testdatagraph - Milestones Professional · Actual Earned Value 12/10/2018 Project Funding Dashboard...
Transcript of testdatagraph - Milestones Professional · Actual Earned Value 12/10/2018 Project Funding Dashboard...
Milestones Professional 2017 New Features © KIDASA Software, Inc. October 2016 www.kidasa.com
New in Vers ion 2017
Full undo feature, with the ability to undo up to 100 actions. An undo counter on the status bar indicates how many actions can be “undone.”
Intuitive CTRL-A to select either all symbols or all tasks.
Independent date headings can be attached to task rows.
View the selected symbol in the status bar.
Add a web or file link to any freeform text block.
Choose border line pattern and colors for free-form text blocks. Also, change the colors of individual lines of text.
Support for hi-res monitors.
It’s now possible to select a group of symbols and
shift their dates.
Show the after status (incomplete) version of a bar in the legend.
Design your own import symbology for Microsoft Project.
When linking to Microsoft Project, select a group of tasks to import.
Create a variety of schedules from Microsoft Outlook calendar or tasks using a simple wizard. Also, export a Milestones Professional schedule to Outlook as a task list.
Create a schedule from Excel and keep it up to date with a refresh.
Much more!
Undo up to 100 actions !
Freeform text—more customization
Hi-res monitor improvements
Show value on point or bar
Task date headings more f lex ib le
ONE TWO THREE FOUR FIVE SIX SEVEN
Level 1In Progress
Level 2In Progress
Level 3In Progress
Level 4In Progress
Level 1 Complete
Level 2Complete
Level 3 Complete
Level 4Complete
Population E-5Testing
Level 1In Progress
Level 2In Progress
Level 3In Progress
Level 4In Progress
Level 1 Complete
Level 2Complete
Level 3 Complete
Level 4Complete
June July
13 20 27 4 11 18 25
Page 1 of 1 10/20/2016
testdatagraph.mpp
Task name%
Complete
Task 1100.0%
Task 1-1100.0%
Task 1-2100.0%
Task 20.0%
Task 2-10.0%
Task 2-20.0%
Task 2-30.0%
0.0%
7/15
7/15
6/23 6/267/2
Des ign your own Project Import symbology
Show af ter status in legend
Milestones Professional 2017 New Features © KIDASA Software, Inc. October 2016 www.kidasa.com
I m p r o v e d U n d o
Improved Undo 2017
A new Multiple Undo feature has been added to Milestones. Now all actions can be undone. You can set the number of actions that
can be undone from 1 to 100 (the default is 20). This is done using the Tools | Program Options | Edit screen:
Milestones Professional 2017 New Features © KIDASA Software, Inc. October 2016 www.kidasa.com
Schedule presentat ion enhancements 2017
Line by Line Color for Freeform Text
Now, individual lines of free-form text can be colored.
Border choices for Freeform text
Change the color and the line pattern for individual blocks
of text..
Milestones Professional 2017 New Features © KIDASA Software, Inc. October 2016 www.kidasa.com
Schedule presentat ion enhancements 2017
Date headings attached to rows can be different than main headings
It is now possible to attach any single type of date heading to a row. Now, when you right-click on the menu to attach a date heading to a row, a
dialog appears that lets you remove the heading, attach a copy of the schedule headings, or a single independent heading of any type:
Milestones Professional 2017 New Features © KIDASA Software, Inc. October 2016 www.kidasa.com
Schedule presentat ion enhancements 2017
Legend can now automatically show after status (incomplete) version of symbols/bar
If you check the “Show After Status Settings” in the Legend Entry Edit screen, the legend will show the after status (incomplete) version of the symbols/
bar. This makes it easier for people who wish to show legend entries for both complete and incomplete tasks. They no longer need to manually create
an incomplete version of their symbols/bar:
Selectively suppress interior column dividers
It’s now possible to suppress the interior column dividers on just one side of the schedule:
Automatic Page Breaks
You can now insert Page Breaks automatical-
ly based upon outline level or number of
rows:
ONE TWO THREE FOUR FIVE SIX SEVEN
Level 1In Progress
Level 2In Progress
Level 3In Progress
Level 4In Progress
Level 1 Complete
Level 2Complete
Level 3 Complete
Level 4Complete
Population E-5Testing
Level 1In Progress
Level 2In Progress
Level 3In Progress
Level 4In Progress
Level 1 Complete
Level 2Complete
Level 3 Complete
Level 4Complete
Milestones Professional 2017 New Features © KIDASA Software, Inc. October 2016 www.kidasa.com
DataGraph and ValueSet Enhancements 2017
2018 2019
Jul Aug Sep Oct Nov Dec Jan Feb Mar
Funds Exhausted
Funds Remaining
Over Funding Limit$0
$1,200
$2,400
$3,600
$4,800
$6,000Budget
$0
$823
$2,313$2,780
$3,561
$4,800$5,293
$5,721 $5,850Actual
Earned Value
12/10/2018
Project Funding Dashboard
Earned
Value
Project
Name
WBS
Number
Baseline
Cost
Costs
to Date
Remaining
Cost
$3,922 Building Improvements1 $5,850 $5,000
$1,300Bass Hall1.1 $1,300 $1,350
$0Approval/Meetings1.1.1 $0 $0
$500Design1.1.2 $500 $550
$800Construction1.1.3 $800 $800
$1,605Parlin Hall1.2 $1,650 $1,275
$0Approval/Meetings1.2.1 $0 $0
$1,400Design1.2.2 $1,400 $1,075
$205Construction1.2.3 $250 $200
$1,016Main Hall Tower1.3 $2,900 $2,375
$0Approval/Meetings1.3.1 $0 $0
$888Design1.3.2 $1,400 $1,075
$129Construction1.3.3 $1,500 $1,300
Funds Exhausted
Funds Remaining
Over Funding Limit
2019 2020
Q4 Q1 Q2 Q3 Q4
Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
($2,000)
$0
$2,000
$4,000
$6,000
$8,000Budget
$849$1,466 $1,536 $1,871
$3,840
$6,436
$2,908
Actual
$525 $870 $1,134$1,876
$2,651
$4,545
$2,199
Government Contract Task Plan
WORK P
DESCRIP
% TASK
COMPLETE
AP
AP
TVP
FINAL
DP
DS
SDA
SDA
SEI
SEITEST MOTOR DESIGN AND
SUPPORT47%
ANALYSIS PLAN
54%
TEST & VERIFICA
TION PLAN
59%
DESIGN PLAN
56%
SYSTEM DESIGN ANALYSI
S
35%
SYSTEMS
ENGINEERING
16%
AP
AP
TVP
FINAL
DP
DS
SDA
SDA
SEI
SEI
AP
AP
TVP
REDLINE DRAFT
FINAL
DP
DS
SDA
SDA
SEI
SEI
PROJECT MILESTONES
2018
Feb'18 Mar'18 Apr'18 May'18 Jun'18 Jul'18 Aug'18
Baseline Track Revised Track Current Status
$0
$400,000
$800,000
$1,200,000
$1,600,000
$2,000,000Cumulative Baseline Costs
Cumulative Current Costs
$96,018
$376,129
$770,560$1,029,677
$1,307,972
$1,584,305 $1,601,305
Baseline Costs $96,018 $280,111 $394,431 $259,117 $278,295 $276,333 $17,000
Current Costs $96,222 $230,483 $288,141 $272,679
$0
$200,000
$400,000Baseline Costs
Current Costs
Baseline vs. Current Costs and Finish Dates
Project Status
Baseline
End
Baseline
Start
Revised
Finish
Start
Date 3.0
Percent
Complete
Baseline
Cost
Current
Costs
Cost
Variance
8/2/182/15/188/2/182/15/18 3.065%$1,601,30
5$887,525 $713,780
4/18/182/15/184/18/182/15/18Project 1100% $432,080 $433,000 ($920)
4/18/183/22/184/18/183/22/18Project 2100% $189,000 $48,775 $140,225
5/11/184/19/185/10/184/19/18Project 3100% $165,000 $165,000 $0
6/12/185/10/186/21/184/19/18Project 454% $317,225 $150,750 $166,475
6/20/185/31/186/28/185/21/18Project 550% $108,000 $90,000 $18,000
7/11/186/21/187/11/186/21/18Project 60% $203,000 $0 $203,000
8/2/187/12/188/2/187/12/18Project 70% $187,000 $0 $187,000
Assign default values to toolbox symbols
It’s now possible to add default ValueSet values to a toolbox symbol. Each
symbol can include a default for any or all of the 9 available ValueSets. This
makes it easy to build DataGraphs which rely on constant values.
Show the value next to the point or bar
A new ValueSet property makes it possible to display values near the point (point and line graphs) or near the bar for a bar graph.
2016
January February March
0
35,000
70,000Billed 67,05567,055
14,50514,505 11,36511,365
0100,000200,000300,000400,000500,000Pages
218,670218,670
410,014410,014
195,975195,975
Page 1 of 1
Press Productivity - Profit Analysis
PressTotal #
PagesBilled
Cost/
Page
Total
CostNet
A 91,443 $15,232.00 $0.12 $10,973.16 $4,258.84
B 74,776 $6,500.00 $0.06 $4,486.56 $2,013.44
C 197,118 $21,005.00 $0.08 $15,769.44 $5,235.56
D 71,076 $12,077.00 $0.08 $5,686.08 $6,390.92
E 173,684 $5,611.00 $0.09 $15,631.56 ($10,020.56)
F 125,452 $16,500.00 $0.12 $15,054.24 $1,445.76
G 91,110 $16,000.00 $0.13 $11,844.30 $4,155.70
34,444 pages10,000
22,333 pages500
12,333 pages4,232
22,333 pages500
7,777 pages5,000
22,333 pages500
22,333 pages500
22,333 pages500
24,444 pages10,000
8,000 pages5,000
120,008 pages5,005
22,333 pages500
22,333 pages500
12,432 pages5,444
12,000 pages5,000
12,000 pages500
22,333 pages500
12,311 pages633
4,343 pages1,111
12,000 pages500
120,008 pages500
22,333 pages500
15,000 pages3,000
34,444 pages10,000
34,342 pages5,000
12,000 pages500
22,333 pages500
22,333 pages500
34,444 pages10,000
12,000 pages5,000
22,333 pages500
22,333 pages500
Milestones Professional 2017 New Features © KIDASA Software, Inc. October 2016 www.kidasa.com
Working wi th Microsoft Pro ject 2017
2017 New Project Interface Features
Design your own custom symbology
Custom symbology is available in 3 places.
As an option for ad-hoc import of tasks, via Link to active Project Task
Import | Let the Wizard Guide You | Custom
In the refresh dialog, used for the Append tasks option.
Whether refreshing, importing, or adding tasks to an existing presentation schedule, it’s possible to
design your own symbology set. Some examples of symbology which can be customized:
2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029
Event + month #
Event type 2 + month #
Key Project Milestonesand Events
Key Deliverables
Testing
Integration
12Key1
6Keya
7
Key2
9
Keyb
4Key3
6Key5
4 Key4
3
Keyc
6
8 Key5
3 Keyd
1
Key6
Key9
2 Key7
5 Event x 3 Event x 3 Event x 6 Event x
6Event x
11
Event x
3
Event x
7
12Event x
3 Event x
5 Event x
6
7TSSTPlan
7 Event x
7 TSST RPT
2 Event x
4 Event x
9 OT-B3
5
5 Event x
8
2 DT-B3
5 Event x
5
5Event x
2 Event x
3
12
5 Event x
6
12 DT-B4
1Event x
1
3
3 Event x
3Event x
8
3
5
Event x
5 Event132
8 Event1
3
Eventa
9
Eventb
10
6Event x
6
9Eventd
1 Event1dd
3 Event2
8
Eventc
2Event13
3
Eventf
3
Evente
5EMALS
8
7DT#1
9
3
Eventa
6 Event1d
9
10 Event4
10 Event3
4 Event6
6
Event8
3
Event7
5 Event5
7Event1b
Event + month #
Event type 2 + month #
2016
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Summary PlannedBaselineSummary
Baseline
Page 1 of 1 10/25/2016
Task Start End Status %
3/9/2016 6/7/2016 10/25/2016Baseline Start
Start Finish
Baseline Finish
2016
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Summary PlannedBaselineSummary
Baseline
Page 1 of 1 10/25/2016
Task Start End Status %
3/9/2016 6/7/2016 10/25/2016Baseline Start
Start Finish
Baseline Finish
2016
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Summary PlannedBaselineSummary
Baseline
Page 1 of 1 10/25/2016
Task Start End Status %
3/9/2016 6/7/2016 10/25/2016
2/16/2016 8/13/2016 10/25/2016
Baseline Start
Start Finish
Baseline Finish
Date1 Date2 Date3 Date4 Date5 Date6 Date7 Date8
Milestones Professional 2017 New Features © KIDASA Software, Inc. October 2016 www.kidasa.com
Working wi th Microsoft Pro ject 2017
Link to Active MS Project Task—add several tasks at once
In past versions, one Microsoft Project task could be linked via the “Link to Active MS Project task” feature. Now, groups of tasks can be selected in
Microsoft Project. Then, the link feature makes it possible to link all selected tasks at once. One option is add all dates from selected tasks to a single
row on the Milestones chart. The other option is to have Milestones add new rows for each Project task.
Add new Project tasks to Milestones more easily
When using the refresh feature, an option to “append” new tasks is available. Now, it’s possible to use a Project Flag field to indicate the tasks to be
added. Additionally, it’s possible to use a Microsoft Project Number field to specify the Milestones row for the new task(s).
Milestones Professional 2017 New Features © KIDASA Software, Inc. October 2016 www.kidasa.com
Working wi th Microsoft Exce l 2017
Excel: Smart Import and Custom Import enhanced
Importing from Microsoft Excel (or any table) is now easier than ever. Two methods
for importing have been enhanced.
Smart Import, which maps the Microsoft Excel (or table) column headings to fields in
Milestones automatically has been enhanced to:
Allow the use of a UniqueID field to tag task rows and symbols in Milestones for
future update when the table changes.
Offer a set up screen which can be used to add more flexibility to the column
naming. For example, if the spreadsheet column heading for the start date is
My Start Date, the setup screen can be used to map that to the task start date.
Custom Import, which offers field mapping using a simple two column mechanism,
has also been enhanced to allow the use of a UniqueID field.
Excel: Refresh from a Spreadsheet
it is possible to add a tag to items imported from Excel. It’s also possible to refresh a schedule using an Excel table when the dates in
the Excel table have changed.
2015
July August September October November December
Page 1 of 1 10/26/2016
TaskName%
Project 1
Research
Design
Procurement
Production
Testing
Review
Delivery
Milestones Professional 2017 New Features © KIDASA Software, Inc. October 2016 www.kidasa.com
Working wi th Microsoft Out look 2017
Outlook Import/Export
A new Outlook to Milestones wizard
makes it easy to import from Microsoft
Outlook. Bring calendar or task items in
and produce several presentation Mile-
stone charts using a simple step-by-step
wizard.
'18 '19
Q2 Q3 Q4 Q1 Q2 Q3
Presentation Timeline
Category
Category 1
Category 2
Category 3
Category 4
Category 5
Category 6
Start DemoSV
Const Finish
EV
Const
FVPS
SV Start Demo
DV
PS
SV DV
Const
FVEV
Start Demo
PS
SV Const
FVEV
DV
Start Demo
Const
PS
SV DV
FVEV
Start Demo
Const
PS
SV DV
FVEV
Start Demo
'13 '14 '15 '16 '17
IV I II III IV I II III IV I II III IV I II III
Planned Not Started Waiting on someone else
Deferred In Progress Complete
Stoplight Report
Tasks%
Comp. Status Priority
taskFolder1
Project ABC Task 3 Low
Project ABC Task 4 Normal
Project ABC Task 1 High
Project ABC Task 2 Normal
taskFolder1Subfolder1
Task 1-3 Add order 1 Normal
Task 1-1 Add order 2 Normal
Task 1-9 Add order 3 Normal
Task 1-4 Add order 4 Normal
Task 1-1 Addorder 5 Normal
taskFolder1Subfolder1
Task 1-3 Add order 1 Normal
Task 1-1 Add order 2 Normal
Task 1-9 Add order 3 Normal
Task 1-4 Add order 4 Normal
Task 1-1 Addorder 5 Normal
Task 1-1 Addorder 5 Normal
Milestones Professional 2017 New Features © KIDASA Software, Inc. October 2016 www.kidasa.com
Improved Usabi l i ty 2017
Pick your own toolbox background color
Change the color for the selected item’s background. Pick a
color that makes it easier for you to be able to see which items
are currently selected.Project task)
Show Symbol Type in Status Bar when Symbol is Selected
Now when a symbol is selected, then actual symbol will be shown in the Status Bar:
Milestones Professional 2017 New Features © KIDASA Software, Inc. October 2016 www.kidasa.com
More! 2017
Select all symbols or all tasks
In previous versions, it was necessary to hold down the Shift key to select multiple symbols. Now, once a symbol is selected there are op-
tions on the right-click menu to select all symbols of the same type or all symbols on the schedule.
Shift just selected symbols
In addition to shift all dates and shift selected tasks, it’s now possible to shift selected symbols.
Select all symbols of the same toolbox type:
Select all symbols:
Milestones Professional 2017 New Features © KIDASA Software, Inc. October 2016 www.kidasa.com
More! 2017
E n h a n c e d s u p p o r t f o r h i g h r e s o l u t i o n
m o n i t o r s
Milestones now automatically adjusts to operating on a high resolution monitor, sometimes referred to as a “4K” monitor. In the Apple
world, these are referred to as “Retina” displays.
These high resolution monitors come in such resolutions as 3200x1600, 3840x2160 etc.
Autosave Improvements
When a Milestones session exits it now only clear autosaves done by its own Process ID (PID), not any others whether they are running or not.
This should prevent an autosave entry from disappearing without the user being able to restore it. This fixes the problem of multiple Milestones
sessions running and deleting autosaved files from a crashed session before the user gets a chance at a restore.
The autosave Restore dialog now prompts the user to select an entry before OK is accepted. Before, if the user forgot to select an entry the au-
tosave files were deleted.
Also added, was a new button in the Tools | Program Options | Files and Automation screen which lets you display the current list of Autosaved
files.
New Symbol Date Format
The Time of a symbol may now be appended to the displayed symbol date. Before, it was not possible to display both date and time in the sym-
bol date display area. Show time using 12 hour or 24 hour formats. Optionally, choose to append “AM” and “PM.”
Milestones Professional 2017 New Features © KIDASA Software, Inc. October 2016 www.kidasa.com
Samples 2017
2016 2017 2018
M J J A S O N D J F M A M J Jul Aug Sep Oct Nov Dec J F M
Watch
OK
Ahead
Actual Hours 75 150 75 250 175 175 175 100 175 125 300 350 175 200 300 200 150
0
200
400Actual Hours
Maximum Hours
100
200
100
300
200 200 200
150
200
150
350
400
200 200
300
250
300
400
250
350
200
Minimum Hours
Monthly Review
Integration Master Phasing Schedule
MajorMilestones
Design
Testing
5
Request
21
PDR
27
CDR HW
19
CDR SW
22
Asm 16
ReAsm
11
Demo
23
Demo 8
TI
20
TI
28
ReAsm
26
TI
10
Demo
Prelim Design
Complete
Design Integration Prove In Prep
31
TR
R
Prelim Design
Complete
Design Integration Prove In Prep
31
TR
R
Prelim Design
Complete
Design Integration Prove In Prep
31
TR
R
124
1
1422
30
1310
5
1717
10
615
31
219
3
2130
4
2412
30
2119
27
1329
9
274
26
1714
3
1427
31
M J J A S O N D J F M A M J Jul Aug Sep Oct Nov Dec J F M
Watch
OK
Ahead
LEGENDCDRHW- Critical Design Review HardwareCDRSW-Critical Design Review SoftwarePDR-Preliminary Design ReviewTRR-Test Readiness ReviewTI-Test IntegrationAsm-AssembleReAsm-Reassemble
Deploy Expand Renew
Deploy Expand Renew
IIQ sold
CSMengages
status calls
monthly newsletter
Executivetouchpoint(strategic accounts)
CustomerGo Live
survey
Executivetouchpoint(strategic accounts)
Director levelCheckpoint
(key accounts)
Executivetouchpoint(strategic accounts)
Director levelCheckpoint
(key accounts)
survey
Executivetouchpoint(strategic accounts)
Director levelCheckpoint
(key accounts)
renewal
•account background•business drivers•key contacts•license info•partner info
Sales debriefs CSM
a) CSM updates SalesForceto ensure support is awareof critical Go Live period
b) Post Go live, CSM captures key data points & updates SalesForce
CSM updates SalesForce
CSM ensures proper customer contactreceives renewal quote well in advance
of software renewal expiration date
Renewal
Topics covered:•license overview•support best practices•services overview•reference program•customer success plan
CSM customer intro meeting
*For Strategic Key accounts only
Assigned SailPoint executivecontacts client executive to:•celebrate key wins•build relationship•understand concerns
TouchpointsExecutive and Director level
CSM engaged earlier in the lifecycle tolessen customer confusion & provideadditional project oversight
Topics covered:•open cases•current/future objectives and status•key SailPoint news
CSM status calls begin
Handoff/debrief step from Sales to CSM added
Key SalesForce datapoints captured earlier in the lifecycle
Life
cycl
e m
ilest
on
es
Pro
cess
bre
akd
ow
n
IIQ Customer Lifecycle - Strategic Account - Year 1
IMPROVEMENTS
2017 2018 2019 2020 2021
J A S O N D J F M A M J J A S O N D Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec J F M A M J J A S O N D J F M A M J
Project Roadmap
PROPOSAL
10/2511/9
HMU AVAIL
1/6
Task 1-19/7
1st FLIGHT
7/18
H/W FCA/PCA
S/WFCA/PCA
1/16CRB PHASE III6/12
SYST.
GOVERNMENT
5/25
PROG AUTH
5/4
NEGOTIATION
5/18
FCA/PCA
12/26
DELTA PDR
4/17
Task 2-12/7
LONG LEAD AUTH.5 A/C
8/1
H/W CRB
2/6
LRIP KIT1 MAINT. VAN1/21
RR / SSR
5/26
PDR
8/11
CDR
11/10
DELTA RR/SSR6/27
Task 3-1
TOOLING
1/22
DELTA CDR10/8
TIM #1
6/22
TIM #2
8/24
TIM #3
10/19
TIM #4
12/21
TIM #5
2/22
TIM #6
4/25
TIM #7
6/20
TIM #8
9/5
TIM #9
11/7
TIM #10
9/6 11/9
6/15
L/L AMO
9/7FSDAMO
11/26
TKI
1/8
FSD 90%
5/11
TKI 90%
3/24 3/12RETRO START
INCORP. CHGS.
3/4 6/7
1/7
4/25 8/7
RETRO. GO-AHEAD
PREP. F/F NEGOTI.10/20
GO-AHEAD2/5 8/11
IMPACT ASSESSMENT
4/15 8/16 4/11
DEFINE & TRADES PREPARE GOVN PROCURE/DEVEL - FAB - INTEG - TEST
H/W FCA/PCA11/22 1/21 5/26 8/13 11/9 1/8 2/22
RA PD DD S/W DEV INT T&E
A/C GROUND TEST4/12
S/W MERGE11/22 1/21 5/26 8/11 12/14 1/25 4/12
RA PD DD S/W DEV INT T & E7/13 8/21 10/11
9/7 11/10
DD DEV INT T & E
12/13 3/14
RA PD DD S/W DEV INT T & E
5/11
S/W DEV INT T & E
11/22 2/21 4/24 8/149/7 11/10 2/9 5/11 7/13 8/19 10/11
RA PD DD DEV INT T & E
12/13 3/14
DEV INT T & E
5/3 8/14
7/13
DEV INT T & E
11/22 2/2110/11 3/24 8/14 12/8
Milestones Professional 2017 New Features © KIDASA Software, Inc. October 2016 www.kidasa.com
Samples 2017
2016
July August September
Status Marker Summary Task Duration
$0
$8,000
Earned Value $62$141$141
$354$354
$838$838
$1,357$1,357
$2,351$2,351
$3,590$3,590$3,763$3,763
Budget
$88$207$207
$517$517
$1,133$1,133
$1,786$1,786
$2,868$2,868
$4,167$4,167
$5,423$5,423
$6,777$6,777
$7,100$7,100
Earned Value Report with Budget and Actual Costs%
Comp.
Project /
Task
FACWP
(Actual Cost)
EV
(Earned Value)
BAC
(Budget)
60% Project ABC $3,585 $3,762 $7,100
71%Task 1 $200 $213 $300
52%Task 2 $350 $208 $400
66%Task 3 $175 $164 $250
73%Task 4 $710 $943 $1,300
62%Task 5 $500 $451 $725
81%Task 6 $100 $181 $225
53%Task 7 $200 $185 $350
65%Task 8 $1,200 $1,154 $1,775
48%Task 9 $150 $264 $550
0%Task 10 $0 $0 $800
0%Task 11 $0 $0 $425
Status Marker Summary Task Duration
3Q'19 4Q'19 1Q'20 2Q'20 3Q'20 4Q'20
July August September October November December Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Detailed Schedule with "Logarithmic" date headings
Phase 1
Phase 1 Milestones
SOW for Phase 1
Task 1.
Task 2.
Task 2-1
Task 2-1-1
Task 2-1-2
Task 2-2
Task 2-3
Task 3.
Task 4.
Task 5. Final Report
Task 6. Working Group Meetings
7/26
9/13
Funding
9/16Supplemental
Funding
7/18
12/7
7/18 1/10 7/4
7/18
8/31 6/26
7/18
8/31 6/26
7/18
8/31 8/11
7/18
8/31 6/16
8/20 8/31
1 2 3 4
6/24
8/20 8/31
1 2 3 4
6/4
7/18 1 2 3 4 5 11/18
9/18
1 2 3 4
7/1
1/21
6/10
3Q'19 4Q'19 1Q'20 2Q'20 3Q'20 4Q'20
7/26
No. 1
8/30
No. 2
10/8
No. 3
11/23
No. 4
3/13
No. 5
C:\Users\suebutler\Documents\KIDASA\Development\2017\best schedules\Detailed Schedule with Logarithmic date headings.mlg