Post on 03-Jul-2020
Robotics Evaluation FrameworkCIFE SEED RESEARCH UPDATE I
Cynthia Brosque
Martin Fischer
11/7/2018
Motivation & Background Case Study 1 Case Study 2 & Next Steps
• What are the repercussions of using a robot on site? What are the potential benefits?
• What are the planning activities and workflow required?
• What are the safety and quality differences?
• How does it affect decision making?
• How many product, organizational, and process boundaries have to be crossed to make a robot cost- and schedule-effective?
Research questions
Motivation & Background
Analysis method
Motivation & Background
5
Case Study 1
Motivation & Background Case Study 1
• What are the repercussions of using a drilling robot on site? What are the potential benefits? -40hs, +$29K
• What are the planning activities and workflow required? Collect design information, automate hanger-placement, and clash detection (+10d)
• What are the safety and quality differences? 98% reduction on muscle strain hs, -50 clashes
• How does it affect decision making? Until 1 day before to make changes
• How many product, organizational, and process boundaries have to be crossed to make a robot cost-and schedule-effective? 4 main boundaries
Research answers
Motivation & Background Case Study 1
EXTRA COSTCHANGES IN WORK PROCESS ANDCOORDINATION TIME
INCREASE LEVEL OF BIM DEVELOPMENT
ORGANIZATION CHANGES (PROJECT PARTICIPANTS)
Social acceptance of technologyAvailability of human resources
Automation benefits:Safety and qualityCalendar time reduction (scale)
Technical feasibility Extra clash detection and prefabrication
Faster installation (33% reduction thanks to pre-drilled holes)Predictability
MANUALROBOT
Motivation & Background Case Study 1
Product, process, and organizational barriers
Lack of manual drilling metrics
Variability
• Drilling and installation rework• Overtime work• Number of clashes• Percent plan complete
• Waiting time to access a zone• Sequencing and use of resources• % manual rework • Adoption of new technology• Project zones and accessibility• Diameters used for robot
Observed analysis challenges
Motivation & Background Case Study 1
1. Shorten the effort and duration for coordination of robot work
2. Consider the scale of the project and the key benefit for automation (shorter duration, safety, quality, reliability, other?)
3. Obtain benchmark data of manual and robot work to back-up the decision
Recommendations
Motivation & Background Case Study 1
How general is this information and this approach to analyze other types of robots?
1 2
3
4
6 7 8 9
1. nLink concrete drilling robot2. Taisei automatic façade coat and paint applier 3. Construction Robotics SAM 100 semi-automated brick laying robot 4. Taisei Corporation and University of Tsukuba T- iROBO slab finisher5. Drywall robot Build-R6. Tsukuba University Hal exoskeleton7. Tokio University of Science muscle suit8. NEDO project teleoperation of construction machines9. Built Robotics self-driving excavator
5
Motivation & Background Case Study 1 Case Study 2 & Next Steps
Information:Structures and architecture BIM updated until one day before
Robotic operation:Lift and fasten tool Battery powerMachine vision identification (QR code at mm level)Intelligent navigation system (10cm tolerance)Robot operator and site cutting crew
Limitations:Installation of full boards (90cm x 250cm) only - cutting not integratedInstallation of ceiling not possible yet
Case Study 2
Motivation & Background Case Study 1 Case Study 2 & Next Steps
Next Steps
Case Study 1:Drilling robot
completed
Case Study 2:Drywall robot
completed
Case Study 3:…
completed
Analysis and comparison of cases finished
Existing research of robotics in construction studied and analyzed
Existing manufacture evaluation frameworks studied
Robotics Evaluation Framework
developed and validated
Motivation & Background Case Study 1 Case Study 2 & Next Steps
Questions?