Coupling Coil Status
S. Gourlay
August 1, 2012
Office of Science
Coupling Coil Test Prep
• Cooling tube welding– Pressure test
• Horizontal and vertical milling operations– Lead, Quench Protection mounts
• Coil vacuum epoxy impregnation– Gap between cover plate and coil– Seal gap (no leaks!)
• Design/fab holding fixture for potting• Manufacture QP and lead support parts• Install temp sensors, strain gauges
Office of Science
Coupling Coil Status/Activities
• Pressure test complete– Documentation in progress
• QP hardware installed
• Thermal test with fixture complete
• Should start potting today– Out by tomorrow
• Install strain gauges (six) in strategic areas
• Assemble lead stabilizers
• Shipping crate will arrive this week