Dollo-Ado Shelter Project

Post on 16-Apr-2017

21 views 0 download

Transcript of Dollo-Ado Shelter Project

International Organization

for Migration

Objective………..

Construction of 1145 Transitional shelters

for the Year 2013

Funding source :- UNHCR / DFID

Brief description about IOM

Shelter design

Floor area - 6.0mx3.5m=21.0Sqm

Wall Height - 2.4m

Ridge Height - 3.4m

Main components of the shelter………

Eucalyptus timber frame work

Bamboo walling

CGI sheet roofing

Floor Plan of the shelter

Sequence of operation in shelter

construction……….

At workshop….

Preparing timber columns and components

for frames.

Preparing roof trusses .

Preparing doors and windows .

Slicing bamboo poles .

Preparing timber columns and

components for frames.

Preparing timber columns and

components for frames.

Preparing roof trusses

Preparing doors and windows

Slicing bamboo poles

Sequence of operation in shelter

construction……….

At site…..

Setting out and column erection.

Fabricating timber Skelton.

Fixing roof trusses.

Attaching bamboo slices.

Roofing

Fixing door and windows

Setting out and column erection

column erection

Fabricating timber Skelton

Attaching bamboo slices

Roofing

Materials and prefabricated items

delivered to the site for shelter

construction…..

From Workshop….

Transporting shelter components to

the site……

Materials and prefabricated items

delivered to the site for shelter

construction…..

From Store….

Quality Control monitoring…….

At workshop…….

Quality Controlling at workshop…...

Quality Control monitoring…….

At site….

Shelters completed per Zone

. ZONE # OF SHELTERS COMPLETED

ZONE A 26

ZONE B 69

ZONE C 51

ZONE D 51

ZONE E 54

ZONE F 29

ZONE G 35

ZONE H 50

ZONE I 55

ZONE J 59

ZONE K 62

ZONE L 56

ZONE M 50

ZONE N 54

ZONE O 77

ZONE P 73

ZONE Q 100

ZONE R 70

ZONE S 64

ZONE T 70

TOTAL 1155

Monthly Progress-2013

MELKEDIDA SHELTER CONSTRUCTION

PROGRAM & PROGRESS-2013

0.0

100.0

200.0

300.0

400.0

# O

F SH

ELTE

RS

ORIGINEL PROGRAM 100.0 120.0 140.0 140.0 140.0 140.0 140.0 140.0 85.0

PROGRESS 54.0 108.0 105.0 67.0 56.0 120.0 102.0 197.0 346.0

Apr- May- Jun- Jul-13 Aug-1 Sep- Oct- Nov- Dec-

A tool using to find the impact of IOM shelters and gathering beneficiary

details

Major challenges Encountered

Delay in Commencement of the project

Failure in supplying the materials in time by local

suppliers from Dollo-Ado

Poor quality materials by the local supplier

Delay in material supply due to road taxation

Delay in supplying the materials due to rain in

November.

Road condition between Dollo and Melkedida

THANK YOU