Reef crushing - Lonmin

Post on 03-Jul-2015

15 views 0 download

description

Opencast Contract Mining, drill Blast, Load, Haul, Crushing

Transcript of Reef crushing - Lonmin

www.construction.murrob.com

REEF CRUSHING - LONMIN North-West, Marikana

PROJECT TYPE: CRUSHING

CLIENT:

Lonmin, Eastern Platinum

VALUE:

<R40 Million

CONSULTANTS:

None

PROJECT DURATION:

48 Months

DATE OF PROJECT:

1 October 2009

PROJECT DESCRIPTION:

Hard Rock, crushing of Merensky Reef.

Approximate volumes mined for the project :-

• Crushing Merensky Reef 1,000,000 m³