Brevard Public Schools Independent Citizens Oversight Committee

Report to Audit Committee April 28, 2016

ICOC Members

• Gary Shiffrin, Chair – Education - Viera

• Gene Cavallucci, Vice Chair – Legal - Melbourne

• Terry Chevallier, Secretary – Financial – Palm Bay

• Kayla Spellman, Treasurer – Financial - Rockledge

• Brian Blenis – Design – Palm Bay

• Daniel Daniels – Construction – Merritt Island

• Sherri O’Shea – Technology – Satellite Beach

• Billy Stover – Design - Titusville

• Matthew Susin – Business - Melbourne

• Mark Young – Business - Cocoa

ICOC Purpose

General oversight of sales surtax expenditures

Assure that expenditures are consistent with the site-based priority list

Evaluate capital expenditures that are substituted due to higher priority need

Excerpt from ICOC Charter

Audit Committee Report

• Financial Summary

• From inception through March 31, 2016

• ICOC Reporting:

• Covers major projects accomplished

• Notes planned projects

• Highlights exceptions

• Out-of-sequence components and systems

• Contingency use

• ICOC packages and audio posted on the web site

Revenue

Mar-15 Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16

Estimated Cumulative $2,266,486 $4,776,379 $8,385,920 $10,814,21 $13,010,87 $16,136,36 $18,398,91 $20,820,40 $24,025,41 $26,234,49 $28,396,50 $31,422,10 $33,690,60

Actual Cumulative $2,646,407 $5,546,855 $9,685,144 $12,694,63 $15,642,91 $19,510,99 $22,710,59 $25,437,27 $29,354,67 $32,214,81 $35,231,53 $39,961,18 $42,822,54

Variance Cumulative $379,921 $770,476 $1,299,224 $1,880,417 $2,632,041 $3,374,627 $4,311,683 $4,616,873 $5,329,259 $5,980,312 $6,835,036 $8,539,083 $9,131,946

$0

$5,000,000

$10,000,000

$15,000,000

$20,000,000

$25,000,000

$30,000,000

$35,000,000

$40,000,000

$45,000,000

Cumulative Estimated Revenue vs. Actual Cumulative Revenue

Estimated Cumulative

Actual Cumulative

Variance Cumulative

$1,242,986

$5,486,050

$33,950,137

$2,143,377

Allocation by Group Through March 2016

School Security

Educational Technology

Facility Renewal

Contingency

Expenditures

Expenses and Encumbrances through March 31, 2016

• Facility Renewal $19 million

• Educational Technology $2.3 million

• Structured cabling at Rockledge High

• First round of computers purchased at all schools

• District Security $429k

• Oak Park pilot project operational and under review

• +/- 20 schools planned this summer

• Contingency

• About 2/3 of facility renewal contingency has been invested in failed critical components

Projects

Summer 2015

• Ocean Breeze Elementary – complete!

• Audubon Elementary

• Oak Park Elementary

• Andersen Elementary

• DeLaura Middle

• Palm Bay Elementary

• Sherwood Elementary (component)

• Atlantis Elementary (component)

• Jefferson Middle (component)

Ocean Breeze Elementary (#1)

Facility Renewal project complete summer 2015 Project includes renewal of central mechanical plant, air

conditioning and air distribution equipment, electrical distribution and fire alarm systems

Partially funded with sales surtax

Audubon Elementary (#4)

Mechanical systems completed summer 2015 utilizing sales surtax funds

Summer 2016 construction of electrical system renewal and plumbing and fire alarm system upgrades

Andersen Elementary (#5)

HVAC renewal complete for Buildings 2, 3 and 5 Additional HVAC work, electrical system renewal

– summer 2016 Roof renewal planned summer 2017

Palm Bay Elementary (#10)

Chiller replacement (sales surtax funds) and roof membrane renewal (capital renewal funds) complete summer 2015

Air conditioning, fire alarm and plumbing systems renewal – summer 2016

DeLaura Middle (#3)

Replacement of equipment and related piping in central HVAC plant completed with capital renewal funds

HVAC system renewal for Pods 2 and 4 completed summer 2015 Renewal of entire AC system to be constructed in phases, as

funding is available Electrical and fire alarm system renewals summer 2016

Oak Park Elementary (#12)

HVAC system renewal complete (partially funded with sales surtax)

Additional facility, electrical system, plumbing system and building envelope construction - summer 2016

Sherwood Elementary (out of sequence)

Failed chiller replaced with sales surtax funds, summer 2015 Addressed out of sequence due to failure

Atlantis Elementary (out of sequence)

Failed chiller replaced summer 2015 Replacement funded with sales surtax contingency – was

not on the original list, but failed this summer

Jefferson Middle (#6, emergency replacement)

Failed cooling tower replaced using sales surtax funds Facility renewal scheduled summer 2016 – design build

Rockledge High (#1 Educational Technology)

Structural cabling project underway (educational technology) Includes network, fiber optic, telephone and instructional

television components Approximately 7500’ of 2” backbone conduit installed

Complete the First Group of Schools Summer 2016 Construction

• Audubon Elementary (Art Johnson)

• Oak Park Elementary (Art Johnson)

• Andersen Elementary (Dave Martin)

• DeLaura Middle (Dave Martin)

• Palm Bay Elementary (Dave Martin)

Design Build Projects Under Contract Summer 2016 Construction

• Discovery Elementary (Jim Hudson)

• Jefferson Middle (Tom Hood)

• Tropical Elementary (Tom Hood)

• Roosevelt Elementary (Jim Hudson)

• Sea Park Elementary (Tom Hood)

• Cape View Elementary (Jim Hudson)

Unplanned Critical Needs

• System and/or component replacements planned at:

• Relocatable classroom A/C replacements – 65 units @ 23 schools

Bayside Lewis Carroll

Coquina Merritt Island High

Creel Palm Bay High

Eau Gallie High Roy Allen

Endeavour Titusville High

Freedom 7 West Shore

Johnson Westside

Other Projects In Progress

• District School Security

• Completed Oak Park as pilot project

• +/- 20 schools planned this summer

• +/- 60 schools planned for single design build project

• Educational Technology

• Atlantis Elementary – Educational Technology and Fire Alarm Renewal – under contract

• Longleaf Elementary - Educational Technology Design Criteria Package is underway

• Structured cabling also coming at Meadowlane Primary, Melbourne High

• Planning underway for switches, wireless access points and telephone renewal

Oak Park Elementary (Security Project)

Single point of entry for screening and badging of visitors Fencing in accordance with District standards

Design Build Projects Under Contract Major Construction Summer 2017

•Hoover, Sabal (Jim Hudson)

•Melbourne High (Tom Hood)

• Saturn, Fairglen, Kennedy (Jim Hudson)

• Apollo, Pinewood, Jackson (Art Johnson)

Design Build Projects Proposed Major Construction Summer 2017 and 2018

• Stone (Dave Martin)

• Turner, Southwest (Chris Ault)

• Coquina (Dave Martin)

• Rockledge High, Cocoa High

• Croton, Lewis Carrol, Williams

• Mila

• Golfview

• Creel

Conclusions

Conclusions

• Surtax revenues are exceeding estimates

• Surtax expenditures are consistent with the Sales Surtax Funded Detail Report (Attachment F)

• Unplanned critical needs/use of contingency are reported to the ICOC and expenditures are consistent with the parameters established for the use of the surtax

• Age of facilities and deferred maintenance contribute to failing systems and components

• Projects reflect high level of collaboration among District staff members (energy, code compliance, environmental health & safety, maintenance, purchasing & finance)