Microeconomics Lecture 13

!

The Costs of Production

Key Termstotal cost profit explicit costs implicit costs economic profit accounting profit production function marginal product diminishing marginal product

fixed costs variable costs average total costs average fixed costs average variable costs marginal costs efficient scale economies of scale diseconomies of scale constant returns to scale

Riyadh Pizza Company

Total Cost TC

Total Cost TC

The market value of all of the inputs a

firm uses in production

Total Revenue TR

Total Revenue TR

Price x Quantity !

TR = P x Q

Profit PR

Profit PR

Total Revenue minus Total Cost

!

PR = TR - TC

Production Function

Production Function

The relationship between inputs and

outputs

Marginal Product

Marginal Product

Additional output of a unit of input

Diminishing Marginal Product

Diminishing Marginal Product

Marginal product declines as input

increases

Fixed Costs FC

Fixed Costs FC

Costs that do not vary with output

Variable Costs VC

Variable Costs VC

Costs that do vary with output

Total Costs TC

Total Costs TC

Fixed costs plus variable costs

!

TC = FC + VC

Average Total Costs ATC

Average Total Costs ATC

Total costs divided by quantity of output

ATC = TC ÷ Q

Average Fixed Costs AFC

Average Fixed Costs AFC

Fixed costs divided by quantity of output

AFC = FC ÷ Q

Average Variable Costs AVC

Average Variable Costs AVC

Variable costs divided by quantity

of output AVC = VC ÷ Q

Marginal Cost MC

Marginal Cost MC

The increase in total cost for the next

unit MC = ∆TC ÷ ∆Q

Q0

1

2

3

4

5

6

7

8

9

10

Q0

1

2

3

4

5

6

7

8

9

10

Fixed Cost FC100

100

100

100

100

100

100

100

100

100

100

Q0

1

2

3

4

5

6

7

8

9

10

Fixed Cost FC100

100

100

100

100

100

100

100

100

100

100

Variable Cost VC

20

39

59

84

120

160

212

270

340

420

Q0

1

2

3

4

5

6

7

8

9

10

Fixed Cost FC100

100

100

100

100

100

100

100

100

100

100

Variable Cost VC

20

39

59

84

120

160

212

270

340

420

Total Cost TC

FC + VC100

120

139

159

184

220

260

312

370

440

520

Q0

1

2

3

4

5

6

7

8

9

10

Fixed Cost FC100

100

100

100

100

100

100

100

100

100

100

Variable Cost VC

20

39

59

84

120

160

212

270

340

420

Total Cost TC

FC + VC100

120

139

159

184

220

260

312

370

440

520

Average Fixed Cost AFC

FC ÷ Q

100

50

33

25

20

17

14

13

11

10

Q0

1

2

3

4

5

6

7

8

9

10

Fixed Cost FC100

100

100

100

100

100

100

100

100

100

100

Variable Cost VC

20

39

59

84

120

160

212

270

340

420

Total Cost TC

FC + VC100

120

139

159

184

220

260

312

370

440

520

Average Fixed Cost AFC

FC ÷ Q

100

50

33

25

20

17

14

13

11

10

Average Variable

Cost AVC

VC ÷ Q

20.0

19.5

19.7

21.0

24.0

26.7

30.3

33.8

37.8

42.0

Q0

1

2

3

4

5

6

7

8

9

10

Fixed Cost FC100

100

100

100

100

100

100

100

100

100

100

Variable Cost VC

20

39

59

84

120

160

212

270

340

420

Total Cost TC

FC + VC100

120

139

159

184

220

260

312

370

440

520

Average Fixed Cost AFC

FC ÷ Q

100

50

33

25

20

17

14

13

11

10

Average Variable

Cost AVC

VC ÷ Q

20.0

19.5

19.7

21.0

24.0

26.7

30.3

33.8

37.8

42.0

Average Total Cost ATC

TC ÷ Q

120.0

69.5

53.0

46.0

44.0

43.3

44.6

46.3

48.9

52.0

Q0

1

2

3

4

5

6

7

8

9

10

Fixed Cost FC100

100

100

100

100

100

100

100

100

100

100

Variable Cost VC

20

39

59

84

120

160

212

270

340

420

Total Cost TC

FC + VC100

120

139

159

184

220

260

312

370

440

520

Average Fixed Cost AFC

FC ÷ Q

100

50

33

25

20

17

14

13

11

10

Average Variable

Cost AVC

VC ÷ Q

20.0

19.5

19.7

21.0

24.0

26.7

30.3

33.8

37.8

42.0

Average Total Cost ATC

TC ÷ Q

120.0

69.5

53.0

46.0

44.0

43.3

44.6

46.3

48.9

52.0

Marginal Cost MC

∆TC ÷ ∆Q

20

19

20

25

36

40

52

58

70

80

0306090

120150180210240270300330360390420450480510540570600

0 1 2 3 4 5 6 7 8 9 10

Total Cost Curve

Explicit Costs

Explicit Costs

Costs that require money

Implicit Costs

Implicit Costs

Costs that do not require money

Accounting Profit

Accounting Profit

Total Revenue minus explicit costs

Economic Profit

Economic Profit

Total Revenue minus both explicit costs and implicit costs

0

25

50

75

100

Accounting Profit Economic Profit

Accounting Profit = Total Revenue - Explicit Costs 100 - 30 = 70

Economic Profit = Total Revenue -

Explicit Costs - Implicit Cost 100 - 30 - 40 = 30

Efficient Scale

Efficient Scale

The quantity of output that

minimizes average total cost

Short Run vs.

Long Run

Short-Run

Short-Run

Cannot change a fixed cost

Long-Run

Long-Run

Can change all costs !

All costs become variable

Economies of Scale

Economies of Scale

Long-run average costs fall as quantity of output increases

Diseconomies of Scale

Diseconomies of Scale

Long-run average costs rise as quantity of output increases

Constant Returns to Scale

Constant Returns to Scale

Long-run average costs stays the same as quantity of output

increases

Qty

Break Even AnalysisSAR

Qty

Break Even AnalysisSAR

Fixed Cost - must pay regardless of quantity

Qty

Break Even AnalysisSAR

Fixed Cost - must pay regardless of quantityVariable Cost - must

pay with each increase in quantity

Qty

Break Even AnalysisSAR

Total Cost = FC + VC x Qty

Fixed Cost - must pay regardless of quantityVariable Cost - must

pay with each increase in quantity

Qty

Break Even AnalysisSAR

Total Cost = 500 + 100 x Q

Total Cost = FC + VC x Qty

Fixed Cost - must pay regardless of quantityVariable Cost - must

pay with each increase in quantity

Qty

Break Even AnalysisSAR

Total Cost = 500 + 100 x Q

Total Cost = FC + VC x Qty

Fixed Cost - must pay regardless of quantityVariable Cost - must

pay with each increase in quantity

Qty

Break Even AnalysisSAR

500

Total Cost = 500 + 100 x Q

Total Cost = FC + VC x Qty

Fixed Cost - must pay regardless of quantityVariable Cost - must

pay with each increase in quantity

Qty

Break Even AnalysisSAR

500

Total Cost = 500 + 100 x Q

Total Cost = FC + VC x Qty

Fixed Cost - must pay regardless of quantityVariable Cost - must

pay with each increase in quantity

Qty

Break Even AnalysisSAR

500

Total Cost = 500 + 100 x Q

Total Cost = FC + VC x Qty

Fixed Cost - must pay regardless of quantityVariable Cost - must

pay with each increase in quantity

Fixed Cost

Qty

Break Even AnalysisSAR

500

Total Cost = 500 + 100 x Q

Total Cost = FC + VC x Qty

Fixed Cost - must pay regardless of quantityVariable Cost - must

pay with each increase in quantity

Fixed Cost

Qty

Break Even AnalysisSAR

500

Total Cost = 500 + 100 x Q

Total Cost = FC + VC x Qty

Fixed Cost - must pay regardless of quantityVariable Cost - must

pay with each increase in quantity

Fixed Cost

Fixed Cost

plus Variable

Cost

Qty

Break Even AnalysisSAR

500

Total Cost = 500 + 100 x Q

Total Cost = FC + VC x Qty

Fixed Cost - must pay regardless of quantityVariable Cost - must

pay with each increase in quantity

Total Revenue = Price x Qty

Fixed Cost

Fixed Cost

plus Variable

Cost

Qty

Break Even AnalysisSAR

500

Total Cost = 500 + 100 x Q

Total Revenue = 200 x Q

Total Cost = FC + VC x Qty

Fixed Cost - must pay regardless of quantityVariable Cost - must

pay with each increase in quantity

Total Revenue = Price x Qty

Fixed Cost

Fixed Cost

plus Variable

Cost

Qty

Break Even AnalysisSAR

500

Total Cost = 500 + 100 x Q

Total Revenue = 200 x Q

Total Cost = FC + VC x Qty

Fixed Cost - must pay regardless of quantityVariable Cost - must

pay with each increase in quantity

Total Revenue = Price x Qty

Fixed Cost

Fixed Cost

plus Variable

Cost

Qty

Break Even AnalysisSAR

500

Total Cost = 500 + 100 x Q

Total Revenue = 200 x Q

Total Cost = FC + VC x Qty

Fixed Cost - must pay regardless of quantityVariable Cost - must

pay with each increase in quantity

Total Revenue = Price x Qty

Fixed Cost

Fixed Cost

plus Variable

Cost

Qty

Break Even AnalysisSAR

500

Total Cost = 500 + 100 x Q

Total Revenue = 200 x Q

Total Cost = FC + VC x Qty

Fixed Cost - must pay regardless of quantityVariable Cost - must

pay with each increase in quantity

Total Revenue = Price x Qty

Fixed Cost

Fixed Cost

plus Variable

Cost

Qty

Break Even AnalysisSAR

500

Total Cost = 500 + 100 x Q

Total Revenue = 200 x Q

Total Cost = FC + VC x Qty

Fixed Cost - must pay regardless of quantityVariable Cost - must

pay with each increase in quantity

Total Revenue = Price x Qty

Fixed Cost

Fixed Cost

plus Variable

Cost

Loss

Qty

Break Even AnalysisSAR

500

Total Cost = 500 + 100 x Q

Total Revenue = 200 x Q

Total Cost = FC + VC x Qty

Fixed Cost - must pay regardless of quantityVariable Cost - must

pay with each increase in quantity

Total Revenue = Price x Qty

Fixed Cost

Fixed Cost

plus Variable

Cost

Loss

Profit

Qty

Break Even AnalysisSAR

500

Total Cost = 500 + 100 x Q

Total Revenue = 200 x Q

Total Cost = FC + VC x Qty

Fixed Cost - must pay regardless of quantityVariable Cost - must

pay with each increase in quantity

Total Revenue = Price x Qty

Fixed Cost

Fixed Cost

plus Variable

Cost

Loss

Profit

Qty

Break Even AnalysisSAR

500

Total Cost = 500 + 100 x Q

Total Revenue = 200 x Q

Total Cost = FC + VC x Qty

Fixed Cost - must pay regardless of quantityVariable Cost - must

pay with each increase in quantity

Total Revenue = Price x Qty

Fixed Cost

Fixed Cost

plus Variable

Cost

Loss

Profit

Qty

Break Even AnalysisSAR

500

Total Cost = 500 + 100 x Q

Total Revenue = 200 x Q

Qty

Break Even AnalysisSAR

500

Total Cost = 500 + 100 x Q

Total Revenue = 200 x Q

Total Cost = Total Revenue

Qty

Break Even AnalysisSAR

500

Total Cost = 500 + 100 x Q

Total Revenue = 200 x Q

Total Cost = Total Revenue500 + 100 x Q = 200 x Q

Qty

Break Even AnalysisSAR

500

Total Cost = 500 + 100 x Q

Total Revenue = 200 x Q

Total Cost = Total Revenue500 + 100 x Q = 200 x Q

500 + 100Q = 200Q

Qty

Break Even AnalysisSAR

500

Total Cost = 500 + 100 x Q

Total Revenue = 200 x Q

Total Cost = Total Revenue500 + 100 x Q = 200 x Q

500 + 100Q = 200Q500 = 100Q

Qty

Break Even AnalysisSAR

500

Total Cost = 500 + 100 x Q

Total Revenue = 200 x Q

Total Cost = Total Revenue500 + 100 x Q = 200 x Q

500 + 100Q = 200Q500 = 100Q

5 = Q

Qty

Break Even AnalysisSAR

500

Total Cost = 500 + 100 x Q

Total Revenue = 200 x Q

Total Cost = Total Revenue500 + 100 x Q = 200 x Q

500 + 100Q = 200Q500 = 100Q

5 = Q

5

Qty

Break Even AnalysisSAR

500

Total Cost = 500 + 100 x Q

Total Revenue = 200 x Q

Total Cost = Total Revenue500 + 100 x Q = 200 x Q

500 + 100Q = 200Q500 = 100Q

5 = Q

5

1000