Post on 04-Jun-2018
8/13/2019 Earned Value and Weighted Milestones
1/22
Earned Value and Weighted
Milestones
8/13/2019 Earned Value and Weighted Milestones
2/22
Lesson Objectives
Define earned value
Define performance percent complete
Review the results of different earnedvalue techniquesRealize the benefits of using earned valuetechniques
12-1
8/13/2019 Earned Value and Weighted Milestones
3/22
Earned Value Analysis
A technique for measuring projectperformance according to project cost
and schedule. This technique compares the budgeted(planned) cost of work to the actual cost.
12-2
8/13/2019 Earned Value and Weighted Milestones
4/22
The cost of the work that should havebeen accomplished as of the data date,if the project had proceeded according tothe baseline plan.
Planned Value Cost =Budget At Completion * Schedule %Complete
Schedule % Complete specifies how muchof an activitys baseline duration has beencomplete so far.
Answers the question: How much work should be done?
Planned Value Cost
12-2
8/13/2019 Earned Value and Weighted Milestones
5/22
Earned Value Cost is the monetary value ofthe work performed by a resource as of thedata date.
Earned Value Cost =Budget At Completion * Performance %Complete
The method for computing performance percentcomplete depends on the earned valuetechnique selected at the WBS level.
Answers the question: How much work is done?
Earned Value Cost
12-2
8/13/2019 Earned Value and Weighted Milestones
6/22
Actual Cost is the actual total costincurred for the work accomplished asof the data date.
Actual Cost = Actual Labor Cost + ActualNonlabor Cost + Actual Expense Cost Actual Cost is the same as the Actual Total
Cost.
Answers the question: How much did the completed work cost?
Actual Cost
12-2
8/13/2019 Earned Value and Weighted Milestones
7/22
Performance % Complete can bedifferent from the Activity % Completedepending on the technique used to
compute it. These techniques are set at the WBS
level.
Performance % Complete
12-8
8/13/2019 Earned Value and Weighted Milestones
8/22
Activity percent complete Calculated based on the activitys percent
complete type
WBS Milestones percent complete Calculated based on the completion of the
WBS elements weighted milestones
0/100 Calculated as 0% after an actual start is
assigned, then as 100% after an actualfinish is assigned
Techniques
12-8
8/13/2019 Earned Value and Weighted Milestones
9/22
50/50 Calculated as 50% after an actual start is
assigned, then as 100% after an actualfinish is assigned
Custom percent complete Calculated as a user-defined percentage
after an actual start is assigned, then as100% after an actual finish is assigned
Techniques cont.
12-8
8/13/2019 Earned Value and Weighted Milestones
10/22
Weighted Milestones
Weighted milestones can be used whenhigher-level task increments comprise abody of activities and you want to control
the activities at the WBS level. When you assign weights to the WBS
milestones, the completion of each
specific milestone is used to calculatethe performance percent complete of theWBS.
12-9
8/13/2019 Earned Value and Weighted Milestones
11/22
Weight of the milestone can be anynumber between 0 and 999999.
Performance percent complete iscalculated based on the relative weightsof the completed milestones vs. theincomplete milestones. The performance percent complete is
applied to all the activities under that WBSlevel, and then rolled back up to the WBS.
Weighted Milestones cont.
12-9
8/13/2019 Earned Value and Weighted Milestones
12/22
The following option must be set to useweighted milestones: In the WBS window, select the Earned
Value tab in WBS Details. Mark the WBSMilestone percent complete checkbox.
Use when calculating earned value.
Weighted Milestones cont.
12-9
8/13/2019 Earned Value and Weighted Milestones
13/22
Cost and SchedulePerformance Indices
A way to analyze how efficiently theproject is progressing is to calculate cost
and schedule performance indices.
12-17
8/13/2019 Earned Value and Weighted Milestones
14/22
Relates the amount of physical earnedvalue accomplished against the dollarsactually spent to accomplish the earnedvalue
CPI = Earned Value Cost / Actual Cost A value of less than one (1) indicates that
actual costs have exceeded the value ofthe work performed.
Cost Performance Index (CPI)
12-17
8/13/2019 Earned Value and Weighted Milestones
15/22
Relates the amount of physical earnedvalue accomplished against the workthat was planned
SPI = Earned Value Cost / Planned ValueCost A value of less than one (1) indicates that
less work was actually performed than wasscheduled.
Schedule Performance Index (SPI)
12-18
8/13/2019 Earned Value and Weighted Milestones
16/22
Techniques for CalculatingEstimate to Complete (ETC)
P3e contains various techniques forcalculating ETC.
Techniques take into consideration adelay in the schedule and an overrun incosts.
Set at the WBS level.
12-19
8/13/2019 Earned Value and Weighted Milestones
17/22
Techniques for Calculating Estimateto Complete (ETC)
The ETC identifies how much money youare projected to spend from now to theend of the project.
Calculated using two formulas: ETC = remaining cost for activity
Remaining Units * Resource Price/Time
ETC = Performance Factor * (Budget atCompletion Earned Value Cost).
Where Performance Factor is calculateddepending on the earned-value techniqueselected for the WBS. 12-19
8/13/2019 Earned Value and Weighted Milestones
18/22
8/13/2019 Earned Value and Weighted Milestones
19/22
8/13/2019 Earned Value and Weighted Milestones
20/22
This is the system default and calculatesETC based on the remaining units. This calculation does not take a
schedule delay or overspending intoconsideration. Historical evidence shows that these trends
do not correct themselves over time; theytend to get worse.
Remaining Cost
12-21
8/13/2019 Earned Value and Weighted Milestones
21/22
Represents a reliable indicator of theminimum total required costs Viewed as the very best the project will do
based on its history ETC = (1/CPI) * (Budget at Completion
Earned Value Cost)
Using CPI to Calculate ETC
12-22
8/13/2019 Earned Value and Weighted Milestones
22/22
Represents a reliable indicator of themaximum total required costs Incorporates the cost overrun to date
with a behind-schedule condition toproduce a more severe statisticalforecast Viewed as the very worst the project will do
based on its history
ETC = [1/(CPI * SPI)] * (Budget atCompletion Earned Value Cost)
Using CPI and SPI to Calculate ETC
12-24