ROCKY CREEK VIADUCTFINAL DESIGN

PROJECT DEVELOPMENT TEAM

HERNAN PEREZ – STRUCTURE PROJECT ENGINEER

FRITZ HOFFMAN – SENIOR BRIDGE ENGINEER

BRIAN FULLER – PROJECT ENGINEER

STEVE WYATT – SENIOR DESIGN ENGINEER

WENDY WALDRON – SENIOR ENVIRONMENTAL PLANNER

BRYAN PARKER – PROJECT LANDSCAPE ARCHITECT

PROJECT DEVELOPMENT

TYPICAL PROJECT SCHEDULEVS

EMERGENCY PROJECT SCHEDULE

0 1 2 3 4 5 6

COMPARISON OF PROJECT TIMELINES

YEARS

KKNON-EMERGENCYPRESERVATION

PROJECT

0 1 2 3 4 5 6

COMPARISON OF PROJECT TIMELINES

YEARS

KKNON-EMERGENCYPRESERVATION

PROJECT

SCOPING12 MONTHS

0 1 2 3 4 5 6

COMPARISON OF PROJECT TIMELINES

YEARS

KKNON-EMERGENCYPRESERVATION

PROJECT

SCOPING12 MONTHS

PROGRAMMING12 MONTHS

0 1 2 3 4 5 6

COMPARISON OF PROJECT TIMELINES

YEARS

KKNON-EMERGENCYPRESERVATION

PROJECT

SCOPING12 MONTHS

ENVIRONMEN-TALCLEARANCE18 MONTHS

PROGRAMMING12 MONTHS

0 1 2 3 4 5 6

COMPARISON OF PROJECT TIMELINES

YEARS

KKNON-EMERGENCYPRESERVATION

PROJECT

SCOPING12 MONTHS

ENVIRONMEN-TALCLEARANCE18 MONTHS

PROGRAMMING12 MONTHS

DESIGN18 MONTHS

0 1 2 3 4 5 6

COMPARISON OF PROJECT TIMELINES

YEARS

KKNON-EMERGENCYPRESERVATION

PROJECT

SCOPING12 MONTHS

ENVIRONMEN-TALCLEARANCE18 MONTHS

PROGRAMMING12 MONTHS

DESIGN18 MONTHS

ADVERTISE &AWARD12 MONTHS

0 1 2 3 4 5 6

COMPARISON OF PROJECT TIMELINES

YEARS

KKNON-EMERGENCYPRESERVATION

PROJECT

ROCKY CREEK

VIADUCT

SCOPING12 MONTHS

ENVIRONMEN-TALCLEARANCE18 MONTHS

PROGRAMMING12 MONTHS

DESIGN18 MONTHS

ADVERTISE &AWARD12 MONTHS

0 1 2 3 4 5 6

COMPARISON OF PROJECT TIMELINES

YEARS

KKNON-EMERGENCYPRESERVATION

PROJECT

ROCKY CREEK

VIADUCT

SCOPING12 MONTHS

ENVIRONMEN-TALCLEARANCE18 MONTHS

PROGRAMMING12 MONTHS

DESIGN18 MONTHS

ADVERTISE &AWARD12 MONTHS

SAME PROCESSES15 MONTHS TOTAL

LAYOUT

TYPICAL SECTION - VIADUCT

TYPICAL SECTION – ROADWAY CONFORMS

STAGE CONSTRUCTION – STAGE 1

STAGE CONSTRUCTION – STAGE 2

LANE CLOSURES

CONTRACTOR SUBMITS WEEKLY LANE CLOSURE SCHEDULE TO RESIDENT

ENGINEER ON FRIDAY OF PRECEDING WEEK

RESIDENT ENGINEER REPORTS LANE CLOSURE SCHEDULE TO PUBLIC

INFORMATION OFFICE (PIO)

PIO SENDS OUT LANE CLOSURE NOTIFICATIONS TO BIG SUR BUSINESSES

AND OFFICIALS

CHANGES TO LANE CLOSURE SCHEDULE REPORTED IN REAL-TIME