EPRI's XIII Annual Power Switching Safety and Reliability...

Post on 20-Jan-2021

4 views 0 download

Transcript of EPRI's XIII Annual Power Switching Safety and Reliability...

September 14, 2009 EPRI's XIII Annual Power Switching Safety and Reliability Conference

1

Distributed GenerationPresented by: Doug Fairchild & Chris Cooper

September 14, 2009 EPRI's XIII Annual Power Switching Safety and Reliability Conference

2

Agenda

• Hydro One Overview• The state of DG in the Province of Ontario• Technical Issues• Operational Requirements Overview• Control Room Network Management

System

September 14, 2009 EPRI's XIII Annual Power Switching Safety and Reliability Conference

3

Hydro One Overview

September 14, 2009 EPRI's XIII Annual Power Switching Safety and Reliability Conference

4

Family of Companies

September 14, 2009 EPRI's XIII Annual Power Switching Safety and Reliability Conference

5

Hydro One Networks

Hydro One Networks

AssetManagement

Engineering &Constructions Grid Ops Customer Ops

September 14, 2009 EPRI's XIII Annual Power Switching Safety and Reliability Conference

6

Our Mission

September 14, 2009 EPRI's XIII Annual Power Switching Safety and Reliability Conference

7

Where are we?

September 14, 2009 EPRI's XIII Annual Power Switching Safety and Reliability Conference

8

Ontario Grid Control Center (OGCC)

September 14, 2009 EPRI's XIII Annual Power Switching Safety and Reliability Conference

9

System DetailsStations Transmission - 274Distribution - 1035

Lines/UG Cables500kV - 3,784km230kV - 13,824/50km115kV -10,953/220km 4 to 44kV - 119,800km

CustomersTransmission:Large Direct - 94Local Distribution - 83Generation - 33

Distribution:Customers - 1.3 M

Generators174 (includes 77 OPG)

2007 Peak Demand25,707 MW 28,005 MW (Highest Peak recorded Aug 1, 06)

September 14, 2009 EPRI's XIII Annual Power Switching Safety and Reliability Conference

10

Eastern Inter Ties

New York 1,700-2,050 MW in 1,700-2,350 MW out

Ontario

Michigan1,250-1,400 MW in 1,550-

1,700 MW out

Minnesota90 MW in

140 MW out

Quebec1,500 MW in;620 MW out

Manitoba330 MW in;260 MW out

September 14, 2009 EPRI's XIII Annual Power Switching Safety and Reliability Conference

11

The State of DG in the Province of Ontario

September 14, 2009 EPRI's XIII Annual Power Switching Safety and Reliability Conference

12

Current Supply Mix

As of: 1st Quarter 2009 RESOP Supply Mix

September 14, 2009 EPRI's XIII Annual Power Switching Safety and Reliability Conference

13

DG Supply Mix (RESOP)

As of: 1st Quarter 2009

Renewable Energy Standard Offer Program

September 14, 2009 EPRI's XIII Annual Power Switching Safety and Reliability Conference

14

DG Connection Process

CIA CIA

Cost EstimateCost Estimate

Design & ConstructDesign & Construct

Init. Consult./FeasibilityInit. Consult./Feasibility

Impact on Distribution System and supply station

How much willit cost?

Design, Construct & Commission

Cost Recovery Agreement

Cost Estimate Agreement

CIA Study Agreement

ConnectConnect Connect

Connection Agreement

September 14, 2009 EPRI's XIII Annual Power Switching Safety and Reliability Conference

15

Renewable Generation

September 14, 2009 EPRI's XIII Annual Power Switching Safety and Reliability Conference

16

Generator Categories

ConnectionTransmission

TS BusH1 DistributionLDC (Co-op)

Embedded LDC

MeteringNet MeteringWholesale

RetailLoad Displacement

Emergency Back-Up

FuelWind

Hydro ElectricWaste

Bio-fuelSolar

SizeMicroSmall

Mid-SizedLarge

September 14, 2009 EPRI's XIII Annual Power Switching Safety and Reliability Conference

17

Ontario Electricity Stakeholders

ExternalOntario GovernmentMinistry of Energy

OEBOPAIESOESA

DevelopersOFA

LDC'sCSA

InternalDistribution System

Development Legal

Engineering and Construction Services

Provincial LinesRegulatory

Metering and SettlementsGrid Operations

September 14, 2009 EPRI's XIII Annual Power Switching Safety and Reliability Conference

18

Technical Issues

19

TS

Tran

smission

 System

Distribution 

System

LoadLoad

Load

Load

Generator

Distributed Generation Base Case: No Distributed Generation

20

GeneratorTran

smission

 System

TS

LoadLoad

Load

Load

Distributed Generation Case 1: Loads > DG

DG

Tran

smission

 System

Distribution 

System

21

Generator

TS

LoadLoad

Load

Load

Distributed Generation Case 2: DG > Load

DG

Tran

smission

 System

Distribution 

System

22

Generator

TS

LoadLoad

Load

Load

Distributed Generation Case 2: DG >> Load, Reach Dx Feeder Thermal Limits

DG DG

Tran

smission

 System

Distribution 

System

23

Generator

TS

LoadLoad

Load

Load

Distributed Generation Case 4: Voltage Fluctuation – Sudden disconnection of DG

Tran

smission

 System

Distribution 

System

24

Generator

TS

LoadLoad

Load

Load

Distributed Generation Case 5: Fault Causes “Islanding” due to Distribution Fault

DG

Supplied by DG Only

Tran

smission

 System

Distribution 

System

25

Generator

TS

LoadLoad

Load

Load

Distributed Generation Case 5: Protection, Control, & Telecom Corrects Islanding

DG

Breaker left open to 

protect DG

Tran

smission

 System

Distribution 

System

Momentary Outage

26

Generator

TS

LoadLoad

Load

Load

Distributed Generation Case 6:DG >> Load; Exceed Station Equipment Limits

DG DG

Tran

smission

 System

Distribution 

System

27

Generator

TS

LoadLoad

Load

Load

Distributed Generation Case 6:Exceed Interface Limits

DG DG

Tran

smission

 System

Distribution 

System

September 14, 2009 EPRI's XIII Annual Power Switching Safety and Reliability Conference

28

Operational Requirements

September 14, 2009 EPRI's XIII Annual Power Switching Safety and Reliability Conference

29

Telemetry Requirements

Generators > 250 kW’s:• MW• MVAR• Current• Voltage

** As measured at the Point of Common Coupling (PCC)

September 14, 2009 EPRI's XIII Annual Power Switching Safety and Reliability Conference

30

Customer Interface Protections

• Over/Under Voltage• Over/Under Frequency• Overcurrent Protection• Distance Protection

September 14, 2009 EPRI's XIII Annual Power Switching Safety and Reliability Conference

31

Power Quality

• DG’s are not allowed to actively control the voltage. They currently operate at a fixed power factor.

• Must meet industry standards for:– Flicker– Harmonic Distortion

• PQ meter required – data logged

September 14, 2009 EPRI's XIII Annual Power Switching Safety and Reliability Conference

32

Connection Agreement

• Connection Agreement template updated to reflect DG operating requirements;– Real Time Contact– Emergency Switching– Limitations of the Distribution System– Loss of telemetry

September 14, 2009 EPRI's XIII Annual Power Switching Safety and Reliability Conference

33

Operational Requirements

• DG must disconnect if the normal (or approved alternate) supply changes. Established at the CIA stage.

• Any temporary feeder parallels using an air break switch requires DG’s to come off-line.

• No automatic re-synchronization unless:– DG has 24 hr contact with ability to disconnect or– Hydro One has remote control of customer LBS

• Lock out auto re-synch. after 15 minutes of loss of supply (voltage/frequency).

September 14, 2009 EPRI's XIII Annual Power Switching Safety and Reliability Conference

34

Commissioning

• Customer is responsible to commission their own facilities

• Hydro One is obligated to ensure safe & reliable operation of the distribution system

• The “COVER” provides a documented process to ensure interconnected systems have been verified to operate as designed

COVER – Confirmation of Verification Evidence Report

September 14, 2009 EPRI's XIII Annual Power Switching Safety and Reliability Conference

35

Long term Strategy

• Need to develop a long term strategy• Control Room primarily monitors Transmission Assets.• Smart Grid occurs at the Distribution level.• DG is not evenly spread across the province.• How do we grow the control room?• Should we develop both Tx & Dx specific Operators?• Or should our Operators know both systems?• Need for a higher level of service to our DG customers.

September 14, 2009 EPRI's XIII Annual Power Switching Safety and Reliability Conference

36

Network Management System

• Display all Generation above 250 kW’s• Real Time Data:

• Analogs• Alarms• Status• Control

• Need for Aggregate DG output per:• Feeder• Station

September 14, 2009 EPRI's XIII Annual Power Switching Safety and Reliability Conference

37

EMS Display Template

September 14, 2009 EPRI's XIII Annual Power Switching Safety and Reliability Conference

38

Sample EMS Displays

September 14, 2009 EPRI's XIII Annual Power Switching Safety and Reliability Conference

39

Thank You