Post on 17-Jan-2017
Teamnet Engineering
Table of Contents
1. Company profile
2. Reference projects, SCADA Projects and Industrial Automations
3. Research & Development and Innovation projects
4. Certifications
5. Customers and Collaborators
Company profile
• Teamnet Group founded in 2001
• In TOP 3 IT&C integrators in Romania
• 93 mil. EUR turnover in 2014
• 20+ R&D European projects
• 800 employees
• 1.500 + certifications of the team
members
Teamnet Engineering - A company of the Teamnet Group
Teamnet Engineering - Skills
We provide the entire
development cycle of a
complex project
Design
Technological processes
Modelling of industrial processes
Intelligent automatic driving systems
Electrical systems, industrial automation and SCADA systems
Application specific software
Implementation
Technologicalenvironmental solutionsand other industrial processes
Water and sewage works, as well as water treatment stations, pumping, collection, water network systems
Waste management systems, automatic waste sorting stations, waste incinerators
Industrial automation and SCADA systems
Entrepreneurship
General contracting for complex works
Consulting
Water and sewage systems
Waste management systems
Automation andelectrical
engineering
SCADA (Supervisory Control and Data
Acquisition)
Industrial water treatment systems
Teamnet Engineering SCADA products and activities
Products
Technological installations
Design, industrial automation, software
Industrial communications for automation systems
Activities
Provider of solutions for environmentaltechnologies
Commissioning of technological installations
Design, Research & Development, Industrial Automation
Specific software for industrial applications
Reference projects, SCADA Projects and Industrial Automation
Upgrading of wastewater treatment stations in Bistrița - Năsăud County - Bistrița, Salva, Năsăud, Sângeorz Băi
Name Number of equivalent inhabitants
Bistrița 131.000
Beclean 20.000
Salva 20.000
Sângeorz-B i 12.000
Total beneficiaries
183.000
Sângeorz-
Salva
BecleanBistrița
Addressable population in the modernization project of wastewater treatment stations in Bistriţa County
• fully functional purge system for both sewage and sludge from the wastewater treatment processfrom Salva, Beclean, Sângeorz-
• a new water and sewage infrastructure by using the optimized collection and wastewater treatment plants systems
• supplement of the water treatment capacity through the rehabilitation of the activated sludge basins, as well as primary and secondary decanters
• the works were carried out within the POS MEDIU 1 program
• new purification station /Salva;
• wastewater transfer collector from the existing wastewater treatment plant to the new waste water treatment plant Salva;
• transformation of the existing wastewater treatment station
in a transfer pumping station.
• the works were carried out within the POS MEDIU 1 program
Sângeorz-
• expansion of the new wastewater treatment plant Sangeorz Bai built under another contract with funding from CNIfunds;
• collector main transfer pumping station to the treatment plant Rodna transfer Sângeorz ;
• transforming the existing wastewater treatment plant in Rodna in a transfer pump
• the works were carried out within the POS MEDIU 1 program
Beclean
• new purification station
• transfer wastewater collector Bata Beclean
• the works were carried out within the POS MEDIU 1 program
Upgrading wastewater treatment stations in Bistrița
Roughwater
Thin grate
Fine grate
Sand and fat separation
Primary decanters
Primary sludge
Coagulant dosing if needed
nitrogen recirculation Secondary decanters effluent
Line 2
Line 1
Line 3
effluentSecondary decanters
Secondary decanters
recirculated mud
Coagulant dosing if neededExcess sludge
Excess sludge
recirculated mud
nitrogen recirculation
Coagulant if needed
nitrogen recirculation
recirculated mud
Upgrading wastewater treatment stations in Sângeorz – Băi
Upgrading wastewater treatment stations in Salva
Upgrading wastewater treatment stations in Beclean
Sistemul de managemet integrat al deșeurilor din județul Bihor - Beiuș, Marghita, Salonta, Săcuieni, Stei
Name Number of equivalent inhabitants
Salonta 17.735
Marghita 15.770
Beiu 10.667
S cuieni 11.526
Stei 6.529
Total beneficiaries 62.227
Stei
Marghita
Salonta
Beiu
Addressable population in the SMID Bihor project (Integrated waste management system)
SMID Bihor (Integrated waste management system)
• This project solves operational and environmental problems
caused by waste generation and management, such as an
integrated waste management system is elaborated.
Sorting stations are designed for the following capabilities:
• BEIU : 7000 tonnes/year, operable 260 days a year with 1 eight-hour shift, thus 26.7 tonnes/day or about 3.3 tons/hour.
• MARGHITA: 4,500 tonnes/year, operable 260 days a year with 1 six-hour shift, thus 17.3 tonnes/day or about 2.9 tonnes/hour.
• SALONTA: 4,500 tonnes/year, operable 260 days a year with 1 six-hour shift, thus 17.3 tonnes/day or about 2.9 tonnes/hour
Transfer stations are designed for the following capabilities:
• BEIU : 16.100 tonnes/year , operable 312 days a year with 1 eight-hour shift
• MARGHITA: 10.600 tonnes/year, operable 312 days a year with 1 eight-hour shift
• SALONTA: 9.900 tone/year, operable 312 days a year with 1 eight-hour shift
• S CUIENI: 13.000 tone/year, operable 312 days a year with 1 eight-hour shift
• STEI: 3.500 tone/year, operable 312 days a year with 1 eight-hour shift
Automation and SCADA system for wastewater treatment plant expansion - Galați
Projected capacity: 370,000 equivalent inhabitants :
• Max. dry weather daily flow rate: 66,00 m3/day
• Rainy weather max. flow: 9,200 m3/hour
The water line has been extended with :
• Four lines for biological treatment with nutrient removing, 70,000 m3
• Four final clarification pools 23,600 m3
• Four final clarification pools, 8,000 Nm3/h. 250 kW
• Chemical dosing plant for phosphorus removal
• Recirculated and surplus mud pumping station
• Buffer pool for surplus thicken sludge. Anaerobic digestor, 6,000 m3
• Motor/generator combined equipment with biogas 130 m3/h / 260 kW
Galați WWTP2 automation system - SCADA operating interface
Galați WWTP2 automation system - SCADA operating interfaces
Extension and rehabilitation of wastewater treatment plants in Arges County
Other projectsModernization of the wagons loading
system to the CF Ramp (SCADA), integration and connection with the
OpenTAS ROMINSERV SRL Bucharest computer system
Automation and SCADA system for WWTP wastewater treatment plants -
Pechea and Lie
Integrated solid waste management system in Vaslui County
Technical support for the Ministry of Environment and Climate Change of Romania
Development of the monitoring system of Vidraru dam
Tranforming finishing demineralized water for Termoelectrica Midia within -
Technical Project; Details of execution
Modernization of existing water chemical treatment of the SC Electrocentrale Oradea
S.A. - approval documentation for intervention works; Technical project;
Details of execution
Research, Development and Innovation Projects
VIBROCHANGE
Vibrational Process
Sensors & Transducers
Detection / Diagnosis / Communication
Modeling / Identification / Fusion
Signal Processing
Ultrasonicwaves
Acoustic Waves
MechanicWaves
Experimental Model
Decisions
We offer an innovative solution for automatic monitoring andconditional maintenance systems, which can optimize coststhrough the early detection of defective industrial equipmentoperation.
Experimental model for the detection
and diagnosis of the changes in the
vibration processes of industrial
equipment, using advanced
techniques of measurement and
predictive analysis, in order to prevent
abnormal operation and to avoid
economic or environmental disaster.
BIOCON Advanced control system of a BIORAFINERY-type installation
Biorafinery-type installation: anaerobic digestor + fotobioreactor
BIOCONAdvanced control system of a BIORAFINERY-type
installation
• Modeling of processes of anaerobic digestionand photosynthetic growth of microalgae andthe identification of the second process, basedon of the experiments carried out on the pilotplant.
• Study of the process of obtaining methanethrough anaerobic wastewater treatment basedon the mathematical model, through numericsimulation
• Study on the use of biomass residues remainingfollowing the extraction of biodiesel as asubstrate for biogas production in anaerobicstep;
• Synthesis of control algorithms for bothprocesses (complex processes and powerfullynon-linear) treated individually and coupled tothe HILS structure adopted within the project
Certifications
Indusoft
ANRE
ISWAARA
MOLDSWA
Certifications
• Quality management system according to ISO 9001
• Environmental management system according to ISO 1400
• Occupational health and safety management system according to OHSAS
18001
• Information security management system according to ISO 27001
• Social responsibility management systems according to SRM 8000
• ANRE type B certification for design and execution of Electrical installations
• ANRE authorized electricians gr. IIIA/IIIB, IIA/IIB
• Integrating System and Software Provider Indusoft Web Studio (Schneider)
• Integrating System and Software Provider Siemens Germany
• Integrating System and Software Provider (RASI) Rockwell Software
Customers and collaborators
Customers at Local and Regional level
Bihor County Council
Galați City Hall SC Farming Matering SRL
Rompetrol SA - Năvodari
Dunărea de Jos University of Galați
Apă Canal SA Galați Arcelor Mittal Galați
Tehnopol SRL Galați
Rominserv SRL București
UEFISCDI Bucharest
Vega93 SRL Galați
Biogest International GmbH Germany
Passavant GmbH Germania
GE Power Franta (part of General
Electric SUA Group)
Arcelor Mittal Tubular Products Galati
UZINA TERMOELECTRICA MIDIA SA
Electrocentrale Oradea SA
SC Aquabis SA
Tancrad SRL Brăila Indas SRL București
Collaborators