Concept of Super Grid in Northeast Asia

Post on 13-Feb-2017

223 views 0 download

Transcript of Concept of Super Grid in Northeast Asia

Results of Feasibility Study on Super Grid in Northeast Asia

Asia Super Grid Workshop

JW Marriott Hotel, Seoul, 25 May, 2016

International Consortium of Super Grid Korean Consortium for Super Grid in NEA

Jinsoo Song

Distinguished Professor, Silla University

Concept of Super Grid in Northeast Asia

Wind Photovoltaic

Hydro Biomass

Participating Countries : Korea, China, Mongolia, (Japan) Core Technologies Large Scale RE power generation in Gobi desert ESS, WAMS, HVDC Electricity transmission through connected grid to neighboring country

Experiences

Domestic Installation

1990 2000 2010 1980

Collaborative Projects in Northeast Asia

2003 : Mongolia (Gobi Desert) 2004 : China(Tibet) 2002 : Vietnam (HCM City)

Agreements for Int’l Consortium

27-28th November, 2012 (Jeju,Korea)

6th November, 2012 (Ulaanbaatar, Mongolia)

8

Korea-Mongolia(August 2014)

MOU for Feasibility study on Super Grid

Korea-China(September 2014)

Japan

Mongolia

China

Korea hybridization & integration

HVDC & construction

maintenance & operation

Int’l Consortium: KCSG, MSASG, CRES

Nat’l Consortium: KEPCO, KT, KIER, KSNRE, Universities & Industries

Job description for Super Grid in Northeast Asia

1st International Joint Workshop

25-26 June, 2015

Mongolia National University Ulaanbaatar, Mongolia

2nd International Joint Workshop & Round Table Discussion

5-7 November, 2015

Lotte Hotel, Jeju, Korea Grand Hotel, Busan, Korea

Progress of Feasibility Study

Site Selection - Candidates for FT & Demonstration, Super Grid in Gobi desert

Analysis of Status - Technologies, Transmission

On-site Survey - Meteorological, Geological & Topographical survey

Basic Design - Lay out of FT & Demonstration site for the next stage

Expectations -Technology, Economy, Socio-Environment

Candidate Sites for Demonstration & Construction

Site #1: 42°38'54.84“N/107°18'7.82"E (Umnugovi province, Khanbogd Soum) Site #2: 44°28'4.98“N/111° 7'9.07"E (Dornogovi province, ErdeneSoum) Site #3: 46°22'8.54“N/108°22'16.32"E (Govisumber province, Choir Soum)

Layout of Demonstration Site

Milestone with Action plan

2015 2020 2030

1st Feasibility

Study

2nd FieldTest/

Demonstration

3rd

Engineering/Procurement/

Construction(EPC)

4th Deployment

1st Phase(2014-2015) : Feasibility Study

• Selection of candidate sites • Meteorological & topographical survey • Basic design for the next phase

2nd Phase(2016-2020) : Field Test/Demonstration

• Test-bed construction, performance test • Master plan completion

3rd Phase(2021-2030) : Engineering/Procurement/Construction(EPC)

• Financing & scale-up construction • Operation & maintenance

4th Phase(2031- ) : Deployment

• Extension to Asia, Africa & America, and finally to Global Grid

Conceptual Image of Super Grid

Electrical Transmission to Neighboring Countries

Conclusion

After successful feasibility study, discuss with participating countries about construction of field test & demonstration site and Super Grid as next stages Strongly recommend to each Governments for political decision and financial support Cooperate with other countries and organization to realize the dream project based on trust and consensus