********************************************************** 26 Sections - Pr… · IEEE C57.13...
Transcript of ********************************************************** 26 Sections - Pr… · IEEE C57.13...
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 11 13.00 20 Page 1
***************************************************************************
USACE / NAVFAC / AFCEC / NASA UFGS-26 11 13.00 20 (April 2007)
Change 1 - 08/17
--------------------------------
Preparing Activity: NAVFAC Superseding
UFGS-26 11 13.00 20 (April 2006)
UNIFIED FACILITIES GUIDE SPECIFICATIONS
References are in agreement with UMRL dated October 2017
***************************************************************************
SECTION 26 11 13.00 20
PRIMARY UNIT SUBSTATION
04/07
***************************************************************************
NOTE: This guide specification covers the
requirements for for primary substations and
associated load break switches and switchgear.
Adhere to UFC 1-300-02 Unified Facilities Guide
Specifications (UFGS) Format Standard when editing
this guide specification or preparing new project
specification sections. Edit this guide
specification for project specific requirements by
adding, deleting, or revising text. For bracketed
items, choose applicable item(s) or insert
appropriate information.
Remove information and requirements not required in
respective project, whether or not brackets are
present.
Comments, suggestions and recommended changes for
this guide specification are welcome and should be
submitted as a Criteria Change Request (CCR).
***************************************************************************
***************************************************************************
NOTE: TO DOWNLOAD UFGS GRAPHICS
Go to http://www.wbdg.org/FFC/NAVGRAPH/graphtoc.pdf
***************************************************************************
***************************************************************************
NOTE: A primary substation as used in this
specification is a substation in which the primary
and secondary voltages are both rated 1000 volts and
above, normally in the medium voltage range of 5 kV
to 35 kV. This specification includes indoor and
outdoor applications.
USE THE FOLLOWING RELATED GUIDE SPECIFICATIONS FOR
POWER DISTRIBUTION EQUIPMENT:
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 11 13.00 20 Page 2
--Section 26 08 00 APPARATUS INSPECTION AND TESTING
--Section 26 12 19.10 THREE-PHASE PAD-MOUNTED
TRANSFORMERS
--Section 26 12 21 SINGLE-PHASE PAD-MOUNTED
TRANSFORMERS
--Section 33 71 01 OVERHEAD TRANSMISSION AND
DISTRIBUTION
--Section 33 71 02 UNDERGROUND ELECTRICAL
DISTRIBUTION
--Section 26 13 00 SF6/HIGH-FIREPOINT FLUID INSULATED
PAD-MOUNTED SWITCHGEAR
--Section 26 11 16 SECONDARY UNIT SUBSTATIONS
--Section 26 23 00 LOW VOLTAGE SWITCHGEAR
--Section 26 24 13 SWITCHBOARDS
***************************************************************************
***************************************************************************
NOTE: The following information shall be indicated
on the project drawings or specified in the project
specifications:
1. Single-line diagram showing transformers, buses,
and interrupting devices with interrupting
capacities; current transformers and potential
transformers with ratings; instruments and meters
required; and description of instruments and meters.
2. Location, space available, arrangement, and
elevations of substations and switchgear.
3. Grounding plan.
4. Type and number of cables, size of conductors for
each power circuit, and point of entry (top or
bottom).
5. Minimum and maximum overall dimensions of
shipping section which can be handled and installed
at destination, as applicable.
6. Transformer primary and secondary voltages. (Use
IEEE C57.12.00, Table 11(b), Designation of voltage
ratings of three-phase windings".) State the primary
voltage (nominal) actually in service and not the
voltage class.
7. Special conditions, such as altitude, temperature
and humidity, exposure to fumes, vapors, dust, and
gases.
8. Where extensions or additions to existing
substations or switchgear are being specified,
clearly distinguish the difference between existing
equipment and the equipment the Contractor is
required to provide under this contract. Clearly
indicate the extent of the Contractor's
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 11 13.00 20 Page 3
responsibility for testing the existing equipment
upon completion of his work.
***************************************************************************
PART 1 GENERAL
1.1 REFERENCES
***************************************************************************
NOTE: This paragraph is used to list the
publications cited in the text of the guide
specification. The publications are referred to in
the text by basic designation only and listed in this
paragraph by organization, designation, date, and
title.
Use the Reference Wizard's Check Reference feature
when you add a Reference Identifier (RID) outside of
the Section's Reference Article to automatically
place the reference in the Reference Article. Also
use the Reference Wizard's Check Reference feature to
update the issue dates.
References not used in the text will automatically be
deleted from this section of the project
specification when you choose to reconcile references
in the publish print process.
***************************************************************************
The publications listed below form a part of this specification to the
extent referenced. The publications are referred to within the text by the
basic designation only.
AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)
ANSI C12.1 (2008) Electric Meters Code for Electricity
Metering
ANSI C39.1 (1981; R 1992) Requirements for Electrical
Analog Indicating Instruments
ASTM INTERNATIONAL (ASTM)
ASTM A123/A123M (2015) Standard Specification for Zinc (Hot-
Dip Galvanized) Coatings on Iron and Steel
Products
ASTM A153/A153M (2016) Standard Specification for Zinc
Coating (Hot-Dip) on Iron and Steel Hardware
ASTM A167 (2011) Standard Specification for Stainless
and Heat-Resisting Chromium-Nickel Steel
Plate, Sheet, and Strip
ASTM A653/A653M (2015; E 2016) Standard Specification for
Steel Sheet, Zinc-Coated (Galvanized) or
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 11 13.00 20 Page 4
Zinc-Iron Alloy-Coated (Galvannealed) by the
Hot-Dip Process
ASTM A780/A780M (2009; R 2015) Standard Practice for Repair
of Damaged and Uncoated Areas of Hot-Dip
Galvanized Coatings
ASTM D117 (2010) Standard Guide for Sampling, Test
Methods, Specifications and Guide for
Electrical Insulating Oils of Petroleum
Origin
ASTM D1535 (2014) Specifying Color by the Munsell System
ASTM D2472 (2000; R 2014) Standard Specification for
Sulphur Hexafluoride
ASTM D3455 (2011) Compatibility of Construction Material
with Electrical Insulating Oil of Petroleum
Origin
ASTM D3487 (2016) Standard Specification for Mineral
Insulating Oil Used in Electrical Apparatus
ASTM D877/D877M (2013) Standard Test Method for Dielectric
Breakdown Voltage of Insulating Liquids Using
Disk Electrodes
ASTM D92 (2012a) Standard Test Method for Flash and
Fire Points by Cleveland Open Cup Tester
FM GLOBAL (FM)
FM APP GUIDE (updated on-line) Approval Guide
http://www.approvalguide.com/
INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)
IEEE C2 (2017; Errata 1-2 2017; INT 1 2017) National
Electrical Safety Code
IEEE C37.04 (1999; R 2006; AMD 1 2003; R 2006; ERTA 2005;
R 2006; AMD 2 2008; CORR 2009; INT 2010)
Standard for Rating Structure for AC High-
Voltage Circuit Breakers
IEEE C37.06 (2009) Standard for AC High-Voltage Circuit
Breakers Rated on a Symmetrical Current Basis
- Preferred Ratings and Related Required
Capabilities for Voltage Above 1000 V
IEEE C37.121 (2012) American National Standard for
Switchgear-Unit Substations - Requirements
IEEE C37.20.2 (1999; Corr 2000; R 2005) Standard for Metal-
Clad Switchgear
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 11 13.00 20 Page 5
IEEE C37.20.3 (2013) Standard for Metal-Enclosed
Interrupter Switchgear
IEEE C37.41 (2016) Standard Design Tests for High-Voltage
(>1000 V) Fuses and Accessories
IEEE C37.46 (2010) Standard for High Voltage Expulsion
and Current-Limiting Type Power Class Fuses
and Fuse Disconnecting Switches
IEEE C37.71 (2001) Standard Three-Phase, Manually
Operated Subsurface or Vault Load-
Interrupting Switches for Alternating-Current
Systems
IEEE C37.90 (2005; R 2011) Standard for Relays and Relay
Systems Associated With Electric Power
Apparatus
IEEE C57.12.00 (2015) General Requirements for Liquid-
Immersed Distribution, Power, and Regulating
Transformers
IEEE C57.12.28 (2014) Standard for Pad-Mounted Equipment -
Enclosure Integrity
IEEE C57.12.80 (2010) Standard Terminology for Power and
Distribution Transformers
IEEE C57.12.90 (2015; Corr 2017) Test Code for Liquid-
Immersed Distribution, Power, and Regulating
Transformers
IEEE C57.13 (2016) Requirements for Instrument
Transformers
IEEE C57.96 (2013) Guide for Loading Dry-Type
Distribution and Power Transformers
IEEE C57.98 (2011) Guide for Transformer Impulse Tests
IEEE C62.11 (2012) Standard for Metal-Oxide Surge
Arresters for Alternating Current Power
Circuits (>1kV)
INTERNATIONAL ELECTRICAL TESTING ASSOCIATION (NETA)
NETA ATS (2017) Standard for Acceptance Testing
Specifications for Electrical Power Equipment
and Systems
NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)
NEMA C12.4 (1984; R 2011) Registers - Mechanical Demand
NEMA C37.72 (1987) Manually-Operated, Dead-Front
Padmounted Switchgear with Load Interrupting
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 11 13.00 20 Page 6
Switches and Separable Connectors for
Alternating-Current Systems
NEMA LI 1 (1998; R 2011) Industrial Laminating
Thermosetting Products
NEMA ST 20 (1992; R 1997) Standard for Dry-Type
Transformers for General Applications
NEMA TP 1 (2002) Guide for Determining Energy
Efficiency for Distribution Transformers
NEMA/ANSI C12.10 (2011) Physical Aspects of Watthour Meters -
Safety Standards
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 70 (2017; ERTA 1-2 2017; TIA 17-1; TIA 17-2; TIA
17-3) National Electrical Code
UNDERWRITERS LABORATORIES (UL)
UL 1437 (2006) Electrical Analog Instruments - Panel
Board Types
UL 467 (2013; Reprint Jun 2017) UL Standard for
Safety Grounding and Bonding Equipment
1.2 RELATED REQUIREMENTS
***************************************************************************
NOTE: Include Section 26 08 00 APPARATUS INSPECTION
AND TESTING on all projects involving medium voltage
and specialized power distribution equipment
***************************************************************************
Section 26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS and Section 26
08 00 APPARATUS INSPECTION AND TESTING apply to this section, with the
additions and modifications specified herein.
1.3 SUBMITTALS
***************************************************************************
NOTE: Review Submittal Description (SD) definitions
in Section 01 33 00 SUBMITTAL PROCEDURES and edit the
following list to reflect only the submittals
required for the project.
The Guide Specification technical editors have
designated those items that require Government
approval, due to their complexity or criticality,
with a "G". Generally, other submittal items can be
reviewed by the Contractor's Quality Control System.
Only add a “G” to an item, if the submittal is
sufficiently important or complex in context of the
project.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 11 13.00 20 Page 7
For submittals requiring Government approval on Army
projects, a code of up to three characters within the
submittal tags may be used following the "G"
designation to indicate the approving authority.
Codes for Army projects using the Resident Management
System (RMS) are: "AE" for Architect-Engineer; "DO"
for District Office (Engineering Division or other
organization in the District Office); "AO" for Area
Office; "RO" for Resident Office; and "PO" for
Project Office. Codes following the "G" typically
are not used for Navy, Air Force, and NASA projects.
Use the "S" classification only in SD-11 Closeout
Submittals. The "S" following a submittal item
indicates that the submittal is required for the
Sustainability eNotebook to fulfill federally
mandated sustainable requirements in accordance with
Section 01 33 29 SUSTAINABILITY REPORTING.
Choose the first bracketed item for Navy, Air Force
and NASA projects, or choose the second bracketed
item for Army projects.
***************************************************************************
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are [for Contractor Quality Control
approval.][for information only. When used, a designation following the "G"
designation identifies the office that will review the submittal for the
Government.] Submittals with an "S" are for inclusion in the Sustainability
eNotebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
***************************************************************************
NOTE: Include the bracketed options on "CI44 and 074
review" for NAVFAC LANT and NAVFAC SE projects
respectively. For other projects, submittal review
shall be performed by the designer of record. If
submittal review by NAVFAC LANT or NAVFAC SE is
specifically desired, the responsible Government
agency must coordinate with the respective Code CI44
or 074 during the design process. Add appropriate
information in Section 01 33 00 SUBMITTAL PROCEDURES
to coordinate with the special requirements.
***************************************************************************
[Submit in accordance with paragraph entitled "Coordinated Submittal
Reviews" herein.
]1.3.1 Coordinated Submittal Reviews
a. Submit transformer submittals to Code [CI44, Atlantic][074, Southern]
Division, Naval Facilities Engineering Command for approval. In
addition, submit one set of the remaining substation components for
surveillance.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 11 13.00 20 Page 8
b. Submit remaining substation component submittals to Engineer of Record
for approval. In addition, submit one set of transformer submittals
for surveillance and to insure alignment of equipment and coordination
for interconnections.
SD-02 Shop Drawings
Unit substation drawings; G[, [_____]]
[Transformer drawings [(to Code [CI44][074])]; G[, [_____]]
]SD-03 Product Data
***************************************************************************
NOTE: Use bracketed options referring to Codes CI44
and 074 for NAVFAC LANT and NAVFAC SE projects,
respectively. This requires the designer of record
to review and approve the substation equipment
submittals except for the transformer. The EFD will
review and approve the transformer submittals.
***************************************************************************
Primary unit substations[ excluding transformer data]; G[, [_____]]
[Unit substation transformer[ (to Code [CI44][074])]; G[, [_____]]
] Submittal shall include manufacturer's information for each
component, device and accessory provided with the equipment.
SD-05 Design Data
Capacity calculations for battery charger and batteries; G[,
[_____]]
SD-06 Test Reports
***************************************************************************
NOTE: Include "Calibration test reports" for NAVFAC
SE projects.
***************************************************************************
[Calibration test reports; G[, [_____]]]
Submit report of results of acceptance checks and tests specified
by paragraph entitled "Field Quality Control"; G[, [_____]]
***************************************************************************
NOTE: Field dielectric tests are recommended only
when new units added to an existing installation or
after major field modifications. If necessary,
service the equipment prior to the field test.
***************************************************************************
[Certified copies of dielectric tests report; G[, [_____]]]
SD-07 Certificates
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 11 13.00 20 Page 9
***************************************************************************
NOTE: Use "Tested transformer losses" for other than
NAVFAC LANT and NAVFAC SE projects. Use "Transformer
losses" for NAVFAC LANT projects. Use "Transformer
loss calculations" for NAVFAC SE projects.
***************************************************************************
[Tested Transformer Losses; G[, [_____]]]
[Transformer losses; G[, [_____]]]
[Transformer loss calculations; G[, [_____]]]
SD-09 Manufacturer's Field Reports
***************************************************************************
NOTE: Include following option if "less-flammable
transformer liquid" is chosen.
***************************************************************************
[Silicone compatibility tests[ (to code [CI44] [074])]; G[,
[_____]]
]
***************************************************************************
NOTE: If project includes special requirements or
unusual application of the equipment specified in
this section, factory tests may be specified on
completely assembled unit substations as well as
individual components. These completely assembled
tests involve additional cost and specific
requirements must be added to this specification when
they are deemed necessary.
***************************************************************************
Switchgear design tests; G[, [_____]]
Switchgear production tests; G[, [_____]]
Load interrupter switch design tests; G[, [_____]]
Load interrupter switch production tests; G[, [_____]]
Transformer design tests[ to code [CI44][074]]; G[, [_____]]
Transformer routine and other tests[ (to code [CI44][074])]; G[,
[_____]]
SD-10 Operation and Maintenance Data
Primary unit substations, Data Package 5; G[, [_____]]
[Unit substation transformer, Data Package 5; G[, [_____]]
] Submit in accordance with Section 01 78 23 OPERATION AND
MAINTENANCE DATA.
SD-11 Closeout Submittals
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 11 13.00 20 Page 10
***************************************************************************
NOTE: Include "Calibration schedule" and "Formal
request for settings" for NAVFAC SE projects.
***************************************************************************
[Calibration schedule; G[, [_____]]
][Formal request for settings; G[, [_____]]
]Equipment test schedule[ (to Code [CI44][074])]; G[, [_____]]
1.4 QUALITY ASSURANCE
1.4.1 Battery Power Calculations
Submit capacity calculations for battery charger and batteries. Calculation
shall verify that battery capacity exceeds station d.c. power requirements.
1.4.2 [Transformer Losses
***************************************************************************
NOTE: Use this paragraph for NAVFAC LANT projects
only.
***************************************************************************
Submit certification from the manufacturer indicating conformance with the
paragraph entitled "Specified Transformer Losses".
]1.4.3 Unit Substation Drawings
Drawings shall include, but are not limited to the following:
a. An outline drawing with front, top, and side views
b. Ampere ratings of bus bars
c. Maximum short-circuit bracing
d. Nameplate data
[e. Provisions for future extension[ and future forced air equipment]
][f. Circuit breaker[ and switch] type(s), interrupting ratings, and trip
devices including available settings
]g. Elementary diagrams and wiring diagrams with terminals identified and
indicating prewired interconnections between items of equipment and the
interconnection between the items
h. One-line diagram, including switch(es),[ circuit breakers,][ current
transformers, meters,] and fuses
i. Manufacturer's instruction manuals and published time-current curves
(on full size 279 by 431 mm (11 by 17 inches) logarithmic paper) of
the[ fuse in the load interrupter switch,][ main secondary breaker,][
largest secondary feeder device]; transformer thermal and magnetic
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 11 13.00 20 Page 11
damage information; and transformer inrush current information
(magnetic inrush point). These shall be used by the designer of record
to verify fuse size and to[ provide breaker settings that will] ensure
protection and coordination are achieved.
[1.4.4 Transformer Drawings
***************************************************************************
NOTE: Include bracketed option for separate
transformer drawings on NAVFAC LANT and NAVFAC SE
projects only.
***************************************************************************
Drawings shall include, but are not limited to the following:
a. An outline drawing, with top, front, and side views
b. ANSI nameplate data
][1.4.5 Calibration Schedule
***************************************************************************
NOTE: Include "Calibration schedule" and "Formal
request for settings" for NAVFAC SE projects only.
***************************************************************************
a. Provide a calibration schedule including the anticipated dates when
equipment requiring coordination and protection will be installed, the
anticipated date when the Contractor will submit a formal request for
settings, and the anticipated date when the manufacturer's technical
representative will perform settings and calibrate equipment.
b. Submit the calibration schedule, via the Contracting Officer to:
NAVFAC SE, Code 05, Construction Department
NAVFAC SE; Code 162; Director, Utilities Engineering Division
][1.4.6 Formal Request for Settings
***************************************************************************
NOTE: The "30" days in brackets below may be
extended for projects involving major electrical
distribution work. Consult with NAVFAC SE Code 162.
***************************************************************************
a. Where settings will be provided by the Government to achieve protection
and coordination via relays and protective devices, submit a formal
request for settings [30][_____] days in advance of the date that
settings will be needed, to allow the Contracting Officer to forward a
copy of approved shop drawings to NAVFAC SE; Code 162; Director,
Utilities Engineering Division.
b. The equipment requiring protection and coordination shall be installed
prior to making this request.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 11 13.00 20 Page 12
c. Include approved shop drawings, manufacturer's instructions to set the
protective devices, and manufacturer's time-current curves.
d. Submit the formal request for settings, via the Contracting Officer to:
NAVFAC SE; Code 162; Director, Utilities Engineering Division.
][1.4.7 Calibration Test Reports
***************************************************************************
NOTE: Include this paragraph for NAVFAC SE projects.
***************************************************************************
Submit test results on protective relays via the Contracting Officer to
NAVFAC SE; Code 162; Director, Utilities Engineering Division.
Submit operation and maintenance data in accordance with Section 01 78 23
OPERATION AND MAINTENANCE DATA.
]1.5 MAINTENANCE
1.5.1 Additions to Operation and Maintenance Data
In addition to requirements of Data Package 5, include the following on the
actual primary unit substations provided.
a. An instruction manual with pertinent items and information highlighted
b. An outline drawing, including front view and sectional views with items
and devices identified
c. Prices for spare parts and supply list
d. Routine and field acceptance test reports
e. Time-Current-Characteristic (TCC) curves of fuses[and circuit breakers]
[f. Information on metering
]g. Actual nameplate diagram
h. Date of purchase
PART 2 PRODUCTS
2.1 PRODUCT COORDINATION
Products and materials not considered to be secondary unit substations and
related accessories are specified in Section 33 71 02 UNDERGROUND ELECTRICAL
DISTRIBUTION, and Section 26 20 00 INTERIOR DISTRIBUTION SYSTEM.
2.2 PRIMARY UNIT SUBSTATIONS
IEEE C37.121, [single-ended][double-ended] arrangement, consisting of
[one][two] incoming sections, [one][two] transformer sections, [one][two]
transition sections, the number of auxiliary sections, bus-tie sections, and
outgoing sections indicated.[ Substation shall be designed for indoor
service.][ Substation shall be designed for outdoor service with
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 11 13.00 20 Page 13
ventilation openings and gasketing provided to ensure a weatherproof
assembly under rain, snow, sleet, and hurricane conditions.] External doors
shall have provisions for padlocking.
2.2.1 Incoming Sections
***************************************************************************
NOTE: Choose one of the following three choices for
each incoming section: a metal-clad switchgear
section, a metal-enclosed switch section, or an air
filled terminal chamber.
***************************************************************************
[The][Each] incoming section shall consist of [a metal-clad switchgear
section][a metal-enclosed switch section][an air filled terminal chamber]
for connecting the incoming circuit [directly][through a [circuit breaker]
[[fused][nonfused]load interrupter switch]] to the transformer. If required
for proper connection and alignment, include a transition section with the
incoming section. Connection between [circuit breaker][interrupter switch]
and transformer shall be insulated copper bus or insulated copper cable
mounted on porcelain insulators spaced no more than 610 mm (2 feet) apart.
2.2.1.1 Conductor Termination
Conductor terminations shall be designed for terminating [one][two][_____]
single conductor cables per phase and shall be arranged for conduits
entering from [below][above]. Provide cable terminations of the [modular
molded rubber][porcelain insulator] type as specified in Section 33 71 02
UNDERGROUND ELECTRICAL DISTRIBUTION.
[2.2.1.2 [Vacuum][ or ][SF6] Circuit Breaker as Main Protective Device
***************************************************************************
NOTE: When a separately enclosed, pad mounted SF6
switch is provided as the incoming
disconnecting/overcurrent protection device for the
primary unit substation, use Section 26 13 00
SF6/HIGH-FIREPOINT FLUID INSULATED PAD-MOUNTED
SWITCHGEAR. Modify Section 26 13 00 for vault-type
switches, where applicable.
***************************************************************************
***************************************************************************
NOTE: Choose this subparagraph or "Load Interrupter
Switch as Main Protective Device".
***************************************************************************
***************************************************************************
NOTE: Circuit breakers are more costly than fused
switches, but may be needed where switching is
frequent, and quick reclosing is required.
***************************************************************************
The [vacuum][ or ][SF6] circuit breaker shall be an electrically-operated,
three-pole, circuit interrupting device rated for [_____] amperes continuous
at [_____] kV and [_____] kV BIL. Breaker shall be designed for service on
a [_____] kV system with a short-circuit capacity of not less than [_____]
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 11 13.00 20 Page 14
[amperes symmetrical][MVA]. Rating shall be based on IEEE C37.04 and IEEE
C37.06. Circuit breaker shall be drawout-mounted with position indicator,
operation counter, auxiliary switches, and primary and secondary disconnect
devices. Circuit breaker shall be operated by an electrically charged,
mechanically and electrically trip-free, stored-energy operating mechanism.
Provide for manual charging of the mechanism. Circuit breaker control
voltage shall be [[_____] Vdc][[_____] Vac].[ SF6 circuit breakers shall be
shipped factory filled with SF6 gas conforming to ASTM D2472.]
a. Contacts: Silver-plated, multifinger, positive pressure, self-aligning
type for main drawout contacts.
b. Each drawout breaker shall be provided with three-position operation.
The connected position and the test/disconnect position shall be
clearly identified by an indicator on the circuit breaker front panel.
1. Connected position: Contacts are fully engaged. Breaker shall be
tripped before it can be racked into or out of this position.
2. Test/disconnect position: Position shall allow for complete
testing and operation of the breaker without energizing the primary
circuit.
3. Withdrawn (removed) positions: Places breaker completely out of
compartment, ready for removal.
][2.2.1.3 Load Interrupter Switch as Main Protective Device
IEEE C37.20.3. Provide a three-pole, single-throw, deadfront, metal-
enclosed, load interrupter switch with manual stored energy operator. Switch
shall be [fused, with fuses mounted on a single frame][non-fused][in series
with [vacuum][ or ][SF6] interrupters] and designed for easy inspection[ and
fuse replacement].[ SF6 gas shall conform to ASTM D2472.] The switch shall
be operated by a manually charged spring stored energy mechanism which shall
simultaneously disconnect or connect ungrounded conductors. The moveable
blade of the switch shall be deenergized when in the open position. The
mechanism shall enable the switch to close against a fault equal to the
momentary rating of the switch without affecting its continuous current
carrying or load interrupting ability. A ground bus shall extend the width
of the switch enclosure and shall be bolted directly thereto. Connect frame
of unit to ground bus. The door shall have an inspection window to allow
full view of the position of the three switch blades through the closed
door. Switch ratings shall be:
a. [_____] kV, [_____] kV BIL for service on a [_____] kV system with a
fault close rating of not less than [_____] amperes asymmetrical.
b. The switch shall be capable of carrying continuously or interrupting
[_____] amperes with a momentary rating of [_____] amperes at [_____]
kV.
c. Switch shall have provision for padlocking in the open and closed
positions.
d. [Fuses shall be current limiting type rated [[_____] amperes
continuous, and [_____] [amperes interrupting capacity.]][approximately
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 11 13.00 20 Page 15
[_____] percent of the transformer full-load rating and in accordance
with the fuse manufacturer's recommendation.]]
]2.2.2 Primary Transition Section
***************************************************************************
NOTE: Transition section should only be specified
where absolutely necessary.
***************************************************************************
Provide transition section for insulated copper [cable][bus-bar] connections
to the transformer primary terminals. Support [bus][cable] connections
between high-voltage [switch][breaker] and transformer primary by porcelain
insulators[ spaced no more than 610 mm (2 feet) apart]. Size and brace
[bus][cable] to withstand the specified available fault.
2.2.3 Transformer Sections
***************************************************************************
NOTE: Indicate and specify the type of transformers
required for the project.
1. Use mineral oil filled transformers and locate
transformers at least 7.6 meters (25 feet) from
buildings wherever possible. Where adequate distance
from structures cannot be attained, consult NAVFAC
design manuals and MIL-HDBK-1008, "Fire Protection
for Facilities Engineering, Design, and
Construction." Caution should be used in specifying
less-flammable liquid filled transformers. A
thorough analysis should be made by the designer
prior to using silicone filled transformers due to
the concern over operation of tap changers within the
silicone liquid.
2. Use the following option(s) when additional
capacity is required. This involves special
coordination with transformer KVA rating, as well as
sizes and ratings of fuses and secondary breakers.
a. If it is anticipated that future load
requirements will necessitate increasing the capacity
of the transformer, the specification for the
transformer should require the provision of
components and brackets for future forced air
cooling. Forced-air-cooling increases capacity by:
15 percent (750-2000 KVA); 25 percent (2500-5000
KVA).
b. On rare occasions, change "... insulation
system rated for a 65 degrees C rise..." to read
"...insulation system rated for a 55/65 degrees C
rise to allow transformer(s) to have a continuous
overload capacity of 12 percent at rated voltage
without exceeding 75 degrees C winding temperature
rise."
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 11 13.00 20 Page 16
3. Use IEEE C57.12.00, Figure 3(b), voltage
designations, such as "13200 V - 4160Y/2400 V".
4. Tap ratings may vary from those indicated,
especially in lower kVA ratings.
5. Energy efficient transformers usually have
impedance values in the range of 2.95 to 5.75
percent. Perform fault current calculations to
determine minimum acceptable transformer impedance.
Be sure that specified impedance is available in the
size and type transformer required.
6. Delete inapplicable sound levels.
7. Delete last sentence, referring to removable
ground strap, if transformer secondary winding is
delta type.
***************************************************************************
IEEE C57.12.00. [Less-flammable [bio-based] liquid-insulated] [Oil-
insulated][Less-flammable liquid-insulated], two winding, 60 hertz, 65
degrees C rise above a 30 degrees C average ambient, self-cooled type.
2.2.3.1 Transformer Ratings
a. Transformer shall be rated [_____] kVA, [_____] kV BIL primary, [_____]
kV BIL secondary.
b. Transformer voltage ratings: [_____] V - [_____] V.[ For GrdY - GrdY
transformers, provide transformer with five-legged core design for
third harmonic suppression.]
c. Provide four 2.5 percent full capacity taps, two above and two below
rated primary voltage. Provide tap changer, with external, pad-
lockable, manual type operating handle, for changing tap setting when
the transformer is de-energized.
***************************************************************************
NOTE: Change 85 degrees C to 75 degrees C when
transformers are specifically rated for 55/65 degrees
C rise.
***************************************************************************
d. Minimum tested impedance shall not be less than [_____] percent at 85
degrees C.
e. Audible sound levels shall comply with the following:
kVA DECIBELS (MAX)
225 55
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 11 13.00 20 Page 17
kVA DECIBELS (MAX)
300 55
500 56
750 58
1000 58
1500 60
2000 61
2500 62
5000 65
7500 67
10000 68
f. Diagrammatic stainless steel or laser-etched anodized aluminum
nameplate.
g. Transformer shall include ground pads, lifting lugs and provisions for
jacking under base. The transformer base construction shall be
suitable for using rollers or skidding in any direction. Provide
transformer top with an access handhole. The transformer shall have an
insulated low-voltage neutral bushing with lugs for ground cable, and
with removable ground strap.
h. Transformer shall have the following accessories:
1. Liquid-level indicator
2. Pressure-vacuum gage
3. Liquid temperature indicator
4. Drain and filter valves
5. Pressure relief device
[6. Auxiliary cooling equipment and controls
[(a) Transformer shall have provisions for future addition of
automatically controlled fans for forced-air-cooling.
][(b) Transformer shall be forced-air-cooled. Forced-air-cooling
fans shall have [automatic temperature control relay][winding
temperature indicator with sequence contacts].
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 11 13.00 20 Page 18
]][2.2.3.2 Specified Transformer Efficiency
***************************************************************************
NOTE: On other than NAVFAC LANT and NAVFAC SE
projects, use "Specified Transformer Efficiency".
Delete "Specified Transformer Losses", "Transformer
Loss Calculations", and "Deduct Clause".
Efficiency shall be specified based on NEMA TP 1
until actual loss values can be coordinated with
industry using life cycle cost economics.
***************************************************************************
Minimum efficiency, based on test results, shall not be less than NEMA Class
1 efficiency as defined by NEMA TP 1.
a. Tested transformer losses: Submit certification from the manufacturer,
with the submitted catalog data, to show conformance with the specified
efficiency requirements. The values used to determine the actual
efficiency shall be the tested no-load losses (NLL) (in watts) at a
reference temperature of 20 degrees C and the tested load losses (LL)
(in watts) at a reference temperature of 85 degrees C. If the
efficiency based on the aforementioned test results, is less than the
NEMA Class 1 efficiency, the transformer is unacceptable. Transformer
efficiency values at both full load and at one-half full load shall be
included on the routine test report.
][2.2.3.3 Specified Transformer Losses
***************************************************************************
NOTE: On NAVFAC LANT projects, use "Specified
Transformer Losses". Delete "Specified Transformer
Efficiency", "Transformer Loss Calculations", and
"Deduct Clause". The appropriate NLL and LL values
for each transformer will be provided by Code CI44 at
the 100 percent review. Until that time, leave the
following bracketed values blank.
***************************************************************************
No-load losses (NLL shall be [_____] watts at 20 degrees C, and load losses
(LL) shall be [_____] watts at 85 degrees C. The values for the specified
losses shall be used for comparison with the losses determined during the
routine tests. If the routine test values exceed the specified no-load
losses by more than 10 percent, or the total losses exceed the specified
total losses (sum of no-load and load losses) by more than 6 percent, the
transformer is unacceptable.
***************************************************************************
NOTE: On NAVFAC SE projects, use "Transformer Loss
Calculations" and "Deduct Clause". Delete "Specified
Transformer Efficiency" and "Specified Transformer
Losses".
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 11 13.00 20 Page 19
TRANSFORMER LOSSES (WATTS)
kVA 1000 1500 2000 2500
NLL 1250 1725 2100 2775
LL 6050 7300 8425 12000
***************************************************************************
***************************************************************************
Specify values for the variables "A", "B", & "C"
using Transformer Losses (Watts) table above, Table I
below, and C equals A(NLL) plus B(LL).
TABLE I
ACTIVITY LOSS FACTORS
NAS KEY WEST A = 8.36 B = 2.95
CHARLESTON AFB A = 3.79 B = 1.91
GLAKES COMPLEX A = 4.89 B = 2.14
DFSP CHARLESTON A = 4.54 B = 2.36
NAS CORPUS CHRISTI A = 3.98 B = 2.10
MCAS BEAUFORT A = 4.54 B = 2.36
NAS KINGSVILLE A = 3.98 B = 2.10
MCRD PARRIS ISLAND A = 4.54 B = 2.36
NS INGLESIDE A = 3.98 B = 2.10
NH BEAUFORT A = 4.54 B = 2.36
NAS MERIDIAN A = 4.65 B = 2.19
NH CHARLESTON A = 4.54 B = 2.36
CAPE CANAVERAL A = 6.25 B = 1.78
NISE A = 4.54 B = 2.36
MCLB ALBANY A = 5.26 B = 1.50
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 11 13.00 20 Page 20
TABLE I
ACTIVITY LOSS FACTORS
NWS CHARLESTON A = 4.54 B = 2.36
NAS ATLANTA A = 5.26 B = 1.50
NS PASCAGOULA A = 5.30 B = 1.51
NSB, KINGS BAY A = 5.26 B = 1.50
BARKSDALE AFB A = 3.59 B = 1.44
CSS PANAMA CITY A = 4.23 B = 1.96
NAS FORT WORTH A = 3.70 B = 1.70
NAS PENSACOLA A = 4.23 B = 1.96
NAS MEMPHIS A = 3.93 B = 2.09
NAS SAUFLEY A = 4.23 B = 1.96
ANDROS ISLAND A = 3.56 B = 1.84
NAS WHITING FIELD A = 4.23 B = 1.96
ASCENSION ISLAND A = 3.56 B = 1.84
NTTC CORRY A = 4.23 B = 1.96
DETROIT A = 3.56 B = 1.84
BLOUT ISLAND A = 4.72 B = 1.89
DFSP ALASKA A = 3.56 B = 1.84
NAS JACKSONVILLE A = 4.72 B = 1.89
EGLIN AFB A = 3.56 B = 1.84
NS MAYPORT A = 4.72 B = 1.89
INDIAN NAWC A = 3.56 B = 1.84
NAS NEW ORLEANS A = 3.23 B = 2.07
NASC LOUISVILLE A = 3.56 B = 1.84
SA NOLA WEST BAN A = 3.23 B = 2.07
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 11 13.00 20 Page 21
TABLE I
ACTIVITY LOSS FACTORS
NPC FRINDLEY A = 3.56 B = 1.84
KEESLER AFB A = 4.03 B = 1.64
NWS CRANE A = 3.02 B = 1.55
NCBC GULFPORT A = 4.03 B = 1.64
POPE AFB A = 3.56 B = 1.84
STENNIS SPC A = 4.03 B = 1.64
SELFRIDGE ANG A = 3.56 B = 1.84
NSA NOLA EAST BANK A = 5.10 B = 1.97
SEYMOUR JOHNSON AFB A = 3.56 B = 1.84
ORLANDO COMPLEX A = 4.62 B = 1.84
SHAW AFB A = 3.56 B = 1.84
TINKER AFB A = 3.56 B = 1.84
***************************************************************************
][2.2.3.4 Transformer Loss Calculations
a. "A" and "B" are given loss factors. A equals [_____]; B equals
[_____]
b. "C" is the cost of losses. C equals $ [_____]
c. "NLL" and "LL" are the transformer no-load losses (watts) at 20 degrees
C, and load-losses (watts) at 85 degrees C, respectively.
][2.2.3.5 Deduct Clause
After routine test results are available, Contractor shall perform actual
transformer loss calculations (D) using test result values for NLL and LL,
and values specified above for A and B. Submit calculations for each
transformer with the routine test submittal. Calculate using equation: "D
equals A(NLL) plus B(LL)".
a. If D is less than or equal to C: No adjustment will be made to
contract price.
b. If D is greater than C: A unilateral contract modification will be
issued in the amount of difference between C and D.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 11 13.00 20 Page 22
c. If D is greater than 1.25(C): The transformer is unacceptable.
]2.2.3.6 Insulating Liquids
a. Less-flammable [bio-based] transformer liquids: NFPA 70 and FM APP
GUIDE for less-flammable liquids having a fire point not less than 300
degrees C tested in accordance with ASTM D92 and a dielectric strength
not less than 33 kV tested in accordance with ASTM D877/D877M. Do not
provide askarel or insulating liquids containing polychlorinated
biphenyls (PCB's), tetrachloroethylene (perchloroethylene), chlorine
compounds, and halogenated compounds.
[1. Silicone compatibility tests: When silicone is used as a less-
flammable transformer liquid, compatibility of silicone with seals
and gasketing materials in oil-immersed type tap changers shall be
determined by compatibility tests conducted in accordance with ASTM
D3455. Test results shall show no evidence of shrinkage, swelling,
or absorption caused by the liquid.
][ba. Mineral oil: ASTM D3487, Type II, tested in accordance with ASTM
D117. Provide identification of transformer as "non-PCB" on the
nameplate.
][b. Less-flammable transformer liquids: NFPA 70 and FM APP GUIDE for
less-flammable liquids having a fire point not less than 300 degrees C
tested in accordance with ASTM D92 and a dielectric strength not less
than 33 kV tested in accordance with ASTM D877/D877M. Do not provide
askarel or insulating liquids containing polychlorinated biphenyls
(PCB's), tetrachloroethylene (perchloroethylene), chlorine compounds,
and halogenated compounds.
[1. Silicone compatibility tests: When silicone is used as a less-
flammable transformer liquid, compatibility of silicone with seals and
gasketing materials in oil-immersed type tap changers shall be
determined by compatibility tests conducted in accordance with ASTM
D3455. Test results shall show no evidence of shrinkage, swelling, or
absorption caused by the liquid.
]]2.2.4 Secondary Transition[ and Auxiliary] Section(s)
The secondary transition[ and auxiliary] section(s) shall have a hinged
front panel, a [_____]-ampere, three-phase, [three][four]-wire[ insulated]
main bus and connections, a ground bus, necessary terminal blocks, wiring
and control buses, control power transformer, and cable supports.[ In the
auxiliary section provide a [_____]-V battery complete with rack and
standard accessories, and a battery charger, static type, [without voltage
regulation][with automatic charger control], complete with ammeter,
voltmeter, and rheostat.]
2.2.4.1 Control Power Transformers
Transformers shall be designed for continuous operation at rated kVA 24
hours a day, 365 days a year with normal life expectancy as defined in IEEE
C57.96. Dry-type, two-winding type, 115 degrees C rise above 40 degrees C
maximum ambient designed for mounting in switchgear cubicle or drawer.
Transformer shall be sized as required to serve the connected load and shall
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 11 13.00 20 Page 23
have a voltage rating of [_____] kV three-phase, delta primary, and
[120/208][277/480] V wye secondary, 60 Hz.
2.2.4.2 Primary Protection
Provide drawout-mounted, primary current limiting fuses rated for the
specified transformer size and the available short-circuit current.
2.2.4.3 Secondary Protection
Provide molded-case circuit breakers or molded-case switch sized as
required, mounted in same compartment with transformer and primary fuses to
serve the indicated loads.
2.2.5 Metal-Clad Switchgear Outgoing Section
***************************************************************************
NOTE: This paragraph may also be used to specify
freestanding switchgear not directly connected to a
unit substation. This paragraph is not intended to
be used for generator control switchgear without
extensive modification and coordination with
applicable diesel engine generator guide
specifications. Specify Category A requirements when
switchgear area is subject to access by the
unsupervised general public. Category B enclosures
must be fence enclosed or in a locked room.
***************************************************************************
***************************************************************************
NOTE: To help determine whether metal-clad
switchgear or metal-enclosed interrupter switchgear
is more appropriate for a project, consider that the
primary applications for interrupter switchgear are
where there are no instantaneous relaying and where
switching is infrequent. Also interrupter switchgear
is significantly less costly than metal-clad
switchgear.
***************************************************************************
IEEE C37.20.2 for metal-clad medium-voltage [vacuum][SF6] circuit breaker
type, insulated for [5][15] kV for use on [_____] kV system. Each steel
unit forming part of the switchgear structure shall be self-contained and
shall house [one-high][two-high] breaker or instrument compartments, and a
full height center and rear compartment for the buses and outgoing cable
connections. For two-high breaker units, provide a removable metal barrier
to separate the two cable circuits. Equip individual circuit-breaker
compartments with drawout contacts, rails, disconnecting mechanism, and a
cell interlock to prevent moving the removable element into or out of the
"connected" position while the circuit breaker is closed. Provide a steel
door for each breaker compartment. Enclosures shall be designed for
[indoor][outdoor] location and shall conform to the Category [A][B]
requirements of Table A1 of Appendix A to IEEE C37.20.2. Design the
structure to allow for future additions. Provide laminated plastic
nameplates for each relay, switch, meter, device, and cubicle to identify
its function. Provide permanent labels for wiring and terminals
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 11 13.00 20 Page 24
corresponding to the designations on approved shop drawings. Mount
nameplates on each circuit breaker compartment door.
a. Phase buses and connections: Mount bus structure on insulated supports
of high-impact, non-tracking, high-quality insulating material and
brace bus to withstand the mechanical forces exerted during short-
circuit conditions when connected directly to a source having maximum
of [_____] amperes rms symmetrical available. Bus bars shall be rated
[_____] amperes and shall be high conductivity copper having silver
plated joints. Make bus bar connections from main buses to the
incoming circuit breaker studs. Equip outgoing circuit breaker studs
with mechanical clamp type cable connectors for the size of cables
shown. Provide cable supports for outgoing cables. Wire secondary
circuits, including heater circuits, to terminal blocks. Terminal
blocks shall be readily accessible for making external connections as
required.
b. Ground bus: Provide a copper ground bus sized for full short-circuit
capacity. Secure ground bus to each vertical structure and extend
ground bus the entire length of switchgear. Include provisions for
making the station ground connections.
c. DC bus: Provide an insulated copper bus or wire extending the entire
length of switchgear. Bus shall be rated 100 amperes at 125 Vdc. Wire
shall be No. 6 AWG minimum.
d. Each breaker compartment shall have provision for mounting up to four
sets of ANSI rated current transformers, two on line side and two on
load side of each breaker.
2.2.5.1 Circuit Breaker
Each [vacuum][SF6] circuit breaker shall be an electrically operated, three-
pole, circuit interrupting device rated as indicated at maximum voltage of
[_____] kV and [_____] kV BIL. Breaker shall be designed for service on a
[_____] kV system with a short-circuit capacity of not less than [_____]
[amperes symmetrical][MVA]. Rating shall be based on IEEE C37.04 and IEEE
C37.06. Breaker frame size shall be as indicated. Circuit breaker shall be
drawout-mounted with position indicator, operation counter, auxiliary
switches, and primary and secondary disconnect devices. Circuit breaker
shall be operated by an electrically charged, mechanically and electrically
trip-free, stored-energy operating mechanism. Provide for manual charging
of the mechanism and for slow closing of the contacts for inspection or
adjustment. Circuit breaker control voltage shall be [_____] Vdc.
a. Contacts: Silver-plated, multifinger, positive pressure, self-aligning
type for main drawout contacts.
b. Each drawout breaker shall be provided with three-position operation.
The connected position and the test/disconnect position shall be
clearly identified by an indicator on the circuit breaker front panel.
1. Connected position: Contacts are fully engaged. Breaker shall be
tripped before it can be racked into or out of this position.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 11 13.00 20 Page 25
2. Test/disconnect position: Position shall allow for complete
testing and operation of the breaker without energizing the primary
circuit.
3. Withdrawn (removed) positions: Places breaker completely out of
compartment, ready for removal.
2.2.5.2 Space Only Compartments
Provide fully equipped with busing, control switch, indicating lights, and
drawout breaker mounting and connecting straps to accommodate future
breakers. Provide compartments with doors.
2.2.5.3 Breaker Lifter
Provide a portable lifter rated for lifting and lowering circuit breakers
from two-high cubicles. Portable lifter shall have swivel casters in front
for ease of movement.
2.2.6 Protective Relays, Metering, and Control Devices
2.2.6.1 Relays
***************************************************************************
NOTE: The definition and application of device
function numbers used in electrical substations and
switchgear are found in ANSI C37.2, "IEEE Standard
Electrical Power System Device Function Numbers." For
description and application of commonly used relays,
refer to MIL-HDBK-1004/3, "Switchgear and Relaying."
This guide specification does not cover all possible
relay applications. Choose only the relay types
applicable to the specific project.
***************************************************************************
Relays shall conform to IEEE C37.90. Protective relays shall be induction
type or solid-state type enclosed in rectangular, semiflush, switchboard-
type drawout cases with indicating targets and provisions for testing in
place by use of manufacturer's standard test blocks or test switches. One
complete set of test blocks or test switches to fit each type of relay in
the equipment shall be provided. Auxiliary and lockout relays are not
required to have drawout cases or test provisions. Controls, relays, and
protective functions shall be provided completely assembled and wired.
a. Phase overcurrent relays (device [50/]51): Provide [_____] sets of
three time overcurrent relays responding to phase currents wired to
trip associated circuit breakers upon the occurrence of a current above
the tap setting of the relays. Each relay shall have [very][extremely]
inverse time characteristics with a tap range of [_____] to [_____]
amperes.[ Each relay shall be equipped with an instantaneous
overcurrent unit having a pickup value over the range of [_____] to
[_____] amperes.][ Relays shall be Type [_____].]
b. Ground overcurrent relays (device [50/]51N): Provide a time
overcurrent relay responding to ground (residual) current, wired to
trip the associated circuit breaker upon occurrence of ground current
above the tap setting of the relay. Relay shall have [very][extremely]
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 11 13.00 20 Page 26
inverse time characteristics with a tap range of [_____] to [_____]
amperes. Relay shall be equipped with an instantaneous overcurrent
unit having a pickup value adjustable over the range of [_____] to
[_____] amperes.[ Relays shall be Type [_____].]
c. Ground overcurrent relays (device 51N): Provide a time overcurrent
relay responding to ground (residual) current, wired to trip the
associated circuit breaker upon occurrence of ground current above the
tap setting of the relay. Relay shall have [very][extremely] inverse
time characteristics with a tap range of [_____] to [_____] amperes.[
Relay shall be equipped with an instantaneous overcurrent unit having a
pickup value adjustable over the range of [_____] to [_____] amperes.][
Relays shall be Type [_____].]
d. Directional phase overcurrent relays (device 67): Provide [_____] sets
of three directionally controlled time overcurrent relays sensing phase
current, wired to trip associated circuit breakers upon a current
exceeding the tap setting in the direction indicated. Relays shall
have a voltage polarized directional unit and an inverse time
characteristic overcurrent unit. Overcurrent unit shall have a tap
range of [_____] to [_____] amperes.[ Relays shall be Type [_____].]
e. Directional ground overcurrent relays (device 67N): Provide
directionally controlled time overcurrent relays sensing ground
(residual) current. Relays shall be wired to trip the associated
circuit breaker upon a current exceeding the tap setting in the
direction indicated. Relays shall have a current and voltage polarized
directional unit and an inverse time characteristic overcurrent unit.
Relays shall be voltage polarized. Auxiliary potential transformers
shall be provided to obtain polarizing voltage. Overcurrent unit shall
have a tap range of [_____] to [_____] amperes.[ Relays shall be Type
[_____].]
f. Lockout relays (device 86): Provide hand reset, electrically tripped,
high-speed auxiliary relays where indicated. Relays shall be tripped
by the indicated devices and shall be wired to trip the associated
circuit breaker and prohibit closing of the circuit breaker by local
and remote controls until the lockout relay has been reset by hand to
its normal position. Each relay shall be provided with the number of
contacts required to perform the indicated function and, in addition,
shall have a minimum of two spare normally closed contacts and two
spare normally open contacts.
g. Bus differential relays (device 87B): Provide a set of three high-
speed, high-impedance, single-phase bus differential relays, wired to
trip the circuit breakers connected to the protected bus upon
occurrence of a fault within the zone of protection. Relays shall not
trip the circuit breakers on through current to a fault outside the
zone of protection. Current signals shall be obtained from dedicated
current transformers. Bus differential relay shall include a voltage-
operated unit which shall operate in three to six cycles for low-
magnitude faults and a current-operated unit which shall operate in one
to three cycles on moderate to severe faults. Relay shall include a
thyrite voltage-limiting unit. Voltage-operated unit shall have an
adjustment range of 75 to 500 V. Current-operated unit shall have an
adjustment range of 2 to 50 amperes.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 11 13.00 20 Page 27
[h. Trip blocking test switches: Trip blocking test switches shall be
provided to block tripping of 34.5-kV circuit breakers from the bus
differential lockout relay. Trip blocking test switches shall be back-
connected knife switches in a semiflush panel-mounted insulating case
with removable clear glass or acrylic cover. Knife switches shall be
rated for at least 125 Vdc and 30 amperes. Knife switches shall have
an insulated operating knob.
][i. Transformer differential relays (device 87T): Provide a set of three
high-speed, percentage differential relays for protection of three-
phase, delta-wye, two-winding transformer. Relays shall sense phase
currents from the transformer primary current transformers and
transformer secondary breaker current transformers. Relays shall trip
the primary circuit breakers and the transformer secondary breakers.
Relays shall have a sensitive differential unit to detect faults within
the protected zone. Relays shall have a harmonic restraint unit to
prevent tripping on transformer inrush current and two restraint
transformers to prevent tripping on through-current to a fault outside
the zone. Relays shall have a sensitivity of 0.35 times the tap value.
Relays shall have ratio taps in the range of 2.9 to 8.7 amperes.
Relays shall be Type [_____].
][j. Fault pressure relay (device 63): Provide a fault pressure relay
sensitive to rate of rise of transformer tank pressure to detect
internal faults in transformer windings. Fault pressure relay shall be
wired to a compatible auxiliary seal-in relay (Device 63X), which shall
trip primary circuit breakers and transformer secondary breakers of the
associated transformer via a lockout relay. Fault pressure relay shall
be transformer mounted and auxiliary relay shall be panel mounted in a
semiflush case. Auxiliary relay shall have trip-indicating targets.
]k. Thermal relay (device 49): Provide a winding thermal relay, with
associated accessories. Equipment shall indicate the winding
temperature of the transformer, provide automatic cooling fan control,
and shall have one spare single-pole, double-throw contact for remote
indication of overtemperature for connection to a future Supervisory
Control and Data Acquisition (SCADA) System.
l. Auxiliary control relays: Provide as required to implement protective
functions and interlocking as indicated. Auxiliary relays shall have
contacts rated to carry 30 amperes for one minute and 12 amperes
continuously. Coils shall be a long-life design with a projected
service life of 40 years.
1. Auxiliary relays used for tripping circuit breakers shall be
multicontact, high-speed relays operating in one-half cycle or
less.
2. Auxiliary relays for functions other than tripping circuit breakers
shall be normal-speed relays operating in two cycles or less.
3. Auxiliary timing relays shall be electro-pneumatic relays with
contacts rated for at least the load they are controlling.
2.2.6.2 Instruments
***************************************************************************
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 11 13.00 20 Page 28
NOTE: Select essential instruments and meters. Add
to the specification any special metering not listed
which is required for a specific project. Use of an
Electronic Monitoring System and Electronic Trip
Assemblies in the breakers may eliminate the need for
many individual electro-mechanical meters. This may
also be accomplished on simpler systems by using the
electronic watthour meter and identifying the desired
special programming features. For NAVFAC SE
projects, provide three thermal demand ammeters.
***************************************************************************
ANSI C39.1 for electrical indicating switchboard instruments, with one
percent accuracy class, antiparallax pointer, and glare-free face with
scales as indicated and coordinated to the ratios of the current and
potential transformers provided. AC ammeters and voltmeters shall be a
minimum of [50][115] mm ([2][4 1/2] inches) square, with 4.36 rad (250
degree )scale. Provide single-phase indicating instruments with flush-
mounted transfer switches for reading three phases.
a. AC ammeters: Transformer rated, 5-ampere input, 60 Hz.
b. AC voltmeters: Transformer rated, 150-volt input, 60 Hz.[ Provide
external dropping resistors.]
c. AC wattmeters: Transformer rated for 120-volt input, 60 Hz, three-
phase, four-wire, with scale range coordinated to the ratios of the
associated current transformers and potential transformers.[ Provide
external dropping resistors.]
d. Frequency meters: Rated for 120-volt input, 60 Hz nominal frequency,
[_____] to [_____] Hz scale range.
e. Synchroscope: Transformer rated at 120-volt input, 60 Hz, with slow-
fast scale.
f. Power-factor meters: Transformer rated 5-ampere, [120][208]-volt
input, [_____] scale range for use on [three][four]-wire, three-phase
circuits. The accuracy shall be plus or minus 0.01.
g. DC ammeters: [Self-contained][Shunt-rated], [0 to [_____]
ampere][[_____] to 0 to [_____] ampere] scale range.
h. DC voltmeters: Self-contained, [0 to [_____] volt][[_____] to 0 volt]
scale range. Furnish resistors, if required, with the voltmeter.
2.2.6.3 Instrument Control Switches
Provide rotary cam-operated type with positive means of indicating contact
positions. Switches shall have silver-to-silver contacts enclosed in a
protective cover which can be removed to inspect the contacts.
2.2.6.4 Electronic Watthour Meter
***************************************************************************
NOTE: On standard projects, use of the electronic
meter versus the optional electro-mechanical meter is
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 11 13.00 20 Page 29
recommended due to decreasing availability of
electro-mechanical meters.
***************************************************************************
Provide a switchboard style electronic programmable watthour meter, semi-
drawout, semi-flush mounted, [in the outgoing section][as indicated]. Meter
shall either be programmed at the factory or shall be programmed in the
field. When field programming is performed, turn field programming device
over to the Contracting Officer at completion of project. Meter shall be
coordinated to system requirements.
a. Design: Provide meter designed for use on a 3-phase, 4-wire, [___/___]
volt system with 3 current transformers. Include necessary KYZ pulse
initiation hardware for Energy Monitoring and Control System (EMCS)[ as
specified in Section 23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC].
b. Coordination: Provide meter coordinated with ratios of current
transformers and transformer secondary voltage.
c. Class: [_____]. Form: [_____]. Accuracy: plus or minus 1.0 percent.
Finish: Class II.
d. Kilowatt-hour Register: 5 digit electronic programmable type.
e. Demand Register:
1. Provide solid state.
2. Meter reading multiplier: Indicate multiplier on meter face.
3. Demand interval length: shall be programmed for [15][30][60]
minutes with rolling demand up to six subintervals per interval.
f. Meter fusing: Provide a fuse block mounted in the metering compartment
containing one fuse per phase to protect the voltage input to the
watthour meter. Size fuses as recommended by the meter manufacturer.
[g. Special Programming Instructions: [_____].
]2.2.6.5 Electro-mechanical Watthour Meters
***************************************************************************
NOTE: On bases that employ Energy Monitoring and
Control Systems (EMCS) and monitor each building
individually, add the following to this paragraph:
"Provide watthour meter with a three-wire, single-
pole double-throw, quick-make, quick-break pulse
initiator. Coordinate pulse output ratio with main
circuit breaker rating."
***************************************************************************
NEMA/ANSI C12.10. Kilowatt-hour meters shall be transformer rated,
polyphase, 60 Hz, semiflush mounted, drawout or semidrawout switchboard
meters for use on a four-wire wye, three-phase system. Kilowatt-hour meters
shall be [two and one-half][three]-stator.[ Totalizing kilowatt-hour meters
shall be four-stator, two-circuit. For totalizing meters, provide devices
and equipment required to provide single point metering of real power and
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 11 13.00 20 Page 30
reactive power from two inputs as indicated.] Each meter shall have a five-
dial pointer type register and shall be secondary reading. Register ratio
shall be selected to provide a meter reading multiplier of even hundreds
after applying the product of the current transformer ratio and the
potential transformer ratio. Indicate the meter reading multiplier on the
meter face. The kilowatt-hour meter shall have a [sweep hand][cumulative]
type KW demand register with 15-minute interval conforming to NEMA C12.4.
2.2.6.6 Electric Strip-Chart Recording AC Wattmeter
UL 1437 for [surface][semiflush] mounting. Chart speed shall be [_____] mm
([_____] inches)per [hour][minute] and chart drive motor shall be rated
[240][120][120/240] V, 60 Hz. The instrument shall have a full scale
accuracy of one percent.
2.2.6.7 Instrument Transformers
IEEE C57.13, as applicable.
a. Current transformers: Transformers shall be [multi-ratio][ or ][single
ratio] as indicated, 60 Hz, and coordinated to the rating of the
associated switchgear, relays, meters, and instruments.
b. Potential transformers: Transformers shall be drawout type, 60 Hz,
with voltage ratings and ratios coordinated to the ratings of the
associated switchgear, relays, meters, and instruments. Potential
transformers shall be with [one fuse][two fuses] in the primary. Fuses
shall be current limiting and sized as recommended by the potential
transformer manufacturer.
2.2.6.8 Heaters
Provide 120-volt heaters in each switchgear section. Heaters shall be of
sufficient capacity to control moisture condensation in the compartments,
and shall be sized 250 watts minimum. Heaters shall be controlled by a
thermostat[ and humidistat] located inside each section. Thermostats shall
be industrial type, high limit, to maintain compartments within the range of
15 to 32 degrees C (60 to 90 degrees F).[ Humidistats shall have a range of
30 percent to 60 percent relative humidity.] Provide transformer rated to
carry 125 percent of heater full load rating. Transformers shall have 220
degrees C insulation system with a temperature rise not exceeding 115
degrees C and shall conform to NEMA ST 20. Provide panelboard and circuit
breakers in each switchgear assembly to serve the heaters in that switchgear
assembly. Energize electric heaters in switchgear assemblies while the
equipment is in storage or in place prior to being placed in service.
Provide method for easy connection of heater to external power source.
2.2.6.9 Pilot and Indicating Lights
Provide transformer, resistor, or diode type.
2.2.7 Station Batteries and Charger
***************************************************************************
NOTE: For NAVFAC SE projects, specify maintenance-
free sealed batteries only.
***************************************************************************
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 11 13.00 20 Page 31
Provide station batteries and charger, suitable for the requirements of the
switchgear and [vacuum][SF6] circuit breakers. Batteries shall be [_____]
V, 60 cells, lead-acid, [pasted plate type][ or ][sealed, totally absorbed
electrolyte type].
a. Pasted plate type batteries: Positive plates shall be of the
manchester type and negative plates shall have a life equal to or
greater than the positive plates. Battery containers shall be heat and
impact resistant clear plastic with electrolyte level lines permanently
marked on all four sides. A permanent leakproof seal shall be provided
between cover and container and around cell posts. Sprayproof vent
plugs shall be provided in covers. Sufficient sediment space shall be
provided so that the battery will not have to be cleaned out during its
normal life. High porosity separators to provide correct spacing
between plates shall be provided. Capacity shall be calculated by
switchgear manufacturer and approved by Contracting Officer before
acceptance.
b. Sealed batteries: Provide batteries with leakproof, spillproof
electrolyte utilizing highly absorbent material to separate the
positive and negative plates. Battery jars shall be hermetically
sealed with welded seams. Batteries shall be maintenance-free and
shall not require water to be added. Capacity shall be calculated by
switchgear manufacturer and approved by Contracting Officer before
acceptance.
c. Battery charger shall be full-wave rectifier type, utilizing silicon
semiconductor devices. Charger shall maintain a float charge of 2.15 V
per cell and an equalizing charge of 2.33 V per cell. An equalizing
charge timer shall be provided which operates automatically after an AC
power failure of 5 seconds or more. Timer shall be adjustable for any
time period up to 24 hours. Timer shall also be capable of being
actuated manually. Adjustable float and equalizing voltage
potentiometers shall be provided. Charger voltage shall be maintained
within plus or minus 1/2 percent from no load to full load with AC line
variations of plus or minus 10 percent and frequency variations of plus
or minus 5 percent. DC voltmeter and ammeter with a minimum 90 mm (3
1/2 inch) scale and 2 percent accuracy of full scale shall be provided.
Output current shall be limited to 115 percent of rated output current,
even down to short circuit of the DC output terminals. Solid state
circuit shall have AC and DC transient voltage terminals. AC and DC
magnetic circuit breakers shall be provided. Circuit breakers shall
not be overloaded or actuated under any external circuit condition,
including recharge of a fully discharged battery and short circuit of
the output terminals. Charger shall be capable of continuous operation
at rated current at an ambient temperature of 40 degrees C. Output DC
current capacity shall match the requirements of the batteries
provided.
d. Secure battery rack such that it can not overturn or be disrupted by
lateral forces accompanying a seismic disturbance. Provide steel,
three-step racks, painted with two coats of acid resistant paint for
mounting batteries. Provide lead-plated copper inter-rack connectors
and cell numbers with each rack.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 11 13.00 20 Page 32
2.2.8 Metal-Enclosed Interrupter Switchgear Outgoing Section
***************************************************************************
NOTE: This paragraph may also be used to specify
freestanding switchgear not directly connected to a
unit substation. This paragraph can not be used for
generator control switchgear. Specify Category A
requirements when switchgear area is subject to
access by the unsupervised general public. Category
B enclosures must be fence enclosed or in a locked
room.
***************************************************************************
***************************************************************************
NOTE: To help determine whether metal-clad
switchgear or metal-enclosed interrupter switchgear
is more appropriate for a project, consider that the
primary applications for interrupter switchgear are
where there are no instantaneous relaying and where
switching is infrequent. Also interrupter switchgear
is significantly less costly than metal-clad
switchgear.
***************************************************************************
IEEE C37.20.3 for metal-enclosed [air][vacuum][SF6] load interrupter type
switches, insulated for [5][15][27] kV for use on [_____] kV system. The
metal-enclosed switchgear assembly shall consist of individual, factory-
assembled, freestanding modular units, each with provisions for bolt-
together installation. Modules shall have uniform dimensions, constructed
of rigidly braced 14-gage steel with a durable corrosion-resistant finish.
Units shall include a removable front panel, capable of being locked, for
access to cable connections and fusing, internal venting for air
circulation, lifting/mounting provisions and centralized, front facing
controls[ with mimic bus line diagram] and identification nameplates.
Modules shall allow incoming/outgoing cable entry from the bottom, sides or
rear with adequate access for training and connection of cable using lugs
and indoor terminations. Modular units shall include necessary provisions
for future expansion with removable end covers and extendable high-
conductivity copper main and ground bus interconnections. Main bus shall be
fully insulated and mounted on insulated supports of high-impact, non-
tracking, high-quality insulating material. Bus shall be braced to
withstand the mechanical forces exerted during short-circuit conditions when
connected directly to a source having maximum of [_____] amperes rms
symmetrical available. Phase bus bars shall be rated [_____] amperes.
Ground bus shall be sized for full short-circuit capacity and shall include
provisions for external ground connections. Enclosures shall be designed
for [indoor][outdoor] location and shall conform to Category [A][B]
requirements of Table A1 of Appendix A to IEEE C37.20.3. Provide permanent
labels for wiring and terminals corresponding to the designations on
approved shop drawings. A safety glass window shall be provided in the door
panel in front of each interrupter switch to observe its position.
[2.2.8.1 Air-Insulated Load Interrupter Switches
***************************************************************************
NOTE: Choose this paragraph or one of the
subparagraphs below entitled, "SF6-Insulated Load
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 11 13.00 20 Page 33
Interrupter Switches" or "Vacuum-Insulated Load
Interrupter Switches."
***************************************************************************
Load interrupter switches shall be three-pole, gang-operated, [fused][non-
fused], arranged with hinge end of switch on load side to provide for "dead
blade."[ Fuses shall be located on hinge side of switch.] Switch handles
shall be non-removable, operable from front of cubicle. Switch shall be
equipped with stored-energy, quick-make and quick-break device to operate
the switch independent of the handle or power operator speed. Load
interrupter switches shall be rated at [600][1200] amperes continuous, 61 kA
momentary, 38 kA short-time fault closing. Switches shall be [manual handle
operated "close" and "open"][manual handle operated "close" and remote
operated "open" by electrical release device][power operated "close" and
"open" utilizing motor charged closing spring mechanism and electrical
release device].
][2.2.8.2 SF6-Insulated Load Interrupter Switches
SF6 filled, puffer-type load interrupter switches shall be [fused][ or
][non-fused] as indicated. Switches shall incorporate self-aligning,
copper-silver plated, wiping-type contacts. SF6 puffer interrupters to
minimize arcing during operation; and an internal absorbent to neutralize
arc by-products. Switch contacts shall be enclosed and sealed in
maintenance-free, SF6 filled, molded epoxy insulated case, surrounded by
dead-front metallic barriers. Switch operation shall be controlled by
permanently lubricated quick-make, quick-break spring operator with solid
linkage connection to contact operating shaft. Switch operator shall be
mounted in separate dead-front compartment with access for addition of
remote or automatic accessories, and shall include removable operating
handle with storage provision, positive position indicators, and padlock
provisions. SF6 gas shall conform to ASTM D2472.[ Fused load interrupter
switches shall be provided with clip-style, mounted air-insulated current
limiting fuses and molded epoxy interphase barriers. Provide neon voltage
indicators for blown fuse indication.] Load interrupter switch shall be
rated [_____] continuous, [_____] kA momentary, [_____] kA short-time fault
closing.
][2.2.8.3 Vacuum-Insulated Load Interrupter Switches
Circuit interrupting device shall be [fused][non-fused], fixed mounted,
[manually][electrically] operated, and shall be quick-make, quick-break with
speed of operation independent of the operator. Electrically operated
device shall be [120 Vac][125 Vdc]. Spring charging mechanism shall not
rely on chains or cables.[ Motor operator assembly shall be a separate
device, isolated from high voltage and coupled through a direct drive
shaft.] Circuit interrupter shall consist of automatic visible blade
disconnects in series with vacuum interrupters. Arc interruption shall take
place within the envelope of the vacuum interrupter. Upon opening, contacts
in the vacuum interrupter shall separate 12 to 18 milliseconds before
disconnect blades open. Total circuit interrupt opening time shall not
exceed 3.0 cycles after the trip coil is energized at 85 to 100 percent of
rated control voltage. Upon closing, disconnect blades shall close 9 to 12
milliseconds before contact is made in the vacuum interrupter. Local
interrupter switch shall be rated [_____] continuous, [_____] kA momentary,
[_____] kA short-time fault closing.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 11 13.00 20 Page 34
][2.2.8.4 Fuses
***************************************************************************
NOTE: Other fuse types may be specified if more
appropriate to the project.
***************************************************************************
IEEE C37.41 and IEEE C37.46 as applicable. High-voltage fuses and non-
disconnecting fuse mountings shall be accessible only through a separate
door mechanically interlocked with the load break switch, to ensure the
switch is in the open position when fuses are accessible. Switch shall be
designed with full height fuse access doors and shall have a solid barrier
covering the area of the main cross bus and line side of the switch. Metal
screen barriers are not acceptable. No energized parts shall be within
normal reach of the opened doorway. Four single full length interphase
barriers shall isolate the three phases of the switch from each other and
from the enclosures. Fuses shall be [current limiting type of self-
contained design to limit available fault current stresses on the system and
shall have interrupting capacity [as indicated][of [_____] amperes
symmetrical rms].][boric acid type with provisions for refill units complete
with muffler exhaust. Furnish three spare fuse refill units for each switch
and fuse assembly.] Fuses shall be affixed in position with provisions for
removal and replacement from the front of the gear without the use of
special tools.
]2.2.9 Insulated Barriers
Where insulated barriers are required by reference standards, provide
barriers in accordance with NEMA LI 1, Type GPO-3, 6.35 mm (0.25 inch)
minimum thickness.
[2.2.10 SF6 Refill Cylinders
***************************************************************************
NOTE: Coordinate with activity to determine if
refill cylinders are required. Many activities have
an adequate supply of SF6 gas on hand.
***************************************************************************
Provide two SF6 refill cylinders, with a minimum of 2.724 kg (6 pounds) of
SF6 in each. Include regulator, valves, and hose for connection to the fill
valve of the switch.
]2.2.11 Corrosion Protection
***************************************************************************
NOTE: Choose the level of corrosion protection
required for the specific project location. Use
stainless steel bases for most applications. In less
corrosive environments galvanized steel can be
included as an alternative to stainless steel. In
hostile environments, the additional cost of totally
stainless steel tanks and metering may be justified.
Manufacturer's standard construction material is
acceptable only in noncoastal and noncorrosive
environments.
***************************************************************************
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 11 13.00 20 Page 35
Bases frames, and channels of unit substation shall be corrosion resistant
and shall be fabricated of stainless steel[ or galvanized steel]. Base
shall include any part of unit substation that is within 75 mm (3 inches) of
concrete pad. Paint unit substation, including bases, light gray No. 61 or
No. 49.[ Paint coating system shall comply with IEEE C57.12.28 regardless
of base and substation material.] The color notation is specified in ASTM
D1535.
2.2.11.1 Stainless Steel
ASTM A167, Type 304 or 304L.
[2.2.11.2 Galvanized Steel
ASTM A123/A123M, ASTM A653/A653M G90 coating, and ASTM A153/A153M, as
applicable. Galvanize after fabrication where practicable.
]2.2.12 Terminal Boards
Provide with engraved plastic terminal strips and screw type terminals for
external wiring between components and for internal wiring between removable
assemblies. Terminal boards associated with current transformers shall be
short-circuiting type. Terminate conductors for current transformers with
ring-tongue lugs. Terminal board identification shall be identical in
similar units. External wiring shall be color coded consistently for
similar terminal boards.
2.2.13 Wire Marking
Mark control and metering conductors at each end. Provide factory-installed
white plastic tubing heat stamped with black block type letters on factory-
installed wiring. On field-installed wiring, provide multiple white
preprinted polyvinyl chloride (PVC) sleeves, heat stamped with black block
type letters. Each sleeve shall contain a single letter or number, shall be
elliptically shaped to fit the wire securely, and shall be keyed, or
otherwise arranged, in such a manner to ensure alignment with adjacent
sleeves. Provide specific wire markings using the appropriate combination
of individual sleeves. Wire markers for factory installed conductors shall
indicate wire designations corresponding to the schematic drawings. Wire
markers on field installed conductors shall indicate the device or
equipment, including specific terminal number to which the remote end of the
wire is attached, as well as the terminal number to which the wire is
directly attached (near end/far end marking).
2.2.14 Surge Arresters
Provide one surge arrester for each conductor on circuits where indicated.
Surge arresters shall conform to IEEE C62.11 for [station class][class
indicated] and shall be rated [_____] kV.
2.3 SOURCE QUALITY CONTROL
***************************************************************************
NOTE: Use "reserves the right to" on all projects,
except those for NAVFAC SE.
***************************************************************************
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 11 13.00 20 Page 36
2.3.1 Equipment Test Schedule
The Government [reserves the right to][will] witness tests. Provide
equipment test schedules for tests to be performed at the manufacturer's
test facility. Submit required test schedule and location, and notify the
Contracting Officer 30 calendar days before scheduled test date. Notify
Contracting Officer 15 calendar days in advance of changes to scheduled
date.
a. Test Instrument Calibration
1. The manufacturer shall have a calibration program which assures
that all applicable test instruments are maintained within rated
accuracy.
2. The accuracy shall be directly traceable to the National Institute
of Standards and Technology.
3. Instrument calibration frequency schedule shall not exceed 12
months for both test floor instruments and leased specialty
equipment.
4. Dated calibration labels shall be visible on all test equipment.
5. Calibrating standard shall be of higher accuracy than that of the
instrument tested.
6. Keep up-to-date records that indicate dates and test results of
instruments calibrated or tested. For instruments calibrated by
the manufacturer on a routine basis, in lieu of third party
calibration, include the following:
(a) Maintain up-to-date instrument calibration instructions and
procedures for each test instrument.
(b) Identify the third party/laboratory calibrated instrument to
verify that calibrating standard is met.
[2.3.2 Integral Assembly Test
***************************************************************************
NOTE: Coordinate with paragraph "Factory Test
Reports" prior to use of option requiring testing of
integral assemblies.
***************************************************************************
Switchgear and substation transformer shall be tested as an integral
assembly at the transformer manufacturer's test facility. Once acceptance
of test results is received, ship switchgear and substation.
]2.3.3 Switchgear Design Tests
IEEE C37.20.2 or IEEE C37.20.3 as applicable. Furnish documentation showing
the results of design tests on a product of the same series and rating as
that provided by this specification. Required tests shall be as follows:
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 11 13.00 20 Page 37
a. Design Test
[1. Dielectric test
][2. Rated continuous current test
][3. Short-time current withstand tests
][4. Short-circuit current withstand tests
]5. Mechanical endurance tests
6. Flame-resistance tests
7. Rod entry tests
[8. Rain test for outdoor MV switchgear
]2.3.4 Switchgear Production Tests
IEEE C37.20.2 or IEEE C37.20.3 as applicable. Furnish reports which include
results of production tests performed on the actual equipment for this
project. Required tests shall be as follows:
a. Production Test
1. Dielectric test
2. Mechanical operation tests
3. Grounding of instrument transformer case test
4. Electrical operation and control-wiring tests
5. Impulse withstand test.
2.3.5 Load Interrupter Switch Design Tests
IEEE C37.71 or NEMA C37.72 as applicable, and IEEE C37.20.3. Furnish
documentation showing the results of design tests on a product of the same
series and rating as that provided by this specification. Required tests
shall be as follows:
a. Design Tests
1. Dielectric:
(a) Low-frequency withstand
(b) Impulse withstand
2. Continuous current
3. Short-time current withstand (2 - second)
4. Momentary current (10 cycles)
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 11 13.00 20 Page 38
5. Mechanical endurance
6. Insulator supports
(a) Flame-resistance
(b) Tracking-resistance
7. Bus-bar insulation
(a) Dielectric strength
(b) Flame-resistance
8. Paint qualification
9. Rain
2.3.6 Load Interrupter Switch Production Tests
IEEE C37.71 or NEMA C37.72 as applicable, and IEEE C37.20.3. Furnish
reports of production tests performed on the actual equipment for this
project. Required tests shall be as follows:
a. Production Tests
1. Dielectric
2. Mechanical operation
[3. Grounding of instrument transformer case
][4. Electrical operation and control wiring
]2.3.7 Transformer Design Tests
In accordance with IEEE C57.12.00 and IEEE C57.12.90. Additionally, IEEE
C57.12.80, section 5.1.2 states that "design tests are made only on
representative apparatus of basically the same design." Submit design test
reports (complete with test data, explanations, formulas, and results), in
the same submittal package as the catalog data and drawings for[ each of]
the specified transformer(s). Design tests shall have been performed prior
to the award of this contract.
a. Tests shall be certified and signed by a registered professional
engineer.
b. Temperature rise: "Basically the same design" for the temperature rise
test means a unit-substation transformer with the same coil
construction (such as wire wound primary and sheet wound secondary),
the same kVA, the same cooling type (ONAN), the same temperature rise
rating, and the same insulating liquid as the transformer specified.
c. Lightning impulse: "Basically the same design" for the lightning
impulse dielectric test means a unit-substation transformer with the
same BIL, the same coil construction (such as wire wound primary and
sheet wound secondary), and a tap changer (if specified). Design
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 11 13.00 20 Page 39
lightning impulse tests shall include both the primary and secondary
windings of that transformer.
1. IEEE C57.12.90 paragraph entitled "Lightning Impulse Test
Procedures" and IEEE C57.98.
2. State test voltage levels.
3. Provide photographs of oscilloscope display waveforms or plots of
digitized waveforms with test report.
d. Lifting and moving devices: "Basically the same design" for the
lifting and moving devices test means a transformer in the same weight
range as the transformer specified.
e. Pressure: "Basically the same design" for the pressure test means a
unit-substation transformer with a tank volume within 30 percent of the
tank volume of the transformer specified.
2.3.8 Transformer Routine and Other Tests
In accordance with IEEE C57.12.00 and IEEE C57.12.90. Routine and other
tests shall be performed by the manufacturer on[ each of] the actual
transformer(s) prepared for this project to ensure that the design
performance is maintained in production. Submit test reports, by serial
number and receive approval before delivery of equipment to the project
site. Required tests and testing sequence shall be as follows:
a. Cold resistance measurements (provide reference temperature)
b. Phase relation
c. Ratio
d. Insulation power-factor by manufacturer's recommended test method.
e. No-load losses (NLL) and excitation current
f. Load losses (LL) and impedance voltage
g. Dielectric
1. Impulse: Per IEEE C57.12.90 paragraph 10.3 entitled "Lightning
Impulse Test Procedures," and IEEE C57.98. Test the primary
winding only.
(a) State test voltage levels
(b) Provide photographs of oscilloscope display waveforms or
plots of digitized waveforms with test reports.[ As an
alternative, photographs of oscilloscope display waveforms or plots
of digitized waveforms may be hand-delivered at the factory witness
test.]
2. Applied voltage
3. Induced voltage
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 11 13.00 20 Page 40
h. Leak
PART 3 EXECUTION
3.1 INSTALLATION
Electrical installations shall conform to IEEE C2, NFPA 70, and to the
requirements specified herein.
3.2 GROUNDING
***************************************************************************
NOTE: Where rock or other soil conditions prevent
obtaining a specified ground value, specify other
methods of grounding. Where it is impractical to
obtain indicated ground resistance values, the
designer should make every effort, to obtain ground
resistance values as near as possible to the
indicated values.
***************************************************************************
NFPA 70 and IEEE C2, except that grounds and grounding systems shall have a
resistance to solid earth ground not exceeding 5 ohms.
3.2.1 Grounding Electrodes
Provide driven ground rods as specified in Section 33 71 02 UNDERGROUND
ELECTRICAL DISTRIBUTION. Connect ground conductors to the upper end of the
ground rods by exothermic welds or compression connectors. Provide
compression connectors at equipment ends of ground conductors.
3.2.2 Substation Grounding
Provide bare copper cable not smaller than No. 4/0 AWG, not less than 610 mm
(24 inches) below grade connecting to the indicated ground rods. Substation
transformer neutral connections shall not be smaller than No. 1/0 AWG. When
work, in addition to that indicated or specified, is directed to obtain the
specified ground resistance, the provision of the contract covering
"Changes" shall apply.[ Fence and equipment connections shall not be
smaller than No. 4 AWG. Ground fence at each gate post and corner post and
at intervals not exceeding 3050 mm (10 feet). Bond each gate section to the
fence post through a 3 by 25 mm (1/8 by one inch) flexible braided copper
strap and clamps.]
3.2.3 Connections
Make joints in grounding conductors and loops by exothermic weld or
compression connector. Exothermic welds and compression connectors shall be
installed as specified in Section 33 71 02 UNDERGROUND ELECTRICAL
DISTRIBUTION, paragraph regarding "Grounding".
3.2.4 Ground Cable Crossing Expansion Joints in Structures and Pavements
Protect from damage by means of approved devices or methods of installation
to allow the necessary slack in the cable across the joint to permit
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 11 13.00 20 Page 41
movement. Provide stranded or other approved flexible copper cable across
such separations.
3.2.5 Grounding and Bonding Equipment
UL 467, except as indicated or specified otherwise.
3.3 INSTALLATION OF EQUIPMENT AND ASSEMBLIES
Install and connect unit substations furnished under this section as
indicated on project drawings, the approved shop drawings, and as specified
herein.
3.3.1 Medium-Voltage Switchgear and Load Interrupter Switches
IEEE C37.20.2 and IEEE C37.20.3 as applicable.
3.3.2 Meters and Instrument Transformers
ANSI C12.1.
3.3.3 Galvanizing Repair
Repair damage to galvanized coatings caused by handling, transporting,
cutting, welding, or bolting. Make repairs in accordance with ASTM
A780/A780M, zinc rich paint. Do not heat surfaces that repair paint has
been applied to.
3.4 FOUNDATION FOR EQUIPMENT AND ASSEMBLIES
***************************************************************************
NOTE: Mounting slab connections may have to be given
in detail depending on the requirements for the
seismic zone in which the equipment is located.
Include construction requirements for concrete slab
only if slab is not detailed in drawings. Curbs or
raised edges may also be required around liquid
filled transformers.
***************************************************************************
3.4.1 Exterior Location
Mount[ substation][ and][ switchgear] on concrete slab. Unless otherwise
indicated, the slab shall be at least 200 mm (8 inches) thick, reinforced
with a 152 by 152 - MW19 by MW19 (6 by 6 - W2.9 by W2.9) mesh, placed
uniformly 100 mm (4 inches) from the top of the slab. Slab shall be placed
on a 150 mm (6 inch) thick, well-compacted gravel base. Top of concrete
slab shall be approximately 100 mm (4 inches) above finished grade. Edges
above grade shall have 15 mm (1/2 inch) chamfer. Slab shall be of adequate
size to project at least 200 mm (8 inches) beyond equipment, except that
front of slab shall be large enough to serve as a platform to withdraw
breakers or to operate two-high breaker lifters. Provide conduit turnups
and cable entrance space required by the equipment to be mounted[ and as
indicated]. Seal voids around conduit openings in slab with water- and oil-
resistant caulking or sealant. Cut off and bush conduits 75 mm (3 inches)
above slab surface. Concrete work shall be as specified in Section 03 30 00
CAST-IN-PLACE CONCRETE.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 11 13.00 20 Page 42
3.4.2 Interior Location
Mount[ substation][ and][ switchgear] on concrete slab. Unless Otherwise
indicated, the slab shall be at least 100 mm (4 inches) thick. Top of
concrete slab shall be approximately 100 mm (4 inches) above finished floor.
Edges above floor shall have 15 mm (1/2 inch) chamfer. Slab shall be of
adequate size to project at least 200 mm (8 inches) beyond the equipment,
except that front of slab shall be large enough to serve as a platform to
withdraw breakers or to operate two-high breaker lifters. Provide conduit
turnups and cable entrance space required by the equipment to be mounted.
Seal voids around conduit openings in slab with water- and oil-resistant
caulking or sealant. Cut off and bush conduits 75 mm (3 inches) above slab
surface. Concrete work shall be as specified in Section 03 30 00 CAST-IN-
PLACE CONCRETE.
3.5 FIELD QUALITY CONTROL
3.5.1 Performance of Acceptance Checks and Tests
Perform in accordance with the manufacturer's recommendations and include
the following visual and mechanical inspections and electrical tests,
performed in accordance with NETA ATS.[ The [_____] Division, Naval
Facilities Engineering Command will witness formal tests after receipt of
written certification that preliminary tests have been completed and that
system is ready for final test and inspection.]
***************************************************************************
NOTE: Thermographic surveying is not required on
most projects. NETA recommends that surveys be
performed during periods of maximum possible loading
but with not less than 40 percent of rated load on
the electrical equipment being inspected. Testing at
start-up will therefore not be beneficial except for
hard-to-reach areas where solid connections cannot be
verified by mechanical methods. Thermographic
surveying may be useful if equipment operates under
load for a specified period of time, preferably 3 to
6 months, before testing. The additional costs and
the additional trip (3 to 6 months after the initial
inspection) for the NETA contractor to perform the
survey should be considered prior to specifying the
requirement.
***************************************************************************
3.5.1.1 Interrupter Switch(es)
a. Visual and Mechanical Inspection
1. Compare equipment nameplate data with specifications and approved
shop drawings.
2. Inspect physical and mechanical condition.
3. Confirm correct application of manufacturer's recommended
lubricants.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 11 13.00 20 Page 43
4. Verify appropriate anchorage and required area clearances.
5. Verify appropriate equipment grounding.
6. Verify correct blade alignment, blade penetration, travel stops,
and mechanical operation.
[7. Verify that fuse sizes and types correspond to approved shop
drawings.
][8. Verify that each fuse holder has adequate mechanical support.
]9. Verify tightness of accessible bolted electrical connections by
calibrated torque-wrench method. Thermographic surveying[ is not][
is]required.
10. Test interlocking systems for correct operation and sequencing.
11. Verify correct phase barrier materials and installation.
12. Compare switch blade clearances with industry standards.
13. Inspect all indicating devices for correct operation
b. Electrical Tests
1. Perform insulation-resistance tests.
2. Perform over-potential tests.
3. Measure contact-resistance across each switch blade[ and fuse
holder].
[4. Measure fuse resistance.
]5. Verify heater operation.
3.5.1.2 Medium-Voltage Circuit Breakers (Vacuum)
a. Visual and mechanical inspection
1. Compare equipment nameplate data with specifications and approved
shop drawings.
2. Inspect physical and mechanical condition.
3. Confirm correct application of manufacturer's recommended
lubricants.
4. Inspect anchorage, alignment, and grounding.
5. Perform all mechanical operational tests on both the circuit
breaker and its operating mechanism.
6. Measure critical distances such as contact gap as recommended by
manufacturer.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 11 13.00 20 Page 44
7. Verify tightness of accessible bolted connections by calibrated
torque-wrench method. Thermographic survey[ is not][ is] required.
8. Record as-found and as-left operation counter readings.
b. Electrical Tests
1. Perform a contact-resistance test.
2. Verify trip, close, trip-free, and antipump function.
3. Trip circuit breaker by operation of each protective device.
4. Perform insulation-resistance tests.
5. Perform vacuum bottle integrity (overpotential) test across each
bottle with the breaker in the open position in strict accordance
with manufacturer's instructions. Do not exceed maximum voltage
stipulated for this test.
3.5.1.3 Medium-Voltage Circuit Breakers (SF6)
a. Visual and mechanical inspection
1. Compare equipment nameplate data with specifications and approved
shop drawings.
2. Inspect physical and mechanical condition.
3. Confirm correct application of manufacturer's recommended
lubricants.
4. Inspect anchorage and grounding.
5. Inspect and verify adjustments of mechanism in accordance with
manufacturer's instructions.
[6. Inspect and service air compressor in accordance with
manufacturer's instructions.
]7. Test for gas leaks in accordance with manufacturer's instructions.
8. Verify correct operation of all air and SF6 gas pressure alarms
and cutouts.
9. Slow close/open breaker and check for binding.
10. Perform time-travel analysis.
11. Verify tightness of accessible bolted connections by calibrated
torque-wrench method. Thermographic survey[ is not][ is] required.
12. Record as-found and as-left operation counter readings.
b. Electrical Tests
1. Measure contact resistances.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 11 13.00 20 Page 45
2. Perform insulation-resistance tests.
3. Verify trip, close, trip-free, and antipump functions.
4. Trip circuit breaker by operation of each protective device.
3.5.1.4 Transformers (Liquid-Filled)
a. Visual and mechanical inspection
1. Compare equipment nameplate data with specifications and approved
shop drawings.
2. Inspect physical and mechanical condition. Check for damaged or
cracked insulators and leaks.
[3. Verify that cooling fans operate correctly and that fan motors
have correct overcurrent protection.
][4. Verify operation of all alarm, control, and trip circuits from
temperature and level indicators, pressure relief device, and fault
pressure relay.
]5. Verify tightness of accessible bolted electrical connection by
calibrated torque-wrench method. Thermographic survey[ is not][
is] required.
6. Verify correct liquid level in transformer tank.
7. Perform specific inspections and mechanical tests as recommended by
manufacturer.
8. Verify correct equipment grounding.
b. Electrical Tests
1. Perform insulation-resistance tests.
2. Perform turns-ratio tests.
3. Perform insulation power-factor/dissipation-factor tests on
windings.
4. Sample insulating liquid. Sample shall be tested for:
(a) Dielectric breakdown voltage
(b) Acid neutralization number
(c) Specific gravity
(d) Interfacial tension
(e) Color
(f) Visual condition
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 11 13.00 20 Page 46
(g) Parts per million water
(h) Measure dissipation factor or power factor.
5. Perform dissolved gas analysis (DGA).
6. Test for presence of PCB.
7. Verify that tap-changer is set at specified ratio.
8. Verify proper secondary voltage phase-to-phase and phase-to-neutral
after energization and prior to loading.
3.5.1.5 Switchgear Assemblies
a. Visual and Mechanical Inspection
1. Compare equipment nameplate data with specifications and approved
shop drawings.
2. Inspect physical, electrical, and mechanical condition.
3. Confirm correct application of manufacturer's recommended
lubricants.
4. Verify appropriate anchorage, required area clearances, and correct
alignment.
5. Inspect all doors, panels, and sections for paint, dents,
scratches, fit, and missing hardware.
6. Verify that[ fuse and] circuit breaker sizes and types correspond
to approved shop drawings.
[7. Verify that current and potential transformer ratios correspond to
approved shop drawings.
]8. Verify tightness of accessible bolted electrical connections by
calibrated torque-wrench method. Thermographic survey[ is not][
is] required.
9. Confirm correct operation and sequencing of electrical and
mechanical interlock systems.
10. Clean switchgear.
11. Inspect insulators for evidence of physical damage or contaminated
surfaces.
12. Verify correct barrier[ and shutter] installation[ and operation].
13. Exercise all active components.
14. Inspect all mechanical indicating devices for correct operation.
15. Verify that vents are clear.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 11 13.00 20 Page 47
16. Test operation, alignment, and penetration of instrument
transformer withdrawal disconnects.
17. Inspect control power transformers.
b. Electrical Tests
1. Perform insulation-resistance tests on each bus section.
2. Perform overpotential tests.
3. Perform insulation-resistance test on control wiring; Do not
perform this test on wiring connected to solid-state components.
4. Perform control wiring performance test.
5. Perform primary current injection tests on the entire current
circuit in each section of assembly.
[6. Perform phasing check on double-ended switchgear to ensure correct
bus phasing from each source.
]7. Verify operation of heaters.
3.5.1.6 Instrument Transformers
a. Visual and Mechanical Inspection
1. Compare equipment nameplate data with specifications and approved
shop drawings.
2. Inspect physical and mechanical condition.
3. Verify correct connection.
4. Verify that adequate clearances exist between primary and secondary
circuit.
5. Verify tightness of accessible bolted electrical connections by
calibrated torque-wrench method. Thermographic survey[ is not][
is] required.
6. Verify that all required grounding and shorting connections provide
good contact.
7. Verify correct operation of transformer with drawout mechanism and
grounding operation.
8. Verify correct primary and secondary fuse sizes for potential
transformers.
b. Electrical Tests - Current Transformers
1. Perform insulation-resistance tests.
2. Perform polarity tests.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 11 13.00 20 Page 48
3. Perform ratio-verification tests.
4. Perform excitation test on transformers used for relaying
applications.
5. Measure circuit burden at transformer terminals and determine the
total burden.
6. When applicable, perform insulation resistance and dielectric
withstand tests on the primary winding with secondary grounded.
7. CAUTION: Changes of connection, insertion, and removal of
instruments, relays, and meters shall be performed in such a manner
that the secondary circuits of energized current transformers are
not opened momentarily.
c. Electrical Tests - Voltage (Potential) Transformers
1. Perform insulation-resistance tests.
2. Perform a polarity test on each transformer to verify the polarity
marks or H1 - X1 relationships as applicable
3. Perform a turns ratio test on all tap positions , if applicable.
4. Measure potential circuit burdens at transformer terminals and
determine the total burden.
5. Measure circuit burden at transformer terminals and determine the
total burden.
3.5.1.7 Battery Systems
a. Visual and mechanical inspection
1. Compare equipment nameplate data with specifications and approved
shop drawings.
2. Inspect physical and mechanical condition.
3. Verify tightness of accessible bolted electrical connections by
calibrated torque-wrench method. Thermographic survey[ is not] [
is] required.
4. Measure electrolyte specific gravity and temperature and visually
check fill level.
5. Verify adequacy of battery support racks, mounting, anchorage, and
clearances.
b. Electrical tests
1. Set charger float and equalizing voltage levels.
2. Verify all charger functions and alarms.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 11 13.00 20 Page 49
3. Measure each cell voltage and total battery voltage with charger
energized and in float mode of operation.
4. Perform a capacity load test.
3.5.1.8 Metering and Instrumentation
a. Visual and Mechanical Inspection
1. Compare equipment nameplate data with specifications and approved
shop drawings.
2. Inspect physical and mechanical condition.
3. Verify tightness of electrical connections.
b. Electrical Tests
1. Determine accuracy of meters at 25, 50, 75, and 100 percent of full
scale.
2. Calibrate watthour meters according to manufacturer's published
data.
3. Verify all instrument multipliers.
4. Electrically confirm that current transformer and voltage
transformer secondary circuits are intact.
3.5.1.9 Grounding System
a. Visual and Mechanical Inspection
1. Inspect ground system for compliance with contract plans and
specifications.
b. Electrical Tests
1. Perform ground-impedance measurements utilizing the fall-of-
potential method. On systems consisting of interconnected ground
rods, perform tests after interconnections are complete. On
systems consisting of a single ground rod perform tests before any
wire is connected. Take measurements in normally dry weather, not
less than 48 hours after rainfall. Use a portable ground testing
megger in accordance with manufacturer's instructions to test each
ground or group of grounds. The instrument shall be equipped with
a meter reading directly in ohms or fractions thereof to indicate
the ground value of the ground rod or grounding systems under test.
Submit the measured ground resistance of each ground rod and grounding
system, indicating the location of the rod and grounding system.
Include the test method and test setup (i.e., pin location) used to
determine ground resistance and soil conditions at the time the
measurements were made.
[3.5.2 Field Dielectric Tests
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 11 13.00 20 Page 50
***************************************************************************
NOTE: Field dielectric tests are recommended when
new units are added to an existing installation or
after major field modifications. If necessary,
service the equipment prior to the field test.
***************************************************************************
Perform field dielectric tests on medium-voltage switchgear according to
IEEE C37.20.2 or IEEE C37.20.3 as applicable.
]3.5.3 Follow-Up Verification
***************************************************************************
NOTE: Use "10" working days and include last
bracketed sentence in the paragraph for NAVFAC SE
projects.
***************************************************************************
Upon completion of acceptance checks, settings, and tests, the Contractor
shall show by demonstration in service that circuits and devices are in good
operating condition and properly performing the intended function. Circuit
breakers shall be tripped by operation of each protective device. Test
shall require each item to perform its function not less than three times.
As an exception to requirements stated elsewhere in the contract, notify the
Contracting Officer [5][10] working days in advance of the dates and times
for checks, settings, and tests[, to allow the Contracting Officer to notify
NAVFAC SE Code 0742; Electrical Engineering Division and Code 162; Director,
Utilities Engineering Division].
-- End of Section --
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 19.10 Page 1
***************************************************************************
USACE / NAVFAC / AFCEC / NASA UFGS-26 12 19.10 (May 2017)
--------------------------------
Preparing Activity: NAVFAC Superseding
UFGS-26 12 19.10 (February 2012)
UNIFIED FACILITIES GUIDE SPECIFICATIONS
References are in agreement with UMRL dated October 2017
***************************************************************************
SECTION 26 12 19.10
THREE-PHASE PAD-MOUNTED TRANSFORMERS
05/17
***************************************************************************
NOTE: This guide specification covers the
requirements for three-phase pad-mounted transformers
of the dead-front and live-front types for exterior
applications.
Adhere to UFC 1-300-02 Unified Facilities Guide
Specifications (UFGS) Format Standard when editing
this guide specification or preparing new project
specification sections. Edit this guide
specification for project specific requirements by
adding, deleting, or revising text. For bracketed
items, choose applicable item(s) or insert
appropriate information.
Remove information and requirements not required in
respective project, whether or not brackets are
present.
Comments, suggestions and recommended changes for
this guide specification are welcome and should be
submitted as a Criteria Change Request (CCR).
***************************************************************************
***************************************************************************
NOTE: Use pad-mounted transformers (properly
protected with bayonet type, oil-immersed, expulsion
fuses in series with oil-immersed, partial-range,
current-limiting fuses) for kVA ratings up to and
including 1500 kVA on 5 kV systems and for kVA
ratings up to and including 2500 kVA on 15, 25, and
35 kV systems.
For voltages above 35 kV and in ratings above those
previously indicated, this specification requires
significant modifications and additional
specification sections may need to be added on the
project.
This specification is for standard step-down
applications in utility distribution systems. For
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 19.10 Page 2
step-up applications (i.e. solar/wind generation,
etc.), this specification requires significant
modifications to address proper voltage designations,
overcurrent and fault protection, etc.
The use of pad-mounted transformers with secondary
currents exceeding 3000 amperes is discouraged due to
the size and quantity of secondary conductors.
Therefore, transformers above 1000 kVA serving
208Y/120 volt loads and transformers above 2500 kVA
serving 480Y/277 volt loads should be in a secondary
unit substation configuration.
Available fault current level and arc-flash energy
become extremely hazardous at the larger kVA size
transformers. Designer should consider these
parameters and evaluate multiple service points.
***************************************************************************
***************************************************************************
NOTE: For Navy and Air Force projects, this
specification incorporates a "reduced shop drawing
submittal process" for listed manufacturers who
previously satisfied reduced shop drawing submittal
process requirements. This specification also
includes unique routine and other test requirements,
transformer loss certificate, transformer test
schedule, and field quality control acceptance tests
and reports. The preparing activity, NAVFAC LANT,
has significant experience and technical expertise in
these areas. If Reach-back support is desired, for a
specific NAVFAC or Air Force project, the technical
representative (electrical engineer) editing this
document for that project must contact the NAVFAC
LANT Capital Improvements Electrical Engineering
(Code CI44) Office for consultation during the design
stage of the project, prior to including the
requirement in the specification.
***************************************************************************
***************************************************************************
NOTE: Use the following related guide specifications
for power distribution equipment:
--Section 26 08 00 APPARATUS INSPECTION AND TESTING
--Section 26 11 13.00 20 PRIMARY UNIT SUBSTATIONS
--Section 26 11 16 SECONDARY UNIT SUBSTATION
--Section 26 12 21 SINGLE-PHASE PAD-MOUNTED
TRANSFORMERS
--Section 26 13 00 SF6/HIGH-FIREPOINT FLUID INSULATED
PAD-MOUNTED SWITCHGEAR
--Section 26 20 00 INTERIOR DISTRIBUTION SYSTEM
--Section 26 23 00 LOW VOLTAGE SWITCHGEAR
--Section 26 24 13 SWITCHBOARDS
--Section 26 27 13.10 30 ELECTRIC METERS
--Section 26 27 14.00 20 ELECTRICITY METERING
--Section 33 71 01 OVERHEAD TRANSMISSION AND
DISTRIBUTION
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 19.10 Page 3
Do not use the following related guide specifications
except for Army Civil Works projects. They have not
been unified.
--Section 26 11 14.00 10 MAIN ELECTRIC SUPPLY STATION
AND SUBSTATION
--Section 26 28 00.00 10 MOTOR CONTROL CENTERS,
SWITCHBOARDS AND PANELBOARDS
--Section 26 22 00.00 10 480-VOLT STATION SERVICE
SWITCHGEAR AND TRANSFORMERS
***************************************************************************
***************************************************************************
NOTE: Coordination is required between this section
and metering equipment specification sections. See
Section 26 27 14.00 20 ELECTRICITY METERING or 26 27
13.10 30 ELECTRIC METERS for transformer and metering
details, which are available in metric (SI) and U.S.
Customary (IP) system dimension. Use these files to
develop project specific drawings, including:
File Name Description
PADMDE1 Three Phase, Ungrounded or Single Grounded Primary System
- with Surge Arresters
PADMDE2 Three Phase, Ungrounded or Single Grounded Primary System
- without Surge Arresters
PADMDE3 Three Phase, Multi-Grounded Primary System (Delta-Wye) -
with Surge Arresters
PADMDE4 Three Phase, Multi-Grounded Primary System (Delta-Wye) -
without Surge Arresters
PADMDE5 Three Phase, Multi-Grounded Primary System (Wye-Wye) -
with Surge Arresters
PADMDE6 Three Phase, Multi-Grounded Primary System (Wye-Wye) -
without Surge Arresters
ARCFLASH Arc Flash Warning Label
TO DOWNLOAD UFGS GRAPHICS
Go to http://www.wbdg.org/FFC/NAVGRAPH/graphtoc.pdf
Select the appropriate Electrical .ZIP file(s) and
extract the desired details.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 19.10 Page 4
Do not include list of details, or details
themselves, in project specifications. Insert the
appropriate details on drawings and modify optional
and blank items. If special features are required,
do not modify details, but indicate these changes as
notes below the detail.
***************************************************************************
***************************************************************************
NOTE: Show the following information on the project
drawings:
1. Single-line diagram showing pad-mounted
transformer connectors, inserts, surge arresters,
switches, fuses, current transformers with ratings,
and meters as applicable.
2. Grounding plan.
3. Type and number of cables, and size of conductors
for each power circuit.
4. Transformer primary and secondary voltages. (Use
IEEE C57.12.00, Table 8, "Designation of voltage
ratings of three-phase windings (schematic
representation)".) State the primary voltage
(nominal) actually in service and not the voltage
class.
5. Special conditions, such as altitude, temperature
and humidity; exposure to fumes, vapors, dust, and
gases; and seismic requirements.
***************************************************************************
PART 1 GENERAL
1.1 REFERENCES
***************************************************************************
NOTE: This paragraph is used to list the
publications cited in the text of the guide
specification. The publications are referred to in
the text by basic designation only and listed in this
paragraph by organization, designation, date, and
title.
Use the Reference Wizard's Check Reference feature
when you add a Reference Identifier (RID) outside of
the Section's Reference Article to automatically
place the reference in the Reference Article. Also
use the Reference Wizard's Check Reference feature to
update the issue dates.
References not used in the text will automatically be
deleted from this section of the project
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 19.10 Page 5
specification when you choose to reconcile references
in the publish print process.
***************************************************************************
The publications listed below form a part of this specification to the
extent referenced. The publications are referred to within the text by the
basic designation only.
AMERICAN CONCRETE INSTITUTE INTERNATIONAL (ACI)
ACI 318 (2014; Errata 1-2 2014; Errata 3-5 2015;
Errata 6 2016; Errata 7 2017) Building Code
Requirements for Structural Concrete and
Commentary
ACI 318M (2014; ERTA 2015) Building Code Requirements
for Structural Concrete & Commentary
AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)
ANSI C12.1 (2008) Electric Meters Code for Electricity
Metering
ASTM INTERNATIONAL (ASTM)
ASTM A240/A240M (2016) Standard Specification for Chromium
and Chromium-Nickel Stainless Steel Plate,
Sheet, and Strip for Pressure Vessels and for
General Applications
ASTM C260/C260M (2010a; R 2016) Standard Specification for
Air-Entraining Admixtures for Concrete
ASTM D117 (2010) Standard Guide for Sampling, Test
Methods, Specifications and Guide for
Electrical Insulating Oils of Petroleum
Origin
ASTM D1535 (2014) Specifying Color by the Munsell System
ASTM D3487 (2016) Standard Specification for Mineral
Insulating Oil Used in Electrical Apparatus
ASTM D877/D877M (2013) Standard Test Method for Dielectric
Breakdown Voltage of Insulating Liquids Using
Disk Electrodes
ASTM D92 (2012a) Standard Test Method for Flash and
Fire Points by Cleveland Open Cup Tester
ASTM D97 (2017a) Standard Test Method for Pour Point
of Petroleum Products
FM GLOBAL (FM)
FM APP GUIDE (updated on-line) Approval Guide
http://www.approvalguide.com/
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 19.10 Page 6
INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)
IEEE 386 (2016) Separable Insulated Connector Systems
for Power Distribution Systems Rated 2.5 kV
through 35 kV
IEEE C2 (2017; Errata 1-2 2017; INT 1 2017) National
Electrical Safety Code
IEEE C37.47 (2011) Standard for High Voltage Distribution
Class Current-Limiting Type Fuses and Fuse
Disconnecting Switches
IEEE C57.12.00 (2015) General Requirements for Liquid-
Immersed Distribution, Power, and Regulating
Transformers
IEEE C57.12.28 (2014) Standard for Pad-Mounted Equipment -
Enclosure Integrity
IEEE C57.12.29 (2014) Standard for Pad-Mounted Equipment -
Enclosure Integrity for Coastal Environments
IEEE C57.12.34 (2009) Standard for Requirements for Pad-
Mounted, Compartmental-Type, Self-Cooled,
Three-Phase Distribution Transformers, 5 MVA
and Smaller; High Voltage, 34.5 kV Nominal
System Voltage and Below; Low Voltage, 15 kV
Nominal System Voltage and Below
IEEE C57.12.80 (2010) Standard Terminology for Power and
Distribution Transformers
IEEE C57.12.90 (2015; Corr 2017) Test Code for Liquid-
Immersed Distribution, Power, and Regulating
Transformers
IEEE C57.13 (2016) Requirements for Instrument
Transformers
IEEE C57.98 (2011) Guide for Transformer Impulse Tests
IEEE C62.11 (2012) Standard for Metal-Oxide Surge
Arresters for Alternating Current Power
Circuits (>1kV)
IEEE Stds Dictionary (2009) IEEE Standards Dictionary: Glossary of
Terms & Definitions
INTERNATIONAL ELECTRICAL TESTING ASSOCIATION (NETA)
NETA ATS (2017) Standard for Acceptance Testing
Specifications for Electrical Power Equipment
and Systems
NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 19.10 Page 7
ANSI C12.7 (2014) Requirements for Watthour Meter
Sockets
NEMA 260 (1996; R 2004) Safety Labels for Pad-Mounted
Switchgear and Transformers Sited in Public
Areas
NEMA LI 1 (1998; R 2011) Industrial Laminating
Thermosetting Products
NEMA Z535.4 (2011) American National Standard for Product
Safety Signs and Labels
NEMA/ANSI C12.10 (2011) Physical Aspects of Watthour Meters -
Safety Standards
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 70 (2017; ERTA 1-2 2017; TIA 17-1; TIA 17-2; TIA
17-3) National Electrical Code
ORGANISATION FOR ECONOMIC CO-OPERATION AND DEVELOPMENT (OECD)
OECD Test 203 (1992) Fish Acute Toxicity Test
U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA)
EPA 712-C-98-075 (1998) Fate, Transport and Transformation
Test Guidelines - OPPTS 835.3100- "Aerobic
Aquatic Biodegradation"
EPA 821-R-02-012 (2002) Methods for Measuring the Acute
Toxicity of Effluents and Receiving Waters to
Freshwater and Marine Organisms
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
10 CFR 431 Energy Efficiency Program for Certain
Commercial and Industrial Equipment
UNDERWRITERS LABORATORIES (UL)
UL 467 (2013; Reprint Jun 2017) UL Standard for
Safety Grounding and Bonding Equipment
1.2 RELATED REQUIREMENTS
***************************************************************************
NOTE: Include Section 26 08 00 APPARATUS INSPECTION
AND TESTING on all projects involving medium voltage
and specialized power distribution equipment.
***************************************************************************
Section 26 08 00 APPARATUS INSPECTION AND TESTING applies to this section,
with the additions and modifications specified herein.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 19.10 Page 8
1.3 DEFINITIONS
Unless otherwise specified or indicated, electrical and electronics terms
used in these specifications, and on the drawings, are as defined in IEEE
Stds Dictionary.
1.4 SUBMITTALS
***************************************************************************
NOTE: Review Submittal Description (SD) definitions
in Section 01 33 00 SUBMITTAL PROCEDURES and edit the
following list to reflect only the submittals
required for the project.
The Guide Specification technical editors have
designated those items that require Government
approval, due to their complexity or criticality,
with a "G." Generally, other submittal items can be
reviewed by the Contractor's Quality Control System.
Only add a "G" to an item, if the submittal is
sufficiently important or complex in context of the
project.
For submittals requiring Government approval on Army
projects, a code of up to three characters within the
submittal tags may be used following the "G"
designation to indicate the approving authority.
Codes for Army projects using the Resident Management
System (RMS) are: "AE" for Architect-Engineer; "DO"
for District Office (Engineering Division or other
organization in the District Office); "AO" for Area
Office; "RO" for Resident Office; and "PO" for
Project Office. Codes following the "G" typically
are not used for Navy, Air Force, and NASA projects.
Use the "S" classification only in SD-11 Closeout
Submittals. The "S" following a submittal item
indicates that the submittal is required for the
Sustainability eNotebook to fulfill federally
mandated sustainable requirements in accordance with
Section 01 33 29 SUSTAINABILITY REPORTING.
Choose the first bracketed item for Navy, Air Force
and NASA projects, or choose the second bracketed
item for Army projects.
***************************************************************************
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are [for Contractor Quality Control
approval.][for information only. When used, a designation following the "G"
designation identifies the office that will review the submittal for the
Government.] Submittals with an "S" are for inclusion in the Sustainability
eNotebook, in conformance with Section 01 33 29 SUSTAINABILITY REPORTING.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-02 Shop Drawings
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 19.10 Page 9
Pad-mounted Transformer Drawings; G[, [_____]]
SD-03 Product Data
Pad-mounted Transformers; G[, [_____]]
SD-06 Test Reports
Acceptance Checks and Tests; G[, [_____]]
SD-07 Certificates
Transformer Efficiencies; G[, [_____]]
SD-09 Manufacturer's Field Reports
Transformer Test Schedule; G[, [_____]]
Pad-mounted Transformer Design Tests; G[, [_____]]
Pad-mounted TransformerRoutine and Other Tests; G[, [_____]]
SD-10 Operation and Maintenance Data
Transformer(s), Data Package 5; G[, [_____]]
***************************************************************************
NOTE: Include the bracketed option below on Navy and
Air Force projects where "reach-back support" has
already been coordinated with NAVFAC LANT per the 3rd
introductory Technical Note. Add appropriate
information in Section 01 33 00 SUBMITTAL PROCEDURES
to coordinate with the special requirements.
***************************************************************************
[1.4.1 Government Submittal Review
[Code CI44, NAVFAC LANT, Naval Facilities Engineering Command][_____] will
review and approve all submittals in this section requiring Government
approval.
]1.4.2 Reduced Submittal Requirements
Transformers designed and manufactured by ABB in Jefferson City, MO; by
Easton's Cooper Power Series Transformers in Waukesha, WI; by ERMCO in
Dyersburg, TN; or by Howard Industries in Laurel, MS need not submit the
entire submittal package requirements of this contract. Instead, the
following items shall be submitted:
a. A certification, signed by the manufacturer, stating that the
manufacturer will meet the technical requirements of this
specification.
b. An outline drawing of the transformer with devices identified
(paragraph PAD-MOUNTED TRANSFORMER DRAWINGS, item a).
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 19.10 Page 10
c. ANSI nameplate data of the transformer (paragraph PAD-MOUNTED
TRANSFORMER DRAWINGS, item b).
***************************************************************************
NOTE: The designer is responsible for providing
proper settings for secondary over-current device(s)
to ensure proper protection of equipment and
coordination with transformer high side fuses.
Include the following option for transformers serving
secondary over-current devices containing adjustable
trips.
***************************************************************************
[d. Manufacturer's published time-current curves in PDF format and in
electronic format suitable for import or updating into the [EasyPower]
[SKM PowerTools for Windows] [_____] computer program of the
transformer high side fuses (paragraph PAD-MOUNTED TRANSFORMER
DRAWINGS, item e).
]e. Routine and other tests (in PART 2, see paragraph SOURCE QUALITY
CONTROL, subparagraph ROUTINE AND OTHER TESTS), conducted by the
manufacturer. These tests may be witnessed by the government. Provide
transformer test schedule required by submittal item "SD-11 Closeout
Submittals". Provide certified copies of the tests.
f. Provide acceptance test reports required by submittal item "SD-06 Test
Reports".
g. Provide operation and maintenance manuals required by submittal item
"SD-10 Operation and Maintenance Data".
1.5 QUALITY ASSURANCE
1.5.1 Pad-Mounted Transformer Drawings
***************************************************************************
Note: Delete bracketed information for Navy and Air
Force projects when separate metering specification
is used. May still need for Army and NASA projects
until metering specification is unified.
***************************************************************************
Include the following as a minimum:
a. An outline drawing, including front, top, and side views.
b. IEEE nameplate data.
c. Elementary diagrams and wiring diagrams[ with terminals identified of
watthour meter and current transformers].
d. One-line diagram, including switch(es)[, current transformers, meters,
and fuses].
e. Manufacturer's published time-current curves in PDF format and in
electronic format suitable for import or updating into the [EasyPower]
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 19.10 Page 11
[SKM PowerTools for Windows] [_____] computer program of the
transformer high side fuses.
1.5.2 Regulatory Requirements
In each of the publications referred to herein, consider the advisory
provisions to be mandatory, as though the word, "shall" or "must" had been
substituted for "should" wherever it appears. Interpret references in these
publications to the "authority having jurisdiction," or words of similar
meaning, to mean the Contracting Officer. Provide equipment, materials,
installation, and workmanship in accordance with NFPA 70 unless more
stringent requirements are specified or indicated.
1.5.3 Standard Products
Provide materials and equipment that are products of manufacturers regularly
engaged in the production of such products which are of equal material,
design and workmanship, and:
a. Have been in satisfactory commercial or industrial use for 2 years
prior to bid opening including applications of equipment and materials
under similar circumstances and of similar size.
b. Have been on sale on the commercial market through advertisements,
manufacturers' catalogs, or brochures during the 2-year period.
c. Where two or more items of the same class of equipment are required,
provide products of a single manufacturer; however, the component parts
of the item need not be the products of the same manufacturer unless
stated in this section.
1.5.3.1 Alternative Qualifications
Products having less than a 2-year field service record will be acceptable
if a certified record of satisfactory field operation for not less than 6000
hours, exclusive of the manufacturers' factory or laboratory tests, is
furnished.
1.5.3.2 Material and Equipment Manufacturing Date
Products manufactured more than 3 years prior to date of delivery to site
are not acceptable.
1.6 MAINTENANCE
1.6.1 Additions to Operation and Maintenance Data
***************************************************************************
Note: Delete bracketed information for Navy and Air
Force projects when separate metering specification
is used. May still need for Army and NASA projects
until metering specification is unified.
***************************************************************************
Submit operation and maintenance data in accordance with Section 01 78 23
OPERATION AND MAINTENANCE DATA and as specified herein. In addition to
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 19.10 Page 12
requirements of Data Package 5, include the following on the actual
transformer(s) provided:
a. An instruction manual with pertinent items and information highlighted
b. An outline drawing, front, top, and side views
c. Prices for spare parts and supply list
d. Routine and field acceptance test reports
e. Fuse curves for primary fuses
[f. Information on watthour demand meter, CT's, and fuse block
]g. Actual nameplate diagram
h. Date of purchase
PART 2 PRODUCTS
2.1 PRODUCT COORDINATION
Products and materials not considered to be pad-mounted transformers and
related accessories are specified in[ Section 33 71 01 OVERHEAD TRANSMISSION
AND DISTRIBUTION,][ Section 26 20 00 INTERIOR DISTRIBUTION SYSTEM,][ and][
Section 33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION].
2.2 THREE-PHASE PAD-MOUNTED TRANSFORMERS
***************************************************************************
NOTE: According to IEEE 386, 200 ampere separable
insulated connectors normally used on dead-front pad-
mounted transformers have both a fault closure and a
short-time current rating of 10,000 amperes.
Therefore, from a safety standpoint, dead-front
configurations which utilize these connectors should
only be used at system locations which have available
fault currents of less than 10,000 rms symmetrical
amperes.
This specification does not address the materials
used for the winding (copper versus aluminum) and it
is assumed that the manufacturer will provide their
standard product with respect to the winding
construction, based on the cost of materials at the
time of order acceptance. No failure data has been
obtained indicating that copper windings have a
longer life than aluminum windings. If copper
windings are specified, the cost increase for three-
phase distribution transformers has recently been
about 15 percent. Do NOT specify winding materials.
***************************************************************************
IEEE C57.12.34, IEEE C57.12.28 and as specified herein. Submit
manufacturer's information for each component, device, insulating fluid, and
accessory provided with the transformer.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 19.10 Page 13
2.2.1 Compartments
Provide high- and low-voltage compartments separated by steel isolating
barriers extending the full height and depth of the compartments.
Compartment doors: hinged lift-off type with stop in open position and
three-point latching.
2.2.1.1 High Voltage, Dead-Front
***************************************************************************
NOTE: Current policy is to use oil-immersed fuses in
series with current limiting fuses to achieve better
protection and obtain life cycle cost benefits.
For 15 kV and 25 kV, 200 A bushings, select bushing
wells and bushing well inserts. For 15 kV and 25 kV,
600 A bushings and for 35 kV bushings, select one-
piece bushings.
Do not provide standoff bushings unless this
transformer is the only dead-front transformer on the
base. The Public Works Department normally carries
standoff bushings in their vehicles. Provide
protective caps when providing standoff bushings and
to cover unused bushing well inserts when not
providing surge arresters.
Coordinate lead-in paragraph with bracketed options
below.
Choose minimum high-voltage compartment dimensions
for transformers used in loop feed applications to
accomodate installation of loop feed, feed-through
inserts, and surge arresters.
NOTE: For systems with a fault capability greater
than 10,000 amps, for applications utilizing loop
feed load-break switches, or when the primary cable
size is greater than No. 4/0 AWG, use 600A separable
insulated dead-break connectors.
***************************************************************************
High-voltage compartment contains: the incoming line, insulated high-
voltage [load-break ][dead-break ]connectors, [bushing well inserts,][ feed-
thru inserts,] six high-voltage [bushing wells][one-piece bushings]
configured for loop feed application, load-break switch handle(s), [access
to oil-immersed bayonet fuses,][ dead-front surge arresters,] tap changer
handle, connector parking stands[ with insulated standoff bushings],[
protective caps,] and ground pad.
[Minimum high-voltage compartment dimensions: IEEE C57.12.34, Figures 16
and 17.
][a. Insulated high-voltage load-break connectors: IEEE 386, rated [15
kV, 95 kV BIL][25 kV, 125 kV BIL][35 kV, 150 kV BIL]. Current rating:
200 amperes rms continuous. Short time rating: 10,000 amperes rms
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 19.10 Page 14
symmetrical for a time duration of 0.17 seconds. Connector shall have
a steel reinforced hook-stick eye, grounding eye, test point, and arc-
quenching contact material.
][b. Insulated high-voltage dead-break connectors: IEEE 386, rated [15
kV, 95 kV BIL][25 kV, 125 kV BIL][35 kV, 150 kV BIL]. Current rating:
600 amperes rms continuous. Short time rating: 25,000 amperes rms
symmetrical for a time duration of 0.17 seconds. Connector shall have
a [200 ampere bushing interface for surge arresters,] steel reinforced
hook-stick eye, grounding eye, test point, and arc-quenching contact
material.
***************************************************************************
NOTE: Provide bushing well inserts and feed-through
inserts only on load-break applications, not on dead-
break.
***************************************************************************
][c. Bushing well inserts[ and feed-thru inserts]: IEEE 386, 200 amperes,
[15][25] kV Class. Provide a bushing well insert for each bushing well
unless indicated otherwise.[ Provide feed-thru inserts as indicated.]
][d. One-piece bushings: IEEE 386, [200][600] amperes,
[15][25][35][_____] kV Class.
]e. Load-break switch
***************************************************************************
NOTE: Choose between load-break radial-feed switch
and load-break loop feed switches.
***************************************************************************
[Radial-feed oil-immersed type rated at [15 kV, 95 kV BIL][25 kV, 125
kV BIL][35 kV, 150 kV BIL], with a continuous current rating and load-
break rating of [200][300][_____] amperes, and a make-and-latch rating
of 12,000 rms amperes symmetrical. Locate the switch handle in the
high-voltage compartment.
][Loop feed sectionalizer switches: Provide three, two-position, oil-
immersed type switches to permit closed transition loop feed and
sectionalizing. Each switch must be rated at [15 kV, 95 kV BIL][25 kV,
125 kV BIL][35 kV, 150 kV BIL], with a continuous current rating and
load-break rating of [200][300][_____] amperes, and a make-and-latch
rating of 12,000 rms amperes symmetrical. Locate the switch handles in
the high-voltage compartment. Operation of switches must be as
follows:
ARRANGEMENT
NO.
DESCRIPTION OF SWITCH
ARRANGEMENT
SWITCH POSITION
LINE A SW. LINE B SW XFMR. SW
OPEN CLOSE OPEN CLOSE OPEN CLOSE
1 Line A connected to
Line B and both lines
connected to
transformer
X X X
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 19.10 Page 15
2 Transformer connected
to Line A only
X X X
3 Transformer connected
to Line Bonly
X X X
4 Transformer open and
loop closed
X X X
5 Transformer open and
loop open
X X X
***************************************************************************
NOTE: Provide bayonet type fuses for all transformer
applications 38 kV and below.
***************************************************************************
][f. Provide bayonet oil-immersed, expulsion fuses in series with oil-
immersed, partial-range, current-limiting fuses. The bayonet fuse
links sense both high currents and high oil temperature in order to
provide thermal protection to the transformer. Coordinate transformer
protection with expulsion fuse clearing low-current faults and current-
limiting fuse clearing high-current faults beyond the interrupting
rating of the expulsion fuse. Include an oil retention valve inside
the bayonet assembly housing, which closes when the fuse holder is
removed, and an external drip shield to minimize oil spills. Display a
warning label adjacent to the bayonet fuse(s) cautioning against
removing or inserting fuses unless the transformer has been de-
energized and the tank pressure has been released.
Bayonet fuse assembly: 150 kV BIL.
***************************************************************************
NOTE: For transformers with loop-feed sectionalizer
switching, delete the bracketed option regarding
placement of current-limiting fuses.
***************************************************************************
Oil-immersed current-limiting fuses: IEEE C37.47; 50,000 rms amperes
symmetrical interrupting rating at the system voltage specified.[
Connect current-limiting fuses ahead of the radial-feed load-break
switch.]
***************************************************************************
NOTE: Provide bushing-mounted elbow type arresters
at the ends of all radials and in normally open
locations in loops. Provide arresters for all
voltage levels above 5 kV.
***************************************************************************
][g. Surge arresters: IEEE C62.11, rated
[3][6][9][10][12][15][18][21][24][27][30][36][_____] kV, fully
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 19.10 Page 16
shielded, dead-front, metal-oxide-varistor, elbow type with resistance-
graded gap.[ Provide three arresters for radial feed circuits.][
Provide [three][six] arresters for loop feed circuits.]
]h. Parking stands: Provide a parking stand near each bushing.[ Provide
insulated standoff bushings for parking of energized high-voltage
connectors on parking stands.]
[i. Protective caps: IEEE 386, [200][600] amperes, [15][25][35][_____] kV
Class. Provide insulated protective caps (not shipping caps) for
insulating and sealing out moisture from unused bushings.
][2.2.1.2 High Voltage, Live-Front
***************************************************************************
NOTE: When live-front is selected, delete the above
paragraphs on dead-front.
***************************************************************************
High-voltage compartment contains: the incoming line, transformer high-
voltage bushings, load-break switch handle(s),[ access to oil-immersed
bayonet fuses,][ surge arresters,] tap changer handle, insulated phase
barriers, and ground pad.
a. Cable terminators: Provide as specified in Section 33 71 02
UNDERGROUND ELECTRICAL DISTRIBUTION.
b. Load-break switch
***************************************************************************
NOTE: Choose between load-break radial-feed switch
and load-break loop feed switches.
***************************************************************************
[Radial-feed oil-immersed type rated at [15 kV, 95 kV BIL][25 kV, 125
kV BIL][35 kV, 150 kV BIL], with a continuous current rating and load-
break rating of [200][300][_____] amperes, and a make-and-latch rating
of 12,000 rms amperes symmetrical. Locate the switch handle in the
high-voltage compartment.
][Loop feed sectionalizer switches: Provide three, two-position, oil-
immersed type switches to permit closed transition loop feed and
sectionalizing. Each switch must be rated at [15 kV, 95 kV BIL][25 kV,
125 kV BIL][35 kV, 150 kV BIL], with a continuous current rating and
load-break rating of [200][300][_____] amperes, and a make-and-latch
rating of 12,000 rms amperes symmetrical. Locate the switch handles in
the high-voltage compartment. Operation of switches must be as
follows:
ARRANGEMENT
NO.
DESCRIPTION OF SWITCH
ARRANGEMENT
SWITCH POSITION
LINE A SW. LINE B SW XFMR. SW
OPEN CLOSE OPEN CLOSE OPEN CLOSE
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 19.10 Page 17
1 Line A connected to
Line B and both lines
connected to
transformer
X X X
2 Transformer connected
to Line A only
X X X
3 Transformer connected
to Line B only
X X X
4 Transformer open and
loop closed
X X X
5 Transformer open and
loop open
X X X
***************************************************************************
NOTE: Provide bayonet type fuses for all transformer
applications 38 kV and below.
***************************************************************************
][c. Provide bayonet oil-immersed, expulsion fuses in series with oil-
immersed, partial-range, current-limiting fuses. The bayonet fuse
links sense both high currents and high oil temperature in order to
provide thermal protection to the transformer. Coordinate transformer
protection with expulsion fuse clearing low-current faults and current-
limiting fuse clearing high-current faults beyond the interrupting
rating of the expulsion fuse. Include an oil retention valve inside
the bayonet assembly housing, which closes when the fuse holder is
removed, and an external drip shield to minimize oil spills. Display a
warning label adjacent to the bayonet fuse(s) cautioning against
removing or inserting fuses unless the transformer has been de-
energized and the tank pressure has been released.
Bayonet fuse assembly: 150 kV BIL.
***************************************************************************
NOTE: For transformers with loop-feed sectionalizer
switching, delete the bracketed option regarding
placement of current-limiting fuses.
***************************************************************************
Oil-immersed current-limiting fuses: IEEE C37.47; 50,000 rms amperes
symmetrical interrupting rating at the system voltage specified.[
Connect current-limiting fuses ahead of the radial-feed load-break
switch.]
***************************************************************************
NOTE: Provide arresters at the ends of all radials
and in normally open locations in loops. Provide
arresters for all voltage levels above 5 kV.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 19.10 Page 18
***************************************************************************
][d. Surge arresters: IEEE C62.11, rated
[3][6][9][10][12][15][18][21][24][27][30][36][_____] kV.[ Provide
three arresters for radial feed circuits.][ Provide [three][six]
arresters for loop feed circuits.]
]e. Insulated phase barriers: NEMA LI 1, Type GPO-3, 6.35 mm (0.25 inch)
minimum thickness. Provide vertical barriers between the high-voltage
bushings and a single horizontal barrier above the high-voltage
bushings.
]2.2.1.3 Low Voltage
***************************************************************************
NOTE: Installation of circuit breakers in the
secondary compartment is not recognized by IEEE
standards, and limits accessibility by covering lugs,
gages, and accessories. Do not use.
***************************************************************************
Low-voltage compartment contains: low-voltage bushings with NEMA spade
terminals, accessories, metering, stainless steel or laser-etched anodized
aluminum diagrammatic transformer nameplate, and ground pad.
a. Include the following accessories: drain valve with sampler device,
fill plug, pressure relief device, liquid level gage, pressure-vacuum
gage, and dial type thermometer with maximum temperature indicator.
***************************************************************************
NOTE: Many Activities have, or are in the process
of, converting to basewide metering systems. A
unified metering specification is under development
to replace the metering requirements in this section.
Use the first bracketed metering paragraph below for
Navy projects and possibly for Air Force projects.
Navy projects require use of section 26 27 14.00 20
ELECTRICITY METERING. Air Force projects may require
use of section 26 27 13.10 30 ELECTRIC METERS.
Delete theAir Force and Navy projects.
Coordinate with the Activity and provide specific
requirements "to match existing systems" when
necessary. If specifying proprietary products,
insure that appropriate "Justification and
Authorization (J & A)" documentation has been
obtained by project manager and "proprietary language
requirements" have been added to Division 1 as well
as to this section of the specifications.
If there are any components (such as meters, housing,
or current transformers) that will be Government
Furnished Contractor Installed (GFCI), or Government
Furnished Government Installed (GFGI), edit Division
1 and this specification.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 19.10 Page 19
***************************************************************************
[b. Metering: Provide as specified in Section [26 27 14.00 20 ELECTRICITY
METERING][26 27 13.10 30 ELECTRIC METERS].
][c. Metering: NEMA/ANSI C12.10. Provide a socket-mounted electronic
programmable outdoor watthour meter, surface mounted flush against the
side of the low-voltage compartment as indicated. Program the meter at
the factory or in the field. When field programming is performed, turn
field programming device over to the Contracting Officer at completion
of project. Coordinate the meter to system requirements.
***************************************************************************
NOTE: When Section 23 09 00 INSTRUMENTATION AND
CONTROL FOR HVAC is used, coordinate meter
requirements. Form 9S, in text below, is for three-
phase, four-wire wye systems, for other system
configurations, designer must determine the
appropriate form designation.
***************************************************************************
(1) Design: Provide meter designed for use on a 3-phase, 4-wire,
[208Y/120][480Y/277] volt system with 3 current transformers.
Include necessary KYZ pulse initiation hardware for Energy
Monitoring and Control System (EMCS)[ as specified in Section 23 09
00 INSTRUMENTATION AND CONTROL FOR HVAC].
(2) Coordination: Provide meter coordinated with ratios of current
transformers and transformer secondary voltage.
(3) Class: 20; Form: [9S][_____]; Accuracy: plus or minus 1.0
percent; Finish: Class II
(4) Cover: Polycarbonate and lockable to prevent tampering and
unauthorized removal.
(5) Kilowatt-hour Register: five digit electronic programmable type
(6) Demand Register:
(a) Provide solid state
(b) Meter reading multiplier: Indicate multiplier on the meter
face.
(c) Demand interval length: programmed for [15][30][60] minutes
with rolling demand up to six subintervals per interval.
(7) Meter fusing: Provide a fuse block mounted in the secondary
compartment containing one fuse per phase to protect the voltage
input to the watthour meter. Size fuses as recommended by the
meter manufacturer.
(8) Socket: ANSI C12.7. Provide NEMA Type 3R, box-mounted socket
having automatic circuit-closing bypass and having jaws compatible
with requirements of the meter. Cover unused hub openings with
blank hub plates. Paint box Munsell 7GY3.29/1.5 green to match the
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 19.10 Page 20
pad-mounted transformer to which the box-mounted socket is
attached. The Munsell color notation is specified in ASTM D1535.
(9) Current transformers: IEEE C57.13. Provide butyl-molded window
type current transformers with 600-volt insulation, 10 kV BIL and
mount on the low-voltage bushings. Route current transformer leads
in a location as remote as possible from the power transformer
secondary cables to permit current measurements to be taken with
hook-on-ammeters. Provide three current transformers per power
transformer with characteristics listed in the following table.
***************************************************************************
NOTE: The following guidelines for specifying
current transformers are based on the standard
current transformer primary rating which is just
below the full load current of the power transformer.
1. Select the appropriate current transformer (CT)
ratio, continuous-thermal-current rating factor (RF)
at 30 degrees C and ANSI Metering Accuracy Class
values based on transformer kVA size and secondary
voltage. Example: for a 500 kVA transformer at 208
volts - select 1200/5, 1.5, 0.3 - B-0.5.
VOLTS
208 240
kVA CT Ratio RF Meter Class CT Ratio RF Meter Class
75 200/5 4.0 0.3 thru B-0.1 200/5 4.0 0.3 thru B-0.1
112.5 300/5 3.0 0.3 thru B-0.2 200/5 4.0 0.3 thru B-0.1
150 400/5 4.0 0.3 thru B-0.2 300/5 3.0 0.3 thru B-0.2
225 600/5 3.0 0.3 thru B-0.5 400/5 4.0 0.3 thru B-0.2
300 800/5 2.0 0.3 thru B-0.5 600/5 3.0 0.3 thru B-0.5
500 1200/5 1.5 0.3 thru B-0.5 1200/5 1.5 0.3 thru B-0.5
750 2000/5 1.5 0.3 thru B-1.8 1500/5 1.5 0.3 thru B-0.9
VOLTS
480 600
kVA CT Ratio RF Meter Class CT Ratio RF Meter Class
75 200/5, 4.0 0.3 thru B-0.1 200/5 4.0 0.3 thru B-0.1
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 19.10 Page 21
VOLTS
480 600
kVA CT Ratio RF Meter Class CT Ratio RF Meter Class
112.5 200/5, 4.0 0.3 thru B-0.1 200/5 4.0 0.3 thru B-0.1
150 200/5, 4.0 0.3 thru B-0.1 200/5 4.0 0.3 thru B-0.1
225 200/5, 4.0 0.3 thru B-0.1 200/5 4.0 0.3 thru B-0.1
300 300/5, 3.0 0.3 thru B-0.2 200/5 4.0 0.3 thru B-0.1
500 600/5, 3.0 0.3 thru B-0.5 400/5 4.0 0.3 thru B-0.2
750 800/5, 2.0 0.3 thru B-0.5 600/5 3.0 0.3 thru B-0.5
1000 1200/5 1.5 0.3 thru B-0.5 800/5 2.0 0.3 thru B-0.5
1500 1500/5 1.5 0.3 thru B-0.9 1200/5 1.5 0.3 thru B-0.5
2000 2000/5 1.5 0.3 thru B-1.8 1500/5 1.5 0.3 thru B-0.9
2500 3000/5 1.33 0.3 thru B-1.8 2000/5 1.5 0.3 thru B-1.8
2. Incorporate the appropriate values in table
below.
***************************************************************************
kVA Sec. Volt CT Ratio RF Meter Acc. Class
[500] [208Y/120] [1200/5] [1.5] [0.3 thru B-0.5]
[750] [480Y/277] [ 800/5] [2.0] [0.3 thru B-0.5]
]2.2.2 Transformer
***************************************************************************
NOTE: Use the following guidelines for specifying
transformers and insulating liquids.
1. On Navy projects use of biodegradable less-
flammable liquid is required.
For other projects, biodegradable less-flammable
liquid and mineral oil are permitted. Previously the
use of mineral oil-filled transformers was
recommended wherever possible. Currently,
biodegradable less-flammable transformer liquids that
improve transformer operating characteristics are
available with little, if any premium cost. This
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 19.10 Page 22
requirement is supported by UFC 3-600-01, "Fire
Protection Engineering for Facilities", identifies
building and equipment separation distances based on
insulating liquid type. Mineral oil is more
restrictive than less-flammable liquid. For example,
a 1500 kVA transformer containing 600 gallons of
less-flammable liquid requires a building separation
distance of 1.5 meters (5 feet) when the construction
is fire-resistant or non-combustible. An equally
sized mineral oil-filled transformer requires 4.6
meters (15 feet) and 7.6 meters (25 feet) of
separation for fire-resistant and non-combustible
construction, respectively. Do not specify silicone-
filled transformers.
2. Use IEEE C57.12.00, Table 8 - Designation of
voltage ratings of three-phase windings, such as
"4160 V - 480Y / 277 V". Connections must be Delta-
GrdY configuration for three phase systems. Other
system connections require waiver from UFC 3-550-01
criteria.
3. Include bracketed option to display transformer
rating on enclosure when directed by Activity. For
NASA projects only, include 3 inch yellow lettering
bracketed options.
4. Delete last sentence of item g regarding
removable ground strap if transformer secondary
winding is delta type.
***************************************************************************
a. Less-flammable [bio-based] ]liquid-insulated[ or oil-insulated], two
winding, 60 hertz, 65 degrees C rise above a 30 degrees C average
ambient, self-cooled type.
b. Transformer rated [_____] kVA.
c. Transformer voltage ratings: [_____] V [Delta][_____] - [_____] V
[GrdY][_____].[ For GrdY - GrdY transformers, provide transformer with
five-legged core design for third harmonic suppression.]
d. Tap changer: externally operated, manual type for changing tap
setting when the transformer is de-energized. Provide four 2.5 percent
full capacity taps, two above and two below rated primary voltage.
Indicate which tap setting is in use, clearly visible when the
compartment is opened.
e. Minimum tested percent impedance at 85 degrees C:
2.50 for units rated 75kVA and below
2.87 for units rated 112.5kVA to 300kVA
4.03 for 500kVA rated units
5.32 for units rated 750kVA and above
f. Comply with the following audible sound level limits:
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 19.10 Page 23
kVA DECIBELS
(MAX
75 51
112.5 55
150 55
225 55
300 55
500 56
750 57
1000 58
1500 60
2000 61
2500 62
g. Include:
(1) Lifting lugs and provisions for jacking under base, with base
construction suitable for using rollers or skidding in any
direction.
(2) An insulated low-voltage neutral bushing with NEMA spade terminal,
and with removable ground strap.
(3) Provide transformer top with an access handhole.
[(4) kVA rating conspicuously displayed [using 75 mm (3 inch) high
yellow letters ]on its enclosure.
]2.2.2.1 Specified Transformer Efficiencies
***************************************************************************
NOTE: Transformer losses and efficiency requirements
have been modified into the table included within the
specification and the previous Navy loss tables have
been deleted. The requirement for transformers
larger than 2500 kva is an addition to the table in
10 CFR 431, Subpart K and was coordinated with
leading transformer manufacturers.
10 CFR 431, Subpart K is a result of the Energy
Policy and Conservation Act (EPACT) of 2005 and is
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 19.10 Page 24
the "minimum" industry standard for distribution
transformers manufactured on or after January 1,
2016.
***************************************************************************
Provide transformer efficiency calculations utilizing the actual no-load and
load loss values obtained during the routine tests performed on the actual
transformer(s) prepared for this project. Reference no-load losses (NLL) at
20 degrees C. Reference load losses (LL) at 55 degrees C and at 50 percent
of the nameplate load. The transformer is not acceptable if the calculated
transformer efficiency is less than the efficiency indicated in the "KVA /
Efficiency" table below. The table is based on requirements contained
within 10 CFR 431, Subpart K. Submit certification, including supporting
calculations, from the manufacturer indicating conformance.
kVA EFFICIENCY
(percent)
15 98.65
30 98.83
45 98.92
75 99.03
112.5 99.11
150 99.16
225 99.23
300 99.27
500 99.35
750 99.40
1000 99.43
1500 99.48
2000 99.51
2500 99.53
above
2500
99.54
2.2.3 Insulating Liquid
a. Less-flammable [bio-based ]transformer liquids: NFPA 70 and FM APP
GUIDE for less-flammable liquids having a fire point not less than 300
degrees C tested per ASTM D92 and a dielectric strength not less than
33 kV tested per ASTM D877/D877M. Provide identification of
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 19.10 Page 25
transformer as "non-PCB" and "manufacturer's name and type of fluid" on
the nameplate.
Provide a fluid that is a biodegradable, [bio-based ]electrical
insulating, and cooling liquid classified by UL and approved by FM as
"less flammable" with the following properties:
(1) Pour point: ASTM D97, less than -15 degree C
(2) Aquatic biodegradation: EPA 712-C-98-075, 100 percent
(3) Trout toxicity: OECD Test 203, zero mortality of EPA 821-R-02-012,
pass
[b. Mineral oil: ASTM D3487, Type II, tested in accordance with ASTM
D117. Provide identification of transformer as "non-PCB" and "Type II
mineral oil" on the nameplate.
]2.2.3.1 Liquid-Filled Transformer Nameplates
Provide nameplate information in accordance with IEEE C57.12.00 and as
modified or supplemented by this section.
2.2.4 Corrosion Protection
***************************************************************************
NOTE: Use stainless steel bases and cabinets for
most applications. In hostile environments, the
additional cost of totally stainless steel tanks and
metering enclosures may be justified. Manufacturer's
standard construction material is acceptable only in
noncoastal and noncorrosive environments. Choose the
second bracketed option for hostile environments.
***************************************************************************
[Provide corrosion resistant bases and cabinets of transformers, fabricated
of stainless steel conforming to ASTM A240/A240M, Type 304 or 304L. Base
includes any part of pad-mounted transformer that is within 75 mm (3 inches)
of concrete pad.
][Provide entire transformer assembly, including tank and radiator, base,
enclosure, and metering enclosure fabricated of stainless steel conforming
to ASTM A240/A240M, Type 304 or 304L. Form enclosure of stainless steel
sheets. The optional use of aluminum is permitted for the metering
enclosure.
]Paint entire transformer assembly [Munsell 7GY3.29/1.5 green][Munsell
5BG7.0/0.4 sky gray (ANSI 70)][_____], with paint coating system complying
with IEEE C57.12.28 [and IEEE C57.12.29 ]regardless of base, cabinet, and
tank material. The Munsell color notation is specified in ASTM D1535.
2.3 WARNING SIGNS AND LABELS
Provide warning signs for the enclosures of pad-mounted transformers having
a nominal rating exceeding 600 volts in accordance with NEMA Z535.4 and NEMA
260.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 19.10 Page 26
a. When the enclosure integrity of such equipment is specified to be in
accordance with IEEE C57.12.28, such as for pad-mounted transformers,
provide self-adhesive warning labels (decals, Panduit No. PPSO710D72 or
approved equal) on the outside of the high voltage compartment
door(s)with nominal dimensions of 178 by 255 mm (7 by 10 inches) with
the legend "WARNING HIGH VOLTAGE" printed in two lines of nominal 50 mm
(2 inch) high letters. Include the work "WARNING" in white letters on
an orange background and the words "HIGH VOLTAGE" in black letters on a
white background.
[b. When such equipment is guarded by a fence, mount signs on the fence.
Provide metal signs having nominal dimensions of 355 by 255 mm (14 by
10 inches) with the legend "WARNING HIGH VOLTAGE KEEP OUT" printed in
three lines of nominal 75 mm (3 inch) high white letters on an orange
and black field.
]2.4 ARC FLASH WARNING LABEL
***************************************************************************
NOTE: Include the Arc Flash Warning Label detail on
the drawings. See the technical notes at the
beginning of section to obtain the AutoCAD drawing
file of the label.
***************************************************************************
Provide arc flash warning label for the enclosure of pad-mounted
transformers. Locate this self-adhesive warning label on the outside of the
high voltage compartment door warning of potential electrical arc flash
hazards and appropriate PPE required. Provide label format as indicated..
2.5 GROUNDING AND BONDING
UL 467. Provide grounding and bonding as specified in Section 33 71 02
UNDERGROUND ELECTRICAL DISTRIBUTION.
[2.6 PADLOCKS
***************************************************************************
NOTE: Designer must assure that Section 08 71 00
DOOR HARDWARE is included and is edited to include
padlocks.
Do not use this paragraph for Navy and Air Force
projects.
***************************************************************************
Provide padlocks for pad-mounted equipment[ and for each fence gate], keyed
[alike][as directed by the Contracting Officer]. Comply with Section 08 71
00 DOOR HARDWARE.
]2.7 CAST-IN-PLACE CONCRETE
***************************************************************************
NOTE: Use the first bracketed paragraph when project
includes a concrete section in Division 03;
otherwise, the second bracketed paragraph may be
used. Coordinate requirements with Section 03 30
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 19.10 Page 27
00.00 10 CAST-IN-PLACE CONCRETE or Section 03 30 00
CAST-IN-PLACE CONCRETE. Use Section 03 30 00 for
Navy projects and Section 03 30 00.00 10 for other
projects.
***************************************************************************
[Provide concrete associated with electrical work for other than encasement
of underground ducts rated for 30 MPa (4000 psi) minimum 28-day compressive
strength unless specified otherwise. Conform to the requirements of
Section[ 03 30 00 CAST-IN-PLACE CONCRETE][ 03 30 00.00 10 CAST-IN-PLACE
CONCRETE].
]
***************************************************************************
NOTE: If concrete requirements are detailed and no
cast-in-place section is to be included in the
project specification, refer to Section 03 30 00
CAST-IN-PLACE CONCRETE or Section 03 30 00.00 10
CAST-IN-PLACE CONCRETE and select such portions as
needed to provide complete requirements in addition
to the requirements below.
***************************************************************************
[Provide concrete associated with electrical work as follows:
a. Composed of fine aggregate, coarse aggregate, portland cement, and
water so proportioned and mixed as to produce a plastic, workable
mixture.
b. Fine aggregate: hard, dense, durable, clean, and uncoated sand.
c. Coarse aggregate: reasonably well graded from 4.75 mm to 25 mm (3/16
inch to 1 inch).
d. Fine and coarse aggregates: free from injurious amounts of dirt,
vegetable matter, soft fragments or other deleterious substances.
e. Water: fresh, clean, and free from salts, alkali, organic matter, and
other impurities.
f. Concrete associated with electrical work for other than encasement of
underground ducts: 30 MPa (4000 psi) minimum 28-day compressive
strength unless specified otherwise.
g. Slump: Less than 100 mm (4 inches). Retempering of concrete will not
be permitted.
h. Exposed, unformed concrete surfaces: smooth, wood float finish.
i. Concrete must be cured for a period of not less than 7 days, and
concrete made with high early strength portland cement must be repaired
by patching honeycombed or otherwise defective areas with cement mortar
as directed by the Contracting Officer.
j. Air entrain concrete exposed to weather using an air-entraining
admixture conforming to ASTM C260/C260M.
k. Air content: between 4 and 6 percent.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 19.10 Page 28
]2.8 SOURCE QUALITY CONTROL
2.8.1 Transformer Test Schedule
The Government reserves the right to witness tests. Provide transformer
test schedule for tests to be performed at the manufacturer's test facility.
Submit required test schedule and location, and notify the Contracting
Officer 30 calendar days before scheduled test date. Notify Contracting
Officer 15 calendar days in advance of changes to scheduled date.
a. Test Instrument Calibration
(1) Provide a calibration program which assures that all applicable
test instruments are maintained within rated accuracy.
(2) Accuracy: Traceable to the National Institute of Standards and
Technology.
(3) Instrument calibration frequency schedule: less than or equal to
12 months for both test floor instruments and leased specialty
equipment.
(4) Dated calibration labels: visible on all test equipment.
(5) Calibrating standard: higher accuracy than that of the instrument
tested.
(6) Keep up-to-date records that indicate dates and test results of
instruments calibrated or tested. For instruments calibrated by
the manufacturer on a routine basis, in lieu of third party
calibration, include the following:
(a) Maintain up-to-date instrument calibration instructions and
procedures for each test instrument.
(b) Identify the third party/laboratory calibrated instrument to
verify that calibrating standard is met.
2.8.2 Design Tests
IEEE C57.12.00, and IEEE C57.12.90. Section 5.1.2 in IEEE C57.12.80 states
that "design tests are made only on representative apparatus of basically
the same design." Submit design test reports (complete with test data,
explanations, formulas, and results), in the same submittal package as the
catalog data and drawings for[ each of] the specified transformer(s), with
design tests performed prior to the award of this contract.
a. Tests: certified and signed by a registered professional engineer.
b. Temperature rise: "Basically the same design" for the temperature rise
test means a pad-mounted transformer with the same coil construction
(such as wire wound primary and sheet wound secondary), the same kVA,
the same cooling type (ONAN), the same temperature rise rating, and the
same insulating liquid as the transformer specified.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 19.10 Page 29
c. Lightning impulse: "Basically the same design" for the lightning
impulse dielectric test means a pad-mounted transformer with the same
BIL, the same coil construction (such as wire wound primary and sheet
wound secondary), and a tap changer, if specified. Design lightning
impulse tests includes the primary windings only of that transformer.
(1) IEEE C57.12.90, paragraph 10.3 entitled "Lightning Impulse Test
Procedures," and IEEE C57.98.
(2) State test voltage levels.
(3) Provide photographs of oscilloscope display waveforms or plots of
digitized waveforms with test report.
d. Lifting and moving devices: "Basically the same design" requirement
for the lifting and moving devices test means a test report confirming
that the lifting device being used is capable of handling the weight of
the specified transformer in accordance with IEEE C57.12.34.
e. Pressure: "Basically the same design" for the pressure test means a
pad-mounted transformer with a tank volume within 30 percent of the
tank volume of the transformer specified.
f. Short circuit: "Basically the same design" for the short circuit test
means a pad-mounted transformer with the same kVA as the transformer
specified.
2.8.3 Routine and Other Tests
IEEE C57.12.00. Routine and other tests: performed in accordance with IEEE
C57.12.90 by the manufacturer on[ each of] the actual transformer(s)
prepared for this project to ensure that the design performance is
maintained in production. Submit test reports, by serial number and receive
approval before delivery of equipment to the project site. Required tests
and testing sequence as follows:
a. Phase relation
b. Ratio
c. No-load losses (NLL) and excitation current
d. Load losses (LL) and impedance voltage
e. Dielectric
(1) Impulse
(2) Applied voltage
(3) Induced voltage
f. Leak
PART 3 EXECUTION
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 19.10 Page 30
3.1 INSTALLATION
Conform to IEEE C2, NFPA 70, and to the requirements specified herein.
Provide new equipment and materials unless indicated or specified otherwise.
3.2 GROUNDING
NFPA 70 and IEEE C2, except provide grounding systems with a resistance to
solid earth ground not exceeding 925 [_____] ohms.
3.2.1 Grounding Electrodes
Provide driven ground rods as specified in Section 33 71 02 UNDERGROUND
ELECTRICAL DISTRIBUTION. Connect ground conductors to the upper end of
ground rods by exothermic weld or compression connector. Provide
compression connectors at equipment end of ground conductors.
3.2.2 Pad-Mounted Transformer Grounding
***************************************************************************
NOTE: Ensure plans show the secondary neutral
grounding conductor sized in accordance with NFPA 70
and the primary neutral grounding conductor when
required. Ensure the CADD detail used matches how
this paragraph is edited. Transformer is to have a
ground ring and the normal number of ground rods is
either four or two. The one ground rod option should
only be chosen if required by local installation
requirements.
***************************************************************************
Provide a ground ring around the transformer with [1/0][4/0] AWG bare
copper.[ Provide four ground rods in the ground ring, one per corner.][
Provide two ground rods in the ground ring at opposite corners.][ Provide
one ground rod in the ground ring with the ground rod located in the
transformer cabinet.] Install the ground rods at least 3000 mm (10 feet)
apart from each other. Provide separate copper grounding conductors and
connect them to the ground loop as indicated. When work in addition to that
indicated or specified is required to obtain the specified ground
resistance, the provision of the contract covering "Changes" applies.
3.2.3 Connections
Make joints in grounding conductors and loops by exothermic weld or
compression connector. Install exothermic welds and compression connectors
as specified in Section 33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION.
3.2.4 Grounding and Bonding Equipment
UL 467, except as indicated or specified otherwise.
3.3 INSTALLATION OF EQUIPMENT AND ASSEMBLIES
Install and connect pad-mounted transformers furnished under this section as
indicated on project drawings, the approved shop drawings, and as specified
herein.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 19.10 Page 31
[3.3.1 Meters and Current Transformers
***************************************************************************
Note: Delete bracketed paragraph for Navy and Air
Force projects, this information is covered in their
associated metering specifications.
***************************************************************************
ANSI C12.1.
]3.4 FIELD APPLIED PAINTING
Where field painting of enclosures is required to correct damage to the
manufacturer's factory applied coatings, provide manufacturer's recommended
coatings and apply in accordance with manufacturer's instructions.
[3.5 WARNING SIGN MOUNTING
***************************************************************************
NOTE: Include the following option when pad-mounted
transformer is guarded by a fence.
***************************************************************************
Provide the number of signs required to be readable from each accessible
side, but space the signs a maximum of 9 meters (30 feet) apart.
]3.6 FOUNDATION FOR EQUIPMENT AND ASSEMBLIES
***************************************************************************
NOTE: Mounting slab connections may have to be given
in detail depending on the requirements for the
seismic zone in which the requirement is located.
Include construction requirements for concrete slab
only if slab is not detailed on drawings. Do not
provide curbs or raised edges around liquid filled
transformers unless specifically approved by
Technical Proponent (link provided in the technical
note at the beginning of this section).
***************************************************************************
Mount transformer on concrete slab as follows:
a. Unless otherwise indicated, provide the slab with dimensions at least
200 mm (8 inches) thick, reinforced with a 152 by 152 mm MW19 by MW19
(6 by 6 inches - W2.9 by W2.9) mesh placed uniformly 100 mm (4 inches)
from the top of the slab.
b. Place slab on a 150 mm (6 inch) thick, well-compacted gravel base.
c. Install slab such that top of concrete slab is approximately 100 mm (4
inches) above the finished grade with gradual slope for drainage.
d. Provide edges above grade with 15 mm (1/2 inch) chamfer.
e. Provide slab of adequate size to project at least 200 mm (8 inches)
beyond the equipment.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 19.10 Page 32
Stub up conduits, with bushings, 50 mm (2 inches) into cable wells in the
concrete pad. Coordinate dimensions of cable wells with transformer cable
training areas.
3.6.1 Cast-In-Place Concrete
***************************************************************************
NOTE: Use the first bracketed option when project
includes a concrete section in Division 03;
otherwise, the second bracketed option may be used.
***************************************************************************
Provide cast-in-place concrete work in accordance with the requirements of[
Section[ 03 30 00 CAST-IN-PLACE CONCRETE][ 03 30 00.00 10 CAST-IN-PLACE
CONCRETE]][ ACI 318][ ACI 318M].
[3.6.2 Sealing
***************************************************************************
NOTE: Require sealing of cable wells (windows) in
the concrete pad if rodent intrusion is a problem.
***************************************************************************
When the installation is complete, seal all entries into the equipment
enclosure with an approved sealing method. Provide seals of sufficient
strength and durability to protect all energized live parts of the equipment
from rodents, insects, or other foreign matter.
]3.7 FIELD QUALITY CONTROL
3.7.1 Performance of Acceptance Checks and Tests
Perform in accordance with the manufacturer's recommendations and include
the following visual and mechanical inspections and electrical tests,
performed in accordance with NETA ATS. Submit reports, including acceptance
criteria and limits for each test in accordance with NETA ATS "Test Values".
3.7.1.1 Pad-Mounted Transformers
a. Visual and mechanical inspection
(1) Compare equipment nameplate data with specifications and approved
shop drawings.
(2) Inspect physical and mechanical condition. Check for damaged or
cracked insulators and leaks.
(3) Inspect anchorage, alignment, and grounding.
(4) Verify the presence of PCB content labeling.
(5) Verify the bushings and transformer interiors are clean.
(6) Inspect all bolted electrical connections for high resistance using
low-resistance ohmmeter, verifying tightness of accessible bolted
electrical connections by calibrated torque-wrench method, or
performing thermographic survey.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 19.10 Page 33
(7) Verify correct liquid level in tanks and bushings.
(8) Verify that positive pressure is maintained on gas-blanketed
transformers.
(9) Perform specific inspections and mechanical tests as recommended by
manufacturer.
(10) Verify de-energized tap changer position is left as specified.
[(11) Verify the presence of transformer surge arresters.
]b. Electrical tests
(1) Perform resistance measurements through all bolted connections with
low-resistance ohmmeter.
(2) Verify proper secondary voltage phase-to-phase and phase-to-neutral
after energization and prior to loading.
***************************************************************************
NOTE: Include the bracketed option for additional
field electrical tests for NASA projects only.
***************************************************************************
[(3) Perform insulation-resistance tests, winding-to-winding and each
winding-to-ground. Calculate polarization index.
(4) Perform turns-ratio tests at all tap positions.
(5) Perform insulation power-factor or dissipation-factor tests on all
windings in accordance with test equipment manufacturer’s published
data.
(6) Perform power-factor or dissipation-factor tests on each bushing
equipped with a power-factor/capacitance tap. In the absence of a
power-factor/capacitance tap, perform hot-collar tests.
(7) Measure the resistance of each high-voltage winding in each de-
energized tap-changer position. Measure the resistance of each
low-voltage winding in each de-energized tap-changer position, if
applicable.
(8) Remove and test a sample of insulating liquid for the following:
Dielectric breakdown voltage, Acid neutralization number, Specific
gravity, Interfacial tension, Color, Visual Condition, Water in
insulating liquids (Required on 25 kV or higher voltages and on all
silicone-filled units.), and Power factor or dissipation factor.
(9) Perform dissolved-gas analysis (DGA) on a sample of insulating
liquid.
][3.7.1.2 Current Transformers
***************************************************************************
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 19.10 Page 34
Note: Delete bracketed optional paragraphs for Navy
and Air Force projects. This information is covered
in their associated metering specifications.
***************************************************************************
a. Visual and mechanical inspection
(1) Compare equipment nameplate data with specifications and approved
shop drawings.
(2) Inspect physical and mechanical condition.
(3) Verify correct connection.
(4) Verify that adequate clearances exist between primary and secondary
circuit wiring.
(5) Verify the unit is clean.
(6) Inspect all bolted electrical connections for high resistance using
low-resistance ohmmeter, verifying tightness of accessible bolted
electrical connections by calibrated torque-wrench method, or
performing thermographic survey.
(7) Verify that all required grounding and shorting connections provide
good contact.
(8) Verify correct operation of transformer withdrawal mechanism and
grounding operation.
(9) Verify appropriate lubrication on moving current-carrying parts and
on moving and sliding surfaces.
b. Electrical tests
(1) Perform resistance measurements through all bolted connections with
low-resistance ohmmeter, if applicable.
(2) Perform insulation-resistance test.
(3) Perform a polarity test.
(4) Perform a ratio-verification test.
][3.7.1.3 Watthour Meter
***************************************************************************
Note: Delete bracketed optional paragraphs for Navy
and Air Force projects. This information is covered
in their associated metering specifications.
***************************************************************************
a. Visual and mechanical inspection
(1) Compare equipment nameplate data with specifications and approved
shop drawings.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 19.10 Page 35
(2) Inspect physical and mechanical condition.
(3) Verify tightness of electrical connections.
b. Electrical tests
(1) Calibrate watthour meters according to manufacturer's published
data.
(2) Verify that correct multiplier has been placed on face of meter,
where applicable.
(3) Verify that current transformer secondary circuits are intact.
]3.7.1.4 Grounding System
a. Visual and mechanical inspection
(1) Inspect ground system for compliance with contract plans and
specifications.
b. Electrical tests
(1) Perform ground-impedance measurements utilizing the fall-of-
potential method. On systems consisting of interconnected ground
rods, perform tests after interconnections are complete. On
systems consisting of a single ground rod perform tests before any
wire is connected. Take measurements in normally dry weather, not
less than 48 hours after rainfall. Use a portable ground
resistance tester in accordance with manufacturer's instructions to
test each ground or group of grounds. Use an instrument equipped
with a meter reading directly in ohms or fractions thereof to
indicate the ground value of the ground rod or grounding systems
under test.
(2) Submit the measured ground resistance of each ground rod and
grounding system, indicating the location of the rod and grounding
system. Include the test method and test setup (i.e., pin
location) used to determine ground resistance and soil conditions
at the time the measurements were made.
[3.7.1.5 Surge Arresters, Medium- and High-Voltage
a. Visual and mechanical inspection
(1) Compare equipment nameplate data with specifications and approved
shop drawings.
(2) Inspect physical and mechanical condition.
(3) Inspect anchorage, alignment, grounding, and clearances.
(4) Verify the arresters are clean.
(5) Inspect all bolted electrical connections for high resistance using
low-resistance ohmmeter, verifying tightness of accessible bolted
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 19.10 Page 36
electrical connections by calibrated torque-wrench method, or
performing thermographic survey.
(6) Verify that the ground lead on each device is individually attached
to a ground bus or ground electrode.
b. Electrical tests
(1) Perform resistance measurements through all bolted connections with
low-resistance ohmmeter, if applicable.
(2) Perform an insulation-resistance test on each arrester, phase
terminal-to-ground.
(3) Test grounding connection.
]3.7.2 Follow-Up Verification
Upon completion of acceptance checks and tests, show by demonstration in
service that circuits and devices are in good operating condition and
properly performing the intended function. As an exception to requirements
stated elsewhere in the contract, notify the Contracting Officer 5 working
days in advance of the dates and times of checking and testing.
-- End of Section --
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 21 Page 1
***************************************************************************
USACE / NAVFAC / AFCEC / NASA UFGS-26 12 21 (May 2017)
-----------------------------
Preparing Activity: NAVFAC Superseding
UFGS-26 12 21 (November 2013)
UNIFIED FACILITIES GUIDE SPECIFICATIONS
References are in agreement with UMRL dated October 2017
***************************************************************************
SECTION 26 12 21
SINGLE-PHASE PAD-MOUNTED TRANSFORMERS
05/17
***************************************************************************
NOTE: This guide specification covers the
requirements for single-phase clam shell type and
two-compartment type pad-mounted transformers of the
dead-front type for exterior applications.
Adhere to UFC 1-300-02 Unified Facilities Guide
Specifications (UFGS) Format Standard when editing
this guide specification or preparing new project
specification sections. Edit this guide
specification for project specific requirements by
adding, deleting, or revising text. For bracketed
items, choose applicable item(s) or insert
appropriate information.
Remove information and requirements not required in
respective project, whether or not brackets are
present.
Comments, suggestions and recommended changes for
this guide specification are welcome and should be
submitted as a Criteria Change Request (CCR).
***************************************************************************
***************************************************************************
NOTE: For Navy and Air Force projects, this
specification incorporates a "reduced shop drawing
submittal process" for listed manufacturers who
previously satisfied reduced shop drawing submittal
process requirements. This specification also
includes unique routine and other test requirements,
transformer loss certificate, transformer test
schedule, and field quality control acceptance tests
and reports. The preparing activity, NAVFAC LANT,
has significant experience and technical expertise in
these areas. If Reach-back support during
construction is desired, for a specific NAVFAC or Air
Force project, the technical representative
(electrical engineer) editing this document for that
project must contact the NAVFAC LANT Capital
Improvements Electrical Engineering (Code CI44)
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 21 Page 2
Office for consultation during the design stage of
the project, prior to including the requirement in
the specification.
***************************************************************************
***************************************************************************
NOTE: Use the following related guide specifications
for power distribution equipment:
--Section 26 08 00 APPARATUS INSPECTION AND TESTING
--Section 26 11 13.00 20 PRIMARY UNIT SUBSTATION
--Section 26 11 16 SECONDARY UNIT SUBSTATIONS
--Section 26 12 19.10 THREE-PHASE PAD-MOUNTED
TRANSFORMERS
--Section 26 13 00 SF6/HIGH-FIREPOINT FLUID INSULATED
PAD-MOUNTED SWITCHGEAR
--Section 26 20 00 INTERIOR DISTRIBUTION SYSTEM
--Section 26 23 00 LOW VOLTAGE SWITCHGEAR
--Section 26 24 13 SWITCHBOARDS
--Section 26 27 13.10 30 ELECTRIC METERS
--Section 26 27 14.00 20 ELECTRICITY METERING
--Section 33 71 01 OVERHEAD TRANSMISSION AND
DISTRIBUTION
Do not use the following related guide specifications
except for Army Civil Works projects. They have not
been unified:
--Section 26 11 14.00 10 MAIN ELECTRIC SUPPLY STATION
AND SUBSTATION
--Section 26 22 00.00 10 480-VOLT STATION SERVICE
SWITCHGEAR AND TRANSFORMERS
--Section 26 28 00.00 10 MOTOR CONTROL CENTERS,
SWITCHBOARDS AND PANELBOARDS
***************************************************************************
***************************************************************************
NOTE: Coordination is required between this Section
and metering equipment specification sections. See
Section 26 27 14.00 20 ELECTRICITY METERING or
Section 26 27 13.10 30 ELECTRIC METERS for
transformer and metering details, which are available
in metric (SI) and U.S. Customary (IP) system
dimension. Use these files to develop project
specific drawings, including:
File Name Description
PADMDE7 Single Phase, One Circuit with Surge Arresters
PADMDE8 Single Phase, Feed-Thru Circuit with Surge Arresters
ARCFLASH Arc Flash Warning Label
TO DOWNLOAD DRAWINGS
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 21 Page 3
Go to http://www.wbdg.org/FFC/NAVGRAPH/graphtoc.pdf.
Select the appropriate Electrical .ZIP file(s) and
extract the desired details.
Do not include list of details, or details
themselves, in project specifications. Insert the
appropriate details on drawings and modify optional
and blank items. If special features are required,
do not modify details, but indicate these changes as
notes below the detail.
***************************************************************************
***************************************************************************
NOTE: Show the following information on the project
drawings:
1. Single-line diagram showing pad-mounted
transformer connectors, inserts, surge arresters,
switches, fuses, current transformers with ratings,
and meters as applicable.
2. Grounding plan.
3. Type and number of cables, and size of conductors
for each power circuit.
4. Transformer primary and secondary voltages. (Use
IEEE C57.12.00, Table 7, "Designation of voltage
ratings of single-phase windings"). State the
primary voltage (nominal) actually in service and not
the voltage class.
5. Special conditions, such as altitude,
temperature, and humidity; exposure to fumes, vapors,
dust, and gases; and seismic requirements.
***************************************************************************
PART 1 GENERAL
1.1 REFERENCES
***************************************************************************
NOTE: This paragraph is used to list the
publications cited in the text of the guide
specification. The publications are referred to in
the text by basic designation only and listed in this
paragraph by organization, designation, date, and
title.
Use the Reference Wizard's Check Reference feature
when you add a Reference Identifier (RID) outside of
the Section's Reference Article to automatically
place the reference in the Reference Article. Also
use the Reference Wizard's Check Reference feature to
update the issue dates.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 21 Page 4
References not used in the text will automatically be
deleted from this section of the project
specification when you choose to reconcile references
in the publish print process.
***************************************************************************
The publications listed below form a part of this specification to the
extent referenced. The publications are referred to within the text by the
basic designation only.
AMERICAN CONCRETE INSTITUTE INTERNATIONAL (ACI)
ACI 318 (2014; Errata 1-2 2014; Errata 3-5 2015;
Errata 6 2016; Errata 7 2017) Building Code
Requirements for Structural Concrete and
Commentary
ACI 318M (2014; ERTA 2015) Building Code Requirements
for Structural Concrete & Commentary
AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)
ANSI C12.1 (2008) Electric Meters Code for Electricity
Metering
ASTM INTERNATIONAL (ASTM)
ASTM A240/A240M (2016) Standard Specification for Chromium
and Chromium-Nickel Stainless Steel Plate,
Sheet, and Strip for Pressure Vessels and for
General Applications
ASTM C260/C260M (2010a; R 2016) Standard Specification for
Air-Entraining Admixtures for Concrete
ASTM D117 (2010) Standard Guide for Sampling, Test
Methods, Specifications and Guide for
Electrical Insulating Oils of Petroleum
Origin
ASTM D1535 (2014) Specifying Color by the Munsell System
ASTM D3487 (2016) Standard Specification for Mineral
Insulating Oil Used in Electrical Apparatus
ASTM D877/D877M (2013) Standard Test Method for Dielectric
Breakdown Voltage of Insulating Liquids Using
Disk Electrodes
ASTM D92 (2012a) Standard Test Method for Flash and
Fire Points by Cleveland Open Cup Tester
ASTM D97 (2017a) Standard Test Method for Pour Point
of Petroleum Products
FM GLOBAL (FM)
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 21 Page 5
FM APP GUIDE (updated on-line) Approval Guide
http://www.approvalguide.com/
INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)
IEEE 386 (2016) Separable Insulated Connector Systems
for Power Distribution Systems Rated 2.5 kV
through 35 kV
IEEE C2 (2017; Errata 1-2 2017; INT 1 2017) National
Electrical Safety Code
IEEE C37.47 (2011) Standard for High Voltage Distribution
Class Current-Limiting Type Fuses and Fuse
Disconnecting Switches
IEEE C57.12.00 (2015) General Requirements for Liquid-
Immersed Distribution, Power, and Regulating
Transformers
IEEE C57.12.25 (1990) Standard for Transformers - Pad-
Mounted, Compartmental-Type, Self-Cooled,
Single-Phase Distribution Transformers With
Separable Insulated High-Voltage Connectors;
High Voltage, 34,500 Grdy/ 19,920 Volts and
Below; Low Voltage, 240/120 Volts; 167 kVa
and Smaller Requirements
IEEE C57.12.28 (2014) Standard for Pad-Mounted Equipment -
Enclosure Integrity
IEEE C57.12.29 (2014) Standard for Pad-Mounted Equipment -
Enclosure Integrity for Coastal Environments
IEEE C57.12.80 (2010) Standard Terminology for Power and
Distribution Transformers
IEEE C57.12.90 (2015; Corr 2017) Test Code for Liquid-
Immersed Distribution, Power, and Regulating
Transformers
IEEE C57.13 (2016) Requirements for Instrument
Transformers
IEEE C57.98 (2011) Guide for Transformer Impulse Tests
IEEE C62.11 (2012) Standard for Metal-Oxide Surge
Arresters for Alternating Current Power
Circuits (>1kV)
IEEE Stds Dictionary (2009) IEEE Standards Dictionary: Glossary of
Terms & Definitions
INTERNATIONAL ELECTRICAL TESTING ASSOCIATION (NETA)
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 21 Page 6
NETA ATS (2017) Standard for Acceptance Testing
Specifications for Electrical Power Equipment
and Systems
NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)
ANSI C12.7 (2014) Requirements for Watthour Meter
Sockets
NEMA 260 (1996; R 2004) Safety Labels for Pad-Mounted
Switchgear and Transformers Sited in Public
Areas
NEMA Z535.4 (2011) American National Standard for Product
Safety Signs and Labels
NEMA/ANSI C12.10 (2011) Physical Aspects of Watthour Meters -
Safety Standards
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 70 (2017; ERTA 1-2 2017; TIA 17-1; TIA 17-2; TIA
17-3) National Electrical Code
ORGANISATION FOR ECONOMIC CO-OPERATION AND DEVELOPMENT (OECD)
OECD Test 203 (1992) Fish Acute Toxicity Test
U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA)
EPA 712-C-98-075 (1998) Fate, Transport and Transformation
Test Guidelines - OPPTS 835.3100- "Aerobic
Aquatic Biodegradation"
EPA 821-R-02-012 (2002) Methods for Measuring the Acute
Toxicity of Effluents and Receiving Waters to
Freshwater and Marine Organisms
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
10 CFR 431 Energy Efficiency Program for Certain
Commercial and Industrial Equipment
UNDERWRITERS LABORATORIES (UL)
UL 467 (2013; Reprint Jun 2017) UL Standard for
Safety Grounding and Bonding Equipment
1.2 RELATED REQUIREMENTS
***************************************************************************
NOTE: Include Section 26 08 00 APPARATUS INSPECTION
AND TESTING on all projects involving medium voltage
and specialized power distribution equipment.
***************************************************************************
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 21 Page 7
Section 26 08 00 APPARATUS INSPECTION AND TESTING applies to this Section,
with the additions and modifications specified herein.
1.3 DEFINITIONS
Unless otherwise specified or indicated, electrical and electronics terms
used in these specifications, and on the drawings, are as defined in IEEE
Stds Dictionary.
1.4 SUBMITTALS
***************************************************************************
NOTE: Review Submittal Description (SD) definitions
in Section 01 33 00 SUBMITTAL PROCEDURES and edit the
following list to reflect only the submittals
required for the project.
The Guide Specification technical editors have
designated those items that require Government
approval, due to their complexity or criticality,
with a "G." Generally, other submittal items can be
reviewed by the Contractor's Quality Control System.
Only add a "G" to an item, if the submittal is
sufficiently important or complex in context of the
project.
For submittals requiring Government approval on Army
projects, a code of up to three characters within the
submittal tags may be used following the "G"
designation to indicate the approving authority.
Codes for Army projects using the Resident Management
System (RMS) are: "AE" for Architect-Engineer; "DO"
for District Office (Engineering Division or other
organization in the District Office); "AO" for Area
Office; "RO" for Resident Office; and "PO" for
Project Office. Codes following the "G" typically
are not used for Navy, Air Force, and NASA projects.
Use the "S" classification only in SD-11 Closeout
Submittals. The "S" following a submittal item
indicates that the submittal is required for the
Sustainability eNotebook to fulfill federally
mandated sustainable requirements in accordance with
Section 01 33 29 SUSTAINABILITY REPORTING.
Choose the first bracketed item for Navy, Air Force
and NASA projects, or choose the second bracketed
item for Army projects.
***************************************************************************
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are [for Contractor Quality Control
approval.][for information only. When used, a designation following the "G"
designation identifies the office that will review the submittal for the
Government.] Submittals with an "S" are for inclusion in the Sustainability
eNotebook, in conformance with Section 01 33 29 SUSTAINABILITY REPORTING.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 21 Page 8
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-02 Shop Drawings
Pad-Mounted Transformer Drawings; G[, [_____]]
SD-03 Product Data
Single-Phase Pad-Mounted Transformers (Dead-Front); G[, [_____]]
SD-06 Test Reports
Acceptance Checks and Tests; G[, [_____]]
SD-07 Certificates
Transformer Efficiencies; G[, [_____]]
SD-09 Manufacturer's Field Reports
Transformer Test Schedule; G[, [_____]]
Pad-Mounted Transformer Design Tests; G[, [_____]]
Pad-Mounted Transformer Routine and Other Tests; G[, [_____]]
SD-10 Operation and Maintenance Data
Transformer(s), Data Package 5; G[, [_____]]
[1.4.1 Government Submittal Review
***************************************************************************
NOTE: Include this bracketed option on Navy and Air
Force projects where "reach-back support" has already
been coordinated with NAVFAC LANT per the 2nd
introductory Technical Note. Add appropriate
information in Section 01 33 00 SUBMITTAL PROCEDURES
to coordinate with the special requirements.
***************************************************************************
[Code CI44, NAVFAC LANT, Naval Facilities Engineering Command][_____] will
review and approve all submittals in this section requiring Government
approval.
][1.4.2 Reduced Submittal Requirements
***************************************************************************
NOTE: Include this bracketed reduced submittal
requirements paragraph on Navy and Air Force
Projects.
***************************************************************************
Transformers designed and manufactured by ABB in Jefferson City, MO; by
Eaton's Cooper Power Series Transformers in Waukesha, WI; by ERMCO in
Dyersburg, TN; or by Howard Industries in Laurel, MS need not submit the
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 21 Page 9
entire submittal package requirements of this contract. Instead, submit the
following items:
a. A certification, signed by the manufacturer, stating that the
manufacturer will meet the technical requirements of this
specification.
b. An outline drawing of the transformer with devices identified
(paragraph PAD-MOUNTED TRANSFORMER DRAWINGS, item a).
c. ANSI nameplate data of the transformer (paragraph PAD-MOUNTED
TRANSFORMER DRAWINGS, item b).
***************************************************************************
NOTE: The designer is responsible for providing
proper settings for secondary over-current device(s)
to ensure proper protection of equipment and
coordination with transformer high side fuses.
Include the following option for transformers serving
secondary over-current devices containing adjustable
trips.
***************************************************************************
[d. Manufacturer's published time-current curves in PDF format and in
electronic format suitable for import or updating into the [EasyPower]
[SKM PowerTools for Windows] [_____] computer program of the
transformer high side fuses (paragraph PAD-MOUNTED TRANSFORMER
DRAWINGS, item e).
]e. Routine and other tests (in PART 2, see paragraph SOURCE QUALITY
CONTROL, subparagraph ROUTINE AND OTHER TESTS), conducted by the
manufacturer. These tests may be witnessed by the government. Provide
transformer test schedule required by submittal item "SD-11 Closeout
Submittals". Provide certified copies of the tests.
f. Provide acceptance test reports required by submittal item "SD-06 Test
Reports".
g. Provide operation and maintenance manuals required by submittal item
"SD-10 Operation and Maintenance Data".
]1.5 QUALITY ASSURANCE
1.5.1 Pad-Mounted Transformer Drawings
***************************************************************************
NOTE: Delete bracketed information for Navy and Air
Force projects when separate metering specification
is used. May still need for Army and NASA projects
until metering specification is unified.
***************************************************************************
Include the following as a minimum:
a. An outline drawing, including front, top, and side views.
b. IEEE nameplate data.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 21 Page 10
[c. Elementary diagrams and wiring diagrams with terminals identified of
meter and current transformers.
]d. One-line diagram, including switch(es)[, current transformers,
meters,] and fuses.
e. Manufacturer's published time-current curves in PDF format and in
electronic format suitable for import or updating into the [EasyPower]
[SKM PowerTools for Windows] [_____] computer program of the
transformer high side fuses.
1.5.2 Regulatory Requirements
In each of the publications referred to herein, consider the advisory
provisions to be mandatory, as though the word "shall" or "must" had been
substituted for "should" wherever it appears. Interpret references in these
publications to the "authority having jurisdiction," or words of similar
meaning, to mean the Contracting Officer. Provide equipment, materials,
installation, and workmanship in accordance with NFPA 70 unless more
stringent requirements are specified or indicated.
1.5.3 Standard Products
Provide materials and equipment that are products of manufacturers regularly
engaged in the production of such products which are of equal material,
design and workmanship, and:
a. Have been in satisfactory commercial or industrial use for 2 years
prior to bid opening including applications of equipment and materials
under similar circumstances and of similar size.
b. Have been on sale on the commercial market through advertisements,
manufacturers' catalogs, or brochures during the 2-year period.
c. Where two or more items of the same class of equipment are required,
provide products of a single manufacturer; however, the component parts
of the item need not be the products of the same manufacturer unless
stated in this section.
1.5.3.1 Alternative Qualifications
Products having less than a 2-year field service record will be acceptable
if a certified record of satisfactory field operation for not less than 6000
hours, exclusive of the manufacturers' factory or laboratory tests, is
furnished.
1.5.3.2 Material and Equipment Manufacturing Date
Products manufactured more than 3 years prior to date of delivery to site
are not acceptable.
1.6 MAINTENANCE
1.6.1 Additions to Operation and Maintenance Data
***************************************************************************
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 21 Page 11
Note: Delete bracketed information for Navy and Air
Force projects when separate metering specification
is used. May still need for Army and NASA projects
until metering specification is unified.
***************************************************************************
Submit operation and maintenance data in accordance with Section 01 78 23
OPERATION AND MAINTENANCE DATA and as specified herein. In addition to
requirements of Data Package 5, include the following on the actual
transformer(s) provided:
a. An instruction manual with pertinent items and information highlighted.
b. An outline drawing, front, top, and side views.
c. Prices for spare parts and supply list.
d. Routine and field acceptance test reports.
e. Fuse curves for primary fuses.
[f. Information on watthour demand meter, CT's, and fuse block.
]g. Actual nameplate diagram.
h. Date of purchase.
PART 2 PRODUCTS
2.1 PRODUCT COORDINATION
Products and materials not considered to be pad-mounted transformers and
related accessories are specified in[ Section 33 71 01 OVERHEAD TRANSMISSION
AND DISTRIBUTION,][ Section 26 20 00 INTERIOR DISTRIBUTION SYSTEM,][ and][
Section 33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION].
2.2 SINGLE-PHASE PAD-MOUNTED TRANSFORMERS (DEAD-FRONT)
***************************************************************************
NOTE: According to IEEE 386, 200 ampere separable
insulated connectors normally used on dead-front pad-
mounted transformers have both a fault closure and a
short-time current rating of 10,000 amperes.
Therefore, from a safety standpoint, dead-front
configurations which utilize these connectors should
only be used at system locations which have available
fault currents of less than 10,000 rms symmetrical
amperes.
Normally use single compartment (clam shell)
transformers. If two-compartment transformers are
required, their use must be approved by the the
technical review authority.
Utilization of 35 kV single-phase transformers is not
a recommended design practice. Therefore, approval
for use is required by the technical review authority
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 21 Page 12
and significant changes to this specification would
be required.
This specification does not address the materials
used for the winding (copper versus aluminum) and it
is assumed that the manufacturer will provide their
standard product with respect to the winding
construction, based on the cost of materials at the
time of order acceptance. No failure data has been
obtained indicating that copper windings have a
longer life than aluminum windings. If copper
windings are specified, the cost increase for single-
phase distribution transformers has recently been
about 15 percent. Do NOT specify winding materials.
***************************************************************************
IEEE C57.12.25, IEEE C57.12.28 and as specified herein. Submit
manufacturer's information for each component, device, insulating fluid, and
accessory provided with the transformer.
2.2.1 Compartment Construction
[a. Single compartment: Provide Type 1 combination high- and low-voltage
compartment, clam shell style, with lockable (having pad-locking
provisions) hinged cover and single-point latching. Type 1 is defined
by IEEE C57.12.25.
][b. Two compartment: Provide high- and low-voltage compartments
separated by steel isolating barriers extending the full height and
depth of the compartments. Compartment doors:
(1) Hinged lift-off type with stop in open position and three-point
latching.
(2) High voltage door fastening accessible only after the low voltage
door has been opened.
]2.2.1.1 High Voltage
***************************************************************************
NOTE: Current policy is to use oil-immersed fuses in
series with current limiting fuses to achieve better
protection and obtain life cycle cost benefits.
For 15 kV and 25 kV, 200 A bushings, select bushing
wells and bushing well inserts.
Use two bushing wells for phase-to-neutral systems
and four bushing wells for phase-to-phase systems.
Coordinate with transformer voltage designations in
paragraph TRANSFORMER. If feed through applications
are required, special transformer compartment sizing
may be necessary.
If feed through inserts are used, then ensure the
enclosure is specified to be wide enough and deep
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 21 Page 13
enough to contain the inserts with conductors
terminated.
Delete dead-break connectors and load-break switch
handle options except for systems with a fault
capability greater than 10,000 amps or when the
primary cable size is greater than No. 4/0 AWG. This
design requires approval of the technical review
authority.
Do not provide standoff bushings unless this
transformer is the only dead-front transformer on the
base. Public works normally carries standoff
bushings in their vehicles. Provide protective caps
when providing standoff bushings and to cover unused
bushing well inserts when not providing surge
arresters.
Coordinate lead-in paragraph with bracketed options
below.
***************************************************************************
High-voltage portion contains: the incoming line, insulated high-voltage
[load-break ][dead-break ]connectors, bushing well inserts,[ feed-through
inserts,] [two][four] high-voltage bushing wells configured for loop feed
application,[ load-break switch handle(s),] access to oil-immersed fuses,[
dead-front surge arresters,] tap changer handle, connector parking stands[
with insulated standoff bushings],[ protective caps,] and ground pad.
[a. Insulated high-voltage load-break connectors: IEEE 386, rated
[15][_____] kV, [95][_____] kV BIL. Current rating: 200 amperes rms
continuous. Short time rating: 10,000 amperes rms symmetrical for a
time duration of 0.17 seconds. Provide connectors and inserts from the
same manufacturer. Provide connectors with a steel reinforced hook-
stick eye, grounding eye, test point, and arc-quenching contact
material.
][b. Insulated high-voltage dead-break connectors: IEEE 386, rated [15
kV, 95 kV BIL][25 kV, 125 kV BIL]. Current rating: 600 amperes rms
continuous. Short time rating: 25,000 amperes rms symmetrical for a
time duration of 0.17 seconds. Provide connectors with a [200 ampere
bushing interface for surge arresters,] steel reinforced hook-stick
eye, grounding eye, test point, and arc-quenching contact material.
]c. Bushing well inserts[ and feed-through inserts]: IEEE 386, 200
amperes, [15][_____] kV class. Provide a bushing well insert for each
bushing well unless indicated otherwise.[ Provide feed-through inserts
as indicated.]
[d. One-piece bushings: IEEE 386, 600 amperes, [15][25] kV Class.
][e. Load-break switch: Radial-feed oil-immersed type rated at [15 kV, 95
kV BIL][25 kV, 125 kV BIL], with a continuous current rating and load-
break rating of [200][300][_____] amperes, and a make-and-latch rating
of 12,000 rms amperes symmetrical. Locate the switch handle in the
high-voltage compartment.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 21 Page 14
]f. Provide bayonet oil-immersed, expulsion fuses in series with oil-
immersed, partial-range, current-limiting fuses. The bayonet fuse
links sense both high currents and high oil temperature in order to
provide thermal protection to the transformer. Coordinate transformer
protection with expulsion fuse clearing low-current faults and current-
limiting fuse clearing high-current faults beyond the interrupting
rating of the expulsion fuse. Include an oil retention valve inside
the bayonet assembly housing, which closes when the fuse holder is
removed, and an external drip shield to minimize oil spills. Display a
warning label adjacent to the bayonet fuse(s) cautioning against
removing or inserting fuses unless the transformer has been de-
energized and the tank pressure has been released.
Bayonet fuse assembly: 150 kV BIL.
***************************************************************************
NOTE: Delete the bracketed option regarding
placement of current-limiting fuses except when load-
break switch is specified.
***************************************************************************
Oil-immersed current-limiting fuses: IEEE C37.47; 50,000 rms amperes
symmetrical interrupting rating at the system voltage specified.[
Connect current-limiting fuses ahead of the radial-feed load-break
switch.]
***************************************************************************
NOTE: Provide bushing-mounted elbow type arresters
at the ends of all radials. Provide arresters for
all voltage levels above 5 kV.
***************************************************************************
[g. Surge arresters: IEEE C62.11, rated [3][6][9][10][12][15][_____] kV,
fully shielded, dead-front metal-oxide-varistor, elbow type with
resistance-graded gap suitable for plugging into inserts as indicated.
]h. Parking stands: Provide a parking stand near each bushing well.[
Provide insulated standoff bushings for parking of energized load-break
connectors on parking stands.]
[i. Protective caps: IEEE 386, 200 amperes, [15][25][_____] kV class.
Provide insulated protective caps (not shipping caps) for insulating
and sealing out moisture from unused bushing well inserts[ and
insulated standoff bushings].
]2.2.1.2 Low Voltage
***************************************************************************
NOTE: Installation of circuit breakers in the
transformer is not recognized by IEEE standards, and
limits accessibility by covering lugs, gauges, and
accessories. Do not use.
Coordinate lead-in paragraph with bracketed options
below.
***************************************************************************
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 21 Page 15
Low-voltage portion contains: low-voltage bushings with NEMA spade
terminals, accessories,[ metering,] stainless steel or laser-etched anodized
aluminum diagrammatic transformer nameplate, and ground pad.
a. Include the following accessories: drain plug, fill plug, pressure
relief device and a liquid level sight gage.
***************************************************************************
NOTE: Many Activities have, or are in the process
of, converting to basewide metering systems. A
unified metering specification is under development
to replace the metering requirements in this section.
For single-compartment (clam shell type)
transformers, use the first bracketed paragraph to
provide a self-contained meter base at the facility
served by the transformer, such as individual housing
units or lift stations. For two-compartment
transformers, use the second bracketed paragraph
below for Navy projects and possibly for Air Force
projects. Navy projects require use of Section 26 27
14.00 20 ELECTRICITY METERING. Air Force projects
may require use of Section 26 27 13.10 30 ELECTRIC
METERS. Delete the third bracketed paragraphs below
for Air Force and Navy projects.
Coordinate with the Activity and provide specific
requirements "to match existing systems" when
necessary. If specifying proprietary products,
insure that appropriate "Justification and
Authorization (J & A)" documentation has been
obtained by project manager and "proprietary language
requirements" have been added to Division 1 as well
as to this section of the specifications.
If there are any components (such as meters, housing,
or current transformers) that will be Government
Furnished Contractor Installed (GFCI), or Government
Furnished Government Installed (GFGI), edit Division
1 and this specification section.
***************************************************************************
b. Metering
[For single-compartment (clam shell type) transformers, provide a self-
contained meter base at the facility to be served by the transformer,
as specified in Section 26 20 00 INTERIOR DISTRIBUTION SYSTEM.
][For two-compartment transformers, provide as specified in Section [26
27 13.10 30 ELECTRIC METERS][26 27 14.00 20 ELECTRICITY METERING].
][For two-compartment transformers, provide a transformer-rated meter
at the secondary portion of the transformer.
[(1) NEMA/ANSI C12.10. Provide a socket-mounted electronic
programmable outdoor watthour meter, surface mounted flush against
the side of the low-voltage compartment as indicated. Program the
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 21 Page 16
meter at the factory or in the field. When field programming is
performed, turn field programming device over to the Contracting
Officer at completion of project. Coordinate the meter to system
requirements.
***************************************************************************
NOTE: When Section 23 09 00 INSTRUMENTATION AND
CONTROL FOR HVAC is used, coordinate meter
requirements. Form 4S, in text below, is for single-
phase, three-wire systems, for other system
configurations, designer must determine the
appropriate form designation.
***************************************************************************
(a) Design: Provide meter designed for use on a single-phase,
three-wire, [240/120][480/240] volt system with two current
transformers. Include necessary KYZ pulse initiation hardware for
energy monitoring and control system (EMCS)[ as specified in
Section 23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC].
(b) Coordination: Provide meter coordinated with ratios of current
transformers and transformer secondary voltage.
(c) Class: 20; Form: 4S, accuracy: plus or minus 1.0 percent
Finish: Class II.
(d) Cover: Polycarbonate and lockable to prevent tampering and
unauthorized removal.
(e) Kilowatt-hour register: five digit electronic programmable
type.
(f) Demand register:
1. Provide solid state.
2. Meter reading multiplier: Indicate multiplier on the meter
face.
3. Demand interval length: programmed for [15][30][60]
minutes with rolling demand up to six subintervals per interval.
(g) Meter fusing: Provide a fuse block mounted in the secondary
side containing one fuse per phase to protect the voltage input to
the meter. Size fuses as recommended by the meter manufacturer.
(h) Socket: ANSI C12.7. Provide NEMA Type 3R, box-mounted socket
having automatic circuit-closing bypass and having jaws compatible
with requirements of the meter. Cover unused hub openings with
blank hub plates. Paint box Munsell 7GY3.29/1.5 green to match the
pad-mounted transformer to which the box-mounted socket is
attached. The Munsell color notation is specified in ASTM D1535.
](2) Current transformers IEEE C57.13. Provide butyl-molded window
type current transformers with 600-volt insulation, 10 kV BIL and
mount on the low-voltage bushings. Route current transformer leads
in a location as remote as possible from the power transformer
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 21 Page 17
secondary cables to permit current measurements to be taken with
hook-on-ammeters. Provide two current transformers per power
transformer with characteristics listed in the following table.
***************************************************************************
NOTE: The following guidelines for specifying
current transformers are based on the standard
current transformer primary rating which is just
below the full load current of the power transformer.
1. Select the appropriate current transformer (CT)
ratio, continuous-thermal-current rating factor (RF)
at 30 degrees C and ANSI metering accuracy class
values based on transformer kVA size and secondary
voltage. Example: for a 50 kVA transformer at 240
volts - select 200/5, 4.0, 0.3 through B-0.1.
VOLTS
240 480
kVA CT Ratio RF Meter Class CT Ratio RF Meter Class
15 200/5, 4.0, 0.3 thru B-0.1 200/5, 4.0, 0.3 thru B-0.1
25 200/5, 4.0, 0.3 thru B-0.1 200/5, 4.0, 0.3 thru B-0.1
37.5 200/5, 4.0, 0.3 thru B-0.1 200/5, 4.0, 0.3 thru B-0.1
50 200/5, 4.0, 0.3 thru B-0.1 200/5, 4.0, 0.3 thru B-0.1
75 300/5, 3.0, 0.3 thru B-0.2 200/5, 4.0, 0.3 thru B-0.1
160 400/5, 4.0, 0.3 thru B-0.2 200/5, 4.0, 0.3 thru B-0.1
167 600/5, 3.0, 0.3 thru B-0.5 300/5, 3.0, 0.3 thru B-0.2
2. Incorporate the appropriate values in table.
***************************************************************************
NAME kVA Sec. Volt CT Ratio RF Meter Acc. Class
[T1] [50] [240] [200/5] [4.0] [0.3 thru B-0.1]
[T2] [75] [480] [200/5] [4.0] [0.3 thru B-0.1]
]2.2.2 Transformer
***************************************************************************
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 21 Page 18
NOTE: Use the following guidelines for specifying
transformers and insulating liquids.
1. On Navy projects use of biodegradable less-
flammable liquid is required.
For other projects, biodegradable less-flammable
liquid and mineral oil are permitted. Previously the
use of mineral oil-filled transformers was
recommended wherever possible. Currently,
biodegradable less-flammable transformer liquids that
improve transformer operating characteristics are
available with little, if any premium cost. This
requirement is supported by UFC 3-600-01, "Fire
Protection Engineering for Facilities", identifies
building and equipment separation distances based on
insulating liquid type. Mineral oil is more
restrictive than less-flammable liquid. For example,
a 1500 kVA transformer containing 600 gallons of
less-flammable liquid requires a building separation
distance of 1.5 meters (5 feet) when the construction
is fire-resistant or non-combustible. An equally
sized mineral oil-filled transformer requires 4.6
meters (15 feet) and 7.6 meters (25 feet) of
separation for fire-resistant and non-combustible
construction, respectively. Do not specify silicone-
filled transformers.
2. Use IEEE C57.12.00, Table 7, voltage
designations, such as "4160 V - 240/120 V" for
transformers connected phase-phase on the primary
side, or "4160GrdY/2400 V - 240/120 V" for
transformers connected phase-neutral on the primary
side. Coordinate the number of bushing wells (either
two or four depending on phase-to-neutral, or phase-
to-phase systems) with the primary voltage.
3. Tap ratings may vary from those indicated,
especially in lower kVA ratings.
4. Include bracketed option to display transformer
rating on enclosure when directed by Activity. For
NASA projects only, include 3 inch yellow lettering
bracketed options.
***************************************************************************
a. Less-flammable[ bio-based] liquid-insulated[ or oil-insulated], two
winding, 60 hertz, 65 degrees C rise above a 30 degrees C average
ambient, self-cooled type.
[b. Rated [_____] kVA][With characteristics per the following table:
NAME LOCATION kVA Voltage
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 21 Page 19
NAME LOCATION kVA Voltage
[T1] [AMTC Site 1] [50] [240/120]
[T2] [AMTC Site 2] [75] [240/120]
]c. Voltage ratings: [[_____] V - [240/120][480/240] V][see table].
d. Tap changer: externally operated, manual type for changing tap setting
when the transformer is de-energized. Provide four 2.5 percent full
capacity taps, two above and two below rated primary voltage. Indicate
which tap setting is in use, clearly visible when the compartment is
opened.
e. Minimum tested percent impedance at 85 degrees C:
2.50 for units rated 25 kVA and below
2.87 for units rated 37.5 kVA to 100 kVA
4.03 for 167 kVA rated units
f. Comply with the following audible sound level limits:
kVA DECIBELS
(MAX)
10 48
15 48
25 48
37.5 48
50 48
75 51
100 51
167 55
***************************************************************************
NOTE: Use "lifting lugs" on two-compartment and
"recessed stainless steel lifting provisions" on clam
shell type transformers. Delete the "access
handhole" on clam shell type transformers.
***************************************************************************
g. Include:
(1) [Lifting lugs and provisions for jacking under base][Recessed
stainless steel lifting provisions], with base construction
suitable for using rollers or skidding in any direction.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 21 Page 20
(2) An insulated low-voltage neutral bushing with NEMA spade terminal,
and with removable ground strap.
[(3) Provide transformer top with an access handhole.
][(4) kVA rating conspicuously displayed [using 75 mm (3 inch) high
yellow letters ]on its enclosure.
]2.2.2.1 Specified Transformer Efficiencies
***************************************************************************
NOTE: Transformer losses and efficiency requirements
have been modified into the table included within the
specification and the previous Navy loss tables have
been deleted.
10 CFR 431, Subpart K is a result of the Energy
Policy and Conservation Act (EPACT) of 2005 and is
the "minimum" industry standard for distribution
transformers manufactured on or after January 1,
2016.
***************************************************************************
Provide transformer efficiency calculations utilizing the actual no-load and
load loss values obtained during the routine tests performed on the actual
transformer(s) prepared for this project. Reference no-load losses (NLL) at
20 degrees C. Reference load losses (LL) at 55 degrees C and at 50 percent
of the nameplate load. The transformer is not acceptable if the calculated
transformer efficiency is less than the efficiency indicated in the "KVA /
Efficiency" table below. The table is based on requirements contained
within 10 CFR 431, Subpart K. Submit certification, including supporting
calculations, from the manufacturer indicating conformance.
kVA EFFICIENCY
(percent)
10 98.70
15 98.82
25 98.95
37.5 99.05
50 99.11
75 99.19
100 99.25
167 99.33
2.3 INSULATING LIQUID
***************************************************************************
NOTE: On Navy projects use of biodegradable less-
flammable liquid is required.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 21 Page 21
***************************************************************************
a. Less-flammable[ bio-based] transformer liquids: NFPA 70 and FM APP
GUIDE for less-flammable liquids having a fire point not less than 300
degrees C tested per ASTM D92 and a dielectric strength not less than
33 kV tested per ASTM D877/D877M. Provide identification of
transformer as "non-PCB" and "manufacturer's name and type of fluid" on
the nameplate.
Provide a fluid that is a biodegradable,[ bio-based] electrical
insulating, and cooling liquid classified by UL and approved by FM as
"less flammable" with the following properties:
(1) Pour point: ASTM D97, less than -15 degree C.
(2) Aquatic biodegradation: EPA 712-C-98-075, 100 percent.
(3) Trout toxicity: OECD Test 203, zero mortality of EPA 821-R-02-012,
pass.
[b. Mineral oil: ASTM D3487, Type II, tested in accordance with ASTM
D117. Provide identification of transformer as non-PCB and Type II
mineral oil on the nameplate.
]2.4 LIQUID-FILLED TRANSFORMER NAMEPLATES
Provide nameplate information in accordance with IEEE C57.12.00 and as
modified or supplemented by this section.
2.5 CORROSION PROTECTION
***************************************************************************
NOTE: Use stainless steel bases and cabinets for
most applications. In hostile environments, the
additional cost of totally stainless steel tanks and
metering enclosures may be justified. Manufacturer's
standard construction material is acceptable only in
noncoastal and noncorrosive environments. Choose the
second main bracketed option for hostile
environments.
***************************************************************************
[Provide corrosion resistant bases and cabinets of transformers, fabricated
of stainless steel conforming to ASTM A240/A240M, Type 304 or 304L. Base
includes any part of pad-mounted transformer that is within 75 mm (3 inches)
of concrete pad.
][Provide entire transformer assembly, including tank and radiator, base,
enclosure, and metering enclosure fabricated of stainless steel conforming
to ASTM A240/A240M, Type 304 or 304L. Form enclosure of stainless steel
sheets. The optional use of aluminum is permitted for the metering
enclosure.
]Paint entire transformer assembly [Munsell 7GY3.29/1.5 green][Munsell
5BG7.0/0.4 sky gray (ANSI 70)][_____], with paint coating system complying
with IEEE C57.12.28 [and IEEE C57.12.29 ]regardless of base, cabinet, and
tank material. The Munsell color notation is specified in ASTM D1535.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 21 Page 22
2.6 WARNING SIGNS AND LABELS
Provide warning signs for the enclosures of pad-mounted transformers having
a nominal rating exceeding 600 volts in accordance with NEMA Z535.4 and NEMA
260.
a. When the enclosure integrity of such equipment is specified to be
in accordance with IEEE C57.12.28, such as for pad-mounted
transformers, provide self-adhesive warning labels (decals, Panduit
No. PPSO710D72 or approved equal) on the outside of the high
voltage compartment door(s) with nominal dimensions of 178 by 255
mm (7 by 10 inches) with the legend "WARNING HIGH VOLTAGE" printed
in two lines of nominal 50 mm (2 inch) high letters. Include the
word "WARNING" in white letters on an orange background and the
words "HIGH VOLTAGE" in black letters on a white background.
[b. When such equipment is guarded by a fence, mount signs on the
fence. Provide metal signs having nominal dimensions of 355 by 255
mm (14 by 10 inches) with the legend "WARNING HIGH VOLTAGE KEEP
OUT" printed in three lines of nominal 75 mm (3 inch) high white
letters on an orange and black field.
]
***************************************************************************
NOTE: Include the Arc Flash Warning Label detail on
the drawings. See the technical notes at the
beginning of section to obtain the AutoCAD drawing
file of the label.
***************************************************************************
Provide arc flash warning label for the enclosure of pad-mounted
transformers. Locate this self-adhesive warning label on the outside of the
high voltage compartment side warning of potential electrical arc flash
hazards and appropriate PPE required. Provide label format as indicated.
2.7 GROUNDING AND BONDING
UL 467. Provide grounding and bonding as specified in Section 33 71 02
UNDERGROUND ELECTRICAL DISTRIBUTION.
[2.8 PADLOCKS
***************************************************************************
NOTE: Designer must assure that Section 08 71 00
DOOR HARDWARE is included and is edited to include
padlocks.
Do not use this paragraph for Navy and Air Force
projects.
***************************************************************************
Provide padlocks for pad-mounted equipment[ and for each fence gate], keyed
[alike][as directed by the Contracting Officer]. Comply with Section 08 71
00 DOOR HARDWARE.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 21 Page 23
]2.9 CAST-IN-PLACE CONCRETE
***************************************************************************
NOTE: Use the first bracketed paragraph when project
includes a concrete section in Division 03;
otherwise, the second bracketed paragraph may be
used. Coordinate requirements with Section 03 30
00.00 10 CAST-IN-PLACE CONCRETE or Section 03 30 00
CAST-IN-PLACE CONCRETE. Use Section 03 30 00 for
Navy projects and Section 03 30 00.00 10 for other
projects.
***************************************************************************
[Provide concrete associated with electrical work for other than encasement
of underground ducts rated for 30 MPa (4000 psi) minimum 28-day compressive
strength unless specified otherwise. Conform to the requirements of
Section[ 03 30 00 CAST-IN-PLACE CONCRETE][ 03 30 00.00 10 CAST-IN-PLACE
CONCRETE].
]
***************************************************************************
NOTE: If concrete requirements are detailed and no
cast-in-place section is to be included in the
project specification, refer to Section 03 30 00
CAST-IN-PLACE CONCRETE or Section 03 30 00.00 10
CAST-IN-PLACE CONCRETE and select such portions as
needed to provide complete requirements in addition
to the requirements below.
***************************************************************************
[Provide concrete associated with electrical work as follows:
a. Composed of fine aggregate, coarse aggregate, portland cement, and
water so proportioned and mixed as to produce a plastic, workable
mixture.
b. Fine aggregate: hard, dense, durable, clean, and uncoated sand.
c. Coarse aggregate: reasonably well graded from 4.75 mm to 25 mm (3/16
inch to 1 inch).
d. Fine and coarse aggregates: free from injurious amounts of dirt,
vegetable matter, soft fragments or other deleterious substances.
e. Water: fresh, clean, and free from salts, alkali, organic matter, and
other impurities.
f. Concrete associated with electrical work for other than encasement of
underground ducts: 30 MPa (4000 psi) minimum 28-day compressive
strength unless specified otherwise.
g. Slump: Less than 100 mm (4 inches). Retempering of concrete will not
be permitted.
h. Exposed, unformed concrete surfaces: smooth, wood float finish.
i. Concrete must be cured for a period of not less than 7 days, and
concrete made with high early strength portland cement must be repaired
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 21 Page 24
by patching honeycombed or otherwise defective areas with cement mortar
as directed by the Contracting Officer.
j. Air entrain concrete exposed to weather using an air-entraining
admixture conforming to ASTM C260/C260M.
k. Air content: between 4 and 6 percent.
]2.10 SOURCE QUALITY CONTROL
2.10.1 Transformer Test Schedule
The Government reserves the right to witness tests. Provide transformer
test schedule for tests to be performed at the manufacturer's test facility.
Submit required test schedule and location, and notify the Contracting
Officer 30 calendar days before scheduled test date. Notify Contracting
Officer 15 calendar days in advance of changes to scheduled date.
2.10.2 Test Instrument Calibration
a. Provide a calibration program which assures that all applicable test
instruments are maintained within rated accuracy.
b. Accuracy: Traceable to the National Institute of Standards and
Technology.
c. Instrument calibration frequency schedule: less than or equal to 12
months for both test floor instruments and leased specialty equipment.
d. Dated calibration labels: visible on all test equipment.
e. Calibrating standard: higher accuracy than that of the instrument
tested.
f. Keep up-to-date records that indicate dates and test results of
instruments calibrated or tested. For instruments calibrated by the
manufacturer on a routine basis, in lieu of third party calibration,
include the following:
(1) Maintain up-to-date instrument calibration instructions and
procedures for each test instrument.
(2) Identify the third party/laboratory calibrated instrument to verify
that calibrating standard is met.
2.10.3 Design Tests
IEEE C57.12.00, and IEEE C57.12.90. Section 5.1.2 in IEEE C57.12.80 states
that "design tests are made only on representative apparatus of basically
the same design." Submit design test reports (complete with test data,
explanations, formulas, and results), in the same submittal package as the
catalog data and drawings for[ each of] the specified transformer(s), with
design tests performed prior to the award of this contract.
a. Tests: certified and signed by a registered professional engineer.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 21 Page 25
b. Temperature rise: "Basically the same design" for the temperature rise
test means a pad-mounted transformer with the same coil construction
(such as wire wound primary and sheet wound secondary), the same kVA,
the same cooling type (ONAN), the same temperature rise rating, and the
same insulating liquid as the transformer specified.
c. Lightning impulse: "Basically the same design" for the lightning
impulse dielectric test means a pad-mounted transformer with the same
BIL, the same coil construction (such as wire wound primary and sheet
wound secondary), and a tap changer, if specified. Design lightning
impulse tests includes the primary windings only of that transformer.
(1) IEEE C57.12.90, paragraph 10.3 entitled "Lightning Impulse Test
Procedures," and IEEE C57.98.
(2) State test voltage levels.
(3) Provide photographs of oscilloscope display waveforms or plots of
digitized waveforms with test report.
d. Lifting and moving devices: "Basically the same design" requirement
for the lifting and moving devices test means a test report confirming
that the lifting device being used is capable of handling the weight of
the specified transformer in accordance with IEEE C57.12.25.
e. Pressure: "Basically the same design" for the pressure test means a
pad-mounted transformer with a tank volume within 30 percent of the
tank volume of the transformer specified.
f. Short circuit: "Basically the same design" for the short circuit test
means a pad-mounted transformer with the same kVA as the transformer
specified.
2.10.4 Routine and Other Tests
IEEE C57.12.00. Routine and other tests: performed by the manufacturer on[
each of] the actual transformer(s) prepared for this project to ensure that
the design performance is maintained in production. Submit test reports, by
serial number and receive approval before delivery of equipment to the
project site. Required tests include:
a. Polarity.
b. Ratio.
c. No-load losses (NLL) and excitation current.
d. Load losses (LL) and impedance voltage.
e. Dielectric.
(1) Impulse.
(2) Applied voltage.
(3) Induced voltage.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 21 Page 26
f. Leak.
PART 3 EXECUTION
3.1 INSTALLATION
Conform to IEEE C2, NFPA 70, and to requirements specified herein. Provide
new equipment and materials unless indicated or specified otherwise.
3.2 GROUNDING
NFPA 70 and IEEE C2, except provide grounding systems with a resistance to
solid earth ground not exceeding [25][_____] ohms.
3.2.1 Grounding Electrodes
Provide driven ground rods as specified in Section 33 71 02 UNDERGROUND
ELECTRICAL DISTRIBUTION. Connect ground conductors to the upper end of
ground rods by exothermic weld or compression connector. Provide
compression connectors at equipment end of ground conductors.
3.2.2 Pad-Mounted Transformer Grounding
***************************************************************************
NOTE: Ensure plans show the secondary neutral
grounding conductor sized in accordance with NFPA 70
and the primary neutral grounding conductor when
required. Ensure the CADD detail used matches how
this paragraph is edited. Transformer is to have a
ground ring and the normal number of ground rods is
either four or two. The one ground rod option should
only be chosen if required by local installation
requirements.
***************************************************************************
Provide a ground ring around the transformer with [1/0][4/0] AWG bare
copper.[ Provide four ground rods in the ground ring, one per corner.][
Provide two ground rods in the ground ring at opposite corners.][ Provide
one ground rod in the ground ring with the ground rod located in the
transformer cabinet.] Install the ground rods at least 3000 mm (10 feet)
apart from each other. Provide separate copper grounding conductors and
connect them to the ground loop as indicated. When work in addition to that
indicated or specified is required to obtain the specified ground
resistance, the provision of the contract covering "Changes" applies.
3.2.3 Connections
Make joints in grounding conductors and loops by exothermic weld or
compression connector. Install exothermic welds and compression connectors
as specified in Section 33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION.
3.2.4 Grounding and Bonding Equipment
UL 467, except as indicated or specified otherwise.
3.3 INSTALLATION OF EQUIPMENT AND ASSEMBLIES
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 21 Page 27
Install and connect pad-mounted transformers furnished under this section as
indicated on project drawings, the approved shop drawings, and as specified
herein.
[3.3.1 Meters and Current Transformers
***************************************************************************
Note: Delete bracketed paragraph for Navy and Air
Force projects, this information is covered in their
associated metering specifications.
***************************************************************************
ANSI C12.1.
]3.4 FIELD APPLIED PAINTING
Where field painting of enclosures is required to correct damage to the
manufacturer's factory applied coatings, provide manufacturer's recommended
coatings and apply in accordance with manufacturer's instructions.
[3.5 WARNING SIGN MOUNTING
***************************************************************************
NOTE: Include the following option when pad-mounted
transformer is guarded by a fence.
***************************************************************************
Provide the number of signs required to be readable from each accessible
side, but space the signs a maximum of 9 meters (30 feet) apart.
]3.6 FOUNDATION FOR EQUIPMENT AND ASSEMBLIES
***************************************************************************
NOTE: Mounting slab connections may have to be given
in detail depending on the requirements for the
seismic zone in which the requirement is located.
Include construction requirements for concrete slab
only if slab is not detailed in drawings. Do not
provide curbs or raised edges around liquid filled
transformers unless specifically approved by
Technical Proponent (link provided in the technical
note at the beginning of this section).
***************************************************************************
Mount transformer on concrete slab as follows:
a. Unless otherwise indicated, provide the slab with dimensions at least
200 mm (8 inches) thick, reinforced with a 152 by 152 mm MW19 by MW19
(6 by 6 inches - W2.9 by W2.9) mesh placed uniformly 100 mm (4 inches)
from the top of the slab.
b. Place slab on a 150 mm (6 inch) thick, well-compacted gravel base.
c. Install slab such that top of concrete slab is approximately 100 mm (4
inches) above the finished grade with gradual slope for drainage.
d. Provide edges above grade with 15 mm (1/2 inch) chamfer.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 21 Page 28
e. Provide slab of adequate size to project at least 200 mm (8 inches)
beyond the equipment.
Stub up conduits, with bushings, 50 mm (2 inches) into cable wells in the
concrete pad. Coordinate dimensions of cable wells with transformer cable
training areas.
3.6.1 Cast-In-Place Concrete
***************************************************************************
NOTE: Use the first bracketed option when project
includes a concrete section in Division 03;
otherwise, the second bracketed option may be used.
***************************************************************************
Provide cast-in-place concrete work in accordance with the requirements of
[Section [03 30 00 CAST-IN-PLACE CONCRETE][03 30 00.00 10 CAST-IN-PLACE
CONCRETE]][ACI 318M(ACI 318)].
[3.6.2 Sealing
***************************************************************************
NOTE: Require sealing of cable wells (windows) in
the concrete pad if rodent intrusion is a problem.
***************************************************************************
When the installation is complete, seal all entries into the equipment
enclosure with an approved sealing method. Provide seals of sufficient
strength and durability to protect all energized live parts of the equipment
from rodents, insects, or other foreign matter.
]3.7 FIELD QUALITY CONTROL
3.7.1 Performance of Acceptance Checks and Tests
Perform in accordance with the manufacturer's recommendations, and include
the following visual and mechanical inspections and electrical tests,
performed in accordance with NETA ATS. Submit reports, including acceptance
criteria and limits for each test in accordance with NETA ATS "Test Values".
3.7.1.1 Pad-Mounted Transformers
a. Visual and mechanical inspection.
(1) Compare equipment nameplate information with specifications and
approved shop drawings.
(2) Inspect physical and mechanical condition. Check for damaged or
cracked insulators and leaks.
(3) Inspect anchorage, alignment, and grounding.
(4) Verify the presence of PCB content labeling.
(5) Verify the bushings and transformer interiors are clean.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 21 Page 29
(6) Inspect all bolted electrical connections for high resistance using
low-resistance ohmmeter, verifying tightness of accessible bolted
electrical connections by calibrated torque-wrench method, or
performing thermographic survey.
(7) Verify correct liquid level in tanks.
(8) Verify that positive pressure is maintained on gas-blanketed
transformers.
(9) Perform specific inspections and mechanical tests as recommended by
manufacturer.
(10) Verify correct equipment grounding.
[(11) Verify the presence of transformer surge arresters.
]b. Electrical tests.
(1) Perform resistance measurements through all bolted connections with
low-resistance ohmmeter.
(2) Verify proper secondary voltage phase-to-phase and phase-to-neutral
after energization and prior to loading.
***************************************************************************
NOTE: Include the bracketed option for additional
field electrical tests for NASA projects only.
***************************************************************************
[(3) Perform insulation-resistance tests, winding-to-winding and each
winding-to-ground. Calculate polarization index.
(4) Perform turns-ratio tests at all tap positions.
(5) Perform insulation power-factor or dissipation-factor tests on all
windings in accordance with test equipment manufacturer's published
data.
(6) Perform power-factor or dissipation-factor tests on each bushing
equipped with a power-factor/capacitance tap. In the absence of a
power-factor/capacitance tap, perform hot-collar tests.
(7) Measure the resistance of each high-voltage winding in each de-
energized tap-changer position. Measure the resistance of each
low-voltage winding in each de-energized tap-changer position, if
applicable.
(8) Remove and test a sample of insulating liquid for the following:
Dielectric breakdown voltage, Acid neutralization number, Specific
gravity, Interfacial tension, Color, Visual Condition, Water in
insulating liquids (Required on 25 kV or higher voltages and on all
silicone-filled units.), and Power factor or dissipation factor.
(9) Perform dissolved-gas analysis (DGA) on a sample of insulating
liquid.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 21 Page 30
][3.7.1.2 Current Transformers
***************************************************************************
NOTE: Delete bracketed optional paragraphs for Navy
and Air Force projects. This information is covered
in their associated metering specifications.
***************************************************************************
a. Visual and mechanical inspection.
(1) Compare equipment nameplate data with specifications and approved
shop drawings.
(2) Inspect physical and mechanical condition.
(3) Verify correct connection.
(4) Verify that adequate clearances exist between primary and secondary
circuit wiring.
(5) Verify the unit is clean.
(6) Inspect all bolted electrical connections for high resistance using
low-resistance ohmmeter, verifying tightness of accessible bolted
electrical connections by calibrated torque-wrench method, or
performing thermographic survey.
(7) Verify that all required grounding and shorting connections provide
good contact.
(8) Verify correct operation of transformer withdrawal mechanism and
grounding operation.
(9) Verify appropriate lubrication on moving current-carrying parts and
on moving and sliding surfaces.
b. Electrical tests.
(1) Perform resistance measurements through all bolted connections with
low-resistance ohmmeter, if applicable.
(2) Perform insulation-resistance test.
(3) Perform a polarity test.
(4) Perform a ratio-verification test.
][3.7.1.3 Watthour Meter
***************************************************************************
NOTE: Delete bracketed optional paragraphs for Navy
and Air Force projects. This information is covered
in their associated metering specifications.
***************************************************************************
a. Visual and mechanical inspection.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 21 Page 31
(1) Compare equipment nameplate data with specifications and approved
shop drawings.
(2) Inspect physical and mechanical condition.
(3) Verify tightness of electrical connections.
b. Electrical tests.
(1) Calibrate watthour meters according to manufacturer's published
data.
(2) Verify that correct multiplier has been placed on face of meter,
where applicable.
(3) Verify that current transformer secondary circuits are intact.
]3.7.1.4 Grounding System
a. Visual and mechanical inspection.
(1) Inspect ground system for compliance with contract plans and
specifications.
b. Electrical tests.
(1) Perform ground-impedance measurements utilizing the fall-of-
potential method. On systems consisting of interconnected ground
rods, perform tests after interconnections are complete. On
systems consisting of a single ground rod perform tests before any
wire is connected. Take measurements in normally dry weather, not
less than 48 hours after rainfall. Use a portable ground
resistance tester in accordance with manufacturer's instructions to
test each ground or group of grounds. Use an instrument equipped
with a meter reading directly in ohms or fractions thereof to
indicate the ground value of the ground rod or grounding systems
under test.
(2) Submit the measured ground resistance of each ground rod and
grounding system, indicating the location of the rod and grounding
system. Include the test method and test setup (i.e., pin
location) used to determine ground resistance and soil conditions
at the time the measurements were made.
[3.7.1.5 Surge Arresters, Medium- and High-Voltage
a. Visual and mechanical inspection.
(1) Compare equipment nameplate data with specifications and approved
shop drawings.
(2) Inspect physical and mechanical condition.
(3) Inspect anchorage, alignment, grounding, and clearances.
(4) Verify the arresters are clean.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 12 21 Page 32
(5) Inspect all bolted electrical connections for high resistance using
low-resistance ohmmeter, verifying tightness of accessible bolted
electrical connections by calibrated torque-wrench method, or
performing thermographic survey.
(6) Verify that the ground lead on each device is individually attached
to a ground bus or ground electrode.
b. Electrical tests.
(1) Perform resistance measurements through all bolted connections with
low-resistance ohmmeter, if applicable.
(2) Perform an insulation-resistance test on each arrester, phase
terminal-to-ground.
(3) Test grounding connection.
]3.7.2 Follow-Up Verification
Upon completion of acceptance checks and tests, show by demonstration in
service that circuits and devices are in good operating condition and
properly performing the intended function. As an exception to requirements
stated elsewhere in the contract, notify the Contracting Officer 5 working
days in advance of the dates and times of checking and testing.
-- End of Section --
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 27 13.10 30 Page 1
***************************************************************************
USACE / NAVFAC / AFCEC / NASA UFGS-26 27 13.10 30 (October 2007)
Change 1 - 11/14
----------------------------------
Preparing Activity: AFCEC
UNIFIED FACILITIES GUIDE SPECIFICATIONS
References are in agreement with UMRL dated October 2017
***************************************************************************
SECTION 26 27 13.10 30
ELECTRIC METERS
10/07
***************************************************************************
NOTE: This guide specification covers the
requirements for the installation of poly-phase
electricity meters suitable for billing, allocation
of costs, and recording of data for energy management
and control applications and is intended to comply
with the metering requirements of EPACT05.
Adhere to UFC 1-300-02 Unified Facilities Guide
Specifications (UFGS) Format Standard when editing
this guide specification or preparing new project
specification sections. Edit this guide
specification for project specific requirements by
adding, deleting, or revising text. For bracketed
items, choose applicable item(s) or insert
appropriate information.
Remove information and requirements not required in
respective project, whether or not brackets are
present.
Comments, suggestions and recommended changes for
this guide specification are welcome and should be
submitted as a Criteria Change Request (CCR).
***************************************************************************
***************************************************************************
NOTE: Since metering for energy management and costs
allocation varies widely, it is expected that the
designer will make significant adjustments and
additions to this guide specification.
NOTE: Use the following related guide specifications
for power distribution equipment:
- - Section 26 12 19.10 THREE-PHASE PAD-MOUNTED
TRANSFORMERS
- - Section 26 11 14.00 10 MAIN ELECTRIC SUPPLY
STATION AND SUBSTATION
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 27 13.10 30 Page 2
- - Section 26 22 00.00 10 480-VOLT STATION SERVICE
SWITCHBOARD AND TRANSFORMERS
- - Section 26 23 00 SWITCHBOARDS AND SWITCHGEAR
NOTE: This specification provides guidance for the
facility energy manager or design engineer after
determining what data will be gathered and what
analysis procedures will be used.
***************************************************************************
PART 1 GENERAL
1.1 REFERENCES
***************************************************************************
NOTE: This paragraph is used to list the
publications cited in the text of the guide
specification. The publications are referred to in
the text by basic designation only and listed in this
paragraph by organization, designation, date, and
title.
Use the Reference Wizard's Check Reference feature
when you add a Reference Identifier (RID) outside of
the Section's Reference Article to automatically
place the reference in the Reference Article. Also
use the Reference Wizard's Check Reference feature to
update the issue dates.
References not used in the text will automatically be
deleted from this section of the project
specification when you choose to reconcile references
in the publish print process.
***************************************************************************
The publications listed below form a part of this specification to the
extent referenced. The publications are referred to within the text by the
basic designation only.
INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)
IEEE 100 (2000; Archived) The Authoritative Dictionary
of IEEE Standards Terms
IEEE C2 (2017; Errata 1-2 2017; INT 1 2017) National
Electrical Safety Code
IEEE C37.90.1 (2013) Standard for Surge Withstand
Capability (SWC) Tests for Relays and Relay
Systems Associated with Electric Power
Apparatus
IEEE C57.13 (2016) Requirements for Instrument
Transformers
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 27 13.10 30 Page 3
INTERNATIONAL ELECTROTECHNICAL COMMISSION (IEC)
IEC 61000-4-5 (2017) Electromagnetic Compatibility (EMC) -
Part 4-5: Testing and Measurement Techniques
- Surge Immunity Test
IEC 62053-22 (2003; ED 1.0) Electricity Metering Equipment
(a.c.) - Particular Requirements - Part 22:
Static Meters for Active Energy (Classes 0,2
S and 0,5 S)
NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)
ANSI C12.18 (2006; R 2016) Protocol Specification for
ANSI Type 2 Optical Port
ANSI C12.20 (2015) Electricity Meters - 0.1, 0.2, and 0.5
Accuracy Classes
ANSI C62.61 (1993) American National Standard for Gas
Tube Surge Arresters on Wire Line Telephone
Circuits
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 70 (2017; ERTA 1-2 2017; TIA 17-1; TIA 17-2; TIA
17-3) National Electrical Code
1.2 DEFINITIONS
Unless otherwise specified or indicated, electrical and electronics terms
used in this specification and on the drawings shall be as defined in IEEE
100.
1.3 SUBMITTALS
***************************************************************************
NOTE: Review submittal description (SD) definitions
in Section 01 33 00 SUBMITTAL PROCEDURES and edit the
following list to reflect only the submittals
required for the project.
The Guide Specification technical editors have
designated those items that require Government
approval, due to their complexity or criticality,
with a "G." Generally, other submittal items can be
reviewed by the Contractor's Quality Control System.
Only add a “G” to an item, if the submittal is
sufficiently important or complex in context of the
project.
For submittals requiring Government approval on Army
projects, a code of up to three characters within the
submittal tags may be used following the "G"
designation to indicate the approving authority.
Codes for Army projects using the Resident Management
System (RMS) are: "AE" for Architect-Engineer; "DO"
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 27 13.10 30 Page 4
for District Office (Engineering Division or other
organization in the District Office); "AO" for Area
Office; "RO" for Resident Office; and "PO" for
Project Office. Codes following the "G" typically
are not used for Navy, Air Force, and NASA projects.
Use the "S" classification only in SD-11 Closeout
Submittals. The "S" following a submittal item
indicates that the submittal is required for the
Sustainability eNotebook to fulfill federally
mandated sustainable requirements in accordance with
Section 01 33 29 SUSTAINABILITY REPORTING.
Choose the first bracketed item for Navy, Air Force
and NASA projects, or choose the second bracketed
item for Army projects.
***************************************************************************
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for [Contractor Quality Control
approval.] [information only. When used, a designation following the "G"
designation identifies the office that will review the submittal for the
Government.] Submittals with an "S" are for inclusion in the Sustainability
eNotebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
a. Maintenance manual shall provide:
1. Condensed description of how the equipment operates.
2. Block diagram indicating major assemblies.
3. Troubleshooting information
4. Preventive maintenance.
5. Spare parts information.
b. Provide operation and maintenance manuals required by submittal item "SD-
10 Operation and Maintenance Data."
SD-02 Shop Drawings
SD-03 Product Data
Power Meters; G[, [_____]]
Current Transformers; G[, [_____]]
Potential Transformer; G[, [_____]]
Communications Module; G[, [_____]]
Protocol Modules; G[, [_____]]
Data Recorder; G[, [_____]]
Modem; G[, [_____]]
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 27 13.10 30 Page 5
Submittals shall include manufacturer's information for each component,
device, and accessory provided with the meter, protocol module or
communications module.
SD-06 Test Reports
Acceptance Checks and Tests; G[, [_____]]
SD-10 Operation and Maintenance Data
Power Meters; G[, [_____]]
Communications Module; G[, [_____]]
Protocol Modules; G[, [_____]]
Data Recorder; G[, [_____]]
Modem; G[, [_____]]
SD-11 Closeout Submittals
System Function Verification; G[, [_____]]
1.4 QUALITY ASSURANCE
1.4.1 Installation Drawings
Drawings shall indicate but not be limited to the following:
a. Elementary diagrams and wiring diagrams with terminals identified of[
kilowatt][ advanced] meter,[ current transformers,][ potential
transformers,][ protocol modules,][ communications modules,][ Ethernet
connections,][ telephone lines]. [For each meter installation, provide a
diagram identified by the building number.]
b. One-line diagram, including meters,[ switch(es),][ current
transformers,][ potential transformers,][ protocol modules,][ communications
modules,][ Ethernet connections,][ telephone outlets,][ and fuses]. [For
each meter installation, provide a diagram identified by the building
number.]
1.4.2 Standard Products
Provide materials and equipment that are products of manufacturers regularly
engaged in the production of such products which are of equal material,
design and workmanship. Products shall have been in satisfactory commercial
or industrial use for 2 years prior to bid opening. The 2-year period shall
include applications of equipment and materials under similar circumstances
and of similar size. The product shall have been on sale on the commercial
market through advertisements, manufacturers' catalogs, or brochures during
the 2-year period. Where two or more items of the same class of equipment
are required, these items shall be products of a single manufacturer;
however, the component parts of the item need not be the products of the
same manufacturer unless stated in this section.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 27 13.10 30 Page 6
1.4.3 Alternative Qualifications
Products having less than a 2-year field service record will be acceptable
if a certified record of satisfactory field operation for not less than 6000
hours, exclusive of the manufacturers' factory or laboratory tests, is
furnished.
1.4.4 Material and Equipment Manufacturing Data
Products manufactured more than 2 years prior to date of delivery to site
shall not be used, unless specified otherwise.
1.5 WARRANTY
The equipment items shall be supported by service organizations which are
reasonably convenient to the equipment installation in order to render
satisfactory service to the equipment on a regular and emergency basis
during the warranty period of the contract.
1.6 SYSTEM DESCRIPTION
1.6.1 System Requirements
The metering and reading system, consisting of commercial, off-the-shelf
meters, protocol modules, communications modules, and communication
channels, will be used to record the electricity consumption and other
values as described in the sections that follow and as shown on the
drawings.
1.6.2 Selection Criteria
Metering components are part of a system that includes the physical meter,
data recorder function and communications (modem) method. Every building
site identified shall include sufficient metering components to measure the
electrical parameters identified and to store and communicate the values as
required in the following sections. Contractor shall verify that the
metering system installed on any building site is compatible with the
facility-wide communication and meter-reading protocol system.[ Contractor
must connect the metering system to the facility-wide energy and utility
monitoring and control system.]
PART 2 PRODUCTS
2.1 POWER METERS
***************************************************************************
NOTE: This specification is designed for projects
where multiple metering systems will be installed on
the same project. It is expected that different
buildings may have different metering systems
depending on the metering system that can be
installed economically for any specific building and
that meets the needs of the facility analysis and
billing system.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 27 13.10 30 Page 7
Metering features that are unique to a building
should be listed in a schedule either in this
specification or on accompanying drawings.
***************************************************************************
2.1.1 Physical and Common Requirements
***************************************************************************
NOTE: Meters will generally be installed outside the
building in a readily accessible location. In that
case, use the socket-mount design. In the situations
where panel-mounting is required, add the panel-
mounting section.
***************************************************************************
a. Metering system components shall be installed according to the Metering
System Schedule shown[ in this specification][ on the drawings].
[b. Power meter shall be socket-mount design.]
[c. Power meter shall be panel-mounted design. Meters shall be semi-flush,
back-connected, dustproof, draw-out switchboard type. Cases shall have
window removable covers capable of being sealed against tampering.
Meters shall be of a type that can be withdrawn through approved
sliding contacts from fronts of panels or doors without opening
current-transformer secondary circuits, disturbing external circuits,
or requiring disconnection of any meter leads. Necessary test devices
shall be incorporated within each meter and shall provide means for
testing either from an external source of electric power or from
associated instrument transformers or bus voltage.]
d. If existing meter base is usable, the meter base determines meter form
factor. If a new meter is being installed, use meter and base form
factor of 9S.
***************************************************************************
NOTE: If the measured load is less than 220 amps,
use Class 200 meters for direct current reading
without current transformers.
***************************************************************************
[e. Use Class 200 meters for direct current reading without current
transformers.]
f. Meter shall be a Class 20, transformer rated design.
g. Meter shall be rated for use at temperature from -40 [_____] degrees
Centigrade to +70 [_____] degrees Centigrade.
h. Meter shall have NEMA 3R enclosure for surface mounting.
***************************************************************************
NOTE: Select if the recorded data will be in a
module inside the meter or external in a data logger.
The preferred method is to install the recording
module inside the meter case. Some retrofit
applications may require an external data logger.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 27 13.10 30 Page 8
***************************************************************************
i. Surge withstand shall conform to IEEE C37.90.1.
j. Meter shall have a standard[ 4] [_____]-year warranty.
k. Meter shall comply with IEC 62053-22 (Part 21: Static Meter for Active
Energy, classes 0.2S and 0.5S), certified by a qualified third party
test laboratory.
2.1.2 Voltage Requirements
a. Meter shall be capable of connection to the service voltage phases and
magnitude being monitored. If the meter is not rated for the service
voltage, provide suitable potential transformers to send an acceptable
voltage to the meter.
b. Meter shall be capable of connection to the service voltage indicated in
the Metering System Schedule:
c. Meter shall accept independent voltage inputs from each phase. Meter
shall be auto-ranging over the full range of input voltages.
d. Voltage input shall be optically isolated to 2500 volts DC from signal
and communications outputs. Components shall meet or exceed IEEE
C37.90.1 (Surge Withstand Capability).
e. The Contractor shall be responsible for determining the actual voltage
ratio of each potential transformer. Transformer shall conform to IEEE
C57.13 and the following requirements.
1. Type: Dry type, of two-winding construction.
2. Weather: Outdoor or Indoor rated for the application.
3. Frequency: Nominal 60Hz, 50Hz for those bases that operate on
50Hz.
4. Accuracy: Plus or minus 0.3% at 60Hz or 0.3% for those systems
that operate at 50Hz.
2.1.3 Current Requirements
a. Meter shall accept independent current inputs from each phase. Current
transformer shall be installed with a full load rating as shown in the
schedule.
b. Single ratio current transformer shall have an Accuracy Class of [ 0.3][
0.6] [ 1.2] with a maximum error of +/- [ 0.3%][ 0.6%][ 1.2%] at 5.0
amps.
c. Current transformer shall have:
1. Insulation Class: All 600 volt and below current transformers
shall be rated 10 KV BIL. Current transformers for 2400 and 4160
volt service shall be rated 25 KV BIL.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 27 13.10 30 Page 9
2. Frequency: Nominal 60Hz, 50Hz for bases that operate on 50Hz.
3. Burden: Burden class shall be selected for the load.
4. Phase Angle Range: 0 to 60 degrees.
d. Meter shall accept current input from standard instrument transformers
(5A secondary current transformers.)
e. Current inputs shall have a continuous rating in accordance with IEEE
C57.13.
***************************************************************************
NOTE: Since loads in building can vary over time,
multi-ratio current transformers allow the
flexibility to change the ratio of the current
transformer to match the load. The accuracy of
current transformer performance decreases when the
actual current is in the lower band of its measuring
range.
***************************************************************************
f. Multi-ratio current transformer where indicated shall have a top range
equal to or greater than the actual load. The Contractor shall be
responsible for determining the actual ratio of each transformer.
Current transformer shall conform to IEEE C57.13.
2.1.4 Electrical Measurements
Power meter shall measure and report the following quantities:
***************************************************************************
NOTE: Select each of the following measuring
capabilities that are required and include the
abbreviation in the Metering System Schedule for each
building. Since power meters have a service life
greater that 10 years, include optional features that
are expected to be used and analyzed over the life of
the meter.
***************************************************************************
a. Kilowatt-hours ("kWh" in Metering Systems Schedule) of consumption.
Cumulative.
b. Kilowatts of demand ("kW" in Metering Systems Schedule). Peak average
over a selectable demand interval between 5 and 60 minutes (typically
15 minutes).
c. Reactive power ("kVAR" in Metering Systems Schedule). Measured over the
same interval as the peak kW reading.
d. Power factor ("PF" in Metering Systems Schedule). Measured over the same
interval as the peak kW reading.
***************************************************************************
NOTE: At locations where time of use (TOU) billing
is required by the electric company, this
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 27 13.10 30 Page 10
specification provides that all TOD meters cover the
same periods as defined in the next section.
***************************************************************************
e. Time of use consumption ("TOU" in Metering Systems Schedule). Kilowatt-
hours recorded separately for each period set by programming into the
meter. Time periods shall be capable of being changed without removal
from service. The meter shall internally record and store Time of Use
data.
1. [Four (4)] minimum [_____] TOU Rates (Registers)
2. [Twenty (20)][_____] Year Calendar
3. [Two (2)] minimum [_____] seasons per year
***************************************************************************
NOTE: Interval recording is an important tool for
analyzing energy consumption within a building. For
billing purposes, real-time reporting is not
required. For non EPACT05 meters, the meter can be
read nominally once per month with all recorded
interval data captured at that time. Where real-time
data is needed by an energy management control system
(EMCS) or other system, the systems may have their
own connection to the meter or its own current and
potential transformers.
***************************************************************************
f. Interval recording ("IR" in Metering Systems Schedule). Kilowatt-hours
shall be recorded for each[ 15][_____] minute interval and shall
accumulate for[ 30][_____] days. Memory for recording the interval
readings shall be internal to the meter and ANSI C12.19 compliant.
Meter shall provide time-stamped readings for every measured parameter.
g. Meter readings shall be true RMS.
2.1.5 Meter Accuracy
***************************************************************************
NOTE: Meters used for billing purposes should
generally be held to the same metering accuracies as
established standards by utility companies.
***************************************************************************
Power meter shall provide the following accuracies. Accuracies shall be
measured as percent of reading at standard meter test points.
a. Power meter shall meet ANSI C12.20 for Class 0.2 and IEC 62053-22
accuracy requirements.
2.1.6 An on the Meter Display, Output and Reading Capabilities
Meter shall include the following output signals.
a. The meter will have a face display plate and shall display every
electrical parameter indicated to be recorded. Meters shall not be
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 27 13.10 30 Page 11
required to indicate interval data collected in a data logger with a
communications output feature. Peak values, instantaneous and
cumulative values shall be displayed.
[b. Meter shall include optical output port capable of 9600 bps
communication with a hand-held reading device. Optical device shall be
compatible with ANSI C12.18]
***************************************************************************
NOTE: The following optional features will usually
be deleted. These features could be used for
connection to an Energy Management and Control
System.
***************************************************************************
[c. Meter shall include output options for analog milliamp signals.]
[d. Meter shall have two channels of analog output, 0-1mA or 4-20mA, for
positive[ and negative] watt/hour readings.]
[e. Meter shall include output option for pulse output. KYZ pulse output
related to kWatts/HR.]
[f. Meter shall have two form C, dry contact relay outputs for alarm or
control.]
2.1.7 Installation Methods
***************************************************************************
NOTE: Pad-mounted transformers have proven to be
very reliable over a long life span. Installing the
meters on the outside of the secondary wiring
compartment has become somewhat a standard
installation for military facilities, resulting in
minimal maintenance. However, meters may be installed
on the sides of buildings or within buildings.
***************************************************************************
a. Transformer mounted (XFMR)
1. Meter base shall be located outside on the secondary side of the
pad-mounted transformer.
***************************************************************************
NOTE: Do not use the stand-mounted method unless the
transformer pad is being poured and the
instrumentation conduit can be installed before the
pour. Provide a drawing to show details for mounting
and routing conduit and wires.
***************************************************************************
b. Stand-mounted adjacent to transformer ("STAND" in Metering Systems
Schedule)
1. Meter base shall be mounted on a structural steel pole
approximately 4 feet from the transformer pad. See detail on the
drawings.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 27 13.10 30 Page 12
***************************************************************************
NOTE: Provide a drawing to show details for building
mounting and routing conduit and wires.
***************************************************************************
c. Building mounted ("BLDG" in Metering Systems Schedule)
1. Meter base shall be mounted on the side of the existing building
near the service entrance. See detail on the drawings.
d. Panel mounted. ("PNL" in Metering Systems Schedule)
1. Meter shall be mounted where directed. See detail on the
drawings.
e. Common features.
1. PTs (if required for proper voltage range) and CTs shall be
physically connected to the service entrance cables inside the
service entrance disconnect enclosure.
2.1.8 Disconnecting Switches
***************************************************************************
NOTE: Shorting-type wiring blocks are recommended to
allow connections to be corrected and changed without
the necessity of disconnecting power to the
transformer, resulting in another power outage to the
building being served.
***************************************************************************
a. Disconnecting wiring blocks shall be provided between the current
transformer and the meter. A shorting mechanism shall be built into the
wiring block to allow the current transformer wiring to be changed
without removing power to the transformer. The wiring blocks shall be
located where they are accessible without the necessity of
disconnecting power to the transformer. For multi-ratio current
transformers, provide a shorting block from each tap to the common
lead.
b. Voltage-monitoring circuits shall be equipped with disconnect switches
to isolate the meter base or socket from the voltage source.
***************************************************************************
NOTE: If programming capability is not required,
omit the following section.
***************************************************************************
2.1.9 Meter Programming
a. Power meter shall be programmable by software supplied by the meter
manufacturer.
b. Software shall have a user-friendly, Windows-compatible interface.
c. Software shall operate on [Windows][_____] operating systems.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 27 13.10 30 Page 13
d. Software shall allow the user to configure the meter, troubleshoot
meter, query and display meter parameters and configuration data and
stored values.
e. Meter firmware shall be upgradeable through one of the communications
ports without removing the unit from service.
2.2 COMMUNICATIONS
***************************************************************************
NOTE: Communications features may not be needed.
Data logging of one month of data may be recorded
inside the meter. Recorded data may be read simply by
a handheld instrument, if read daily.
***************************************************************************
2.2.1 Communications Methods
2.2.1.1 Optical Port
The optical port shall communicate with a hand-held reading device according
to the following requirements.
a. Communications standards
1. ANSI C12.18
2. MV90 protocol
3. ANSI C12.20
b. Read operations
1. Current kWh values
2. Demand (kW) values since last reset
3. Last reset value
4. Meter status
[5. Load profile]
c. Write operations
1. Meter setup
2.2.1.2 Serial Port
Provide serial port for connection to modem module where required in this
specification.
[a. On-Board serial port types]
[1. RS232]
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 27 13.10 30 Page 14
[2. \[RS485]]
2.2.1.3 Ethernet
For those meters using the Ethernet, logged information shall be sent using
open standard Internet Protocols.
a. On-board Ethernet port support
1. HTTP
2. SMTP
(a) Modbus
b. Distribute stored data by
1. FTP
[2. E-Mail]
[(a) On-board web server]
2.2.2 Communications Protocols and Methods
Communications protocols and methods shall be native to the meter. Provide
communications module(s) as required to accomplish the following.
a. Meter shall include an IR port ("IR" in Metering Systems Schedule) for
communication to external devices such as handheld readers that support
a minimum speed of 9600 baud.
b. [Meter shall include[ one][ RS-232 ("RS232" in Metering Systems
Schedule)] or[ one][ RS-485 ("RS485" in Metering Systems Schedule)]
digital communication port. Each port shall be user configurable with
regard to speed, protocol, address, and other communications
parameters. Ports shall support a minimum communication speed of 9600
baud for the RS232 port.]
[c. Meter shall have a port that can be configured as a[ 10/100 Base-T
Ethernet port ("BaseT" in Metering Systems Schedule)]]
[1. A communication module that converts serial RS232 or RS485 to
Ethernet will be acceptable.]
[d. Auto Answer minimum 1200 baud internal modem ("A56K" in Metering
Systems Schedule). Internal modem shall include automatic data
buffering to provide faster, more reliable communications and the
ability to automatically answer on a connected line.]
[e. Meter shall be equipped with one pulse output channel ("Pulse" in
Metering Systems Schedule) that can be configured for operation as KYZ
pulse output.]
2.2.3 Communications Channels Surge Protection
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 27 13.10 30 Page 15
Communications equipment shall be protected against surges induced on its
communications channels. Communication interfaces to all field equipment
shall be protected to meet the requirements of IEEE C37.90.1 or the
requirements of IEC 61000-4-5, test level 4, while the equipment is
operating. Fuses shall not be used for surge protection. Metallic cables
and conductors which serve as communications channels between buildings
shall have surge protection installed at equipment rated for the application
installed at each end, within( 3 feet) (0.9 meters) of the building cable
entrance. Surge protectors shall meet the requirements of the applicable
extension of ANSI C62 (for example, ANSI C62.61).
***************************************************************************
NOTE: Communication methods, modules and software
can be used for automatic meter reading (AMR). AMR
may not be needed. If automatic meter reading (AMR)
is to be implemented, considerable coordination of
the communications sending, receiving and protocols
will be required.
***************************************************************************
2.3 METER DATA PROTOCOL
Power meters shall have communicating data protocols native or provided in
supplemental modules to communicate with the communications methods that
follow.
2.3.1 Open Protocol
***************************************************************************
NOTE: This section should be modified to be facility
specific.
***************************************************************************
Power meter shall support the following open protocols. Contractor shall
verify that the meter native protocol is consistent with the facility data
recording and communication and data storage system. Contractor shall
provide additional converters and modules as required for a complete
measurement, recording, communicating and data storage system.
a. Meter shall be fully supported by MV-90 software system or existing AMR
software that is MV-90 compatible.
b. For systems that use proprietary software, an alternative, competitive
software system must be available.
Systems capable of using more than one brand of commercially available
meters are expected. In addition, if proprietary meter reading software is
used, meters are to be capable of being read by more than one manufacturer's
software.
2.4 SPARE PARTS
2.4.1 Parts List
Provide spare parts as follows:
a. Power meter - two for each type used.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 27 13.10 30 Page 16
b. Current transformer - three for each type used.
c. Potential transformer - three for each type used.
d. Communications module - one for each type used.
e. Protocol module - one for each type used.
f. Other electronic and power components - one for each type used.
2.5 METERING SYSTEM SCHEDULE
***************************************************************************
NOTE: Each building should be listed on a separate
row. Identify the characteristics for the specific
meter and communications method for each building.
The following completed data is an example only.
Delete existing values.
***************************************************************************
Metering System Schedule is available at
http://www.wbdg.org/FFC/NAVGRAPH/graphtoc.pdf
***************************************************************************
NOTE: Provide a drawing to show locations and
details for mounting and routing conduit and wires.
Identify CT ratio and multi-tap ratios if known.
***************************************************************************
PART 3 EXECUTION
3.1 INSTALLATION
Electrical installations shall conform to IEEE C2, NFPA 70, and to the
requirements specified herein. Provide new equipment and materials unless
indicated or specified otherwise.
[3.1.1 Existing Condition Survey
***************************************************************************
NOTE: Remove the following section if existing
condition surveys are not required.
***************************************************************************
The Contractor shall perform a field survey, including inspection of all
existing equipment, resulting clearances, and new equipment locations
intended to be incorporated into the system, and furnish an existing
conditions report to the Government. The report shall identify those items
that are non-workable as defined in the contract documents. The Contractor
shall be held responsible for repairs of modifications necessary to make the
system perform as required.
]3.1.2 Scheduling of Work and Outages
***************************************************************************
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 27 13.10 30 Page 17
NOTE: Installation of current transformers and
potential transformers will require that power be
disconnected from the transformer and/or building.
Provide coordination steps for the work and require
Contractor to perform the work after normal hours.
***************************************************************************
The Contract Clauses shall govern regarding permission for power outages,
scheduling of work, coordination with Government personnel, and special
working conditions.
[3.2 FIELD APPLIED PAINTING
Where field painting of enclosures is required to correct damage to the
manufacturer's factory-applied coatings, provide manufacturer's recommended
coatings and apply in accordance with manufacturer's instructions.
]3.3 FIELD QUALITY CONTROL
3.3.1 Performance of Acceptance Checks and Tests
3.3.1.1 Meter Assembly
a. Visual and mechanical inspection
1. Compare equipment nameplate data with specification and approved
shop drawings.
2. Inspect physical and mechanical condition.
3. Inspect all bolted electrical connections for high resistance
using low-resistance ohmmeter, verifying tightness of accessible
bolted electrical connections by calibrated torque-wrench method.
4. Verify grounding of metering enclosure.
5. Verify the presence of surge arresters.
6. Verify that the CT ratio and the PT ratio are properly included
in the meter multiplier or the programming of the meter.
b. Electrical tests
[1. Calibrate watthour meters according to manufacturer's published
data.]
2. Verify that correct multiplier has been placed on face or meter
where applicable.
3. Prior to system acceptance, the Contractor will demonstrate and
confirm the meter is properly wired and is displaying correct and
accurate electrical information.
3.3.1.2 Current Transformers
a. Visual and mechanical inspection
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 27 13.10 30 Page 18
1. Compare equipment nameplate data with specification and approved
shop drawings.
2. Inspect physical and mechanical condition.
3. Verify correct connection.
4. Inspect all bolted electrical connections for high resistance
using low-resistance ohmmeter, verifying tightness of accessible
bolted electrical connections by calibrated torque-wrench method.
5. Verify that required grounding and shorting connections provide
good contact.
b. Electrical tests
1. Perform resistance measurements through all bolted connections
with low-resistance ohmmeter, if applicable.
2. Perform insulation-resistance test.
3. Perform a polarity test.
4. Perform a ratio-verification test.
3.3.1.3 Potential Transformers
a. Visual and mechanical inspection
1. PT's are rigidly mounted.
2. PT's are correct voltage.
3. Verify that adequate clearances exist between primary and
secondary circuit.
b. Electrical tests
1. Perform a ratio-verification test.
3.3.2 Follow-Up System Function Verification
Upon completion of acceptance checks and tests, the Contractor shall show by
demonstration in service that circuits and devices are in good operating
condition and properly performing the intended function. As an exception to
requirements stated elsewhere in the contract, the Contracting Officer shall
be given 5 working days' advance notice of the dates and times of checking
and testing.
3.3.3 Training
The Contractor shall conduct a training course for meter configuration,
operation, and maintenance of the system as specified. The training shall be
oriented for all components and systems installed under this contract.
Training manuals shall be delivered for [_____] trainees with two additional
copies delivered for archiving at the project site. The Contractor shall
furnish all audiovisual equipment and all other training materials and
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 27 13.10 30 Page 19
supplies. A training day is defined as eight hours of classroom instruction,
including two 15-minute breaks and excluding lunchtime, Monday through
Friday, during the daytime shift in effect at the training facility. For
guidance in planning the required instruction, the Contractor shall assume
that attendees have a high school education or equivalent, and are familiar
with utility systems. Approval of the planned training schedule shall be
obtained from the Government at least 30 days prior to the training.
a. Training: The course shall be taught at the project site within thirty
days after completion of the installation for a period of one [_____]
day(s). A maximum of [6][_____] personnel will attend the course. The
training shall include:
1. Physical layout of each piece of hardware.
2. Meter configuration, troubleshooting and diagnostics procedures.
3. Repair instructions.
4. Preventive maintenance procedures and schedules.
5. Testing and calibration procedures.
-- End of Section --
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 27 14.00 20 Page 1
***************************************************************************
USACE / NAVFAC / AFCEC / NASA UFGS-26 27 14.00 20 (February 2011)
-----------------------------------
Preparing Activity: NAVFAC New
UNIFIED FACILITIES GUIDE SPECIFICATIONS
References are in agreement with UMRL dated October 2017.
***************************************************************************
SECTION 26 27 14.00 20
ELECTRICITY METERING
02/11
***************************************************************************
NOTE: Many Activities have, or are in the process
of, converting to basewide metering systems.
This Navy guide specification covers the requirements
for the installation of electricity meters suitable
for billing, allocation of costs, and recording of
data for energy management and control applications
for Navy projects. This specification is intended to
comply with the metering requirements of EPACT05.
Although a unified metering specification is under
development, some Air Force projects may require use
of Section 26 27 13.10 30 ELECTRIC METERS.
Coordinate with the Activity and provide specific
requirements "to match existing systems" when
necessary. If specifying proprietary products,
insure that appropriate "Justification and
Authorization (J & A)" documentation has been
obtained by project manager and "proprietary language
requirements" have been added to Division 1 as well
as adding the following lines above the section
number and title at the top of the first page of this
section of the specifications:
"***********************************************
This specification section contains proprietary
products.
***********************************************"
If there are any components (such as meters, housing,
or current transformers) that will be Government
Furnished Contractor Installed (GFCI), or Government
Furnished Government Installed (GFGI), edit Division
1 and this specification section appropriately.
The following related guide specifications for power
distribution equipment may contain outdated meter
information. Avoid duplication and ensure conflicting
information has been removed from project documents.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 27 14.00 20 Page 2
These specifications are slated for update in
FY11/FY12.
- Section 26 12 19.10 THREE-PHASE PAD-MOUNTED
TRANSFORMERS
- Section 26 12 21 SINGLE-PHASE PAD-MOUNTED
TRANSFORMERS
- Section 26 11 13.00 20 PRIMARY UNIT SUBSTATIONS
- Section 26 11 16 SECONDARY UNIT SUBSTATIONS
- Section 26 23 00 LOW VOLTAGE SWITCHGEAR
--Section 26 24 13 SWITCHBOARDS
Comments, suggestions and recommended changes for
this guide specification are welcome and should be
submitted as a Criteria Change Request (CCR).
Use of electronic communication is encouraged.
Adhere to UFC 1-300-02 Unified Facilities Guide
Specifications (UFGS) Format Standard when editing
this guide specification or preparing new project
specification sections. Edit this guide
specification for project specific requirements by
adding, deleting, or revising text. For bracketed
items, choose applicable item(s) or insert
appropriate information. Brackets are used in the
text to indicate designer choices or locations where
text must be supplied by the designer.
NOTE: TO DOWNLOAD UFGS GRAPHICS
Go to http://www.wbdg.org/FFC/NAVGRAPH/graphtoc.pdf
NOTE: This section utilizes the following sketches,
details, and forms (Graphics), and are available in
metric (SI) and U.S. Customary (IP) system
dimensions. Sketch titles and style numbers are
unchanged for both types. The metric values
indicated are a conversion of the IP system
dimensions.
Do not include this list of sketches, or the
sketches themselves, in project specifications. Use
sketches as details on drawings whenever possible.
SKETCH NUMBER TITLE
E-M101 Form 9S - Typical Wye Configuration With Single-Ratio CT's
and Without PT's
E-M102 Form 9S - Typical Wye Configuration With Dual-Ratio CT's and
Without PT's
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 27 14.00 20 Page 3
SKETCH NUMBER TITLE
E-M103 Form 9S - Typical Wye Configuration With Multi-Ratio CT's and
Without PT's
E-M104 Form 9S - Typical Wye Configuration With 10 Pole Test Switch
E-M105 Form 9S - Typical Delta Configuration Without PT's
E-M106 Form 2S - Typical
E-M107 Form 5S - Typical
E-M108 Form 6S - Typical
E-M110 Form 9S - Typical Wye Configuration With Single-Ratio CT's
and With PT's
E-M111 Form 9S - Typical Wye Configuration With Dual-Ratio CT's and
With PT's
E-M112 Form 9S - Typical Wye Configuration With Multi-Ratio CT's and
With PT's
E-M113 Form 9S - Typical Delta Configuration With PT's
E-M201 Inside Meter Installation - Typical
E-M202 Outside Meter Installation on Wall - Preferred Distance to
Gas Meter
E-M203 Outside Meter Installation on Wall - Acceptable Distance to
Gas Meter
E-M204 Single Phase Self Contained Meters Residential Service: 0-600
Volts, Enclosed Installation
E-M205 Single Phase Self Contained Meters Residential Service: 0-600
Volts, Semi-Flush Installation
E-M206 Meter Cabinet Enclosure Clearances: 0-600 Volts
DETAILS TITLE
PADMDE1 Pad-Mounted Transformer Detail
PADMDE2 Pad-Mounted Transformer Detail
PADMDE3 Pad-Mounted Transformer Detail
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 27 14.00 20 Page 4
DETAILS TITLE
PADMDE4 Pad-Mounted Transformer Detail
PADMDE5 Pad-Mounted Transformer Detail
PADMDE6 Pad-Mounted Transformer Detail
FORMS TITLE
E-S1 Building Meter Installation Sheet Per Building
E-S2 Electricity Meter Installation Schedule - Large Project
E-S3 Electricity Meter Data Schedule - Large Project
E-S4 Sample Contract Data Requirements List (CDRL)- Blank
E-S5 Sample Contract Data Requirements List (CDRL)- Example
The Contract Data Requirements List (CDRL) can also be downloaded at
http://www.dtic.mil/dtic/pdf/customer/STINFOdata/DD14231.pdf.
***************************************************************************
PART 1 GENERAL
1.1 REFERENCES
***************************************************************************
NOTE: This paragraph is used to list the
publications cited in the text of the guide
specification. The publications are referred to in
the text by basic designation only and listed in this
paragraph by organization, designation, date, and
title.
Use the Reference Wizard's Check Reference feature
when you add a Reference Identifier (RID) outside of
the Section's Reference Article to automatically
place the reference in the Reference Article. Also
use the Reference Wizard's Check Reference feature to
update the issue dates.
References not used in the text will automatically be
deleted from this section of the project
specification when you choose to reconcile references
in the publish print process.
***************************************************************************
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 27 14.00 20 Page 5
The publications listed below form a part of this specification to the
extent referenced. The publications are referred to within the text by the
basic designation only.
AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)
ANSI C12.1 (2008) Electric Meters Code for Electricity
Metering
INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)
IEEE C2 (2017; Errata 1-2 2017; INT 1 2017) National
Electrical Safety Code
IEEE C37.90.1 (2013) Standard for Surge Withstand
Capability (SWC) Tests for Relays and Relay
Systems Associated with Electric Power
Apparatus
IEEE C57.13 (2016) Requirements for Instrument
Transformers
IEEE Stds Dictionary (2009) IEEE Standards Dictionary: Glossary of
Terms & Definitions
INTERNATIONAL ELECTRICAL TESTING ASSOCIATION (NETA)
NETA ATS (2017) Standard for Acceptance Testing
Specifications for Electrical Power Equipment
and Systems
INTERNATIONAL ELECTROTECHNICAL COMMISSION (IEC)
IEC 60687 (1992) Alternating Current Static Watt-Hour
Meters for Active Energy (Classes 0,2 S and
0,5 S)
IEC 62053-22 (2003; ED 1.0) Electricity Metering Equipment
(a.c.) - Particular Requirements - Part 22:
Static Meters for Active Energy (Classes 0,2
S and 0,5 S)
NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)
ANSI C12.18 (2006; R 2016) Protocol Specification for
ANSI Type 2 Optical Port
ANSI C12.20 (2015) Electricity Meters - 0.1, 0.2, and 0.5
Accuracy Classes
ANSI C12.7 (2014) Requirements for Watthour Meter
Sockets
NEMA C12.19 (2012) Utility Industry End Device Data
Tables
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 27 14.00 20 Page 6
NFPA 70 (2017; ERTA 1-2 2017; TIA 17-1; TIA 17-2; TIA
17-3) National Electrical Code
1.2 DEFINITIONS
Unless otherwise specified or indicated, electrical and electronics terms
used in these specifications, and on the drawings, shall be as defined in
IEEE Stds Dictionary.
1.3 SUBMITTALS
***************************************************************************
NOTE: Review Submittal Description (SD) definitions
in Section 01 33 00 SUBMITTAL PROCEDURES and edit the
following list to reflect only the submittals
required for the project.
The Guide Specification technical editors have
designated those items that require Government
approval, due to their complexity or criticality,
with a "G". Generally, other submittal items can be
reviewed by the Contractor's Quality Control System.
Only add a “G” to an item, if the submittal is
sufficiently important or complex in context of the
project.
For submittals requiring Government approval on Army
projects, a code of up to three characters within the
submittal tags may be used following the "G"
designation to indicate the approving authority.
Codes for Army projects using the Resident Management
System (RMS) are: "AE" for Architect-Engineer; "DO"
for District Office (Engineering Division or other
organization in the District Office); "AO" for Area
Office; "RO" for Resident Office; and "PO" for
Project Office. Codes following the "G" typically
are not used for Navy, Air Force, and NASA projects.
Use the "S" classification only in SD-11 Closeout
Submittals. The "S" following a submittal item
indicates that the submittal is required for the
Sustainability eNotebook to fulfill federally
mandated sustainable requirements in accordance with
Section 01 33 29 SUSTAINABILITY REPORTING.
Choose the first bracketed item for Navy, Air Force
and NASA projects, or choose the second bracketed
item for Army projects.
***************************************************************************
***************************************************************************
NOTE: In this specification, special submittals are
required for Contract Data Requirements List (CDRL).
The CDRL submittals are indicated as bracketed
options.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 27 14.00 20 Page 7
When used, include a completed DD Form 1423, Contract
Data Requirements List with the project
specifications. This form is essential to obtain
delivery of all documentation. Each deliverable must
be clearly specified, with both description and
quantity required. A sample CDRL and an editable
blank CDRL are included in the graphics list at the
front of this specification, as Graphics ES-4 and ES-
5.
The acquisition of all technical data, data bases and
computer software items that are identified herein
will be accomplished strictly in accordance with the
Federal Acquisition Regulation (FAR) and the
Department of Defense Acquisition Regulation
Supplement (DOD FARS).
Those regulations as well as the Services
implementation thereof should also be consulted to
ensure that a delivery of critical items of technical
data is not inadvertently lost. Specifically, the
Rights in Technical Data and Computer Software
Clause, DOD FARS 52.227-7013, and the Data
Requirements Clause, DOD FAR 52.227-7031, as well as
any requisite software licensing agreements will be
made a part of the CONTRACT CLAUSES or SPECIAL
CONTRACT REQUIREMENTS. In addition, the appropriate
DD Form 1423 Contract Data Requirements List (CDRL),
will be filled out for each distinct deliverable data
item and made a part of the contract. Where
necessary, a DD Form 1664, Data Item Description,
will be used to explain and more fully identify the
data items listed on the DD Form 1423. It is to be
noted that all of these clauses and forms are
required to ensure the delivery of the data in
question and that such data is obtained with the
requisite rights to use by the Government.
***************************************************************************
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for [Contractor Quality Control
approval.] [information only. When used, a designation following the "G"
designation identifies the office that will review the submittal for the
Government.]
[Technical data packages consisting of technical data and computer software
(meaning technical data which relates to computer software) which are
specifically identified in this project and which may be defined/required in
other specifications shall be delivered strictly in accordance with the
CONTRACT CLAUSES and in accordance with the Contract Data Requirements List,
DD Form 1423. Data delivered shall be identified by reference to the
particular specification paragraph against which it is furnished. All
submittals not specified as technical data packages are considered 'shop
drawings' under the Federal Acquisition Regulation Supplement (FARS) and
shall contain no proprietary information and be delivered with unrestricted
rights.]
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 27 14.00 20 Page 8
Submittals with an "S" are for inclusion in the Sustainability eNotebook, in
conformance to Section 01 33 29 SUSTAINABILITY REPORTING. Submit the
following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES[, the
CONTRACT CLAUSES and DD Form 1423]:
SD-02 Shop Drawings
Installation Drawings; G[, [_____]]
SD-03 Product Data
Electricity meters; G[, [_____]]
***************************************************************************
NOTE: Determine if a Technical Data Package will be
required for electrical meters as described in the
above note. If a Technical Data Package is required,
include the bracketed option below.
***************************************************************************
[The most recent meter product data shall be submitted as a
Technical Data Package and shall be licensed to the project site.
Any software shall be submitted on CD-ROM and [_____] hard copies
of the software user manual shall be submitted for each piece of
software provided.]
Current transformer; G[, [_____]]
Potential transformer; G[, [_____]]
External communications devices; G[, [_____]]
[Configuration Software; G[, [_____]]
The most recent version of the configuration software for each type
(manufacturer and model) shall be submitted as a Technical Data
Package and shall be licensed to the project site. Software shall
be submitted on CD-ROM and [_____] hard copies of the software user
manual shall be submitted for each piece of software provided.
]SD-06 Test Reports
Acceptance checks and tests; G[, [_____]]
System functional verification; G[, [_____]]
Building meter installation sheet, per building; G[, [_____]]
Completed meter installation schedule; G[, [_____]]
Completed meter data schedule; G[, [_____]]
Meter configuration template; G[, [_____]]
Contractor shall fill in the meter configuration template and
submit to the Activity for concurrence.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 27 14.00 20 Page 9
Meter configuration report; G[, [_____]]
The meter configuration report shall be submitted as a Technical
Data Package.
SD-10 Operation and Maintenance Data
Electricity Meters and Accessories, Data Package 5; G[, [_____]]
Submit operation and maintenance data in accordance with Section 01 78 23
OPERATION AND MAINTENANCE DATA and as specified herein.
SD-11 Closeout Submittals
System functional verification; G[, [_____]]
1.4 QUALITY ASSURANCE
***************************************************************************
NOTE: Select from the identified bracketed options
the information that is to be provided on the
drawings. Delete the items not needed for the
project. Determine if communications information
will be addressed in the drawings for the metering
project or as a separate documentation package. The
level of detail required might vary with the project.
Identify the required electronic drawing format in
the selection below.
***************************************************************************
1.4.1 Installation Drawings
Drawings shall be provided in hard-copy and [_____] electronic format, and
shall include but not be limited to the following:
a. Wiring diagrams with terminals identified of [kilowatt] [advanced]
meter, [current transformers, ] [potential transformers, ][protocol
modules, ][communications interfaces, ][Ethernet connections,
][telephone lines]. [For each typical meter installation, provide a
diagram.]
b. One-line diagram, including meters, [switch(es), ][current
transformers, ][potential transformers, ] [protocol modules,
][communications interfaces, ][Ethernet connections, ][telephone
outlets, ][ and fuses]. [For each typical meter installation, provide
a diagram.]
1.4.2 Standard Products
Provide materials and equipment that are products of manufacturers regularly
engaged in the production of such products which are of equal material,
design and workmanship. Products shall have been in satisfactory commercial
or industrial use for 1 year prior to bid opening. The 1-year period shall
include applications of equipment and materials under similar circumstances
and of similar size. The product, or an earlier release of the product,
shall have been on sale on the commercial market through advertisements,
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 27 14.00 20 Page 10
manufacturers catalogs, or brochures during the prior 1-year period. Where
two or more items of the same class of equipment are required, these items
shall be products of a single manufacturer; however, the component parts of
the item need not be the products of the same manufacturer unless stated in
this section.
1.4.3 Material and Equipment Manufacturing Data
Products manufactured more than 1 year prior to date of delivery to site
shall not be used, unless specified otherwise.
1.5 MAINTENANCE
1.5.1 Additions to Operation and Maintenance Data
In addition to requirements of Data Package 5, include the following on the
actual electricity meters and accessories provided:
a. A condensed description of how the system operates
b. Block diagram indicating major assemblies
c. Troubleshooting information
d. Preventive maintenance
e. Prices for spare parts and supply list
1.6 WARRANTY
The equipment items and software shall be supported by service organizations
which are reasonably convenient to the equipment installation in order to
render satisfactory service to the equipment and software on a regular and
emergency basis during the warranty period of the contract.
1.7 SYSTEM DESCRIPTION
1.7.1 System Requirements
Electricity metering, consisting of meters and associated equipment, will be
used to record the electricity consumption and other values as described in
the requirements that follow and as shown on the drawings. Communication
system requirements are contained in a separate specification section as
identified in paragraph entitled "Communications Interfaces".
1.7.2 Selection Criteria
***************************************************************************
NOTE: Select a bracketed option below if it is
intended that the new meter system be compatible with
the existing system components.
***************************************************************************
Metering components and software are part of a system that includes the
physical meter, data recorder function and communications method. Every
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 27 14.00 20 Page 11
building site identified shall include sufficient metering components to
measure the electrical parameters identified and to store and communicate
the values as required.
[Contractor shall verify that the electricity meter installed on any
building site is compatible with the base-wide metering system with respect
to the types of meters selected and the method used to program the meters
for initial use. Software and meter programming tools are necessary to set
up the meters described by this specification. New software tools different
from the meter programming methods currently used by base personnel will
require separate approval for use.]
[Contractor shall verify that the metering system installed on any building
site is compatible with the facility-wide or base-wide communication and
meter reading protocol system.]
PART 2 PRODUCTS
2.1 ELECTRICITY METERS AND ACCESSORIES
***************************************************************************
NOTE: When an activity has a metering system
installed, provide meters to match. Coordinate with
the project manager and include proprietary
specification information.
Metering features that are unique to a building
should be listed in a schedule either in this
specification or on accompanying drawings. See
Graphic ES-2 for a sample "Metering System Schedule".
***************************************************************************
***************************************************************************
ACTIVITY CURRENT AMI
CONTRACTOR
EXISTING
METER
TYPE
COMM
METHOD
COMMENTS
Naval Base
Ventura
County
Square D ION 8600 Note 1 Ion Enterprise Data
Acquisition System (DAS)
Software
NAVFAC SW American
Systems
ION 8600 Note 2 WinPM
NAVFAC SE Square D ION 8600 Note 1 Ion Enterprise DAS
Software
NAVFAC NW Square D ION 8600 Note 3 Ion Enterprise DAS
Software
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 27 14.00 20 Page 12
ACTIVITY CURRENT AMI
CONTRACTOR
EXISTING
METER
TYPE
COMM
METHOD
COMMENTS
Naval
District
Washington
Weston NEXUS
1272
Note 1 Energy ICT, EI Server
Software
NAVFAC HI TBD Abandoning TWACS; system
will include Hickam AFB
with existing Square D
system; Pacific Missile
Test Range is also
Square D with all fiber
NAVFAC LANT TWACS LANT in process to get a
new metering system for
selected meters. TWACS
system to remain for
remaining meters with
appropriate interface.
Note 1: Combination radio mesh with fiber optic links.
Note 2: Radio mesh. WinPM, similar to Ion enterprise with a wrap
interface.
Note 3: Combination radio mesh with fiber optic links. Includes
some existing copper infrastructure.
***************************************************************************
***************************************************************************
NOTE: One example of a specification paragraph is
provided below for the case in which the meter is
programmed using government-owned equipment. If this
type of paragraph is used, develop wording applicable
to the specific project.
***************************************************************************
[Provide meter(s) and connect the meter(s) to the existing AMI DAS. The
contractor shall use the existing government laptop computers to configure
the meter using existing software loaded on the computer. The contractor
will not be allowed to modify any software or add any additional software to
the computer. Alternatively, the government will configure the meter(s),
which must be compatible with the existing system, using existing software.
Contract shall insure that the meter(s) will transmit the specified data to
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 27 14.00 20 Page 13
the DAS. The current meters being used by [_____] are: [ION 8600A meters
with X MB of memory] [_____].]
2.1.1 Physical and Common Requirements
***************************************************************************
NOTE: This specification is designed for projects
where multiple metering systems will be installed as
part of the same project. It is expected that
different buildings may have different metering
systems depending on the metering system that can be
installed economically for any specific building and
that meets the needs of the facility analysis and
billing system.
This specification has been developed for 60-Hz
applications. Designer must review and provide
additional modifications necessary for 50-Hz use.
Sub-metering (versus single-metering at a facility)
is not specifically addressed and the specification
will require modification to address unique sub-
metering requirements.
If the "Two-Way Automatic Communications System
(TWACS)" is used for communications, this system has
additional wire size and fuse requirements. The use
of TWACS might limit the maximum voltage provided at
each meter. Edit this specification to address these
unique needs.
Class 320 meters are not allowed by this
specification.
Define the configuration that is required to be
initially programmed into each meter. If possible,
define a standard programming profile and identify
any exceptions to that profile.
***************************************************************************
a. Provide metering system components in accordance with the Metering
System Schedule shown [in this specification][on the drawings].
Provide Meter configuration template.
***************************************************************************
NOTE: The bracketed option below allows the
selection of whether to use or replace existing meter
bases.
Meter bases should be inspected if they are to be re-
used. The second bracketed option requires an
assessment of their physical condition before use.
For existing panelboard, switchboard, and switchgear
installations, provide the same style meter. A
direct replacement with a similar configuration can
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 27 14.00 20 Page 14
minimize the need for a design change and avoid
clearance issues inside the enclosure.
The designer must have concurrence from the Activity
and should exercise caution if changing an existing
installation to a socket arrangement using a Form 9S
adaptor kit. This can reduce the number of unique
meters styles to maintain for spares, but can also
cost more during the initial installation and can
result in inadequate clearances within the equipment
and the exterior.
***************************************************************************
b. [Replace all existing meter bases. For socket arrangements, use meter
and base form of 9S unless installation-specific limitations require
the use of a different form type. For panelboards, switchboards, and
switchgear, match the existing installation with the new meter base.]
[Existing meter bases can be re-used if they are electrically
functional, in physically good condition, and show no signs of
corrosion on the electrical contacts. If the existing meter base is
usable, the meter base determines meter form factor. If a new meter is
being installed, use meter and base form factor of 9S unless
installation-specific limitations require the use of a different form
type.] [If use of a socket adaptor arrangement has been approved by
the activity, contractor shall verify that all clearances are met and
doors are able to be properly closed.]
***************************************************************************
NOTE: Select the bracketed option below if the meter
will be installed in an enclosure. A stainless steel
enclosure might be necessary for coastal or high
humidity areas.
***************************************************************************
c. [Meter shall have NEMA [3R] [3R stainless steel] enclosure for surface
mounting with bottom or rear penetrations.]
d. Surge withstand capability shall conform to IEEE C37.90.1.
***************************************************************************
NOTE: Modify the color scheme below if the activity
uses a different identification system. This color
scheme is for metering wiring only and does not match
the color coding requirements for power conductors.
Wire labeling is also an acceptable approach to
identification. If wire labeling is selected, modify
the color scheme listed below to identify the label
information for each wire.
***************************************************************************
e. Use #12 SIS (XHHW, or equivalent) wiring with ring lugs for all meter
connections. Color code and mark the conductors [as follows:
(1) Red - Phase A CT - C1
(2) Orange - Phase B CT - C2
(3) Brown - Phase C CT - C3
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 27 14.00 20 Page 15
(4) Gray with white stripe - neutral current return - C0
(5) Black - Phase A voltage - V1
(6) Yellow - Phase B voltage - V2
(7) Blue - Phase C voltage - V3
(8) White - Neutral voltage]
***************************************************************************
NOTE: The electricity meters covered by this section
are intended for low voltage applications and should
be capable of receiving input nominal voltages of 120
to 480 volts. This section assumes that the
available low voltage will be used as the meter
supply. Potential transformers are not required.
If new medium voltage applications are planned, then
include potential transformer requirements as part of
the associated switchgear specification. If this
section is applied to an existing installation, then
use the bracketed options below to establish the
potential transformer requirements.
***************************************************************************
2.1.2 Potential Transformer Requirements
a. Meter shall be capable of connection to the service voltage phases and
magnitude being monitored. If the meter is not rated for the service
voltage, provide suitable potential transformers to send an acceptable
voltage to the meter.
b. Voltage input shall be optically isolated to 2500 volts DC from signal
and communications outputs. Components shall meet or exceed IEEE
C37.90.1.
***************************************************************************
NOTE: Fusing is required to provide circuit
protection and to minimize arc flash levels. Include
bracketed option if pull-out type arrangement is
required.
***************************************************************************
c. Provide [a pull-out type fuse block containing] one fuse per phase,
Class RK type, to protect the voltage input to the meter. Size fuses
as recommended by the meter manufacturer. Fusing shall either be
inside the secondary compartment of the transformer or inside the same
enclosure as the CT shorting device.
***************************************************************************
NOTE: Select the following bracketed option if
potential transformers will be used to transform 480
volt inputs to 120 volts.
***************************************************************************
[d. Potential transformers will be used to convert 480 volt inputs to 120
volts for the locations shown on the metering schedule. Potential
transformers shall be rated indoor or outdoor, as required for the
specific application. Voltage rating shall provide 120 volts, wye-
connected, 3 phase, 4 wire, 60 Hz, insulation class, 600 volts.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 27 14.00 20 Page 16
Potential transformers BIL shall be 10 kV and shall have an accuracy
class of 0.3 at burdens w, x, and y. Thermal rating shall be 500 VA.]
***************************************************************************
NOTE: The following paragraphs are necessary only
for medium voltage applications.
***************************************************************************
[e. The Contractor shall be responsible for determining the actual voltage
ratio of each potential transformer for medium voltage applications.
Transformer shall conform to IEEE C57.13 and the following
requirements.
(1) Type: Dry type, of two-winding construction.
(2) Weather: Outdoor or indoor rated for the application.
(3) Frequency: Nominal 60 Hz.
(4) Accuracy: Plus or minus 0.3 percent at 60 Hz.
f. Potential transformers installed inside switchgear and panels shall be
rated for interior use. Voltage rating shall provide 120 volts, wye-
connected, 3 phase, 4 wire, 60 Hz, insulation class, 600 volts.
Potential transformers BIL shall be a minimum of 10 kV, and have an
insulation class and BIL rating that equals or exceeds the ratings of
the associated switchgear. Potential transformers shall have an
accuracy class of 0.3 at burdens w, x, and y. Thermal rating shall be
500 VA. Potential transformers shall be accessed from the front and
mounted in a metering section.]
2.1.3 Current Transformer Requirements
a. Current transformer shall be installed with a rating as shown in the
schedule.
b. Current transformers shall have an Accuracy Class of 0.3 (with a
maximum error of plus/minus 0.3 percent at 5.0 amperes) when operating
within the specified rating factor.
c. Current transformers shall be solid-core, bracket-mounted for new
installations using ring-tongue lugs for electrical connections.
Current transformers shall be accessible and the associated wiring
shall be installed in an organized and neat workmanship arrangement.
Current transformers that are retrofitted onto existing switchgear
busbar can be a busbar split-core design.
d. Current transformers shall have:
***************************************************************************
NOTE: Include the bracketed option below only if
medium voltage current transformers are used for the
electricity metering covered by this specification.
***************************************************************************
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 27 14.00 20 Page 17
(1) Insulation Class: All 600 volt and below current transformers
shall be rated 10 KV BIL. [Current transformers for 2400 and 4160
volt service shall be rated 25 KV BIL.]
(2) Frequency: Nominal 60 Hz.
(3) Burden: Burden class shall be selected for the load.
(4) Phase Angle Range: 0 to 60 degrees.
e. Meter shall accept current input from standard instrument transformers
(5A secondary current transformers).
f. Current inputs shall have a continuous rating in accordance with IEEE
C57.13.
***************************************************************************
NOTE: Single-ratio current transformers (CTs) are
specified below and are based on a per-meter
application. Dual-ratio or multi-ratio CTs are only
allowed if future requirements are expected to change
the load demand.
This specification will require additional editing if
dual-ratio or multi-ratio CTs are used.
***************************************************************************
g. Provide one single-ratio current transformer for each phase per power
transformer with characteristics listed in the following table.
***************************************************************************
NOTE: This specification uses the CT rating factor
and requires 55 degrees C as the basis for selection.
Many CTs are installed outdoors; relying on the CT 30
degrees C rating is not appropriate for these
installations.
Select the appropriate CT ratio, continuous-thermal-
current rating factor (RF) at 55 degrees C (versus 30
degrees C which was used for previous guidance) and
ANSI Metering Accuracy Class values based on
transformer kVA size and secondary voltage. The
basis for the 55 degrees C value is to allow for CT
heating effects and higher ambient temperatures
during operation.
The rating factor establishes the minimum electrical
current range that will meet the CT accuracy rating.
The CT should meet its accuracy requirement for
measured current between 10 percent of the CT ratio
and the rating factor multiplier applied to the CT
ratio.
Example #1: for a 500 kVA transformer at 208 volts -
select 1200/5, 1.33, 0.3 - B-0.5. For this selection,
the CT should be accurate within its specifications
for an input current between 10 percent to 133
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 27 14.00 20 Page 18
percent of the rating, or 120 to 1,600 amperes. The
transformer full-load current rating is 1,388
amperes.
Example #2: for a 150 kVA transformer at 480 volts -
select 200/5, 2.0, 0.3 - B-0.1. For this selection,
the CT should be accurate within its specifications
for an input current between 10 percent to 200
percent of the rating, or 20 to 400 amperes. The
transformer full-load current rating is 180 amperes.
The table below lists the minimum allowed rating
factor. Some manufacturers might be capable of higher
rating factors.
VOLTS
208 240
kVA CT Ratio RF Meter Class CT Ratio RF Meter Class
75 200/5 2.0 0.3 thru B-0.1 200/5 2.0 0.3 thru B-0.1
112.5 200/5 2.0 0.3 thru B-0.2 300/5 2.0 0.3 thru B-0.2
150 300/5 2.0 0.3 thru B-0.2 400/5 2.0 0.3 thru B-0.2
225 400/5 2.0 0.3 thru B-0.2 600/5 2.0 0.3 thru B-0.5
300 500/5 1.5 0.3 thru B-0.5 1200/5 1.5 0.3 thru B-0.5
500 1200/5 1.33 0.3 thru B-0.5 2000/5 1.33 0.3 thru B-0.9
750 2000/5 1.0 0.3 thru B-0.9 3000/5 1.0 0.3 thru B-1.8
VOLTS
480 600
kVA CT Ratio RF 55
C
Meter Class CT Ratio RF 55
C
Meter Class
75 100/5 2.0 0.3 thru B-0.1 100/5 2.0 0.3 thru B-0.1
112.5 200/5 2.0 0.3 thru B-0.1 100/5 2.0 0.3 thru B-0.1
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 27 14.00 20 Page 19
VOLTS
480 600
kVA CT Ratio RF 55
C
Meter Class CT Ratio RF 55
C
Meter Class
150 200/5 2.0 0.3 thru B-0.1 200/5 2.0 0.3 thru B-0.1
225 200/5 2.0 0.3 thru B-0.1 200/5 2.0 0.3 thru B-0.1
300 300/5 2.0 0.3 thru B-0.2 300/5 2.0 0.3 thru B-0.2
500 600/5 1.5 0.3 thru B-0.5 600/5 1.5 0.3 thru B-0.5
750 800/5 1.33 0.3 thru B-0.5 800/5 1.33 0.3 thru B-0.5
1000 1200/5 1.33 0.3 thru B-0.5 1200/5 1.33 0.3 thru B-0.5
1500 1500/5 1.33 0.3 thru B-0.9 1500/5 1.33 0.3 thru B-0.9
2000 2000/5 1.0 0.3 thru B-0.9 2000/5 1.0 0.3 thru B-0.9
2500 3000/5 1.0 0.3 thru B-1.8 3000/5 1.0 0.3 thru B-1.8
NOTE: 2. Incorporate the appropriate values in a
table similar to the one shown below.
***************************************************************************
Single-Ratio Current Transformer Characteristics
kVA Sec. Volt CT Ratio RF Meter Acc. Class
[500] [208Y/120] [1200/5] [1.33] [0.3 thru B0.05]
[750] [480Y/277] [800/5] [1.33] [0.3 thru B0.05]
2.1.4 Meter Requirements
***************************************************************************
NOTE: If J&A documentation has been obtained, use
the first bracketed option below and fill in the
manufacturer and complete model number that defines
the intended meter characteristics. Otherwise select
the second bracketed option below and edit the
general list of meter characteristics.
***************************************************************************
[Notwithstanding any other provision of this contract, meters shall be
[_____]; no other product will be acceptable.]
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 27 14.00 20 Page 20
[Electricity meters shall include the following features:
a. Meter shall comply with ANSI C12.1, NEMA C12.19, and ANSI C12.20.
b. Meter sockets shall comply with ANSI C12.7.
***************************************************************************
NOTE: Select the following bracketed industry
standards if applicable for an OCONUS application.
***************************************************************************
[c. Meter shall comply with IEC 62053-22, certified by a qualified third
party test laboratory.
d. Meter shall comply with IEC 60687 certified by a qualified 3rd party
test laboratory.]
e. Provide socket-mounted or panel mounted meters as indicated on the
meter schedule.
[(1) Panel-mounted meters shall be semi-flush, back-connected,
dustproof, draw-out switchboard type. Cases shall have window
removable covers capable of being sealed against tampering. Meters
shall be of a type that can be withdrawn through approved sliding
contacts from fronts of panels or doors without opening current-
transformer secondary circuits, disturbing external circuits, or
requiring disconnection of any meter leads. Necessary test devices
shall be incorporated within each meter and shall provide means for
testing either from an external source of electric power or from
associated instrument transformers or bus voltage.]
[(2) For meter replacement projects, meter shall match the existing
installation.]
***************************************************************************
NOTE: The default design is a Class 20, transformer
rated meter. If the measured or expected load is
less than 200 amperes, Class 200 meters can be used
for direct current reading without current
transformers. Specify the location of these meters.
***************************************************************************
f. Meter shall be a Class 20, transformer rated design.
g. [Use Class 200 meters for direct current reading without current
transformers for applications with an expected load less than 200
amperes, where indicated.]
h. Meter shall be rated for use at temperature from minus 40 [_____]
degrees Centigrade to plus 70 [_____] degrees Centigrade.
i. The meters shall have an electronic demand recording register and shall
be secondary reading as indicated. The register shall be used to
indicate maximum kilowatt demand as well as cumulative or continuously
cumulative demand. Demand shall be measured on a block-interval basis
and shall be capable of a 5 to 60 minute interval and initially set to
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 27 14.00 20 Page 21
a 15-minute interval. It shall have provisions to be programmed to
calculate demand on a rolling interval basis. Meter readings shall be
true RMS.
j. The meter electronic register shall be of modular design with non-
volatile data storage. Downloading meter stored data shall be capable
via an optical port. Recording capability of data storage with a
minimum capability of 89 days of 15 minute, 2 channel interval data.
The meter shall be capable of providing at least 2 KYZ pulse outputs
(dry contacts). Default initial configuration (unless identified
otherwise by base personnel) shall be:
(1) First channel - kWh
(2) Second channel - kVARh
(3) KYZ output #1 - kWh
(4) KYZ output #2 - kVARh
k. All meters shall have identical features available in accordance with
this specification. The meter schedule identifies which features shall
be activated at each meter location.
l. Enable switches for Time of Use (TOU), pulse and load profile
measurement module at the factory.
m. Meter shall have an optical port on front of meter capable of speeds
from 9600 to a minimum of 19.2k baud, and shall be initially set at
9600 baud. Optical device shall be compatible with ANSI C12.18.
n. Meters shall be 120-480 volts auto ranging.
***************************************************************************
NOTE: Include the bracketed option below only if
potential transformers are used.
***************************************************************************
o. Provide blank tag fixed to the meter faceplate for the addition of the
meter multiplier, which will be the product of the current transformer
[and potential transformer] ratio and will be filled in by base
personnel on the job site. The meter's nameplate shall include:
(1) Meter ID number.
(2) Rated voltage.
(3) Current class.
(4) Metering form.
(5) Test amperes.
(6) Frequency.
(7) Catalog number.
(8) Manufacturing date.
p. On switchboard style installations, provide switchboard case with
disconnect means for meter removal incorporating short-circuiting of
current transformer circuits.
q. Meter covers shall be polycarbonate resins with an optical port and
reset. Backup battery shall be easily accessible for change-out after
removing the meter cover.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 27 14.00 20 Page 22
r. The normal billing data scroll shall be fully programmable. Data
scroll display shall include the following.
(1) Number of demand resets.
(2) End-of-interval indication.
(3) Maximum demand.
(4) New maximum demand indication.
(5) Cumulative or continuously cumulative.
(6) Time remaining in interval.
(7) Kilowatt hours.
s. The register shall incorporate a built-in test mode that allows it to
be tested without the loss of any data or parameters. The following
quantities shall be available for display in the test mode:
(1) Present interval's accumulating demand.
(2) Maximum demand.
(3) Number of impulses being received by the register.
t. Pulse module simple I/O board with programmable ratio selection.
u. Meters shall be programmed after installation via an optical port.
Optical display shall show TOU data, peak kWh, semi-peak kWh, off peak
kWh, and phase angles.
v. Self-monitoring to provide for:
(1) Unprogrammed register.
(2) RAM checksum error.
(3) ROM checksum error.
(4) Hardware failure.
(5) Memory failure.
(6) EPROM error.
(7) Battery status (fault, condition, or time in service).
w. Liquid crystal alphanumeric displays, 9 digits, blinking squares
confirm register operation. 6 Large digits for data and smaller digits
for display identifier.
x. Display operations, programmable sequence with display identifiers.
Display identifiers shall be selectable for each item. Continually
sequence with time selectable for each item.
y. The meters shall support three modes of registers: Normal Mode,
Alternate Mode, and Test Mode. The meter also shall support a
"Toolbox" or "Service Information" (accessible in the field) through an
optocom port to a separate computer using the supplied software to
allow access to instantaneous service information such as voltage,
current, power factor, load demand, and the phase angle for individual
phases.
***************************************************************************
NOTE: Determine the desired warranty period and
update the bracketed option below.
***************************************************************************
z. Meter shall have a standard [4] [_____]-year warranty.]
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 27 14.00 20 Page 23
2.1.5 Disconnect Method
***************************************************************************
NOTE: The standard design shall include a 10-pole
safety disconnect. This permits meter removal
without service interruption and includes shorting
type wiring blocks so that CTs are not inadvertently
open circuited.
The options for the disconnecting wiring blocks
requires approval by the authority having
jurisdiction and would only be used when installing a
meter system using individual components rather than
an integrated switch.
***************************************************************************
a. Provide a 10-pole safety disconnect complete with isolation devices for
the voltage and current transformer inputs, including a shorting means
for the current transformers.
[b. Disconnecting wiring blocks shall be provided between the current
transformer and the meter. A shorting mechanism shall be built into
the wiring block to allow the current transformer wiring to be changed
without removing power to the transformer. The wiring blocks shall be
located where they are accessible without the necessity of
disconnecting power to the transformer.
c. Voltage monitoring circuits shall be equipped with disconnect switches
to isolate the meter base or socket from the voltage source. [Provide
fuse protection in accordance with paragraph entitled "Voltage
Requirements"]]
2.1.6 Installation Methods
***************************************************************************
NOTE: Pad-mounted transformers have proven to be
very reliable over a long life span. Installing one
meter on the outside of the secondary wiring
compartment has become the standard installation for
military facilities resulting in minimal maintenance.
However, to prevent additional compromise of the
transformer enclosure integrity, if more than one
meter is required for a location or service, add a
separate free-standing unistrut frame with each meter
in its own enclosure or use commercial meter
pedestals for each meter.
Meters may be installed on the sides of buildings.
Installing meters inside of a building and behind
locked doors has proven to be a burden for meter
readers in some instances and is not recommended.
***************************************************************************
a. Transformer Mounted ("XFMR" in Metering Systems Schedule). Meter base
shall be located outside on the secondary side of the pad-mounted
transformer.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 27 14.00 20 Page 24
b. Stand Mounted Adjacent to Transformer ("STAND" in Metering Systems
Schedule). Meter base shall be mounted on a structural steel pole
approximately 1.2 meters (4 feet) from the transformer pad. This can
be used for multiple meters associated with a single transformers.
***************************************************************************
NOTE: Provide a drawing to show details for building
mounting and routing conduit and wires. Typical
detail drawings are referenced at the beginning of
this specification.
***************************************************************************
c. Building Mounted ("BLDG" in Metering Systems Schedule). Meter base
shall be mounted on the side of the existing building near the service
entrance.
d. Panel Mounted. ("PNL" in Metering Systems Schedule). Meter shall be
mounted where directed.
e. Commercial meter pedestal ("PED" in Metering Systems Schedule).
2.2 COMMUNICATIONS INTERFACES
***************************************************************************
NOTE: The default metering condition is to provide
two-way communication with an existing DAS, if
installed at the Activity already. If a DAS is not
installed or is outdated (inadequate), then
coordinate with the activity to determine if a new
DAS should be provided as part of the contract. If a
new DAS is determined to be necessary, edit the
requirements below as needed to identify the DAS
requirements.
The communications requirements must be determined
for each location and are not addressed by this
specification. Possible communications options
include:
RS-232
RS-485
Optical port
Ethernet (RJ-45)
Fiber-optic ST connection
RF (Wireless) Module and
Power line carrier
Determine the communications requirements for the
metering system and modify the paragraph below as
necessary to define the selected communication
system.
***************************************************************************
Meter shall have two-way communication with the existing data acquisition
system (DAS). Provide a communications interface utilizing [_____]. [Refer
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 27 14.00 20 Page 25
to Section [_____] for the communication interface requirements for these
meters.]
Provide interfacing software if a meter is used that is different than the
existing meters at the Activity to ensure compatibility within the metering
system.
***************************************************************************
NOTE: Determine the connections requirements for the
AMI network and modify the paragraph below as
necessary to provide equipment for the system. This
could be as simple as providing a fiber optic link to
the closest connection point or could be more
extensive and requires close coordination with the
Activity.
***************************************************************************
Connect to the AMI network utilizing [_____].
***************************************************************************
NOTE: Determine what modifications need to be done
to the existing DoD Information Assurance
Certification and Accreditation Process (DIACAP) to
maintain accreditation. Check with the local Command
Information Officer (CIO) for the latest
requirements.
***************************************************************************
[Provide [_____].]
2.3 SPARE PARTS
***************************************************************************
NOTE: Spare parts are not normally included as part
of the construction contract or on contracts
involving a small number of meters. On large
projects, involving ten or more meters, the following
may be an example of spare parts requirements.
***************************************************************************
[Provide the following spare parts:
a. Power Meter - two for each type used with batteries.
b. Communications interface - one for each type used.]
2.4 METERING SYSTEM SCHEDULE
***************************************************************************
NOTE: A schedule of meters and their associated
requirements are preferentially included on a
separate drawing. As an alternate, the required
tabular information can be provided below. In each
case, identify the characteristics for the specific
meter and communications method for each building.
***************************************************************************
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 27 14.00 20 Page 26
[_____]
PART 3 EXECUTION
3.1 INSTALLATION
Electrical installations shall conform to IEEE C2, NFPA 70 (National
Electrical Code), and to the requirements specified herein. Provide new
equipment and materials unless indicated or specified otherwise.
***************************************************************************
NOTE: Remove the following section if existing
condition surveys are not required. If an existing
condition survey is not required as part of the
installation, the metering system schedule should
address any unique requirements for each
installation.
***************************************************************************
[3.1.1 Existing Condition Survey
The Contractor shall perform a field survey, including inspection of all
existing equipment, resulting clearances, and new equipment locations
intended to be incorporated into the system and furnish an existing
conditions report to the Government. The report shall identify those items
that are non-workable as defined in the contract documents. The Contractor
shall be held responsible for repairs and modifications necessary to make
the system perform as required.
3.1.1.1 Existing Meter Sockets
In some cases, the existing meter sockets will have to be replaced to
accommodate the new electrical meters. An existing socket is considered
unacceptable for any of the following conditions:
a. It is a non-ANSI form factor meter socket.
b. It is weathered beyond the point of being safe to reuse.
c. It is installed incorrectly, such as a non-weather resistant enclosure
installed outdoors.
d. It is not the correct form factor for the existing electrical service.
3.1.1.2 Existing Installations
As part of the existing condition survey, the following applies for
installations with existing meters:
***************************************************************************
NOTE: Coordinate with the activity for the desired
re-use or disposition of existing PTs.
***************************************************************************
a. Replace any meters that do not comply with this section.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 27 14.00 20 Page 27
b. If CTs are installed, verify that they comply with this section. If
they do not comply, replace them with CTs that comply with this
section. One CT per phase is required for wye-connected systems.
[c. If potential transformers are installed on low-voltage systems, remove
the PTs as part of the installation.]
d. Install disconnect switches as specified in this section.
][3.1.2 Scheduling of Work and Outages
***************************************************************************
NOTE: Installation of current transformers and
potential transformers will require that power be
disconnected from the transformer and building.
Provide coordination steps for the work and require
the Contractor to perform the work after normal
hours. Coordinate with Division 1 Sections.
***************************************************************************
The Contract Clauses shall govern regarding permission for power outages,
scheduling of work, coordination with Government personnel, and special
working conditions.[_____]
]3.1.3 Configuration Software
The standard meter shall include the latest available version of firmware
and software. Meter shall either be programmed at the factory or shall be
programmed in the field. Meters shall have a password that shall be
provided to the contracting officer upon project completion. When field
programming is performed, turn field programming device over to the
Contracting Officer at completion of project. When interfacing software is
used for a meter that is different than the existing meters in use at the
Activity, turn the software over to the Contracting Officer at completion of
the project.
3.2 FIELD QUALITY CONTROL
***************************************************************************
NOTE: Apply 100 percent checks for smaller projects.
Use random sampling of acceptance checks and tests
for large projects. If no problems are identified in
the acceptance checks and tests of the random sample,
then the results would be accepted. If problems are
identified in the acceptance checks and tests of the
random sample, then an additional random sample would
be selected for verification.
***************************************************************************
Perform the following acceptance checks and tests on [a random sample of 10
percent of the installed meters as designated by the Contracting Officer]
[all installed meters].
3.2.1 Performance of Acceptance Checks and Tests
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 27 14.00 20 Page 28
Perform in accordance with the manufacturer's recommendations and include
the following visual and mechanical inspections and electrical tests,
performed in accordance with NETA ATS.
a. Meter Assembly
***************************************************************************
NOTE: The following requirements are derived from
NETA ATS and have been modified for this
specification.
***************************************************************************
(1) Visual and mechanical inspection.
(a) Compare equipment nameplate data with specifications and
approved shop drawings.
(b) Inspect physical and mechanical condition. Confirm the meter
is firmly seated in the socket, the socket is not abnormally
heated, the display is visible, and the ring and seal on the cover
are intact.
(c) Inspect all electrical connections to ensure they are tight.
For Class 200 services, verify tightness of the service conductor
terminations for high resistance using low-resistance ohmmeter, or
by verifying tightness of accessible bolted electrical connections
by calibrated torque-wrench method.
(d) Record model number, serial number, firmware revision,
software revision, and rated control voltage.
(e) Verify operation of display and indicating devices.
(f) Record password and user log-in for each meter.
(g) Verify grounding of metering enclosure.
(h) Set all required parameters including instrument transformer
ratios, system type, frequency, power demand methods/intervals, and
communications requirements. Verify that the CT ratio and the PT
ratio are properly included in the meter multiplier or the
programming of the meter. Confirm that the multiplier is provided
on the meter face or on the meter.
(i) Provide building meter installation sheet, per building for
each facility. See example Graphic E-S1.
(j) Provide the completed meter installation schedule for the
installation. See example Graphic E-S2
(k) Provide the completed meter data schedule for the installation.
See example Graphic E-S3.
(2) Electrical tests.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 27 14.00 20 Page 29
(a) Apply voltage or current as appropriate to each analog input
and verify correct measurement and indication.
(b) Confirm correct operation and setting of each auxiliary
input/output feature including mechanical relay, digital, and
analog.
(c) After initial system energization, confirm measurements and
indications are consistent with loads present.
(d) Make note of, and report, any "Error-Code" or "Caution-Code"
on the meter's display.
(3) Provide meter configuration report.
b. Current Transformers
(1) Visual and mechanical inspection.
(a) Compare equipment nameplate data with specification and
approved shop drawings.
(b) Inspect physical and mechanical condition.
(c) Verify correct connection, including polarity.
(d) Inspect all electrical connections to ensure they are tight.
(e) Verify that required grounding and shorting connections provide
good contact.
(2) Electrical Tests.
Verify proper operation by reviewing the meter configuration
report.
***************************************************************************
NOTE: Include the following inspections and tests if
potential transformers are included within the scope
of the project.
***************************************************************************
[c. Potential Transformers
(1) Visual and mechanical inspection.
(a) Verify potential transformers are rigidly mounted.
(b) Verify potential transformers are the correct voltage.
(c) Verify that adequate clearances exist between the primary and
secondary circuit.
(2) Electrical Tests.
(a) Verify by the meter configuration report that the polarity and
phasing are correct.]
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 27 14.00 20 Page 30
3.2.2 System Functional Verification
Verify that the installed meters are working correctly in accordance with
the meter configuration report:
a. The correct meter form is installed.
b. All voltage phases are present.
c. Phase rotation is correct.
d. Phase angles are correct.
e. The new meter accurately measures power magnitude and direction, and
can communicate as required by paragraph entitled "Communications
Interfaces".
-- End of Section --
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 29 23 Page 1
***************************************************************************
USACE / NAVFAC / AFCEC / NASA UFGS-26 29 23 (April 2006)
--------------------------
Preparing Activity: NAVFAC Replacing without change
UFGS-16261 (August 2004)
UNIFIED FACILITIES GUIDE SPECIFICATIONS
References are in agreement with UMRL dated October 2017
***************************************************************************
SECTION 26 29 23
VARIABLE FREQUENCY DRIVE SYSTEMS UNDER 600 VOLTS
04/06
***************************************************************************
NOTE: This guide specification covers the
requirements for variable frequency drive for motors
rated up to 575 volts, for use on electric power
systems of 600 volts or less, 50/60 hertz.
Adhere to UFC 1-300-02 Unified Facilities Guide
Specifications (UFGS) Format Standard when editing
this guide specification or preparing new project
specification sections. Edit this guide
specification for project specific requirements by
adding, deleting, or revising text. For bracketed
items, choose applicable item(s) or insert
appropriate information.
Remove information and requirements not required in
respective project, whether or not brackets are
present.
Comments, suggestions and recommended changes for
this guide specification are welcome and should be
submitted as a Criteria Change Request (CCR).
***************************************************************************
***************************************************************************
NOTE: Pulse width modulated (PWM) is the predominant
type of variable frequency drive (VFD). Other VFD
types include current source inverter (CSI), voltage
source inverter (VSI), and flux vector drive (FVD).
For a description of each type of VFD, basic
information on the principles of operation of VFD's,
guidance of the proper application of VFD's, and
installation guidelines, refer to Appendix D of MIL-
HDBK-1003/3, which is part of UFC 3-410-02N,
"Heating, Ventilating, Air Conditioning and
Dehumidifying Systems".
***************************************************************************
PART 1 GENERAL
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 29 23 Page 2
1.1 REFERENCES
***************************************************************************
NOTE: This paragraph is used to list the
publications cited in the text of the guide
specification. The publications are referred to in
the text by basic designation only and listed in this
paragraph by organization, designation, date, and
title.
Use the Reference Wizard's Check Reference feature
when you add a Reference Identifier (RID) outside of
the Section's Reference Article to automatically
place the reference in the Reference Article. Also
use the Reference Wizard's Check Reference feature to
update the issue dates.
References not used in the text will automatically be
deleted from this section of the project
specification when you choose to reconcile references
in the publish print process.
***************************************************************************
The publications listed below form a part of this specification to the
extent referenced. The publications are referred to within the text by the
basic designation only.
INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)
IEEE 519 (2014) Recommended Practices and Requirements
for Harmonic Control in Electrical Power
Systems
IEEE C62.41.1 (2002; R 2008) Guide on the Surges
Environment in Low-Voltage (1000 V and Less)
AC Power Circuits
IEEE C62.41.2 (2002) Recommended Practice on
Characterization of Surges in Low-Voltage
(1000 V and Less) AC Power Circuits
NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)
NEMA 250 (2014) Enclosures for Electrical Equipment
(1000 Volts Maximum)
NEMA ICS 1 (2000; R 2015) Standard for Industrial
Control and Systems: General Requirements
NEMA ICS 3.1 (2009; R 2014) Guide for the Application,
Handling, Storage, Installation and
Maintenance of Medium-Voltage AC Contactors,
Controllers and Control Centers
NEMA ICS 6 (1993; R 2016) Industrial Control and
Systems: Enclosures
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 29 23 Page 3
NEMA ICS 7 (2014) Adjustable-Speed Drives
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 70 (2017; ERTA 1-2 2017; TIA 17-1; TIA 17-2; TIA
17-3) National Electrical Code
U.S. DEPARTMENT OF DEFENSE (DOD)
MIL-STD-461 (2015; Rev G) Requirements for the Control of
Electromagnetic Interference Characteristics
of Subsystems and Equipment
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
47 CFR 15 Radio Frequency Devices
UNDERWRITERS LABORATORIES (UL)
UL 489 (2016) UL Standard for Safety Molded-Case
Circuit Breakers, Molded-Case Switches and
Circuit-Breaker Enclosures
UL 508C (2002; Reprint Nov 2010) Power Conversion
Equipment
1.2 RELATED REQUIREMENTS
Section 26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS, and Section
26 20 00 INTERIOR DISTRIBUTION SYSTEM apply to this section with additions
and modifications specified herein.
1.3 SYSTEM DESCRIPTION
1.3.1 Performance Requirements
1.3.1.1 Electromagnetic Interference Suppression
Computing devices, as defined by 47 CFR 15, MIL-STD-461 rules and
regulations, shall be certified to comply with the requirements for class A
computing devices and labeled as set forth in part 15.
1.3.1.2 Electromechanical and Electrical Components
Electrical and electromechanical components of the Variable Frequency Drive
(VFD) shall not cause electromagnetic interference to adjacent electrical
or electromechanical equipment while in operation.
1.3.2 Electrical Requirements
1.3.2.1 Power Line Surge Protection
IEEE C62.41.1 and IEEE C62.41.2, IEEE 519 Control panel shall have surge
protection, included within the panel to protect the unit from damaging
transient voltage surges. Surge arrestor shall be mounted near the incoming
power source and properly wired to all three phases and ground. Fuses shall
not be used for surge protection.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 29 23 Page 4
1.3.2.2 Sensor and Control Wiring Surge Protection
I/O functions as specified shall be protected against surges induced on
control and sensor wiring installed outdoors and as shown. The inputs and
outputs shall be tested in both normal mode and common mode using the
following two waveforms:
a. A 10 microsecond by 1000 microsecond waveform with a peak voltage of
1500 volts and a peak current of 60 amperes.
b. An 8 microsecond by 20 microsecond waveform with a peak voltage of 1000
volts and a peak current of 500 amperes.
1.4 SUBMITTALS
***************************************************************************
NOTE: Review Submittal Description (SD) definitions
in Section 01 33 00 SUBMITTAL PROCEDURES and edit the
following list to reflect only the submittals
required for the project.
The Guide Specification technical editors have
designated those items that require Government
approval, due to their complexity or criticality,
with a "G". Generally, other submittal items can be
reviewed by the Contractor's Quality Control System.
Only add a “G” to an item, if the submittal is
sufficiently important or complex in context of the
project.
For submittals requiring Government approval on Army
projects, a code of up to three characters within the
submittal tags may be used following the "G"
designation to indicate the approving authority.
Codes for Army projects using the Resident Management
System (RMS) are: "AE" for Architect-Engineer; "DO"
for District Office (Engineering Division or other
organization in the District Office); "AO" for Area
Office; "RO" for Resident Office; and "PO" for
Project Office. Codes following the "G" typically
are not used for Navy, Air Force, and NASA projects.
Use the "S" classification only in SD-11 Closeout
Submittals. The "S" following a submittal item
indicates that the submittal is required for the
Sustainability eNotebook to fulfill federally
mandated sustainable requirements in accordance with
Section 01 33 29 SUSTAINABILITY REPORTING.
Choose the first bracketed item for Navy, Air Force
and NASA projects, or choose the second bracketed
item for Army projects.
***************************************************************************
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are [for Contractor Quality Control
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 29 23 Page 5
approval.][for information only. When used, a designation following the "G"
designation identifies the office that will review the submittal for the
Government.] Submittals with an "S" are for inclusion in the Sustainability
eNotebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-02 Shop Drawings
Schematic diagrams; G[, [_____]]
Interconnecting diagrams; G[, [_____]]
Installation drawings; G[, [_____]]
Submit drawings for government approval prior to equipment
construction or integration. Modifications to original drawings
made during installation shall be immediately recorded for
inclusion into the as-built drawings.
SD-03 Product Data
Variable frequency drives; G[, [_____]]
Wires and cables
Equipment schedule
Include data indicating compatibility with motors being driven.
SD-06 Test Reports
VFD Test
Performance Verification Tests
Endurance Test
SD-08 Manufacturer's Instructions
Installation instructions
SD-09 Manufacturer's Field Reports
VFD Factory Test Plan; G[, [_____]]
Factory test results
SD-10 Operation and Maintenance Data
Variable frequency drives, Data Package 4
Submit in accordance with Section 01 78 23 OPERATION AND
MAINTENANCE DATA. Provide service and maintenance information
including preventive maintenance, assembly, and disassembly
procedures. Include electrical drawings from electrical general
sections. Submit additional information necessary to provide
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 29 23 Page 6
complete operation, repair, and maintenance information, detailed
to the smallest replaceable unit. Include copies of as-built
submittals. Provide routine preventative maintenance instructions,
and equipment required. Provide instructions on how to modify
program settings, and modify the control program. Provide
instructions on drive adjustment, trouble-shooting, and
configuration. Provide instructions on process tuning and system
calibration.
1.5 QUALITY ASSURANCE
1.5.1 Schematic Diagrams
Show circuits and device elements for each replaceable module. Schematic
diagrams of printed circuit boards are permitted to group functional
assemblies as devices, provided that sufficient information is provided for
government maintenance personnel to verify proper operation of the
functional assemblies.
1.5.2 Interconnecting Diagrams
Show interconnections between equipment assemblies, and external interfaces,
including power and signal conductors. Include for enclosures and external
devices.
1.5.3 Installation Drawings
Show floor plan of each site, with V.F.D.'s and motors indicated. Indicate
ventilation requirements, adequate clearances, and cable routes.
1.5.4 Equipment Schedule
Provide schedule of equipment supplied. Schedule shall provide a cross
reference between manufacturer data and identifiers indicated in shop
drawings. Schedule shall include the total quantity of each item of
equipment supplied. For complete assemblies, such as VFD's, provide the
serial numbers of each assembly, and a sub-schedule of components within the
assembly. Provide recommended spare parts listing for each assembly or
component.
1.5.5 Installation instructions
Provide installation instructions issued by the manufacturer of the
equipment, including notes and recommendations, prior to shipment to the
site. Provide operation instructions prior to acceptance testing.
1.5.6 Factory Test Results
Document test results and submit to government within 7 working days after
completion of test.
1.6 DELIVERY AND STORAGE
Equipment delivered and placed in storage shall be stored with protection
from the weather, humidity and temperature variations, dirt and dust, or
other contaminants.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 29 23 Page 7
1.7 WARRANTY
The complete system shall be warranted by the manufacturer for a period of
one year, or the contracted period of any extended warrantee agreed upon by
the contractor and the Government, after successful completion of the
acceptance test. Any component failing to perform its function as specified
and documented shall be repaired or replaced by the contractor at no
additional cost to the Government. Items repaired or replaced shall be
warranted for an additional period of at least one year from the date that
it becomes functional again, as specified in the FAR CLAUSE 52.246-21.
1.8 MAINTENANCE
1.8.1 Spare Parts
Manufacturers provide spare parts in accordance with recommended spare parts
list.
1.8.2 Maintenance Support
During the warranty period, the Contractor shall provide on-site, on-call
maintenance services by Contractor's personnel on the following basis: The
service shall be on a per-call basis with 36 hour response. Contractor
shall support the maintenance of all hardware and software of the system.
Various personnel of different expertise shall be sent on-site depending on
the nature of the maintenance service required. Costs shall include travel,
local transportation, living expenses, and labor rates of the service
personnel while responding to the service request. The provisions of this
Section are not in lieu of, nor relieve the Contractor of, warranty
responsibilities covered in this specification. Should the result of the
service request be the uncovering of a system defect covered under the
warranty provisions, all costs for the call, including the labor necessary
to identify the defect, shall be borne by the Contractor.
PART 2 PRODUCTS
2.1 VARIABLE FREQUENCY DRIVES (VFD)
Provide frequency drive to control the speed of induction motor(s). The VFD
shall include the following minimum functions, features and ratings.
a. Input circuit breaker per UL 489 with a minimum of 10,000 amps
symmetrical interrupting capacity and door interlocked external
operator.
b. A converter stage per UL 508C shall change fixed voltage, fixed
frequency, ac line power to a fixed dc voltage. The converter shall
utilize a full wave bridge design incorporating diode rectifiers.
Silicon Controlled Rectifiers (SCR) are not acceptable. The converter
shall be insensitive to three phase rotation of the ac line and shall
not cause displacement power factor of less than .95 lagging under any
speed and load condition.
c. An inverter stage shall change fixed dc voltage to variable frequency,
variable voltage, ac for application to a standard NEMA design B
squirrel cage motor. The inverter shall be switched in a manner to
produce a sine coded pulse width modulated (PWM) output waveform.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 29 23 Page 8
***************************************************************************
NOTE: If constant torque required modify to 150
percent of rated full load.
***************************************************************************
d. The VFD shall be capable of supplying 120 percent of rated full load
current for one minute at maximum ambient temperature.
e. The VFD shall be designed to operate from a [_____] volt, plus or minus
10 percent, three phase, 60 Hz supply, and control motors with a
corresponding voltage rating.
f. Acceleration and deceleration time shall be independently adjustable
from one second to 60 seconds.
***************************************************************************
NOTE: Modify this paragraph if constant torque
required.
***************************************************************************
g. Adjustable full-time current limiting shall limit the current to a
preset value which shall not exceed 120 percent of the controller rated
current. The current limiting action shall maintain the V/Hz ratio
constant so that variable torque can be maintained. Short time
starting override shall allow starting current to reach 175 percent of
controller rated current to maximum starting torque.
h. The controllers shall be capable of producing an output frequency over
the range of 3 Hz to 60 Hz (20 to one speed range), without low speed
cogging. Over frequency protection shall be included such that a
failure in the controller electronic circuitry shall not cause
frequency to exceed 110 percent of the maximum controller output
frequency selected.
i. Minimum and maximum output frequency shall be adjustable over the
following ranges: 1) Minimum frequency 3 Hz to 50 percent of maximum
selected frequency; 2) Maximum frequency 40 Hz to 60 Hz.
j. The controller efficiency at any speed shall not be less than 96
percent.
k. The controllers shall be capable of being restarted into a motor
coasting in the forward direction without tripping.
l. Protection of power semiconductor components shall be accomplished
without the use of fast acting semiconductor output fuses. Subjecting
the controllers to any of the following conditions shall not result in
component failure or the need for fuse replacement:
1. Short circuit at controller output
2. Ground fault at controller output
3. Open circuit at controller output
4. Input undervoltage
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 29 23 Page 9
5. Input overvoltage
6. Loss of input phase
7. AC line switching transients
8. Instantaneous overload
9. Sustained overload exceeding 115 percent of controller rated
current
10. Over temperature
11. Phase reversal
m. Solid state motor overload protection shall be included such that
current exceeding an adjustable threshold shall activate a 60 second
timing circuit. Should current remain above the threshold continuously
for the timing period, the controller will automatically shut down.
n. A slip compensation circuit shall be included which will sense changing
motor load conditions and adjust output frequency to provide speed
regulation of NEMA B motors to within plus or minus 0.5 percent of
maximum speed without the necessity of a tachometer generator.
o. The VFD shall be factory set for manual restart after the first
protective circuit trip for malfunction (overcurrent, undervoltage,
overvoltage or overtemperature) or an interruption of power. The VFD
shall be capable of being set for automatic restart after a selected
time delay. If the drive faults again within a specified time period
(adjustable 0-60 seconds), a manual restart will be required.
p. The VFD shall include external fault reset capability. All the
necessary logic to accept an external fault reset contact shall be
included.
q. Provide critical speed lockout circuitry to prevent operating at
frequencies with critical harmonics that cause resonant vibrations. The
VFD shall have a minimum of three user selectable bandwidths.
r. Provide the following operator control and monitoring devices mounted
on the front panel of the VFD:
1. Manual speed potentiometer.
2. Hand-Off-Auto ( HOA ) switch.
3. Power on light.
4. Drive run power light.
5. Local display.
s. Provide properly sized NEMA rated by-pass and isolation contactors to
enable operation of motor in the event of VFD failure. Mechanical and
electrical interlocks shall be installed between the by-pass and
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 29 23 Page 10
isolation contactors. Provide a selector switch and transfer delay
timer.
2.2 ENCLOSURES
Provide equipment enclosures conforming to NEMA 250, NEMA ICS 7, NEMA ICS 6.
2.3 WIRES AND CABLES
All wires and cables shall conform to NEMA 250, NEMA ICS 7, NFPA 70.
2.4 NAMEPLATES
Nameplates external to NEMA enclosures shall conform with the requirements
of Section 26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS.
Nameplates internal to enclosures shall be manufacturer's standard, with the
exception that they must be permanent.
2.5 SOURCE QUALITY CONTROL
2.5.1 VFD Factory Test Plan
To ensure quality, each VFD shall be subject to a series of in-plant quality
control inspections before approval for shipment from the manufacturer's
facilities. Provide test plans and test reports.
PART 3 EXECUTION
3.1 INSTALLATION
Per NEMA ICS 3.1, install equipment in accordance with the approved
manufacturer's printed installation drawings, instructions, wiring
diagrams, and as indicated on project drawings and the approved shop
drawings. A field representative of the drive manufacturer shall supervise
the installation of all equipment, and wiring.
3.2 FIELD QUALITY CONTROL
Specified products shall be tested as a system for conformance to
specification requirements prior to scheduling the acceptance tests.
Contractor shall conduct performance verification tests in the presence of
Government representative, observing and documenting complete compliance of
the system to the specifications. Contractor shall submit a signed copy of
the test results, certifying proper system operation before scheduling
tests.
3.2.1 VFD Test
A proposed test plan shall be submitted to the contracting officer at least
28 calendar days prior to proposed testing for approval. The tests shall
conform to NEMA ICS 1, NEMA ICS 7, and all manufacturer's safety
regulations. The Government reserves the right to witness all tests and
review any documentation. The contractor shall inform the Government at
least 14 working days prior to the dates of testing. Contractor shall
provide video tapes, if available, of all training provided to the
Government for subsequent use in training new personnel. All training aids,
texts, and expendable support material for a self-sufficient presentation
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 29 23 Page 11
shall be provided, the amount of which to be determined by the contracting
officer.
3.2.2 Performance Verification Tests
"Performance Verification Test" plan shall provide the step by step
procedure required to establish formal verification of the performance of
the VFD. Compliance with the specification requirements shall be verified
by inspections, review of critical data, demonstrations, and tests. The
Government reserves the right to witness all tests, review data, and request
other such additional inspections and repeat tests as necessary to ensure
that the system and provided services conform to the stated requirements.
The contractor shall inform the Government 14 calendar days prior to the
date the test is to be conducted.
3.2.3 Endurance Test
Immediately upon completion of the performance verification test, the
endurance test shall commence. The system shall be operated at varying
rates for not less than 192 consecutive hours, at an average effectiveness
level of .9998, to demonstrate proper functioning of the complete PCS.
Continue the test on a day-to-day basis until performance standard is met.
During the endurance test, the contractor shall not be allowed in the
building. The system shall respond as designed.
3.3 DEMONSTRATION
3.3.1 Training
Coordinate training requirements with the Contracting Officer.
3.3.1.1 Instructions to Government Personnel
Provide the services of competent instructors who will give full instruction
to designated personnel in operation, maintenance, calibration,
configuration, and programming of the complete control system. Orient the
training specifically to the system installed. Instructors shall be
thoroughly familiar with the subject matter they are to teach. The
Government personnel designated to attend the training will have a high
school education or equivalent. The number of training days of instruction
furnished shall be as specified. A training day is defined as eight hours
of instruction, including two 15-minute breaks and excluding lunch time;
Monday through Friday. Provide a training manual for each student at each
training phase which describes in detail the material included in each
training program. Provide one additional copy for archiving. Provide
equipment and materials required for classroom training. Provide a list of
additional related courses, and offers, noting any courses recommended.
List each training course individually by name, including duration,
approximate cost per person, and location of course. Unused copies of
training manuals shall be turned over to the Government at the end of last
training session.
3.3.1.2 Operating Personnel Training Program
Provide one 2 2-hour training session at the site at a time and place
mutually agreeable between the Contractor and the Government. Provide
session to train 4 operation personnel in the functional operations of the
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 29 23 Page 12
system and the procedures that personnel will follow in system operation.
This training shall include:
a. System overview
b. General theory of operation
c. System operation
d. Alarm formats
e. Failure recovery procedures
f. Troubleshooting
3.3.1.3 Engineering/Maintenance Personnel Training
Accomplish the training program as specified. Training shall be conducted
on site at a location designated by the Government. Provide a one one-day
training session to train 4 engineering personnel in the functional
operations of the system. This training shall include:
a. System overview
b. General theory of operation
c. System operation
d. System configuration
e. Alarm formats
f. Failure recovery procedures
g. Troubleshooting and repair
h. Maintenance and calibration
i. System programming and configuration
-- End of Section --
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 33 53.00 20 Page 1
***************************************************************************
USACE / NAVFAC / AFCEC / NASA UFGS-26 33 53.00 20 (April 2008)
----------------------------------
Preparing Activity: NAVFAC Superseding
UFGS-26 33 53.00 20 (January 2008)
UNIFIED FACILITIES GUIDE SPECIFICATIONS
References are in agreement with UMRL dated October 2017
***************************************************************************
SECTION 26 33 53.00 20
UNINTERRUPTIBLE POWER SUPPLY (UPS)
04/08
***************************************************************************
NOTE: This guide specification covers the
requirements for static UPS to provide continuous ac
power to critical loads and/or to improve the quality
of ac power to critical loads. The covered range of
UPS units is between 10kVA and 750kVA 3-phase systems
only. Single phase systems are not addressed. This
specification covers UPS with electro-chemical
batteries. Electro-mechanical (stored energy) UPS are
not addressed.
Use of electronic communication is encouraged.
Adhere to UFC 1-300-02 Unified Facilities Guide
Specifications (UFGS) Format Standard when editing
this guide specification or preparing new project
specification sections. Edit this guide
specification for project specific requirements by
adding, deleting, or revising text. For bracketed
items, choose applicable item(s) or insert
appropriate information. Brackets are used in the
text to indicated designer choices or locations where
text must be supplied by the designer.
Comments, suggestions and recommended changes for
this guide specification are welcome and should be
submitted as a Criteria Change Request (CCR).
***************************************************************************
***************************************************************************
NOTE: For Air Force projects only, UPS
specifications, criteria, and purchases shall be
approved by the Power Conditioning and Continuation
Interfacing Equipment (PCCIE) Group Manager at Ogden
Air Logistics Center (OO-ALC/LGHC)
http://www.hill.af.mil/lg2/WebLGH.htm
***************************************************************************
***************************************************************************
NOTE: This guide specification is intended to be
used with individual UPS units which contain a single
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 33 53.00 20 Page 2
module or multiple modules within the same assembly.
Parallel units are not specifically addressed and
require additional components. There are two types
of parallel systems commonly available. One is a
parallel system that requires a system control panel,
external static bypass switch to control the
individual units and additional output switchgear
with maintenance bypass to connect the output of all
the units; the other is individual units that have
integrated controls and static bypass switches that
communicate with one another and only require the
output switchgear with maintenance bypass to connect
the output of all the parallel units. The designer
should be aware of the differences and select the
system that addresses the design requirements.
Parallel systems require additional paragraphs to
address the additional components (system control
panel with static bypass switch, output switchgear,
etc) and overall system requirements.
***************************************************************************
***************************************************************************
NOTE: This guide specification will not be used in
the preparation of project documents for installation
of Government-furnished (GFE) UPS systems. For UPS
and battery installation instructions for GFE
projects refer to "UPS Manufacturer's Installation
Drawings" and "Battery Manufacturer's Rack Assembly
and Battery Installation Instructions" which must be
obtained from the Contracting Officer.
All plans/specifications having uninterruptible power
supply systems, which were procured as Government-
furnished/Contractor installed equipment, must be
reviewed and concurred by the Contracting Officer.
***************************************************************************
PART 1 GENERAL
1.1 REFERENCES
***************************************************************************
NOTE: This paragraph is used to list the
publications cited in the text of the guide
specification. The publications are referred to in
the text by basic designation only and listed in this
paragraph by organization, designation, date, and
title.
Use the Reference Wizard's Check Reference feature
when you add a Reference Identifier (RID) outside of
the Section's Reference Article to automatically
place the reference in the Reference Article. Also
use the Reference Wizard's Check Reference feature to
update the issue dates.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 33 53.00 20 Page 3
References not used in the text will automatically be
deleted from this section of the project
specification when you choose to reconcile references
in the publish print process.
***************************************************************************
The publications listed below form a part of this specification to the
extent referenced. The publications are referred to within the text by the
basic designation only.
ACOUSTICAL SOCIETY OF AMERICA (ASA)
ASA S1.4 (1983; Amendment 1985; R 2006) Specification
for Sound Level Meters (ASA 47)
ASTM INTERNATIONAL (ASTM)
ASTM B173 (2017) Standard Specification for Rope-Lay-
Stranded Copper Conductors Having Concentric-
Stranded Members, for Electrical Conductors
ASTM D709 (2017) Standard Specification for Laminated
Thermosetting Materials
INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)
IEEE 100 (2000; Archived) The Authoritative Dictionary
of IEEE Standards Terms
IEEE 450 (2010) Recommended Practice for Maintenance,
Testing, and Replacement of Vented Lead-Acid
Batteries for Stationary Applications
IEEE C2 (2017; Errata 1-2 2017; INT 1 2017) National
Electrical Safety Code
IEEE C57.110 (2008) Recommended Practice for Establishing
Liquid-Filled and Dry-Type Power and
Distribution Transformer Capability When
Supplying Nonsinusoidal Load Currents
IEEE C62.41.1 (2002; R 2008) Guide on the Surges
Environment in Low-Voltage (1000 V and Less)
AC Power Circuits
IEEE C62.41.2 (2002) Recommended Practice on
Characterization of Surges in Low-Voltage
(1000 V and Less) AC Power Circuits
INTERNATIONAL ELECTRICAL TESTING ASSOCIATION (NETA)
NETA ATS (2017) Standard for Acceptance Testing
Specifications for Electrical Power Equipment
and Systems
INTERNATIONAL ORGANIZATION FOR STANDARDIZATION (ISO)
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 33 53.00 20 Page 4
ISO 9001 (2008; Corr 1 2009) Quality Management
Systems- Requirements
NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)
NEMA 250 (2014) Enclosures for Electrical Equipment
(1000 Volts Maximum)
NEMA PE 1 (2012) Uninterruptible Power Systems (UPS)
Specification and Performance Verification
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 70 (2017; ERTA 1-2 2017; TIA 17-1; TIA 17-2; TIA
17-3) National Electrical Code
U.S. DEPARTMENT OF ENERGY (DOE)
Energy Star (1992; R 2006) Energy Star Energy Efficiency
Labeling System (FEMP)
UNDERWRITERS LABORATORIES (UL)
UL 1449 (2014; Reprint Jul 2017) UL Standard for
Safety Surge Protective Devices
UL 1778 (2014; Reprint Aug 2015) Uninterruptible
Power Systems
1.2 RELATED REQUIREMENTS
***************************************************************************
NOTE: Include Section 26 08 00 APPARATUS INSPECTION
AND TESTING on all projects involving medium voltage
and specialized power distribution equipment.
***************************************************************************
Section 26 08 00 APPARATUS INSPECTION AND TESTING applies to this section,
with the additions and modifications specified herein.
1.3 DEFINITIONS
Unless otherwise specified or indicated, electrical and electronics terms
used in these specifications, and on the drawings, shall be as defined in
IEEE 100.
1.4 SUBMITTALS
***************************************************************************
NOTE: Review Submittal Description (SD) definitions
in Section 01 33 00 SUBMITTAL PROCEDURES and edit the
following list to reflect only the submittals
required for the project.
The Guide Specification technical editors have
designated those items that require Government
approval, due to their complexity or criticality,
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 33 53.00 20 Page 5
with a "G". Generally, other submittal items can be
reviewed by the Contractor's Quality Control System.
Only add a “G” to an item, if the submittal is
sufficiently important or complex in context of the
project.
For submittals requiring Government approval on Army
projects, a code of up to three characters within the
submittal tags may be used following the "G"
designation to indicate the approving authority.
Codes for Army projects using the Resident Management
System (RMS) are: "RE" for Resident Engineer
approval, "ED for Engineering approval, and "AE" for
Architect-Engineer approval"AE" for Architect-
Engineer; "DO" for District Office (Engineering
Division or other organization in the District
Office); "AO" for Area Office; "RO" for Resident
Office; and "PO" for Project Office. Codes
following the "G" typically are not used for Navy
projects.
Use the "S" classification only in SD-11 Closeout
Submittals. The "S" following a submittal item
indicates that the submittal is required for the
Sustainability eNotebook to fulfill federally
mandated sustainable requirements in accordance with
Section 01 33 29 SUSTAINABILITY REPORTING.
Submittal items not designated with a "G" are
considered as being for information only for Army
projects and for Contractor Quality Control approval
for Navy projects.
***************************************************************************
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are [for Contractor Quality Control
approval.][for information only. When used, a designation following the "G"
designation identifies the office that will review the submittal for the
Government.] Submittals with an "S" are for inclusion in the Sustainability
eNotebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-02 Shop Drawings
UPS Drawings; G[, [_____]]
UPS Installation; G[, [_____]]
SD-03 Product Data
UPS Module; G[, [_____]]
Submittal shall include manufacturer's information for each
component, device, and accessory provided with the transformer.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 33 53.00 20 Page 6
Factory Testing
UPS System
Energy Star label for battery charging systems and AC-DC/AC-AC
power supply products; S
***************************************************************************
NOTE: Delete submittal for spare parts on Navy
projects.
***************************************************************************
[UPS Spare Parts; G[, [_____]]]
SD-06 Test Reports
Work Plan; G[, [_____]]
Factory Test Plan; G[, [_____]]
Performance Test Plan; G[, [_____]]
Factory Tests; G[, [_____]]
Performance Tests Report; G[, [_____]]
Factory Tests Report; G[, [_____]]
SD-09 Manufacturer's Field Reports
Initial Inspection and Tests; G[, [_____]]
Performance Tests; G[, [_____]]
SD-10 Operation and Maintenance Data
UPS Operation and Maintenance, Data Package 5; G[, [_____]]
Submit operation and maintenance data in accordance with Section
01 78 23 OPERATION AND MAINTENANCE DATA and as specified herein.
SD-11 Closeout Submittals
Installation
1.5 PERFORMANCE REQUIREMENTS
1.5.1 Normal Operation
The UPS module rectifier/charger shall convert the incoming ac input power
to dc power for the inverter and for float charging the battery. The
inverter shall supply ac power to the critical load continuously. Inverter
output shall be synchronized with the bypass ac power source, provided that
the bypass ac power source is within the specified voltage and frequency
range.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 33 53.00 20 Page 7
1.5.2 Emergency Operation (Loss or deviation of AC Input Power)
Whenever the ac input power source deviates from the specified tolerances or
fails completely, the inverter shall draw its power from the battery system
and shall supply AC power to the critical load without any interruption or
switching. The battery shall continue to supply power to the inverter for
the specified protection time or until return of ac input source. At the
same time, an alarm shall sound to alert operating personnel and a trouble
signal shall be sent over the communication network, allowing startup of a
secondary power source or orderly shutdown of the critical load.
1.5.3 Return of AC Input Power Source
When stable ac input power source returns the rectifier/charger shall resume
operation and shall simultaneously supply the inverter with dc power and
recharge the battery. This shall be an automatic function and shall cause
no disturbance to the critical load.
1.5.4 Failure of AC Input Power to Return
Should the ac input power fail to return before the battery voltage reaches
the discharge limit, the UPS system shall disconnect from the critical load
to safeguard the battery.
1.5.5 Transfer to Bypass AC Power Source
When the UPS controller senses an overload or degradation of the inverter
output, the bypass switch shall automatically transfer the critical load
from the inverter output to the bypass ac power source without an
interruption of power. If the bypass ac power source is outside of
specified tolerance limits, the UPS and the critical load shall shut down.
1.5.6 Retransfer to Inverter
The static bypass switch shall be capable of automatically retransferring
the load back to the inverter output after the inverter output has returned
to normal conditions. Retransfer shall only occur if the two sources are
synchronized.
1.5.7 UPS Bypass Maintenance
Manual closure of the maintenance bypass switch shall transfer the critical
load from the inverter output to the bypass ac power source without
disturbing the critical load bus. UPS module shall be capable of manual
return to normal operation after completion of maintenance.
1.5.8 Battery Maintenance
The battery protective device shall provide the means of disconnecting the
battery from the rectifier/charger and inverter for maintenance. The UPS
module shall continue to function and meet the performance criteria
specified except for the battery back-up time function.
1.6 QUALITY ASSURANCE
The manufacturer shall have a documented quality assurance program
including:
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 33 53.00 20 Page 8
a. Inspections of incoming parts, modular assemblies and final product.
b. Final test procedure for the product including proof of performance
specifications.
c. On-site test procedure shall include an inspection of controls and
indicators after installation of the equipment.
d. ISO 9001 quality certification.
1.6.1 UPS Drawings
Detail drawings consisting of a complete list of equipment and materials,
manufacturer's descriptive and technical literature, battery sizing
calculations per IEEE 485, installation instructions, single-line diagrams,
ladder-type schematic diagrams, elevations, layout drawings, and details
required to demonstrate that the system has been coordinated and will
function properly as a unit.
1.6.2 UPS Installation
Include wiring diagrams and installation details of equipment indicating
proposed location, layout and arrangement, control panels, accessories,
piping, ductwork, and other items that must be shown to ensure a coordinated
installation. Wiring diagrams shall identify circuit terminals and indicate
the internal wiring for each item of equipment and the interconnection
between each item of equipment. Drawings shall indicate adequate clearance
for operation, maintenance, and replacement of operating equipment devices.
Submittals shall include the nameplate data, size, and capacity. Submittals
shall also include applicable federal, military, industry, and technical
society publication references.
1.6.3 Work Plan
Submit [6][_____] copies of schedules of dates for factory tests,
installation, field tests, and operator training for the UPS system.
Furnish a list of instrumentation equipment for factory and field test
reports.
1.6.4 Factory Test Plan
Submit [6][_____] copies of factory test plans and procedures at least
[21][_____] calendar days prior to the tests being conducted. Provide
detailed description of test procedures, including test equipment and
setups, to be used to ensure the UPS meets the performance specification and
explain the test methods to be used. As a minimum, the test procedures
shall include the test required under the paragraph entitled "Factory
Testing."
1.6.5 Performance Test Plan
Submit [6][_____] copies of test plans and procedures at least [15][_____]
calendar days prior to the start of field tests. Provide detailed
description and dates and times scheduled for performance of tests, and
detailed description of test procedures, including test equipment (list make
and model and provide functional description of the test instruments and
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 33 53.00 20 Page 9
accessories) and setups of the tests to be conducted to ensure the UPS meets
the performance specification. Explain the test methods to be used. As a
minimum, the test procedures shall include the tests required under the
paragraph entitled "Performance Tests."
1.6.6 Factory Tests Report
Submit [6][_____] copies of factory test report within [45][_____] calendar
days after completion of tests. Receive approval of test prior to shipping
unit. Factory test reports shall be signed by an official authorized to
certify on behalf of the UPS manufacturer of that the system meets specified
requirements in accordance with the requirements set forth in paragraph
entitled "Factory Testing". Test reports in shall be in booklet form
tabulating factory tests and measurements performed, upon completion and
testing of the installed system. Reports shall state the Contractor's name
and address, the name of the project and location, and list the specific
requirements which are being certified.
1.6.7 Performance Tests Report
Submit report of test results as specified by paragraph entitled
"Performance Tests" within [15][_____] calendar days after completion of
tests. Field test reports shall be signed by an official authorized to
certify on behalf of the UPS manufacturer that the system meets specified
requirements in accordance with the requirements set forth in paragraph
entitled "Performance Tests". Test reports in shall be in booklet form
tabulating factory tests and measurements performed, upon completion and
testing of the installed system. Reports shall state the Contractor's name
and address, the name of the project and location, and list the specific
requirements which are being certified.
1.6.8 Regulatory Requirements
In each of the publications referred to herein, consider the advisory
provisions to be mandatory, as though the word, "shall" had been substituted
for "should" wherever it appears. Interpret references in these
publications to the "authority having jurisdiction," or words of similar
meaning, to mean the Contracting Officer. Equipment, materials,
installation, and workmanship shall be in accordance with the mandatory and
advisory provisions of NFPA 70 unless more stringent requirements are
specified or indicated.
1.6.8.1 Reference Standard Compliance
Where equipment or materials are specified to conform to industry and
technical society reference standards of the organizations such as American
National Standards Institute (ANSI), American Society for Testing and
Materials (ASTM), National Electrical Manufacturers Association (NEMA),
Underwriters Laboratories (UL), and Association of Edison Illuminating
Companies (AEIC), submit proof of such compliance. The label or listing by
the specified organization will be acceptable evidence of compliance.
1.6.8.2 Independent Testing Organization Certificate
In lieu of the label or listing, submit a certificate from an independent
testing organization, competent to perform testing, and approved by the
Contracting Officer. The certificate shall state that the item has been
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 33 53.00 20 Page 10
tested in accordance with the specified organization's test methods and that
the item complies with the specified organization's reference standard.
1.6.9 Standard Products
Provide materials and equipment that are products of manufacturers regularly
engaged in the production of such products which are of equal material,
design and workmanship. Products shall have been in satisfactory commercial
or industrial use for 2 years prior to bid opening. The 2-year period shall
include applications of equipment and materials under similar circumstances
and of similar size. The product shall have been on sale on the commercial
market through advertisements, manufacturers' catalogs, or brochures during
the 2-year period. Where two or more items of the same class of equipment
are required, these items shall be products of a single manufacturer;
however, the component parts of the item need not be the products of the
same manufacturer unless stated in this section. Equipment shall be
supported by a service organization that is, in the opinion of the
Contracting Officer, reasonably convenient to the site.
1.6.9.1 Alternative Qualifications
Products having less than a 2-year field service record will be acceptable
if a certified record of satisfactory field operation for not less than 6000
hours, exclusive of the manufacturers' factory or laboratory tests, is
furnished.
1.6.9.2 Material and Equipment Manufacturing Date
Products manufactured more than 2 years prior to date of delivery to site
shall not be used, unless specified otherwise.
1.7 DELIVERY AND STORAGE
Equipment placed in storage shall be protected from humidity and temperature
variations, moisture, water intrusion, dirt, dust, or other contaminants.
In harsh environments where temperatures exceed non-operational parameters
established within this specification, the equipment storage facility shall
be environmentally controlled to ensure temperature parameters are within
equipment specification. Documentation of same shall be provided to the
Government when storage is implemented.
1.8 PROJECT/SITE CONDITIONS
***************************************************************************
NOTE: This paragraph with subparagraphs is used by
the Army. Delete for other projects.
***************************************************************************
1.8.1 Environmental Conditions
***************************************************************************
NOTE: Designer must show approximate elevation
above sea level for project location if it exceeds
1,000 meters (3,300 feet). UPS system including
batteries must be derated if 50 degrees C (122
degrees F) operating temperature is required.
***************************************************************************
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 33 53.00 20 Page 11
The UPS and battery system shall be capable of withstanding any combination
of the following external environmental conditions without mechanical or
electrical damage or degradation of operating characteristics.
a. Operating altitude: Sea level to 1,000 meters (3,300 ft). (Systems
applied at higher altitudes shall be derated in accordance with the
manufacturer's instructions).
b. Non-operating altitude: Sea level to 11,000 meters (36,000 ft).
c. Operating ambient temperature range: 0 to 40 degrees C (32 to 104
degrees F). Range for batteries is 10 to 30 degrees C (50 to 86
degrees F).
d. Non-operating and storage ambient temperature range: Minus 20 to plus
50 degrees C (Minus 4 to plus 122 degrees F).
e. Operating relative humidity: 0 to 95 percent, without condensation.
1.8.2 Sound Pressure Levels
***************************************************************************
NOTE: UPS modules rated up to 125 kVA should have a
dB rating of 65 dBA or lower at 1 meter (39 inches).
UPS modules rated above 125 kVA should have a dBA
rating of 75 dB or lower at 1.5 meters (5 feet).
***************************************************************************
Sound pressure levels produced by the UPS, when operating under full rated
load, at a distance of[ 1.5 meters (5 feet)][ 1 meter (39 inches)][_____] in
any direction from the perimeter of the unit, shall not exceed
[75][65][_____] dB as measured on the A scale of a Type 1 sound level meter
at slow response conforming to ASA S1.4.
1.8.3 Verification of Dimensions
The Contractor shall become familiar with details of the work, verify
dimensions in the field, and shall advise the Contracting Officer of any
discrepancy before performing the work.
1.9 SPECIAL TOOLS
Provide one set of special tools, calibration devices, and instruments
required for operation, calibration, and maintenance of the equipment.
1.10 OPERATION AND MAINTENANCE MANUALS
1.10.1 Additions to UPS Operation and Maintenance Manuals
In addition to requirements of Data Package 5, include the followings on the
actual UPS system provided:
a. An outline drawing, front, top, and side views.
b. Prices for spare parts and supply list.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 33 53.00 20 Page 12
c. Routine and field acceptance test reports.
d. Date of Purchase.
e. Corrective maintenance procedures.
f. Test measurement levels with specific test points.
[1.10.2 Spare Parts
***************************************************************************
NOTE: Do not provide spare parts for Navy projects.
***************************************************************************
Furnish the following spare parts, of the same material and workmanship,
meeting the same requirements, and interchangeable with the corresponding
original parts.
a. Fuses: Two of each type and rating.
b. Circuit boards: One circuit board for each critical circuit.
c. Air Filters: One set of filters.
]1.11 WARRANTY
The equipment items shall be supported by service organizations which are
reasonably convenient to the equipment installation in order to render
satisfactory service to the equipment on a regular and emergency basis
during the warranty period of the contract.
PART 2 PRODUCTS
2.1 UPS SYSTEM DESCRIPTION
***************************************************************************
NOTE: Connect alternate power source to
bypass/maintenance bypass for systems requiring dual
input.
***************************************************************************
The UPS system shall conform to UL 1778 and shall consist of UPS module,
battery system, battery protective device, static bypass transfer switch,
controls and monitoring. Input ac power shall be connected to the normal
source ac input of the UPS module. [Alternate power source shall be
connected to bypass/maintenance bypass. ]The battery shall be connected to
the dc input of the UPS module through the battery protective device. The ac
output of the UPS system shall be connected to the critical loads.
Provide Energy Star labeled battery charging systems and AC-DC/AC-AC power
supplies. Provide proof of Energy Star label for battery charging systems
and AC-DC/AC-AC power supply products.
2.1.1 Semiconductor Fusing
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 33 53.00 20 Page 13
Power semiconductors shall be fused with fast-acting fuses to prevent
cascaded or sequential semiconductor failures. Indicator lamp or display
panel denoting blown fuse conditions shall be readily observable by the
operator without removing panels or opening cabinet doors.
2.1.2 Control Power
***************************************************************************
NOTE: Most manufacturers do not have input and
output control power source feature as standard. Use
for systems requiring high reliability.
***************************************************************************
Provide dual control power supplies. [Control power shall be derived from
two sources, input and output, with automatic selective control. ] The
control power circuit shall have suitable protection, appropriately marked
and located in the immediate vicinity of the input protective device.
2.1.3 EMI/RFI Protection
The components and the system shall be designed to minimize the emission of
electromagnetic waves that may cause interference with other equipment.
2.1.4 Internal Wiring
Wiring practices, materials, and coding shall be in accordance with the
requirements of NFPA 70, OSHA, and other applicable standards. Wire runs
shall be protected in a manner which separates power and control wiring.
Control wiring shall be minimum No. 16 AWG extra-flexible stranded copper.
Logic-circuit wiring may be smaller. Ribbon cables shall be minimum No. 22
AWG. Control wiring shall have permanently attached wire numbers.
2.1.5 Internal Assembly
The printed circuit board (PCB) subassemblies shall be mounted in pull-out
and/or swing-out trays where feasible. Cable connections to the trays shall
be sufficiently long to allow easy access to all components. Where not
feasible to mount PCB subassemblies in pull-out or swing-out trays, they
shall be firmly mounted inside the enclosure. Every PCB subassembly shall be
monitored. Self-test and diagnostic circuitry shall be included in the
logic circuits such that a fault can be isolated down to the PCB subassembly
level.
2.1.6 Cabinets
UPS system shall be installed in cabinets of heavy-duty structure meeting
the NEMA PE 1 standards for floor mounting. UPS module cabinet shall be
structurally adequate for forklift handling or lifting. Removable lifting
eyes shall be provided on top of each cabinet. UPS module cabinet shall have
hinged and lockable doors on the front only, with assemblies and components
accessible from the front. Doors shall be [key] lockable. Operating
controls shall be located outside the locked doors. Input, output, and
battery cables shall be installed through the top or bottom of the cabinet.
2.1.6.1 Cabinet Finish
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 33 53.00 20 Page 14
Equipment cabinet shall be cleaned, primed and painted in the manufacturer's
standard colors, in accordance with accepted industry standards. Cabinets
shall be labeled in accordance with NFPA 70 for arc flash hazard with
warning sign reading: "Warning-Potential Arc Flash Hazard. Appropriate PPE
and Tools Required when working on this equipment" or similar wording.
2.1.6.2 Live Parts (300 Volts and Above)
Live parts (300 volts and above) that are exposed when front access doors
are open shall be adequately protected or covered to minimize the chance of
accidental contact.
2.1.6.3 Drawout Assemblies
***************************************************************************
NOTE: Drawout applies to large units for removing
inverter modules, static switches assemblies, etc.
Delete for units smaller than 500 kVA.
***************************************************************************
Drawout assemblies weighing 23 kg (50 lbs)or more shall be provided with a
means of lifting, either an overhead device or a hoisting device.
2.1.7 Safety
UPS shall be equipped with instruction plates including warnings and
cautions, suitably located, and describing any special or important
procedures to be followed in operating and servicing the equipment. The
control panel display shall also provide warning messages prior to
performing a critical function.
2.1.8 UPS System Load Profile
***************************************************************************
NOTE: Refer to UFC 3-520-01, "Interior Electrical
Systems" for additional information.
***************************************************************************
The UPS system shall be compatible with the load characteristics defined in
the LOAD PROFILE below and load configuration. Compensation for UPS/load
interaction problems resulting from nonlinear loads or transformer and motor
inrush shall be provided.
LOAD PROFILE
Type of load: [data processing equipment][main frame][chilled water
pump][_____].
Size of load: [_____][kVA][kW], [_____]horsepower, [_____]voltage,
[[_____]amperage].
Switching pattern: [unswitched][cycled daily][cycled hourly][operated by
thermostat][building management system control][_____].
Transient characteristics: inrush current magnitude of [_____] times steady
state rms current for duration of [_____] cycle; range of power factor
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 33 53.00 20 Page 15
variation of [_____] to [_____] [lagging][leading]; voltage dip of
[_____] percent.
Steady-state characteristics: [0.8 lagging][0.9 lagging][1.0][_____] power
factor.
Special factors: [harmonic characteristics - Total Harmonic Distortion
[_____] percent][high elevation][nonstandard input and output
voltages][_____].
2.2 UPS SYSTEM RATINGS
Unless stated otherwise, the parameters listed are under full output load at
[0.8][0.9] power factor, with batteries fully charged and floating on the dc
bus and with nominal input voltage.
2.2.1 System Capacity
***************************************************************************
NOTE: Typical capacities in kVA are 10, 15, 20, 30,
40, 50, 80, 100, 125, 150, 225, 250, 300, 500 and
750.
***************************************************************************
[_____] kVA, [_____] kW.
2.2.2 Battery Capacity
***************************************************************************
NOTE: Typical battery discharge times are 5, 10, 12,
15, and 30 minutes. If no emergency source is
available, longer battery discharge time may be
required.
***************************************************************************
Discharge time to end voltage: [15][_____] minutes, at 25 degrees C (77
degrees F). End voltage at full discharge shall be 1.67 volts per cell.
Battery shall be capable of delivering 150 percent of full rated UPS load at
initial start-up.
2.2.3 Static Switch
***************************************************************************
NOTE: The static switch or static disconnect is a
solid-state disconnect device used to apply or
disconnect ac power. The interrupting capacity
requirements must be determined for each project
distribution system. Typical interrupting capacities
are 30,000 AIC and 50,000 AIC. Interrupting
capacities are normally found on the single line
diagram or in the short circuit calculations provided
with the drawings.
***************************************************************************
[_____] amperes symmetrical interrupting capacity.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 33 53.00 20 Page 16
2.2.4 Module Bus Bracing
Braced for [_____] amperes symmetrical interrupting capacity.
2.2.5 AC Input
***************************************************************************
NOTE: Total harmonic current distortion (THD) is
usually specified as follows: modules 15-224 kVA: 10
percent; modules above 225 kVA: 5 percent. If UPS
will be supplied from a generator, the generator
capacity must be at least twice the UPS capacity if
THD exceeds 5 percent. Some of the manufacturers can
provide units with the above THD without input
filters while others require optional input filters
to achieve the desired THD. Delete transformer
inrush paragraph if input isolation transformer is
not required. Use 50 Hz for units shipped or
purchased in Europe. Before specifying them, be
certain units having 60 Hz input with 50 Hz output
and units having 50 Hz input with 60 Hz output are
available in the size specified. Be certain that
units having foreign voltages are clearly specified
since they are not standard for U.S. manufactured
products. For transformer sub-cycle inrush,
selecting a lower value like 6 or 4 in lieu of the
range (4 to 8) is better for coordination of UPS
feeder protection but might add some cost and extra
components. If the range is selected than upstream
breaker should have instantaneous current adjustment.
***************************************************************************
a. Voltage [208][240][480][_____] volts line-to-line.
***************************************************************************
NOTE: Some of the smaller UPS units usually <100 kVA
are designed for 3 phase, 4 wire configuration only.
***************************************************************************
b. Number of phases: 3-phase, 3 [4]-wire, plus ground.
c. Voltage Range: Plus 10 percent, minus 20 percent, without affecting
battery float voltage or output voltage.
d. Frequency: [50][60] Hz, plus or minus 5 percent.
e. Power walk-in: 20 percent to 100 percent over 10 to 20 seconds.
f. Total harmonic current distortion (THD) reflected into the primary
line: [5][10] percent maximum.
[g. Transformer sub-cycle inrush: [4 to 8][_____] times full load rating.
]h. Input surge protection: per IEEE C62.41.1 and IEEE C62.41.2.
i. Input power factor: Lagging from 1-100 percent load.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 33 53.00 20 Page 17
2.2.6 AC Output
***************************************************************************
NOTE: If the output voltage is 120/208 V and the
same voltage is not available for the static bypass
and maintenance bypass, a transformer will be
required in the bypass distribution system.
***************************************************************************
a. Voltage [208][240][480][_____] volts line-to-line, [120][277][_____]
volts line-to-neutral.
b. Number of phases: 3-phase, 4-wire, plus ground.
c. Voltage regulation:
(1) Balanced load: Plus or minus 1.0 percent.
(2) 50 percent load imbalance, phase-to-phase: Plus or minus 2 percent.
(3) No-load voltage modulation: Plus or minus 1 percent.
(4) Voltage drift: Plus or minus 1 percent over any 30 day interval (or
length of test) at stated ambient conditions.
d. Voltage adjustment: Plus or minus 5 percent manually.
e. Frequency: [50][60] Hz.
f. Frequency regulation: Plus or minus 0.1 percent.
g. Frequency drift: Plus or minus 0.1 percent over any 24 hour interval
(or length of test) at stated ambient conditions when on internal
oscillator.
h. Harmonic content (RMS voltage): Voltage THD shall be a maximum of 2
percent with 100 percent linear load and 5 percent with 100 percent
nonlinear load and a crest factor of less than 3 to 1.
i. Load power factor operating range: 1.0 to 0.8 lagging.
j. Phase displacement:
(1) Balanced load: Plus or minus 1 degree of bypass input.
(2) 50 percent load imbalance phase-to-phase: Plus or minus 3
degrees of bypass input.
k. Wave-form deviation factor: 5 percent at no load.
l. Overload capability (at full voltage) (excluding battery):
(1) 125 percent load for 10 minutes.
(2) 150 percent load for 60 seconds.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 33 53.00 20 Page 18
(3) 300 percent load for one cycle after which it shall be current
limited to 150 percent until fault is cleared or UPS goes to
bypass.
2.2.7 Transient Response
2.2.7.1 Voltage Transients
a. 100 percent load step: Plus or minus 5 percent.
b. Loss or return of ac input: Plus or minus 1 percent.
c. Automatic transfer of load from UPS to bypass: Plus or minus 4
percent.
d. Manual retransfer of load from bypass to UPS: Plus or minus 4
percent.
e. Response time: Recovery to 99 percent steady-state condition within 20
milliseconds after any of the above transients.
2.2.7.2 Frequency
a. Transients: Plus or minus 0.6 Hz maximum.
b. Slew Rate: 1.0 Hz maximum per second.
2.2.8 Efficiency
***************************************************************************
NOTE: Minimum efficiencies at full load are as
follows:
UPS capacity Module
10 kVA to 125 kVA 88 Percent
Above 125 kVA 90 Percent
Above 300 kVA 92 Percent
A higher efficiency UPS will save money on
electricity bills on the long run and will pay off to
spend more money up front if the funds are available.
***************************************************************************
Minimum Efficiency: [90][_____] percent at full load kW and [90] [_____]
percent at 50 percent load.
2.3 UPS MODULE
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 33 53.00 20 Page 19
***************************************************************************
NOTE: Delete input isolation transformer if not
required.
***************************************************************************
2.3.1 General Description
UPS module shall consist of a rectifier/charger unit and a 3-phase inverter
unit with their associated transformers, synchronizing equipment, protective
devices, surge suppression, [input isolation transformer,] and accessories
as required for operation.
2.3.1.1 Interchangeability
The subassemblies in one UPS module shall be interchangeable with the
corresponding modules within the same UPS, and from one UPS system to
another of identical systems.
2.3.2 Rectifier/Charger Unit
Rectifier/charger unit shall be solid state and shall provide regulated
direct current to the dc bus, supplying power to the inverter and charging
the battery plant.
2.3.2.1 Input Protective Device
***************************************************************************
NOTE: Calculate/verify AIC on the single line
diagram at input of the UPS.
***************************************************************************
Rectifier/charger unit shall be provided with an input protective device.
The protective device shall be sized to accept simultaneously the full-rated
load and the battery recharge current. The protective device shall be
capable of shunt tripping and shall have [_____] amperes symmetrical
interrupting rating. The protective device shall have
provision for locking in the "off" position.
2.3.2.2 Surge Protection
A surge suppression device shall be installed at the UPS input to protect
against lightning and switching surges. Internal components shall be
protected from surges that enter at each ac input connection including main
input, static bypass transfer switch, [and maintenance bypass/isolation
switch]. Surge suppressors shall protect internal components according to
IEEE C62.41.1 and IEEE C62.41.2, Category B. Surge suppressors shall be UL
1449 approved to fail in "safe" mode.
[2.3.2.3 Input Isolation Transformer
***************************************************************************
NOTE: Delete the input isolation transformer if it's
not required. Isolation transformers provide
isolation of line induced EMI, common mode noise and
dc offsets. Some of the UPS manufacturers require a
separate cabinet for the transformer.
***************************************************************************
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 33 53.00 20 Page 20
A dry-type, isolated-winding power transformer shall be used for the
rectifier unit. The transformer's hottest spot winding temperature shall not
exceed the temperature limit of the transformer insulation material when
operating at full load. The transformer insulation shall be Class H, 150
degrees C rise. Transformer connections shall be accessible from the front.
Transformer cabinet, if required, shall match the UPS cabinet and attach to
it.
]2.3.2.4 Power Walk-In
Rectifier/charger unit shall be protected by a power walk-in feature such
that when ac power is returned to the ac input bus, the total initial power
requirement will not exceed 20 percent of the rated full load current. This
demand shall increase gradually to 100 percent of the rated full load
current plus the battery charging current over the specified time interval.
2.3.2.5 Sizing
Rectifier/charger unit shall be sized for the following two simultaneous
operating conditions:
a. Supplying the full rated load current to the inverter.
b. Recharging a fully-discharged battery to 95 percent of rated ampere-
hour capacity within ten times the discharge time after normal ac power
is restored.
2.3.2.6 Battery Charging Current
***************************************************************************
NOTE: Delete second step current limiting if the UPS
system will not be supplied with ac power from an
auxiliary generator system or if the generator has
been sized to accommodate the recharge current of the
battery. Second step current limit is usually found
in larger units of 150kVA and above.
***************************************************************************
a. Primary current limiting: Battery-charging current shall be voltage
regulated and current limited. The battery-charging current limit shall
be separately adjustable from 2 percent to 25 percent of the maximum
discharge current. After the battery is recharged, the
rectifier/charger unit shall maintain the battery at full float charge
until the next operation under input power failure. Battery charger
shall be capable of providing equalizing charge to the battery.
[b. Second step current limiting: The rectifier/charger unit shall also
have a second-step battery current limit. This second-step current
limit shall sense actual battery current and reduce the input power
demand for battery recharging to 50 percent (adjustable from 30 percent
to 70 percent) of the normal rate without affecting the system's
ability to supply full-rated power to the connected load. The second-
step current-limit circuit shall be activated by a dry contact signal
from the generator set controls and shall prevent normal rate battery
recharging until utility power is restored.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 33 53.00 20 Page 21
]2.3.2.7 DC Ripple
Rectifier/charger unit shall minimize ripple current and voltage supplied to
the battery; the ripple current into the battery shall not exceed 3 percent
RMS of the inverter input rated current; the ripple voltage into the battery
shall not exceed 2 percent RMS of the float voltage.
2.3.2.8 DC Voltage Adjustment
Rectifier/charger unit shall have manual means for adjusting dc voltage for
battery equalization, to provide voltage within plus 10 percent of nominal
float voltage.
2.3.2.9 Battery Isolation Protective Device
Module shall have a dc protective device to isolate the module from the
battery system. The protective device size and interrupting rating shall be
as required by system capacity and shall incorporate a shunt trip as
required by circuit design. The protective device shall have provision for
locking in the "off" position.
2.3.3 Inverter Unit
Inverter unit shall be a solid-state device deriving its power from the dc
bus (rectifier or battery source) and providing ac power within specified
limits to the critical load. Inverter shall utilize microprocessor
controlled solid state Pulse Width Modulation (PWM) controlled IGBT power
transistor technology to shape the ac output.
2.3.3.1 Output Overload
The inverter shall be able to sustain an overload as specified across its
output terminals. The inverter shall not shut off, but shall continue to
operate within rated parameters, with inverse-time overload shutdown
protection. If the overload condition persists beyond the rated parameters
of the inverter, the inverter shall current limit, load shall be transferred
to the bypass source, and the inverter shall disconnect automatically from
the critical load bus.
If the bypass source is not available and the overload/fault condition
continues, the inverter shall current limit for a limited time as determined
by the manufacturer and shall shut down to protect the internal components.
2.3.3.2 Output Frequency Control
The inverter shall normally operate in phase-lock and synchronism with the
bypass source. When the bypass source frequency deviates by more than ±0.5
Hz, the internal frequency oscillator shall automatically take control and
become the new frequency reference. Upon restoration of the bypass source
within the required tolerance, the inverter shall synchronize back with that
source at a slew rate not exceeding the specified rate. The oscillator shall
be temperature compensated and shall be manually adjustable.
2.3.3.3 Output Protective Device
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 33 53.00 20 Page 22
The output protective device shall be capable of shunt tripping or opening
on an applied control signal and shall have the proper frame size and trip
rating to supply overload current as specified. External output protective
device shall have provision for locking in the "off" position. The inverter
output protective device shall work in conjunction with the bypass
protective device for both manual and automatic load transfers to and from
bypass power.
[2.3.3.4 Output Transformer
***************************************************************************
NOTE: Delete the output transformer unless isolation
is required or the design output voltage is different
then the normal UPS output voltage. Some of the UPS
manufacturers require a separate cabinet for the
transformer.
***************************************************************************
The inverter output transformer shall be similar to the input transformer
and shall be capable of handling up to [K-13][_____] nonlinear loads as
described in IEEE C57.110.
]2.3.4 External Protection
UPS module shall have built-in self-protection against undervoltage,
overvoltage, overcurrent and surges introduced on the ac input source and/or
the bypass source. The UPS shall also have built-in self-protection against
overvoltage and voltage surges introduced at the output terminals by
paralleled sources, load switching, or circuit breaker operation in the
critical load distribution system.
2.3.5 Internal Protection
UPS module shall be self-protected against overcurrent, sudden changes in
output load and short circuits at the output terminals. UPS module shall be
provided with output reverse power detection which shall cause the module to
be disconnected from the critical load bus when output reverse power is
present. UPS module shall have built-in protection against permanent damage
to itself and the connected load for predictable types of failure within
itself and the connected load. At the end of battery discharge limit, the
module shall shut down without damage to internal components.
2.4 STATIC BYPASS TRANSFER CIRCUIT
A static bypass transfer circuit shall be provided as an integral part of
the UPS and shall consist of a static switch, made up of two reverse-
paralleled SCRs (silicon-controlled rectifiers) per phase conductor, and a
bypass protective device or bypass switch, made up of a contactor or motor
operated circuit breaker. The bypass protective device shall be in parallel
with the static switch. The inverter output protective device shall
disconnect and isolate the inverter from the bypass transfer circuit.
The control logic shall contain an automatic transfer circuit that senses
the status of the inverter logic signals and alarm conditions and provides
an uninterrupted transfer of the load to the bypass ac power source, without
exceeding the transient limits specified herein, when a malfunction occurs
in the UPS or when an external overload condition occurs. The power section
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 33 53.00 20 Page 23
of the static bypass transfer circuit shall be provided as a plug-in type
assembly to facilitate maintenance. The static bypass transfer circuit shall
be used to connect the input bypass ac power source to the critical load
when required, and shall have the following features:
2.4.1 Uninterrupted Transfer
The static bypass transfer switch shall automatically cause the bypass ac
power source to assume the critical load without interruption when the
bypass control logic senses one of the following conditions and the UPS
inverter output is synchronized to the bypass ac power source:
a. Inverter overload exceeds unit's rating.
b. Battery protection period is expired and bypass is available.
c. System failure.
d. Inverter output undervoltage or overvoltage.
2.4.2 Interrupted Transfer
If an overload occurs and the UPS inverter output is not synchronized to the
bypass ac power source, the UPS inverter output shall current-limit for 200
milliseconds minimum. The inverter shall then turn off and an interrupted
transfer to the bypass ac power source shall be made.
If the bypass ac power source is beyond the conditions stated below, an
interrupted transfer shall be made upon detection of a fault condition:
a. Bypass voltage greater than plus or minus 10 percent from the UPS rated
output voltage.
b. Bypass frequency greater than plus or minus 0.5 Hz from the UPS rated
output frequency.
c. Phase differential of ac bypass voltage to UPS output voltage greater
than plus or minus 3 degrees.
2.4.3 Manual Transfer
It shall be possible to make a manually-initiated static transfer from the
system status and control panel. The transfer shall be make-before-break
utilizing the bypass switch.
2.4.4 Automatic Uninterrupted Forward Transfer
The static bypass transfer switch shall automatically forward transfer,
without interruption after the UPS inverter is turned "on", or after an
instantaneous overload-induced reverse transfer has occurred and the load
current has returned to less than the unit's 100 percent rating.
2.4.5 Forced Transfer
The control logic circuitry shall provide the means of making a forced or
reverse transfer of the static bypass transfer circuit on an interrupted
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 33 53.00 20 Page 24
basis. Minimum interruption shall be 200 milliseconds when the UPS inverter
is not synchronized to the bypass ac power source.
2.4.6 Overload Ratings
***************************************************************************
NOTE: Select 'one minute' for greater than 150kVA;
select '30 seconds' for 10-150kVA.
***************************************************************************
The static bypass transfer switch shall withstand the following overload
conditions:
a. 1000 percent of UPS output rating for one cycle.
b. 150 percent of UPS output rating for [one minute][30 seconds].
c. 125 percent of UPS output rating for 10 minutes.
2.4.7 Static Switch Disconnect
***************************************************************************
NOTE: Delete if the static switch is of the
draw-out type.
***************************************************************************
A static switch disconnect shall be incorporated to isolate the static
bypass transfer switch assembly so it can be removed for servicing. The
switch shall be equipped with auxiliary contacts.
2.5 MAINTENANCE BYPASS SWITCH
2.5.1 General
***************************************************************************
NOTE: Multi-module UPS systems require a UPS
maintenance bypass that should be incorporated into
the UPS output switchgear.
There are two methods of installing a maintenance
bypass switch. One is a cabinet that bolts to the
UPS module and becomes part of the line-up or is
integral to the UPS module cabinet. The second is
physically isolated from the UPS module in a separate
cabinet mounted on the wall or free-standing floor-
mounted. Choose the appropriate method based on
project conditions and requirements.
***************************************************************************
A maintenance bypass switch shall be provided [as an integral part of the
UPS and located within the UPS module or in a matching cabinet adjacent to
the UPS cabinet][in a wall-mounted enclosure][in a free-standing floor-
mounted enclosure]. The maintenance bypass switch shall provide the
capability to continuously support the critical load from the bypass AC
power source while the UPS is isolated for maintenance. The maintenance
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 33 53.00 20 Page 25
bypass switch shall be housed [in an isolated compartment inside the UPS
cabinet][in a separate cabinet or enclosure] in such a way that service
personnel will not be exposed to electrically live parts while maintaining
the equipment. Switch shall contain a maintenance bypass protective device
and a module isolation protective device.
2.5.2 Load Transfer
The maintenance bypass switch shall provide the capability of transferring
the critical load from the UPS static bypass transfer switch to maintenance
bypass and then back to the UPS static bypass transfer switch with no
interruption to the critical load.
[2.5.3 Load Bank Protection Device
***************************************************************************
NOTE: Delete if the ability to load bank test the
UPS system is not required.
***************************************************************************
A load bank protective device shall be provided to allow the UPS system to
be tested using a portable load bank. The load bank protective device shall
be connected on the line side of the maintenance bypass switch isolation
protective device.
][2.5.4 [Voltage Matching][Isolation Transformer]
***************************************************************************
NOTE: Delete if the input and output voltages are
the same and an isolation transformer is not
required.
***************************************************************************
The maintenance bypass cabinet shall contain [a voltage matching
transformer][an isolation transformer] as required to match the output
voltage requirements.
]2.6 MODULE CONTROL PANEL
The UPS module shall be provided with a control/indicator display panel. The
display panel shall be on the front of the UPS module. Controls, meters,
alarms and indicators for operation of the UPS module shall be on this
panel. The display panel shall be menu driven for browsing all the screens.
2.6.1 Module Meters
2.6.1.1 Monitored Functions
The following functions shall be monitored and displayed:
a. Input voltage, phase-to-phase (all three phases).
b. Input current, all three phases.
c. Input frequency.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 33 53.00 20 Page 26
d. Battery voltage.
e. Battery current (charge/discharge).
f. Output voltage, phase-to-phase and phase-to-neutral (all three phases).
g. Output current, all three phases.
h. Output frequency.
i. Output kilowatts.
j. Elapsed time meter to indicate hours of operation, 6 digits.
k. Bypass voltage, phase-to-phase and phase-to-neutral (all three phases).
l. Output kilovars.
m. Output kilowatt hours, with 15-minute demand attachment.
n. Battery temperature.
o. Output Percentage load.
p. Remaining battery time.
2.6.1.2 Meter Construction
The display panel shall display alphanumeric parameters based on true RMS
metering with 1 percent accuracy (minimum 4 significant digits).
2.6.2 Module Controls
Module shall have the following controls:
a. Lamp test/reset pushbutton.
b. Alarm test/reset pushbutton.
c. Module input protective device trip pushbutton, with guard.
d. Module output protective device trip pushbutton, with guard.
e. Battery protective device trip pushbutton, with guard.
f. Emergency off pushbutton, with guard.
g. DC voltage adjustment potentiometer, with locking guard.
h. Control power off switch.
i. UPS/bypass transfer selector switch.
j. Static bypass transfer switch enable/disable selector switch.
2.6.3 Module Alarm Indicators
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 33 53.00 20 Page 27
***************************************************************************
NOTE: Delete 'input transformer overtemperature' if
input transformer is not provided.
***************************************************************************
Module shall have indicators for the following alarm items. Any one of these
conditions shall turn on an audible alarm and the appropriate summary
indicator. Each new alarm shall register without affecting any previous
alarm.
a. Input ac power source failure.
b. Input protective device open.
c. Input power out of tolerance.
d. Overload.
e. Overload shutdown.
f. DC overvoltage/shutdown.
g. DC ground fault.
h. Low battery.
i. Battery discharged.
j. Battery protective device open.
k. Blower fan failure.
[l. Input transformer overtemperature.
]m. Low battery shutdown.
n. UPS on battery.
o. Equipment overtemperature.
p. Fuse blown (with indication where).
q. Control power failure.
r. Charger off/problem.
s. Inverter fault/off.
t. Emergency power off.
u. External shutdown (remote EPO activated).
v. Critical load on static bypass.
w. Static bypass transfer switch disabled/failure.
x. Inverter output overvoltage.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 33 53.00 20 Page 28
y. Inverter output undervoltage.
z. Inverter output overfrequency.
aa. Inverter output underfrequency.
bb. Bypass source voltage outside limits.
cc. Bypass frequency out of range.
dd. Bypass source to inverter out of synchronization.
ee. Overtemperature shutdown.
ff. Hardware shutdown.
2.6.4 Module Emergency OFF Button
Pressing the emergency off button shall cause the module to be disconnected
from the system, via its input protective device, output protective device,
and battery protective device. The button shall include a protective cover
to prevent unintentional activation.
[2.7 SELF-DIAGNOSTIC CIRCUITS
***************************************************************************
NOTE: Delete if self-diagnostic circuits are not
required. These circuits are normally required in
high reliability applications where it becomes
critical to identify the faulty circuit card in the
shortest time possible. This option is not normally
available in off the shelf UPS units.
***************************************************************************
The control logic shall include status indicators for trouble-shooting the
control circuits. These indicators shall be mounted on the circuit card edge
or face such that they will be visible without repositioning the card, and
shall be labeled with the function name.
][2.8 REMOTE MONITORING PANEL
***************************************************************************
NOTE: Delete if a remote monitoring panel is not
required.
***************************************************************************
A remote monitoring panel shall be provided to monitor system status. The
panel shall be designed for wall mounting near the critical load.
2.8.1 Indicators
Minimum display shall include the following indicators:
a. Load on UPS.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 33 53.00 20 Page 29
b. Load on battery.
c. Load on bypass.
d. Low battery.
e. Summary alarm.
f. New alarm (to alert the operator that a second summary alarm
condition has occurred).
2.8.2 Audible Alarm
Any single indicator shall also turn on the audible alarm. An audible alarm
test/reset button and lamp test/reset button shall be included. This reset
button shall not affect nor reset the alarm on the module.
]2.9 COMMUNICATIONS AND DATA ACQUISITION
***************************************************************************
NOTE: Delete the communication and data options that
are not required. RS-485 port is not supported by
some of the UPS manufacturers.
***************************************************************************
An [RS 232][RS 485] communications and data acquisition port shall be
provided. This port shall allow the system parameters, status, alarm
indication and control panel functions specified to be remotely monitored
and controlled.
Additionally, a second communication port shall be provided for use with the
following:
a. A set of [six][eight] Form C remote alarm contacts rated at 120V, 0.5A,
shall be provided for remote alarm monitoring.
b. Auto-dial modem communication shall be provided to communicate with a
remote modem in case an alarm function is active.
c. A SNMP (Simple Network Management Protocol) adapter shall be provided
to communicate UPS monitoring via a network or direct connection to a
PC.
d. A standard Web Browser adapter shall be provided to remotely view and
monitor UPS functions over the Internet.
All the communication ports and contacts shall be capable of simultaneous
communication.
[2.9.1 Emergency Control Contacts
***************************************************************************
NOTE: Include this paragraph only when the UPS will
be installed in conjunction with an emergency
generator/alternate source.
***************************************************************************
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 33 53.00 20 Page 30
Provide normally open contacts to signal when power is supplied to the UPS
from emergency engine generators or alternate source.
]2.10 TEMPERATURE CONTROL
2.10.1 General
Cabinet and enclosure ventilation shall be adequate to ensure that
components are operated within their ratings. Forced-air cooled rectifier,
inverter, and control unit will be acceptable. The cooling fans shall
continue operation if UPS input power is lost. Redundancy shall be provided
so that failure of one fan or associated circuit breaker will not cause an
overheat condition. Cooling air shall enter the lower front of the cabinets
and exhaust at the top. Blower power failure shall be indicated as a visual
and audible alarm on the control panel. Air inlets shall have replaceable
filters that may be located on the inside of the cabinet doors and shall be
easily accessible for replacement.
2.10.2 Blower Power Source
***************************************************************************
NOTE: Select 'output side' for 10-225kVA; select
'input and output sides' for over 225kVA.
***************************************************************************
Blower power source shall be internally derived from the [output side]
[input and output sides] of UPS module, with automatic transfer arrangement.
2.10.3 Temperature Sensors
Temperature sensors shall be provided to monitor the air temperature.
Separate sensors shall monitor the temperature of rectifier and inverter
heat sinks. Separate sensors shall also monitor the transformer temperature.
Critical equipment over-temperature indication shall start a timer that
shall shut down the UPS system if the temperature does not return below the
setpoint level recommended by the UPS manufacturer.
2.11 BATTERY SYSTEM
***************************************************************************
NOTE: Refer to UFC 3-520-01, "Interior Electrical
System"s for battery types and selection information.
***************************************************************************
2.11.1 General
Battery system shall contain the battery cells, racks, battery disconnect,
battery monitor and cabinet, if required. A storage battery with sufficient
ampere-hour rating to maintain UPS output at full capacity for the specified
duration shall be provided for each UPS module. The battery shall be of
heavy-duty, industrial design suitable for UPS service. The cells shall be
provided with flame arrestor vents, intercell connectors and cables, cell-
lifting straps, cell-numbering sets, and terminal grease. Intercell
connectors shall be sized to maintain terminal voltage within voltage window
limits when supplying full load under power failure conditions. Cell and
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 33 53.00 20 Page 31
connector hardware shall be stainless steel of a type capable of resisting
corrosion from the electrolyte used.
2.11.2 Battery Ratings
a. Type: [lead calcium][lead antimony][nickel cadmium].
b. Specific gravity when fully charged: [1.215][_____].
c. End voltage [1.67][_____] volts per cell.
d. Float voltage: [2.17 to 2.26][2.15 to 2.22] volts per cell.
e. Equalizing voltage: [2.33 to 2.38][_____] volts per cell.
2.11.3 Battery Construction
The battery shall be of the [valve-regulated, sealed, non-gassing,
recombinant type][wet-cell type and shall be supplied complete with
thermometer and hydrometer holder].
[2.11.4 Battery Cabinet
***************************************************************************
NOTE: Delete if a battery cabinet is not required.
***************************************************************************
The battery pack assembly shall be furnished in a battery cabinet matching
the UPS cabinet. The battery cabinet shall be designed to allow for checking
the torque on the connections in the battery system and to provide adequate
access for annual housekeeping chores. External wiring interface shall be
through the bottom or top of the assembly. A smoke and high temperature
alarm shall annunciate detection of either smoke or high temperature within
the battery cabinet.
][2.11.5 Battery Rack
***************************************************************************
NOTE: Delete if a battery rack is not required.
Three tier racks should be used only where floor
space is limited. They increase floor loading and
make maintenance more difficult.
***************************************************************************
The battery shall be provided with a suitable number of [two-tier][three-
tier] racks to fit the room layout shown. Battery rack shall be steel and
shall be protected with electrolyte-resistant paint. Battery rack shall be
shipped unassembled and shall include hardware necessary for assembly. Each
rack shall be complete with bus bars to accommodate cables from UPS module.
Bus bar connectors for battery-to-battery connections and high-flex multi-
stranded copper cable (ASTM B173 stranding class H) with proper cable
supports for connecting top row of batteries to bottom row of batteries at
rack ends shall be provided. End sections shall be cut to length to prevent
wasting floor space.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 33 53.00 20 Page 32
]2.11.6 Cell-Terminal Covers
Acid-resistant transparent cell-terminal covers not exceeding 1.83 meters (6
feet) in length and with vent holes drilled on top where needed shall be
provided.
2.11.7 Battery Disconnect
Each battery pack assembly shall have a fused disconnect switch provided in
a NEMA 1 enclosure, finished with acid-resistant paint and located in line
with the assembly. Switch shall be complete with line side and load side bus
bars for connection to battery cells. Switch shall be rated [_____] V dc,
[_____] amperes, 3-pole with interrupting rating as required by system
capacity, and shall have an external operator that is lockable in the "off"
position.
[2.11.8 Seismic Requirements
***************************************************************************
NOTE: Do not use this paragraph for Navy projects.
When directed to meet seismic requirements for
battery supports, Section 13 48 00 SEISMIC PROTECTION
FOR MISCELLANEOUS EQUIPMENT and 26 05 48.00 10
SEISMIC PROTECTION FOR ELECTRICAL EQUIPMENT must be
edited to suit the project and be included in the
contract documents. Edit the following paragraph and
include it in the project specification. When the
Government designer is the Engineer of Record and for
Navy projects, provide seismic requirements on the
drawings.
***************************************************************************
The battery support system shall [conform to [Section 13 48 00 SEISMIC
PROTECTION FOR MISCELLANEOUS EQUIPMENT] [and to] [Section 26 05 48.00 10
SEISMIC PROTECTION FOR ELECTRICAL EQUIPMENT]][be as indicated].
]2.11.9 Battery Monitor
A battery monitor shall be provided for each battery pack assembly. At a
minimum, this device shall monitor the following parameters:
a. Total system voltage.
b. Ambient room temperature.
c. Total battery discharge cycles with a duration of [30 seconds or
less][greater than 30 seconds but less than 5 minutes][greater than 5
minutes].
The monitor shall also record the total accumulated discharge minutes and
accumulated battery system discharge kW hours.
2.12 FACTORY TESTING
***************************************************************************
NOTE: The designer should carefully evaluate the UPS
application and the user's mission to determine
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 33 53.00 20 Page 33
critical tests for the UPS that will ensure UPS/load
compatibility. These tests should be conducted at
the factory and the results validated prior to
shipment to the site. The required UPS/load
interaction can be achieved by requesting the
following tests plus any other tests the designer
deems necessary:
a. Tests to ensure that the UPS rated power factor
is verified;
b. Tests to ensure that the UPS system will operate
in total accord and support the rated load;
c. Tests to ensure that the UPS system can deal
with load anomalies (odd harmonics, etc.) associated
with the user's equipment load.
***************************************************************************
The UPS system shall be factory tested to meet the requirements specified
using a test battery (not the battery to be supplied with the system). UPS
module shall be factory load tested as an independent assembly with 3-phase
ac input power and with battery power for a minimum of 8 hours, with meter
readings taken every 30 minutes. Load shall be balanced at rated kVA and
rated power factor. Factory tests for the UPS module shall be run under full
load, and will be witnessed by the Government. Should a malfunction occur,
the problem shall be corrected and the test shall be repeated. As a
minimum, the factory tests shall include the parameters described in
paragraphs ac Input, ac Output, Transient Response and Efficiency. The tests
shall encompass all aspects of operation, such as module failure, static
bypass operation, battery failure, input power failure and overload ratings.
The Contracting Officer shall be notified in writing at least 2 weeks before
testing. Factory-test time shall not be used for system debugging and/or
checkout. Such work shall be done prior to notifying the Government that the
system is ready for testing. Factory tests shall be performed during normal
business hours. The system shall be interconnected and tested for an
additional 8 hours to ensure proper wiring and performance.
2.12.1 Transient Tests
Transient tests shall be conducted using high-speed oscillograph type
recorders to demonstrate the operation of the components to the satisfaction
of the Government. These tests shall include 50 percent to 100 percent load
changes, manual transfer, manual retransfer, low dc bus initiated transfer
and low ac output bus transfer. A recording instrument equipped with an
event marker shall be used.
2.12.2 Efficiency Tests
Testing for efficiency shall be performed at zero output up to 100 percent
of stated kVA output in 25 percent steps, [0.8][0.9] power factor, with
battery fully charged and floating on the dc bus, with nominal input
voltage, and with module connected to represent actual operating conditions.
2.13 CABLE LUGS AND TERMINATIONS
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 33 53.00 20 Page 34
2.13.1 Cable Lugs
Provide appropriate compression type lugs on all ac and dc power connections
to the UPS system and battery as required. Aluminum or bare copper cable
lugs are not suitable.
2.13.2 Terminations
Terminals shall be supplied for making power and control connections.
Terminal blocks shall be provided for field wiring terminals. Terminal
blocks shall be heavy-duty, strap-screw type. Terminal blocks for field
wiring shall be located in one place in each module. Control wiring shall be
extended to the terminal block location. No more than two wires shall land
on any terminal point. Where control wiring is attached to the same point as
power wiring, a separate terminal shall be provided. If bus duct is used,
bus stubs shall be provided where bus duct enters cabinets.
2.14 INSPECTION
Inspection before shipment is required. The manufacturer shall notify the
Government at least 2 weeks before shipping date so that an inspection can
be made.
2.15 FIELD FABRICATED NAMEPLATES
ASTM D709. Provide laminated plastic nameplates for each equipment
enclosure, relay, switch, and device; as specified or as indicated on the
drawings. Each nameplate inscription shall identify the function and, when
applicable, the position. Nameplates shall be melamine plastic, 3 mm (0.125
inch) thick, white with [black][_____] center core. Surface shall be matte
finish. Corners shall be square. Accurately align lettering and engrave
into the core. Minimum size of nameplates shall be 25 by 65 mm (1.0 by 2.5
inches). Lettering shall be a minimum of 6.35 mm (0.25 inch) high normal
block style.
2.16 MANUFACTURER'S NAMEPLATES
Each item of equipment shall have a nameplate bearing the manufacturer's
name, address, model number, and serial number securely affixed in a
conspicuous place; the nameplate of the distributing agent will not be
acceptable.
2.17 FACTORY APPLIED FINISH
Electrical equipment shall have factory-applied painting systems which
shall, as a minimum, meet the requirements of NEMA 250 corrosion-resistance
test.
PART 3 EXECUTION
3.1 INSTALLATION
Electrical installations shall conform to IEEE C2, NFPA 70, and to
requirements specified herein. Provide new equipment and materials unless
indicated or specified otherwise.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 33 53.00 20 Page 35
3.1.1 Control Cable
***************************************************************************
NOTE: UPS sizes 200 KVA and above are shipped in
sections. Control wiring between module sections
will be connected by the UPS manufacturer's technical
representative.
***************************************************************************
UPS control wiring shall be installed in individual separate rigid steel
conduits, unless connections are made between side by side matching cabinets
of UPS. Tag control wires with numeric identification tags corresponding to
the terminal strip location to where the wires are connected. In addition to
manufacturer's requirements, provide four additional spare conductors
between UPS module and remote alarm panel in same conduit. When routing
control cables inside UPS module, maintain a minimum 155 mm (6 inches)
separation from power cables.
3.1.2 Grounding Conductor
Provide an insulated equipment grounding conductor in feeder and branch
circuits. Conductor shall be separate from the electrical system neutral
conductor. Ground battery racks and battery breaker cabinets with a separate
equipment grounding conductor to the UPS cabinet.
3.1.3 UPS Output Conductors
Isolate the UPS output conductors from the UPS cabinet to the critical load
panels and from other conductors by installing in separate conduit.
Isolation shall prevent inductive coupling from other conductors.
[3.1.4 DC Power Conductors
***************************************************************************
NOTE: Include this paragraph only when shipping
splits occur or when batteries are remote from the
UPS cabinet.
***************************************************************************
When installed in conduits, place dc power conductors from the UPS cabinet
to the battery circuit breaker such that each conduit contains an equal
number of positive and negative conductors, for example, two positive and
two negative conductors in each conduit.
]3.1.5 Seismic Protection
***************************************************************************
NOTE: Do not use this paragraph for Navy projects.
When directed to meet seismic requirements for UPS
enclosure anchoring, Section 13 48 00 SEISMIC
PROTECTION FOR MISCELLANEOUS EQUIPMENT and 26 05
48.00 10 SEISMIC PROTECTION FOR ELECTRICAL EQUIPMENT
must be edited to suit the project and be included in
the contract documents. Edit the following paragraph
and include it in the project specification. When
the Government designer is the Engineer of Record and
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 33 53.00 20 Page 36
for Navy projects, provide seismic requirements on
the drawings.
***************************************************************************
The UPS enclosure shall [conform to [Section 13 48 00 SEISMIC PROTECTION FOR
MISCELLANEOUS EQUIPMENT][ and to ][26 05 48.00 10 SEISMIC PROTECTION FOR
ELECTRICAL EQUIPMENT]][be as indicated].
3.1.6 Conduit Entries
Conduit entries shall use the available conduit areas shown on
manufacturer's installation drawings. Conduit entries shall not be made
through the front, side or rear panels of the UPS[ or Maintenance Bypass
Cabinet].
[3.1.7 Battery Rack Assembly
***************************************************************************
NOTE: Choose this paragraph or the one below
entitled "Battery Cabinet".
***************************************************************************
Battery racks are typically shipped dismantled in separate rail, frame, and
brace packages. Ensure that manufacturer furnished assembly hardware is used
to assemble battery racks. Installation of battery racks shall conform to
the manufacturer's instructions.
][3.1.8 Battery Cabinet Assembly
Battery cabinets are typically factory assembled for up to 100 KVA UPS
systems. Battery cabinets for larger units typically require assembly at
the site. Installation of battery cabinets shall conform to the
manufacturer's instructions.
][3.1.9 Battery Installation
***************************************************************************
NOTE: Delete paragraph and subparagraphs for smaller
UPS units that have batteries installed in the unit
cabinet by the manufacturer at the factory.
***************************************************************************
Installation of batteries shall conform to the manufacturer's instructions.
]3.2 FIELD QUALITY CONTROL
***************************************************************************
NOTE: The UPS manufacturer's technical
representative is required to inspect the completed
UPS and battery installation. The representative's
visit to the site must be scheduled by the
Contractor.
***************************************************************************
Contractor shall notify Contracting Officer in writing at least 45 calendar
days prior to completion of the UPS system installation. At this time the
Contractor, will schedule the UPS manufacturer's technical representative to
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 33 53.00 20 Page 37
inspect the completed installation. The UPS technical representative shall
provide instruction for activity personnel as specified in paragraph titled
"DEMONSTRATION".
3.2.1 Installation Preparation
***************************************************************************
NOTE: In subparagraph b. choose either battery racks
or cabinets based on the UPS size and configuration.
In subparagraph o. delete the bracketed statement
when the project does not require a UPS maintenance
bypass cabinet.
***************************************************************************
The following items shall be completely installed by the Contractor and be
operational prior to the arrival of the UPS representative for inspection,
unit start-up and testing:
a. Ventilation equipment in the UPS and battery rooms.
b. Battery [racks][cabinets] and cells. This is not applicable for
maintenance-free battery.
c. Battery connections including cell-to-cell, tier-to-tier, and rack-to-
rack connections, with correct polarity;
d. DC power and control connections between UPS and battery circuit
breaker, with correct polarity;
e. DC power connection between battery circuit breaker and battery, with
correct polarity;
f. Clockwise phase rotation of ac power connections;
g. AC power to rectifier input bus;
h. AC power to UPS bypass input bus;
i. AC power to UPS maintenance bypass circuit breaker;
j. AC power from UPS output to UPS maintenance bypass output circuit
breaker;
k. Remote monitors and control wiring;
l. UPS system and battery system properly grounded;
m. Emergency shower and eye wash;
[n. Control connections between UPS and emergency engine generator signal
contacts;
]o. Control connections between UPS module [and UPS maintenance bypass
cabinet];
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 33 53.00 20 Page 38
p. Clean and vacuum UPS and battery room floors, battery cells, and
UPS equipment, both inside and outside.
q. Ensure that shipping members have been removed.
r. Provide IEEE 450 battery installation certification.
3.2.2 Initial Inspection and Tests
The UPS technical representative and the Contracting Officer, in the
presence of the Contractor, will inspect the completed installation. The
Contractor shall correct construction or installation deficiencies as
directed. Perform acceptance checks in accordance with the manufacturer's
recommendations and include the following visual and mechanical inspections,
performed in accordance with NETA ATS.
a. Visual and mechanical inspection
(1) Compare equipment nameplate data with drawings, specifications and
approved shop drawings.
(2) Inspect physical and mechanical condition. Inspect doors, panels,
and sections for paint, dents, scratches, fit, and missing
hardware. Inspect the displays for scratches, dark pixels or
uneven brightness.
(3) Inspect anchorage, alignment, grounding, and required clearances.
(4) Verify that fuse sizes and types correspond to drawings.
(5) Verify the unit is clean inside and out.
(6) Test all electrical and mechanical interlock systems for correct
operation and sequencing.
(7) Inspect bolted electrical connections for high resistance using
one of the following methods:
(a) Use a low-resistance ohmmeter.
(b) Verify tightness of accessible bolted electrical connections
by calibrated torque-wrench method.
(c) Perform thermographic survey.
(8) Verify operation of forced ventilation.
(9) Verify that vents are clear and new clean filters are installed.
3.2.3 Performance Tests
Provide equipment, test instruments, power, load bank, materials and labor
required for tests. Contracting Officer will witness all tests and the tests
shall be subject to his approval. Perform tests in accordance with the
manufacturer's recommendations and include the following electrical tests.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 33 53.00 20 Page 39
3.2.3.1 UPS Unit Performance Tests
Upon completion of battery activation procedures, Contractor shall connect
load bank to UPS output. Load bank required shall be determined by the
following:
UPS KVA RATING X 0.8 = KW of LOAD BANK
Performance test is to be run under the supervision of the UPS technical
representative. UPS unit shall be operated under full load for a minimum of
one hour. Contractor shall be required to operate feeder and bypass power
feeder breakers during testing of the UPS.
a. Electrical Tests
(1) Perform resistance measurements through bolted connections with a
low-resistance ohmmeter.
(2) Test static transfer from inverter to bypass and back. Use normal
load, if possible.
(3) Set free running frequency of oscillator.
(4) Test dc undervoltage trip level on inverter input breaker. Set
according to manufacturer's published data.
(5) Test alarm circuits.
(6) Verify synchronizing indicators for static switch and bypass
switches.
(7) Perform electrical tests for UPS system breakers.
(8) Perform electrical tests for UPS system batteries.
b. Test Values
(1) Compare bolted connection resistances to values of similar
connections.
(2) Verify bolt-torque levels.
(3) Micro-ohm or millivolt drop values shall not exceed the high
levels of the normal range as indicated in the manufacturer's
published data. If manufacturer's data is not available,
investigate any values which deviate from similar connections by
more than 50 percent of the lowest value.
[c. Load Test
***************************************************************************
NOTE: Edit as required, depending upon whether a
temporary or permanent load bank is to be provided
and on the type of UPS system. This paragraph may
be deleted for small UPS systems.
***************************************************************************
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 33 53.00 20 Page 40
The installed system shall be load tested for a continuous 24 hour period
by means of resistive load banks. The system shall be continuously tested
at 1/2 load for 8 hours, 3/4 load for 8 hours and full load for 8 hours.
Provide resistive load banks of total kW load of equipment to facilitate
startup under load conditions, and to conduct load tests described above.
Instrument readings shall be recorded every half hour for the following:
(1) Input voltage (all three phases).
(2) Input current (all three phases).
(3) Input frequency.
(4) Battery voltage.
(5) Output voltage (all three phases).
(6) Output current (all three phases).
(7) Output kilowatts.
(8) Output frequency.
][d. Full Load Burn In Test
***************************************************************************
NOTE: Delete emergency source testing requirements
if no emergency source is available. This paragraph
may be deleted for small UPS system.
***************************************************************************
The installed system shall undergo an additional full load burn-in period
of 24 continuous hours. If a failure occurs during the burn-in period, the
tests shall be repeated. Instrument readings shall be recorded every half
hour as above. During the burn-in period, the following tests shall be
performed:
(1) With the UPS carrying maximum continuous design load and supplied
from the normal source, switch [100 percent load][50 percent load] on
and off a minimum of five times within [the burn-in period]
[_____].
[(2) With the UPS carrying maximum continuous design load and supplied
from the emergency source, repeat the switching operations
described in step a. Also, verify that the UPS module rectifier
charger unit(s) go into the second-step current limit mode.]
(3) With the UPS carrying maximum continuous design load and operating
on battery power, repeat the switching operations described in step
a above.
(4) Continue operation on battery power for 1 minute, then restore
normal power.
The Contractor shall furnish a high-speed dual trace oscillograph to
monitor ten or more cycles of the above tests at the ON and OFF transitions
and two typical steady-state periods, one shortly after the load is
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 33 53.00 20 Page 41
energized (at 30 to 60 seconds) and one after operation has stabilized (at
8 to 10 minutes). Four copies of the traces shall be delivered to the
Contracting Officer.
][e. Battery Discharge Test
***************************************************************************
NOTE: This paragraph may be deleted for small UPS
system.
***************************************************************************
With the battery fully charged, the system shall undergo a complete battery
discharge test to full depletion and a recharge to nominal conditions.
Instrument readings shall be recorded every minute during discharge for the
following:
(1) Battery voltage.
(2) Battery current.
(3) Output voltage (all three phases).
(4) Output current (all three phases).
(5) Output kilowatts.
(6) Output frequency.
][3.2.3.2 Emergency Generator Operation
***************************************************************************
NOTE: Include this paragraph only when the UPS will
be installed in conjunction with an emergency
generator.
***************************************************************************
Test UPS to observe operation with emergency generator service. UPS
technical representative shall verify UPS battery current limiting feature
functions properly.
][3.2.3.3 Battery Performance Test (Constant KW)
***************************************************************************
NOTE: This paragraph is applicable for large wet-
cell type battery systems. Delete for sealed (valve
regulated) battery system.
***************************************************************************
Furnish all labor, material and test equipment necessary to conduct
performance test under the direction of UPS technical representative. The
following shall be accomplished:
a. Install a calibrated voltmeter across the battery terminals to measure
voltage, and install a calibrated voltmeter across the UPS dc shunt to
read charging current. UPS technical representative will advise
connection to dc shunt.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 33 53.00 20 Page 42
b. Record temperature of pilot cells in battery immediately prior to start
of discharge performance test.
c. Read and record total battery voltage and battery current at start of
discharge and every minute during discharge test.
d. Record minutes and seconds when battery voltage drops below minimum
discharge voltage of 291 volts dc. On initial discharge test, a battery
may be expected to deliver 95 percent of its rated capacity. This will
increase to 100 percent after several complete discharge cycles or
after 12 months of float charge service.
e. Should battery fail to meet the requirements of the first discharge
performance test, open the inverted output breaker. Then put battery on
equalizing charge, with rectifier adjusted to normal equalizing voltage
of [424][_____] volts dc. Equalize for a minimum of [100][_____] hours.
Measure and record time and battery voltage. Run a second discharge
performance test.
]3.3 DEMONSTRATION
***************************************************************************
NOTE: Delete video tape references if not required.
***************************************************************************
3.3.1 Instructing Government Personnel
Furnish the services of competent instructors to give full instruction to
designated Government personnel in the adjustment, operation, and
maintenance of the specified systems and equipment, including pertinent
safety requirements as required. Instructors shall be thoroughly familiar
with all parts of the installation and shall be trained in operating theory
as well as practical operation and maintenance work. Instruction shall be
given during the first regular work week after the equipment or system has
been accepted and turned over to the Government for regular operation.
Provide [8][_____] hours of instruction for [_____] personnel.[ When more
than 4 man-days of instruction are specified, use approximately half of the
time for classroom instruction. Use other time for instruction with
equipment or system. When significant changes or modifications in the
equipment or system are made under the terms of the contract, provide
additional instructions to acquaint the operating personnel with the changes
or modifications.][ Field training shall be videotaped and the tape shall
be left with the Contracting Officer.][ A factory training videotape shall
be provided as part of the training materials.]
3.4 FINAL ADJUSTMENTS
a. Remove load bank and reconnect system for normal operation.
b. Equalize battery at [424][_____] volts for a period of [72]
[_____] hours.
***************************************************************************
NOTE: Delete this paragraph if battery is sealed
(valve regulated) type.
***************************************************************************
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 33 53.00 20 Page 43
[c. Bring electrolyte level of all cells up to the bottom of the high
level line by adding original filling gravity electrolyte.
]d. Resume charging battery at normal float voltage of [411][_____] volts
dc.
e. Check battery connections are properly torqued to manufacturer's
specifications. Take and record, for cell-to-cell and terminal
connections, detailed micro-ohm resistance readings. Remake connections
having a resistance of more than 10 percent above the average.
f. All manufacturer's data and operation manuals, which are an integral
part of, and shipped with UPS, shall be delivered to Contracting
Officer.
3.5 NAMEPLATE MOUNTING
Provide number, location, and letter designation of nameplates as indicated.
Fasten nameplates to the device with a minimum of two sheet-metal screws or
two rivets.
3.6 FIELD APPLIED PAINTING
Paint electrical equipment as required to match finish of adjacent surfaces
or to meet the indicated or specified safety criteria. Painting shall be as
specified in Section 09 90 00 PAINTS AND COATINGS.
3.7 DISPOSAL
Upon completion of UPS installation and testing, Contractor shall remove and
dispose of empty, partially full and excess acid drums, including shipping
containers, obsolete batteries, and obsolete UPS modules. Removal shall be
accomplished off-base and in conformance with local laws and regulations
regarding disposal of hazardous material.
-- End of Section --
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 55 80.00 20 Page 1
***************************************************************************
USACE / NAVFAC / AFCEC / NASA UFGS-26 55 80.00 20 (April 2006)
--------------------------------
Preparing Activity: NAVFAC Replacing without change
UFGS-16553N (Septermber 1999)
UNIFIED FACILITIES GUIDE SPECIFICATIONS
References are in agreement with UMRL dated October 2017
***************************************************************************
SECTION 26 55 80.00 20
SURGICAL LIGHTING FIXTURES
04/06
***************************************************************************
NOTE: This guide specification covers the
requirements for surgical lighting fixtures and
similar related specialities.
Adhere to UFC 1-300-02 Unified Facilities Guide
Specifications (UFGS) Format Standard when editing
this guide specification or preparing new project
specification sections. Edit this guide
specification for project specific requirements by
adding, deleting, or revising text. For bracketed
items, choose applicable item(s) or insert
appropriate information.
Remove information and requirements not required in
respective project, whether or not brackets are
present.
Comments, suggestions and recommended changes for
this guide specification are welcome and should be
submitted as a Criteria Change Request (CCR).
***************************************************************************
***************************************************************************
NOTE: This guide specification shall be used in
conjunction with additional design guidance supplied
for that particular project.
***************************************************************************
***************************************************************************
NOTE: The following information shall be shown on
the project drawings:
1. Lighting fixture schedule.
2. Lighting fixture wiring diagram.
***************************************************************************
PART 1 GENERAL
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 55 80.00 20 Page 2
1.1 REFERENCES
***************************************************************************
NOTE: This paragraph is used to list the
publications cited in the text of the guide
specification. The publications are referred to in
the text by basic designation only and listed in this
paragraph by organization, designation, date, and
title.
Use the Reference Wizard's Check Reference feature
when you add a Reference Identifier (RID) outside of
the Section's Reference Article to automatically
place the reference in the Reference Article. Also
use the Reference Wizard's Check Reference feature to
update the issue dates.
References not used in the text will automatically be
deleted from this section of the project
specification when you choose to reconcile references
in the publish print process.
***************************************************************************
The publications listed below form a part of this specification to the
extent referenced. The publications are referred to within the text by the
basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM E308 (2017) Standard Practice for Computing the
Colors of Objects by Using the CIE System
NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)
NEMA ST 20 (1992; R 1997) Standard for Dry-Type
Transformers for General Applications
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 70 (2017; ERTA 1-2 2017; TIA 17-1; TIA 17-2; TIA
17-3) National Electrical Code
UNDERWRITERS LABORATORIES (UL)
UL 544 (1998; R 1999) Standard for Medical and
Dental Equipment
1.2 RELATED REQUIREMENTS
Section 11 70 00 GENERAL REQUIREMENTS FOR MEDICAL AND DENTAL EQUIPMENT,
Section 26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS, Section 26 20
00 INTERIOR DISTRIBUTION SYSTEM, apply to this section with the additions
and modifications specified herein.
1.3 DESIGN REQUIREMENTS
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 55 80.00 20 Page 3
1.3.1 Lighthead Illumination Level
Lighthead shall produce a minimum of [80,000 lux] ([7440 footcandles])
[_____] of illumination when measured at 1070 mm (42 inches) from the face
of the light.
1.3.2 Color Temperature
Correlated color of the lightbeam shall be between 3,500 degrees and 6,700
degrees Kelvin after filtration, as measured on the ASTM E308 chromaticity
diagram.
1.3.3 Shadow Reduction
Lighting system shall provide a minimum level of 10 percent of the
unshadowed level when measured inside and at the bottom of a tube 50 mm (2
inch) in diameter, and 76 mm (3 inch) long, from a distance of 1070 mm (42
inches) when the beam is obstructed by a disk 254 mm (10 inch) in diameter,
580 mm (23 inches) above the operating table, and normal to the axis of the
tube. Paint inside of tube with flat black.
1.3.4 Beam Temperature
Radiant heat energy in the light beam 1070 mm (42 inches) below the
lighthead shall not exceed 25,000 microwatts per square centimeter at
maximum intensity in the light pattern.
1.3.5 Pattern Size
Smallest pattern size in the focal range shall be a minimum of 150 mm (6
inches). Pattern size shall be adjustable by either raising and lowering
the unit or through operation of a focus control which changes the pattern
size without movement of the unit.
1.3.6 Current Leakage
A maximum of 0.1 milliampere, as measured between the metal parts and
ground.
1.4 SUBMITTALS
***************************************************************************
NOTE: Review Submittal Description (SD) definitions
in Section 01 33 00 SUBMITTAL PROCEDURES and edit the
following list to reflect only the submittals
required for the project.
The Guide Specification technical editors have
designated those items that require Government
approval, due to their complexity or criticality,
with a "G". Generally, other submittal items can be
reviewed by the Contractor's Quality Control System.
Only add a “G” to an item, if the submittal is
sufficiently important or complex in context of the
project.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 55 80.00 20 Page 4
For submittals requiring Government approval on Army
projects, a code of up to three characters within the
submittal tags may be used following the "G"
designation to indicate the approving authority.
Codes for Army projects using the Resident Management
System (RMS) are: "AE" for Architect-Engineer; "DO"
for District Office (Engineering Division or other
organization in the District Office); "AO" for Area
Office; "RO" for Resident Office; and "PO" for
Project Office. Codes following the "G" typically
are not used for Navy, Air Force, and NASA projects.
Use the "S" classification only in SD-11 Closeout
Submittals. The "S" following a submittal item
indicates that the submittal is required for the
Sustainability eNotebook to fulfill federally
mandated sustainable requirements in accordance with
Section 01 33 29 SUSTAINABILITY REPORTING.
Choose the first bracketed item for Navy, Air Force
and NASA projects, or choose the second bracketed
item for Army projects.
***************************************************************************
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are [for Contractor Quality Control
approval.][for information only. When used, a designation following the "G"
designation identifies the office that will review the submittal for the
Government.] Submittals with an "S" are for inclusion in the Sustainability
eNotebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-02 Shop Drawings
Installation drawings; G[, [_____]]
SD-03 Product Data
Light fixtures; G[, [_____]]
Controls; G[, [_____]]
Surgical Light Transformer; G[, [_____]]
SD-07 Certificates
Installation report
Design requirements
Certify that the equipment has been properly installed, adjusted,
and tested, and that each surgical light fixture meets the
provisions of the paragraph entitled "Design Requirements."
SD-10 Operation and Maintenance Data
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 55 80.00 20 Page 5
Light fixtures, Data Package 5
Submit in accordance with Section 01 78 23 OPERATION AND
MAINTENANCE DATA.
1.5 QUALITY ASSURANCE
1.5.1 Installation drawings
Submit shop drawing for each specified lighting fixture to include the
following:
a. Mounting detail for the lighting fixture[, transformer and control]
assembly.
b. Wiring diagrams indicating the internal wiring for each item of
equipment, the interconnections between the items of equipment and
connections to normal and emergency power in the building.
Manufacturer's catalog data may be submitted for internal wiring
description.
1.6 DELIVERY, STORAGE, AND HANDLING
Package each lighting fixture and protect in accordance with the
manufacturer's instructions.
PART 2 PRODUCTS
2.1 LIGHT FIXTURES
2.1.1 One Lighthead
One lighthead, ceiling mounted on a single extension arm assembly. Lighthead
shall rotate within a clearance circle of 4720 mm (15 1/2 feet) and the
lighthead center describes a circle 3810 mm (12 1/2 feet) when fully
extended. Center of lighthead adjustable vertically from 1190 mm (3 feet 11
inches) to 2250 mm (7 feet 4 1/2 inches) above the floor.
2.1.2 Two Lightheads
Two lightheads, ceiling mounted on a dual extension arm assembly. One
lighthead mounted on the shorter arm and the other lighthead mounted on the
longer arm to enable the outer lighthead to pass by the inner lighthead
without interference. Outer lighthead shall rotate within a clearance
circle of 4720 mm (15 1/2 feet) and the lighthead center describes a circle
3810 mm (12 1/2 feet) when fully extended. Center of the lighthead shall be
adjustable vertically from 1190 mm (3 feet 11 inches) to 2250 mm (7 feet 4
1/2 inches) above the floor.
2.1.3 Track Mounted Light Fixtures
[Single-track system with one or more lightheads] [or] [dual-track system
with one or more lightheads] per track. Lightheads are suspended from a
carriage which rides in track [or tracks] mounted in the ceiling. Steel
suspension tube shall have sufficient length for cutting to the proper
length at installation.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 55 80.00 20 Page 6
2.1.3.1 Light Ceiling Tracks
Ceiling tracks shall have end closures finished to match the fixture and
shall have an opening in bottom a maximum of 50 mm (2 inches) wide extending
the entire length of track to receive the part of the carriage that moves
inside the track. Provide each track with insulated duct enclosing two
copper bus bars, and a grounding path. Provide tracks with all the
necessary components for mounting, and provide for sliding, nonsparking
electrical contacts and current-conducting components within the track.
2.1.3.2 [One] [and] [Two] Lighthead[s]
Lighthead shall rotate within a clearance circle of 2800 mm (9 feet 2
inches) and the lighthead center describes a circle 1900 mm (3 feet) when
fully extended. Lighthead center shall be adjustable vertically from 1200
mm (3 feet 11 inches) to 2200 mm (7 feet 2 inches) above the floor.
2.1.3.3 Fixture on Two Parallel Tracks
Two lightheads; twin track mounted; including two parallel, 2745 mm (9 foot)
long, surface-mounted fixed tracks, each with a lighthead and carriage.
2.1.3.4 Fixture on Single Lighthead Track
Single lighthead; short track mounted; including a 1370 mm (54 inch) long,
surface-mounted fixed track with a lighthead, and carriage.
2.1.4 Components
UL 544; The surgical lighting fixtures shall be specifically designed for
use in surgical operating rooms.
2.1.5 Electrical Characteristics
120 volts, 60 Hz, single-phase, three-wire grounded circuits.
2.1.6 Lamp
[Quartz halogen][LED] [_____] enclosed by heat-absorbing filter. Lamp shall
be color corrected and heat filtered and shall have a minimum lifespan of
500 hours. Furnish one spare lamp with each lighthead.
2.1.7 Suspension Systems
Mount each lighthead on a counterbalanced arm that can rotate 6.28 rad (360
degrees) horizontally and can provide both vertical and horizontal
adjustments. Fixture shall be controllable from both inside and outside the
sterile field and shall move in a free, smooth, and silent manner throughout
its range of maneuverability without drifting, regardless of position. [In
systems with multiple arms attached to the same mount, each individual arm
and lighthead shall operate independently and shall be mounted so that each
individual arm and lighthead can be positioned outside the sterile area, can
bypass each other and be raised, and can be lowered and rotated.]
2.1.8 [Movement Limits
***************************************************************************
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 55 80.00 20 Page 7
NOTE: Include this paragraph where flammable
anesthestics are used.
***************************************************************************
Provide lighthead with stops which shall prevent surgical light from being
lowered less than 1520 mm (5 feet) above the finished floor.
]2.2 CONTROLS
***************************************************************************
NOTE: Designer should coordinate with User for the
number of controllers required and indicate this
information on the drawing.
***************************************************************************
[Recessed] [or] [Surfaced] mounted. Include circuit breaker, an on/off
switch located outside the sterile field, and a pilot light. Controls shall
have a continuously variable intensity control range from the maximum lux
(footcandle) rating of the lighting fixture to a minimum of 60 percent of
the maximum lux (footcandle) rating of the lighting fixture. Include a
radio frequency suppressor. Provide time-of-use meter to determine when to
replace the lamp. Provide control units with electrical plug connections
designed to allow eased of service or replacement.
2.3 SURGICAL LIGHT TRANSFORMER
NEMA ST 20, [_____] VA, 120 V, 60 Hz primary, 22.8 V - 24 V, 60 Hz
secondary.
PART 3 EXECUTION
3.1 INSTALLATION
Section 11 70 00 GENERAL REQUIREMENTS FOR MEDICAL AND DENTAL EQUIPMENT, and
NFPA 70. Install lighthead in accordance with the approved installation
drawings and submit installation report for each lighthead.
3.1.1 Wiring Methods
Provide conduit and wiring in accordance with Section 26 20 00 INTERIOR
DISTRIBUTION SYSTEM.
3.1.1.1 [Outlet Box
***************************************************************************
NOTE: Delete this paragraph if lighthead intensity
control is surface mounted.
***************************************************************************
Provide three-gang outlet box 75 mm (3 inches) depth for recessed mounted
intensity control. Install box 1525 mm (5 feet) from finished floor to
center line of box.
]3.1.2 Surgical Light Transformer
***************************************************************************
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 55 80.00 20 Page 8
NOTE: Locate transformer so that the maximum length
of wires shall not exceed 9144 mm (30 feet) from
transformer to the lighthead.
***************************************************************************
Provide [mounting bracket] [seismic anchoring] for the transformer. Mount
transformer on the [ceiling] [wall, 1525 mm (5 feet), minimum, from finished
floor].
3.2 FIELD QUALITY CONTROL
3.2.1 Inspection
Examine each item visually for conformance to the requirements of this
section.
3.2.2 Tests
Upon completion of installation, conduct an operating test to demonstrate
that each surgical lighting fixture meets the requirements of this section.
-- End of Section --
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 56 00 Page 1
***************************************************************************
USACE / NAVFAC / AFCEC / NASA UFGS-26 56 00 (May 2013)
--------------------------
Preparing Activity: NAVFAC Superseding
UFGS-26 56 00 (July 2006)
UNIFIED FACILITIES GUIDE SPECIFICATIONS
References are in agreement with UMRL dated October 2017
***************************************************************************
SECTION 26 56 00
EXTERIOR LIGHTING
05/13
***************************************************************************
NOTE: This guide specification covers lighting
system requirements for exterior installations.
This specification does not cover all possible
methods or requirements for exterior lighting;
therefore, designer should add special information
required to suit a specific project. Industry
publications exist to aid the designer in choosing
the best lighting system for the project.
Publications include, but are not limited to, the
Illuminating Engineering Society (IES) HB-10,
LIGHTING HANDBOOK and RP-8, RECOMMENDED PRACTICE FOR
ROADWAY LIGHTING.
Adhere to UFC 1-300-02 Unified Facilities Guide
Specifications (UFGS) Format Standard when editing
this guide specification or preparing new project
specification sections. Edit this guide
specification for project specific requirements by
adding, deleting, or revising text. For bracketed
items, choose applicable item(s) or insert
appropriate information.
Remove information and requirements not required in
respective project, whether or not brackets are
present.
Comments, suggestions and recommended changes for
this guide specification are welcome and should be
submitted as a Criteria Change Request (CCR).
***************************************************************************
***************************************************************************
NOTE: TO DOWNLOAD UFGS GRAPHICS
Go to http://www.wbdg.org/FFC/NAVGRAPH/graphtoc.pdf
***************************************************************************
***************************************************************************
NOTE: This section contains the following sketches
(plates) and are available in metric (SI) and U.S.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 56 00 Page 2
Customary (IP) system dimensions. Sketch titles and
style numbers are unchanged for both types.
Do not include list of sketches, or sketches
themselves, in project specifications. Use luminaire
sketches as details (plates) on drawings whenever
possible. If special features are required, do not
modify sketches, but indicate these changes as notes
in luminaire schedule. The "XL" style numbers and
dates should remain on the drawing details. If
additional luminaire types are needed that are not
covered in sketches, provide additional sketches or
details on drawings, but do not label as XL sketch
type.
Sketch No. Title
XL-1 LED Roadway Luminaire
XL-2 HID/Induction Roadway Luminaire
XL-3 LED Area Luminaire
XL-4 HID Area Luminaire
XL-5 Induction Area Luminaire
XL-6 Low Pressure Sodium Area Luminaire
XL-7 HID High Mast Luminaire
XL-8 HID Apron/Large Sports Field Luminaire
XL-9 HID Sports Field Luminaire
XL-10 LED Pedestrian Post Top Luminaire
XL-11 HID/CFL/Induction Pedestrian Post Top Luminaire
XL-12 Decorative Bollard
XL-13 LED Parking Garage Luminaire
XL-14 HID/Induction Parking Garage Luminaire
XL-15 Exterior Recessed Downlight
XL-16 LED Linear Wall Wash
XL-17 LED Wall Pack
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 56 00 Page 3
Sketch No. Title
XL-18 HID/Induction Wall Pack
XL-19 Decorative Wall Sconce
XL-20 Aviation Obstruction Luminaire
XL-21 LED Flood Luminaire
XL-22 HID/Induction Flood Luminaire
XL-23 Direct-Set Fiberglass Pole
XL-24 Direct-Set Concrete Pole
XL-25 Direct-Set Steel/Aluminum Pole
XL-26 Anchor Base Fiberglass Pole
XL-27 Anchor Base Steel/Aluminum Pole
XL-28 Anchor Base Concrete Pole
XL-29 Anchor Base Pole Foundation
XL-30 Direct Set Pole Grounding Detail
XL-31 Luminaire Mounting Arm Details
XL-32 Luminaire Mounting Arm Details
XL-33 Luminaire Mounting Bracket Details
XL-34 Luminaire Mounting Bracket Details
NOTE: Do not include this index in project specification.
***************************************************************************
***************************************************************************
NOTE: The following information shall be shown on
the project drawings or specified in the project
specifications:
a. Luminaire schedule indicating luminaire type,
mounting, and light source type and quantity;
b. Accessories required, such as photocell, mounting
brackets or arms and pole type;
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 56 00 Page 4
c. Wattage, operating voltage and frequency;
d. Location and mounting height of poles or
standards;
e. Referenced XL sketch or detail;
f. NEMA distribution type and BUG rating when
applicable; and
g. Extent and location of the work to be
accomplished with wiring and equipment necessary for
a complete installation.
***************************************************************************
***************************************************************************
NOTE: Demolition work that involves disposal of
fluorescent and HID light sources and ballasts will
require the use of Section 02 84 16 HANDLING OF
LIGHTING BALLASTS AND LAMPS CONTAINING PCBs AND
MERCURY.
***************************************************************************
PART 1 GENERAL
1.1 REFERENCES
***************************************************************************
NOTE: This paragraph is used to list the
publications cited in the text of the guide
specification. The publications are referred to in
the text by basic designation only and listed in this
paragraph by organization, designation, date, and
title.
Use the Reference Wizard's Check Reference feature
when you add a Reference Identifier (RID) outside of
the Section's Reference Article to automatically
place the reference in the Reference Article. Also
use the Reference Wizard's Check Reference feature to
update the issue dates.
References not used in the text will automatically be
deleted from this section of the project
specification when you choose to reconcile references
in the publish print process.
***************************************************************************
The publications listed below form a part of this specification to the
extent referenced. The publications are referred to in the text by the
basic designation only.
ALLIANCE FOR TELECOMMUNICATIONS INDUSTRY SOLUTIONS (ATIS)
ATIS ANSI O5.1 (2008) Wood Poles -- Specifications &
Dimensions
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 56 00 Page 5
AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS
(AASHTO)
AASHTO LTS (2013; Errata 2013) Standard Specifications
for Structural Supports for Highway Signs,
Luminaires and Traffic Signals
AMERICAN SOCIETY OF HEATING, REFRIGERATING AND AIR-CONDITIONING
ENGINEERS (ASHRAE)
ASHRAE 189.1 (2014) Standard for the Design of High-
Performance Green Buildings Except Low-Rise
Residential Buildings
ASHRAE 90.1 - IP (2013) Energy Standard for Buildings Except
Low-Rise Residential Buildings
ASHRAE 90.1 - SI (2013) Energy Standard for Buildings Except
Low-Rise Residential Buildings
AMERICAN WOOD PROTECTION ASSOCIATION (AWPA)
AWPA U1 (2017) Use Category System: User
Specification for Treated Wood
ASTM INTERNATIONAL (ASTM)
ASTM A123/A123M (2015) Standard Specification for Zinc (Hot-
Dip Galvanized) Coatings on Iron and Steel
Products
ASTM A153/A153M (2016) Standard Specification for Zinc
Coating (Hot-Dip) on Iron and Steel Hardware
ASTM B108/B108M (2015) Standard Specification for Aluminum-
Alloy Permanent Mold Castings
ASTM B117 (2016) Standard Practice for Operating Salt
Spray (Fog) Apparatus
ASTM C1089 (2013) Standard Specification for Spun Cast
Prestressed Concrete Poles
ASTM G154 (2016) Standard Practice for Operating
Fluorescent Light Apparatus for UV Exposure
of Nonmetallic Materials
CALIFORNIA ENERGY COMMISSION (CEC)
CEC Title 24 (2008; Effective Jan 2010) California's
Energy Efficiency Standards for Residential
and Nonresidential Buildings
ILLUMINATING ENGINEERING SOCIETY (IES)
IES HB-10 (2011; Errata 2015) IES Lighting Handbook
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 56 00 Page 6
IES LM-79 (2008) Electrical and Photometric
Measurements of Solid-State Lighting Products
IES LM-80 (2015) Measuring Lumen Maintenance of LED
Light Sources
IES RP-16 (2010; Addendum A 2008; Addenda B 2009;
Addendum C 2016) Nomenclature and Definitions
for Illuminating Engineering
IES RP-8 (2014) Roadway Lighting
IES TM-15 (2011) Luminaire Classification System for
Outdoor Luminaires
IES TM-21 (2011; Addendum B 2015) Projecting Long Term
Lumen Maintenance of LED Light Sources
INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)
IEEE 100 (2000; Archived) The Authoritative Dictionary
of IEEE Standards Terms
IEEE C2 (2017; Errata 1-2 2017; INT 1 2017) National
Electrical Safety Code
IEEE C62.41 (1991; R 1995) Recommended Practice on Surge
Voltages in Low-Voltage AC Power Circuits
IEEE C62.41.1 (2002; R 2008) Guide on the Surges
Environment in Low-Voltage (1000 V and Less)
AC Power Circuits
IEEE C62.41.2 (2002) Recommended Practice on
Characterization of Surges in Low-Voltage
(1000 V and Less) AC Power Circuits
NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)
ANSI ANSLG C78.41 (2016) Electric Lamps--Guidelines for Low-
Pressure Sodium Lamps
ANSI ANSLG C78.42 (2009; R 2016) For Electric Lamps: High-
Pressure Sodium Lamps
ANSI C136.13 (2004; R 2009) American National Standard for
Roadway Lighting Equipment, Metal Brackets
for Wood Poles
ANSI C136.21 (2014) American National Standard for Roadway
and Area Lighting Equipment - Vertical Tenons
Used with Post-Top-Mounted Luminaires
ANSI C136.3 (2014) American National Standard for Roadway
and Area Lighting Equipment Luminaire
Attachments
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 56 00 Page 7
ANSI C78.1381 (1998) American National Standard for
Electric Lamps - 250-Watt, 70 Watt, M85
Metal-Halide Lamps
ANSI C82.4 (2017) Lamp Ballasts - Ballasts for High-
Intensity-Discharge and Low-Pressure Sodium
Lamps
ANSI/ANSLG C78.43 (2013) American National Standard for
Electric Lamps - Single-Ended Metal-Halide
Lamps
ANSI/NEMA C78.LL 1256 (2003; R 2015) Procedures for Fluorescent
Lamp Sample Preparation and the Toxicity
Characteristic Leaching Procedure (TCLP)
NEMA 250 (2014) Enclosures for Electrical Equipment
(1000 Volts Maximum)
NEMA ANSLG C78.377 (2017) Electric Lamps— Specifications for the
Chromaticity of Solid State Lighting Products
NEMA ANSLG C78.380 (2007) Electric Lamps - High Intensity
Discharge Lamps, Method of Designation
NEMA ANSLG C78.44 (2008) For Electric Lamps - Double-Ended
Metal Halide Lamps
NEMA ANSLG C82.11 (2017) Lamp Ballasts - High-Frequency
Fluorescent Lamp Ballasts
NEMA ANSLG C82.14 (2016) Lamp Ballasts Low-Frequency Square
Wave Electronic Ballasts -- for Metal Halide
Lamps
NEMA C136.10 (2010) American National Standard for Roadway
and Area Lighting Equipment-Locking-Type
Photocontrol Devices and Mating Receptacles--
Physical and Electrical Interchangeability
and Testing
NEMA C136.20 (2012) American National Standard for Roadway
and Area Lighting Equipment - Fiber
Reinforced Composite (FRC) Lighting Poles
NEMA C136.31 (2010) American National for Roadway and Area
Lighting Equipment - Luminaire Vibration
NEMA C78.LL 3 (2003; R 2015) Electric Lamps - Procedures
for High Intensity Discharge Lamp Sample
Preparation and the Toxicity Characteristic
Leaching Procedure
NEMA C82.77 (2002) Harmonic Emission Limits - Related
Power Quality Requirements for Lighting
Equipment
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 56 00 Page 8
NEMA ICS 2 (2000; R 2005; Errata 2008) Industrial
Control and Systems Controllers, Contactors,
and Overload Relays Rated 600 V
NEMA ICS 6 (1993; R 2016) Industrial Control and
Systems: Enclosures
NEMA IEC 60529 (2004) Degrees of Protection Provided by
Enclosures (IP Code)
NEMA WD 7 (2011; R 2016) Occupancy Motion Sensors
Standard
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 70 (2017; ERTA 1-2 2017; TIA 17-1; TIA 17-2; TIA
17-3) National Electrical Code
U.S. DEPARTMENT OF AGRICULTURE (USDA)
RUS Bull 1728F-700 (2011) Specification for Wood Poles, Stubs,
and Anchor Logs
U.S. DEPARTMENT OF ENERGY (DOE)
Energy Star (1992; R 2006) Energy Star Energy Efficiency
Labeling System (FEMP)
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
47 CFR 15 Radio Frequency Devices
47 CFR 18 (2011) Industrial, Scientific, and Medical
Equipment
UNDERWRITERS LABORATORIES (UL)
UL 1029 (1994; Reprint May 2017) UL Standard for
Safety High-Intensity-Discharge Lamp Ballasts
UL 1310 (2011; Reprint Dec 2014) UL Standard for
Safety Class 2 Power Units
UL 1598 (2008; Reprint Oct 2012) Luminaires
UL 773 (1995; Reprint Jul 2015) Standard for Plug-
In, Locking Type Photocontrols for Use with
Area Lighting
UL 773A (2016) Standard for Nonindustrial
Photoelectric Switches for Lighting Control
UL 8750 (2015; Reprint Aug 2017) UL Standard for
Safety Light Emitting Diode (LED) Equipment
for Use in Lighting Products
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 56 00 Page 9
UL 916 (2007; Reprint Aug 2014) Standard for Energy
Management Equipment
UL 935 (2001; Reprint Aug 2014) Standard for
Fluorescent-Lamp Ballasts
1.2 RELATED REQUIREMENTS
***************************************************************************
NOTE: Select applicable tri-service, Army, Navy, Air
Force or NASA specification section reference(s).
***************************************************************************
Materials not considered to be luminaires or lighting equipment are
specified in Section(s) [33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION] [33
71 01.00 40 OVERHEAD TRANSMISSION AND DISTRIBUTION] [33 71 01 OVERHEAD
TRANSMISSION AND DISTRIBUTION]. Luminaires and accessories installed in
interior of buildings are specified in Section [26 51 00 INTERIOR LIGHTING]
[26 51 00.00 40 INTERIOR LIGHTING].
1.3 DEFINITIONS
***************************************************************************
NOTE: Delete definitions that are not applicable to
project.
***************************************************************************
a. Unless otherwise specified or indicated, electrical and electronics
terms used in these specifications, and on the drawings shall be as
defined in IEEE 100 and IES RP-16.
[b. For HID, fluorescent, and induction luminaire light sources, "Average
Rated Life" is the time after which 50 percent of a large group of
light sources will have failed and 50 percent will have survived under
normal operating conditions.]
[c. For LED luminaire light sources, "Useful Life" is the operating hours
before reaching 70 percent of the initial rated lumen output (L70) with
no catastrophic failures under normal operating conditions. This is
also known as 70 percent "Rated Lumen Maintenance Life" as defined in
IES LM-80.]
[d. The "Groundline Section" of wood poles is that portion of the pole
between 305 mm (one foot) above, and 610 mm (2 feet) below the
groundline.]
1.4 SUBMITTALS
***************************************************************************
NOTE: Review Submittal Description (SD) definitions
in Section 01 33 00 SUBMITTAL PROCEDURES and edit the
following list to reflect only the submittals
required for the project. Submittals should be kept
to the minimum required for adequate quality control.
The Guide Specification technical editors have
designated those items that require Government
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 56 00 Page 10
approval, due to their complexity or criticality,
with a "G". Generally, other submittal items can be
reviewed by the Contractor's Quality Control System.
Only add a “G” to an item, if the submittal is
sufficiently important or complex in context of the
project.
For submittals requiring Government approval on Army
projects, a code of up to three characters within the
submittal tags may be used following the "G"
designation to indicate the approving authority.
Recommended codes for Army projects are "RE" for
Resident Engineer approval, "ED" for Engineering
approval, and "AE" for Architect-Engineer approval.
Codes following the "G" typically are not used for
Navy projects.
Use the "S" classification only in SD-11 Closeout
Submittals. The "S" following a submittal item
indicates that the submittal is required for the
Sustainability eNotebook to fulfill federally
mandated sustainable requirements in accordance with
Section 01 33 29 SUSTAINABILITY REPORTING.
Submittal items not designated with a "G" are
considered as being for information only for Army
projects and for Contractor Quality Control approval
for Navy projects.
***************************************************************************
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are [for Contractor Quality Control
approval] [for information only]. [When used, a designation following the
"G" designation identifies the office that will review the submittal for the
Government.] Submittals with an "S" are for inclusion in the Sustainability
eNotebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
***************************************************************************
NOTE: Required for all area and roadway designs.
Contractor shall provide calculations to verify
luminaires and design layout meet required
illumination and photometric values of the design.
This requirement has been added as a quality
assurance step. Absolute photometry of LED
luminaires provided by IES LM-79 data should provide
accurate values to assure contractor's luminaires
meet the standards of the initial design.
***************************************************************************
Photometric Plan; G[, [_____]]
LED Luminaire Warranty; G[, [_____]]
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 56 00 Page 11
SD-02 Shop Drawings
Luminaire drawings; G[, [_____]]
Poles; G[, [_____]]
SD-03 Product Data
***************************************************************************
NOTE: Designer may include Energy Star label for LED
luminaire if it is confirmed that adequate
availability exists of Energy Star products that are
appropriate for the project.
***************************************************************************
[[LED,] [HID,] [LPS,] [Fluorescent,][ and] [Induction] [and LED]
Luminaires; G[, [_____]]]
[Energy Star label for LED luminaire product; S]
Luminaire Light Sources; G[, [_____]]
***************************************************************************
NOTE: Choose "Ballasts" for HID, LPS and
fluorescent; "Generators" for induction; and "Power
Supply Units (Drivers)" for LED applications.
***************************************************************************
Luminaire[ Ballasts,][ Generators][ and][ Power Supply Units
(Drivers)]; G[, [_____]]
Lighting contactor; G[, [_____]]
Time switch; G[, [_____]]
Lighting Control Relay Panel; G[, [_____]]
Motion Sensor; G[, [_____]]
Bi-level HID Controller; G[, [_____]]
Photocell; G[, [_____]]
Concrete poles; G[, [_____]]
Aluminum poles; G[, [_____]]
Steel poles; G[, [_____]]
Fiberglass poles; G[, [_____]]
Brackets
Obstruction Marker Luminaires; G[, [_____]]
[SD-04 Samples
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 56 00 Page 12
***************************************************************************
NOTE: Samples involve additional shipping cost. Use
only for special luminaires or for an item for which
a large quantity is required on a project.
***************************************************************************
[LED, ][HID,] [LPS,] [Fluorescent,][ and] [Induction] [and] [LED]
Luminaires; G[, [_____]]
Submit one sample of each luminaire type[, complete with light
source and ballast, generator or power supply unit].[ Submit one
sample for each item other than luminaires.] Sample will be
returned to the Contractor for installation in the project work.
]SD-05 Design Data
Design Data for luminaires; G[, [_____]]
SD-06 Test Reports
LED Luminaire - IES LM-79 Test Report; G[, [_____]]
LED Light Source - IES LM-80 Test Report; G[, [_____]]
[Pressure treated wood pole quality
][Tests for fiberglass poles; G[, [_____]]
]Operating test
Submit operating test results as stated in paragraph entitled
"Field Quality Control."
SD-07 Certificates
Luminaire Useful Life Certificate; G[, [_____]]
Submit certification from the manufacturer indicating the expected
useful life of the luminaires provided. The useful life shall be
directly correlated from the IES LM-80 test data using procedures
outlined in IES TM-21. Thermal properties of the specific
luminaire and local ambient operating temperature and conditions
shall be taken into consideration.
SD-08 Manufacturer's Instructions
Concrete poles
Submit instructions prior to installation.
Fiberglass poles
Submit instructions prior to installation.
SD-10 Operation and Maintenance Data
Electronic Ballast Warranty
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 56 00 Page 13
Operational Service
Submit documentation that includes contact information, summary of
procedures, and the limitations and conditions applicable to the
project. Indicate manufacturer's commitment to reclaim materials
for recycling and/or reuse.
1.5 QUALITY ASSURANCE
1.5.1 Drawing Requirements
1.5.1.1 Luminaire Drawings
Include dimensions, effective projected area (EPA), accessories, and
installation and construction details. Photometric data, including zonal
lumen data, average and minimum ratio, aiming diagram, and[ computerized]
candlepower distribution data shall accompany shop drawings.
[1.5.1.2 Poles
Include dimensions, wind load determined in accordance with AASHTO LTS, pole
deflection, pole class, and other applicable information.[ For concrete
poles, include: section and details to indicate quantities and position of
prestressing steel, spiral steel, inserts, and through holes; initial
prestressing steel tension; and concrete strengths at release and at 28
days.]
][1.5.2 Pressure Treated Wood Pole Quality
Ensure the quality of pressure treated wood poles. Furnish an inspection
report (for wood poles) of an independent inspection agency, approved by the
Contracting Officer, stating that offered products comply with AWPA U1 and
RUS Bull 1728F-700 standards. The RUS approved Quality Mark "WQC" on each
pole will be accepted, in lieu of inspection reports, as evidence of
compliance with applicable AWPA treatment standards.
]1.5.3 Photometric Plan
For LED luminaires, include computer-generated photometric analysis of the
"designed to" values for the "end of useful life" of the luminaire
installation using a light loss factor of 0.7. For LED and all other types
of luminaires, the submittal shall include the following:
Horizontal illuminance measurements at finished grade, taken at a maximum
of every 3050 mm (10 feet).
Vertical illuminance measurements at 1500 mm (5 feet) above finished grade.
Minimum and maximum lux (footcandle) levels.
Average maintained lux (footcandle) level.
Maximum to minimum ratio for horizontal illuminance only.
1.5.4 Design Data for Luminaires
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 56 00 Page 14
a. Provide distribution data according to IES classification type as
defined in IES HB-10.
b. Shielding as defined by IES RP-8 or B.U.G. rating for the installed
position as defined by IES TM-15.
c. Provide safety certification and file number for the luminaire family.
Include listing, labeling and identification per NFPA 70 (NEC).
Applicable testing bodies are determined by the US Occupational Safety
Health Administration (OSHA) as Nationally Recognized Testing
Laboratories (NRTL) and include: CSA (Canadian Standards Association),
ETL (Edison Testing Laboratory), and UL (Underwriters Laboratories).
d. Provide long term lumen maintenance projections for each LED luminaire
in accordance with IES TM-21. Data used for projections shall be
obtained from testing in accordance with IES LM-80.
e. Provide wind loading calculations for luminaires mounted on poles.
Weight and effective projected area (EPA) of luminaires and mounting
brackets shall not exceed maximum rating of pole as installed in
particular wind zone area.
1.5.5 LED Luminaire - IES LM-79 Test Report
Submit test report on manufacturer's standard production model luminaire.
Submittal shall include all photometric and electrical measurements, as well
as all other pertinent data outlined under "14.0 Test Report" in IES LM-79.
1.5.6 LED Light Source - IES LM-80 Test Report
Submit report on manufacturer's standard production LED package, array, or
module. Submittal shall include:
a. Testing agency, report number, date, type of equipment, and LED light
source being tested.
b. All data required by IES LM-80.
1.5.6.1 Test Laboratories
Test laboratories for the IES LM-79 and IES LM-80 test reports shall be one
of the following:
a. National Voluntary Laboratory Accreditation Program (NVLAP) accredited
for solid-state lighting testing as part of the Energy-Efficient
Lighting Products laboratory accreditation program.
b. One of the qualified labs listed on the Department of Energy - Energy
Efficiency & Renewable Energy, Solid-State Lighting web site.
c. A manufacturer's in-house lab that meets the following criteria:
1. Manufacturer has been regularly engaged in the design and
production of high intensity discharge roadway and area luminaires
and the manufacturer's lab has been successfully certifying these
fixtures for a minimum of 15 years.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 56 00 Page 15
2. Annual equipment calibration including photometer calibration in
accordance with National Institute of Standards and Technology.
[1.5.7 \[Tests for Fiberglass Poles
a. Ultraviolet resistance tests: Perform according to ASTM G154 using a
UV-B light source having a 313 nanometer wavelength, operated at 54
degrees C (130 degrees F), cycling the light source on for 4 hours and
off for 4 hours for a total test period of 1500 hours minimum with the
following results:
Fiber exposure: None
Crazing: None
Checking: None
Chalking: None
Color: May dull slightly
b. Flexural strength and deflection test: Test loading shall be as a
cantilever beam with pole butt as fixed end and a force simulating wind
load at the free end.
\]]1.5.8 Regulatory Requirements
In each of the publications referred to herein, consider the advisory
provisions to be mandatory, as though the word, "shall" had been substituted
for "should" wherever it appears. Interpret references in these
publications to the "authority having jurisdiction," or words of similar
meaning, to mean the Contracting Officer. Equipment, materials,
installation, and workmanship shall be in accordance with the mandatory and
advisory provisions of NFPA 70 unless more stringent requirements are
specified or indicated.
1.5.9 Standard Products
Provide materials and equipment that are products of manufacturers regularly
engaged in the production of such products which are of equal material,
design and workmanship. Products shall have been in satisfactory commercial
or industrial use for 2 years prior to bid opening. The 2-year period shall
include applications of equipment and materials under similar circumstances
and of similar size. The product shall have been on sale on the commercial
market through advertisements, manufacturers' catalogs, or brochures during
the 2-year period. Where two or more items of the same class of equipment
are required, these items shall be products of a single manufacturer;
however, the component parts of the item need not be the products of the
same manufacturer unless stated in this section.
1.5.9.1 Alternative Qualifications
Products having less than a 2-year field service record will be acceptable
if the manufacturer has been regularly engaged in the design and production
of high intensity discharge roadway and area luminaires for a minimum of 15
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 56 00 Page 16
years. Products shall have been in satisfactory commercial or industrial
use for 15 years prior to bid opening. The product shall have been on sale
on the commercial market through advertisements, manufacturers' catalogs, or
brochures during the 15-year period.
1.5.9.2 Material and Equipment Manufacturing Date
Products manufactured more than 1 year prior to date of delivery to site
shall not be used, unless specified otherwise.
[1.6 DELIVERY, STORAGE, AND HANDLING OF POLES
[1.6.1 Wood Poles
Do not store poles on ground. Stack poles stored for more than 2 weeks on
decay-resisting skids arranged to support the poles without producing
noticeable distortion. Store poles to permit free circulation of air; the
bottom poles in the stack shall be at least 305 mm (one foot) above ground
level and growing vegetation. Do not permit decayed or decaying wood to
remain underneath stored poles. Do not drag treated poles along the ground.
Do not use pole tongs, cant hooks, and other pointed tools capable of
producing indentation more than 25 mm (one inch) in depth in handling the
poles. Do not apply tools to the groundline section of any pole.
][1.6.2 Concrete Poles
Do not store poles on ground. Support poles so they are at least 305 mm
(one foot) above ground level and growing vegetation.
][1.6.3 [Fiberglass] [Aluminum] [Steel] Poles
Do not store poles on ground. Support poles so they are at least 305 mm
(one foot) above ground level and growing vegetation. Do not remove
factory-applied pole wrappings until just before installing pole.
]]1.7 WARRANTY
The equipment items shall be supported by service organizations which are
reasonably convenient to the equipment installation in order to render
satisfactory service to the equipment on a regular and emergency basis
during the warranty period of the contract.
[1.7.1 LED Luminaire Warranty
***************************************************************************
NOTE: Choose this paragraph for LED applications.
***************************************************************************
Provide Luminaire Useful Life Certificate.
The equipment items shall be supported by service organizations which are
reasonably convenient to the equipment installation in order to render
satisfactory service to the equipment on a regular and emergency basis
during the warranty period of the contract.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 56 00 Page 17
a. Provide a written five year on-site replacement warranty for material,
fixture finish, and workmanship. On-site replacement includes
transportation, removal, and installation of new products.
1. Finish warranty shall include warranty against failure and against
substantial deterioration such as blistering, cracking, peeling,
chalking, or fading.
2. Material warranty shall include:
(a) All power supply units (drivers).
(b) Replacement when more than 10 percent of LED sources in any
lightbar or subassembly(s) are defective or non-starting.
b. Warranty period must begin on date of beneficial occupancy. Contractor
shall provide the Contracting Officer signed warranty certificates
prior to final payment.
][1.7.2 Electronic Ballast Warranty
***************************************************************************
NOTE: Choose this paragraph for HID, LPS, and
fluorescent applications.
***************************************************************************
Furnish the electronic ballasts manufacturer's warranty. The warranty
period shall not be less than five (5) years from the date of manufacture.
Ballast assembly in the lighting fixture, transportation, and on-site
storage shall not exceed twelve (12) months, thereby permitting four (4)
years of the five (5) year warranty to be in service and energized. The
warranty shall state that the malfunctioning ballast shall be exchanged by
the manufacturer and promptly shipped to the using Government facility. The
replacement ballast shall be identical to, or an improvement upon, the
original design of the malfunctioning ballast.
]1.8 OPERATIONAL SERVICE
***************************************************************************
NOTE: Maintenance agreements are standard practice
in the building industry. Take-back programs refer
to programs in which the product manufacturer "takes-
back" scrap material and/or packaging associated with
its product. Under a green lease, when the customer
no longer requires the use of the particular product
or requires an updated model, the manufacturer is
obligated to reclaim it and refurbish it or
disassemble it for recycling as appropriate. Using
one of these manufacturer's services contributes to
the following LEED credit: MR2may contribute to
achievement of sustainability requirements.
NOTE: This is optional for Army Projects.
***************************************************************************
Coordinate with manufacturer for [maintenance agreement] [take-back
program]. Collect information from the manufacturer about [maintenance
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 56 00 Page 18
agreement] [green lease] options, and submit to Contracting Officer.
Services shall reclaim materials for recycling and/or reuse. Services shall
not deposit materials in landfills or burn reclaimed materials. Indicate
procedures for compliance with regulations governing disposal of mercury.
When such a service is not available, local recyclers shall be sought after
to reclaim the materials.
PART 2 PRODUCTS
2.1 PRODUCT COORDINATION
***************************************************************************
NOTE: Choose bracketed options as applicable for
Army, Navy or Air Force project.
***************************************************************************
Products and materials not considered to be luminaires, equipment or
accessories are specified in[ Section 33 71 02 UNDERGROUND ELECTRICAL
DISTRIBUTION,][ Section 33 71 01 OVERHEAD TRANSMISSION AND DISTRIBUTION,][
and Section 26 20 00 INTERIOR DISTRIBUTION SYSTEM.] Luminaires and
associated equipment and accessories for interior applications are specified
in Section 26 51 00 INTERIOR LIGHTING.
2.2 [LED, ][HID,] [LPS,] [FLUORESCENT,][ AND] [INDUCTION] [AND] [LED]
LUMINAIRES
***************************************************************************
NOTE: XL series luminaire plates and details shown
on project plans are provided for a visual
perspective of the luminaire desired. Shapes,
dimensions and other requirements shown are not
intended to restrict selection to luminaires of a
specific manufacturer. Luminaires producing
comparable or competitive photometric results on a
given plan area, and of similar or equal material,
finish and craftsmanship will be considered for
approval.
Choose appropriate bracketed options for type of
luminaires being used.
NOTE: Designer may include Energy Star label for LED
luminaire if it is confirmed that adequate
availability exists of Energy Star products that are
appropriate for the project.
***************************************************************************
UL 1598, NEMA C82.77 and UL 8750. Provide luminaires as indicated in
luminaire schedule and XL plates or details on project plans. Provide
luminaires complete with light sources of quantity, type, and wattage
indicated. All luminaires of the same type shall be provided by the same
manufacturer. [Provide Energy Star labeled LED luminaire product. Provide
proof of Energy Star label for LED luminaire product.]
2.2.1 General Requirements
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 56 00 Page 19
a.[ LED luminaire housings shall be die cast or extruded aluminum.][
Housings for luminaires other than LED shall be die cast, extruded, or
fabricated aluminum. Fabricated aluminum housings shall have all seams
and corners internally welded to resist weathering, moisture and dust.]
***************************************************************************
NOTE: 40 degrees C (104 degrees F) is "standard"
upper level rating of most LED luminaires. Choose
higher 50 degrees C (122 degrees F) rating when an
installation location warrants a higher ambient
temperature rating and the additional cost it incurs.
***************************************************************************
[b. LED luminaires shall be rated for operation within an ambient
temperature range of minus 30 degrees C (minus 22 degrees F) to[ 40
degrees C (104 degrees F)][ 50 degrees C (122 degrees F)].
]c. Luminaires shall be UL listed for wet locations per UL 1598.[ Optical
compartment for LED luminaires shall be sealed and rated a minimum of
IP65 per NEMA IEC 60529.]
[d. LED luminaires shall produce a minimum efficacy as shown in the
following table, tested per IES LM-79. Theoretical models of initial
raw LED lumens per watt are not acceptable.
Application Luminaire Efficacy in
Lumens per Watt
Exterior Pole/Arm-Mounted Area and
Roadway Luminaires
65
Exterior Pole/Arm-Mounted Decorative
Luminaires
65
Exterior Wall-Mounted Area Luminaires 60
Bollards 35
Parking Garage Luminaires 70
]e. Luminaires shall have IES distribution and NEMA field angle
classifications as indicated in luminaire schedule on project plans per
IES HB-10.
f. Housing finish shall be baked-on enamel, anodized, or baked-on powder
coat paint. Finish shall be capable of surviving ASTM B117 salt fog
environment testing for 2500 hours minimum without blistering or
peeling.
***************************************************************************
NOTE: Lighting zones referenced below are taken from
the joint IDA/IES Model Lighting Ordinance, published
in 2011. Zones included range from LZ-0 through LZ-4,
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 56 00 Page 20
and outline requirements for minimal to very high
ambient light levels respectively.
***************************************************************************
g. Luminaires shall not exceed the following IES TM-15 Backlight, Uplight
and Glare (B.U.G.) ratings:
1. Maximum Backlight (B) rating shall be determined by lighting zone
in which luminaire is placed.
2. Maximum Uplight (U) rating shall be U0.
3. Maximum Glare (G) rating shall be determined by lighting zone in
which luminaire is placed.
h. Luminaires shall be fully assembled and electrically tested prior to
shipment from factory.
i. The finish color shall be as indicated in the luminaire schedule or
detail on the project plans.
[j. Luminaire arm bolts shall be 304 stainless steel or zinc-plated steel.
]k. Luminaire lenses shall be constructed of[ clear][ frosted] tempered
glass or UV-resistant acrylic.[ Provide polycarbonate vandal-resistant
lenses as indicated.]
[l. The wiring compartment on pole-mounted, street and area luminaires
must be accessible without the use of hand tools to manipulate small
screws, bolts, or hardware.
]m. Incorporate modular electrical connections, and construct luminaires
to allow replacement of all or any part of the optics, heat sinks,
power supply units, ballasts, surge suppressors and other electrical
components using only a simple tool, such as a manual or cordless
electric screwdriver.
n. Luminaires shall have a nameplate bearing the manufacturer's name,
address, model number, date of manufacture, and serial number securely
affixed in a conspicuous place. The nameplate of the distributing
agent will not be acceptable.
[o. Roadway and area luminaires shall have an integral tilt adjustment of
plus or minus 5 degrees to allow the unit to be leveled in accordance
with ANSI C136.3.
]p. Luminaire must pass 3G vibration testing in accordance with NEMA
C136.31.
q. All factory electrical connections shall be made using crimp, locking,
or latching style connectors. Twist-style wire nuts are not
acceptable.
2.2.2 Luminaire Light Sources
***************************************************************************
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 56 00 Page 21
NOTE: The Energy Independence and Security Act
(EISA) of 2007, Title III, Subtitle B, Section 324
limits the use of certain metal halide light sources
and ballasts. Do not specify any of the light
sources listed in that document.
***************************************************************************
[2.2.2.1 High Pressure Sodium (HPS) Light Sources
***************************************************************************
NOTE: For Army and Navy projects, high pressure
sodium light sources are not recommended for new
installations, but can be used where existing
conditions and continuity of source type make their
use necessary. For Air Force projects, high pressure
sodium light sources should be avoided for new
installations if possible and considered only when a
more energy efficient alternative is not available to
meet photometric and performance requirements.
***************************************************************************
ANSI ANSLG C78.42 and NEMA ANSLG C78.380. HPS light sources shall have a
minimum average rated life of 24,000 hours, minimum color rendering index
(CRI) of 21, and a minimum correlated color temperature (CCT) of 1900
degrees K. Provide type and wattage as indicated in luminaire schedule on
project plans. Light sources shall be compliant with the most current TCLP
test procedure per NEMA C78.LL 3 at the time of manufacture.
][2.2.2.2 Metal Halide (MH) Light Sources
***************************************************************************
NOTE: Metal halide light sources are available in a
wide variety of configurations and wattages. Only a
few typical examples are shown below. Utilize pulse-
start technology for all wattages as they become
available. They have longer life and better lumen
maintenance. Some are rated for vertical use only,
so be wary of light source orientation. Like other
HID sources, re-strike time is a factor to consider.
PAR envelopes are an efficient choice for lower
wattage applications, but must be specified with beam
type and angle. In most cases, choose light sources
rated for use in an enclosed luminaire. Typically,
choose sources with highest CRI and longest life, and
closest CCT to match LED temperature of no greater
than 4300 degrees K.
***************************************************************************
ANSI/ANSLG C78.43, NEMA ANSLG C78.44, ANSI C78.1381, and NEMA ANSLG C78.380.
Provide type and wattage as indicated in luminaire schedule on project
plans. Open fixtures are prohibited unless provided with a mechanism to
utilize only Type O light sources and prohibit the use of Type E or S light
sources. Light sources shall be specifically suited to operate in the
burning position which they are installed, and shall be compliant with the
most current TCLP test procedure per NEMA C78.LL 3 at the time of
manufacture.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 56 00 Page 22
[a. All probe-start metal halide light sources shall utilize [a] [an] BT
[ED][ET]-type envelope, with an E-39[_____] screw base. The arc tube
shall be a ceramic[-fused quartz]-type, with a rating of
[400][1000][_____] watts, having a minimum initial output of
[35,000][105,000][_____] lumens. The correlated color temperature
(CCT) shall be [3000][_____] degrees K, with a minimum color rendering
index (CRI) of [65][_____]. The minimum average rated life shall be
[15,000][12,000] hours, based on 10 hours operation per start.
][b. All pulse-start metal halide light sources shall utilize [a] [an]
[Tube][PAR][ED][ET][BD]-type envelope, [G-12][E-26 Medium][E-39][mogul]
base, ceramic[fused quartz] arc tube type, rated at
[70][100][250][_____] watts, with a minimum initial output of
[6300][6200][21,000][_____] lumens. Correlated color temperature (CCT)
shall be [3000][_____] degrees K, minimum color rendering index (CRI)
shall be [80] [_____], with a minimum average rated life of [12,000]
hours, based on 10 hours operation per start.
]][2.2.2.3 Low Pressure Sodium (LPS) Light Sources
***************************************************************************
NOTE: Use low-pressure sodium light sources only in
unique applications such as sea turtle nesting
habitats and only when approved by the state or local
governing authority.
***************************************************************************
ANSI ANSLG C78.41 and NEMA ANSLG C78.380. Low Pressure Sodium light sources
shall have average rated life of 18,000 hours minimum and a correlated color
temperature (CCT) of 1700 degrees K. Provide in a T17 or T21 type envelope
with a D.C. Bayonet type base rated at [55][90][135][180] watts, with an
initial output of [7800][14300][22600][32000] lumens.
][2.2.2.4 Fluorescent Light Sources
[a. T5HO fluorescent light sources shall have miniature bi-pin bases, be
low-mercury type, in nominal length(s) of 1170 mm (46 in) 1475 mm (58
in), rated at [54][80] watts, with minimum initial output of [4450]
[6150] lumens. Light source correlated color temperature (CCT) shall
be [3500] [4100] degrees K, with a minimum CRI value of 75, and a
minimum average rated life of [25,000][_____] hours, based on 3 hours
operation per start. Light sources shall be compliant with the most
current TCLP test procedure per ANSI/NEMA C78.LL 1256 at time of
manufacture.
][b. T8 fluorescent light sources shall have medium bi-pin bases, be low-
mercury type, in nominal length(s) of 1220 mm (48 in) 2438 mm (96 in),
rated at [32] [59] watts, with minimum initial output of [2800] [5700]
lumens. Light source correlated color temperature (CCT) shall be
[3500] [4100] degrees K, with a minimum CRI value of 75, and a minimum
average rated life of [30,000][_____] hours, based on 3 hours operation
per start. Light sources shall be compliant with the most current TCLP
test procedure per ANSI/NEMA C78.LL 1256 at time of manufacture.
][c. Compact fluorescent (CFL) light sources shall be 4-pin base, low-
mercury, programmed-start, energy-savings type, rated at [26] [32]
[42][57][70] watts, correlated color temperature of [3500] [4100]
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 56 00 Page 23
degrees K, minimum CRI of 82, with an average rated life of
[16,000][_____] hours minimum. Light sources shall be compliant with
the most current TCLP test procedure per ANSI/NEMA C78.LL 1256 at time
of manufacture.
]][2.2.2.5 Induction Light Sources
***************************************************************************
NOTE: Induction light sources have high
efficiencies, superior color rendering, instant
on/off switching ability, and extremely long lives.
Relamping is typically in the 60,000 plus hour range
and because of this, savings in maintenance make
these a viable solution to certain outdoor
applications. Typically select CCT of 4000 degrees K
to match LED and other exterior light sources.
***************************************************************************
Induction light sources shall consist of an electrodeless, inductively-
coupled, phosphor-coated fluorescent envelope rated at [55] [85] [100] [150]
[165] watts, color temperature of [3000/3500] [4000/4100] [5000] degrees K,
minimum CRI of 80, with an average rated life of 100,000 hours minimum based
on 3 hours operation per start.
][2.2.2.6 LED Light Sources
***************************************************************************
NOTE: Typically, select a CCT in the range of 4000
degrees K. Some studies have shown that luminaires
with higher CCT values approaching 6500 degrees K
attribute to skyglow, cause erratic behavior in some
animals, and possibly cause circadium rhythm
abnormalities. Although all of these issues have not
been fully documented, a lower color temperature is
recommended.
***************************************************************************
a. Correlated Color Temperature (CCT) shall be in accordance with NEMA
ANSLG C78.377:
[Nominal CCT: 4000 degrees K: 3985 plus or minus 275 degrees K
]b. Color Rendering Index (CRI) shall be:
Greater than or equal to [70] [_____] for 4000 degrees K light sources.
c. Color Consistency:
Manufacturer shall utilize a maximum 4-step MacAdam ellipse binning
tolerance for color consistency of LEDs used in luminaires.
]2.2.3 Luminaire[ Ballasts,][ Generators][ and][ Power Supply Units
(Drivers)]
***************************************************************************
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 56 00 Page 24
NOTE: Choose "Ballasts" for HID, LPS and
fluorescent; "Generators" for induction; and "Power
Supply Units (Drivers)" for LED applications.
***************************************************************************
[2.2.3.1 HID Ballasts
2.2.3.1.1 Electronic HID Ballasts
NEMA ANSLG C82.14, IEEE C62.41, 47 CFR 18 and shall meet the following
requirements:
a. Minimum power factor shall be greater than 90 percent.
b. Input voltage shall be 120-277 volts plus or minus 10 percent.
c. Shall have end of life circuitry to prevent ballast from operating if
light source is inoperable.
d. Shall have a sound rating of A and a lamp current crest factor less
than 1.5.
e. Input current total harmonic distortion shall be less than 15 percent.
f. Minimum starting temperature shall be minus 30 degrees C (minus 22
degrees F).
g. Shall be thermally protected to prevent overheating.
h. Shall be UL listed and RoHS compliant.
2.2.3.1.2 Magnetic HID and LPS Ballasts
***************************************************************************
NOTE: For metal halide luminaires, provide
electronic ballasts whenever available. Otherwise,
constant wattage autotransformer (CWA) or high
reactance/high power factor (HX-HPF), pulse-start
magnetic ballasts should be specified.
***************************************************************************
ANSI C82.4. Pulse-start constant wattage autotransformer (CWA) type shall
be used when available. Probe-start constant wattage autotransformer (CWA),
high reactance/high power factor (HX-HPF) or regulator type shall be used
for metal halide light sources when pulse-start is not available, and for
high and low pressure sodium light sources. Ballasts shall meet the
following requirements:
a. Shall have minimum Class "H" insulation rating.
b. Shall be designed for 60,000 hours of operation at maximum rated
temperature.
c. Shall have minimum starting temperature for high and low pressure
sodium shall be minus 40 degrees C (minus 40 degrees F), and for metal
halide minus 30 degrees C (minus 22 degrees F).
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 56 00 Page 25
d. Nominal ballast factor shall be 1.0.
e. Capacitors shall have a self-contained bleeder resistor as required by
UL 1029.
f. Oil-filled capacitors shall be housed in an aluminum or corrosion-
resistant steel can and be provided with 6 mm (0.25 in) quick
disconnect terminals.
g. Capacitor maximum case temperature shall be 90 degrees C (194 degrees
F) for oil-filled and 105 degrees C (221 degrees F) for dry film type.
h. Starter/igniter shall provide six months of light source open circuit
operation without failure and be designed to withstand 10,000 hours of
continuous pulsing (not applicable for LPS).
][2.2.3.2 Fluorescent Ballasts
UL 935, NEMA ANSLG C82.11, NFPA 70 and CEC Title 24, with no magnetic core
and coil components, and shall meet the following requirements:
a. Shall provide transient protection as recommended by IEEE C62.41.1 and
IEEE C62.41.2.
b. Shall be programmed-start or instant-start type as indicated in
luminaire schedule on project drawings elsewhere in this specification.
c. Shall be UL listed Class P, have a Class A sound rating, and have a
minimum power factor of 0.98.
d. Shall be designed for the wattage and quantity of light sources powered
in the luminaire specified, and have circuit diagrams and lamp
connection information printed on the exterior of the ballast housing.
e. Shall contain no PCBs and be RoHS compliant.
f. Shall be manufactured in an ISO 9001-certified facility.
g. Shall operate at a frequency greater than 20 kHz minimum, preferably
greater than 40 kHz, and shall have a Lamp Current Crest Factor less
than 1.7.
h. Shall have a light regulation of plus or minus 10 percent of lumen
output when operated within a plus or minus 10 percent range of input
voltage.
i. Shall have a full replacement warranty of 5 years from date of
manufacture for a maximum case temperature of 70 degrees C (158 degrees
F) and 3 years for a maximum case temperature of 90 degrees C (194
degrees F).
j. All ballasts provided to operate 1220 mm (48 in) T8 light sources shall
be NEMA Premium type.
2.2.3.2.1 T5HO Electronic Fluorescent Ballasts
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 56 00 Page 26
Shall be programmed-start type with nominal ballast factor of 1.0, maximum
input current THD of 10 percent, lamp end of life protection circuitry, and
have a minimum starting temperature of minus 18 degree C (0 degree F).
Ballast efficacy factor (BEF), rated at 120 volts shall be:
[Minimum 3.66 for one 24W light source.
][Minimum 1.83 for two 24W light sources.
][Minimum 2.23 for one 39W light source.
][Minimum 1.11 for two 39W light sources.
][Minimum 1.62 for one 54W light source.
][Minimum 0.83 for two 54W light sources.
][Minimum 0.57 for three 54W light sources.
][Minimum 0.42 for four 54W light sources.
]
Input power shall be:
[Maximum 30 watts for one 24W light source.
][Maximum 59 watts for two 24W light sources.
][Maximum 47 watts for one 39W light source.
][Maximum 90 watts for two 39W light sources.
][Maximum 63 watts for one 54W light source.
][Maximum 120 watts for two 54W light sources.
][Maximum 184 watts for three 54W light sources.
][Maximum 240 watts for four 54W light sources.
]
2.2.3.2.2 T8 Electronic Fluorescent Ballasts
Shall be[ programmed-start][ instant-start] type, with minimum ballast
factor of 0.87, maximum current THD of 10 percent, and have a minimum
starting temperature of minus 18 degrees C (0 degrees F).
[For programmed-start ballasts:
Ballast efficacy factor (BEF), rated at 120 volts shall be:
[Minimum 2.9 for one 32 W, 1220 mm (48 in) light source (NEMA
Premium).
][Minimum 1.49 for two 32 W, 1220 mm (48 in) light sources (NEMA
Premium).
][Minimum 1.03 for three 32 W, 1220 mm (48 in) light sources (NEMA
Premium).
][Minimum 0.8 for four 32 W, 1220 mm (48 in) light sources (NEMA
Premium).
]Input power shall be:
[Maximum 35 watts for one 32 W, 1220 mm (48 in) light source (NEMA
Premium).
][Maximum 59 watts for two 32 W, 1220 mm (48 in) light sources
(NEMA Premium).
][Maximum 85 watts for three 32 W, 1220 mm (48 in) light sources
(NEMA Premium).
][Maximum 112 watts for four 32 W, 1220 mm (48 in) light sources
(NEMA Premium).
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 56 00 Page 27
]][For instant-start ballasts:
Ballast efficacy factor (BEF), rated at 120 volts shall be:
[Minimum 2.9 for one 32 W, 1220 mm (48 in) light source (NEMA
Premium).
][Minimum 1.49 for two 32 W, 1220 mm (48 in) light sources (NEMA
Premium).
][Minimum 1.03 for three 32 W, 1220 mm (48 in) light sources (NEMA
Premium).
][Minimum 0.8 for four 32 W, 1220 mm (48 in) light sources (NEMA
Premium).
][Minimum 1.36 for one 59 W, 2438 mm (96 in) light source.
][Minimum 0.77 for two 59 W, 2438 mm (96 in) light sources.
]Input power shall be:
[Maximum 35 watts for one 32 W, 1220 mm (48 in) light source (NEMA
Premium).
][Maximum 59 watts for two 32 W, 1220 mm (48 in) light sources
(NEMA Premium).
][Maximum 85 watts for three 32 W, 1220 mm (48 in) light sources
(NEMA Premium).
][Maximum 112 watts for four 32 W, 1220 mm (48 in) light sources
(NEMA Premium).
][Maximum 72 watts for one 59 W, 2438 mm (96 in) light source.
][Maximum 113 watts for two 59 W, 2438 mm (96 in) light sources.
]]2.2.3.2.3 Compact Fluorescent (CFL) Electronic Ballasts
Shall be programmed start type with ballast factor greater than or equal to
0.98, maximum input current THD of 10 percent, lamp end of life protection
circuitry, and have a minimum starting temperature of minus 18 degrees C (0
degrees F) for primary light source(s).
The ballast efficacy factor rated at 120 volts shall be:
[Minimum 3.64 for one 26W CFL light source.
][Minimum 2.72 for one 32W CFL light source.
][Minimum 2.13 for one 42W CFL light source.
][Minimum 1.56 for one 57W CFL light source.
][Minimum 1.28 for one 70W CFL light source.
]
The input power shall be:
[Maximum 29 watts for one 26W CFL light source.
][Maximum 36 watts for one 32W CFL light source.
][Maximum 46 watts for one 42W CFL light source.
][Maximum 59 watts for one 57W CFL light source.
][Maximum 75 watt for one 70W CFL light source.
]
][2.2.3.3 Induction Generators
Generator shall be connected to, and operate in conjunction with, an
inductive power coupler or coil(s). These in turn activate a glass light
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 56 00 Page 28
source enclosure from either inside or outside of the enclosure. The
generator shall be solid-state, high-frequency (200kHz - 2.67MHz) type, with
a power factor greater than 0.9, a Class A sound rating, a maximum input
current THD of 15 percent, an operating voltage of 120-277V and a minimum
starting temperature of minus 40 degrees C (minus 40 degrees F). Generator
shall be dimmable to 50 percent of lumen output and be UL, CSA, and RoHS
compliant.
][2.2.3.4 LED Power Supply Units (Drivers)
UL 1310. LED Power Supply Units (Drivers) shall meet the following
requirements:
a. Minimum efficiency shall be 85 percent.
b. Drive current to each individual LED shall not exceed 600 mA, plus or
minus 10 percent.
***************************************************************************
NOTE: 40 degrees C (104 degrees F) is "standard"
upper level rating of most LED luminaires. Choose
higher 50 degrees C (122 degrees F) rating when an
installation location warrants a higher ambient
temperature rating and the additional cost it incurs.
***************************************************************************
c. Shall be rated to operate between ambient temperatures of minus 30
degrees C (minus 22 degrees F) and 40 degrees C (104 degrees F)[ 50
degrees C (122 degrees F)].
d. Shall be designed to operate on the voltage system to which they are
connected, typically ranging from 120 V to 480 V nominal.
e. Operating frequency shall be: 50 or 60 Hz.
f. Power Factor (PF) shall be greater than or equal to 0.90.
g. Total Harmonic Distortion (THD) current shall be less than or equal to
20 percent.
h. Shall meet requirements of 47 CFR 15, Class B.
i. Shall be RoHS-compliant.
j. Shall be mounted integral to luminaire. Remote mounting of power supply
is not allowed.
k. Power supplies in luminaires mounted under a covered structure, such as
a canopy, or where otherwise appropriate shall be UL listed with a
sound rating of A.
[l. Shall be dimmable, and compatible with a standard dimming control
circuit of 0 - 10V or other approved dimming system.
]m. Shall be equipped with over-temperature protection circuit that turns
light source off until normal operating temperature is achieved.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 56 00 Page 29
]2.2.4 LED Luminaire Surge Protection
Provide surge protection integral to luminaire to meet C Low waveforms as
defined by IEEE C62.41.2, Scenario 1, Location Category C.
[2.3 OBSTRUCTION MARKER LUMINAIRES
***************************************************************************
NOTE: If no other airfield lighting is required in
project, cut and paste required paragraph on
obstruction marker luminaires in this paragraph. If
other airfield lighting is required, include entire
section in project specifications as noted below.
Designer shall also be aware of a conflict between
LED obstruction luminaires and pilots using night
vision goggles (NVG). The output wavelength and low
heat signature of LED luminaires render them
invisible for pilots using NVG.
Do not use LED obstruction luminaires for Air Force
projects. See Air Force ETL 11-29 "Use of Light-
Emitting Diode (LED) Fixtures in Airfield Lighting
Systems on Air Force Installations and
Enduring/Contingency Locations" for more information.
***************************************************************************
Provide obstruction marker luminaires for facilities as required by the FAA
and in accordance with [ Section 26 56 20.00 10 AIRFIELD AND HELIPORT
LIGHTING AND VISUAL NAVIGATION AIDS] [Section 26 54 21.00 10HELIPAD LIGHTING
AND VISUAL NAVIGATION AIDS][ Section 34 43 00.00 20 AIRFIELD LIGHTING].
]2.4 EXTERIOR LUMINAIRE CONTROLS
***************************************************************************
NOTE: Currently, policy for networked control of
lighting systems are still being developed. Issues
such as security and standard protocols need further
review and certification. So, lighting control
"systems" at this point shall be limited to stand-
alone type, and wireless control strategies shall not
be employed at this time.
Typically, controls shall be provided to turn
luminaires on at dusk and off after a certain time
period, when sufficient daylight is available, or
when illumination is not required.
Provide control at each individual luminaire or by a
single device or system controlling a group of
luminaires.
Use reference to ASHRAE 189.1 in lieu of ASHRAE 90.1
for Army projects.
***************************************************************************
Controls shall comply with[ Section 9 of ASHRAE 90.1 - SI (ASHRAE 90.1 -
IP)] [ASHRAE 189.1].[ Provide a control system interface within each
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 56 00 Page 30
luminaire that is compatible with the energy management or control system
used by the utility department in charge of the project area for control of
site lighting.]
[2.4.1 Photocell
***************************************************************************
NOTE: Cadmium sulfide is the older of the two
technologies. Silicon diode sensors are a solid
state device and more resistant to higher
temperatures and environmental contamination.
Silicon diode type are usually specified when
mounting directly to luminaires, but both types are
proven, reliable technologies.
***************************************************************************
UL 773 or UL 773A. Photocells shall be hermetically sealed,[ cadmium
sulfide][ silicon diode] light sensor type, rated at [_____] watts, [_____]
volts, 50/60 Hz with single-pole, [single][double]-throw contacts.
Photocell shall be designed to fail to the ON position. Housing shall be
constructed of [polycarbonate] [die cast aluminum] [UV stabilized
polypropylene], rated to operate within a temperature range of minus 40 to
70 degrees C (minus 40 to 158 degrees F).[ Photocell shall have a 13 mm
(1/2 in) threaded base for mounting to a junction box or conduit. Provide[
fixed][ swivel] base type housing.][ Photocell shall be twist-lock
receptacle type conforming to NEMA C136.10. Provide with solid brass prongs
and voltage markings and color coding on exterior of housing.] Photocell
shall turn on at 10-30 lux (1-3 footcandles) and turn off at 30 to 150 lux
(3 to 15 footcandles). A time delay shall prevent accidental switching from
transient light sources.[ Provide a directional lens in front of the cell
to prevent fixed light sources from creating a turnoff condition.][ Provide
photocell with metal oxide varistor (MOV) type surge protection.]
][2.4.2 Timeswitch
[Timeswitch shall be electromechanical type with a [24 hour] [7 day]
[astronomic] dial [that changes on/off settings according to seasonal
variations of sunset and sunrise]. Switch shall be powered by an enclosed
synchronous motor with a maximum 3 watt operating rating. Timeswitch
contacts shall be rated for [40] [_____] amps at 120-277 VAC resistive load
in a [SPST][DPST][SPDT][DPST][ normally open (NO)][ normally closed (NC)]
configuration. Switch shall have an automatic spring mechanism to maintain
accurate time for up to 16 hours during a power failure.[ Provide switch
with function that allows automatic control to be skipped on certain
selected days of the week.][ Provide switch with manual bypass or remote
override control.]]
[Timeswitch shall be an electronic type with a[ 24 hour][ 7 day]
[astronomic] programming function [that changes on/off settings according to
seasonal variations of sunset and sunrise], providing a total of [56][_____]
on/off set points. Digital clock display format shall be[ AM/PM 12 hour][24
hour] type. Provide power outage backup for switch utilizing a[ capacitor][
alkaline batteries][ lithium battery] which provides coverage for a minimum
of [7 days][3 years][8 years]. Timeswitch shall provide control to
[1][2][4][_____] channels or loads. Contacts shall be rated for [30]
[_____] amps at 120-277 VAC resistive load in a [SPST][DPST][SPDT][DPST]
[normally open (NO)][normally closed (NC)] configuration. [Provide switch
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 56 00 Page 31
with [function that allows automatic control to be skipped on certain
selected days of the week][manual bypass or remote override
control][daylight savings time automatic adjustment][EEPROM memory
module][momentary function for output contacts][ability for photosensor
input]].]
Timeswitch shall be housed in a surface-mounted, lockable NEMA [1][3R]
enclosure constructed of painted steel or plastic polymer conforming to NEMA
ICS 6.
][2.4.3 Lighting Contactor
NEMA ICS 2. Provide a [mechanically][electrically]-held lighting contactor
[housed in a NEMA [1][3R][4][_____] enclosure conforming to NEMA ICS 6].
Contactor shall have [2][4][6][_____] poles, configured as [normally open
(NO)][normally closed (NC)]. Contacts shall be rated [600] [_____] volts,
[30][_____] amperes for a resistive load. Coil operating voltage shall be
[24][120][277][_____] volts. Contactor shall have silver cadmium oxide
double-break contacts [and coil clearing contacts for mechanically held
contactors] and shall require no arcing contacts. [Provide contactor with
hand-off-automatic [on-off] selector switch.] [Provide contactor as
specified above along with [disconnect switch][circuit breaker] in integral
NEMA [1][3R][_____] enclosure with flange-mounted handle to satisfy
requirement for a "combination lighting contactor" when specified.]
][2.4.4 Lighting Control Relay Panel
***************************************************************************
NOTE: NOTE: When providing a control panel that
interfaces with the building automated control
system, reference IES Technical Memorandum IES TM-23-
11 for technical information on various protocols,
architectures and topologies for such systems.
***************************************************************************
Panel shall consist of a single NEMA [1][3R] [flush][surface]-mounted
enclosure with two separate interior sections; one for Class 1 (branch
circuit) and one for Class 2 (low voltage) wiring. Provide panel with
[8][16][32][_____] relays. Panel shall be designed as [a stand alone][an
automated control system interface] type. The Class 1 section shall contain
the load side of all relays and the incoming branch circuit wiring. The
Class 2 section shall contain the control power transformer (24 volt
output), relays, relay control modules, and control wiring[, and native
BACnet[LONworks] field-programmable application controller for panels
connected to the facility automated control system]. Panel enclosure shall
be constructed of [16][14] gauge cold-rolled steel with baked-on enamel
finish. Panel shall meet requirements of UL 916, ASHRAE 90.1 - SI ( ASHRAE
90.1 - IP), CEC Title 24 and 47 CFR 15.
Relays shall be [1][2]-pole, rated at 20 amperes [300][480] VAC with rated
life of 120,000 mechanical operations minimum.
Relay control module shall be 24 volt, electronic type and control up to 16
separate relays (16 channel) or programmed groups of relays. Provide with
inputs for signals from devices such as photocells, timeclocks, and motion
sensors. [Relay control module with integral timeclock function shall be 24
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 56 00 Page 32
volt, electronic type with LCD display and control up to 8 separate relays
(8 channel)].
][2.4.5 Motion Sensor
NEMA WD 7, UL 773A. Provide [passive infrared][microwave][dual technology
passive infrared/microwave] type sensors with [270][_____] degree coverage,
time delay that can be adjusted from 15 seconds to 15 minutes, and "fail to
ON position" default state. Sensors shall be located to achieve coverage of
areas as indicated on project plans. Coverage patterns shall be derated as
recommended by manufacturer based on mounting height of sensor and any
obstructions such as trees. Do not use gross rated coverage in
manufacturer's product literature. Sensors installed integral to the
luminaire must be provided by the luminaire manufacturer. Sensors shall
have an integral light level sensor that does not allow luminaires to
operate during daylight hours and shall be designed to operate on a voltage
of [120/277 VAC][24 VDC]. [Provide sensors to operate in conjunction with
bi-level controllers that lower HID or LED luminaires to a 50 percent
output.] Sensor shall be [equipped with a threaded base for mounting to a
weatherproof junction box][mounted directly to luminaire].
][2.4.6 Bi-level HID Controller
UL 1598. Provide device to switch full lumen output of HID luminaires to 50
percent output upon receiving 24 VDC signal from motion sensor, photocell or
control system circuit. Device shall be compatible with constant wattage
autotransformer (CWA) ballasts only and have maximum load rating of 1000
watts. Provide controller in a weatherproof housing and mount adjacent to
luminaire on pole or luminaire mounting structure. Controller requires
separate bi-level capacitor[, supplied with luminaire][, supplied with
controller] to operate.
][2.5 POLES
***************************************************************************
NOTE: This specification does not cover decorative
poles or high-mast lighting systems. Poles,
luminaire mounting assemblies, and lowering
mechanisms for high-mast lighting are specially
fabricated and should be individually designed to
suit a specific project. Pole specifications for
high-mast system should, as a minimum, include wind
loading and ultimate strength meeting the loading
requirements of AASHTO LTS. Do not specify embedded
type metal poles for Army facilities.
***************************************************************************
Provide poles designed for wind loading of [161][_____] km/hr ([100][_____]
miles per hour) determined in accordance with AASHTO LTS while supporting
luminaires and all other appurtenances indicated. The effective projected
areas of luminaires and appurtenances used in calculations shall be specific
for the actual products provided on each pole. Poles shall be[ embedded][
anchor]-base type designed for use with[ underground][ overhead] supply
conductors.[ Poles[, other than wood poles,] shall have oval-shaped
handhole having a minimum clear opening of 65 by 130 mm (2.5 by 5 inches).
Handhole cover shall be secured by stainless steel captive screws.][ Metal
poles shall have an internal grounding connection accessible from the
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 56 00 Page 33
handhole near the bottom of each pole.] Scratched, stained, chipped, or
dented poles shall not be installed.
[2.5.1 Concrete Poles
Provide concrete poles conforming to ASTM C1089. Cross-sectional shape
shall be[ round][ or][ multi-sided].
2.5.1.1 Steel Reinforcing
Prestressed concrete pole shafts shall be reinforced with steel prestressing
members. Design shall provide internal longitudinal loading by either
pretensioning or post tensioning of longitudinal reinforcing members.
2.5.1.2 Tensioned Reinforcing
Primary reinforcement steel used for a prestressed concrete pole shaft shall
be tensioned between 60 to 70 percent of its ultimate strength. The amount
of reinforcement shall be such that when reinforcement is tensioned to 70
percent of its ultimate strength, the total resultant tensile force does not
exceed the minimum section compressive strength of the concrete.
2.5.1.3 Coating and Sleeves for Reinforcing Members
Where minimum internal coverage cannot be maintained next to required core
openings, such as handhole and wiring inlet, reinforcing shall be protected
with a vaporproof noncorrosive sleeve over the length without the 13 mm (1/2
inch) concrete coverage. Each steel reinforcing member which is to be post-
tensioned shall have a nonmigrating slipper coating applied prior to the
addition of concrete to ensure uniformity of stress throughout the length of
such member.
2.5.1.4 Strength Requirement
As an exception to the requirements of ASTM C1089, poles shall be naturally
cured to achieve a 28-day compressive strength of 48.23 MPa (7000 psi).
Poles shall not be subjected to severe temperature changes during the curing
period.
2.5.1.5 Shaft Preparation
Completed prestressed concrete pole shaft shall have a hard, smooth,
nonporous surface that is resistant to soil acids, road salts, and attacks
of water and frost, and shall be clean, smooth, and free of surface voids
and internal honeycombing. Poles shall not be installed for at least 15
days after manufacture.
][2.5.2 Aluminum Poles
Provide aluminum poles manufactured of corrosion resistant aluminum alloys
conforming to AASHTO LTS for Alloy 6063-T6 or Alloy 6005-T5 for wrought
alloys and Alloy 356-T4 (3,5) for cast alloys. Poles shall be seamless
extruded or spun seamless type with minimum 4.8 mm (0.188 inch) wall
thickness. Provide a pole grounding connection designed to prevent
electrolysis when used with copper ground wire. Tops of shafts shall be
fitted with a round or tapered cover. Base shall be anchor bolt mounted,
made of cast 356-T6 aluminum alloy in accordance with ASTM B108/B108M and
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 56 00 Page 34
shall be machined to receive the lower end of shaft. Joint between shaft
and base shall be welded. Base cover shall be cast 356-T6 aluminum alloy in
accordance with ASTM B108/B108M. Hardware, except anchor bolts, shall be
either 2024-T4 anodized aluminum alloy or stainless steel.[ Aluminum poles
and brackets for [walkway][_____] lighting shall have a[ uniform satin][
dark anodic bronze][_____] finish to match fixtures and shall not be
painted.] Manufacturer's standard provision shall be made for protecting
the finish during shipment and installation. Minimum protection shall
consist of spirally wrapping each pole shaft with protective paper secured
with tape, and shipping small parts in boxes.
][2.5.3 Steel Poles
AASHTO LTS. Provide steel poles having minimum 11-gage steel with minimum
yield/strength of 331 MPa (48,000 psi) and[ hot-dipped galvanized in
accordance with ASTM A123/A123M][ iron-oxide primed] factory finish.
Provide a pole grounding connection designed to prevent electrolysis when
used with copper ground wire. Pole shall be[ direct set][ anchor bolt
mounted] type. Poles shall have tapered tubular members, either round in
cross section or polygonal.[ Pole shafts shall be one piece. Poles shall
be welded construction with no bolts, rivets, or other means of fastening
except as specifically approved.] Pole markings shall be approximately 900
to 1270 mm (3 to 4 feet) above grade and shall include manufacturer, year of
manufacture, top and bottom diameters, and length.[ Base covers for steel
poles shall be structural quality hot-rolled carbon steel plate having a
minimum yield of 248 MPa (36,000 psi).]
][2.5.4 Wood Poles
***************************************************************************
NOTE: Other wood species which are covered by ATIS
ANSI 05.1 and AWPA may be specified, provided they
are available at the project location. Indicate pole
class and height on the drawings.
***************************************************************************
ATIS ANSI O5.1 and RUS Bull 1728F-700 of[ Southern Yellow Pine][ Douglas
Fir][_____]. Poles shall be gained, bored, and roofed before treatment.
Poles shall be treated full length with chromated copper arsenate (CCA) or
ammoniacal copper arsenate (ACA) according to AWPA U1 as referenced in RUS
Bull 1728F-700. Poles shall be branded by manufacturer with manufacturer's
mark and date of treatment, height and class of pole, wood species,
preservation code, and retention. Place the brand so that the bottom of the
brand or disc is 3050 mm (10 feet) from the pole butt for poles up to 15250
mm (50 feet) long[ and 4270 mm (14 feet) from the butt for poles over 15250
mm (50 feet) long].
][2.5.5 Fiberglass Poles
NEMA C136.20. Designed specifically for supporting luminaires and having
factory-formed cable entrance and handhole. Resin color shall be[ dark
bronze][ as indicated][_____], and pigment shall provide uniform coloration
throughout entire wall thickness. Finish surface shall be pigmented
polyurethane having a minimum dry film thickness of 0.038 mm (1.5 mils).
Polyurethane may be omitted if the surface layer of the pole is inherently
ultraviolet inhibited. Minimum fiberglass content shall be 65 percent with
resin and pigment comprising the other 35 percent material content.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 56 00 Page 35
]][2.6 BRACKETS AND SUPPORTS
ANSI C136.3, ANSI C136.13, and ANSI C136.21, as applicable. Pole brackets
shall be not less than 31.75 mm (1 1/4 inch)[ galvanized steel pipe][
aluminum] secured to pole. Slip-fitter or pipe-threaded brackets may be
used, but brackets shall be coordinated to luminaires provided, and brackets
for use with one type of luminaire shall be identical. Brackets for pole-
mounted street lights shall correctly position luminaire no lower than
mounting height indicated. Mount brackets not less than 7320 mm (24 feet)
above street. Special mountings or brackets shall be as indicated and shall
be of metal which will not promote galvanic reaction with luminaire head.
][2.7 POLE FOUNDATIONS
Anchor bolts shall be steel rod having a minimum yield strength of 344.5 MPa
(50,000 psi); the top 305 mm (12 inches) of the rod shall be galvanized in
accordance with ASTM A153/A153M. Concrete shall be as specified in[ Section
03 30 00 CAST-IN-PLACE CONCRETE][ Section 03 30 00.00 10 CAST-IN-PLACE
CONCRETE].
]2.8 EQUIPMENT IDENTIFICATION
2.8.1 Manufacturer's Nameplate
Each item of equipment shall have a nameplate bearing the manufacturer's
name, address, model number, and serial number securely affixed in a
conspicuous place; the nameplate of the distributing agent will not be
acceptable.
2.8.2 Labels
***************************************************************************
NOTE: Labeling of lighting components is an
inexpensive and effective method for helping
facilities personnel properly operate and maintain
the lighting systems. The labels shall be easy to
read when standing next to the equipment, and durable
to match the life of the equipment to which they are
attached. Refer to the FEMP guidelines for lighting
at
http://www.eere.energy.gov/femp/technologies/eep_ligh
ting_guidance.cfm.
***************************************************************************
Provide labeled luminaires in accordance with UL 1598 requirements.
Luminaires shall be clearly marked for operation of specific light sources
and ballasts according to proper light source type. The following light
source characteristics shall be noted in the format "Use Only _____":
***************************************************************************
NOTE: Choose requirements as applicable for project.
***************************************************************************
[a. Light source tube diameter code (e.g. T-5, T-8), tube quantity
configuration (e.g. twin, quad, triple), base type (e.g. G24q-2, GX 24
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 56 00 Page 36
q-4), and nominal wattage for fluorescent and compact fluorescent
luminaires.
][b. Light source type, wattage, bulb type (e.g. ED17, BD56) and coating
(clear or coated) for HID luminaires.
][c. Start type (e.g. programmed-start, rapid-start, instant-start) for
fluorescent and compact fluorescent luminaires.
][d. ANSI ballast type (e.g. M98, M57) for HID luminaires.
]e. Correlated color temperature (CCT) and color rendering index (CRI) for
all luminaires.
Markings related to lamp type shall be clear and located to be readily
visible to service personnel, but unseen from normal viewing angles when
lamps are in place.[ Ballasts shall have clear markings indicating multi-
level outputs and indicate proper terminals for the various outputs.]
2.9 FACTORY APPLIED FINISH
***************************************************************************
NOTE: This paragraph covers only the basic painting
requirements for most electrical equipment. Include
any special finishes for high or low temperatures and
corrosive atmospheres.
***************************************************************************
Electrical equipment shall have factory-applied painting systems which
shall, as a minimum, meet the requirements of NEMA 250 corrosion-resistance
test.
PART 3 EXECUTION
3.1 INSTALLATION
Electrical installations shall conform to IEEE C2, NFPA 70, and to the
requirements specified herein.
[3.1.1 Wood Poles
***************************************************************************
NOTE: Poles set in swampy or rocky soil will require
different settings or foundations than those set in
average bearing soils. Consult pole manufacturer and
structural engineer for proper setting or foundation
requirements for these and other unusual soil
conditions.
***************************************************************************
Pole holes shall be at least as large at the top as at the bottom and shall
be large enough to provide 100 mm (4 inches) of clearance between the pole
and the side of the hole.
***************************************************************************
NOTE: At the text below, delete setting information
for pole lengths not required.
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 56 00 Page 37
***************************************************************************
a. Setting depth: Pole setting depths shall be as follows:
Length of Pole (mm) Setting in Soil (mm)
6100 1575
7625 1575
9150 1575
10675 1830
12200 1830
13725 1985
12250 2135
16775 2285
18300 2440
(
Length of Pole (feet) Setting in Soil (feet)
20 5.0
25 5.5
30 5.5
35 6.0
40 6.0
45 6.5
50 7.0
55 7.5
60 8.0
)b. Soil setting: "Setting in Soil" depths shall apply where pole holes
are in soil, sand, or gravel or any combination of these.[ At corners,
dead ends and other points of extra strain, poles 12,200 mm (40 feet)
long or more shall be set 150 mm (6 inches) deeper.]
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 56 00 Page 38
c. Setting on sloping ground: On sloping ground, measure the depth of the
hole from the low side of the hole.
d. Backfill: Tamp pole backfill for the full depth of the hole and mound
the excess fill around the pole.
][3.1.2 Concrete Poles
***************************************************************************
NOTE: Poles set in swampy or rocky soil will require
different settings or foundations than those set in
average bearing soils. Consult pole manufacturer and
structural engineer for proper setting or foundation
requirements for these and other unusual soil
conditions.
***************************************************************************
Install according to pole manufacturer's instructions.
][3.1.3 Fiberglass Poles
***************************************************************************
NOTE: Poles set in swampy or rocky soil will require
different settings or foundations than those set in
average bearing soils. Consult pole manufacturer and
structural engineer for proper setting or foundation
requirements for these and other unusual soil
conditions.
***************************************************************************
Install according to pole manufacturer's instructions.
][3.1.4 [Aluminum][Steel] Poles
***************************************************************************
NOTE: Poles set in swampy or rocky soil will require
different settings or foundations than those set in
average bearing soils. Consult pole manufacturer and
structural engineer for proper setting or foundation
requirements for these and other unusual soil
conditions.
***************************************************************************
Provide pole foundations with galvanized steel anchor bolts, threaded at the
top end and bent 1.57 rad (90 degrees) at the bottom end. Provide
ornamental covers to match pole and galvanized nuts and washers for anchor
bolts. Concrete for anchor bases, polyvinyl chloride (PVC) conduit ells,
and ground rods shall be as specified in Section 33 71 02 UNDERGROUND
ELECTRICAL DISTRIBUTION. Thoroughly compact backfill with compacting
arranged to prevent pressure between conductor, jacket, or sheath and the
end of conduit ell. Adjust poles as necessary to provide a permanent
vertical position with the bracket arm in proper position for luminaire
location.[ After installation, paint exposed surfaces of steel poles with
two finish coats of[ exterior oil paint of a color as indicated][ aluminum
paint]. Install according to pole manufacturer's instructions. Alterations
to poles after fabrication will void manufacturer's warranty and shall not
be allowed.]
UFGS Energy Updates 2017-Option 1 60516512SO1
Section 26 56 00 Page 39
]3.1.5 Pole Setting
[Depth shall be as indicated. ][Poles in straight runs shall be in a
straight line. Dig holes large enough to permit the proper use of tampers
to the full depth of the hole. Place backfill in the hole in 150 mm (6
inch) maximum layers and thoroughly tamp. Place surplus earth around the
pole in a conical shape and pack tightly to drain water away.]
[3.1.6 Photocell Switch Aiming
Aim switch according to manufacturer's recommendations.[ Mount switch on or
beside each luminaire when switch is provided in cast weatherproof aluminum
housing with swivel arm.][ Set adjustable window slide for [_____] lux
([_____] footcandles) photocell turn-on.]
]3.1.7 GROUNDING
Ground noncurrent-carrying parts of equipment including[ metal poles,]
luminaires, mounting arms, brackets, and metallic enclosures as specified in
Section 33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION. Where copper
grounding conductor is connected to a metal other than copper, provide
specially treated or lined connectors suitable for this purpose.
3.1.8 FIELD APPLIED PAINTING
***************************************************************************
NOTE: Use and coordinate paint and coating
requirements with Section 09 90 00 PAINTS AND
COATINGS when provided in the job. When requirements
are beyond what is specified in Section 09 90 00,
specify the requirements in this paragraph.
***************************************************************************
Paint electrical equipment as required to match finish of adjacent surfaces
or to meet the indicated or specified safety criteria. Painting shall be as
specified in Section 09 90 00 PAINTS AND COATINGS.
3.2 FIELD QUALITY CONTROL
Upon completion of installation, verify that equipment is properly
installed, connected, and adjusted. Conduct an operating test after 100
hours of burn-in time to show that the equipment operates in accordance with
the requirements of this section.
-- End of Section --