CFSPPP-PLTU LAMPUNG (2 x 100 MW). PT. GAKA KARYA ENGINEERING. RIGGING DEPARTMENT. RIGGING DEPARTMENT. ANALYZE AND PLANED ACTIVITY FOR LIFTING AND ERECTION WORK. START. DATA MATERIAL DIMENSION WEIGHT. REFERENCE 1. RIGGING BOOK 2. EQUIP. MANUAL 3. B30.24-2003 Safety Standard - PowerPoint PPT Presentation

Transcript of PT. GAKA KARYA ENGINEERING

RIGGING DEPARTMENT

ANALYZE AND PLANED ACTIVITY FOR LIFTING AND ERECTION

WORK

RIGGING DEPARTMENT

RIGGING & EQPTEDI TRIANTO

DESGN ENGINEER RIGGING ENGINEER RIGGING SUPERVI. SCAFOLDER SUPERV.HAGUN GUNAWAN SARPAN KARTONO

Foreman, Scafolder, Helper Foreman, Scafolder, Helper

START

DATA MATERIAL1. DIMENSION2. WEIGHT

REFERENCE1. RIGGING BOOK 2. EQUIP. MANUAL

3. B30.24-2003 Safety Standard4. B30.21-2005 manually lever operated hoist

5. Australian Standard, AS 3569--1989, Wire ropes6. Australian Standard, AS 2759--1985, Wire ropes

7. NAVFAC P-307, Juni 20038. Construction Industry Crane Safety Summit, 2009

NEED DUO

CRANE

TAILING DESIGNMONO CRANE

A

No

Yes

B

A

JSA

BRisk

Safe

RIGGING PLAN

STOP

CONTROL

REPORT

ACTION

STEP-11.TAHAP PERTAMA, OBJECT YANG AKAN DI ANGKAT ADALAH GENERATOR UNIT 2 (BARAT)2.INSTALL RAIL WAY FOR SLINDING.3.MENURUNKAN GENARATOR DARI ATAS "GOLDEFER"4.TAKE IT ON RAIL WAY.5.READY TO SLIDING.6.MOVE IT UNTIL 30.000MM OVER THAN BEFORE ON ELEVATION +500.

STEP-21.TAHAP KEDUA, OBJECT YANG AKAN DI ANGKAT ADALAH GENERATOR UNIT 1 (TIMUR)2.MENURUNKAN GENARATOR DARI ATAS "GOLDEFER"3.TAKE IT ON RAIL WAY.4.READY TO SLIDING.5.MOVE IT UNTIL TO CENTERLINE OF GENERATOR ON ELEVATION +500.

STEP-31.INSTALL RAIL WAY SEJAJAR DENGAN SUMBU GENERATOR.

2.MOVE IT UNTIL 7000MM OVER THAN BEFORE.

STEP-41.INSTALL GANTRY CRANE FOR LIFTING GENERATOR UNIT 1 (TIMUR)

STEP-51.CONNECTED ALL CONNECTOR,

2.LIFT OBJECT UNTIL ELEVATION 10.000 UP TO GROUND FLOOR,3.MOVE OBJECT BY CRANE UNTIL POSITION (FROM BARAT TO TIMUR)

STEP-61.INSTAL SKIDDING UNIT KETGA DAN KEEMPAT DI KAKI TENGAH.

2.LEPASKAN KAKI PANJANG.

STEP-71.GESER OBJECT KE POSISI TARGET.

STEP-81.TURUNKAN OBJECT KE POSISI TARGET.

STEP-91.SLIDING GENERATOR UNIT 2 (BARAT) TO CENTER LINE ON GROUND FLOOR.

STEP-101.PREPARATION ACTIVITIES FOR GENERATOR UNIT 2 (BARAT)

STEP-111.CONNECTED ALL CONNECTOR,

2.LIFT OBJECT UNTIL ELEVATION 10.000 UP TO GROUND FLOOR,3.MOVE OBJECT BY CRANE UNTIL POSITION (FROM TIMUR TO BARAT)

STEP-121.INSTAL SKIDDING UNIT KETGA DAN KEEMPAT DI KAKI TENGAH.2.LEPASKAN KAKI PANJANG.

STEP-131.GESER OBJECT KE POSISI TARGET.

STEP-141.TURUNKAN OBJECT KE POSISI TARGET.

RIGGING DEPARTMENT LOGOLIFT

SWINGMOVEDOWN

In safety corridor

THINK SAFEDO SAFELY

SAFETY FIRST