Unit 8Confirmations
Unit Overview Prerequisites for confirmations Confirmation procedure Confirmation options
Time ticket/confirmation slipCollective entryTime eventProgress confirmationMilestone confirmationOrder confirmation
Unit ObjectivesAfter completing this unit, you will be able to:
Describe the confirmation procedures for production orders Define the control parameters for confirmations in Customizing Use the various transactions for the confirmation of production orders Describe the effects of confirmations
Unit ContentsLesson: Procedure, Prerequisites and Effects (Overview) .. . . . . . . . . . . . . . .272
Exercise 18: Confirmations Parameters.. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .277Lesson: Execution of Confirmations... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .281
Exercise 19: Confirmations ... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .289
2009 2011 SAP AG. All rights reserved. 271
Unit 8: Confirmations TSCM42
Lesson: Procedure, Prerequisites and Effects (Overview)
Lesson OverviewIn this lesson, you will learn about various confirmation procedures.
Lesson ObjectivesAfter completing this lesson, you will be able to:
Describe the confirmation procedures for production orders Define the control parameters for confirmations in Customizing
Business ExampleConfirmations are the premise for progress control and capacity planning. Theyshould be as prompt and efficient as possible. Due to the different requirementsthat arise in practice, SAP provides several confirmation procedures.
Confirmation Procedure
Figure 111: Confirmation - Overview
Confirmations are an important basis for entering internal activities performedfor the order, for the progress check and the resulting capacity requirementsplanning.
272 2011 SAP AG. All rights reserved. 2009
TSCM42 Lesson: Procedure, Prerequisites and Effects (Overview)
Precise, real-time confirmations are therefore especially important.
A confirmation causes various additional functions to be executed (see above).
Confirmations are executed in principle in the SAP ECC component, but can beimplemented using various technical procedures.
The standard system provides a range of online transactions in SAP ECC (seethe next slide).
Users of the browser-based Enterprise Portal can carry out confirmations aspart of the role of a production scheduler.
Confirmations from PDC systems are possible using the PP-PDC interface(see previous unit).
Confirmations can be automatically generated and processed using automaticprocess messages which, in turn, are generated from work instructions, using thePI-PCS interface, or using SAP ODA. (See previous unit.)
Confirmations can be generated and updated via anMii server (see previousunit).
As of release 4.6, custom-programmed confirmation interfaces and externalsystems can be linked to the SAP ECC system by using and adapting thefollowing BAPIs:
BAPI_PRODORDCONF_PDC_UPLOAD_TE (Time event confirmation)
BAPI_PRODORDCONF_PDC_UPLOAD_TT (Time ticket confirmation)
Figure 112: Confirmation Procedures
2009 2011 SAP AG. All rights reserved. 273
Unit 8: Confirmations TSCM42
There are different confirmation procedures.
Each procedure supports different practical requirements that a company mayhave.
Depending on the application, one or more procedure may be used. Proceduresmust be selected to suit the methods of organization within your company andaccording to the degree of time and effort required.
For the most part, the two main types are operation-related and order-relatedconfirmations.
Order confirmation is a confirmation of the entire order at order header level.
An operation confirmation allows you to confirm the order step by step.Various procedures are available for this type of confirmation.
You can only carry out a confirmation for an order if no confirmations havealready been entered for the operations.
Each confirmation is entered with a status (partial confirmation, final confirmation,automatic final confirmation).
A confirmation can be made with an automatic goods receipt. Control is thenmaintained using either the operation control key or the production schedulingprofile.
A material overview enables you to correct backflushing for postable materialwithdrawals, or to enter any number of unplanned goods movements.
You can only perform a cancellation for the individual, entire confirmation(no correction).
There are a whole range of Business Application Interfaces (BAPI) available thatcan be used to enhance the standard confirmations to suit specific users.
274 2011 SAP AG. All rights reserved. 2009
TSCM42 Lesson: Procedure, Prerequisites and Effects (Overview)
Requirements for Confirmations
Figure 113: Requirements for Confirmations
Confirmations are controlled by confirmation parameters (see next graphic).
Each operation is automatically given a confirmation number when the order iscreated. You can then clearly identify it without having to enter any other data.
Each operation contains an operation control key. This defines whether theoperation requires confirmation.
An operation can be marked as a milestone. This means that when the milestoneoperation is confirmed, the operations that precede it are also confirmed withproportional quantities.
An operation that is to be confirmed must first be released.
2009 2011 SAP AG. All rights reserved. 275
Unit 8: Confirmations TSCM42
Figure 114: Control Parameters for Confirmations
You control confirmations with Customizing settings (parameters).
You set the control parameters with reference to the order type and plant.
You have to differentiate between confirmation parameters for:
Time ticket confirmation with selection screen (can only be used withtransaction CO11)
Time ticket confirmation using single screen entry (new form of the normaloperation confirmation)
Collective confirmation / fast entry
You can change some settings online.
You must also enter the reasons for variance.
The reasons for variance can trigger statuses that, in turn, control trigger points.
Various programs are available for copying PDC confirmation data into the HRmodule. Make sure you activate the No HR Update switch if you do not executethe transfer.
You can enter confirmations with a shift. Relevant settings are required forautomatic determination of the shift number (ECC 6.0, EhP3).
Error messages can be generated for the confirmation of scrap and reworkquantities. The corresponding settings are required for this (ECC 6.0, EhP3).
276 2011 SAP AG. All rights reserved. 2009
TSCM42 Lesson: Procedure, Prerequisites and Effects (Overview)
Exercise 18: Confirmations Parameters
Exercise ObjectivesAfter completing this exercise, you will be able to: Define confirmation parameters for the order type
Business ExampleYou will make the necessary Customizing settings to make confirmations forproduction orders possible.
Task 1:Create and release a production order for material R-F1## and your order typePO## in production plant 1000.
Save your production order.
Order number: _______________________
Task 2:Try to confirm your production order.
Choose transaction CO15(SAP menu: Logistics Production Shop Floor Control Confirmation Enter For Order) to enter the following order confirmation:
Order:
You get the error message No parameters defined for plant 1000 order type PO##.
Task 3:Define the confirmation parameters for your order type PO## and plant 1000. Todo so, copy the confirmation parameters for order type PP01.
Then try to confirm your order again.
1. Choose the following Customizing activity:(SPRO: SAP Reference IMG: Production Shop Floor Control Operations Confirmation Define Confirmation Parameters)
Define Confirmation Parameters
Select the line for Plant 1000 and Order Type PP01.
Choose icon Copy As
In Change View Parameters for Order Confirmation:
Continued on next page
2009 2011 SAP AG. All rights reserved. 277
Unit 8: Confirmations TSCM42
Field Order type:Delete entry PP01 and set your order type PO##.
Choose Enter to copy the settings.
Save your confirmation parameters.
2. Now try to confirm your order again.
Order confirmation should now be possible.
278 2011 SAP AG. All rights reserved. 2009
TSCM42 Lesson: Procedure, Prerequisites and Effects (Overview)
Solution 18: Confirmations ParametersTask 1:Create and release a production order for material R-F1## and your order typePO## in production plant 1000.
Save your production order.
Order number: _______________________
Task 2:Try to confirm your production order.
Choose transaction CO15(SAP menu: Logistics Production Shop Floor Control Confirmation Enter For Order) to enter the following order confirmation:
Order:
You get the error message No parameters defined for plant 1000 order type PO##.
Task 3:Define the confirmation parameters for your order type PO## and plant 1000. Todo so, copy the confirmation parameters for order type PP01.
Then try to confirm your order again.
1. Choose the following Customizing activity:(SPRO: SAP Reference IMG: Production Shop Floor Control Operations Confirmation Define Confirmation Parameters)
Define Confirmation Parameters
Select the line for Plant 1000 and Order Type PP01.
Choose icon Copy As
In Change View Parameters for Order Confirmation:
Field Order type:Delete entry PP01 and set your order type PO##.
Choose Enter to copy the settings.
Save your confirmation parameters.
a) - - -
2. Now try to confirm your order again.
Order confirmation should now be possible.
a) - - -
2009 2011 SAP AG. All rights reserved. 279
Unit 8: Confirmations TSCM42
Lesson Summary
You should now be able to: Describe the confirmation procedures for production orders Define the control parameters for confirmations in Customizing
280 2011 SAP AG. All rights reserved. 2009
TSCM42 Lesson: Execution of Confirmations
Lesson: Execution of Confirmations
Lesson OverviewThis lesson familiarizes you with the various confirmation transactions.
Lesson ObjectivesAfter completing this lesson, you will be able to:
Use the various transactions for the confirmation of production orders Describe the effects of confirmations
Business ExampleYou will use different confirmation transactions, depending on the specificapplication. These must be tailored to your methods of organization for productionand require a minimum of effort.
Confirmation Transactions and Options
Figure 115: Confirmation Transactions and Options (I)
2009 2011 SAP AG. All rights reserved. 281
Unit 8: Confirmations TSCM42
Figure 116: Confirmation Transactions and Options (II)
Confirmation with Transaction CO11N
Figure 117: Field Groups for Single Screen Entry
As of Release 4.6, the time ticket confirmation of an operation using transactionCO11N is performed on one screen (single screen entry).