Light Rail Transit Improving mobility Easing congestion Strengthening our communities Central Corridor Metropolitan Council May 28, 2008

Transcript of - Light Rail Transit Improving mobility Easing congestion Strengthening our communities Central...

Page 1: - Light Rail Transit Improving mobility Easing congestion Strengthening our communities Central Corridor Metropolitan Council May 28, 2008.

-

Light Rail Transit

Improving mobility

Easingcongestion

Strengtheningour communities

Central Corridor

Metropolitan CouncilMay 28, 2008

Page 2: - Light Rail Transit Improving mobility Easing congestion Strengthening our communities Central Corridor Metropolitan Council May 28, 2008.

2

Today’s Agenda

• Washington Ave. Transit/ Pedestrian Mall Update

• U of M’s Northern Alignment Feasibility Study

• Northern Alignment Issues and Risks

Light Rail Transit

Central Corridor

Page 3: - Light Rail Transit Improving mobility Easing congestion Strengthening our communities Central Corridor Metropolitan Council May 28, 2008.

3

Washington Ave. Transit/Pedestrian Mall

Light Rail Transit

Central Corridor

• Mitigation Package Update

• Running Time and CEI calculation

• Adjustments to Cost and CEI

• Project Schedule/SDEIS Status

Page 4: - Light Rail Transit Improving mobility Easing congestion Strengthening our communities Central Corridor Metropolitan Council May 28, 2008.

4

Washington Ave. UpdateIssues Being Addressed in PELight Rail

Transit

Central Corridor

Traffic Impacts

Conducted four traffic studies that looked at intra-campus roads and surrounding roadways

Safety Concerns

Created transit/pedestrian mall

Removed 20,000 vehicles/day

Environmental Impacts

Analyzed electromagnetic impacts

Completed Phase I&II site analysis

Aesthetics Developed design criteria

Created concept design for transit/pedestrian mall

Page 5: - Light Rail Transit Improving mobility Easing congestion Strengthening our communities Central Corridor Metropolitan Council May 28, 2008.

5

Washington Ave. Transit/Pedestrian Mall Mitigation Package Update

Light Rail Transit

Central Corridor

Page 6: - Light Rail Transit Improving mobility Easing congestion Strengthening our communities Central Corridor Metropolitan Council May 28, 2008.

6

1

9A

9D

6E

6A

6C

6B

6D

7B

7C

7F

7E7D

7A

4

5

8A

9G9C

9E 9F

10

2B

2B

9B

11A&B

2A

2A

8B

3

Overview of Stakeholder-Identified Improvement Needs

3

Page 7: - Light Rail Transit Improving mobility Easing congestion Strengthening our communities Central Corridor Metropolitan Council May 28, 2008.

7

Stakeholder-Identified Improvement NeedsBase Project

CostCCLRT

Mitigation*Stake-holder

1. Washington Avenue Transit/Pedestrian Mall $11,100,000

2. Free Fare Zone Stadium Village to West Bank X

3. Granary Road - I35W to TH 280 X

4. U of M Fairview Hospital Loading Dock X

5. Traffic light improvements Wash. Ave. intersections $2,600,000

6. Intersections directly impacted by CCLRT $2,800,000

7. Intersections not directly impacted CCLRT X

8. East River Road/Harvard Street/Fulton Street $1,200,000 X

9. East Bank Campus Area Street Connections $5,100,000

10. Modify Huron Blvd/University/23rd/25th Aves. $4,300,000

11. Environmental Issues $4,400,000

12. Impact on Freeway System X

13. Signage and Wayfinding $20,000

14. Cedar Riverside Small Area Plan X

Total Central Corridor Mitigation Participation $6,900,000 $24,600,000 TBD* CCLRT Participation subject to FTA approval

Page 8: - Light Rail Transit Improving mobility Easing congestion Strengthening our communities Central Corridor Metropolitan Council May 28, 2008.

8

1

Washington Ave. Transit/Pedestrian Mall

Light Rail Transit

Central Corridor

Oak

OakCh

urc

hC

hu

rch

Un

ion

Un

ion

Har

vard

Har

vard

Wal

nu

tW

aln

ut

Ple

asan

tP

leas

ant

Page 9: - Light Rail Transit Improving mobility Easing congestion Strengthening our communities Central Corridor Metropolitan Council May 28, 2008.

9

Washington Ave. Transit/Pedestrian Mall

Passenger Rail HistoryLight Rail Transit

Central Corridor

Page 10: - Light Rail Transit Improving mobility Easing congestion Strengthening our communities Central Corridor Metropolitan Council May 28, 2008.

10

Washington Ave. Transit/Ped Mall ConceptLight Rail

Transit

Central Corridor

Graphic shows a two-block segment of the Washington Ave. Transit/Pedestrian Mall that is proposed to go from Pleasant Ave. to Walnut St.

Page 11: - Light Rail Transit Improving mobility Easing congestion Strengthening our communities Central Corridor Metropolitan Council May 28, 2008.

11

6A

6B

• Reduce backup @ Cedar & Riverside • Eliminate parking on east side of 20th• Provide additional approach lane

• 2nd WB right turn lane on Riverside• NB left turn on Cedar• Traffic signal detection• Re-time signal

Central Corridor Project Mitigation Package

West Bank Traffic ImprovementsLight Rail Transit

Central Corridor

1919thth

2020thth

Ced

ar

Ced

ar

Washington Ave.

Washington Ave.

Riverside

Riverside

6C

Page 12: - Light Rail Transit Improving mobility Easing congestion Strengthening our communities Central Corridor Metropolitan Council May 28, 2008.

12

Har

vard

Har

vard

Wal

nu

tW

aln

ut

Un

ion

Un

ion

Ple

asan

tP

leas

ant

Oak

Oak

Central Corridor Project Mitigation Package

East Bank Traffic ImprovementsLight Rail Transit

Central Corridor

9A9B

Install traffic signal and construct turn lanes

9D Stripe NB left turn lane andmodify signal phasing

9E 9F

Construct new segment and overlay existing

10

Modify intersection

5

Traffic signal improvements

9GInstall traffic signal and construct turn lanes

8A

6E 9C

Install traffic signals and construct turn lanes

•Install all way stop•Construct turn lanes•Resurface E. River Rd

Ch

urc

hC

hu

rch

6D Cromwell & Franklin Remove parking from north side of, peak hours

Page 13: - Light Rail Transit Improving mobility Easing congestion Strengthening our communities Central Corridor Metropolitan Council May 28, 2008.

13

Central Corridor Project Mitigation Package

Environmental IssuesLight Rail Transit

Central Corridor

11

1111

11

11

Oak

Oak

Ch

urc

hC

hu

rch

Un

ion

Un

ion

Har

vard

Har

vard

Wal

nu

tW

aln

ut

Ple

asan

tP

leas

ant

Page 14: - Light Rail Transit Improving mobility Easing congestion Strengthening our communities Central Corridor Metropolitan Council May 28, 2008.

14

Central Corridor Project Mitigation Package

Environmental Issues Light Rail Transit

Central Corridor

Locations of Sensitive Equipment

Page 15: - Light Rail Transit Improving mobility Easing congestion Strengthening our communities Central Corridor Metropolitan Council May 28, 2008.

15

Electromagnetic Technical SolutionsLight Rail

Transit

Central Corridor

Page 16: - Light Rail Transit Improving mobility Easing congestion Strengthening our communities Central Corridor Metropolitan Council May 28, 2008.

16

7B

7C

7F7E

7D

7A

4

2B

2B

2A

2A

8B

3

Stakeholder-Identified Improvements Outside of Project Scope & Budget

Light Rail Transit

Central Corridor

Page 17: - Light Rail Transit Improving mobility Easing congestion Strengthening our communities Central Corridor Metropolitan Council May 28, 2008.

17

Washington Ave. Transit/Pedestrian Mall Running Time & CEI Update

Light Rail Transit

Central Corridor

Page 18: - Light Rail Transit Improving mobility Easing congestion Strengthening our communities Central Corridor Metropolitan Council May 28, 2008.

18

Washington Ave. Transit/Pedestrian Mall

Running Time and CEI Update

Page 19: - Light Rail Transit Improving mobility Easing congestion Strengthening our communities Central Corridor Metropolitan Council May 28, 2008.

19

Washington Ave. Transit/Pedestrian Mall Running Time & CEI Update

• Identified 1300’ missing from travel time calculations

• Added into travel time model– Added 39 seconds to Washington

Ave. alignment travel time– Increased CEI to $24.39

Light Rail Transit

Central Corridor

Page 20: - Light Rail Transit Improving mobility Easing congestion Strengthening our communities Central Corridor Metropolitan Council May 28, 2008.

20

Washington Ave. Transit/Pedestrian Mall Cost and CEI Adjustments

Light Rail Transit

Central Corridor

Page 21: - Light Rail Transit Improving mobility Easing congestion Strengthening our communities Central Corridor Metropolitan Council May 28, 2008.

21

Washington Ave, Transit/Pedestrian Mall Cost and CEI Adjustments

Light Rail Transit

Central Corridor

Capital Cost Change CEI

$909 million = 23.80

$909 million Add 39 seconds to running time

24.39

$892 million Adjust costs to keep CEI under $24

23.98

Page 22: - Light Rail Transit Improving mobility Easing congestion Strengthening our communities Central Corridor Metropolitan Council May 28, 2008.

22

Washington Ave. Transit/Pedestrian Mall Project Schedule and SDEIS

Status

Light Rail Transit

Central Corridor

Page 23: - Light Rail Transit Improving mobility Easing congestion Strengthening our communities Central Corridor Metropolitan Council May 28, 2008.

23

Central Corridor LRT Project ScheduleCCLRT

Master Schedule

Start SDEIS environmental review July 9, 2007

Define Project Alignment and Elements Feb. 27, 2008

Complete environmental analysis, prepare SDEIS April 4, 2008

Provide final administrative draft SDEIS to FTA April 29, 2008

Receive SDEIS comments from FTA May 28, 2008

Publish SDEIS in Federal Register June 27, 2008

Hold Public Hearing July 21, 2008

Adopt Updated LPA by Met Council Aug. 27, 2008

Submit New Starts Application Sept. 5, 2008

Publish draft FEIS Jan. 11, 2009

FTA issues Record of Decision on FEIS Feb. 25, 2009

FTA approves project to move into Final Design May 6, 2009

Full Funding Grant Agreement Execution April 2, 2010

Major Construction Contract Awards May 2010

Page 24: - Light Rail Transit Improving mobility Easing congestion Strengthening our communities Central Corridor Metropolitan Council May 28, 2008.

24

Northern Alignment Outstanding

Risks & Issues

Light Rail Transit

Central Corridor

Page 25: - Light Rail Transit Improving mobility Easing congestion Strengthening our communities Central Corridor Metropolitan Council May 28, 2008.

25

Outstanding Issues: Site Contamination-West Bank

19th A

venu

e S

outh

Washington Avenue

1956

Gas Holder #5

Gas Holder #4

Pure Oil (Unocal) Site

Minneapolis Gas Works (Minnegasco)

Page 26: - Light Rail Transit Improving mobility Easing congestion Strengthening our communities Central Corridor Metropolitan Council May 28, 2008.

26

Former Gas Holder #4 State VIC Site

State Superfund Site

Outstanding Issues: Site Contamination-West Bank

Page 27: - Light Rail Transit Improving mobility Easing congestion Strengthening our communities Central Corridor Metropolitan Council May 28, 2008.

27

Outstanding Risks/Issues Site Contamination – East

Bank• Dinkytown railroad trench

• McLaughlin Gormley King – Pesticides – 17th Avenue & 5th Street

• Reichold Manufacturing– Chemicals– 23rd Avenue

Light Rail Transit

Central Corridor

Page 28: - Light Rail Transit Improving mobility Easing congestion Strengthening our communities Central Corridor Metropolitan Council May 28, 2008.

28

Outstanding Risks/Issues Site Contamination – East

BankLight Rail Transit

Central Corridor

Chem

icals

Pesticides

University Ave.

4 th St.

17th A

ve.

18th A

ve.

Railroad corridor

Page 29: - Light Rail Transit Improving mobility Easing congestion Strengthening our communities Central Corridor Metropolitan Council May 28, 2008.

29

Outstanding Risks/Issues Railroad Issues

• Right-of-way space/clearance for freight railroad, LRT, Granary Road & bike trail

• New Minnesota Commercial Rail Yard

• Multiple owners• Acquisition and operating

agreement• Insurance and indemnification

Light Rail Transit

Central Corridor

Page 30: - Light Rail Transit Improving mobility Easing congestion Strengthening our communities Central Corridor Metropolitan Council May 28, 2008.

30

Outstanding Issues: Freight Rail/Light Rail Proximity

Page 31: - Light Rail Transit Improving mobility Easing congestion Strengthening our communities Central Corridor Metropolitan Council May 28, 2008.

31

1414thth Avenue Avenue

University Avenue

Freight rail

Light rail

Future Granary Road

Outstanding Issues: Railroad Right-of-Way

Bike Trail

Light rail

Page 32: - Light Rail Transit Improving mobility Easing congestion Strengthening our communities Central Corridor Metropolitan Council May 28, 2008.

32

Outstanding Issues: Railroad Right-of-Way

Minnesota Commercial Railway constructing transload yard to replace one lost in I-35W bridge collapse

Page 33: - Light Rail Transit Improving mobility Easing congestion Strengthening our communities Central Corridor Metropolitan Council May 28, 2008.

33

Outstanding Issues: Railroad Right-of-Way

Page 34: - Light Rail Transit Improving mobility Easing congestion Strengthening our communities Central Corridor Metropolitan Council May 28, 2008.

34

Outstanding Issues: Railroad Right-of-Way

Railyard

Northern AlignmentFuture Granary Road

Page 35: - Light Rail Transit Improving mobility Easing congestion Strengthening our communities Central Corridor Metropolitan Council May 28, 2008.

35

Outstanding Risks/Issues Schedule Impacts

• Issue identification

• Environmental analysis– 4(f) and Section 106 issues– Historic #9 Bridge – Parklands – Cultural resources– Section 8 Housing – Phase I&II Environmental

Surveys

• SDEIS/FEIS

Light Rail Transit

Central Corridor

Page 36: - Light Rail Transit Improving mobility Easing congestion Strengthening our communities Central Corridor Metropolitan Council May 28, 2008.

36

Historic railroad bridge

Section 8 Housing Bike/pedestrian path

Mississippi National River and Recreation Area

Page 37: - Light Rail Transit Improving mobility Easing congestion Strengthening our communities Central Corridor Metropolitan Council May 28, 2008.

37

Outstanding Risks/Issues Schedule Impacts

• Federal approvals required– Corp. of Engineers– National Park Service/ MNRRA– Federal Emergency Management

Administration (FEMA)– Coast Guard– Environmental Protection Agency (EPA)– Housing and Urban Development (HUD)– Federal Railroad Administration (FRA)– Federal Transit Administration (FTA)

Light Rail Transit

Central Corridor

Page 38: - Light Rail Transit Improving mobility Easing congestion Strengthening our communities Central Corridor Metropolitan Council May 28, 2008.

38

Outstanding Risks/Issues Schedule Impacts

• Local approvals required– Minnesota Pollution Control

Agency (MPCA)– State Historic Preservation

Office (SHPO)– Minneapolis Historic

Preservation Commission

Light Rail Transit

Central Corridor

Page 39: - Light Rail Transit Improving mobility Easing congestion Strengthening our communities Central Corridor Metropolitan Council May 28, 2008.

39

Outstanding Risks/Issues Schedule Impacts

• Railroad negotiations– Right-of-way acquisition – Operating agreement– Insurance and indemnification

Light Rail Transit

Central Corridor

Page 40: - Light Rail Transit Improving mobility Easing congestion Strengthening our communities Central Corridor Metropolitan Council May 28, 2008.

40

Outstanding Issues: Schedule Impacts

CCLRT

Master Schedule

Northern Alignment

Estimated Schedule

Start SDEIS environmental review July 9, 2007

Define Project Alignment and Elements Feb. 27, 2008 May 21, 2008

Restart SDEIS environmental review for Northern Alignment June/July 2008

Complete environmental analysis, prepare SDEIS April 4, 2008 Feb. 2009

Provide final administrative draft SDEIS to FTA April 29, 2008 March 2009

Receive SDEIS comments from FTA May 28, 2008 May 2009

Publish SDEIS in Federal Register June 27, 2008 June 2009

Hold Public Hearing July 21, 2008 July 2009

Adopt Revised LPA by Met Council Aug. 27, 2008 Aug. 2009

Submit New Starts Application Sept. 5, 2008 Sept. 4, 2009

Publish draft FEIS Jan. 11, 2009 Jan. 2010

FTA issues Record of Decision on FEIS Feb. 25, 2009 Feb. 2010

FTA approves project to move into Final Design May 6, 2009 May 2010

Full Funding Grant Agreement Execution April 2, 2010 April 2011

Major Construction Contract Awards May 2010 May 2011

Page 41: - Light Rail Transit Improving mobility Easing congestion Strengthening our communities Central Corridor Metropolitan Council May 28, 2008.

41

Comparison of Washington Ave.

Transit/Pedestrian Mall & Northern Alignment

Light Rail Transit

Central Corridor

Page 42: - Light Rail Transit Improving mobility Easing congestion Strengthening our communities Central Corridor Metropolitan Council May 28, 2008.

42

Comparison of AlignmentsSummary Table

Light Rail Transit

Central Corridor

Updated CCLRT

Northern Alignment

CCLRT vs. NA

Ridership model FTA-accepted

FTA-accepted

Travel time 40:15 40:26 -0:11

Capital Cost $892 million $894 million -$2 million

Ridership 42,170 35,240 +6,930

CEI $23.98 $28.44 -$4.46

Page 43: - Light Rail Transit Improving mobility Easing congestion Strengthening our communities Central Corridor Metropolitan Council May 28, 2008.

43

Employment by TAZ

University Ave.

Northern Alignment

Washington Ave. Alignment

Page 44: - Light Rail Transit Improving mobility Easing congestion Strengthening our communities Central Corridor Metropolitan Council May 28, 2008.

44

Population by TAZ

University Ave.

Northern Alignment

Washington Ave. Alignment

Page 45: - Light Rail Transit Improving mobility Easing congestion Strengthening our communities Central Corridor Metropolitan Council May 28, 2008.

45

University Ave.

Northern Alignment

Washington Ave. Alignment

Special Trips by TAZ

Page 46: - Light Rail Transit Improving mobility Easing congestion Strengthening our communities Central Corridor Metropolitan Council May 28, 2008.

46

Northern Alignment Comparison of 2001 & 2008 Studies

Light Rail Transit

Central Corridor

2001 A/A

2008 Feasibility Comments

RidershipVery Poor

Poor6,900 lower than

CCLRT

Capital Cost Good GoodAbout same as

CCLRT

Traffic ImpactsVery Good

GoodBetter than CCLRT

before mitigation

Bus Connectivity

Very Poor

PoorWould require

reconfiguring the bus network

Page 47: - Light Rail Transit Improving mobility Easing congestion Strengthening our communities Central Corridor Metropolitan Council May 28, 2008.

47

Northern Alignment Summary

• Significantly lower ridership using FTA-accepted ridership model

• Significantly higher CEI• Includes risks not reflected in cost

estimate– Site contamination– Federal permits required– Railroad right-of-way acquisition,

insurance & indemnification– Schedule delay and cost escalation

Light Rail Transit

Central Corridor

Page 48: - Light Rail Transit Improving mobility Easing congestion Strengthening our communities Central Corridor Metropolitan Council May 28, 2008.

48

Washington Ave. Summary

• Moves more people faster for less money– Transportation System User

Benefits (TSUB) is significantly higher

– Significantly higher ridership

• Meets federal CEI guidelines• Keeps project on schedule

and within budget

Light Rail Transit

Central Corridor

Page 49: - Light Rail Transit Improving mobility Easing congestion Strengthening our communities Central Corridor Metropolitan Council May 28, 2008.

49

Light Rail Transit

Central Corridor

More Information

Check out our website:

• www.centralcorridor.org

Contact Central Corridor Project Office:

• 540 Fairview Avenue NorthSt. Paul, MN 55104

• Comment Line: 651-602-1645

• Email: [email protected]