PT. GAKA KARYA ENGINEERING

21

description

CFSPPP-PLTU LAMPUNG (2 x 100 MW). PT. GAKA KARYA ENGINEERING. RIGGING DEPARTMENT. RIGGING DEPARTMENT. ANALYZE AND PLANED ACTIVITY FOR LIFTING AND ERECTION WORK. START. DATA MATERIAL DIMENSION WEIGHT. REFERENCE 1. RIGGING BOOK 2. EQUIP. MANUAL 3. B30.24-2003 Safety Standard - PowerPoint PPT Presentation

Transcript of PT. GAKA KARYA ENGINEERING

Page 1: PT. GAKA KARYA ENGINEERING
Page 2: PT. GAKA KARYA ENGINEERING

RIGGING DEPARTMENT

ANALYZE AND PLANED ACTIVITY FOR LIFTING AND ERECTION

WORK

Page 3: PT. GAKA KARYA ENGINEERING

RIGGING DEPARTMENT

RIGGING & EQPTEDI TRIANTO

DESGN ENGINEER RIGGING ENGINEER RIGGING SUPERVI. SCAFOLDER SUPERV.HAGUN GUNAWAN SARPAN KARTONO

Foreman, Scafolder, Helper Foreman, Scafolder, Helper

Page 4: PT. GAKA KARYA ENGINEERING

START

DATA MATERIAL1. DIMENSION2. WEIGHT

REFERENCE1. RIGGING BOOK 2. EQUIP. MANUAL

3. B30.24-2003 Safety Standard4. B30.21-2005 manually lever operated hoist

5. Australian Standard, AS 3569--1989, Wire ropes6. Australian Standard, AS 2759--1985, Wire ropes

7. NAVFAC P-307, Juni 20038. Construction Industry Crane Safety Summit, 2009

NEED DUO

CRANE

TAILING DESIGNMONO CRANE

A

No

Yes

B

Page 5: PT. GAKA KARYA ENGINEERING

A

JSA

BRisk

Safe

RIGGING PLAN

STOP

CONTROL

REPORT

ACTION

Page 6: PT. GAKA KARYA ENGINEERING

STEP-11.TAHAP PERTAMA, OBJECT YANG AKAN DI ANGKAT ADALAH GENERATOR UNIT 2 (BARAT)2.INSTALL RAIL WAY FOR SLINDING.3.MENURUNKAN GENARATOR DARI ATAS "GOLDEFER"4.TAKE IT ON RAIL WAY.5.READY TO SLIDING.6.MOVE IT UNTIL 30.000MM OVER THAN BEFORE ON ELEVATION +500.

Page 7: PT. GAKA KARYA ENGINEERING

STEP-21.TAHAP KEDUA, OBJECT YANG AKAN DI ANGKAT ADALAH GENERATOR UNIT 1 (TIMUR)2.MENURUNKAN GENARATOR DARI ATAS "GOLDEFER"3.TAKE IT ON RAIL WAY.4.READY TO SLIDING.5.MOVE IT UNTIL TO CENTERLINE OF GENERATOR ON ELEVATION +500.

Page 8: PT. GAKA KARYA ENGINEERING

STEP-31.INSTALL RAIL WAY SEJAJAR DENGAN SUMBU GENERATOR.

2.MOVE IT UNTIL 7000MM OVER THAN BEFORE.

Page 9: PT. GAKA KARYA ENGINEERING

STEP-41.INSTALL GANTRY CRANE FOR LIFTING GENERATOR UNIT 1 (TIMUR)

Page 10: PT. GAKA KARYA ENGINEERING

STEP-51.CONNECTED ALL CONNECTOR,

2.LIFT OBJECT UNTIL ELEVATION 10.000 UP TO GROUND FLOOR,3.MOVE OBJECT BY CRANE UNTIL POSITION (FROM BARAT TO TIMUR)

Page 11: PT. GAKA KARYA ENGINEERING

STEP-61.INSTAL SKIDDING UNIT KETGA DAN KEEMPAT DI KAKI TENGAH.

2.LEPASKAN KAKI PANJANG.

Page 12: PT. GAKA KARYA ENGINEERING

STEP-71.GESER OBJECT KE POSISI TARGET.

Page 13: PT. GAKA KARYA ENGINEERING

STEP-81.TURUNKAN OBJECT KE POSISI TARGET.

Page 14: PT. GAKA KARYA ENGINEERING

STEP-91.SLIDING GENERATOR UNIT 2 (BARAT) TO CENTER LINE ON GROUND FLOOR.

Page 15: PT. GAKA KARYA ENGINEERING

STEP-101.PREPARATION ACTIVITIES FOR GENERATOR UNIT 2 (BARAT)

Page 16: PT. GAKA KARYA ENGINEERING

STEP-111.CONNECTED ALL CONNECTOR,

2.LIFT OBJECT UNTIL ELEVATION 10.000 UP TO GROUND FLOOR,3.MOVE OBJECT BY CRANE UNTIL POSITION (FROM TIMUR TO BARAT)

Page 17: PT. GAKA KARYA ENGINEERING

STEP-121.INSTAL SKIDDING UNIT KETGA DAN KEEMPAT DI KAKI TENGAH.2.LEPASKAN KAKI PANJANG.

Page 18: PT. GAKA KARYA ENGINEERING

STEP-131.GESER OBJECT KE POSISI TARGET.

Page 19: PT. GAKA KARYA ENGINEERING

STEP-141.TURUNKAN OBJECT KE POSISI TARGET.

Page 20: PT. GAKA KARYA ENGINEERING

RIGGING DEPARTMENT LOGOLIFT

SWINGMOVEDOWN

In safety corridor

THINK SAFEDO SAFELY

SAFETY FIRST

Page 21: PT. GAKA KARYA ENGINEERING