j Daily Report Summary

Date: 05 Nov 2012

# Name of the Inspector /Safety Engineer

Project No Name Of the Contractor

Purpose of the Visit

Summary Of the safety Deficiencies/ Issues

1 Mohammed Jai Sujiya Khan

PIC A 1093A MASCO Regular Inspection

Excavation, Housekeeping, Heavy Equipment, PPE, Positive Observations.

2Kashirajyam Kammari

3 Fernando Q. Uligan

PIC G 1507C Samama Regular Inspection

Ladder, Work platform, Electrical, Open manhole, PPE and Housekeeping.

4 Reynaldo C. Pulgo

PIC G 1626 BULGU Regular Inspection

Electrical Hazard, PPE, Scaffolds, Barricades and Signage