Critique of the International Safety
Management (ISM) Code
Nautical Institute Command Seminar
Sydney16 June 2014
7/25/2019 Ism Code-r Nijjer
2/30
Rena, Costa Concordia & Sewol
7/25/2019 Ism Code-r Nijjer
3/30
Safety Management System
(SMS)
Themain purpose of a SMS is to
prevent a large scale accident
7/25/2019 Ism Code-r Nijjer
4/30
Safety Management Systems (SMS) - History
1950sNuclear Power Industry challenge of developing
safety standards in a totally new industry with extremeset of hazards
Existing safety standards inadequate and a new approach
had to be developed from the ground up with the goal of
zero accidents
All hazards were carefully identified in advance by domain
experts and systems built-in to manage all aspects of risk
and safety at the design stage from construction, and
operation to decommissioninglifecycle of the project
This proactive systematic approach to safety became
known as the Safety Case
7/25/2019 Ism Code-r Nijjer
5/30
SMS Chemical Plants
Seveso disaster in 1976 which involved a
large scale release of highly toxic dioxin from
a small chemical plant in Italy giving rise tothe Seveso I IDirective.
The Directive mandated systematic safety
management systems across facilities inEurope that handled dangerous substances.
7/25/2019 Ism Code-r Nijjer
6/30
SMSOffshore Industry
Piper Alpha was a North Sea oil productionplatform. On 6 July 1988 an explosion and the
resulting oil and gas fires destroyed it, killing 167
men. (Total insured loss was about US$3.4 billion).
The subsequent inquiry headed by Lord Cullen made
106 recommendations
Most significant of these recommendations was that
operators were required to present a safetycaseformanaging safety.
Safety Case implies a proactive approach
7/25/2019 Ism Code-r Nijjer
7/30
Safety CaseLord Cullen
Asafety case regime provides a comprehensive frameworkwithin which the duty holders arrangements andprocedures for the management of safety can bedemonstrated and exercised in a consistent manner. Inbroad terms the Safety Case is a document, meant to bekept up-to-date, in which the operator sets out its approachto safety and the safety management system, which itundertakes to apply. It is, on the one hand, a tool forinternal use in the management of safety and, on the otherhand, a point of reference in the scrutiny by an external
body of the adequacy of that management system, ascrutiny which is considered to be necessary for maintainingconfidence on the part of the public.
7/25/2019 Ism Code-r Nijjer
8/30
SMS - Shipping
Herald of Free Enterprise - 06 March 1987 capsized and sank afew minutes after leaving Zeebruge resulting in the deaths of193 passengers and crew
Scandinavian Star - On 07 April 1990 a fire broke out andrapidly spread through the ship resulting in the deaths of 158persons
Development of International Safety Management (ISM)Code for the Safe Operation of Ships and for PollutionPrevention1990 - 1995 Gestation period1998 - 2002 Staggered compliance in shipping industry
Large emphasis on closing the gap between the boardroomand the bridge). Prior to ISM it was felt that some risks werecreated in the boardroom and carried by the shipspersonnel - Herald of Free Enterprise
Accidents such as the Costa Concordia indicate inadequateidentification and classification of risk in the ISM Code
7/25/2019 Ism Code-r Nijjer
9/30
SMS - Ports
On 15 February 1996 the tanker Sea Empress under
pilotage became grounded at the entrance of Milford
Haven spilling 72,000 tons of crude oil into the sea
In March 2000 the Port Authority was found guilty
under the strict liability Water Resources Actfor not
having a safety management system. This judgement
bypassed the civil immunity of the pilot and port that
had withstood many challenges since 1913
7/25/2019 Ism Code-r Nijjer
10/30
SMS - Ports
Theport authority created and then operated a system
which resulted in Sea Empress attempting to enter the
Havenat a time as late or later, in terms of proximity to
low water, than any comparable vessel had attemptedpreviously. It thereby put (the pilot) in a position where as
a direct consequence of the management system
operated by the port he could make an error*of
navigation..Justice Steel2002 U.K . Port Safety Code introduced. (Mirror image
of ISM Code)
*Error seen as a consequence rather than a cause
7/25/2019 Ism Code-r Nijjer
11/30
Basis of ISM Code
The ISM Code is based on a Quality Management(QM) and Quality Assurance (QA) approach and
hastily adopted by the shipping industry after the
high profile 'Herald of Free Enterprise' and
Scandinavian Starincidents
The ISMCodeuses the same terminology, tools,
techniques and clauses as QM
Main difference:- QMhas focus on the Customerand Service
- ISMCodehas focus on Safetyand Environment
7/25/2019 Ism Code-r Nijjer
12/30
Aims of ISM Code
To provide an international standard for the
safe management and operation of ships and
for pollution prevention
To minimize the scope for poor human
decisions that contribute directly or indirectly
to a casualty or pollution incident through
better management
7/25/2019 Ism Code-r Nijjer
13/30
ISM Code - Deficiencies
QA/QM based safety management systems such as theISM Code take an engineering approach to safety
More suitable for manufacturing and other processdriven industries
Limited application on a moving ship operating in adynamic environment
In a dynamic environment safe outcomes are achievedthrough the timely interventions and adjustments of
skilled human operators to changes in an uncertainenvironment
(Many operations in shipping particularly in pilotage aresituated in the operational chain where activefailuresoccur)
7/25/2019 Ism Code-r Nijjer
14/30
Implementing a SMS in different Industries
A safety management system can be defined as a planned,
documented and verifiable method of managing hazards and
associated risks(Bottomley,1999).
Proper identification and classification of risk is a critical factor in
the protection encompassed in a safety management system
In the nuclear power industry SMS built in at design stageidealsituation. Hazards and risks clearly defined.
Relatively simple to transfer the concept to the process based
chemical and offshore industries
In shipping the industry to be managed:- is up and running.
- has its own strong traditions and culture
- involves a moving platform and incorporates a large element of dynamic risk
which is much more difficult to assess.
7/25/2019 Ism Code-r Nijjer
15/30
ISM Code - Deficiencies
In shipping it was very difficult to identify and classify risksand hazards with the same level of clarity as the processbased industries
It is also possible that existing risk controls in such areas as
bridge operations were considered sufficient It appears that no appraisal was done to check if existing risk
controls were adequate in meeting contemporary communitystandards in regard to acceptable risk and that availableknowledge and concepts on safety were taken into
consideration The practical solution was to consolidate existing practices as
a standard and amend the system after failures and accidents
7/25/2019 Ism Code-r Nijjer
16/30
ISM Code Viewed as a Safety Case
But what the ISM Code seeks to do is tosuperimpose a safety case regime which isregulatory in the sense that it is compulsory
and is intended to be fully enforceable, whilstbeing specific only in its generalrequirements
The ISM Code: The Road to Discovery ?
By Lord Donaldson of Lymington, Cadwallader Lecture 26 March 1998
Ship safety, and the consequences of the lack of it, is a topic which is asfascinating as it complex also by Lord Donaldson
7/25/2019 Ism Code-r Nijjer
17/30
ISM Code - Deficiencies
In practical terms this has made the ISM Code
a normative, top down and reactivesystem
With the level of safety required for shipping
the SMS must be proactive
Also the dynamic nature of bridge operations
demands a proactive approach
7/25/2019 Ism Code-r Nijjer
18/30
ISM Code - Decision Making, Human
Factors & Error Management
Aim of ISM code to minimize the scope for poorhuman decisions that contribute directly or indirectlyto a casualty or pollution incident through theapplication of better management
Decision makingis a process thoroughly permeated byhuman factors
QA based Safety Management System (SMS) such asthe ISM Code is not properly informed by humanfactors knowledge
In SMS context human factors implies errormanagement
7/25/2019 Ism Code-r Nijjer
19/30
Error Management (EM)
Human error is inevitable (Part of the humancondition). The most dedicated, conscientious,experienced and professional person can make theworst error (Fundamental)
Error Management (EM) must be a vital part of a properSMS for shipping
EM is bottom-up
Errors fall into recurrent patterns: the same situationkeeps on producing the same error in different people
QM based SMS is reactive. For something as dynamic aspilotage a SMS must be proactive
An SMS without human factors/error management hasbeen likened to a car without an engine (JamesReason)
7/25/2019 Ism Code-r Nijjer
20/30
Error ManagementRaising awareness of the types of individualhuman and teamwork errors that commonlyoccur and how we might prevent, trap and
mitigate these before they lead to an accidentis error management
The issue is not that an
error occurred, but how itfailed to be corrected
7/25/2019 Ism Code-r Nijjer
21/30
SMS and Risk A safety management system can be defined as a planned,
documented and verifiable method of managing hazards andassociated risks(Bottomley,1999).
Proper identification and classification of risk is a critical factor inthe protection encompassed in a safety management system
The demands of managing risks of workplace injury are very
different to the risks associated with a Low Probability/HighConsequence/High Profile (LP/HC/HP) transportation accidents. Yeta study concludes Even given the very different demands ofmanaging the risks of workplace injury compared to the risksassociated with LP/HC accidents, the overarching structures,individual components and major functionality of safety
management systems have remained very similar regardless ofindustrial context.
*Matthew J W Thomas (2012) A Systematic Review of theEffectiveness of Safety Management Systems (ATSB TransportSafety Report)
7/25/2019 Ism Code-r Nijjer
22/30
Risk AssessmentIACS Approach
Proper Risk Assessment is critical for the development of aSMSAccording to the International Association of Classification Societies IACS
There is no universally accepted definition of risk, but the one commonlyapplied and regarded as authoritative in most industrial contexts is:
Acombination of the probability, or frequency, of occurrence of a defined
hazard and the magnitude of the consequences of the occurrence. (ISO8402:1995/BS 4778)
From AGuide to Risk Assessment in Ship Operations- IACS No 127 (June2010)
IACS response to new requirement for risk assessment added as anamendment to the ISM Code 2010
How valid is this approach for assessing risk inshipping operations such as pilotage that involvedynamic risk?
7/25/2019 Ism Code-r Nijjer
23/30
IACS - Risk Assessment (Shipping)
The IACS approach to risk assessment issuitable for managing the type of risk inherent
in situations with a potential for personal
injury and death. The ISM Code does not address the risks
inherent in bridge operations beyond
mentioning a passage plan as a risk control.
7/25/2019 Ism Code-r Nijjer
24/30
Costa Concordia
The Costa Concordia (2012) accident occurred a decade after theintroduction of the ISM code. In terms of the IACS risk assessmentapproach it is a 1 in a 100 year accident and was therefore notincluded in the organisationsrisk matrix. [The cause of the accidentwas that more compartments were breached as result of theallision than the ship was designed to withstand. (Titanic - 1912)]
In all the post Costa Concordia analysis and discussion the role ofthe ISM Code in preventing/reducing the risk of such an accidentis conspicuous by its absence
The main purpose of a SMS is to prevent a large scale accident
7/25/2019 Ism Code-r Nijjer
25/30
Risk Assessment & Due Diligence
The combinationof probability, frequency, of occurrence of adefined hazard and the magnitude of the consequences of the
occurrence approach to risk assessment does not provide a
legal defence in case of an accident in Australia
The courts in Australia tend to take a very harsh view of safety
management systems based on methodologies backed by risk
experts but contrary to common sense.
Only a Safety Management System underpinned by a due
diligence approach can provide a credible legal defence
against negligence after an accident
7/25/2019 Ism Code-r Nijjer
26/30
Due Diligence - Negligence
Where it is possible to guard against aforeseeable risk, which though perhaps notgreat, nevertheless cannot be called remoteor fanciful, by adopting a means which
involves little difficulty or expense, the failureto adopt such a means will in general benegligent
High Court of AustraliaJustices Gibbs, MurphyBrennan, Deane
7/25/2019 Ism Code-r Nijjer
27/30
ISO 31000 versus Due Diligence
Costa Concordia
According to ISO 8402:1995/BS 4778 Standardfor Risk Assessment the Costa Concordia was a1 in a 100 year accident
In terms of due diligence what would haveguarded against the Costa Concordia accident?
Application of Bridge Resource Management(BRM/Error Management (EM) techniqueswould have greatly reduced the risk of an
accident(What is the cost and effort involved inimplementing BRM?)
7/25/2019 Ism Code-r Nijjer
28/30
Due Diligence
Legal basis of Risk and Liability:Are all reasonably practical precautions in place basedon the balance of the risk versus the effort required?
Two questions relating To Due Diligence- Does the way we operate meet contemporary
community standards in regard to acceptablerisk?
- Are we using all available knowledge in our
approach to safety or is it restricted to industrypractice?
7/25/2019 Ism Code-r Nijjer
29/30
Need for a Reappraisal
The criminal indictment and jailing of seafarersindicates the need for a reappraisal of the ISM Codeand consideration given to:
- taking into account a seafarers practical perspective (too much
emphasis on process and paperwork)- adopting a DueDiligence approach in developing resilience inregard to Low Probability/High Consequence/High Profile(LP/HC/HP) shipping accidents
Under Workplace, Health and Safety Actsdemonstrating Due Diligence is the only credibledefence