DATE: JANUARY 5, 2012 TO: BOARD OF DIRECTORS FROM: RICHARD D. THORPE CHIEF EXECUTIVE OFFICER ACTION: RECEIVE AND FILE THE MONTHLY PHASE 1 AND PHASE 2
PROJECT STATUS UPDATE AND THE LOCAL JOBS AND DBE PROGRAM UPDATE FOR EACH PHASE OF THE PROJECT
RECOMMENDATION Receive and File the Monthly Phase 1 and Phase 2 Project Status Update and receive an update on the Local Jobs and DBE Program for each phase of the project. SUMMARY The presentation will summarize key project activities completed during the previous month, and key activities planned for next month for both Phase 1 and Phase 2 of the project. Staff will also provide an update on the Contractor Local Jobs and DBE Program for each phase of the project. FINANCIAL IMPACT None ATTACHMENT(S) None
Expo Light Rail Line
Safety Bollards and Signage at Pedestrian Crossing
at Expo Park/USC Station
Phase 1
Construction Progress
Expo Light Rail Line
Installed Canopy and Rain Shields at Farmdale Station
Phase 1
Construction Progress
Expo Light Rail Line Project Status
Major Issues
Schedule
• FFP has not attained Substantial Completion (SC):
Authority and FFP have entered into an agreement to defer assessment of
Liquidated Damages pending project closeout
Per the latest independent Authority evaluation, the estimate for SC is January
2012
Authority and Metro are working to resolve issues with the signaling system at
the Blue Line junction
Initial Pre-Revenue Operations are scheduled to begin in early January
Metro will subsequently determine the date for Revenue Service
• Remaining construction elements of the Project are scheduled to be completed in early
2012:
Farmdale Station
Culver City Work (including Bike Facilities at the Culver City Station)
Phase 1
Expo Light Rail Line Project Status
Major Issues
Schedule (cont.)
• Other construction elements remaining to be completed:
Foshay Safety Improvements (including parking and pedestrian facilities at
Western Avenue and Exposition Boulevard)
Cimarron/Rodeo Replacement Parking
Miscellaneous City Street Work
Punch List Items
Phase 1
Expo Light Rail Line Project Status
Phase 1
Major Issues
Project Budget
• The latest budget analysis forecasts a budget shortfall of $3.4 million for cost elements
that are known or anticipated at this time.
• There are several outstanding items that could adversely affect the current Project
budget forecast. These outstanding risk items include:
Changes as a result of unforeseen or differing site conditions
Disputed Potential Change Orders
Additional Third Party Costs
Additional Professional Service Costs
• Cost Containment Efforts:
Continue discussions with third parties on reimbursement of certain Project
costs estimated to be approximately $2.8 million
Explore other cost saving measures estimated to be approximately $800,000
Expo Light Rail Line Project Status
Phase 1
Expo Phase 1 Cost: Forecast-At-Completion
Month
Budget
Forecast-at-
Completion
$ 932.0$ 935.3
$ 932.0
Δ = $ 3.4 M Δ = $ 3.3 M Δ = $ 3.4 M
$ 935.4$ 932.0
$ 935.4
Expo Light Rail Line Project Status
Other Issues
Noise
• Collected noise readings during recent monitoring
Initial indications are that noise levels are consistent with those specified in
the FEIR
• Will conduct further analysis upon Metro’s commencement of a full operating schedule
prior to opening to the public
Privacy Screens
• Staff has estimated he cost of privacy screens between La Brea Avenue and Dunsmuir
Avenue to be approximately $300,000
• The cost is based on adding a two foot screen on top of the existing sound walls
Phase 1
Expo Light Rail Line Project Status
Other Issues
Clean Mobility Center
• Met with members of the Culver City Bicycle coalition to discuss deferment of the Clean
Mobility Center (CMC) at the Culver City Station
• Staff is evaluating alternatives for the installation of the CMC:
1. Balfour Beatty Infrastructure – Venice Boulevard Aerial Structure contractor
2. SkanskaRados Joint Venture – Phase 2 Design-Build contractor
3. Piggy back on a Metro’s procurement of CMC facilities
• The budget for the remaining elements of the CMC is $250,000
• Other locations for the CMC were explored, but lack the necessary sewer and water
connections for CMC operations
Phase 1
Expo Light Rail Line
FFP Local Jobs Program and DBE
Local Jobs Program
DBE Performance (through November 20, 2011)
Local Jobs and DBE Update
Phase 1
This Month
Nov 27 – Dec 24
Cumulative
To Date
Forecast at
Completion
FFP Local Hire Hours 29.1% 37.3% 36.5%
Subcontractor Local Hire Hours 25% 24.7% 24.4%
Total Local Hire Hours 27.5% 30.1% 30%
Goal Attainment
To Date
Forecast at
Completion
Design Services 20% 24.1% 24.5%
Professional Services 20% 36.3% 36.7%
Construction Services 20% 19.2% 19.7%
Overall 20% 21.4% 21.9%
Expo Light Rail Line
Installed Security Fencing at Federal and Exposition
Phase 2
Pre-Construction Activities
Expo Light Rail Line Project Status
Phase 2
Alignment Design-Build Contract
Received 60% design submittals for:
City of SM Civil Work
Motor, Olympic, and Sepulveda Aerial Structures
Expo/Sepulveda, National/Palms, and Olympic/26th St. Stations
Continued advancing remaining design elements to 60%
Continued analysis of the Kenter Canyon Storm Drain based upon completed field analysis
Survey work, potholing activities and pre-construction surveys are ongoing
Coordination meetings continue with DWP and SCE for overhead power line relocations
A partnering workshop with SCE has been scheduled for January 9, 2012
Maintenance Facility Design Contract
Maintenance Design Group has completed Preliminary Engineering
Design work will continue after contract negotiations with the Expo Authority for final design
Expo Light Rail Line Project Status
Phase 2
Venice Boulevard Aerial Structure
Submitted Final PSR/PR to Caltrans
Received 100% design submittals for sanitary sewer line relocation
BBII submitted 95% bridge design to Caltrans and Expo Authority for review/comment
Community Outreach
Hosted an Urban Design Committee Meeting on December 20, 2011
Hosted three stakeholder meetings regarding the Parking Replacement Plan for
Colorado Avenue in the City of Santa Monica
Conducted stakeholder briefing for:
Overland Elementary School Parent-Teacher Association (PTA)
Business assessments continue for businesses located adjacent to the alignment
Design Update Community Meeting for the maintenance facility is scheduled for
January 23, 2012
Expo Light Rail Line
June 2011
Thru Nov. 19th
This Month
Nov. 20th – Dec. 24th
Cumulative
To Date
SKANSKA-RADOS JOINT VENTURE
Total Hours 10,875 605 11,480
Hours Worked by Local Residents 4,115 248 4,363
Local Resident Percentage 37.8% 41.0% 38.0%
SUBCONTRACTORS
Total Hours 7,867.3 176 8,043.3
Hours Worked by Local Residents 1,204.3 160 1,364.3
Local Resident Percentage 15.3% 90.9% 17.0%
TOTALS TO DATE
All Hours Worked 18,742.3 781 19,523.3
All Hours Worked by Local Residents 5,319.3 408 5,727.3
Local Resident Percentage 28.4% 52.2% 29.3%
PROJECTED AT COMPLETION
Total Project Hours Local Resident Hours Local Resident %
1,404,792 421,308 30%
Local Hourly UtilizationPhase 2