Post on 06-Apr-2018
8/3/2019 2012 Corporate Update January
1/33
C o r p o r a t e U p d a t eJ A N U A R Y 2 0 1 2
8/3/2019 2012 Corporate Update January
2/33
This presentation contains forward-looking statements, within the meaning of the United States Private Securities Litigation Reform Act
of 1995 and applicable Canadian securities legislation, concerning the business, operations and financial performance and condition ofGoldcorp Inc. (Goldcorp). Forward-looking statements include, but are not limited to, statements with respect to the future price of gold,silver, copper, lead and zinc, the estimation of mineral reserves and resources, the realization of mineral reserve estimates, the timing andamount of estimated future production, costs of production, capital expenditures, costs and timing of the development of new deposits,success of exploration activities, permitting time lines, hedging practices, currency exchange rate fluctuations, requirements for additionalcapital, government regulation of mining operations, environmental risks, unanticipated reclamation expenses, timing and possibleoutcome of pending litigation, title disputes or claims and limitations on insurance coverage. Generally, these forward-looking statementscan be identified by the use of forward-looking terminology such as plans, expects or does not expect, is expected, budget,scheduled, estimates, forecasts, intends, anticipates or does not anticipate, believes or variations of such words and phrases orstatements that certain actions, events or results may, could, would, might or will be taken, occur or be achieved. Forward-
looking statements are subject to known and unknown risks, uncertainties and other factors that may cause the actual results, level ofactivity, performance or achievements of Goldcorp to be materially different from those expressed or implied by such forward-lookingstatements, including but not limited to: risks related to the integration of acquisitions; risks related to international operations; risks relatedto joint venture operations; actual results of current exploration activities; actual results of current reclamation activities; conclusions ofeconomic evaluations; changes in project parameters as plans continue to be refined; future prices of gold, silver, copper, lead and zinc;possible variations in ore reserves, grade or recovery rates; failure of plant, equipment or processes to operate as anticipated; accidents,labour disputes; delays in obtaining governmental approvals or financing or in the completion of development or construction activities andother risks of the mining industry, as well as those factors discussed in the section entitledDescription of the Business Risk Factors inGoldcorps annual information form for the year ended December 31, 2010 available at www.sedar.com. Although Goldcorp hasattempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking
statements, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no assurance thatsuch statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in suchstatements. Accordingly, readers should not place undue reliance on forward-looking statements. Goldcorp does not undertake to updateany forward-looking statements that are included in this document, except in accordance with applicable securities laws.
All amounts are in U.S. dollars, unless otherwise stated.
Forward Looking Statements
2
8/3/2019 2012 Corporate Update January
3/33
3
Growth Leader
Low Cost Producer
Outstanding BalanceSheet
Low Political Risk
Responsible Mining
SUSTAINABLE
PROSPERITY
8/3/2019 2012 Corporate Update January
4/33
163
305 295 274
209
540
563683
966 1,329
2007 2008 2009 2010 Q3'11 YTD
By-Product Cash Costs Cash Margin
$703
$868$978
$1,240
($ per Oz)REALIZED GOLD PRICE $1,538
Sector Leading Cash Margins
4
8/3/2019 2012 Corporate Update January
5/33
Strong Growth on a Per Share Basis
5
$1.22 $1.31
$1.61
$2.33 $2.32
$0.00
$0.50
$1.00
$1.50
$2.00
$2.50
2007 2008 2009 2010 Q3'11 YTD
Cash flow / Share1(US$ / share)
61.565.0 66.7
78.0
40.0
50.0
60.0
70.0
80.0
2007 2008 2009 2010
$0.62 $0.56
$0.80
$1.37$1.59
$0.00
$0.40
$0.80
$1.20
$1.60
2007 2008 2009 2010 Q3'11YTD
Reserves / Share3(per 1000 shares)
Earnings / Share2(US$ / share)
1 Cash flow before changes in working capital2 Adjusted earnings per share3 Reserves for gold only4 Includes Cerro Negro update March 2011
4
8/3/2019 2012 Corporate Update January
6/33
39,700
43,40046,300
48,800
62,250
2006 2007 2008 2009 2010*Gold proven & probable reserves (000s oz)
2012 Exploration Budget - $200M
2010* INCREASE OF 28%,17% ON A PER SHARE BASIS
Steady, Continuous Reserve Growth Success
6
* Includes Cerro Negro update March 2011
8/3/2019 2012 Corporate Update January
7/33
Gold production (oz) 2,600,000 2,514,700
Cash costs $/oz - By-Product $250 - $275 ~$220
- Co-Product $550 - $600 ~$530Capital expenditures $2.6B TBA
Exploration expenditures $200M TBA
Corporate administration $160M TBA
Depreciation /oz $325 TBA
Tax rate 30% TBA
20121
Guidance
2012 Guidance
7
1 2012 price assumptions: Au=$1600/oz, Ag=$34/oz, Cu=$3.50/lb, Zn=$0.90/lb, Pb=$0.90/lb
2011
Actual
8/3/2019 2012 Corporate Update January
8/33
Cash & cash equivalents ~$1.7B
Available debt facility undrawn $2.0B
Convertible senior notes due 2014 $862.5M
Forecast avg. annual operating $3.7B2
cash flow over next 5 years
Financial Position Excellent Liquidity
1 Moodys: Baa2; S&P: BBB+; Fitch: BBB2 Price assumptions 2012-2016: Au=$1600/oz, Ag=$34/oz, Cu=$3.50/lb, Zn=$0.90/lb, Pb=$0.90/lb
Investment Grade1 Balance Sheet
As at Dec. 31, 2011
8
8/3/2019 2012 Corporate Update January
9/33
19%17%
13%
11%10%
9%
15%
13%
11%
9%8%
6%
0%
2%
4%
6%
8%
10%
12%
14%
16%
18%20%
Newmont Goldcorp Yamana Newcrest Barrick Kinross
2011E 2012E
9
Source: Bloomberg consensusCompany reports
Dividend as % of Operating Cash Flow
8/3/2019 2012 Corporate Update January
10/33
Focus on Stable Jurisdictions
2012E Gold Production
OPERATING MINES
DEVELOPMENT PROJECTS
AMERICAS ORIENTATION
ARGENTINA
DOMINICANREPUBLIC
CANADA
CHILE
MEXICO
GUATEMALA
USA
10
Canada
46%
US
5%
Mexico
33%
Guatemala
8%
Argentina
5%
Dominican
Republic
3%
8/3/2019 2012 Corporate Update January
11/33
2011A 2012E 2013E 2014E 2015E 2016E
Current Operations New Projects
(Ounces)
Steady, Strong Growth Profile
11
2,514,700 2,600,000
3,200,000
3,800,0004,000,000 4,200,000
8/3/2019 2012 Corporate Update January
12/33
Scoping
Feasibility
Construction
Production
Red Lake & other operating mines
Marlin (2006)
Los Filos (2008)
Peasquito (2010)
Pueblo Viejo (2012)
Cerro Negro (2013)
Cochenour (2014)
lonore (2014)
El Morro (2017)
Camino Rojo (2014)
Noche Buena
Cerro Blanco
Agua Rica
Red Lake Bulk UG
Peasquito UG
A Robust Development Pipeline
12
8/3/2019 2012 Corporate Update January
13/33
High grade vein system Outstanding reserve growth
potential
Updated feasibility study results:
- 550 koz Au annually (1st 5 years)
-
8/3/2019 2012 Corporate Update January
14/33
Cerro Negro Advancing Construction
140,350 meters exploration drilling
in 2011 Eureka decline advanced to
1,620 meters
6 levels of development into Eureka
vein Construction & development
activities advancing: Approval of amended EIA received Plant construction underway Development of Mariana Central
and Mariana Norte veinscommenced
14
8/3/2019 2012 Corporate Update January
15/33
15
Cerro Negro Large Percentage of Veins Untested
San Marcos
Mariana Norte
Mariana Central
Mariana SurEureka
Buena Vista
El Retiro
Vein Zone
Bajo Negro
Sur Vein
4810000N
4805000N
5 kilometersAreas of vein tested
Pre-mineral rock within Bonanza elevation
Concession Boundary
Quartz vein
11.0m111.00 g/t Au238 g/t Ag
2.0m5.4 g/t Au3,244 g/t Ag
4.0m3.67 g/t Au3 g/t Ag
8.0m20.1 g/t Au265 g/t Ag
2400000E Fault
6.5m
150 g/t Au172 g/t Ag
1.5m92.6 g/t Au72 g/t Ag
2.0m41.12 g/t Au217 g/t Ag
8/3/2019 2012 Corporate Update January
16/33
lonore Pure Gold in a Safe Jurisdiction
Currently sinking exploration shaft 3.03M oz Au reserves
+0.48M oz Au M&I resources+4.17M oz Au inferred resources
Development plan:- Upper/lower mine concept; 7 ktpd- Mine life ~15 years- +600,000 oz Au
- Cash costs:
8/3/2019 2012 Corporate Update January
17/33
Exploration shaft over 640 metres
Exploration ramp extended over 830metres
Plant construction underway
Surface preparation for sinking ofsecond production shaft advancing
EPCM contract awarded Continued exploration success
lonore Progressing Towards Construction
17
8/3/2019 2012 Corporate Update January
18/33
5.9 million ounces of Au reserves1
4.3 billion pounds of Cu reserves1
Large, under-explored land position
Access infrastructure in progress
Feasibility study update completed 17-year mine life Capital cost ~ $3.9B First production: 2017 +210,000 oz Au2; +200Mlb Cu2
By-product cash costs: ($700)/oz
El Morro A World Class Project in Mining Friendly Chile
18
1Goldcorp interest 70%2 LOM average annual production (70% interest)
8/3/2019 2012 Corporate Update January
19/33
9.5 million ounces of Au reserves*
Life of mine +25 years
$350 million capital budget for 2012
First gold mid-2012
Average annual output 415,000 to450,000 ounces per year* in first fiveyears
Pueblo Viejo Next New Source of Gold Production
19
* Goldcorp interest 40%
8/3/2019 2012 Corporate Update January
20/33
Initial resource of 2.7M gold ounces Construction underway:
- Mine life ~20 years
- 250,000 - 275,000 ounces Auannually
- Cash costs < $350 per ounce
- Capex - $420M
- First production late 2014
Cochenour Key Growth Driver in Red Lake District
20
8/3/2019 2012 Corporate Update January
21/33
Shaft widening underway Haulage drift 36% complete
- 2 rigs actively drilling
- Exploration potential on untestedground
Surface exploration with 4 drill rigs
Installation of headframe surfaceinfrastructure completed andoperational
Cochenour Construction Progress
21
8/3/2019 2012 Corporate Update January
22/33
22
High Speed Drift
Rahill - Bonanza
Bruce Channel Discovery
WesternDiscovery
Zone
EastWest
Drift location at end of 2012 Current drif t location
Red Lake HSD Provides Exciting Exploration Opportunities
8/3/2019 2012 Corporate Update January
23/33
Red Lake New Opportunities at Worlds Richest Gold Mine
Robust, low cost gold production 2012 gold production forecast of
650,000 ounces
2012 exploration budget $38M- Focus on High Grade Zone
extension- Hanging Wall exploration
success
District optimization plansadvancing: Cochenour, bulk u/gmining
23
8/3/2019 2012 Corporate Update January
24/33
Peasquito Hitting Stride in 2012
2012 gold production forecast -
425,000 ozs at negative cash costs
Ramp up to full capacity on track forend of Q1 2012
Largest cash flow generator in 2012
Average annual production:- 500Koz Au; 204Kt Zn; 90.7Kt Pb;28Moz Ag
22-year mine life
24
8/3/2019 2012 Corporate Update January
25/33
Peasquito Advancing District Projects
25
Camino Rojo Over 77,000 meters drilled in 2011
Testing oxide & sulphide expansion
Feasibility study due H1 2012
Noche Buena
Resource expansion drillingcontinues
In-fill drilling on higher grademineralization trends
8/3/2019 2012 Corporate Update January
26/33
Delivering Superior Returns
Goldcorp+627%
Peers*+266%PhiladelphiaGold / SilverIndex+232%
Gold Price
+461%
Dow Industrials+22%
* Peers include Barrick, Newmont, Kinross and AgnicoSource: Bloomberg data Dec. 31/01 - Dec. 31/11
26
-30%
70%
170%
270%
370%
470%
570%
670%
770%
870%
2001 2003 2005 2007 2009 2011
8/3/2019 2012 Corporate Update January
27/33
Flat mine supply
- Inflation hedge- Currency protection- Safe haven/asset class
Why Gold?
Growing physical demand- Asia- Central bank buying
Growing investment demand
Gold Price Has Increased 12 Consecutive Years
27
8/3/2019 2012 Corporate Update January
28/33
28
Growth Leader Low Cost Producer
Outstanding Balance
Sheet
Low Political Risk
Responsible Mining
SUPERIOR
INVESTMENTPROPOSITION
8/3/2019 2012 Corporate Update January
29/33
Appendix A Metals Production (% of Revenues)
29
Price assumptions 2012-2016: Au=$1400/oz, Ag=$26/oz, Cu=$3.30/lb, Zn=$0.90/lb, Pb=$0.90/lb
86% 84% 87%88% 90% 91%
14% 16% 13%12% 10% 9%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
2011E 2012E 2013E 2014E 2015E 2016E
Total Precious Metals Base Metals
8/3/2019 2012 Corporate Update January
30/33
-
1,000,000
2,000,000
3,000,000
4,000,000
5,000,000
6,000,000
2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016
GEO actual production
5.2 Moz
(Ounces)
GEO est. production
Appendix B Increasing GEO Production
30
8/3/2019 2012 Corporate Update January
31/33
CFPS($/share)
Appendix C 2012 Sensitivities
31
Base Price Change
Increments
CFPS
($/share)
By Product Cash
Costs ($/oz)
FCF
($mm)Gold Price ($/oz) $1,600 $100 $0.23 $186
Silver Price ($/oz) $34.00 $2.00 $0.06 $23 $41
Copper Price ($/lb) $3.50 $0.50 $0.04 $14 $25
Zinc Price ($/lb) $0.90 $0.10 $0.04 $15 $28
Lead Price ($/lb) $0.90 $0.10 $0.02 $8 $15
Canadian Dollars 1.00 10% $0.04 $17 $118
Mexican Peso 13.00 10% $0.04 $17 $40
Diesel ($/barrel) $95.00 10% $0.01 $7 $12
Electricity ($/kWh) $0.09 10% $0.02 $10 $17
8/3/2019 2012 Corporate Update January
32/33
Appendix D Operating Costs Breakdown
32
22%
14%
7%
10%
10%
15%
2%
5%
4%
11%
Consolidated
Labour Contractors Fuel Costs Power Maintenance Parts Consumables Tires Explosives Site Costs Others
38%
19%
5%
6%
9%
10%
1%2%
6%4%
Canada / USA12%
14%
8%
12%
9%
18%
2%
6%
4%
15%
Mexico
18%
8%
7%
14%
13%
16%
1%
6%
4%
13%
CSA
8/3/2019 2012 Corporate Update January
33/33
1. Goldcorp has included non-GAAP performance measures, total cash costs, by-product and co-product, per gold ounce, throughout thispresentation. Total cash costs are defined as cost of sales divided by ounces of gold and silver sold or pounds of copper sold. The calculation
of total cash costs per ounce of gold is net of by-product sales revenue (by-product copper revenues for Alumbrera; by-product silver revenuesfor Marlin at market silver prices; by-product lead, zinc and 75% of the silver for Peasquito at market silver prices and 25% of the silver forPeasquito at $3.90 per silver ounce sold to Silver Wheaton). The Company reports total cash costs on a sales basis. In the gold miningindustry, this is a common performance measure but does not have any standardized meaning. The Company follows the recommendations ofthe Gold Institute Production Cost Standard. The Company believes that, in addition to conventional measures prepared in accordance withGAAP, certain investors use this information to evaluate the Companys performance and ability to generate cash flow. Accordingly, it isintended to provide additional information and should not be considered in isolation or as a substitute for measures of performance prepared inaccordance with GAAP. Total cash costs on a by-product basis are calculated by deducting by-product copper, silver, lead and zinc salesrevenues from production cash costs.
Production costs in 2012 are allocated to each co-product based on the ratio of actual sales volumes multiplied by budget metals prices of$1,600 per ounce of gold, $34 per ounce of silver, $3.50 per pound of copper, $0.90 per pound of lead and $0.90 per pound of zinc, rather thanrealized sales prices.
2. All Mineral Reserves and Mineral Resources have been calculated as at December 31, 2010 in accordance with the standards of the CanadianInstitute of Mining, Metallurgy and Petroleum and National Instrument 43-101, or the AusIMM JORC equivalent. Cautionary Note to UnitedStates Investors Concerning Estimates of Measured, Indicated and Inferred Resources. United States investors are advised that while suchterms are recognized and required by Canadian regulations, the United States Securities and Exchange Commission does not recognize them.Inferred Mineral Resources have a great amount of uncertainty as to their existence, and as to their economic and legal feasibility. It cannot beassumed that all or any part of an Inferred Mineral Resource will ever be upgraded to a higher category. Under Canadian rules, estimates ofInferred Mineral Resources may not form the basis of feasibility or other economic studies. United States investors are cautioned not to assumethat all or any part of Goldcorps Measured or Indicated Mineral Resources will ever be converted into Mineral Reserves. United States investorsare also cautioned not to assume that all or any part of an Inferred Mineral Resource exists, or is economically or legally mineable. Calculationshave been prepared by employees of Goldcorp, its joint venture partners or its joint venture operating companies, as applicable, under thesupervision of Maryse Belanger, Director Technical Services. Reserve calculations incorporate current and/or expected mine plans and costlevels at each property. Varying cut-off grades have been used depending on the mine and type of ore contained in the reserves. Goldcorpsnormal data verification procedures have been employed in connection with the calculations. For a breakdown of Reserves and Resources by
category and for a more detailed description of the key assumptions, parameters and methods used in calculating Goldcorps Reserves andResources, see Goldcorps Annual information Form/ Form 40-F on file with Canadian provincial securities regulatory authorities and the U.S.Securities and Exchange Commission.
3. Goldcorps exploration programs are designed and conducted under the supervision of Charlie Ronkos, Senior Vice-President, Exploration ofGoldcorp. For information on geology, exploration activities generally, and drilling and analysis procedures on Goldcorps material properties,see Goldcorps Annual Information Form/Form 40-F on file with Canadian provincial securities regulatory authorities and the U.S. Securities andExchange Commission.
Endnotes
33