Schedule Lag Drag

Post on 18-Jan-2015

577 views 0 download

Tags:

description

Explains problem of Start to Start and Finish to Finish lag calculations dragging the Early Start to right.

Transcript of Schedule Lag Drag

Scheduling 102A Solution to the Problem of Lag Drag

Dr. Raphael DuaCEO & OwnerMicroplanning International Asia Pacific P/L

Progressive Feed Activities

1 2 3

4 5 6 7

8 9 10 11

12 13 14

A1 A2 A3

B1

B2 B3

C1

C2

D2 D3

A = TOOL MANUFACTUREB = PARTS MANUFACTURE

C = ASSEMBLY MANUFACTURED = UNITS MANUFACTURE

The Ladder Convention

The Ladder Convention

Basic Element of a Ladder

Make Parts

Make Last Parts

Make First Parts

Basic Element of a Ladder

ES(i,j) = PEE(i)

Basic Element of a Ladder

PrecEvent

Or i node

SuccEvent

Or j node

PEE PEL SEE SEL

ESLS

EFLF

Duration d

PEE = Preceding Event EarliestPEL = Preceding Event LatestES = Earliest Start LS = Latest Start

SEE = Succeeding Event EarliestSEL = Succeeding Event LatestEF = Earliest FinishLF = Latest Finish

Calculating a Ladder

Progressive Feed

10Dur = 1

11Dur = 15

13Dur = 9

15Dur = 8

17Dur = 3

1

3 3

1

Progressive Feed

Progressive Feed

Progressive Feed

Progressive Feed

Thank YouFor Attending!