US Army Corps of Engineers
BUILDING STRONG
DALLAS FLOODWAY
Feasibility Cost Share Agreement
TRINITY RIVER CORRIDOR PROJECT(TRCP) COMMITTEE BRIEFING
MARCH 2, 2010
8/14/2019 4-74 Million - Feasiblity Study From Trinity River Committee Combined 03-02-10-2
2/16
BUILDING STRONG2
To provide information and requestapproval from the Trinity River Corridor
Project Committee for the upcomingFeasibility Cost Share Agreement with
the U.S. Army Corps of Engineers(USACE)
PURPOSE
8/14/2019 4-74 Million - Feasiblity Study From Trinity River Committee Combined 03-02-10-2
3/16
BUILDING STRONG3
Legal document binding USACE and the City toundertake a Feasibility Study and Integrated
Environmental Impact Statement (EIS) for the DallasFloodway
Provides cost sharing and other responsibilities of
both parties Identifies studies and plan of action for completion of
EIS
WHAT IS A FEASIBILITY COST SHARE
AGREEMENT (FCSA)?
8/14/2019 4-74 Million - Feasiblity Study From Trinity River Committee Combined 03-02-10-2
4/16
BUILDING STRONG4
Required by National Environmental Policy Act(NEPA) for projects that have federal fundingand may have environmental, economic orsocial impacts
Typically includes studies for hydraulics,geology, economics, historic and culturalresources, wildlife and vegetation
Also includes 35% design level of projectcomponents
Completion of this document is required toreceive approval to construct the project
WHAT IS AN ENVIRONMENTAL IMPACTSTATEMENT (EIS)?
8/14/2019 4-74 Million - Feasiblity Study From Trinity River Committee Combined 03-02-10-2
5/16
BUILDING STRONG5
1945 / 1950 Dallas Floodway Project Authorized 1960 US Army Corps of Engineers (USACE) Construction Completed
1996 Feasibility Study Initiatedo Level of Protection decreased from 800-year to 300-500 yearo Basin-wide modeling completedo Economic database developedo Regional Corridor Development Certificate (CDC) process developedo Preliminary work completed on flood damage reduction, ecosystem restoration and recreation
componentso Efforts continued in conjunction with Dallas Floodway Extension study, development of Citys
Balanced Vision Plan and Interior Drainage Plan, and preliminary work on Trinity Parkway
2007 (Nov) Dallas Floodway Project authorized in Water Resources DevelopmentAct (WRDA)
2007 (Dec) Periodic Inspection of existing Dallas Floodway Levee SystemConducted
2009 (Mar) Periodic Inspection Report on Dallas Floodway Levee SystemProvided to City with Unacceptable Rating
2009 (May) Decision made to analyze all proposed actions within DallasFloodway comprehensively
BACKGROUND
8/14/2019 4-74 Million - Feasiblity Study From Trinity River Committee Combined 03-02-10-2
6/16
BUILDING STRONG6
Modified 1945 and 1950 Project Authorizations
Authorized Construction of City Plans
o Balanced Vision Plan (BVP)
o Interior Drainage Plan (IDP)
Required Determination of Technical Soundness &Environmental Acceptability Study Required
Authorized Total Project Cost $459 million
o Federal $298 million / Non-Federal $161 million
Allowed Advancement of City Funds to Maintain Schedule -Credit Given in Future Phases of Project Development
Water Resources Development Act 2007(Section 5141)
8/14/2019 4-74 Million - Feasiblity Study From Trinity River Committee Combined 03-02-10-2
7/16
BUILDING STRONG7
Dallas Floodway Feasibility StudyDallas Floodway Balanced Vision Plan
8/14/2019 4-74 Million - Feasiblity Study From Trinity River Committee Combined 03-02-10-2
8/16
BUILDING STRONG8
8/14/2019 4-74 Million - Feasiblity Study From Trinity River Committee Combined 03-02-10-2
9/16
BUILDING STRONG9
Feasibility Cost Share Agreement (FCSA)
o Legal Instrument / Study Agreement (w/costs)
o Requires 50/50 Cost Share for Studyo Execution Needed to Access Federal & Non-Federal Funds
Project Management Plan (PMP)o Provides Detailed Scope, Schedule, Budget
o Supports FCSA
o Guides Study/Project
o Identifies USACE and City Responsibilities
Feasibility Cost Share Agreement
8/14/2019 4-74 Million - Feasiblity Study From Trinity River Committee Combined 03-02-10-2
10/16
BUILDING STRONG10
Levee Remediation Plan (LRP)o Identify Measures to Restore Levees to Authorized Design Standards
Balanced Vision Plan (BVP ) - Flood Risk Management (FRM)o Potential Levee Raises at Current Design Standards
o Removal of AT&SF Bridge
Balanced Vision Plan (BVP) Ecosystem / Recreationo Lakes, Parks, River Meanders, Wetlands, Athletic Fields, etc.
Interior Drainage Plan (IDP)o Pumps, Sumps, Gravity/Pressure Storm Sewers, etc.
Local Featureso Trinity Parkway, Bridges, Santa Fe Trestle Trail, etc.
Major Study Elements
8/14/2019 4-74 Million - Feasiblity Study From Trinity River Committee Combined 03-02-10-2
11/16
BUILDING STRONG11
Total study costs estimated at $38.4 milliono 50/50 cost share Federal and City
Citys 2009 contract award to HNTB includes an estimated
$23 million directly applicable to this new Feasibility Study
Citys cost share requirements already met
However, in order to maintain schedule, WRDA language
allows City to provide funds to keep study progressing WRDA language provides opportunity for credit of Citys
additional funding toward future phases of projectdevelopment
Remaining study costs estimated at $15.4 million
Feasibility Study Costs
8/14/2019 4-74 Million - Feasiblity Study From Trinity River Committee Combined 03-02-10-2
12/16
BUILDING STRONG12
Presidents Budget request comes out inFebruary for the next fiscal year
Congress is scheduled to approve budgetsby October of the current fiscal year
If appropriations bill is not approved at that
time, temporary funding is providedthrough a continuing resolution until finalbill is approved
Continuing resolution typically limits theamount of funding available
USACE Funding Process
8/14/2019 4-74 Million - Feasiblity Study From Trinity River Committee Combined 03-02-10-2
13/16
BUILDING STRONG13
Needed for FY 10 (ending 9/30/10) $4.70 M Needed for FY 11 thru 3/2011* $2.05 M USACE funding FY 10 ($1.30 M)
USACE funding FY 11** ($0.70 M) TOTAL FUNDING NEEDS $4.75 MFOR USACE thru 3/2011
To keep the study moving at full speed, the Cityneeds to advance $4.75 M to USACE
* In the event that the appropriations bill is not passed by the start of October 2010,the City proposes to provide funds to maintain schedule
** Included in Presidents Budget; however, there is an opportunity for additionalfunding through Congressional appropriations bills that could increase this amount
Funding Needs for USACE
8/14/2019 4-74 Million - Feasiblity Study From Trinity River Committee Combined 03-02-10-2
14/16
BUILDING STRONG14
WRDA 2007 language allows the City to receive credittoward future design and construction phases of the
project for any City contributions over 50% cost shareduring the Feasibility Study
When the Dallas Floodway project begins design
and/or construction phases, agreements between Cityand USACE will incorporate this credit, thereby
reducing the Citys future funding requirements
How does the City get credited for
advance contributions?
8/14/2019 4-74 Million - Feasiblity Study From Trinity River Committee Combined 03-02-10-2
15/16
BUILDING STRONG15
Council approval on March 10, 2010 of FCSA andto provide $4.75 million to USACE to ensurecontinued USACE progress through March 2011
If federal funding does not meet project needs forFY 11, City may be required to provide additionalfunds at that time
Staff Recommendation
8/14/2019 4-74 Million - Feasiblity Study From Trinity River Committee Combined 03-02-10-2
16/16
BUILDING STRONG16
Dallas Floodway Feasibility Study
QUESTIONS?