Office of Science Coupling Coil Status S. Gourlay August 1, 2012.
-
Upload
luke-webster -
Category
Documents
-
view
215 -
download
2
Transcript of Office of Science Coupling Coil Status S. Gourlay August 1, 2012.
Office of Science
Coupling Coil Status
S. Gourlay
August 1, 2012
Office of Science
Coupling Coil Test Prep
• Cooling tube welding– Pressure test
• Horizontal and vertical milling operations– Lead, Quench Protection mounts
• Coil vacuum epoxy impregnation– Gap between cover plate and coil– Seal gap (no leaks!)
• Design/fab holding fixture for potting• Manufacture QP and lead support parts• Install temp sensors, strain gauges
Office of Science
Coupling Coil Status/Activities
• Pressure test complete– Documentation in progress
• QP hardware installed
• Thermal test with fixture complete
• Should start potting today– Out by tomorrow
• Install strain gauges (six) in strategic areas
• Assemble lead stabilizers
• Shipping crate will arrive this week