Department of Human ServicesProject Management Office
Work Breakdown Structure (WBS) Development
2
Agenda Items
What is a Breakdown Structure Where does it fit in PMBottom Up DevelopmentTop Down DevelopmentHelp and ReferencesAdditional Questions
3
WBS Introduction
Training Goal To understand the process, it’s purpose and benefits.To learn enough about the process to begin using it.To know where you can access the process and any of the supporting materials.
4
Applicability of DHS Core Valuesto Project Management
Professionalism
Responsibility
Stewardship
Integrity
Respect
5
WBS Definition
A deliverable-oriented grouping of project elements that organizes and defines the total scope of the project work.
Work not in the WBS is not in scope of the project.
Each descending level represents an increasinglydetailed description of the project elements.
Often used to develop or confirm a commonunderstanding of project scope.
6
Where the WBS Fits
Initiate
Plan
Execute
Control
CloseStrategic
Tactical
Physical
7
Where WBS FitsLe
vel o
f Act
ivity
Start FinishTime
Initiate
Execute
Close
Monitoring and Control
Plan
8
What does a WBS look like?Example - WBS/How?
Project
DesignRqmts Build DeliverManage
PlanExecuteControlClose••
AssessDetermineAnalyzePropose••
EngineerSpecify•••
ConstructTestValidateIntegrate•••
InstallTrain•••
Hierarchy Diagram Format
1 MANAGEMENT1.1 Initiate1.2 Plan1.3 Execute1.4 Control1.5 Close
2 REQUIREMENTS2.1 Assess2.2 Determine2.3 Analyze2.4 Propose2.5 …..
3 DESIGN3.1 Engineer3.2 Specify3.3 ….3.4 …..
4 BUILD4.1 Construct4.2 Test4.3 Validate4.4 Integrate
5 DELIVER5.1 Install5.2 Train5.3 …..5.4 …..
Table of Co ntent s For m
at
1. Write First draft of policy.2. Review with team/manager.3. Make changes as needed.4. File notice w/Secretary of the State
(SOS) 45 days before effective date.5. Formally review policy analysts and
advocates.6. Make changes as needed.7. Update program manuals and forms
to reflect changes.8. Submitted to the SOS by 5:00pm the
day before it is to be effective.
List Format
9
PBS WBS OBS
Product Breakdown Structure
Work Breakdown Structure
Organizational Breakdown Structure
WHAT? HOW? WHO?
Breakdown Structures
10
SteeringFuelOdometersWipersLights• •
FendersRoofHoodsDoorsWindows• •
Front SeatsBack SeatsRadio •
CAR
EngineFrame Interior ControlsCarburetorCylindersPistonCam• • •
Example - PBS/What?
11
Project
DesignRqmts Build DeliverManage
PlanExecuteControlClose • •
AssessDetermineAnalyzePropose• •
EngineerSpecify• • •
ConstructTestValidateIntegrate• • •
InstallTrain• • •
Example - WBS/How?
12
Staff1Staff2Staff3 Staff4
• • •
Staff1Staff2Staff3
• • •
Staff1Staff2Staff3 Staff4Staff5
•
Director
Mgr.Mgr. Mgr. Mgr.
Staff1Staff2
• •
Example - OBS/Who?
13
Project
Deliverable 1.0 Deliverable 3.0Deliverable 2.0
Work Package 1.1
Work Package 1.2
Work Package 1.3
Work Package 2.4
Work Package 2.3
Work Package 2.2
Work Package 2.1
Work Package 3.3
Work Package 3.2
Work Package 3.1
E-1
WBS Diagram
14
Benefits of the WBS
WBS
EstimatesSchedule
Project Plan
Risk and Contingency Plans
ProgressReports
Activity List
Risk Control
Project Control Change
Control
Communication Control
15
Brainstorming all work to be done
and then grouping into a hierarchy.
Bottom Up
Using a general-to-specific structure to progressively detail the work.
Top Down
Common Approaches
Bottom up WBS Development
NO
Yes
1. Create the “to-do” list of work.
2. Organize the “to-dos”.
3. Review and Adjustwith group.
4. Correctand
Complete?
WBS Complete16
Bottom Up
17
1. Create the to-do list of work
Review/Discuss “WHAT” is to be delivered. Review no-limitations brainstorming. Brainstorm list of work on a ….. End first meeting. Compile list into tool that allows all
participants easy access.
Bottom Up
18
Step 1 - TIPS
Sit down and participate as a peer.Have someone else write on the board.Encourage starting with a verb. Don’t correct or worry about wording. Capture all phrases, thoughts.Explanation not required.
Bottom Up
19E - 2
Assessment Review, Research, Collect, Analyze, Assess,
Determine, Identify
Requirements Define, Describe, Design, Develop work activities,
Choose, Obtain, Prepare, Approve
Construction Construct, Build, Write, Obtain, Create
Validation Validate, Pilot, Check, Test
Implementation Implement, Move, Train, Replace, Evaluate
Useful Brainstorming Verbs
Bottom Up
20
2. Organize the “to-do” list.
Back at a desk have someone organize the list.
Take very detailed, but related steps and group them into tasks. Name the task.
Take related tasks and group them into activities. Name the activity.
Group activities into phases.
Bottom Up
Step 2 - TIPS
Do what appears easiest first.Go back & adjust as you go through it.Adjust the wording now, not intent. Create a miscellaneous activity.For the under-developed tasks or activities leave space for adding later.
Bottom Up
21
3. Review/adjust structure with group
Tell the group what has been done.
Go through structure, fix and confirm groupings. Adjust names.
Add additional forgotten tasks or activities.
Bottom Up
22
Step 3 - TIPS
Constrain Level of Detail Lowest level should be completedin approximately 1-3 weeks. Lowest level should contain a definition that includes the detailed steps.
Bottom Up
23
4. Verify Correctness /Completeness
At the lowest level you should be able to:
Name all the work packages; e.g. scope definition document, code specification #1, painted exterior.
Indicate Dependencies.Apply approximate duration.Assign a resource role; e.g. carpenter, tester.
Bottom Up
24
4. Common Obstacles
Discussing or setting requirements. Talking about solutions rather than the work.Wanting to sequence and assign resources too early.Level of detail issues.Other issues.
Top Down WBS Development
1. Choose your model.
2. Verify highest levelDeliverables/Phases.
4. Review, Verify and or modify the
next subsequent level.
3. Can adequate
ests. be made atthis level?
WBS CompleteYes
No
5. Confirm lowest level.
25
Top Down
Note* Various life cycle templates and examples
from other projects are
available on the PMO web site.
26
Review various: life cycle models, similar project’s WBS, or life cycle templates.
Choose a model closest to your specific project.
1. Choose your model
2827
Top Down
Start at the top of a model - Deliverables
28
Verify deliverables represent the major phases of your project,
Verify purpose/need of each major deliverable or phase,
Determine if a previous project completed a major deliverable, e.g. Feasibility.
Choose to: eliminate or modify deliverable after review of previous completed work
2. Verify highest level phases/deliverables
Note* This step’s question means - different levels of decomposition are appropriate for each of the major deliverables/phases.
Top Down
“Yes” Decisions Guidelines
29
3. Can adequate estimates be made at this level?
Can it be completed within a 2 – 3 week period?
Adequate may change over the course of the project.
Estimating a major work package that will be produced 6 – 12 months out may not be possible.
Top Down4. Review, verify and or modify the next subsequent level.
30
Very, from the model, the next subsequent level’s, more specific work detail.
Choose the appropriate work elements. elements should be described in tangible,
verifiable results in order to facilitate the project progress.
Repeat step 3 for each work element that you have chosen necessary for the project.
5. Confirm lowest level
Can the item be scheduled? Budgeted? Assigned to a specific organizational unit (e.g., department, team, or person)?
If no, combine items, add to, delete, redefine.
If no, revise or expand the descriptions
If no, the item must be modified,split, redefined.
Top DownAre the lower-level items both necessary and sufficient?
Does the work item description provide a scope?
31
33
Top Down
• Requires more up front discussion.
• Terminology & structure can get in the way.
• Decreases participation. • Slower to start.
Lesson Learned
Bottom Up
• Easy to start.• No terminology issues.• Higher participation. • What do we do with this?
34
What’s Next?
Briefly describe each item Reference by number List associated activitiesList milestonesList other information needed
to facilitate work
Further decomposition into a WBS Dictionary
35
Closing
The greatest benefit of developing a work breakdown structure is providing a common understanding of all the work required to deliver the product or service.
36
37
Additional Questions?
38
Please take some time for Class Evaluation!
Please fill out both sides.
Top Related