POPLAR RIVER, LUTSEN, MN. SEPARATING THE MEGA-SLIDE FROM THE RIVER (AND MORE) By the stream dream...

Post on 02-Jan-2016

213 views 0 download

Tags:

Transcript of POPLAR RIVER, LUTSEN, MN. SEPARATING THE MEGA-SLIDE FROM THE RIVER (AND MORE) By the stream dream...

POPLAR RIVER, LUTSEN, MN.

SEPARATING THE MEGA-SLIDE FROM

THE RIVER (AND MORE)

By the stream dream team

Stream stabilization/restoration: Conceptually we will separate the stream from the hill, and in the channel we will make the inside of the bend smoother and the outer section of the stream rougher.

Stream stabilization/restoration methods: A Keyed, Minimal, Toe-Down Continuous Natural Boulder Revetment with Integrated Vegetation Combined with an Engineered Vegetated Mini-Swale combined with Bendway Weirs with pre-dug scour holes forming a pool-riffle-pool regime toward the inside of the bend with boulder fields between the Bendway Weirs. {Exhale here}

Stream Project Functions:

Fully functioning both hydraulically & environmentally. Multiple protection redundancy. Revetment provides direct armor protection. Bendway Weirs and boulder fields move scour & thalweg away from attacked bank, with velocities reduced within the Bendway Weir field & boulder fields & on outer bank. Vegetation roughness reduces near-bank flow velocities. Roots strengthen bank & bind soil. Mini-swale captures up-slope colluvium from eroding slope.

PRE-PROJECT PHOTOSby Dave Derrick

AUGUST 13, 2007

(Lowest flow in almost 30 years)

Approximately 200 ft US of the project, looking US

Derrick-8-13-2007-lowest flow in 30 yrs

Derrick-8-13-2007-lowest flow in 30 yrs

Looking DS at the project, upper project limit is at red line

Derrick-8-13-2007

Looking at Mega slump. Note undercut mature veg. None of this will be fixed

Derrick-8-13-2007-lowest flow in 30 yrs

Looking DS. The DS end of the mega slump.

Derrick-8-13-2007-lowest flow in 30 yrs

Looking US. Larger bed material on inside of bend will be relocated to the outside of the bend.

THE PLAN

Stream Project Functions:

Bendway Weirs move scour & the thalweg away from attacked bank, with velocities reduced within weir field & on bank. Vegetation roughness reduces near-bank flow velocities. Roots strengthen bank & bind soil. Mini-swale captures colluvium.

Mega- Slump Stream Project

Planform

Mega Slump

Bridge

Bendway Weir

Keys

Pre-dug Scour Holes

Boulder Revetment

Mini SwaleTransplanted Veg

SUITABLE STONEStone used for toe protection & boulder fields was either natural stone from the

stream or rounded medium-sized boulders in the 1,500 to 2,000 pound class. Stone for the Bendway Weirs

were extremely large rounded boulders, most from the quarry,

typically 4 ft by 5 ft by 6 ft. Stone for keys was a mix of native medium

boulders, very large rounded boulders from the quarry, & gravel-cobble-small

boulder “choke” stone from the stream.

CONSTRUCTION PHOTOS

by Dave Derrick and Jay Michels

AUGUST 5-8, 2008

CONSTRUCTION PIX OF THE

KEY FOR BENDWAY WEIR # 1

A KEY HAS ONE MAIN JOB, TO CONNECT THE

RIVER TRAINING STRUCTURE TO THE REST

OF THE WORLD (DON’T LET THE STREAM GET BEHIND {FLANK} RIVER TRAINING STRUCTURES)

Stream stabilization/restoration: All keys will be trenched perpendicular to the stream into the bank. One side of each key trench will be lined with adventitious rooting willow poles (harvested locally). All keys will use a gravel filter (harvested from the stream), with the key constructed of a mix of monster boulders & well-graded stone (from both the stream and quarry). Stone will then be choked with soil & seeded.

Cross-section for keyway

Detail for keys for the Bendway Weirs & the Minimal Stone Toe Protection

Jay Michels cut about 1,000 willow from near the sewage treatment ponds at the top of the hill for planting within the project.

CONSTRUCTION-POPLAR RIVER @ MEGA-SLUMP-PIX BY JAY MICHELS 8/08

Place Willow Poles against one side of

the trench

Detail for keys for the Bendway Weirs & the Minimal Stone Toe Protection

Granular filter

Dave Derrick in key trench placing large willow poles on DS side of trench

CONSTRUCTION-POPLAR RIVER @ MEGA-SLUMP-PIX BY JAY MICHELS 8/08

Deeply planted willows oriented perpendicular to flow will act as a “Living Dike”, slowing near-bank

flow velocities.

Place stone in trench

Detail for keys for the Bendway Weirs & the Minimal Stone Toe Protection

Choke stone with gravel (white areas) & water in to settle

choke material & water poles

Detail for keys for the Bendway Weirs & the Minimal Stone Toe Protection

Robust key starting to look good!!

CONSTRUCTION-POPLAR RIVER @ MEGA-SLUMP-PIX BY DERRICK 8/5-8/2008

Backfill and overfill with native soils, then compact

(some settling will still occur over time)

Detail for keys for the Bendway Weirs & the Minimal Stone Toe Protection

Key complete except for seeding & mulch. Willow poles will be trimmed (approx. 2/3 of pole in ground, 1/3 out of ground).

CONSTRUCTION-POPLAR RIVER @ MEGA-SLUMP-PIX BY DERRICK 8/5-8/2008

Seeding was accomplished the day after we left

DONE

Detail for keys for the Bendway Weirs & the Minimal Stone Toe Protection

CONSTRUCTION PIX OF

BENDWAY WEIR # 1

Dave Derrick setting the upstream angle of the Bendway Weir #5 (20 degrees upstream from perpendicular, or in other words 70 degrees from the bank).

All Bendway Weirs were angled 20 degrees upstream.

CONSTRUCTION-POPLAR RIVER @ MEGA-SLUMP-PIX BY JAY MICHELS 8/08

From top of key looking down @ hoe digging into streambed so that large stones for the Bendway Weir can be placed at the proper elevation.

CONSTRUCTION-POPLAR RIVER @ MEGA-SLUMP-PIX BY DERRICK 8/5-8/2008

From key looking @ hoe placing first stone (that will abut the key that was just built) for Bendway Weir #1.

CONSTRUCTION-POPLAR RIVER @ MEGA-SLUMP-PIX BY DERRICK 8/5-8/2008

Bendway Weir will be angled toward trees behind hoe bucket.

CONSTRUCTION-POPLAR RIVER @ MEGA-SLUMP-PIX BY DERRICK 8/5-8/2008

LET’S LOOK AT, & ALL AROUND, BENDWAY WEIR

#1

Looking DS @ constructed mini-weir & Bendway Weir #1. Constructed boulder field to left & pool-riffle-pool complex on right side of channel.

CONSTRUCTION-POPLAR RIVER @ MEGA-SLUMP-PIX BY DERRICK 8/5-8/2008

Looking DS @ constructed mini-weir & Bendway Weir #1. Note constructed boulder field & pool riffle-pool complex on right side of channel

CONSTRUCTION-POPLAR RIVER @ MEGA-SLUMP-PIX BY DERRICK 8/5-8/2008

Looking straight at Bendway Weir #1. Jay shooting as-built elevations. Note complex flow.

CONSTRUCTION-POPLAR RIVER @ MEGA-SLUMP-PIX BY DERRICK 8/5-8/2008

CONSTRUCTION PIX OF SEVERAL

SECTIONS OF THE LONGITUDINAL

STONE TOE PROTECTION

Minimal Toe-Down Continuous Natural Appearing Boulder Revetment: Large & small boulders from stream & quarry were placed to form a continuous longitudinal revetment constructed to a height equal to the Q-1.5 flow event plus 2.75 ft (minimum). Revetment has 10-15 ft long vegetated stone keys that tie into the bank. Keys will be located at the end of each Bendway Weir. Bendway Weir spacing varies from 41 to 79 ft.

CONSTRUCTION-POPLAR RIVER @ MEGA-SLUMP-PIX BY DERRICK 8/5-8/2008

A smooth path was cleared on the left side of the channel so that equipment could traverse the length of the project. This stone was

placed in the right side of the channel.

THE MEGA-SLUMP FAILURE ON THE POPLAR RIVER, MN

1 of 8

Stream channel

Eroding bank

2 of 8

Existing earth loosened & some soil-gravel

added in preparation for planting.

THE MEGA-SLUMP FAILURE ON THE POPLAR RIVER, MN

THE MEGA-SLUMP FAILURE ON THE POPLAR RIVER, MN

3 of 8Willow poles will be laid against the bank. Basal

ends should be in vadose zone (capillary zone)

Willow pole plantings (in bunches) at intervals

At intervals soil was loosened, willow poles were placed against the bank & soil placed over the lower half of the willow poles.

CONSTRUCTION-POPLAR RIVER @ MEGA-SLUMP-PIX BY DERRICK 8/5-8/2008

4 of 8

Rounded boulders from both the stream & quarry will be used as a continuous longitudinal revetment.

THE MEGA-SLUMP FAILURE ON THE POPLAR RIVER, MN

Looking DS @ the first section of longitudinal toe we constructed. It is too uniform. We will deconstruction this section & build in more chaos !!!!!

CONSTRUCTION-POPLAR RIVER @ MEGA-SLUMP-PIX BY DERRICK 8/5-8/2008

Looking DS @ the smooth stone revetment in foreground & more chaotic stone toe immediately past the very large boulder

CONSTRUCTION-POPLAR RIVER @ MEGA-SLUMP-PIX BY DERRICK 8/5-8/2008

5 of 8

THE MEGA-SLUMP FAILURE ON THE POPLAR RIVER, MNMini swale can

catch colluvium from eroding upper bank

Looking DS @ the mini-swale landward of the crest of the toe stone that will capture mass wasted material (colluvium) from the unimproved mega-slide.

CONSTRUCTION-POPLAR RIVER @ MEGA-SLUMP-PIX BY DERRICK 8/5-8/2008

6 of 8

THE MEGA-SLUMP FAILURE ON THE POPLAR RIVER, MN

County Soil & Water is considering planting 200 rooted stock plants on the Mega-Slump

6 of 8

THE MEGA-SLUMP FAILURE ON THE POPLAR RIVER, MN

8 Bendway Weirs, each 2 boulders wide, 15 to 22 ft

long, spaced 42 to 79 ft apart

Looking DS @ the stone toe & Bendway Weirs, boulder field not added yet.

CONSTRUCTION-POPLAR RIVER @ MEGA-SLUMP-PIX BY DERRICK 8/5-8/2008

CONSTRUCTION PIX OF RANDOM

SCATTERING OF BOULDERS TO CREATE THE

BOULDER FIELDS BETWEEN THE

BENDWAY WEIRS

Looking DS @ boulder flying though air

CONSTRUCTION-POPLAR RIVER @ MEGA-SLUMP-PIX BY DERRICK 8/5-8/2008

Looking DS @ the big boulder splash

CONSTRUCTION-POPLAR RIVER @ MEGA-SLUMP-PIX BY DERRICK 8/5-8/2008

Stream Project Functions::::::::• Longitudinal toe stone provides scour protection• Toe stone protection completely separates stream from Mega Slump• Willow poles provide vegetative roughness, increase height of “soft

protection”, shades stone & water, & has many wildlife functions {everything from carbon input to structure cover to insect production, beneficial to pollinators, etc.}

• Mini-Swale provides a storage area for colluvium from Mega Slump• Bendway Weirs increase stream roughness, reduce toe scour,

provide diversity & complexity of depth, velocity (horizontal & vertical) & substrate, plus they move the thalweg away from the toe of the eroding bank.

• The dug pools at the ends of the Bendway Weirs provide mini pool-riffle-pool sequences throughout the bend.

• Boulder fields provide additional roughness, plus a “natural” look

CONSTRUCTION COMPLETE

INDIVIDUAL SHOTS OF KEYS &

BENDWAY WEIRS #1-8

Looking at short Bendway Weir US of Bendway Weir # 1. All construction appears quite natural!!!

CONSTRUCTION COMPLETE-POPLAR R. @ MEGA-SLUMP-PIX BY DERRICK 8-8-2008

Looking at Key # 2 and Bendway Weir # 2.

CONSTRUCTION COMPLETE-POPLAR R. @ MEGA-SLUMP-PIX BY DERRICK 8-8-2008

From the Mega-Slump, looking US @ Bendway Weir # 2.

CONSTRUCTION-POPLAR RIVER @ MEGA-SLUMP-PIX BY DERRICK 8/5-8/2008

Looking at Key # 3 and Bendway Weir # 3.

CONSTRUCTION COMPLETE-POPLAR R. @ MEGA-SLUMP-PIX BY DERRICK 8-8-2008

Watching the river flow, looking @ Key #4 & Bendway Weir #4

CONSTRUCTION COMPLETE-POPLAR R. @ MEGA-SLUMP-PIX BY DERRICK 8-8-2008

Looking at Key # 5 & Bendway Weir # 5. Constructed riffle mimics pre-project condition

CONSTRUCTION COMPLETE-POPLAR R. @ MEGA-SLUMP-PIX BY DERRICK 8-8-2008

Pre-project riffle

Looking at Key # 6 & Bendway Weir # 6. Note veg in key

CONSTRUCTION COMPLETE-POPLAR R. @ MEGA-SLUMP-PIX BY DERRICK 8-8-2008

Looking at Key # 7 and Bendway Weir # 7.

CONSTRUCTION COMPLETE-POPLAR R. @ MEGA-SLUMP-PIX BY DERRICK 8-8-2008

Looking at Key # 8 and Bendway Weir # 8.

CONSTRUCTION COMPLETE-POPLAR R. @ MEGA-SLUMP-PIX BY DERRICK 8-8-2008

CONSTRUCTION COMPLETE

(going from upstream to downstream)

Photos by Dave Derrick AUGUST 8, 2008

Looking DS. Boulder field to left, dug pools & riffles on right

CONSTRUCTION COMPLETE-POPLAR R. @ MEGA-SLUMP-PIX BY DERRICK 8-8-2008

Looking from BW #2 US @ upper end of project.

CONSTRUCTION COMPLETE-POPLAR R. @ MEGA-SLUMP-PIX BY DERRICK 8-8-2008

Looking DS @ toe stone & Bendway Weirs 2 - 4.

CONSTRUCTION COMPLETE-POPLAR R. @ MEGA-SLUMP-PIX BY DERRICK 8-8-2008

BW#2BW#3

BW#4

Looking @ Bendway Weir #3. Note flow around weir & through boulders.

CONSTRUCTION COMPLETE-POPLAR R. @ MEGA-SLUMP-PIX BY DERRICK 8-8-2008

BW#3

CONSTRUCTION COMPLETE-POPLAR R. @ MEGA-SLUMP-PIX BY DERRICK 8-8-2008

Looking DS @ toe stone & Bendway Weirs 2 - 4.

BW#2

BW#3

BW#4

Looking at constructed natural appearing random boulder field (foreground) & random chaotic stone toe

CONSTRUCTION COMPLETE-POPLAR R. @ MEGA-SLUMP-PIX BY DERRICK 8-8-2008

Looking US @ pool & colorful riffle

CONSTRUCTION COMPLETE-POPLAR R. @ MEGA-SLUMP-PIX BY DERRICK 8-8-2008

Watching the river flow, looking DS @ Bendway Weir # 5.

CONSTRUCTION COMPLETE-POPLAR R. @ MEGA-SLUMP-PIX BY DERRICK 8-8-2008

Looking @ a riffle & longitudinal stone toe protection. Note pools & rifles.

CONSTRUCTION COMPLETE-POPLAR R. @ MEGA-SLUMP-PIX BY DERRICK 8-8-2008

Looking US @ Bendway Weirs # 7 & # 8 & stone toe.

CONSTRUCTION COMPLETE-POPLAR R. @ MEGA-SLUMP-PIX BY DERRICK 8-8-2008

Looking DS @ Key #8 (with veg) & BW #8. Note pools & flow at end of weir

CONSTRUCTION COMPLETE-POPLAR R. @ MEGA-SLUMP-PIX BY DERRICK 8-8-2008

9 MONTHS AFTER PROJECT

COMPLETIONPhotos by Jay Michaels

May 9, 2009

9 MONTHS LATER-POPLAR R. @ MEGA-SLUMP-PIX BY JAY MICHAELS 5-9-2009

From top of Mega Slump, looking US at entrance conditions into project. White water DS of each Bendway Weir shows weirs are working as designed.

From top of Mega Slump, flow right to left. White water DS of each Bendway Weir shows weirs are working as designed (dissipating energy, producing mini pool-riffle-pool sequences). Thalweg realigned to a location off the stream ends

of the weirs. Inner channel flow reduces bank stress along Mega-Slump.

9 MONTHS LATER-POPLAR R. @ MEGA-SLUMP-PIX BY JAY MICHAELS 5-9-2009

9 MONTHS LATER-POPLAR R. @ MEGA-SLUMP-PIX BY JAY MICHAELS 5-9-2009

From top of Mega Slump, looking DS at second half of project. Bendway Weirs working well, slow water near left bank, thalweg realigned to a

location off the stream ends of the weirs. Exit conditions well behaved.

WE ARE DOG TIRED, THIS PROJECT IS DONE !!

Cleophus Speed Elvis Derrick

to the doubters & nay-sayers, the old raspberry, this project is working!!