LA PALOMA MSW TREATMENT PLANT

ClientMadrid City Government

Residents served540,000 residents

Processes• Treated waste (total): 245,567 t• Recovered materials (total): 28,795 t

• Pre-treatment of remaining waste: 12,789 t

• Packaging treatment: 16,006 t• Composting: 566 t of compost produced

2016 data

Treatment capacity• 219,000 t/year remaining waste• 36,500 t/year local entities

70.6 kt CO2 prevented