority’s Health and Safety Plan with all of the chemical constituents identified at the site will be provided to the contractor for reference. All Contractors performing work on this project shall be OSHA 40-hour Hazardous Waste Operations and Emergency Response (HAZWOPER) trained in accordance with 29 CFR 1910.120. The Contractor shall comply with all the health and safety requirements in accordance with the OSHA HAZWOPER Standards, including but not limited to training and the preparation of a site specific Health and Safety Plan (HASP).

1.8 ARCHAEOLOGICAL AND HISTORICAL FINDINGS

A. Notify immediately, through the COTR, the PMC Archaeology/Historic Preservation Coordinator if subsurface structural features, concentrations of artifacts, rubble, bone/shell, or burnt material are uncovered or otherwise discovered. Prompt reporting will avoid potentially severe problems resulting from the destruction of significant resources and may limit the impact on construction operations and schedules.

1.9 DAMAGES AND PRE-EXISTING CONDITIONS

A. Be responsible for all damages caused by Contractor’s construction activities. Provide all labor, materials, etc. to return any damaged areas, systems or equipment to their original condition at no additional cost to the Authority.

B. Perform a survey of pre-existing conditions in the vicinity of Contractor’s construction activities, utilizing photographs and other means as necessary to document existing damage or conditions. Submit two copies of this survey to the Contracting Officer within 21 calendar days after Notice-to-Proceed. This survey will assist in resolving any damage claims against the Contractor during and after construction.

Page 12: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON EXPANSION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

SUPPLEMENTARY CONDITIONS 007300 - 4

C. Preserve all roadways, pedestrian and directional signage. Deliver all signs removed and not required for reinstallation to the Authority as directed by the COTR.

D. Replace or repair lost or damaged signs at no cost to the Authority.

1.10 SECURITY DURING CONSTRUCTION

A. Maintain the integrity of the Airport Security fence. Maintain the integrity of doors and walls between public areas and Air Operations Area (AOA) at all times. Comply with Title 49 Code of Federal Regulations, Parts 1500, 1540, 1542 and 1544.

B. Possession of and display of a proper and current Airport Identification Badge, issued by Airport Operations is required for all Contractor personnel passing into the AOA. Refer to "Airport Orders and Instructions" attached as part of the Contract for specific requirements. Security requirements have increased significantly at Washington Dulles International Airport and Ronald Reagan Washington National Airport. Contractor can expect possible short delays clearing construction vehicles into the AOA. Offerors shall become intimately familiar with all TSA and Authority security requirements. No increase in contract price will be provided to the Contractor should the contractor not be aware of any security procedure in place at time of submitting their offer that leads to increased time and inconvenience to accomplish the work.

C. Pay all fines levied by the Transportation Security Administration for penalties resulting from security infractions perpetrated by or caused by Contractor’s personnel or work forces of Contractor’s subcontractors or suppliers.

D. Establish and maintain the security of Contractor’s staging areas, equipment and materials.

E. Provide escort for delivery vehicles transporting materials and supplies to or from the Contractor's staging or work areas into the AOA, in accordance with requirements stated in "Airport Orders and Instructions" attached as part of the Contract.

F. Do not park within 300 feet of a terminal building unless specifically authorized by Airport Operations.

G. All workers in the sterile areas, which are defined as areas accessible to ticketed passengers only, may utilize tools in their work provided that:

1. Tools are essential and necessary to the Work. 2. Keep tools controlled at all times. 3. Do not leave tools unattended. 4. Store tools in locked boxes.

H. No knives will be permitted in the sterile areas.

I. No firearms or weapons of any type are allowed on the airport.

J. No cartridge style nail guns, nor any tools that use a cartridge or any explosive charge, are allowed without prior written notification of COTR. Obtain written approval from the COTR before bringing such tools on the project.

Page 13: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON EXPANSION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

SUPPLEMENTARY CONDITIONS 007300 - 5

K. Conform to all Orders and Instructions pertaining to vehicle inspection.

1.11 MATERIAL HAULING

A. Access and egress to and from the Airport for hauling operations shall be through the entrances indicated. Conduct hauling operations as indicated on the drawings.

B. The designated haul routes for hauling operations will not require vehicles crossing and/or utilizing existing taxi lanes or taxiways. Under no conditions shall the Contractor plan use of taxiways and taxi lanes for hauling equipment. Haul routes for this project are as indicated on the drawings.

C. Schedule, phase, and sequence work operations to minimize the number and duration of taxiway closures. Submit a detailed Work Plan for Contractor’s entire operations to the COTR for approval prior to commencing work. Obtain written approval from the COTR of the Work Plan. Identify clearly on Work Plan each operation requiring coordination with Airport Operations.

D. Notify the COTR at least 72 hours in advance of his requirement for scheduled taxiway, taxi lane or roadway closures. Obtain the written approval of the Authority prior to closing or crossing a taxiway, taxi lane or roadway.

E. Bear all costs associated with establishing, maintaining, signing, lighting and marking haul routes and taxiway crossings. These costs are considered incidental to the pay items of this Contract.

F. Use load covers on all dump trucks. Load dump trucks so that no spillage occurs during transit on the State, municipal, or Airport roadways, taxiways, and aprons. Clean wheels of trucks leaving the Project construction site of all soil and rocks. Provide a truck washing rack on the Project site to minimize the tracking of soil onto paved surfaces.

G. Be responsible for the cost of the immediate cleaning of earth tracking and spills on paved surfaces resulting from the Contractor's operations. Because of the potential for extreme damage to aircraft engines due to the ingestion of foreign objects, maintain on the project mechanical sweeper/vacuum (wet/dry) equipment with nylon brushes complete with operators. Maintain a water truck on site at all times in order to effectively control dust rising from construction activities.

H. Provide sweeper/vacuum equipment with a usable hopper capacity of 6 cubic yards and with a regenerative air capacity of 15,000 CFM. Provide equipment with gutter brooms of poly brush material so as not to damage airfield pavement markings; a dust control system that includes an external spray system with front mounted spray bar, nozzles located at each gutter broom; and an internal spray system with nozzles in the internal air stream. Maintain the equipment in good working order throughout the project and replace the brooms and or spray systems, as necessary, to ensure proper sweeping and vacuuming of paved surfaces.

Page 14: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON EXPANSION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

SUPPLEMENTARY CONDITIONS 007300 - 6

1.12 PORTABLE LIGHTING

A. Portable lighting: If used for Contractor operations, aim and shield portable lighting at all times to eliminate glare that could impair runway, taxiway, apron, ground operations, and Airport Traffic Control Tower operations. Equip portable lighting with reflectors and glare shields to prevent spillover of light into operational areas.

1.13 RADIO COMMUNICATIONS

A. Provide two-way radio communication between certain of the Contractor’s personnel on the job site. Provide radios with a minimum of 5 watts transmitting power. Select the frequency utilized for these transmissions. Submit proposed frequencies to COTR for approval in writing by the COTR. Frequencies shall not conflict with or overlay any of the Airports radio frequencies.

B. Provide, at a minimum, the following with radio equipment: The Project Superintendent, Foreman of all work groups physically separated from the general vicinity of the Project Superintendent, gate guards, and others who may be working in a separate and remote area. Provide two additional radios with the same frequencies to PMC for use by the COTR and the Lead Inspector.

C. Provide two-way radios capable of operating on both the "Ground" and "Ramp" frequencies for work adjacent to or affecting taxiways. Such radios shall be either a handheld programmable type capable of operating off of vehicle power and antenna or a vehicle-mounted type, which operates solely off of the vehicle’s power, and antenna. Provide radios that provide a minimum of 3 watts transmitting power. Provide radios of sufficient power to communicate with the appropriate controller.

D. Cellular telephones are an acceptable alternative at Ronald Reagan Washington National Airport. For information purposes the Authority currently uses the Nextel system.

1.14 SPECIAL AUTHORITY CONSULTANT

A. The Contractor is hereby advised of the involvement of Parsons Management Consultants (PMC) as Program Management Support Services Consultant to the Authority for the capital construction programs at Ronald Reagan Washington National Airport and Washington Dulles International Airport. PMC will have a continuing role in this project by assisting the Authority in specialized areas.

1. PMC will provide administrative support during design, solicitation, and construction. 2. PMC will coordinate Contractor requests for technical information and receive, review

and manage all Contractor submittals. 3. PMC has reviewed technical submittals during design, including drawings, specifications,

cost estimates, construction phasing plans, and technical reports. 4. PMC will be responsible for review of technical submittals during construction, including

selected shop drawings, certifications, test reports, calculations and samples. 5. PMC will conduct field inspections of the Work in progress and inspect for Substantial

Completion and Final Acceptance. PMC inspection does not relieve Contractor of

Page 15: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON EXPANSION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

SUPPLEMENTARY CONDITIONS 007300 - 7

responsibilities of performing Contract required inspections as required by contract documents.

B. All other contract management is the sole responsibility of the Authority.

1.15 SAFETY

A. Comply with all requirements set forth in the most current edition of the Authority Construction Safety Manual”. Offerors are provided with the most recent addition when obtaining contract documents prior to proposal. Requirements included in this Section are in addition to the Authority’s Construction Safety Manual. Comply with all local, State and Federal requirements. Where conflicts or discrepancies exist between requirements, the more stringent requirement shall govern. For additional information see Division 01 Section “Quality Requirements”.

B. Contractor Safety Organization:

1. Safety Engineer.

a. Duties: Outlined in The Authority Construction Safety Manual. b. Qualifications: Outlined in The Authority Construction Safety Manual .

C. Submit the résumés of individuals proposed to serve in the role of Contractor’s Safety Engineer to the COTR for approval in writing. In addition to indicating the qualifications in the Authority Construction Safety Manual résumés shall include but not be limited to such items as: work experience, education, safety and health training completed, memberships in professional associations, professional certifications, professional registrations and professional references confirming the qualifications and personal references of contacts for verification shall also be required.

D. Provide safe and healthful working conditions on each operation at all times during execution the work of this Contract. Conduct the various operations connected with the Work so that they will not be injurious to safety or health. Comply with all provisions, regulations and recommendations issued pursuant to the Occupational Safety and Health Act of 1970 and the Construction Safety Act of 1969, as well as amendments to these laws. Comply with laws, rules and regulations of other authorities having jurisdiction, with regard to all matters relating to the safety and health of workers and the general public. Compliance with government requirements is mandated by law and considered only a minimum level of safety performance. Perform all work in accordance with best safe work practices recognized by the construction industry. Stop work whenever a work procedure or a condition at a work site is deemed unsafe by the either of the following individuals: COTR, Program Safety Manager (PSM), the Contractor’s Project Manager, the Contractor’s Foreman, or the Contractor’s Safety Engineer(s).

E. Provide the services of at least one full-time on-site Contractor Safety Engineer per construction work shift with no other duties assigned.

F. Provide a full-time on-site Contractor Safety Engineer for the duration of this Contract with no other duties assigned. The Safety Engineer shall be responsible for all safety and health requirements as included herein and as required by the Authority’s Construction Safety Manual.

Page 16: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON EXPANSION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

SUPPLEMENTARY CONDITIONS 007300 - 8

G. The Contractor shall submit the resumes of all proposed safety and health professionals who shall serve in the role of contractor’s Safety Engineer(s) to the COTR for approval. The resumes shall include, but not be limited to such items as: work experience, education, safety and health training completed, memberships in professional associations, professional certifications, professional registrations, and professional references confirming the qualifications shall also be required. Documentation confirming the qualifications and personal references of contacts for verification shall also be required.

H. Comply with all requirements set forth in the Authority's "Construction Safety Manual." Provide during the Work the services of Safety Manager(s)/Safety Engineer(s) as outlined in the Authority’s “Construction Safety Manual” and in Division 01 Section “Quality Requirements”. The Safety Engineer shall undertake the duties and responsibilities as stated in the Authority's "Construction Safety Manual".

I. Prior to start of construction activities in the Air Operations Area (AOA), the Contractor's Safety Engineer(s) shall tour the AOA with the Authority Safety Program Manager.

J. Flagmen Training: The Authority will sponsor Flagman training sessions. Contractor's personnel who will be assigned flagmen duties on the Airport for this project shall attend training sessions.

K. Fire Safety: Conform to the following requirements:

1. Obtain a permit to perform any welding, cutting, or hot work from the Office of the Authority Fire Marshal.

2. Ensure adequate access to all construction areas for emergency response. 3. Obtain a permit from the Office of the Authority Fire Marshal to store, handle, or use any

hazardous material, including but not limited to fuels for equipment. Complete an application prior to issuance.

4. Remove combustible debris from the site daily. 5. Provide at least seven (7) days notice for any request for inspections, tests, permits, etc.,

required of personnel from the Office of the Authority Fire Marshal. 6. Provide to the Office of the Authority Fire Marshal a list of emergency contact numbers

for the COTR and the Contractor prior to the commencement of Work.

L. Submit Site-Specific Safety and Health Plans to COTR within 15 calendar days of Notice to Proceed and prior to the start of any construction activities. Prepare this plan using the Authority’s Guidelines as defined in the Authority’s “Construction Safety Manual” and as supplemented by these specifications for each and every work zone as shown on the drawings or as anticipated by the Contractor. COTR must approve the Site-Specific Safety Plan prior to the start of any work.

M. Be responsible for the safe operation of all job site motor vehicles. Provide a “spotter” or flagman for all backing operations of construction vehicles with restricted rear vision.

N. All motorized equipment and vehicles working on or entering MWAA construction project work areas shall be equipped with functional audible backup alarms.

O. Crane Operators. On Airports Authority projects, Crane Operators shall be certified to operate the equipment by an approved independent certifying agency.

Page 17: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON EXPANSION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

SUPPLEMENTARY CONDITIONS 007300 - 9

P. For all airside projects attach a Safety Plan to the Safety Program. Include in the Safety Plan, to the extent applicable, provisions for the following:

1. Scope of work performed by Contractor, including proposed duration of work. 2. Possible safety problems (job hazard analysis program). 3. Work control measures. 4. Limitations on equipment height. 5. Location of airport operational areas. 6. Location of and access to stockpiled construction materials and equipment. 7. Inspection requirements. 8. Trenches and excavations, and cover requirements. 9. Threshold marking and lighting. 10. Closed runway marking. 11. Vehicle operation and pedestrian access in airport movement areas. 12. Construction site access and haul roads, includes maintenance of and keeping open ARFF

access routes. 13. Limitations on construction. 14. Radio communications. 15. Foreign object debris (FOD) control provisions. 16. Hazardous materials (HAZMAT) management. 17. Wildlife abatement. 18. NOTAM issuance. 19. Vehicle identification. 20. Vehicle parking. 21. Use of temporary visual aids. 22. Obstacle-free zones (OFZ). 23. Approach clearance to runways. 24. Runway and taxiway safety areas. 25. Procedures and equipment, such as barricades (identify type) for closing portions of the

movement area. 26. Required compliance of contractor personnel. 27. Procedures for notification of aircraft rescue firefighting (ARFF) if deactivating water

lines or fire hydrants, or if emergency access routes are rerouted or blocked. 28. Emergency notification for fire, medical, and police response. 29. Coordination of plan with an FAA airport certification safety inspector.

1.16 HEIGHT LIMITATION

A. For all demolition and construction within the Airport, limit the height of Contractor's equipment as indicated on the Drawings.

B. Prior to beginning any work coordinate with the COTR the height of all cranes, boom trucks, scaffolds or similar vehicles of construction. Properly mark all construction equipment with safety flags and warning lights in accordance with current FAA and Airport Operations requirements. Submit FAA Form 7460, provided by COTR, for all variations on approved crane heights.

Page 18: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON EXPANSION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

SUPPLEMENTARY CONDITIONS 007300 - 10

1.17 NOISE CONTROL

A. The Authority recognizes and can tolerate a normal level of noise created by a majority of construction activity. However, in the interest of the Authority's neighbors, the maximum acceptable noise level between the hours of 5:00 pm and 7:00 am the following morning is limited to 55 decibels. During daytime hours of 7:00 am through 5:00 pm, the maximum acceptable noise level for sustained or repetitive noises is 72 decibels. Measure the noise level using an "A" scale at a point 4'-0" above ground at property line nearest noise source.

B. Secure advance written approval from the COTR prior to scheduling any activity that is anticipated to produce a sustained or repetitive noise level higher than the decibel limits indicated above.

C. In and around terminal facilities and buildings whose normal occupancy is from 7 a.m. to 7 p.m., perform work that causes noise that is disruptive to the airport’s tenants or the traveling public between the hours of 11:00 pm and 5:00 am. Measure noise for this situation using an “A” scale at a point 4’-0” above ground at the closest point to airport tenants or the traveling public.

1.18 EXAMINATION OF PLANS, SPECIFICATIONS AND SITE OF WORK

A. The offeror is expected to examine carefully the site of the proposed work, the proposal, plans, specifications, solicitation provisions, contract provisions, special provisions and contract forms before submitting a proposal. The submission of a proposal will be considered conclusive evidence that the offeror has made such examination and is satisfied as to the conditions to be encountered in performing the work as to the requirements of the Contract.

1.19 AIRPORT SECURITY/VEHICLE INSPECTION PROCEDURE

A. The number of vehicular access points into secure areas at Ronald Reagan Washington National Airport has been reduced to an operational minimum. Two gates are available for vehicular traffic. Gate A and A5.

B. Contractor shall coordinate the use of Gate A5 with the COTR 72 hours in advance. The Contractor shall provide the COTR the work days and hours in which Gate A5 will be needed for their operations. The COTR will coordinate with the Airport to provide a security guard for Gate A5 during the Contractor’s operations.

C. The following procedures will be utilized for all escorted vehicles and AOA approved vehicles with non-badged passengers seeking entry to the AOA:

1. All vehicles are searched. 2. Coordinate all vehicle deliveries with the COTR in advance. Provide the vehicle license

plate number and expected delivery time for all vehicle deliveries. Contractor may compile the expected daily delivery schedule on one sheet for submission to the COTR.

3. The vehicle operator shall have in his or her possession a commercial manifest, which identifies the contents of the vehicle and/or trailer.

4. An escort from the company for whom the shipment is intended shall respond to the vehicle access gate and remain with the vehicle until the vehicle exits the secured area.

Page 19: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON EXPANSION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

SUPPLEMENTARY CONDITIONS 007300 - 11

5. A vehicle search will be conducted and once cleared; vehicles will be permitted escorted access to their delivery point.

6. Contractors should expect minor delays up at Gate A as a result of these security provisions.

7. Priority consideration may be offered to concrete trucks with resulting delays estimated to be 20 minutes. To receive priority consideration, schedule concrete deliveries with Airport Operations and COTR at time of batching.

D. Prior approval from the Manager of Airport Operations or his/her designated representative is required for any exceptions to the above procedures.

1.20 AIRPORT SAFETY AND TRAFFIC CONTROL PROCEDURE

A. Dump trucks will be allowed on the AOA only under official escort. Security Gate guards will ensure only escort vehicles are opening gates to allow trucks on/off the AOA for while escorting. Also, any construction vehicles that are staging or moving equipment on the AOA during non working construction hours must be pre-coordinated with Airport Operations.

B. One or two dump trucks or oversized loads will require one lead escort vehicles at all times. If three or more dump trucks are to be escorted, both a lead escort and follow-on vehicle will be required.

C. Contractor shall conduct nightly formal safety briefs as part of nightly kick-off meetings with work force drivers. At the nightly safety, coordination meeting, lead PMC Inspector will verbally discuss haul routes, off limit areas and escort procedures with all escorts.

D. Prior to any construction activity on the AOA a nightly face-to-face Operations and construction crew meeting on-site, PMC personnel will cover ground vehicle operations as part of the brief to include placement of lighted barriers on both east & west side of Runway 1/19 on Runway 15/33. During daylight hours, PMC & OPS will conduct formal in-person safety briefs with each shift change of PMC & Ops personnel on-site. Require contractor safety reps on-site nightly during AOA work periods. ‘On call’ status is not acceptable.

E. Contractor shall conduct pre-construction safety briefing with AOA work force to include escort drivers and hired drivers by Airport, PMC and contractor management personnel.

F. Contractor shall provide approved haul route maps to PMC and to all escort drivers to ensure safe compliance with routes and reduce likelihood of rogue driver.

G. Airport Operations and PMC personnel will utilize airport maps to ensure haul routes and closed work areas are clearly understood by all concerned. Haul maps will be provided to Contractor, PMC, and Operations personnel and faxed nightly to FAA Tower prior to construction.

H. In the event no signage will be placed on non-construction side of the runway, the Contractor will position a manned vehicle operator where the barriers would have been placed to act as a deterrent to stray vehicles. Once it is determined the barriers will be put into position, the driver and vehicle requirement will no longer be required.

Page 20: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON EXPANSION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

SUPPLEMENTARY CONDITIONS 007300 - 12

I. All truck rally points shall be manned streetside where escorts will pick-up vehicles for escorts. Manned rally point(s) will have a contractor representative present to ensure all vehicle drivers stop and wait for escort vehicles. Contractor will provide an on-site vehicle rally coordinator.

J. Semi-annual driver IET safety training is required for all designated ‘DM’ drivers from active driving groups – Fire Department, Airport Maintenance, PMC, select tenants, FAA, PMC and contractors. Annual safety briefings conducted by an Airport Operations rep for the aforementioned groups will be designed to ensure movement area drivers know of the serious nature of runway incursions.

K. All barricades placed on DCA runways should extend across the runway(s) from pavement to pavement (200’) whenever feasible.

L. Do not use Levee Road to transit from South end of airfield to the North end of the airfield unless specifically approved by Airport Operations and with prior coordination.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 007300

Page 21: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON EXPANSION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

SUMMARY 011000 - 1

SECTION 011000 - SUMMARY

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings, Contract Provisions, Special Provisions, Supplementary Conditions, and other Division 01 Specification Sections apply to this Section.

1.2 SUMMARY

A. This Section includes the following:

1. Work covered by the Contract Documents. 2. Type of the Contract. 3. Work phases. 4. Work under other contracts.

5. Use of premises. 6. The Authority's occupancy requirements. 7. Work restrictions. 8. Specification formats and conventions.

B. Related Sections include the following:

1. Division 01 Section "Temporary Facilities and Controls" for limitations and procedures governing temporary use of the Authority's facilities.

1.3 WORK COVERED BY CONTRACT DOCUMENTS

A. Project Identification: Project consists of the construction of a new blast fence at TV-900 for the Runway 1-19 Safety Area Improvements and Runway 1 Hold Apron Modification project.

1. Project Location: Ronald Reagan Washington National Airport.

B. Architect/Engineer Identification: The Contract Documents, dated July 19, 2011, were prepared for Project by Airport Design Consultants Inc. and CH2M HILL, 15010 Conference Center Drive, Suite 200, Chantilly, Virginia 20151.

C. Construction Manager: Parsons Management Consultants has been engaged as Construction Manager for this Project to serve as an advisor to the Authority and to provide assistance in administering the Contract for Construction between the Authority and Contractor, according to a separate contract between the Authority and Construction Manager.

1. For additional functions of Parsons Management Consultants, see "Supplementary Conditions."

Page 22: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON EXPANSION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

SUMMARY 011000 - 2

D. The Work consists of construction of a new blast fence as part of the Runway 1-19 Safety Area Improvements and Runway 1 Hold Apron Modification project

1. The Work includes the installation of new blast fence and obstruction lighting at TV-900, including associated foundations and sitework.

2. For additional requirements for the examination of plans, specifications, and Project site see Section "Supplementary Conditions."

1.4 TYPE OF CONTRACT

A. Project will be constructed under a general construction contract.

1.5 WORK PHASES

A. Conduct the Work in accordance with the restrictions shown on the plans.

B. Schedule the execution of the Work according to the phasing sequence indicated and to avoid interference with normal functions of the Airport.

C. Before commencing Work of each phase, submit a schedule to COTR showing the sequence, the commencement and completion dates, and the move-out and move-in dates of personnel for the various phases of the Work.

D. On completion, each phase of the Work shall be fully operational.

1.6 WORK UNDER OTHER CONTRACTS

A. General: Cooperate fully with separate contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract. Coordinate the Work of this Contract with work performed under separate contracts.

B. Concurrent Work: Authority has awarded separate contract(s) for the following construction

operations at Project site. Those operations will be conducted simultaneously with work under this Contract.

1. Runway 1-19 Overlays and Taxiway Rehabilitation Project: A separate contract has been awarded to Lagan Construction for Resurfacing Runway 1-19.

2. Runway 1-19 Safety Area Improvements and Runway 1 Hold Apron Expansion –

General Construction Package: A separate contract has been awarded to Archer Western Contracting for construction of a 300 linear foot extension of Runway 1-19 and parallel Taxiway J to the south for the purpose of establishing full safety areas on both runway ends. The project also includes expansion of Runway 1 Hold Apron, and new Glide Slope Facility and removal of the existing Runway 1 ALSF-2.

Page 23: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON EXPANSION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

SUMMARY 011000 - 3

1.7 USE OF PREMISES

A. Use of Site: Limit use of premises to work in areas indicated. Do not disturb portions of site beyond areas in which the Work is indicated.

1. Limits: Confine constructions operations to the limits shown on the plans. 2. Authority Occupancy: Allow for Authority occupancy of site and day-to-day use by

tenants, air carriers, and the public. 3. Contractor shall have full use of premises for construction operations within the Contract

Limit Lines indicated during construction period, during the hours indicated, and as directed by COTR. Contractor's use of premises is limited only by the Authority's right to perform work or to retain other contractors on portions of Project.

4. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to the Authority, the Authority's employees, tenants, air carriers, and emergency vehicles at all times. Do not use driveways and entrances for parking or storage of materials.

a. Schedule deliveries to minimize use of driveways and entrances. b. Schedule deliveries to minimize space and time requirements for storage of

materials and equipment on-site.

B. Utilize areas designated for Contractor staging, storage, and parking, as indicated. For additional requirements, see Section "Supplementary Conditions."

1.8 CONTRACTOR HOURS OF OPERATION

A. Contractor Working Hours: The Authority anticipates that the Contractor may be required to work multiple shifts to accomplish the work of this Contract within the established schedule. Contractor will be allowed and may be required by the nature of the Project to work 24 hours a day, seven days a week in the performance of the Work. Work is subject to restrictions of the Airport operational requirements as indicated on the plans. Notify the COTR 24-hours in advance of any change to the work schedule.

1.9 SPECIFICATION FORMATS AND CONVENTIONS

A. Specification Format: With the exception of Federal Aviation Administration (FAA) standard specifications and Virginia Department of Transportation standard specifications the Specifications are organized into Divisions and Sections using the 33-Division format using the CSI/CSC's "MasterFormat 2004" numbering system.

1. Section Identification: The Specifications use Section titles to help with cross-referencing in the Contract Documents. Sections in the Project Manual are in numeric sequence; however, the sequence is incomplete as all available Sections and Section numbers are not used and the CSI numbering system is not sequentially complete. Consult the table of contents at the beginning of the Project Manual to determine numbers and names of sections in the Contract Documents.

Page 24: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON EXPANSION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

SUMMARY 011000 - 4

B. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows:

1. Abbreviated Language: Language used in the Specifications and other Contract Documents is abbreviated. Interpret words and meanings as appropriate. Infer words implied, but not stated, as the sense requires. Interpret singular words as plural, and plural words as singular where applicable as the context of the Contract Documents indicates.

2. Imperative mood and streamlined language are used in these Specifications. This imperative language is directed to the Contractor, unless specifically noted otherwise. Requirements expressed in the imperative mood are to be performed by Contractor. Occasionally, the indicative or subjunctive mood may be used in the Section Text for clarity to describe responsibilities that must be fulfilled indirectly by Contractor or by others when so noted.

a. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.

1.10 MARKING UTILITY SERVICES

A. Employ underground utilities location subcontractor to locate and mark the horizontal location of all utility lines, that might be impacted by construction activities, including but not limited to the following:

1. Electric power lines. 2. Natural gas lines. 3. Sanitary Sewers. 4. Storm Sewers. 5. FAA communications, signal, and security lines. 6. Runway lighting lines 7. Water supply piping. 8. 530 KHz AM radio line - Parking Lot Availability Notification System -buried cable

parallel to the Airport access road. The system utilizes antennas on the Airport thus there are no buried cables for this system within the fenced portion of the Airport property.

9. Fuel Lines. 10. Telephone lines. 11. Data lines. 12. Underground Storage Tanks. 13. High Temperature Hot Water (HTHW) and chilled water lines.

B. Contact the Airport Communications System (ACS) Help Desk at (703) 417-8300 a minimum of 72 hours prior to starting activities that include but are not limited to location and marking of horizontal locations of telephone and telecommunications lines belonging to the Authority as part of the Airport Communication System. Contact the Airport Communications System (ACS) Help Desk a minimum of 72 hours prior to beginning operations, that include but are not limited to excavating, boring, pile-driving, digging or planting. Note the ACS does not locate utilities. Location is the responsibility of the Contractor’s underground utilities location

Page 25: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON EXPANSION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

SUMMARY 011000 - 5

subcontractor. The Airport Communications System (ACS) is merely notified as indicated previously.

C. The information in the Contract Documents concerning the type and location of underground utilities is neither guaranteed nor inclusive. The Contractor is responsible for determining the type and location of underground utilities, regardless of whether such utilities are indicated or not, so as to avoid damage thereto.

D. Check and verify the horizontal and vertical location (coordinates and elevation) of all utility lines that may exist within the limits of new work, regardless of whether such utilities are indicated or not, by use of a Subsurface Utility Engineering company. Reconfirm such locations and verification of utilities discovered, regardless of whether such utilities are indicated or not, and submit to the COTR a dimensional survey with such notations.

E. Dig test pits by hand shovel in the vicinity of the discovered utilities. Excavate test holes utilizing a vacuum excavator.

F. Repair any damage to discovered utility lines due to construction operations at no expense to the Authority. The Authority will assist the Contractor by making available any known information.

G. Submit to the COTR, for written approval, the name of the independent subsurface utility engineering company to be used.

H. The individual who performs the utility detection and location work shall have as a minimum five (5) years of similar experience in the area of subsurface utility detection and location engineering.

I. Submit to COTR the following:

1. List of utility detection equipment along with product information and data sheets that will be used specifically for this contract.

2. List of employee qualifications and résumés of those individuals who will be assigned specifically to this contract.

3. Within 60 calendar days of Notice to Proceed, a survey of all subsurface utility engineering results indicating the horizontal and vertical location, coordinates and elevation of all utilities.

1.11 UTILITY OUTAGES

A. Prior to any utility outage/interruption, prepare a schedule of such outage. Include in outage schedule duration, identification of the service affected, temporary utility service to be provided, identification of available service alternative, and the action to be taken in any emergency. Apply for all outages of utility systems in writing. Fully coordinate outage requests with COTR. Obtain approval in writing by COTR. Schedule all outages at least three (3) weeks in advance with a 96-hour notification provided by the Contractor confirming date, time, and duration. Outages will normally be scheduled to occur between the hours of 11:00 pm and 5:30 am, Tuesday through Thursday.

Page 26: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON EXPANSION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

SUMMARY 011000 - 6

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Note Used)

END OF SECTION 011000

Page 27: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON EXPANSION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

UNIT PRICES 012200 - 1

SECTION 012200 - UNIT PRICES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings, Contract Provisions, Special Provisions, Supplementary Conditions, and other Division 01 Specification Sections apply to this Section.

B. The Price Proposal Form can be found in Section III, "Schedule”.

1.2 SUMMARY

A. This Section includes administrative and procedural requirements for unit prices.

B. Related Sections include the following: 1. Division 01 Section "Measurement and Payment" for procedures for measurement and

payment for unit-price items.

1.3 DEFINITIONS

A. A unit price is an amount proposed by offerors and stated on the Schedule as a price per unit of measurement for materials or services. An estimate of the quantities of work to be done and materials to be furnished under these specifications is given in Section III, "Schedule." It is given only as a basis for comparison of proposals and the award of the Contract. The Authority does not expressly or by implication agree that the actual quantities involved will correspond exactly therewith; nor shall Contractor plead misunderstanding or deception because of such estimates of quantities, or of the character, location, or other conditions pertaining to the work. Payment to Contractor will be made only for the actual quantities of work performed or materials furnished according to the plans and specifications. Refer to “Contract Provisions”, Section VII, Payments - Construction Contracts, Paragraph H, "Variation in Estimated Quantities."

1.4 PROCEDURES

A. Unit prices include all necessary material, plus cost for delivery, installation, insurance, applicable taxes, overhead, and profit. The sum of all extended unit prices in the Section III, "Schedule," shall be deemed to include all work described in the Contract Documents including Drawings and Specifications.

B. Measurement and Payment: Refer to individual Specification Sections for work that requires establishment of` unit prices. Methods of measurement and payment for unit prices are specified in those Sections and in Division 01 Section "Measurement and Payment."

Page 28: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON EXPANSION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

UNIT PRICES 012200 - 2

C. The Authority reserves the right to reject Contractor's measurement of work-in-place that involves use of established unit prices and to have this work measured, at the Authority's expense, by an independent surveyor acceptable to Contractor.

D. List of Unit Prices: A list of unit prices is included in Section III “Schedule” of the Contract Documents Specification Sections referenced in the Schedule contain requirements for materials described under each unit price.

1. The Price Proposal Form can be found in Section III, "Schedule," of the Contract Documents. If applicable, Specification Sections referenced in the Schedule contain requirements for materials and methods described under each unit price.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 012200

Page 29: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON EXPANSION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

MEASUREMENT AND PAYMENT 012210 - 1

SECTION 012210 - MEASUREMENT AND PAYMENT

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings, Contract Provisions, Special Provisions, Supplementary Conditions, and other Division 01 Specification Sections apply to this Section.

1.2 SUMMARY

A. This Section includes administrative and procedural requirements governing methods of measurement and computations to be used in determination of quantities of material furnished and unit amount of Work performed under the Contract in order for Contractor to receive payment according to pre-established unit prices.

B. At the discretion of the COTR, payment may be reduced for any Work which is not in full compliance with the Contract Documents or which has been damaged or repaired by Contractor. Such action may be used when the end product may have a reduced service life or less than desirable aesthetic characteristics.

C. Descriptions of unit-price items are specified in Section III, "Schedule," of the Contract Provisions.

1.3 MEASUREMENT OF QUANITITES

A. All volumes or quantities used to determine unit-price payment will be measured by COTR, or by COTR’s authorized representatives, using methods generally recognized as conforming to good engineering practice. Unless otherwise indicated, measurement shall be in U.S. Customary Units of Measurement.

B. Unless otherwise indicated, longitudinal measurements for area computations will be made horizontally, and no deductions will be made for individual fixtures (or leave-outs) having an area of 9 sq. ft. or less. Unless otherwise indicated, transverse measurements for area computations will be the neat dimensions shown on Drawings.

1. Structures will be measured according to neat lines shown on the plans or as altered to fit field conditions.

2. Measure all Contract items measured by the linear foot, such as electrical ducts, conduits, pipe culverts, under drains, and similar items, parallel to the base of foundation on which such items are placed, unless otherwise indicated.

3. In computing volumes of excavation, use the average end area method or other acceptable method.

Page 30: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON EXPANSION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

MEASUREMENT AND PAYMENT 012210 - 2

C. The thickness of plates and galvanized sheet used in the manufacture of corrugated metal pipe, metal plate pipe culverts and arches, and metal cribbing will be specified and measured in decimal fraction of inches.

D. Haul materials, to be measured by volume in the hauling vehicle, in approved vehicles and measured therein at the point of delivery. Vehicles for this purpose may be of any size or type acceptable to and approved in advance by COTR, provided that the body is of such shape that the actual contents may be readily and accurately determined. Load all vehicles to at least their water-level capacity. Level loads when the vehicles arrive at the point of delivery.

1. When requested by Contractor and approved by COTR in writing, material specified to be measured by the cubic yard may be weighed, and such weights will be converted to cubic yards for payment purposes. Factors for conversion from weight measurement to volume measurement will be determined by COTR and agreed to by Contractor before such method of measurement of pay quantities is used.

2. The term "ton" will mean the short ton consisting of 2000-lb avoirdupois. Weigh all materials, which are measured or proportioned by weights, on accurate, approved scales by competent, qualified personnel at locations designated by COTR.

a. If material is shipped by rail, the car weight may be accepted, provided that only the actual weight of material will be paid for. However, car weights will not be acceptable for material to be passed through mixing plants.

b. Weigh trucks used to haul material being paid for by weight empty daily at such times as COTR directs. Each truck shall bear a plainly legible identification mark.

E. Measure bituminous materials by the gallon or ton. When measured by volume, measure such volumes at 60 deg F or measure corrected to the volume at 60 deg F, using ASTM D 1250 for asphalts or ASTM D 633 for tars.

1. Net certified scale weights or weights based on certified volumes in the case of rail shipments will be used as a basis of measurement, subject to correction when bituminous material has been lost from the car or the distributor, wasted, or otherwise not incorporated into the Work.

2. When bituminous materials are shipped by truck or transport, net certified weights by volume, subject to correction for loss or foaming, may be used for computing quantities.

F. Concrete will be measured by the cubic yard in place, unless otherwise indicated.

G. The term "each" when used as an item of payment shall mean complete payment for the work described in the Contract.

1. When a complete structure or structural unit is to be provided, and "each" is specified, as the unit of measurement, the unit will be construed to include all necessary fitting, accessories, and work incidental to the work item.

H. Rental of equipment will be measured by time in hours of actual working time and necessary traveling time of the equipment within the limits of the Work. Special equipment ordered by COTR in connection with "force account work" will be measured as agreed in Contract Modification authorizing such force account work as provided in the Contract Documents.

Page 31: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON EXPANSION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

MEASUREMENT AND PAYMENT 012210 - 3

I. When standard manufactured items are specified such as fence, wire, plates, rolled shapes, pipe conduit, etc., and these items are identified by gage, unit weight, section dimensions, etc., such identification will be considered to be nominal weights or dimensions. Unless more stringently controlled by tolerances in cited Specifications, manufacturing tolerances established by the industries involved will be accepted.

J. When estimated quantities for a specific portion of the Work are designated as the pay quantities in the Contract, they shall be the final quantities for which payment for such specific portion of the Work will be made, unless the dimensions of said portions of the Work shown on Drawings are revised by Contract Modification signed by the Contracting Officer.

1. If revised dimensions result in an increase or decrease in quantities of such Work, final quantities for payment will be revised in the amount represented by the authorized changes in the dimensions.

1.4 SCALES

A. Scales for weighing materials, which are required to be proportioned or measured and paid for by weight, shall be furnished, erected, and maintained by Contractor or be certified permanently installed commercial scales.

B. Scales shall be accurate within one-half percent of the current weight throughout the range of use. Contractor shall have scales checked under the observation of the inspector before beginning Work and at such other times as requested. The intervals shall be uniform in spacing throughout the graduated or marked length of the beam or dial and shall not exceed one-tenth of 1 percent of the nominal rated capacity of the scale, but not less than 1 lb. The use of spring balances will not be permitted.

1. Beams, dials, platforms, and other scale equipment shall be so arranged that the operator and the inspector can safely and conveniently view them.

2. Scale installations shall have available 10 standard 50-lb weights for testing the weighing equipment or suitable weights and devices for other approved equipment.

3. Scales must be tested for accuracy and serviced before use at a new site. Platform scales shall be installed and maintained with the platform level and rigid bulkheads at each end.

4. Scales "overweighing" (indicating more than correct weight) will not be permitted to operate, and all materials received subsequent to the last previous correct weighing-accuracy test will be reduced by the percentage of error in excess of one-half of 1 percent.

5. In the event inspection reveals the scales have been "under-weighing" (indicating less than correct weight), they shall be adjusted, and no additional payment to Contractor will be allowed for materials previously weighted and recorded.

C. All costs in connection with furnishing, installing, certifying, testing, and maintaining scales; for furnishing check weights and scale house; and for all other items specified in this Section for the weighing of materials for proportioning or payment shall be included in the unit Contract prices for the various items of Project.

Page 32: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON EXPANSION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

MEASUREMENT AND PAYMENT 012210 - 4

1.5 PAYMENT FOR MATERIALS ON HAND

A. Partial payments may be made to the extent of the delivered cost of materials to be incorporated into the Work, provided that such materials meet the requirements of the Contract, Drawings, and Specifications and are delivered to acceptable sites on the Airport property or at other sites in the vicinity that are acceptable to COTR. Such delivered costs of stored or stockpiled materials may be included in the next partial payment application after the following conditions are met:

1. COTR accepts the manner in which the material has been stored at or on an approved site.

2. Contractor provides COTR with acceptable evidence of quantity and quality of the materials.

3. Contractor provides COTR with acceptable evidence that the material and transportation costs have been paid.

4. Contractor provides the Authority legal title, free of liens or encumbrances of any kind, to the material so stored and stockpiled.

5. Contractor provides the Authority evidence that the material so stored or stockpiled is insured against loss by damage to or disappearance of such materials at anytime before use in the Work.

6. Contractor provides the Authority with manufacturer’s installation and maintenance information.

B. It is understood and agreed that the transfer of title and the Authority's payment for such stored or stockpiled materials shall in no way relieve Contractor of responsibilities for furnishing and placing such materials according to the requirements of the Contract Documents.

C. In no case will the amount of partial payments of materials on hand exceed the Contract price for the materials or the Contract price for the Contract item in which the material is intended to be used.

D. No partial payment will be made for living or perishable plant materials.

E. Contractor bears all costs associated with the partial payment of stored or stockpiled materials according to the provisions of this Section.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 012210

Page 33: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

APPLICATION FOR PAYMENT 012900 - 1

SECTION 012900 – APPLICATION FOR PAYMENT

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings, Contract Provisions, Special Provisions, Supplementary Conditions, and other Division 01 Specification Sections apply to this Section.

1.2 SUMMARY

A. This Section specifies administrative and procedural requirements necessary to prepare and process Applications for Payment.

1. Coordinate the Schedule of Values and Applications for Payment with Contract CPM Schedule, List of Subcontracts, and Submittal Log.

B. Related Sections include the following: 1. Division 01 Section "Unit Prices" for administrative requirements governing use of unit

prices. 2. Division 01 Section "Measurement and Payment" for administrative requirements

governing methods of measurement and determination of quantities of materials for use with unit prices.

3. Division 01 Section "Construction Progress Documentation" for administrative requirements governing preparation and submittal of Contractor's Construction Schedule and Submittals Schedule.

4. Division 01 Section “Project Closeout” for submittal of items required before final payment.

5. Division 01 Section “Project Record Documents” for procedural requirements governing the submission of Project Record Documents.

1.3 DEFINITIONS

A. Schedule of Values: A statement furnished by Contractor allocating portions of the Contract Price to various portions of the Work and once accepted, to be used as the basis for reviewing Contractor's Applications for Payment.

1.4 SCHEDULE OF VALUES

A. Coordination: Coordinate preparation of the Schedule of Values with preparation of Contractor's Construction Schedule.

1. Correlate line items in the Schedule of Values with other required administrative forms and schedules, including the following:

Page 34: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

APPLICATION FOR PAYMENT 012900 - 2

a. Application for Payment forms with Continuation Sheets. b. Submittals Schedule. c. Contract CPM Schedule. d. List of products. e. List of principal suppliers and fabricators.

2. Submit the Schedule of Values to Contracting Officer at earliest possible date, but no later than 21 calendar days after the date of the Notice to Proceed.

a. On projects requiring cost-loaded CPM Schedules, the accepted cost loading will satisfy the requirements for the Schedule of Values.

B. Format and Content: Use the Project Manual table of contents as a guide to establish line items for the Schedule of Values. Provide at least one line item for each Specification Section.

1. Identification: Include the following Project identification on the Schedule of Values:

a. Project name and location. b. Name of COTR. c. Name of Architect/Engineer. d. The Authority’s Project number. e. Contractor's name and address. f. Date of submittal.

2. Arrange the Schedule of Values in tabular form with separate columns to indicate the following for each item listed:

a. Related Specification Section or Division. b. Description of the Work. c. Name of subcontractor. d. Name of manufacturer or fabricator. e. Name of supplier. f. Contract Modifications (numbers) that affect value. g. Dollar value.

1) Percentage of the Contract Price to nearest one-hundredth percent, adjusted to total 100 percent.

3. Provide a breakdown of the Contract Price in enough detail to facilitate continued evaluation of Applications for Payment and progress reports. Coordinate with the Project Manual table of contents. Provide several line items for principal subcontract amounts, where appropriate. Include separate line items under required principal subcontracts for the following items. The value assigned to the total of these line items shall be 5 percent of the Contract Price:

a. Testing and commissioning activities. b. Operation and Maintenance manuals. c. Punch list activities. d. Project Record Documents. e. Bonds and warranties.

Page 35: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

APPLICATION FOR PAYMENT 012900 - 3

f. Demonstration and training.

4. Round amounts to nearest whole dollar. Total shall equal the Contract Price.

5. Provide a separate line item in the Schedule of Values for each part of the Work where Application for Payment may include materials or equipment purchased or fabricated and stored, but not yet installed.

a. Differentiate between potential items stored on-site and items stored off-site. Include evidence of insurance or bonded warehousing if required.

6. Provide separate line items in the Schedule of Values for initial cost of materials, for each subsequent stage of completion, and for total installed value of that part of the Work.

7. Each item in the Schedule of Values and Application for Payment shall be complete. Include total cost and proportionate share of general overhead and profit for each item.

a. At COTR’s option, temporary facilities and other major cost items that are not direct cost of actual work-in-place may be shown either as separate line items in the Schedule of Values or distributed as general overhead expense.

8. Schedule Updating: Update and resubmit the Schedule of Values with the next Applications for Payment when Contract Modifications result in a change in the Contract Price.

1.5 APPLICATION FOR PAYMENT

A. Each Application for Payment shall be consistent with previous applications and payments as certified by Contracting Officer and paid for by the Authority.

1. Initial Application for Payment, Application for Payment at time of Substantial Completion, and final Application for Payment involve additional requirements.

B. Payment Application Times: Application for Payment shall coincide with CPM schedule monthly update, or as otherwise indicated in the Agreement between the Authority and Contractor. The period covered by each Application for Payment starts on the day following the end of the preceding period and shall not exceed one calendar month, unless otherwise approved by COTR.

C. Payment Application Forms: Use forms provided by the Contracting Officer, but supplied by COTR, for Application for Payment.

D. Application Preparation: Complete every entry on form. Notarize and execute by a person authorized to sign legal documents on behalf of Contractor. The Authority will return incomplete applications without action.

1. Entries shall match data on the Schedule of Values and Contractor's Construction Schedule. Use updated schedules if revisions were made.

2. Include amounts of Contract Modifications issued before last day of construction period covered by application.

Page 36: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

APPLICATION FOR PAYMENT 012900 - 4

E. Transmittal: Submit one original and four copies of Application for Payment to the address indicated in the Section VII - Contract Provision, paragraph 04.B, each one signed and notarized. Include waivers of lien and similar attachments if required.

1. Transmit Applications for Payment with a transmittal form listing attachments and recording appropriate information about application in a manner acceptable to Contracting Officer.

F. Waivers of Mechanic's Lien: With Final Application for Payment, submit waivers of mechanic's liens from subcontractors, sub-subcontractors, and suppliers.

1. The Authority reserves the right to designate which entities involved in the Work must submit waivers.

2. Waiver Forms: Submit waivers of lien on forms, executed in a manner acceptable to the Authority.

G. Initial Application for Payment: Administrative actions and submittals that shall precede or coincide with submittal of first Application for Payment include the following:

1. List of subcontractors. 2. Schedule of Values. 3. Contractor's Construction Schedule (preliminary if not final). 4. Schedule of unit prices. 5. Submittals Schedule (preliminary if not final). 6. List of Contractor's staff assignments. 7. List of Contractor's principal consultants. 8. Copies of building permits. 9. Copies of authorizations and licenses from authorities having jurisdiction for performance

of the Work. 10. Initial progress report. 11. Report of pre-construction conference. 12. Performance and payment bonds. 13. Initial settlement survey and damage report if required. 14. Submittal and approval of Contractor Safety Plan. 15. Subcontractor Payment Form: (Form J, "Contract Conditions," Section IX, "LDBE").

H. Monthly Application for Payment: Administrative actions and submittals that shall accompany the submittal of Contractor's monthly Application for Payment include the following:

1. Subcontractor Payment Form. 2. Monthly Progress Report, prepared according to requirements specified in Division 01

Section "Construction Progress Documentation." 3. Evidence of payment for material on-site if reimbursement for such material is being

requested. 4. Update of Contract Record Documents.

I. Application for Payment at Substantial Completion: After issuance of the Certificate of Substantial Completion, submit an Application for Payment showing 100 percent completion for portion of the Work claimed as substantially complete.

Page 37: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

APPLICATION FOR PAYMENT 012900 - 5

1. Include documentation supporting claim that the Work is substantially complete and a statement showing an accounting of changes to the Contract Price.

2. This application shall reflect Certificates of Partial Substantial Completion issued previously for Authority occupancy of designated portions of the Work, if applicable.

3. Advise COTR of change-over in security provisions.

J. Final Payment Application: Submit final Application for Payment with releases and supporting documentation not previously submitted and accepted, including, but not limited, to the following:

1. Evidence of completion of Project closeout requirements. 2. Insurance certificates for products and completed operations where required and proof

that taxes, fees, and similar obligations were paid. 3. Updated final statement, accounting for final changes to the Contract Price. 4. Evidence that claims have been settled. 5. Final meter readings for utilities, a measured record of stored fuel, and similar data as of

date of Substantial Completion or when the Authority took possession of and assumed responsibility for corresponding elements of the Work.

6. Final, liquidated damages settlement statement. 7. Return of all Airport identification badges and keys.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 012900

Page 38: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final
Page 39: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

PROJECT MANAGEMENT AND COORDINATION 013100 - 1

SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings, Contract Provisions, Special Provisions, Supplementary Conditions, and other Division 01 Specification Sections apply to this Section.

1.2 SUMMARY

A. This Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

1. General project coordination procedures. 2. Conservation. 3. Coordination drawings. 4. Administrative and supervisory personnel. 5. Project meetings.

a. Pre-award conference. b. Pre-construction conference. c. Pre-installation conference. d. Progress meetings.

B. Related Sections include the following:

1. Division 01 Section: "Execution" for the coordination of general installation and field-engineering services, including establishment of benchmarks and control points.

2. Division 01 Section "Project Closeout" for coordinating Contract closeout.

1.3 COORDINATION

A. Coordination: Coordinate construction operations included in various Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections that depend on each other for proper installation, connection, and operation.

1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

2. Coordinate installation of different components with other contractors to ensure maximum accessibility for required maintenance, service, and repair.

3. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, mechanical, electrical, and otherwise. Contractor is cautioned

Page 40: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

PROJECT MANAGEMENT AND COORDINATION 013100 - 2

that, where specific dimensions are not indicated or where Drawings are schematic in nature, as with most Electrical and Mechanical Drawings, Contractor shall have sole responsibility to coordinate the work to meet this requirement. Prepare and submit Coordination Drawings to COTR for review and approval as provided in "Coordination Drawings" Paragraph in "Submittals" Article of this Section.

4. Make adequate provisions to accommodate items scheduled for later installation.

B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.

1. Prepare similar memoranda for COTR and separate contractors if coordination of their Work is required.

C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work and completion within the specified Contract duration. Such administrative activities include, but are not limited to, the following:

1. Preparation of Contractor's Construction Schedule. 2. Preparation of the Schedule of Values. 3. Installation and removal of temporary facilities and controls. 4. Delivery and processing of submittals. 5. Progress meetings. 6. Pre-installation conferences. 7. Start-up, check-out, and final acceptance of systems. 8. Project closeout activities. 9. Protection of existing and new work.

D. Conservation: Coordinate construction activities to ensure that operations are carried out with consideration given to conservation of energy, water, and materials.

1. Salvage materials and equipment involved in performance of, but not actually incorporated into, the Work. Refer to other sections for disposition of salvaged materials that are designated as the Authority's property.

E. Temporary Utility Outages: Comply with requirements in Division 01 Section "Summary."

1.4 SUBMITTALS

A. Coordination Drawings: Before start of the Work, prepare Coordination Drawings for areas with limited space availability that necessitate maximum utilization of space for efficient installation of different components, and areas requiring coordination for installation of products and materials fabricated by separate entities.

1. Indicate relationship of components shown on separate Shop Drawings. 2. Indicate all dimensions provided on Contract Drawings and make specific note of

dimensions that appear to be in conflict with submitted equipment, minimum clearance requirements, amounts of equipment and material to be installed, or other requirements. Provide alternate sketches for resolution of such conflicts to COTR for review. Minor

Page 41: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

PROJECT MANAGEMENT AND COORDINATION 013100 - 3

dimension changes and difficult installations shall not be considered changes to the Contract.

3. Indicate required installation sequences. 4. Comply with requirements contained in Division 01 Section "Submittals." 5. Prepare coordination drawings of involved trades in a scale of not less than 1/4 inch = 1

foot or larger for integration of different construction elements. Show sequences and relationships of separate components to avoid conflicts in use of space. Any Work installed prior to review of coordination drawings will be at the Contractor’s risk and subsequent relocation require to avoid interference shall be made at no additional cost to the Authority.

B. Key Personnel Names: At the pre-construction meeting, submit a list of Contractor's key personnel assignments. Key personnel shall include but not necessarily be limited to Project Manager, Project Superintendent, Safety Manager, Safety Engineer, Quality Control Manager, Project Scheduler, Soil Excavation Engineers, and other personnel in attendance at Project site along with alternates. Identify individuals and their duties and responsibilities; list addresses and telephone numbers, including home and office telephone numbers. Provide names, addresses, and telephone numbers of individuals assigned as standbys in the absence of individuals assigned to Project.

1. Post copies of list in Project meeting room, in temporary field office, and by each temporary telephone. Keep the list current at all times.

1.5 REQUESTS FOR INFORMATION (RFIs)

A. Procedure: Immediately on discovery of the need for interpretation of the Contract Documents, prepare and submit an RFI in the form specified. 1. RFIs shall originate with Contractor. RFIs submitted by entities other than Contractor

will be returned with no response. 2. Coordinate and submit RFIs in a prompt manner so as to avoid delays in Contractor's

work or work of subcontractors.

B. Content of the RFI: Include a detailed, legible description of item needing interpretation and the following: 1. Contract Name 2. Contract Number 3. Date. 4. Name of Contractor. 5. Name of Resident Engineer 6. Name of Task Manager 7. RFI number, numbered sequentially. 8. Specification Section number and title and related paragraphs, as appropriate. 9. Drawing number and detail references, as appropriate. 10. Field dimensions and conditions, as appropriate. 11. Contractor's suggested solution(s). If Contractor's solution(s) impact the Contract Time

or the Contract Sum, Contractor shall state impact in the RFI. 12. Contractor's signature.

Page 42: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

PROJECT MANAGEMENT AND COORDINATION 013100 - 4

13. Attachments: Include drawings, descriptions, measurements, color photos, Product Data, Shop Drawings, and other information necessary to fully describe items needing interpretation. a. Supplementary drawings prepared by Contractor shall include dimensions,

thicknesses, structural grid references, and details of affected materials, assemblies, and attachments.

C. Software-Generated RFIs: Software-generated form with substantially the same content as indicated above. 1. Attachments shall be electronic files in Adobe Acrobat PDF format. 2. RFI must be signed and scanned for electronic transmission. 3. Hard-Copy RFI shall follow Software-Generated RFI for the record.

D. COTR’s Action: COTR will review each RFI, determine action required, and return it. Allow seven working days for COTR's response for each RFI. RFIs received after 1:00 p.m. will be considered as received the following working day. 1. The following RFIs will be returned without action:

a. Requests for approval of submittals. b. Requests for approval of substitutions. c. Requests for coordination information already indicated in the Contract

Documents. d. Requests for adjustments in the Contract Time or the Contract Sum. e. Requests for interpretation of Architect's actions on submittals. f. Incomplete RFIs or RFIs with numerous errors.

2. COTR's action may include a request for additional information, in which case COTR's time for response will start again.

3. COTR's action on RFIs that may result in a change to the Contract Time or the Contract Sum may be eligible for Contractor to submit Change Proposal. a. If Contractor believes the RFI response warrants change in the Contract Time or

the Contract Sum, notify COTR in writing within 10 days of receipt of the RFI response.

E. On receipt of COTR’s action, update the RFI log and immediately distribute the RFI response to affected parties. Review response and notify COTR within seven days if Contractor disagrees with response.

F. RFI Log: Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number. Submit log weekly prior to progress meeting for inclusion in progress meeting minutes. Software log with not less than the following: 1. Project name. 2. Name and address of Contractor. 3. Name of COTR. 4. RFI number including RFIs that were dropped and not submitted. 5. RFI description. 6. Date the RFI was submitted. 7. Date COTR’s response was received. 8. Identification of related Field Order, Work Change Directive, and Proposal Request, as

appropriate.

Page 43: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

PROJECT MANAGEMENT AND COORDINATION 013100 - 5

1.6 ADMINISTRATIVE AND SUPERVISORY PERSONNEL

A. General: In addition to Project Superintendent, provide other administrative and supervisory personnel as required for proper performance of the Work.

1.7 PROJECT MEETINGS

A. Pre-award Conference:

1. General: At the request of the Contracting Officer, a pre-award conference with Contractor may be held before actual award of the Contract. The meeting will review Contractor's understanding of the Contract Documents, cost and pricing data, contractual requirements, and Contractor's capabilities, financial standing, and past experience prior to award.

a. Minutes: COTR will record and distribute meeting minutes to all attendees and all relevant parties.

2. Attendees: Contracting Officer, COTR, Authority Design Project Manager, Architect/Engineer, Contractor and its key personnel nominated for assignment to the Contract, and major subcontractors if so requested by the Contracting Officer. Concerned parties shall each be represented by persons thoroughly familiar with and authorized to conclude matters relating to the work described in the Contract Documents. The Contracting Officer will chair the pre-award meeting.

3. Agenda: Significant discussion items that could affect award include, but are not limited to, the following:

a. Provision and acceptability of payment and performance bonds. b. LDBE/MBE/WBE/DBE participation. c. Qualifications of key individuals. d. Quality-control experience. e. Percentage of work performed by own forces. f. Contractor's experience with similar work, including previous Authority contracts. g. Scheduling capabilities of Contractor. h. Financial standing of Contractor. i. Mobilization plan. j. Understanding of work described in the Contract Documents and the physical

constraints associated with work at the Airport. k. Equipment and manpower availability. l. Cost and pricing data.

4. Representations and commitments made by Contractor or its subcontractors shall be construed as binding to the Contract.

B. Pre-construction Conference:

1. General: COTR will schedule pre-construction conference and organizational meeting with Contractor after the Contracting Officer issues a notice of intent to award, or actually awards the Contract. The meeting will review the parties' responsibilities and personnel assignments.

Page 44: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

PROJECT MANAGEMENT AND COORDINATION 013100 - 6

a. Minutes: COTR will record and distribute meeting minutes to all attendees and relevant parties.

2. Attendees: Contracting Officer, COTR, Architect/Engineer, and their sub-consultants; Contractor and its superintendent; major subcontractors; manufacturers; suppliers; and other concerned parties. All participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.

3. Agenda: Discuss items of significance that could affect progress, including the following:

a. Airport security. b. LBDE/MBE/WBE/DBE participation and certifications. c. Authority-controlled wrap-up insurance program. d. Airport Operations coordination. e. Preliminary construction schedule. f. Phasing. g. Critical work sequencing. h. Designation of key personnel. i. Procedures for processing field decisions and Contract Modifications. j. Procedures for processing Applications for Payment. k. Distribution of the Contract Documents. l. Authority Construction guidelines. m. Submittal procedures. n. Preparation of Record Documents. o. Use of the premises. p. Responsibility for temporary facilities and controls. q. Parking availability. r. Office, work, and storage areas. s. Equipment deliveries and priorities. t. Safety procedures. u. Quality-control requirements. v. First aid. w. Progress cleaning. x. Working hours. y. Authority Building Code requirements/permits.

4. Refer to Contract Provision "Pre-construction Requirements" for required submittals due at the pre-construction conference.

C. Pre-installation Conferences:

1. General: COTR will conduct a pre-installation conference at Project site before each construction activity that requires coordination with other construction.

a. Minutes: COTR will record and distribute meeting minutes.

2. Attendees: Contractor, Installer, and representatives of manufacturers and fabricators involved in or affected by the installation and its coordination or integration with other materials and installations that have proceeded, or will follow.

Page 45: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

PROJECT MANAGEMENT AND COORDINATION 013100 - 7

3. Agenda: Review progress of other construction activities and preparations for the particular activity under consideration, including requirements for the following:

a. Contract Documents. b. Options. c. Related Contract Modifications. d. Purchases. e. Deliveries. f. Submittals. g. Review of mockups. h. Possible conflicts. i. Compatibility problems. j. Time schedules. k. Weather limitations. l. Manufacturer's written recommendations. m. Warranty requirements. n. Compatibility of materials. o. Acceptability of substrates. p. Temporary facilities and controls. q. Space and access limitations. r. Governing regulations and permits. s. Safety. t. Testing and inspecting requirements. u. Required performance results. v. Recording requirements. w. Protection of construction and personnel. x. Review material selection. y. Fabrication and installation procedures. z. Coordination of involved trades.

4. Do not proceed with installation if the conference cannot be successfully concluded. Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at earliest feasible date.

D. Weekly Progress Meetings:

1. General: COTR will conduct progress meetings weekly at regularly scheduled times convenient for all parties involved. Progress meetings are in addition to specific meetings held for other purposes, such as coordination and special pre-installation meetings. Additionally, discussions will address administrative and technical issues of concern, determining resolutions, and development of deadlines for resolution within allowable time frames.

a. Minutes: COTR will record and distribute meeting minutes.

2. Attendees: As may be required by COTR, in addition to representatives of the Authority and Contractor, each subcontractor, supplier, Contractor’s Project Scheduler, and other entities concerned with current progress or involved in planning, coordination, or performance of future activities. All participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.

Page 46: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

PROJECT MANAGEMENT AND COORDINATION 013100 - 8

3. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. Include topics for discussion as appropriate to status of Project.

a. Contractor's Construction Schedule: Review progress since the last meeting. Determine whether each activity is on time, ahead of schedule, or behind schedule, in relation to Contractor's Construction Schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time.

b. Review present and future needs of each entity present, including the following:

1) Safety and Security. 2) Interface requirements. 3) Time. 4) Sequence of operations. 5) Status of submittals. 6) Deliveries. 7) Off-site fabrication. 8) Storage Areas 9) Access. 10) Site utilization. 11) Requests for information. 12) Submittals. 13) Noncompliance notices. 14) Temporary facilities and controls. 15) Work hours. 16) Resource allocation. 17) Hazards and risks. 18) Progress cleaning. 19) Quality and work standards. 20) Contract Modifications. 21) Documentation of information for payment requests. 22) Preparation of Record Documents.

4. Submit at the weekly progress meeting, a two-week look-ahead schedule. This schedule shall include a three-week period, one week showing actual progress from the previous week and two weeks showing planned work for the two weeks after the meeting date. Include in the schedule all activities in sufficient detail as approved by COTR. A two-week look-ahead schedule form will be distributed at the pre-construction conference. Submit a list of subcontractors identifying dates of when subcontractors will be on-site or off-site. A form for this information will be provided by COTR.

5. Schedule Updating: Revise Contractor's Construction Schedule after each progress meeting where revisions to the schedule have been made or recognized. Issue revised schedule concurrently with the report of each meeting.

E. Schedule Update Meetings:

1. Conduct schedule update meetings before submittal of Contractor's Application for Payment. Determine where each activity is, in relation to Contractor's CPM Schedule.

Page 47: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

PROJECT MANAGEMENT AND COORDINATION 013100 - 9

Ensure the incorporation of all changes made to the sequence of work and all change notices issued by the Contracting Officer. Submit the narrative and information specified in Division 01 Section "Construction Progress Documentation" if applicable.

2. Attendees: COTR, Contractor's Project manager or superintendent, the Contractor’s Project Scheduler, and the Authority's representative.

3. Submit the updated schedule, as bilaterally agreed on, along with the Application for Payment.

4. Present delay claims for discussion and, when possible, resolution.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 013100

Page 48: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final
Page 49: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

CONSTRUCTION PROGRESS DOCUMENTATION 013200 - 1

SECTION 013200 - CONSTRUCTION PROGRESS DOCUMENTATION

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings, Contract Provisions, Special Provisions, Supplementary Conditions, and other Division 01 Specification Sections apply to this Section.

1.2 SUMMARY

A. This Section specifies administrative and procedural requirements for various CPM schedules and reports required for proper performance of the Work.

B. All costs incurred by Contractor to correctly implement and update the schedule shall be borne by Contractor and are part of this Contract.

C. Schedules required include the following:

1. Contract Construction Progress Schedule in CPM format and related narrative and cash flow projection curves.

2. Submittals Schedule. 3. Schedule of Tests and Inspections. 4. Record, As-Built CPM Schedule.

D. Reports required include the following:

1. Daily Construction Reports. 2. Material Location Reports. 3. Field Correction Reports. 4. Special Reports. 5. Monthly Progress Reports. 6. Contractor Quality Control Reports.

E. Related Sections include the following:

1. Division 01 Section "Application for Payment" for Schedule of Values. 2. Division 01 Section "Project Management and Coordination" for Project meeting

minutes. 3. Division 01 Section "Quality Requirements" for test and inspection reports. 4. Division 01 Section "Product Requirements" for Product List.

Page 50: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

CONSTRUCTION PROGRESS DOCUMENTATION 013200 - 2

1.3 DEFINITIONS

A. Activity: The fundamental unit of work in a Project plan and schedule. Each activity has defined geographical boundaries and a detailed estimate of resources required to construct the task. Each activity is assigned a unique description, activity number, activity codes, and dollar value.

B. CPM Network: The structure of the schedule. The network is the representation that defines the construction logic in terms of all the activities with their logical dependencies.

C. Contract CPM Schedule: A cost-loaded CPM schedule covering the entire Contract Duration from the Notice to Proceed through Final Acceptance of the Work.

D. Contract Duration/Time: The total time, in calendar days identified in Section III, "Schedule," representing the duration necessary for completion of all physical and administrative requirements under this Contract and any authorized extension thereof.

E. Critical Path: The critical path is the longest connected chain of interdependent activities in a CPM network that impacts the completion of the Project.

F. Excusable Delay: An unforeseeable delay, beyond the control of Contractor, experienced due to no fault or negligence by Contractor, its subcontractors, or suppliers.

G. Predecessor Activity: An activity that precedes another activity in the network.

H. Cost Loading: The allocation of the Schedule of Values for the completion of an activity as scheduled. The sum of costs for all activities shall equal the total Contract Price, unless otherwise approved by COTR.

I. Successor Activity: An activity that follows another activity in the network.

J. Total Float: The amount of time an activity can be delayed from its earliest start date without delaying the end of Project.

1. Float time is not for the exclusive use or benefit of either the Authority or Contractor, but is a jointly owned, expiring Project resource available to both parties as needed to meet schedule milestones and Contract completion date.

2. Free float is the amount of time an activity can be delayed without adversely affecting the early start of the successor activity.

1.4 PLANNING

A. The total Contract Duration and intermediate milestones if applicable, as indicated in Section III, "Schedule," are the Contract requirements.

B. Contractor shall prepare a practical work plan to complete the Work within the Contract Duration, and complete those portions of work relating to each intermediate milestone date and other Contract requirements. Contractor shall generate a computerized cost-loaded CPM schedule in Precedence Diagram Method (PDM) format for the Work.

Page 51: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

CONSTRUCTION PROGRESS DOCUMENTATION 013200 - 3

C. Failure to include any work item required for performance of this Contract shall not excuse Contractor from completing all work within applicable completion dates, regardless of COTR approval of the Schedule.

D. Failure of Contractor to comply with requirements of this Section may be considered cause for withholding progress payments or termination for default.

1.5 SUBMITTALS

A. General: Contractor shall provide all schedule submittals on computer disk media as well as tabular printouts, resource curves and histograms, and 24-by-36-inch time-scaled logic diagrams. The latest version of Primavera P3 or SureTrak scheduling software shall be used. All costs incurred by Contractor to correctly implement, computerize and update the CPM Schedule shall be borne by Contractor and are included in the Contract Price. The number of copies of each submittal shall be as described in this Section or as may be requested by COTR.

B. Contract CPM Schedule: The Contract CPM Schedule and its related narrative as described in this Section shall be submitted along with the projected cash-flow curve as early as practicable after the Notice to Proceed, but in no event later than 30 calendar days after the Notice to Proceed. Within 15 calendar days, COTR will respond with approval or direction to change and Contractor shall resubmit within 10 calendar days, if required.

C. Daily Progress Report: Submit duplicate copies to COTR by noon on the day following the date of actual progress.

D. Monthly Progress Report: All components of the Monthly Progress Report described in this Section shall be submitted as attachments to Contractor's monthly Application for Payment.

E. Record As-Built CPM Schedule: A Record CPM Schedule accurately reflecting actual progress of Work shall be submitted, as part of this Contract's Record Documents. All activities shall have actual dates that are true and accurate.

F. Qualification Data: For Project Scheduler.

1.6 QUALITY ASSURANCE

A. Project Scheduler Qualifications: Minimum of two years experience and not less than one project of similar size and scope, with capability to produce CPM reports and diagrams within 24 hours of COTR's request. Project Scheduler is classified as one of Contractor's key personnel.

Page 52: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

CONSTRUCTION PROGRESS DOCUMENTATION 013200 - 4

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 PROJECT SCHEDULER

A. Engage a project scheduler, either as Contractor's employee or as Contractor's consultant, to provide planning, evaluation, and reporting using CPM scheduling, and to prepare required schedules.

1. Project Scheduler shall be an active participant at all meetings related to Project progress, alleged delays, and time impact.

3.2 CONTRACT CPM SCHEDULE

A. Scheduling Requirements: The Contract CPM Schedule shall be a computerized cost-loaded, time-scaled CPM Schedule in PDM format that includes the following:

1. The order, sequence, and interdependence of all significant work items including mobilization, demobilization, testing and commissioning, construction, procurement, fabrication, and delivery of critical or special materials and equipment; utility interruption coordination; submittals and approvals of critical Samples, Shop Drawings, procedures, or other reasonable requirements that may be requested by COTR.

2. Work by the Authority, or utility agencies, and other third parties that may affect or be affected by Contractor's activities.

3. Adequate referencing of all work items to identify subcontractors or other performing parties.

4. Activity Coding may be provided by the COTR to establish minimum requirements for structure and values for the first 5 code fields.

5. Activity durations not in excess of 14 calendar days, except nonconstruction activities such as procurement and fabrication. Activities shall be broken down in the level of detail prescribed by COTR.

6. Activities that are cost loaded to show the direct costs required to perform the Work, including work by subcontractors.

7. A narrative that explains the basis for Contractor's determination of construction logic, estimated durations, cost allocations, estimated quantities and production rates, hours per shift, workdays per week, and types, numbers, and capacities of major construction equipment to be used. A listing of nonworking days and holidays incorporated into the schedule shall be provided.

B. Critical Path Activities: The Contract CPM Schedule shall be prepared to include the data for the total Contract and the critical path activities shall be identified, including critical paths for interim completion dates. Scheduled start or completion dates imposed on the schedule by Contractor shall be consistent with Contract milestone dates. Milestone dates shall be the scheduled dates specified in Section III, "Schedule," if applicable, and shall be prominently identified. The Contract CPM Schedule shall accurately show all as-built activities completed from the issuance of the Notice to Proceed up to the submittal of this schedule.

Page 53: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

CONSTRUCTION PROGRESS DOCUMENTATION 013200 - 5

C. Assignment of Costs to Activities for Progress Payments:

1. Contractor shall assign cost to construction activities on the Contract CPM Schedule. Costs shall not be assigned to submittal activities unless specified otherwise but may, with COTR's approval, be assigned to fabrication and delivery activities. Costs shall be assigned to testing and commissioning activities, O&M manuals, punchlist activities, and Project Record Documents.

2. Each activity cost shall reflect an accurate value subject to approval by COTR. 3. The total cost assigned to activities shall equal the total Contract Price. 4. Activities shall be cost coded as directed by COTR.

D. Required Submittals: On a monthly basis, Contractor shall submit five copies of each of the following components of the Contract CPM Schedule:

1. A time-scaled plot of the schedule network in PDM format showing logic ties for all activities including submittals and procurement activities.

2. Computer-generated CPM Schedule Reports that contain the following data for each work item: activity identification number, description, resource loading, duration, early start and early finish calendar dates, late start and late finish calendar dates, and total float in calendar days. The reports shall also show the logic ties of successor and predecessor work items. The reports shall be sorted as follows, or other sorts as required by COTR:

a. By activity identification. b. By total float x early start. c. By early start x early finish x total float.

3. The narrative described in Subparagraph 3.2-A-6 above. 4. A cash-flow report showing monthly expenditures projected over the life of the Contract.

A cumulative cash-flow curve based on early and late schedule events shall also be submitted. These reports shall be derived from the Contract CPM Schedule.

3.3 DAILY CONSTRUCTION REPORTS

A. Prepare a daily construction report, recording the following information concerning events at the site, coordinate with requirements in Division 01 Section "Quality Requirements," and submit duplicate copies to COTR by noon of the day following day of actual progress:

1. List of subcontractors (by trade group) at the site. 2. List of separate contractors at the site. 3. Approximate count of personnel (by trade group) at the site. 4. Equipment (by trade group) at the site. 5. High and low temperatures, general weather conditions. 6. Accidents (refer to accident reports). 7. Meetings and significant decisions. 8. Unusual events (refer to special reports). 9. Stoppages, delays, shortages, losses. 10. Meter readings and similar recordings. 11. Emergency procedures. 12. Orders and requests of governing authorities.

Page 54: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

CONSTRUCTION PROGRESS DOCUMENTATION 013200 - 6

13. Change Notices/Directives and Contract Modifications received, implemented. 14. Services connected, disconnected. 15. Equipment or system tests and startups. 16. Partial Completions, occupancies. 17. Substantial Completions authorized. 18. Material deliveries.

3.4 MATERIAL LOCATION REPORTS

A. At weekly intervals, prepare a comprehensive list of materials delivered to and stored at the site. List shall be cumulative, showing materials previously reported plus items recently delivered. Include with list a statement of progress on and delivery dates for all materials or items of equipment being fabricated or stored away from the building site. Submit copies of list to COTR at weekly intervals.

3.5 FIELD CORRECTION REPORT

A. When the need to take corrective action that requires a departure from the Contract Documents arises, prepare a detailed report including a statement describing the problem and recommended changes. Indicate reasons the Contract Documents cannot be followed. Submit a copy to COTR immediately.

3.6 SPECIAL REPORTS

A. When an event of unusual or significant nature occurs at the site, prepare and submit a special report. List the chain of events, persons participating, response by Contractor's personnel, an evaluation of the results or effects, and similar pertinent information. Advise COTR in advance when such events are known or predictable.

1. Include tabular CPM reports, time-scaled logic diagrams, resource curves and histograms, and narratives as requested by COTR.

B. Submit special reports directly to COTR within seven calendar days of an occurrence. Submit a copy to other parties affected by the occurrence.

3.7 MONTHLY PROGRESS REPORTING

A. General: Approval of Contractor's monthly Application for Payment shall be contingent, among other factors, on the submittal of a satisfactory monthly schedule update.

B. Monthly Schedule Update Meetings: Monthly schedule updates shall be the product of joint review meetings between Contractor, COTR, and major active subcontractors. The joint review shall focus on actual progress for the preceding month, planned progress for the upcoming month supported by a Contractor-prepared Four-Week Look-Ahead Schedule, impact to schedule if any due to change notices issued, adverse weather, and any effected changes to the Construction CPM Schedule. The agreed on progress, and changes, if any, shall be

Page 55: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

CONSTRUCTION PROGRESS DOCUMENTATION 013200 - 7

incorporated into the schedule update to be submitted. The update shall always represent the actual history of accomplishment of all activities, and will form the basis for Contractor's Application for Payment. Contractor's delay claims shall be presented for discussion and, when possible, resolution.

C. Required Submittals: On a monthly basis, Contractor shall submit two copies in electronic format of the updated CPM schedule and five copies of each of the following components of the Monthly Progress Report:

1. A monthly progress narrative, the content of which shall be prescribed by COTR, but shall include as a minimum a description of overall progress for the preceding month, a critical path analysis, a discussion of problems encountered and proposed solution thereof, delays experienced and proposed recovery measures, a monthly reconciliation of weather impact, the status and impact of contract modifications, documentation of any logic changes, and any other changes made to the schedule since the previous monthly update.

2. CPM schedule reports listing completed activities, activities in progress, and remaining activities in the format requested by COTR. For each activity, Contractor shall provide those details identified in Subparagraph 3.2-D-2.

3. Monthly and cumulative cash-flow curves that show actual vs. planned cash-flow status. 4. Documentation of delivered material in the form of paid invoices or other evidence that

Contractor has clear title for the material delivered.

D. If critical activities of the schedule are delayed and such delay is not excusable as defined in this Section, the remaining sequence of activities and/or duration thereof shall be adjusted by Contractor through such measures as additional manpower, additional shifts, or the implementation of concurrent operations until the schedule produced indicates Work will be completed on schedule. Except as provided elsewhere in the Contract, all costs incurred by Contractor to recover from inexcusable delays shall be borne by Contractor.

E. The monthly schedule update shall form the basis for Contractor's Application for Payment. The progress payment for an activity shall be based on its agreed on percentage of completion. On unit-priced contracts, the approval of Contractor's monthly requisition is contingent on the submittal of a satisfactory monthly schedule update; however, the basis of payment will be the actual measurement of COTR-accepted, in-place units of work.

3.8 DELAYS AND REQUESTS FOR EXTENSION OF TIME

A. The determination for an extension of the Contract Time will be made by the Contracting Officer according to the Contract Provision "Default."

B. Contractor acknowledges and agrees that delays in activities, irrespective of the party causing the delay, which according to the computer mathematical analysis do not affect any critical activity or milestone dates on the CPM network at the time of the delay, shall not become the basis for an extension of the Contract Time. The only basis for any extension of time will be the demonstrated impact of an excusable delay on the critical path. In demonstrating such impact, Contractor shall provide adequate detail as required by the Contract, and Contractor shall prove that:

Page 56: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

CONSTRUCTION PROGRESS DOCUMENTATION 013200 - 8

1. An event occurred. 2. Contractor was not responsible for the event in that the event was beyond the control of

Contractor, and was without fault or negligence of Contractor, subcontractor, or supplier, and the event was unforeseeable.

3. The event was the type for which an excuse is granted according to the "Default" provision of this Contract.

4. Activities on the critical path of the Work were delayed. 5. The event in fact caused the delay of the Work. 6. The requested additional time is an appropriate and reasonable extension of the Contract

Time, given the actual delay encountered.

C. Time Extensions for Unusually Severe Weather:

1. If unusually severe weather conditions are the basis for a request for an extension of the Contract Time, such request shall be documented by data substantiating that weather conditions were abnormal for the period of time and could not have been reasonably anticipated, and that weather conditions had an adverse effect on the critical activities of the scheduled construction.

2. The schedule of anticipated adverse weather below will constitute the base line for monthly (or a prorated portion thereof) weather/time evaluation by the Contracting Officer. On issuance of the Notice to Proceed and continuing throughout the Contract on a monthly basis, actual adverse weather days will be recorded by Contractor on a calendar day basis (include weekends and holidays) and compared to the monthly anticipated adverse weather days set forth below.

a. For purposes of this clause, the term "actual adverse weather days" shall include days that can be demonstrated to have been impacted by adverse weather.

b. Monthly Anticipated Adverse Weather Calendar Days:

1) January - 7. 2) February - 5. 3) March - 6. 4) April - 6. 5) May - 8. 6) June - 6. 7) July - 6. 8) August - 7. 9) September - 5. 10) October - 5. 11) November - 5. 12) December - 6.

c. The number of actual adverse weather days shall be calculated chronologically from the first to the last day in each month. Contractor shall not be entitled to any claim for time extension based on adverse weather unless the number of actual adverse weather days exceeds the number of anticipated adverse weather days, and unless such adverse weather days prevent work for 50 percent or more of Contractor's workday. In preparing the Contract Schedule, Contractor shall reflect the above anticipated adverse weather days on all weather-dependent activities.

Page 57: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

CONSTRUCTION PROGRESS DOCUMENTATION 013200 - 9

Weather-caused delays shall not result in any additional compensation to Contractor.

3. On days where adverse weather is encountered, Contractor shall list all critical activities under progress and shall indicate the impact adverse weather had, if any, on the progress of such activities. This information shall be presented at the end of the adverse weather day to COTR or its authorized representative for its review and approval.

4. If Contractor is found eligible for an extension of the Contract Time, the Contracting Officer will issue a modification extending the time for Contract completion. The extension of time will be made on a calendar day basis.

D. Required Submittals:

1. Provide time-impact analysis that illustrates impact during update period in which event occurred, that event has been mitigated to greatest possible extent, and that event still impacts overall completion of Project.

2. Include with request, two copies of submittal of impacted schedule, in electronic format, and photocopies of all relevant documents that support the claim.

3. Submit all required items within the following time periods:

a. 10 calendar days of event occurrence. b. 10 calendar days of Contractor's knowledge of impact. c. 14 calendar days of written request by COTR.

4. Expiration of time periods without submittal shall constitute forfeiture of rights for these specific impacts.

3.9 RECORD SCHEDULE

A. After all Contract work items are complete, and as a condition of final payment, Contractor shall submit three copies of a Record, As-Built CPM Schedule showing actual start and finish dates for all work activities and milestones, based on the accepted monthly updates. These schedule submittals shall be in tabular and in time-scaled PDM plot formats.

END OF SECTION 013200

Page 58: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final
Page 59: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

PHOTOGRAPHIC DOCUMENTATION 013233 - 1

SECTION 013233 - PHOTOGRAPHIC DOCUMENTATION

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings, Contract Provisions, Special Provisions, Supplementary Conditions, and other Division 01 Specification Sections apply to this Section.

1.2 SUMMARY

A. This Section includes administrative and procedural requirements for the following:

1. Preconstruction photographs. 2. Periodic construction photographs. 3. Final Completion construction photographs.

B. Related Sections include the following:

1. Division 01 Section "Unit Prices" for procedures for unit prices for extra photographs. 2. Division 01 Section "Submittals" for submitting construction photographs. 3. Division 01 Section "Project Closeout" for submitting photographic negatives as Project

Record Documents at Project closeout.

1.3 UNIT PRICES

A. Basis for Proposals: Base number of construction photographs on twenty photographs per month over the duration of Project.

1.4 SUBMITTALS

A. Qualification Data: For firms and persons specified in "Quality Assurance" Article to demonstrate their capabilities and experience. Include lists of completed projects with project names and addresses, names and addresses of architects and owners, and other information specified.

B. Key Plan: Submit key plan of Project site and building including a detailed description of each project area with notation of vantage points marked for location and direction of each photograph. Indicate elevation or story of construction. Include the same label information as the corresponding set of photographs.

C. Construction Photographs: Submit four prints of each photographic view within five days of taking photographs.

Page 60: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

PHOTOGRAPHIC DOCUMENTATION 013233 - 2

1. Format: 8-by-10-inch smooth-surface matte prints on single-weight commercial-grade photographic paper mounted on card stock to allow a 1-inch-wide margin and enclosed back to back in clear plastic sleeves that are punched for standard 3-ring binder.

2. Identification: On back of each print, provide a computer generated applied label with the following information:

a. Name of Project. b. Name and address of photographer. c. Name of COTR. d. Name of Architect/Engineer. e. Name of Contractor. f. Date photograph was taken. g. Description of vantage point, indicating location, direction (by compass point), and

elevation or story of construction.

3. Negatives: Submit a complete set of photographic negatives in protective envelopes with each submittal of prints. Identify date photographs were taken.

1.5 QUALITY ASSURANCE

A. Photographer Qualifications:

1. Photographer: Individual of established reputation who has been regularly engaged as a professional construction photographer for not less than three years.

B. Costs: Include photographer's services in the Contract Price.

1.6 COORDINATION

A. Auxiliary Services: Cooperate with photographer. Provide auxiliary services requested, including access to Project site and use of temporary facilities including temporary lighting required to produce clear, well-lighted photographs without obscuring shadows.

1.7 USAGE RIGHTS

A. Obtain and transfer copyright usage rights from photographer to the Authority for unlimited reproduction of photographic documentation.

1.8 EXTRA PRINTS

A. Extra Prints: If requested by COTR, photographer shall prepare extra prints of photographs. Contractor will not be responsible for the cost of such additional prints.

Page 61: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

PHOTOGRAPHIC DOCUMENTATION 013233 - 3

PART 2 - PRODUCTS

2.1 PHOTOGRAPHIC MEDIA

A. Photographic Film: Manual Single Lens Reflex camera using 35 mm 100, 200 or 400 ISO color film. Do not use point and shoot cameras. Use lenses with focal length of either 50 mm or 55 mm.

B. Videotape Format: Digital mini-DV. Finished product shall be an authored DVD.

PART 3 - EXECUTION

3.1 PHOTOGRAPHS, GENERAL

A. Photographer: Engage a qualified commercial photographer to take construction photographs.

B. Date Stamp: Unless otherwise indicated, date and time stamp each photograph as it is being taken so stamp is integral to photograph.

C. Field Office Prints: Retain one set of prints of progress photographs in the field office at Project site, available at all times for reference. Identify photographs the same as for those submitted to COTR.

3.2 CONSTRUCTION PHOTOGRAPHS

A. Preconstruction Photographs: Before starting construction, take color photographs of Project site and surrounding properties from different vantage points, as directed by COTR.

1. Take four (4) photographs to show existing conditions adjacent to the project before starting the Work.

2. Take four (4) photographs of existing buildings either on or adjoining the project to accurately record the physical conditions at the start of construction.

B. Periodic Construction Photographs: Take a minimum of 10 color photographs monthly, coinciding with the cutoff date associated with each Application for Payment. The COTR will select vantage points to best show status of construction and progress since the last photographs were taken.

C. Time-Lapse-Sequence Construction Photographs: Take five (5) color photographs as indicated, to best show status of construction and progress since the last photographs were taken.

1. Frequency: Take photographs monthly, coinciding with the cutoff date associated with each Application for Payment.

2. Vantage Points: Following suggestions by COTR and Contractor, photographer shall select vantage points. During each of the following construction phases, take not less than two (2) of the required shots from the same vantage point each time to create a time-lapse sequence as follows:

Page 62: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

PHOTOGRAPHIC DOCUMENTATION 013233 - 4

a. Commencement of the Work, through completion of subgrade construction. b. Above-grade structural framing. c. Exterior building enclosure. d. Interior Work, through date of Substantial Completion.

D. Final Completion Construction Photographs: Take eight (8) color photographs after date of Substantial Completion for submission as Project Record Documents. COTR will direct photographer for desired vantage points.

1. Do not include date stamp.

E. Additional Photographs: COTR may issue requests for additional photographs, in addition to periodic photographs specified. Additional photographs will be paid for by Contract Modification and are not included in the Contract Price.

1. Photographer will be given three days notice, where feasible. 2. In emergency situations, photographer shall take additional photographs within 24 hours

of request. 3. Circumstances that could require additional photographs include, but are not limited to,

the following:

a. Special events planned at Project site. b. Immediate follow-up when on-site events result in construction damage or losses. c. Photographs to be taken at fabrication locations away from Project site. These

photographs are not subject to unit prices or unit-cost allowances. d. Substantial Completion of a major phase or component of the Work. e. Extra record photographs at time of final acceptance. f. COTR's request for special publicity photographs.

END OF SECTION 013233

Page 63: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

SUBMITTALS 013300 - 1

SECTION 013300 - SUBMITTALS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings, Contract Provisions, Special Provisions, Supplementary Conditions, and other Division 01 Specification Sections apply to this Section.

1.2 SUMMARY

A. This Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other miscellaneous submittals.

B. Related Sections include the following: 1. Division 01 Section "Project Closeout" for submitting warranties. 2. Division 01 Section "Project Record Documents" for submitting Record Drawings,

Record Specifications, and Record Product Data. 3. Divisions 02 through 33 Sections for specific requirements for submittals in those

Sections.

1.3 DEFINITIONS

A. Action Submittals: Written and graphic information that requires COTR's responsive action.

B. Informational Submittals: Written information that does not require COTR's approval. Submittals may be rejected for not complying with requirements.

1.4 SUBMITTAL PROCEDURES

A. General: COTR will provide electronic copies of CADD electronic files of the drawings for Contractor's use in preparing submittals.

B. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.

1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that requires sequential activity.

2. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.

a. Without change to the Contract Duration, COTR reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.

Page 64: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

SUBMITTALS 013300 - 2

C. Submittals Schedule: Comply with requirements in Division 01 Section "Construction Progress Documentation" for list of submittals and time requirements for scheduled performance of related construction activities.

D. Contractor's Responsibilities: Contractor is responsible for the scheduling and submission of all submittals. Submit to COTR all required Submittals. The COTR will forward submittals to the appropriate parties for review.

E. Processing Time: Allow enough time for submittal review, including time for re-submittals, as follows. Time for review shall commence on COTR’s receipt of submittal. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including re-submittals.

1. Initial Review: Allow 15 calendar days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required. COTR will advise Contractor when a submittal processed must be delayed for coordination. Allow an additional 45 calendar days for submittals related to fire-protection systems.

2. Intermediate Review: If intermediate submittal is necessary, process it in same manner as initial submittal.

3. Re-submittal Review: Allow 15 calendar days for review of each re-submittal. 4. No extension of the Contract Time will be authorized because of failure to transmit

submittals to COTR enough in advance of the Work to permit processing. Processing of incomplete or unacceptable submissions by COTR shall not reduce the number of calendar days specified above for COTR's review. Resubmissions shall be treated the same as initial submissions relative to review time.

5. Notations on submittals that increase the Contract cost or time of completion shall be brought to COTR's attention before proceeding with the Work.

F. Identification: Place a permanent label or title block on each submittal for identification.

1. Indicate name of firm or entity that prepared each submittal on label or title block. 2. Provide a space approximately 6 by 8 inches on label or beside title block to record

Contractor's review and approval markings and action taken by COTR and Architect. 3. Include the following information on label for processing and recording action taken:

a. Contract name and number. b. Date. c. Name and address of Architect/Engineer. d. Name and address of Contractor. e. Name and address of subcontractor, if applicable. f. Name and address of supplier, if applicable. g. Name of manufacturer, if applicable. h. Submittal number or other unique identifier, including revision identifier.

1) Submittal number shall use Specification Section number followed by a decimal point and then a sequential number (e.g., 06 10 00.01). Re-submittals shall include an alphabetic suffix after another decimal point (e.g., 06 10 00.01.A).

Page 65: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

SUBMITTALS 013300 - 3

i. Alphanumeric project Identifier. Identifier is shown on the Project Drawings cover sheet.

j. Number and title of appropriate Specification Section. k. Drawing number and detail references, as appropriate. l. Location(s) where product is to be installed, as appropriate. m. Transmittal number. n. Allow 15 calendar days for processing each re-submittal.

G. Resubmissions: Re-submittal procedure shall follow the same procedures and same number as the initial submittal with the following exceptions:

1. Transmittal shall contain the same information as the first transmittal and the submission number shall indicate second, third, etc., submission. The drawing number/description shall be identical to the initial submission and the date shall be the revised date for that submission.

2. No new material shall be included on the same transmittal for a resubmission. 3. COTR rejection shall not warrant a claim by Contractor for additional time or cost.

H. Deviations: Highlight, encircle, or otherwise specifically identify deviations from the Contract Documents on submittals. Where significant deviations from the Contract requirements exist, follow the guidelines set forth in Division 01 Section "Product Requirements" for substitutions.

I. Additional Copies: Unless additional copies are required for final submittal, and unless COTR observes noncompliance with provisions of the Contract Documents, initial submittal may serve as final submittal.

1. Additional copies submitted for Operations and Maintenance manuals will be marked with action taken and will be returned.

J. Transmittal: Package each submittal individually and appropriately for transmittal and handling. Transmit each submittal from Contractor to COTR using the approved transmittal form provided by COTR. COTR will return submittals, without review, received from sources other than Contractor.

1. Transmittal Form: Use transmittal forms and follow other submittal procedures according to information provided to Contractor at the preconstruction meeting.

K. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, and authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms.

1. Bear all costs incurred for such reproduction and distribution. Prints of all reviewed Shop Drawings may be made from transparencies that carry the appropriate review stamps.

L. Use for Construction: Use only final submittals with mark indicating “approved” by COTR in connection with construction.

1.5 SUBMITTAL LOG

Page 66: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

SUBMITTALS 013300 - 4

A. Prepare a log that contains a complete listing of all submittals required by Contract. Submit the log at the preconstruction meeting along with Contractor's construction schedule specified in Division 01 Section "Construction Progress Documentation." Organize the submittal log by Section number. Assign each submittal a sequential number for identification and tracking purposes.

1. Coordinate the submittal log with Division 01 Section "Construction Progress Documentation." The submittal log shall be submitted for COTR's review. Include the following information:

a. Title of submittal/description. b. Submittal number (sequential). c. Scheduled date for the first submittal. d. Drawing number, if applicable. e. Applicable Section number. f. Name of subcontractor/vendor. g. Scheduled date of COTR's final release or approval.

PART 2 - PRODUCTS

2.1 ACTION SUBMITTALS

A. General: Prepare and submit Action Submittals required by individual Specification Sections

B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.

1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data.

2. Mark each copy of each submittal to show which products and options are applicable. 3. Include the following information, as applicable:

a. Manufacturer's written recommendations. b. Manufacturer's product specifications. c. Manufacturer's installation instructions. d. Standard color charts. e. Manufacturer's catalog cuts. f. Wiring diagrams showing factory-installed wiring. g. Printed performance curves. h. Operational range diagrams. i. Mill reports. j. Standard product operating and maintenance manuals. k. Compliance with recognized trade association standards. l. Compliance with recognized testing agency standards. m. Application of testing agency labels and seals. n. Notation of coordination requirements.

4. Submit Product Data before or concurrent with Samples.

Page 67: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

SUBMITTALS 013300 - 5

5. Number of Copies: Submit six copies, in addition to the number of copies to be returned to Contractor. Provide one additional copy for submittals related to fire-protection system.

6. Do not submit Product Data until compliance with requirements of the Contract Documents has been confirmed.

C. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.

1. Preparation: Include the following information, as applicable:

a. Dimensions. b. Identification of products. c. Fabrication and installation drawings. d. Roughing-in and setting diagrams. e. Wiring diagrams showing field-installed wiring, including power, signal, and

control wiring. Differentiate between manufacturer-installed and field-installed wiring.

f. Shopwork manufacturing instructions. g. Templates and patterns. h. Schedules. i. Design calculations. j. Compliance with specified standards. k. Notation of coordination requirements. l. Notation of dimensions established by field measurement. m. Relationship to adjoining construction clearly indicated. n. Seal and signature of professional engineer if specified.

2. Sheet Size: Except for templates, patterns, and similar full-size drawings, submit Shop Drawings on sheets at least 8-1/2 by 11 inches but no larger than 30 by 40 inches.

3. Number of Copies: Submit one reproducible transparency and two black-line prints of each submittal. Provide one additional black-line print for items related to fire-protection systems. COTR will return the marked up reproducible transparency for Contractor’s distribution.

a. Both the reproducible transparency and the prints shall bear Contractor's approval stamp on each sheet.

D. Coordination Drawings:

1. Coordination Drawings are Shop Drawings prepared by Contractor that detail the relationship and integration of different construction elements that require careful coordination during fabrication or installation. Preparation of Coordination Drawings is specified in Division 01 Section "Project Management and Coordination."

2. Submit Coordination Drawings for integration of different construction elements. Show sequences and relationships of separate components to avoid conflicts in use of space.

E. Samples: Submit Samples for review of kind, color, pattern, and texture for a check of these characteristics with other elements and for a comparison of these characteristics between submittal and actual component as delivered and installed.

Page 68: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

SUBMITTALS 013300 - 6

1. Transmit Samples that contain multiple, related components such as accessories together in one submittal package.

2. Identification: Attach label on unexposed side of Samples that includes the following:

a. Generic description of Sample. b. Product name and name of manufacturer. c. Sample source. d. Number and title of appropriate Specification Section.

3. Disposition: Maintain sets of approved Samples at Project site, available for quality-control comparisons throughout the course of construction activity. Sample sets may be used to determine final acceptance of construction associated with each set. a. Samples not incorporated into the Work, or otherwise designated as the

Authority’s property, are the property of Contractor.

F. Product Schedule or List: As required in individual Specification Sections, prepare a written summary indicating types of products required for the Work and their intended location. Include the following information in tabular form:

1. Type of product. Include unique identifier for each product. 2. Number and name of room or space. 3. Location within room or space. 4. Number of Copies: Submit three copies of product schedule or list, unless otherwise

indicated. COTR will return two copies.

a. Mark up and retain one returned copy as a Project Record Document.

G. Submittals Schedule: Comply with requirements in Division 01 Section "Construction Progress Documentation."

H. Application for Payment: Comply with requirements in Division 01 Section "Application for Payment."

I. Schedule of Values: Comply with requirements in Division 01 Section "Application for Payment."

J. Subcontract List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design. Include the following information in tabular form:

1. Name, address, and telephone number of entity performing subcontract or supplying products.

2. Number and title of related Specification Section(s) covered by subcontract. 3. Drawing number and detail references, as appropriate, covered by subcontract.

K. Contractor Warranty Letter: Comply with requirements in Contract Provision "Warranty of Construction." Provide the dates of warranty coverage and provide point of contact information for warranty service.

Page 69: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

SUBMITTALS 013300 - 7

L. Special Warranty Letters: Provide dates of warranty coverage and provide point of contact information for warranty service for special warranties required in Division 02 through 33 Sections.

2.2 INFORMATIONAL SUBMITTALS

A. General: Prepare and submit Informational Submittals required by other Specification Sections.

1. Number of Copies: Submit four copies of each submittal, unless otherwise indicated. COTR will not return copies.

2. Certificates and Certifications: Provide a notarized statement that includes signature of entity responsible for preparing certification. An officer shall sign certificates and certifications or other individual authorized to sign documents on behalf of that entity.

3. Test and Inspection Reports: Comply with requirements in Division 01 Section "Quality Requirements."

B. Contractor's Construction Schedule: Comply with requirements in Division 01 Section "Construction Progress Documentation."

C. Qualification Data: Prepare written information that demonstrates capabilities and experience of firm or person. Include lists of completed projects with project names and addresses, names and addresses of Architects and Owners, and other information specified.

D. Product Certificates: Prepare written statements on manufacturer's letterhead certifying that product complies with requirements.

E. Welding Certificates: Prepare written certification that welding procedures and personnel comply with requirements. Submit record of Welding Procedure Specification (WPS) and Procedure Qualification Record (PQR) on AWS forms. Include names of firms and personnel certified.

F. Installer Certificates: Prepare written statements on manufacturer's letterhead certifying that Installer complies with requirements and, where required, is authorized for this specific Project.

G. Manufacturer Certificates: Prepare written statements on manufacturer's letterhead certifying that manufacturer complies with requirements. Include evidence of manufacturing experience where required.

H. Material Certificates: Prepare written statements on manufacturer's letterhead certifying that material complies with requirements.

I. Material Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements.

J. Preconstruction Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of tests performed before installation of product, for compliance with performance requirements.

Page 70: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

SUBMITTALS 013300 - 8

K. Compatibility Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of compatibility tests performed before installation of product. Include written recommendations for primers and substrate preparation needed for adhesion.

L. Field Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements.

M. Product Test Reports: Prepare written reports indicating current product produced by manufacturer complies with requirements. Base reports on evaluation of tests performed by manufacturer and witnessed by a qualified testing agency, or on comprehensive tests performed by a qualified testing agency.

N. Research/Evaluation Reports: Prepare written evidence from a model code organization acceptable to the Authority that product complies with USBC. Include the following information:

1. Name of evaluation organization. 2. Date of evaluation. 3. Time period when report is in effect. 4. Product and manufacturers' names. 5. Description of product. 6. Test procedures and results. 7. Limitations of use.

O. Maintenance Data: Prepare written and graphic instructions and procedures for operation and normal maintenance of products and equipment. Comply with requirements in Division 01 Section "Operation and Maintenance Data."

P. Design Data: Prepare written and graphic information, including, but are not limited to, performance and design criteria, list of applicable codes and regulations, and calculations. Include list of assumptions and other performance and design criteria and a summary of loads. Include load diagrams if applicable. Provide name and version of software, if any, used for calculations. Include page numbers.

Q. Manufacturer's Instructions: Prepare written or published information that documents manufacturer's recommendations, guidelines, and procedures for installing or operating a product or equipment. Include name of product and name, address, and telephone number of manufacturer. Include the following, as applicable:

1. Preparation of substrates. 2. Required substrate tolerances. 3. Sequence of installation or erection. 4. Required installation tolerances. 5. Required adjustments. 6. Recommendations for cleaning and protection.

Page 71: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

SUBMITTALS 013300 - 9

R. Manufacturer's Field Reports: Prepare written information documenting factory-authorized service representative's tests and inspections. Include the following, as applicable:

1. Name, address, and telephone number of factory-authorized service representative making report.

2. Statement on condition of substrates and their acceptability for installation of product. 3. Statement that products at Project site comply with requirements. 4. Summary of installation procedures being followed, whether they comply with

requirements and, if not, what corrective action was taken. 5. Results of operational and other tests and a statement of whether observed performance

complies with requirements. 6. Statement on whether conditions, products, and installation will affect warranty. 7. Other required items indicated in individual Specification Sections.

S. Bonds: Prepare written information indicating current status of bonding coverage. Include name of entity covered by insurance or bond, limits of the coverage, amounts of deductibles, if any and term of coverage.

T. Manufacturers' warranties.

U. Construction Photographs : Comply with requirements in Division 01 Section "Photographic Documentation."

V. Material Safety Data Sheets: Submit information directly to COTR.

2.3 DELEGATED DESIGN

A. Performance and Design Criteria: Where professional design services or certifications by a design professional are specifically required of Contractor by the Contract Documents, provide products and systems complying with specific performance and design criteria indicated.

1. If criteria indicated are not sufficient to perform services or certification required, submit a written request for additional information to COTR.

B. Delegated-Design Submittal: In addition to Shop Drawings, Product Data, and other required submittals, submit three (3) copies of a statement, signed and sealed by the responsible design professional, for each product and system specifically assigned to Contractor to be designed or certified by a design professional.

1. Indicate that products and systems comply with performance and design criteria in the Contract Documents. Include list of codes, loads, and other factors used in performing these services.

PART 3 - EXECUTION

3.1 CONTRACTOR'S REVIEW

Page 72: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

SUBMITTALS 013300 - 10

A. Review each submittal and check for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to COTR.

1. In checking Shop Drawings and Product Data, verify all dimensions and field conditions and check and coordinate Shop Drawings and Product Data of any Section or trade with the requirements of other sections or trades as related thereto, as required for proper and complete installation of the Work.

B. Approval Stamp: Stamp each submittal with a uniform, approval stamp. Include Project name and location, submittal number, Section title and number, name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents, which shall include dimensions, clearances, compatibility, and coordination with Shop Drawings and Product Data submitted for other work.

C. If Contractor has not checked the submittals carefully, even though stamped as checked and approved, submittals shall be returned to Contractor for proper checking before further processing or review by COTR regardless of any urgency claimed by Contractor. In such a situation, Contractor will be responsible for any resulting delays to the scheduled Contract completion. Furthermore, Contracting Officer may hold Contractor responsible for increased Authority costs resulting from Contractor's failure to comply with the requirements set forth herein.

3.2 COTR’S ACTION

A. General: COTR will not review submittals that do not bear Contractor's approval stamp and will return them without action.

B. COTR Responsibilities: The review of Shop Drawings and other submittals by COTR will be for general conformance with the Contract only, and the review shall not be interpreted as a checking of detailed dimensions, quantities, or approval of deviations from the Contract Documents. COTR review shall not relieve Contractor of its responsibility for accuracy of Shop Drawings nor for the furnishing and installation of materials or equipment according to the Contract requirements.

1. Approval of Shop Drawings or other submittals is not to be interpreted as approval of a substitute material. Approval of substitutions will be accomplished according to requirements set forth in Division 01 Section "Product Requirements."

C. Action Submittals: COTR will review each submittal, make marks to indicate corrections or modifications required, and return it. COTR will stamp each submittal with an action stamp and will mark stamp appropriately to indicate action taken, as follows. Do not permit submittals marked "Revise and Resubmit" or "Rejected" to be used at Project site, or elsewhere where Work is in progress.

1. Approved: Means fabrication/installation may be undertaken. Approval does not authorize changes to the Contract Price or the Contract Time.

Page 73: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

SUBMITTALS 013300 - 11

2. Approved as Corrected: Same as "Approved," providing Contractor complies with corrections noted on submittal. Resubmission required only if Contractor is unable to comply with noted corrections.

3. Revise and Resubmit: Fabrication and/or installation may not be undertaken. Make appropriate revisions and resubmit, limiting corrections to items marked.

4. Rejected: Submittal does not comply with requirements. Fabrication and/or installation may not be undertaken. Prepare a new submittal according to requirements and submit without delay.

D. Informational Submittals: COTR will review each submittal and will not return it, or will reject and return it, if it does not comply with requirements. COTR will forward each submittal to appropriate party.

E. Partial submittals are not acceptable, will be considered non-responsive, and will be returned without review.

F. Submittals not required by the Contract Documents will not be reviewed and may be discarded.

END OF SECTION 013300

Page 74: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final
Page 75: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

QUALITY REQUIREMENTS 014000 - 1

SECTION 014000 - QUALITY REQUIREMENTS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and Contract Provisions, Special Provisions, Supplementary Conditions, and other Division 01 Specification Sections apply to this Section.

B. Related Sections:

1. Division 01 Section “Submittals” for process required to submit the Contractor’s Quality Control Plan.

2. Division 01 Section “Construction Progress Documentation” for developing a schedule of required tests and inspections.

3. Division 01 “Project Management and Coordination” 4. Division 01 Section “Project Closeout” 5. Divisions 02 through 33 Sections for specific test and inspection requirements.

1.2 SUMMARY

A. This Section includes the following:

1. Administrative and procedural requirements for Contractor to provide and maintain an effective Quality-Control Program that complies with this Section and with requirements of the "Contract Provisions," Section VII, "Inspection of Construction and Final Inspection and Acceptance."

2. Establish a QC Program that consists of the following:

a. QC Organization b. QC Plan c. QC Plan Meeting d. Coordination and Mutual Understanding Meeting e. QC meetings f. Phases of Control g. Submittal review and approval h. Operation & Maintenance data and Warranty receipt verification prior to product

delivery i. Material verification at delivery j. Testing, completion inspections, and QC certifications and documentation

necessary to provide materials, equipment, workmanship, fabrication, construction and operations that comply with the requirements of this Contract.

3. Contractor is not responsible for Special Inspections according to requirements of the current Virginia Uniform Statewide Building Code (USBC). The Authority’s agent shall provide these Special Inspection services. Special Inspections coordination should be

Page 76: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

QUALITY REQUIREMENTS 014000 - 2

discussed at weekly progress meetings and scheduled dates for Special Inspections carried on the two-week look ahead. Contractor shall be responsible for coordination of and notification to the Authority for the following Special Inspections.

a. Special inspections are required for, but are not necessarily limited to, the following:

1) Concrete construction.

4. Specific quality-control requirements for individual construction activities are specified in the Sections that require those activities. Requirements in those Sections may also cover production of standard products.

5. Schedule of Values: Contractor shall include all test and inspection activities in its CPM and establish a Schedule of Values for all quality test and inspection activities; and all required reports, and procedures required in the Contract on a Section-by-Section basis. Additionally, Contractor shall include a pay line item specifically for CQC activities and QCM position(s) required by the General Conditions. CQC activities shall be reported per Division 01 Section "Applications for Payment."

6. Testing and inspecting services are required to verify compliance with requirements specified or indicated. These services do not relieve Contractor of its responsibilities for compliance with the Contract Document requirements.

7. Specified tests, inspections, and related actions do not limit Contractor's quality-control procedures that facilitate compliance with the Contract Document requirements.

8. The provisions of this Section shall not limit requirements for Contractor to provide quality-control services required by the Authority or other agencies having jurisdiction.

1.3 REFERENCES

A. The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.

1. AMERICAN SOCIETY FOR TESTING AND MATERIALS (ASTM)

a. ASTM C 1077 Laboratories Testing Concrete and Concrete Aggregates for Use

in Construction and Criteria for Laboratory Evaluation latest edition. b. ASTM D 3666 Minimum Requirements for Agencies Testing and Inspecting

Road and Paving Materials latest edition. c. ASTM D 3740 Minimum Requirements for Agencies Engaged in the Testing

and/or Inspection of Soil and Rock as Used in Engineering Design and Construction latest edition.

d. ASTM E 329 Agencies engaged in the Testing and/or Inspection of Materials Used in Construction latest edition. ASTM E 543 Agencies Performing Nondestructive Testing latest edition.

e. ASTM E 543 Agencies performing Nondestructive Testing latest edition.

Page 77: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

QUALITY REQUIREMENTS 014000 - 3

2. METROPOLITAN WASHINGTON AIRPORT AUTHORITY

a. Construction Safety Manual, most current edition

1.4 DEFINITIONS

A. Quality: Conformance to the requirements established by the contract specifications and drawings.

B. Control: To guide and have influence over.

C. Contractor Quality Control (CQC): The construction contractor’s system to manage, control, and document their own, their supplier’s, and their subcontractor’s activities to comply with the contract requirements.

D. Contracting Officers Technical Representative (COTR). Primary on-site representative of the Contracting Officer for technical matters. Duties and responsibilities of the COTR will be transmitted to the contractor via letter from the Contracting Officer.

E. Quality-Assurance Services: Activities, actions, and procedures performed by the Authority before and during execution of the Work to guard against defects and deficiencies and substantiate that proposed construction will comply with requirement. Additionally, the Authority fulfills its responsibility to be certain that the CQC is functioning and the specified end product is achieved.

F. Definable Feature of Work: A definable feature of work (DFOW) is a task, which is separate and distinct from other tasks, has the same control requirements and work crews.

G. Experienced: When used with an entity, “experienced” means having successfully completed a minimum of 10 projects similar in size and scope to this Project; being familiar with special requirements indicated; and having complied with requirements of authorities having jurisdiction. Specific experience requirements enumerated in these specifications supersede this requirement.

1.5 CONFLICTING REQUIREMENTS

A. General: If compliance with two standards is specified and the standards establish different or conflicting requirements for minimum quantities or quality levels, comply with the most stringent requirement. Refer uncertainties and requirements that are different, but apparently equal, to the COTR for a decision before proceeding. This paragraph refers to industry and government standards. In case of a difference between drawings and the specifications, the specifications shall govern.

1.6 SUBMITTALS

A. Submit the following in accordance with Division 01 Section, "Submittals."

1. Action Submittals.

Page 78: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

QUALITY REQUIREMENTS 014000 - 4

a. Quality Control (QC) Plan.

B. NOTE: Coordinate the submittal requirement dates with the submittal dates in Division 01 Section “Construction Progress Documentation”.

C. Submit a QC plan within 20 calendar days after receipt of Notice to Proceed. The QC Plan shall include a preliminary submittal of the list of definable features of work that shall cover the first 90 calendar days of construction.

1. Submit at this time résumés of key personnel to be assigned to this contract and the limits of their authority. Show how this project management structure fits into the Contractor’s corporate management structure.

D. Any approval by the COTR of the QC Plan shall be treated as “accepted, predicated upon successful implementation.” Stop work if the QC Plan becomes disapproved. The exception is the work authorized in the paragraph entitled "Preliminary Work Authorized Prior to Approval," shall stop.

1.7 INFORMATION FOR THE CONTRACTING OFFICER

A. Provide a sample copy set of report forms to the Contracting Officer during the Pre-Construction Conference. The report forms shall consist of the Quality Control Daily Report, Preparatory Phase Report, Initial Phase Report, and Project Quality Control Monthly Summary. These forms may be edited to support the project. Other reports referenced below may be in formats customarily used by the Contractor, Testing Laboratories, etc. and shall contain the information required by this specification.

B. Deliver the following listed items to the COTR at the times specified:

1. Quality Control Daily Report: Original and 6 copies, by 12:00 noon the next working day after each day that work is performed.

2. Superintendent’s Daily Report: Original and 6, by 12:00 noon the next working day after each day that work is performed, attached to the Quality Control Daily Report.

3. Material Receiving Inspection Report: Original and 6 copies, by 12:00 noon the next working day after each day that work is performed, attached to the Quality Control Daily Report.

4. Preparatory Phase Report: Original attached to the original Quality Control Daily Report and 1 copy attached to each copy of the Quality Control Daily Report.

5. Initial Phase Report: Original attached to the original Quality Control Daily Report and 1 copy attached to each copy of the Quality Control Daily Report.

6. Field Test Reports: 2 copies, within 2 working days after the test is performed, do not attach to the Quality Control Daily Report.

7. Monthly Summary Report of Tests: 2 copies, do not attach to a Quality Control Daily Report.

8. Project Quality Control Monthly Summary Report: 2 copies, do not attach to a Quality Control Daily Report.

9. Inspection Log and Signoff Sheets: one copy, submitted daily within 1 day of the inspection.

10. Testing Plan and Log: 2 copies, submitted within 2 working days of the end of the month. 11. Deficiency List: 2 copies, submitted to the COTR weekly. 12. Monthly Deficiency Report: 2 copies within two working days of the end of the month.

Page 79: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

QUALITY REQUIREMENTS 014000 - 5

13. QC Meeting Minutes: 2 copies, within 2 working days after the meeting. 14. QC Certifications: As required by paragraph entitled "QC Certifications."

1.8 QC PROGRAM REQUIREMENTS

A. Establish and maintain a QC Program as described in this Section. The QC Program consists of but is not limited to the following:

1. QC Organization. 2. QC Plan. 3. QC Plan Meeting. 4. Coordination and Mutual Understanding Meeting 5. QC meetings. 6. Phases of Control. 7. Submittal review and approval. 8. Operations and Maintenance data. 9. Warranty receipt verification prior to product delivery. 10. Material verification at delivery. 11. Testing. 12. Completion inspections. 13. QC certifications and documentation necessary to provide materials, equipment,

workmanship, fabrication, construction and operations that comply with the requirements of this Contract.

14. The QC Program shall cover on-site and off-site work and shall be keyed to the work sequence.

15. No work or testing may be performed unless the QCM or a pre-approved alternate is on the work site.

16. The QCM shall report to an officer of the firm and shall not be subordinate to the Project Superintendent or the Project Manager.

17. Quality Control Manager is the primary individual responsible for quality control. The QCM, Project Superintendent and Project Manager shall be responsible for the quality of work on the job. Project Superintendent shall be held responsible for the quality of production.

B. Preliminary Work Authorized Prior to Approval

1. The only work that is authorized to proceed prior to the approval of the QC Plan is mobilization of storage and office trailers, temporary utilities, and surveying.

C. Approval

1. Approval of the QC Plan is required prior to the start of any construction. The Contracting Officer reserves the right to require changes in the QC Plan and operations as necessary, including but not limited to removal of personnel, to ensure the specified quality of work. The Contracting Officer reserves the right to interview any member of the QC organization at any time in order to verify the submitted qualifications. All QC organization personnel shall be subject to acceptance by the Contracting Officer. The Contracting Officer may require the removal of any individual for non-compliance with quality requirements specified in the contract.

Page 80: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

QUALITY REQUIREMENTS 014000 - 6

D. Notification of Changes

1. Notify the COTR, in writing, of any proposed change, including changes in the QC organization personnel, a minimum of seven calendar days prior to a proposed change. Proposed changes shall be subject to acceptance by the Contracting Officer.

1.9 QC ORGANIZATION

A. Staffing Levels: Provide sufficient qualified quality-control personnel to monitor each work activity at all times. Scheduling and coordinating of all inspections and testing shall match the type and pace of work activity.

1. In cases where multiple trades, disciplines, or subcontractors are on site at same time, each activity shall be tested and inspected by personnel skilled in that portion of the work.

2. In cases where multiple shifts are employed, the quality-control staff shall be increased as required to monitor the work on each shift.

B. The following positions are key personnel as defined by the Authority in this and other Division 01 Specification Sections.

1. Project Manager

a. To enhance the effectiveness of the Quality Control Organization Project Manager shall be intimately involved in Quality Control. To this end, the Project manager shall have successfully completed the Army Corps of Engineers/NAVFAC Contractor Quality Control Course (details in Paragraph “Construction Quality Management Training” below).

2. Project Superintendent

a. Qualifications: Fifteen years of experience, with five years experience in a supervisory role coordinating various trades at multiple work areas.

3. Quality Control Manager (QCM)

a. Duties

1) Provide a QCM at the work site to implement and manage the QC Program. In addition to implementing and managing the QC Program, the QCM may perform the duties of project superintendent. The QCM is required to attend the QC Plan Meeting, attend the Coordination and Mutual Understanding Meeting, conduct the QC meetings, perform the Phases Control, perform submittal review and approval, ensure testing is performed and provide QC certifications and documentation required in this contract. The QCM is responsible for managing and coordinating the Phases Control and documentation performed by Testing Laboratory personnel and any other inspection and testing personnel required by this Contract.

b. Qualifications

Page 81: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

QUALITY REQUIREMENTS 014000 - 7

1) An individual with a minimum of 5 years experience as a superintendent, inspector, QCM, project manager, project engineer or construction manager on similar size and type construction contracts which included the major trades that are part of this Contract. The individual shall be familiar with the requirements of the Construction Safety Manual, and have experience in the areas of hazard identification and safety compliance. The QCM shall be interviewed and approved by COTR.

c. Construction Quality Management Training

1) In addition to the above experience and education requirements, the QCM shall have completed the course entitled "Construction Quality Management for Contractors." If the QCM does not have a current certification, they shall obtain the CQM course certification within 60 - calendar days of award. This short course is periodically offered in alternate months by: (1) the Maryland Chapter, Associated General Contractors (AGC), 410-321-7870; [email protected] and by (2) the Virginia Chapter, Associated Builders and Contractors (ABC), 703-968-6205, [email protected]; [email protected]. The training uses Army Corps of Engineers course content. The course is facilitated by instructors from Army Corps of Engineers, North Atlantic Division, Baltimore District, and by instructors from the Naval Facilities Engineering Command, Engineering Field Activity Chesapeake.

4. Alternate QCM Duties and Qualifications

a. Designate an alternate for the QCM at the work site to serve in the event of the designated QCM's absence. The period of absence may not exceed two weeks at one time, and not more than 30 workdays during a calendar year. The qualification requirements for the Alternate QCM shall be the same as for the QCM.

5. Erosion and Sediment Control Inspector

a. The Erosion and Sediment Control Inspector shall be responsible for inspecting the erosion and sediment controls, reporting requirements, and for ensuring conformance with the approved Storm Water Pollution Prevention Plan (SPPP). The Erosion and Sediment Control Inspector may have other duties, however, the designated individual shall be familiar with the requirements set forth in the Virginia Erosion and Sediment Control Handbook.

6. Project Engineer/Scheduler

a. Qualifications: Refer to Division 01 Section “Construction Progress Documentation”.

7. Professional Land Surveyor

a. Qualifications: Registered Professional Land Surveyor licensed to practice in the Commonwealth of Virginia.

Page 82: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

QUALITY REQUIREMENTS 014000 - 8

1.10 QC PLAN MEETING

A. Within 10 calendar days of notice of award and prior to submission of the QC plan, meet with the COTR to discuss the QC plan requirements of this Contract. The purpose of this meeting is to communicate expectations and facilitate understanding of the QC plan requirements prior to plan development and submission.

1.11 QUALITY CONTROL (QC) PLAN

A. Provide, for approval by the COTR, a QC plan submitted in a 3-ring binder with pages numbered sequentially that covers both on-site and off-site work and includes but may not necessarily be limited to the following:

B. A table of contents listing the major sections identified with tabs in the following order:

1. QC ORGANIZATION 2. PERSONNEL MATRIX 3. NAMES AND QUALIFICATIONS 4. DUTIES, RESPONSIBILITY AND AUTHORITY OF QC PERSONNEL 5. APPOINTMENT LETTERS 6. OUTSIDE ORGANIZATIONS INCLUDING BOCA INSPECTION COMPANIES 7. TESTING LABORATORY INFORMATION AND CERTIFICATIONS 8. TESTING PLAN AND LOG 9. SUBMITTAL PROCEDURES AND INITIAL SUBMITTAL REGISTER 10. LIST OF DEFINABLE FEATURES 11. PROCEDURES FOR PERFORMING THE PHASES OF CONTROL 12. SPECIAL INSPECTIONS 13. DOCUMENTATION PROCEDURES 14. PROCEDURES TO COMPLETE REWORK ITEMS 15. PROCEDURES FOR COMPLETION INSPECTION 16. FORMS 17. ATTACHMENTS

C. A chart showing the QC organizational structure.

D. A personnel matrix showing for each Section of the specification who shall review and approve submittals, who shall perform and document the Phases Control, and who shall perform and document the testing.

E. Names and qualifications, in résumé format, for each person in the QC organization. Include the CQM course certifications for the QCM and Alternate QCM as required by the paragraphs entitled "Construction Quality Management Training" and "Alternate QCM Duties and Qualifications".

F. Duties, responsibilities and authority of each person in the QC organization.

G. Letters signed by an officer of the firm appointing the QCM and Alternate QCM and stating that they are responsible for implementing and managing the QC Program as described in this contract. Include in this letter the responsibility of the QCM and Alternate QCM to implement

Page 83: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

QUALITY REQUIREMENTS 014000 - 9

and manage the three phases of quality control, and their authority to stop work that is not in compliance with the contract. The QCM shall issue letters of direction to

H. A listing of outside organizations such as, architectural and consulting engineering firms that will be employed by the Contractor and a description of the services these firms will provide.

I. Testing laboratory information required by the paragraphs entitled "Accreditation Requirements" or "Construction Materials Testing Laboratory Requirements", as applicable.

J. A Testing Plan and Log that includes the tests required, referenced by the specification paragraph number requiring the test, the frequency, the desired results and the person responsible for each test and shall be identified as a scheduled (CPM) activity.

K. Procedures for reviewing, approving and managing submittals. Provide the name(s) of the person(s) in the QC organization authorized to review and certify submittals prior to approval. Provide the initial submittal of the Submittal Register as specified in Section entitled "Submittals."

L. List of definable features of work. The list shall be cross-referenced to the contractor's Construction Schedule and the specification sections. For projects requiring a Progress Chart, the list of definable features of work shall include but not be limited to all items of work on the schedule. For projects requiring a Network Analysis Schedule, the list of definable features of work shall include but not be limited to all critical path activities. Include a chart of common deficiencies for the Definable Feature of work. Detail the control procedures that shall be employed to eliminate this common deficiency.

M. Procedures for Performing the Phases of Control. The contractor shall develop a plan for incorporating each of the control phases into the work. The plan shall detail who shall be responsible for scheduling the phases, conducting the phase as well as documenting the phase. The use of project specific forms may be helpful. However, the entire plans and specifications establish the quality and not just the checklists. The Preparatory and Initial Phases and meetings shall be conducted with a view towards obtaining quality construction by planning ahead and identifying potential problems for each definable feature of work.

N. Include all activities for which this specification requires QC specialists or Specialty Inspection Personnel, and for any specific definable features of work as identified in the QC Plan.

O. Documentation procedures, including proposed report formats.

P. Procedures to identify, record, track and complete rework items.

Q. Procedures for Identifying and Documenting the Completion Inspection process. Include in these procedures the responsible party for punch out inspection, pre-final inspection, and final acceptance inspection.

R. A complete set of report forms to be utilized on this project.

S. All applicable subcontractors and suppliers Quality Control Plans complete with Contactor’s CQC planned involvement.

Page 84: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

QUALITY REQUIREMENTS 014000 - 10

1.12 COORDINATION AND MUTUAL UNDERSTANDING MEETING

A. After submission of the QC Plan, and prior to the start of any physical construction, meet with the COTR to present the QC Program required by this Contract. The purpose of this meeting is to develop a mutual understanding of the QC details, including documentation, administration for on-site and off-site work, and the coordination of the Contractor's management, production and QC personnel. At the meeting, the Contractor shall be required to explain in detail how Phases Control shall be implemented for each definable feature of work. As a minimum, the Contractor's personnel required to attend shall include an officer of the firm, the project manager, project superintendent, QCM, Alternate QCM and subcontractor representatives. Each subcontractor who shall be assigned QC responsibilities shall have a principal of the firm at the meeting. Minutes of the meeting shall be prepared by the QCM and signed by the Contractor. The Contractor shall provide a copy of the signed minutes to all attendees.

1.13 QC MEETINGS

A. After the start of construction, the QCM shall conduct weekly QC meetings at the work site with the project superintendent. The QCM shall prepare the minutes of the meeting and provide a copy to the COTR within 2 working days after the meeting. The COTR may attend these meetings. The QCM shall notify the COTR at least 48 hours in advance of each meeting. These meetings shall be scheduled to precede or follow the regular weekly progress meeting. As a minimum, the following shall be accomplished at each meeting:

1. Review the minutes of the previous meeting

2. Review the schedule and the status of work:

a. Work or testing accomplished since last meeting b. Rework items identified since last meeting c. Rework items completed since last meeting;

3. Review the status of submittals, O & M data and Warranty Manuals:

a. Submittals, O & M data and Warranties reviewed and approved since last meeting b. Submittals, O & M data and Warranties required in the near future;

4. Review the work to be accomplished in the next two (2) week(s) and documentation required:

a. Establish completion dates for rework items b. Update the schedule showing planned and actual dates of the preparatory, initial

and follow-up phases, including testing and any other inspection required by this contract

c. Discuss construction methods and the approach that shall be used to provide quality construction by planning ahead and identifying potential problems for each definable feature of work

d. Discuss status of off-site work or testing e. Documentation required; f. Discuss upcoming Activity Hazard Analyses.

Page 85: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

QUALITY REQUIREMENTS 014000 - 11

5. Resolve QC and production problems, assist in resolving Request for Information issues; 6. Address items that may require revising the QC plan:

a. Changes in QC organization personnel b. Changes in procedures.

7. Review health and safety plan

1.14 PHASES OF CONTROL

A. The Phases of Control shall adequately cover both on-site and off-site work and shall include the following for each definable feature of work.

B. Material Receiving Inspection: Contractor shall establish a formal material receiving inspection program to verify material compliance to approved Shop Drawings, approved submittals, and the contract plans and specifications.

C. Preparatory Phase: Notify the COTR at least 2 workdays in advance of each preparatory phase. This phase shall include a meeting conducted by the QCM and attended by the superintendent, and the foreman responsible for the definable feature. Document the results of the preparatory phase actions in the daily Quality Control Daily Report and in the Preparatory Phase Report. As a minimum the following should be covered prior to beginning work on each definable feature of work:

1. Review each paragraph of the applicable specification sections. 2. Review the project drawings. 3. Verify that appropriate shop drawings, O & M data, Warranties, and submittals for

materials and equipment have been submitted and approved. Verify receipt of approved factory test results, when required.

4. Establish control to be utilized to assure work complies with the contract plans and specifications.

5. Review the testing plan and ensure that provisions have been made to provide the required QC testing.

6. Examine the work area to ensure that the required preliminary work has been completed. 7. Examine the required materials, equipment and sample work to ensure that they are on

hand and conform to the approved shop drawings and submitted data. 8. Discuss construction methods, construction tolerances, workmanship standards, and the

approach that shall be used to provide quality construction by planning ahead and identifying potential problems for each definable feature of work.

9. Review the safety plan and appropriate activity hazard analysis to ensure that applicable safety requirements are met, and that required Material Safety Data Sheets (MSDS) are submitted.

D. Initial Phase: Notify the COTR at least 2 workdays in advance of each initial phase. When construction crews are ready to start work on a definable feature of work, conduct the initial phase with the superintendent, and the foreman responsible for that definable feature of work. Observe the initial segment of the definable feature of work to ensure that the work complies with Contract requirements. Document the results of the initial phase in the daily Quality Control Daily Report and in the Initial Phase Report. Repeat the initial phase for each new crew

Page 86: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

QUALITY REQUIREMENTS 014000 - 12

to work on-site, or when acceptable levels of specified quality are not being met. As a minimum the following should be covered for each definable feature of work:

1. Ensure controls established during Preparatory Phase are adequate to allow work to proceed in compliance with the plans and specifications.

2. Establish the quality of workmanship required. 3. Resolve conflicts. 4. Ensure that testing is performed by the approved laboratory. 5. Check work procedures for compliance with the Safety Plan and the appropriate activity

hazard analysis to ensure that applicable safety requirements are met.

E. Follow-Up Phase: Perform the following for on-going work daily, or more frequently as necessary until the completion of each definable feature of work and document in the daily Quality Control Daily Report:

1. Ensure the work is in compliance with Contract requirements. 2. Maintain the quality of workmanship required. 3. Ensure that testing is performed by the approved laboratory. 4. Ensure that rework items are being corrected. 5. Perform safety inspections.

F. Code-Required Inspections:

1. Comply with current edition approved by the Commonwealth of Virginia of the USBC, "Special Inspections” or other agencies having jurisdiction. Special Inspections are to be performed by the Authority’s agent. Perform and document all tests, inspections, notifications to the Authority, coordination with the Authority’s agent and other activities listed in the USBC or other agencies having jurisdiction.

2. Notice to COTR: Notify COTR, in writing, at least 48 hours in advance of all code-required inspections. COTR should be apprised in advance of every preparatory and initial inspection. All preparatory, initial, and follow-up inspections shall be made a matter of record in Contractor's quality-control documentation.

G. Additional Preparatory and Initial Phases

1. Additional Preparatory and Initial Phases shall be conducted on the same definable features of work if the quality of on-going work is unacceptable, if there are changes in the applicable QC organization, if there are changes in the on-site production supervision or work crew, if work on a definable feature is resumed after substantial period of inactivity, or if other problems develop as directed by the COTR in writing.

H. Notification of Phases of Control for Off-Site Work

1. On determination by COTR that an item shall require surveillance by the Authority at the point of production, manufacture, or shipment, Contractor shall be notified, in writing, of such determination. Contractor shall furnish to COTR three copies of all purchase orders or subcontracts, for all tiers of subcontractors or suppliers for each item. In addition, copies of documented quality-control operations, tests, and inspections shall be made available to the Authority's representative at the point of production, manufacture, or shipment. The CQC shall notify the COTR at least two weeks prior to the start of the preparatory and initial phases.

Page 87: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

QUALITY REQUIREMENTS 014000 - 13

1.15 SUBMITTAL REVIEW AND APPROVAL

A. Procedures for submission, review and approval of submittals are described in Division 01 Section “Submittals”.

1.16 TESTING

A. Except as stated otherwise in the technical specification sections, perform sampling and testing required under this Contract.

B. Independent Testing Laboratory: When tests are required by civil, electrical, USBC and other codes in effect, a corporately and financially independent testing organization that can function as an unbiased testing authority, professionally independent of manufacturers, suppliers, and installers of equipment, or systems evaluated by the testing organization shall be contracted by the Contractor to perform the contractually required tests. The various types of independent laboratories and their requirements are listed below:

C. Accreditation Requirements: Construction materials testing laboratories performing work for Authority construction contracts shall be accredited by one of the laboratory accreditation authorities. The laboratory's scope of accreditation shall include the ASTM standards listed in the paragraph titled "Construction Materials Testing Laboratory Requirements" as appropriate to the testing field. The policy applies to the specific laboratory performing the actual testing, not just the "Corporate Office".

D. Electrical testing of components, equipment and systems: The testing firm shall be regularly engaged in the testing of electrical equipment, devices, installations, and systems. The testing firm shall have at least five years experience in the testing of electrical equipment of the type, rating, and voltage used on this Project. The testing laboratories shall be a current full-member company of the International Electrical Testing Association (http://www.neta.org/). This independent testing firm shall perform duties as required under the terms of this Contract.

E. Structural and Pipe Welding: An independent testing firm shall perform all structural and pipe welding examinations as required by this Contract. The inspectors employed by the firm shall hold current certification as an AWS Certified Welding Inspector (CWI) for visual weld examinations and ASNT-TC-1A Certification for nondestructive examination of welds. ASNT-TC-1A certifications shall be by an ASNT-TC-1A ACCP Level III.

F. Construction Materials Testing Laboratory Requirements: Provide an independent construction material testing laboratory accredited by an acceptable laboratory accreditation authority to perform sampling and tests required by this Contract. Testing laboratories that have obtained accreditation by an acceptable laboratory accreditation authority listed in the paragraph entitled "Laboratory Accreditation Authorities" submit with the Quality Control Plan, a copy of the Certificate of Accreditation and Scope of Accreditation. The scope of the laboratory's accreditation shall include the test methods required by the Contract. On-site testing facilities shall submit a certified statement by the Supervising Professional Engineer, licensed in the Commonwealth of Virginia, as meeting the requirements of the following minimum ASTM standards listed below as appropriate to the testing field.

1. Laboratories engaged in testing of construction materials shall meet the requirements of ASTM E 329.

Page 88: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

QUALITY REQUIREMENTS 014000 - 14

2. Laboratories engaged in testing of concrete and concrete aggregates shall meet the requirements of ASTM C 1077.

3. Laboratories engaged in testing of bituminous paving materials shall meet the requirements of ASTM D 3666.

4. Laboratories engaged in testing of soil and rock, as used in engineering design and construction, shall meet the requirements of ASTM D 3740.

5. Laboratories engaged in nondestructive testing (NDT) shall meet the requirements of ASTM E 543.

6. Laboratories engaged in Hazardous Materials Testing shall meet the requirements of OSHA and EPA.

G. Laboratory Accreditation Authorities: Laboratory Accreditation Authorities are the National Voluntary Laboratory Accreditation Program (NVLAP) administered by the National Institute of Standards and Technology, the American Association of State Highway and Transportation Officials (AASHTO) program, ICBO Evaluation Service, Inc. (ICBO ES), and the American Association for Laboratory Accreditation (A2LA) program and the Washington Area Council of Engineering Laboratories (WACEL). Furnish to the COTR, a copy of the current Certificate of Accreditation and Scope of Accreditation. The scope of the laboratory's accreditation shall include the test methods required by the Contract.

H. Capability Check: The COTR retains the right to check laboratory equipment in the proposed laboratory and the laboratory technician's testing procedures, techniques, and other items pertinent to testing, for compliance with the standards set forth in this Contract.

I. Capability Recheck: If non-conformities are discovered during the capability check or any succeeding recheck, Contractor shall be assessed a charge of $750.00 to reimburse the Authority for each recheck of the laboratory or the checking of a subsequently selected laboratory. These charges shall be deducted from the total amount due Contractor.

J. Test Results: Cite applicable Contract requirements, tests or analytical procedures used. Provide actual results and include a statement that the item tested or analyzed conforms or fails to conform to specified requirements. If the item fails to conform, notify COTR immediately. Conspicuously stamp the cover sheet for each report in large red letters "CONFORMS" or "DOES NOT CONFORM" to the specification requirements, whichever is applicable. A testing laboratory representative authorized to sign certified test reports shall sign test results. Furnish the signed reports, certifications, and other documentation to the COTR via the QCM. Furnish a summary report of field tests at the end of each month

K. Test Reports and Monthly Summary Report of Tests:

1. The QCM shall furnish the signed reports, certifications, and a summary report of field tests at the end of each month to the COTR.

L. Control and Verification Tests: Control tests are those tests made for Contractor under the Quality Control Plan to assist Contractor in maintaining control of his operations. As described above, Contractor shall procure the services of an independent commercial laboratory to perform the required control tests. The Specifications contain the minimum of the following:

1. Testing criteria 2. Frequency of testing 3. Procedures

Page 89: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

QUALITY REQUIREMENTS 014000 - 15

4. Methods of construction 5. Number of control tests to be made for each phase of the Work. 6. Notify COTR a minimum of 24 hours in advance of the time samples shall be taken by

Contractor for quality control testing. COTR shall then notify its own testing laboratory contractor so that verification test samples may be taken.

M. Check Tests: Contractor shall furnish to COTR the quantities of materials to be used for check testing as required in the Specifications. Check testing shall be performed by the Authority at an independent laboratory at no cost to Contractor. No direct payment shall be made to Contractor for the furnishing of materials used for check testing.

N. Staffing: All laboratory personnel shall work under the supervision of a Professional Engineer licensed in the Commonwealth of Virginia.

1.17 QC CERTIFICATIONS

A. Quality Control Daily Report Certification

1. Each Quality Control Daily Report shall contain the following statement:

a. “On behalf of (Name of Contractor), I certify that this report and the Inspector's Daily Reports are complete and correct, and that all materials and equipment used, as well as work performed during this reporting period are in compliance with Drawings, Specifications, and Contract provisions, except as noted in this report or attached reports.”

B. Application for Payment Certification

1. Refer to Division 01 Section "Application for Payment" for address to which the Applications shall be sent.

C. Completion Certification:

1. Upon completion of work under this Contract, the QCM shall furnish a certificate to the Contracting Officer attesting that "the work has been completed, inspected, tested and is in compliance with the Contract."

1.18 COMPLETION INSPECTIONS

A. Punch-Out Inspection: Near the completion of all work or any increment thereof established by a completion time stated in the Contract Clause entitled "Commencement, Prosecution, and Completion of Work," or stated elsewhere in the specifications, the QCM shall conduct an inspection of the work and develop a "punch list" of items which do not conform to the approved drawings and specifications. Include in the punch list any remaining items on the "Rework Items List" which were not corrected prior to the Punch-Out Inspection. The punch list shall include the estimated date by which the deficiencies will be corrected. A copy of the punch list shall be provided to the COTR. The QCM or staff shall make follow-on inspections to ascertain that all deficiencies have been corrected. Once this is accomplished the Contractor shall notify the COTR that the facility is ready for the Authority "Pre-Final Inspection."

Page 90: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

QUALITY REQUIREMENTS 014000 - 16

B. Pre-Final Inspection: The Authority will perform this inspection to verify that the facility is complete and ready to be occupied. An Authority "Pre-Final Punch List" may be developed as a result of this inspection. The QCM shall ensure that all items on this list are corrected prior to notifying the Authority that a "Final" inspection with the customer can be scheduled. Any items noted on the "Pre-Final" inspection shall be corrected in timely manner and shall be accomplished before the contract completion date for the work or any particular increment thereof if the project is divided into increments by separate completion dates.

C. Final Acceptance Inspection: The QCM, the superintendent or other primary contractor management personnel shall be in attendance at this inspection. The COTR will be in attendance at this inspection. Additional Authority personnel may be in attendance. The Contracting Officer based upon results of the “Pre-Final” inspection will formally schedule the final acceptance inspection. Notice shall be given to the COTR at least 14 calendar days prior to the final inspection stating that all specific items previously identified to the Contractor, as being unacceptable, along with all the remaining work performed under the contract, shall be complete and acceptable by the date scheduled for the final acceptance inspection. Failure of the Contractor to have all contract work acceptably complete for this inspection shall be cause for the Contracting Officer to bill the Contractor for the Authority's additional inspection cost in accordance with the clause in the Contract Provisions entitled "Inspection of Construction." When the Contracting Officer takes possession of partially completed work, it shall be in accordance with clause in the Contract Provisions entitled "Use and Possession Prior to Completion".

1.19 DOCUMENTATION

A. Contractor shall maintain current quality control records, on approved forms, of all control activities, production, tests and inspections performed. These records shall include factual evidence that required tests or inspections have been performed, including type and number of tests or inspections involved; results of tests or inspections; nature of defects, causes for rejection, etc.; proposed remedial action; and corrective actions taken. These records shall cover both conforming and defective or deficient features (non-conforming) and shall include a statement that all supplies and materials incorporated into the Work are in full compliance with terms of the Contract. Legible copies of these records shall be furnished to COTR daily. The records shall cover all work placed subsequent to the previously furnished records and shall be verified by Contractor's QCM. Contractor shall document tests and inspections as specified in the technical provisions of the Specifications, and these records shall be available for review by COTR throughout the life of the Contract.

B. Maintain current and complete records of on-site and off-site QC Program operations and activities. Establish and maintain the following in a series of 3 ring binders. Binders shall be divided and tabbed as shown below. These binders shall be readily available to the Authority's Quality Assurance Team during normal business hours.

1. All completed Preparatory and Initial Phase Reports, arranged by specification Section. 2. All milestone inspections, arranged by Activity/Event Number. 3. A current up-to-date copy of the Testing Plan and Log with supporting field test reports,

arranged by specification section. 4. Copies of all contract modifications, arranged in numerical order. Also include

documentation that modified work was accomplished. 5. A current, up-to-date copy, of the Deficiency List.

Page 91: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

QUALITY REQUIREMENTS 014000 - 17

C. Report Forms - The contractor shall design all forms to be used in the Quality Control Program. A copy of all forms shall be included with the Quality Control Plan. The forms shall be designed to assist in the control of the quality. The following minimum requirements are listed for specific reports:

1. Quality Control Daily Report: Reports are required for each day that work is performed and for every seven consecutive calendar days of no work and on the last day of a no-work period. Account for each calendar day throughout the life of the Contract. The reporting of work shall be identified by terminology consistent with the construction schedule. Quality Control Daily Reports are to be prepared, signed and dated by the QCM and shall contain the following information:

a. Date of report, report number, Contract Number, and Contract Title. b. Identify Schedule Activity No., Submittal # and list equipment/material received

each day that is incorporated into the job. c. Indicate if Preparatory Phase work was performed today (Yes/No checkboxes). d. If Preparatory Phase work was performed today (including on-site and off-site

work), identify its Schedule Activity Number and Definable Feature of Work. The Index number is a cross reference to the Preparatory Phase Checklist. An example of the Index number is: 0025-P01, where "0025" is the Quality Control Daily Report Number, "P" indicates Preparatory Phase, and "01" is the Preparatory Phase Checklist number(s) for this date. Each entry in this Section shall be accompanied with a corresponding Preparatory Phase Checklist.

e. Indicate if Initial Phase work was performed today (Yes/No checkboxes). f. If Initial Phase work was performed today (including on-site and off-site work),

identify its Schedule Activity Number and Definable Feature of Work. The Index Number is a cross reference to the Initial Phase Checklist. An example of the Index Number is: 0025-I01, where "0025" is the Quality Control Daily Report Number, "I" indicates Initial Phase, and "01" is the Initial Phase Checklist number(s) for this date. Each entry in this Section shall be accompanied with a corresponding Initial Phase Checklist.

g. Results of the Follow-up Phase inspections held today (including on-site and off-site work), including Schedule Activity Number, location of definable feature of work, Specification Sections, etc. Indicate in the report for this definable feature of work that the work complies with the Contract as approved in the Initial Phase, work complies with safety requirements, and that required testing has been performed. Include a list of who performed the tests.

h. List the rework items identified, but not corrected by close of business, along with its associated Schedule Activity Number.

i. List the rework items corrected from the rework items list along with the corrective action taken and its associated Schedule Activity Number.

j. Include a "remarks" section in this report that shall contain pertinent information including but not limited to:

1) Directions received. 2) Quality control problem areas. 3) Deviations from the QC plan. 4) Construction deficiencies encountered. 5) QC meetings held,. 6) Acknowledgement that record drawings, specifications, O & M data, and

Warranty Manuals, have been updated.

Page 92: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

QUALITY REQUIREMENTS 014000 - 18

7) Corrective direction given by the QC Organization and corrective action taken by the Contractor.

8) For each remark given, identify the Schedule Activity Number that is associated with the remark.

k. Quality Control Daily Report certification, signature and date.

2. Preparatory Phase Report: Each Definable Feature of Work that is in the Preparatory Phase shall have this report filled out for it. The report shall be identified by terminology consistent with the construction schedule. Attach this report to the Quality Control Daily Report of the same date.

a. Specification Section, date of report, and Contract number shall be filled out. Duplicate this information in the header of the second page of the report.

b. Definable Feature of Work, Schedule Activity Number and Index Number entry and format shall match entry in the Preparatory Phase section of the Quality Control Daily Report. Duplicate this information in the header of the second page of the report.

c. Personnel Present: Indicate the number of hours of advance notice that was given to the COTR and indicate (Yes/No checkboxes) whether or not the COTR was notified. Indicate the Names of Preparatory Phase Meeting attendees, their position and their company affiliation.

d. Submittals: Indicate if submittals have been approved (Yes/No checkboxes), if no indicate what has not been submitted. Are materials on hand (Yes/No checkboxes) and if not, what items are missing. Check delivered material/equipment against approved submittals and comment as required.

e. Material Storage: Indicate if materials/equipment is stored properly (Yes/No checkboxes) and if not, what action is/was taken.

f. Specifications: Review and comment on Specification Paragraphs that describe the material/equipment, procedure for accomplishing the work and clarify any differences.

g. Preliminary Work & Permits: Ensure preliminary work is in accordance with the contract documents and necessary permits are on file, if not, describe the action taken.

h. Testing: Identify who performs tests, the frequency, and where tests are to occur. Review the testing plan, report abnormalities, and if the test facilities have been approved.

i. Discuss Control Procedures that shall be employed to consistently obtain the required specified quality.

j. Safety: Indicate if the activity hazard analysis has been approved (Yes/No checkboxes) and comment on the review of the applicable portions of the Construction Safety Manual.

k. Meeting Comments: Note comments and remarks during the Preparatory Phase Meeting that was not addressed in previous sections of this checklist.

l. Other Items or Remarks: Note any other remarks or items that were a result of the Preparatory Phase.

m. QCM shall sign and date the report.

3. Initial Phase Report: Complete this report for each Definable Feature of Work that is in the Initial Phase. The report shall be identified by terminology consistent with the

Page 93: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

QUALITY REQUIREMENTS 014000 - 19

construction schedule. Attach this report to the Quality Control Daily Report of the same date.

a. Specification Section, date of report, and Contract number shall be entered. b. Definable Feature of Work, Schedule Activity Number and Index Number entry

and format shall match entry in the Initial Phase section of the Quality Control Daily Report.

c. Personnel Present: Indicate the number of hours of advance notice that was given to the COTR and indicate (Yes/No checkboxes) whether or not the COTR was notified. Indicate the Names of Initial Phase Meeting attendees, their position and company/Authority they are with.

d. Control Procedures: Comment on control procedures identified at Preparatory Phase of Control and assurance that work is in accordance with plans, specifications and submittals. Control procedures not producing the required compliance shall be adjusted until the procedures consistently obtain the required quality.

e. Preliminary Work: Ensure preliminary work being placed is in compliance and if not, what action is/was taken.

f. Workmanship: Identify where initial work is located; if a sample panel is required (Yes/No checkboxes); is the initial work the sample (Yes/No checkboxes); and if Yes, describe the panel location and precautions taken to preserve the sample.

g. Resolution: Comment on any differences and the resolutions reached. h. Check Safety: Comment on the safety review of the job conditions. i. Other: Note any other remarks or items that were a result of the Initial Phase. j. QCM shall sign and date the report.

D. Testing Log: As tests are performed, the QCM shall record on the "Testing Log" the date the test was conducted, the date the test results were forwarded to the COTR, remarks and acknowledgement that an accredited or Contracting Officer approved testing laboratory was used. Forward a copy of the updated "Testing Plan and Log" on the last day of each month. Do not attach to the Quality Control Daily Report.

E. Deficiency Log: The QCM shall maintain a list of work that does not comply with the Contract, identifying what items need to be reworked, the date the item was originally discovered, the date the item shall be corrected by, and the date the item was corrected. There is no requirement to report a rework item that is corrected the same day it is discovered. Provide a copy of the deficiency log to the COTR at the weekly progress meeting. The Contractor shall be responsible for including on this list items needing rework including those identified by the COTR.

F. Special Inspection Control Log: Contractor shall maintain a Special Inspection Control Log chronologically recording each Special test and inspection performed under the USBC, or other agencies having jurisdiction on-site, including the nature of the test or inspection, the date performed, the results, causes for rejection, corrective action taken, and dates of subsequent tests and final acceptance.

G. Test Reports: Contractor shall be responsible for establishing a system that shall record all tests results. Information on test designation, location, date of test, specification requirements, results and retest results, causes for rejection and recommended remedial actions shall be documented. A copy of the test results shall be sent directly from the Agency performing the testing services to COTR. A copy of any failing report shall be sent immediately. All test

Page 94: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

QUALITY REQUIREMENTS 014000 - 20

reports shall be reviewed and signed by a professional engineer, licensed in the Commonwealth of Virginia.

H. Signoff Sheets: Contractor shall be responsible for establishing a system of signoff sheets certifying that all work required before the construction or startup of critical work elements has been constructed and installed according to the plans and specifications.

I. Monthly Deficiency Report: Contractor shall submit a monthly deficiency report to COTR identifying all substandard tests and inspections taken during the month including the nature of the test or inspection, location and nature of defects, causes for rejection, and remedial actions taken or proposed for any open items on prior deficiency reports including the date scheduled for resolution of the item.

J. Record Drawings: The QCM is required to ensure the record drawings, required by Division 01 Section "Project Record Documents," are kept current on a daily basis and marked to show deviations which have been made from the construction drawings. Ensure each deviation has been identified with the appropriate modifying documentation (e.g. CN No., Modification No., Request for Information No., etc.). The QCM shall initial each deviation and each revision. Upon completion of work, the QCM shall furnish a certificate attesting to the accuracy of the record drawings prior to submission to the COTR.

K. Operation, Maintenance, and Warranty Manuals: The QCM shall ensure that the Operation and Maintenance data required by Division 01 Section “Operation and Maintenance Data” and the Warranties specified in Division 01 Section “Project Closeout” are inserted on a daily basis in the appropriate sections of the approved formatted manuals after they have been approved by the COTR.

L. Materials Receiving Inspection Report: Contractor shall establish a formal materials receiving inspection program to verity material compliance to approved Shop Drawings, approved submittals, and the contract plans and specifications.

1.20 NOTIFICATION ON NON-COMPLIANCE

A. The COTR will notify the Contractor of any detected non-compliance with the foregoing requirements. The Contractor shall take immediate corrective action after receipt of such notice. Such notice, when delivered to the Contractor at the work site, shall be deemed sufficient for the purpose of notification. If the Contractor fails or refuses to comply promptly, the Contracting Officer may:

1. Issue an order stopping all or part of the work until satisfactory corrective action has been taken. The Contractor shall make no part of the time lost due to such stop orders the subject of a claim for extension of time for excess costs or damages.

2. Repair, replace or otherwise remedy the defective work at the Contractor’s expense. Cost incurred by the Authority to correct defective work shall be deducted from the total amount due the Contractor.

3. Withhold an amount from the payment due the Contractor as may be deemed necessary at the discretion of the Contracting Officer.

4. Terminate the Contractor’s right to proceed for Default after providing required notice.

Page 95: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

QUALITY REQUIREMENTS 014000 - 21

B. In cases where implementation of the Quality Control Program does not comply with the Contractor’s Quality Control Plan or the contract provisions. Or Contractor fails to properly operate and maintain an effective Quality Control Program, the Contracting Officer may:

1. Order the Contractor to replace ineffective or unqualified Quality Control Personnel or subcontractors.

2. Issue an order stopping all or part of the work until acceptable personnel are on site and a new Quality Control Plan is approved by the COTR. The Contractor shall make no part of the time lost due to such stop orders the subject of claim for extension of time for excess costs or damages.

3. Take a credit from the contract for Quality Control Activities not performed. 4. Terminate the Contractors right to proceed for Default after providing required notice.

C. The Contractor shall maintain a detailed record of every non-compliance and corrective action taken.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 014000

Page 96: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final
Page 97: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

REFERENCES 014200 - 1

SECTION 014200 - REFERENCES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings, Contract Provisions, Special Provisions, Supplementary Conditions, and other Division 01 Specification Sections apply to this Section.

1.2 SUMMARY

A. This Section defines many of the terms used elsewhere in the Construction Documents and lists complete names and telephone numbers for many of the associations and agencies identified elsewhere in the Construction Documents by their acronym.

B. Abbreviations, where not defined in the Contract Documents, will be interpreted by the Contracting Officer to mean the normal construction industry terminology.

C. Plural words will be interpreted as singular and singular words will be interpreted as plural where applicable for context of the Contract Documents.

1.3 DEFINITIONS

A. General: Basic Contract definitions are included in Sections I and II of the Authority Solicitation Offer and Award. Certain terms used in the Contract Documents are defined generally in this Article. Definitions and explanations contained in this Section are not necessarily either complete or exclusive, but are general for the Work to the extent that they may not be stated more explicitly in another element of the Contract Documents.

B. Approve: The term "approved," where used in regard to COTR's action on Contractor's submittals, applications, and requests, is limited to COTR's duties and responsibilities as delegated by the Contracting Officer in the Contract and Special Provisions.

C. Architect/Engineer: For the purpose of this Project, the "Design Professional of Record." To distinguish from the Contracting Officer and Contracting Officer's Technical Representative (COTR).

D. Authority: Metropolitan Washington Airports Authority

E. Award: The acceptance, by the Authority, of the successful offeror's proposal.

F. Award Date: The date on which the Authority gives notice of acceptance to the successful offeror.

G. AOA (or A.O.A.): Air Operations Area. The area of the Airport used or intended to be used for landing, taking off, surface maneuvering, loading, unloading, or servicing aircraft. This security

Page 98: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

REFERENCES 014200 - 2

area requires security badging. Workers in this area are required to obtain and display an AOA photo I.D. credential. Drivers in this area are required to obtain an Airport Vehicle Operator's Permit for the Air Operations Area.

H. Beneficial Use: Use by the Authority prior to 100 percent completion and final acceptance.

I. Contract Documents: Documents containing requirements of the Work. These include all Contract provisions and attachments made thereto or referenced therein.

J. Contract Provisions: The administrative and procedural requirements starting at Award Date and ending at Final Acceptance, as provided for in Section VII, "Contract Provisions."

K. Contract Time or Duration (Time Limit): The number of calendar days established in Section III, "Schedule," indicating the time allowed for the completion of all physical and administrative work contemplated in the Contract, including any authorized extensions thereto.

L. Contracting Officer's Technical Representative (COTR): The Contracting Officer's designated representative, as defined in Section VII, "Contract Provisions."

M. Contractor: Individual, partnership, corporation or joint venture under Contract to the Authority for performance of prescribed Work.

N. Drawings: Erection/installation/construction plans, or any other supplementary plans or similar graphic data, illustrating work to be performed that are provided to Contractor as part of the Contract Documents.

O. Directed: A command or instruction by the Authority. Other terms including "requested," "authorized," "selected," "required," and "permitted" have the same meaning as "directed."

P. Final Acceptance: Refer to Division 01 Section "Project Closeout."

Q. "Indicated": Requirements expressed by graphic representations or in written form on drawings, in Specifications, and in other Contract Documents. Other terms including "shown," "noted," "scheduled," and "specified" have the same meaning as "indicated."

R. "Regulations": Laws, ordinances, statutes, and lawful orders issued by authorities having jurisdiction, and rules, conventions, and agreements within the construction industry that control performance of the Work.

S. "Furnish": Supply and deliver to Project site, ready for unloading, unpacking, assembly, installation, and similar operations.

T. "Install": Operations at Project site including unloading, temporarily storing, unpacking, assembling, erecting, placing, anchoring, applying, working to dimension, finishing, curing, protecting, cleaning, and similar operations.

U. "Provide": Furnish and install, complete and ready for the intended use.

V. "Installer": Contractor or another entity engaged by Contractor as an employee, Subcontractor, or Sub-subcontractor, to perform a particular construction operation, including installation, erection, application, and similar operations.

Page 99: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

REFERENCES 014200 - 3

1. Using a term such as "carpentry" does not imply that certain construction activities must be performed by accredited or unionized individuals of a corresponding generic name, such as "carpenter." It also does not imply that requirements specified apply exclusively to trades people of the corresponding generic name.

W. "Experienced": When used with an entity, "experienced" means having successfully completed a minimum of ten previous projects similar in size and scope to this Project; being familiar with special requirements indicated; and having complied with requirements of authorities having jurisdiction.

X. "Project Site": Space available for performing construction activities. The extent of Project site is indicated.

Y. Punch list Work: Minor corrective actions required to achieve "Final Acceptance." Occurs after "Substantial Completion" of the Work in strict compliance with quality-control requirements.

Z. Roadway: General term denoting a public way for purposes of vehicular travel, including the entire area within the right-of-way.

AA. Special Provisions: For the purpose of this Contract, the directions and requirements provided for in Section VI of the Contract Documents.

BB. Shop Drawings: Refer to Division 01 Section "Submittals."

CC. Specifications: General term comprising all directions, provisions and requirements contained herein, together with any other contractual requirements such as may be added or adopted as the Contract Provisions, Special Provisions, or Supplementary Conditions, all of which are necessary for the proper performance of the Contract.

DD. Substantial Completion: Refer to Division 01 Section "Project Closeout."

EE. Factory-Authorized Service Representative: An authorized representative of a manufacturer who is trained and approved by the manufacturer to inspect and approve the installation of manufacturer’s products and that are similar in material, design, and extent to those indicated for this Project and who is authorized by the manufacturer to confirm the issuance of appropriate warranties.

1.4 INDUSTRY STANDARDS

A. Applicability of Standards: Unless the Contract Documents include more stringent requirements, applicable construction industry standards have the same force and effect as if bound or copied directly into the Contract Documents to the extent referenced. Such standards are made a part of the Contract Documents by reference.

B. Publication Dates: Comply with standards in effect as of date of the Contract Documents, unless otherwise indicated.

C. Conflicting Requirements: Refer to Division 01 Section "Quality Requirements" for additional information regarding conflicting requirements.

Page 100: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

REFERENCES 014200 - 4

1. Minimum Quantity or Quality Levels: The quantity or quality level shown or specified shall be the minimum provided or performed. The actual installation may comply exactly with the minimum quantity or quality specified, or it may exceed the minimum within reasonable limits. To comply with these requirements, indicated numeric values are minimum or maximum, as appropriate, for the context of requirements. Refer uncertainties to COTR for a decision before proceeding.

D. Copies of Standards: Each entity engaged in construction on Project shall be familiar with industry standards applicable to its construction activity. Copies of applicable standards are not bound with the Contract Documents.

1. Where copies of standards are needed to perform a required construction activity, obtain copies directly from publication source and make them available on request.

E. Abbreviations and Acronyms for Standards and Regulations: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they shall mean the recognized name of the standards and regulations in the following list. Names, telephone numbers, and Web site addresses are subject to change and are believed to be accurate and up-to-date as of the date of the Contract Documents.

ADAAG Americans with Disabilities Act (ADA) (800) 872-2253 Accessibility Guidelines for Buildings and Facilities (202) 272-0080 Available from Access Board www.access-board.gov CFR Code of Federal Regulations (888) 293-6498 Available from Government Printing Office (202) 512-1530 www.access.gpo.gov/nara/cfr CRD Handbook for Concrete and Cement (601) 634-2355 Available from Army Corps of Engineers Waterways Experiment Station www.wes.army.mil DOD Department of Defense Military Specifications and Standards (215) 697-6257 Available from Department of Defense Single Stock Point www.dodssp.daps.mil DSCC Defense Supply Center Columbus (See FS) FED-STD Federal Standard (See FS) FS Federal Specification (215) 697-6257 Available from Department of Defense Single Stock Point.

www.dodssp.daps.mil

Available from General Services Administration (202) 501-1021

Page 101: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

REFERENCES 014200 - 5

www.fss.gsa.gov Available from National Institute of Building Sciences

www.nibs.org (202) 289-7800

FTMS Federal Test Method Standard (See FS) ICC-ES ICC Evaluation Service, Inc. (800) 423-6587 www.icc-es.org MIL See MILSPEC MS MIL See MILSPEC MILSPEC Military Specification and Standards (215) 697-6257 Available from Department of Defense Single Stock Point www.dodssp.daps.mil MUTCD Manual on Uniform Traffic Control Devices

Department of Transportation Federal Highway Administration (See FHA. Located in Paragraph Federal Government Agencies").

UFAS Uniform Federal Accessibility Standards (800) 872-2253 Available from Access Board (202) 272-0080 www.access-board.gov

1.5 ABBREVIATIONS AND ACRONYMS

A. Industry Organizations: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they shall mean the recognized name of the entities in the following list. Names, telephone numbers, and Web site addresses are subject to change and are believed to be accurate and up-to-date as of the date of the Contract Documents.

AA Aluminum Association, Inc. (The) (202) 862-5100 www.aluminum.org AAADM American Association of Automatic Door Manufacturers (216) 241-7333 www.aaadm.com AABC Associated Air Balance Council (202) 737-0202 www.aabchq.com AAMA American Architectural Manufacturers Association (847) 303-5664 www.aamanet.org

Page 102: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

REFERENCES 014200 - 6

AASHTO American Association of State Highway and (202) 624-5800 Transportation Officials http://www.transportation.org AATCC American Association of Textile Chemists and Colorists (The) (919) 549-8141 www.aatcc.org ABMA American Bearing Manufacturers Association (202) 367-1155 www.abma-dc.org ACI ACI International (248) 848-3700 (American Concrete Institute) www.aci-int.org ACPA American Concrete Pipe Association (972) 506-7216 http://www.concrete-pipe.org AEIC Association of Edison Illuminating Companies, Inc. (The) (205) 257-2530 www.aeic.org AF&PA American Forest & Paper Association (800) 878-8878 www.afandpa.org (202) 463-2700 AGA American Gas Association (202) 824-7000 www.aga.org AGC Associated General Contractors of America (The) (703) 548-3118 www.agc.org AHA American Hardboard Association (Now part of CPA) AHAM Association of Home Appliance Manufacturers (202) 872-5955 www.aham.org AI Asphalt Institute (859) 288-4960 http://www.asphaltinstitute.org AIA American Institute of Architects (The) (800) 242-3837 www.aia.org (202) 626-7300 AISC American Institute of Steel Construction (800) 644-2400 www.aisc.org (312) 670-2400 AISI American Iron and Steel Institute (202) 452-7100 www.steel.org AITC American Institute of Timber Construction (303) 792-9559 http://www.aitc-glulam.org

Page 103: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

REFERENCES 014200 - 7

ALCA Associated Landscape Contractors of America (800) 395-2522 www.alca.org (703) 736-9666 ALSC American Lumber Standard Committee, Incorporated (301) 972-1700 www.alsc.org AMCA Air Movement and Control Association International, Inc. (847) 394-0150 www.amca.org ANSI American National Standards Institute (202) 293-8020 www.ansi.org AOSA Association of Official Seed Analysts (505) 522-1437 Http://www.aosaseed.com APA APA - The Engineered Wood Association (253) 565-6600 http://www.apawood.org APA Architectural Precast Association (239) 454-6989 http://www.archprecast.org API American Petroleum Institute (202) 682-8000 www.api.org ARI Air-Conditioning & Refrigeration Institute (703) 524-8800 www.ari.org ARMA Asphalt Roofing Manufacturers Association (202) 207-0917 http://www.asphaltroofing.org ASCE American Society of Civil Engineers (800) 548-2723 www.asce.org (703) 295-6300 ASHRAE American Society of Heating, Refrigerating and (800) 527-4723 Air-Conditioning Engineers www.ashrae.org (404) 636-8400 ASME ASME International (800) 843-2763 (The American Society of Mechanical Engineers International) (212) 591-7722 www.asme.org ASSE American Society of Sanitary Engineering (440) 835-3040 http://www.asphaltroofing.org ASTM ASTM International (610) 832-9585 (American Society for Testing and Materials International) www.astm.org AWCI AWCI International (703) 534-8300 (Association of the Wall and Ceiling Industries International)

Page 104: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

REFERENCES 014200 - 8

www.awci.org AWCMA American Window Covering Manufacturers Association (See WCSC) AWI Architectural Woodwork Institute (800) 449-8811 www.awinet.org (703) 733-0600 AWPA American Wood-Preservers' Association (334) 874-9800 www.awpa.com AWS American Welding Society (800) 443-9353 www.aws.org (305) 443-9353 AWWA American Water Works Association (800) 926-7337 www.awwa.org (303) 794-7711 BHMA Builders Hardware Manufacturers Association (212) 297-2122 http://www.buildershardware.com BIA Brick Industry Association (The) (703) 620-0010 www.bia.org BICSI BICSI (813) 979-1991 www.bicsi.org BIFMA BIFMA International (616) 285-3963 (Business and Institutional Furniture Manufacturer's Association International) www.bifma.com BISSC Baking Industry Sanitation Standards Committee (773) 761-4100 www.bissc.com CCC Carpet Cushion Council (203) 637-1312 http://www.asphaltroofing.org CCFSS Center for Cold-Formed Steel Structures (573) 341-4471 http://www.asphaltroofing.org CDA Copper Development Association Inc. (800) 232-3282 www.copper.org (212) 251-7200 CFFA Chemical Fabrics & Film Association, Inc. (216) 241-7333 http://www.asphaltroofing.org CGA Compressed Gas Association (703) 788-2700 www.cganet.com CGSB Canadian General Standards Board (800) 665-2472

Page 105: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

REFERENCES 014200 - 9

http://www.asphaltroofing.org (819) 956-0425 CIMA Cellulose Insulation Manufacturers Association (888) 881-2462 http://www.asphaltroofing.org (937) 222-2462 CISCA Ceilings & Interior Systems Construction Association (630) 584-1919 www.cisca.org CISPI Cast Iron Soil Pipe Institute (423) 892-0137 www.cispi.org CLFMI Chain Link Fence Manufacturers Institute (301) 596-2583 http://www.asphaltroofing.org CPA Composite Panel Association (301) 670-0604 www.pbmdf.com CPPA Corrugated Polyethylene Pipe Association (800) 510-2772 http://www.cppa-info.org (202) 462-9607 CRI Carpet & Rug Institute (The) (800) 882-8846 http://www.carpet-rug.com (706) 278-3176 CRSI Concrete Reinforcing Steel Institute (847) 517-1200 www.crsi.org CSA CSA International (800) 463-6727 (Formerly: IAS - International Approval Services) (416) 747-4000 http://www.csa-international.org CSI Construction Specifications Institute (The) (800) 689-2900 www.csinet.org (703) 684-0300 CSSB Cedar Shake & Shingle Bureau (604) 820-7700 http://www.cedarbureau.org CTI Cooling Technology Institute (281) 583-4087 (Formerly: Cooling Tower Institute) www.cti.org DHI Door and Hardware Institute (703) 222-2010 www.dhi.org EIA Electronic Industries Alliance (703) 907-7500 www.eia.org EIMA EIFS Industry Members Association (800) 294-3462 http://www.eima.com/ (770) 968-7945 EJCDC Engineers Joint Contract Documents Committee (800) 548-2723

Page 106: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

REFERENCES 014200 - 10

www.asce.org (703) 295-6300 EJMA Expansion Joint Manufacturers Association, Inc. (914) 332-0040 www.ejma.org ESD ESD Association (315) 339-6937 www.esda.org FCI Fluid Controls Institute (216) 241-7333 http://www.asphaltroofing.org FMG FM Global (401) 275-3000 (Formerly: FM - Factory Mutual System) www.fmglobal.com FRSA Florida Roofing, Sheet Metal & Air Conditioning Contractors

Association, Inc. (407) 671-3772

www.floridaroof.com FSA Fluid Sealing Association (610) 971-4850 www.fluidsealing.com FSC Forest Stewardship Council 52 951 5146905 www.fscoax.org GA Gypsum Association (202) 289-5440 www.gypsum.org GANA Glass Association of North America (785) 271-0208 www.glasswebsite.com GS Green Seal (202) 872-6400 www.greenseal.org GSI Geosynthetic Institute (610) 522-8440 www.geosynthetic-institute.org HI Hydraulic Institute (888) 786-7744 www.pumps.org (973) 267-9700 HI Hydronics Institute (908) 464-8200 www.gamanet.org HMMA Hollow Metal Manufacturers Association (See NAAMM) HPVA Hardwood Plywood & Veneer Association (703) 435-2900 www.hpva.org HPW H. P. White Laboratory, Inc. (410) 838-6550

Page 107: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

REFERENCES 014200 - 11

www.hpwhite.com IAS International Approval Services (See CSA) ICEA Insulated Cable Engineers Association, Inc. (770) 830-0369 www.icea.net ICRI International Concrete Repair Institute, Inc. (847) 827-0830 www.icri.org IEC International Electrotechnical Commission 41 22 919 02 11 www.iec.ch IEEE Institute of Electrical and Electronics Engineers, Inc. (The) (212) 419-7900 www.ieee.org IESNA Illuminating Engineering Society of North America (212) 248-5000 www.iesna.org IGCC Insulating Glass Certification Council (315) 646-2234 www.igcc.org IGMA Insulating Glass Manufacturers Alliance (The) (613) 233-1510 www.igmaonline.org ILI Indiana Limestone Institute of America, Inc. (812) 275-4426 www.iliai.com ISO International Organization for Standardization 41 22 749 01 11 www.iso.ch ISSFA International Solid Surface Fabricators Association (702) 567-8150 www.issfa.net ITS Intertek (800) 345-3851 www.intertek.com (607) 753-6711 ITU International Telecommunication Union 41 22 730 51 11 www.itu.int/home KCMA Kitchen Cabinet Manufacturers Association (703) 264-1690 www.kcma.org LMA Laminating Materials Association (201) 664-2700 www.lma.org LPI Lightning Protection Institute (800) 488-6864 www.lightning.org (847) 577-7200

Page 108: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

REFERENCES 014200 - 12

MBMA Metal Building Manufacturers Association (216) 241-7333 www.mbma.com MFMA Maple Flooring Manufacturers Association (847) 480-9138 www.maplefloor.org MFMA Metal Framing Manufacturers Association (312) 644-6610 www.metalframingmfg.org MH Material Handling Industry of America (See MHIA) MHIA Material Handling Industry of America (800) 345-1815 www.mhia.org (704) 676-1190 MIA Marble Institute of America (440) 250-9222 www.marble-institute.com MPI Master Painters Institute (888) 674-8937 www.paintinfo.com MSS Manufacturers Standardization Society of The Valve and (703) 281-6613 Fittings Industry Inc. www.mss-hq.com NAAMM National Association of Architectural Metal Manufacturers (312) 332-0405 www.naamm.org NACE NACE International (281) 228-6200 (National Association of Corrosion Engineers International) www.nace.org NADCA National Air Duct Cleaners Association (202) 737-2926 www.nadca.com NAIMA North American Insulation Manufacturers Association (The) (703) 684-0084 www.naima.org NBGQA National Building Granite Quarries Association, Inc. (800) 557-2848 www.nbgqa.com NCMA National Concrete Masonry Association (703) 713-1900 www.ncma.org NCPI National Clay Pipe Institute (262) 248-9094 www.ncpi.org NCTA National Cable & Telecommunications Association (202) 775-3550 www.ncta.com

Page 109: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

REFERENCES 014200 - 13

NEBB National Environmental Balancing Bureau (301) 977-3698 www.nebb.org NECA National Electrical Contractors Association (301) 657-3110 http://www.necanet.org/ NeLMA Northeastern Lumber Manufacturers' Association (207) 829-6901 www.nelma.org NEMA National Electrical Manufacturers Association (703) 841-3200 www.nema.org NETA InterNational Electrical Testing Association (303) 697-8441 www.netaworld.org NFPA NFPA (800) 344-3555 www.nfpa.org (617) 770-3000 NFRC National Fenestration Rating Council (301) 589-1776 www.nfrc.org NGA National Glass Association (703) 442-4890 www.glass.org NHLA National Hardwood Lumber Association (800) 933-0318 www.natlhardwood.org (901) 377-1818 NLGA National Lumber Grades Authority (604) 524-2393 www.nlga.org NOFMA National Oak Flooring Manufacturers Association (901) 526-5016 www.nofma.org NRCA National Roofing Contractors Association (800) 323-9545 www.nrca.net (847) 299-9070 NRMCA National Ready Mixed Concrete Association (888) 846-7622 www.nrmca.org (301) 587-1400 NSF NSF International (800) 673-6275 (National Sanitation Foundation International) (734) 769-8010 www.nsf.org NSSGA National Stone, Sand & Gravel Association (800) 342-1415 www.nssga.org (703) 525-8788 NTMA National Terrazzo & Mosaic Association, Inc. (800) 323-9736 www.ntma.com (540) 751-0930 NTRMA National Tile Roofing Manufacturers Association

Page 110: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

REFERENCES 014200 - 14

(See RTI) NWWDA National Wood Window and Door Association (See WDMA) OPL Omega Point Laboratories, Inc. (800) 966-5253 www.opl.com (210) 635-8100 PCI Precast/Prestressed Concrete Institute (312) 786-0300 www.pci.org PDCA Painting & Decorating Contractors of America (800) 332-7322 www.pdca.com (314) 514-7322 PDI Plumbing & Drainage Institute (800) 589-8956 www.pdionline.org (978) 557-0720 PGI PVC Geomembrane Institute (217) 333-3929 Website Unavalible PTI Post-Tensioning Institute (602) 870-7540 www.post-tensioning.org RCSC Research Council on Structural Connections (800) 644-2400 www.boltcouncil.org (312) 670-2400 RFCI Resilient Floor Covering Institute (301) 340-8580 www.rfci.com RIS Redwood Inspection Service (888) 225-7339 calredwood.org (415) 382-0662 RTI Roof Tile Institute (312) 670-4177 (Formerly: NTRMA - National Tile Roofing Manufacturers

Association)

www.ntrma.org SAE SAE International (724) 776-4841 www.sae.org SDI Steel Deck Institute (847) 462-1930 www.sdi.org SDI Steel Door Institute (440) 899-0010 www.steeldoor.org SEFA Scientific Equipment and Furniture Association (516) 294-5424 www.sefalabs.com SGCC Safety Glazing Certification Council (315) 646-2234

Page 111: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

REFERENCES 014200 - 15

www.sgcc.org SIA Security Industry Association (703) 683-2075 www.sefalabs.com SIGMA Sealed Insulating Glass Manufacturers Association (See IGMA) SJI Steel Joist Institute (843) 626-1995 www.steeljoist.org SMA Screen Manufacturers Association (561) 533-0991 www.smacentral.org SMACNA Sheet Metal and Air Conditioning Contractors' (703) 803-2980 National Association www.smacentral.org SPFA Spray Polyurethane Foam Alliance (800) 523-6154 (Formerly: SPI/SPFD - The Society of the Plastics Industry, Inc.; Spray Polyurethane Foam Division) www.sprayfoam.org SPIB Southern Pine Inspection Bureau (The) (850) 434-2611 www.spib.org SPI/SPFD Society of the Plastics Industry, Inc. (The) Spray Polyurethane Foam Division (See SPFA) SPRI SPRI (781) 647-7026 (Single Ply Roofing Institute) www.spri.org SSINA Specialty Steel Industry of North America (800) 982-0355 www.ssina.com (202) 342-8630 SSPC SSPC: The Society for Protective Coatings (877) 281-7772 www.sspc.org (412) 281-2331 STI Steel Tank Institute (847) 438-8265 www.steeltank.com SWI Steel Window Institute (216) 241-7333 www.steelwindows.com SWRI Sealant, Waterproofing, & Restoration Institute (816) 472-7974 www.swrionline.org TCA Tile Council of America, Inc. (864) 646-8453

Page 112: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

REFERENCES 014200 - 16

www.tileusa.com TIA/EIA Telecommunications Industry Association/Electronic (703) 907-7700 Industries Alliance www.tiaonline.org TMS The Masonry Society (303) 939-9700 www.masonrysociety.org TPI Truss Plate Institute, Inc. (608) 833-5900 www.tpinst.org TPI Turfgrass Producers International (800) 405-8873 www.turfgrasssod.org (847) 705-9898 UL Underwriters Laboratories Inc. (800) 285-4476 www.ul.com (847) 272-8800 UNI Uni-Bell PVC Pipe Association (972) 243-3902 www.uni-bell.org USGBC U.S. Green Building Council (202) 828-7422 www.usgbc.org WASTEC Waste Equipment Technology Association (800) 424-2869 www.wastec.org (202) 244-4700 WCLIB West Coast Lumber Inspection Bureau (800) 283-1486 www.wclib.org (503) 639-0651 WCMA Window Covering Manufacturers Association (See WCSC) WCSC Window Covering Safety Council (800) 506-4636 (Formerly: WCMA - Window Covering Manufacturers (212) 661-4261 Association) www.windowcoverings.org WDMA Window & Door Manufacturers Association (800) 223-2301 (Formerly: NWWDA - National Wood Window and (847) 299-5200 Door Association) www.wdma.com WMMPA Wood Moulding & Millwork Producers Association (800) 550-7889 www.wmmpa.com (530) 661-9591

B. Code Agencies: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they shall mean the recognized name of the entities in the following list. Names,

Page 113: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

REFERENCES 014200 - 17

telephone numbers, and Web site addresses are subject to change and are believed to be accurate and up-to-date as of the date of the Contract Documents.

IAPMO International Association of Plumbing and Mechanical Officials (909) 472-4100 www.iapmo.org ICBO International Conference of Building Officials (See ICC) ICBO ES ICBO Evaluation Service, Inc. (See ICC-ES) ICC International Code Council (703) 931-4533 (Formerly: CABO - Council of American Building Officials) www.iccsafe.org ICC-ES ICC Evaluation Service, Inc. (800) 423-6587 www.icc-es.org (562) 699-0543

C. Federal Government Agencies: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they shall mean the recognized name of the entities in the following list. Names, telephone numbers, and Web site addresses are subject to change and are believed to be accurate and up-to-date as of the date of the Contract Documents.

CE Army Corps of Engineers www.usace.army.mil CPSC Consumer Product Safety Commission (800) 638-2772 www.cpsc.gov (301) 504-0990 DOC Department of Commerce (202) 482-2000 www.doc.gov EPA Environmental Protection Agency (202) 260-2090 www.epa.gov FAA Federal Aviation Administration (202) 366-4000 www.faa.gov FCC Federal Communications Commission (202) 225-5322 www.fcc.gov FDA Food and Drug Administration (888) 463-6332 www.fda.gov FHA Federal Highway Administration (410) 962-0093 www.fhwa.dot.gov

Page 114: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

REFERENCES 014200 - 18

GSA General Services Administration (202) 708-5082 www.gsa.gov HUD Department of Housing and Urban Development (202) 708-1112 www.hud.gov LBL Lawrence Berkeley Laboratory National Laboratory (510) 486-4000 www.lbl.gov NIST National Institute of Standards and Technology (301) 975-6478 www.nist.gov OSHA Occupational Safety & Health Administration (800) 321-6742 www.osha.gov (202) 693-1999 PBS Public Building Service (See GSA) PHS Office of Public Health and Science (202) 690 7694 phs.os.dhhs.gov TRB Transportation Research Board (202) 334-2934 www.nas.edu/trb TSA Transportation Security Administration 1(866)-289-9673 www.tsa.gov/public/index.jsp USDA Department of Agriculture (202) 720-2791 www.usda.gov USPS United States Postal Service (202) 268-2000 www.usps.com

D. State Government Agencies: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they shall mean the recognized name of the entities in the following list. Names, telephone numbers, and Web site addresses are subject to change and are believed to be accurate and up-to-date as of the date of the Contract Documents.

DCR Virginia Department of Conservation and Recreation (804) 786-1712 http://www.dcr.state.va.us VDH Virginia Department of Health (540) 829-7340 Culpepper District www.vdh.state.va.us

Page 115: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

REFERENCES 014200 - 19

USBC The Virginia Statewide Building Code (USBC) The Commonwealth of Virginia – Uniform Statewide Building Code

(804) 371- 7160

VDHCD Virginia Department of Housing and Community Development Division of Building and Fire Regulation 501 North 2nd Street Richmond, VA 23219-1321

VDOT Virginia Department of Transportation (703) 383-8368 www.virginiadot.org VDEQ Virginia Department of Environmental Quality 1-800-592-5482 www.deq.state.va.us

1.6 GOVERNING REGULATIONS/AUTHORITIES

A. Contact authorities having jurisdiction directly for information and decisions having a bearing on the work. Names and addresses are subject to change; they are believed to be but are not assured to be accurate and up to date as of the date of the Contract Documents.

B. Codes: The contractor shall adhere to all applicable portions of code standards and specifications in the construction of the work. Unless otherwise noted (reference Division 01 Section “Quality Requirements”), the Authority will review the Contractor’s submittals and construction of the work for code compliance. The Authority’s acceptance of completed construction does not relieve the Contractor from strict compliance with all applicable regulations and codes.

1. Definition: The Metropolitan Washington Airports Authority has a “building department” recognized by the Commonwealth of Virginia. This department is charged with enforcing the Virginia Uniform Statewide Building Code (VUSBC). Where the words “code official”, “department having jurisdiction” or “agency having jurisdiction” is referenced in any code, including the VUSBC or its adopted model codes (ICC), those terms shall mean the Authority Building Official and/or his designated representative.

2. Standards that influence the construction of the project include, but are not limited to, all applicable federal and Commonwealth laws, all applicable codes, rules, regulations and standards applicable to this project.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 014200

Page 116: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final
Page 117: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

TEMPORARY FACILITIES AND CONTROLS 015000 - 1

SECTION 015000 - TEMPORARY FACILITIES AND CONTROLS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and Contract Provisions, Special Provisions, Supplementary Conditions, and other Division 01 Specification Sections apply to this Section.

1.2 SUMMARY

A. This Section includes requirements for temporary facilities and controls, including temporary utilities, support facilities, security, and protection facilities for Contractor staging area.

B. Support facilities include, but are not limited to, the following: 1. Dewatering facilities and drains. 2. Project identification and temporary signs. 3. Waste disposal facilities. 4. Construction aids and miscellaneous services and facilities.

C. Security and protection facilities include, but are not limited to, the following:

1. Environmental protection. 2. Storm water control. 3. Tree and plant protection. 4. Pest control. 5. Site enclosure fence. 6. Security enclosure and lockup. 7. Barricades, warning signs, and lights. 8. Temporary enclosures. 9. Temporary partitions. 10. Fire protection.

D. Related Sections include the following:

1. Division 01 Section "Submittals" for procedures for submitting copies of implementation and termination schedule and utility reports.

2. Divisions 02 through 33 Sections for temporary heat, ventilation, and humidity requirements for products used in those Sections.

1.3 DEFINITIONS

A. Permanent Enclosure: As determined by COTR, permanent or temporary roofing is complete, insulated, and weather tight; exterior walls are insulated and weather tight; and all openings are closed with permanent construction or substantial temporary closures.

Page 118: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

TEMPORARY FACILITIES AND CONTROLS 015000 - 2

1.4 USE CHARGES

A. General: Temporary utilities are available from the Authority at no charge unless otherwise noted. Provide necessary labor and materials to connect to the Authority's utilities at points designated by COTR and extend utilities to trailers, offices, sheds, etc.

1. Provide COTR approved meters for water, natural gas, electricity, and each other utility used for Project. Supply utilities to Subcontractors' temporary facilities through Contractor's meters. The requirement to provide meters for utilities does not imply that the Contractor will be charged for these utilities, except under provisions outlined in this and other Sections.

2. Report consumption of each utility to COTR each month. Contractor is expected to consume reasonable amounts of each utility. Should Contractor, in COTR's opinion, use excessive amounts of any utility or waste a utility, Contractor may be required to pay for temporary utilities.

B. Allow other entities to use temporary services and facilities without cost, including, but are not limited to, the following:

1. The Authority’s construction forces. 2. Occupants of Project. 3. COTR. 4. Architect/Engineer. 5. Testing agencies. 6. Personnel of authorities having jurisdiction.

1.5 SUBMITTALS

A. Shop Drawings: Submit to COTR, for the Authority's review and approval, site plans indicating all temporary facilities, support and security; utility connections and traffic flows. Provide detailed drawings of utility connections and special facilities.

B. Temporary Utility Reports: Submit reports of tests, inspections, meter readings, and similar procedures performed on temporary utilities at both staging area and the Project site. Make all structures weather proof when heated and air-conditioned. Should Contractor, in COTR's opinion fail to keep the heated and cooled structures sealed and weather proof, Contractor may be required to pay for temporary utilities.

C. Implementation and Termination Schedule: Within 15 calendar days of date established for submittal of Contractor's first Construction Schedule, submit a schedule indicating implementation and termination of each temporary utility.

1.6 QUALITY ASSURANCE

A. Regulations: Comply with industry standards and applicable laws and regulations of authorities having jurisdiction, that include but are not limited to, the following:

1. Building Code requirements. 2. Health and safety regulations.

Page 119: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

TEMPORARY FACILITIES AND CONTROLS 015000 - 3

3. Police and Fire Department regulations. 4. Environmental protection regulations. 5. ADA Compliance: All temporary facilities shall be ADA compliant.

B. Standards: Comply with ANSI A10.6, NECA's "Temporary Electrical Facilities," and NFPA 241.

1. Trade Jurisdictions: Assigned responsibilities for installation and operation of temporary utilities are not intended to interfere with trade regulations and union jurisdictions.

2. Electrical Service: Comply with NECA, NEMA, and UL standards and regulations for temporary electrical service. Install service to comply with NFPA 70.

C. Tests and Inspections: Arrange for the Authority's Building Codes/Environmental Department to test and inspect each temporary utility before use. Coordinate with the Authority’s Building Codes/Environmental Department for requirements for certifications, permits, and inspections.

1. Obtain permits from the Authority's Building Codes/Environmental Department for temporary construction and temporary utilities.

D. Fire-retardant and Flame Spread Requirements: Unless otherwise noted, fire – retardant treat all wood and wood composition products utilized in the Project and preservative treat all wood utilized on the exterior of any building. Preservative treat all wood utilized on other items indicated or specified with preservative treatment. Provide lumber and plywood with an Underwriters’ Laboratory (UL) stamp certifying a value of 25 or less flame spread and a value of 200 or less smoke development. Fire retardant lumber shall not be ripped or milled.

1.7 PROJECT CONDITIONS

A. Conditions of Use: The following conditions apply to use of temporary services, permanent services, and facilities by all parties engaged in the Work:

1. Keep temporary services and facilities clean and neat. 2. Relocate temporary services and facilities as required by progress of the Work. 3. Take necessary fire-prevention measures. 4. Do not overload facilities. 5. Do not allow hazardous, dangerous, or unsanitary conditions, or public nuisances to

develop or persist on-site.

1.8 CONTRACTOR PERSONNEL PARKING

A. Contractor is limited to the construction area as defined in the contract documents the parking and staging of both company-owned and personal vehicles will be limited to the construction area as defined in the contract documents. There is no other area available for contractor parking at Ronald Reagan Washington National Airport. Contractors are allowed to use “Employee Only” shuttle busses. Control and enforce these limitations for all personnel including Subcontractor's personnel.

B. If off-airport parking or storage of materials and equipment is required, Contractor will be

responsible for the maintenance, security, safety, and operation of these facilities off-airport

Page 120: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

TEMPORARY FACILITIES AND CONTROLS 015000 - 4

parking or storage of materials and equipment is required. This cost will be considered part of the Contractor's general conditions. Transportation of materials, equipment, and personnel to the Work site is the responsibility of the Contractor.

C. Contractor is responsible for busing his employees from the off airport parking lot to the Contractor's Staging areas or work areas.

PART 2 - PRODUCTS

2.1 MATERIALS

A. General: Provide new materials. Undamaged, previously used materials in serviceable condition may be used if approved by COTR. Provide materials suitable for use intended.

B. Paint: Comply with requirements in Division 09 Sections "Exterior Painting." and "Interior Painting"

C. Water: Potable.

D. Temporary Fuel Tanks: For requirements for temporary fuel tanks see Division 31 Section “Storm Water Pollution Protection Plan.” Comply with applicable safety and environmental regulations for temporary surface fuel tanks. Location and installation of tanks will be subject to review and approval of COTR and the Authority's Fire Marshal.

2.2 EQUIPMENT

A. General: Provide new equipment suitable for use intended. If acceptable to COTR, undamaged, previously used equipment in serviceable condition may be used.

B. Field Offices: Mobile units with lockable entrances, operable windows, and serviceable finishes; heated and air conditioned; on foundations adequate for normal loading, and provided with proper tie-downs.

C. Self-Contained Toilet Units: Single-occupant units of chemical, aerated re-circulation, or combustion type; vented; fully enclosed with a glass-fiber-reinforced polyester shell or similar nonabsorbent material.

D. Drinking-Water Fixtures: Containerized, tap-dispenser, bottled-water drinking-water units, including paper cup supply.

1. Where power is accessible, provide electric water coolers to maintain dispensed water temperature at 45 to 55 deg F.

E. Heating Equipment: Unless COTR authorizes use of permanent heating system, provide temporary heating units with individual space thermostatic control.

1. Use of gasoline-burning space heaters, open-flame heaters, or salamander-type heating units is prohibited.

Page 121: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

TEMPORARY FACILITIES AND CONTROLS 015000 - 5

2. Heating Units: Listed and labeled, by a testing agency acceptable to authorities having jurisdiction, and marked for intended use for type of fuel being consumed.

F. Electrical Outlets: Properly configured, NEMA-polarized outlets that will prevent insertion of 110v or 120v plugs into higher-voltage outlets, and equipped with ground-fault circuit interrupters with reset button.

G. Power Distribution System Circuits: Where permitted, overhead, and visible wiring circuits, not exceeding 125-V ac, 20-A rating, and lighting circuits may be nonmetallic-sheathed cable.

H. Electrical Power Cords: Provide grounded extension cords; use hard-service as defined by NFPA 70, Article 400, where exposed to abrasion and traffic. If single lengths of extension cords will not reach areas where construction activities are in progress provide waterproof connectors to connect separate lengths of electrical extension cords.

PART 3 - EXECUTION

3.1 INSTALLATION, GENERAL

A. Prior to installation of temporary facilities and utilities, submit to the COTR a site layout providing locations and details of the facilities and utilities.

B. Use qualified personnel for installation of temporary facilities. Locate facilities where they will serve Project adequately and result in minimum interference with performance of the Work. Relocate and modify facilities as required.

C. Provide each facility ready for use when needed to avoid delay. Maintain and modify as required. Do not remove until facilities are no longer needed or are replaced by authorized use of completed permanent facilities.

3.2 CONTRACTOR STAGING AREA - GENERAL

A. Contractor will be allowed to store and stage his materials in a staging area located on Airport property as indicated or as designated by the COTR for such purposes. Space is limited to area indicated. COTR and Contractor will make a joint site visit to document condition of staging area prior to occupancy. Take photos for the record.

B. Upon completion of Construction, remove all temporary staging area facilities and return the areas to their original condition.

C. Park construction equipment in the storage site or storage area identified by the COTR when equipment is not engaged in construction activity.

D. Do not stockpile construction materials, spoils, debris or refuse in any area other than that specifically approved for such purpose by the COTR.

E. Constrain stockpiled material in a manner to prevent its movement by wind, jet blast or propeller wash.

Page 122: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

TEMPORARY FACILITIES AND CONTROLS 015000 - 6

3.3 TEMPORARY UTILITY INSTALLATION

A. General: Provide temporary service for each utility required. Comply with requirements of the Authority's Building Codes Manual, the Authority's Construction Safety Manual, and the requirements of all Sections of these specifications.

1. Arrange with COTR for time when service can be interrupted, if necessary, to make connections for temporary services. For additional information on utility outages see Division 01 Section, "Summary."

2. Provide adequate capacity at each stage of construction. Before temporary utility is available, provide trucked-in services.

3. Perform work associated with utilities owned by the Authority as approved by the Authority.

4. See additional information in Contract Provisions entitled "Availability and Use of Utility Service."

B. Sewers and Drainage: If sewers are available, provide temporary connections to remove effluent that can be discharged lawfully. If sewers are not available or cannot be used, provide drainage ditches, dry wells, stabilization ponds, and similar facilities. If neither sewers nor drainage facilities can be lawfully used for discharge of effluent, provide containers to remove and dispose of effluent off-site in a lawful manner.

C. When using Authority sewers:

1. Filter out excessive soil, construction debris, chemicals, oils, and similar contaminants that might clog sewers or pollute waterways before discharge.

2. Connect temporary sewers to the Authority's system as directed by COTR. 3. Maintain temporary sewers and drainage facilities in a clean, sanitary condition. After

heavy use, restore normal conditions promptly. 4. Provide temporary filter beds, settlement tanks, separators, and similar devices to purify

effluent to levels acceptable to authorities having jurisdiction.

D. Sanitary Facilities: Provide temporary toilets, wash facilities, and drinking-water fixtures. Comply with regulations and health codes for type, number, location, operation, and maintenance of fixtures and facilities.

1. Disposable Supplies: Provide toilet tissue, paper towels, paper cups, and similar disposable materials for each facility. Maintain adequate supply. Provide covered waste containers for disposal of used material.

2. Toilets: Install self-contained toilet units, located as approved by COTR. Shield toilets to ensure privacy. Provide separate facilities for male and female personnel. Use of the Authority's existing toilet facilities will not be permitted.

3. Wash Facilities: Install wash facilities supplied with potable water at convenient locations for personnel who handle materials that require wash up. Dispose of drainage properly. Supply cleaning compounds appropriate for each type of material handled.

a. Provide safety showers, eyewash fountains, and similar facilities for convenience, safety, and sanitation of personnel.

4. Drinking-Water Facilities: Provide bottled-water, drinking-water units.

Page 123: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

TEMPORARY FACILITIES AND CONTROLS 015000 - 7

a. Where power is accessible, provide electric water coolers to maintain dispensed water temperature at 45 to 55 deg F.

5. Locate toilets and drinking-water fixtures so personnel need not walk more than or 500 feet horizontally to facilities.

E. Heating and Cooling: Provide temporary heating and cooling required by construction activities for curing or drying of completed installations or for protecting installed construction from adverse effects of low temperatures or high humidity. Select equipment from that specified that would not have a harmful effect on completed installations or elements being installed.

1. Maintain a minimum temperature of 50 deg F in permanently enclosed portions of building for normal construction activities, and 65 deg F for finishing activities and areas where finished Work has been installed.

F. Ventilation and Humidity Control: Provide temporary ventilation and humidity control required by construction activities for curing or drying of completed installations or for protecting installed construction from adverse effects of high humidity. Select equipment from that specified that would not have a harmful effect on completed installations or elements being installed. Coordinate ventilation requirements to produce ambient condition required and minimize energy consumption. Provide and operate either exhaust or supply fans/blowers, or both, sufficient to ventilate work areas adequately.

G. Electric Power Service: Provide weatherproof, grounded electric power service and distribution system of sufficient size, capacity, and power characteristics during construction period. Include meters, transformers, overload-protected disconnecting means, automatic ground-fault interrupters, and main distribution switchgear. Provide kilowatt-hour meters with demand capability.

1. Install electric power service underground, unless overhead service is authorized by COTR.

2. Connect temporary service to the Authority's existing power source, as directed by COTR.

H. Electrical Distribution: Provide receptacle outlets adequate for connection of power tools and equipment.

1. Provide waterproof connectors to connect separate lengths of electrical power cords if single lengths will not reach areas where construction activities are in progress. Do not exceed safe length-voltage ratio.

2. Provide warning signs at power outlets other than 110 to 120 V. 3. Provide metal conduit, tubing, or metallic cable for wiring exposed to possible damage.

Provide rigid steel conduits for wiring exposed on grades, floors, decks, or other traffic areas.

4. Provide metal conduit enclosures or boxes for wiring devices. 5. Provide 4-gang outlets, spaced so 100-foot extension cord can reach each area for power

hand tools and task lighting. Provide a separate 125-V ac, 20-A circuit for each outlet.

Page 124: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

TEMPORARY FACILITIES AND CONTROLS 015000 - 8

I. Lighting: Provide temporary lighting with local switching that provides adequate illumination for construction operations and traffic conditions.

1. Provide and operate temporary lighting that fulfills security and protection requirements without operating entire system.

2. Provide exterior-yard site lighting that will provide adequate illumination for construction operations, traffic conditions, and signage visibility when the Work is being performed. Provide exterior yard and site lighting aligned as directed by the COTR. Provide lighting so as not to interfere with ground, air traffic and air traffic control.

3. Install lighting for Project identification signs.

J. Telephone Service: Provide temporary telephone service for key personnel engaged in construction activities, throughout the construction period. Install telephones on separate lines for each temporary office and first aid station. Where an office has more that two occupants, install a telephone for each additional occupant or pair of occupants. Provide telephones with exchanges within the Metropolitan Washington service area. The Authority owns and operates an airport-wide Airport Communication System (ACS). This system accommodates all normal telecommunications service requirements, i.e., local, long distance, fax, data, etc. The Contractor may obtain information about and choose to utilize this service by contacting the ACS Help Desk at (703) 417-8300.

1. At each telephone, post a list of emergency telephone numbers approved by COTR. 2. Provide a portable cellular telephone for superintendent's use in making and receiving

telephone calls when away from field office. 3. At the present time the Authority uses cell phones to communicate. The Authority uses

Nextel service.

3.4 SUPPORT FACILITIES INSTALLATION

A. General: Comply with the following:

1. Locate field offices, storage sheds, sanitary facilities, and other temporary construction and support facilities for easy access.

2. Provide incombustible construction for offices, shops, and sheds located within construction area or within 30 feet of building lines. Comply with NFPA 241 and USBC.

B. Dewatering Facilities and Drains: Comply with requirements in applicable Division 31 and Division 32 Sections for temporary drainage and dewatering facilities and operations not directly associated with construction activities included in individual Sections. Where feasible, use same facilities. Maintain Project site, excavations, and construction free of water.

1. Dispose of rainwater in a lawful manner that will not result in flooding Project or adjoining property nor endanger permanent Work or temporary facilities.

2. Remove snow and ice as required to minimize accumulations.

C. Project Identification and Temporary Signs: Prepare Project identification and other signs in sizes indicated. Install signs where indicated or where directed by COTR to inform public and persons seeking entrance to Project. Provide two Project signs.

Page 125: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

TEMPORARY FACILITIES AND CONTROLS 015000 - 9

1. Engage an experienced sign painter to apply graphics for Project identification signs. Comply with details indicated.

2. Prepare temporary signs to provide directional information to construction personnel and visitors.

3. Construct signs of exterior-type, Grade B-B, high-density concrete form overlay plywood in sizes and thickness indicated. Support on nominal 4-inch-by-4-inch-by-10-foot-long posts or framing of preservative-treated wood or steel.

4. Paint sign panel and applied graphics with exterior-grade alkyd gloss enamel over exterior primer.

5. The following signs will be allowed on the Project:

a. Identifying captions over offices. b. Other signs as required by the Contract Documents.

6. Take necessary steps to prevent installation of unauthorized signs and, should any appear, remove them immediately. Repair and repaint damage caused thereby at no additional cost to the Authority.

7. No more that two Project Identification Signs will be permitted. Project identification signs are the only signs on which the Contractors name and logo will be permitted.

D. Waste Disposal Facilities: Provide waste-collection containers in sizes adequate to handle waste from construction operations. Containerize and clearly label hazardous, dangerous, or unsanitary waste materials separately from other waste. Comply with Division 01 Section "Execution " for progress cleaning requirements.

1. If required by COTR, provide separate containers, clearly labeled, for each type of waste material to be deposited.

2. Develop a waste management plan for Work performed on Project. Indicate types of waste materials Project will produce and estimate quantities of each type. Provide detailed information for on-site waste storage and separation of recyclable materials. Provide information on destination of each type of waste material and means to be used to dispose of all waste materials.

E. Janitorial Services: Provide janitorial services on a daily basis for temporary offices, first-aid stations, toilets, wash facilities, lunchrooms, and similar areas.

F. Storage and Fabrication Sheds: Provide sheds sized, furnished, and equipped to accommodate materials and equipment involved, including temporary utility services. Sheds may be open shelters or, if permitted by COTR, fully enclosed spaces within building or elsewhere on-site subject to approval of COTR.

1. Construct framing, sheathing, and siding using fire-retardant-treated lumber and plywood.

2. Paint exposed lumber and plywood with exterior-grade acrylic-latex emulsion over exterior primer.

3. Submit the design of storage structures of more than 150 sq. ft. to COTR for review and approval by the Authority's Building Codes/Environmental Department.

Page 126: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

TEMPORARY FACILITIES AND CONTROLS 015000 - 10

3.5 SECURITY AND PROTECTION FACILITIES INSTALLATION

A. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction in ways and by methods that comply with environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects. Avoid using tools and equipment that produce harmful noise. Restrict use of noisemaking tools and equipment to hours of 11:00 p.m. to 5:00 a.m., unless directed otherwise by the COTR, which will minimize complaints from persons or firms near Project site.

B. Storm water Control: Provide earthen embankments and similar barriers in and around excavations and sub grade construction, sufficient to prevent flooding by runoff of storm water from heavy rains.

C. Barricades, Warning Signs, and Lights: Comply with standards and code requirements for erecting structurally adequate barricades. Paint with appropriate colors, graphics, and warning signs to inform personnel and public of possible hazard. Where appropriate and needed, provide lighting, including flashing red or amber lights. See the Authority's Construction Safety Manual for additional requirements.

D. Temporary Fire Protection: Until fire-protection needs are supplied by permanent facilities, install and maintain temporary fire-protection facilities of types needed to protect against reasonably predictable and controllable fire losses. Comply with NFPA 241 and VUSBC.

1. Provide fire extinguishers, installed on walls on mounting brackets, visible and accessible from space being served, with sign mounted above.

a. Field Offices: Class A, stored-pressure, water-type extinguishers. b. Other Locations: Class ABC, dry-chemical extinguishers or a combination of

extinguishers of NFPA-recommended classes for exposures. c. Locate fire extinguishers per NFPA 10 and where convenient and effective for

their intended purpose; provide not less than one extinguisher on each floor at or near each usable stairwell.

2. Store combustible materials in containers in fire-safe locations. 3. Maintain unobstructed access to fire extinguishers, fire hydrants, temporary fire-

protection facilities, stairways, and other access routes for firefighting. Prohibit smoking in hazardous fire-exposure areas.

4. Supervise welding operations, combustion-type temporary heating units, and similar sources of fire ignition.

5. Permanent Fire Protection: At earliest feasible date in each area of Project, complete installation of permanent fire-protection facility, including connected services, and place into operation and use. Instruct key personnel on use of facilities.

6. Develop and supervise an overall fire-prevention and first-aid fire-protection program for personnel at Project site. Review needs with local fire department and establish procedures to be followed. Instruct personnel in methods and procedures. Post warnings and information.

7. Provide temporary standpipes with fire hose valve connections for fire protection.

Page 127: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

TEMPORARY FACILITIES AND CONTROLS 015000 - 11

E. Storage: Where materials and equipment are stored, and are of value or attractive for theft, provide secure lockup. Enforce discipline in connection with installation and release of material to minimize opportunity for theft and vandalism.

3.6 OPERATION, TERMINATION, AND REMOVAL

A. Supervision: Enforce strict discipline in use of temporary facilities. Limit availability of temporary facilities to essential and intended uses to minimize waste and abuse.

B. Maintenance: Maintain facilities in good operating condition until removal. Protect from damage caused by freezing temperatures and similar elements.

1. Maintain operation of temporary enclosures, heating, cooling, humidity control, ventilation, and similar facilities on a 24-hour basis where required to achieve indicated results and to avoid possibility of damage.

2. Prevent water-filled piping from freezing. Maintain markers for underground lines. Protect from damage during excavation operations.

C. Temporary Facility Changeover: Unless Contractor is able to utilize permanent fire protection, do not change over from using temporary security and protection facilities to permanent facilities until Substantial Completion.

D. Termination and Removal: Remove each temporary facility when need for its service has ended, when it has been replaced by authorized use of a permanent facility, or no later than Substantial Completion. Complete or, if necessary, restore permanent construction that may have been delayed because of interference with temporary facility. Repair damaged Work, clean exposed surfaces, and replace construction that cannot be satisfactorily repaired.

1. Properly recondition and restore those portions of the site occupied by temporary facilities and controls to condition acceptable to COTR, at least equal to condition at time of start of Work, unless otherwise authorized in writing by COTR.

2. Materials and facilities that constitute temporary facilities are the property of Contractor. Owner reserves right to take possession of Project identification signs.

3. Remove temporary paving not intended for or acceptable for integration into permanent paving. Where area is intended for landscape development, remove soil and aggregate fill that do not comply with requirements for fill or subsoil. Remove materials contaminated with road oil, asphalt and other petrochemical compounds, and other substances that might impair growth of plant materials or lawns. Repair or replace roadway paving, curbs, and sidewalks at temporary entrances, as required by authorities having jurisdiction.

4. At Substantial Completion, clean and renovate permanent facilities used during construction period. Comply with final cleaning requirements in Division 01 Section "Project Closeout."

END OF SECTION 015000

Page 128: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final
Page 129: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

PRODUCT REQUIREMENTS 016000 - 1

SECTION 016000 - PRODUCT REQUIREMENTS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings, Contract Provisions, Special Provisions, Supplementary Conditions, and other Division 01 Specification Sections apply to this Section.

1.2 SUMMARY

A. This Section includes the following administrative and procedural requirements: selection of products for use in Project; product delivery, storage, and handling; manufacturers' standard warranties on products; special warranties; product substitutions; and comparable products.

1. This Section includes substitutions made for "or as approved by the Authority" items.

B. Related Sections include the following: 1. Division 01 Section "References" for applicable industry standards for products

specified. 2. Divisions 02 through 33 Sections for specific requirements for warranties on products

and installations specified to be warranted.

1.3 DEFINITIONS

A. Products: Items purchased for incorporating into the Work, whether purchased for Project or taken from previously purchased stock. The term "product" includes the terms "material," "equipment," "system," and terms of similar intent.

1. Named Products: Items identified by manufacturer's product name, including make or model number or other designation, shown or listed in manufacturer's published product literature that is current as of date of the Contract Documents.

2. New Products: Items that have not previously been incorporated into another project or facility , except that products consisting of recycled-content materials are allowed, unless explicitly stated otherwise. Products salvaged or recycled from other projects are not considered new products.

3. Comparable Product: Product that is demonstrated and approved through submittal process, or where indicated as a product substitution, to have the indicated qualities related to type, function, dimension, in-service performance, physical properties, appearance, and other characteristics that equal or exceed those of specified product.

B. Substitutions: Changes in products, materials, equipment, and methods of construction from those required by the Contract Documents and proposed by Contractor.

C. Basis-of-Design Product Specification: Where a specific manufacturer's product is named and accompanied by the words "basis of design," including make or model number or other

Page 130: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

PRODUCT REQUIREMENTS 016000 - 2

designation, to establish the significant qualities related to type, function, dimension, in-service performance, physical properties, appearance, and other characteristics for purposes of evaluating comparable products of other named manufacturers.

1.4 SUBMITTALS

A. Product List: Submit a list, in tabular form acceptable to COTR, showing specified products. Include generic names of products required. Include manufacturer's name and proprietary product names for each product.

1. Coordinate product list with Contractor's Construction Schedule and Submittals Schedule.

2. Form: Tabulate information for each product under the following column headings:

a. Specification Section number and title. b. Generic name used in the Contract Documents. c. Proprietary name, model number, and similar designations. d. Manufacturer's name and address. e. Supplier's name and address. f. Installer's name and address. g. Projected delivery date or time span of delivery period. h. Identification of items that require early submittal approval for scheduled delivery

date. i. Item Tag Number or similar ID if identified in the drawings j. Location (room number from the drawings) k. Serial Number (once available)

3. Initial Submittal: Within 90 calendar days after the Notice to Proceed, submit 3 copies of initial product list. Include a written explanation for omissions of data and for variations from the Contract requirements.

4. COTR's Action: COTR will respond in writing to Contractor within 15 calendar days of receipt of initial product list. COTR's response will include a list of unacceptable product selections and a brief explanation of reasons for this action. COTR's response, or lack of response, does not constitute a waiver of requirement that products comply with the Contract Documents.

5. Updated submittal: Submit updated product list every 30 days following initial submittal. The updated list shall be submitted in approved electronic spread sheet format with additional fields as required by COTR.

6. Completed List: Submit 10 hard copies and one electronic copy of completed product list 30 calendar days before requesting inspection for substantial completion. Include a written explanation for omissions of data and for variations from the Contract requirements.

B. Substitution Requests: Submit six copies of each request for consideration. Identify product or fabrication or installation method to be replaced. Include Section number and title and Drawing numbers and titles.

Page 131: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

PRODUCT REQUIREMENTS 016000 - 3

1. Substitution Request Form: Submit requests in the form and according to procedures required for Contract Modification proposals supplied to Contractor at the pre-construction meeting or as directed by COTR. Do not submit requests for substitutions as "Requests for Information" (RFIs).

2. Documentation: Show compliance with requirements for substitutions and the following, as applicable:

a. Statement indicating why specified material or product cannot be provided. b. Coordination information, including a list of changes or modifications needed to

other parts of the Work and to construction performed by the Authority and separate contractors that will be necessary to accommodate proposed substitution.

c. Detailed comparison of significant qualities of proposed substitution with those of the Work specified. Significant qualities may include attributes such as performance, weight, size, durability, visual effect, and specific features and requirements indicated.

d. Product Data, including drawings and descriptions of products and fabrication and installation procedures.

e. Samples, where applicable or requested. f. List of similar installations for completed projects with project names and

addresses and names and addresses of architects and owners. g. Material test reports from a qualified testing agency indicating and interpreting test

results for compliance with requirements indicated. h. Research/evaluation reports evidencing compliance with building code in effect for

Project, from a model code organization acceptable to authorities having jurisdiction.

i. Detailed comparison of Contractor's Construction Schedule using proposed substitution with products specified for the Work, including effect on the overall Contract Time. If specified product or method of construction cannot be provided within the Contract Time, include letter from manufacturer, on manufacturer's letterhead, stating lack of availability or delays in delivery.

j. Cost information, including a proposal of change, if any, in the Contract Price. k. Contractor's certification that proposed substitution complies with requirements in

the Contract Documents and is appropriate for applications indicated. l. Contractor's waiver of rights to additional payment or time that may subsequently

become necessary because of failure of proposed substitution to produce indicated results.

m. Failure by Contractor to include the above requirements in the submittal may cause rejection of the submittal in its entirety.

3. COTR's Action: If necessary, COTR will request additional information or documentation for evaluation within 15 calendar days of receipt of a request for substitution. COTR will notify Contractor of acceptance or rejection of proposed substitution within 15 calendar days of receipt of request, or two weeks of receipt of additional information or documentation, whichever is later.

a. Form of Acceptance: Change notice. b. Use product specified if COTR couldn’t make a decision on use of a proposed

substitution within time allocated.

Page 132: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

PRODUCT REQUIREMENTS 016000 - 4

C. Comparable Product Requests: Submit three copies of each request for consideration. Identify product or fabrication or installation method to be replaced. Include Specification Section number and title and Drawing numbers and titles.

1. COTR’s Action: If necessary, COTR will request additional information or documentation for evaluation within 7 working days of receipt of a comparable product request. COTR will notify Contractor of approval or rejection of proposed comparable product request within 15 calendar days of receipt of request, or 7 calendar days of receipt of additional information or documentation, whichever is later.

a. Form of Approval: As specified in Division 01 Section "Submittals." b. Use product specified if COTR couldn’t make a decision on use of a comparable

product request within time allocated.

D. Basis-of-Design Product Specification Submittal: Comply with requirements in Division 01 Section "Submittals." Show compliance with requirements.

1.5 QUALITY ASSURANCE

A. Compatibility of Options: If Contractor is given option of selecting between two or more products for use on Project, product selected shall be compatible with products previously selected, even if previously selected products were also options.

1.6 PRODUCT DELIVERY, STORAGE, AND HANDLING

A. Deliver, store, and handle products using means and methods that will prevent damage, deterioration, and loss, including theft. Comply with manufacturer's written instructions.

B. Delivery and Handling:

1. Schedule delivery to minimize long-term storage at Project site and to prevent overcrowding of construction spaces.

2. Coordinate delivery with installation time to ensure minimum holding time for items that are flammable, hazardous, easily damaged, or sensitive to deterioration, theft, and other losses.

3. Deliver products to Project site in an undamaged condition in manufacturer's original sealed container or other packaging system, complete with labels and instructions for handling, storing, unpacking, protecting, and installing.

4. Inspect products on delivery to ensure compliance with the Contract Documents and to ensure that products are undamaged and properly protected.

C. Storage:

1. Store products to allow for inspection and measurement of quantity or counting of units. 2. Store materials in a manner that will not endanger Project structure. 3. Store products that are subject to damage by the elements, under cover in a weather tight

enclosure above ground, with ventilation adequate to prevent condensation. 4. Comply with product manufacturers written instructions for temperature, humidity,

ventilation, and weather-protection requirements for storage.

Page 133: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

PRODUCT REQUIREMENTS 016000 - 5

5. Store foam plastic from exposure to sunlight, except to extent necessary for period of installation and concealment.

6. Store cementitious products and materials on elevated platforms. 7. Protect stored products from damage. 8. Replace products and materials damaged by the elements due to improper storage at no

additional cost to the Authority. This damage can be, but not limited to, oxidization, mold, mildew, warping, and rust.

1.7 PRODUCT WARRANTIES

A. Warranties specified in other Sections shall be in addition to, and run concurrent with, other warranties required by the Contract Documents. Manufacturer's disclaimers and limitations on product warranties do not relieve Contractor of obligations under requirements of the Contract Documents.

1. Manufacturer's Warranty: Preprinted written warranty published by individual manufacturer for a particular product and specifically endorsed by manufacturer to Authority.

2. Special Warranty: Written warranty required by or incorporated into the Contract Documents, either to extend time limit provided by manufacturer's warranty or to provide more rights for Authority.

B. Special Warranties: Prepare a written document that contains appropriate terms and identification, ready for execution. Submit a draft for approval before final execution.

1. Manufacturer's Standard Form: Modified to include Project-specific information and properly executed.

2. Specified Form: When specified forms are included with the Specifications, prepare a written document using appropriate form properly executed.

3. Refer to Divisions 02 through 33 Sections for specific content requirements and particular requirements for submitting special warranties.

C. Submittal Time: Comply with requirements in Division 01 Section "Project Closeout."

PART 2 - PRODUCTS

2.1 PRODUCT OPTIONS

A. General Product Requirements: Provide products that comply with the Contract Documents, that are undamaged and, unless otherwise indicated, that are new at time of installation.

1. Provide products complete with accessories, trim, finish, fasteners, and other items needed for a complete installation and indicated use and effect.

2. Standard Products: If available, and unless custom products or nonstandard options are specified, provide standard products of types that have been produced and used successfully in similar situations on other projects.

3. The Authority reserves the right to limit selection to products with warranties not in conflict with requirements of the Contract Documents.

Page 134: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

PRODUCT REQUIREMENTS 016000 - 6

4. Where products are accompanied by the term "as selected," COTR will make selection. 5. Where products are accompanied by the term "match sample," sample to be matched is

COTR's. 6. Descriptive, performance, and reference standard requirements in the Specifications

establish "salient characteristics" of products. 7. "Or as approved by the Authority": Note that products submitted under an "or as

approved by the Authority” provision are considered to be substitutions. Substitutions shall follow the requirements of Paragraph VII-42 of Contract Provisions and provisions in "Comparable Products" Article to obtain approval for use of an unnamed product.

B. Product Selection Procedures:

1. Product: Where Specifications name a single product and manufacturer, provide the named product that complies with requirements.

2. Manufacturer/Source: Where Specifications name a single manufacturer or source, provide a product by the named manufacturer or source that complies with requirements.

3. Products: Where Specifications include a list of names of both products and manufacturers, provide one of the products listed that complies with requirements.

4. Manufacturers: Where Specifications include a list of manufacturers' names, provide a product by one of the manufacturers listed that complies with requirements.

5. Available Products: Where Specifications include a list of names of both products and manufacturers, provide one of the products listed, or an unnamed product, that complies with requirements. Comply with provisions in Part - 2 "Comparable Products" Article for consideration of an unnamed product.

6. Available Manufacturers: Where Specifications include a list of manufacturers, provide a product by one of the manufacturers listed, or an unnamed manufacturer, that complies with requirements. Comply with provisions in Part - 2 "Comparable Products" Article for consideration of an unnamed product.

7. Product Options: Where Specifications indicate that sizes, profiles, and dimensional requirements on Drawings are based on a specific product or system, provide the specified product or system. Comply with provisions in Part 2 "Product Substitutions" Article for consideration of an unnamed product or system.

8. Basis-of-Design Product: Where Specifications name a product and include a list of manufacturers, provide the specified product or a comparable product by one of the other named manufacturers. Drawings and Specifications indicate sizes, profiles, dimensions, and other characteristics that are based on the product named. Comply with provisions in Part 2 "Comparable Products" Article for consideration of an unnamed product by the other named manufacturers.

9. Visual Matching Specification: Where Specifications require matching an established Sample, select a product that complies with requirements and matches COTR's sample. COTR's decision will be final on whether a proposed product matches.

a. If no product available within specified category matches and complies with other specified requirements, comply with provisions in Part 2 "Product Substitutions" Article for proposal of product.

10. Visual Selection Specification: Where Specifications include the phrase "as selected from manufacturer's colors, patterns, textures" or a similar phrase, select a product that complies with other specified requirements.

Page 135: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

PRODUCT REQUIREMENTS 016000 - 7

a. Standard Range: Where Specifications include the phrase "standard range of colors, patterns, textures" or similar phrase, COTR will select color, pattern, density, or texture from manufacturer's product line that does not include premium items.

b. Full Range: Where Specifications include the phrase "full range of colors, patterns, textures" or similar phrase, COTR will select color, pattern, density, or texture from manufacturer's product line that includes both standard and premium items.

2.2 PRODUCT SUBSTITUTIONS

A. Timing: COTR will consider requests for substitution if received within 60 calendar days after issuance of the Notice to Proceed. Requests received after that time may be considered or rejected at the sole discretion of the Contracting Officer.

B. Conditions: COTR will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, COTR will return requests without action, except to record noncompliance with these requirements:

1. Requested substitution does not require extensive revisions to the Contract Documents. 2. Requested substitution is consistent with the Contract Documents and will produce

indicated results. 3. Substitution request is fully documented and properly submitted. 4. Requested substitution will not adversely affect Contractor's Construction Schedule. 5. Requested substitution has received necessary approvals of authorities having

jurisdiction. 6. Requested substitution is compatible with other portions of the Work. 7. Requested substitution has been coordinated with other portions of the Work. 8. Requested substitution provides specified warranty. 9. If requested substitution involves more than one contractor, requested substitution has

been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.

C. Contractor's submittal and COTR's review or approval of Shop Drawings, Product Data, or Samples that relate to a substitute does not by itself constitute a final approval of the requested substitution, nor does it relieve Contractor from fulfilling existing Contract requirements.

D. If a substitution offers a substantial advantage to the Authority, in terms of cost, time, energy conservation, or other considerations of merit, after deducting offsetting responsibilities the Authority may be required to bear, the substitution shall be submitted as a Value Engineering Change Proposal.

2.3 COMPARABLE PRODUCTS

A. Conditions: COTR will consider Contractor's request for comparable product when the following conditions are satisfied. If the following conditions are not satisfied, COTR will return requests without action, except to record noncompliance with these requirements:

Page 136: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

PRODUCT REQUIREMENTS 016000 - 8

1. Evidence that the proposed product does not require extensive revisions to the Contract Documents, it is consistent with the Contract Documents, it will produce the indicated results, and that it is compatible with other portions of the Work.

2. Detailed comparison of significant qualities of proposed product with those named in the Specifications. Significant qualities include attributes such as performance, weight, size, durability, visual effect, and specific features and requirements indicated.

3. Evidence that proposed product provides specified warranty. 4. List of similar installations for completed projects with project names and addresses and

names and addresses of architects and owners, if requested. 5. Samples, if requested.

PART 3 - EXECUTION (Not Used)

END OF SECTION 016000

Page 137: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

MOBILIZATION/DEMOBILIZATION 017113 - 1

SECTION 017113 - MOBILIZATION/DEMOBILIZATION

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This work shall consist of the performance of construction preparatory operations, including the movement of personnel, equipment, and materials to the project site, and for establishment and maintenance of the Contractor's Staging Area and facilities necessary to begin and sustain work on the Contract. In addition, the following items are to be included in the cost of mobilization:

1. Obtaining personnel identification and other items as necessary to facilitate work. 2. Monthly recurring costs and costs for photographic and record documentation for the

duration of the project. 3. Utility investigation and test pitting. 4. Barrier relocation as shown on plans 5. Any costs related to security and escorting 6. Initial Schedule/Manuals/Submittals 7. Other work items necessary to begin construction, as shown in the plans. 8. Demobilization efforts at completion of the Project.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION (NOT USED)

PART 4 - METHOD OF MEASUREMENT

A. Mobilization/Demobilization will be measured on a lump sum basis.

PART 5 - BASIS OF PAYMENT

A. This item will be paid for at the Contract lump sum price, which shall be full compensation for performing the work specified and the furnishing of all materials, labor, tools, equipment, and incidentals necessary to mobilize and subsequently demobilize the construction operations.

B. The mobilization/demobilization item shall not exceed 28 percent of the total Contract Amount, excluding the amount of this item. The first payment of 40 percent of the lump sum price item will be made on the first estimate following partial mobilization and the initiation of construction work including set up of the staging area and facilities. Payments of 20 percent of the lump sum price item will be made on the two (2) subsequent estimates following the completion of substantial mobilization. The final 20 percent of the lump sum price will be made after demobilization has been completed and the site has been cleared to the satisfaction of the COTR.

Page 138: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

MOBILIZATION/DEMOBILIZATION 017113 - 2

Payment will be made under:

Item 017113-5.1 Mobilization/Demobilization - per lump sum.

END OF SECTION 017113

Page 139: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

EXECUTION 017300 - 1

SECTION 017300 - EXECUTION

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings, Contract Provisions, Special Provisions, Supplementary Conditions, and other Division 01 Specification Sections apply to this Section.

1.2 SUMMARY

A. This Section includes general procedural requirements governing execution of the Work including, but not limited to, the following:

1. Construction layout. 2. Field engineering and surveying. 3. General installation of products. 4. Coordination of Authority-installed products. 5. Progress cleaning. 6. Starting and adjusting. 7. Protection of installed construction. 8. Correction of the Work.

B. Related Sections include the following:

1. Division 01 Section "Project Management and Coordination" for procedures for coordinating field engineering with other construction activities.

1.3 SUBMITTALS

A. Qualification Data: Submit qualification data for land surveyors.

B. Certificates: Submit certificate signed and sealed by land surveyor certifying that location and elevation of improvements comply with requirements.

C. Certified Surveys: Submit 2 copies signed and sealed by land surveyor.

D. Project Record Documents: Submit a record of Work performed (materials tests, inspections, acceptance tests, etc.) and record survey data as required under provisions in Division 01 Sections "Submittals" and "Project Closeout."

Page 140: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

EXECUTION 017300 - 2

1.4 QUALITY ASSURANCE

A. Land Surveyor Qualifications: A professional land surveyor who is legally qualified to practice in the Commonwealth of Virginia and who is experienced in providing land-surveying services of the kind indicated.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 EXAMINATION

A. Existing Conditions: The existence and location of site improvements, utilities, and other construction indicated as existing are not guaranteed. Before beginning work, investigate and verify the existence and location of mechanical and electrical systems and other construction affecting the Work, including all site utility systems.

1. Before construction, verify the location and points of connection of utility services.

B. Existing Utilities: The existence and location of underground and other utilities and construction indicated as existing are not guaranteed. Before beginning site work, investigate and verify the existence and location of underground utilities and other construction affecting the Work.

1. Before construction, verify the location and invert elevation at points of connection ofstorm sewer, and underground electrical and communication services.

2. For additional requirements for locating and marking existing utilities, see Division 01 Section "Summary."

C. Acceptance of Conditions: Examine substrates, areas, and conditions, with Installer or Applicator present where indicated, for compliance with requirements for installation tolerances and other conditions affecting performance. Record observations.

1. Written Report: Where a written report listing conditions detrimental to performance of the Work is required by other Sections, include the following:

a. Description of the Work. b. List of detrimental conditions, including substrates. c. List of unacceptable installation tolerances. d. Recommended corrections.

2. Examine roughing-in for mechanical and electrical systems to verify actual locations of connections before equipment and fixture installation.

3. Proceed with installation only after unsatisfactory conditions have been corrected. Proceeding with the Work indicates acceptance of surfaces and conditions.

Page 141: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

EXECUTION 017300 - 3

3.2 PREPARATION

A. Existing Utility Information: Furnish information to COTR that is necessary to adjust, move, or relocate existing utility structures, utility poles, lines, services, or other utility appurtenances located in or affected by construction.

B. Field Measurements: Take field measurements as required to fit the Work properly. Recheck measurements before installing each product. Where portions of the Work are indicated to fit to other construction, verify dimensions of other construction by field measurements before fabrication. Coordinate fabrication schedule with construction progress to avoid delaying the Work.

C. Space Requirements: Verify space requirements and dimensions of items shown diagrammatically on Drawings.

D. Review of Contract Documents and Field Conditions: Immediately on discovery of the need for clarification of the Contract Documents, submit a request for information (RFI) to COTR. Include a detailed description of problem encountered, together with recommendations for changing the Contract Documents.

3.3 CONSTRUCTION LAYOUT

A. Verification: Before proceeding to lay out the Work, verify layout information shown on Drawings, in relation to the property survey and existing benchmarks. If discrepancies are discovered, notify COTR promptly.

B. General: Engage a land surveyor to layout the Work using accepted surveying practices.

1. Establish benchmarks and control points to set lines and levels at each story of construction and elsewhere as needed to locate each element of Project.

2. Establish dimensions within tolerances indicated. Do not scale Drawings to obtain required dimensions.

3. Inform installers of lines and levels to which they must comply. 4. Check the location, level and plumb, of every major element as the Work progresses. 5. Notify COTR when deviations from required lines and levels exceed allowable

tolerances. 6. Close site surveys with an error of closure equal to or less than one inch in 10,000 feet.

C. Site Improvements: Locate and lay out site improvements, including pavements, grading, fill and topsoil placement, utility slopes, and invert elevations.

D. Record Log: Maintain a log of layout control work. Record deviations from required lines and levels. Include beginning and ending dates and times of surveys, weather conditions, name and duty of each survey party member, and types of instruments and tapes used. Make the log available for reference by COTR.

Page 142: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

EXECUTION 017300 - 4

3.4 FIELD ENGINEERING

A. Identification: Existing control points and property line corner stakes are as identified on the Contract Documents.

B. Reference Points: Locate existing permanent benchmarks, control points, and similar reference points before beginning the Work. Preserve and protect permanent benchmarks and control points during construction operations.

1. Do not change or relocate existing benchmarks or control points without prior written approval of COTR. Report lost or destroyed permanent benchmarks or control points promptly. Report the need to relocate permanent benchmarks or control points to COTR before proceeding.

2. Replace lost or destroyed permanent benchmarks and control points promptly with the approval of COTR. Base replacements on the original survey control points.

C. Benchmarks: Establish and maintain a minimum of two permanent benchmarks on Project site, referenced to data established by survey control points. Comply with the Authority for type and size of benchmark.

1. Record benchmark locations, with horizontal and vertical data, on Project Record Documents.

2. Where the actual location or elevation of layout points cannot be marked, provide temporary reference points sufficient to locate the Work.

3. Remove temporary reference points when no longer needed. Restore marked construction to its original condition.

D. Certified Survey: On completion of site improvements and other work requiring field-engineering services, including utilities, prepare a certified survey showing coordinates, dimensions, locations, angles, and elevations of construction and site work. Coordinates shall be ACS and elevations shall be NGVD 29.

3.5 INSTALLATION

A. Inspection of Conditions: Require Installer of each major component to inspect both the substrate and conditions under which Work is to be performed. Proceed only after unsatisfactory conditions have been corrected in a manner acceptable to COTR. Coordinate this requirement with Division 01 Section "Quality Requirements."

B. General: Locate the Work and components of the Work accurately, in correct alignment and elevation, as indicated.

1. Make vertical work plumb and make horizontal work level. 2. Where space is limited, install components to maximize space available for maintenance

and ease of removal for replacement.

C. Comply with manufacturer's written instructions and recommendations for installing products in applications indicated.

Page 143: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

EXECUTION 017300 - 5

D. Install products at the time and under conditions that will ensure the best possible results. Maintain conditions required for product performance until Substantial Completion.

E. Conduct construction operations so no part of the Work is subjected to damaging operations or loading in excess of that expected during normal conditions of occupancy.

F. Tools and Equipment: Do not use tools or equipment that produce harmful noise levels. For additional requirements see Section "Supplementary Conditions."

G. Anchors and Fasteners: Provide anchors and fasteners as required to anchor each component securely in place, accurately located and aligned with other portions of the Work.

1. Mounting Heights: Where mounting heights are not indicated, mount components at heights directed by COTR.

2. Allow for building movement, including thermal expansion and contraction.

H. Joints: Make joints of uniform width. Where joint locations in exposed work are not indicated, arrange joints as directed by COTR. Fit exposed connections together to form hairline joints.

I. Hazardous Materials: Use products, cleaners, and installation materials that are not considered hazardous.

3.6 AUTHORITY-INSTALLED PRODUCTS

A. Site Access: Provide access to Project site for the Authority's construction forces.

B. Coordination: Coordinate construction and operations of the Work with work performed by the Authority's construction forces.

1. Construction Schedule: Inform COTR of Contractor's preferred construction schedule for the Authority's portion of the Work. Adjust construction schedule based on a mutually agreeable timetable. Notify COTR if changes to schedule are required due to differences in actual construction progress.

2. Pre-installation Conferences: Include the Authority's construction forces at pre-installation conferences covering portions of the Work that are to receive the Authority's work. Attend pre-installation conferences conducted by the Authority's construction forces if portions of the Work depend on the Authority's construction.

3.7 PROGRESS CLEANING

A. General: Clean Project site and work areas daily, including common areas. Coordinate progress cleaning for joint-use areas where more than one installer has worked. Enforce requirements strictly. Dispose of materials lawfully.

1. Comply with requirements in NFPA 241 for removal of combustible waste materials and debris.

2. Remove combustible debris from the site daily. 3. Do not hold materials more than 7 days during normal weather or 3 days if the

temperature is expected to rise above 80 deg F.

Page 144: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

EXECUTION 017300 - 6

4. Containerize hazardous and unsanitary waste materials separately from other waste. Mark containers appropriately and dispose of legally, according to regulations.

B. Site: Maintain Project site free of waste materials and debris.

C. Work Areas: Clean areas where work is in progress to the level of cleanliness necessary for proper execution of the Work.

1. Remove liquid spills promptly. 2. Where dust would impair proper execution of the Work, broom-clean or vacuum the

entire work area, as appropriate.

D. Installed Work: Keep installed work clean. Clean installed surfaces according to written instructions of manufacturer or fabricator of product installed, using only cleaning materials specifically recommended. If specific cleaning materials are not recommended, use cleaning materials that are not hazardous to health or property and that will not damage exposed surfaces.

E. Concealed Spaces: Remove debris from concealed spaces before enclosing the space.

F. Exposed Surfaces: Clean exposed surfaces and protect as necessary to ensure freedom from damage and deterioration at time of Substantial Completion.

G. Cutting and Patching: Clean areas and spaces where cutting and patching are performed. Completely remove paint, mortar, oils, putty, and similar materials.

1. Thoroughly clean piping, conduit, and similar features before applying paint or other finishing materials. Restore damaged pipe covering to its original condition.

H. Waste Disposal: Burying or burning waste materials on-airport property will not be permitted. Washing waste materials down sewers or into waterways will not be permitted.

I. During handling and installation, clean and protect construction in progress and adjoining materials already in place. Apply protective covering where required to ensure protection from damage or deterioration at Substantial Completion.

J. Clean and provide maintenance on completed construction as frequently as necessary through the remainder of the construction period. Adjust and lubricate operable components to ensure operability without damaging effects.

K. Limiting Exposures: Supervise construction operations to ensure that no part of the construction completed or in progress, is subject to harmful, dangerous, damaging, or otherwise deleterious exposure during the construction period.

L. Grass Mowing: Mow grass areas contained in Project site, or made inaccessible to the Authority's mowing contractors.

3.8 STARTING AND ADJUSTING

A. Follow equipment manufacturer's startup procedures, unless otherwise directed by COTR.

Page 145: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

EXECUTION 017300 - 7

B. Start equipment and operating components to confirm proper operation. Remove malfunctioning units, replace with new units, and retest.

C. Adjust operating components for proper operation without binding. Adjust equipment for proper operation.

D. Test each piece of equipment to verify proper operation. Test and adjust controls and safeties. Replace damaged and malfunctioning controls and equipment.

E. Manufacturer's Field Service: If a factory-authorized service representative is required to inspect field-assembled components and equipment installation, comply with qualification requirements in Division 01 Section "Quality Requirements."

3.9 PROTECTION OF INSTALLED CONSTRUCTION

A. Provide final protection and maintain conditions that ensure that installed Work is without damage or deterioration at time of Substantial Completion.

B. Comply with manufacturer's written instructions for temperature and relative humidity.

3.10 CORRECTION OF THE WORK

A. Repair or remove and replace defective construction. Restore damaged substrates and finishes.

1. Repairing includes replacing defective parts, refinishing damaged surfaces, touching up with matching materials, and properly adjusting operating equipment.

B. Restore permanent facilities used during construction to their specified condition.

C. Remove and replace damaged surfaces that are exposed to view if surfaces cannot be repaired without visible evidence of repair.

D. Repair components that do not operate properly. Remove and replace operating components that cannot be repaired.

E. Remove and replace chipped, scratched, and broken glass or reflective surfaces.

END OF SECTION 017300

Page 146: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final
Page 147: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

PROJECT CLOSEOUT 017700 - 1

SECTION 017700 - PROJECT CLOSEOUT

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings, Contract Provisions, Special Provisions, Supplementary Conditions, and other Division 01 Specification Sections apply to this Section.

1.2 SUMMARY

A. This Section includes administrative and procedural requirements for Project closeout, including, but not limited to, the following:

1. Inspection procedures. 2. Warranties. 3. Final cleaning.

B. Related Sections include the following:

1. Division 01 Section “Quality Requirements” for final requirements of the Warranty Manual.

2. Division 01 Section "Photographic Documentation" for submitting Final Acceptance construction photographs and negatives.

3. Division 01 Section "Project Record Documents" for submitting Record Drawings, Record Specifications, Record Product Data, and other Record Documents.

4. Divisions 02 through 33 Sections for specific closeout and special cleaning requirements for products of those Sections.

1.3 SUBSTANTIAL COMPLETION

A. Definition: "Substantial Completion" is the stage in the progress of the work when COTR determines that all the Work, or a designated portion thereof, is sufficiently complete and functional according to the Contract Documents so that the Authority can occupy or utilize the Work for its intended use. The only remaining physical work shall be the completion of punch list work prior to Final Acceptance.

B. Preliminary Procedures: Before requesting inspection for determining date of Substantial Completion, complete the following. List items below that are incomplete in request.

1. Prepare a list of items to be completed and corrected (punch list), the value of items on the list, reasons why the Work is not complete, and a schedule for completing punch list work according to Section III of the Contract.

2. Ensure previously outstanding technical submittals and Shop Drawings have been submitted and approved.

3. Advise COTR of pending insurance changeover requirements.

Page 148: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

PROJECT CLOSEOUT 017700 - 2

4. Submit warranties required by Contract Documents, workmanship bonds, maintenance service agreements, final certifications, and similar documents.

a. Submit Contractor Warranty Letter, for review and approval, a minimum of 60 days before requesting inspection for determining date of Substantial Completion. After date of Substantial Completion has been determined revise the Contractor’s Warranty Letter to include that date as start of Warranty period.

5. Obtain and submit releases permitting the Authority unrestricted use of the Work and access to services and utilities. Include occupancy permits, operating certificates, and similar releases.

6. Prepare and submit Project Record Documents except Record Contract CPM Schedule; also prepare and submit Operation and Maintenance manuals, Final Completion construction photographs and photographic negatives, damage or settlement surveys, and similar final record information.

7. Prepare and submit proof that specified testing and code inspections have been completed, accepted and certified, including, but not limited to, structural work, sprinkler piping systems, fire alarm and FPS systems, bacteriological testing of domestic lines, back-flow prevention, electrical system testing, and hydrostatic pressure testing of sanitary lines. Submit approvals of Health Department or the FDA as applicable.

8. Deliver tools, spare parts, extra materials, and similar items to location designated by COTR. Label with manufacturer's name and model number where applicable.

9. Complete startup testing of systems. 10. Submit test/adjust/balance records. 11. Terminate and remove temporary facilities from Project site, along with construction

tools and similar elements. 12. Advise the Authority of changeover in utilities. 13. Submit changeover information related to the Authority's occupancy, use, operation, and

maintenance. 14. Complete final cleaning requirements, including touchup painting. 15. Touch up and otherwise repair and restore marred exposed finishes to eliminate visual

defects.

C. Inspection: Submit a written request for inspection for Substantial Completion. On receipt of request, COTR will either proceed with inspection or notify Contractor of unfulfilled requirements. COTR will prepare the Certificate of Substantial Completion after inspection or will notify Contractor of items, either on Contractor's list or additional items identified by COTR, that must be completed or corrected before certificate will be issued.

1. Re-inspection: Request re-inspection when the Work identified in previous inspections as incomplete is completed or corrected.

2. Punch list work must be completed within the duration specified in Section III, "Schedule." Failure to complete the punch list work within the duration specified may result in the Contracting Officer ordering the work to be completed by others at the cost to Contractor.

3. Results of completed inspection will form the basis of requirements for Final Acceptance.

Page 149: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

PROJECT CLOSEOUT 017700 - 3

1.4 FINAL COMPLETION AND ACCEPTANCE

A. Definition: "Final Completion" is the stage in the Contract when the Contracting Officer determines that all Work has been 100 percent completed according to the terms and conditions of the Contract Documents, including administrative obligations. The date of Final Acceptance is the date of execution by the Contracting Officer of a Certificate of Final Acceptance.

B. Preliminary Procedures: Before requesting final inspection for determining date of Final Completion, complete the following:

1. Submit a final Application for Payment according to Division 01 Section "Application for Payment."

2. Submit certified copy of COTR's Substantial Completion inspection list of items to be completed or corrected (punch list), endorsed and dated by COTR. The certified copy of the list shall state that each item has been completed or otherwise resolved for acceptance.

3. Submit a Contractor/COTR joint statement evidencing that all Record Documents, Operation and Maintenance Manuals, warranties, and similar required submittals have been approved.

4. Complete demobilization and removal of temporary facilities from the site including construction equipment and facilities, mockups, and other similar elements. Restore areas to previously existing condition, if applicable.

5. Execute final Contract Modification and submit final Subcontractor Payment Form. 6. Return all AOA badging and all Authority Ids. 7. Submit evidence of final, continuing insurance coverage complying with insurance

requirements. 8. Submit Record Contract CPM Schedule. 9. Submit warranty book.

C. Inspection: Submit a written request for final inspection for acceptance. On receipt of request, COTR will either proceed with inspection or notify Contractor of unfulfilled requirements. COTR will prepare a final Certificate for Payment after inspection or will notify Contractor of construction that must be completed or corrected before certificate will be issued.

1. Re-inspection: Request re-inspection when the Work identified in previous inspections as incomplete is completed or corrected.

1.5 LIST OF INCOMPLETE ITEMS (PUNCH LIST)

A. Preparation: Submit four copies of list. Include name and identification of each space and area affected by construction operations for incomplete items and items needing correction including, if necessary, areas disturbed by Contractor that are outside the limits of construction. 1. Include the following information at the top of each page:

a. Contract name and number. b. Date. c. Name of COTR. d. Name of Architect/Engineer. e. Name of Contractor.

Page 150: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

PROJECT CLOSEOUT 017700 - 4

f. Page number.

1.6 WARRANTIES

A. Submittal Time: Submit one draft copy of proposed Warranty Manual Specified below within 90 days of Notice to Proceed. COTR will return comments to the Contractor no later than 30 calendar days after receipt.

1. Provide Manufacturer’s Standard Warranties, made out to the Authority, and statement of willingness to provide any applicable Special Warranties required by the Contract Documents 14 calendar days prior to shipping of materials and equipment. Products and Equipment shall not be considered delivered (for payment purposes) until the approved warranties have been received.

2. Submit written warranties on request of COTR for designated portions of the Work where commencement of warranties other than date of Substantial Completion is indicated.

B. Partial Occupancy: Submit properly executed warranties within 15 days of completion of designated portions of the Work that are completed and occupied or used by the Authority during construction period by separate agreement with Contractor.

C. Warranty Manual: Organize warranty documents into an orderly sequence based on the table of contents of the Contract Specifications. Warranty documents include Contractor and major subcontractors warranty letters, special warranty documents, and manufacturer's warranties.

1. Binders: Heavy-duty, 3-ring, vinyl-covered, loose-leaf binders, in thickness necessary to accommodate contents, sized to hold 8-1/2-by-11-inch paper; with clear plastic sleeve on spine to hold label describing contents. Binders shall not be filled beyond 75 percent of their rated capacity. Binders shall also have boomerang plastic sheet lifters, metal backbone, concealed rivet construction, and three-trigger position locking mechanism (lock, unlock, open) on top and bottom. Binder color shall be black unless another color is selected by COTR.

a. Provide maximum 3-inch binder thickness. b. Identify each binder on front and spine, with printed title "PROJECT

WARRANTIES," Contract number and name, and subject matter of contents. If identification cannot be attached to the front include it as the first page in the manual. Indicate volume number for multiple-volume sets. The use of business labels is prohibited.

2. Dividers: Provide three-hole, heavyweight, plastic tabbed dividers, (, or as approved by the Authority) for each separate section. Provide laser printed description for each tabbed section on the front and back of tabs. Tabs shall indicate the appropriate Specification Section. Provide a description of the warranty or heading for sub tabs using the same laser printed format on the dividers. Provide an index of the contents in each section on the first page behind each section divider. The index shall be generated using a word processor and printed on a laser printer. Include a matching master table of contents for each volume using the same indexing system. Install a colored sheet between each different warranty within a tabbed section.

Page 151: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

PROJECT CLOSEOUT 017700 - 5

D. Provide additional copies of each warranty that shall be included in Operation and Maintenance Manuals.

PART 2 - PRODUCTS

2.1 MATERIALS

A. Cleaning Agents: For final cleaning, use cleaning materials and agents recommended by manufacturer or fabricator of the surface to be cleaned. Do not use cleaning agents that are potentially hazardous to health or property or that might damage finished surfaces.

PART 3 - EXECUTION

3.1 FINAL CLEANING

A. General: Provide final cleaning. Conduct cleaning and waste-removal operations to comply with Authority requirements, local laws and ordinances and Federal and local environmental and antipollution regulations. General cleaning during construction is included in Division 01 Section "Execution."

B. Cleaning: Employ experienced workers or professional cleaners for final cleaning. Clean each surface or unit to condition expected in an average commercial building cleaning and maintenance program. Comply with manufacturer's written instructions.

1. Complete the following cleaning operations before requesting inspection for certification of Substantial Completion for entire Project or for a portion of Project:

a. Clean Project site, yard, and grounds, in areas disturbed by construction activities, including landscape development areas, of rubbish, waste material, litter, and other foreign substances.

b. Sweep paved areas broom clean. Remove petrochemical spills, stains, and other foreign deposits.

c. Rake grounds that are neither planted nor paved to a smooth, even-textured surface.

d. Remove tools, construction equipment, machinery, and surplus material from Project site.

e. Remove snow and ice to provide safe access to building. f. Clean exposed exterior hard-surfaced finishes to a dirt-free condition, free of

stains, films, and similar foreign substances. Avoid disturbing natural weathering of exterior surfaces. Restore reflective surfaces to their original condition.

g. Remove debris and surface dust from limited access spaces, including trenches, equipment vaults, manholes, and similar spaces.

h. Remove labels that are not permanent. i. Touch up and otherwise repair and restore marred, exposed finishes and surfaces.

Replace finishes and surfaces that cannot be satisfactorily repaired or restored or that already show evidence of repair or restoration.

Page 152: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

PROJECT CLOSEOUT 017700 - 6

1) Do not paint over "UL" and similar labels, including mechanical and electrical nameplates.

j. Wipe surfaces of mechanical and electrical equipment and similar equipment. Remove excess lubrication, paint and mortar droppings, and other foreign substances.

k. Replace parts subject to unusual operating conditions. l. Clean light fixtures, lamps, globes, and reflectors to function with full efficiency. m. Leave Project clean and ready for occupancy.

C. Comply with safety standards for cleaning. Do not burn waste materials. Do not bury debris or excess materials on the Authority's property. Do not discharge volatile, harmful, or dangerous materials into drainage systems. Remove waste materials from Project site and dispose of lawfully.

1. Where extra materials of value remaining after completion of associated Work have become the Authority's property, arrange for disposition of these materials as directed by COTR.

END OF SECTION 017700

Page 153: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final
Page 154: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final
Page 155: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

PROJECT RECORD DOCUMENTS 017839 - 1

SECTION 017839 - PROJECT RECORD DOCUMENTS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings, Contract Provisions, Special Provisions, Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section includes administrative and procedural requirements for Project Record Documents, including the following:

1. Record Drawings. 2. Record Specifications 3. Record Product Data. 4. Record Samples. 5. Record Schedule. 6. Miscellaneous Record Submittals. 7. Computer Aided Design and Drafting (CADD) requirements for Record Drawings.

B. Related Sections include the following:

1. Division 01 Section “Construction Progress Documentation" for construction schedules as basis for Record Schedule.

2. Division 01 Section “Quality Requirements” for ensuring the record drawings and specifications are kept current on a daily basis and marked to show deviations which have been made from the original Contract documents

3. Division 01 Section "Project Closeout " for general closeout procedures 4. Division 01 Section "Operation and Maintenance Data" for operation and maintenance

manual requirements. 5. Divisions 02 through 33 Sections for specific requirements for Project Record

Documents of products in those Sections.

1.3 SUBMITTALS

A. CADD Record Drawings. Comply with the following:

1. Submit copies of CADD Record Drawings as follows:

a. Initial Submittal: Submit one set of complete, full-sized, CADD Record Drawings. Additional sets of drawings are not to be copied and submitted until after substantial completion to insure all changes are shown on the drawings. The COTR will facilitate review of drawings and indicate whether the CADD Record Drawings are acceptable. The COTR will return review comments indicating any

Page 156: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

PROJECT RECORD DOCUMENTS 017839 - 2

corrections that need to be made to the drawings. The corrected CADD Record Drawings may then be reproduced, and organized into sets, printed, bound, and submitted as final submittal.

b. Final Submittal: After construction is complete and changes are recorded, submit six complete, full-sized, printed sets of CADD Record Drawings. Include each sheet, whether or not changes and additional information were recorded. Submit two copies of the CADD Record drawings in the approved electronic format. In addition, submit the original set of marked-up record drawings onto which the mark-ups were made.

B. Record Specifications: Submit two copies of Project Specifications, including addenda and contract modifications.

C. Record Product Data: Submit one copy of each Product Data submittal at the direction of the COTR.

1. Where Record Product Data is required as part of operation and maintenance manuals, submit marked-up Product Data as an insert in the manual instead of submittal as Record Product Data.

D. Record Samples: Submit Record Samples as specified.

E. Record Schedule: Submit three copies of Record Schedule.

F. Miscellaneous Record Submittals: Submit miscellaneous Record Submittals as specified.

PART 2 - PRODUCTS

2.1 RECORD DRAWINGS

A. Record Prints: During construction, maintain one complete, full sized, set of blue- or black-line prints of the Drawings, applicable shop drawings, and coordination drawings for record purposes. These drawings shall be updated periodically, by the contractor, in CADD to replace the hand mark-ups. The mark-ups shall be preserved for the record. A complete set of Conformed Drawings in CADD will be provided to the Contractor for his use in maintaining the CADD Record Drawings. The CADD files will be provided in Bentley Microstation v8.

1. Maintenance of Drawings: Maintain the drawings in a clean, dry, legible condition. Keep drawings available during normal working hours for inspection by the COTR.

2. Preparation: Routinely mark Record Prints to show the actual installation where installation varies from that shown originally. Require individual or entity who obtained record data, whether individual or entity is Installer, subcontractor, or similar entity, to prepare the mark-ups on the record set.

a. Give particular attention to information on concealed elements that would be difficult to identify or measure and record later especially underground structures.

b. Record information in an understandable drawing technique. Ensure mark-ups are legible and reproducible.

Page 157: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

PROJECT RECORD DOCUMENTS 017839 - 3

c. Record data as soon as possible after obtaining it. Record and check markups before enclosing concealed installations.

3. Content: Types of items requiring marking include, but are not limited to, the following:

a. Dimensional changes to Drawings. b. Revisions to details shown on Drawings. c. Depths of foundations below first floor. d. Locations and depths of underground utilities. e. Revisions to routing of piping and conduits. f. Revisions to electrical circuitry. g. Actual equipment locations. h. Duct size and routing. i. Locations of concealed internal utilities. j. Changes made by Change Notice and RFI. k. Changes made following COTR's written orders. l. Details not on the original Drawings. m. Field records for variable and concealed conditions. n. Record information on the Work that is shown only schematically.

4. Mark the Drawings or Shop Drawings, whichever is most capable of showing actual physical conditions, completely and accurately. If Shop Drawings are marked, insert them into drawing set and assign an appropriate sheet number (one that follows the number sequence of the contract drawings). Show cross-references to the new sheets on the Drawings. Update drawing index as needed to reflect new sheets.

5. Mark record drawings with red pen that will reproduce clearly. Use different colors to distinguish between changes for different categories of the Work at the same location.

6. Mark important additional information that was either shown schematically or not indicated on the original Drawings.

7. Note applicable Construction Change Notices, Requests for Information, Technical Support Requests, and similar identification numbers, where applicable. Copies of change documentation shall be inserted into the set for clarification but are not a substitute for mark-ups. If identification numbers for documentation are marked on the drawing when no change resulted, indicate "No Change".

B. Newly Prepared Project Record Drawing Sheets: The contractor may add new sheets with supporting sketches and change documentation instead of marking original sheets when neither the original Drawings nor Shop Drawings are suitable to show actual installation or if the new sheets can show the changes more clearly or additional space is required for markup information.

1. Assign a number to each new sheet and cross-reference on the appropriate related sheets. 2. Consult with COTR for proper scale and scope of detailing and notations required to

record the actual physical installation and its relation to other construction. 3. Integrate newly prepared sheets into Record Drawing sets and update drawing index to

reflect new sheets.

C. Format:

Page 158: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

PROJECT RECORD DOCUMENTS 017839 - 4

1. Identify and date each Record Drawing. Include the designation “PROJECT RECORD DRAWING” in a prominent location on each sheet.

2. Cover Sheet shall have the designation “PROJECT RECORD DRAWINGS”, Date, Name of Contractor, and signature.

3. Record CADD Drawings:

a. CADD files provided by COTR and utilized for recording of record mark-ups shall maintain the format of the files provided. Place electronic mark-ups in a newly created layer on each drawing.

b. CADD files created by Contractor: Organize CADD information into separate electronic files that correspond to each sheet of the Record Drawing set. Name each file with the sheet identification. Include identification in each CADD file.

4. Include the following identification on newly prepared Project Record Drawing Sheets:

a. Project name. b. Date. c. Designation "PROJECT RECORD DRAWING." d. Name of Architect/Engineer (if applicable). e. Name of Contractor. f. Initials of person incorporating the change. g. Drawing identification number. (Ixx/Dxx)

5. Organization of Newly Prepared Project Record Drawing Prints: Organize newly prepared Record Drawings into manageable sets. Include any contract required coordination drawings and applicable shop drawings. Bind each set with durable paper cover sheets. Include identification on cover sheets.

D. ADDITIONAL REQUIREMENTS FOR RECORD DRAWINGS

1. When there are multiple copies of the same sheet with different mark-ups on each copy, the General Contractor is responsible for consolidating all mark-ups onto a single copy of each individual sheet.

2. The information from all RFI's, Change Notices, Design Clarifications, field adjustments, or any other changes, must be noted on the appropriate drawing. These mark-ups must include enough information to clearly show the actual constructed conditions resulting from the change. The information may be drawn onto the drawing, copied onto the drawing or copied onto a new full size sheet. Every change in construction must have RFI’s, Change Orders or similar supplementary documents; therefore they must be copied in original size and attached to the back of the preceding drawing or at the end of the drawing set, as an appendix, as a full size sheet, same in size as the drawing set. Multiple RFI’s, CN’s and other supplemental documents may be copied in each single sheet.

3. All changes made on the drawings shall reference the appropriate RFI, Change Notices, Design Clarification, or details from the contractor prepared shop drawings. If the mark-up is due to a field adjustment, it shall be indicated as such.

4. Additional Sheets such as shop drawings and sheets showing copies of applicable change documentation must be inserted into the set as necessary. Such sheets shall have a title block.

Page 159: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

PROJECT RECORD DOCUMENTS 017839 - 5

5. All shop drawings showing information not on the construction drawings (with the exception of concrete embedded steel reinforcement bending drawings and steel reaction and fabrication drawings) shall be marked up and included in the record drawing set. They shall be the same size (changes in scale noted) as all other drawings, include a title block, and clearly indicate that they are record shop drawings. When the shop drawings more accurately show locations and conditions, they may be marked in lieu of referenced on the original drawings. This does not relieve the contractor from the shop drawing inclusion requirements in the Operation and Maintenance Manuals that are a separate item

6. Include contract required coordination drawings in the record drawing set.

2.2 RECORD SPECIFICATIONS

A. Preparation: Mark Specifications to indicate the actual product installation where installation varies from that indicated in Specifications, addenda, and contract modifications. Print marked specifications, addenda, and contract modifications on paper any color but white and ensure that black font is clearly legible on the color chosen. Use the same paper color throughout the project. Use black font for these changes.

1. Give particular attention to information on concealed products and installations that cannot be readily identified and recorded later.

2. Mark copy with the brand name and model number of products, materials, and equipment furnished, including substitutions and product options selected.

3. Record the name of the manufacturer, supplier, Installer, and other information necessary to provide a record of selections made.

4. For each principal product, indicate whether Record Product Data has been submitted in operation and maintenance manuals instead of submitted as Record Product Data.

5. Note related Change Orders, Record Drawings, and Product Data where applicable.

2.3 RECORD PRODUCT DATA

A. Preparation: Mark Product Data to indicate the actual product installation where installation varies substantially from that indicated in Product Data submittal.

1. Give particular attention to information on concealed products and installations that cannot be readily identified and recorded later.

2. Include significant changes in the product delivered to Project site and changes in manufacturer's written instructions for installation.

3. Note related Change Orders, Record Drawings, and Product Data where applicable. 4. Upon completion of mark-up, submit a complete set of record Product Data to COTR for

the Authority's records. 5. Where Record Product Data is required as part of maintenance manuals, submit

marked-up product data as an insert in the manual.

2.4 RECORD SAMPLE SUBMITTAL

A. Prior to date of Substantial Completion, the Contractor shall meet the Authority's personnel at the site to determine which of the samples maintained during the construction period shall be

Page 160: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

PROJECT RECORD DOCUMENTS 017839 - 6

transmitted to the Authority for record purposes. Comply with the COTR's instructions for packaging, identification marking, and delivery to the Authority's sample storage space. Dispose of other samples in manner specified for disposal of surplus and waste materials.

2.5 RECORD SCHEDULE

A. Record Schedule Submittal: Immediately prior to date of inspection for Final Acceptance, submit a copy of the As-built Contract CPM Schedule (if applicable) to the COTR.

B. Mark the Contractor’s Construction Schedule to show actual start and finish dates for all work activities and milestones, based on the accepted monthly updates. This Record Schedule shall be in same format as Contractor’s Construction Schedule. This Record Schedule shall be in tabular and in time-scaled PDM plot formats.

2.6 MISCELLANEOUS RECORD SUBMITTALS

A. Assemble miscellaneous records required by other Specification Sections for miscellaneous record keeping and submittal in connection with actual performance of the Work. Bind or file miscellaneous records and identify each, ready for continued use and reference. Submit to COTR.

1. Categories of requirements resulting in miscellaneous records include, but are not limited to the following:

a. Field records on excavations and foundations. b. Field records on underground construction and similar Work. c. Survey showing locations and elevations of underground lines. d. Invert elevations of drainage piping. e. Surveys establishing building lines and levels. f. Authorized measurements utilizing unit prices or allowances. g. Records of plant treatment. h. Ambient and substrate condition tests. i. Certifications received in lieu of labels on bulk products. j. Batch mixing and bulk delivery records. k. Testing and qualification of tradesmen. l. Documented qualification of installation firms. m. Load and performance testing. n. Inspections and certifications by governing authorities. o. Leakage and water-penetration tests. p. Fire resistance and flame spread test results. q. Final inspection and correction procedures. r. Summary letter from Special Inspector indicating structural work was completed in

accordance with applicable standards. s. Report of potable water testing. t. Backflow prevention certificates. u. Final inspections of all trades. v. Certificates for piping for fire protection systems and FPS supervisory systems. w. Approvals of Health Department or FDA as applicable.

Page 161: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

PROJECT RECORD DOCUMENTS 017839 - 7

PART 3 - EXECUTION

3.1 RECORDING AND MAINTENANCE

A. Recording: Maintain one copy of each submittal during the construction period for Project Record Document purposes. Post changes and modifications to Project Record Documents as they occur.

B. Maintenance of Record Documents and Samples: Store Record Documents and Samples in the field office apart from the Contract Documents used for construction. Do not use Project Record Documents for construction purposes. Maintain Record Documents in good order and in a clean, dry, legible condition, protected from deterioration and loss. Repair or reproduce torn or dirty sheets. Provide access to Project Record Documents for COTR's reference during normal working hours.

END OF SECTION 017839

Page 162: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final
Page 163: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

EXCAVATION AND EMBANKMENT P-152 - 1

SECTION P-152 - EXCAVATION AND EMBANKMENT

PART 1 - DESCRIPTION

1.1 This item covers excavation, disposal, placement, and compaction of all materials within the limits of work required to construct the blast fence in accordance with these specifications and in conformity to the dimensions and typical sections shown on the Plans.

1.2 CLASSIFICATION

A. Unclassified Excavation. Unclassified excavation shall consist of the excavation and placement as embankment and compaction of all material.

B. Unsuitable Material. Any material containing vegetable or organic matter, such as muck, peat, organic silt, or sod that is classified as OL, OH, or PT in accordance with the Unified Soil Classification System shall be considered unsuitable for use in embankment construction. Material, when approved by the COTR as suitable to support vegetation, may be used on the embankment slope.

C. Suitable Material. Any material that is classified as GW, GP, GM, SW, SP, SM, CL, ML, in accordance with the Unified Soil Classification System.

PART 2 - MATERIAL

2.1 OPEN GRADED AGGREGATE BASE COURSE MATERIAL

A. Open graded aggregate base course for use in dressing up the completed site shall consist of an open-graded aggregate material conforming to Virginia Department of Transportation (VDOT) Size Number 67 open-graded coarse aggregate. Grading for the material shall conform to the following requirements:

Sieve Size Percent Passing 1 inches Minimum 100 ¾ inches 90-100 3/8 inches 20-55 No. 4 Maximum 10 No. 8 Maximum 5

2.2 SUBMITTALS

A. The following submittals shall be required as part of this item:

1. Open Graded Aggregate Base Course Material.

2. Various items listed in the Field Quality Control Section.

PART 3 - CONSTRUCTION METHODS

3.1 GENERAL

Page 164: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

EXCAVATION AND EMBANKMENT P-152 - 2

A. Before beginning excavation, grading, and embankment operations in any area, the area shall be completely stripped of any topsoil within the area of excavation for the blast fence foundation. Topsoil shall be excavated and stockpiled for testing as described in paragraph 3.2C.

B. The suitability of material to be placed as backfill and embankment shall be subject to approval by the COTR. All unsuitable material shall be temporarily stockpiled and tested by the Authority’s Environmental Contractor as described in paragraph 3.2C.

C. When the Contractor’s excavating operations encounter artifacts of historical or archaeological significance, the operations shall be temporarily discontinued. At the direction of the COTR, the Contractor shall excavate the site in such a manner as to preserve the artifacts encountered and allow for their removal. Such excavation will be paid for as extra work.

D. If it is necessary to interrupt existing surface drainage, sewers or under-drainage, conduits, utilities, or similar underground structures, the Contractor shall be responsible for and shall take all necessary precautions to preserve them or provide temporary services. When such facilities are encountered, the Contractor shall notify the COTR, who shall arrange for their removal if necessary. The Contractor shall, at his/her own expense, satisfactorily repair or pay the cost of all damage to such facilities or structures which may result from any of the Contractor’s operations during the period of the contract.

3.2 EXCAVATION

A. No excavation shall be started until the work has been staked out by the Contractor and the Contractor has obtained elevations and measurements of the ground surface.

B. Excavated materials shall be kept separate in accordance with the various areas and limits shown on the plans. Suitable material and topsoil excavated from a particular area shall be used in the formation of embankment and backfilling within that area only. Movement and placement of excavated materials throughout the site to different areas will not be permitted.

C. When volume of the excavation exceeds that required to complete the work, the excess material shall be stockpiled as shown on the plans and sampled and tested by the Authority’s Environmental Contractor. All excess material is assumed to be contaminated. The Authority will characterize the soil for disposal but the Contractor is responsible for hauling and placing all excess soil material in the designated soil waste area as shown on the plans. The Authority will sample and characterize each soil stockpile and dispose of any contaminated material at a recycling facility capable of accepting low level contaminated soil. The contractor shall be responsible for loading the contaminated soil for disposal. If the Authority soil tests indicate the material is clean, the contractor is responsible for disposal of the material off-site.

D. The grade shall be maintained so that the surface is well drained at all times. When necessary, temporary drains and drainage ditches shall be installed to intercept or divert surface water which may affect the work. No additional measurement or payment will be made for temporary drainage as costs associated with this effort shall be incidental to unclassified excavation.

Page 165: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

EXCAVATION AND EMBANKMENT P-152 - 3

E. Unsuitable Material. Muck, peat, matted roots, or other material classified as unsuitable material, or directed by the COTR as unsatisfactory for subgrade foundation, shall be removed to the depth encountered or as directed by the COTR. Unsuitable materials, not suitable for topsoil, shall be disposed of in the temporary stockpile area shown on the plans for characterization by the Authority or as directed by the COTR.

F. Overbreak, including slides, is that portion of any material displaced or loosened beyond the finished work as planned or authorized by the COTR. The COTR shall determine if the displacement of such material was unavoidable. All overbreak shall be graded or removed by the Contractor and disposed of as directed by the COTR at no additional cost to the Authority.

G. The subgrade under the foundations shall be compacted to a depth of 6 inches and to a density of not less than 95% of the maximum density as determined by ASTM D 1557. The material to be compacted shall be within ±20% of the optimum moisture content value before being rolled to obtain the prescribed compaction. If deemed necessary by the COTR, undercut the subgrade and backfill with Select Backfill Material. The excavation equipment and methods shall minimize subgrade disturbance.

H. Under areas of the foundations, there shall be no standing water and the groundwater shall be maintained a minimum 2 feet below the lowest point of the excavation. Any dewatering shall be continuous until the pavement has been constructed.

I. The in-place field density shall be determined in accordance with ASTM D 6938 (Nuclear Density Method) to verify the density, degree of compaction, and moisture content.

J. Do not route haul traffic on the subgrade or open graded aggregate base course.

K. Blasting shall not be permitted.

L. Contractor shall do all bracing, sheathing, or shoring necessary to implement and protect excavations as required for safety or conformance to governing laws. The cost for bracing, sheathing, or shoring shall be considered incidental to unclassified excavation.

3.3 FORMATION OF EMBANKMENTS

A. All excavated material with the exception of unsuitable material, is designated for reuse in the same area from which it was removed.

B. Embankments shall be formed in successive horizontal layers of not more than 8 inches in loose depth of for the full width of the cross section, unless otherwise approved by the COTR.

C. The grading operations shall be conducted, and the various soil strata shall be placed, to produce a soil structure as shown on the typical cross section or as directed. Materials such as brush, hedge, roots, stumps, grass and other organic matter, shall not be incorporated or buried in the embankment.

D. Operations on earthwork shall be suspended at any time when satisfactory results cannot be obtained because of rain, freezing, or other unsatisfactory conditions of the field. The Contractor shall drag, blade, or slope the embankment to provide proper surface drainage.

Page 166: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

EXCAVATION AND EMBANKMENT P-152 - 4

E. The material in the layer shall be within 20% of the optimum moisture content value at the time of compaction. In order to achieve uniform moisture content throughout the layer, wetting or drying of the material and manipulation shall be required when necessary. Should the material be too wet to permit proper compaction or rolling, all work on all of the affected portions of the embankment shall be delayed until the material has dried to the required moisture content or mechanical aeration of the subgrade adjusts the moisture content to that specified. Sprinkling of dry material to obtain the proper moisture content shall be done with approved equipment that will sufficiently distribute the water. Sufficient equipment to furnish the required water shall be available at all times. Samples of all embankment materials for testing, both before and after placement and compaction, will be taken for each 10 cubic yards. Based on these tests, the Contractor shall make the necessary corrections and adjustments in methods, materials or moisture content in order to achieve the correct embankment density.

F. Rolling operations shall be continued until the embankment is compacted to a minimum of 95 percent of maximum dry density as determined by ASTM D 1557. Compaction shall be determined in accordance with ASTM D 6938 (Nuclear Density Method) to verify the density, degree of compaction, and moisture content.

G. Compaction areas shall be kept separate, and no layer shall be covered by another until the proper density and degree of compaction is obtained and written permission is given by the COTR.

H. During construction of the embankment, the Contractor shall route his/her equipment at all times, both when loaded and when empty, over the layers as they are placed and shall distribute the travel evenly over the entire width of the embankment. The equipment shall be operated in such a manner that hardpan, cemented gravel, clay, or other chunky soil material will be broken up into small particles and become incorporated with the other material in the layer.

I. In the construction of embankments, layer placement shall begin in the deepest portion of the fill; as placement progresses, layers shall be constructed approximately parallel to the finished pavement grade line.

J. Frozen material shall not be placed in the embankment nor shall embankment be placed upon frozen material.

3.4 FINISHING AND PROTECTION OF SUBGRADE

A. After the subgrade has been substantially completed the full width shall be conditioned by removing any soft or other unstable material which will not compact properly. The resulting areas and all other low areas, holes or depressions shall be brought to grade with suitable select material. Scarifying, blading, rolling and other methods shall be performed to provide a thoroughly compacted subgrade shaped to the lines and grades shown on the Plans.

B. Compact subgrade to a minimum of 95 percent of the maximum dry density as determined by ASTM D 1557.

C. Grading of the subgrade shall be performed so that it will drain readily. The Contractor shall take all precautions necessary to protect the subgrade from damage. He/she shall limit hauling over the finished subgrade to that which is essential for construction purposes.

Page 167: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

EXCAVATION AND EMBANKMENT P-152 - 5

D. All ruts or rough places that develop in a completed subgrade shall be smoothed and recompacted.

E. No permanent seeding of the finished grade shall be allowed until the finished grading has been approved by the COTR.

3.5 HAUL

A. All hauling will be considered a necessary and incidental part of the work. Its cost shall be considered by the Contractor and included in the contract unit price for the pay of items of work involved. No payment will be made separately or directly for hauling on any part of the work or for transport of the excess excavation to the stockpiling site shown on the drawings or from intermediate stockpiles to the project site.

3.6 TOLERANCES

A. The subgrade/surface elevation shall not vary more than 0.05 foot from true grade shown on the Plans as established by grade hubs. Any deviation in excess of this amount shall be corrected by loosening, adding or removing materials, and reshaping.

PART 4 - CONTRACTOR QUALITY CONTROL

4.1 FIELD QUALITY CONTROL

A. Division 1 Section "Quality Requirements" specifies the general requirements for the Contractor's Quality Control Program.

B. The following describes the minimum inspection and testing required in the Contractor's Quality Control (CQC) Plan and Program for the work of this section and is for CQC only. The implementation of the Contractor Quality Control Program does not relieve the Contractor from the responsibility to provide the work in accordance with the Contract Documents, applicable codes, regulations, and governing authorities. The CQC Plan and Program shall include, but not be limited to, the following testing and inspection elements. These elements are provided only as a minimum starting point for the Contractor to use to generate his complete CQC Program.

C. Testing Agency: The Contractor shall engage the services of an independent testing agency qualified according to ASTM E329, to conduct soil materials and rock-defining testing, as documented according to ASTM D3740 and ASTM E548, and approved by the COTR.

D. Allow testing agency to inspect and test subgrades and each fill or backfill layer. Proceed with subsequent earthwork only after test results for previously completed work comply with requirements.

E. Tests: Contractor's qualified independent testing agency will test compaction of soils in place according to ASTM D1556, ASTM D2167, ASTM D6938, as applicable. The testing agency shall conduct tests and interpret the test results; shall state in each report whether or not tested earthwork materials and operations comply with all requirements on the Contract Documents and shall specifically note any deviations there from. Testing results shall cover

Page 168: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

EXCAVATION AND EMBANKMENT P-152 - 6

the results of all tests performed, and be both on and off site as required. Test results shall be certified as complete, signed by a qualified testing agency representative authorized to sign certified test reports, and delivered every week to the COTR. Test results shall cite the Contract Document requirements, the test or analytical procedures used, and the actual results. Conforming, non-conforming, and retesting shall be clearly indicated. Test results shall state specifically what is non-conforming, the date discovered, the date corrected, and the date retested. A summary report of all field tests containing both "required" and "actual" results plus "passed" or "failed" for conforming, non-conforming, and repeated test results shall be submitted to the COTR at the end of each month. Testing agency shall perform all tests herein specified and any additional soil tests and inspections required by the COTR during earthwork operations. When testing agency reports that subgrades, fills, or backfills have not achieved degree of compaction specified, scarify and moisten or aerate, or remove and replace soil to depth required; re-compact and retest until specified compaction is obtained. Tests shall be performed at the following locations and frequencies:

1. Field Sampling and Testing: a. Samples: Submit one 50-pound composite sample taken at random three times

per week of subgrade being compacted and material being place. Submit samples, in the number directed, whenever the source or character of the embankment material changes. Contain each sample in a clean container and fasten to prevent loss of material. Tag each sample for identification. The tag shall contain the following information:

Contract No. Sample No. Date of Sample Sampler Source Intended Use

b. Tests: Test fill and backfill in accordance with ASTM D 422, ASTM D2419, and ASTM D2487. Test fill and backfill for material finer than the No. 200 sieve in accordance with ASTM D1140. Test fill and backfill for liquid limit and plasticity index in accordance with ASTM D4318. Test fill and backfill materials for moisture density relations in accordance with ASTM D1557. Perform one of each of the required tests for each material used when directed by the COTR. Provide additional tests as specified above for each material source change. Perform density tests in randomly selected locations in accordance with ASTM D1556 or ASTM D6938. Determine moisture content of soil material in place in accordance with ASTM D6938 at every location where in-place density is tested. Where ASTM D6938 is used to test field compaction densities, verify the results of the tests by performing one test using ASTM D1556 for every 20 tests performed using ASTM D6938.

2. Analysis of Existing Subgrade: Analysis of existing subgrade and fills within 3 feet of finished grades of exterior areas, to determine frost susceptibility, per ASTM D422.

3. Trench Backfill: On each compacted layer, at least one test for each 150 feet or less of trench length, but no fewer than two tests.

4. Review of Quality Control Testing During Construction: If, in the opinion of the COTR, based on Testing Laboratory reports and inspection, subgrade or backfills that

Page 169: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

EXCAVATION AND EMBANKMENT P-152 - 7

have been placed are below specified density, perform additional compaction and testing until specified density is obtained at no additional cost to the Authority. a. Do not add to or build upon non-conforming work.

F. Inspection:

1. Inspect all utility trenches for conformance with contract requirements on a continuing basis. Ensure that backfill is not placed until lines are tested and approved.

2. Check all earthwork for conformance with profiles and contours shown, before subsequent operations proceed.

3. Where structural, drainage fill or pipe bedding material is required, inspect to ensure that proper depth and configuration is placed.

4. Inspect procedures for erosion control and ensure that methods used are performing properly.

5. Ensure that all-necessary mechanical protection of excavation faces have been installed to the extent required by the COTR.

6. Perform additional inspections as necessary to reconfirm any non-conformance of original work and to show conformance of corrected work.

7. Verify that defective work is corrected properly and approved by the COTR.

G. Special Inspections:

1. Special Inspections as defined by Section 1704 of IBC 2006 may be required by the building officials to secure approval of the work. The Special Inspections program shall be provided by others. The contractor shall provide the special inspections engineer free access to the work site.

PART 5 - METHOD OF MEASUREMENT

5.1 Unclassified excavation shall not be measured separately for payment. Unclassified excavation, backfilling, and stockpiling and re-handling of excess material shall be incidental to the installation to Item 323113.80 Blast Protection Fence.

5.2 The quantity of open graded aggregate used to restore the site shall not be measured but shall be consider incidental to Item 323113.80 Blast Protection Fence.

5.3 The quantity of disposal of contaminated soil shall not be measured as disposal will be handled by the Authority.

The quantity of disposal of non-contaminated soil shall be measured by the cubic yard.

PART 6 - BASIS OF PAYMENT

6.1 Payment will be made at the contract unit price per cubic yard of non-contaminated soil loaded and hauled from the stockpile to an offsite location. The price shall be full compensation for furnishing all materials, labor, tools, equipment and incidentals necessary to complete this item.

Page 170: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

EXCAVATION AND EMBANKMENT P-152 - 8

Payment will be made under:

Item P-152-6.1 Disposal of non-contaminated soil – per cubic yard

TESTING REQUIREMENTS

ASTM D 422 Standard Test Method for Particle-Size Analysis of Soils

ASTM D 1140 Standard Test Method for Amount of Material in Soils Finer than No. 200 (75-mm) Sieve

ASTM D 1557 Laboratory Compaction Characteristics of Soil Using Modified Effort (56,000 ft-lbf/ft3 (2,700 kN-m/m3)

ASTM D 1883 CBR (California Bearing Ratio) of Laboratory-Compacted Soils

ASTM D 2167 Density and Unit Weight of Soil in Place by the Rubber Balloon Method

ASTM D 2419 Sand Equivalent Value of Soils and Fine Aggregate

ASTM D 2487 Classification of Soils for Engineering Purposes (Unified Soil Classification System)

ASTM D 4318 Liquid Limit, Plastic Limit, and Plasticity Index of Soils

ASTM D 6938 In-Place Density and Water Content of Soil and Soil-Aggregate by Nuclear Methods (Shallow Depth)

MATERIAL REQUIREMENTS

ASTM C 51 Standard Terminology Relating to Lime and Limestone (as Used by the Industry)

ASTM D 2487 Soils for Engineering Purposes (Unified Soil Classification System)

END OF SECTION P-152

Page 171: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

STRUCTURAL PORTLAND CEMENT CONCRETE P-610 - 1

SECTION P-610 – STRUCTURAL PORTLAND CEMENT CONCRETE

PART 1 - DESCRIPTION

1.1 GENERAL

A. This item shall consist of plain and reinforced structural Portland cement concrete, prepared and constructed in accordance with these specifications, at the locations and of the form and dimensions shown on the plans.

PART 2 - MATERIALS

2.1 GENERAL

A. Only approved materials, conforming to the requirements of these specifications, shall be used in the work. They may be subjected to inspection and tests at any time during the progress of their preparation or use. The source of supply of each of the materials shall be approved by the COTR before delivery or use is started. Representative preliminary samples of the materials shall be submitted by the Contractor, when required, for examination and test. Materials shall be scored and handled to insure the preservation of their quality and fitness for use and shall be located to facilitate prompt inspection. All equipment for handling and transporting materials and concrete must be clean before any material or concrete is placed therein.

B. In no case shall the use of pit-run or naturally mixed aggregates be permitted. The mixing of different kinds of aggregates from different sources in one storage pile or alternating batches of different aggregates will not be permitted.

C. Aggregates shall be tested for deleterious reactivity with alkalies in the cement that may cause excessive expansion of the concrete. Acceptance of aggregates shall be based upon satisfactory evidence furnished by the Contractor that the aggregates, combined with other mixture constituents, do not produce excessive expansion in the concrete. This evidence shall include service records of concrete of comparable properties under similar conditions or exposure and certified records of tests by a testing laboratory that meets the requirements of ASTM C 1077. Tests shall be made in accordance with ASTM C 1260. Test specimens shall be produced using all components (e.g. coarse aggregate, fine aggregate, cement and fly ash) to be included in the produced concrete. If the mean expansion of the test specimens, tested in accordance with ASTM C 1260, does not exceed 0.10 % at 16 days from casting the aggregates shall be accepted. If the mean expansion at 16 days is greater than 0.10% but less than 0.15%, the aggregate may be accepted based upon satisfactory service records and acceptance of the aggregate by a State Highway Department specifically addressing Alkali-Silica Reactivity. If the expansion is greater than 0.15%, the aggregate shall not be accepted for use.

Page 172: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

STRUCTURAL PORTLAND CEMENT CONCRETE P-610 - 2

2.2 COARSE AGGREGATE

A. The coarse aggregate for concrete shall meet the requirements of ASTM C 33. Crushed stone aggregate shall have a durability factor, as determined by ASTM C 666, greater than or equal to 95. The COTR may consider and reserve final approval of other State classification procedures addressing aggregate durability.

B. Coarse aggregate shall be well graded from coarse to fine and shall meet one of the gradations shown in Table 1, using ASTM C 136.

2.3 FINE AGGREGATE

A. The fine aggregate for concrete shall meet the requirements of ASTM C 33.

B. The fine aggregate shall be well graded from fine to coarse and shall meet the requirements of Table 2 when tested in accordance with ASTM C 136:

TABLE 1. GRADATION FOR COARSE AGGREGATE Sieve Designation (square

openings) Percentage by Weight Passing Sieves

2” 1-1/2” 1” 3/4'' 1/2'' 3/8'' No.4 No. 4 to 3/4 in.

100

90-100

20-55

0-10

No. 4 to 1 in. 100 90-100

25-60

0-10

No. 4 to 1-1/2 in. 100 95-100

35-70 10-30

0-5

TABLE 2. GRADATION FOR FINE AGGREGATE Sieve Designation (square openings)

Percentage by Weight Passing Sieves

3/8 inch (9.5 mm) No. 4 (4.75 mm) No. 16 (1.18 mm) No. 30 (0.60 mm) No. 50 (0.30 mm) No. 100 (0.15 mm)

100

95-100 45-80 25-55 10-30 2-10

C. Blending will be permitted, if necessary, in order to meet the gradation requirements for fine aggregate. Fine aggregate deficient in the percentage of material passing the No. 50 mesh sieve may be accepted, provided that such deficiency does not exceed 5% and is remedied by the addition of pozzolanic or cementitious materials other than portland cement, as specified in 610-2.6 on admixtures, in sufficient quantity to produce the required workability as approved by the COTR.

Page 173: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

STRUCTURAL PORTLAND CEMENT CONCRETE P-610 - 3

2.4 CEMENT

A. Cement shall conform to the requirements of ASTM C 150 Type I.

B. The Contractor shall furnish vendors' certified test reports for each carload, or equivalent, of cement shipped to the project. The report shall be delivered to the COTR before permission to use the cement is granted. All such test reports shall be subject to verification by testing sample materials received for use on the project.

2.5 WATER

A. The water used in concrete shall be free from sewage, oil, acid, strong alkalies, vegetable matter, and clay and loam. If the water is of questionable quality, it shall be tested in accordance with AASHTO T 26.

B. Maximum water/cement ratio shall be 0.45.

2.6 ADMIXTURES

A. The use of any material added to the concrete mix shall be approved by the COTR. Before approval of any material, the Contractor shall be required to submit the results of complete physical and chemical analyses made by an acceptable testing laboratory. Subsequent tests shall be made of samples taken by the COTR from the supply of the material being furnished or proposed for use on the work to determine whether the admixture is uniform in quality with that approved.

B. Pozzolanic admixtures shall be fly ash or raw or calcined natural pozzolons meeting the requirements of ASTM C 618.

C. Air-entraining admixtures shall meet the requirements of ASTM C 260. Air-entraining admixtures shall be added at the mixer in the amount necessary to produce the specified air content.

D. Water-reducing, set-controlling admixtures shall meet the requirements of ASTM C 494, Type A, water-reducing or Type D, water-reducing and retarding. Water-reducing admixtures shall be added at the mixer separately from air-entraining admixtures in accordance with the manufacturer's printed instructions.

2.7 PREMOLDED JOINT MATERIAL

A. Premolded joint material for expansion joints shall meet the requirements of ASTM 1751.

2.8 STEEL REINFORCEMENT

A. Reinforcing shall consist of epoxy coated, Welded Steel Wire frabric and Rebar conforming to the requirements of ASTM A 184 and ASTM A775, respectively.

Page 174: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

STRUCTURAL PORTLAND CEMENT CONCRETE P-610 - 4

B. The minimum concrete cover for reinforcement shall be 2” for formed concrete exposed to earth and 3” for concrete cast directly against earth.

2.9 COVER MATERIALS FOR CURING

A. Curing materials shall conform to one of the following specifications:

Waterproof paper for curing concrete ASTM C 171

Polyethylene Sheeting for Curing Concrete ASTM C 171

Liquid Membrane-Forming Compounds for Curing Concrete

ASTM C 309, Type 2

PART 3 - CONSTRUCTION METHODS

3.1 GENERAL

A. The Contractor shall furnish all labor, materials, and services necessary for, and incidental to, the completion of all work as shown on the drawings and specified herein. All machinery and equipment owned or controlled by the Contractor, which he proposes to use on the work, shall be of sufficient size to meet the requirements of the work, and shall be such as to produce satisfactory work; all work shall be subject to the inspection and approval of the COTR.

3.2 CONCRETE COMPOSITION

A. The concrete shall develop a compressive strength of, 4,000 psi for all structures including foundations and concrete stoops in 28 days as determined by test cylinders made in accordance with ASTM C 31 and tested in accordance with ASTM C 39. The concrete shall contain not less than 470 pounds of cement per cubic yard. The concrete shall contain 5 percent of entrained air, plus or minus 1 percent, as determined by ASTM C 231 and shall have a slump of not more than 4 inches as determined by ASTM C 143.

3.3 PROPORTIONING AND MEASURING DEVICES

A. When package cement is used, the quantity for each batch shall be equal to one or more whole sacks of cement. The aggregates shall be measured separately by weight. If aggregates are delivered to the mixer in batch trucks, the exact amount for each mixer charge shall be contained in each batch compartment. Weighing boxes or hoppers shall be approved by the COTR and shall provide means of regulating the flow of aggregates into the batch box so that the required and exact weight of aggregates can be readily obtained.

3.4 CONSISTENCY

A. The consistency of the concrete shall be checked by the slump test specified in ASTM C 143.

Page 175: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

STRUCTURAL PORTLAND CEMENT CONCRETE P-610 - 5

3.5 MIXING

A. Concrete may be mixed at the construction site, at a central point, or wholly or in part in truck mixers. The concrete shall be mixed and delivered in accordance with the requirements of ASTM C 94.

3.6 MIXING CONDITIONS

A. The concrete shall be mixed only in quantities required for immediate use. Concrete shall not be mixed while the air temperature is below 40°F without permission of the COTR. If permission is granted for mixing under such conditions, aggregates or water, or both, shall be heated and the concrete shall be placed at a temperature not less than 50°F nor more than 100°F. The Contractor shall be held responsible for any defective work, resulting from freezing or injury in any manner during placing and curing, and shall replace such work at his/her expense.

B. Retempering of concrete by adding water or any other material shall not be permitted.

C. The delivery of concrete to the job shall be in such a manner that batches of concrete will be deposited at uninterrupted intervals.

3.7 FORMS

A. Concrete shall not be placed until all the forms and reinforcements have been inspected and approved by the COTR. Forms shall be of suitable material and shall be of the type, size, shape, quality, and strength to build the structure as designed on the plans. The forms shall be true to line and grade and shall be mortar-tight and sufficiently rigid to prevent displacement and sagging between supports. The Contractor shall bear responsibility for their adequacy. The surfaces of forms shall be smooth and free from irregularities, dents, sags, and holes.

B. The internal ties shall be arranged so that, when the forms are removed, no metal will show in the concrete surface or discolor the surface when exposed to weathering. All forms shall be applied with a form releasing agent before the placement of reinforcement. Care shall be taken when placing reinforcement to keep the form releasing agent off reinforcement. Forms shall be constructed so that they can be removed without injuring the concrete or concrete surface. The forms shall not be removed before the expiration of at least 30 hours from vertical faces, walls, slender columns, and similar structures; forms supported by falsework under slabs, beams, girders, arches, and similar construction shall not be removed until tests indicate that at least 80% of the design strength of the concrete has developed.

3.8 PLACING REINFORCEMENT

A. All reinforcement shall be accurately placed, as shown on the plans, and shall be firmly held in position during concreting. Bars shall be fastened together at intersections. The reinforcement shall be supported by approved metal chairs. Shop drawings, lists, and bending details shall be supplied by the Contractor when required.

Page 176: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

STRUCTURAL PORTLAND CEMENT CONCRETE P-610 - 6

3.9 EMBEDDED ITEMS

A. Before placing concrete, any items that are to be embedded shall be firmly and securely fastened in place as indicated. All such items shall be clean and free from coating, rust, scale, oil, or any foreign matter. The embedding of wood shall be avoided. The concrete shall be spaded and consolidated around and against embedded items.

3.10 PLACING CONCRETE

A. All concrete shall be placed during daylight, unless otherwise approved or the work is restricted to take place at night. The concrete shall not be placed until the depth and character of foundation, the adequacy of forms and falsework, and the placing of the steel reinforcing have been approved. Concrete shall be placed as soon as practical after mixing and in no case later than 1 hour after water has been added to the mix. The method and manner of placing shall be such to avoid segregation and displacement of the reinforcement. Troughs, pipes, and chutes shall be used as an aid in placing concrete when necessary. Dropping the concrete a distance of more than 5 feet, or depositing a large quantity at one point, will not be permitted. Concrete shall be placed upon clean, damp surfaces, free from running water, or upon properly consolidated soil.

B. The concrete shall be compacted with suitable mechanical vibrators operating within the concrete. When necessary, vibrating shall be supplemented by hand spading with suitable tools to assure proper and adequate compaction. Vibrators shall be manipulated so as to work the concrete thoroughly around the reinforcement and embedded fixtures and into corners and angles of the forms. The vibration at any joint shall be of sufficient duration to accomplish compaction but shall not be prolonged to the point where segregation occurs. Concrete deposited under water shall be carefully placed in a compact mass in its final position by means of a tremie, a closed bottom dump bucket, or other approved method and shall not be disturbed after being deposited.

3.11 CONSTRUCTION JOINTS

A. When the placing of concrete is suspended, necessary provisions shall be made for joining future work before the placed concrete takes its initial set. For the proper bonding of old and new concrete, such provisions shall be made for grooves, steps, keys, dovetails, reinforcing bars or other devices as may be prescribed. The work shall be arranged so that a section begun on any day shall be finished during daylight of the same day. Before depositing new concrete on or against concrete that has hardened, the surface of the hardened concrete shall be cleaned by a heavy steel broom, roughened slightly, wetted, and covered with a neat coating of cement paste or grout.

3.12 EXPANSION JOINTS

A. Expansion joints shall be constructed at such points and of such dimensions as may be indicated on the drawings. The premolded filler shall be cut to the same shape as that of the surfaces being joined. The filler shall be fixed firmly against the surface of the concrete already in place in such manner that it will not be displaced when concrete is deposited against it.

Page 177: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

STRUCTURAL PORTLAND CEMENT CONCRETE P-610 - 7

3.13 DEFECTIVE WORK

A. Any defective work discovered after the forms have been removed shall be immediately removed and replaced. If any dimensions are deficient, or if the surface of the concrete is bulged, uneven, or shows honeycomb, which in the opinion of the COTR cannot be repaired satisfactorily, the entire section shall be removed and replaced at the expense of the Contractor.

3.14 SURFACE FINISH

A. All exposed concrete surfaces shall be true, smooth, and free from open or rough spaces, depressions, or projections. The concrete in horizontal plane surfaces shall be brought flush with the finished top surface at the proper elevation and shall be struck-off with a straightedge and floated. Mortar finishing shall not be permitted, nor shall dry cement or sand-cement mortar be spread over the concrete during the finishing of horizontal plane surfaces.

B. When directed, the surface finish of exposed concrete shall be a rubbed finish. If forms can be removed while the concrete is still green, the surface shall be pointed and wetted and then rubbed with a wooden float until all irregularities are removed. If the concrete has hardened before being rubbed, a carborundum stone shall be used to finish the surface. When approved, the finishing can be done with a rubbing machine.

3.15 CURING AND PROTECTION

A. All concrete shall be properly cured and protected by the Contractor. The work shall be protected from the elements, flowing water, and from defacement of any nature during the building operations. The concrete shall be cured as soon as it has sufficiently hardened by covering with an approved material. Water-absorptive coverings shall be thoroughly saturated when placed and kept saturated for a period of at least 3 days. All curing mats or blankets shall be sufficiently weighted or tied down to keep the concrete surface covered and to prevent the surface from being exposed to currents of air. Where wooden forms are used, they shall be kept wet at all times until removed to prevent the opening of joints and drying out of the concrete. Traffic shall not be allowed on concrete surfaces for 7 days after the concrete has been placed.

3.16 DRAINS OR DUCTS

A. Drainage pipes, conduits, and ducts that are to be encased in concrete shall be installed by the Contractor before the concrete is placed. The pipe shall be held rigidly so that it will not be displaced or moved during the placing of the concrete.

3.17 COLD WEATHER PROTECTION

A. When concrete is placed at temperatures below 40°F, the Contractor shall provide satisfactory methods and means to protect the mix from injury by freezing. The aggregates,

Page 178: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

STRUCTURAL PORTLAND CEMENT CONCRETE P-610 - 8

or water, or both, shall be heated in order to place the concrete at temperatures between 50°F and 90°F.

B. After the concrete has been placed, the Contractor shall provide sufficient protection such as cover, canvas, framework, heating apparatus, etc., to enclose and protect the structure and maintain the temperature of the mix at not less than 50°F until at least 80% of the designed strength has been attained.

3.18 HOT WEATHER PROTECTION

A. Prepare ingredients, mix, place, cure, and protect in accordance with ACI 305R.

B. Maintain concrete temperature below 90°F at time of placement, or furnish test data or provide other proof that admixtures and mix ingredients do not produce flash set plastic shrinkage, or cracking due to head of hydration. Cool ingredients before mixing to maintain fresh concrete temperatures as specified or less.

C. Provide for windbreaks, shading, fog spraying, sprinkling, ice, wet cover, or other means as necessary to maintain concrete at or below specified temperature.

D. Prevent differential temperature between reinforcing steel and concrete.

E. Apply evaporation retardant as required.

3.19 FILLING JOINTS

A. All joints that require filling shall be thoroughly cleaned, and any excess mortar or concrete shall be cut out with proper tools. Joint filling shall not be started until after final curing and shall be done only when the concrete is completely dry. The cleaning and filling shall be carefully done with proper equipment and in a manner to obtain a neat looking joint free from excess filler.

PART 4 - CONTRACTOR QUALITY CONTROL

4.1 FIELD QUALITY CONTROL

A. Division 1 Section “Quality Requirements” specifies the general requirements for the Contractor’s Quality Control Program.

B. The following describes the minimum inspection and testing required in the Contractor’s Quality Control (CQC) Plan and Program for the work of this section and is for CQC only. The implementation of the Contractor Quality Control Program does not relieve the Contractor from the responsibility to provide the work in accordance with the Contract Documents, applicable codes, regulations, and governing authorities. The CQC Plan and Program shall include, but not be limited to, the elements listed in Section 4.2. These elements are provided only as a minimum starting point for the Contractor to use to generate his complete CQC Program.

Page 179: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

STRUCTURAL PORTLAND CEMENT CONCRETE P-610 - 9

4.2 ACCEPTANCE SAMPLING AND TESTING

A. Concrete for each structure will be accepted on the basis of the specified 28-day compressive strength. Evaluation will be in accordance with ACI 301 and Specifications.

B. Prior to discharging into forms, test entrained air concrete in accordance with ASTM C231. The sample secured for the tests will be taken after at least 2 cubic feet of concrete has been discharged from the delivery vehicle. Perform tests for each batch of concrete (minimum), or every 10 cubic yards (maximum) of concrete.

C. Prior to discharge into forms, take concrete samples for slump in accordance with ASTM C143. Perform slump tests for each batch of concrete (minimum), or every 10 cubic yards (maximum) of concrete.

D. Test the temperature of the concrete delivered and in the concrete forms. Perform tests in hot or cold weather conditions (blow 50 degrees F and above 80 degrees F) for each batch of concrete (minimum), or every 10 cubic yards (maximum) of concrete.

E. Specimens shall be made, cured, and tested in accordance with ASTM C31 and ASTM C39. Provide concrete cylinders for compressive tests not less than once a day, nor less than once for each 50 cubic yards of concrete.

F. Provide adequate facilities for safe storage and proper curing of concrete testing cylinders onsite for first 24 hours, and for additional time as may be required before transporting to test lab.

G. Concrete represented by cylinders failing to meet strength and air content specified shall be rejected.

H. Special Inspections as defined by Section 1704 of IBC 2006 may be required by the building officials to secure approval of the work. The Special Inspections program shall be provided by others. The contractor shall provide the special inspections engineer free access to the work site.

PART 5 - METHOD OF MEASUREMENT

5.1 GENERAL

A. No separate measurement of this item will be made.

PART 6 - BASIS OF PAYMENT

6.1 GENERAL

A. No separate payment will be made for structural Portland Cement Concrete. Measurement and payment for this item shall be made under the appropriate items(s) requiring use of Portland Cement Concrete as specified at the unit and/or lump sum prices for these items,

Page 180: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

STRUCTURAL PORTLAND CEMENT CONCRETE P-610 - 10

including furnishing all materials and for all preparation, delivery, and installation of these materials, and for all labor, equipment, tools and incidentals necessary to complete the item.

TESTING REQUIREMENTS ASTM C 31 Making and Curing Test Specimens in the Field ASTM C 39 Compressive Strength of Cylindrical Concrete Specimens ASTM C 136 Sieve Analysis of Fine and Coarse Aggregates ASTM C 138 Density (Unit Weight), Yield, and Air Content (Gravimetric) of Concrete ASTM C 143 Slump of Hydraulic Cement Concrete ASTM C 231 Air Content of Freshly Mixed Concrete by the Pressure Method ASTM C 666 Resistance of Concrete to Rapid Freezing and Thawing ASTM C 1077 Laboratories Testing Concrete and Concrete Aggregates for Use in

Construction and Criteria for Laboratory Evaluation ASTM C 1260 Potential Alkali Reactivity of Aggregates (Mortar-Bar Method) MATERIAL REQUIREMENTS ASTM A 184 Specification for Fabricated Deformed Steel Bar or Rod Mats for

Concrete Reinforcement ASTM A 185 Steel Welded Wire Fabric, Plain, for Concrete Reinforcement ASTM A 497 Steel Welded Wire Fabric, Deformed, for Concrete Reinforcement ASTM A 615 Deformed and Plain Billet-Steel Bars for Concrete Reinforcement ASTM A 704 Welded Steel Plain Bars or Rod Mats for Concrete Reinforcement ASTM C 33 Concrete Aggregates ASTM C 94 Ready-Mixed Concrete ASTM C 150 Portland Cement ASTM C 171 Sheet Materials for Curing Concrete ASTM C 172 Sampling Freshly Mixed Concrete ASTM C 260 Air-Entraining Admixtures for Concrete ASTM C 309 Liquid Membrane-Forming Compounds for Curing Concrete

Page 181: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

STRUCTURAL PORTLAND CEMENT CONCRETE P-610 - 11

ASTM C 494 Chemical Admixtures for Concrete ASTM C 595 Blended Hydraulic Cements ASTM C 618 Coal Fly Ash and Raw or Calcined Natural Pozzolan for Use as a

Mineral Admixture in Concrete ASTM D 1751 Specification for Preformed Expansion Joint Fillers for Concrete Paving

and Structural Construction (Non-extruding and Resilient Bituminous Types)

ASTM D 1752 Specification for Preformed Sponge Rubber and Cork Expansion Joint

Fillers for Concrete Paving and Structural Construction AASHTO T 26 Quality of Water to be Used in Concrete

END OF SECTION P-610

Page 182: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final
Page 183: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

GENERAL PROVISIONS AND REQUIREMENTS FOR ELECTRICAL WORK L-100 - 1

ITEM L-100 GENERAL PROVISIONS AND REQUIREMENTS FOR ELECTRICAL WORK

PART 1 - DESCRIPTION

1.1 SPECIAL REQUIREMENTS FOR ELECTRICAL WORK. These special requirements shall apply for the electrical work. Where the contract special conditions or general provisions also apply, the stricter of the documents shall apply.

1.2 AUXILIARIES AND ACCESSORIES. Include all auxiliaries and accessories for a complete and properly operating system, to the satisfaction of the COTR.

Provide and install all electrical systems and any necessary appurtenances as per FAA Advisory Circulars, NEC and local codes whether specified or shown on drawings or not. The content of these specifications and contract documents in general only refers to work required above and beyond the requirements of the NEC and applicable local codes.

1.3 PROJECT PAY ITEMS. The project pay items are provided to be inclusive of all work to be performed as shown in the contract documents. All work not identified with a specific pay item is to be considered work to complete the project and is to be subsidiary to the cost of project pay items provided.

1.4 REFERENCES.

A. ANSI - American National Standards Institute.

B. ANSI/NFPA 70 - National Electrical Code.

C. AWS - American Welding Society.

D. EPA - U.S. Environmental Protection Agency.

E. FS - Federal Specifications.

F. ICEA - Insulated Cable COTRs Association.

G. IEEE - The Institute of Electrical and Electronic COTRs.

H. IES - Illuminating Engineering Society.

I. International Electrical Testing Association.

J. National Bureau of Standards.

K. NECA - National Electrical Contractors' Association.

L. NEMA - National Electrical Manufacturers' Association.

M. NESC - National Electrical Safety Code.

Page 184: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

GENERAL PROVISIONS AND REQUIREMENTS FOR ELECTRICAL WORK L-100 - 2

N. NFPA - National Fire Protection Association.

O. OSHA - Occupational Safety and Health Administration.

P. UL - Underwriters' Laboratories, Inc.

Q. Other standards as referenced in individual sections.

PART 2 – SUMMARY OF WORK

2.1 SUPERVISION AND ATTENDANCE. The Contractor shall provide a resident field superintendent who has had a minimum of four years previous successful experience on projects of comparable sizes and complexity. The Superintendent shall be present at all times that work under this division is being installed or affected.

2.2 RECORD DOCUMENTS. The Contractor shall maintain the contract documents, shop drawings and samples at the site, in good order and annotated daily to show all changes made during the construction process, per Section L-106, Submittals, Record Documents and Maintenance Manuals. These shall be available to the COTR for examination.

2.3 SAFETY AND PROTECTION. The Contractor shall be solely and completely responsible for initiating, maintaining and supervising all safety precautions and programs in connection with the work. The Contractor shall take all necessary precautions for the safety of, and shall provide the necessary protection to prevent damage, injury or loss to:

A. All employees on the work and other persons (including but not limited to the general public) who may be affected thereby,

B. All the work and all materials or equipment to be incorporated therein, whether in storage on or off the site, and

C. Other property at the site, adjacent thereto, or utilized by the Contractor including but not limited to trees, shrubs, lawns, walks, pavements, structures, underground facilities, and other utilities not designated for removal, relocation or replacement in the course of construction regardless of whether or not such other property is indicated in the Contract Documents.

D. Existing underground utilities and systems both shown on the plans and those not shown. The Contractor shall have all utilities and systems field located by the FAA or appropriate authorities having jurisdiction and shall take whatever measures necessary to protect the utilities and systems from damage.

The Contractor shall comply with all applicable laws, ordinances, rules, regulations and orders of any public body having jurisdiction for the safety of persons or property or to protect them from damage, injury or loss.

All hoisting machinery shall be inspected by a competent person or by a government or private agency recognized by the U.S. Department of Labor. A copy of the written inspection report shall be submitted to the COTR prior to the start of work requiring the use of this equipment.

Page 185: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

GENERAL PROVISIONS AND REQUIREMENTS FOR ELECTRICAL WORK L-100 - 3

The installation and/or removal of lighting equipment may be critical to airport operations; therefore, the Contractor shall follow work schedules established in the plans and specifications or as directed by the COTR. The system shall be installed in accordance with the National Electrical Code and/or local code requirements.

The Contractor shall provide temporary wiring as required to reconnect existing circuits to provide guidance for aircraft to pass through the construction areas on those taxiways/runways, which must remain open. The Contractor shall check all temporary circuits before dark each day to assure that they are operational. In the event of failure, the Contractor shall immediately take steps to restore operation.

The Contractor shall provide all safety rails as required in the performance of the work at building perimeters, at perimeters of floor and/or roof openings and on scaffold systems or platforms in accordance with the above regulations. Maintain safety rails during the duration of the work for this Contract. This Contractor shall be responsible for the removal and replacement of any safety rail necessary for the installation of equipment or materials provided in this work.

Powder-actuated fasteners will not be allowed without express written approval of the COTR. No fasteners shall pierce the structure until approved by the COTR.

Clean up of scrap materials and waste of the Contractor to be completed daily or more frequently as needed.

2.4 COTR INSPECTIONS. Items noted by the COTR, or their authorized representative during construction and before final acceptance, which do not comply with the contract, documents will be listed in accordance with the specifications. These items will be sent to the Contractor for action. The Contractor shall have these items corrected.

Items noted after acceptance during the warranty period shall be checked and corrected by the Contractor in a timely manner acceptable to the COTR.

2.5 EXISTING CONDITIONS. Investigate the construction site thoroughly and reroute all conduit and wiring in area of new construction in order to maintain continuity of existing circuitry. Existing conduit shown on plans show approximate locations only. The Contractor must verify and coordinate existing site utilities, conduits and piping. The specifications include hand digging within 5 feet of all existing utilities and all required rerouting in areas of existing utilities, conduits and/or pipes.

The Contractor shall check the construction site and existing conditions thoroughly before bidding. The Contractor shall advise the COTR of discrepancies or questions noted.

Special attention is called to the fact that work involved in this project is in connection with existing systems/facilities, which must remain in operation while work is being performed. Work must be done in accordance with the schedule specified in the contract documents. Schedule work for a minimum outage to the Authority. Request written permission and receive written approval from the COTR a minimum of 72 hours in advance of any shut-down of existing systems. Perform work required at other than standard working hours where outages cannot be approved during regular working hours. Protect existing buildings and equipment during construction as required.

Page 186: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

GENERAL PROVISIONS AND REQUIREMENTS FOR ELECTRICAL WORK L-100 - 4

Special attention is called to the fact that there may be piping, fixtures or other items in the existing systems, which must be removed or relocated in order to perform the alteration work. All conduit, wiring, boxes, etc. that do not comply with these specifications shall be removed or corrected to comply with these specifications. All unused conduit not removed shall be identified and a pull line shall be installed. Bid shall include all removal and relocation required for completion of the alterations and the new construction.

If any difference is discovered between the existing conditions and the drawings or specifications, the COTR shall be notified in writing immediately.

2.6 SPECIAL PROVISIONS FOR PROTECTION OF CABLES, CONTROLS, NAVAIDS AND WEATHER BUREAU FACILITIES. This provision for the protection of cables, controls, navigational aids and weather bureau facilities has been taken from Appendix 3 of FAA Advisory Circular 150/5370-4. Although the Advisory Circular has been cancelled, the requirements of Appendix 3 are included herein and made a part of this specification.

The Contractor is hereby informed that there are installed on the Airport FAA NAVAIDS; including, without limitation, ASR, UHF and VHF Receivers and Transmitters; U.S. Weather Bureau facilities; electric cables and controls relating to such NAVAIDS and facilities, and other electric power cables serving other facilities. Such NAVAIDS, Weather Bureau and other facilities, and electric cables must be fully protected during the entire construction time. Work under this contract can be accomplished in the vicinity of these facilities and cables only at approved periods of time. Approval is subject to withdrawal at any time because of changes in the weather, emergency conditions on the existing airfield areas, anticipation of emergency conditions, and for any other reason determined by the COTR acting under the orders and instructions of the airport management and/or the designated FAA representatives. Any instructions to the Contractor to clear any given area, at any time, by the COTR, or the FAA Air Traffic Control Tower (by radio or other means) shall be immediately executed. Construction work will be commenced in the cleared area only when additional instructions are issued by the proper authorities.

Power and control cables leading to and from any FAA NAVAIDS, Weather Bureau and other facilities, will be marked in the field by the authority having jurisdiction or the utility locating authority for the information of the Contractor, before any work in their general vicinity is started. Thereafter, through the entire time of this construction they shall be protected from any possible damage, including crossing with unauthorized equipment, etc.

These provisions intend to make perfectly clear the need for protection of FAA NAVAIDS, Weather Bureau and other facilities, and cables by the Contractor at all times.

The Contractor shall immediately repair, with identical or higher quality material by skilled workmen, any underground cables serving FAA NAVAIDS, Weather Bureau and other airport facilities, which are damaged by the Contractor’s workmen, equipment or work. Prior approval of the FAA must be obtained for the materials, workmen, time of day or night, method of repairs, and for any temporary or permanent repairs the Contractor proposes to make to any FAA NAVAIDS and facilities damaged by the Contractor. Prior approval of the COTR must be obtained for the materials, workmen, time of day or night, and for the method of repairs for any temporary or permanent repairs the Contractor proposes to make to any other airport facilities and cables damaged by the Contractor.

Page 187: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

GENERAL PROVISIONS AND REQUIREMENTS FOR ELECTRICAL WORK L-100 - 5

2.7 WORK SEQUENCE.

A. Install Work to accommodate Airport's present occupancy requirements during the construction period. Coordinate electrical schedule and operations with COTR, Contractors working on site and other requirements of the specifications. The Airport will remain in operation during construction.

B. Shutdown of existing electrical facilities shall be kept to an absolute minimum and coordinated with the COTR. Shutdown shall be made at hours convenient to the Airport. This includes evening and weekend hours.

C. The cost of any anticipated overtime work shall be included in the Contractor’s base bid. Requests for additional compensation for this work after award of contract will be refused

D. Coordinate all work with all other contractors and subcontractors.

2.8 SYSTEMS GUARANTEE. The work required under this specification shall include a 1-year warranty unless required otherwise by these specifications. This warranty shall be by the Contractor to the Authority for any defective workmanship or material, which has been furnished under this contract for a period of 1 year from the date of final acceptance of the system. This warranty shall not include light bulbs in service after 1 month from date of final acceptance of the system. Explain the provisions of the warranty to the Authority at the "Demonstration of Completed System."

2.9 SUBSTANTIAL COMPLETION. All specified work shall be complete prior to final inspection of the work, and all forms and other information requested, including maintenance manuals, shall be submitted to the COTR for approval 1 week before the request for substantial completion of the work.

The Contractor shall demonstrate the function of any equipment and system as requested. In the event that any equipment or system does not function correctly, the Contractor shall perform any tests and provide test equipment required to ascertain the cause.

2.10 FINAL ACCEPTANCE. All work specified shall be complete after the substantial completion observation, all repairs made, and all required information approved at which time the COTR shall formally accept the project and take possession of all work on a permanent basis.

2.11 CONTRACTOR’S RESPONSIBILITIES. Provide necessary layout, labor, material, equipment, tools, transportation, full time supervision and services required for the satisfactory and timely completion of the work in accordance with the drawings and specifications and contract documents.

Unload, store, protect and re-handle the materials required for this contract until such time that material is in place. Provide protection of materials required of this contract after installation.

Provide all required transportation, erection, maintenance, dismantling and removal of temporary facilities and equipment required by this contract.

Provide all transportation, unloading, distribution, hoisting, rigging, material handling and scaffolding required to install the work of this contract.

Page 188: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

GENERAL PROVISIONS AND REQUIREMENTS FOR ELECTRICAL WORK L-100 - 6

Provide all engineering and layout required to perform the work.

Prior to start of his work the Contractor is to inspect work performed by others on which this work is to be placed on or adjacent to, and report in writing to the COTR, any condition found to be unacceptable. Failure to make said report shall constitute acceptance of the conditions found and any claims made thereafter due to the unacceptable conditions will not be considered by the COTR.

Provide all required coordination and supervision where work connects to or is affected by work of others, and comply with all requirements affecting this work. Work required under other sections, specifications or drawings to be performed by this section shall be coordinated with the respective contractor, and such work performed at no additional cost to the Authority including but not limited to electrical work in support of the mechanical division of the specifications and drawings.

It is the responsibility of the Contractor to coordinate the exact required location of any electrical or electronic equipment, system, or cabinets to be installed in or relocated inside an existing electrical or electronic equipment space. No existing equipment may be relocated in any existing electrical or electronic equipment room without prior coordination and with written approval of the COTR.

The Contractor shall pay all sales, consumer, use and other taxes required to be paid in accordance with the laws of the place of the project.

Provide all tests as required, per the drawings and specifications and submit all test reports to the COTR.

Provide all excavation, backfill, compaction, shoring and dewatering required for performance of the work.

Provide sleeves for all conduit required as specified.

Protect all work of this contract from damage and intrusion of dirt and foreign objects. Close off open ends of conduit and sleeves on work, which is to be completed at a later date. Remove closure material prior to continuance of work.

Prior to Final Inspection, submit to the COTR, all Record Drawings and Operation and Maintenance Manuals as specified. Instruct maintenance personnel in the operation and maintenance of the systems as required by the Specifications.

The above is not all inclusive of the work described by the drawings and Specifications, which form the basis for this contract, but is presented for the Contractor's convenience.

2.12 INTERPRETATION OF DRAWINGS AND SPECIFICATIONS. Should anything necessary for the clear understanding of the electrical work be omitted from the contract documents, or should the requirements appear to be in conflict, the Contractor shall secure written instructions from the COTR before proceeding with the work affected thereby; otherwise the Contractor will be deemed to be proceeding at his own risk and expense. It is understood and agreed that the work shall be performed according to the true intent of the contract documents.

Page 189: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

GENERAL PROVISIONS AND REQUIREMENTS FOR ELECTRICAL WORK L-100 - 7

PART 3 - BASIC MATERIAL AND METHODS

3.1 REQUIREMENTS OF BASIC MATERIALS AND METHODS. The work shall include the furnishing of the systems, equipment and material specified in these specifications and as called for on the drawings, to include: supervision, operations, methods and labor for the fabrication, installation, startup and tests for the complete electrical installation. Provide the necessary intertrade/Contractor coordination for the installation to be in a neat and workman like manner.

Drawings for the work are diagrammatic, intended to convey the scope of the work and to indicate the general arrangement and locations of the work. The drawings shall not be scaled for exact sizes or locations. Because of the scale of the drawings, certain basic items such as: conduit fittings, access panels, sleeves, pull and junction boxes may not be shown. Where such items are required by Code or by other sections or where they are required for proper installation of the work, such items shall be included. Coordinate final equipment locations with governing architectural and structural drawings. Layout equipment before installation so that all trades may install equipment in the space available.

Equipment Specifications may not deal with minute items such as components, parts, controls and devices, which may be required to produce the equipment performance specified, or as required to meet the equipment warranties. Where such items are required, they shall be included by the Contractor or the supplier of the equipment, whether or not specifically called for.

Conduit routed through any buildings that interferes with other equipment and construction shall not constitute a reason for an extra charge. Equipment, conduit, and fixtures shall fit into available spaces in the building; do not introduce these into the building at such times or in such manner as to cause damage to the structure. Equipment that requires servicing shall be readily accessible.

Locate all openings required for work performed under this section. Provide sleeves, guards or other approved methods to allow passage of items installed under this section.

Keep cutting and patching to a minimum. Insofar as possible, determine in advance the proper chase size and openings necessary for the work.

Where cutting and patching are required due to an error of the Contractor, or where the Contractor has not given enough advance notice of the need for holes, recesses, and chases, patching shall be performed by those trades skilled in the use of the materials involved and shall be done at the Contractor's expense.

Any cutting of work in place shall be patched and decorated by such mechanics and in such a manner that the quality of workmanship and finish shall be compatible with that of adjacent construction.

The approximate location of building fixtures, wall switches, etc., is indicated on the drawings. Exact locations shall be determined by the COTR as building work progresses. The indicated locations may be changed by 10 feet in any direction without additional cost before the items are installed.

The drawings and specifications describe specific sizes of switches, breakers, fuses, conduits, conductors, motor starters and other items of wiring equipment. These sizes are based on specific

Page 190: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

GENERAL PROVISIONS AND REQUIREMENTS FOR ELECTRICAL WORK L-100 - 8

items of power consuming equipment (heaters), lights, motors for fans, compressors, pumps, etc.) Wherever the Contractor provides power consuming equipment, which differs from drawings and specifications, the wiring and associated circuit components for such equipment shall be changed to proper sizes to match at no additional expense to the Authority.

The basis for new design requires that electrical services, switchgear, panelboard and transformers total calculated connected load not be more than 60 percent of the service size. The total calculated load requirements for alterations shall not be more than 80 percent.

Furnish to roofer all pitch pans required for electrical items, which pierce roof whether or not shown on drawings. Roof penetrations are to be waterproofed in such a manner that roofing guarantees are fully in force. Floor penetrations shall be sealed with fire proof sealant to prevent water from leaking to floor below and to provide a 3-hour fire and smoke barrier. Wall penetrations shall be sealed to provide a 3-hour rated fire seal.

Surface mounted fixtures, outlets, cabinets, conduit, panels, etc., shall have finish or shall be painted as directed by the COTR. Paint shall be in accordance with other applicable sections of these specifications.

All materials utilized shall be suitable for the environment encountered. No combination of materials shall be used that forms an electrolytic coupling of such nature that in the presence of moisture corrosion is accelerated.

In general, all relays, contactors, starters, motor control centers, switchboards, panelboards, dry type transformers, disconnect switches, circuit breakers, and manual motor starter switches are to be supplied and manufactured by the same manufacturer and shall be submitted and approved as equal to that specified.

Make electrical connections to constant current regulators, transformers, motors, instruments, mechanical equipment, controls and at other locations as required with approximately 3 feet (12 inches minimum) of Sealtight flexible conduit. The sealtight electrical conduit shall utilize strain relief type connectors by adding a T&B wire mesh grip, WMG-LT series, or approval equal to each sealtight connector. Determine the requirements from drawings, these specifications, and the approved manufacturer drawings.

Provide inserts, hangers, supports, braces, and anchor bolts as necessary for all work called for under these specifications.

All conduits shall contain one copper grounding conductor, in accordance with NFPA 70, NEC Article 250. No. 6 AWG and smaller shall have green insulation. No. 4 AWG and larger shall be bare. The only exception is the 5KV airfield lighting conduits and ductbanks.

All galvanized materials shall be hot-dip galvanized after fabrication, conforming to ASTM A 123 and/or A 153, unless noted otherwise.

Unless noted otherwise, all panelboards, motor starters, junction boxes, wireways, etc., shall be spaced off the concrete structure by using a Unistrut P-1060 series square washer or approved equivalent between the mounting surface and the equipment at each mounting point. Equipment as listed above, mounted on Unistrut or approved equivalent shall have Unistrut P-1060 series square washer or approved equivalent installed between the Unistrut channel or approved

Page 191: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

GENERAL PROVISIONS AND REQUIREMENTS FOR ELECTRICAL WORK L-100 - 9

equivalent and the equipment at each mounting point. All bolted connections and equipment mountings shall utilize a flat washer, lock washer and hex head A-325 bolting hardware.

Unless noted otherwise, all wire sizes are based on a 135 degrees F (75 degrees C), XHHW THWN-2 600 volt insulation, copper conductors, not more than three single insulated conductors, in raceway, in free air. The conduit sizes are based on the use of XHHW THWN-2 600 volt insulated conductors. The Contractor shall make the necessary increase in conduit sizes for other types of wire insulation. In no case shall the conduit size be reduced. The minimum wire size shall be No. 12 AWG.

All electrical conductors, windings, busbars, etc. shall be high conductivity (98 percent conductivity) copper.

The Contractor shall furnish and install all required motor overcurrent protection required by the NEC and these drawings and specifications. The overcurrent protection shall be sized according to the motor nameplate data.

3.2 ELECTRICAL REFERENCE SYMBOLS. Symbols used on the plans are defined in the Electrical Legend on the Drawings. Not necessarily will all symbols scheduled be applicable to the project.

3.3 ACTIVE SERVICES. Existing active services i.e., water, gas, sewer, electric, communications, etc. when encountered, shall be protected against damage. Do not prevent or disturb operation of active services, which are to remain. If active services are encountered which require relocation, the Contractor shall make a written request to the COTR for determination of procedures. Where existing services are to be abandoned, they shall be terminated in conformance with requirements of the Utility or Municipality or Authority having jurisdiction.

3.4 ELECTRIC SERVICE INTERRUPTIONS.

A. Electrical service is defined as any electrical, communication, data, fire alarm and any other electrical transmission system. Other services include but are not limited to water, sanitary, gas, HVAC and storm water systems.

B. The Contractor shall notify the COTR of the intent to perform any Work requiring service interruptions and shall proceed with such work only after receiving a time schedule approved by the COTR. The COTR shall have the right to cancel or delay the time of any service interruption. The Contractor shall provide personnel and equipment to assist in the proper coordination of service interruptions. The Contractor shall not leave the job site until resumption of normal service is satisfactory to the COTR.

C. Coordinate required facility shutdowns through the COTR.

D. When service interruptions are required to perform the contract work on transformers, circuit breakers or feeder cables, the Contractor shall arrange the distribution system from dual service to single service. In the event that service interruptions cannot be accomplished by supplying single line utility service, the Contractor shall provide reliable and adequate capacity generators including all temporary connections, secondary distribution equipment, disconnections, cables, safety devices and fuel unless otherwise

Page 192: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

GENERAL PROVISIONS AND REQUIREMENTS FOR ELECTRICAL WORK L-100 - 10

noted. The use of temporary transformers and substation equipment will be considered by the COTR.

E. Shutdown times must be minimized where entire building or sections of buildings are to be shut down. Shut down periods shall occur between 0100 and 0500 hours. On site generators will be necessary in areas where facilities are out of service for more than 1/2 hour. All switching and change-overs will be performed by the Contractor and witnessed by the COTR. Coordination of all service interruptions will be performed by the COTR

F. Contractor shall perform all work involving service interruptions at times designated by the COTR or at night and/or Saturday or Sunday. No allowances will be made by the Authority for overtime labor costs.

G. Where Contractor interrupts any electrical or other service due to damaging equipment or cable through their negligence, they shall be required to repair or replace the equipment or cable immediately, working continuously to restore service until satisfactory to the COTR. Repair, replacement or both shall be at the discretion of the COTR and at the expense of the Contractor.

H. Contractor shall note that the Airport shall be occupied and in use during the construction period. Contractor shall not disturb continuity of service to any area without the written approval and agreement as to time and duration of such interruption. Contractor shall perform any of this work at any time without extra cost to Authority.

I. Contractor shall fully examine all areas of demolition in this contract. Contractor shall identify all services related to its trades. Contractor shall provide protection of such service to prevent disruption of service. Contractor shall reroute all services to remain as required to approved locations without extra cost to the Authority.

3.5 CODES AND FEES. Install in accordance with latest edition of FAA Advisory Circulars, the National Electrical Code and the regulations of governing Federal, State, County, local and other applicable codes, including the Utilities Company. Where a conflict in code requirements occurs the most stringent requirement shall govern. The Contractor shall be responsible and pay all required permits, licenses, services, fees and inspections including meter installation fee. The cost for such shall be included in the bid price.

Deliver to the COTR, prior to the start of construction, a copy of all permits and licenses required for the work. At the completion of the work, secure and deliver to the COTR all certificates of compliance of local authorities.

The work shall meet the requirements and recommendations of applicable portions of the latest editions of these standards:

A. ANSI.

B. Applicable Local Building Code

C. AWS D1.1.

D. Certified Ballast Manufacturers (CBM).

Page 193: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

GENERAL PROVISIONS AND REQUIREMENTS FOR ELECTRICAL WORK L-100 - 11

E. Federal Aviation Administration Advisory Circulars (AC).

F. Institute of Electrical and Electronics COTRs (IEEE).

G. Life Safety Code (NFPA 101).

H. Lightning Protection Code (NFPA) 780 and UL 96A).

I. National Electrical Code (NFPA 70).

J. National Electrical Safety Code (ANSI C2).

K. NEMA Standards (NEMA).

L. NFPA.

M. Underwriter's Laboratories (UL).

The above is not all inclusive of applicable codes and standards, but is presented for the Contractors convenience.

3.6 STANDARDS. All materials shall be new and free of defects and shall be U.L. listed, bear the U.L. label or be labeled or listed with an approved, nationally recognized Electrical Testing Agency. Where no labeling or listing service is available for certain types of equipment, test data shall be submitted to prove to the COTR that equipment meets or exceeds available standards. All listed, labeled or approved material shall be used only for the intended purpose.

3.7 TESTS. Systems shall be tested by the Contractor and placed in proper working order prior to demonstrating systems to the COTR. Refer to the requirements in each section for other applicable standards.

After work is completed a load balance test shall be made, as required, to demonstrate that with full lighting and mechanical load the balance between phases is within 5 percent. Unbalance beyond this limit shall be corrected.

Perform such tests as required by any Authorities having jurisdiction over the site. Refer to specification L-131, Demonstrations, Tests and Performance Verification.

Testing methods shall be acceptable to the COTR and shall be submitted to the COTR for review, a minimum of 30 days prior to the scheduled test.

The Contractor shall supply all labor, materials, instruments and miscellaneous equipment for any examination of work or tests as required. All test results shall be recorded and submitted to the COTR.

3.8 LAMINATED PHENOLIC PLASTIC NAMEPLATES. The Contractor shall provide nameplates for wiring systems and equipment as called for herein. All nameplates shall have beveled edges and 1/2 inch lettering. If equipment is smaller than 10 inches by 6 inches, 1/4 inch lettering may be used. Smaller lettering may be used with permission of the COTR.

Page 194: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

GENERAL PROVISIONS AND REQUIREMENTS FOR ELECTRICAL WORK L-100 - 12

Nameplates shall be laminated phenolic plastic, black front and back with white core, with lettering etched through the outer covering. White engraved letters on black background. Emergency systems shall use red front and back with white core for nameplates. Attach nameplates with 4-40 stainless steel self tapping screws. Where conditions do not warrant piercing the enclosure "LOCTITE" brand adhesive or approved equivalent may be used with permission of the COTR.

The following items shall be equipped with nameplates: all constant current regulators, pushbutton stations, control panels, system cabinets, terminal cabinets, disconnect switches, panelboards, circuit breakers, contactors or relays in separate enclosures, high voltage boxes and cabinets whether existing or planned by these specifications. Special electrical systems shall be identified at junction and pull boxes, terminal cabinets and equipment racks. Junction boxes shall comply with paragraph 100-3.10, Junction/Pull Box Color Code.

Nameplates shall adequately describe the function of the particular equipment involved. Where nameplates are detailed on the drawings, inscription and size of letters shall be as shown and shop drawing submitted for approval. Nameplates for panelboards and switchboards shall include the panel designation, panel name, circuit designation source of power and voltage and phase of the supply. For example, "Equip YY, Panel A, CKT XX fed from Panel XYZ, 480/277V, 3-phase, 4-wire." The name of the machine on the nameplates for a particular machine shall be the same as the one used on all motor starters, disconnects and pull box station nameplates for that machine. Nameplates shall include as a minimum the following:

A. Equipment number.

B. Equipment name.

C. Power source with circuit designation.

D. Voltage level and number of phases.

All major pull and junction boxes in service areas, tunnels, above accessible ceilings and in accessible chases shall have nameplates identifying the feeder or system.

Systems with conductors exceeding 100 volts to ground shall have voltage identification nameplates with 1/2-inch-high letters on all panels, switches, pull boxes and junction boxes.

3.9 ADHESIVE-BACKED CLOTH MARKERS. All raceways containing conductors exceeding 150 volts to ground shall have adhesive backed cloth/vinyl markers installed at each end and every 30 feet in-between identifying the voltage level (Example: "480 VOLTS"). If the conduit is less than 10 feet in length one marker is acceptable. The markers shall be installed so they are visible from floors and walkways. Normal power system shall use black letters, emergency systems shall use red letters.

The markers shall be "Brady" brand or approved equivalent with 1/2 inch letters.

The markers shall be suitable for the environmental conditions encountered.

Page 195: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

GENERAL PROVISIONS AND REQUIREMENTS FOR ELECTRICAL WORK L-100 - 13

3.10 JUNCTION/PULL BOX COLOR CODE. Circuit numbers and circuit identification shall be printed on junction box and pull box covers using ink markers and shall be plainly visible after paint is applied. The entire box and cover shall be color coded as listed below:

Color Code for Junction Boxes Krylon Color and Paint No. or Approved Equivalent

Normal Power 480/277 Volt Brown 2501-6

Normal Power 208/120 Volt Black 1601-6

3.11 WELDING. All welding and weld procedures shall be in accordance with AWS D1.1, Latest

Edition. Qualifications of welders and welding operators shall be in accordance with AWS D1.1, Latest Edition. The welder qualification test shall be performed on a 1-inch A-36 Test Coupon in the 3G and 4G positions. The welder qualification shall be current within 12 months of the work being performed. Weld inspections shall be per the criteria set forth in AWS D1.1 for visual weld inspection.

PART 4 - DESIGNATION OF MATERIALS

4.1 CRITERION DESIGNATION OF MATERIALS AND EQUIPMENT. Where a criterion specification is designated for any material or equipment to be installed by the name or catalog number of one specific manufacturer, such designation is intended only for the purpose of establishing the style, quality, performance characteristics, etc., and is not intended to limit acceptability of competitive products. Products of other manufacturers which are approved by the COTR as similar and equal will be equally acceptable unless specifically otherwise stated.

Where equipment or materials are specified by the use of the name and catalog number of more than one manufacturer, that equipment or material shall be one of those specified. No alternative will be acceptable.

Where no brand name is specified, the source and quality shall be subject to the COTR's review and acceptance.

When a product is specified to be in accordance with a trade association or government standard, at the request of the COTR, the Contractor shall furnish a certificate that the product complies with the referenced standard. Upon request of the COTR, the Contractor shall submit supporting test data to substantiate compliance.

The COTR shall be the sole judge of whether the proposed "or equal" is suitable for use in the work.

Each Bidder represents their bid is based upon the materials and equipment described in these specifications. Substitutions will not be considered unless a written request has been submitted to the COTR.

If the Contractor desires to use a method or type of equipment other than specified in the contract documents, a written request therefore shall be made to the COTR. If approval is given, the Contractor will not be excused from producing work in conformity with contract requirements. If a trial use establishes that work does not meet the contract requirements, the Contractor shall take such action as the COTR determines necessary to correct any deficiency in the work. No change

Page 196: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

GENERAL PROVISIONS AND REQUIREMENTS FOR ELECTRICAL WORK L-100 - 14

in contract time will be made as a result of changes made under this Subparagraph. By making a request for substitution, the Contractor:

A. Represents that it has personally investigated the proposed substitution and determined the proposed substitution equal or superior in all respects to the specified method or equipment;

B. Represents that it will provide a warranty for the substitution identical in all respects to the warranty for the specified method or equipment;

C. Represents that it will coordinate the installation of the accepted substitute, making changes as may be required for the work to be complete in all respects at no additional cost to the Authority.

PART 5 - REQUIREMENT FOR THE PROTECTION OF MATERIALS, EQUIPMENT AND WORK

5.1 REQUIREMENT FOR THE PROTECTION OF MATERIALS, EQUIPMENT AND WORK. Materials shall be stored so as to assure the preservation of their quality and fitness for the work. Stored materials, even though approved before storage, shall be subject to reinspection prior to their use in the work. The Contractor shall coordinate the storage of all materials with the COTR.

Authority-furnished materials, if any, shall be made available to the Contractor at the location specified herein. All costs of handling, transportation from the specified location to the site of the work, storage and installation of Authority-furnished materials shall be included in the Total Contract Price. All risk of loss or damage to Authority-furnished materials shall pass to the Contractor after delivery of said material to the site of the work. The Authority shall be entitled to deduct from any monies due or to become due to the Contractor any cost incurred by the Authority resulting directly or indirectly from a loss caused in whole or in part by the Contractor's handling, storage or use of Authority-furnished materials.

The Contractor shall protect electrical raceway, cables of any sort, lighting fixtures and associated support systems against damage from movement of equipment and material, welding, flame cutting, and other construction damage. Raceways and supporting structures for raceway and lighting fixtures shall not be used as access scaffolding at any time. Whenever welding or flame cutting operations occur above or near raceways, cables or lighting fixtures not shielded from such operations by concrete floor or other protective covers, the Contractor shall protect the raceways, cables, and lighting fixtures from damage by means of fireproof boards or blankets. Damaged materials shall be repaired or replaced, by and at the Contractor's expense, subject to the COTR's direction and acceptance.

Surfaces of most equipment, such as panels, switchgear, transformers, constant current regulators and circuit breakers, are finished at the factory. Great care shall be exercised to prevent damage to this original finish during installation of the equipment and during construction work.

If the factory finish is damaged during the course of construction, the entire surface of the damaged component shall be refinished or replaced by and at the expense of the Contractor.

Page 197: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

GENERAL PROVISIONS AND REQUIREMENTS FOR ELECTRICAL WORK L-100 - 15

The refinished surface shall be equivalent in every respect to the original surface, including color, texture and smoothness. Refinishing paint, if furnished with the equipment, may be used; otherwise, the paint shall be obtained from the equipment manufacturer.

All cut edges of galvanized materials and marred or scratched galvanized surfaces shall be repaired using LPS-1G cold galvanizing compound or approved equivalent.

All threaded conduit joints shall use T&B Kopr-shield or Aluma-Shield or approved equivalent for galvanized and aluminum conduits respectively, as joint compound.

PART 6 - GENERAL CONSTRUCTION REQUIREMENTS

6.1 ADDITIONAL REQUIREMENTS. Provide the bracing, shoring, rails, guards, and covers necessary to prevent damage or injury. Do not leave energized electrical items unnecessarily exposed or unprotected. Protect personnel from exposure to contact with electricity. Deliver equipment and materials to the job site in their original, unopened, labeled containers. Store ferrous materials so as to prevent rusting. Store finished materials and equipment so as to prevent staining and discoloring.

All materials stored prior to installation, shall be stored in a bonded and secured facility.

All sheeting, shoring, dewatering and cleaning necessary to keep trenches and their grades in proper condition for the work to be carried on, including the removal of water by mechanical means, shall be the Contractor's responsibility.

PART 7 – METHOD OF MEASUREMENT

7.1 The items described in this section are incidental to other sections and shall not be measured for payment.

PART 8 - BASIS OF PAYMENT

8.1 No direct payment shall be made for the work described in this specification. The work described in this specification is incidental to other items and shall be paid for in the respective bid item of which it is a component part.

END OF ITEM L-100

Page 198: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final
Page 199: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

GENERAL ELECTRICAL SAFETY REQUIREMENTS L-104 - 1 AND TEMPORARY AIRFIELD LIGHTING

ITEM L-104 GENERAL ELECTRICAL SAFETY REQUIREMENTS AND TEMPORARY AIRFIELD LIGHTING

PART 1 - GENERAL

1.1 PURPOSE. The purpose of this item is to establish the proper safety guidelines necessary to protect aircraft, passengers, crews, the general public, all workers and vehicles involved in their daily tasks. The Contractor is solely responsible for all issues related to the safety program and guidelines and implementation of such programs and guidelines necessary to protect aircraft, passengers, crews, the general public, all workers and vehicles involved in their daily tasks.

1.2 FAA ADVISORY CIRCULARS. All applicable requirements of the below listed Advisory Circulars, latest edition, standards and related reading shall be complied with:

150/5200-18 Airport Safety Self-Inspection (Latest Edition)

150/5340-18 Standards for Airport Sign Systems (Latest Edition)

150/5340-26 Maintenance of Airport Visual Aid Facilities. (Latest Edition)

150/5340-30 Design and Installation Details for Airport Visual Aids (Latest Edition)

150/5370-2 Operational Safety on Airports during construction (Latest Edition)

Occupational Safety and Health Standards for the construction industry 29 CFR Part 1926/1910

ANSI C2 National Electrical Safety Code (Latest Edition)

NFPA 70 National Electrical Code (Latest Edition)

NFPA 70E Standard for Electrical Safety Requirements for Employee Work Places (Latest Edition)

The Contractor is responsible for obtaining and using the latest edition of the referenced FAA Advisory Circulars and related standards. This list is not all inclusive but is offered as a convenience to the Contractor.

1.3 GENERAL SAFETY PROVISIONS. The Contractor shall take safety and health measures in performing work under this contract. The Contractor shall meet with the COTR to develop a mutual understanding relative to administration of the safety requirements. The Contractor is subject to applicable federal, state and local laws, regulations, ordinances, codes and orders relating to safety and health in effect on the date of this contract. Attention is invited to the regulations issued by the Secretary of Labor pursuant to the Contract Work Hours and Safety Standards Act and the Safety and Health Regulations for construction. The Contractor shall comply with the Secretary's Regulations as applicable and shall comply with specific requirements stated.

Page 200: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

GENERAL ELECTRICAL SAFETY REQUIREMENTS L-104 - 2 AND TEMPORARY AIRFIELD LIGHTING

As a minimum, work place safety shall comply with NFPA 70E Standard for Electrical Safety Requirements for Employee Work Places, OSHA, federal, state and local requirements. Where a conflict in code requirements occurs the most stringent requirement shall govern.

During the performance of work under this contract, the Contractor shall comply with procedures prescribed for control and safety of persons visiting the project site.

The Contractor is responsible for his personnel and for familiarizing each of his subcontractors with safety requirements.

The Contractor shall advise the COTR of any special safety restrictions he has established so that the Authority personnel can be notified of these restrictions.

1.4 FIRE PREVENTION AND PROTECTION. All tools producing sparks or heat, open-flame heating devices, or operations utilizing such devices, etc., shall be in accordance with the local Fire Department and the Authority's Burn Permit procedures. Work shall not start until all requirements of the Burn Permit procedures are met.

Open-flame heating devices will not be permitted except by approval in writing. Such permission will not be granted unless the Contractor has taken reasonable precautions to make such devices safe. Burning trash, brush or wood on the project site will not be permitted. Approval for use of open fires and open-flame heating devices will in no way relieve the Contractor from the responsibility for any damage incurred because of fires.

Flammable liquids shall be stored and handled in accordance with the Flammable and Combustible Liquids Code, NFPA 30.

Open fires and salamanders will not be permitted in construction areas.

Smoking will not be permitted within the Air Operations Area (AOA) and in areas such as paint storage, fuel storage, and posted no smoking areas.

Welding, flame cutting, melting and other such operations in all operating areas, shall not be permitted until approved at the beginning of each workday by the COTR. The COTR may approve longer periods of time for welding and burning in some operating areas if the detailed safety procedures are established beforehand. Operating open flame devices shall not be left unattended in any area.

The Contractor shall provide the necessary firefighting equipment and fire prevention methods and, before operations begin, clear all welding and cutting operations with the COTR.

A Contractor's employee shall be assigned as fire watch for every welding and burning operation. He shall be equipped with 2 full 15 pound carbon dioxide fire extinguishers and shall check all areas around and below the welding or burning operation for fires. He shall continue this check for at least 60 minutes after the completion of the welding or burning operation.

The Contractor shall discontinue all burning, welding, or cutting operations, one hour prior to the end of the normal work day. The Contractor shall provide a workman to remain at the site for one hour after discontinuing these operations. This workman shall make a thorough inspection of the area for possible sources of latent combustion. Any unsafe conditions shall be corrected.

Page 201: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

GENERAL ELECTRICAL SAFETY REQUIREMENTS L-104 - 3 AND TEMPORARY AIRFIELD LIGHTING

During operations involving possible fire hazard, the Contractor shall notify the COTR and not proceed until clearance is obtained in writing. The COTR may request a standby from the Aircraft Rescue and Firefighting (ARFF). However, this does not relieve the Contractor of his responsibility for welding and cutting safety.

1.5 TEMPORARY EXITS AND ENTRANCES. Such passageways shall provide adequate fire protection and safety of Authority personnel and representatives.

1.6 SWITCHING. Electrical switching required for clearance to work on equipment operating from electrical circuits will be performed only by Authority personnel authorized as safety operators for the specific equipment unless otherwise authorized in writing by the COTR.

1.7 REMOVAL OF EQUIPMENT. When permanently removing equipment, the electrical wiring, conduit and control boxes shall be removed to the source of feed, unless otherwise specified or indicated.

After equipment has been removed, the electrical wiring diagrams, schematics, etc., shall be marked to show the change.

Conduit not removed shall have a pull string installed.

1.8 OTHER SAFETY REQUIREMENTS. Temporary wiring shall comply with NEC. Indiscriminate use of extension cords, portable cable or junction boxes creating tripping hazards as well as overloaded circuits will not be permitted.

Unplug portable electrical hand tools when not in use. Inadvertent operation of equipment can take place if it is left plugged into an energized receptacle.

Before maintaining or repairing any electrical equipment, it shall be disconnected from the power source.

Do not use any equipment that has frayed cords or three-wire plugs that have had the grounding prongs removed. Faulty equipment and tools shall be repaired by qualified electrical personnel.

Do not use metal ladders when working on electrical equipment.

PART 2 - EXCAVATION

2.1 EXCAVATION OPERATIONS. Methods of excavation, means of earth support, and manner of backfill shall be conducted with consideration for the safety of persons and work, and prevention of damage to adjacent pavement, utilities, structures and other facilities, due to settlement, lateral movement, undermining and washout. Excavation shall be performed in a manner to prevent surface water and subsurface or ground water from flowing into excavations, and to prevent water from flooding conduit trench and adjacent or surrounding area.

The Contractor and all his subcontractors performing trench excavation on this contract shall comply with the State Trench Safety Act in which the project is occurring and the Occupational Safety and Health Administration's (OSHA) trench excavation safety standards, 29 C.F.R., subpart P, s.1926.650, including all subsequent revisions or updates to these standards as adopted by the Department of Labor and Employment Security (DLES). The Contractor shall consider all available geotechnical information in

Page 202: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

GENERAL ELECTRICAL SAFETY REQUIREMENTS L-104 - 4 AND TEMPORARY AIRFIELD LIGHTING

his design of the trench excavation safety system. Inspections required by OSHA trench excavation safety standards shall be provided by the Contractor.

PART 3 - PROTECTION OF WORK

3.1 PROTECTION OF WORK. Provide adequate stand-by mechanical equipment for emergency use.

Excavations shall have substantial barricades and be posted with warning signs for the safety of persons. Warning lights shall be provided during hours of darkness.

Barricades shall be erected immediately around manhole openings when covers are removed or opened. For personnel safety and to prevent possible interruption of major utility services encountered during excavation, the following procedures shall be followed:

A. Prior to performing any excavation work or any surface penetrations 6-inches or deeper (such as driving stakes more than 6-inches in the ground) on any ground surface, the Contractor shall obtain from the COTR, local utilities, etc., the current up-to-date subsurface utility drawing of the particular area to be worked on.

B. All Agencies/Utilities, etc. that may be affected by the excavating shall be contacted by the Contractor so that all lines, pipes, etc., can be marked/staked.

C. The Contractor shall stake out all subsurface utilities i.e., high voltage cables, communication cables, pipe lines, etc., indicated within the scope of the work contemplated. All subsurface utilities shall be located by hand digging; hand digging shall extend for 5-feet on both sides of the subsurface utility.

D. After hand exposure of cable or pipelines, the Contractor shall obtain agreement from the COTR, Agency/Utility on how much closer to cable or pipe the excavations can be permitted.

E. Detectable marker tape, with metalized foil core, printed with the words "CAUTION ELECTRIC LINE BELOW," "CAUTION WATER LINE BELOW," "CAUTION SEWER LINE BELOW," etc., as applicable, shall be installed 8-inches below grade over the underground utility. Tape shall be in accordance with Item L-108, Installation of Underground Cable for Airports.

F. The Contractor shall notify the COTR, 72 hours prior to the start of excavation work or surface penetration, to enable the COTR to review measures being taken to prevent hazard to employees and to prevent possible damage to subsurface utilities. Where emergency conditions preclude the 72 hours advance notification, the Contractor shall nevertheless inform the COTR of his intention to initiate work.

G. After all existing utilities have been located and marked or staked, the Contractor shall proceed with excavating work, or other surface penetration work. The Contractor however, shall temporarily halt any machine excavation work or other surface penetration when approaching within 5-feet of the staked out subsurface utility until the Contractor has hand excavated down to expose the utility to exactly fix its location.

Page 203: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

GENERAL ELECTRICAL SAFETY REQUIREMENTS L-104 - 5 AND TEMPORARY AIRFIELD LIGHTING

H. No digging, dirt moving or other heavy equipment shall enter physically any approved construction area before all utilities have been located and properly staked out. It is the Contractor's responsibility to locate all utilities before digging, sawing, coring, boring, etc.. Any damage caused by digging, sawing, boring, coring, etc., is the Contractor's responsibility for repair. Any damage must be reported immediately to the COTR. No repair shall be attempted without approval.

I. All high voltage cables shall be disconnected before excavation is attempted.

J. To protect subsurface utilities, provide as a minimum, a 1-inch thick steel plate cover over electrical duct, cables and other subsurface utilities when heavy equipment is being used in the area.

K. The requirements listed above shall be considered incidental to the item for which the excavation is required.

PART 4 - SAFETY TAGGING AND LOCKOUT

4.1 SAFETY WITH ELECTRICAL CIRCUITS AND EQUIPMENT. No one may work on an energized circuit without written permission from the Contractor's project manager. The Contractor's project manager shall review the circumstances and the necessary safety precautions with the COTR prior to giving permission for the "hot" work. The Contractor assumes all liability in connection with any work on energized circuits.

No one may disconnect or cause to be disconnected any electrical circuit before permission is requested from and granted by Airport Operations or their authorized representative through the COTR.

Identification markings on building light and power distribution circuits shall not be relied on for established safe work conditions. Always verify the proper safe "deenergized" conditions with properly operating test equipment.

Before any circuit supplying radar, ILS, weather, VORTAC, airport beacon, runway/taxiway lighting equipment or any other equipment is disconnected, permission must first be granted by Airport Operations or their authorized representative, and, if applicable, FAA Airways Facilities Office.

Work shall not commence on any circuit until:

A. The circuit is correctly identified in the presence of the electrical contractor's superintendent or foreman, the COTR, Airport Operations, or their authorized representative.

B. After identity of the circuit is established, and the circuit disconnected, the time and date shall be recorded by the COTR.

C. The switch shall be locked in the open position or opened in a manner, which will prevent accidental restoration.

Page 204: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

GENERAL ELECTRICAL SAFETY REQUIREMENTS L-104 - 6 AND TEMPORARY AIRFIELD LIGHTING

D. The circuit shall be tagged with an approved warning tag by the electrical contractor's superintendent. The tag shall state, the company's name, the electrician's name responsible for the disconnection, date and time and the project name and project number.

Restoration shall be accomplished and tags removed only by the electrical contractor's superintendent in the presence of Airport Operations, or their authorized representative.

The COTR shall record time, date and operational status of circuit after restoration.

No circuit shall be disconnected or unplugged before color code identification by taping.

No circuit shall be disconnected at power source before proper safety precautions are taken to prevent accidental restoration.

When possible, circuits shall be restored by the same person who disconnected the circuit. When not possible, Airport Operations or their authorized representative shall perform restoration.

E. As a minimum, the Lock/Tag/Try procedure shall comply with NFPA 70E and the Authority's requirements.

PART 5 - METHOD OF MEASUREMENT

5.1 The items described in this section are incidental to other sections and shall not be measured for payment.

PART 6 - BASIS OF PAYMENT

6.1 No direct payment shall be made for the work described in this specification. The work described in this specification is incidental to other items and shall be paid for in the respective bid item of which it is a component part.

END OF ITEM L-104

Page 205: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

ALTERATIONS, REMOVAL AND DEMOLITION L-105 - 1

ITEM L-105 ALTERATIONS, REMOVAL AND DEMOLITION

PART 1 - GENERAL

1.1 DEFINITIONS. Alterations shall mean any change or rearrangement in the component parts, including structural, mechanical, electrical systems, or internal or external arrangements of an existing structure.

Removal shall mean the dismantling of existing materials, components, equipment, and utilities. Removed items shall be handled, prepared for storage, transported to storage areas as specified.

Demolition shall mean the dismantling and disposal of existing materials, components, equipment, and utilities which cannot or will not be reused or which will have no salvage value, or which cannot be reused due to unrepairable damage caused by age, non-demolition related reasons, etc. All demolished items not designated to be turned over to the Authority shall be disposed of in a safe manner and at a location acceptable to the COTR.

All items to be turned over to the Authority shall be properly enclosed or boxed to protect the items from damage and transported by the Contractor to a location on the Authority’s property, designated by the COTR.

The installation and/or removal of lighting equipment may be critical to airport operations; therefore, the Contractor shall follow the work schedule established in the plans and specifications or as directed by the COTR. The system shall be installed in accordance with the National Electrical Code and/or local code requirements.

The Contractor shall provide temporary wiring as required to reconnect existing circuits to provide guidance for aircraft to pass through the construction areas on those taxiways/runways which must remain open. The Contractor shall check all temporary circuits before dark each day to assure that they are operational. In the event of failure, the Contractor shall immediately take steps to restore operation. The cost of temporary and reconnected lighting shall be absorbed in the various work items.

1.2 CONDITION OF EXISTING FACILITIES. The Contractor shall verify the areas, conditions, and features necessary to tie into existing construction. This verification shall be done prior to submittal of shop drawings, fabrication or erection, construction or installation. The Contractor shall be responsible for the accurate tie-in of the new work to existing facilities.

Special attention is called to the fact that there may be piping, fixtures or other items in the existing systems which must be removed or relocated in order to perform the alteration work. All conduit, wiring, boxes, etc., that do not comply with these specifications shall be removed or corrected to comply with these specifications. All unused conduit not removed shall be identified and a pull line shall be installed. The work shall include all removal and relocation required for completion of the alterations and the new construction.

Whenever the scope of work requires connection to an existing circuit, the circuit’s insulation resistance shall be tested, in the presence of the COTR. The Contractor shall record the results on the forms included in these specifications. When the circuit is returned to its final condition, the circuit’s insulation resistance shall be checked again in the presence of the COTR. The Contractor

Page 206: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

ALTERATIONS, REMOVAL AND DEMOLITION L-105 - 2

shall record the results on the forms included in these specifications. The second reading shall be equal to or greater than the first reading or the Contractor shall make the necessary repairs to the circuit to bring the second reading above the first reading. All repair costs including a complete replacement of the cable, if necessary, shall be borne by the Contractor. All test results shall be submitted in Operation and Maintenance Manuals.

1.3 OCCUPANCY AND USE OF EXISTING FACILITIES. The Authority will occupy and use the facilities within the areas of work during the entire construction period. The Contractor shall be required to plan and coordinate his activities in order to provide all necessary controls for the abatement of dust, noise, and inconvenience to the Authority personnel during all phases of the work.

1.4 SAFETY REQUIREMENTS. The Contractor shall conduct alterations and removal operations in a manner that will ensure the safety of persons in accordance with the requirements of CFR 29 PART 1926 and 1910.

1.5 CLASSIFICATION OF REMOVED/DEMOLISHED ITEMS. Existing materials and equipment indicated to be removed will be classified as "salvageable" and shall remain the property of the Authority or will be classified as "debris" and shall be disposed of legally off the airport.

Reusable Salvaged Items.

Salvaged materials and equipment shall be reused in the work as described on the contract drawings, unless noted otherwise.

Items classified as debris shall be legally disposed of off the airport property. The cost of such disposal shall be included in the cost of other items of work.

Retained Salvaged Items:

Salvaged materials and equipment to be retained by the Authority but not reused in the work shall be turned over to the Authority at a site at the facility to be determined by the COTR. Retained salvaged items shall be stored on Authority property where indicated by the Authority.

1.6 TEMPORARY PROTECTION. The Contractor shall provide and maintain the following requirements.

Protection of persons and property shall be provided throughout the progress of the work in accordance with these specifications.

Provide temporary enclosures and partitions prior to starting alterations and removal of work. Such items shall protect existing materials, equipment, and other remaining building or system components from damage by weather and construction operations.

Provide temporary enclosures to isolate space utilized by equipment during construction, from dirt, dust, noise, and unauthorized entry.

Provide temporary exits, entrances, and protected passages where work prevents the use of existing facilities.

Page 207: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

ALTERATIONS, REMOVAL AND DEMOLITION L-105 - 3

Provide weathertight temporary enclosures over and around openings to be made in existing exterior construction prior to the start of work. The Contractor shall maintain such temporary enclosures until new construction will protect the interior of existing facilities from the elements.

Provide temporary exterior wall construction which will be designed and fabricated to resist an applied horizontal wind pressure of not less than 130 mph.

Provide temporary exterior roof construction which will be capable of supporting an applied vertical live load of not less than 200 psf, uniformly distributed over the entire roof area.

Design and fabricate temporary enclosures to maintain temperatures inside the existing facilities within a range of plus-or-minus 5 degrees F of normal operating conditions.

Provide temporary jet blast structures which will withstand the jet blast with a safety factor of 2.

PART 2 - EXECUTION

2.1 DISCONNECTING UTILITIES. Prior to the start of work, the necessary utilities serving each area of alteration or removal will be shut off by the Authority and shall be disconnected and sealed by the Contractor, as required. Lockout/Tag/Try procedures shall be utilized in accordance with Item L-104, General Electrical Safety Requirements and Temporary Airfield Lighting.

2.2 TEMPORARY UTILITY SERVICES. The Contractor shall install temporary utility services in satisfactory operating condition before disconnecting existing utilities. Such temporary services shall be maintained during the period of construction and removed only after new permanent services have been tested and are in operation.

2.3 REMOVAL WORK. The Contractor shall not disturb the existing construction beyond that indicated or necessary for installation of new work. Temporary shoring and bracing for support of building components to prevent settlement or other movement shall be as indicated and as required to protect the work.

The Contractor shall provide protective measures to control accumulation and migration of dust and dirt in all areas of work, particularly those adjacent to occupied areas. The Contractor shall remove dust, dirt, and debris from the areas of work daily.

2.4 SALVAGEABLE MATERIALS AND EQUIPMENT. The Contractor shall remove all salvageable materials and equipment in a manner that will cause the least possible damage thereto. Removed items which are to be retained by the Authority shall be carefully handled, stored, and protected.

The Contractor shall provide identification tags on all items boxed or placed in containers, indicating the type, size, and quantity of materials.

2.5 BUILDINGS AND STRUCTURES. The Contractor shall perform removal operations in existing buildings as indicated and as otherwise required to complete the work.

Existing concrete shall be demolished, removed, and disposed of. Square, straight edges shall be provided where existing concrete adjoins new work and at other locations where indicated.

Page 208: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

ALTERATIONS, REMOVAL AND DEMOLITION L-105 - 4

Existing steel reinforcement shall be protected where indicated; otherwise, it shall be cut off flush with face of concrete.

The Contractor shall dismantle steel components at field connections and in a manner that will prevent bending or damage.

The use of flame-cutting torches will be permitted only when other methods of dismantling are not practical, and when approved in writing by the COTR.

2.6 ELECTRICAL EQUIPMENT AND FIXTURES. Wiring systems and components shall be salvaged. Loose items shall be boxed and tagged for identification.

All unused conduit not removed shall have a pull string installed and shall be noted on the record drawings.

Primary, secondary, control, communication, and signal circuits shall be disconnected at the point of attachment to their distribution system.

The Contractor shall remove and salvage electrical fixtures. Incandescent lamps, mercury-vapor lamps, and fluorescent lamps shall be salvaged, boxed and tagged for identification, and protected from breakage.

The Contractor shall remove and salvage switches, receptacles, fixtures, transformers, constant current regulators, meters, instruments, plates, circuit breakers, panelboards, outlet boxes, and similar items. These items shall be boxed, and tagged for identification according to type and size.

The Contractor shall remove and dispose of conductors and conduits not used in the finished work and shown to be demolished on the plans.

PART 3 - DEMOLITION

3.1 DEMOLITION OPERATIONS. Demolition operations shall be conducted to ensure the safe passage of persons to and from facilities occupied and used by the Authority and to prevent damage by falling debris or other cause to adjacent buildings, structures, and other facilities.

The sequence of operations shall be such that maximum protection from inclement weather will be provided for materials and equipment located in partially dismantled structures.

3.2 MAINTAINING TRAFFIC. Demolition operations and removal of debris to disposal areas shall be conducted to ensure minimum interference with runways, taxiways, aprons, roads, streets, walks, and other facilities occupied and used by the Authority.

Streets, walks, runways, taxiways and other facilities occupied and used by the Authority shall not be closed or obstructed without written permission from the COTR.

3.3 REFERENCE STANDARDS REQUIREMENTS. Demolition operations shall be conducted to ensure the safety of persons in accordance with ANSI A 10.6 Safety Requirements for Demolition.

Page 209: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

ALTERATIONS, REMOVAL AND DEMOLITION L-105 - 5

Demolition shall be conducted in accordance with OSHA, State and local requirements.

PART 4 - DISPOSAL OF DEMOLISHED MATERIALS

4.1 GENERAL. The Contractor shall dispose of debris, rubbish, scrap, and other non-salvageable materials resulting from demolition operations. Demolished materials shall not be stored or disposed of on Airport property.

4.2 REMOVAL FROM AUTHORITY PROPERTY. Materials classified as debris shall be transported from Airport property and legally disposed of at no additional cost to the Authority. Permits and fees for disposal shall be paid by the Contractor.

PART 5 - ALTERATION WORK

5.1 GENERAL. Cutting, patching, repairing, and other alteration work shall be done by tradesman skilled in the particular trade or work required.

Where required to patch or extend existing construction, or both, such alteration work shall match existing exposed surface materials in finish, color, texture, and pattern.

Salvaged items for reuse shall be as approved by the COTR.

PART 6 - METHOD OF MEASUREMENT

6.1 The items described in this section are incidental to other sections and shall not be measured for payment.

PART 7 - BASIS OF PAYMENT

No direct payment shall be made for the work described in this specification. The work described in this specification is incidental to other items and shall be paid for in the respective bid item of which it is a component part.

END OF ITEM L-105

Page 210: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final
Page 211: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

POWER CABLE FOR AIRPORTS L-108 - 1

ITEM L-108 POWER CABLE FOR AIRPORTS PART 1 - GENERAL 1.1 DESCRIPTION. This item shall consist of furnishing and installing power cables within conduit

or ductbanks in accordance with these specifications at the locations shown on the plans. It includes excavation and backfill of trench for direct-buried cables only. Also included are the installation of counterpoise wires, ground wires, ground rods and connections, cable splicing, cable marking, cable testing, and all incidentals necessary to place the cable in operating condition as a completed unit to the satisfaction of the COTR. This item shall not include the installation of ductbanks or conduit, trenching and backfilling for ductbanks or conduit, or furnishing or installation of any cable for FAA facilities. Requirements and payment for trenching and backfilling for the installation of underground conduit and ductbanks are covered under Item L-110 “Airport Underground Electrical Ductbanks and Conduits.”

PART 2 - EQUIPMENT AND MATERIALS 2.1 GENERAL.

A. Airport lighting equipment and materials covered by Federal Aviation Administration (FAA) specifications shall be approved under the Airport Lighting Equipment Certification Program described in Advisory Circular (AC) 150/5345-53, current version.

B. All other equipment and materials covered by other referenced specifications shall be

subject to acceptance through manufacturer's certification of compliance with the applicable specification, when requested by the COTR.

C. Manufacturer's certifications shall not relieve the Contractor of the Contractor’s

responsibility to provide materials in accordance with these specifications and acceptable to the COTR. Materials supplied and/or installed that do not materially comply with these specifications shall be removed, when directed by the COTR and replaced with materials, which do comply with these specifications, at the sole cost of the Contractor.

D. All materials and equipment used to construct this item shall be submitted to the COTR

for approval prior to ordering the equipment. Submittals consisting of marked catalog sheets or shop drawings shall be provided. Submittal data shall be presented in a clear, precise and thorough manner. Original catalog sheets are preferred. Photocopies are acceptable provided they are as good a quality as the original. Clearly and boldly mark each copy to identify pertinent products or models applicable to this project. Indicate all optional equipment and delete non-pertinent data. Submittals for components of electrical equipment and systems shall identify the equipment for which they apply on each submittal sheet. Markings shall be boldly and clearly made with arrows or circles (highlighting is not acceptable). Contractor is solely responsible for delays in project accruing directly or indirectly from late submissions or resubmissions of submittals.

E. The data submitted shall be sufficient, in the opinion of the COTR, to determine

compliance with the plans and specifications. The COTR reserves the right to reject any

Page 212: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

POWER CABLE FOR AIRPORTS L-108 - 2

and all equipment, materials or procedures, which, in the COTR’s opinion, does not meet the system design and the standards and codes, specified herein.

F. All equipment and materials furnished and installed under this section shall be guaranteed

against defects in materials and workmanship for a period of at least twelve (12) months from final acceptance by the Authority. The defective materials and/or equipment shall be repaired or replaced, at the Authority's discretion, with no additional cost to the Authority. The Contractor shall be responsible to maintain an insulation resistance of 50 megohms minimum, (1000V megger) with isolation transformers connected in new circuits and new segments of existing circuits through the end of the contract warranty period.

2.2 CABLE. Underground cable for airfield lighting facilities (runway and taxiway lights and signs)

shall conform to the requirements of AC 150/5345-7, Specification for L-824 Underground Electrical Cable for Airport Lighting Circuits. Conductor sizes noted above shall not apply to leads furnished by manufacturers on airfield lighting transformers and fixtures.

Wire for electrical circuits up to 600 volts shall comply with Underwriters Standard 44 and shall be XHHW-2.

Cable type, size, number of conductors, strand and service voltage shall be as specified on the plans.

2.3 BARE COPPER WIRE (COUNTERPOISE OR GROUND) AND GROUND RODS. Wire for

counterpoise or ground installations for airfield lighting systems shall be No. 6 AWG solid for counterpoise and or No. 6 AWG stranded for ground wire conforming to ASTM B 3 and ASTM B 8, and shall be tinned copper conforming to the requirements of ASTM D 33.

Ground rods shall copper-clad steel. The ground rods shall be of the length and diameter

specified on the plans, but in no case shall they be less than 10-feet long nor less than 5/8 inch in diameter.

2.4 CABLE CONNECTIONS. In-line connections of underground primary cables shall be of the

type called for on the plans, and shall be one of the types listed below. No separate payment will be made for cable connections.

A. The Taped or Heat-Shrinked Splice. Taped splices employing field-applied rubber, or

synthetic rubber tape covered with plastic tape is acceptable. The rubber tape should meet the requirements of ASTM D 4388 and the plastic tape should comply with Mil Spec. MIL-I-24391or Fed. Spec. A-A-55809. Heat shrinkable tubing shall be heavy-wall, self-sealing tubing rated for the voltage of the wire being spliced and suitable for direct-buried installations. The tubing shall be factory coated with a thermoplastic adhesive-sealant that will adhere to the insulation of the wire being spliced forming a moisture- and dirt-proof seal. Additionally, heat shrinkable tubing for multi-conductor cables, shielded cables, and armored cables shall be factory kits designed for the application. Heat shrinkable tubing and tubing kits shall be manufactured by Tyco Electronics/ Raychem Corporation, Energy Division, or approved equivalent.

B. In all the above cases, connections of cable conductors shall be made using crimp

connectors utilizing a crimping tool designed to make a complete crimp before the tool

Page 213: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

POWER CABLE FOR AIRPORTS L-108 - 3

can be removed. All L-823/L-824 splices and terminations shall be made in accordance with the manufacturer’s recommendations and listings.

C. All connections of counterpoise, grounding conductors and ground rods shall be made by the exothermic process or approved equivalent, except the base can ground clamp connector shall be used for attachment to the base can. All exothermic connections shall be made in accordance with the manufacturer’s recommendations and listings.

2.5 SPLICER QUALIFICATIONS. Every airfield lighting cable splicer shall be qualified in making

cable splices and terminations on cables rated above 5,000 volts AC. The Contractor shall submit to the COTR proof of the qualifications of each proposed cable splicer for the cable type and voltage level to be worked on. Cable splicing/terminating personnel shall have a minimum of three (3) years continuous experience in terminating/splicing medium voltage cable.

2.6 CONCRETE. Concrete for cable markers shall conform to Specification Item P-610, ``Structural

Portland Cement Concrete.'' 2.7 CABLE IDENTIFICATION TAGS AND MARKING.

A. Cable identification tags shall be made from a non-corrosive material with the circuit

identification stamped or etched onto the tag. The tags shall be of the type as detailed on the plans.

B. Airfield lighting series circuit cable, in addition to cable tags, shall be marked at accessible points with colored tape in accordance with the marking scheme used by the airport.

2.8 TAPE. Electrical tapes shall be Scotch Electrical Tapes – number Scotch 88 (1-1/2” wide) and

Scotch 130C linerless rubber splicing tape (2” wide), as manufactured by the Minnesota Mining and Manufacturing Company, or approved equivalent.

2.9 ELECTRICAL COATING. Scotchkote shall be as manufactured by Minnesota Mining and

Manufacturing Company, or approved equivalent. 2.10 EXISTING CIRCUITS. Whenever the scope of work requires, connection to an existing circuit,

the circuit’s insulation resistance shall be tested, in the presence of the COTR. The test shall be performed in accordance with this item and prior to any activity affecting the respective circuit. The Contractor shall record the results on forms acceptable to the COTR. When the work affecting the circuit is complete, the circuit’s insulation resistance shall be checked again, in the presence of the COTR. The Contractor shall record the results on forms acceptable to the COTR. The second reading shall be equal to or greater than the first reading or the Contractor shall make the necessary repairs to the circuit to bring the second reading above the first reading. All repair costs including a complete replacement of the L-823 connectors, L-830 transformers and L-824 cable, if necessary, shall be borne by the Contractor. All test results shall be submitted in the Operation and Maintenance (O&M) Manual.

2.11 LIGHTNING PROTECTION EQUIPMENT. Lightning protection equipment including air

terminals, terminal bases, connections, clamps, wire, down conductors, holders, fittings, etc. shall be UL listed for lightning protection.

Page 214: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

POWER CABLE FOR AIRPORTS L-108 - 4

PART 3 - CONSTRUCTION METHODS 3.1 GENERAL. The Contractor shall install the specified cable at the approximate locations

indicated on the plans. Unless otherwise shown on the plans, all cable required to cross under pavements expected to carry aircraft loads shall be installed in concrete encased ductbanks. Wherever possible, cable shall be run without splices, from connection to connection.

Cable connections between lights will be permitted only at the light locations for connecting the underground cable to the primary leads of the individual isolation transformers. The Contractor shall be responsible for providing cable in continuous lengths for home runs or other long cable runs without connections, unless otherwise authorized in writing by the COTR or shown on the plans.

In addition to connectors being installed at individual isolation transformers, L-823 cable connectors for maintenance and test points shall be installed at locations shown on the plans. Cable circuit identification markers shall be installed on both sides of the L-823 connectors installed or at least once in each access point where L-823 connectors are not installed, and shall be marked with colored tape in accordance with the airport scheme and as indicated.

Provide not less than 3 feet of cable slack on each side of all connections, isolation transformers, light units, and at points where cable is connected to field equipment. Where provisions must be made for testing or for future above grade connections, provide enough slack to allow the cable to be extended at least one foot vertically above the top of the access structure. This requirement also applies where primary cable passes through empty base cans, junction and access structures to allow for future connections, or as designated by the COTR.

3.2 INSTALLATION IN DUCTBANKS OR CONDUITS. This item includes the installation of the

cable in ductbanks or conduit as described below. The maximum number and voltage ratings of cables installed in each single duct or conduit, and the current-carrying capacity of each cable shall be in accordance with the latest National Electric Code, or the code of the local agency or authority having jurisdiction.

The Contractor shall make no connections or splices of any kind in cables installed in conduits or ductbanks. Unless otherwise designated in the plans, where ducts are in tiers, use the lowest ducts to receive the cable first, with spare ducts left in the upper levels. Check duct routes prior to construction to obtain assurance that the shortest routes are selected and interferences are avoided. Ductbanks or conduits shall be installed as a separate item in accordance with Item L-110, ``Airport Underground Electrical Ductbanks and Conduit.'' The Contractor shall run a mandrel through ductbanks or conduit prior to installation of cable to insure that the ductbank or conduit is open, continuous and clear of debris. Mandrel size shall be compatible with conduit size. The Contractor shall swab out all conduits/ducts and clean base can, manhole, etc. interiors IMMEDIATELY prior to pulling cable. Once cleaned and swabbed the base cans and all accessible points of entry to the duct/conduit system shall be kept closed except when installing cables. Cleaning of ducts, base cans, manholes, etc. is incidental to the pay item of the item being cleaned. All raceway systems left open, after initial cleaning, for any reason shall be re-cleaned at the Contractor’s expense. All accessible points shall be kept closed when not installing cable.

Page 215: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

POWER CABLE FOR AIRPORTS L-108 - 5

The Contractor shall verify existing ducts proposed for use in this project as clear and open. The Contractor shall notify the COTR of any blockage in the existing ducts. The cable shall be installed in a manner to prevent harmful stretching of the conductor, injury to the insulation, or damage to the outer protective covering. The ends of all cables shall be sealed with moisture-seal tape providing moisture-tight mechanical protection with minimum bulk, or alternately, heat shrinkable tubing before pulling into the conduit and it shall be left sealed until connections are made. Where more than one cable is to be installed in a conduit, all cable shall be pulled in the conduit at the same time. The pulling of a cable through ductbanks or conduits may be accomplished by handwinch or power winch with the use of cable grips or pulling eyes. Maximum pulling tensions shall be governed by cable manufacturer’s recommendations. A non-hardening lubricant recommended for the type of cable being installed shall be used where pulling lubricant is required. Contractor shall submit pulling tension values to the COTR prior to any cable installation. If required by the COTR, pulling tension values for cable pulls shall be monitored by a dynamometer in the presence of the COTR. Cable pull tensions shall be recorded by the Contractor and reviewed by the COTR. Cables exceeding the maximum allowable pulling tension values shall be removed and replaced by the Contractor at the Contractor’s expense. The manufacturer's minimum bend radius or the NEC requirements, whichever is more restrictive, shall apply. Cable installation, handling and storage shall be per manufacturer's recommendations. During cold weather, particular attention shall be paid to the manufacturer's minimum installation temperature. Cable shall not be installed when the temperature is at or below the manufacturer's minimum installation temperature. At the Contractor’s option, the Contractor may submit a plan, for review by the COTR, for heated storage of the cable and maintenance of an acceptable cable temperature during installation when temperatures are below the manufacturer’s minimum cable installation temperature. Cable shall not be dragged across base can or manhole edges, pavement or earth. When cable must be coiled, lay cable out on a canvas tarp or utilize other appropriate means to prevent abrasion to the cable jacket.

3.4 3.4 SPLICING. Connections of the type shown on the plans shall be made by experienced personnel

regularly engaged in this type of work and shall be made as follows:

A. Cast Splices. These shall be made by using crimp connectors for jointing conductors. Molds shall be assembled, and the compound shall be mixed and poured in accordance with manufacturer's instructions and to the satisfaction of the COTR.

B. Taped or Heat-Shrinked Splices. A taped splice shall be made in the following manner:

Bring the cables to their final position and cut so that the conductors will butt. Remove insulation and jacket allowing for bare conductor of proper length to fit compression sleeve connector with 1/4 inch of bare conductor on each side of the connector. Prior to splicing, the two ends of the cable insulation shall be penciled using a tool designed specifically for this purpose and for cable size and type. Do not use emery paper on splicing operation since it contains metallic particles. The copper conductors shall be thoroughly cleaned. Join the conductors by inserting them equidistant into the compression connection sleeve. Crimp conductors firmly in place with crimping tool that

Page 216: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

POWER CABLE FOR AIRPORTS L-108 - 6

requires a complete crimp before tool can be removed. Test the crimped connection by pulling on the cable. Scrape the insulation to assure that the entire surface over which the tape will be applied (plus 3 inches on each end) is clean. After scraping wipe the entire area with a clean lint-free cloth. Do not use solvents. Apply high-voltage rubber tape one-half lapped over bare conductor. This tape should be tensioned as recommended by the manufacturer. Voids in the connector area may be eliminated by highly elongating the tape, stretching it just short of its breaking point. Throughout the rest of the splice less tension should be used. Always attempt to exactly half-lap to produce a uniform buildup. Continue buildup to 1-1/2 times cable diameter over the body of the splice with ends tapered a distance of approximately 1 inch over the original jacket. Cover rubber tape with two layers of vinyl pressure-sensitive tape one-half lapped. Do not use glyptol or lacquer over vinyl tape as they react as solvents to the tape. No further cable covering or splice boxes are required. Heat shrinkable tubing shall be installed following manufacturer’s instructions. Direct flame heating shall not be permitted unless recommended by the manufacturer. Cable surfaces within the limits of the heat-shrink application shall be clean and free of contaminates prior to application.

3.5 BARE COUNTERPOISE WIRE INSTALLATION FOR LIGHTNING PROTECTION AND

GROUNDING. If shown on the plans or included in the job specifications, bare counterpoise copper wire shall be installed for lightning protection of the underground cables. Counterpoise wire shall be installed in the same trench for the entire length of buried cable, conduits and ductbanks that are installed to contain airfield cables. Where the cable or duct/conduit trench runs parallel to the edge of pavement, the counterpoise shall be installed in a separate trench located half the distance between the pavement edge and the cable or duct/conduit trench. In trenches not parallel to pavement edges, counterpoise wire shall be installed continuously a minimum of 4 inches above the cable, conduit or ductbank, or as shown on the plans. Additionally, counterpoise wire shall be installed at least 8 inches below the top of subgrade in paved areas or 10 inches below finished grade in un-paved areas. This dimension may be less than 4 inches where conduit is to be embedded in existing pavement. Counterpoise wire shall not be installed in conduit.

The counterpoise wire shall be routed around to each light fixture base, mounting stake, or junction/access structures. The counterpoise wire shall also be exothermically welded to ground rods installed as shown on the plans but not more than 500 feet apart around the entire circuit. The counterpoise system shall be continuous and terminate at the transformer vault or at the power source. It shall be securely attached to the vault or equipment external ground ring or other made electrode grounding system. The connections shall be made as shown on the plans and in the specifications. If shown on the plans or in the specifications, a separate equipment (safety) ground system shall be provided in addition to the counterpoise wire using one of the following methods:

(1) A ground rod installed at and securely attached to each light fixture base,

mounting stake if painted, and to all metal surfaces at junction/access structures.

Page 217: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

POWER CABLE FOR AIRPORTS L-108 - 7

(2) Install an insulated equipment ground conductor internal to the conduit system and securely attached it to each light fixture base and to all metal surfaces at junction/access structures. This equipment ground conductor shall also be exothermically welded to ground rods installed not more than 500 feet apart around the circuit.

3.7 EXOTHERMIC BONDING. Bonding of counterpoise wire shall be by the exothermic welding

process. Only personnel experienced in and regularly engaged in this type of work shall make these connections.

Contractor shall demonstrate to the satisfaction of the COTR, the welding kits, materials and

procedures to be used for welded connections prior to any installations in the field. The installations shall comply with the manufacturer's recommendations and the following: All slag shall be removed from welds.

For welds at light fixture base cans, all galvanized coated surface areas and "melt" areas, both inside and outside of base cans, damaged by exothermic bond process shall be restored by coating with a liquid cold-galvanizing compound conforming to U.S. Navy galvanized repair coating Mil. Spec. MIL-P-21035. Surfaces to be coated shall be prepared and compound applied in accordance with manufacturer's recommendations. All buried copper and weld material at weld connections shall be thoroughly coated 6 mil of 3M “Scotchkote,” or approved equivalent, or coated with coal tar bitumastic material to prevent surface exposure to corrosive soil or moisture.

3.8 TESTING. The Contractor shall furnish all necessary equipment and appliances for testing the

airport electrical systems and underground cable circuits before and after installation. The Contractor shall perform all tests in the presence of the COTR. The Contractor shall demonstrate the electrical characteristics to the satisfaction of the COTR. All costs for testing are incidental to the respective item being tested. For phased projects, the tests must be completed by phase and results meeting the specifications below must be maintained by the Contractor throughout the entire project as well as during the ensuing warranty period.

Earth resistance testing methods shall be submitted to the COTR for approval. Earth resistance

testing results shall be recorded on an approved form and testing shall be performed in the presence of the COTR. All such testing shall be at the sole expense of the Contractor.

Should the counterpoise or ground grid conductors be damaged or suspected of being damaged by

construction activities the Contractor shall test the conductors for continuity with a low resistance ohmmeter. The conductors shall be isolated such that no parallel path exists and tested for continuity. The COTR shall approve of the test method selected. All such testing shall be at the sole expense of the Contractor.

After installation, the Contractor shall test and demonstrate to the satisfaction of the COTR the

following:

A. That all affected lighting power and control circuits (existing and new) are continuous and free from short circuits.

Page 218: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

POWER CABLE FOR AIRPORTS L-108 - 8

B. That all affected circuits (existing and new) are free from unspecified grounds. C. That the insulation resistance to ground of all new non-grounded series circuits or cable

segments is not less than 50 megohms. D. That the insulation resistance to ground of all non-grounded conductors of new multiple

circuits or circuit segments is not less than 50 megohms. E. That all affected circuits (existing and new) are properly connected in accordance with

applicable wiring diagrams. F. That all affected circuits (existing and new) are operable. Tests shall be conducted that

include operating each control not less than 10 times and the continuous operation of each lighting and power circuit for not less than 1/2 hour.

G. That the impedance to ground of each ground rod does not exceed 25 ohms prior to

establishing connections to other ground electrodes. The fall-of-potential ground impedance test shall be utilized, as described by ANSI/IEEE Standard 81, to verify this requirement.

Two copies of tabulated results of all cable tests performed shall be supplied by the Contractor to the COTR. Where connecting new cable to existing cable, ground resistance tests shall be performed on the new cable prior to connection to the existing circuit. There are no approved "repair" procedures for items that have failed testing other than complete replacement.

PART 4 - METHOD OF MEASUREMENT 4.1 The cost of all excavation, backfill, dewatering and restoration regardless of the type of material

encountered shall be included in the unit price bid for the work. 4.2 Cable installed in trench, ductbank or conduit shall be measured by the number of linear feet of

cable installed in trenches, ductbank or conduit, including pulling cable through above and below grade conduits, splices, terminations, and testing, and trench marking tape ready for operation, and accepted as satisfactory. Separate measurement shall be made for each cable installed in trench, ductbank or conduit. The measurement for this item shall not include additional quantities required for slack. Cable slack is considered incidental to this item and is included in the contractor’s unit price. No separate measurement or payment will be made for cable or counterpoise slack.

4.3 Ground Connections shall be measured on a lump sum basis. This item includes ground rods

driven though space in fence foundation, air terminals for lightning protection, ground cable, exothermic welds, wiring, mounting hardware, and all labor, equipment, tools and incidentals, aligned and level as required

Page 219: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

POWER CABLE FOR AIRPORTS L-108 - 9

PART 5 - BASIS OF PAYMENT 5.1 Payment will be made at the contract unit price cabling or wire installed in trench (direct-buried),

ductbank or conduit, in place by the Contractor, and tested and accepted by the COTR. This price shall be full compensation for furnishing all materials and for all preparation and installation of these materials, and for all labor, equipment, tools, and incidentals, including trench marking tape, necessary to complete this item.

5.2 Payment shall be made at the contract unit price per lump sum for Ground Connections. This

price shall be full compensation for furnishing all materials, for preparing and placing these materials, and for all labor, equipment tools, and incidentals necessary to complete the item.

Payment will be made under:

Item L-108-5.1 2-1/C No. 10 AWG, 600V Cable, XHHW, and 1-1/C No. 10,

600V GND—per linear foot Item L-108-5.2 Ground Connections – per lump sum Work of this item shall include work associated with the ground rod, but not be limited to, ground rod, splices, terminations, embedded and exposed raceways, down conductor, wiring, wiring devices, grounding connections and terminations, air terminals for lightning protection, mounting hardware, testing, commissioning and all labor, equipment, tools and incidentals necessary to complete in place the item in accordance with these specifications and as indicated on the drawings. Payment shall be made at the contract lump sum price.

MATERIAL REQUIREMENTS

AC 150/5345-7 Specification for L-824 Underground Electrical Cable for Airport Lighting Circuits

AC 150/5345-26 Specification for L-823 Plug and Receptacle Cable Connectors

FED SPEC J-C-30 Cable and Wire, Electrical Power, Fixed Installation (cancelled; replaced by A-A-59544 Cable and Wire, Electrical (Power, Fixed Installation))

FED SPEC A-A-55809 Insulation Tape, Electrical, Pressure-Sensitive Adhesive, Plastic ASTM B 3 Soft or Annealed Copper Wire ASTM D 4388 Rubber tapes, Nonmetallic Semiconducting and Electrically

Insulating

REFERENCE DOCUMENTS

Page 220: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

POWER CABLE FOR AIRPORTS L-108 - 10

NFPA No. 70 National Electrical Code (NEC) MIL-S-23586C Sealing Compound, Electrical, Silicone Rubber Building Industry Consulting Service International (BICSI) ANSI/IEEE Std 81 IEEE Guide for Measuring Earth Resistivity, Ground Impedance,

and Earth Surface Potentials of a Ground System

END OF ITEM L-108

Page 221: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

AIRPORT ELECTRICAL DUCT BANKS L-110 - 1 AND CONDUITS

ITEM L-110 AIRPORT ELECTRICAL DUCTBANKS AND CONDUITS

PART 1 DESCRIPTION

1.1 This item shall consist of underground electrical conduits and ductbanks (single or multiple conduits encased in concrete) installed in accordance with this specification at the locations and in accordance with the dimensions, designs, and details shown on the plans. This item shall include furnishing and installing of all underground electrical ductbanks and individual and multiple underground conduits. It shall also include all turfing trenching, backfilling, removal, and restoration of any paved or turfed areas; counterpoise wire, concrete encasement, mandrelling, pulling lines, detectable tape, duct markers, plugging of conduits, and the testing of the installation as a completed system ready for installation of cables in accordance with the plans and specifications. This item shall also include furnishing and installing conduits and all incidentals for providing positive drainage of the system. Verification of existing ducts is incidental to the pay items provided in this specification.

PART 2 - EQUIPMENT AND MATERIALS

2.1 GENERAL.

A. All equipment and materials covered by referenced specifications shall be subject to acceptance through manufacturer's certification of compliance with the applicable specification when so requested by the COTR.

B. Manufacturer's certifications shall not relieve the Contractor of the Contractor’s responsibility to provide materials in accordance with these specifications and acceptable to the COTR. Materials supplied and/or installed that do not materially comply with these specifications shall be removed, when directed by the COTR and replaced with materials, which do comply with these specifications, at the sole cost of the Contractor.

C. All materials and equipment used to construct this item shall be submitted to the COTR for approval prior to ordering the equipment. Submittals consisting of marked catalog sheets or shop drawings shall be provided. Submittal data shall be presented in a clear, precise and thorough manner. Original catalog sheets are preferred. Photocopies are acceptable provided they are as good a quality as the original. Clearly and boldly mark each copy to identify pertinent products or models applicable to this project. Indicate all optional equipment and delete non-pertinent data. Submittals for components of electrical equipment and systems shall identify the equipment for which they apply on each submittal sheet. Markings shall be boldly and clearly made with arrows or circles (highlighting is not acceptable). Contractor is solely responsible for delays in project accruing directly or indirectly from late submissions or resubmissions of submittals. .

D. The data submitted shall be sufficient, in the opinion of the COTR, to determine compliance with the plans and specifications. The Contractor's submittals shall be neatly bound in a properly sized 3-ring binder, tabbed by specification section. The Contractor’s submittals shall be submitted to the COTR within 15 days of the notice to proceed. The COTR reserves the right to reject any and all equipment, materials or procedures, which,

Page 222: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

AIRPORT ELECTRICAL DUCT BANKS L-110 - 2 AND CONDUITS

in the COTR’s opinion, does not meet the system design and the standards and codes, specified herein.

E. All equipment and materials furnished and installed under this section shall be guaranteed against defects in materials and workmanship for a period of at least 12 months from final acceptance by the Authority. The defective materials and/or equipment shall be repaired or replaced, at the COTR's discretion, with no additional cost to the Authority.

2.2 STEEL CONDUIT. Rigid galvanized steel conduit and fittings shall be hot dipped galvanized inside and out and conform to the requirements of Underwriters Laboratories Standard 6, 514B, and 1242.

2.3 PLASTIC CONDUIT. Plastic conduit and fittings-shall conform to the requirements of Fed. Spec. W--C-1094, Underwriters Laboratories Standards UL-651 and Article 347 of the current National Electrical Code shall be one of the following, as shown on the plans:

A. Type I–Schedule 40 PVC suitable for underground use either direct-buried or encased in concrete.

B. Type II–Schedule 40 PVC suitable for either above ground or underground use.

The type of adhesive shall be as recommended by the conduit/fitting manufacturer.

2.4 SPLIT CONDUIT. Split conduit shall be pre-manufactured for the intended purpose and shall be made of steel or plastic. Split conduit shall be of the interlocking design as manufactured by Carlon or approved equal.

2.5 CONDUIT SPACERS. Conduit spacers shall be prefabricated interlocking units manufactured for the intended purpose. They shall be of double wall construction made of high grade, high density polyethylene complete with interlocking cap and base pads, They shall be designed to accept No. 4 reinforcing bars installed vertically.

2.6 CONCRETE. Concrete shall conform to Item P-610, Structural Portland Cement Concrete, using 1-inch maximum size coarse aggregate with a minimum 28-day compressive strength of 4,000 psi. Where reinforced ductbanks are specified, reinforcing steel shall conform to ASTM A 615 Grade 60. Concrete and reinforcing steel are incidental to the respective pay item of which they are a component part.

2.7 2.7 DETECTABLE WARNING TAPE. Plastic, detectable, color as noted magnetic tape shall be polyethylene film with a metallized foil core and shall be 4 to 6 inches (75 to 150 mm) wide. The tape shall be as manufactured by Reef Industries, Inc., or approved equal. Detectable tape is incidental to the respective bid item.

2.8 COUNTERPOISE WIRE. Counterpoise wire shall be as specified in Item L-108 Airport Underground Electrical Ductbanks and Conduits

PART 3 - CONSTRUCTION METHODS

3.1 GENERAL. The Contractor shall install underground ductbanks and conduits at the approximate locations indicated on the plans. The COTR shall indicate specific locations as the work

Page 223: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

AIRPORT ELECTRICAL DUCT BANKS L-110 - 3 AND CONDUITS

progresses, if required to differ from the plans. Ductbanks and conduits shall be of the size, material, and type indicated on the plans or specifications. Where no size is indicated on the plans or in the specifications, conduits shall be not less than 2 inches (50 mm) inside diameter or comply with the National Electrical Code based on cable to be installed, whichever is larger. All ductbank and conduit lines shall be laid so as to grade toward access points and duct or conduit ends for drainage. Unless shown otherwise on the plans, grades shall be at least 3 inches (75 mm) per 100 feet (30 m). On runs where it is not practicable to maintain the grade all one way, the ductbank and conduit lines shall be graded from the center in both directions toward access points or conduit ends, with a drain into the storm drainage system. Pockets or traps where moisture may accumulate shall be avoided. No ductbank or underground conduit shall be less than 18 inches below finished grade. Where under pavement, the top of the ductbank shall not be less than 18 inches below the subgrade.

The Contractor shall mandrel each individual conduit whether the conduit is direct-buried or part of a ductbank. A flexible mandrel, not more than 1/4-inch (6 mm) smaller than the bore of the conduit shall be pulled or pushed through each conduit. The mandrel shall have a leather or rubber gasket slightly larger than the conduit hole.

The Contractor shall swab out all conduits/ducts and clean base can, manhole, pull boxes, etc. interiors IMMEDIATELY prior to pulling cable. Once cleaned and swabbed the base cans, manhole, pull boxes, etc. and all accessible points of entry to the duct/conduit system shall be kept closed except when installing cables. Cleaning of ducts, base cans, manholes, etc. is incidental to the pay item of the item being cleaned. All raceway systems left open, after initial cleaning, for any reason shall be recleaned at the Contractor’s expense. All accessible points shall be kept closed when not installing cable. The Contractor shall verify existing ducts proposed for use in this project as clear and open. The Contractor shall notify the COTR of any blockage in the existing ducts.

For pulling the permanent wiring, each individual conduit, whether the conduit is direct-buried or part of a ductbank, shall be provided with a 200-pound test polypropylene pull rope. Pull ropes shall be installed in all conduits and ducts, whether cables will be installed or not during this project. The ends shall be secured and sufficient length shall be left in access points to prevent it from slipping back into the conduit. Where spare conduits are installed, as indicated on the plans, the open ends shall be plugged with removable tapered plugs, designed for this purpose.

All conduits shall be securely fastened in place during construction and shall be plugged to prevent contaminate from entering the conduits. Any conduit section having a defective joint shall not be installed. Ducts shall be supported and spaced apart using approved spacers at intervals not to exceed 5 feet.

Unless otherwise shown on the plans, concrete encased ductbanks shall be utilized when crossing under pavements expected to carry aircraft loads.

Trenches for conduits and ductbanks may be excavated manually or with mechanical trenching equipment unless in pavement, in which case they shall be excavated with mechanical trenching equipment. Walls of trenches shall be essentially vertical so that a minimum of shoulder surface is disturbed. Blades of graders shall not be used to excavate the trench.

When rock is encountered, the rock shall be removed to a depth of at least 3 inches below the required conduit or ductbank depth and it shall be replaced with bedding material of earth or sand

Page 224: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

AIRPORT ELECTRICAL DUCT BANKS L-110 - 4 AND CONDUITS

containing no mineral aggregate particles that would be retained on a 1/4-inch sieve. The Contractor shall ascertain the type of soil or rock to be excavated before bidding.

Underground electrical warning (caution) tape shall be installed in the trench above all underground ductbanks and conduits in unpaved areas. Contractor shall submit a sample of the proposed warning tape for approval by the COTR. If not shown on the plans, the warning tape shall be located 6 inches above the duct/conduit or the counterpoise wire if present.

Joints in plastic conduit shall be prepared in accordance with the manufacturer's recommendations for the particular type of conduit. Plastic conduit shall be prepared by application of a plastic cleaner and brushing a plastic solvent on the outside of the conduit ends and on the inside of the couplings. The conduit fitting shall then be slipped together with a quick one-quarter turn twist to set the joint tightly. Where more than one conduit is placed in a single trench, or in ductbanks, joints in the conduit shall be staggered a minimum of 2 feet.

Changes in direction of runs exceeding 10 degrees, either vertical or horizontal, shall be accomplished using manufactured sweep bends.

Whether or not specifically indicated on the drawings, where the soil encountered at established ductbank grade is an unsuitable material, as determined by the COTR, the unsuitable material shall be removed in accordance with Item P-152 and replaced with suitable material. Alternatively, additional ductbank supports that are adequate and stable shall be installed, as approved by the COTR.

All excavation shall be unclassified and shall be considered incidental to the respective L-110 pay item of which it is a component part. Dewatering necessary for duct installation, erosion and turbidity control, in accordance with Federal, State, and Local requirements is incidental to its respective pay item as a part of Item L-110. The cost of all excavation regardless of type of material encountered, shall be included in the unit price bid for the L-110 item.

Unless otherwise specified, excavated materials that are deemed by the COTR to be unsuitable for use in backfill or embankments shall be removed, stockpiled, and tested by the Authority’s Environmental Contractor in accordance with Item P-152.

Any excess excavation shall be filled with suitable material approved by the COTR and compacted in accordance with item P-152.

It is the Contractor's responsibility to locate existing utilities within the work area prior to excavation. Where existing active cable(s) cross proposed installations, the Contractor shall insure that these cable(s) are adequately protected. Where crossings are unavoidable, no splices will be allowed in the existing cables, except as specified on the plans. Installation of new cable where such crossings must occur shall proceed as follows:

A. Existing cables shall be located manually. Unearthed cables shall be inspected to assure absolutely no damage has occurred.

B. Trenching, etc., in cable areas shall then proceed with approval of the COTR, with care taken to minimize possible damage or disruption of existing cable, including careful backfilling in area of cable.

Page 225: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

AIRPORT ELECTRICAL DUCT BANKS L-110 - 5 AND CONDUITS

In the event that any previously identified cable is damaged during the course of construction, the Contractor shall be responsible for the complete repair.

All pavement surfaces that are to have ducts installed therein shall be neatly saw cut to form vertical face. All excavation shall be included in the contract unit price for the duct.

When existing cables are to be placed in split duct, encased in concrete, the cable shall be carefully located and exposed by hand tools. Prior to being placed in duct, the COTR shall be notified so that he may inspect the cable and determine that it is in good condition. Where required, split duct shall be installed as shown on the drawings or as directed by the COTR.

3.2 DUCTBANKS. Unless otherwise shown in the plans, ductbanks shall be installed so that the top of the concrete envelope is not less than 18 inches below the bottom of the base or stabilized base course layers where installed under runways, taxiways, aprons, or other paved areas, and not less than 18 inches below finished grade where installed in unpaved areas.

Unless otherwise shown on the plans, ductbanks under paved areas shall extend at least 5 feet beyond the edges of the pavement or 5 feet beyond any underdrains that may be installed alongside the paved area. Trenches for ductbanks shall be opened the complete length before concrete is placed so that if any obstructions are encountered, proper provisions can be made to avoid them. Unless otherwise shown on the plans, all ductbanks shall be placed on a layer of concrete not less than 3 inches (75 mm) thick prior to its initial set. Where two or more conduits in the ductbank are intended to carry conductors of equivalent voltage insulation rating, the Contractor shall space the conduits not less than 1-1/2 inches (37 mm) apart (measured from outside wall to outside wall). Where two or more conduits in the ductbank are intended to carry conductors of differing voltage insulation rating, the Contractor shall space the conduits not less than 3 inches apart (measured from outside wall to outside wall). All such multiple conduits shall be placed using conduit spacers applicable to the type of conduit. As the conduit laying progresses, concrete shall be placed around and on top of the conduits not less than 3 inches (75 mm) thick unless otherwise shown on the plans. End bells or couplings shall be installed flush with the concrete encasement at access points.

Conduits forming the ductbank shall be installed using conduit spacers. No. 4 reinforcing bars shall be driven vertically into the soil a minimum of 6 inches to anchor the assembly into the earth prior to placing the concrete encasement. For this purpose, the spacers shall be fastened down with locking collars attached to the vertical bars. Spacers shall be installed at 5-foot intervals. Spacers shall be in the proper sizes and configurations to fit the conduits. Locking collars and spacers shall be submitted to the COTR for review prior to use.

When specified, the Contractor shall reinforce the bottom side and top of encasements with steel reinforcing mesh or fabric or other approved metal reinforcement. When directed, the Contractor shall supply additional supports where the ground is soft and boggy, where ducts cross under roadways, or where shown on the plans. Under such conditions, the complete duct structure shall be supported on reinforced concrete footings, piers, or piles located at approximately 5-foot intervals. All construction joints in concrete-encased ducts shall have a minimum of four steel dowels evenly spaced and installed at the joint. The dowels shall be deformed steel reinforcing bars, one-inch diameter and twenty-four inches long, with ½” of the length embedded in the concrete that is constructed initially.

Page 226: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

AIRPORT ELECTRICAL DUCT BANKS L-110 - 6 AND CONDUITS

All pavement surfaces that are to have ducts installed therein shall be neatly saw cut to form a vertical face. All excavation shall be included in the contract unit price for the duct.

Install a plastic, detectable, color as noted, 4 to 6 inches (75 to 150 mm) wide tape 8 inches (200 mm) minimum below grade above all underground conduit or duct lines not installed under pavement.

When existing cables are to be placed in split duct, encased in concrete, the cable shall be carefully located and exposed by hand tools. Prior to being placed in duct, the COTR shall be notified so that he may inspect the cable and determine that it is in good condition. Where required, split duct shall be installed as shown on the drawings or as required by the COTR.

3.3 CONDUITS WITHOUT CONCRETE ENCASEMENT. Trenches for single-conduit lines shall be not less than 6 inches (150 mm) nor more than 12 inches (300 mm) wide, and the trench for two or more conduits installed at the same level shall be proportionately wider. Trench bottoms for conduits without concrete encasement shall be made to conform accurately to grade so as to provide uniform support for the conduit along its entire length.

Unless otherwise shown on the plans, a layer of fine earth material, at least 4 inches (100 mm) thick (loose measurement) shall be placed in the bottom of the trench as bedding for the conduit. The bedding material shall consist of soft dirt, sand or other fine fill, and it shall contain no particles that would be retained on a 1/4 inch (6 mm) sieve. The bedding material shall be tamped until firm. Flowable backfill may alternatively be used.

Unless otherwise shown on plans, conduits shall be installed so that the tops of all conduits are at least 18 inches below the finished grade.

When two or more individual conduits intended to carry conductors of equivalent voltage insulation rating are installed in the same trench without concrete encasement, they shall be spaced not less than 2 inches (50 mm) apart (measured from outside wall to outside wall) in a horizontal direction and not less than 6 inches (150 mm) apart in a vertical direction. Where two or more individual conduits intended to carry conductors of differing voltage insulation rating are installed in the same trench without concrete encasement, they shall be spaced not less than 3 inches (75 mm) apart (measured from outside wall to outside wall) in a horizontal direction and not less than 6 inches (150 mm) apart in a vertical direction.

Trenches shall be opened the complete length between normal termination points before conduit is installed so that if any unforeseen obstructions are encountered, proper provisions can be made to avoid them.

Conduits shall be installed using conduit spacers. No. 4 reinforcing bars shall be driven vertically into the soil a minimum of 6 inches to anchor the assembly into the earth while backfilling. For this purpose, the spacers shall be fastened down with locking collars attached to the vertical bars. Spacers shall be installed at 5-foot intervals. Spacers shall be in the proper sizes and configurations to fit the conduits. Locking collars and spacers shall be submitted to the COTR for review prior to use.

3.4 MARKERS. The location of each end and of each change of direction of conduits and ductbanks shall be marked by a concrete slab marker 2 feet square and 4 to 6 inches (100 to 150 mm) thick extending approximately 1 inch (25 mm) above the surface. The markers shall also be located

Page 227: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

AIRPORT ELECTRICAL DUCT BANKS L-110 - 7 AND CONDUITS

directly above the ends of all conduits or ductbanks, except where they terminate in a junction/access structure or building.

The Contractor shall impress the word “DUCT” or “CONDUIT” on each marker slab. The Contractor shall also impress on the slab the number and size of conduits beneath the marker along with all other necessary information as determined by the COTR. The letters shall be 4 inches (100 mm) high and 3 inches (75 mm) wide with width of stroke 1/2-inch (12 mm) and 1/4-inch (6 mm) deep or as large as the available space permits. Furnishing and installation of duct markers is incidental to the respective duct pay item.

3.5 BACKFILLING FOR CONDUITS. For conduits, 8 inches of sand, soft earth, or other fine fill (loose measurement) shall be placed around the conduits ducts and carefully tamped around and over them with hand tampers. The remaining trench shall then be backfilled and compacted in accordance with Item P-152 Excavation and Embankment except that material used for backfill shall be select material not larger than 4 inches in diameter.

Trenches shall not contain pools of water during backfilling operations.

The trench shall be completely backfilled and tamped level with the adjacent surface.

Any excess excavated material shall be removed, stockpiled, and tested by the Authority’s Environmental Contractor in accordance with Item P-152.

3.6 BACKFILLING FOR DUCTBANKS. After the concrete has cured, the remaining trench shall be backfilled and compacted in accordance with Item P-152 Excavation and Embankment except that the material used for backfill shall be select material not larger than 4 inches in diameter. In addition to the requirements of P-152, where ductbanks are installed under pavement, one moisture/density test per lift shall be made for each 250 linear feet of ductbank or one work period's construction, whichever is less.

Trenches shall not contain pools of water during backfilling operations.

The trench shall be completely backfilled and tamped level with the adjacent surface.

Any excess excavated material shall be removed, stockpiled, and tested by the Authority’s Environmental Contractor in accordance with Item P-152.

3.7 RESTORATION. Where soil and sod has been removed, it shall be replaced as soon as possible after the backfilling is completed. All areas disturbed by work shall be restored to its original condition. The restoration shall include topsoiling and seeding and mulching as shown on the plans. Refer to specifications T-901 Seeding, T-905 Topsoiling, and T-908 Mulching. The Contractor shall be held responsible for maintaining all disturbed surfaces and replacements until final acceptance.

3.8 COUNTERPOISE WIRE. Counterpoise wire shall be installed as specified in Item L-108.

PART 4 - METHOD OF MEASUREMENT

4.1 Underground and above ground conduits and ductbanks shall be measured by the linear feet of conduits and ductbanks installed, including encasement, counterpoise wire, locator tape, and

Page 228: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

AIRPORT ELECTRICAL DUCT BANKS L-110 - 8 AND CONDUITS

trenching and backfill with designated resolution, all measured in place, completed, and accepted. Separate measurement shall be made for the various types and sizes.

PART 5 - BASIS OF PAYMENT

5.1 Payment will be made at the contract unit price per linear foot for each type and size of conduit and ductbank completed and accepted, including trench and backfill with the designated material. This price shall be full compensation for furnishing all materials and for all preparation, assembly, and installation of these materials, and for all labor, equipment, tools, and incidentals necessary to complete this item in accordance with the provisions and intent of the plans and specifications

Payment will be made under:

Item L-110-5.1 1” RGS Conduit - per linear foot

MATERIAL REQUIREMENTS

Fed.Spec.W-C-1094 Conduit and Conduit Fittings; Plastic, Rigid (cancelled; replaced by UL 514 Boxes, Nonmetallic Outlet, Flush Device Boxes, & Covers, and UL 651 Standard for Conduit & Hope Conduit, Type EB & A Rigid PVC)

Underwriters Laboratories Standard 6 Rigid Metal Conduit

Underwriters Laboratories Standard 514B Fittings for Cable and Conduit

Underwriters Laboratories Standard 1242 Intermediate Metal Conduit

Underwriters Laboratories Standard 651 Schedule 40 and 80 Rigid PVC Conduit (for Direct Burial)

Underwriters Laboratories Standard 651A Type EB and A Rigid PVC Conduit and HDPE Conduit (for concrete encasement)

END OF ITEM L-110

Page 229: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

AIRFIELD LIGHTING SYSTEM TESTING L-111 - 1

ITEM L-111 AIRFIELD LIGHTING SYSTEM TESTING

PART 1 - DESCRIPTION

1.1 This item shall consist of furnishing all equipment, materials and appliances necessary for testing of airfield lighting circuit installations and associated systems. Airfield lighting systems include airfield signage systems.

A. The Contractor shall provide all testing as required by this item, including retesting of failed items. The Contractor shall provide all electrical testing to confirm that lighting system installations associated with this project are acceptable. The Authority shall engage an independent agency to perform the repairs. Specified photometric testing, with the Contractor providing all testing support and assistance, shall be made at the Contractor’s expense.

B. Requirements under this item shall be coordinated with the COTR.

C. This section describes the testing and demonstrations furnished by the Contractor. All items furnished and/or installed by the Contractor shall be tested and demonstrated in accordance with these specifications. All equipment and labor required for testing and demonstrations shall be furnished by the Contractor.

D. The Contractor shall perform the necessary inspection and tests for some items concurrently with the installation because of subsequent inaccessibility of some components. The COTR shall be notified by the Contractor 48 hours in advance of any testing.

PART 2 - EQUIPMENT AND MATERIALS

2.1 GENERAL. Materials and equipment covered by this item shall be subject to acceptance through manufacturer's certification of compliance with the applicable specification when requested by the COTR. All equipment, materials, methods and record keeping procedures shall be submitted to the COTR for review.

2.2 TEST EQUIPMENT. All test equipment proposed for use shall have a current calibration. Calibration certifications are current for 1 year from date of calibration. At any time, the COTR may require the Contractor to have a piece of test equipment recalibrated. The test equipment will be removed from the project until recalibrated. The Contractor shall submit the Calibration Laboratory’s qualifications and the test equipments serial numbers and calibration certificates to the COTR for review.

PART 3 - CONSTRUCTION METHODS

3.1 GENERAL. The Contractor shall furnish all necessary equipment and appliances for testing installations as indicated below.

Page 230: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

AIRFIELD LIGHTING SYSTEM TESTING L-111 - 2

3.2 GROUND ROD TESTING.

A. The Contractor shall provide equipment and personnel to measure the resistance to earth for all ground rods installed using Fall of Potential Method. Earth resistance measurement tests shall adhere to recommendations of IEEE Standard 142, latest edition. The Contractor shall submit testing procedure and equipment and report form to the COTR for approval.

B. Tests shall be administered as each rod is installed. Tests shall be conducted prior to the connection of any grounding or counterpoise conductors. The resistance between each ground rod and absolute earth shall not exceed 25 ohms. Any rod, which does not have a resistance to ground of 25 ohms or less, shall be augmented by an additional 10-foot section of rod until the 25 ohm maximum earth resistance requirement is met. Test results shall be submitted to the COTR for approval.

3.3 CIRCUITS TESTING. The Contractor shall notify the COTR 72 hours prior to cable testing. All testing shall be conducted in the presence of the COTR. All test results shall be simultaneously recorded by the Contractor and COTR. The Contractor shall submit test report information to the COTR. Test procedures for the following required tests, including field test report forms, shall be submitted to the COTR for review prior to testing.

A. Testing Requirements:

1. Testing Required for Existing Circuits and Existing Portions of Circuits to be Extended: The existing circuits to be extended shall be subjected to low voltage tests in accordance with paragraph B.1 below. Tests shall be performed with the isolation transformers and other lighting system devices connected. Test results shall be submitted to the COTR for approval prior to extending or revising the existing circuit.

2. Testing Required for Existing Circuits with Circuit Modifications and/or Extensions Completed: Each existing series circuit that has been modified and/or extended shall be subjected to low voltage tests in accordance with paragraph B.1 below. Tests shall be performed with the lighting isolation transformers and other lighting system devices connected. Circuits tested shall meet the requirements of paragraph C.2 below. Any faults indicated by these tests shall be corrected before proceeding with additional testing. Test results shall be submitted to the COTR for approval.

3. Testing Required for New Circuits and New Portions of Existing Circuits: Each new series circuit, or new segment of existing circuits being extended, modified, or replaced, shall be tested as follows.

a. After new cable with new connectors is installed and prior to connecting

isolation transformers, the following tests shall be performed. 1) Low voltage continuity and insulation resistance (IR) tests in

accordance with paragraph B.1 below to determine if the total insulation resistance of each circuit is satisfactory so that the series lighting circuit will operate without excessive leakage current when energized. Circuits tested shall meet the

Page 231: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

AIRFIELD LIGHTING SYSTEM TESTING L-111 - 3

requirements of paragraph C.3.a below. Any faults indicated by these tests shall be corrected before proceeding with additional testing. All test results shall be submitted to the COTR for approval.

b. New segments of existing circuits meeting the requirements of paragraph A.3.a above shall then have the isolation transformers connected and shall again be subjected to the low voltage continuity and IR tests of paragraph B.1. Any faults indicated by these tests shall be corrected before energizing the circuit. All test results shall be submitted to the COTR for approval.

4. All Circuits: Upon completion of all wiring of each circuit, the low voltage continuity and IR tests shall be performed on the completed circuit in accordance with paragraph B.1 below. All isolation transformers and other lighting system devices shall be connected to the completed circuit. Circuits tested shall meet the requirements of paragraph C.3.a below. Any faults indicated by these tests shall be corrected before proceeding with additional testing. All test results shall be submitted to the COTR for approval.

B. Testing Procedures:

1. Low Voltage Tests: Low voltage continuity and IR tests. a. Test Required: As noted in paragraph A. above, circuits and segments of

circuits shall be subjected to a low voltage continuity test and to a 2,500 volt IR (Megger) test. IR tests shall test the insulation resistance to ground and other conductors within the same raceway of each lighting system conductor.

b. Test Equipment: Contractor shall provide a 2,500-volt direct current IR test set for low voltage testing. IR test set shall be a 120V AC device, non-crank type, as manufactured by Associated Research Meg-Check, the James Biddle Megger, General Radio Megohmmeter, or approved equivalent. The Contractor shall be responsible for providing any required 120V AC power source at testing locations remote from available power. Equipment calibration information shall be readily available for review by the COTR if requested.

c. Test Procedures. "Lock-Tag-Try Procedure" requirements shall comply

with OSHA 1926.417. Test procedures for the required tests, including field test report forms, shall be submitted to the COTR for approval prior to testing. 1) Test equipment grounding electrode shall be adjacent to the test

equipment and be a part of/connected to the airfield grounding counterpoise/ground rod system.

2) Verify that all devices and accessories connected to the cable are rated for the test voltage to be applied.

3) Ground other cables in the same conduit as cable under test. 4) Clean and isolate “remote” end of cable to be tested.

Page 232: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

AIRFIELD LIGHTING SYSTEM TESTING L-111 - 4

5) Ground the cable for a minimum of 1 minute prior to testing. 6) Test cable. 7) After testing is complete, cable shall be discharged to the

grounding electrode using resistor designed for the purpose. Solidly ground the cable after discharge. Cable shall remain solidly grounded for a minimum of 5 minutes.

d. Test Results. Cable specimens that do not meet the test criteria given in paragraph C.2 for existing circuits that have been modified and/or extended, and paragraph C.3, for new circuits and new segments of existing circuits, shall be considered unacceptable. Refer to paragraph D. below for cables not meeting testing requirements.

2. For all Testing: All existing and/or new cables, equipment, and materials damaged during testing shall be repaired and/or replaced by the Contractor at no additional cost to the Authority as directed by the COTR. Tests shall be performed and faulty installations corrected until satisfactory results are obtained. Exact correction procedures for specific faulty installation circumstances shall be as specified and approved by the COTR. The Contractor is not responsible for the repair of existing cables that are to be modified or extended that are deemed by the COTR to be faulty prior to modification or extension unless directed by the Contract Documents.

C. Testing Results:

1. New Circuits and New Segments of Existing Circuits:

a. Low voltage tests shall demonstrate to the satisfaction of the COTR the following: 1) All circuits are properly connected in accordance with the

applicable wiring diagrams. 2) All lighting power and control circuits are continuous and free

from short circuits. 3) All circuits are free from unspecified grounds. 4) The IR is equal to or greater than 400 megohms for new circuits

and new segments of existing circuits. Isolation transformers shall be connected. In addition, new circuits and new segments of existing circuits shall maintain an insulation resistance of not less than 300 megohms, with isolation transformers connected, through the end of the construction warranty period.

5) Insulation-resistance of cables of approximately the same length installed in same duct bank shall not show a comparison ratio of over 3 to 1.

D. Deficient Testing Results (Circuits Not Meeting Requirements):

1. Existing circuits and existing portions of circuits that have been extended or modified.

Page 233: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

AIRFIELD LIGHTING SYSTEM TESTING L-111 - 5

2. Cables that do not meet the test criteria of paragraph C.2 above shall be considered unacceptable and shall not be energized until corrected.

3. If all "Lock-Tag-Try Procedure" requirements established OSHA 1926.417 have

been satisfied by the Contractor and the COTR determines non-complying circuits or segments of circuits are the responsibility of the Authority, then the Contractor shall provide to the Authority, through the COTR, all test reports identifying location of non-complying cables.

4. New Circuits and New Portions of Existing Circuits: Cables that do not meet the

test criteria of subparagraph C.3 above shall be considered unacceptable and shall not be energized until corrected.

E. Submittal of Testing Data:

1. Low Voltage Tests: Contractor shall submit 12 copies of tests reports for approval of the COTR. Reports shall include all measured data including applied voltage, time length of voltage application and measured megohms from each segment of cable in a circuit.

The low voltage tests data form shall also include, as a minimum;

Date Cable number Start time End time Operating voltage Maximum test voltage Cable routing Cable description Ambient temperature Humidity Relative humidity Measure equipment number Equipment calibration due date

3.4 SYSTEM TESTS. After the airfield lighting systems installation is complete and at such times as the COTR may direct, the contractor shall conduct airfield lighting systems operating tests for approval.

A. The equipment shall be demonstrated to operate in accordance with the requirements of this specification. The test shall be performed in the presence of the COTR. The Contractor shall furnish all equipment and personnel required for the test.

B. Each applicable control device in the control tower lighting panels shall be operated so that each control device position is engaged at least ten times. During this process, all lights and associated equipment shall be observed to determine that each control device switch properly commands the corresponding circuit. Radio communication between the operator and the observers shall be provided by the Contractor.

Page 234: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

AIRFIELD LIGHTING SYSTEM TESTING L-111 - 6

C. The above tests shall be repeated for each individual circuit from the local control switches on the regulators. Each installed or revised lighting circuit shall be tested by operating the lamps throughout the range of applicable steps and shall be operated separately at step 3, step 5 or step 7 as appropriate for full intensity for not less than 8 hours. Visual examination shall be made at the beginning and at the end of this test to determine that the installed airfield light fixtures are illuminating at full intensity.

D. If circuit regulators are installed under project construction, regulator output ampacity shall be adjusted for proper outputs in accordance with manufacturer's recommendations and requirements to insure proper circuit operation.

E. Systems tests shall confirm by demonstration in service that all lighting circuits are in good operating condition to the satisfaction of the COTR. If the tests are unsatisfactory, lighting systems installed shall be corrected and systems tests shall again be implemented.

PART 4 - METHOD OF MEASUREMENT

4.1 The items described in this section are incidental to other sections and shall not be measured for payment.

PART 5 - BASIS OF PAYMENT

5.1 No direct payment shall be made for the work described in this section. The work described in this section is incidental to other items and shall be paid for in the respective bid item of which it is a component part.

END OF ITEM L-111

Page 235: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

OBSTRUCTION LIGHTS L-121 - 1

ITEM L-121 OBSTRUCTION LIGHTS

PART 1 DESCRIPTION

1.1 GENERAL. This item shall consist of taxiway lighting systems furnished and installed in accordance with this specification, any referenced specifications, and the applicable Federal Aviation Administration Advisory Circulars. The systems shall be installed at the location and in accordance with the dimensions, layout, design, and details shown in the plans. This item shall include furnishing and installing all lights, transformers, light bases, mounting assemblies, base plates, flange rings, spacer rings, concrete work, cable connections, lamps, testing of the installation and all incidentals and appurtenances necessary to place the systems in operation as completed units to the satisfaction of the COTR.

1.2 REFERENCED MATERIALS. Additional details pertaining to specific systems covered in this section are contained in the Federal Aviation Administration (FAA) Advisory Circulars (AC's), latest edition, listed below.

150/5340-1 Standards for Airport Markings 150/5340-26 Maintenance of Airport Visual Aid Facilities 150/5340-30 Design and Installation Details For Airport Visual Aids 150/5345-1 Approved Airport Equipment 150/5345-7 Specification for L-824 Underground Electrical Cable for Airport Lighting Circuits 150/5345-26 FAA Specification for L-823 Plug and Receptacle, Cable Connectors 150/5345-39 FAA Specification L-853, Runway and Taxiway Centerline Retroreflective Markers

150/5345-42 Specification for Airport Light Bases, Transformer Houses, Junction Boxes and Accessories

150/5345-46 Specification for Runway and Taxiway Light Fixtures 150/5345-47 Isolation Transformers for Airport Lighting Systems 150/5345-53 Airport Lighting Equipment Certification Program

The Contractor is responsible for obtaining and using the latest edition of the referenced FAA Advisory Circulars. This is not all inclusive but is offered as a convenience to the Contractor.

PART 2 - EQUIPMENT AND MATERIALS

2.1 GENERAL.

A. All equipment and materials covered by referenced specifications shall be subject to acceptance through manufacturer's certification of compliance with the applicable specification when so requested by the COTR.

B. Manufacturer's certifications shall not relieve the Contractor of the Contractor’s responsibility to provide materials in accordance with these specifications and acceptable to the COTR. Materials supplied and/or installed that do not materially comply with these

Page 236: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

OBSTRUCTION LIGHTS L-121 - 2

specifications shall be removed, when directed by the COTR and replaced with materials, which do comply with these specifications, at the sole cost of the Contractor.

C. All materials and equipment used to construct this item shall be submitted to the COTR for approval prior to ordering the equipment. Submittals consisting of marked catalog sheets or shop drawings shall be provided. Submittal data shall be presented in a clear, precise and thorough manner. Original catalog sheets are preferred. Photocopies are acceptable provided they are as good a quality as the original. Clearly and boldly mark each copy to identify pertinent products or models applicable to this project. Indicate all optional equipment and delete non-pertinent data. Submittals for components of electrical equipment and systems shall identify the equipment for which they apply on each submittal sheet. Markings shall be boldly and clearly made with arrows or circles (highlighting is not acceptable). Contractor is solely responsible for delays in project accruing directly or indirectly from late submissions or resubmissions of submittals.

D. The data submitted shall be sufficient, in the opinion of the COTR, to determine compliance with the plans and specifications. The Contractor’s submittals shall be submitted to the COTR within 15 days of the notice to proceed. The COTR reserves the right to reject any and all equipment, materials or procedures, which, in the COTR’s opinion, does not meet the system design and the standards and codes, specified herein.

E. All equipment and materials furnished and installed under this section shall be guaranteed against defects in materials and workmanship for a period of at least 12 months from final acceptance by the Authority. The defective materials and/or equipment shall be repaired or replaced, at the COTR's discretion, with no additional cost to the Authority.

F. All items required per this section are for use on a 6.6 amp primary series circuit unless specifically noted otherwise

2.2 BASIS OF DESIGN. The airfield lighting systems are designed using the below listed maximum fixture wattages. Approved airfield lighting fixtures with higher wattages are permissible provided the Contractor assumes all costs for the redesign of the airfield lighting and necessary power distribution systems and all costs incurred furnishing and installing any additional equipment. In no case shall the Contractor be allowed to reduce the size of the constant current regulators or the power distribution systems.

L-810 Obstruction Light 15W

2.3 CABLES. Cables shall comply with specification L-108, Installation of Cable for Airports.

2.4 L-823 CONNECTORS. Connectors shall comply with specification L-108, Installation of Cable for Airports.

2.5 OBSTRUCTION LIGHTS. The obstruction lights shall be FAA type L-810, with LED lamps, Dialight Vigilant L-810 860 Series or approved equal, conforming to AC 150/5345-47A, latest edition.

2.6 FRANGIBLE COUPLINGS. All elevated items shall be installed on frangible couplings in accordance with the respective Federal Aviation Administration Advisory Circular. Frangible

Page 237: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

OBSTRUCTION LIGHTS L-121 - 3

couplings shall be metallic and provide an electrical grounding path between the fixture and the light base.

2.7 LAMPS. Obstruction lighting fixture lamps shall be LED type to provide distribution and minimum output requirements of isocandela curves shown for each size in AC 150/5345-46B, (latest edition). All airfield lighting fixtures shall be installed with lamps.

2.8 COLORED FILTERS. Colored filters, or colored lenses, to be used for Airfield Lighting Fixtures shall conform to the requirements of Military Specification SAE-AS25050 type I and FAA Advisory Circulars.

2.9 TAPE. Plastic electrical tapes shall be Scotch Electrical Tape number 88 as manufactured by the Minnesota Mining and Manufacturing Company or an approved equivalent. Electrical coating shall be Scotchkote as manufactured by the Minnesota Mining and Manufacturing Company or approved equivalent.

2.10 CONCRETE. Concrete for backfill shall comply with Item P-610, Structural Portland Cement Concrete and have a maximum size coarse aggregate of 1 inch and shall have a 28-day comprehensive strength of not less than 4,000 PSI and increasing with age, unless otherwise noted.

2.11 CONDUIT. Conduit shall comply with Item L-110, Installation of Airport Electrical Duct.

2.12 HEAT SHRINK KIT. Heat shrinkable tubing with integral sealant for waterproofing L-823 connectors shall be Sigmaform Corporation Type APL, Raychem Corporation Type ADL, Crouse Hinds Type HSK or approved equivalent.

2.13 IDENTIFICATION/NUMBER PLATES. The identification/number plates shall be 2" diameter brass tags/monuments as shown in the plans and details. The identification shall be permanently stamped. Text height shall be 3/8".

2.14 REINFORCING STEEL. All reinforcing steel shall be ASTM A 615, Grade 60".

2.15 BOLTING HARDWARE. All airfield bolting hardware shall be meet FAA requirements. Bolts shall be epoxy-coated and epoxy coating shall be orange in color. All bolts 1/4" and larger shall be hex head type. All bolts smaller than 1/4" trade size shall be recessed allen type. All bolted connections shall utilize an anti-rotational locking type device. The light base cover and fixture mounting bolts shall extend through the light base mounting flange into the light base a minimum of 0.5". The bolts shall have enough thread length so they do not shoulder out before the fixture is securely tightened. Bolts shall be manufactured by MCB Industries or approved equal.

Washers shall be stainless, two-piece, vibration resistant type, manufactured by Nord-Lock or approved equal.

2.16 ANTI-SEIZE COMPOUND. The anti-seize compound shall be Ideal "Noalox" or approved equivalent. Use GE-RTV-118 non-curing sealant to seal between sections of light bases, spacer rings, adaptor rings or fixtures

2.17 STRAIN RELIEF CONNECTORS. Strain relief connectors shall be Liquid Tight Thomas & Betts 2500 series with WMG-PG wire mesh cable grip or approved equivalent.

Page 238: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

OBSTRUCTION LIGHTS L-121 - 4

2.18 PHOTOCELL. The photocell shall be a photocontrol device designed for outdoor use with ratings for the proposed installation. The photocell shall be an Intermatic model K4236C, with a swivel stem and light level shield or approved equivalent.

2.19 DELIVERY, STORAGE AND HANDLING. Ship materials and equipment disassembled only to the extent necessary for reasons of shipping limitations, handling facilities, and to avoid damage during shipment. Maintain materials and equipment in new condition. This shall include the use of heat lamps, suitable coverings, indoor storage, etc. to properly protect the equipment and materials. Any equipment or materials, in the opinion of the COTR, damaged during construction or storage periods shall be replaced by and at the expense of the Contractor.

2.20 SPARE PARTS. The following table lists the electrical spare parts required to be furnished by the Contractor. All spare parts shall be identical to the same parts approved and installed in the project. The cost of all defined spare parts to be furnished to the Authority shall be included in the respective spare part bid item.

The Manufacturer/Contractor by submitting a bid assures the Authority that it will sell to the Authority or any of the Authority's designated representatives any and all parts for materials furnished under this contract at the lowest price the Contractor or its subcontractors, or suppliers furnish them to any second party. This pricing requirement shall apply for five (5) years from the date of final acceptance of the contract. In furnishing parts at this price, the Contractor shall provide the parts within one week of an approved purchase agreement. The Authority shall have the right to verify that the prices the Authority pays for the parts are the lowest and if they are determined not to be, then the Authority shall receive a payment from the Manufacturer/Contractor in the amount of one and one-half (1.5) times the difference. The Contractor is responsible to coordinate and obtain this agreement, in writing, from the manufacturer.

SPARE PARTS LIST Category Description Quantity Fixtures: L-810 Obstruction Lights 2 Equipment: Photocell 1

PART 3 - CONSTRUCTION METHODS

3.1 INSTALLATION OF FIXTURES. All fixtures, etc. shall be installed as shown in the plans or approved shop drawings and in accordance with the applicable FAA Advisory Circulars and manufacturers' recommendations. Survey instruments shall be used to position all items to insure precise orientation. Tolerances given in the FAA Advisory Circulars, these specifications, and the plans shall not be exceeded. Where no tolerance is given, no deviation is permitted. Items not installed in accordance with the FAA Advisory Circulars, these specifications and plans shall be removed and replaced by and at the expense of the Contractor.

Survey instruments shall be used to position all items to insure precise orientation. Orient the axis of the light beam centerline parallel to the centerline of the taxiway or taxi path respectively. Tolerances given in the FAA Advisory Circulars, these specifications, and the plans shall not be exceeded. Where no tolerance is given, no deviation is permitted. Items not installed in accordance with the FAA Advisory Circulars, these specifications and plans shall be removed and replaced by and at the expense of the Contractor.

Page 239: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

OBSTRUCTION LIGHTS L-121 - 5

The Contractor shall completely survey and stake out each areas lighting layout prior to starting any installation. The survey shall be performed by a professional licensed surveyor in the applicable state. Should any irregularities occur in the layout, the COTR shall be notified immediately. The bid item price shall include the necessary surveyed layout for each item and the cost for any additional adjustment or resurvey of the location of the items due to the existing geometric conditions. The new lighting installation shall be coordinated with and blend into the existing lighting installation.

All loose material shall be removed from all excavations for electrical equipment, raceways, manholes, pads, etc. The bottom of the excavation shall be compacted to 95% compaction in accordance with ASTM D 1557 prior to the installation of the electrical item and backfill.

Level and align each light. Verify level and alignment of each base after each time access to light occurs.

Assemble units and connect to the system in accordance with the manufacturer's recommendations and instructions. Light fixtures shall not be installed closer than or within two (2) feet of a paving joint without written permission of the COTR.

An identification tag shall be installed with each fixture as shown in the plans. Brass circuit identification tags identifying each circuit shall be attached to each circuit as shown in the plans.

Provide six feet (6') of slack in each end of each cable in each light base. All connections shall be able to be made above ground.

Painted and galvanized surfaces that are damaged shall be repaired according to the manufacturer's recommendations, and to the satisfaction of the COTR. Use LPS-1G cold galvanizing compound or approved equivalent to repair galvanized surfaces. Obtain paint and primer, of same batch number, from the equipment manufacturer to repair painted surfaces.

GE RTV-118 non-curing sealant or approved equivalent shall be used to seal between sections of the light base, spacer rings, flange rings and fixtures.

All threaded portions of frangible couplings, etc. shall be coated with Ideal "Noalox" compound or approved equivalent before being assembled.

Deliver leveling and aligning equipment to the Airport Maintenance Department at completion of the work. At the end of the job, deliver any remaining lamps to the Airport Maintenance Department.

3.2 TESTING. This section describes the testing and demonstrations furnished by the Contractor. All items furnished and/or installed by the Contractor shall be tested and demonstrated in accordance with these specifications. All equipment and labor required for testing and demonstrations shall be furnished by the Contractor.

A. Fully test the installation by continuous operation for a period of not less than seventy-two (72) hours as a completed unit, prior to acceptance by the COTR.

Page 240: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

OBSTRUCTION LIGHTS L-121 - 6

B. Up to two (2) walk-throughs may be initiated by the COTR during which the airfield lighting units would be required to be in operation. Additional walk-throughs may be necessary depending upon the number of discrepancies found on the previous walk-throughs.

C. The Contractor is responsible for lamp replacements and necessary maintenance of airfield items during the testing, construction and walk-through periods.

D. Test cabling per specification L-108, Installation of Cable for Airports.

E. Demonstrate all features and functions of all systems and instruct the Authority personnel in the proper and safe operation of the systems.

F. The Contractor shall perform the necessary inspection and tests for some items concurrently with the installation because of subsequent inaccessibility of some components. The COTR shall be notified by the Contractor forty-eight (48) hours in advance of any testing.

3.3 OPERATION AND MAINTENANCE MANUALS. The Contractor shall provide data for all equipment, material and components supplied or furnished under this section in the Operation and Maintenance Manuals. This data shall include cut sheets from the manufacturer and the manufacturer's installation, operation and maintenance manuals, recommended spare parts lists, any required test results, and other data as required. Final payment for any contract amounts shall not be processed without proper submittal of these manuals and review and approval by the COTR.

3.4 CONTRACT DRAWINGS. Where the electrical drawings indicate (diagrammatically or otherwise) the work intended and the functions to be performed, even though some minor details are not shown, the Contractor shall furnish all equipment, material, and labor to complete the installation work, and accomplish all the indicated functions of the electrical installation. Further, the Contractor shall be responsible for taking the necessary actions to ensure that all electrical work is coordinated and compatible with the civil plans.

3.5 MINOR DEPARTURES. Minor departures from exact dimensions shown in the electrical plans may be permitted where required to avoid conflict or unnecessary difficulty in placement of a dimensional item, provided contract requirements are met. The Contractor shall promptly obtain approval from the COTR prior to undertaking any such proposed departure.

PART 4 - METHOD OF MEASUREMENT

4.1 The quantity of airfield lighting units to be paid for under this item shall be the number of each type installed, complete and in place, ready for operation, and accepted by the COTR. Each airfield lighting unit shall include the installation of an identification plate or tag as detailed in the plans.

Page 241: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

OBSTRUCTION LIGHTS L-121 - 7

PART 5 - BASIS OF PAYMENT

5.1 Payment will be made under:

Item L-121-5.1 L-810 Dual-Obstruction Light Assembly – per each

Work of this item shall include work associated with the obstruction light assembly, but not be limited to, L-810, dual obstruction light assembly, mounting hardware, conduit body, junction boxes, conduit, fittings, wiring, connections, and all labor, equipment, tools and incidentals, aligned and level as required, and all labor, equipment, tools and incidentals necessary to complete in place the item in accordance with these specifications and as indicated on the drawings. Payment shall be made at the contract each unit price. Item L-121-5.2 Photocell - per each Work of this item shall include work associated with the photocell, but not be limited to, photo-cell light assembly, contactor, junction box, mounting hardware, conduit body, conduit, fittings, wiring, connections, and all labor, equipment, tools and incidentals necessary to complete in place the item in accordance with these specifications and as indicated on the drawings. Payment shall be made at the contract each unit price.

.

Item L-121-5.3 NEMA 3R 6” x 6” x 4” Junction Box for Obstruction Light Wiring - per each

Work of this item shall include work associated with the junction box, but not be limited to, junction box, mounting hardware, conduit, wiring, connections, and all labor, equipment, tools and incidentals necessary to complete in place the item in accordance with these specifications and as indicated on the drawings. Payment shall be made at the contract each unit price.

.

Item L-121-5.4 Safety Disconnect Switch - per each Work of this item shall include work associated with the disconnect switch, but not be limited to, disconnect switch, mounting hardware, conduit, wiring, connections, and all labor, equipment, tools and incidentals necessary to complete in place the item in accordance with these specifications and as indicated on the drawings. Payment shall be made at the contract each unit price. Item L-121-5.5 L-810 Dual-Obstruction Light Assembly (Spare Part) – per each

Item L-121-5.6 Photocell (Spare Part) - per each

END OF ITEM L-121

Page 242: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final
Page 243: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

DEMONSTRATIONS, TESTS AND PERFORMANCE VERIFICATION L-131 - 1

ITEM L-131 DEMONSTRATIONS, TESTS AND PERFORMANCE VERIFICATION

PART 1 - DESCRIPTION

1.1 GENERAL. This item includes the furnishing of all labor, materials, equipment and services necessary to provide demonstrations, testing and performance verification necessary to show electrical system compliance to these specifications.

PART 2 - DEMONSTRATIONS

2.1 CHECK-OUT MEMO. Where required by the plans and specifications, provide manufacturer assistance during the testing, startup, performance verification, demonstrations and Authority training. Complete the Check-Out Memo contained in Appendix A, Figure 1.

2.2 Demonstrate the essential features of the following electrical systems:

Circuit breakers Electrical systems controls and equipment Electrical power equipment Relays Wiring devices Grounding systems Obstruction Lights Photocells Contactors

2.3 The demonstration shall be held upon completion of all systems, including testing, at a date to be agreed upon in writing by the COTR or his designated representative. The demonstration shall be held by the Contractor in the presence of the Authority and the Manufacturer's Representative.

2.4 Prior to acceptance of the work, the Contractor shall demonstrate to the Authority, or his designated representative, all features and functions of all systems and shall instruct the Authority in the proper operation of the systems. After testing is completed satisfactorily, each system shall be demonstrated once.

The demonstration shall consist of not less than the following:

A. Point out the actual location of each component of the system and demonstrate its function and its relationship to other components within the system.

B. Demonstrate the electrical systems by actual "start-stop" operation showing how to work controls, how to reset protective devices, how to replace fuses, and what to do in an emergency. Indicate each items relationship to the riser diagrams and drawings.

C. Demonstrate communication, signal, alarm and detection systems by actual operation of the systems and show how to reset signal, alarm and detection devices.

Page 244: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

DEMONSTRATIONS, TESTS AND PERFORMANCE VERIFICATION L-131 - 2

The Contractor shall furnish the necessary trained personnel to perform the demonstration and instructions, and shall arrange to have the manufacturer's representatives present to assist with the demonstrations.

All functional and operational testing of protective interlocking, automatic controls, instrumentation, alarm systems, and all other field testing of the main systems will be completed before the systems are demonstrated.

2.5 Submit 6 copies of the Performance Verification and Demonstration to Authority Form (Appendix A, Figure 2), signed by the Contractor, subcontractor and Authority and insert one copy in each operation and maintenance (O&M) manual and the original shall be inserted in the Project Closeout Documentation Manual.

PART 3 - TESTS AND PERFORMANCE

3.1 TESTS AND PERFORMANCE VERIFICATION. Operate system for a 3-day period. Do performance verification work as required to show that the system is operating correctly in accordance with design. Supply instruments required to read data. Adjust system to operate at the required performance levels. Tabulate data for submission. Submit data on 8-1/2-inch by 11-inch sheets with time and name of checker. Where specific performance verification information is called for in the specifications, use copies of the sheets provided for recording readings. Data shall be submitted and approved before Check-Out Memos are signed or a request for final inspection is made. Submit data in O&M manuals.

At completion of construction after all performance verification and testing information has been gathered, submitted, and approved, provide one copy of this information to the Manufacturer's representative of the equipment. Work required under this section shall include having the representative examine the performance verification information, check the equipment in the field while it is operating, and sign a Check-Out Memo for a record. Submit 6 copies of the Check-Out Memo on each major item of equipment. Approved memos shall be inserted in each O&M manual with the performance verification information. Memos shall be submitted and approved before instruction to COTR or a request for final inspection.

3.2 TESTS. After cables are in place, but before being connected to devices and equipment, the system shall be tested for shorts, opens, intentional and unintentional grounds by means of an approved type of "megger." Airfield lighting cables shall be tested in accordance with Item L-108 Installation of Underground Cable for Airports.

The tests shall be performed and recorded in the presence of the COTR and the test results shall be placed in the O&M manuals. All wires in conduit that are shorted or unintentionally grounded shall be replaced.

Take readings of voltage and amperage at building main disconnect switch and at main for each panel, at primary side of each lighting transformer and at the end of the longest branch circuit at each panel. The above readings shall be taken (1) “no load” conditions and (2) at “full load” conditions with all equipment using electricity. Tabulate readings, complete “Voltage and Amperage Readings/Tabulated Data” form (see Appendix A, Figure 3) and submit in the O&M manuals.

Page 245: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

DEMONSTRATIONS, TESTS AND PERFORMANCE VERIFICATION L-131 - 3

The resistance between ground and absolute earth shall be measured by the Contractor before equipment is placed in operation. Record data on the Ground Test Information form contained in Appendix A, Figure 4. All ground rods shall be tested.

Perform such tests as required by authorities having jurisdiction over the site, or other tests/inspections as required by other sections of this specification.

There are no approved "repair" procedures for items that have failed testing other than complete replacement. Any other corrective measures shall be approved by the COTR. The addition of ground rod sections to the ground rods shall be considered replacement for this item.

3.3 CORRECTION OF ERRORS. The Contractor shall immediately correct any errors or omissions in his work which are discovered during testing. This shall include but not be limited to, improper phasing resulting in reverse rotation, misinterpretations, incomplete grounding, damaged equipment or materials, or incomplete work the Contractor has already verified as being complete. The Contractor shall immediately replace, repair, or complete these errors and omissions as soon as they are brought to his attention, even if this requires disruption of his scheduled construction activities or work on an overtime basis. Failure to take immediate action or an excessive number of errors or omissions shall make the Contractor liable for the time lost by the Authority's operating forces, and any other personnel.

PART 4 - METHOD OF MEASUREMENT

4.1 The items described in this section are incidental to other sections and shall not be measured for payment.

PART 5 - BASIS OF PAYMENT

5.1 No direct payment shall be made for the work described in this section. The work described in this section is incidental to other items and shall be paid for in the respective bid item of which it is a component part.

Page 246: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

DEMONSTRATIONS, TESTS AND PERFORMANCE VERIFICATION L-131 - 4

APPENDIX A, FIGURE 1

CHECK-OUT MEMO

This form shall be completed and a copy provided to the Authority at the Authority's Performance Verification and Demonstration meeting. A copy shall also be included in the specification section of the O & M manual for the equipment checked.

Project Name: Type of Equipment Checked: Equipment Number: Name of Manufacturer:

Signature below by the manufacturer's authorized representative signifies that the equipment has been satisfactorily tested and checked out on the job by the manufacturer.

1. The attached Test Data and Performance Verification information was used to evaluate the equipment installation and operation.

2. The equipment is properly installed, has been tested by the manufacturer's authorized representative, and is operating satisfactorily in accordance with all requirements, except for items noted below.*

3. Written operating and maintenance information has been presented to the Contractor, and gone over with him in detail.

4. Sufficient copies of all applicable operating and maintenance information, parts lists, lubrication checklists, and warranties have been furnished to the Contractor for insertion in the Operating and Maintenance Manuals.

Checked By: (Print or Type Name of Manufacturer's Representative)

(Address and Phone No. of Representative)

(Signature and Title of Representative)

(Date Checked)

Witnessed By: (Signature and Title of Contractor Representative)

* Exceptions noted at time of check-out (use additional page if necessary):

Page 247: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

DEMONSTRATIONS, TESTS AND PERFORMANCE VERIFICATION L-131 - 5

APPENDIX A, FIGURE 2

PERFORMANCE VERIFICATION AND DEMONSTRATION TO AUTHORITY

This form verifies that the Authority has been given a demonstration of the proper operation on the equipment or systems noted below:

Project Name: Specification Division Number and Name: Equipment/System Demonstrated:

Along with a complete demonstration of the equipment/system, these items have been reviewed at this demonstration and shall be included in the O&M manuals, under the appropriate specification section:

1) Written operating instructions.

2) Test data and performance verification information as required by the installer and/or manufacturer.

3) Maintenance information published by manufacturer or equipment.

4) Check-out Memo signed by manufacturer's representative.

5) Printed warranties by manufacturer of equipment.

6) Explanation of the warranty/guarantee on the system.

7) Prints showing actual "As Built" conditions.

(Name of Contractor)

(Signature, Title, Date)

(Name of Subcontractor)

(Signature, Title, Date)

Demonstration of the system/equipment in operation and of the maintenance procedures has been successfully completed.

AUTHORITY

(Signature, Date)

(Authority's Department)

Page 248: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

DEMONSTRATIONS, TESTS AND PERFORMANCE VERIFICATION L-131 - 6

APPENDIX A, FIGURE 3

VOLTAGE AND AMPERAGE READINGS/TABULATED DATA

This form may be used to record voltage and amperage readings (within the panel and from the farthest point, please check the appropriate item below). Copy of this completed form shall be included in the specification section of the O&M manual for the equipment from which readings are taken. Project Name: Specification Division Number and Name: Switchgear/Panel Number: Readings taken within panel: from farthest point:

Full Load Amperage Readings:

Date: Time:

Phase: A B

C N

Full Load Voltage Readings:

Date: Time:

Phase: A to N A to B

B to N A to C

C to N B to C

No Load Voltage Readings:

Date: Time:

Phase: A to N A to B

B to N A to C

C to N B to C

Contractor's Representative:

Engineer's Representative:

Authority's Representative:

Page 249: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

DEMONSTRATIONS, TESTS AND PERFORMANCE VERIFICATION L-131 - 7

APPENDIX A, FIGURE 4

GROUND TEST INFORMATION

GROUND LOCATION:

PRIOR TO CONNECTION TO SYSTEM:

GROUND: (OHMS)

WEATHER CONDITIONS FOR PREVIOUS WEEK:

AFTER CONNECTION TO SYSTEM:

GROUND: (OHMS)

CONTRACTOR'S REPRESENTATIVE:

DATE:

Page 250: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

DEMONSTRATIONS, TESTS AND PERFORMANCE VERIFICATION L-131 - 8

APPENDIX A, FIGURE 5

MOTOR TEST INFORMATION NOT USED

Project Name: Description of Motor: Checked By: Date Checked: a) Name and Identifying Mark of Motor: b) Manufacturer: c) Model Number: d) Serial Number: e) RPM: f) Frame Size: g) Code Letter: h) Horsepower: i) Nameplate Voltage and Phase: j) Nameplate Amps: k) Actual Voltage: l) Actual Amps: m) Starter Manufacturer: n) Starter Size: o) Heater Size, Catalog No. and AMP Rating: p) Manufacturer of Dual-Element Fuse: q) Amp Rating of Fuse: r) Power Factor:

(Signature of Checker)

(Print or Type Name of Checker)

(Company Name of Checker)

(Signature of Contractor Representative)

(Print or Type Name of Contractor Representative)

(Company Name of Contractor Representative)

Page 251: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

DEMONSTRATIONS, TESTS AND PERFORMANCE VERIFICATION L-131 - 9

APPENDIX A, FIGURE 6

CABLE INSULATION RESISTANCE TEST RECORD

Circuit Description:

Date: Time:

Phase A to Ground Megohms

Phase B to Ground Megohms

Phase C to Ground Megohms

Neutral to Ground Megohms

Phase A to B Megohms Phase A to Neutral Megohms

Phase A to C Megohms Phase B to Neutral Megohms

Phase B to C Megohms Phase C to Neutral Megohms

Weather Conditions:

Temperature:

Circuit Condition Prior to Test:

Tested By: Date:

Witnessed By:

Authority's Authorized Representative:

Date:

END OF ITEM L-131

Page 252: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final
Page 253: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

STORM WATER POLLUTION PREVENTION 312514 - 1

SECTION 31 25 14 - STORM WATER POLLUTION PREVENTION

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings, Contract and Special Provisions, Supplementary Conditions, latest version of Virginia Erosion and Sediment Control Handbook and other Division-01 Specifications apply to this Section.

1.2 SUMMARY

A. This Section includes preparation for and submitting for approval for a Storm Water Pollution Prevention Plan (SPPP).

1. Provisions for furnishing, installing and removal of silt fence, filter boxes, storm drain inlet protection, straw bale barriers, construction entrances, sediment traps, diversion berm, dust control and other erosion control measures during construction, and temporary and permanent soil stabilization measures, as noted on the contract plans and in the approved SPPP. All measures and practices shall be in accordance with the latest version of the Virginia Erosion and Sediment Control Handbook and for preventing contamination of storm water from construction activities in accordance with the Commonwealth Of Virginia Regulation 9VAC 25-180 (i.e., temporary fuel storage, fueling operations, equipment maintenance, hazardous material and waste handling, good housekeeping practices, etc.).

B. Related Sections 1. Division 01 Section “Quality Requirements” for quality issues.

1.3 DEFINITIONS

A. CWA- Clean Water Act means the law passed by the Congress of the United States in 1972 controlling the Discharge of Pollutants into the Nation's waterways.

B. BMP- Best Management Practices are defined as any one or group of management practices, activities, policies, equipment, and structures that will: prevent pollutants from entering the environment, minimize pollutants from entering the environment, and mitigate, reduce, and treat prior to the pollutant entering the environment.

C. NPDES- National Pollutant Discharge Elimination System is the national program for issuing, modifying, revoking, reissuing, terminating, monitoring and enforcing permits pursuant to sections 402, 318, and 405 of the CWA.

D. VDEQ- Virginia Department of Environmental Quality is the agency of the Commonwealth of Virginia that manages the Commonwealth of Virginia's environmental regulations.

Page 254: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

STORM WATER POLLUTION PREVENTION 312514 - 2

E. VPDES- Virginia Pollutant Discharge Elimination System is the Commonwealth of Virginia program and regulations that describe the proper management of discharges of pollutants into the waters of the Commonwealth

F. DCR- The Commonwealth of Virginia Department of Conservation and Recreation, Division of Soil and Water Conservation, regulates land disturbing activities and erosion and sedimentation compliance.

1.4 Submittals

A. Storm water Pollution Prevention Plan (SPPP) - Prepare and submit for written approval by the Authority in accordance with the information provided below. Do not initiate ground-disturbing activities until the Authority has approved the SPPP. In addition, the SPPP will serve as the Soil Erosion and Sediment Control Plan required as a condition of the Authority's issuance of a Construction Permit by the Authority's Building Codes Department. Issuance of this Construction Permit is required prior to initiation of any project construction.

B. The SPPP may utilize plans, details, notes and other information provided in the construction documents, however, such information shall not, in itself, be construed to meet the requirements of this Section. Provide additional details to ensure that the SPPP accurately reflects means and methods for construction.

C. Prepare the SPPP on regular 8 ½ X 11 inch paper. Include attachments of the plans showing locations of erosion and sediment control devices and BMPs. Submit four bound copies to the COTR for review and approval.

D. The Contractor shall apply and receive permit coverage under the Construction General Permit (CGP) prior to starting land disturbing activities. The Contractor shall complete and submit the appropriate EPA NPDES permitting Authority a Notice of Intent (NOI) Form. To discontinue permit coverage, the Contractor shall complete and submit the appropriate EPA NPDES permitting Authority a Notice of Termination (NOT) Form upon satisfying the appropriate permit conditions described in the CGP.

E. Submit the name, and a copy of the certificate of competence issued by the Department of Conservation and Recreation for the person in charge of and responsible for carrying out the land-disturbing activity prior to conducting any land-disturbing activities.

F. Prepare the SPPP narrative and associated drawings in accordance with the following outline:

1. Site Description: A detailed description of the construction activities, physical features of the site, and other pertinent information shall be included in this Section.

a. A description of the nature of the construction activities; b. A description of the intended sequence of major activities which disturb soils for

major portions of the site (e.g. grubbing, excavation, grading); c. Estimate of the total area of land disturbing activities. Land disturbing areas

greater than 2,500 square feet require the implementation and enforcement of a SPPP.

d. Describe the quality of any discharge water from the site;

Page 255: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

STORM WATER POLLUTION PREVENTION 312514 - 3

e. A description of the existing vegetative cover at the site, include an estimate of the total buffer area that is covered by the vegetation before construction activities commence.

f. The name of the receiving water(s), their tributaries, and the ultimate receiving water(s). A description of the aerial extent of wetlands present at the site and other sensitive habitats present on site describe measures that will be used to protect wetlands.

g. Include in the plan a schedule of the planned start and completion of construction activities, major grading activities, and other activities that may require stabilization measures to be initiated at the site.

2. Potential Pollution Sources:

a. Describe potential pollution sources. Description should include, but not be limited to, the following:

1) Vehicle Fueling: A description of the location and number of all above ground storage tanks (ASTs) and any storage containers that will be used for the purpose of fueling vehicles or storing any materials used during construction activities (indicate location on the site map).

2) Storage Tanks: ASTs storing regulated substances and greater than 660 gallons shall be registered with the Department of Environmental Quality. All ASTs shall be properly equipped and follow the AST requirements. For example, requirements include that ASTs be double walled or have 110% secondary containment devices that will not collect rainwater. Tanks shall have spill containment buckets and be properly labeled, etc. Earthen berms shall not be permitted.

3) Materials Storage: A description of the storage location and a minimum quantity of all hazardous and non-hazardous materials that might pollute storm water. Pollutants such as, but not limited to, paints, solvents, hydraulic fluids, engine oil, form oil, etc. that will be used during the course of construction activities. All containers of materials of any size that are used on site and their associated secondary containment shall be covered to prevent rainwater from coming in contact with the containers. Earthen berms shall not be permitted. All drums and containers shall be removed from the site as they become empty.

4) Sanitary Waste Facility: A description of the location and the number of sanitary waste facilities (e.g. portable chemical toilets) and method of disposal for the subject waste during the course of construction activities on site.

5) Equipment Maintenance: A detailed description of how and where equipment will be maintained. This shall include fluid changes, servicing, breakdowns, etc. The plan shall provide a standard operating procedure that shall be used for the protection of the environment while maintaining the equipment.

6) The SPPP shall include a drum and container management plan. The plan shall describe the methods and location for the containment, protection, and storage of all solvents, chemicals, petroleum products, and all toxic material as defined by the EPA brought on site. All drums and containers shall be stored within a secondary containment system and shall be covered to prevent rainwater from entering the secondary containment.

Page 256: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

STORM WATER POLLUTION PREVENTION 312514 - 4

3. Best Management Practices (BMPs) And Control Measures. The purpose of this Section is to identify all appropriate BMPs and control measures that shall be implemented at the construction site. This Section of the plan shall clearly describe the construction activities in sequence and their associated BMPS, control measures, and Erosion and Sediment (E&S) controls that are applicable. This Section shall indicate the timing to achieve the above-referenced sequencing relative to the installation of BMPs, E&S, and the control measures.

a. The components of this Section of the plan shall, at a minimum, include but not be limited to the following:

1) Stabilization Practices: All stabilization practices, including interim and permanent stabilization measures as well as specific scheduling of the Implementation of the practices, shall be included in this Section. Where possible, this portion of the plan shall describe all existing vegetation that is preserved for the purpose of site stabilization. Stabilization measures include, but are not limited to the following:

a) Vegetative buffer strips b) Sod stabilization c) Geotextile d) Mulching e) Temporary Seeding f) Permanent Seeding g) Protection of trees h) Preservation of mature vegetation i) Other measures/stabilization practices

2) Structural BMPS: This Section shall adequately describe the structural BMPs and practices that will divert and mitigate storm water runoff from soils, sediments, exposed materials, ASTs, and containers of hazardous/non-hazardous materials. Structural BMPs include, but are not limited to the following list:

a) Silt fences b) Earth dikes c) Drainage swales d) Sediment traps e) Subsurface drains f) Secondary containment for ASTs and containers g) Pipe slope drains h) Coverage for ASTs and containers i) Level spreaders j) Storm drain inlet protection k) Reinforced soil retaining systems l) Rock outlet protection/wheel washers m) Gabions n) Construction rock entrance o) Temporary or permanent sediment basins p) Other BMPs and structural controls.

Page 257: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

STORM WATER POLLUTION PREVENTION 312514 - 5

3) The installation of these structural BMPs may be subject to the CWA Section 404 "Permitting Requirements". Be responsible for determination whether the above-permitting requirements apply to any of the structural BMPs.

4) Provide wheel washers and construction rock entrances for all projects where constructions traffic enters or exits paved surfaces. Be responsible for ensuring that all wheel washers and construction rock entrances are designed and constructed to adequately meet the expected construction traffic demand.

5) Temporary or Permanent Sediment Basins

a) If the project site involves common drainage areas that serve 3 acres or more of disturbed area(s), a temporary or permanent sediment basin is required. Such a basin shall provide 134 cubic feet of storage per acre drained. Where 134 cubic feet of storage per acre drained or equivalent is not attainable due to site constraints, smaller sediment basins and sediment traps shall be used as approved by the COTR on a case-by-case basis.

b) To prevent the movement and erosion of soils, structural measures should be placed on all upland areas.

4. `Operational Practices (Good Housekeeping Practices). This Section shall include measures and BMPs including good housekeeping practices that address the following sources of pollution:

a. The plan shall contain measures that prevent trash, innocuous solid materials, building materials, garbage, and debris from entering the Authority's storm sewer system or directly into a stream or waterway.

b. Provide a daily program of vacuum or hand sweeping or other acceptable means of cleaning sediments that are tracked or transported onto the public roads from the construction sites shall be implemented. The roads may be washed only after the sediments have been removed.

5. Inspection And Maintenance of BMPs

a. Provide a schedule of inspection of all structural BMPs, the necessary maintenance and corrective action to correct all discrepancies found on site. Designate qualified personnel that have adequate knowledge of E&S requirements and storm water management and pollution prevention requirements, to inspect all structural control measures and BMPs at "least every seven calendar days and within 24 hours of the end of a storm event that is .5 inches or greater."

b. At a minimum develop a checklist for these inspections that conforms to the inspection checklist of Appendix I. Areas where final stabilization has been established need only be inspected once every month. Provide the completed inspection checklist and a report summarizing the corrective actions taken by the contractor to the COTR according to the following schedule of frequencies:

c. Every seven calendar days: Under the normal circumstances. d. Every 24 hours: After a rainfall of 0.5 inches or greater, of intensity. e. Every 30 days: for the areas where final stabilization has been accomplished. f. Correct any and all discrepancies immediately upon discovery. The SPPP shall be

revised as necessary to reflect any modifications to strengthen the BMPs and other

Page 258: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

STORM WATER POLLUTION PREVENTION 312514 - 6

structural controls in order to address the discrepancies. The above inspections and findings shall be subject to Authority field verification. Be responsible for responding to all regulatory inquiries from the Virginia Department of Environmental Quality-Water Division (VDEQ-Water), Virginia Department of Conservation and Recreation (DCR), and the Environmental Protection Agency (EPA) Region III. Be responsible for addressing the outcome of all compliance monitoring inspections conducted by the above regulatory agencies. Take all corrective actions as required by VDEQ-Water, DCR or EPA Region III.

6. Non-Storm water Discharge. This SPPP is for the sole purpose of preventing pollution associated with storm water runoff (Act of God: rain, snow, etc.). Plan shall identify all non-storm water components, process waste water discharges, and any other non-storm water influent that may exist in this particular construction site. Plan shall ensure that all of the above non-storm water discharges are appropriately eliminated, permitted or addressed through other acceptable regulatory permitting mechanisms.

7. Detailed Composite SPPP Map. Prepare the following:

a. Drainage pattern and approximate slopes anticipated after completing major grading activities on site

b. Soil disturbance areas c. Location of all Best Management Practices (BMPs), structural controls, non-

structural controls, good housekeeping practices (GHP) and other erosion and sediment (E&S) control measures to be used during the course of construction activities

d. Locations where stabilization is expected to be used, including the types of vegetative cover which will be employed on site

e. Location of all receiving waters, including their tributaries and the ultimate receiving waters (including wetlands/sensitive habitats)

f. Location of all points of discharge to existing storm sewers and outfalls g. Existing and planned paved areas, impervious surfaces, and buildings h. Location of all post-construction BMPs and Storm water management practices

that will address the long-term water quality improvement needs for the site, if applicable.

i. Location of any fuel storage, materials storage and sanitary waste and other potential pollution sources and their associated BMPs. shall be reflected on the site map.

j. Two site maps shall be developed, one indicating pre-construction and during construction site conditions and the second indicating final site conditions. Maps shall be to the same scale.

1.5 Quality Assurance

A. Prepare and submit the SPPP with input from each subcontractor.

Page 259: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

STORM WATER POLLUTION PREVENTION 312514 - 7

PART 2 - PRODUCTS

2.1 General

A. Provide erosion and sediment control devices and products as indicated, in accordance with the SPPP and in accordance with the latest updated version of the Virginia Erosion and Sediment Control Handbook.

PART 3 - EXECUTION

3.1 Implementation

A. Implement and maintain the approved SPPP throughout the life of the contract in accordance with provisions of the Virginia Erosion and Sediment Control Handbook and applicable contract documents.

B. Exercise every reasonable precaution, including temporary and permanent measures, throughout the duration of the project to control erosion and prevent or minimize pollution of rivers, streams, lakes and other receiving waters. Apply siltation and stabilization control measures to material, subject to erosion, exposed by any activity associated with construction including but not limited to local material sources, stockpiles, disposal areas, and haul roads.

C. Initiate stabilization measures as soon as practicable in portions of the site where construction activities have temporarily or permanently ceased but no later than 14 days after the construction activities have temporarily or permanently ceased. Except as provided in the following paragraphs:

1. If snow cover and or severe weather conditions preclude initiation of the stabilization measures by the 14th day after construction activities have ceased, either temporarily or permanently, the stabilization practices shall be initiated as soon as practicable.

2. If construction activities resume on a portion of the site within 21 days from the date that construction activities have temporarily ceased, then stabilization practices need not be initiated on that particular portion of the site by the 14th day after construction activities have temporarily ceased.

D. Be solely responsible for complying with the soil erosion, sedimentation control and good housekeeping requirements of this Contract, and for otherwise preventing contamination of storm water from construction activities. Be solely responsible for any and all fines, penalties or damage that result from the Contractor’s failure to comply.

3.2 Erosion and Siltation Control:

A. Control erosion and siltation through the use of the devices and measures specified herein, in the approved SPPP or as is otherwise necessary. The Authority reserves the right to require other temporary measures not specifically described herein to correct an erosion or siltation condition.

Page 260: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

STORM WATER POLLUTION PREVENTION 312514 - 8

B. Maintenance: Maintain erosion and siltation control devices and measures in a functional condition at all times. Inspect temporary and permanent erosion and sedimentation control measures after each rainfall and at least daily during periods of prolonged rainfall. Correct deficiencies immediately. Make a daily review of the location of erosion and sediment control devices to ensure that they are properly located for effectiveness. Where deficiencies exist, make corrections immediately as approved or directed by the COTR.

PART 4 - CONTRACTOR’S QUALITY CONTROL

4.1 Field Quality Control

A. Conform to all applicable provisions of Division 01 Section “Quality Requirements". Be responsible for periodic inspections for conformance with the approved SPPP. The results of the periodic inspections shall be submitted to the COTR upon completion.

PART 5 - METHOD OF MEASUREMENT

5.1 Stormwater Pollution Prevent Plan shall be measured on a lump sum basis for payment.

PART 6 - BASIS OF PAYMENT

6.1 This item will be paid at the contract lump sum price, which shall be full compensation for installation, maintenance, removal, permit fees, quality control, and all other incidentals required for work associated with this item.

Payment will be made under:

Item 312514-5.1 – Stormwater Pollution Prevention Plan – per lump sum

Page 261: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

STORM WATER POLLUTION PREVENTION 312514 - 9

APPENDIX I

Page 262: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

STORM WATER POLLUTION PREVENTION 312514 - 10

SPPP INSPECTION CHECKLIST

BMP Proper Installation Yes, No. or

NA

Proper Operation Yes or No

Housekeeping Practices

Good-Poor

Potential Hazard Yes or

No

Discharge: Storm water Non-storm

water

Effectiveness

of BMP

Observations

Comme

nts

1. Drainage Swale

2. Gabion

3. Silt Fence

4. Dry Pond

5. Cattle Grate

6. Earth Dike

7. Sediment Trap

8. Hay Bale

9. Subsurface Drains

10. Pipe Slope Drains

11. Level Spreaders

12. Storm Drain Inlet Protection

13. Reinforced Soil Retaining Basins

Page 263: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

STORM WATER POLLUTION PREVENTION 312514 - 11

SPPP INSPECTION CHECKLIST

BMP Proper Installation Yes, No. or

NA

Proper Operation Yes or No

Housekeeping Practices

Good-Poor

Potential Hazard Yes or

No

Discharge: Storm water Non-storm

water

Effectiveness

of BMP

Observations

Comments

14. Temporary or Permanent Sediment Basins

15. Construction Rock Entrance

16. Rock Outlet Protection

17. Secondary Containment for all ASTs

18. Evidence of oil, fuel or other material spills or releases on site

19. Other BMPs

20. Other BMPs

Page 264: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

STORM WATER POLLUTION PREVENTION 312514 - 12

Please list any discrepancies or items that are not in compliance in the space provided below.

Please list the corrective actions necessary to abate the above-listed discrepancies.

Note: All corrective actions must take place within 7 days of the discovery of the above discrepancies and non-compliance item(s). Inspector: Signature: Date: ________________

Page 265: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

STORM WATER POLLUTION PREVENTION 312514 - 13

APPENDIX II

Page 266: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

STORM WATER POLLUTION PREVENTION 312514 - 14

Metropolitan Washington Airports Authority

Notice of Project Termination For

Storm water Discharges from Construction Activities Note: This form shall be completed by the construction contractors upon final stabilization of the site,

upon elimination of all storm water, or when the construction contractor has changed within the same construction project. The contractor shall submit a completed copy of this form to the Authority, at the address provided below and a copy to PMC's Resident Engineer within 30 days after final stabilization has been achieved or when it is no longer the construction contractor for this project. (An officer of the company shall sign this certification)

Completed form shall be submitted to: Manager, Building Codes/Environmental Branch Engineering Division Ronald Reagan Washington National Airport Washington, D.C. 20001 Copy to: Parsons Management Consultants For DCA Projects Hangar 6 Construction Management Program Ronald Reagan Washington National Airport Washington, D.C. 20001 Attn: Project's Resident Engineer For IAD Projects Parsons Management Consultants 23835 Wind Sock Drive Chantilly, VA 20166 Attn: Project’s Resident Engineer

Page 267: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

STORM WATER POLLUTION PREVENTION 31 25 14 - 15

Contract Number: Contractor Information: Contractor's name and mailing address: Subcontractor(s) name and mailing address:

Location of Construction Site: Project Name Address City State Zip Code ____________ Latitude Longitude ______________________ If there is a change in the contractor(s) please provide the new contractor's information here:

Certification: "I certify under penalty of law that disturbed soils at the identified project have been finally

stabilized and temporary erosion and sediment control measures have been removed or will be removed at an appropriate time and that all storm water discharges associated with construction activities in this project have been eliminated, or that I am no longer the contractor for this construction site."

Print name: Title: Signature: Date: (This certification shall be signed by an officer of the company)

Page 268: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

STORM WATER POLLUTION PREVENTION 31 25 14 - 16

APPENDIX III

Page 269: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 RUNWAY 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

STORM WATER POLLUTION PREVENTION 31 25 14 - 17

METROPOLITAN WASHINGTON AIRPORTS AUTHORITY WASHINGTON DULLES INTERNATIONAL AIRPORT

HAZARDOUS MATERIALS SPILL NOTIFICATION CHECKLIST

Note: This checklist shall be completed by all tenants of Washington Dulles International Airport (IAD) in the event of a hazardous material spill (under CERCLA, CWA, CAA, TSCA and/or a release of hazardous waste under RCRA). It is the responsibility of the tenants to notify all pertinent regulatory agencies within the time frame prescribed under the respective statutes and regulations.

1. Tenant Name: 2. Facility location within IAD where spill occurred: 3. Facility Environmental Manager, Foreman, or person in charge: 4. Time and date of release: 5. Amount of release material: 6. Description of how the release occurred and whether material reached a floor drain (if

this situation occurred, describe amount of material that entered drain): 7. Type of material released (include common and chemical name; attach MSDS and/or

Waste Manifest): 8. In the event of a release, verbal notification to IAD Fire Department and IAD

Environmental Coordinator must be made immediately as follows: Fire Department: (703) 572-2970 IAD Government Programs Engineer (703) 572-0210

END OF SECTION 312514

Page 270: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final
Page 271: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 R/W 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

BLAST PROTECTION FENCE 323113.80-1

SECTION 32 31 11.80 - BLAST PROTECTION FENCE PART 1 – DESCRIPTION

1.1 This item shall consist of designing, fabricating and installing a blast protection fence (jet- blast bar-rier system) of the specified heights complete, including structure, foundations, and other items required for proper installation, designed in accordance with the plans and specifications, or as directed by the COTR. 1.2 Related construction specified in other sections includes. Item P-152 “Excavation and Embanke-ment”, Item P-610 “Structural Concrete”, Item L-100 “General Provisions and Requirements for Electric-al Work”, Item L-108 “Installation of Underground Cable for Airports”, L-110 “Installation of Airport Underground Electrical Duct”, and Item L-121 “Obstruction Lights”.

PART 2 - GENERAL

2.1 DESIGN CRITERIA. Blast protection fence shall be designed in accordance with the American As-sociation of State Highway and Transportation Officials (AASHTO) "Standard Specifications for Struc-tural Supports for Highway Signs, Luminaires and Traffic Signals," Fifth Edition, and American Institute of Steel Construction (AISC) " Manual of Steel Construction, Allowable Stress Design," Thirteenth Edi-tion, for the loads indicated below:

a. In the direction of applied jet blast force, as indicated on the Contract Drawings, the assem-blies shall be designed to resist a 130 mph jet blast velocity. b. In the other direction, the assemblies shall be designed to resist the following loading condi-tions or the combination of the loadings whichever develops the greatest stress:

(1) A wind speed of 100 mph (3 second gust) in accordance with the 2010 Authority De-sign Manual. (2) The impact of moving vehicles such as GSE Equipment and delivery trucks.

2.2 SUBMITTAL REQUIREMENTS. The Contractor shall submit the following items to the COTR for approval:

a. Complete shop drawings including design calculations. Calculations shall bear the stamp of a Professional Engineer registered in the Commonwealth of Virginia. b. Material Certificates certifying that all materials and components of the Blast Protection Fence system conform to the requirements of the plans and specifications. c. Manufacturer’s Qualifications per section 2.6.

2.3 PRODUCTS. The Blast Protection Fence system furnished shall be a vertical type system with a maximum above grade footprint (width) of 18 inches. The product shall be designed in accordance with

Page 272: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 R/W 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

BLAST PROTECTION FENCE 323113.80-2

the requirements of Section 2.1 above and closely conform to the type and dimensions shown on the con-tract plans and specifications. 2.4 MATERIALS. Materials for the Blast Protection Fence system shall conform to the following:

a. Concrete shall have a minimum compressive strength of 4,000 psi at 28 days unless otherwise noted. b. Reinforcing bars shall conform to ASTM A615, Grade 60. c. Post Base Plates and Gussets shall be fabricated from structural steel plate per ASTM A36. d. End and Corner Posts shall be fabricated from structural steel tubing per ASTM A500, Grade B. e. Intermediate Posts shall be fabricated from structural steel I-beam per ASTM A36. f. Horizontal Angle Braces and Tabs shall be fabricated from structural steel angle per ASTM A36. g. Vertical Pipe Stiffeners shall be fabricated from Schedule 40 steel pipe per ASTM A53, Type E, Grade B, Galvanized, supplied with End Caps. h. Vertical Pipe Stiffeners shall be fabricated from Schedule 40 steel pipe per ASTM A53, Type E, Grade B, Galvanized, supplied with End Caps. i. Anchor Bolts shall conform to ASTM A449. j. Structural Bolts shall conform to ASTM A325. k. Nuts shall conform ASTM A563, Grade DH. 1. Lock Washers shall conform to ANSI B18-21-1. m. Flat Washers shall conform to ASTM F436. n. Welding shall be conducted in accordance with American Welding Society (AWS) D1.1 Structural Welding Code for Steel, 2006 Edition. Welding electrodes shall conform to E70XX, or approved equal. o. Galvanized Coatings: All structural steel materials shall be galvanized after fabrication in accor-dance with ASTM Al23, and all, hardware shall be galvanized after fabrication in accordance with ASTM A153.

2.5 SUBSTITUTION. Substitution for the specified system for the blast fence shall be subject to the ap-proval of the airport and the COTR. Submittal of a proposed substitution shall be accompanied by com-plete design calculations including the foundations prepared by a Professional Engineer registered in the Commonwealth of Virginia. 2.6 MINIMUM QUALIFICATIONS. The fence manufacturer shall have a minimum of 5 years expe-rience designing and manufacturing blast protection fences. The manufacturer’s fence shall have been

Page 273: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 R/W 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

BLAST PROTECTION FENCE 323113.80-3

installed at a minimum of 3 medium or large hub commercial airports over the past 5 years serving as jet-blast protection. Submit the airports along with references (name, phone number and email address) in the maintenance or operations departments for the COTR to contact.

PART 3 - CONSTRUCTION METHODS 3.1 GENERAL. The Contractor shall perform all work necessary to provide a completely assembled and properly installed blast protection fence in the location and alignment as indicated on the Contract Draw-ings. Blast protection fence shall be fabricated by an established experienced bonafide manufacturer of blast fences. The contractor shall use erectors approved by the manufacturer. 3.2 FOUNDATIONS. Excavation shall extend to the depth shown on the plans. Surrounding soil shall remain undisturbed using methods approved by the COTR. Reinforcing Bars shall be placed in the loca-tions shown on the plans. Anchor Bolts shall be located to match the specified bolt configuration of the post base plates. The projection height of each anchor bolt shall be 3-1/2 in ± 1/2 in (89 mm ± 13 mm). Concrete shall be placed and consolidated in accordance with ACI standard procedures. Top surface of all foundations shall be smooth, level, and at the same elevation, ± 1/2 in (13 mm). Concrete shall cure for a minimum of seven (7) days prior to backfilling. All excavation adjacent to foundations shall be backfilled and compacted to the satisfaction of the COTR prior to erection of the superstructure. For installation of foundations in existing pavement areas, the pavement shall be sawcut to the required width and shall be repaired after foundation installation. All costs related to sawcutting, excavation and subsequent pavement repair will not be paid separately and shall be considered incidental to the blast fence installation. 3.3 POSTS. Posts shall be positioned plumb on top of the foundations. Flat washers shall be placed on each anchor bolt on top of the base plate. All base plate nuts shall be tightened on to the anchor bolts in accordance with American Institute of Steel Construction (AISC) Turn-of Nut Tightening Methods. 3.4 HORIZONTAL ANGLE BRACES. Horizontal Angle Braces shall be positioned level at their proper locations as shown on the plans, and secured with bolts, lock washers and nuts. All nuts shall be tightened in accordance with American Institute of Steel Construction (AISC) Turn-of-Nut Tightening Methods. 3.5 BARRIER FABRIC AND VERTICAL PIPE STIFFENERS. Barrier Fabric and Vertical Pipe Stif-feners shall be installed starting at the top of the barrier at an End 'or Corner Post. Fabric panels shall be held in position while a Vertical Pipe Stiffener is threaded down through holes in the Horizontal Angle Braces and corrugations in the fabric, one fabric panel at a time. Once one end of a fabric panel is se-cured, -the fabric shall be pulled taut while the next adjacent Vertical Pipe Stiffener is threaded down through the closest corrugations in the fabric. Fabric shall remain taut throughout the barrier system with no sags permitted. Joints between fabric panels shall occur only at a post. Excess fabric remaining at the end of a run shall be cut off leaving sufficient material for a solid connection to the last Vertical Pipe Stif-fener. Fabric installation shall progress down the barrier until all Vertical Pipe Stiffeners reach the bottom Angle Braces. Then, Pipe Caps shall be secured to both the top and bottom of each Vertical Pipe Stiffen-er.

PART 4 – QUALITY CONTROL, CERTIFICATION AND GUARANTEE

Page 274: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 R/W 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

BLAST PROTECTION FENCE 323113.80-4

4.1 FIELD QUALITY CONTROL

A. Division 1 Section "Quality Requirements" specifies the general requirements for the Contrac-

tor's Quality Control Program.

B. The following describes the minimum inspection and testing required in the Contractor's Quali-ty Control (CQC) Plan and Program for the work of this section and is for CQC only. The im-plementation of the Contractor Quality Control Program does not relieve the Contractor from the responsibility to provide the work in accordance with the Contract Documents, applicable codes, regulations, and governing authorities. The CQC Plan and Program shall include, but not be limited to, the recommendations of the selected fence manufacturer.

C. Testing Agency: The Contractor shall engage the services of the blast fence manufacturer’s technical support to ensure proper installation of the fence materials and hire a testing agency to ensure the requirements listed in P-152-4.1 and P-610-4.1 are met and produce a proper founda-tion for the blast fence.

D. Proceed with installation only after test results for previously completed work comply with re-quirements.

E. Special Inspections:

1. Special Inspections as defined by Section 1704 of IBC 2006 may be required by the building officials to secure approval of the work. The Special Inspections program shall be provided by others. The contractor shall provide the special inspections engineer free access to the work site.

4.2 The Contractor shall schedule a pre-work meeting before beginning any foundation work. Atten-dance at the pre-work meeting is required of the contractor and his subcontractors to discuss coordination, schedule and preparation to ensure the work is performed in a productive manner.

4.3 The Contractor shall furnish to the COTR, a manufacturer's written one-year guarantee on the

workmanship, materials, and installation; in addition, the guarantee shall warrant that the blast protection fence is free of structural defects and fatigue failures for a period of not less than five (5) years.

4.4 After the erection of blast protection fence has been completed, the Contractor shall submit to the

COTR a certification that the blast protection fence has been constructed in accordance with the approved design and it shall satisfactorily perform to the design function.

PART 5 - METHOD OF MEASUREMENT

Page 275: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final

RONALD REAGAN WASHINGTON NATIONAL AIRPORT DA1102 R/W 1-19 SAFETY AREA IMPROVEMENTS AND RUNWAY 1 HOLD APRON MODIFICATION TV-900 BLAST FENCE PACKAGE 19 JULY 2011

BLAST PROTECTION FENCE 323113.80-5

5.1 Blast protection fence of specified heights shall be measured by the linear foot of fence com-pleted and approved. Measurement will be along the top of the fence from center to center of posts.

PART 6 - BASIS OF PAYMENT

6.1 Payment for blast protection fence of specified heights shall be made at the contract unit price per linear foot. This price shall be full compensation for furnishing all materials/products and for all preparation, foundation, excavation, subgrade preparation, hauling, erection and installation; all required pavement removal and repair; all testing and record keeping; and for all labor, equip-ment, tools, and incidentals necessary to complete the item.

Payment will be made under:

Item 323113.80-5.1 Blast Protection Fence (10-Foot High) – per Linear Foot END OF ITEM 323113.80

Page 276: · PDF fileD. Maintain the construction operations affecting pedestrian, vehicular, or aircraft traffic movement from the beginning of construction operations until final