Post on 18-Nov-2015
description
SULTANATE OF OMAN
MINISTRY OF TRANSPORT AND COMMUNICATIONS DIRECTORATE GENERAL OF ROADS & LAND TRANSPORT
MUSCAT
UPGRADING OF FALAJ AL QABAIL ROUNDABOUT TENDER NO. 51/2012
MONTHLY PROGRESS REPORT NO. 14
FEBRUARY 2015
CONSULTANT:
RENARDET S.A. & PARTNERS CONSULTING ENGINEERS LLC. P.O. Box 579, Muscat, P.C. 100, Sultanate of Oman
CONTRACTOR:
CONSOLIDATED CONTRACTORS CO. LLC P.O. Box 614, Muscat, P.C. 100, Sultanate of Oman
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report February 2015
RENARDET S.A. & PARTNERS Page 1
Table of Contents
1. PROJECT PARTICULARS .............................................................................................................................................. 2
2. SCOPE OF WORK ....................................................................................................................................................... 3
3. TYPICAL CROSS SECTIONS .......................................................................................................................................... 4
4. SITE VISITS/ MEETINGS .............................................................................................................................................. 6
5. F DEPLOYMENT ....................................................................................................................... 7
6. PROGRESS S-CURVE ................................................................................................................................................... 8
7. STATUS OF MAJOR ACTIVITIES ................................................................................................................................ 10
8. BRIDGE PROGRESS SCHEDULE ................................................................................................................................. 11
9. MSE WALLS PROGRESS SCHEDULE ........................................................................................................................... 12
10. BOX CULVERTS PROGRESS SCHEDULE ...................................................................................................................... 17
11. PROGRESS STATUS OF RETAINING WALLS ............................................................................................................... 22
12. PROGRESS STATUS OF UTILITY CROSSING DUCTS .................................................................................................... 23
13. PROJECT PROGRESS STRIP CHART ........................................................................................................................... 27
14. FINANCIAL STATUS OF PAYMENTS .......................................................................................................................... 33
15. DETAILS OF EQUIPMENT AVAILABLE AT SITE ........................................................................................................... 34
16. EQUIPMENT HISTOGRAM ........................................................................................................................................ 35
17. DETAILS OF MANPOWER AVAILABLE AT SITE .......................................................................................................... 36
18. MANPOWER HISTOGRAM ....................................................................................................................................... 37
19. QA/QC REPORTS ...................................................................................................................................................... 38
20. STATUS OF MATERIAL APPROVALS .......................................................................................................................... 43
21. ......................................................................................................................................... 45
22. CORRESPONDENCE DURING THE MONTH................................................................................................................ 46
23. PROGRESS PHOTOGRAPHS ...................................................................................................................................... 49
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report February 2015
RENARDET S.A. & PARTNERS Page 2
1.
Client: Ministry of Transport & Communications
P.O. Box 684, Muscat, Postal Code 113
Directorate General of Roads
Sultanate of Oman.
Consultant: Renardet S.A & Partners L.L.C.
P.O. Box 579, Muscat, Postal Code 100
Sultanate of Oman.
Contractor: Consolidated Contractors Company L.L.C.
P.O. Box 614, Muscat, Postal Code 100
Sultanate of Oman.
Project Commencement Date: 30.10.2013
Mobilization Period: 60 Days
Construction Period: 548 Days
Completion date: 29.06.2015
Original Contract Value:
(Including Contingencies) R.O. 17,884,403.000
Amount of Contingencies: R.O. 1,402,155.613
Original Contract Value:
(Excluding Contingencies) R.O. 16,482,247.387
Planned Physical Progress for January 2015 6.50%
Actual Physical Progress for January 2015 4.61%
Planned physical progress cumulative up to
end of January 2015
77.31%
Achieved physical progress cumulative up
to end of January 2015 67.88%
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report February 2015
RENARDET S.A. & PARTNERS Page 3
2.
This project is located in Batinah Region on existing Batinah Highway in the Wilayat Sohar and
consists of construction of an interchange in place of existing roundabout along with allied works.
Total length of the project along Batinah highway is about 4.0 km which shall be converted from four
lanes to six lanes with tapering back to 4lanes, all as shown on plans. Also included in the scope of
work is the construction of service roads, pedestrian underpasses.
The work also includes expropriation of properties, relocation/protection of services (sewerage,
telephone, electricity, water, irrigation) road lighting works and traffic signals.
Major items within the scope of work consist of but not limited to the following:
Removal of existing asphalt surface, extension of existing embankment and earthwork to
achieve the designed profile and gradient.
Removal of existing drainage structures and construction of new ones including protection
works as shown on construction drawings and as directed.
Expropriation of open/built up properties and removal of existing structures thereupon.
Construction of interchange ramps, Box Girder Bridge, roundabout, pedestrian underpasses and
service roads.
Provision of new street lighting system/traffic signals and removal/disposal of existing street
light poles including conductors/cables, transformers, feeder pillars, foundations etc., all for the
proper completion of the job.
Construction of earthen embankment/sub grade, sub-base, aggregate base course, bituminous
base course and bituminous wearing course as per details on the construction drawings.
Installation of road side furniture (traffic signs, road marking etc.) and protection works on
embankment slopes.
Relocation/Protection of existing LT, 11KV and 33KV transmission lines and allied items
(transformers etc.) as per the requirements of concerned authority.
Relocation/Protection of existing utilities (sewerage, telephone, electricity, water lines and
irrigation) as per the requirements of concerned authorities.
Provision of ducts for future utilities as per the requirements of utility operator.
Construction of concrete safety barriers, fixing of guard rails and paving tiles.
Provision of traffic diversion in coordination with concerned authorities.
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report February 2015
RENARDET S.A. & PARTNERS Page 4
3.
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report February 2015
RENARDET S.A. & PARTNERS Page 5
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report February 2015
RENARDET S.A. & PARTNERS Page 6
4.
S. No. Details of Site Visit/ meeting Date Final Outcome/ Decisions
1 Meeting with Director of QS at
Muscat Office.
02.02.2015 Director instructed Consultant to
get the Variation Order quantities
verified by Renardet QS.
2 Evaluation of Payment Application
Surveyor.
04.02.2015
to
07.02.2015
Application No. 10 is completed.
3 Meeting with Dept. of Water Supply 19.02.2015 1. Water Supply Department
instructed to submit corrected
drawing showing the fittings details
for their approval.
2. Electrical Cable Routing Drawing
shall be submitted.
3. Material Submittal for Fittings and
Valves shall be submitted for
approval.
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report February 2015
RENARDET S.A. & PARTNERS Page 7
5.
S.
No. Name Designation
Date of
Joining
1. Roberto Benigni Head Supervision Projects
2. Muneer Abdul Resident Engineer 19.03.2014
3. Hussein Shah Material Engineer 04.01.2014
4. Ernesto B. Paredes Bridge Engineer 16.04.2014
5. Sande H Tangaras Civil Engineer 08.06.2014
6. Danilo Quantity Surveyor 19.06.2014
6. Mohamed Safie Land Surveyor 04.01.2014
7. Aseef Iqbal Site Inspector 10.02.2014
8. Alaa Aldin Abdelfatah Site Inspector 30.03.2014
9. Walid Samy Abdoh Mostafa Material Inspector 01.04.2014
10. Haneefa Mohmmed Al Zadjali Secretary 13.04.2014
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report February 2015
RENARDET S.A. & PARTNERS Page 8
6. -
2013
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
0.01 0.25 1.42 4.23 7.25 10.06 9.42 9.73 10.21 9.79 8.49 5.72 4.55 3.56 2.79 3.83 3.55 3.47 1.67 - - - -
0.11 0.14 0.23 0.28 1.71 3.18 6.84 9.16 9.14 9.08 7.69 7.98 8.32 6.96 6.50 4.68 3.59 3.34 4.43 3.29 1.64 1.11 0.62
- 0.28 0.18 1.01 3.69 4.85 5.18 7.36 7.30 9.33 6.20 6.02 6.23 5.64 4.52 - - - - - - - -
0.01 0.26 1.67 5.91 13.15 23.21 32.64 42.37 52.58 62.37 70.86 76.59 81.13 84.69 87.48 91.31 94.86 98.33 100.00 100.00 100.00 100.00 100.00
0.11 0.25 0.48 0.76 2.47 5.64 12.48 21.64 30.78 39.87 47.55 55.53 63.86 70.81 77.31 81.99 85.59 88.93 93.35 96.64 98.28 99.39 100.00
- 0.28 0.45 1.46 5.16 10.01 15.19 22.55 29.86 39.18 45.39 51.41 57.63 63.27 67.79
CUMULATIVE PROGRESS
CL14 Org Plan Cumulative %
Actual Cumulative
2014 2015
MONTHLY PROGRESS
CL14 Org Plan per Month %
Actual per Month
Revised Sch. per Month %
Revised Sch. Cummulative %
0.00
20.00
40.00
60.00
80.00
100.00
120.00
-
2
4
6
8
10
12
Dec
Jan
Fe
b
Ma
r
Apr
Ma
y
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Fe
b
Ma
r
Apr
Ma
y
Jun
Jul
Aug
Sep
Oct
2013 2014 2015
% C
um
ula
tive
% M
ON
TH
LY
MONTHS
UPGRADING OF FALAJ AL QABAIL ROUNDABOUT PROJECT - OMANMONTHLY CL 14 PLANNED VS. ACTUAL MANHOURS
CL14 Org Plan per Month % Revised Sch. per Month % Actual per Month CL14 Org Plan Cumulative % Revised Sch. Cummulative % Actual Cumulative
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report February 2015
RENARDET S.A. & PARTNERS Page 9
REV.: 0
PERIOD ENDING: Feb-15
2013
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
CL14 Plan % 0.30 8.67 19.23 26.89 31.77 36.64 41.51 46.39 51.26 56.13 61.01 65.88 70.76 75.63 80.50 85.38 90.25 95.13 100.00 100.00 100.00 100.00 100.00
Revised Plan % 4.11 9.30 17.58 24.18 30.90 35.16 38.97 42.78 46.60 50.41 54.23 58.04 61.86 65.67 69.48 73.30 77.11 80.93 84.74 88.56 92.37 96.18 100.00
Actual - 6.62 13.03 22.36 37.31 43.00 44.11 51.21 56.24 60.13 65.67 69.96 74.25 74.25 78.54
CL14 Plan % 0.00 0.00 0.38 20.37 47.70 48.33 48.33 48.33 48.33 48.33 48.33 48.33 48.33 59.91 77.84 90.27 94.93 100.00 100.00 100.00 100.00 100.00 100.00
Revised Plan % - - - - - 7.40 29.85 78.13 78.13 78.13 78.13 78.13 78.13 78.13 78.13 78.13 78.13 80.66 87.59 88.57 100.00 100.00 100.00
Actual - 10.09 10.09 17.59 19.52 77.42 69.96 70.18 70.18 70.18 83.49 84.12 84.95 84.46 84.46
CL14 Plan % 0.00 0.00 0.00 0.78 6.58 16.76 29.38 41.37 58.64 66.60 74.18 82.85 84.75 84.75 85.24 92.34 92.34 98.36 100.00 100.00 100.00 100.00 100.00
Revised Plan % - - - - - - - 3.32 12.89 28.83 43.89 60.03 74.82 90.03 95.24 95.95 95.95 96.09 98.30 99.46 99.54 100.00 100.00
Actual - - - - 4.35 4.89 - 5.27 14.93 29.52 47.15 47.31 67.50 79.41 74.90
CL14 Plan % 0.00 0.00 1.01 9.21 29.30 45.91 56.90 62.24 64.59 67.94 69.08 69.08 75.05 82.85 93.48 98.64 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Revised Plan % - - - - - 4.26 8.17 16.03 32.68 53.13 67.05 67.47 67.47 67.90 68.32 68.32 68.32 81.11 93.02 97.11 100.00 100.00 100.00
Actual - - - 5.00 5.00 53.23 62.16 74.91 78.29 91.86 98.62 115.33 55.50 60.38 55.97
CL14 Plan % 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11.07 26.27 41.98 59.98 78.73 79.90 79.90 85.20 89.45 92.60 100.00 100.00 100.00 100.00 100.00
Revised Plan % - - - - - - - - - - - 3.58 17.42 31.37 51.32 75.82 75.82 75.82 75.82 87.25 87.25 98.60 100.00
Actual 1.26 3.19 5.42 10.68 27.25 39.98
CL14 Plan % 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.08 7.77 19.32 31.22 44.94 51.98 52.14 90.14 90.14 100.00 100.00 100.00 100.00 100.00
Revised Plan % - - - - - - - - - - - - - 0.08 8.44 22.42 46.57 51.97 52.05 86.74 90.13 93.11 100.08
Actual
CL14 Plan % 0.00 0.00 0.23 1.43 2.97 10.17 23.65 36.51 51.47 63.06 74.26 75.97 77.37 80.05 82.40 88.97 92.13 98.55 100.00 100.00 100.00 100.00 100.00
Revised Plan % - - - 0.26 2.64 7.33 20.62 35.14 50.06 62.76 68.40 72.78 74.07 74.67 83.42 84.04 84.30 87.32 95.58 98.11 99.44 100.00 100.00
Actual - - - 0.48 1.26 5.59 14.93 27.72 40.08 55.38 66.20 71.35 77.45 79.50 81.70
CL14 Plan % 0.00 0.00 4.02 15.21 34.62 57.89 69.26 81.40 83.38 83.46 84.50 92.89 99.96 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Revised Plan % - - - - 2.77 7.75 13.76 22.09 29.64 39.02 49.64 59.51 71.33 85.14 87.00 93.50 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Actual - - - 0.01 6.05 14.73 18.14 22.33 26.30 30.75 34.14 46.19 56.00 70.86 76.31
CL14 Plan % 0.00 0.00 0.00 0.00 0.00 0.38 1.21 2.63 3.42 4.23 5.50 6.08 6.08 34.35 99.38 99.76 99.76 100.00 100.00 100.00 100.00 100.00 100.00
Revised Plan % - - - - - - - - - - 8.09 26.17 57.85 78.53 94.70 94.70 94.70 94.70 98.41 100.00 100.00 100.00 100.00
Actual - - - 2.50 69.64 14.39 13.24 16.19 16.72 27.56 21.22 41.44 54.32 63.05 83.60
CL14 Plan % 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.80 17.87 43.85 61.59 72.98 81.15 83.94 84.42 85.35 92.86 96.39 100.00 100.00 100.00 100.00 100.00
Revised Plan % - - - - - - - - - - 7.02 20.33 38.29 50.60 59.52 72.89 81.07 83.55 86.89 90.26 95.34 98.27 100.00
Actual - - - - - 2.61 4.98 6.42 8.31 10.67 12.36 14.45 16.54 17.77 24.53
CL14 Plan % 0.00 0.00 0.00 4.43 17.23 33.36 49.13 65.07 80.79 93.82 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Revised Plan % - - - - - 0.99 2.30 17.26 33.64 49.01 64.70 79.88 95.44 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Actual - - - 6.16 9.87 17.63 25.69 35.90 49.03 65.95 72.27 72.29 83.86 91.41 98.93
CL14 Plan % 0.00 0.00 0.00 0.00 0.00 0.17 0.79 1.43 5.65 13.41 21.84 30.56 32.94 70.94 75.04 94.02 96.43 100.00 100.00 100.00 100.00 100.00 100.00
Revised Plan % - - - - - - - 0.33 2.34 9.42 17.07 23.51 31.40 41.66 47.49 47.55 47.55 83.28 93.95 97.61 100.00 100.00 100.00
Actual - - - 0.13 5.52 9.26 13.38 16.87 17.75 20.45 14.38 26.70 24.67 22.20 35.00
Revised Plan 0.11 0.25 0.48 0.76 2.47 5.64 12.48 21.64 30.78 39.87 47.55 55.53 63.86 70.81 77.31 81.99 85.59 88.93 93.35 96.64 98.28 99.39 100.00
Actual Cum - 0.28 0.45 1.46 5.16 10.01 15.19 22.55 29.86 39.18 45.39 51.41 57.63 63.27 67.79 - - - - - - - -
2013
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
0.01 0.25 1.42 4.23 7.25 10.06 9.42 9.73 10.21 9.79 8.49 5.72 4.55 3.56 2.79 3.83 3.55 3.47 1.67 - - - -
0.11 0.14 0.23 0.28 1.71 3.18 6.84 9.16 9.14 9.08 7.69 7.98 8.32 6.96 6.50 4.68 3.59 3.34 4.43 3.29 1.64 1.11 0.62
- 0.28 0.18 1.01 3.69 4.85 5.18 7.36 7.30 9.33 6.20 6.02 6.23 5.64 4.52
0.01 0.26 1.67 5.91 13.15 23.21 32.64 42.37 52.58 62.37 70.86 76.59 81.13 84.69 87.48 91.31 94.86 98.33 100.00 100.00 100.00 100.00 100.00
0.11 0.25 0.48 0.76 2.47 5.64 12.48 21.64 30.78 39.87 47.55 55.53 63.86 70.81 77.31 81.99 85.59 88.93 93.35 96.64 98.28 99.39 100.00
- 0.28 0.45 1.46 5.16 10.01 15.19 22.55 29.86 39.18 45.39 51.41 57.63 63.27 67.79
2014 2015
MONTHLY PROGRESS
CL14 Org Plan per Month %
Actual per Month
CUMULATIVE PROGRESS
CL14 Org Plan Cumulative %
Actual Cumulative
MMEP Works &
Ducts4.03
TOTAL 100.000
Revised Sch. per Month %
Revised Sch. Cummulative %
83,264
2,063,644
L MSE walls 6.84
J Drainage Works 1.50
KIncidental
Construction13.33
30,920
275,037
141,190
IConcrete for
Bridge22.12
H
Concrete for
Box Culvert
/Underpas
38.19788,138
456,522
GBituminous
Pavement3.57
FSubbase &
Aggregate Base2.4250,004
73,724
EStructural
Excavation0.72
D Embankment 3.5974,043
14,821
C
Clearing &
Removal of
Obstructions
0.95
2015
B Road Diversions 2.73
Budgeted
Man-Hrs
56,423
19,558
UPGRADING OF FALAJ AL QABAIL ROUNDABOUT - OMAN
MANHOURS OVERALL PROJECT S-CURVE
Item Description Wtd.
%
Plan/
Actual
2014
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report February 2015
RENARDET S.A. & PARTNERS Page 10
7.
Sl. No.
Description Unit BOQ Qty.
(Revised)
Actual Qty.
% Completion
1 Clearing & Grubbing M2 162,000 138,801 85.67%
2 Borrow Excavation (to embankment)
M3 430,000 289,392 67.30%
3 Granular Sub-base M3 47,000 24,920 53.02%
4 Concrete for Culverts M3 19,000 13,422 70.64%
5 Concrete for Bridge M3 9,500 6,449 67.88%
6 Steel reinforcement Fixing ton 4,800 3,326 69.29%
7 Working Piles M3 2,826 2,826 100.00%
8 Mortared Stone Riprap M3 5,210 0.00 0.00%
9 MSE Walls Fixing M2 13,030 12,394 95.12%
10 RCC Drainage Pipes LM 4,350 3,251 74.74%
11 Aggregate Base Course M3 64,000 22,673 35.43%
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report February 2015
RENARDET S.A. & PARTNERS Page 11
8.
ACTIVITY AB1 L P1L P2L P4L P5L AB2 L
PEDESTAL/POT BEARING 9-Nov-14 9-Nov-14 9-Nov-14 15-Nov-14 - - 24-Feb-15 19-Feb-15
PIER N/A - - - - N/A
2nd Lift (backwall) 13-Aug-14 19-Aug-14 29-Sep-14 4-Sep-14 (backwall)
Height (m) 15-Feb-15 6.920 6.920 6.920 6.920 -
1st Lift (note: recess) 23-Jul-14 7-Aug-14 15-Sep-14 10-Aug-14 (note: recess)
Height (m) 18-Jan-15 1.153 1.210 1.248 1.225 -
BIT. PAINTING on-going 28-May-14 26-Jun-14 4-Sep-14 23-Jun-14 on-going
PILE CAP (Pier & Abut.) 4-Nov-14 17-May-14 18-Jun-14 25-Aug-14 11-Jun-14 7-Jan-15
F/P & BLINDING 21-Oct-14 11-May-14 11-Jun-14 17-Aug-14 3-Jun-14 24-Dec-14
ACTIVITY AB1 R P1R P2R P4R P5R AB2 R
PEDESTAL/POT BEARING 16-Oct-14 14-Oct-14 14-Oct-14 16-Oct-14 22-Jan-15 18-Jan-15 18-Jan-15 12-Jan-15
PIER N/A - - - - N/A
2nd Lift (backwall) 9-Jun-14 28-Jun-14 20-Sep-14 10-Jul-14 (backwall)
Height (m) 13-Jan-15 6.920 6.920 6.920 6.920 -
1st Lift (note: recess) 20-May-14 11-Jun-14 10-Sep-14 22-Jun-14 (note: recess)
Height (m) 16-Dec-15 0.366 0.423 0.461 0.438 -
BIT. PAINTING on-going 12-May-14 25-May-14 4-Sep-14 31-May-14 on-going
PILE CAP (Pier & Abut.) 9-Oct-14 4-May-14 13-May-14 27-Aug-14 20-May-14 22-Dec-14
F/P & BLINDING 2-Oct-14 27-Apr-14 7-May-14 20-Aug-14 14-May-14 14-Dec-14
PREVIOUSPREVIOUS
MONTHTHIS MONTH
0.649
8-May-14
30-Apr-14
22-Apr-14
P3R
-
22-Jun-14
6.920
26-May-14
SUB-STRUCTURE WORK PROGRESS (RHS)
SUB-STRUCTURE WORK PROGRESS (LHS)
P3L
24-Jul-14
6.920
29-Jun-14
1.440
17-May-14
-
8-May-14
1-May-14
AB1 L P1L P2L P3L P3L P4L P5L AB2 L
EXPANSION JOINT - N/A N/A - - N/A N/A -
CONCRETE BARRIER
Grouting
Prestressing
TOP SLAB (DECK) 1-Jan-15 1-Jan-15 1-Jan-15 1-Jan-15 - - - -
WEB: - - - - - - - -
W8 16-Dec-14 16-Dec-14 16-Dec-14 16-Dec-14 - - - -
W7 16-Dec-14 16-Dec-14 16-Dec-14 16-Dec-14 - - - -
W6 16-Dec-14 16-Dec-14 16-Dec-14 16-Dec-14 - - - -
W5 16-Dec-14 16-Dec-14 16-Dec-14 16-Dec-14 - - - -
BOTTOM SLAB (BASE) 7-Dec-14 7-Dec-14 7-Dec-14 7-Dec-14 - - - -
AB1 R P1R P2R P3R P3R P4R P5R AB2 R
EXPANSION JOINT - N/A N/A - - N/A N/A -
CONCRETE BARRIER
Grouting
Prestressing
TOP SLAB (DECK) 26-Nov-14 26-Nov-14 26-Nov-14 26-Nov-14 - - - -
WEB: - - - - - - - -
W4 10-Nov-14 10-Nov-14 10-Nov-14 10-Nov-14 22-Feb-15 22-Feb-15 22-Feb-15 22-Feb-15
W3 10-Nov-14 10-Nov-14 10-Nov-14 10-Nov-14 22-Feb-15 22-Feb-15 22-Feb-15 22-Feb-15
W2 10-Nov-14 10-Nov-14 10-Nov-14 10-Nov-14 22-Feb-15 22-Feb-15 22-Feb-15 22-Feb-15
W1 10-Nov-14 10-Nov-14 10-Nov-14 10-Nov-14 22-Feb-15 22-Feb-15 22-Feb-15 22-Feb-15
BOTTOM SLAB (BASE) 28-Oct-14 28-Oct-14 28-Oct-14 28-Oct-14 9-Feb-15 9-Feb-15 9-Feb-15 9-Feb-15
12/13/2014 (W1, W2, W3, W4)
12/7/2014
-
-
-
-
Dec-14 -
Jan-15 -
1/13/2015 (W5 & W6); 1/15/2015 (W7 & W8)
1/8/2015
ACTIVITY (RHS)SUPER-STRUCTURE (BRIDGE 1 - RHS) SUPER-STRUCTURE (BRIDGE 2 - RHS)
SUPER-STRUCTURE (BRIDGE 4 - LHS) SUPER-STRUCTURE (BRIDGE 3 - LHS)ACTIVITY (LHS)
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report February 2015
RENARDET S.A. & PARTNERS Page 12
9.
DATE Elevation DATE
FROM TOFOUNDATION
/BLINDINGFROM TO
FOUNDATION
/BLINDING
22+702.653 22+760 2-Oct-14 22+718.936 22+810 17-Sep-14
3-Oct-14 18-Sep-14
22+760 22+825 30-Sep-14 22+810 22+893.032 9-Aug-14
1-Oct-14 10-Aug-14
22+825 22+840 13-Jul-14 22+893.032 22+976.294 13-Aug-14
14-Jul-14 14-Aug-14
22+840 22+880 6-Jul-14 22+976.294 23+040 18-Aug-14
13-Jul-14 19-Aug-14
22+880 22+908.387 10-Aug-14 23+040 23+088.046 26-Jul-14
11-Aug-14 27-Jul-14
22+908.387 22+969.478 3-Jul-14 23+088.046 23+130 21-Jul-14
5-Jul-14 22-Jul-14
22+969.478 23+000 4-Aug-14 23+130 23+191.774 7-Jul-14
5-Aug-14 10-Jul-14
23+000 23+025 20-Jul-14 23+191.774 23+270.800 26-Jun-14
21-Jul-14 27-Jun-14
23+025 23+070 17-Jul-14
18-Jul-14
23+070 23+140 30-Jun-14
1-Jul-14 DATE
23+140 23+164.573 16-Jun-14 FROM TOFOUNDATION
/BLINDING
17-Jun-14 23+270.762 (L) 23+270.800 (R ) 26-Jun-14
23+164.573 23+237.536 23-Jun-14 27-Jun-14
24-Jun-14
23+237.536 23+270.762 17-Jun-14
18-Jun-14
PREVIOUSP R EVIOUS
M ON T HTHIS MONTH
El. 21.20
LOCATION (AB 1)
Elevation
Elevation
LOCATION (LHS)
El. 21.20
El. 22.00
El. 22.00
LOCATION (RHS)
El. 20.40
El. 22.00
El. 22.00
El. 22.80
El. 22.00
El. 20.40
El. 22.80
DATE DATE
FROM TOFOUNDATION
/BLINDINGFROM TO
FOUNDATION
/BLINDING
23+508.239 23+520 15-Sep-14 23+508.239 (L) 23+508.197 (R ) 15-Sep-14
16-Sep-14 16-Sep-14
23+520 23+580.877 20-Aug-14
21-Aug-14
23+580.877 23+650 26-Aug-14 Elevation DATE
27-Aug-14 FROM TOFOUNDATION
/BLINDING
23+650 23+735 1-Sep-14 23+508.197 23+607.634 8-Sep-14
2-Sep-14 9-Sep-14
23+735 23+790 19-Sep-14 23+607.634 23+740 22-Sep-14
20-Sep-14 23-Sep-14
23+790 23+827.635 10-Oct-14 23+740 23+750 16-Oct-14
11-Oct-14 17-Oct-14
23+827.635 23+949.895 15-Oct-14 23+750 23+950.153 3-Nov-14
16-Oct-14 4-Nov-14
El. 23.30
El. 24.90
El. 24.10
El. 23.30
LOCATION (LHS) LOCATION (AB 2)Elevation
El. 24.10
Elevation
El. 23.30
LOCATION (RHS)
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report February 2015
RENARDET S.A. & PARTNERS Page 13
22+825 22+840 22+880 22+908.387 22+969.478 22+991 23+084 23+164.573 23+237.536 23+270.762
24.363 Elev. 24.882 Elev. 26.054 Elev. 26.986 Elev. 28.796 Elev. 29.326 Elev. 31.680 Elev. 33.382 Elev. 34.590 Elev. 34.915 Elev.
23+066 23+110 -34.800 - - - - - - 23+036 23+137 23+180 -34.000 - - - - - - 23+007 - - -33.200 - - - - - - - 2-Feb-15 2-Feb-15 2-Feb-1532.400 - - - - - - 21-Jan-15 21-Jan-15 27-Jan-15 29-Jan-1531.600 - - - - - - 15-Jan-15 15-Jan-15 6-Jan-15 6-Jan-1530.800 - - - - - 22+975 11-Jan-15 11-Jan-15 2-Jan-15 5-Jan-1530.000 - - - - - - 8-Jan-15 13-Nov-14 13-Nov-14 8-Jan-1529.200 - - - - - 28-Dec-14 28-Dec-14 19-Oct-14 1-Oct-14 1-Oct-1428.400 - - - - 22+922 22-Dec-14 22-Dec-14 18-Oct-14 24-Sep-14 24-Sep-1427.600 - - 22+870 - - 16-Dec-14 16-Dec-14 20-Sep-14 18-Sep-14 18-Sep-1426.800 - - - - 9-Dec-14 9-Dec-14 18-Nov-14 9-Sep-14 15-Sep-14 15-Sep-1426.000 22+810 - 21-Dec-14 21-Dec-14 4-Dec-14 4-Dec-14 20-Oct-14 4-Sep-14 28-Aug-14 28-Aug-1425.200 22+727 - 21-Dec-14 21-Dec-14 5-Nov-14 5-Nov-14 16-Sep-14 26-Aug-14 19-Aug-14 19-Aug-1424.400 - - 25-Nov-14 25-Nov-14 29-Oct-14 29-Oct-14 4-Sep-14 18-Aug-14 6-Aug-14 6-Aug-1423.600 5-Jan-15 10-Nov-14 10-Nov-14 10-Nov-14 21-Sep-14 17-Sep-14 27-Aug-14 13-Aug-14 24-Jul-14 24-Jul-1422.800 27-Dec-14 22-Sep-14 22-Sep-14 22-Sep-14 11-Sep-14 24-Aug-14 9-Aug-14 28-Jul-14 - 13-Jul-1422.000 27-Nov-14 3-Sep-14 3-Sep-14 3-Sep-14 28-Aug-14 - - - - -21.200 18-Nov-14 28-Aug-14 28-Aug-14 28-Aug-14 - - - - - -
20.400 - - - - - - - - - -
22+810 22+893.032 22+976.294 23+035 23+088.046 23+191.774 23+270.800 23+270.762 (L) 23+270.8 (R )
23.697 Elev. 25.464 Elev. 27.221 Elev. 28.810 Elev. 30.105 Elev. 32.318 Elev. 33.340 Elev. 29.844 Elev. 29.056 Elev.
23+2234 to 23+270
23+137 23+218 to 23+234
23+116 23+234
33.200 - - - - - 23+098 - -32.400 - - - - - - 1/22 & 27/2015 - -31.600 - - 22+948 - 23+066 18-Jan-15 18-Jan-15 - -30.800 - - 22+941 23+005 - 8-Jan-15 8-Jan-15 - -30.000 - - 22+908 - 11-Jan-15 24-Dec-14 24-Dec-14 21-Oct-14 -29.200 - - 22+903 - 7-Jan-15 16-Nov-14 30-Sep-14 28-Sep-14 28-Sep-1428.400 - - - 24-Dec-14 24-Dec-14 30-Sep-14 24-Sep-14 24-Sep-14 24-Sep-1427.600 - 22+866 11-Dec-14 22-Dec-14 22-Dec-14 27-Sep-14 18-Sep-14 19-Sep-14 19-Sep-1426.800 - 22+833 11-Dec-14 16-Nov-14 16-Nov-14 13-Sep-14 13-Sep-14 11-Sep-14 11-Sep-1426.000 22+791 - 1-Dec-14 20-Oct-14 20-Oct-14 2-Sep-14 31-Aug-14 28-Aug-14 28-Aug-1425.200 22+731 31-Dec-14 18-Nov-14 18-Oct-14 18-Oct-14 24-Aug-14 18-Aug-14 18-Aug-14 18-Aug-1424.400 - 22-Dec-14 23-Oct-14 20-Sep-14 20-Sep-14 13-Aug-14 6-Aug-14 7-Aug-14 7-Aug-1423.600 20-Dec-14 20-Dec-14 25-Sep-14 8-Sep-14 8-Sep-14 9-Aug-14 24-Jul-14 24-Jul-14 24-Jul-1422.800 15-Dec-14 15-Dec-14 18-Sep-14 21-Aug-14 18-Aug-14 - 13-Jul-14 13-Jul-14 13-Jul-1422.000 27-Nov-14 23-Sep-14 26-Aug-14 - - - - - -21.200 18-Nov-14 4-Sep-14 - - - - - - -
20.400 - - - - - - - - -
PREVIOUSP R EVIOUS
M ON T HTHIS MONTH
RHS (AB 1), from Sta. 22+718.936 (22.932 Elev.) to Sta. 23+270.800 (33.340 Elev.)
LHS (AB 1), from Sta. 22+702.653 (22.275 Elev.) to Sta. 23+270.762 (34.915 Elev.)
ELEV.
ELEV.
AB 1 Face
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report February 2015
RENARDET S.A. & PARTNERS Page 14
23+520 23+580.877 23+650 23+703 23+730 23+827.635 23+949.895
34.922 Elev. 34.205 Elev. 33.016 Elev. 31.936 Elev. 31.194 Elev. 28.899 Elev. 27.625 Elev.
34.500 - - 23+626 23+669 - - -33.700 - - 22-Feb-15 - - - -32.900 12-Feb-15 12-Feb-15 12-Feb-15 12-Feb-15 - 23+766 -32.100 2-Feb-15 2-Feb-15 20-Jan-15 20-Jan-15 - 23+802 -31.300 15-Jan-15 15-Jan-15 19-Jan-15 19-Jan-15 - - 23+845
30.500 12-Jan-15 12-Jan-15 12-Jan-15 12-Jan-15 12-Jan-15 22-Feb-15 23+914
29.700 - - - - - 15-Jan-15 -28.900 - - 24-Dec-14 24-Dec-14 24-Dec-14 4-Jan-15 4-Jan-1528.100 22-Dec-14 22-Dec-14 22-Dec-14 22-Dec-14 22-Dec-14 31-Dec-14 1-Jan-1527.300 6-Dec-14 6-Dec-14 6-Dec-14 6-Dec-14 6-Dec-14 27-Dec-14 -26.500 8-Nov-14 8-Nov-14 15-Nov-14 15-Nov-14 24-Nov-14 22-Dec-14 22-Dec-1425.700 29-Oct-14 29-Oct-14 1-Nov-14 1-Nov-14 16-Nov-14 20-Dec-14 20-Dec-1424.900 13-Oct-14 13-Oct-14 26-Sep-14 26-Sep-14 13-Nov-14 8-Dec-14 -24.100 25-Sep-14 25-Sep-14 - - - - -23.300 - - - - - - -
23+508.239 (L) 23+508.197-R 23+607.634 23+669 23+720 23+950.15329.951 Elev. 29.165 Elev. 32.167 Elev. 31.032 Elev. 29.874 Elev. 26.050 Elev.
33.700 - - - 23+628 - 23+736
32.900 - - - - - 23+791
32.100 - - 13-Feb-15 13-Feb-15 23+705 23+848
31.300 - - 2-Feb-15 24-Jan-15 - 23+917
30.500 24-Dec-14 - 15-Jan-15 15-Jan-15 20-Jan-15 -29.700 24-Dec-14 22-Dec-14 11-Jan-15 11-Jan-15 18-Jan-15 18-Jan-1528.900 24-Dec-14 22-Dec-14 6-Jan-15 6-Jan-15 18-Jan-15 18-Jan-1528.100 22-Dec-14 22-Dec-14 28-Dec-13 28-Dec-13 12-Jan-15 12-Jan-1527.300 16-Dec-14 6-Dec-14 10-Dec-13 24-Dec-13 7-Jan-15 7-Jan-1526.500 26-Nov-14 26-Nov-14 8-Dec-14 29-Nov-14 29-Nov-14 2-Jan-1525.700 5-Nov-14 5-Nov-14 11-Nov-14 25-Nov-14 25-Nov-14 22-Dec-1424.900 16-Oct-14 16-Oct-14 15-Oct-14 15-Oct-14 21-Nov-14 15-Dec-1424.100 30-Sep-14 30-Sep-14 9-Oct-14 - - -23.300 - - - - - -
ELEV.AB 2 Face
LHS (AB 2), from Sta. 23+508.239 (35.015 Elev.) to Sta. 23+949.895 (27.625 Elev.)ELEV.
R HS ( A B 2 ) , f rom 2 3 +50 8 .19 7 ( 3 3 .4 4 0 Elev.) t o 2 3 +9 50 .153 ( 2 6 .0 50 Elev.)
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report February 2015
RENARDET S.A. & PARTNERS Page 15
FROM TO FROM TO
22+702.653 22+712 15-Jan-15 9-Feb-15 16-Feb-15 20-Feb-15 22+718.936 22+731 5-Jan-15 8-Jan-15 21-Jan-15 18-Jan-15
22+712 22+724 15-Jan-15 24-Jan-15 16-Feb-15 20-Feb-15 22+731 22+743 4-Jan-15 7-Jan-15 21-Jan-15 18-Jan-15
22+724 22+736 15-Jan-15 19-Jan-15 2-Feb-15 5-Feb-15 22+743 22+755 4-Jan-15 7-Jan-15 13-Jan-15 18-Jan-15
22+736 22+748 15-Jan-15 18-Jan-15 2-Feb-15 5-Feb-15 22+755 22+767 4-Jan-15 7-Jan-15 13-Jan-15 18-Jan-15
22+748 22+760 15-Jan-15 19-Jan-15 2-Feb-15 5-Feb-15 22+767 22+779 4-Jan-15 7-Jan-15 13-Jan-15 18-Jan-15
22+760 22+772 15-Jan-15 19-Jan-15 2-Feb-15 5-Feb-15 22+779 22+791 4-Jan-15 7-Jan-15 13-Jan-15 18-Jan-15
22+772 22+784 15-Jan-15 22-Jan-15 2-Feb-15 5-Feb-15 22+791 22+803 28-Dec-14 6-Jan-15 13-Jan-15 18-Jan-15
22+784 22+796 15-Jan-15 22-Jan-15 2-Feb-15 5-Feb-15 22+803 22+815 28-Dec-14 6-Jan-15 13-Jan-15 18-Jan-15
22+796 22+808 15-Jan-15 22-Jan-15 3-Feb-15 5-Feb-15 22+815 22+827 28-Dec-14 6-Jan-15 10-Jan-15 18-Jan-15
22+808 22+820 15-Jan-15 21-Jan-15 3-Feb-15 5-Feb-15 22+827 22+839 28-Dec-14 5-Jan-15 10-Jan-15 18-Jan-15
22+820 22+832 15-Jan-15 21-Jan-15 3-Feb-15 5-Feb-15 22+839 22+851 30-Nov-14 5-Jan-15 10-Jan-15 18-Jan-15
22+832 22+844 30-Nov-14 4-Dec-14 3-Feb-15 6-Feb-15 22+851 22+863 30-Nov-14 5-Jan-15 7-Jan-15 18-Jan-15
22+844 22+856 30-Nov-14 4-Dec-14 3-Feb-15 6-Feb-15 22+863 22+875 16-Dec-14 24-Dec-14 7-Jan-15 18-Jan-15
22+856 22+868 10-Dec-14 15-Dec-14 3-Feb-15 6-Feb-15 22+875 22+887 16-Dec-14 24-Dec-14 7-Jan-15 18-Jan-15
22+868 22+880 10-Dec-14 15-Dec-14 28-Jan-15 6-Feb-15 22+887 22+899 16-Dec-14 24-Dec-14 11-Jan-15 18-Jan-15
22+880 22+892 22-Dec-14 28-Dec-14 28-Jan-15 6-Feb-15 22+899 22+911 16-Dec-14 24-Dec-14 11-Jan-15 18-Jan-15
22+892 22+904 22-Dec-14 28-Dec-14 28-Jan-15 6-Feb-15 22+911 22+923 16-Dec-14 24-Dec-14 11-Jan-15 18-Jan-15
22+904 22+916 22-Dec-14 28-Dec-14 4-Feb-15 7-Feb-15 22+923 22+935 16-Dec-14 24-Dec-14 12-Jan-15 18-Jan-15
22+916 22+928 22-Dec-14 18-Jan-15 4-Feb-15 7-Feb-15 22+935 22+947 16-Dec-14 24-Dec-14 12-Jan-15 18-Jan-15
22+928 22+940 22-Dec-14 19-Jan-15 4-Feb-15 7-Feb-15 22+947 22+959 16-Dec-14 24-Dec-14 12-Jan-15 18-Jan-15
22+940 22+952 31-Dec-14 18-Jan-15 4-Feb-15 7-Feb-15 22+959 22+971 16-Dec-14 24-Dec-14 6-Jan-15 18-Jan-15
22+952 22+964 31-Dec-14 20-Jan-15 4-Feb-15 7-Feb-15 22+971 22+983 16-Dec-14 29-Dec-14 6-Jan-15 18-Jan-15
22+964 22+976 31-Dec-14 20-Jan-15 4-Feb-15 7-Feb-15 22+983 22+995 23-Dec-14 29-Dec-14 6-Jan-15 18-Jan-15
22+976 22+988 31-Dec-14 20-Jan-15 5-Feb-15 7-Feb-15 22+995 23+007 23-Dec-14 30-Dec-14 12-Jan-15 18-Jan-15
22+988 23+000 18-Jan-15 20-Jan-15 5-Feb-15 7-Feb-15 23+007 23+019 23-Dec-14 30-Dec-14 12-Jan-15 18-Jan-15
23+000 23+012 18-Jan-15 20-Jan-15 5-Feb-15 7-Feb-15 23+019 23+031 23-Dec-14 30-Dec-14 12-Jan-15 18-Jan-15
23+012 23+024 18-Jan-15 21-Jan-15 25-Jan-15 8-Feb-15 23+031 23+043 23-Dec-14 30-Dec-14 14-Jan-15 18-Jan-15
23+024 23+036 18-Jan-15 21-Jan-15 25-Jan-15 8-Feb-15 23+043 23+055 23-Dec-14 30-Dec-14 14-Jan-15 18-Jan-15
23+036 23+048 18-Jan-15 21-Jan-15 25-Jan-15 8-Feb-15 23+055 23+067 5-Jan-15 11-Jan-15 14-Jan-15 20-Jan-15
23+048 23+060 18-Jan-15 21-Jan-15 8-Feb-15 16-Feb-15 23+067 23+079 5-Jan-15 11-Jan-15 19-Jan-15 20-Jan-15
23+060 23+072 26-Jan-15 4-Feb-15 8-Feb-15 16-Feb-15 23+079 23+091 5-Jan-15 10-Jan-15 19-Jan-15 20-Jan-15
23+072 23+084 26-Jan-15 4-Feb-15 8-Feb-15 16-Feb-15 23+091 23+103 5-Jan-15 13-Jan-15 19-Jan-15 20-Jan-15
23+084 23+096 1-Feb-15 5-Feb-15 14-Feb-15 17-Feb-15 23+103 23+115 5-Jan-15 14-Jan-15 19-Jan-15 20-Jan-15
23+096 23+108 1-Feb-15 7-Feb-15 14-Feb-15 17-Feb-15 23+115 23+127 5-Jan-15 14-Jan-15 19-Jan-15 20-Jan-15
23+108 23+120 1-Feb-15 7-Feb-15 14-Feb-15 17-Feb-15 23+127 23+139 8-Jan-15 11-Jan-15 19-Jan-15 20-Jan-15
23+120 23+132 1-Feb-15 8-Feb-15 18-Feb-15 22-Feb-15 23+139 23+151 8-Jan-15 12-Jan-15 19-Jan-15 20-Jan-15
23+132 23+144 2-Feb-15 8-Feb-15 18-Feb-15 22-Feb-15 23+151 23+163 8-Jan-15 11-Jan-15 19-Jan-15 20-Jan-15
23+144 23+156 2-Feb-15 8-Feb-15 18-Feb-15 22-Feb-15 23+163 23+175 8-Jan-15 12-Jan-15 19-Jan-15 20-Jan-15
23+156 23+168 2-Feb-15 8-Feb-15 18-Feb-15 22-Feb-15 23+175 23+187 27-Jan-15 4-Feb-15 9-Feb-15 11-Feb-15
23+168 23+180 2-Feb-15 9-Feb-15 18-Feb-15 22-Feb-15 23+187 23+199 27-Jan-15 4-Feb-15 9-Feb-15 11-Feb-15
23+180 23+192 2-Feb-15 9-Feb-15 18-Feb-15 22-Feb-15 23+199 23+211 27-Jan-15 5-Feb-15 9-Feb-15 11-Feb-15
23+192 23+204 2-Feb-15 11-Feb-15 18-Feb-15 22-Feb-15 23+211 23+223
23+204 23+216 23+223 23+235
23+216 23+228 23+235 23+247
23+228 23+240 23+247 23+259
23+240 23+252 23+259 23+271
23+252 23+264
23+264 23+276
23+276 23+288
FRICTION SLAB & CONCRETE BARRIER (@ AB1)
STATIONBLINDING FRICTION SLAB
CONCRETE
BARRIERBITUMEN PAINT
STATIONBLINDING FRICTION SLAB
CONCRETE
BARRIERBITUMEN PAINT
PREVIOUS (MONTH BEFORE)PREVIOUS
MONTHTHIS MONTH
AB1 - LHS AB1 - RHS
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report February 2015
RENARDET S.A. & PARTNERS Page 16
FROM TO FROM TO
23+508 23+520 23+508 23+520
23+520 23+532 23+520 23+532
23+532 23+544 23+532 23+544
23+544 23+556 23+544 23+556
23+556 23+568 23+556 23+568
23+568 23+580 23+568 23+580
23+580 23+592 23+580 23+592 2-Mar-15
23+592 23+604 23+592 23+604 2-Mar-15
23+604 23+616 23+604 23+616 19-Feb-15 26-Feb-15
23+616 23+628 23+616 23+628 19-Feb-15 26-Feb-15
23+628 23+640 23+628 23+640 19-Feb-15 26-Feb-15
23+640 23+652 23+640 23+652 19-Feb-15 26-Feb-15
23+652 23+664 23+652 23+664 19-Feb-15 26-Feb-15
23+664 23+676 23+664 23+676 17-Feb-15 26-Feb-15
23+676 23+688 23+676 23+688 17-Feb-15 26-Feb-15
23+688 23+700 23+688 23+700 17-Feb-15 23-Feb-15
23+700 23+712 23+700 23+712 17-Feb-15 23-Feb-15 26-Feb-15
23+712 23+724 23+712 23+724 17-Feb-15 23-Feb-15 26-Feb-15
23+724 23+736 23+724 23+736 17-Feb-15 21-Feb-15 26-Feb-15
23+736 23+748 23+736 23+748 17-Feb-15 21-Feb-15 25-Feb-15
23+748 23+760 23+748 23+760 17-Feb-15 21-Feb-15 25-Feb-15
23+760 23+772 23+760 23+772 17-Feb-15 19-Feb-15 25-Feb-15
23+772 23+784 23+772 23+784 17-Feb-15 19-Feb-15 24-Feb-15 25-Feb-15
23+784 23+796 23+784 23+796 25-Jan-15 11-Feb-15 24-Feb-15 25-Feb-15
23+796 23+808 23+796 23+808 25-Jan-15 11-Feb-15 24-Feb-15 25-Feb-15
23+808 23+820 19-Feb-15 23+808 23+820 25-Jan-15 10-Feb-15 22-Feb-15 25-Feb-15
23+820 23+832 19-Feb-15 23+820 23+832 14-Jan-15 10-Feb-15 22-Feb-15 25-Feb-15
23+832 23+844 11-Feb-15 17-Feb-15 23+832 23+844 14-Jan-15 10-Feb-15 22-Feb-15 25-Feb-15
23+844 23+856 11-Feb-15 17-Feb-15 23+844 23+856 14-Jan-15 27-Jan-15 21-Feb-15 23-Feb-15
23+856 23+868 11-Feb-15 17-Feb-15 23+856 23+868 15-Jan-15 27-Jan-15 21-Feb-15 23-Feb-15
23+868 23+880 11-Feb-15 16-Feb-15 23+868 23+880 15-Jan-15 26-Jan-15 21-Feb-15 23-Feb-15
23+880 23+892 11-Feb-15 16-Feb-15 23+880 23+892 15-Jan-15 25-Jan-15 15-Feb-15 23-Feb-15
23+892 23+904 24-Jan-15 16-Feb-15 23+892 23+904 15-Jan-15 25-Jan-15 15-Feb-15 23-Feb-15
23+904 23+916 24-Jan-15 16-Feb-15 23+904 23+916 15-Jan-15 24-Jan-15 15-Feb-15 23-Feb-15
23+916 23+928 24-Jan-15 15-Feb-15 23+916 23+928 15-Jan-15 20-Jan-15 11-Feb-15 12-Feb-15
23+928 23+940 24-Jan-15 15-Feb-15 23+928 23+940 15-Jan-15 20-Jan-15 11-Feb-15 12-Feb-15
23+940 23+952 24-Jan-15 15-Feb-15 23+940 23+952 15-Jan-15 20-Jan-15 11-Feb-15 12-Feb-15
BLINDING FRICTION SLABCONCRETE
BARRIER
BITUMEN
PAINT
CONCRETE
BARRIER
STATIONBLINDING FRICTION SLAB
BITUMEN
PAINT
STATION
AB2 - LHS
FRICTION SLAB & CONCRETE BARRIER (@ AB2)
AB2 - RHS
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report February 2015
RENARDET S.A. & PARTNERS Page 17
10.
Rebars Concrete Rebars Concrete Rebars Concrete
1 21+260 3 cells - 2.0 x 1.5 25.546 0 - - - - - - - -LHS Block 1 3 cells - 2.0 x 1.5 19.526 0 19-Oct-14 26-Oct-14 27-Oct-14 9-Nov-14 9-Nov-14 9-Nov-14 9-Nov-14 26-Nov-14RHS Block 2 3 cells - 2.0 x 1.5 14.473 0 19-Oct-14 4-Nov-14 4-Nov-14 15-Nov-14 15-Nov-14 15-Nov-14 15-Nov-14 26-Nov-14RHS Block 3 3 cells - 2.0 x 1.5 6.000 0 - - - - - - - -2 21+485 1 cell - 2.0 x 1.5 39.750 0 - - - - - - - -
Block 1a 1 cell - 2.0 x 1.5 3.000 0 - - - - - - - -Block 1b 1 cell - 2.0 x 1.5 17.290 0 1-Jul-14 31-Aug-14 31-Aug-14 31-Aug-14 31-Aug-14 31-Aug-14 31-Aug-14 1-Sep-14Block 2a 1 cell - 2.0 x 1.5 7.710 0 1-Jul-14 31-Aug-14 31-Aug-14 31-Aug-14 31-Aug-14 31-Aug-14 31-Aug-14 1-Sep-14Block 2b 1 cell - 2.0 x 1.5 10.000 0 19-Oct-14 25-Oct-14 25-Oct-14 25-Oct-14 25-Oct-14 25-Oct-14 25-Oct-14 25-Oct-14Block 2C 1 cell - 2.0 x 1.5 11.730 0 - - - - - - - -
3 21+838 2 x 4 cells (8) - 2.0 x 1.5 52.210 0 - - - - - - - -Block 1a 1 x 4 cells - 2.0 x 1.5 5.000 0 21-Jul-14 4-Sep-14 5-Sep-14 13-Oct-14 13-Oct-14 13-Oct-14 13-Oct-14 26-Nov-14Block 1b 1 x 4 cells - 2.0 x 1.5 17.600 0 3-Jul-14 4-Sep-14 5-Sep-14 13-Oct-14 13-Oct-14 13-Oct-14 13-Oct-14 26-Nov-14Block 2 1 x 4 cells - 2.0 x 1.5 22.600 0 3-Jul-14 20-Aug-14 20-Aug-14 30-Oct-14 30-Oct-14 30-Oct-14 30-Oct-14 26-Nov-14Block 3 1 x 4 cells - 2.0 x 1.5 5.000 0 3-Jul-14 8-Dec-14 8-Dec-14 16-Dec-14 16-Dec-14 16-Dec-14 16-Dec-14 29-Dec-14Block 3a 1 x 4 cells - 2.0 x 1.5 6.970 0 - - - - - - - -Block 4a 1 x 4 cells - 2.0 x 1.5 5.000 0 21-Jul-14 10-Sep-14 12-Sep-14 18-Oct-14 19-Oct-14 18-Oct-14 19-Oct-14 26-Nov-14Block 4b 1 x 4 cells - 2.0 x 1.5 17.600 0 3-Jul-14 10-Sep-14 12-Sep-14 18-Oct-14 19-Oct-14 18-Oct-14 19-Oct-14 26-Nov-14Block 5 1 x 4 cells - 2.0 x 1.5 22.600 0 3-Jul-14 23-Sep-14 24-Sep-14 24-Oct-14 25-Oct-14 24-Oct-14 25-Oct-14 26-Nov-14Block 6 1 x 4 cells - 2.0 x 1.5 5.000 0 3-Jul-14 21-Dec-14 21-Dec-14 27-Dec-14 27-Dec-14 27-Dec-14 27-Dec-14 29-Dec-14Block 6a 1 x 4 cells - 2.0 x 1.5 6.970 0 - - - - - - - -
4 21+972.4 11 x 4 cells (44) - 3.0 x 2.0 57.629 0 - - - - - - - -Block 1 1 x 4 cells - 3.0 x 2.0 28.038 0 24-May-14 5-Jun-14 5-Jun-14 24-Jun-14 24-Jun-14 15-Jul-14 16-Jul-14 16-Aug-14Block 2 1 x 4 cells - 3.0 x 2.0 28.031 0 24-May-14 9-Jul-14 10-Jul-14 3-Aug-14 4-Aug-14 13-Aug-14 14-Aug-14 8-Sep-14Block 3 1 x 4 cells - 3.0 x 2.0 28.026 0 17-May-14 25-May-14 25-May-14 3-Jun-14 3-Jun-14 23-Jun-14 23-Jun-14 8-Sep-14Block 4 1 x 4 cells - 3.0 x 2.0 28.022 0 18-May-14 12-Jul-14 13-Jul-14 5-Aug-14 6-Aug-14 18-Aug-14 19-Aug-14 1-Oct-14Block 5 1 x 4 cells - 3.0 x 2.0 28.019 0 18-May-14 29-May-14 29-May-14 8-Jun-14 8-Jun-14 2-Jul-14 2-Jul-14 1-Oct-14Block 6 1 x 4 cells - 3.0 x 2.0 28.018 0 18-May-14 31-Jul-14 31-Jul-14 12-Aug-14 13-Aug-14 27-Aug-14 28-Aug-14 1-Oct-14Block 7 1 x 4 cells - 3.0 x 2.0 28.019 0 18-May-14 10-Jun-14 10-Jun-14 1-Jul-14 1-Jul-14 23-Jul-14 24-Jul-14 5-Oct-14Block 8 1 x 4 cells - 3.0 x 2.0 28.022 0 26-May-14 9-Aug-14 10-Aug-14 25-Aug-14 26-Aug-14 9-Sep-14 10-Sep-14 26-Nov-14Block 9 1 x 4 cells - 3.0 x 2.0 28.026 0 26-May-14 15-Jun-14 15-Jun-14 7-Jul-14 8-Jul-14 4-Aug-14 5-Aug-14 26-Nov-14Block 10 1 x 4 cells - 3.0 x 2.0 28.031 0 28-May-14 17-Aug-14 18-Aug-14 14-Sep-14 14-Sep-14 24-Sep-14 25-Sep-14 26-Nov-14Block 11 1 x 4 cells - 3.0 x 2.0 28.038 0 28-May-14 19-Jun-14 19-Jun-14 20-Jul-14 20-Jul-14 2-Sep-14 3-Sep-14 25-Sep-14
BASE SLAB WALLF/P &
BLINDING
LHS
RHS
TYPE & DIMENSIONBituminous
Paint (2 Coats)LENGTH (m)SKEW ( )
RHS
LHS
LHS
STATIONNO.
LHS
TOP SLAB
RHS
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report February 2015
RENARDET S.A. & PARTNERS Page 18
Rebars Concrete Rebars Concrete Rebars Concrete
Block 12 1 x 4 cells - 3.0 x 2.0 21.015 0 10-Aug-14 25-Aug-14 26-Aug-14 2-Sep-14 3-Sep-14 1-Oct-14 1-Oct-14 26-Nov-14Block 13 1 x 4 cells - 3.0 x 2.0 21.010 0 27-Jul-14 22-Sep-14 22-Sep-14 29-Sep-14 29-Sep-14 18-Oct-14 19-Oct-14 26-Nov-14Block 14 1 x 4 cells - 3.0 x 2.0 21.006 0 27-Jul-14 12-Oct-14 12-Oct-14 15-Oct-14 15-Oct-14 26-Oct-14 27-Oct-14 26-Nov-14Block 15 1 x 4 cells - 3.0 x 2.0 21.003 0 25-Jul-14 23-Aug-14 23-Aug-14 8-Sep-14 8-Sep-14 18-Sep-14 19-Sep-14 26-Nov-14Block 16 1 x 4 cells - 3.0 x 2.0 21.001 0 16-Jun-14 27-Jul-14 27-Jul-14 14-Aug-14 14-Aug-14 3-Sep-14 4-Sep-14 26-Nov-14Block 17 1 x 4 cells - 3.0 x 2.0 21.000 0 16-Jun-14 14-Sep-14 15-Sep-14 23-Sep-14 24-Sep-14 14-Oct-14 15-Oct-14 26-Nov-14Block 18 1 x 4 cells - 3.0 x 2.0 21.001 0 12-Jun-14 24-Oct-14 24-Oct-14 30-Oct-14 31-Oct-14 7-Nov-14 7-Nov-14 26-Nov-14Block 19 1 x 4 cells - 3.0 x 2.0 21.003 0 12-Jun-14 16-Oct-14 17-Oct-14 21-Oct-14 21-Oct-14 30-Oct-14 30-Oct-14 26-Nov-14Block 20 1 x 4 cells - 3.0 x 2.0 21.006 0 8-Jun-14 29-Sep-14 30-Sep-14 1-Oct-14 1-Oct-14 21-Oct-14 21-Oct-14 26-Nov-14Block 21 1 x 4 cells - 3.0 x 2.0 21.010 0 8-Jun-14 1-Sep-14 2-Sep-14 21-Sep-14 21-Sep-14 30-Sep-14 30-Sep-14 26-Nov-14Block 22 1 x 4 cells - 3.0 x 2.0 21.015 0 8-Jun-14 25-Jun-14 25-Jun-14 30-Jul-14 30-Jul-14 16-Sep-14 17-Sep-14 25-Sep-14Block 23 1 x 4 cells - 3.0 x 2.0 6.635 0 - - - - - - - -Block 24 1 x 4 cells - 3.0 x 2.0 6.782 0 - - - - - - - -Block 25 1 x 4 cells - 3.0 x 2.0 6.819 0 - - - - - - - -Block 26 1 x 4 cells - 3.0 x 2.0 7.217 0 - - - - - - - -Block 27 1 x 4 cells - 3.0 x 2.0 7.975 0 - - - - - - - -Block 28 1 x 4 cells - 3.0 x 2.0 8.571 0 - - - - - - - -Block 29 1 x 4 cells - 3.0 x 2.0 9.267 0 - - - - - - - -Block 30 1 x 4 cells - 3.0 x 2.0 9.949 0 - - - - - - - -Block 31 1 x 4 cells - 3.0 x 2.0 10.260 0 - - - - - - - -Block 32 1 x 4 cells - 3.0 x 2.0 10.262 0 - - - - - - - -Block 33 1 x 4 cells - 3.0 x 2.0 10.265 0 - - - - - - - -
5 22+655 2 x 4 cells (8) - 2.0 x 2.0 95.482 45 R - - - - - - - -(9 cells) 1 cell - 2.0 x 2.0 - - - - - - - -Block 1 1 x 4 cells - 2.0 x 2.0 9.675 45 R 24-Nov-14 29-Nov-14 29-Nov-14 4-Dec-14 4-Dec-14 10-Dec-14 10-Dec-14 8-Jan-15Block 2 1 x 4 cells - 2.0 x 2.0 32.711 45 R 30-Jun-14 6-Aug-14 7-Aug-14 1-Sep-14 2-Sep-14 1-Sep-14 2-Sep-14 13-Oct-14Block 3 1 x 4 cells - 2.0 x 2.0 32.711 45 R 24-Jun-14 21-Jul-14 21-Jul-14 17-Aug-14 18-Aug-14 17-Aug-14 18-Aug-14 13-Oct-14Block 4 1 x 4 cells - 2.0 x 2.0 11.850 45 R 11-Sep-14 12-Oct-14 13-Oct-14 22-Oct-14 22-Oct-14 22-Oct-14 22-Oct-14 15-Nov-14Block 4a 1 x 4 cells - 2.0 x 2.0 13.130 45 R - - - - - - - -Block 5 1 x 4 cells - 2.0 x 2.0 19.035 45 R 24-Nov-14 4-Dec-14 4-Dec-14 8-Dec-14 8-Dec-14 18-Dec-14 18-Dec-14 8-Jan-15Block 6 1 x 4 cells - 2.0 x 2.0 32.711 45 R 29-Jun-14 27-Jul-14 28-Jul-14 13-Sep-14 14-Sep-14 13-Sep-14 14-Sep-14 13-Oct-14Block 7 1 x 4 cells - 2.0 x 2.0 32.711 45 R 24-Jun-14 28-Aug-14 28-Aug-14 24-Sep-14 26-Sep-14 24-Sep-14 26-Sep-14 13-Oct-14Block 8 1 x 4 cells - 2.0 x 2.0 10.95 45 R - - - - - - - -Block 9 1 cell - 2.0 x 2.0 25.03 45 R 24-Nov-14 13-Dec-14 13-Dec-14 18-Dec-14 18-Dec-14 24-Dec-14 24-Dec-14 8-Jan-15Block 10 1 cell - 2.0 x 2.0 32.711 45 R 28-Jun-14 20-Aug-14 23-Aug-14 2-Oct-14 3-Oct-14 2-Oct-14 3-Oct-14 13-Oct-14Block 11 1 cell - 2.0 x 2.0 32.711 45 R 29-Jun-14 3-Aug-14 4-Aug-14 2-Oct-14 3-Oct-14 2-Oct-14 3-Oct-14 13-Oct-14Block 12 1 cell - 2.0 x 2.0 4.960 45 R - - - - - - - -
RHS
RHS
LHS
RHS
RHS
LHS
RHS
NO.
LHS
WALL TOP SLAB Bituminous Paint (2 Coats)
STATION TYPE & DIMENSION LENGTH (m)SKEW ( )F/P &
BLINDING
BASE SLAB
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report February 2015
RENARDET S.A. & PARTNERS Page 19
Rebars Concrete Rebars Concrete Rebars Concrete
6 23+492 1 x 4 cells (4) - 3.0 x 2.0 79.065 15 R - - - - - - - -(5 cells) 1 cell - 3.0 x 2.0 - - - - - - - -Block 1 1 x 4 cells - 3.0 x 2.0 6.457 15 R - - - - - - - -Block 2 1 x 4 cells - 3.0 x 2.0 31.546 15 R 24-Jun-14 9-Jul-14 9-Jul-14 30-Jul-14 30-Jul-14 16-Aug-14 17-Aug-14 6-Sep-14Block 3 1 x 4 cells - 3.0 x 2.0 31.546 15 R 24-Jun-14 14-Jul-14 15-Jul-14 3-Aug-14 3-Aug-14 21-Aug-14 21-Aug-14 6-Sep-14Block 4 1 x 4 cells - 3.0 x 2.0 7.982 15 R 9/172014 23-Sep-14 24-Sep-14 28-Sep-14 28-Sep-14 1-Oct-14 2-Oct-14 18-Oct-14Block 5 1 cell - 3.0 x 2.0 7.039 15 R - - - - - - - -Block 6 1 cell - 3.0 x 2.0 31.546 15 R 24-Jun-14 5-Aug-14 5-Aug-14 9 & 20/8/2014 9 & 23/8/2014 28-Aug-14 28-Aug-14 4-7/9/2014Block 7 1 cell - 3.0 x 2.0 31.546 15 R 24-Jun-14 6-Aug-14 6-Aug-14 11 & 25/8/2014 11 & 26/8/2014 31-Aug-14 1-Sep-14 4-7/9/2014Block 8 1 cell - 3.0 x 2.0 5.525 15 R 17-Sep-14 28-Sep-14 28-Sep-14 2-Oct-14 2-Oct-14 11-Oct-14 11-Oct-14 18-Oct-14
11-Oct-14 11-Oct-14 - - -7 23+756.5 1 cell - 2.0 x 1.5 67.550 0 - - - - - - - -
Block 1 1 cell - 2.0 x 1.5 12.090 0 - - - - - - - -Block 2 1 cell - 2.0 x 1.5 20.180 0 12-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 24-Jul-14Block 3a 1 cell - 2.0 x 1.5 14.430 0 12-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 24-Jul-14Block 3b 1 cell - 2.0 x 1.5 8.700 0 11-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 28-Aug-14Block 4 1 cell - 2.0 x 1.5 12.090 0 - - - - - - - -
8 23+997 1 cell - 2.0 x 1.5 70.268 0 - - - - - - - -Block 1 1 cell - 2.0 x 1.5 16.128 0 - - - - - - - -Block 2a 1 cell - 2.0 x 1.5 4.933 0 - - - - - - - -Block 2b 1 cell - 2.0 x 1.5 13.860 0 8-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 24-Jul-14Block 3a 1 cell - 2.0 x 1.5 16.300 0 8-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 24-Jul-14Block 3b 1 cell - 2.0 x 1.5 4.942 0 10-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 31-Aug-14Block 4a 1 cell - 2.0 x 1.5 7.848 0 10-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 31-Aug-14Block 4b 1 cell - 2.0 x 1.5 6.197 0
9 24+235 1 cell - 2.0 x 1.5 59.106 0 - - - - - - - -Block 1a 1 cell - 2.0 x 1.5 15.566 0 - - - - - - - -Block 1b 1 cell - 2.0 x 1.5 15.000 0 12-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 24-Jul-14Block 2a 1 cell - 2.0 x 1.5 8.900 0 12-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 24-Jul-14Block 2b 1 cell - 2.0 x 1.5 15.600 0 10-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 31-Aug-14Block 2c 1 cell - 2.0 x 1.5 4.020 0 - - - - - - - -
10 24+570 1 cell - 2.0 x 1.5 51.953 0 - - - - - - - -LHS Block 1 1 cell - 2.0 x 1.5 25.846 0 14-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 31-Aug-14
Block 2a 1 cell - 2.0 x 1.5 13.500 0 14-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 31-Aug-14Block 2b 1 cell - 2.0 x 1.5 12.587 0 24-Nov-14 1-Dec-14 1-Dec-14 1-Dec-14 1-Dec-14 1-Dec-14 1-Dec-14 6-Dec-14
11 24+900 1 cell - 2.0 x 1.0 40.850 0 - - - - - - - -LHS Block 1 1 cell - 2.0 x 1.0 20.300 0 - - - - - - - -RHS Block 2 1 cell - 2.0 x 1.0 20.550 0 3-Feb-15 2-Mar-15 2-Mar-15 2-Mar-15 2-Mar-15 2-Mar-15 2-Mar-15 3-Mar-15
RHS
RHS
LHS
RHS
LHS
RHS
RHS
LHS
LHS
LHS
RHS
BASE SLABNO. STATION TYPE & DIMENSION LENGTH (m)SKEW ( )
F/P &
BLINDING
WALL TOP SLAB Bituminous Paint (2 Coats)
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report February 2015
RENARDET S.A. & PARTNERS Page 20
Inlet and Outlet Structures for Culverts:
Cut-off Wall/Apron
Slab: Rebars &
Concrete
Wingwall: Rebars &
Concrete Bit. PaintCut-off Wall/Apron
Slab: Rebars &
Concrete
Wingwall: Rebars &
Concrete Bit. Paint
1 21+260 3 cells - 2.0 x 1.5 - - - - - - - -2 21+485 1 cell - 2.0 x 1.5 - - - - - - - -3 21+838 2 x 4 cells - 2.0 x 1.5 - - - - - - - -4 21+972.4 11 x 4 cells - 3.0 x 2.0 - - - - - - - -
22+655 2 x 4 cells - 2.0 x 2.0 - - - - - - - -
1 cell - 2.0 x 2.0 - - - - - - - -
23+492 1 x 4 cells - 3.0 x 2.0 - - - - 1-Feb-15 10-Feb-15 18-Feb-15 2-Mar-15
1 cell - 3.0 x 2.0 - - - - - - - -
7 23+756.5 1 cell - 2.0 x 1.5 - - - - - - - -
8 23+997 1 cell - 2.0 x 1.5 - - - - - - - -
9 24+235 1 cell - 2.0 x 1.5 - - - - - - - -
10 24+570 1 cell - 2.0 x 1.5 - - - - - - - -
11 24+900 1 cell - 2.0 x 1.0 - - - - - - - -
PREVIOUS PREVIOUS MONTH THIS MONTH
F/P &
BLINDING
OUTLET
NO. STATION TYPEF/P &
BLINDING
5
6
INLET
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report February 2015
RENARDET S.A. & PARTNERS Page 21
Rebars Concrete Rebars Concrete Rebars Concrete
1 21+300 2 cells - 4.0 x 3.0 37.700 0 - - - - - - - - - -LHS Block 1 2 cells - 4.0 x 3.0 15.780 0 19-Oct-14 26-Oct-14 27-Oct-14 1-Nov-14 2-Nov-14 12-Nov-14 2-Nov-14 26-Nov-14 24-Feb-15RHS Block 2 2 cells - 4.0 x 3.0 21.900 0 28-Dec-14 4-Jan-15 4-Jan-15 11-Jan-15 11-Jan-15 20-Jan-15 20-Jan-15 19-Jan-152 24+600 2 cells - 4.0 x 3.0 44.051 0 - - - - - - - -
LHS Block 1 2 cells - 4.0 x 3.0 21.620 0 22-Oct-14 3-Nov-14 3-Nov-14 11-Nov-14 12-Nov-14 19-Nov-14 20-Nov-14 8-Jan-15 26-Jan-15RHS Block 2 2 cells - 4.0 x 3.0 22.411 0 27-Jan-15 29-Jan-15 29-Jan-15 5-Feb-15 5-Feb-15 11-Feb-15 11-Feb-15
Rebars Concrete Rebars Concrete Rebars Concrete
1 23+284.40, SOL-1 1 cells - 4.0 x 4.0 103.772 0 - - - - - - - - -LHS Block 1 1 cells - 4.0 x 4.0 32.000 0 - - - - - - - - -LHS Block 2 1 cells - 4.0 x 4.0 19.886 0 18-Feb-15 21-Feb-15 21-Feb-15 1-Mar-15 1-Mar-15 - - - -LHS Block 3 1 cells - 4.0 x 4.0 25.943 0 21-Feb-15 25-Feb-15 25-Feb-15 5-Mar-15 5-Mar-15 - - - -RHS Block 4a 1 cells - 4.0 x 4.0 15.000 0 - - - - - - - - -RHS Block 4b 1 cells - 4.0 x 4.0 10.943 0 - - - - - - - - -2 24+360, SOL-1 1 cells - 4.0 x 4.0 59.614 0 - - - - - - - - -
LHS Block 1 1 cells - 4.0 x 4.0 9.000 0 - - - - - - - - -LHS Block 2 1 cells - 4.0 x 4.0 20.777 0 15-Sep-14 1-Oct-14 1-Oct-14 19-Oct-14 19-Oct-14 30-Oct-14 31-Oct-14 27-Dec-14 5-Jan-15RHS Block 3 1 cells - 4.0 x 4.0 22.777 0 9-Dec-14 15-Dec-14 15-Dec-14 21-Dec-14 21-Dec-14 30-Dec-14 30-Dec-14 - 5-Jan-15RHS Block 4 1 cells - 4.0 x 4.0 7.000 0 - - - - - - - - -3 0+050, SOL-3 1 cells - 4.0 x 4.0 83.223 0 - - - - - - - - -
LHS Block 1 1 cells - 4.0 x 4.0 17.721 0 - - - - - - - - -LHS Block 2 1 cells - 4.0 x 4.0 17.721 0 - - - - - - - - -LHS Block 3 1 cells - 4.0 x 4.0 17.721 0 - - - - - - - - -RHS Block 4 1 cells - 4.0 x 4.0 30.000 0 25-Nov-14 2-Dec-14 2-Dec-14 14-Dec-14 14-Dec-14 25-Dec-14 25-Dec-14 8-Jan-15 12-Feb-15
PREVIOUSPREVIOUS
MONTHTHIS MONTH
Bituminous
Paint (2
Coats)
WALLNO.
LENGTH
(m)
SKEW (
)
F/P &
BLINDINGTYPE & DIMENSION
PEDESTRIAN UNDERPASS PROGRESS SCHEDULE (BARREL)
TYPE & DIMENSIONLENGTH
(m)
SKEW (
)
TOP SLABVentilationSTATION
STATIONBASE SLAB WALL
F/P &
BLINDING
BASE SLAB
Headwall Crash BarrierNO.
ADDITIONAL BOX CULVERTS PROGRESS SCHEDULE (BARREL)
TOP SLAB Bituminous Paint (2 Coats)
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report February 2015
RENARDET S.A. & PARTNERS Page 22
11.
Additional Box Culverts:
UNIT 1 UNIT 2 UNIT 1 UNIT 2 UNIT 1 UNIT 2 UNIT 1 UNIT 2
Length (Ln.m.) 15.000 15.000 15.000 15.000 15.000 15.000 15.000 15.000
CRASH BARRIER - - - - - - - -
WATER PROOFING 11-Jan-15 11-Jan-15 - - 7-Jan-15 7-Jan-15 - -WALL 6-Jan-15 5-Jan-15 - - 24-Dec-14 17-Dec-14 7-Mar-15 1-Mar-15BASE 23-Dec-14 21-Dec-14 3-Mar-15 5-Mar-15 9-Dec-14 9-Dec-14 1-Mar-15 22-Feb-15F/P & BLINDING 13-Dec-14 13-Dec-14 25-Feb-15 25-Feb-15 30-Nov-14 30-Nov-14 25-Feb-15 18-Feb-15
LHS RHSSta. 21+300 Sta. 24+600
LHS RHSACTIVITY
Retaining Walls in Buraimi Road:
ACTIVITY UNIT 1 UNIT 2 UNIT 3 UNIT 4 UNIT 5 UNIT 6 UNIT 7 UNIT 8
Length (Ln.m.) 11.650 11.650 11.650 11.650 11.650 11.650 11.650 11.650
CRASH BARRIER - - - - - - - -
WATER PROOFING 29-Jan-15 29-Jan-15 4-Feb-15 4-Feb-15 28-Jan-15 28-Jan-15 11-Feb-15 11-Feb-15WALL 19-Jan-15 11-Jan-15 14-Jan-15 12-Jan-15 15-Jan-15 11-Jan-15 1-Feb-15 4-Feb-15BASE 15-Jan-15 6-Jan-15 10-Jan-15 8-Jan-15 11-Jan-15 5-Jan-15 27-Jan-15 1-Feb-15F/P & BLINDING 13-Jan-15 31-Dec-14 31-Dec-14 31-Dec-14 28-Dec-14 28-Dec-14 25-Jan-15 25-Jan-15
ACTIVITY UNIT 9 UNIT 10 UNIT 11 UNIT 12 UNIT 13 UNIT 14 UNIT 15 UNIT 16
Length (Ln.m.) 11.650 10.650 12.650 11.650 11.650 11.650 11.650 9.835
CRASH BARRIER - - - - - - - -
WATER PROOFING 11-Feb-15 11-Feb-15 11-Feb-15 11-Feb-15 6-Feb-15 6-Feb-15 5-Feb-15 5-Feb-15WALL 28-Jan-15 1-Feb-15 4-Feb-15 24-Jan-15 26-Jan-15 13-Jan-15 19-Jan-15 12-Jan-15BASE 25-Jan-15 26-Jan-15 1-Feb-15 19-Jan-15 22-Jan-15 10-Jan-15 13-Jan-15 6-Jan-15F/P & BLINDING 22-Jan-15 22-Jan-15 27-Jan-15 15-Jan-15 15-Jan-15 6-Jan-15 6-Jan-15 28-Dec-14
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report February 2015
RENARDET S.A. & PARTNERS Page 23
12.
DIA TYPE LAYING CONCRETE BACKFILL
LEFT
Middle
RIGHT
LEFT
Middle
RIGHT
LEFT
Middle
RIGHT
LEFT
Middle
RIGHT
LEFT24-Sep-14 24-Sep-14 18-Oct-14 UTL-LAY- 104 UTL-CON-131A
Middle
RIGHT
LEFT15-May-14 15-May-14 18-May-14 12-Jun-14 UTL-LAY- 81 UTL-CON- 65 UTL-BF- 01
Middle11-Jun-14 11-Jun-14 12-Jun-14 10-Jul-14 UTL-LAY- 104 UTL-CON- 83 UTL-BF- 20
RIGHT
LEFT19-May-14 19-May-14 20-May-14 04-Jun-14 UTL-LAY- 87 UTL-CON- 66 UTL-BF- 03
Middle14-Jun-14 14/06/14 14-Jun-14 21-Jun-14 UTL-LAY- 108 UTL-CON- 84 UTL-BF- 21
RIGHT
LEFT02-Oct-14 02-Oct-14 02-Oct-14 UTL-LAY-184 UTL-CON-135
Middle
RIGHT
LEFT02-Oct-14 02-Oct-14 02-Oct-14 UTL-LAY-164 R1UTL-CON-134
Middle
RIGHT
LEFT02-Oct-14 02-Oct-14 02-Oct-14 UTL-LAY-185 UTL-CON-136
Middle
RIGHT
LEFT19-May-14 19-May-14 20-May-14 31-May-14 UTL-LAY- 85 UTL-CON- 63 UTL-BF- 02
Middle15-Jun-14 15-Jun-14 15-Jun-14 UTL-LAY- 107 UTL-CON- 85
RIGHT
LEFT20-May-14 20-May-14 25-May-14 04-Jun-14 UTL-LAY- 86 UTL-CON- 64 UTL-BF- 05
Middle15-Jun-14 15-Jun-14 15-Jun-14 08-Jul-14 UTL-LAY- 109 UTL-CON- 87 UTL-BF- 23
RIGHT
LEFT21-May-14 21-May-14 21-May-14 04-Jun-14 UTL-LAY- 89 UTL-CON- 67 UTL-BF- 04
Middle16-Jun-14 16-Jun-14 18-Jun-14 10-Jul-14 UTL-LAY- 110 UTL-CON- 90 UTL-BF- 29
RIGHT
23 CCC/FQR/IR/10 SOL-3 0+300 200 UPVC
CCC/FQI/SL/01 21+160 150 UPVC 45
SETOUT/
EXCV/ BED
PREP
DRAWING NO.
21+500
21+560
CCC/FQI/SD/07
450 CONC PIPECCC/FQI/SD/08
UPVC
4 CCC/FQR/WA/05 SR-1 0+600 300 UPVC
6 CCC/FQI/EL/01 21+360 150
300 UPVC
11 CCC/FQI/EL/02 21+660 150
7 CCC/FQI/IR/01 21+460
UPVC
12 CCC/FQI/IR/02
2
21+780 300 UPVC
BACKFILLI
NG
RFI REF.S.
NO.
CHAINAG
E
PIPE
2
2UPVC
INSTALLAT
IONCONCRETE
1CCC/FQI/IR/06 SERVICE
ROAD-30+030 200 UPVC
2 CCC/FQR/IR/11 SOL-2 0+150 300
NO. OF
WAYSSTAGE
2
3
13 CCC/FQI/NAW.2
3
2
CCC/FQI/SD/09 CONC PIPE
UPVC10021+870
10
2
450 CONC PIPE8
9
21+620 450
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report February 2015
RENARDET S.A. & PARTNERS Page 24
DIA TYPE LAYING CONCRETE BACKFILL
LEFT25-May-14 25-May-14 25-May-14 04-Jun-14 UTL-LAY- 90 UTL-CON-68 UTL-BF- 07
Middle16-Jun-14 16-Jun-14 17-Jun-14 10-Jul-14 UTL-LAY- 111 UTL-CON- 88 UTL-BF- 28
RIGHT
LEFT30-Aug-14 31-Aug-14 14-Sep-14 30-Sep-14 UTL-LAY-158 UTL-CON-96 UTL-BF-64
Middle27-Nov-14 14-Dec-14 23-Dec-14 UTL-EXC-63 UTL-CON-162 UTL-BF-115
RIGHT21-Jan-15 21-Jan-15 21-Jan-15 28-Jan-15 UTL-EXC-246 SL-CON-173 UTL-BF-148
LEFT17-Jun-14 17-Jun-14 18-Jun-14 09-Jul-14 UTL-LAY- 112 UTL-CON- 89 UTL-BF- 33
Middle20-Jul-14 20-Jul-14 21-Jul-14 27-Jul-14 UTL-LAY- 131 UTL-CON- 106 UTL-BF-44
RIGHT
LEFT19-Jun-14 19-Jun-14 19-Jun-14 06-Jul-14 UTL-LAY- 114 UTL-CON- 92 UTL-BF- 31
Middle20-Jul-14 20-Jul-14 21-Jul-14 17-Jul-14 UTL-LAY- 132 UTL-CON- 107 UTL-BF-46
RIGHT
LEFT19-Jun-14 19-Jun-14 19-Jun-14 05-Jul-14 UTL-LAY- 113 UTL-CON- 91 UTL-BF- 30
Middle20-Jul-14 20-Jul-14 21-Jul-14 17-Jul-14 UTL-LAY- 133 UTL-CON- 108 UTL-BF-45
RIGHT
LEFT
Middle
RIGHT
LEFT
Middle
RIGHT
LEFT26-May-14 26-May-14 26-May-14 08-Jun-14 UTL-LAY- 88 UTL-CON- 69 UTL-BF- 08
Middle11-Jun-14 11-Jun-14 11-Jun-14 22-Jul-14 UTL-LAY-106 UTL-CON- 81 UTL-BF-26
RIGHT
LEFT07-Jul-14 08-Jul-14 08-Jul-14 UTL-LAY-103A UTL-CON-98
Middle12-Aug-14 13-Aug-14 14-Aug-14 15-Aug-14 UTL-LAY-150 UTL-CON-122A UTL-BF- 37A
RIGHT
LEFT09-Jul-14 09-Jul-14 09-Jul-14 UTL-LAY- 116 UTL-CON-100
Middle12-Aug-14 13-Aug-14 14-Aug-14 25-Sep-14 UTL-LAY-151 UTL-CON-121 UTL-BF-81
RIGHT12-Oct-14 13-Oct-14 12-Oct-14 08-Nov-14 UTL-LAY-187 UTL-CON-137 UTL-BF-99
LEFT11-Jan-15 11-Jan-15 11-Jan-15 UTL-LAY-249 UTL-CON-174
Middle
RIGHT
LEFT02-Jul-14 03-Jul-14 03-Jul-14 UTL-LAY-122 UTL-CON-93R1
Middle10-Jul-14 10-Jul-14 14-Jul-14 UTL-LAY-126 UTL-CON-103
RIGHT22-Jul-14 22-Jul-14 23-Jul-14 20-Aug-14 UTL-LAY-136 UTL-CON-110 UTL-BF- 50
LEFT
Middle
RIGHT
LEFT16-Jun-14 16-Jun-14 16-Jun-14 20-Jul-14 UTL-LAY- 102 UTL-CON- UTL-BF-19
Middle08-Jul-14 08-Jul-14 09-Jul-14 27-Jul-14 UTL-LAY- 125 UTL-CON-99 UTL-BF-42
RIGHT
LEFT25-May-14 25-May-14 26-May-14 14-Jun-14 UTL-LAY- 91 UTL-CON- 71 UTL-BF- 06
Middle11/06/201 11-Jun-14 11-Jun-14 23-Jun-14 UTL-LAY- 105 UTL-CON- 82 UTL-BF- 25
RIGHT
22+080
UPVC
CCC/FQI/OMANTEL.1
22+510 150
150
CCC/FQI/SL/03 Rev A 22+820 150 UPVC 4
UPVC 4
23
CCC/FQI/SL/04
CCC/FQI/SL/02
UPVC
UPVC
UPVC
UPVC
UPVC
RC
UPVC
CCC/FQI/EL/05
22+990
CCC/FQI/SL/03 Rev A 22+830 150
28 CCC/FQI/EL/07
21 CCC/FQI/EL/06
22+520
19CCC/FQI/IR/04 JUNCTION
CROSSING
22+520
LHS
CCC/FQI/WA/01
CCC/FQI/WA/02
JUNCTION26
27
23+008
LHS
23+020
22+760
15023+060
14 CCC/FQI/EL/03 21+880
CCC/FQI/EL/04 22+260
UPVC
200
200
200
16
UPVC
UPVC
150
20CCC/FQI/IR/05 JUNCTION
CROSSING
4
3
3
3
2
2
2
3
25
150
22+810
15
22 100
4
4
1
1
3
22+587
LHS
18 CCC/FQI/IR/03
17
150
300
900
150
S.
NO.
UPVC
UPVC
24
RFI REF.DRAWING NO.
CHAINAG
E
PIPE NO. OF
WAYSSTAGE
SETOUT/
EXCV/ BED
PREP
INSTALLAT
IONCONCRETE
BACKFILLI
NG
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report February 2015
RENARDET S.A. & PARTNERS Page 25
DIA TYPE LAYING CONCRETE BACKFILL
LEFT27-May-14 27-May-14 27-May-14 17-Jun-14 UTL-LAY- 92 UTL-CON- 72 UTL-BF- 09
Middle
RIGHT
LEFT28-May-14 28-May-14 28-May-14 17-Jun-14 UTL-LAY- 93 UTL-CON- 70 UTL-BF- 10
Middle
RIGHT
LEFT
Middle
RIGHT
LEFT29-May-14 29-May-14 29-May-14 17-Jun-14 UTL-LAY- 94 UTL-CON- 73 UTL-BF- 11
Middle30-Jul-14 12-Aug-14 30-Jul-14 26-Aug-14 UTL-LAY-142 UTL-CON- 115 UTL-BF-48
RIGHT
LEFT29-May-14 31-May-14 31-May-14 17-Jun-14 UTL-LAY- 96 UTL-CON- 74 UTL-BF- 12
Middle10-Jul-14 10-Jul-14 13-Aug-14 26-Aug-14 UTL-LAY- 120 R1UTL-CON- 95 UTL-BF- 49
RIGHT
LEFT07-Sep-14 07-Sep-14 14-Oct-14 27-Oct-14 UTL-LAY-162 UTL-CON-124 UTL-BF-69
Middle15-Sep-14 15-Sep-14 17-Jan-00 UTL-LAY-162R1
RIGHT27-Oct-14 28-Oct-14 17-Nov-14 17-Nov-14 UTL-LAY-207 UTL-CON-152 UTL-BF-92
LEFT29-May-14 02-Jun-14 02-Jun-14 17-Jun-14 UTL-LAY- 95 UTL-CON- 75 UTL-BF- 15
Middle14-Jul-14 14-Jul-14 14-Jul-14 20-Aug-14 UTL-LAY- 124 UTL-CON- 102 UTL-BF- 36
RIGHT
LEFT29-May-14 02-Jun-14 02-Jun-14 17-Jun-14 UTL-LAY-97 UTL-CON- 76 UTL-BF- 13
Middle14-Jul-14 14-Jul-14 15-Jul-14 20-Aug-14 UTL-LAY- 127 UTL-CON- 101 UTL-BF- 38
RIGHT
LEFT10-Aug-14 11-Aug-14 11-Aug-14 26-Aug-14 UTL-LAY-149A UTL-CON- 120A UTL-BF- 58
Middle27-Oct-14 27-Oct-14 27-Oct-14 UTL-LAY- 206 UTL-CON- 153
RIGHT21-Jan-15 21-Jan-15 21-Jan-15 UTL-LAY- 248 UTL-CON- 172
LEFT 04-Nov-14 UTL-EXC-55
Middle
RIGHT
LEFT29-May-14 02-Jun-14 03-Jun-14 19-Jun-14 UTL-LAY- 98 UTL-CON- 77 UTL-BF- 14
Middle06-Aug-14 06-Aug-14 09-Aug-14 13-Aug-14 UTL-LAY- 134-R1UTL-CON- 109A UTL-BF- 53
RIGHT
LEFT
Middle
RIGHT
LEFT03-Jun-14 04-Jun-14 04-Jun-14 23-Jun-14 UTL-LAY- 99 UTL-CON- 78 UTL-BF- 16
Middle11-Aug-14 11-Aug-14 19-Aug-14 26-Aug-14 UTL-LAY-140 R1 UTL-CON-114 UTL-BF- 52
RIGHT
LEFT04-Jun-14 05-Jun-14 10-Jun-14 23-Jun-14 UTL-LAY- 100 UTL-CON- 79 UTL-BF- 17
Middle23-Jul-14 24-Jul-14 19-Aug-14 26-Aug-14 UTL-LAY-139 UTL-CON-112-R1 UTL-BF- 47
RIGHT
34
3
2
UPVC
CCC/FQI/EL/19 UPVC 2
1
2
600
300
UPVC
CCC/FQI/IR/07
RC
RC
UPVC
UPVC
37 CCC/FQI/SL/11 23+960 UPVC
23+210
150
23+240
23+560
150
150
150
150
600
23+820
23+980
24+000
150
UPVC
UPVC
UPVC
UPVC
3
4
33 CCC/FQI/NAW.3
CCC/FQI/WA/0440
39
41
CCC/FQI/EL/1242
CCC/FQI/EL/11
29 CCC/FQI/EL/13
CCC/FQI/EL/0830
3
1
3
2
CCC/FQI/EL/0932
35
CCC/FQI/WA/0336 23+900
CCC/FQI/EL/10
4
38
CCC/FQI/SD 23+400 60031
CCC/FQI/EL/21 23+965 200
23+580
24+020
24+120
2
CONC PIPE
23+740 150
100 UPVC
STAGESETOUT/
EXCV/ BED
PREP
INSTALLAT
IONCONCRETE
BACKFILLI
NG
RFI REF.S.
NO.DRAWING NO.
CHAINAG
E
PIPE NO. OF
WAYS
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report February 2015
RENARDET S.A. & PARTNERS Page 26
DIA TYPE LAYING CONCRETE BACKFILL
LEFT09-Jun-14 09-Jun-14 10-Jun-14 23-Jun-14 UTL-LAY- 101 UTL-CON- 80 UTL-BF- 18
Middle06-Aug-14 06-Aug-14 06-Aug-14 26-Aug-14 UTL-LAY-138-R1 UTL-CON-111-B UTL-BF- 56
RIGHT
LEFT05-Jul-14 05-Jul-14 05-Jul-14 19-Aug-14 UTL-LAY- 123 UTL-CON- 94 UTL-BF- 39R1
Middle4-Des-14 14-Dec-14 14-Dec-14 UTL-LAY- 222 UTL-CON- 97 R1
RIGHT
LEFT16-Jul-14 16-Jul-14 17-Jul-14 UTL-LAY- 130 UTL-CON- 105
Middle27-Oct-14 27-Oct-14 27-Oct-14 27-Oct-14 UTL-LAY-190R1 UTL-CON- 148 UTL-BF- 72
RIGHT
LEFT21-Jul-14 04-Aug-14 05-Aug-14 UTL-LAY-137-R1 UTL-CON- 118
Middle08-Aug-14 09-Aug-14 09-Aug-14 22-Sep-14 UTL-LAY-148A UTL-CON- 117 UTL-BF- 57
RIGHT16-Sep-14 16-Sep-14 16-Sep-14 UTL-LAY-172 UTL-CON- 126
LEFT14-Sep-14 14-Sep-14 14-Oct-14 20-Oct-14 UTL-LAY- 166 UTL-CON-125 UTL-BF-81
Middle27-Oct-14 30-Oct-14 27-Oct-14 10-Dec-14 UTL-LAY- 205 UTL-CON- 150 UTL-BF-99
RIGHT
LEFT16-Sep-14 17-Sep-14 30-Sep-14 UTL-LAY-174 UTL-CON-127
Middle14-Oct-14 18-Oct-14 14-Oct-14 UTL-LAY-188 UTL-CON-138
RIGHT27-Oct-14 27-Oct-14 27-Oct-14 UTL-LAY-204 UTL-CON-151
LEFT16-Sep-14 20-Sep-14 UTL-LAY- 173
Middle27-Oct-14 27-Oct-14 27-Oct-14 09-Nov-14 UTL-LAY- 203 UTL-CON- 149 UTL-BF-100
RIGHT
LEFT03-Nov-14 10-Nov-14 11-Nov-14 07-Dec-14 UTL-LAY- 211 UTL-CON- 155 UTL-BF-106
Middle
RIGHT
LEFT26-Feb-15 28-Feb-15 26-Feb-15 26-Feb-15 UTL-LAY-271 UTL-CON-191 UTL-BF-159
Middle
RIGHT
LEFT
Middle
RIGHT4-Sep-14 4-Sep-14 28-Sep-14 22-Feb-15 UTL-LAY-159-B UTL-CON-132 UTL-BF-151
LEFT
Middle
RIGHT
LEFT
Middle
RIGHT
LEFT16-Sep-14 17-Sep-14 30-Sep-14 18-Oct-14 UTL-LAY-167 UTL-CON-128 UTL-BF-78
Middle
RIGHT
UPVC
UPVC
UPVC
SOL-03
SOL-02 (R/A)
3
Ch:
0+054.459150
UPVC 2
2
UPVC 6
UPVC
UPVC300
24+850
150
150
24+820
24+960
25+160
43
44
45
47
49
UPVC150
300
24+220
24+340
24+520
46
CCC/FQI/EL/14
CCC/FQI/IR/08
CCC/FQI/EL/15
CCC/FQI/EL/16
CCC/FQI/NAW.4 24+720 2
2
CCC/FQI/IR/09
CCC/FQI/EL/1750
1 CCC/FQI/Omantel/02
UPVC
1 CCC/FQI/SL/18
4-Way
x150mm
SL Ducts
150 UPVC 4
100
0+130 150
0+138.348 110
CCC/FQI/SL/14
CCC/FQI/SL/15
0+415 1503
4
UPVC 4
CCC/FQI/SL/13
2
3
3
2
3UPVC150
UPVC 2-4WAY150CCC/FQI/SL/0148
STAGESETOUT/
EXCV/ BED
PREP
INSTALLAT
IONCONCRETE
BACKFILLI
NG
RFI REF.S.
NO.DRAWING NO.
CHAINAG
E
PIPE NO. OF
WAYS
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report February 2015
RENARDET S.A. & PARTNERS Page 27
13.
Project Name: Upgrading of Falaj Al Qabail Roundabout
Progress Status up to End of: Jan-15
Item Value SN ItemTotal
number
Number
completed
Number in
progressBalance SN
Color
legendItem description
Cumulative
up to end of
last month
Executed
this
month
Cumulative up to end
of this month
Relative
weight
(%)
Remarks
1 44-Cell Box Culvert 44.00 44.00 0.00 0.00 1 Road Diversion 69.96% 7.33% 77.29% 2.73 In Progress
2 9-Cell Box Culvert 9.00 9.00 0.00 0.00 2 Earthwork 80.36% 5.00% 85.36% 5.27 In Progress
Contingency R.O.1,402,155.613 3 8- Cell Box Culvert 8.00 8.00 0.00 0.00 3 Subbase layer 68.80% 6.00% 74.80% 0.49 In Progress
4 5-Cell Box Culvert 5.00 5.00 0.00 0.00 4 Agg. Base course 13.00% 9.00% 22.00% 1.93 In Progress
5 Single Cell Box Culvert 6.00 5.00 0.00 1.00 5 Bit. base course 0.00% - 0.00% 2.30 Not Started
Commencement Date 28.12.2013 6 Pedestrian Underpass @ CH 24+360 - SOL1 1 0.8 0 0.20 6 Bit. wearing course 0.00% - 0.00% 1.27 Not Started
Construction period 548 Days 7 Pedestrian Underpass @ CH 23+300 - SOL 1 1 0 0 1.00 7 Drainage 61.20% 5.00% 66.20% 1.50 In Progress
Completion date 29.6.2015 8 Pedestrian Underpass @ CH 0+050 - SOL 3 1 0.3 0.3 0.70 8 MSE Walls 95.00% 5.00% 100.00% 6.84 In Progress
9 Vehicular Underpass @ CH 21+300 1 1 0 0.00 9 MEP Works & Ducts 35.67% 4.00% 39.67% 4.03 In Progress
10 Vehicular Underpass @ CH 24+600 1 0.5 0.5 0.50 10 Incidental Works 21.99% 3.80% 25.79% 13.33 In Progress
Item Value 11 Bridge Foundation 10 10 0 0.00 11RCC Str.- Culverts &
Underpasses 79.72% 4.25% 83.97% 38.19 In Progress 35
12 Bridge Abutment 4 4 0 0.00 12 RCC Str. Bridges 65.26% 5.00% 70.26% 22.12 In Progress
13 Bridge Pier Column 10 10 0 0.00
Completion date 16.10.2015 14 Bridge Slab 4 2 1 2.00
Client: Project: SCALE
-
CCC DATE
Title: 28.02.2015
RENARDET S.A. & Partners UPGRADING OF FALAJ AL QABAIL ROUNDABOUT
MONTHLY PROFRESS REPORT CHART
SULTANATE OF OMAN
Directorate General of Roads & Land Transport
Revised Contract Details, if any
Total contract including
contingency
Contract Particulars RCC Structures (Culvert, bridge, underpass, tunnel, pedestrian facility) Physical Progress of Main BOQ Items (QTY)
Total contract excluding
ContingencyR.O.16,482,247.387
Total contract including
contingencyR.O.17,884,403.000
Overall project status (Sum of progress x weights) 67.88% 100.00
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report February 2015
RENARDET S.A. & PARTNERS Page 28
BWC 6 cmTack Coat BBC 12 cm
PRIME COAT PrimeABC 2 ND 15 cm ABC 2 ABC 2ABC 1 ST 15 cm ABC 1 ABC 1GSB 20 cm GSB GSBSubgrade Layr 9
Layr 8
Layr 7
Layr 6
Layr 5
Layr 4
Layr 3
Layr 2EMBANK L 1 BED PREPOGL SURVEY
21
+1
60
21
+1
80
21
+2
00
21
+2
20
21
+2
40
21
+2
60
21
+2
80
21
+3
00
21
+3
20
21
+3
40
21
+3
60
21
+3
80
21
+4
00
21
+4
20
21
+4
40
21
+4
60
21
+4
80
21
+5
00
21
+5
20
21
+5
40
21
+5
60
21
+5
80
21
+6
00
21
+6
20
21
+6
40
21
+6
60
21
+6
80
21
+7
00
21
+7
20
21
+7
40
21
+7
60
21
+7
80
21
+8
00
21
+8
20
21
+8
40
21
+8
60
21
+8
80
OGL SURVEY
BED PREPEMBANK L1layer 2
layer 3
layer 4 top of embankmentlayer 5
layer 6layer 7
layer 8
layer 9
Subgrade GSB 20 cm GSB GSBABC 1 ST 15 cm ABC 1 ABC 1 ABC 1ABC 2 ND 15 cm ABC 2 ABC 2 ABC 2PRIME COAT Prime PrimeBBC 12 cmTack Coat BWC 6 cm
LH
S
3 cell & U.pass
RH
S
3 cell & U.pass
Be
gin
nin
g o
f th
e P
roje
ct
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report February 2015
RENARDET S.A. & PARTNERS Page 29
BWC 6 cmTack Coat BBC 12 cm
PRIME COAT Prime PrimeABC 2 ND 15 cm ABC 2 ABC 2ABC 1 ST 15 cm ABC 1 ABC 1GSB 20 cm GSB GSB GSBSubgrade Sub grade Layr 9
Layr 8
Layr 7
Layr 6 SubgrdeLayr 5 embank 2Layr 4 embankLayr 3 Top of embankment 3rd rock soilLayr 2 2nd rock soilEMBANK L 1 BED PREPOGL SURVEY
21
+9
00
21
+9
20
21
+9
40
21
+9
60
21
+9
80
22
+0
00
22
+0
20
22
+0
40
22
+0
60
22
+0
80
22
+1
00
22
+1
20
22
+1
40
22
+1
60
22
+1
80
22
+2
00
22
+2
20
22
+2
40
22
+2
60
22
+2
80
22
+3
00
22
+3
20
22
+3
40
22
+3
60
22
+3
80
22
+4
00
22
+4
20
22
+4
40
22
+4
60
22
+4
80
22
+5
00
22
+5
20
22
+5
40
22
+5
60
22
+5
80
22
+6
00
22
+6
20
22
+6
40
OGL SURVEY
BED PREPEMBANK L1 1st rock soillayer 2 2nd rock soil 2nd rock soillayer 3 3rd rock soil 3rd rock soillayer 4 4th rock soillayer 5 top of Embankment 5th rock soillayer 6 6th rock soillayer 7 embankmen 1layer 8 embankment 2
layer 9 subgarde Subgrade SUBGRADEGSB 20 cm GSB GSB GSB
ABC 1 ST 15 cm ABC 1 ABC 1 ABC 1ABC 2 ND 15 cm ABC 2 ABC 2 ABC 2PRIME COAT Prime Prime Prime
BBC 12 cmTack Coat BWC 6 cm
RH
S
U turn
U turn
LH
S
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report February 2015
RENARDET S.A. & PARTNERS Page 30
BWC 6 cmTack Coat BBC 12 cm
PRIME COAT PrimeABC 2 ND 15 cm ABC 2ABC 1 ST 15 cm ABC 1GSB 20 cm GSBSubgrade top embankmentLayr 9 10 th rock soil
Layr 8
Layr 7 7th layer roock soil 7th layer of rock soil Layr 6 layer 15 of embankment
Layr 5 3th layer of rock soil Layr 4 4th rock soil Embankment layer no 28Layr 3
Layr 2
EMBANK L 1 BED PREPOGL SURVEY
22
+6
60
22
+6
80
22
+7
00
22
+7
20
22
+7
40
22
+7
60
22
+7
80
22
+8
00
22
+8
20
22
+8
40
22
+8
60
22
+8
80
22
+9
00
22
+9
20
22
+9
40
22
+9
60
22
+9
80
23
+0
00
23
+0
20
23
+0
40
23
+0
60
23
+0
80
23
+1
00
23
+1
20
23
+1
40
23
+1
60
23
+1
80
23
+2
00
23
+2
20
23
+2
40
23
+2
60
23
+2
80
23
+3
00
23
+3
20
23
+3
40
23
+3
60
23
+3
80
23
+4
00
23
+4
20
23
+4
40
23
+4
60
23
+4
80
23
+5
00
23
+5
20
OGL SURVEY
BED PREPEMBANK L1layer 2
layer 3
layer 4 4th rock soil Embankment layer no 28layer 5 3th layer of rock soil layer 6 layer 15 of embankmentlayer 7 7th layer roock soil 7th layer of rock soil layer 8
layer 9 10 rock soil 10th layer of rock soil Subgrade Embankment top embankment GSB 20 cm GSB
ABC 1 ST 15 cm ABC 1ABC 2 ND 15 cm ABC 2PRIME COAT Prime
BBC 12 cmTack Coat BWC 6 cm
LH
SR
HS
Bridge
Bridge
9 cell
9 cell
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report February 2015
RENARDET S.A. & PARTNERS Page 31
BWC 6 cmTack Coat BBC 12 cm
PRIME COAT ABC 2 ND 15 cmABC 1 ST 15 cm
GSB 20 cm GSBSubgrade Rock soil 18 th layer Sub grdeLayr 9 top of embankment
Layr 8 Rock siol 16thLayr 7
Layr 6 6th rock soilLayr 5 5th rock soilLayr 4 4th rock soil Layr 3
Layr 2 2nd rock soil2nd rock soilEMBANK L 1 1st rockBED PREPOGL SURVEY
23
+5
40
23
+5
60
23
+5
80
23
+6
00
23
+6
20
23
+6
40
23
+6
60
23
+6
80
23
+7
00
23
+7
20
23
+7
40
23
+7
60
23
+7
80
23
+8
00
23
+8
20
23
+8
40
23
+8
60
23
+8
80
23
+9
00
23
+9
20
23
+9
40
23
+9
60
23
+9
80
24
+0
00
24
+0
20
24
+0
40
24
+0
60
24
+0
80
24
+1
00
24
+1
20
24
+1
40
24
+1
60
24
+1
80
24
+2
00
24
+2
20
24
+2
40
24
+2
60
24
+2
80
24
+3
00
24
+3
20
24
+3
40
24
+3
60
24
+3
80
24
+4
00
24
+4
20
24
+4
40
OGL SURVEY
BED PREPEMBANK L1layer 2 2nd rock soil2nd rock soillayer 3
layer 4 4th rock soil layer 5 5th layer rock soillayer 6 6th layer rock soillayer 7layer 8
layer 9 top of Embankment Subgrade Rock soil 18 th layer Sub grade GSB 20 cm GSB
ABC 1 ST 15 cmABC 2 ND 15 cmPRIME COAT
BBC 12 cmTack Coat BWC 6 cm
1st layer of embankment Rock siol 16th
U turn & under pass
U turn & under pass
LH
SR
HS
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report February 2015
RENARDET S.A. & PARTNERS Page 32
BWC 6 cmTack Coat BBC 12 cm
PRIME COAT ABC 2 ND 15 cmABC 1 ST 15 cm ABC 1
GSB 20 cm GSBSubgrade Layr 9
Layr 8
Layr 7
Layr 6
Layr 5
Layr 4
Layr 3
Layr 2
EMBANK L 1 BED PREP sub grade in cut - verge prepration sub grade in cut OGL SURVEY
24
+4
60
24
+4
80
24
+5
00
24
+5
20
24
+5
40
24
+5
60
24
+5
80
24
+6
00
24
+6
20
24
+6
40
24
+6
60
24
+6
80
24
+7
00
24
+7
20
24
+7
40
24
+7
60
24
+7
80
24
+8
00
24
+8
20
24
+8
40
24
+8
60
24
+8
80
24
+9
00
24
+9
20
24
+9
40
24
+9
60
24
+9
80
25
+0
00
25
+0
20
25
+0
40
25
+0
60
25
+0
80
25
+1
00
25
+1
20
25
+1
40
25
+1
60
25
+1
80
25
+2
00
25
+2
23
OGL SURVEY
BED PREPEMBANK L1layer 2
layer 3
layer 4
layer 5
layer 6
layer 7layer 8
layer 9
Subgrade GSB 20 cm GSB GSB
ABC 1 ST 15 cm ABC 1ABC 2 ND 15 cmPRIME COAT
BBC 12 cmTack Coat BWC 6 cm
En
d o
f th
e p
roje
ct
LH
SR
HS
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report February 2015
RENARDET S.A. & PARTNERS Page 33
14.
Sl. No. DESCRIPTIONPAYMENT FOR
THE MONTH OF
GROSS
AMOUNT
(R.O.)
GROSS
AMOUNT
CLAIMED (R.O.)
REVISED NET
AMOUNT
CLAIMED
(R.O.)
DATE
SUBMITTED
AMOUNT
CERTIFIED (R.O.)DATE CERTIFIED
AMOUNT
RECEIVED
(R.O.)
DATE
PAYMENT DUE
DATE
PAYMENT
RECEIVED
1PAYMENT APPLICATION No. 1
(ADVANCE PAYMENT)Dec-13 1,648,225 1,648,225 1,648,225 23-Nov-13 1,648,225 29-Jan-14 1,648,225 6-Feb-14
2 PAYMENT APPLICATION No. 2 Jan-14 2,291,277 643,052 514,442 12-Feb-14 514,442 02-Apr-14 513,608 30-May-14 10-Apr-14
3 PAYMENT APPLICATION No. 3 Feb&Mar-14 2,808,644 517,367 434,917 06-Apr-14 434,917 03-May-14 414,674 30-Jun-14 22-Jul-14
4 PAYMENT APPLICATION No. 4 Apr-14 3,302,738 494,094 374,179 08-May-14 407,538 05-Jun-14 395,257 2-Aug-14 22-Jul-14
5 PAYMENT APPLICATION No. 5 May-14 3,770,362 467,624 374,172 05-Jun-14 445,708 04-Jul-14 374,172 31-Aug-14 22-Jul-14
6 PAYMENT APPLICATION No. 6 Jun-14 4,293,764 523,402 418,721 15-Jul-14 382,116 16-Jul-14 418,721 12-Sep-14 9-Sep-14
7 PAYMENT APPLICATION No. 7 Jul&Aug-14 5,697,543 1,403,779 1,123,023 14-Sep-14 1,123,023 18-Sep-14 1,123,023 15-Nov-14 19-Oct-14
8 PAYMENT APPLICATION No. 8 Sep-14 6,858,550 1,161,007 875,594 21-Oct-14 928,805 06-Nov-14 875,594 3-Jan-15 18-Dec-14
9 PAYMENT APPLICATION No. 9 Oct&Nov-14 8,435,464 1,576,914 1,053,584 17-Dec-14 1,306,552 29-Dec-14 1,053,584 27-Feb-15 15-Feb-15
10 PAYMENT APPLICATION No. 10 Dec-14 9,304,199 868,735 876,223 12-Jan-15 876,223 10-Feb-15 11-Apr-15
11 PAYMENT APPLICATION No. 11 Jan-15 10,102,517 798,318 718,579 26-Feb-15
12 PAYMENT APPLICATION No. 12 Feb-15
13 PAYMENT APPLICATION No. 13 Mar-15
14 PAYMENT APPLICATION No. 14 Apr-15
15 PAYMENT APPLICATION No. 15 May-15
16 PAYMENT APPLICATION No. 16 Jun-15
17 PAYMENT APPLICATION No. 17 Jul-15
18 PAYMENT APPLICATION No. 18 Aug-15
19 PAYMENT APPLICATION No. 19 Sep-15
20 PAYMENT APPLICATION No. 20 Oct-15
9,304,199 10,102,517 8,411,659 8,067,549 6,816,857 TOTAL AMOUNT (R.O.)
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report February 2015
RENARDET S.A. & PARTNERS Page 34
15.
Sl.
No.CCC HIRED
TOTAL
AVAILABLE
AT SITE
1 COMPRESSOR
2 AIR COMPRESSOR 1 1 2
3 MILLER WELDING MECHINE 2 2
4 GENERATOR 2 1 3
5 CRANES -
6 CRANES 30 TON / 25 TON / 70 TON 2 4 6
7 VEHICLES H.D. -
8 DIESEL TANKER -
9 FLAT TRAILER 3 3
10 HIAB TRUCK 3 3
11 P/MOVER + TIPPING TRAILER 4 6 10
12 TIPPER TRUCKS 13 7 20
13 WATER TANKER 5000 & 10000 GAL 1 3 4
14 EARTH MOVING PLANT
15 BOBCAT 1 3 4
16 EXCAVATOR 1 1
17 JCB 4CX / 3CX 1 6 7
18 SHOVEL / WHEEL LOADER 4 2 6
19 DOZER D9N/D8R -
20 TELEHANDLER -
21 CIVIL ENGINEERING EQUIPMENT
22 GREENE STABILIZER PLANT 1 1
23 STEEL D/D ROLLER 1 1
24 E/WORK ROLLER 3 3
25 MOTOR GRADER 1 2 3
26 TITAN PAVER MACHINE -
27 TYRE / PTR ROLLER 1 1
28 VOOGLE PAVER MACHINE 1 1
29 L. D. VEHICLES & TRUCKS
30 DYNA TRUCK 1 1
31 MAINTENANCE TRUCKS 1 1
32 ASHOK LEYLAND BUS 55 SEAT 5 5
33 TOYOTA COASTER BUS 24 S 1 1
34 TOYOTA COROLLA/CIVIC/YARIS 11 11
35 TOYOTA PICKUP/ISUZU 6 7 13
36 NISSAN PATHFINDER/X-TRAIL 5 5
37 TOYOTA LAND CRUISER/FORTUNER 4 4
38 Total 50 72 122
DESCRIPTION
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report February 2015
RENARDET S.A. & PARTNERS Page 35
16.
J