Maximising control, visualisation and information at the Mix plant at Lonmin.

46
Maximising control, visualisation and information at the Mix plant at Lonmin

Transcript of Maximising control, visualisation and information at the Mix plant at Lonmin.

Page 1: Maximising control, visualisation and information at the Mix plant at Lonmin.

Maximising control, visualisation and information at the Mix plant at Lonmin

Page 2: Maximising control, visualisation and information at the Mix plant at Lonmin.

Brian Davies Senior Technician

Roelf BoshoffSI Engineer

Page 3: Maximising control, visualisation and information at the Mix plant at Lonmin.

Agenda

IntroductionIntroductionIntroductionIntroduction

The ProjectThe Project

Benefits of version 3 graphicsBenefits of version 3 graphics

ConsiderationsConsiderations

Technical ChallengesTechnical Challenges

Page 4: Maximising control, visualisation and information at the Mix plant at Lonmin.

Introduction to Lonmin

► World’s third largest Platinum producer

► Operations based in South Africa▪ North West▪ Limpopo

Page 5: Maximising control, visualisation and information at the Mix plant at Lonmin.

Introduction to Mix Concentrator

Mix Concentrator processes► Stock pile and raw ore conveyor system

▪ Raw ore stockpiles▪ Conveyed to 40 m silos▪ 4 to 5 grams of PGM's per ton

Page 6: Maximising control, visualisation and information at the Mix plant at Lonmin.

Introduction to Mix Concentrator

Mix Concentrator processes► Milling

▪ Raw ore fed into ball mill▪ Diluted with water - Slurry▪ Cyclones separate fine from coarse▪ Coarse returned to mill

Page 7: Maximising control, visualisation and information at the Mix plant at Lonmin.

Introduction to Mix Concentrator

Mix Concentrator processes► Floatation

▪ Chemicals used to attract PGM’s to bubbles ▪ Primary roughers extract 80-90%▪ Secondary roughers collect rest▪ Contaminants removed in cleaning section

Page 8: Maximising control, visualisation and information at the Mix plant at Lonmin.

Introduction to Mix Concentrator

Mix Concentrator processes► Thickener – cone shaped

▪ Feed into centre of cone – 90% of solids▪ Solids settle to bottom - flocculants▪ Lighter particles settle on outside – less turbulent▪ Rake particles to centre at 0.12 RPM▪ Pumped from centre

Page 9: Maximising control, visualisation and information at the Mix plant at Lonmin.

Mix Plant Network Topology

Allen-Bradley Workstation

ArchestrA IDEWorkstation

ControlSwitch

ProductionSwitch

AOS 1

AOS 2

INSQL

GalaxyRepository

MIX PLC 1 MIX PLC 2 MIX PLC 3 MIX PLC 4 MIX PLC 5

Page 10: Maximising control, visualisation and information at the Mix plant at Lonmin.

IntroductionIntroduction

Agenda

The projectThe projectThe projectThe project

Benefits of version 3 graphicsBenefits of version 3 graphics

ConsiderationsConsiderations

Technical ChallengesTechnical Challenges

Page 11: Maximising control, visualisation and information at the Mix plant at Lonmin.

The Project

► Replace TI PLCs with Allen-Bradley PLCs

► Reprogram PLC code using standard routines made possible by using an Allen-Bradley PLC

► Rebuild SCADA using ArchestrA and version 3 graphics▪ Build a modern looking SCADA ▪ Create a standard graphic library for Mix Concentrator▪ Establish a system which is easy to expand and

change using the ArchestrA architecture

Page 12: Maximising control, visualisation and information at the Mix plant at Lonmin.

The projectThe project

IntroductionIntroduction

Agenda

Benefits of version 3 graphicsBenefits of version 3 graphicsBenefits of version 3 graphicsBenefits of version 3 graphics

ConsiderationsConsiderations

Technical ChallengesTechnical Challenges

Page 13: Maximising control, visualisation and information at the Mix plant at Lonmin.

Benefits of version 3 Graphics

Why version 3 graphics?

► The superior graphics (Pretty pictures)► Have all the graphics in one place► Inserting graphics into SCADA is easy ► Graphics can be reused► Added benefit of connection status indication

Page 14: Maximising control, visualisation and information at the Mix plant at Lonmin.

Benefits of version 3 Graphics

Superior Graphics

► Enhanced Graphics► Esthetically Pleasing► Realistic Graphics► Air of Professiolism

Page 15: Maximising control, visualisation and information at the Mix plant at Lonmin.

Benefits of version 3 Graphics

► Enhanced Graphics

Transparency

Embossed Symbols

Patterns

Page 16: Maximising control, visualisation and information at the Mix plant at Lonmin.

Benefits of version 3 Graphics

► Esthetically Pleasing

Lighting Effects

Shaded Tanks

3D Symbols

Page 17: Maximising control, visualisation and information at the Mix plant at Lonmin.

Benefits of version 3 Graphics

► Realistic Graphics

Oil Filter

Solenoid Valve

Mill displaying gears

Animated Fan

Page 18: Maximising control, visualisation and information at the Mix plant at Lonmin.

Benefits of version 3 Graphics

► Air of Professiolism

HMI Time

PLC Time

Control Logix PLC

Allen Bradley DeviceNet

Page 19: Maximising control, visualisation and information at the Mix plant at Lonmin.

Benefits of version 3 Graphics

Have all the graphics in one place(Forcing Standards)

► Add symbols to template

► Link popups to icons

► Populate graphics with attributes

ArchestrA supplied the means to create Standard Templates

With version 3 graphics:

Page 20: Maximising control, visualisation and information at the Mix plant at Lonmin.

Benefits of version 3 Graphics

► Add symbols to template

Popup Graphics

Icon GraphicsGraphic

DescriptionInherited from Master template

Referenced as me.PopUp

Page 21: Maximising control, visualisation and information at the Mix plant at Lonmin.

Benefits of version 3 Graphics

► Populate graphics with attributes

Template Attributes

Icon Graphic

Page 22: Maximising control, visualisation and information at the Mix plant at Lonmin.

Benefits of version 3 Graphics

► Link popups to icons

Reference Popup Graphic

Icon graphic

Activate as Icon

Show popup on click

Example Popup

Page 23: Maximising control, visualisation and information at the Mix plant at Lonmin.

Benefits of version 3 Graphics

Inserting graphics into SCADA is easy

ArchestrA instance

Symbols embedded in instance

Embed ArchestrA Graphic

Page 24: Maximising control, visualisation and information at the Mix plant at Lonmin.

Benefits of version 3 Graphics

Inserting graphics into SCADA is easy

Symbol embedded in SCADA

Page 25: Maximising control, visualisation and information at the Mix plant at Lonmin.

Benefits of version 3 Graphics

Graphics can be reused

► Another Graphic► The SCADA► Template as embedded graphic

After graphic is created in graphic toolbox it can be reused in:

Page 26: Maximising control, visualisation and information at the Mix plant at Lonmin.

Benefits of version 3 Graphics

► Graphic used in another Graphic

Another GraphicAnother Graphic

Graphic from graphic toolbox

Original graphic

Embedded graphic

Page 27: Maximising control, visualisation and information at the Mix plant at Lonmin.

Benefits of version 3 Graphics

► Graphic used in the SCADA(Where graphic is not an icon)

Tag entered in Scada

Graphic from graphic toolbox

Page 28: Maximising control, visualisation and information at the Mix plant at Lonmin.

Benefits of version 3 Graphics

► Graphic used in a template(Graphic becomes an icon)

Graphic from graphic toolbox

ArchestrA template

Symbol nameIcon used in

SCADA

Tag already assigned

Page 29: Maximising control, visualisation and information at the Mix plant at Lonmin.

Benefits of version 3 Graphics

Added benefit of connection status indication

* Status icon indicates status of the connection to the IO server

Add status Indication

Status indication definitions

Status added to Icon

Page 30: Maximising control, visualisation and information at the Mix plant at Lonmin.

Benefits of version 3 Graphics

How did version 3 graphics benefit me?

► Reduced number of windows to maintain► Reduced development time – More time to

focus on optimizing plant► Simplified the development – Any

technician can do development► Graphics self-explanatory – Less time

needed to train operators

Page 31: Maximising control, visualisation and information at the Mix plant at Lonmin.

Benefits of version 3 graphicsBenefits of version 3 graphics

The projectThe project

IntroductionIntroduction

Agenda

ConsiderationsConsiderationsConsiderationsConsiderations

Technical ChallengesTechnical Challenges

Page 32: Maximising control, visualisation and information at the Mix plant at Lonmin.

Consideration

► Do not use minimum hardware specifications for GR▪ Might cause instability,▪ Performance issues,

► Network stability▪ Communication failure

Page 33: Maximising control, visualisation and information at the Mix plant at Lonmin.

ConsiderationsConsiderations

BenefitsBenefits

ObjectiveObjective

IntroductionIntroduction

Agenda

Technical ChallengesTechnical ChallengesTechnical ChallengesTechnical Challenges

Page 34: Maximising control, visualisation and information at the Mix plant at Lonmin.

Technical Challenges

Flushing Sequence Popup

► To clean a pump that carries slurry before stopping and starting

► Typical arrangement:

Flush Valve

Delivery ValveSuction Valve

Slurry Pump

Drain Valve

GSW Analog

GSW Valve

* Many different configurations exist

Page 35: Maximising control, visualisation and information at the Mix plant at Lonmin.

Technical Challenges

Flushing Sequence Popup

All the slurry pumps need flushing valves

Not Enough space to display flush valves – Need a popup

Page 36: Maximising control, visualisation and information at the Mix plant at Lonmin.

Technical Challenges

Flushing Sequence Popup

Flush Button Opens

Flush Button Indicating problem in flush sequence

7 valve positions 3 types of pumps Analog only constant 15120 possible

configurations

Flush popup template graphic

Page 37: Maximising control, visualisation and information at the Mix plant at Lonmin.

Technical Challenge

► HOW was it done?▪ Created a flush template▪ Popup graphic embedded in template▪ Populate popup graphic with dummy icons▪ Define equipment in instance of object▪ Use OwningObject scripts to assign equipment

Flushing Sequence Popup

Page 38: Maximising control, visualisation and information at the Mix plant at Lonmin.

Technical Challenge

► End result

Flushing Sequence Popup

Completely dynamic popup

Page 39: Maximising control, visualisation and information at the Mix plant at Lonmin.

Technical Challenges

PLC LayoutWHY?

Indicate module status

Show Inter-PLC communication

Fault Finding

Grapical devicenet represenation

Page 40: Maximising control, visualisation and information at the Mix plant at Lonmin.

Technical Challenge

► A standard naming convention makes Archestra templates possible

► Naming convention example:▪ Rack R01▪ Slot S04▪ Slot in a rack: R01S04

► Templates created to assign the IO automatically using the naming convention and containment

PLC Layout

Page 41: Maximising control, visualisation and information at the Mix plant at Lonmin.

Technical Challenge

► Templates created and their containmentPLC template – assign PLC path

Rack Template – module status indication

Devicenet template – DNB module

CN2DN templateDevicenet template – CN2DN module

Rack Template

► Example Layout of containment:

PLC Layout

* Contained name very important* PLC path propagated to assign IO

Page 42: Maximising control, visualisation and information at the Mix plant at Lonmin.

Technical Challenge

PLC Layout

► The OLD methodTags Needed for a single Devicenet Scanner

Tags Needed for Slot Status of a single Rack

Tags Needed for:

• One PLC

• Six Racks

• Two Devicenet Scanners

► The NEW method

Page 43: Maximising control, visualisation and information at the Mix plant at Lonmin.

Technical Challenges

Effective alarm annunciation and navigation

► Old methods used▪ Button to open a single alarm list▪ Indicate last four alams on top menu

► 1st stage of new method▪ Divide alarms into four groups ▪ Add animation to indicate alarms▪ Navigate to alarm list

► 2nd stage of new method▪ Display critical alarms on top menu▪ Display mouse-over descriptons▪ Shown critical alarm count▪ Add action to navigate to window and popup

Page 44: Maximising control, visualisation and information at the Mix plant at Lonmin.

Technical Challenges

Effective alarm annunciation and navigation

BUTWith the new and improved system▪ Alarms can be acknowledged from the popup▪ Type of alarm and priority also indicated

Icon indicating alarm (Red)

Alarm acknowledgement button

Alarm latch in PLC indication

Separate button for reset and

acknowledgement

Alarm Priority

Page 45: Maximising control, visualisation and information at the Mix plant at Lonmin.

Technical Challenge

► HOW was it done?▪ Create Alarming template▪ Add attributes to all templates which can alarm

• WindowName

• AlarmingEnabled

• AlarmType

▪ Use Intouch alarm viewer controls to capture alarms▪ Use owning object scripts to populate graphics▪ Link windows to alarms

Effective alarm annunciation and navigation

Page 46: Maximising control, visualisation and information at the Mix plant at Lonmin.

Thank you for attendingWonderware User group

Conference 2009

Any Questions?