Verona Area High School
Visioning Team Meeting #1
May 9, 2017
15/9/2017
5/9/2017 2
MEETING AGENDA
• Introductions• Schedule, Expectations & Goals• Case Studies• Discovery Exercises• Break• Summary• Bubble Exercise
35/9/2017
The Verona Area School District Board of Education believes that EVERY student MUST be successful!
4
PROJECT TIMELINE
5/9/2017
2017 2018
April May June July Aug Sept Oct Nov Dec Jan Feb Mar April May
5
SDSchematic Design
DDDesign Development
CDConstruction Documents
PROJECT TIMELINE
• Information gathering
• Define major design and
learning concepts
• Overall building massing
and layout
• Preliminary material
selection
• Refine building layouts
• Detailed planning of all
spaces
• Refine material selections
• Finalize design
• Full design and
construction detailing
• Final material selection
5/9/2017
5/9/2017 6
MEETING EXPECTATIONS
• One conversation at a time• No idea is a bad idea• Use specific examples• Explain reasoning and intent• Focus on FUTURE• Be present
5/9/2017 7
MEETING GOALS
• Guiding Principles• Building Organization• Space Adjacencies
85/9/2017
5/9/2017 9
CASE STUDIESJOPLIN HSJoplin High School, Joplin, MODLR and Corner Green Architects2500 students / 488,000 sf
5/9/2017 10
CASE STUDIESJOPLIN HSJoplin High School, Joplin, MODLR and Corner Green Architects2500 students / 488,000 sf
5/9/2017 11
CASE STUDIESJOPLIN HSJoplin High School, Joplin, MODLR and Corner Green Architects2500 students / 488,000 sf
5/9/2017 12
CASE STUDIESJOPLIN HSJoplin High School, Joplin, MODLR and Corner Green Architects2500 students / 488,000 sf
5/9/2017 13
CASE STUDIESJOPLIN HSJoplin High School, Joplin, MODLR and Corner Green Architects2500 students / 488,000 sf
5/9/2017 14
CASE STUDIESBLOOMFIELD HSBloomfield Hills, MIFielding Nair International and Stantec1800 students / 372,000 sf
5/9/2017 15
CASE STUDIESBLOOMFIELD HSBloomfield Hills, MIFielding Nair International and Stantec1800 students / 372,000 sf
5/9/2017 16
CASE STUDIESBLOOMFIELD HSBloomfield Hills, MIFielding Nair International and Stantec1800 students / 372,000 sf
5/9/2017 17
CASE STUDIESBLOOMFIELD HSBloomfield Hills, MIFielding Nair International and Stantec1800 students / 372,000 sf
5/9/2017 18
CASE STUDIESALEXANDRIA AREA HSAlexandria, MNCunningham Group/ JLG Architects1400 students / 304,000 sf
5/9/2017 19
CASE STUDIESALEXANDRIA AREA HSAlexandria, MNCunningham Group/ JLG Architects1400 students / 304,000 sf
5/9/2017 20
CASE STUDIESALEXANDRIA AREA HSAlexandria, MNCunningham Group/ JLG Architects1400 students / 304,000 sf
5/9/2017 21
CASE STUDIESALEXANDRIA AREA HSAlexandria, MNCunningham Group/ JLG Architects1400 students / 304,000 sf
5/9/2017 22
CASE STUDIESALEXANDRIA AREA HSAlexandria, MNCunningham Group/ JLG Architects1400 students / 304,000 sf
235/9/2017
IMAGE DISCOVERY
Choose an image which represents the Vision for the new Verona High School
245/9/2017
WORD DISCOVERY
When this project is complete, the 5 words which describe the new Verona High School
are:
255/9/2017
5/9/2017 26
BREAK
5/9/2017 27
SUMMARY
5/9/2017 28
PROGRAM DIAGRAMMING
5/9/2017 29
NEXT STEPS
• Tours
• STOP, START, CONTINUE
• Meeting #2: June 1
• Meetings #3 & #4: TBD
Top Related