This presentation has been modified to update the relevant ... · Distracted Driving Impaired...

Post on 27-Jul-2020

1 views 0 download

Transcript of This presentation has been modified to update the relevant ... · Distracted Driving Impaired...

Highway Safety Improvement Program

Off-System

FY 2017/2018 HSIP (Cycle 3)Call for Applications

WebinarThis presentation has been modified to update the relevant contact information. An updated version of this presentation will be presented October 10, 2018 and subsequently posted on this site. Thank you!

Welcome

Mario Dipola, P.E., MBA, FCCMDistrict Safety Engineer

Agenda

2015/2016 – Off-System HSIP (Cycle 1) 2016/2017 – Off-System HSIP (Cycle 2) 2017/2018 – Off-System HSIP (Cycle 3) Example HSIP Projects Local Agency Safety Team (LAST) Safe Routes to School (SRTS) Example SRTS Projects Re-Cap

2015/2016 & 2016/2017Off-System HSIP

Under MAP-21

MAP-21 into effect on October 1, 2012 Goal: To achieve a significant reduction in

traffic fatalities and serious injuries Data driven strategic approach Lump sum total vs. individual authorizations Road user defined Strategic Highway Safety Plans (SHSP) 5% reports no longer required

Projects Summary

8 Shortlisted

6Advanced for funding

2016/2017Cycle 2

11 Applications

10 Shortlisted

8Advanced for funding

2015/2016Cycle 1

22 Applications

Factors Non data-driven Non crash reduction

projects Constructability Coordination Transferred

Signing & PavementMarking

Apply friction courseoverlay

Mid-Block Crossingwith RRFB

Add Sidewalk Realign Left Turn Lanes Audible markings

Lessons Learned

Requests must be accurate, detailed, data drivenand complete.

Better identification of issues related to roadwaysafety concerns.

All projects need to be constructible, feasible andcost effective.

Coordination with the Local Agency Safety Team(LAST) is needed for each application.

2017/2018 Off-System HSIP (Cycle 3)

Under FAST Act

Maintains focus on safety

Data-driven

Continues the HSIP to reduce fatalities and seriousinjuries using funds for:– Safety projects consistent with State SHSP– Safety projects to correct/improve a hazardous road

location/feature or address a highway safety problem

Limits HSIP eligibility to only those listed in statute

Strategic Highway Safety Plans (SHSPs)

Vision, Mission and Goals Transportation Safety Needs Safety Strategies Performance Measures Development, Implementation and Update

Florida SHSP Emphasis Areas Lane Departures Intersections Work Zones Pedestrians & Bicyclists Aging Road Users Teen Drivers Motorcyclists Distracted Driving Impaired Driving Speeding & Aggressive Driving Occupants Protection Commercial Motor Vehicles Traffic Records & Inf. Systems

4 E's Road Safety ENGINEERING EDUCATION ENFORCEMENT EMERGENCY RESPONSE

Application Process

www.nfltrafficsafety.com

Process

• Attend informational webinarWorkshop

• Identification of Potential Project LocationsPre-Application

• Conduct Safety Study of Advanced Locations from Pre-ApplicationSafety Study

• Application and Signed/Sealed StudyApplication and Study Submittal

• Feasibility/Constructability Review - ShortlistingSubmittal Review

• Identification and requesting for funding of candidateprojects

District Review and Selection

• Approval and funding of projectsCentral Office Review

Requirements and Restrictions

Data-driven and evidence based forecastedsafety improvements

Projects intended not to address: Beautification Drainage Bridge needs

Capacity enhancement Economic development Maintenance (Annual) Railroad quiet zone

HSIP Basic Process

Project Identification

Preliminary Analysis

HSIP Funding Request

Project EvaluationProgrammingDelivery

Pre-Application

Key elements:1. Maintaining Agency

Contact Person2. Project location #13. Project location #24. Project location #35. Where to Submit

1

2

3

4

5

Application

Key elements:1. Project location/Priority2. Maintaining Agency

Contact Person3. LAP Willingness4. Maintaining Agency

Concurrence

1

2

3

4

Application

Key elements:5. Location Details6. Problem Description7. Scope of Work8. Infrastructure Impacts9. Cost Estimate and B/C

5

6

7

8

9

Safety Study

Study must be signed and sealed by a professional engineer.

Recommended Format

Executive Summary Location Map Qualitative Summary Crash Analysis Planned Improvements Concept Plan Cost Estimate, Benefit Cost

Analysis and Net Present Value Appendices

Crash Analysis

Five years of crash data (2011 – 2015)– List of possible causes and countermeasures (site

specific)

Use Signal Four Analytics https://s4.geoplan.ufl.edu

– If you do not have an account, you can register online.– If you use an alternate data source, you will need to

provide the data with the study.

Financial Analysis

Include a detailed preliminary cost estimate– Include PE, CEI, contingencies, and R/W if available– Inflation may be considered in the estimate if selected

Conduct Benefit-Cost (B/C) Analysis– B/C > 2.0– Use B/C tool provided at www.nfltrafficsafety.com– Use Crash Modification Factors from FHWA CMF

Clearinghouse www.cmfclearinghouse.org

Example HSIP Eligible Projects

http://safety.fhwa.dot.gov/provencountermeasures/

Intersection Crashes

S t re et l ights

Pav e m e nt m ark ings

Ov e rs i ze d S igns/B e aco ns

Intersection Crashes

One s igna l he ad pe r lane

B ackp late s

New alignment

Turn re st r i c t io ns

Turn m ark ings

Intersection Crashes

A cce ss m anage m e nt

C lo se dr iv eways Turn lane s

S p l i t te r i s lands

Lane Departure Crashes

Ce nte r l ine /Edge l ine Rum ble S t r ipsPav e d S h o u lde rs

S afety Edge

Lane Departure Crashes

G uardra i l

Enhance d De l ine at io n fo r Ho r i zo nta l Cur v e s

Vulnerable Road Users

Hy b r id B e aco naka HAW K Pe de st r ian I s land Pe de st r ian Co untdown S igna l

I m prov e d Pe de st r ian Fe ature s

Local Agency Safety Team

Responsibilities and Duties

Pre-Application Review

Application Assistance

Recommendations for fundingconsiderations

Coordinate with non-fundedproject applicants for one (1)year for consideration in thenext year cycle.

Matthew Weaver, P.E.(813) 415-8826mweaver@elementeg.com

The LAST does not replace anagency’s existing engineering staffor consultant on contract.

Application Completion

Qualitative assessment/field review Constructability/feasibility review Update improvement concept Update improvement cost estimate using FDOT

construction costs. Develop project scope Update economic analysis (benefit/cost and net

present value)– B/C > 2.0 and NPV > 0– Use Crash Modification Factors from FHWA CMF

Clearinghouse www.cmfclearinghouse.org

2016/2017 Safe Routes to School (SRTS)

Projects Summary

9 Applications

6 Shortlisted

3Advanced for

funding

Factors Applications Surveys & Tallies NCSRTS’s Database Requested Items Constructability Right of Way Public Involvement SRTS Committee

Lessons Learned

SRTS Applications must be accurate, detailed, fullycompleted, and presented on time.

Surveys and Tallies must be fully completed andentered into the NCSRTS’s database.

The requested items need to be approved,constructible, feasible and cost effective.

Need to present proof of Right of Way andsupporting crash data.

2017/2018 Safe Routes to School (SRTS)

Objective

Facilitate the planning, development, andimplementation of projects that will improvesafety and reduce traffic, fuel consumption,and improve air quality in the vicinity ofschools (K-12).

Application

SRTS Eligible applicants have now been extendedKindergarten through 12th grade (Private andCharter Schools are included).

SRTS 3.5 hour Workshop is MANDATORY. Onlyattendees will be allowed to submit applications.

The Student-In-Class Travel Tally and Parent Surveydata summaries need to be attached.

Application Process

Maintaining Agency submits

Application

District Reviews and Scores Application

Feasibility and Cost Review(Top Scored

Applications)

Request for funding from Central Office

Central Office Review and

Approval

District Notifications and Project

Programming

Application: Section 1

Key elements:1. School Information2. Applicant Information3. Maintaining Agency

Information4. Metropolitan/

Transportation PlanningOrganization (M/TPO)Support

1

2

3

4

School, Applicant & Maintaining Agency Information

5

Eligibility and Feasibility Criteria Confirmations

Application: Section 2

Key elements:5. Data Forms

Application: Section 3 and 4

Key Elements:6. Past Activities7. Future Activities8. FTBSEP (http://safety.hhp.ufl.edu/)

9. Public Support

6 7

8

Background Information and Problem Identification

9

Application: Section 5

Key elements:10.Demographics11.In-Class Travel Tally12.Route Data13.Location (within 2

miles of the school)14.Pedestrian/Bike

Features

10

11

12

13

14

Specific Infrastructure Improvement(s) Requested

18

19

Key elements:15.Traffic Control16.Traffic Data17.Cost Estimate18.Cost Narrative19.Checklist

Application: Section 6 and 7Cost Estimate and Submission Checklist

15

16

17

Example SRTSEligible Projects

Pedestrian/Bicycle Facilities

New Sidewalks

S idewa lk W ide n ing

S idewalk G ap C lo sure

B us S to p Ro ute I m prov e m ents

B icyc le L ane s

Share Use Paths

S tarke E le m e ntar yB radfo rd Co unty

S o urce : © G o o g le Maps

Traffic Control Devices

New/UpgradedCrosswalks

Traffic Signs and S igna ls

F lash ing B e aco ns

Pe de st r ian Co untdown S igna ls

Pe de st r ian A ct iv ate d S igna l Upgrade s

Lando n Midd le S cho o lJ u l ia L a ndo n Co l le ge Pre parato r yDuv a l Co unty

Andrew A. Robinson Elementary

Re-Cap

Schedules

SRTS Call for Projects: November 2017 – March 2017

March 31, 2018 – Project Submittal Deadline

April – May 2018 – Project Reviews

June 2018 – Recommendations for project selection and funding

2017/2018 Off-System HSIP (Cycle 3) Call for Projects: November – December 2017

Project Identification: November 2017 Preliminary Project List Review: November 2017 Project Safety Study: December 2017

December 31, 2017 –Project Submittal Deadline

January – May 2018 – Project Reviews

June 2018 – Recommendations for project selection and funding

November 16 3:00 – 4:30 p.m.

Webinar

Questions?

Mario Dipola, P.E., MBA, FCCM FDOT Project Manager District Safety Engineer(904) 360-5633mario.dipola@dot.state.fl.us

Matt Weaver, P.E., CPM ELEMENT Engineering GroupTampa(813) 386-2101 mweaver@elementeg.com

HSIP Program & SRTS Program Contact