MARINER EAST 2 PROJECT UPDATE

SUNOCO PIPELINE L.P.An Energy Transfer Partnership

October 19, 2017

MARINER EAST 2

2

MARINER EAST IS A SIGNIFICANT INVESTMENT IN PA

3

MARINER EAST II PROJECT OVERVIEW

• 350 Mile NGL (not LNG) Pipeline

• Two Pipeline Project– 20” – Scio, Ohio to Marcus Hook, PA– 16” – Delmont, PA to Marcus Hook, PA

• 17 PA Counties:– Washington - Cumberland– Allegheny - York– Westmoreland - Dauphin– Indiana - Lancaster– Cambria - Lebanon– Blair - Berks– Huntingdon - Chester– Juniata - Delaware – Perry

• Parallel to Mariner East I Right of Way for 80%

4

MARCUS HOOK INDUSTRIAL COMPLEX

• Last “Off-Ramp” on the pipelines

• Significant storage capacity for ethane, propane and butane

5

MARCUS HOOK INDUSTRIAL COMPLEX

6

Multi-Modal Outbound Transportation Capabilities

Significant construction of new storage capacity

FIRST ETHANE TRUCK LOADING

7

CONSTRUCTION SPREADS IN PA

• Generally approximately 50 miles each

• PA Spread 1: Washington, Allegheny, Westmoreland– Contractor – Welded Construction

• PA Spread 2: Westmoreland, Indiana, Cambria– Contractor – US Trinity

• PA Spread 3: Blair, Huntingdon, Juniata, Perry– Contractor – Michels

• PA Spread 4: Cumberland, York, Dauphin– Contractor – Precision

• PA Spread 5: Lebanon, Lancaster, Berks– Contractor – Welded Construction

• PA Spread 6: Chester, Delaware– Contractor – Otis Eastern

8

TOTAL ROAD-RELATED PERMITS

• PA1 (Districts 11 & 12) 242• PA2 (Districts 9, 10 & 12) 189• PA3 (Districts 2, 8 & 9) 156• PA4 (District 8) 216• PA5 (Districts 5 & 8) 245• PA6 (District 6) 250

• Total 1,492*Includes Township Permitting

9

TALE OF TWO SIGNS

10

PERMIT APPEALS

Permits issued 2/13/17 3 permit appeals filed 2 by individual landowners 1 by Clean Air Council,

Delaware Riverkeeper and Mountain Watershed Association

– Filed within 24 hours– Also sought supersedeas

and temporary supersedeas – denied 3/3/17 after 3 day hearing

– Refiled for supersedeas and temporary supersedeas re HDDs - 7/19/17

– Stipulated settlement on supersedeas re HDDs -8/9/17

11

CONSTRUCTION

Underway across Commonwealth

Western spread complete –completion progressing east

12

13

WASHINGTON COUNTY

INDIANA COUNTY

14

PERRY COUNTY

CUMBERLAND COUNTY

15

DAUPHIN COUNTY

LEBANON COUNTY

16

CHESTER COUNTY

DELAWARE COUNTY