Barton Elementary School Community Meeting

May 24, 2018

Presented by Alan Reising, Executive Director

Facilities Development and Planning

Long Beach Unified School District

MEASURE E - PLANNING

Ø June 16, 2016, LBUSD Facility Master Plan updated §  $3.5 Billion of need identified

Ø June 23, 2016, LBUSD Board approved a $1.5 billion

bond measure for ballot

Ø November 8, 2016 voters approved Measure E with a 75% Yes vote

Ø Measure E will only cost $5 per $100,000 of property value per month

2

History

Long Beach Unified School District

MEASURE E - PLANNING Areas Addressed

Ø HVAC System Installation Ø Utility Upgrades Ø ADA – Accessibility Upgrades Ø Elevators Ø Fire Alarm Upgrades Ø Intercom, Clocks, Speakers (Measure K) Ø Ceiling/Wall Mounted Projectors/AV System Ø Ceiling Repair Ø Interior Lights Ø Interior and Exterior Painting Ø New windows Ø Other State Funded Repairs

Ø Potential for $300M in matching funds

3

Long Beach Unified School District

MEASURE E - PLANNING Track and Field Upgrades

Ø New Synthetic/All-Weather Field

Ø New Synthetic Running Track

Ø Bleacher/Stadium Upgrades or

Replacement

Ø ADA Upgrades

Ø Lighting Upgrade or Installation

4

Long Beach Unified School District

MEASURE E - PLANNING New Aquatic Centers

5

Ø New 50 M x 25 YD Competition Pool

Ø New Shower/Locker Room Facilities

Ø New Restrooms

Ø Aquatic Coaches Offices

Ø Spectator Bleachers

Long Beach Unified School District

MEASURE E - PLANNING Interim Housing

InterimHousingSites

Monroe

Ke6ering

Riley

Prisk

JordanPlus

Butler

Rogers

Webster

6

Long Beach Unified School District

MEASURE E - PLANNING

7

Planning Process (Continuous)

Phasing Plan

Phase 3 Begin Summer 2018 Phase 4

Begin Summer 2019 Phase 2

Begin January 2018

•  Cleveland – HVAC •  Garfield – HVAC •  Kettering – HVAC •  Riley – HVAC •  Rogers – HVAC •  Stephens – HVAC

•  Barton – HVAC •  Burcham – HVAC •  Jefferson – HVAC

•  Keller – HVAC •  Lakewood – HVAC •  Lindsey – HVAC •  Longfellow – HVAC •  Lowell – HVAC

•  MacArthur – HVAC •  Mann – HVAC •  McKinley – HVAC •  Millikan – New 1000 Bldg. •  Poly Bleachers •  Prisk-Interim Housing

•  Webster – HVAC

•  Alvarado – HVAC •  Bixby – HVAC •  Cubberley – HVAC •  Hughes – HVAC •  Madison – HVAC •  Muir – HVAC •  Naples-HVAC •  Prisk-HVAC •  Wilson – HVAC

Long Beach Unified School District

MEASURE E - PLANNING

87

Barton ES Construction Plan

Ø All students TK-5th grade will stay on site

Ø HVAC project expected to start in Summer 2018 and be completed in 12 months

Ø  Support spaces such as kitchen/cafeteria, and administration to be completed during summer time

Ø Working Hours: Monday through Friday 7:00 AM to 4:30 PM

Long Beach Unified School District

MEASURE E - PLANNING

9

Barton ES– Aerial

Long Beach Unified School District

MEASURE E - PLANNING Project Team

10

Architect: GBA

Mechanical/Plumbing Engineer: Pocock Design Solutions

Electrical Engineer: Pacific Engineers Group

Contractor: Tilden-Coil Constructors

Long Beach Unified School District

MEASURE E - PLANNING

11

Potential Project Concerns

Ø Safety and Security

Ø Traffic Congestion

Ø Construction Dust / Noise

Ø Drop off and Parking

Long Beach Unified School District

MEASURE E - PLANNING Typical Construction - Site

12

New ADA Ramp Compaction

Underground Conduit

New Mechanical Equipment

New Window Installation

Long Beach Unified School District

MEASURE E - PLANNING

13

Typical Construction - Site

Before After

Long Beach Unified School District

MEASURE E - PLANNING Typical Construction - Corridor

14

Finished Corridor

Long Beach Unified School District

MEASURE E - PLANNING Typical Construction - Classroom

15

Finished Classroom

Long Beach Unified School District

MEASURE E - PLANNING Typical Construction - Restroom

16

Bathroom Demolition

New Restroom Fixtures Partitions New Drinking Fountain

New Restroom Tile

Long Beach Unified School District

MEASURE E - PLANNING

17

Typical Completed Exterior

Long Beach Unified School District

MEASURE E - PLANNING Move Details

18

They make frequent visits to each classroom to address packing questions

Movers will move all packed items

BartonElementarySchoolFriday,June15,2018

AKerSchoolDismissal

Long Beach Unified School District

MEASURE E - PLANNING Bell Schedule

19

BellScheduleRemainstheSame