A Status Report On Singur Total land acquired: 997.11 acre Mouzas involved: Beraberi Gopalnagar Singherbheri Bajemelia Khaserbheri Land details:
Name of Mouza Total area of the Mouza (in
acres)
Land acquired in the Mouzas (in acres)
Gopalnagar 1656.55 399.98 Beraberi 1043.82 327.21 Khaserbheri 229.62 180.68 Bajemelia 355.13 47.77 Singherbheri 310.75 41.47 Total 3595.87 997.11
Land Acquisition compensation to owners: Sali Land: Basic Price: Rs. 6.02 Lakh per acre Amount paid: Rs. 8.60 Lakh per acre1 Suna Land:
Basic Price: Rs. 8.92 Lakh per acre Amount paid: Rs.12.76 Lakh per acre2 Land Acquisition compensation to recorded bargadars: The total number of recorded bargadars (according to Collector): 237 25% of the total compensation (including crop compensation) paid to the recorded bargadars. Unrecorded Bargadars: According to local enquiry, the total number of unrecorded bargadars is about 170. Till date 60 such unrecorded bargadars have applied to Collector requesting that they be considered for some compensation to be paid to them.
1 On basic price, solatium @ 30%, Interest (@12% per annum) for 3 months 3% and consent award 10% i.e. 143% of the basic price and in addition to that crop compensation 2 On basic price, solatium @ 30%, Interest( @12% per annum) for 3 months 3% and consent award 10% i.e. 143% of the basic price and in addition to that crop compensation
3
Land Acquisition compensation: Total compensation payable: Rs. 131.49 crore
LA Compensation Bargadars Mouza Total (Rs. in Lakh) Total (Rs. in Lakh)
Total (Rs. in Lakh)
Beraberi 4,148.84 24.61 4,173.45 Khaserbheri 3,765.90 11.81 3,777.71 Singherbheri 743.34 1.85 745.19
Bajemelia 429.88 2.13 432.02 Gopalnagar 3,997.02 23.58 4,020.60
Total 13,084.98 63.99 13,148.96
Disbursement till 2nd December 2006: Rs. 76.64 Crore Number of persons to whom disbursement has been made: 9020 Area of land in respect of which payment has been made: 635 acres Bargadars who has received payment: 88 Compensation amount disbursed to recorded bargadars: Rs. 17 lakh Total Disbursement yet to be made: Rs.54.85 Crore Persons yet to receive payment: 3000 (approx) Consent Status: Pre award: Raiyati consent: 548 acre Factory consent: 38 acre Vested Land: 34 acre Total: 620 acre Post award consent till 4th December 2006: 332 acre Total consent till 4th December 2006: 952 acres
4
Rehabilitation and Training Program at Singur WBIDC camp office:
The camp office has been opened on 11th October 2006. The office is located within the
acquired land. Till 2nd December 1372 landlosers and 443 landless workers have been
enrolled in the office with details as under:
Category Total Men Women
Landlosers 1372 1050 322
Landless workers 443 405 38
Training programs initiated: Belur Math Ramkrishna Shilpa Mandir
179 landlosers are undergoing training at Belur Math Ramkrishna Shilpa Mandir in the following
trades:
Trade No of Trainees
Machinist 42
Welding 31
Two & Three Wheeler Repairing 2
Automobile Repairing 77
House Wiring & Electrical Gadget Repairing 27
Total 179
The total training program is of four months duration. In the second phase of the training
program, another 180 landlosers would be sent for training of which 146 would be graduate. 3
Other Training :
In addition to above program steps have been taken to start the following programs: 4
Trade No of Trainees Training Agency Starting date Tailoring 40(women in 2
batches) Singer India Ltd (duration : 6 months)
6th December 2006
Catering 25 (women) Institute of Hotel Management Catering, Technology & Applied Nutrition (duration: 4 weeks
19th December 2006
Mason 40 (landless labourers) CII (ER) (through its members) Machinist 10 CII (ER) (through its members) Security guard
60 (in 3 batches) G4/ Security Agency
3 The entire training cost is being borne by WBIDC 4 The entire training cost is being borne by WBIDC
5
Community Development works undertaken and proposed: Drinking water: 63 tubewells have been repaired / installed in Gopalnagar (27 tubewells), Beraberi
(24) and K-G-D (12) Gram Panchayets. School Repair: Beraberi High School has been repaired and upgraded for vocational training by
Singer India in sewing. Road Improvement: Initial work for road improvement has been initiated. The works for widening and
strengthening the road used by the local villagers from National Highway to Kamarkundu station would be taken up next week.
Re-excavation of Julkia Canal: Survey work for re-excavation of Julkia canal has been completed. Rehabilitation
of this canal would improve the irrigation potential of adjoining lands as well as facilitate drainage of the entire area. Drainage channels are also being planned within the villages to reduce waterlogging during monsoon.
Irrigation facility : It has been proposed to install 4 to 5 deep tube wells in the area to improve the
cropping intensity of the adjoining area. Mandays generated: All the works are being executed with local labours mostly landless agriculture
workers and landlosers. Till date about 2000 mandays have been generated through the above community works taken up with the active help of local Panchayet Samity and all 3 Gram Panchayets.
In addition, the work of fencing the entire land is being executed with local landless agriculture workers and landlosers and about 5500 mandays have been generated till 5th December 2006.
Total Expenditure:
On account of various community development work, about Rs. 10 lakh has been expended till date on account of wage payment.
6
Classification of land5:
Mouza wise classification of Land Acquired at Singu r in Hooghly District
Mouza Path/ Rasta
Sali6 Suna Others TOTAL
Beraberi 1.71 292.74 19.37 13.39 327.21 Khasherberi 0.00 161.05 8.13 11.50 180.68 Singherberi 0.00 29.36 2.58 9.53 41.47 Bajemelia 0.02 46.91 0.00 0.84 47.77 Gopalnagar 0.00 370.14 6.49 23.35 399.98
Total 1.73 900.20 36.57 58.61 997.11
Mouza Danga Khal/ Nala
Mandir/ Debottar Viti/ Bastu Shashan
Bash bagan N.Juli
Doba/ Pukur Bandh Bagan Others
Beraberi 0.93 0.49 0.20 0.87 0.00 1.13 0.00 4.97 1.73 3.07 0.00 13.39
Khasherberi 0.00 0.04 0.00 0.00 0.26 0.09 0.20 3.76 0.39 6.76 0.00 11.50
Singherberi 0.12 2.49 0.00 0.00 0.00 0.00 0.00 2.38 0.05 4.49 0.00 9.53
Bajemelia 0.00 0.08 0.03 0.00 0.00 0.00 0.00 0.00 0.00 0.67 0.06 0.84
Gopalnagar 0.70 0.00 0.00 0.00 0.00 0.00 0.15 5.40 4.49 12.45 0.16 23.35
Total 1.75 3.10 0.23 0.87 0.26 1.22 0.35 16.51 6.66 27.44 0.22 58.61
Mouza Path/ Rasta Sali Suna Others TOTAL
Beraberi 0.52% 89.47% 5.92% 4.09% 100.00% Khasherberi 0.00% 89.14% 4.50% 6.36% 100.00% Singherberi 0.00% 70.80% 6.22% 22.98% 100.00% Bajemelia 0.04% 98.20% 0.00% 1.76% 100.00% Gopalnagar 0.00% 92.54% 1.62% 5.84% 100.00%
Total 0.17% 90.28% 3.67% 5.88% 100.00%
5Initiative to exclude more fertile land: Initially land Area proposed for acquisition was 1053 Acres. Subsequently 175.57 Acres in two mouzas were taken out from initial proposal and another additional 119.68 Acres was added to initial area identified making the revised proposal for land acquisition for an area of 997.11 Acres. The details is given below: Mouza Wise Summary:
Name of Mouza
Initial Identified Area(Acres)
Land Excluded
Reason for exclusion Land Added
Reason for addition
Present Land
Gopal Nagar 526 126.02 Command area of Deep Tubewell
399.98
Bajemelia 86 38.23 Land in or around habitated area
47.77
Beraberi 208 119.21 Less fertile land
327.21
Khaserberi 192 11.32 180.68 Singerberi 41 0.47 41.47 Total 1053 175.57 119.68 997.11 6 Includes factory land of 38 acres
7
Singur Block Profile: Total area: 156.30 sq. km 39075 acres Total number of Mouzas: 109 Total Population: 216827
Demographic Profile of Five Mouzas
NAME
TOTAL HOUSE HOLD
INDUSTRY WORKER
MAIN
TOTAL HOUSE HOLD
INDUSTRY WORKER
MALE
TOTAL HOUSE HOLD
INDUSTRY WORKER FEMALE
MAIN OTHER POPULATION
MAIN OTHER POPULATION
MALE
MAIN OTHER POPULATION
FEMALE
Beraberi 115 13 102 1231 1150 81 Sinher Bheri 143 39 104 192 177 15 Khaser Bheri 17 13 4 118 113 5
Baje Melia 40 23 17 773 690 83
Gopalnagar 376 193 183 2161 2013 148
Total 691 281 410 4475 4143 332
NAME MARGINAL WORKER
POPULATION
MARGINAL WORKER
MALE
MARGINAL WORKER FEMALE
Beraberi 230 53 177
Sinher Bheri 59 15 44
Khaser Bheri 6 0 6
Baje Melia 233 84 149
Gopalnagar 506 356 150
Total 1034 508 526
NAME TOTAL MAIN
WORKER
TOTAL MAIN
WORKER MALE
TOTAL MAIN
WORKER FEMALE
TOTAL CULTIVATOR
MAIN
TOTAL CULTIVATOR
MALE
TOTAL CULTIVATOR
FEMALE
TOTAL AGRI
WORKER MAIN
TOTAL AGRI
WORKER MALE
TOTAL AGRI
WORKER FEMALE
Beraberi 2177 1886 291 344 322 12 487 391 96 Sinher Bheri 630 440 190 188 153 35 107 71 36 Khaser Bheri 254 241 13 77 73 4 42 42 0
Baje Melia 1069 965 104 167 165 2 89 87 2
Gopalnagar 3580 3162 418 544 508 36 499 448 51
Total 7710 6694 1016 1320 1221 89 1224 1039 185
8
NAME
MARGINAL CULTIVATOR POPULATION
MAIN
MARGINAL CULTIVATOR
MALE
MARGINAL CULTIVATOR
FEMALE
MARGINAL AGRI
WORKER POPULATION
MAIN
MARGINAL AGRI
WORKER POPULATION
MALE
MARGINAL AGRI
WORKER POPULATION
FEMALE
Beraberi 22 13 9 54 29 25 Sinher Bheri 24 2 22 12 6 6 Khaser Bheri 0 0 0 1 0 1
Baje Melia 78 29 49 9 7 2
Gopalnagar 32 24 8 279 239 40
Total 156 68 88 355 281 74
NAME
MARGINAL HOUSE HOLD
WORKER POPULATION
MAIN
MARGINAL HOUSE HOLD
WORKER POPULATION
MALE
MARGINAL HOUSE HOLD
WORKER POPULATION
FEMALE
MARGINAL OTHER
WORKER POPULATION
MAIN
MARGINAL OTHER
WORKER POPULATION
MALE
MARGINAL OTHER
WORKER POPULATION
FEMALE
Beraberi 137 3 134 17 8 9 Sinher Bheri 13 0 13 10 7 3 Khaser Bheri 4 0 4 1 0 1
Baje Melia 16 2 14 130 46 84
Gopalnagar 74 18 56 121 75 46
Total 244 23 221 279 136 143
NAME NON
WORKING POPULATION
NON WORKING
POPULATION MALE
NON WORKING
POPULATION FEMALE
Beraberi 4011 1273 1738 Sinher Bheri 824 289 535 Khaser Bheri 496 138 358
Baje Melia 2062 682 1380
Gopalnagar 7911 2550 5361
Total 15304 4932 9372
9
Annexure: List of Trainees undergoing training at Ramakrishna Mission Shilpamandira, Belur Math
List of Trainees at Ramakrishna Mission Shilpamandi ra, Belur Math. Trade : House Wiring & Electrical Gadget Repairing
Sl. No. Name Fathers' Name Age Qlf. Mouza
1 Suranjan Ghosh Lab Kr. Ghosh 27 M.P. Bajemelia
2 Srimanta Mallik Srikanta Mallik 23 M.P. Bajemelia
3 Manimohan Bangal Biful Ch. Bangal 25 M.P. Gopalnagar
4 Samarendra Bag Bijay Krishna Bag 29 M.P. Berabari
5 Debkumar Pal Nimaichandra Pal 21 H.S. Berabari
6 Monaranjan Ghosh Nabakumar Ghosh 19 M.P. Berabari
7 Malayendu Dhole Lt. Dilip Dhole 34 M.P. Berabari
8 Anupam Ghosh Ginitan Ghosh 20 H.S. Berabari
9 Animesh Das Phanibhusan Das 26 M.P. Berabari
10 Nilkanta Das gokul Das 35 M.P. Berabari
11 Pulakesh De Madhusudan De 38 M.P. Singherveri
12 Avijit Das Billeshwar Das 22 H.S. Singherveri
13 Tanmoy Pal Guiram 37 M.P. Singherveri
14 Shyamapada Mandy Dilip Kr. Mandy 33 H.S. Gopalnagar
15 Pintu Pal Gobardhan Pal Singherveri
16 Surajit Das Tapan Das Singherveri
17 Animesh Maity Panchanan Maity Gopalnagar
18 Smirty Bikash Pal Ranjit Pal Singherveri
19 Niharranjan Ghosh Raghunath Ghosh 26 M.Com Gopalnagar
20 Mrinmoy Mal Sushil Mal 32 B.Com Berabari
21 Shovam Basu Hrishikesh Basu 19 HS Gopalnagar
22 Supriya Adhikary Haradhan Adhikary 33 H.S. Gopalnagar
23 Naba Kumar Malik Prasad Chandra Malik H.S. Bajemelia
24 Raj Kumar Malik Lt. Prasad Chandra Malik H.S. Bajemelia
25 Ujjwal Ghosh Radha Prasad Ghosh 18 M.P. Berabari
26 Kartick Ch. Dey Badan Ch. Dey Berabari
27 Radha Kanta Saha Sukumar Saha 23 M.P. Beraberi
10
List of Trainees at Ramakrishna Mission Shilpamandi ra, Belur Math.
Trade : Automobile Repairing
Sl No. Name Father Name Age Edn. Mouza 1 Mrinalkanti Kole Gobinda Kole 35 H.S. Bajemalia
2 Mrityunjoy Malik Ajay Malik 26 M.P. Bajemalia
3 Taraknath Malik Kantacharan Mallik 24 H.S. Bajemalia
4 Pradip Patra Madhusudan Patra 17 M.P. Bajemalia
5 Amit Maity Paresh Maity 29 H.S. Gopalnagar
6 Gobinda Ghosh Joydeb Ghosh 20 H.S. Gopalnagar
7 Budhyadeb Shaw Anil Shaw 18 M.P. Gopalnagar
8 Malay Polen Mohanlal Polen 32 M.P. Khaserbheri
9 Aloke Kr. Polen Jawar Polen 35 M.P. Khaserbheri
10 Tanmoy Koley Sunil Koley 17 M.P. Khaserbheri
11 Soumya Saha Asis Kr. Saha 18 M.P. Beraberi
12 Rajib Ghosh Arjun Ghosh 24 M.P. Beraberi
13 Snehasis Ghosh Srikanta Ghosh 16 M.P. Beraberi
14 Achinta Das Nemai Das 31 M.P. Beraberi
15 Tapan Kr. Mal Biswanath Mal 38 H.S. Beraberi
16 Prosenjit Ghosh Kamalakanta Ghosh 20 H.S. Beraberi
17 Kajal Saha Bidyut Saha 34 B.Com Beraberi
18 Madhab Ghosh Monoranjan Ghosh 26 M.P. Beraberi
19 Chinmoy Kr. Ghosh Sukumar Ghosh 24 M.P. Beraberi
20 Samit Kr. Ghosh Mohanta Ghosh 24 M.P. Beraberi
21 Subhankar Dey Lt. Aloke Kr. Dey 21 B.Com Beraberi
22 Santu Bag Pawan Bag 17 M.P. Beraberi
23 Sovan Saha Chittaranjan Saha 24 M.P. Beraberi
24 Somnath Ghosh Samarendra Ghosh 21 H.S. Beraberi
25 Pallab Saha Lt. Baidya Nath Saha 26 M.P. Beraberi
26 Abhranil Ghosh Ajit Ghosh 25 H.S. Beraberi
27 Joydeep Hambir Netai Ch,. Hambir 18 M.P. Beraberi
28 Samir Das Joydeb Das 18 M.P. Beraberi
29 Somnath Das Dhananjoy Das 21 B.A. Beraberi
30 Rabi Gopal Das Mrityunjoy Das 32 B.A. Beraberi
31 Uday Das Anil Das 19 M.P. Singherbheri
32 Arun Santra Kartick Santra 19 M.P. Singherbheri
33 Jayanta Singha Maninandra Nath Singha 19 H.S. Khaserbheri
34 Pradeep Chakraborty Sakti pada Chakraborty 30 B.Com
35 Arup Chal Anadi Bhusan Chal 20 H.S. Gopalnagar
36 Amiya Saw Sanat Saw 23 B.Com Gopalnagar
37 Saptarshi Mitra Tarun Kr. Mitra 19 M.P. Gopalnagar
38 Koustav Ghosh Purnasankar Ghosh 22 B.Com Gopalnagar
39 Debkumar Saw Ramchandra Saw 20 B.Com Gopalnagar
40 Saraj Ghosh Tarak Nath Ghosh 20 B.Com Gopalnagar
41 Dipak Dutta Sailendra Nath Datta Beraberi
42 Uday Sankar Das Lt. BadalCh.Das Bajemalia
43 Akul Ch. Ruidas Lt.Adhir Ch.Ruidas Beraberi
44 Rabi Ranjan Ghosh N. K. Ghosh Beraberi
45 Soumen Koley Sudeb Koley Bajemalia
46 Biswajit Das Harendra Nath Das Bajemalia
47 Tapan Ghosh Shyamapada Ghosh Beraberi
48 Somnath Das Sanat Das 16 M.P. Khaserbheri
49 Santu Mullick S S Mullick 21 H.S. Gopalnagar
50 Sailendra Nath Das Mahadeb Das 32 M.P. Khaserbheri
51 Debrup Das Anandamoy Das Khaserbheri
52 Rathin Shaw Lt. Adwaita Shaw 36 H.S. Gopalnagar
53 Tapas Kr. Ghosh Kashi Nath Ghosh 26 B.Sc. Beraberi
11
Trade : Automobile Repairing (contd..)
54 Rabindra Nath Mal Satya Charan Mal 36 M.P. Beraberi
55 Subrata Patra Prasad Patra 20 H.S. Gopalnagar
56 Ramananda Das Gokul Ch.Das Khaserbheri
57 Surajit Malik M.P. Khaserbheri
58 Pintu Maity Kanai Lal Maity M.P. Bajemalia
59 Mantu Jyoti Karuna Jyoti 23 B.A. Beraberi
60 Raj Kr. Jyoti Nirapada Jyoti Gopalnagar
61 Subhasish Ghosh Ratan Ghosh 26 H.S. Beraberi
62 Binoy Kr. Mati Mritunjoy Mati 25 M.P. Beraberi
63 Purna Ch. Das M.P. Beraberi
64 Subir Shaw Lt. Adhir Kr. Shaw 29 H.S. Gopalnagar
65 Arup Das Kartick Ch. Das Khaserberi
66 Nandalal Das Nemai Ch. Das 27 M.P. Beraberi
67 Amit Ghosh Chittarajan Ghosh M.P. Beraberi
68 Amit Kr. Bera Kartick Bera 21 H.S. Beraberi
69 Manoj Patra Gopinath Patra M.P.
70 Susanta Ghosh Niranjan Ghosh 32 M.P Berabari
71 Subhadip Ghosh Tapas Kr. Ghosh 16 M.P. Beraberi
72 Amit Kr. Pal Gobinda Pada Pal 20 M.P. Beraberi
73 Goutam Polen Manindra Nath Polen Khaserberi
74 Samit Ghosh Chittarajan Ghosh 25 H.S. Berabari
75 Surajit Das Biswanath Das Khaserberi
76 Snehasis Ghosh Srikanta Ghosh 16 M.P. Berabari
77 Subhasis Patra Lakhinarayan Patra 17 MP Doulatpur
12
List of Trainees at Ramakrishna Mission Shilpamandi ra, Belur Math.
Trade : Two & Three Wheeler Repairing Sl
No. Name Father Name Age Edn. Mouza
1 Somnath Ghosh Nikhil Kr. Ghosh Berabari
2 Uttam Kr Das Nemai Ch Das
Trade : Welding & Fabrication Sl
No. Name Father Name Age Edn. Mouza
1 Bhaskar Das Kartik Chandra Das 18 H.S. Bajemelia
2 Sukhendu Das Sankar Das 18 M.P. Bajemelia
3 Biswajit Ghosh Sudhir Ch. Ghosh 23 H.S. Beraberi
4 Himanshu Ghosh Dilip ghosh 21 H.S. Beraberi
5 Harekrishna Batabyal Lt. Rashbehari Batabyal 35 M.P. Beraberi
6 Manonnit Das Ajit Kr. Das 22 M.P. Singherbheri
7 Biswanath Das Sambhunath Das 21 H.S. Singherbheri
8 Srimanta Shaw Shyamacharan Shaw 19 M.P. Gopalnagar
9 Amit Oraon Budhram Oraon 20 M.P. Gopalnagar
10 Babusona Neogi Nabakumar Neogi 21 M.P. Beraberi
11 Achinta Ghosh Biswanath Ghosh Beraberi
12 Sudipta Das Ganesh Ch. Das Gopalnagar
13 Bikash Sahana Lakshmi Kanta Sahana Gopalnagar
14 Sibsankar Bangal Ganesh Ch. Bangal Gopalnagar
15 Biswajit Kamley Haradhan Kamley Gopalnagar
16 Goutam Malik Basudeb Malik 20 H.S. Gopalnagar
17 Bobin Das Lt Anil Ch Das M.P. Khaserberi
18 Mrinal Kanti Khanra Dinabandhu Khanra 27 M.P. Beraberi
19 Pulakesh Das Nokuleshwar Das Khaserberi
20 Samar Kumar Koley Haradhan Koley Khaserberi
21 Sumit Mal Subodh Mal 20 H.S. Bajemalia
22 Subhendu Malik Lakshman Malik Gopalnagar
23 Raj Kumar Manna Haradhan Manna 35 M.P. Beraberi
24 Nirmal Chandra Koley Nirapada Koley Gopalnagar
25 Soumitra Santra Yudistir Santra 19 M.P. Gopalnagar
26 Himansu Das Ajit Kr. Das 21 H.S. Gopalnagar
27 Siddhartha Mal Panchu Gopal Mal Beraberi
28 Susanta Kr. Jyoti Haradhan Jyoti M.P. Gopalnagar
29 Saroj Kr. Ghosh Tarak Nath Ghosh Beraberi
30 Paran Ch. Ghorui Prafulla Ch. Ghorui 31 M.P. Gopalnagar
31 Sanatan Guchait Panchanan Guchait 36 Gopalnagar
13
List of Trainees at Ramakrishna Mission Shilpamandi ra, Belur Math.
Trade : MACHINIST Sl
No. Name Father Name Age Edn. Mouza
1 Rajib Khara Birendra Nath Khara 25 B.Com Bajemalia
2 Pallab Patra Lakshmi Patra 21 M.P. Bajemalia
3 Dipankar Bera Mahadeb Bera 20 M.P. Gopalnagar
4 Amal Kr. Pollen Jawarharlal Pollen 34 M.P. Khasherveri
5 Nepal Ch. Bag Late Bibhuti Bhusan Bag 37 M.P. Khasherveri
6 Abhik Kr. Kole Ashoke Kole 24 M.P. Beraberi
7 Suman Bag Kartik Ch. Bag 16 M.P. Beraberi
8 Shankar Barui Lt. Amiya Barui 17 M.P. Beraberi
9 Dharani Dharan Dhara Panchanan Dhara 34 M.P. Beraberi
10 Basudeb Dhara Panchanan Dhara 18 M.P. Beraberi
11 Sanjib Ch. Barui Lt. Krishna Barui 34 M.P. Beraberi
12 Himangshu Shekhar Barui Lt. Krishna Barui 33 M.P. Beraberi
13 Koushik Bag Bijoy Krishna Bag 22 M.P. Beraberi
14 Kokhan Mallick Ratan Mallick 22 H.S. Beraberi
15 Amiya Kr. Santra Tapan Kr. Santra 18 H.S. Beraberi
16 Sanjay Adhikary Sukumar Adhikary 21 H.S. Gopalnagar
17 Sandip Kr Mallik Dulal Ch Mallik 19 H.S. Gopalnagar
18 Biswajit Das Late Subal Ch. Das 32 H.S. Beraberi
19 Bapan Dolui Basudev Dolui 23 H.S. Gopalnagar
20 Haridas Roy Balaram Roy 23 M.P. Gopalnagar
21 Shyam Sundar Bera Bharat Chandra Bera 22 M.P. Beraberi
22 Deb Das Banerjee Dilip Kr. Banerjee 22 M.P. Gopalnagar
23 Tanmoy Kr. Manna Rabindranath Manna 18 H.S. Gopalnagar
24 Bikash Pakira Charan Pakira 29 H.S. Beraberi
25 Bidyut Kr. Santra Ajit Santra 31 M.P. Beraberi
26 Anup Rui Das Adhir Chandra Ruidas 16 M.P. Beraberi
27 Chandrakanta Manna Anil Manna 16 M.P. Gopalnagar
28 Tamal Pakira Sankar Pakira 19 H.S. Beraberi
29 Shyama Pada Ruidas Dilip Ruidas 16 M.P. Gopalnagar
30 Kunal Kanti Koley Radhakanta Koley 40 B.Com Beraberi
31 Pradip Dey Tarak Dey 32 B.A. Beraberi
32 Ashoke Shaw Sanat Shaw 20 H.S. Khaserberi
33 Samir Chakraborty Biswanath Chakraborty M.P. Bajemalia
34 Raghunath Ghosh Gour Ghosh M.P. Beraberi
35 Chiranjib Mal Jayant Mal H.S. Beraberi
36 Suman Chakraborty Deb Kumar Chakraborty 23 M.P. Gopalnagar
37 Jugal Kishore Das Gobinda Das Gopalnagar
38 Asim Kr.Mal Baidyanath Mal 40 B.Com Beraberi
39 Joydeb Pakira Lt.Muchiram Pakira M.P. Gopalnagar
40 Sandeep Dey Mahadeb Dey 34 H.S. Beraberi
41 Bimal Kr. Rui Das Smt. Swarnabala Rui Das 31 M.P. Gopalnagar
42 Surajit Bag Baidyanath Bag 16 M.P. Gopalnagar
14
ANNEXURE II: Discussion with Local People’s Representatives
Chronological History of Meetings:
Date Details Venue Outcome
27th May 2006 DM’s First all political Party meeting
DM’s office
17th June 2006 DM’s second all political Party meeting
DM’s office
4th July 2006 DM’s third all political Party meeting
DM’s office
27th August 2006
DM’s meeting with the leadership of “Krishi Jami Bachao Samity” under leadership of Sri Becharam Manna and six others
DM’s Bungalow
No decision transpired
5th September 2006 DM’s meeting with all three Gram Panchayet Pradhans and Members
DM’s office
Panchayet members of the other political parties did not attend.
13th /14th September 2006
MD WBIDC, Director Industry, DM and SP’s meeting with Sri Becharam Manna
Singur Police Station
No decision transpired
14th September 2006
MD WBIDC, Director Industry’s informal meeting with Sri Dudhkumar Dhara and Sri Mahadeb Das
A private house in Kolkata
No decision transpired
19th September 2006 MD WBIDC’s second meeting with Sri Dudhkumar Dhara and Sri Mahadeb Das
A private house in Kolkata
No decision transpired
21st September 2006 MD WBIDC, Director Industry’s meeting with MLA Singur
Singur Block office
MLA Singur was requested to identify the plots which in his opinion should have been classified for higher compensation to facilitate enquiry and decision , but no response received from him.
15
Chronology of Land Acquisition: Issuance of Notice under Section 4(1) of Land Acquisition Act 1894:
19th July 2006 to 24th July 20067
Issuance of Notice under Section 6 of Land Acquisition Act 1894
29th August 2006 to 31st August 20068 Declaration of award:
21st September 2006 to 23rd September 2006
Commencement of payment of Land Acquisition:
25th September 2006 Constraints faced by WBIDC: From the very beginning of the process of Land acquisition WBIDC was engaged with the idea
that the compensation payable to the landowners and bargadars need to be commensurate with the
market value of land and its present usage pattern. This necessitated reconnaissance of the land.
But such scouting could not be done due to constant obstruction by the detractors. Even reports
were received that land owners are being prevented from attending the hearing by the agitators
and with lot of difficulty, a sense of security could be prevailed in the minds of the landowners to
enable them to participate in the process. However the entry to the land to explore the terrain and
to ascertain the ground condition by WBIDC team could not be ensured till early December.
7 There are altogether 13 LA Cases and the notices pertaining to each case was different. Therefore the dates between which all the notices were published are indicated not the individual dates pertaining to individual cases. 8 There are altogether 13 LA Cases and the notices pertaining to each case was different. Therefore the dates between which all the notices were published are indicated not the individual dates pertaining to individual cases