Download - Week 13 Deliverables

Transcript
Page 1: Week 13 Deliverables

Week 13 Deliverables

Team Highlander

Page 2: Week 13 Deliverables

Modifications from last Mock-Up

• Lever assembly is offset from walker• Ski assembly is now solid• Levers swing upward

Page 3: Week 13 Deliverables

Working shots

Page 4: Week 13 Deliverables

Working Shots

Page 5: Week 13 Deliverables

Working Shots

Page 6: Week 13 Deliverables

Reasons why old design is better

• Less footprint area• Less parts• More aesthetically pleasing• Handle rotation in constrained by frame; less

complex• No drilling through frame required• Able to collapse

Page 7: Week 13 Deliverables

To do list for next week

• Contact REAR (Rehabilitation Engineering and Applied Research lab) about design

• Machine the pieces needed for welding (water jet); this includes all the pivot joints

• Begin machining the stopper legs using wood• Finalize CAD drawings