Continuous Flow Hybrid Intersection Indian River Road and ...€¦ · Continuous Flow Hybrid...

Post on 08-Aug-2020

4 views 0 download

Transcript of Continuous Flow Hybrid Intersection Indian River Road and ...€¦ · Continuous Flow Hybrid...

Continuous Flow Hybrid Intersection Indian River Road and Kempsville

Road Improvements City of Virginia Beach

Taha Ataya, P.E.

Senior Project Manager Transportation Division

July 12, 2012

UCI Annual Meeting

Current Conditions

Most congested intersection in the City.

Access and maintenance issues.

105,000 Vehicles Per Day

Signalized Intersections - V/C Rank

-120%

-70%

-20%

30%

80%

1 7 13

19

25

31

37

43

49

55

61

67

73

79

85

91

97

103

109

115

121

127

133

139

145

151

157

163

169

175

181

187

193

199

205

211

217

223

229

235

241

247

253

259

265

271

277

283

289

295

301

307

313

319

325

331

337

343

Nee

ded

Cap

acity

E

xces

s C

apac

ity

Capacity of Signalized Intersections

Excess Capacity

Needed Capacity

Volume / Capacity = 1.0

Indian River at Lake James

Indian River at Centerville

Indian River at Kempsville

Volume / Capacity = 1.0

Indian River at Kempsville

Indian River Road-Kempsville Road

Balancing Needs

Three traditional options to address the problem: 1. Lane additions at grade. 2. Grade separated interchanges. 3. No build.

Or

Consider an innovative approach: 4. Non-traditional improvement.

Traditional Improvements – At Grade – Lane Additions

Large footprint.

Needs extensive Right of Way.

Expensive, and disruptive.

Estimated at $37 Million.

Traditional Improvements – Grade Separated – Interchanges

Large footprint.

Needs extensive Right of Way.

Eliminates access

Estimated at over $60 Million.

Traditional Improvements – No-Build Option

Does not address problems.

Does not meet future needs.

Stifles commerce.

Impacts quality of life.

Unacceptable congestion.

Hybrid design of two non-traditional solutions.

Minimize right of way and cost.

Maximize traffic flow.

Estimated $10.4 Million

Proposed Alternative – A Non-Traditional Improvement

Intersection Design – Typical Signal

Four typical phases: two through and two turns.

Each phase requires green time and a short clearance time.

Best to eliminate phases when possible.

X X

Median U-Turn on Indian River Road

To Make A Left From Indian River to Kempsville

Time Shared - Greater Green Time Available To Both Movements Simultaneously

Displaced Left Turn on Kempsville Road

To Make A Left From Kempsville to Indian River

Greater Green Time Available To Both

Movements Simultaneously

Moving Forward

Total estimated cost for the project is $10.4 million.

Project is funded with City and Federal Congestion Mitigation and Air Quality funds.

No other option provides the level of improvements for the cost.

Project Development Milestones

Phase Cost Begin End

Design $ 984,000 Ongoing Spring 2013

Right of way $ 3,500,000 Winter 2012 Spring 2014

Utility relocation $ 525,000 Spring 2014 Fall 2015

Construction $ 4,500,000 Fall 2015 Fall 2016

Street lighting $ 150,000 Spring 2016 Fall 2016

Contingencies $ 750,000 Spring 2013 Fall 2016

Total $ 10,409,000

Project Status

1. Approaching 60% Design.

2. Project is fully funded with CMAQ and City funds.

3. NEPA process is ongoing: Phase I ESA complete.

4. Citizen Information Meeting complete.

5. Design & Location meeting November 2012.

September

UCI Annual Meeting

July 12, 2012